Waverley View Investors, LLC v. United States ( 2018 )


Menu:
  •   In the United States Court of Federal Claims
    No. 15-371 L
    Filed: January 5, 2018
    ****************************************
    *
    *                   Comprehensive Environmental Response,
    WAVERLEY VIEW INVESTORS, LLC,          *                       Compensation, and Liability Act of
    *
    1980, 
    42 U.S.C. §§ 9601
    –9675 (2012);
    Plaintiff,                       *
    *                   Just Compensation;
    v.                               *                   Right of Entry Agreement;
    *                   Tucker Act Jurisdiction, 
    28 U.S.C. § 1491
    THE UNITED STATES,                     *                       (2012);
    *                   U.S. CONST. amend. V, Takings Clause;
    Defendant.                       *                   Voluntary Consent.
    *
    *
    ****************************************
    Clifford Jack Zatz, Crowell & Moring LLP, Washington, D.C., Counsel for Plaintiffs.
    Jessica Michelle Held, United States Department of Justice, Environmental and Natural
    Resources Division, Washington, D.C., Counsel for the Government.
    POST-TRIAL MEMORANDUM OPINION AND ORDER DETERMINING THAT THE
    GOVERNMENT HAS TAKEN CERTAIN PORTIONS OF THE WAVERLEY VIEW
    PROPERTY
    BRADEN, Chief Judge.
    Section 104(e) of the Comprehensive Environmental Response, Compensation, and
    Liability Act of 1980 (“CERCLA”), 
    42 U.S.C. §§ 9601
    –9675, authorizes the United States
    Environmental Protection Agency (the “EPA”) “to take action . . . at any . . . property[,] . . . if there
    is a reasonable basis to believe there may be a release or threat of release of a hazardous substance
    or pollutant or contaminant.” 
    42 U.S.C. § 9604
    (e)(1).
    In this case, the owner of real estate in Frederick, Maryland was faced with a demand for
    access to the property to install wells for the testing and monitoring of groundwater contamination.
    Faced with incurring the expenses of fighting federal authorities, potential civil penalties, and even
    potential cleanup costs, the property owner negotiated an agreement to allow federal authorities to
    access the property, install monitoring wells, and perform other necessary and incidental work.
    After the agreement expired, federal authorities withdrew from the property, but left behind the
    monitoring wells and a gravel access road. Some level of contamination was found on the
    property, but, at present, the EPA and the United States Army (the “Army”) do not have a plan for
    remediation and have represented that they have no need to continue testing on the property.
    The property owner has filed suit under the Takings Clause of the Fifth Amendment to the
    United States Constitution. The court has determined that the continued presence of the
    monitoring wells and gravel access road on the property after expiration of the access agreement
    establish the requirements of a physical taking under the precedential decision Hendler v. United
    States, 
    952 F.2d 1364
     (Fed. Cir. 1991)” (“Hendler III”). Ascertaining the actual damage incurred,
    however, is problematic for the reasons discussed herein.
    For the convenience of the parties, the court has prepared a Table Of Abbreviations,
    attached hereto as Exhibit A. To facilitate review of this Post-Trial Memorandum Opinion And
    Order, the court has provided the following outline:
    I.     FACTUAL BACKGROUND.
    A.     Contamination And Remediation Of Area B Of United States Army Garrison,
    Fort Detrick, Maryland.
    B.     The History Of The Waverley View Property.
    C.     The Government’s Interactions With RGHGAB at Frederick, LLC To Gain
    Access To The Waverley View Property.
    D.     The Government’s Interactions With Waverley View Investors, LLC To Gain
    Access To The Waverley View Property.
    II.    PROCEDURAL HISTORY.
    III.   DISCUSSION.
    A.     Subject Matter Jurisdiction.
    B.     Standing.
    C.     Plaintiff’s Takings Clause Claims Against The Government.
    1.      At Trial, Plaintiff Established That It Owns Private Property Under
    Maryland State Law.
    2.      At Trial, Plaintiff Established That The Government’s Activities After
    Expiration Of The Right Of Entry Agreement Effected A Permanent Taking
    Of Those Portions Of The Waverley View Property Physically Occupied
    By The Army-Installed Monitoring Wells And Gravel Access Road.
    a.     Plaintiff’s Argument.
    i.      “Plaintiff Has Proved A Per Se Taking.”
    ii.     “The Right Of Entry Agreement Preserved Plaintiff’s
    Takings Clause Claim.”
    iii.    “The Right Of Entry Agreement Is Not A Contract.”
    b.     The Government’s Response.
    2
    i.     “Plaintiff Has Failed To Prove A Physical Taking Of Its
    Property, Because It Consented To The Army’s
    Groundwater Monitoring.”
    ii.    “Plaintiff Did Not Establish That The Government Has
    Permanently Occupied Its Property.”
    iii.   “Because Plaintiff Consented To The Installation Of The
    Monitoring Wells In A Valid Contract, Its Claims Are
    Governed By Contract Law.”
    c.   Plaintiff’s Reply.
    i.     “Plaintiff’s Takings Clause Claim Is Ripe for Review.”
    ii.    “The Right Of Entry Agreement Does Not Bar Plaintiff’s
    Takings Clause Claim.”
    d.   The Government’s Sur-Reply.
    i.     “The Right Of Entry Agreement Vitiates Plaintiff’s Takings
    Clause Claims.”
    ii.    “The Right Of Entry Agreement Is Supported By Valid
    Consideration.”
    e.   Plaintiff’s Sur-Reply.
    i.     “The Right Of Entry Agreement Does Not Bar Plaintiff’s
    Takings Clause Claim.”
    ii.    “Plaintiff’s Takings Clause Claim Is Ripe For Review.”
    iii.   “The Framework From Arkansas Game and Fish Does Not
    Apply To Permanent Takings Cases Like This One.”
    f.   The Court’s Resolution.
    i.     Governing Precedent.
    ii.    Plaintiff Voluntarily Consented To The Government’s Entry
    And Use Of The Waverley View Property.
    iii.   The Reservation Of Rights In The Right Of Entry
    Agreement Did Not Invalidate Plaintiff’s Consent.
    iv.    The Government’s Activities On The Waverley View
    Property During The Term Of The Right of Entry
    Agreement Did Not Exceed The Scope Of Work Described
    Therein.
    v.     The Continued Presence Of The Army-Installed Monitoring
    Wells And Gravel Access Road On The Waverley View
    Property After Expiration Of The Right Of Entry Agreement
    Effected A Permanent Taking Of Certain Portions Thereof.
    3
    3.   At Trial, Plaintiff Established That It Is Entitled To Just Compensation.
    a.        Plaintiff’s Argument.
    b.        The Government’s Response.
    c.        Plaintiff’s Reply.
    d.        The Government’s Sur-Reply.
    e.        Plaintiff’s Sur-Reply.
    f.        The Court’s Resolution.
    i.        Governing Precedent.
    ii.       Plaintiff Failed To Establish That The Taking Of Certain
    Portions Of The Waverley View Property Prohibited The
    Development Or Sale Thereof.
    iii.      Plaintiff Failed To Establish That Any Stigma Attached To
    The Waverley View Property Was Caused By The
    Government’s Activities Thereon.
    iv.       Plaintiff Is Entitled To $1.06 Per Square Foot Of The
    Waverley View Property Physically Occupied By The
    Army-Installed Monitoring Wells And Gravel Access Road.
    IV.   CONCLUSION.
    4
    I.     FACTUAL BACKGROUND.1
    A.      Contamination And Remediation Of Area B Of United States Army
    Garrison, Fort Detrick, Maryland.
    United States Army Garrison, Fort Detrick, Maryland (“Fort Detrick”) is a Medical
    Command facility owned and operated by the Army. PX 65 at 2. For many years, “Fort Detrick
    was the center of the U.S. biological weapons program.”2 PX 65 at 2. “Since the discontinuation
    of that program, it has hosted elements of the U.S. biological defense program.” PX 65 at 2.
    Today, Fort Detrick consists of three tracts of land: “Area A, comprising about 800 acres where
    the main post area and installation activities are located; Area B, comprising about 400 acres
    generally located west of Area A; and Area C, which consists of two parcels [of land] located on
    the west bank of the Monocacy River.” PX 65 at 2; see also DX 108 at US002779 (depicting
    Areas A and B). Area B is the focus of this case.
    In 1943, the Army established a Biological Warfare Research Center in Area A. PX 24 at
    PL004077. In 1944, the Army acquired Area C “to develop water and sewer treatment plants.”
    PX 24 at PL004077. In September 1946, the Army acquired Area B, “as the primary location for
    Fort Detrick’s waste management activities.” PX 24 at PL004077.
    Until the 1970s, Area B was used as “both a proving ground and a disposal area for
    chemical, biological[,] and radiological material” (PX 65 at 2; see also PX 24 at PL004077),
    including Anthrax and “major components of . . . Agent Orange” (DX 41 at WVI00006710). In
    addition, Area B-11, the “westernmost disposal area” of Area B, was used “from the early 1950s
    through approximately 1972” for disposal of “acids and chemicals, incinerated medical waste,
    waste herbicides and insecticides, [and] phosgene” in “unlined trenches or pits.” PX 24 at
    PL004079.
    1
    The facts recited herein were derived from: testimony adduced at a trial held on January
    17–18 and 24–26, 2017 in Washington, D.C. (“TR 1–1469”), including the parties’ Joint Exhibits
    (“JX 1–31”), Plaintiff’s Exhibits (“PX 1–163”), and the Government’s Exhibits (“DX 1–142”);
    and information obtained during a site visit conducted on December 1, 2017 (“SVTR 1–44”).
    2
    Between 1943 and 1945, Fort Detrick was “the site of an exhaustive biological warfare
    research effort during World War II.” DX 142 at 12. Shortly after the war, the fort was
    “designat[ed] . . . as a permanent installation for peacetime biological research[.]” DX 142 at 12.
    In 1956, Fort Detrick was re-designated “with a mandate of continuing biological research and
    remaining the world’s leading research campus for biological agents that require special
    containment.” DX 142 at 12.
    5
    DX 108 at US002779.
    6
    Fort Detrick, Areas A and B.
    In 1970 and 1971, “after the United States [banned] biological research for offensive
    operations, the Army began a decontamination and certification program at Fort Detrick[.]” PX
    24 at PL004078. But, it was not until 1977 that “[c]ontamination assessments” commenced and
    the Army “determined that activities at [Fort Detrick] could have resulted in [the] release[] of
    chemicals [into] the environment.” PX 24 at PL004078.
    In 1981, after completing a “Field Investigation of Uncontrolled Hazardous Waste Sites,”
    the EPA “recommended that the State [of Maryland] and [the] EPA monitor the Army’s
    investigations to address the potential for off-site migration of toxic materials[.]” PX 24 at
    PL004078.
    In 1988, Fort Detrick was “listed on the federal facilities compliance docket.” DX 142 at
    13. Later that year, the “Army conducted an environmental audit . . . to determine the existence
    of or potential for environmental contamination and to assess [the] risk to human health and the
    environment associated with the installation.” DX 142 at 13.
    In February 1992, the Army discovered trichloroethylene (“TCE”)3 concentrations above
    the maximum contamination level (the “MCL”) established under the Safe Drinking Water Act,
    42 U.S.C. §§ 300f–300j-26, as well as elevated levels of trichlorofluoromethane (“TCFM”)4 in
    Area B. PX 24 at PL004078; see also DX 142 at 13. Thereafter, the United States Army
    Environmental Hygiene Agency “began a study of . . . Area B that included installation and
    sampling of monitoring wells.” PX 24 at PL004078; see also DX 142 at 13.
    In October 1992, the Maryland Department of the Environment (the “MDE”) “sampled 21
    residential wells in the vicinity of Fort Detrick Area B and found TCE concentrations above the
    3
    The Agency for Toxic Substances and Disease Registry, a federal public health agency
    within the United States Department of Health and Human Services, defines TCE as
    a nonflammable, colorless liquid with a somewhat sweet odor and a sweet, burning
    taste. It is used mainly as a solvent to remove grease from metal parts, but it is also
    an ingredient in adhesives, paint removers, typewriter correction fluids, and spot
    removers. [TCE] is not thought to occur naturally in the environment. However,
    it has been found in underground water sources and many surface waters as a result
    of the manufacture, use, and disposal of the chemical.
    Toxic Substances Portal: Trichloroethylene (TCE), AGENCY FOR TOXIC SUBSTANCES AND DISEASE
    REGISTRY (Mar. 3, 2011), https://www.atsdr.cdc.gov/substances/toxsubstance.asp?toxid=30.
    TCE is “[k]nown to be a [h]uman [c]arcinogen” and is classified as a volatile organic compound
    (“VOC”). Id.
    4
    TCFM is a “[colorless] gas or highly volatile liquid,” traditionally used as a refrigerant.
    Trichlorofluoromethane, NAT’L INST. FOR OCCUPATIONAL SAFETY AND HEALTH (July 22, 2015),
    https://www.cdc.gov/niosh/ipcsneng/neng0047.html. TCFM “can be absorbed into the body by
    inhalation . . . causing a serious risk of suffocation when in confined areas [and] . . . effects on the
    cardiovascular system and central nervous system, resulting in cardiac disorders and central
    nervous system depression.” Id.
    7
    MCL in four wells[.]” PX 24 at PL004078. In response, the Army provided bottled water to
    affected residents until their homes could be connected to the public water system. PX 24 at
    PL004079.
    Beginning in 1992, and continuing into 1993, “[e]nvironmental investigations were
    performed at Fort Detrick, including Area B, to investigate, and evaluate conditions, locate
    potential dump sites, and determine whether contamination was present at various Areas of
    Concern[.]” DX 142 at 13.
    In 1993, the Army also convened a Restoration Advisory Board (the “Fort Detrick RAB”)
    to “provide a forum for cooperation between the [Army and the EPA], State representatives, local
    community representatives, and natural resource trustees on actions and proposed actions at the
    [s]ite.” PX 24 at PL004126. Since that time, the Fort Detrick RAB has held “semi-annual [or]
    quarterly” meetings, open to the public, at which it “present[s] information to the community on
    the restoration program, . . . provide[s the community] with updates, statuses of [the Fort Detrick
    RAB’s] findings . . . [and] take[s] feedback from the community.”5 TR 921–22 (Gortva).
    By 1997, the Army became concerned that contamination from Area B-11 had migrated
    southwest onto an adjacent property (the “Waverley View Property”). DX 128 at 19–20. On
    November 13, 1997, the Army reported to the Fort Detrick RAB that wells along a fence line
    abutting the Waverley View Property showed elevated levels of TCE and perchloroethylene
    (“PCE”).6 DX 128 at 2–3, 19–20. The report included images depicting a groundwater plume
    extending from Area B onto the Waverley View Property, which the Army believed to have carried
    TCE and PCE onto Phase II of the property. DX 128 19–20; see also TR 918–19 (Gortva). The
    Army’s report was made available to the public at a Fort Detrick RAB meeting in 1997, at the
    Frederick County Public Library, and on the Fort Detrick website. TR 919–20 (Gortva).
    5
    The Fort Detrick RAB’s meeting minutes and presentations for years 1997 through 2017
    are publicly available on the Fort Detrick website. Restoration Advisory Board (RAB) Meeting
    Minutes, FORT DETRICK, MD. (Aug. 8, 2017), http://www.detrick.army.mil/rab/meeting
    Minutes.cfm.
    6
    PCE, also known as tetrachloroethylene, is “a manufactured chemical used for dry
    cleaning and metal degreasing. . . . It is also used as a starting material (building block) for
    making other chemicals and is used in some consumer products.” Toxic Substances Portal:
    Tetrachloroethylene (PERC), AGENCY FOR TOXIC SUBSTANCES AND DISEASE REGISTRY (Dec. 15,
    2014), https://www.atsdr.cdc.gov/substances/toxsubstance.asp?toxid=30. “Exposure to very high
    concentrations of [PCE] can cause dizziness headaches, sleepiness, incoordination, confusion,
    nausea, unconsciousness, and even death.” Id. The EPA “considers [PCE] likely to be
    carcinogenic to humans by all routes of exposure.” Id.
    8
    DX 128 at 19
    9
    Groundwater PCE Concentrations
    DX 128 at 20
    10
    Groundwater TCE Concentrations
    Beginning in 1999, “quarterly groundwater sampling [was] conducted at Area B
    monitoring wells and drinking water wells along the southern boundary of Area B.” PX 65 at 4.
    The groundwater samples were discovered to include TCE and PCE as “major constituents.” PX
    24 at PL004079; see also PX 65 at 4 (“Since 1999, . . . the [chlorinated VOCs] TCE and [PCE]
    have consistently been the most widespread and thus the focus of chemical constituents detected
    in groundwater at Area B.”).
    On July 14, 2000, the Army began a “hot spot interim removal action,” consisting of
    excavating hazardous waste, i.e., “contaminated soil, chemical containers, compressed gas
    cylinders, and laboratory waste[,]” from the disposal pits in Area B-11, and backfilling and
    capping7 the disposal pits. PX 24 at PL004079–80; PX 65 at 5. This interim removal action was
    completed in May 2004. PX 24 at PL004080; DX 142 at 13. During excavation of the disposal
    pits, “[h]owever, the discovery of live pathogens in medical wastes at [A]rea B-11 caused the
    suspension of [future] intrusive work at the disposal area[.]” PX 65 at 5; DX 142 at 13. As a
    result, “waste remains buried at [A]rea B-11.” PX 65 at 5.
    In addition, “[b]y 2004, several shallow (overburden) and deep (bedrock) monitoring wells
    were installed throughout Area B.” PX 65 at 4. Groundwater samples along the southern property
    line of Area B, adjacent to the Waverley View Property, “demonstrated groundwater
    contamination by PCE and TCE at concentrations above the MCL . . . , with the highest
    concentrations present within the bedrock.” PX 65 at 4. “Groundwater elevation maps prepared
    around 2004 . . . [also] suggest[ed] that groundwater may flow southwest from Area B onto [the
    Waverley View Property].” PX 65 at 4.
    On September 3, 2008, “Fort Detrick Area B Groundwater” was proposed for listing on
    the National Priorities List (the “NPL”).8 PX 65 at 2.
    On April 8, 2009, Fort Detrick Area B Groundwater was listed on the NPL as a CERCLA
    Superfund site. PX 65 at 2. “Four known source areas were identified [including the] Area B-11
    Chemical Waste Disposal Pits[.]” PX 65 at 2.
    In early 2010, the Kristen Renee Foundation, founded by Randy White, launched a public
    campaign, entitled “Fighting for Frederick,” “to research and investigate the findings associated
    with Fort Detrick ‘Area B’ groundwater.” DX 142 at 14. One of Mr. White’s daughters, Kristen
    Renee, died from a brain tumor in April 2008 and another was diagnosed with growths in her
    7
    “Capping involves placing a cover over contaminated material such as landfill waste or
    contaminated soil. Such covers are called ‘caps.’ Caps do not destroy or remove contaminants.
    Instead, they isolate them and keep them in place to avoid the spread of contamination.” U.S.
    ENVTL. PROT. AGENCY, A CITIZEN’S GUIDE TO CAPPING (2012).
    8
    The NPL is a “list of sites of national priority among the known releases or threatened
    releases of hazardous substances, pollutants, or contaminants throughout the United States and its
    territories. The NPL is intended primarily to guide the EPA in determining which sites warrant
    further investigation.” Superfund: National Priorities List (NPL), U.S. ENVTL. PROT. AGENCY,
    https://www.epa.gov/superfund/superfund-national-priorities-list-npl (last visited Oct. 24, 2017).
    11
    abdomen in 2009. DX 41 at WVI00006709, WVI00006712. Both daughters grew up near Fort
    Detrick, on property that “adjoins” the Waverley View Property, and their conditions were
    believed by doctors to be “likely caused by something in their environment.” TR 1187
    (McPherson); DX 41 at WVI00006712.
    On July 10, 2010, Mr. White, called a town hall meeting in Frederick, Maryland to discuss
    concerns about contamination at Fort Detrick and effects on the residents of the surrounding
    community. DX 41 at WVI00006712; DX 142 at 14. The meeting was attended by “[d]ozens of
    base neighbors who shared [Mr. White’s] concerns.” DX 41 at WVI00006712.
    On December 17, 2010, the Army and the EPA signed a Federal Facilities Agreement (the
    “FFA”) that “was made effective [A]utumn 2011.” PX 65 at 2. The FFA described the
    “procedures under which the Army, [the MDE], and the [EPA would] investigate and, if necessary,
    remediate sites at Area B in accordance with CERCLA.” PX 65 at 2.
    On October 8, 2011, The Baltimore Sun published an article, entitled “A death from cancer,
    and a search for answers,” about contamination at Fort Detrick and concerns for the surrounding
    community. DX 41 at WVI00006709–12. The article reported that “[f]or decades, Frederick
    residents had speculated about the possible effects of the experiments at [Fort Detrick] on the
    health of the surrounding community.” DX 41 at WVI00006709. The article also discussed Mr.
    White’s concerns and reported that “[o]fficials [began a] cancer cluster investigation . . . and have
    scheduled regular meetings to keep the community abreast of their findings.” DX 41 at
    WVI00006712. In addition, the article reported that Mr. White “has filed a mass tort lawsuit
    [against the Army]. He has been joined by more than 100 fellow plaintiffs.” DX 41 at
    WVI00006709.
    During 2011 and 2012, the Army installed additional wells throughout Area B, including
    “a nested group of four wells . . . installed on Fort Detrick property along the perimeter of Area B
    adjacent to [the Waverley View Property].” PX 65 at 4; see also TR 926–27 (Gortva) (testifying
    that this “nested group” of wells was located less than 20 feet from the Waverley View Property).
    Groundwater sampling from these wells showed “contamination at concentrations 1000 times
    greater than the MCL[.]” PX 65 at 4; see also TR 927 (Gortva) (testifying that “[i]n [the] October,
    November time frame, [the Army] received . . . results that were significantly elevated, around
    5000 parts per billion, and . . . in subsequent tests, . . . around 11,000 parts per billion”).
    During this time, the Army also requested permission to investigate properties in the
    vicinity of Fort Detrick to “complete the [R]emedial [I]nvestigation of the Area B groundwater.”
    TR 924 (Gortva).9 To explain the purpose of its investigation, the Army prepared a “Project
    Overview” (JX 15), to inform property owners that groundwater contamination was present on the
    “western side of Area B at the highest concentrations and extends to the east, [and] that the [Army]
    suspected contamination also extended onto the Waverley [View P]roperty” (TR 930–31 (Gortva);
    9
    For example, on October 25, 2012, the Army entered into an agreement with Loch Inver
    Court, a residential subdivision near Fort Detrick, entitled “Right-Of-Entry for Environmental
    Assessment and Response” that allowed the Army to enter the property for the purpose of
    “environmental investigation.” DX 37. On April 27, 2015, the Army entered into a similar
    agreement with another nearby subdivision, Carroll Park Manor. DX 103.
    12
    see also JX 15 at US002781). The “Project Overview” included an image depicting a groundwater
    plume extending from Area B onto the Waverley View Property, which the Army believed to have
    carried TCE and PCE onto Phase II of the property. JX 15 at US002781.
    Distribution of PCE and TCE in Groundwater
    JX 15 at US002781
    13
    B.      The History Of The Waverley View Property.
    In 2001, Detrick Overlook, LLC (“Detrick Overlook”) “purchased the land that comprises
    [the] Waverley View [Property]” from the Krantz Family Partnership.10 PX 65 at 2; DX 1 at
    WVI00008560. The Waverley View Property consists of approximately 92.8 acres of land,
    located along the southwest border of Area B of Fort Detrick. PX 76; TR 859 (Harvey). “Area B
    forms the northern boundary of the Waverley View [P]ropert[y], and farmland and residences
    border [the] Waverley View [Property] to the west, east[,] and south.” PX 65 at 2; see also PX 70.
    10
    The Krantz family continues to farm the Waverley View Property (SVTR 13; TR 449
    (Anderson)), however, Waverley View Investors, LLC (“WVI”), the current owner of the property,
    receives no income for this use (SVTR 13–14).
    14
    PX 70.
    15
    Fort Detrick Area B and the Waverley View Property.
    After purchasing the Waverley View Property, Detrick Overlook entered into agreements
    with several firms, including Geo-Technology Associates, Inc. (“GTA”) and W. L. Gore &
    Associates, Inc. (“WLGA”), to investigate the environmental conditions of the property. PX 151
    at 1; DX 1 at WVI00008560. On August 24, 2001, GTA provided an Environmental Site
    Assessment (the “2001 ESA”) to Detrick Overlook. DX 1 at WVI00008560. The 2001 ESA
    concluded that, based on “two surface water samples” collected on land comprising what would
    later become Phase I of the Waverley View Property (compare DX 1 at WVI00008566, with PX
    70), “no VOCs were reported above the laboratory’s reporting limit . . . [and] TCE and PCE were
    not reported above the practical quantification limit” (DX 1 at WVI00008560, WVI00008564–
    65).
    On October 4, 2001, WLGA provided Detrick Overlook with a “limited soil gas screening
    survey” concluding that “1,1,1 [t]richloroethane, tetrachloroethene, and trichloroethene were
    detected [on the Waverley View Property] in September/October 2001.” PX 151 at 1.
    On February 25, 2002, Detrick Overlook submitted an application to the MDE Voluntary
    Cleanup Program (“VCP”), seeking a “No Further Requirements Determination” (“NFRD”) for
    the Waverley View Property.11 PX 65 at 2; see also MD. DEP’T OF THE ENV’T, WAVERLY VIEW,
    ENVTL. RESTORATION & REDEVELOPMENT PROGRAM SITE FACTSHEET (Apr. 6, 2005),
    http://mde.maryland.gov/programs/LAND/MarylandBrownfieldVCP/Documents/www.mde.state
    .md.us/assets/document/brownfields/Waverly_View_Property.pdf. In turn, the MDE “requested
    additional information and further subsurface investigation in order to complete the application
    package.” PX 65 at 3; see also MD. DEP’T OF THE ENV’T, WAVERLY VIEW, ENVTL. RESTORATION
    & REDEVELOPMENT PROGRAM SITE FACTSHEET (Apr. 6, 2005).
    11
    The EPA provided the following relevant information on the MDE VCP and NFRDs:
    The [MDE] . . . administers the [VCP] to provide state oversight for the
    voluntary cleanup of properties contaminated with hazardous substances. . . . Any
    property contaminated or perceived to be contaminated by controlled hazardous
    substances or oil is eligible for participation in the VCP. . . . The VCP provides two
    types of final site approval documents for properties contaminated or perceived to
    be contaminated by controlled hazardous substances or oil: a [NFRD] and a
    certificate of completion. . . . [The] MDE issues a [NFRD] for an eligible property
    when [the] MDE approves the application package and determines that a remedial
    action plan . . . is not required. The determination states there are no further
    requirements related to the investigation of controlled hazardous substances or oil
    at the property. The determination is based on VCP specific land use and may
    contain certain land use requirements.
    U.S. ENVTL. PROT. AGENCY, CLEANING UP BROWNFIELDS UNDER STATE RESPONSE PROGRAMS –
    GETTING TO “NO FURTHER ACTION” (2015).
    16
    On July 1, 2002, Detrick Overlook retained Environmental Service & Technology
    Corporation (“ENSAT”) to “perform an extensive site characterization of the Waverley View
    [P]roperty” to satisfy the requirements for participation in the MDE VCP. PX 151 at 1.
    In November 2002, Detrick Overlook submitted a draft site characterization report to the
    MDE VCP, prepared by ENSAT, seeking a NFRD for the property. PX 151 at 1.
    On February 3, 2003, “the MDE requested additional information and further subsurface
    investigation.” PX 65 at 3.
    On November 11, 2003,12 Rocky Gorge Homes, LLC (“RGH”) and GAB Enterprises, Inc.
    (“GAB”) formed RGHGAB at Frederick, LLC (“RGHGAB”) to “buy, develop, and sell property
    in Frederick County.” PX 65 at 3. RGH was the managing member of RGHGAB, with 80 percent
    ownership; and GAB was a minority member, with 20 percent ownership. TR 78 (Anderson). At
    that time, Christopher Dorment was the Chairman, Chief Executive Officer (“CEO”), and majority
    owner of RGH; John Anderson was a minority owner of RGH; and Gary Berman was President
    of GAB. TR 78–79 (Anderson).
    On January 29, 2004, RGHGAB submitted an application to the MDE VCP seeking a
    NFRD for the Waverley View Property,13 as an inculpable person.14 PX 65 at 3; see also MD.
    DEP’T OF THE ENV’T, WAVERLY VIEW (Apr. 6, 2005).
    The next day, on January 30, 2004, RGHGAB purchased approximately 90 acres of land
    for $5,600,000 from Detrick Overlook, that included most of the Waverley View Property. 15 PX
    12
    See Articles of Organization, RGHGAB at Frederick, LLC, MD. SEC’Y OF STATE: MD.
    BUS. EXPRESS, https://egov.maryland.gov/BusinessExpress/EntitySearch (last visited Dec. 18,
    2017) (search by “Business Name” for “RGHGAB;” then follow the “W07656309” hyperlink
    under “Department ID;” then follow the “ARTICLES OF ORGANIZATION” hyperlink under the
    “Filing History” tab).
    13
    RGHGAB appears to have filed this application as a “prospective purchaser.” See
    Voluntary Cleanup Program Frequently Asked Questions, MD. DEP’T OF THE ENV’T,
    http://mde.maryland.gov/programs/Land/MarylandBrownfieldVCP/Pages/vcp_ info.aspx (last
    visited Dec. 5, 2017) (“[A]n application may be submitted by the responsible person for a
    particular property, and, if the property is being marketed for sale, a prospective purchaser may
    also submit an application seeking inculpable person status.”).
    14
    “An inculpable person, . . . means a person who, at the time of application for
    participation in the VCP, has no prior or current ownership interest in an eligible property and has
    not caused or contributed to contamination at the eligible property.” MD. DEP’T OF THE ENV’T,
    FACTS ABOUT: VOLUNTARY CLEANUP PROGRAM, INCULPABLE & RESPONSIBLE PERSON STATUS
    (2017).
    15
    WVI’s June 16, 2017 Opening Post-Trial Brief (“Pl. Post-Tr. Br.”) asserts that “[t]he
    [Waverley View] Property has been under the continuous control of Mr. Dorment since 2004.” Pl.
    Post-Tr. Br. at 4.
    17
    54. RGHGAB financed a portion of the purchase with a loan secured by a promissory note (the
    “BB&T Note”) held by BB&T Bank (“BB&T”). TR 123 (Anderson); see also GAB Enters.,
    Inc. v. Rocky Gorge Dev., LLC, 
    108 A.3d 521
    , 523 (Md. Ct. Spec. App. 2015) (“GAB v. RGD”)
    (“The parties secured the financing with a Promissory Note dated January 30, 2004 . . . held by
    BB & T Bank[.]”);16 In re RGHGAB at Frederick, LLC, Bankruptcy No. 11–10627PM, Adversary
    No. 11–0346PM, 
    2012 WL 1424684
    , at *1 (Bankr. D. Md. April 24, 2012) (“In re RGHGAB”)
    (“Rocky Gorge executed a promissory note on January 30, 2004, for $2.75 million[.]”).17 That
    same day, “[a]n ‘inculpable person status’ qualifying letter was issued to RGHGAB[.]” PX 65 at
    3; see also MD. DEP’T OF THE ENV’T, WAVERLY VIEW (Apr. 6, 2005). Thereafter, RGHGAB
    divided development of the Waverley View Property into two non-contiguous phases: Phase I,
    approximately 70 acres of land separated from Fort Detrick by Shookstown Road; and Phase II,
    approximately 23 acres of land directly adjacent to Fort Detrick. PX 70.
    On February 4, 2004, in order to file a new application addressing the MDE’s concerns
    regarding Detrick Overlook’s November 2002 Application, RGHGAB engaged Chesapeake
    GeoSciences, Inc. (“CGS”) to “determine the on-site extent . . . of contamination as a direct result
    of potential off-site migration from the adjacent Fort Detrick Military Reservation.” PX 151 at 1.
    Thereafter, CGS “excavat[ed] seventeen (17) test pits, install[ed] seven (7) [groundwater]
    monitoring wells,18 and . . . collect[ed] and analy[zed] soil, [groundwater], stream sediment, and
    surface water samples.” PX 151 at 1. The groundwater monitoring wells were installed “to depths
    of about 115 feet below ground surface” (PX 155 at 5), and “were constructed of 6-inch diameter
    steel casing,” except for GW-7 which “was constructed of 4-inch diameter . . . PVC [pipe]” (PX
    151 at 2–3; see also PX 88 at A-14 (Image 7)).
    16
    This opinion, by the Court of Special Appeals of Maryland, reversed the Circuit Court
    of Frederick County’s partial dismissal of a complaint filed by GAB on September 28, 2012,
    alleging, among other things, “that Mr. Dorment ‘secretly created [WVI] for the purpose of
    improperly transferring RGHGAB's assets to [WVI] and thus wiping out GAB's interest in
    RGHGAB.” GAB v. RGD, 108 A.3d at 527.
    17
    This opinion, by the United States Bankruptcy Court for the District of Maryland,
    dismissed a bankruptcy complaint filed by the Bankruptcy Trustee in RGHGAB’s involuntary
    bankruptcy proceeding, alleging, among other things, “that Mr. Dorment, [RGH], and [WVI] had
    ‘engaged in inequitable conduct’ and improperly engaged in self-dealing that harmed RGHGAB
    and its creditors.” GAB v. RGD, 108 A.3d at 526. The bankruptcy complaint arose from a petition
    for involuntary bankruptcy filed by GAB on January 11, 2011. In re RGHGAB, 
    2012 WL 1424684
    , at *3.
    18
    The monitoring wells are labeled: GW-1–GW-7. TR 433–34 (Anderson); see also PX
    76 (Figures 11A and 11B).
    18
    Image 7: CGS-Installed Monitoring Well.
    PX 88 at A-14 (Image 7).
    In April 2004, CGS provided a Site Characterization Report (the “2004 Site
    Characterization Report”) to RGHGAB summarizing CGS’s findings, including that “[n]o
    contaminants of potential concern . . . were identified in [groundwater], sediment, and surface
    water through generic risk-based screening utilizing MDE Cleanup Standards.” PX 151 at 15.
    Thereafter, RGHGAB submitted an application, including the 2004 Site Characterization Report,
    to the MDE VCP seeking a NFRD. TR 97 (Anderson).
    On September 3, 2004, the MDE issued a NFRD for the Waverley View Property (the
    “2004 NFRD”). PX 65 at 3; DX 4. The 2004 NFRD was conditioned on the Waverley View
    Property being used for “limited residential, commercial[,] or industrial purposes,” and explicitly
    excluded “use of groundwater.” DX 4 at PL003175.
    On September 13, 2004, the City of Frederick Planning Commission (the “Planning
    Commission”) approved RGHGAB’s Planned Neighborhood Development (“PND”) Master
    Plan.19 JX 20; PX 156 at 5; TR 112 (Anderson). The Planning Commission “conditioned [its]
    approval . . . on the preparation of ‘an environmental assessment’ to ensure that ‘no negative
    impacts from Fort Detrick Area B exist.’ The approval required either that an independent
    environmental consultant or the [MDE] concur that the property would suffer no negative impacts
    from Fort Detrick Area B.” PX 156 at 5. Another “condition of approval” required RGHGAB to
    19
    “Generally speaking, a [PND m]aster [p]lan . . . is a land use plan that designates major
    land uses, commercial, residential[, or] open space. It provides a general road network . . . [.] It
    also establishes a maximum density of development.” JX 30 at 11. In other words, a PND master
    plan is a “conceptual . . . plan.” JX 30 at 34.
    19
    “construct or contribute to five (5) major infrastructure improvements to roads and a sewer line
    extension.”20 DX 114 at 39–40.
    On April 6, 2005, the Planning Commission approved a “Preliminary Plan of Subdivision”
    for Phase I and Phase II of the Waverley View Property, authorizing the “construction of 732
    [residential] units, all of which could commence construction by 2011 so long as other
    infrastructure and development approvals were obtained[.]” PX 156 at 5.
    On April 24, 2006, the Planning Commission approved RGHGAB’s Final Site Plan21 for
    Phase I, allowing development of Phase I to begin. PX 120; PX 156 at 6.
    20
    The five “major infrastructure improvements” included:
    1. Construct[ing] the extension of a sewer outfall from Shookstown Road
    through the Bartgis property.
    2. Upgrad[ing] and reconstruct[ing] Shookstown Road for approximately
    1,600 linear feet through [the] Waverley View [Property], including a
    major stream crossing.
    3. Relocat[ing] and construct[ing] Waverley Drive from Waverley
    Elementary School to Shookstown Road.
    4. Provid[ing] an appropriate monetary contribution to the cost of the
    future extension of Old Camp Road, south of Shookstown Road to the
    Waverley View [Property] property line.
    5. Construct[ing] an approximately 2,100 linear foot section of
    Christopher’s Crossing, across the northwest boundary of the [Waverley
    View] Property, which road section would provide no access to [the]
    Waverley View [Property].
    DX 114 at 39–40.
    Improvements 1–3 were conditions on developing Phase I, and Improvements 4 and 5 were
    conditions on developing Phase II. DX 114 at 40. In January 2013, after negotiations, a “Deferral
    Agreement” between the City of Frederick and WVI was executed, permitting WVI, “in lieu of
    constructing a 2,100 linear section of Christopher’s Crossing, to pay a Regional Road
    Improvement Fee . . . in the amount of $880,000 to be paid upon application for building permits
    for the 293 units it proposed on . . . Phase II.” DX 114 at 40; see also TR 175–76 (Anderson).
    This “reduc[ed WVI’s] up-front financial outlay” requirement by “$2 million.” TR 175–76, 471
    (Anderson). As of the December 1, 2017 site visit, however, neither RGHGAB, nor its successor-
    in-interest WVI, had completed each of the remaining “required” improvements. See SVTR 36–
    37.
    21
    “The final site plan . . . establishes . . . finer details of the development, unit locations,
    landscaping, lighting, sidewalk locations, all of that.” JX 30 at 12. “After . . . [final] site plan
    approval, the next course of action is . . . to . . . fine-tune engineering of roadways, water and sewer
    infrastructure, things of that nature . . . through [the] Engineering Department. And then it would
    move into building permits.” JX 30 at 12–13.
    20
    On June 29, 2006 and December 7, 2006, RGHGAB purchased two smaller land parcels,
    comprising approximately 2.8 acres of land for $1,200,000. PX 55; PX 56. These parcels, together
    with the land purchased by RGHGAB on January 30, 2004, became the entirety of the Waverley
    View Property.
    By September 12, 2007, the principal amount of the BB&T Note had grown, so that
    RGHGAB “owe[d] the bank $9 million,” much more than the value of the Waverley View
    Property, i.e., “around $2 million.” TR 122–29 (Anderson); see also PX 152 at WVI00106322;
    GAB v. RGD, 108 A.3d at 524 (“As time went by, the principal amount of the [BB&T] Note was
    amended, ballooning to nearly $9 million as of September 12, 2007[.] . . . By late 2009, the
    [Waverley View] Property's value had dropped far below the increasing amount due under the
    [BB&T] Note.”); In re RGHGAB, 
    2012 WL 1424684
    , at *1 (“Rocky Gorge executed [the BB&T
    N]ote on January 30, 2004, for $2.75 million, later increased to $8.95 million on September 12,
    2007.”)
    On August 19, 2008, RGHGAB submitted a Final Site Plan for Phase II of the Waverley
    View Property to the Planning Commission for approval. PX 156 at 6. This plan quickly
    proceeded through the review process and the Planning Commission provided “review comments”
    to RGHGAB. TR 119 (Anderson). Late in 2008, however, a recession hit Maryland’s housing
    market. PX 156 at 6; TR 119–20 (Anderson); TR 1220–21 (McPherson). As a result, RGHGAB
    withdrew the Final Site Plan for Phase II and never resubmitted it.22 JX 20; PX 120; PX 156 at 6;
    TR 471 (Anderson).
    On June 23, 2010, Mr. Dorment and several other investors formed WVI, with Mr.
    Dorment as the managing member, to acquire the BB&T Note. PX 152 at WVI00106335; see also
    Articles of Organization, Waverley View Investors, LLC, MD. SEC’Y OF STATE: MD. BUS.
    EXPRESS, https://egov.maryland.gov/BusinessExpress/EntitySearch (last visited Dec. 18, 2017)
    (search for “Waverley View Investors;” then follow the “W13627708” hyperlink under
    “Department ID;” then follow the “ARTICLES OF ORGANIZATION” hyperlink under the
    “Filing History” tab); TR 78 (Anderson).
    In September 2010, WVI purchased the BB&T Note for $2.2 million. TR 126 (Anderson)
    (“[T]he [BB&T N]ote was purchased by [WVI] from the bank. . . . I believe it was $2 million,
    $200,000 cash and then a deferral for the $2 million. So, it was $2.2 million.”); see also GAB v.
    RGD, 108 A.3d at 525 (“Rocky Gorge assigned the note purchase agreement to [WVI], completing
    the transaction . . . on September 17, 2010.”).
    On September 23, 2010, CGS conducted a “Site Investigation” of the Waverley View
    Property. PX 150 at PL002152. The Site Investigation entailed “the collection of 12 soil samples
    from six locations and one sediment sample.” PX 150 at PL002152. From these samples CGS
    concluded, in an October 29, 2010 Site Investigation Report (the “2010 CGS Site Investigation
    Report”), that the Waverley View Property exhibited “normal background conditions” and that
    22
    Subsequent promotional materials concerning the Waverley View Property provided that
    “[f]inal plan approval [of Phase II] will be necessary and will need to be completed by the
    purchaser . . . offering the potential to modify the current plan.” PX 29 at WVI00007847.
    21
    “Fort Detrick’s historic testing of Agent Orange does not appear to have impacted the [property].”
    PX 150 at PL002153.
    In October 2010, after RGHGAB defaulted on the BB&T Note, WVI began foreclosure
    proceedings on the BB&T Note (TR 82, 130–31 (Anderson);23 see also GAB v. RGD, 108 A.3d at
    525 (“[I]n October 2010, Waverley undertook to foreclose on the [p]roperty.”)).
    In January 2011, before the foreclosure proceedings were completed, GAB filed a petition
    for involuntary bankruptcy that halted foreclosure and subjected RGHGAB to involuntary
    bankruptcy proceedings. TR 131–35 (Anderson); see also GAB v. RGD, 108 A.3d at 525 (“GAB
    . . . filed a Petition for Involuntary Bankruptcy (Chapter 7) in the Bankruptcy Court on January 11,
    2011. . . . The filing brought the foreclosure proceeding to an abrupt halt[,] because of the
    automatic stay that issued from the Bankruptcy Court[.]”). As a result, RGHGAB’s assets,
    including the Waverley View Property, were turned over to a Bankruptcy Trustee. TR 132–33
    (Anderson).
    After negotiations with the Bankruptcy Trustee, WVI offered to purchase the Waverley
    View Property out of bankruptcy for $4,000,000,24 based on a 2010 appraisal value of “plus or
    [minus] $2 and a half million.” TR 133–34 (Anderson); see also PX 152 at WVI00106324,
    WVI00106350. The Bankruptcy Trustee solicited other offers in order to “bid [WVI’s offer] up
    some;” however, no other offers materialized. TR 133–34 (Anderson); see also PX 152.
    On November 15, 2012, WVI purchased the Waverley View Property out of bankruptcy
    for $4,000,000 “paid via credit bid.” PX 53; PX 152 at WVI00106363; TR 134–35 (Anderson);
    23
    As Mr. Anderson testified at trial:
    [WVI] purchase[d] the bank’s position. So, [WVI] is now effectively the
    lender to RGHGAB, who has an asset that is not performing, doesn’t have a way to
    make payments on the loan, though they weren’t in default with BB&T. I mean,
    they would have been in default in this. It was just–there was no more money.
    So, [WVI], in its role as the–sort of the bank, the owner of the deed of trust
    on the property, as a lender can do, foreclosed on its rights under the deed of trust,
    which was secured by the property. So, the remedy is you go through a foreclosure
    and then the lender, after the foreclosure proceeding, owns the property free and
    clear of any other liens on the property. It just wipes out everything else. So,
    RGHGAB’s ownership is gone. And, now, [WVI] owns both the deed of trust on
    the property and the actual property.
    TR 130–31 (Anderson).
    24
    WVI’s $4,000,000 offer was a “credit bid,” i.e., a non-cash bid, made against the amount
    owed on the BB&T Note owned by WVI (PX 152 at WVI00106363; see also TR 135 (Anderson)),
    which, as of June 30, 2012, was $10,160,787 (PX 152 at WVI00106334).
    22
    DX 88 at 28. That same day, however, CL Group LLC (“CL Group”) appraised the Waverley
    View Property as having an “as is” value of $12,800,000.25 PX 125 at WVI00006628–30.
    On September 19, 2014, WVI entered into a “Sales/Purchase Agreement” with S.L.
    Nusbaum Realty Co. (“Nusbaum”), pursuant to which Nusbaum agreed to purchase approximately
    13.72 acres of Phase I for $5,000,000. PX 127 at WVI00109347, WVI00109377. Nusbaum’s
    obligation to purchase the property was subject to numerous conditions, some of which were to be
    undertaken by WVI. PX 127; DX 112, TR 243–46 (Anderson). In August 2016, WVI
    consummated the sale of the property to Nusbaum. TR 215 (Anderson).
    C.       The Government’s26 Interactions With RGHGAB at Frederick, LLC To
    Gain Access To The Waverley View Property.
    On March 10, 2011, the United States Army Corps of Engineers, Baltimore District (the
    “Army Corps”) sent a letter to RGHGAB27 requesting permission to enter the Waverley View
    25
    The CL Group appraisal, however, provided that:
    The values estimated in this report are based upon the assumption that the
    property is not negatively affected by the existence of hazardous substances or
    detrimental environmental conditions.
    As previously noted, Fort Detrick adjoins the property to the northeast. In
    2009 the [EPA] put the site of major toxic waste contamination at Fort Detrick in
    Frederick on its Superfund [NPL]. Environmental clean-up specialists created a
    landfill “cap” on the area known as “Area B” in a remote northwest corner of the
    Fort Detrick installation. In 1992, off-post contamination from Area B was first
    detected in residential wells. The remediation project at the installation should be
    completed by 2014.
    The Kristen Renee Foundation has launched a campaign to research and
    investigate the findings associated with Fort Detrick “Area B” groundwater. . . . [I]t
    should be emphasized that the subject was submitted to the State of Maryland’s
    [VCP] and later issued a letter of [NFRD].
    Per the subject representative, with regard to the site’s close proximity to
    Area B, tests have revealed no contamination on the subject property. The future
    residents of Waverley View will be served through public water and sewer, so any
    potential for groundwater issues is further removed.
    PX 125 at WVI00006703 (emphasis in original omitted and emphasis added).
    26
    Numerous agencies, including the Army and the EPA, interacted with various owners of
    the Waverley View Property, on behalf of the Government, seeking access to the property.
    27
    The Government asserts in its July 14, 2017 Post-Trial Response Brief (“Gov’t Post-Tr.
    Resp. Br.”) that, as of March 10, 2011, the Army believed that RGHGAB owned the Waverley
    View Property; unbeknownst to the Army, however, the property was under the control of the
    Bankruptcy Trustee from January 11, 2011 to November 15, 2012, and RGHGAB never advised
    23
    Property for the purpose of “conducting site investigation activities in connection with the Fort
    Detrick Area B Groundwater Remedial Investigation[.]” DX 16 at US007141. This letter included
    a “Right of Entry . . . for Environmental Response Form” (the “ROE form”) and requested that
    RGHGAB “sign and return the [ROE] form” to the Army Corps. DX 16 at US007138. The letter
    and the ROE form were sent to an incorrect mailing address, however, and were returned as
    “undeliverable.” TR 924–25 (Gortva).
    On March 22, 2011, the Army Corps resent the letter and the ROE form to RGHGAB. DX
    16 at US007134. The Army Corps did not receive a response. DX 17 at US001211.
    On May 5, 2011, the Army Corps sent another letter and the ROE form to RGHGAB, again
    requesting permission to enter the Waverley View Property. DX 16 at US007138–39; DX 17.
    On May 9, 2011, Mr. Anderson, on behalf of RGHGAB, sent a letter to the Army Corps
    “in response to [its] request for right-of-entry.” JX 1. The letter provided “Your request is denied.
    Any entry on the [Waverley View] Property by the . . . [Army Corps] or [its] contractors will be
    treated as trespassing.” JX 1. The letter also provided that, although RGHGAB “appreciate[d] the
    efforts to clarify the impact of the Fort Detrick Area B groundwater on the area, [RGHGAB] ha[d]
    already performed extensi[ve] investigation on the [Waverley View] Property,” and included
    copies of numerous documents as evidence on a compact disc (“CD”).28 JX 1.
    On May 11, 2011, Mr. Anderson contacted Christine Milligan, Realty Specialist for the
    Army Corps, to inform her of the May 9, 2011 letter and stated that RGHGAB “[didn’t] want to
    be the ‘bad guy’ but [was] declining to sign the ROE [form].” DX 16 at US007134. Thereafter,
    the Army reviewed the documents on the CD included with Mr. Anderson’s May 9, 2011 letter to
    determine whether there was a continued need for access to the Waverley View Property. TR
    1039 (Gortva). After reviewing the documents, however, the Army decided that it could not accept
    the results of RGHGAB’s testing in lieu of conducting its own groundwater monitoring. TR 925
    (Gortva).
    In October 2011, the Army took groundwater samples from several deep monitoring wells
    in Area B-11, located about 20 feet from the Waverley View Property, that showed “significantly
    elevated” levels of contaminants. TR 926–27 (Gortva); see also PX 65 at 4 (Groundwater
    sampling from these wells showed “contamination at concentrations 1000 times greater than the
    MCL[.]”).
    the Army of the bankruptcy proceedings. Gov’t Post-Tr. Resp. Br. at 16; see also, e.g., TR 420,
    490 (Anderson).
    28
    The CD included the following documents: (1) a “Preliminary Subsurface Exploration,”
    dated December 18, 2000; (2) the 2004 Site Characterization Report; (3) a “Phase I ESA
    Screening,” dated August 25, 2004; (4) the 2004 NFRD; (5) a “Professional Opinion Regarding
    Testing of Agent Orange at Fort Detrick;” (6) a “Site Investigation Proposal,” dated September
    14, 2010; (7) a “Laboratory Report,” dated October 12, 2010; and (8) the 2010 CGS Site
    Investigation Report. JX 1.
    24
    On October 17, 2011, the Army Corps sent another letter to Mr. Anderson, confirming
    receipt of RGHGAB’s “acknowledgement and intent to decline participation in . . . [the] site
    investigation activities for the Fort Detrick Area B Groundwater Remedial Investigation[.]” DX
    16 at US007135. Therein, the Army Corps stated that “[it] would like the opportunity to discuss
    the program and address any of [RGHGAB’s] concerns or questions” and provided a list of various
    times during which the Army Corps would be “in [RGHGAB’s] area and available to meet[.]” DX
    16 at US007135. The letter included a “copy of the ‘P[rogram] O[verview] P[amphlet]’ for the
    Fort Detrick Area B Groundwater Remedial Investigation . . . [and] an additional copy of the
    [ROE] form.” DX 16 at US007135.
    Sometime in late October 2011, Mr. Anderson contacted Ms. Milligan again to inform her
    that “even though he [was] not inclined to sign [the] ROE [form], he [would] meet with [the Army
    Corps], at his office, to hear what [the Army Corps had] to say.” DX 16 at US007134; TR 148
    (Anderson).
    On November 16, 2011, Messrs. Anderson and Dorment met with representatives from the
    Army Corps, including John Buck, Project Manager, at RGH’s office in McLean, Virginia. DX
    22; TR 150–51 (Anderson). At this meeting, the Army Corps informed Messrs. Anderson and
    Dorment of the “significantly elevated” levels of contaminants found less than 20 feet from the
    Waverley View Property (TR 926–27 (Gortva)), and again requested access to the Waverley View
    Property (TR 151 (Anderson)). Relying on the 2004 NFRD, however, Messrs. Anderson and
    Dorment indicated that they believed the Waverley View Property was “neat [and] clean.” TR
    151 (Anderson). Thereafter, when the Army Corps declined to “offer . . . any compensation for
    the use of [the] property . . . [Messrs. Anderson and Dorment] said, thank you very much, but
    [access is] denied.” TR 151 (Anderson).
    On February 7, 2012, the Army Corps sent another letter to Mr. Anderson, requesting
    permission to enter the Waverley View Property. JX 3. This letter stated that access to the
    Waverley View Property was “critical to achieving [the Army’s] project goals and no viable
    alternative locations exist.” JX 3 at WVI00009453. The letter included “a modified [ROE form]
    that contain[ed] non-intrusive activities that may be more amenable to [RGHGAB].”29 JX 3 at
    WVI00009453. Again, RGHGAB refused to grant the Army access. TR 152 (Anderson).
    On September 6, 2012, the MDE contacted the Army to report that
    the owner of the Waverley [View] Property . . . ha[s] requested a “comfort letter”
    from the [VCP] regarding the NFRD that [the] MDE issued for the property in
    2004. They hoped that [the] MDE would be willing to state that there would be no
    known health risk if the property were to be developed under the constraints of the
    [2004] NFRD (essentially no groundwater use). [The] MDE politely declined to
    29
    The modified ROE form “eliminate[d] all activities on [the Waverley View P]roperty
    with the exception of access to the stream to conduct stream surveys, collect surface water and
    sediment samples, and conduct dye trace sampling/monitoring activities.” JX 3 at WVI00009453.
    25
    issue such a letter, citing the unknown . . . extent of groundwater contamination
    associated with Area B.
    DX 33 at US000157.
    On November 8, 2012, the Army Corps sent another letter to Mr. Anderson, requesting
    permission to enter the Waverley View Property, emphasizing that access was “critical for the
    completion of [the Army’s] efforts.” PX 7 at WVI0008362. The letter also included a “Program
    Overview Pamphlet” and an original, unmodified, ROE form. PX 7 at WVI00008365–69.
    RGHGAB continued to refuse to grant the Army access. TR 152 (Anderson).
    On November 15, 2012, despite the Army’s “susp[icion of] groundwater contamination on
    [Phase II] of [the] Waverley View [Property],” and without “further environmental testing or other
    due diligence” (TR 393 (Anderson)), WVI purchased the Waverley View Property out of
    bankruptcy (PX 53; TR 134–35 (Anderson)).
    D.      The Government’s Interactions With Waverley View Investors, LLC To
    Gain Access To The Waverley View Property.
    On February 8, 2013, the Associate Director of the EPA’s Office of Federal Facility
    Remediation and Site Assessment, sent a letter to Mr. Anderson,30 requesting permission to enter
    the Waverley View Property. DX 44. This letter “strongly urge[d]” [Mr. Anderson] to consent to
    federal government access to undertake groundwater sampling on [the Waverley View Property]
    . . . as requested by the [Army.]” DX 44 at US000008. The letter also indicated that the “EPA
    believe[d] the proposed work [was] necessary and appropriate to better understand the nature and
    extent of contamination migrating from the Fort Detrick Area B Superfund NPL [S]ite, and to
    ensure the protection of human health and the environment.” DX 44 at US000008. The letter
    stated that the Waverley View Property “lies immediately adjacent to the Area B-11 trenches,
    where contaminated groundwater has been detected flowing in the direction of [the Waverley View
    P]roperty[,]” and that the “EPA and the Army believe[d] . . . that the groundwater contaminant
    plume extend[ed] beneath” the Waverley View Property. DX 44 at US000008. The letter also
    emphasized that,
    [r]epresentatives of the United States government have authority granted by federal
    law to gain access to [the] property to perform response activities related to the
    contaminated groundwater plume migrating from the Fort Detrick Area B
    Superfund NPL [S]ite. Under Section 104(e)(1) of [CERCLA], any officer,
    employee, or representative of the President has the authority to take action at any
    facility, property, or location, at which there is a reasonable basis to believe that
    there may be a release or threat of release of a hazardous substance, pollutant, or
    contaminant. Section 104(e)(1) extends the entry authority to any property or
    30
    Although WVI owned the Waverley View Property by this time, and Mr. Anderson
    “[had] no ownership, [and] no role in [WVI]” (TR 78 (Anderson)), the EPA’s February 8, 2013
    letter was nevertheless received by Mr. Dorment, the managing member of WVI (TR 644
    (Dorment)).
    26
    location, such as [the Waverley View P]roperty, that lies adjacent to any place, such
    as the Fort Detrick Area B Superfund NPL [S]ite, where such representative has a
    reasonable basis to believe that there may be a release or threat of release of a
    hazardous substance, pollutant, or contaminant.
    Section 104(e)(3) of CERCLA gives the federal government the authority
    to gain entry at reasonable times to any place, including [the Waverley View
    P]roperty, where there may be a release or threatened release of a hazardous
    substance, pollutant, or contaminant, or where entry is needed to determine the need
    for response, to determine the appropriate response, or to effectuate a response
    action under CERCLA.
    Under CERCLA, the categories of parties liable for investigation and
    cleanup costs include generators and transporters of hazardous substances disposed
    of at a facility or property, and owners and operators of the facility or property at
    the time of disposal, as well as current owners and operators. (See Section 107(a)
    of CERCLA, 
    42 U.S.C. § 9607
    (a).) Section 107(q) of CERCLA, 
    42 U.S.C. § 9607
    (q), provides a limitation from CERCLA liability, under certain conditions,
    for a person who owns property that is contiguous, or is otherwise similarly
    situated, to a facility or property that is the only source of contamination found on
    that person’s property. However, one of the conditions for the limitation from
    liability is that the owner of the contiguous property must provide full cooperation,
    assistance, and access to authorized persons to conduct response actions. See 
    42 U.S.C. § 9607
    (q)(l)(A)(iv). If you do not agree to provide access for the work
    authorized by CERCLA, you will no longer have the benefit of the “contiguous
    properties” defense to liability provided by Section 107(q) of CERCLA.
    Furthermore, CERCLA Sections 104(e)(5)(A) and (B), 42 U.S.C.
    9604(e)(5)(A) and (B), provide the federal government with enforcement
    authorities to issue a unilateral order to the property owners to grant the request for
    access for response actions, including sampling and other investigation activities;
    and, if access is not granted, to seek a court order to compel cooperation with such
    unilateral order. If the United States does not obtain . . . consent for access to
    perform the necessary sampling on [the Waverley View P]roperty related to the
    contaminated groundwater plume migrating from the Fort Detrick Area B
    Superfund NPL [S]ite, the United States may exercise any other options available
    to it under the law to obtain access, which could include issuing an administrative
    order for access or seeking a warrant for access.
    DX 44 at US000009.
    On February 13, 2013, The Frederick News-Post, after obtaining a copy of the EPA’s
    February 8, 2013 letter, reported that “[t]he federal government wants access to a residential
    development site near Fort Detrick's Area B to drill wells and complete groundwater testing[,]”
    but the owner “has repeatedly ignored requests from the Army to gain access to monitor the 90-
    27
    acre Shookstown Road property.” DX 48 at US144422. On that same day,31 Thomas Lynch, an
    attorney for Messrs. Anderson and Dorment, sent a letter to the EPA agreeing to meet to discuss
    “a plan for addressing [the] EPA’s and the Army’s request.” DX 48 at US144420. The letter also
    provided that “the [Waverley View P]roperty is in the process of being reviewed for purposes of
    development by the City of Frederick and the media has commented in news stories today about
    the request for further investigation on [the] property[,]” and attached a copy of The Frederick
    News-Post’s article.
    On February 25, 2013, representatives from the Army, an Army environmental contractor,
    Arcadis, and the Army Corps met with Messrs. Dorment, Anderson, and Lynch in Frederick,
    Maryland. DX 126. At this meeting, the Army provided Messrs. Dorment, Anderson, and Lynch
    with a presentation prepared by Arcadis, entitled “Waverley Property Right of Entry Discussion,”
    that included a map of proposed drilling locations, all on Phase II of the Waverley View Property.
    DX 52.
    On March 14, 2013, Messrs. Dorment, Anderson, and Lynch met with representatives from
    the Army, the EPA, and the MDE to discuss “on-going efforts to both identify remediation issues
    at Area B and ask that [WVI] grant access to the [Waverley View P]roperty to the [Army] to
    conduct groundwater sampling[.]” DX 125. At this meeting, Mr. Dorment “expressed his
    frustration that the Army [wasn’t] moving faster to financially compensate him for the damage
    . . . caused to his property.” DX 125. Mr. Dorment was advised that he would need to “file a tort
    claim . . . to begin the compensation process.” DX 125.
    Thereafter, on March 25, 2013, WVI filed an administrative tort claim against the Army
    claiming $37,199,488 in property damage, of which $12,800,000 represented the appraisal value
    of the Waverley View Property. PX 1 at PL000873–85.32
    On April 24, 2013, Messrs. Dorment, Anderson, and Lynch again met with representatives
    from the Army, the EPA, and the MDE, in Philadelphia, Pennsylvania, together with:
    representatives from Arcadis; and WVI’s environmental contractor, S.S. Papadopulos &
    Associates, Inc. (“SSPA”). DX 126. At this meeting, SSPA presented “justifications and
    reasoning why [Phase I] of the Waverley [View P]roperty did not need to have any sampling
    conducted on it.” TR 941–42 (Gortva). WVI’s concern focused on Phase I, because “[t]hey [had]
    ‘offers on the table’ . . . for [the] Phase I lots.” DX 126; see also TR 942 (Gortva). After the
    presentation, a tentative agreement was reached to allow the Army to access Phase II of the
    Waverley View Property. TR 945 (Gortva).
    31
    In a July 7, 2013 “mid-year update,” Mr. Dorment indicated to WVI’s investors that
    “[l]ocal media has extensively covered [WVI’s interactions with the Army Corps] which impeded
    our sales program of the parcels in Phase [I] for the time being. The reality is that our site has
    passed test after test . . . , but the ‘perception’ of a problem can trump the reality.” JX 22 at
    WVI00008412.
    32
    WVI’s administrative tort claim was later dismissed without WVI “collect[ing] any
    judgement from the United States.” TR 716–17 (Dorment).
    28
    On May 10, 2013, after “weeks . . . [of] negotiations” (PX 10 at WVI00004486), in which
    WVI was represented by counsel (JX 22; TR 724–25 (Dorment)), and during which WVI
    “exchanged several drafts of [a ROE form] with the EPA and . . . the Army” (TR 725 (Dorment)),
    the Army Corps, on behalf of the Army, sent a final ROE form (the “WVI ROE”) to Mr. Lynch,
    and indicated that “[i]f acceptable, please have [WVI] sign the [WVI ROE] and then return . . . for
    signature by the [Army]” (DX 77). On that same day, Mr. Dorment, on behalf of WVI, signed the
    WVI ROE, granting
    the Government33 an irrevocable right to enter in, on, over and across [34.75 ± acres
    of Phase II (the “ROE Property”)], for a period not to exceed eighteen (18) months,
    unless further extended by [a]greement of the parties commencing on May 14,
    2013, and running through November 13, 2014, or, if sooner, the date of completion
    of the [R]emedial [I]nvestigation.
    JX 5 at US000001, US000004.
    The WVI ROE also granted
    the Government . . . the right to store, move, and remove equipment and supplies;
    investigate and collect samples . . . ; construct, operate, maintain, alter, repair, and
    remove groundwater monitoring wells, appurtenances thereto, and other devices
    for the monitoring of contamination in soil, air, and water; and, perform any other
    such work which may be necessary and incident to the Government’s use for the
    investigation and determination of need for response on [the ROE Property.]
    JX 5 at US000001–02.
    In exchange, the Army and the EPA “agree[d] to provide [WVI with] a copy of all validated
    laboratory results derived from [the] Government’s investigation on the [ROE Property] within a
    reasonable time, but in no event later than four (4) weeks after the completion of such validated
    laboratory results.” JX 5 at US000002. The Army and the EPA also promised that, “[if] any action
    of the Government’s employees or agents in the exercise of [the WVI ROE] results in damage to
    the real property, the Government will . . . either repair such damage or make an appropriate
    settlement with [WVI].” JX 5 at US000003.
    The WVI ROE also provided the following:
    3. All tools, equipment, and other property taken upon or placed upon the
    [ROE Property] by the Government shall remain the property of the Government
    and may be removed by the Government at any time within a reasonable period,
    not to exceed thirty (30) days, after the expiration of [the WVI ROE]. However, if
    it appears from the monitoring results that they remain necessary for the continuing
    investigation, or for the monitoring and assessment of the need for any necessary
    response action, the monitoring wells installed by the Government shall remain the
    The WVI ROE defines “Government” to include both the Army and the EPA. JX 5 at
    33
    US000001.
    29
    property of the Government, and may be maintained on the land, subject to further
    extension of [the WVI ROE] by the parties.
    *       *       *
    5. [WVI] expressly reserves any and all rights it may have to make a claim
    under the Takings Clause of the Fifth Amendment, U.S. Const., amend. V. The
    Government acknowledges this reservation without any concession that any such
    rights or claim may exist.
    JX 5 at US000003–04.
    In addition, the WVI ROE included a map showing the proposed location of “drilling
    areas” and described the “Scope of Work” as follows:
    1. Evaluation, logging, surveying, measuring, and testing of existing wells
    (GW-1, GW-2, GW-3, GW-4) on the [ROE Property], including regular access
    during the groundwater tracer study (e.g., weekly, biweekly, or monthly for the
    duration of the study and/or right-of-entry period).
    2. Drilling, logging, and borehole testing in three areas on the [ROE
    Property] (see Figure 1), including rig access to each drill area, monitoring well
    construction (multiple), surveying, measuring, and testing of completed wells for
    the duration of the right-of-entry period. Any other drilling areas identified by [the]
    EPA, [the] MDE, or the Army would be restricted to the [ROE Property].
    3. Access to any streams, seeps, springs, or other surface water features that
    may exist on the [ROE Property] for surveying, monitoring, and sampling[.]
    JX 5 at US000006.
    30
    JX 5 at US000006.
    On May 24, 2013, Mr. Dorment sent a letter to the Army and the EPA, reiterating that: (1)
    he felt pressured into signing the WVI ROE; (2) the Army and the EPA were interfering with
    WVI’s ability to develop the Waverley View Property; (3) WVI had “made abundantly clear to
    [the Army and the EPA] that the [Waverley View Property] is valuable for real estate development
    purposes[;]” (4) WVI “ha[d] concrete plans to develop” the Waverley View Property because
    “[m]arket conditions [were then] quite favorable[;]” and (5) WVI’s “business plans [were]
    jeopardized by [the Government’s] activities.” PX 10 at WVI00004486. Mr. Dorment concluded
    that “if [the Army] require[s] a substantial and/or prolonged use of [the Waverley View P]roperty,
    [WVI] expect[s] a good faith offer to purchase the property at fair market value and to do so soon.”
    PX 10 at WVI00004487.
    31
    On July 7, 2013, in a “mid-year update,” Mr. Dorment advised WVI’s investors that the
    Army has
    enlisted Ben Cardin, the junior senator from Maryland, to offer an amendment to
    the Defense appropriations bill authorizing Fort Detrick to purchase [the] Phase [II]
    section. [The Army] used a figure of 8 million dollars in the amendment for the
    acquisition.34
    [WVI] currently [has] two lobbyists and a team of six lawyers working on
    advocacy for the amendment as well as pursuit of the [administrative] tort claim.
    Although this effort is expensive, and a bit frustrating, from an investor’s viewpoint
    there is a great deal of equity in this property[.] . . . [I]f the Army paid 8M for 40%
    of the property, the valuation for the whole property would grow extensively so we
    see opportunity in crisis.
    JX 22 at WVI00008412–13.
    On, or just prior to, November 21, 2013, the Army entered the Waverley View Property
    pursuant to the terms of the WVI ROE, to construct a gate35 and gravel access road. TR 199
    (Anderson). The gravel access road consisted of several inches of stone and was “20 [to] 25 feet
    wide and hundreds of feet long.” TR 200 (Anderson); TR 953 (Gortva); see also PX 88 at A-14
    (Image 8). The stone was laid upon “geotextile fabric” to make removal of the gravel access road
    easier. TR 953 (Gortva); SVTR 21–22, 38.
    34
    Contrary to Mr. Dorment’s statement, John Tesner, Director for Restoration in the Office
    of the Deputy Assistant Secretary of the Army for Environmental, Safety, and Occupational
    Health, testified that the Army never “approach[ed] members of Congress about the possibility of
    purchasing the Waverley View [P]roperty.” TR 1335–36 (Tesner).
    35
    During the December 1, 2017 site visit, WVI’s counsel stated that the gate is not located
    on the Waverley View Property; instead, the gate is situated on the boundary between the property
    and Fort Detrick. SVTR 37–38. Therefore, because the gate is not located on the Waverley View
    Property, the installation and continued presence of the gate does not constitute a taking of WVI’s
    property. See Oscanyan v. Arms Co., 
    103 U.S. 261
    , 263–64 (1880) (holding counsel’s statement
    during a trial binding on client); see also Jones v. Morehead, 
    68 U.S. 155
    , 165 (1863) (holding
    that a client is bound by his counsel’s statements, despite evidence to the contrary).
    32
    Image 8: Gravel Access Road on Phase II.
    PX 88 at A-14 (Image 8).
    In December 2013, drilling began on Phase II of the Waverley View Property. TR 949
    (Gortva). At times, drilling could not be performed in the planned location, because of certain
    geologic features that posed a risk of sink holes, requiring the location to be moved or “offset.”
    TR 949–50 (Gortva). When these features were encountered, the Army would contact Mr. Lynch
    to inform WVI of the proposed offset location where the Army wanted to install an alternative
    monitoring well. TR 950, 1142–44 (Gortva); see also DX 127. The Army, however, never
    received any response from WVI. TR 951 (Gortva). Nevertheless, four deep monitoring wells36
    and eleven shallow monitoring wells (or temporary monitoring wells) were installed on Phase II
    of the Waverley View Property.37 TR 951–52 (Gortva).
    The deep monitoring wells are approximately the size of a “dinner plate” in diameter. TR
    335 (Thomson). These wells are “installed into the bedrock” (TR 951 (Gortva)), range in depth
    36
    A fifth deep monitoring well, labeled WVLY-4, was “pilot” drilled but abandoned “due
    to sinkhole concerns.” PX 86; TR 1058 (Gortva); SVTR 36.
    37
    The deep monitoring wells are labeled: WVLY-1–WVLY-3 and WVLY-5; and the
    shallow monitoring wells are labeled TW-1–TW-11. PX 76 (Figures 11A and 11B). The
    Government also was given access to four of the preexisting CGS-installed monitoring wells
    labeled: GW-1–GW-4. JX 5 at US000006.
    33
    from 142 to 400 feet below the ground surface (PX 86), and feature “steel casings that typically
    go down to a depth of 30 to 40 feet” (TR 1008 (Gortva)). The shallow monitoring wells on the
    other hand, are constructed of smaller diameter “PVC pipe,” and are “only installed down through
    the dirt overburden” (TR 952, 955–56 (Gortva)), approximately 10 to 15 feet below the ground
    surface (SVTR 36). The deep monitoring wells project “2 ½ [ to] three feet” above ground and
    are surrounded by concrete and bollards, whereas the shallow monitoring wells project “18 inches”
    above ground and “[t]here is no surface casing . . . [or] protective bollards.”38 TR 951, 955–56,
    1159–60 (Gortva); see also PX 68 (Figures 1, 4).
    Figure 1: Deep Monitoring Well on Phase II.
    PX 68 (Figure 1).
    38
    If necessary, all the monitoring wells can be “cut down so [as to be] slightly below
    ground surface,” and the bollards may be removed. TR 507 (Gortva); see also DX 120 (showing
    “flush-mounted” monitoring wells installed at Cameron Station, a neighborhood community in
    Alexandria, Virginia).
    34
    Figure 4: Shallow Monitoring Well on Phase II.
    PX 68 (Figure 4).
    The Army did not detect PCE in deep monitoring wells WVLY-3 and WVLY-5, however,
    “very low[]level[s]” of PCE were detected in deep monitoring well WVLY-2. PX 76 (Figure
    11A); TR 954 (Gortva). TCE was not detected in deep monitoring wells WVLY-2, WVLY-3, or
    WVLY-5. PX 76 (Figure 11B); see also TR 954 (Gortva). Levels of PCE and TCE, however,
    were detected in deep monitoring well WVLY-1 at 12 parts per billion and 340 parts per billion
    respectively, with the level of TCE exceeding the MCL by “50 times.” TR 355–56 (Thomson).
    Deep monitoring well WVLY-1 is located closest to Area B of Fort Detrick, “about 90 to 100 feet”
    away. PX 76 (Figures 11A and 11B); TR 355–56 (Thomson). PCE and TCE also were detected
    in several shallow monitoring wells along the boundary between Phase II of the Waverley View
    Property and Area B of Fort Detrick. PX 76 (Figures 11A and 11B); TR 954–55 (Gortva). Overall,
    however, the levels of PCE and TCE detected on Phase II “were significantly lower than the [levels
    detected] . . . on Fort Detrick.” TR 956 (Gortva).
    35
    PX 76 (Figure 11A).
    36
    Figure 11A – Concentration of PCE on Phase II.
    PX 76 (Figure 11B).
    37
    Figure 11B – Concentration of TCE on Phase II.
    In August 2014, the Army contacted Mr. Lynch to inquire about a “possible extension” of
    the WVI ROE. JX 7 at WVI00009396. On August 27, 2014, Mr. Lynch sent an email to the
    Army, “asking for a written request.” JX 7 at WVI00009396.
    On October 16, 2014, the Army Corps, on behalf of the Army, sent a letter to Mr. Dorment
    requesting a “one year extension of [the WVI] ROE, through November 13, 2015 . . . [because
    c]ontinued access [was] needed . . . due to the difficulties of, and delays from, attempting to
    successfully drill monitoring wells in the karst39 geology underlying [the Waverley View
    P]roperty[.]” JX 6 at WVI00009383. This letter included a copy of a ROE form indicating that it
    would expire on November 13, 2015 (the “renewal ROE”). JX 6 at WVI00009392–95.
    On October 24, 2014, Mr. Dorment sent a letter to the Army Corps, refusing to grant the
    extension requested in the Army Corps’ October 16, 2014 letter. JX 7.
    On October 31, 2014, WVI “sent a letter to the [United States Department of Justice (the
    “DOJ”)], with copies to . . . the . . . Army and the . . . EPA, stating that [WVI] would cooperate
    and sign the renew[al ROE], so long as the [DOJ] signed a concurrent stipulation to be filed in the
    [United States] Court of Federal Claims, stating that the signing of [the renewal ROE] would not
    waive or diminish [WVI’s] . . . claim for just compensation[.]” JX 9 at WVI00009406,
    WVI00009408.
    On November 6, 2014, the DOJ declined WVI’s offer. JX 9 at WVI00009406.
    On November 13, 2014, the WVI ROE expired. JX 5 at US000001; TR 959–60 (Gortva).
    Since that time, the Army has not entered the Waverley View Property, but the gravel access road
    and the monitoring wells remain on the property.40 TR 1160–61 (Gortva).
    On February 5, 2015, the EPA sent a letter to WVI’s counsel, Clifford J. Zatz, stating that
    “much remains to be done with regard to the continuing [Remedial Investigation] of the
    groundwater plume” and “urg[ing] WVI to continue to provide access to the Army to allow it to
    pursue its investigation of the groundwater plume that extends beneath [the Waverley View
    Property].” JX 8 at WVI00009414. This letter also stated that
    Mr. Dorment, in his October 24, 2014 letter, states that the Army and the EPA have
    not provided him with an estimate of the expected duration of the Army’s activities
    on the property. At this time, since the full extent of the contaminated groundwater
    plume is not yet known, the Army and [the] EPA cannot estimate the total length
    39
    The United States Geological Survey defines “karst” as “[a] distinctive topography that
    indicates dissolution of underlying soluble rocks by surface water or ground water.” Karst
    Topography - Teacher's Guide and Paper Model, U.S. GEOLOGICAL SURVEY (Apr. 21, 2017, 4:35
    PM), https://geomaps.wr.usgs.gov/parks/cave/karst.html; see also TR 296–97 (Thomson)
    (explaining that there is the “ability to form sink holes in karst geology”).
    40
    WVI has never asked the Army to remove or relocate the monitoring wells (TR 1422
    (Tesner)), and also has never consented to the Army reentering the Waverley View Property to do
    so (TR 961, 1161 (Gortva)).
    38
    of time needed to address the contamination on WVI’s property. Once the
    [Remedial Investigation] is completed, and a Feasibility Study . . . to analyze
    remedial alternatives has been performed, the Army and [the] EPA will be in a
    better position to estimate the length of time required to implement a remedy.
    However, in order to get to this point, the Army will need continued access to
    complete the sampling required under the [Remedial Investigation].
    JX 8 at WVI00009415.
    On February 11, 2015, Mr. Zatz sent a letter to the EPA, declining to execute the Renewal
    ROE unless “the [DOJ] execute[d] the requested stipulation, communicated . . . on October 31,
    2014[.]” JX 9 at WVI00009407.
    II.    PROCEDURAL HISTORY.
    On April 13, 2015, WVI filed a Complaint in the United States Court of Federal Claims
    (ECF No. 1 (“Compl.”)) alleging: (1) a permanent physical taking by the Government of WVI’s
    private property, without just compensation (Compl. ¶¶ 56–63); and (2) a temporary physical
    taking by the Government of WVI’s private property, without just compensation (Compl. ¶¶ 64–
    74). On April 17, 2015, WVI filed a Motion For Summary Judgment, arguing that the
    Government’s “installation and servicing of groundwater monitoring wells and other related
    activities on WVI’s property constitute a per se taking” and that the WVI ROE does not negate
    the Government’s liability. ECF No. 7 at 15, 18.
    On July 27, 2015, the Government filed an Answer to WVI’s April 13, 2015 Complaint
    (ECF No. 10 (“Gov’t Ans.”)) asserting three affirmative defenses: (1) “[WVI] fails to state a claim
    upon which relief can be granted;” (2) “[WVI] granted the right to the [Government] to access
    certain portions of its property;” and (3) any liability for compensation is “offset by the special
    benefit [WVI] will derive from the [Government’s] activities.” Gov’t Ans. at 13.
    On July 28, 2015, the parties filed a Joint Motion To Stay Proceedings For Three Months
    (“Motion To Stay”), i.e., until October 28, 2015, while the parties engaged in settlement
    discussions. ECF No. 11. On that same day, the court granted the parties’ Motion To Stay. ECF
    No. 12.
    On October 28, 2015, the parties filed a Joint Status Report, requesting an additional three-
    month stay to continue settlement discussions. ECF No. 13. On November 4, 2015, the court
    convened a status conference. Thereafter, on November 5, 2015, the court issued an Order, staying
    the case until February 4, 2016 “for settlement negotiations.” ECF No. 14. Thereafter, the court
    convened status conferences and issued additional Orders staying the case until July 21, 2016.
    ECF No. 15 (February 8, 2016 Order, staying the case until March 16, 2016); ECF No. 16 (March
    16, 2016 Order, staying the case until May 16, 2016); ECF No. 17 (March 30, 2016 Order, setting
    a status conference for April 13, 2016); ECF No. 18 (April 13, 2016 Order, setting a status
    conference for April 22, 2016); ECF No. 19 (April 22, 2016 Order, setting a status conference for
    May 23, 2016); ECF No. 20 (May 23, 2016 Order, staying the case until June 20, 2016); ECF No.
    21 (June 20, 2016 Order, staying the case until July 19, 2016 and setting an “open court status
    conference [for that same day] . . . [i]f the parties have not reached a settlement by then”); ECF
    39
    No. 22 (June 29, 2016 Order, changing the date of the open court status conference to July 21,
    2016).
    On July 20, 2016, the Government filed an Expedited Motion For Relief From Order
    (“Motion For Relief”) (ECF No. 23) requesting “that the General Counsel of the Army be relieved
    from the obligation to appear in [c]ourt on . . . July 21, 2016 . . . [to] explain . . . why the settlement
    has not yet been approved” (ECF No. 23 at 1, 4). On that same day, the court issued an Order
    granting the Government’s Motion For Relief (ECF No. 24) and a second Order providing that
    “the court will convene the July 21, 2016 Status Conference by telephone” (ECF No. 25). On July
    21, 2016, the court convened a status conference. ECF No. 26 (status conference transcript).
    On August 10, 2016, the parties filed a Joint Preliminary Status Report. ECF No. 28. On
    that same day, the court issued an Order, denying WVI’s April 17, 2015 Motion For Summary
    Judgment as moot, and setting a trial date and pretrial schedule. ECF No. 29. On August 29, 2016,
    the parties filed a Joint Motion For Entry Of An Order Consistent With Fed. R. Evid. 502(d) (“Joint
    Motion For Entry”). ECF No. 30. On August 30, 2016, the court issued an Order, granting the
    parties’ Joint Motion For Entry. ECF No. 31.
    On September 30, 2016, the Army Corps sent a letter to WVI, indicating that “[t]he [WVI
    ROE] . . . has expired, the Army’s rights under [the WVI ROE] are at an end, as specified in the
    [WVI ROE] itself, and the Army has no continuing rights with respect to the [Waverley View
    P]roperty that was the subject of [the WVI ROE], or the wells located thereon.” JX 10 at
    WVI00009417.
    On October 6, 2016, the parties filed a Joint Motion To Extend Time To Complete Fact
    Discovery, requesting “that the deadline for the completion of fact discovery be extended to
    December 23, 2016.” ECF No. 32. On October 11, 2016, the court issued an Order, granting that
    motion. ECF No. 33.
    On November 6, 2016, the Government filed a Motion To Amend Scheduling Order And
    Continue Trial, requesting “that the [c]ourt continue the trial date for seven weeks – from January
    17, 2017 to March 6, 2017 and adjust interim deadlines,” because the Government’s counsel of
    record was retiring and the case was being assigned to a new trial team. ECF No. 35. On
    November 7, 2016, WVI filed an Opposition to that motion. ECF No. 37. On November 14, 2016,
    the court issued an Order, denying the Government’s November 6, 2016 Motion. ECF No. 38.
    On November 22, 2016, the parties filed a Joint Certification Of Meeting Of Counsel. ECF No.
    39.
    On December 16, 2016, WVI filed a Pre-Trial Brief (ECF No. 40), Witness List (ECF No.
    41), Exhibit List (ECF No. 42, Ex. 1–3), and Direct Testimony Of Expert Witnesses (ECF No. 43).
    On January 4, 2017, the Government filed a Pre-Trial Brief (ECF No. 47), Witness List
    (ECF No. 46), Exhibit List (ECF No. 46, Ex. A), and Direct Testimony Of Expert Witnesses (ECF
    No. 44–45). On January 5, 2017, the court convened a pre-trial conference. ECF No. 54. On that
    same day, WVI filed Expert Witness Reports. ECF No. 48.
    On January 9, 2017, WVI filed an Expert Rebuttal Report. ECF No. 49. On January 12,
    2017, the Government filed a Response to that report, “oppos[ing WVI’s] untimely submission of
    40
    [its January 9, 2017] rebuttal report, and [stating its] inten[t] to object to its use at trial.” ECF No.
    51. On that same day, WVI filed a Reply To Defendant’s Response, stating that submission of the
    January 9, 2017 Expert Rebuttal Report was proper, because no deadline was specified and it was
    requested by the Government’s counsel. ECF No. 52.
    On January 17–18 and 24–26, 2017, the court held a trial at the United States Court of
    Federal Claims in Washington, D.C. ECF No. 58, 60, 62, 64, 66.
    On January 25, 2017, the Government filed a Notice Of Objection To Admission Of
    Evidence Of Claims Not Pleaded, because “any testimony or other evidence beyond the scope of
    the claims in [WVI]’s Complaint,” and reaffirming that it did not “consent to the trial of issues or
    claims that were not raised in [WVI’s] pleadings.” ECF No. 55. On January 30, 2017, WVI filed
    a Motion To Complete The Examination Of John Tesner And Close The Trial Record. ECF No.
    56.
    On February 3, 2017, the court sent an email to the parties, instructing the Government to
    file a status report regarding a “pilot project/study” meeting scheduled for February 9, 2017 in
    Newton, Pennsylvania. On February 15, 2017, the Government informed the court that the
    February 9, 2017 meeting “between individuals from the . . . Army and its contractors regarding
    the pilot project/study to be conducted on government-owned property at Fort Detrick regarding
    the remediation of the Area B Groundwater Superfund Site,” was canceled and rescheduled for
    March 14, 2017. ECF No. 67. On March 16, 2017, the Government filed a Status Report,
    informing the court that the March 14, 2017 meeting was canceled and rescheduled for March 30,
    2017. ECF No. 68. On March 20, 2017, the court issued an Order staying the case until April 3,
    2017 and instructing the Government to file a status report on April 3, 2017 “regarding the pilot
    project/study meeting.” ECF No. 69.
    On April 3, 2017, the Government informed the court that the March 30, 2017 meeting
    “took place . . . [and t]he meeting participants . . . confirmed that the pilot project/study would not
    require access to the Waverley View [P]roperty.” ECF No. 70. In addition, the Government stated
    “that completion of [the] meeting ha[d] no bearing on the parties’ ability to complete the trial and
    . . . that it [was joining WVI’s] request that the [c]ourt set a date for the completion of trial.” ECF
    No. 70.
    On May 15, 2017, the court re-convened the trial at the United States Court of Federal
    Claims in Washington, D.C. ECF No. 74. On May 16, 2017, WVI filed a Notice Of Filing Of
    Trial Exhibit 160, Deposition Transcript Of Paul Leonard. ECF No. 71. On May 22, 2017, the
    parties filed a Joint Status Report On Proposed Post-Trial Briefing Schedule. ECF No. 72. On
    May 24, 2017, the court issued a Post-Trial Scheduling Order. ECF No. 75.
    On June 16, 2017, WVI filed an Opening Post-Trial Brief. ECF No. 76. On June 27, 2017,
    WVI also filed a Motion To Compel Disclosure Of Minutes From March 30, 2017 Pilot
    Project/Study Meeting. ECF No. 77. On July 11, 2017, the Government filed a Response. ECF
    No. 78. On July 13, 2017, WVI filed a Reply. ECF No. 79. On July 18, 2017, the court issued
    an Order, granting WVI’s June 27, 2017 Motion To Compel Disclosure. ECF No. 81.
    41
    On July 14, 2017, the Government filed a Post-Trial Response Brief. ECF No. 80. On
    July 31, 2017, WVI filed a Post-Trial Reply Brief. ECF No. 82 (“Pl. Post-Tr. Reply Br.”).
    On August 11, 2017, WVI filed a Motion To Submit Supplemental Trial Exhibits 161, 162,
    And 163—Minutes Of The March 30, 2017 Pilot Project/Study Meeting. ECF No. 83.
    On August 15, 2017, the Government filed a Post-Trial Sur-Reply Brief. ECF No. 86
    (“Gov’t Post-Tr. Sur-Reply Br.”). On August 31, 2017, WVI filed a Post-Trial Sur-Reply Brief.
    ECF No. 87 (“Pl. Post-Tr. Sur-Reply Br.”).
    On November 16, 2017, the court issued an Order, granting WVI’s August 11, 2017
    Motion and ordering the parties to “file a final Joint Exhibit List, Plaintiff’s Exhibit List, and
    Defendant’s Exhibit List on, or before, November 27, 2017.” ECF No. 89.
    On November 27, 2017, WVI filed a Plaintiff’s Exhibit List. ECF No. 90. That same day,
    the Government filed a Joint Exhibit List and a Defendant’s Exhibit List. ECF No. 91.
    On December 1, 2017, the court convened a site visit of the Waverley View Property in
    Frederick, Maryland. ECF No. 93.
    On December 5, 2017, WVI filed a Response To Questions Posed By The Court Following
    December 1, 2017 Site Visit To The Waverley View Property. ECF No. 94. That same day, the
    Government filed a Response To Questions Posed By The Court Following December 1, 2017
    Site Visit To The Waverley View Property. ECF No. 95.
    III.   DISCUSSION.
    A.      Subject Matter Jurisdiction.
    The United States Court of Federal Claims has jurisdiction under the Tucker Act, 
    28 U.S.C. § 1491
    , to adjudicate “any claim against the United States founded either upon the Constitution,
    or any Act of Congress or any regulation of an executive department, or upon any express or
    implied contract with the United States, or for liquidated or unliquidated damages in cases not
    sounding in tort.” 
    28 U.S.C. § 1491
    (a)(1) (2012). The Tucker Act, however, is “a jurisdictional
    statute; it does not create any substantive right enforceable against the United States for money
    damages. . . . [T]he Act merely confers jurisdiction upon [the United States Court of Federal
    Claims] whenever the substantive right exists.” United States v. Testan, 
    424 U.S. 392
    , 398 (1976).
    Therefore, a plaintiff must identify and plead an independent contractual relationship,
    constitutional provision, federal statute, or executive agency regulation that provides a substantive
    right to money damages. See Fisher v. United States, 
    402 F.3d 1167
    , 1172 (Fed. Cir. 2005) (en
    banc) (“The Tucker Act itself does not create a substantive cause of action; in order to come within
    the jurisdictional reach and the waiver of the Tucker Act, a plaintiff must identify a separate source
    of substantive law that creates the right to money damages.”). The burden of establishing
    jurisdiction falls upon the plaintiff. See FW/PBS, Inc. v. Dallas, 
    493 U.S. 215
    , 231 (1990) (holding
    that the burden is on the plaintiff to allege facts sufficient to establish jurisdiction); see also Rule
    of the United States Court of Federal Claims 12(b)(1).
    42
    The United States Court of Appeals for the Federal Circuit has held that the Takings Clause
    of the Fifth Amendment is “money-mandating.” See Schooner Harbor Ventures, Inc. v. United
    States, 
    569 F.3d 1359
    , 1362 (Fed. Cir. 2009) (“The Tucker Act waives sovereign immunity and
    provides jurisdiction for certain types of claims, including . . . where there is a money-mandating
    provision on which the plaintiff may base its recovery. In this case, that provision is the Fifth
    Amendment.” (internal citations omitted)); see also Moden v. United States, 
    404 F.3d 1335
    , 1341
    (Fed. Cir. 2005). Therefore, “to the extent [WVI has] a nonfrivolous takings claim founded upon
    the Fifth Amendment, jurisdiction under the Tucker Act is proper.” See Moden, 
    404 F.3d at 1341
    .
    WVI’s April 13, 2015 Complaint alleges: (1) a permanent physical taking by the
    Government of WVI’s private property, without just compensation (Compl. ¶¶ 56–63); and (2) a
    temporary physical taking by the Government of WVI’s private property, without just
    compensation (Compl. ¶¶ 64–74). Since WVI’s April 13, 2015 Complaint alleges “a taking of
    property within the meaning of the Fifth Amendment to the Constitution of the United States for
    which compensation is due and owing,” it properly invokes the jurisdiction of the United States
    Court of Federal Claims under 
    28 U.S.C. § 1491
    (a)(1). Compl. ¶¶ 3–4, 56–74.
    For these reasons, the court has determined that it has jurisdiction to adjudicate the Takings
    Clause claims alleged in WVI’s April 13, 2015 Complaint.
    B.      Standing.
    “[S]tanding is a threshold jurisdictional issue.” Myers Investigative & Sec. Servs., Inc. v.
    United States, 
    275 F.3d 1366
    , 1369 (Fed. Cir. 2002). The standing requirements derived from
    Article III of the United States Constitution also apply to the United States Court of Federal
    Claims. See Starr Int’l Co. v. United States, 
    856 F.3d 953
    , 964 (Fed. Cir. 2017) (quoting
    Anderson v. United States, 
    344 F.3d 1343
    , 1350 n.1 (Fed. Cir. 2003) (holding that the United States
    Court of Federal Claims, “though an Article I court, . . . applies the same standing requirements
    enforced by other federal courts created under Article III.”)), petition for cert. filed, No. 17-540
    (Oct. 11, 2017). Therefore, a plaintiff must establish “an injury-in-fact that is both fairly traceable
    to the challenged conduct of the defendant and likely redressable by a favorable judicial decision.”
    Figueroa v. United States, 
    466 F.3d 1023
    , 1029 (Fed. Cir. 2006). In addition, the party invoking
    jurisdiction bears the burden of establishing constitutional standing. See Myers Investigative, 
    275 F.3d at 1369
     (quoting Lujan v. Defs. of Wildlife, 
    504 U.S. 555
    , 561 (1992) (“[T]he party invoking
    federal jurisdiction bears the burden of establishing [its] elements.”)).
    WVI’s April 13, 2015 Complaint alleges an injury-in-fact that is traceable to the
    Government’s activities on the Waverley View Property that have caused economic injury that can
    be determined in a specific amount. Compl. ¶¶ 56–74.
    For these reasons, the court has determined that WVI has standing to seek an adjudication
    of the Takings Clause claims alleged in WVI’s April 13, 2015 Complaint.
    C.      Plaintiff’s Takings Clause Claims Against The Government.
    The Takings Clause of the Fifth Amendment to the United States Constitution provides
    that “private property [shall not] be taken for public use, without just compensation.” U.S. CONST.
    amend. V. The purpose of the Takings Clause is to prevent the “Government from forcing some
    43
    people alone to bear public burdens which, in all fairness and justice, should be borne by the public
    as a whole.” Armstrong v. United States, 
    364 U.S. 40
    , 49 (1960). The protections of the Takings
    Clause apply to real property. See Acceptance Ins. v. United States, 583 F.3d849, 854 (Fed. Cir.
    2009). The United States Court of Appeals for the Federal Circuit has “developed a two-part test
    for determining whether ‘fairness and justice’ require compensation for burdens imposed by a
    particular governmental action.” Huntleigh USA Corp. v. United States, 
    525 F.3d 1370
    , 1377 (Fed.
    Cir. 2008) (“First, . . . the court must determine whether the claimant has established a property
    interest for purposes of the Fifth Amendment. . . . Second, after having identified a valid property
    interest, the court must determine whether the government action at issue amounted to a
    compensable taking of that property interest.” (internal citations omitted)).
    1.      At Trial, Plaintiff Established That It Owns Private Property Under
    Maryland State Law.
    As a threshold matter, the court must determine “whether the claimant has identified a
    cognizable Fifth Amendment property interest that is asserted to be the subject of the taking.”
    Acceptance Ins., 583 F.3d at 854; see also Huntleigh USA Corp., 
    525 F.3d at
    1377–78 (“[O]nly
    persons with a valid property interest at the time of the taking are entitled to compensation.”)
    (citations and quotation marks omitted). Because “the Constitution protects rather than creates
    property interests, [however,] the existence of a property interest is determined by reference to
    ‘existing rules or understandings that stem from an independent source such as state law.’”
    Phillips v. Wash. Legal Found., 
    524 U.S. 156
    , 164 (1998) (quoting Bd. of Regents of State
    Colls. v. Roth, 
    408 U.S. 564
    , 577 (1972)).
    Subtitle 6 of Title 14 of the Maryland Code, Real Property, defines “property” as “real
    property or any interest in or appurtenant to real property, including fixtures.” MD. CODE ANN.,
    Real Property § 14-601 (2016). Subtitle 3 of Title 9 of the Maryland Code, Real Property, defines
    “owner,” in part, as “[t]he owner of the land.” Id. § 9-301; see also id. § 7-105.2 (defining “record
    owner,” in part, as “the person holding record title to property”).
    WVI proffered evidence at trial that it is the owner of the Waverley View Property, as
    defined by the Maryland Code. PX 53; TR 134–35 (Anderson); see also Real Property Data, MD.
    DEP’T OF ASSESSMENT & TAXATION, https://sdat.dat.maryland.gov/RealProperty/Pages/default.
    aspx (last visited Dec. 18, 2017) (select “FREDERICK COUNTY” as the “county in which to
    search” and “PROPERTY ACCOUNT IDENTIFIER” as the “search method;” using “02” as the
    “District,” search the following “Account Identifiers” listed in PX 53: “069970;” “070014;”
    “069954;” and “241641”) (listing “Waverley View Investors, LLC” as the current owner of each
    parcel of land).
    For these reasons, the court has determined that WVI established at trial that it is the owner
    of the Waverley View Property, i.e., a “cognizable Fifth Amendment property interest,” under
    Maryland state law. See Acceptance Ins., 583 F.3d at 854.
    44
    2.      At Trial, Plaintiff Established That The Government’s Activities After
    Expiration Of The Right Of Entry Agreement Effected A Permanent
    Taking Of Those Portions Of The Waverley View Property Physically
    Occupied By The Army-Installed Monitoring Wells And Gravel Access
    Road.
    a.      Plaintiff’s Argument.
    i.     “Plaintiff Has Proved A Per Se Taking.”
    WVI argues that the Army and the EPA engaged in a per se taking, because the EPA “used
    its CERCLA authority to take . . . a dominant easement . . . across all of . . . [Phase] II . . . for
    which the [Army and the EPA have] paid nothing.” Pl. Post-Tr. Br. at 35–36. That this is a per
    se taking is “borne out by the [United States Court of Appeals for the Federal Circuit’s] decision
    in Hendler [III].” Pl. Post-Tr. Br. at 36. Hendler III “involved [an EPA] investigation of a
    groundwater contaminant plume from a Superfund site. The [c]ourt had little trouble concluding
    that the Government’s occupation of the plaintiff’s nearby property for purposes of installing,
    servicing, and using groundwater monitoring wells constituted a per se taking of the plaintiff’s
    property[,]” because the EPA: (1) occupied private property, without valid consent; (2) “took for
    itself the right to use the private property to conduct a CERCLA investigation and remediation;”
    (3) used its access “to drill wells that were permanent fixtures;” and (4) never “suggested that its
    intrusion would be brief, or gave any indication of when [it] would return to the plaintiffs the full
    use of their property.” Pl. Post-Tr. Br. at 36–37; see also Hendler III, 952 F.2d at 1376–77. WVI
    contends that the taking in this case goes “far beyond [that] . . . in Hendler [III],” because “the
    [Army’s] repeated delays and complete uncertainty[,]” with respect to further investigation and
    remediation, has impaired WVI’s “ability to develop or sell any part of [Phase] II” of the Waverley
    View Property. Pl. Post-Tr. Br. at 37. In addition, “the value of [Phase] I has been dramatically
    diminished,” because of “the uncertainty surrounding the [Army’s] continued occupation of
    [Phase] II,” making it “impracticable for WVI to move forward with new development plans.” Pl.
    Post-Tr. Br. at 37–38.
    The Army’s promise that it “will work with WVI [to] locat[e] future impediments on the
    [Waverley View] Property is unreliable” for three reasons: (1) no documents commit the Army to
    work with WVI; (2) the EPA’s Model Access Order “states that the property owner shall not
    interfere with or otherwise limit any [CERCLA] activity conducted at the [p]roperty,” confirming
    that WVI’s “use is subservient to the [EPA’s] dominant use;” and (3) regardless of “where future
    wells or remedial structures are located, they will almost inevitably require a new site plan,” made
    impracticable by the Army’s lack of cooperation. Pl. Post-Tr. Br. at 39–40.
    In addition, contradicting letters from the different federal agencies “aggravate[] the
    uncertainty [that] WVI faces.” Pl. Post-Tr. Br. at 40. For example, the EPA’s February 5, 2015
    letter emphasized the “ongoing need for access to the [Waverley View] Property” and indicated
    that the EPA “did not require WVI’s permission to access and use the wells.” Pl. Post-Tr. Br. at
    41. In contrast, the Army Corps’ September 30, 2016 letter, written after a trial date was set in
    this case, “disclaim[ed] any ongoing ownership interest in the wells or right to access the
    [p]roperty.” Pl. Post-Tr. Br. at 40.
    45
    At present, “the [WVI ROE] has expired. Yet the Army’s . . . gravel access road, and
    costly monitoring well network remain on [the Waverley View] Property. [And, t]he [Army] has
    not said if or when it will remove them. At a minimum, this ongoing physical occupation plainly
    constitutes a per se taking under Hendler [III] for which just compensation is owed.” Pl. Post-Tr.
    Br. at 41.
    ii.     “The Right Of Entry Agreement Preserved Plaintiff’s
    Takings Clause Claim.”
    The WVI ROE “provides that WVI ‘expressly reserves any and all rights it may have to
    make a claim under the Takings Clause of the Fifth Amendment, U.S. Const., amend. V.’” Pl.
    Post-Tr. Br. at 41 (citing JX 5 at US000003–04). The United States Court of Claims’s decision in
    Fonalledas v. United States, 
    107 F. Supp. 1019
     (Ct. Cl. 1952), confirms that such a reservation
    preserves a Takings Clause claim. Pl. Post-Tr. Br. at 41.
    According to the Government, “the reservation of rights gives WVI the right to bring a
    takings claim, but the [WVI ROE] — of which the reservation of rights is a part — simultaneously
    dooms that claim to defeat. If that were the case, a [r]ight of [e]ntry with a reservation of rights
    would have no different effect from one without a reservation.” Pl. Post-Tr. Br. at 42. A “familiar
    rule of interpretation, known as the rule against superfluities,” provides that “[a]n interpretation
    which gives effect to all provisions of the [document] is preferred to one which renders part of the
    writing superfluous, useless, or inexplicable.” Pl. Post-Tr. Br. at 42 (quoting 11 RICHARD A. LORD,
    WILLISTON ON CONTRACTS § 32.5 (4th ed.)). This supports WVI’s interpretation of the WVI
    ROE’s reservation of rights and “shows why the Government’s reading is wrong.” Pl. Post-Tr.
    Br. at 42.
    iii.    “The Right Of Entry Agreement Is Not A Contract.”
    The WVI ROE is not “a contractual bar to WVI’s takings claim,” because there was no
    bargained-for consideration. Pl. Post-Tr. Br. at 43. Although the Government claims that WVI
    received a benefit “in the form of certainty about the [Army’s] use [of] WVI[’s p]roperty,” the
    Army’s use has not been limited, because “CERCLA authorizes the [EPA] to force its way onto
    the property wherever and whenever it finds there is a need to do so.” Pl. Post-Tr. Br. at 43.
    Therefore, “[a]ny limitations identified in the [WVI ROE] are . . . illusory and inadequate as
    consideration.” Pl. Post-Tr. Br. at 43 (citing RESTATEMENT (SECOND) OF CONTRACTS
    (“RESTATEMENT OF CONTRACTS”) § 77 (1981)).
    b.     The Government’s Response.
    i.      “Plaintiff Has Failed To Prove A Physical Taking Of Its
    Property, Because It Consented To The Army’s
    Groundwater Monitoring.”
    The Government responds that, “to constitute a taking, the intrusion . . . must be without
    consent.” Gov’t Post-Tr. Resp. Br. at 40. In this case, “the parties negotiated and signed a written
    contract[,] the [WVI ROE,] pursuant to which WVI allowed the Army’s installation of
    groundwater monitoring wells on [Phase] II” of the Waverley View Property. Gov’t Post-Tr. Resp.
    Br. at 40. But, “a person’s property cannot be said to have been ‘taken’ if the property owner and
    46
    the government negotiate a purchase agreement, lease or some other sort of contract allowing for
    entry beforehand.” Gov’t Post-Tr. Resp. Br. at 41.
    In Hendler III, “after the landowner plaintiff refused [the] EPA’s request for access to their
    property, the EPA issued an ‘administrative order granting itself and the State of California access
    to plaintiff[’s] property for, inter alia, locating, constructing, operating, maintaining and repairing
    monitoring/extraction wells.’” Gov’t Post-Tr. Resp. Br. at 42 (italics added) (quoting Hendler III,
    952 F.2d at 1369) (internal quotation marks omitted)). Thereafter, “without any effort to reach an
    agreement with [the] plaintiff as to well placement, the EPA installed a series of wells on [the]
    plaintiff[’s] property.” Gov’t Post-Tr. Resp. Br. at 42. In this case, however, “the Army entered
    WVI’s property with WVI’s express written consent [pursuant to] an agreement negotiated over
    the course of many weeks with the assistance of counsel.” Gov’t Post-Tr. Resp. Br. at 42.
    The WVI ROE “is a valid contract . . . [as it] includes an unambiguous offer and
    acceptance; consideration; and was signed by both parties.” Gov’t Post-Tr. Resp. Br. at 42. In
    exchange for “WVI’s agreement to permit the Army [and the EPA] to access [Phase] II [of the
    Waverley View Property] for a period of eighteen months, . . . the Army agree[d] to install
    groundwater monitoring wells . . . and obtain samples from those wells, all at the Army’s expense.”
    Gov’t Post-Tr. Resp. Br. at 43. In addition, “the Army agreed to provide WVI with the results of
    its testing and to repair damages caused to the property by the Army or its contractors.” Gov’t
    Post-Tr. Resp. Br. at 43. All of “[t]his constitutes consideration.” Gov’t Post-Tr. Resp. Br. at 43.
    Once consideration is established, “courts do not weigh the adequacy of that
    consideration.” Gov’t Post-Tr. Resp. Br. at 43 (quoting Davis Wetlands Bank, LLC v. United
    States, 
    114 Fed. Cl. 113
    , 121 n.9 (Fed. Cl. 2013)). WVI’s argument that no consideration supports
    the WVI ROE, “because it does not limit the [Army’s or the EPA’s] use of the [Waverley View]
    Property[,] is specious.” Gov’t Post-Tr. Resp. Br. at 44. WVI asserts that, “notwithstanding the
    express language of the [WVI] ROE, its limitations are ‘illusory and inadequate as consideration’
    because the [EPA] is supposedly authorized under CERCLA ‘to force its way onto the property.’”
    Gov’t Post-Tr. Resp. Br. at 44 (quoting Pl. Post-Tr. Br. at 43). If that were the case, “then all
    government contractual agreements entered into in lieu of taking unilateral administrative action
    would be illusory.” Gov’t Post-Tr. Resp. Br. at 44.
    Although the WVI ROE reserved “any and all rights [WVI] may have to make a claim
    under the Takings Clause,” it also provided that “[t]he Government acknowledges this reservation
    without any concession that any such rights or claim may exist.” Gov’t Post-Tr. Resp. Br. at 44
    (citing JX 5 at US000003–04). It is well established that “[a]n interpretation that gives meaning
    to all parts of the contract is to be [preferred] over one that leaves a portion of the contract useless,
    [inexplicable], void, or superfluous.” Gov’t Post-Tr. Resp. Br. at 44–45 (quoting NVT Techs,
    Inc. v. United States, 
    370 F.3d 1153
    , 1159 (Fed. Cir. 2004)). WVI construes the WVI ROE “to
    mean that . . . the Army is liable for the very conduct that the [WVI] ROE purportedly authorizes.
    That construction swallows the entire bargained-for agreement. Moreover, it ignores [that] the
    Government expressly refuse[d] to acknowledge that any such rights or claim may exist.” Gov’t
    Post-Tr. Resp. Br. at 45. In short, WVI’s construction “obliterates its consent to access the
    property and indeed the agreement in its entirety.” Gov’t Post-Tr. Resp. Br. at 45.
    47
    In Scogin v. United States, 
    33 Fed. Cl. 568
     (Fed. Cl. 1995), the United States Court of
    Federal Claims determined that because the “plaintiff did not demonstrate that the EPA undertook
    activity on his property ‘beyond the scope of valid agreements granting the [g]overnment access
    to the subject property for specified purposes,’ the plaintiff failed to prove that he did not consent
    fully to the EPA’s presence on his property.” Gov’t Post-Tr. Resp. Br. at 45 (quoting Scogin, 33
    Fed. Cl. at 578). Similarly, in this case, “WVI presented no evidence that the Army’s activities on
    WVI’s property exceeded those authorized under the [WVI] ROE.” Gov’t Post-Tr. Resp. Br. at
    45. Consequently, the consent provided in the WVI ROE “vitiates WVI’s takings claim.” Gov’t
    Post-Tr. Resp. Br. at 45.
    In addition, WVI’s reliance on Fonalledas “is misplaced,” because that “decision . . . has
    never been followed or approved by the [United States Court of Appeals for the] Federal Circuit
    and . . . has been called into question by the [United States] Supreme Court’s subsequent
    development of takings jurisprudence.” Gov’t Post-Tr. Resp. Br. at 45–46. And, “[u]nlike this
    case, . . . in Fonalledas the permit included no refusal on the part of the [government] to
    acknowledge that any . . . ‘rights’ existed. By that omission, the government essentially conceded
    that such rights existed.” Gov’t Post-Tr. Resp. Br. at 46. In contrast, here
    the Army’s explicit refusal to acknowledge that WVI had any right to assert a
    takings claim preserved its argument that the permission given in the [WVI] ROE
    to access the [ROE] Property subject to explicit limitations, vitiated any takings
    claim except to the extent that the Army exceeded the scope of the agreement.
    Gov’t Post-Tr. Resp. Br. at 46.
    Finally, WVI argues that the Government’s construction of the WVI ROE “renders the
    reservation of rights . . . meaningless. This is not so.” Gov’t Post-Tr. Resp. Br. at 45. Although
    WVI effectively waived “any taking claim based on a physical intrusion authorized by the [WVI]
    ROE” by signing that agreement, “WVI retained the right to assert either a regulatory taking claim
    or a taking claim for exceeding the access rights in the [WVI] ROE.” Gov’t Post-Tr. Resp. Br. at
    45.
    ii.     “Plaintiff Did Not Establish That The Government Has
    Permanently Occupied Its Property.”
    WVI’s argument that the EPA “used its CERCLA authority to take for itself [and the Army]
    a dominant easement for CERCLA investigation and remediation purposes across all of the [Phase]
    II property,” is speculative. Gov’t Post-Tr. Resp. Br. at 54 (quoting Pl. Post-Tr. Br. at 36). WVI’s
    permanent Takings Clause claim is “based on actions the [EPA or the Army] may take in the future
    to remediate contaminated groundwater from Area B on WVI’s property. Thus, WVI’s takings
    claims . . . are not ripe.” Gov’t Post-Tr. Resp. Br. at 54. In addition, “[c]ontrary to the thrust of
    WVI’s argument, there is no such thing as an action for ‘anticipatory taking,[’] i.e., a suit such as
    that filed by WVI alleging that the mere possibility the [Army or the EPA] might take the party’s
    property at some unknown date and time in the future gives rise to a cause of action in the present.”
    Gov’t Post-Tr. Resp. Br. at 54–55.
    48
    The CERCLA process is “ongoing” and the Remediation/Feasibility Study has not
    determined “what remediation plan will proceed for the Fort Detrick Area B groundwater
    Superfund Site.” Gov’t Post-Tr. Resp. Br. at 56 (citing DX 136 at 3–4). In addition, “there is no
    evidence at this time that active remediation would be required on the Waverley View [P]roperty.”
    Gov’t Post-Tr. Resp. Br. at 56 (citing DX 136 at 3–4). And, “even if the [Army or the EPA] does
    ultimately require additional access to the Waverley View [P]roperty, that access would be tailored
    to work with any existing or planned development.” Gov’t Post-Tr. Resp. Br. at 56 (citing DX
    136 at 7–8). Accordingly, “the determination of what, if any, taking may occur in the future is
    speculative, [and] WVI cannot assert a ripe claim based on such speculation.” Gov’t Post-Tr.
    Resp. Br. at 56.
    iii.    “Because Plaintiff Consented To The Installation Of The
    Monitoring Wells In A Valid Contract, Its Claims Are
    Governed By Contract Law.”
    WVI is entitled to recover, “only to the extent that the [Army or the EPA] did not comply
    with the [WVI] ROE, and WVI has provided no evidence that the [Army’s or the EPA’s] actions
    did not conform to the provisions of that [a]greement.” Gov’t Post-Tr. Resp. Br. at 56. Even if
    the court concludes that “the [WVI] ROE required the Army to decommission the wells and the
    gravel road installed on the [Waverley View P]roperty, the failure to do so constitutes at most a
    breach of contract, not a taking.” Gov’t Post-Tr. Resp. Br. at 56.
    WVI also has “adduced no evidence that the Army entered WVI's property without . . .
    consent before, during, or after the time in which the [WVI] ROE was in place.” Gov’t Post-Tr.
    Resp. Br. at 57. And, the WVI ROE “did not require, the decommissioning of the wells or removal
    of the gravel road the Army installed on [the Waverley View P]roperty.” Gov’t Post-Tr. Resp. Br.
    at 57. Therefore, “[t]he fact that the wells and gravel road remain on WVI’s property is consistent
    with the parties’ negotiated agreement.” Gov’t Post-Tr. Resp. Br. at 57. Because WVI “did not
    plead and prove a breach of the [WVI ROE] and[,] because the relationship between the [Army]
    and WVI is governed by the terms of that [a]greement, WVI is not entitled to any recovery in this
    action.” Gov’t Post-Tr. Resp. Br. at 57.
    In addition, the “continued existence of the wells and gravel road on [WVI’s] property after
    expiration of the [WVI] ROE” is not a “permanent taking,” because “the [WVI] ROE did not
    require removal of the monitoring wells or gravel road.” Gov’t Post-Tr. Resp. Br. at 57. Moreover,
    even if the continued presence of the wells or road . . . exceeded the scope the
    [WVI] ROE, any taking would only last from the expiration of the [WVI] ROE,
    November 13, 2014, until the issuance of the September 30, 2016 letter from the
    Army [Corps], confirming the expiration of the [WVI] ROE and [the Army’s] lack
    of further rights or interest in the monitoring wells.
    Gov’t Post-Tr. Resp. Br. at 57–58 (citing DX 109).
    49
    c.      Plaintiff’s Reply.
    i.      “Plaintiff’s Takings Clause Claim Is Ripe for Review.”
    WVI replies that “[t]here is nothing ‘anticipatory’ about [its] taking” claim. Pl. Post-Tr.
    Reply Br. at 8 (quoting Gov’t Post-Tr. Resp. Br. at 54). “[The taking] began in 2013 and persists
    to this day. The [Army] . . . forced its way onto WVI’s [p]roperty and installed a network of wells
    [and] a gravel road[.] . . . That is a per se physical taking.” Pl. Post-Tr. Reply Br. at 8 (citing
    Hendler III, 952 F.2d at 1375–76). Moreover, in addition to the ongoing physical occupation, the
    Army and the EPA have “effectively asserted an easement across whole swaths” of the Waverley
    View Property. Pl. Post-Tr. Reply Br. at 9 (citing JX 8).
    ii.     “The Right Of Entry Agreement Does Not Bar Plaintiff’s
    Takings Clause Claim.”
    Regardless of WVI’s consent, “one way or another, the [Army and the EPA were]
    inevitably going to occupy [WVI’s] [p]roperty.” Pl. Post-Tr. Reply Br. at 11. WVI was coerced
    into signing the WVI ROE and Mr. Dorment only agreed, because “‘[WVI] had no leverage, no
    negotiating capacity . . . , and [Mr. Dorment’s] attorneys had informed [him] that [the Army and
    the EPA] were going to get whatever they wanted to get.’” Pl. Post-Tr. Reply Br. at 11 (quoting
    TR 647 (Dorment)). Communications from the Army and the EPA made clear that WVI had two
    choices: “admit the [Army and the EPA] to the [Waverley View] Property involuntarily by
    [agreement], or . . . involuntarily by unilateral administrative order.” Pl. Post-Tr. Reply Br. at 11.
    The Government’s argument that “choos[ing] between ‘unpleasant’ alternatives is not the same
    thing as being coerced” is unsupported by legal authority. Pl. Post-Tr. Reply Br. at 11 (quoting
    TR 57 (Held)). In addition, WVI did not “contaminate the groundwater beneath the property” nor
    did it bring about this “untenable ‘choice.’” Pl. Post-Tr. Reply Br. at 12. Because “the [Army] is
    responsible for both of the ‘unpleasant alternatives’ and [WVI was forced] to yield control of its
    [p]roperty, the [WVI] ROE is a product of coercion.” Pl. Post-Tr. Reply Br. at 12.
    In addition, the WVI ROE is not supported by any bargained-for consideration and is not
    a contract. Pl. Post-Tr. Reply Br. at 14–15. Neither the “provisions about duration, hour of entry,
    notice, installation of the wells, and sampling,” nor “[t]he . . . commitment to supply test results”
    constitute consideration. Pl. Post-Tr. Reply Br. at 14–15.
    Finally, the Government “either mischaracterizes or misunderstands WVI’s argument
    about the reservation of rights in the [WVI] ROE.” Pl. Post-Tr. Reply Br. at 15. The reservation
    of rights does not mean that the Army and the EPA cannot enter WVI’s property; instead, it means
    that, although WVI did not stop the Army and the EPA from entering the ROE Property, WVI will
    “insist on just compensation under the Fifth Amendment for . . . taking of the [p]roperty.” Pl.
    Post-Tr. Reply Br. at 15–16. Likewise, the Government’s argument that WVI may only assert a
    takings claim “for exceeding the access rights in the [WVI] ROE” is without support. Pl. Post-Tr.
    Reply Br. at 16 (quoting Gov’t Post-Tr. Resp. Br. at 45). The reservation of rights does not
    “distinguish between types of takings claims, whether ‘for exceeding the access rights in the [WVI]
    ROE’ or otherwise. It simply says that WVI preserves its right to bring a takings claim[.]” Pl.
    Post-Tr. Reply Br. at 16.
    50
    d.      The Government’s Sur-Reply.
    i.     “The Right Of Entry Agreement Vitiates Plaintiff’s
    Takings Clause Claims.”
    The Government adds that, “because the groundwater monitoring wells on which WVI
    bases its takings claims were installed with WVI’s permission, there was no ‘taking’ within the
    meaning of the Fifth Amendment.” Gov’t Post-Tr. Sur-Reply Br. at 4. As the United States
    Supreme Court explained in Yee v. City of Escondido, 
    503 U.S. 519
     (1992), “[t]he government
    effects a physical taking only where it requires the landowner to submit to the physical occupation
    of his land. ‘This element of required acquiescence is at the heart of the concept of occupation.’”
    
    Id. at 527
     (internal citations omitted). As such, “whether the government floods a landowner's
    property[] or does no more than require the landowner to suffer the installation of a cable, the
    Takings Clause requires compensation[,] if the government authorizes a compelled physical
    invasion of property.” 
    Id.
     Because WVI’s right to exclude was voluntarily relinquished, [its
    property was] not taken. Gov’t Post-Tr. Sur-Reply Br. at 5.
    The WVI ROE is enforceable, because “[c]oercion sufficient to negate WVI’s consent
    requires far more” than the Government’s actions in this case. Gov’t Post-Tr. Sur-Reply Br. at 5.
    Simply because “WVI was unhappy about entering into the [WVI ROE] after the fact does not
    negate its consent to the entry. And that consent vitiates WVI’s per se permanent physical taking
    claim.” Gov’t Post-Tr. Sur-Reply Br. at 8. And, for these same reasons, the reservation of rights
    language in the WVI ROE only “preserve[d] a takings claim for an intrusion exceeding the access
    rights in the [WVI ROE], or for a regulatory taking[.]” Gov’t Post-Tr. Sur-Reply Br. at 11.
    In any event, if the court determines that there was a taking, the court must “determine
    whether such taking was permanent or temporary.” Gov’t Post-Tr. Sur-Reply Br. at 13. This
    requires an analysis of the factors set forth in Arkansas Game and Fish Commission v. United
    States, 
    568 U.S. 23
     (2012). Gov’t Post-Tr. Sur-Reply Br. at 13–14. The Army’s presence “lasted
    for less than two years,” and “WVI had extensive knowledge of the ‘character of the land’ and
    likelihood of contamination when it purchased the [Waverley View] Property.” Gov’t Post-Tr.
    Sur-Reply Br. at 14. As such, the “investment-backed expectations” and the “extent of
    interference” weigh against finding a temporary taking. Gov’t Post-Tr. Sur-Reply Br. at 17.
    ii.    “The Right Of Entry Agreement Is Supported By Valid
    Consideration.”
    WVI does not cite a single case in support of the contention that the WVI ROE “is not a
    contract because it is not supported by consideration.” Gov’t Post-Tr. Sur-Reply Br. at 8 (quoting
    Pl. Post-Tr. Reply Br. at 14). The Government “is aware of no case that has held a [r]ight of [e]ntry
    [a]greement . . . invalid for lack of consideration.” Gov’t Post-Tr. Sur-Reply Br. at 8. Apart from
    the specific terms of any such agreement, both the Government and WVI benefited: “[t]he [Army
    and the EPA] gain[ed] access to obtain necessary data and to remediate environmental
    contamination,” and “[b]y cooperating with the [R]emedial [I]nvestigation, [WVI] avoid[ed] the
    risk of relinquishing any defenses it may have under CERCLA and further benefits[,] because the
    cost of drilling wells and sampling [was] borne by the [Army].” Gov’t Post-Tr. Sur-Reply Br. at
    8. The WVI ROE also provided other benefits that can be seen “by comparing the [WVI]
    51
    ROE . . . with standard [r]ight of [e]ntry [a]greements the Army entered into with neighboring
    subdivisions, Carroll Park . . . and Loch Inver Court[.]” Gov’t Post-Tr. Sur-Reply Br. at 9 (citing
    JX 5; DX 37; DX 103).
    e.      Plaintiff’s Sur-Reply.
    i.      “The Right Of Entry Agreement Does Not Bar Plaintiff’s
    Takings Clause Claim.”
    WVI argues that the WVI ROE “is not supported by consideration.” Pl. Post-Tr. Sur-Reply
    Br. at 7. WVI did not “get anything from the terms of the [WVI] ROE that it did not already have.”
    Pl. Post-Tr. Sur-Reply Br. at 7. And, the Government’s argument that the WVI ROE is “supported
    by consideration because it contains terms not found in other rights of entry,” ignores that “[t]he
    concept of consideration . . . looks to whether this document recites consideration bargained for
    by these parties.” Pl. Post-Tr. Sur-Reply Br. at 7.
    In determining whether the WVI ROE was the product of coercion, the United States Court
    of Appeals for the Federal Circuit has held that a party must establish: “(1) that the [g]overnment
    ‘effectively imposed the terms’ of the action at issue; (2) that the party ‘had no realistic alternative’
    but to accept the [g]overnment’s terms; and (3) that the party’s action ‘was the result of improper
    acts by the agency.’” Pl. Post-Tr. Sur-Reply Br. at 9 (quoting Staats v. United States Postal
    Service, 
    99 F.3d 1120
    , 1124 (Fed. Cir. 1996)). Although Staats “arose in the employment context,
    the principles articulated are not inherently limited to that setting. And[,] the Government has not
    identified any other [United States Court of Appeals for the] Federal Circuit precedent to guide
    this [c]ourt.” Pl. Post-Tr. Sur-Reply Br. at 10.
    The Government’s construction of the WVI ROE’s reservation of rights requires the court
    impermissibly to “insert terms and qualifiers into the reservation of rights.” Pl. Post-Tr. Sur-Reply
    Br. at 10. Even if the court could do so, the “most glaring defect in the Government’s arguments
    about the reservation of rights[, however,] remains [its] inability to account for the [United States]
    Court of Claims’[s] decision in Fonalledas[.]” Pl. Post-Tr. Sur-Reply Br. at 11.
    ii.     “Plaintiff’s Takings Clause Claim Is Ripe For Review.”
    The Army’s continued occupation of the Waverley View Property “rendered [Phase] II [of
    the Waverley View Property] . . . essentially worthless, and caused a significant loss in the market
    value of [Phase] I,” but the “Government continues to urge that this case is not ripe.” Pl. Post-Tr.
    Sur-Reply Br. at 11. The uncertainty that the Government points to is not only an issue of damages
    . . . rather than one of ripeness; it is a part of the taking.” Pl. Post-Tr. Sur-Reply Br. at 12. In fact,
    “[i]t is precisely because the [Army] admittedly cannot provide any specifics about its continuing
    and future occupation . . . that WVI cannot move forward with developing its land.” Pl. Post-Tr.
    Sur-Reply Br. at 12. The court should not dismiss WVI’s claim as “unripe,” simply because the
    Army is unable to provide “a concrete end date to the [Army’s] occupation of the [p]roperty.” Pl.
    Post-Tr. Sur-Reply Br. at 12. Instead, this is a “component of the claim[.]” Pl. Post-Tr. Sur-Reply
    Br. at 12.
    52
    iii.   “The Framework From Arkansas Game and Fish Does
    Not Apply To Permanent Takings Cases Like This One.”
    Finally, the Government argues, for the first time, that the framework set out in Arkansas
    Game and Fish Commission controls in this case, because any taking was only temporary. Pl.
    Post-Tr. Sur-Reply Br. at 12. But, “Hendler [III] could not be clearer: the [Army’s] investigative
    activities on the [Waverley View] Property constitute a permanent physical invasion sufficient to
    establish a per se taking under Loretto [v. Teleprompter Manhattan CATV Corp., 
    458 U.S. 419
    (1982)].” Pl. Post-Tr. Sur-Reply Br. at 13. “[T]his case is a textbook example of a permanent
    physical occupation;” therefore, Arkansas Game and Fish Commission is irrelevant. Pl. Post-Tr.
    Sur-Reply Br. at 13.
    f.      The Court’s Resolution.
    i.     Governing Precedent.
    A compensable taking occurs when the government “physical[ly] inva[des] or
    appropriat[es] . . . private property.” Huntleigh USA Corp., 
    525 F.3d at 1378
    ; see also Acceptance
    Ins., 583 F.3d at 854 (“The Fifth Amendment to the United States Constitution proscribes the
    taking of private property for public use, without just compensation.”) (internal quotations
    omitted). A physical invasion or appropriation occurs when “the government itself occupies the
    property or requires the landowner to submit to physical occupation of its land.” Stearns Co. v.
    United States, 
    396 F.3d 1354
    , 1357 (Fed. Cir. 2005) (emphasis and internal quotations omitted).
    Although physical takings “are relatively rare,” they are “easily identified, and usually represent a
    greater affront to individual property rights.” Tahoe-Sierra Pres. Council, Inc. v. Tahoe Reg’l
    Planning Agency, 
    535 U.S. 302
    , 324 (2002). Therefore, when the government physically takes
    property, “it has a categorical duty to compensate the former owner, . . . regardless of whether the
    interest that is taken constitutes an entire parcel or merely a part thereof.” 
    Id. at 322
     (internal
    citations omitted).
    As the United States Supreme Court observed in Arkansas Game and Fish Comm'n,
    however, “permanent physical occupations” of property must be distinguished from “temporary
    [physical] invasions.” Ark. Game & Fish Comm'n, 
    568 U.S. at 36
    . And, as the United States Court
    of Appeals for the Federal Circuit explained in John R. Sand & Gravel Co. v. United States, 
    457 F.3d 1345
     (Fed. Cir. 2006),
    “[p]ermanent” has a special meaning in the determination of whether a physical
    occupation has occurred. In the context of physical takings “‘permanent’ does not
    mean forever, or anything like it.” A government occupation is “permanent” when
    the government's “intrusion is a substantial physical occupancy of private
    property.” The government's occupation may be permanent[,] even if it is not
    “exclusive, or continuous and uninterrupted.” The [United States] Supreme Court
    held in Loretto that the placement of cable and connection boxes on the plaintiff's
    property was a physical taking. In Hendler [III], [the United States Court of
    Appeals for the Federal Circuit] held that the placement of groundwater monitoring
    wells on the plaintiff's property and the government's periodic presence for
    installing and servicing the wells was “permanent” and therefore a physical taking.
    53
    In contrast, [the court] noted that a transient and relatively inconsequential
    incursion by the government, such as a truckdriver parking on a vacant lot to eat
    lunch, is not sufficiently permanent to comprise a taking. Similarly, in Boise
    Cascade [Corp. v. United States, 
    296 F.3d 1339
     (Fed. Cir. 2002)], [the same court]
    determined that government surveyors who briefly entered the plaintiff's land over
    a period of five months to perform owl surveys did not “permanently” occupy the
    plaintiff's property. Thus, the determination of whether government occupancy is
    “permanent” is highly fact-specific. In any event, the installation of fixed physical
    structures, such as the cable and cable connections in Loretto or the groundwater
    monitoring wells in Hendler [III] is typical of a “permanent” occupation, while the
    transient entry of persons via government authority on a plaintiff's property is
    generally not “permanent.”
    
    Id. at 1357
     (internal citations omitted), aff’d, 
    552 U.S. 130
     (2008).
    A claim for a physical taking, however, may not arise where a property owner voluntarily
    consents to the government’s entry onto private property and to those governmental activities
    giving rise to such a claim. See, e.g., J. J. Henry Co. v. United States, 
    411 F.2d 1246
    , 1249 (Ct.
    Cl. 1969)41 (“[W]here the government possesses property under the color of legal right, as by an
    express contract, there is seldom a taking in violation of the Fifth Amendment. The amendment
    has limited application to the relative rights in property of parties . . . which have been voluntarily
    created by contract.”); see also, e.g., Nat’l Bd. of YMCA v. United States, 
    396 F.2d 467
    , 474 (Ct.
    Cl. 1968), (denying just compensation for damage to plaintiffs’ properties, in part, because “the
    structural changes were made with the consent of the plaintiffs”), aff’d, 
    395 U.S. 85
     (1969); Scogin,
    33 Fed. Cl. at 578 (determining there was no taking, based on physical use and occupation, where
    plaintiff failed to demonstrate any EPA activity that exceeded the scope of plaintiff’s consent).
    In this case, the parties argue at length about whether the WVI ROE is a “valid” contract.
    Although a contract may reflect an agreement to allow the government access to and use of private
    property, the relevant inquiry is only whether there was voluntary consent to the same. As the
    United States Supreme Court explained in Yee, “[t]he government effects a physical taking only
    where it requires the landowner to submit to . . . physical occupation of his land. This element of
    required acquiescence is at the heart of the concept of occupation.” Yee, 
    503 U.S. at 527
    . Required
    acquiescence, however, cannot exist when consent is voluntarily given. Accordingly, whether the
    Army or the EPA required WVI to “submit to . . . physical occupation” of the Waverley View
    Property is dispositive of whether a taking occurred during the term of the WVI ROE, i.e., from
    May 14, 2013 to November 13, 2014.
    ii.     Plaintiff Voluntarily Consented To The Government’s
    Entry And Use Of The Waverley View Property.
    On April 8, 2009, Fort Detrick Area B Groundwater was listed on the NPL as a CERCLA
    Superfund site, thereby triggering the EPA’s authorities under CERCLA. PX 65 at 2.
    41
    The United States Court of Appeals for the Federal Circuit has held that United States
    Court of Claims decisions issued prior to September 30, 1982, are binding precedent. See S.
    Corp. v. United States, 
    690 F.2d 1368
    , 1369 (Fed. Cir. 1982).
    54
    Nevertheless, on November 15, 2012, WVI purchased the Waverley View Property. PX 53; TR
    134–35 (Anderson). Thus, the EPA’s authority to enter the property, pursuant to § 104(e)(3) of
    CERCLA, 
    42 U.S.C. § 9604
    (e)(3), predated WVI’s ownership by more than three and a half years.
    As such, when WVI purchased the Waverley View Property, it did so subject to the EPA’s
    “significant enforcement authorities under . . . CERCLA,” including the right to access the
    Waverley View Property, with or without WVI’s consent. PX 10 at WVI00004487.
    In attempting to gain access to the Waverley View Property, however, the Army and the
    EPA did not exercise the EPA’s CERCLA authority or the power of eminent domain to compel
    WVI’s consent. See United States v. Dow, 
    357 U.S. 17
    , 21 (1958) (“[T]he United States may take
    property pursuant to its power of eminent domain in one of two ways: it can enter into physical
    possession of property without authority of a court order; or it can institute condemnation
    proceedings under various Acts of Congress providing authority for such takings.”). Instead, after
    weeks of negotiations, during which WVI was represented by counsel and “exchanged several
    drafts of the [WVI ROE] with the EPA and . . . the Army” (TR 725 (Dorment)), the parties agreed
    on terms of access and memorialized them in the WVI ROE (JX 5). Neither the Army nor the
    EPA required WVI to sign the WVI ROE. Instead, the WVI ROE was the culmination of “weeks
    . . . [of] negotiations” between the parties. PX 10 at WVI00004486; see also TR 725 (Dorment).
    Although WVI may have felt pressure to participate in these negotiations,42 WVI retained the right
    to walk away; a right that Messrs. Dorment and Anderson exercised on numerous prior occasions.
    See, e.g., JX 1; TR 151–52 (Anderson). Accordingly, when WVI gave its consent by signing the
    WVI ROE, it did so voluntarily.
    WVI nevertheless argues that the WVI ROE was the product of coercion or duress. Pl.
    Post-Tr. Resp. Br. at 12. To render an agreement unenforceable for coercion or duress, a party
    “must establish that (1) it involuntarily accepted [the other party's] terms, (2) circumstances
    permitted no other alternative, and (3) such circumstances were the result of [the other party's]
    coercive acts.” Dureiko v. United States, 
    209 F.3d 1345
    , 1358 (Fed. Cir. 2000).
    Although some evidence43 suggests that WVI signed the WVI ROE “under protest,”44 WVI
    nevertheless failed to establish the second and third elements of the duress test.
    42
    In his May 24, 2013 letter, Mr. Dorment indicates that “all of the negotiations . . . were
    conducted within the coercive context of [the EPA’s] significant enforcement authorities under the
    CERCLA statute.” PX 10 at WVI00004487.
    43
    See, e.g., PX 10 WVI00004486–87 (Mr. Dorment explaining that WVI “could not
    accept” a proposal to include language in the WVI ROE that WVI “‘freely and voluntarily’ grants
    access . . . because all of the negotiations concerning such demanded access were conducted within
    the coercive context of [the EPA’s] significant enforcement authorities under the CERCLA
    statute.”)
    44
    See N. Star Steel Co. v. United States, 
    477 F.3d 1324
    , 1334 (Fed. Cir. 2007) (holding
    that signing an agreement “under protest” may satisfy the first element of the duress test, i.e.,
    involuntary acceptance of the other party’s terms, but that alone is insufficient to demonstrate
    duress).
    55
    As to the second element, WVI could have refused to sign the WVI ROE. Although such
    refusal may have subjected WVI to liability for “investigation and cleanup costs” under CERCLA
    as described in the EPA’s February 8, 2013 letter (DX 44 at US000009), the “threat of considerable
    financial loss” is not sufficient to establish duress (see Rumsfeld v. Freedom NY, Inc., 
    329 F.3d 1320
    , 1330 (Fed. Cir. 2003)). Instead, WVI could have continued to refuse to sign the WVI ROE
    as Messrs. Dorment and Anderson had done on numerous prior occasions. See, e.g., JX 1; TR
    151–52 (Anderson).
    Regarding the third element, “coercion requires a showing that the [g]overnment's action
    was wrongful, i.e., (1) illegal, (2) a breach of an express provision of the [agreement] without a
    good-faith belief that the action was permissible under the [agreement], or (3) a breach of the
    implied covenant of good faith and fair dealing.” N. Star Steel Co., 
    477 F.3d at 1334
     (internal
    citations and quotation marks omitted). There is no evidence that the Army or the EPA acted
    illegally. Nor was the EPA’s February 8, 2013 letter an “improper threat.” See David Nassif
    Assocs. v. United States, 
    644 F.2d 4
    , 12 (Ct. Cl. 1981) (defining “improper threat” as “threats to
    commit a crime or a tort . . . [or] that would accomplish . . . economic duress . . . includ[ing] threats
    that would breach a duty of good faith and fair dealing under a contract as well as threats which,
    though lawful in themselves, are enhanced in their effectiveness in inducing assent to unfair
    terms[,] because they exploit prior unfair dealing on the part of the party making the threat”)
    (internal citations omitted). Instead, the EPA’S February 8, 2013 letter described relevant
    CERCLA provisions and the EPA’s authority thereunder, including that the EPA had legal
    authority to access the Waverley View Property, with or without WVI’s consent.
    Accordingly, the EPA’s February 8, 2013 letter did not threaten WVI; instead, it described
    relevant CERCLA provisions and the EPA’s authority thereunder, including that the EPA had legal
    authority to access the Waverley View Property.
    For these reasons, the court has determined that the WVI ROE was not the product of
    coercion or duress; instead, WVI voluntarily consented to the terms of that agreement, authorizing
    the Army and the EPA to enter and use the ROE Property from May 14, 2013 to November 13,
    2014.
    iii.    The Reservation Of Rights In The Right Of Entry
    Agreement Did Not Invalidate Plaintiff’s Consent.
    The WVI ROE provided that WVI “expressly reserves any and all rights it may have to
    make a claim under the Takings Clause of the Fifth Amendment, U.S. Const., amend. V. The
    Government acknowledges this reservation without any concession that any such rights or claim
    may exist.” JX 5 at US000004 (emphasis added). WVI argues that this reservation of rights
    preserved its right to bring Takings Clause claims based on the Army’s activities pursuant to the
    WVI ROE. Pl. Post-Tr. Br. at 41–43. In effect, WVI argues that the reservation or rights renders
    its voluntary consent, and thus the entire WVI ROE, meaningless. WVI insists, however, that
    Fonalledas, “shows that [the] reservation [of rights] is effective to preserve a takings claim.” Pl.
    Post-Tr. Br. at 41. But, WVI construes the holding in Fonalledas too broadly.
    In Fonalledas, the dredging of a channel in San Juan Harbor, Puerto Rico caused “mud,
    silt and salt water” to flow over the plaintiffs’ lands. See Fonalledas, 
    107 F. Supp. at
    1020–21.
    The plaintiffs “protested . . . to various [g]overnment officials and finally brought a suit in the
    56
    United States District Court to enjoin the [dredging].” 
    Id. at 1021
    . Thereafter, the government
    “advised . . . the plaintiffs that dredging operations . . . would stop, [and] that a drainage canal
    would be dug to drain off the salt water already accumulated on the plaintiffs’ lands and afford
    future drainage.” 
    Id.
     Based on these assurances, plaintiffs’ counsel “gave the [g]overnment a
    letter of authorization to construct the canal,” providing “[i]t is expressly understood that this
    permit is granted[,] without prejudice to any and all rights of our clients, or, in other words, it is
    expressly understood that our clients waive no rights whatsoever by reason of this permit.” 
    Id.
    The drainage canal “was thereupon constructed and the injunction suit was dismissed.” 
    Id.
    Thereafter, plaintiffs’ filed suit in the United States Court of Claims “to recover for the alleged
    taking of [plaintiffs’] lands.” 
    Id. at 1020
    . The government “contend[ed] that the permission given
    by the plaintiffs for the construction of the canal was a waiver of any claims which the plaintiffs
    might otherwise have had for its construction and the harmful effects thereof.” 
    Id. at 1022
    . The
    Fonalledas court disagreed, explaining that, “the statement in the written permission that ‘it is
    expressly understood that our clients waive no rights whatsoever by reason of this permit’ is a
    complete answer to the [g]overnment's contention.” 
    Id.
    Unlike this case, however, in Fonalledas, the plaintiffs’ Takings Clause claims accrued
    before any agreement to permit dredging was reached with the government, i.e., the plaintiffs’
    Takings Clause claims predated its consent, as the letter from plaintiffs’ counsel reflected.
    Therefore, the Fonalledas court determined that a reservation of rights may preserve Takings
    Clause claims predating a consent agreement, not that a reservation of rights invalidates consent,
    as WVI would have it.
    Nevertheless, it is an established canon that, “[w]hen interpreting [an agreement], the
    document must be considered as a whole and interpreted so as to harmonize and give reasonable
    meaning to all of its parts.” NVT Techs., Inc., 
    370 F.3d at 1159
    . Therefore, the court has
    determined that the reservation of rights in the WVI ROE preserves any Takings Clause claim that
    WVI had prior to signing that agreement or which arose outside the scope and duration thereof,
    but not any claim that arose within the scope and duration of the WVI ROE.
    iv.     The Government’s Activities On The Waverley View
    Property During The Term Of The Right of Entry
    Agreement Did Not Exceed The Scope Of Work
    Described Therein.
    The WVI ROE broadly granted the Army and the EPA authority to perform a number of
    activities on the ROE Property. First, the WVI ROE granted the Army and the EPA
    an irrevocable right to enter in, on, over and across [the ROE Property], for a period
    not to exceed eighteen (18) months, unless further extended by [a]greement of the
    parties commencing on May 14, 2013, and running through November 13, 2014,
    or, if sooner, the date of completion of the [R]emedial [I]nvestigation.
    JX 5 at US000001.
    Second, the WVI ROE granted the Army and the EPA
    57
    the right to store, move, and remove equipment and supplies; investigate and collect
    samples . . . ; construct, operate, maintain, alter, repair, and remove groundwater
    monitoring wells, appurtenances thereto, and other devices for the monitoring of
    contamination in soil, air, and water; and, perform any other such work which may
    be necessary and incident to the Government’s use for the investigation and
    determination of need for response on [the ROE Property.]
    JX 5 at US000001–02 (emphasis added).
    The WVI ROE also included a map showing proposed locations of “drilling areas,” and
    described the “Scope of Work” as follows:
    1. Evaluation, logging, surveying, measuring, and testing of existing wells
    (GW-1, GW-2, GW-3, GW-4) on the [ROE Property], including regular access
    during the groundwater tracer study (e.g., weekly, biweekly, or monthly for the
    duration of the study and/or right-of-entry period).
    2. Drilling, logging, and borehole testing in three areas on the [ROE
    Property] (see Figure 1), including rig access to each drill area, monitoring well
    construction (multiple), surveying, measuring, and testing of completed wells for
    the duration of the right-of-entry period. Any other drilling areas identified by [the]
    EPA, [the] MDE, or the Army would be restricted to the [ROE Property].
    3. Access to any streams, seeps, springs, or other surface water features that
    may exist on the [ROE Property] for surveying, monitoring, and sampling[.]
    JX 5 at US000006.
    Pursuant to the WVI ROE, on or about, November 21, 2013, the Army entered the ROE
    Property and constructed a gravel access road. TR 199 (Anderson). This work was within the
    Army’s authority to “perform any other . . . work which may be necessary and incident to the
    Government’s use” under the WVI ROE. JX 5 at US000002. Beginning in December 2013, the
    Army also installed and maintained fifteen monitoring wells on the ROE Property. TR 949
    (Gortva). And, during the term of the WVI ROE, the Army collected samples from these
    monitoring wells. TR 954 (Gortva). All of this work was included within the Army’s authority to
    “investigate and collect samples . . . ; [and] construct, operate, maintain, alter, repair, and remove
    groundwater monitoring wells, appurtenances thereto, and other devices for the monitoring of
    contamination in soil, air, and water” under the WVI ROE. JX 5 at US000002.
    Moreover, all of this work occurred during the term of the WVI ROE, i.e., between May
    14, 2013 and November 13, 2014, and the Army complied with the WVI ROE’s notice and timing
    requirements “[f]or all [of its] activities.” TR 959–60 (Gortva). On expiration of the WVI ROE,
    the Army ceased all work on the ROE Property and has not re-entered the Waverley View Property
    since. JX 5 at US000001; TR 959–60 (Gortva).
    In addition, all of the monitoring wells installed by the Army were located on the ROE
    Property. Compare JX 5 at US000006, with PX 76. And, despite the need to offset some
    monitoring wells (TR 949–50 (Gortva)), there appears to be an attempt to cluster most of the
    58
    monitoring wells within the three “drilling areas” proposed in the WVI ROE’s “Scope of Work”
    (compare JX 5 at US000006, with PX 76). This was done, without any feedback from WVI about
    the proposed offset locations (TR 951 (Gortva)), and despite the Army’s broad authority to identify
    “[a]ny other drilling areas” on the ROE Property (JX 5 at US000006 (“Any other drilling areas
    identified by [the] EPA, [the] MDE or the Army would be restricted to the [ROE Property].”)).
    For these reasons, the court has determined that the Army’s and the EPA’s activities
    throughout the duration of the WVI ROE, i.e., from May 14, 2013 to November 13, 2014, did not
    exceed the scope of work described by that agreement. Therefore, no Takings Clause claims arose
    from those activities.
    v.      The Continued Presence Of The Army-Installed
    Monitoring Wells And Gravel Access Road On The
    Waverley View Property After Expiration Of The Right
    Of Entry Agreement Effected A Permanent Taking Of
    Certain Portions Thereof.
    The duration of the WVI ROE was “not to exceed eighteen (18) months, unless further
    extended by [a]greement of the parties commencing on May 14, 2013, and running through
    November 13, 2014, or, if sooner, the date of completion of the [R]emedial [I]nvestigation.” JX
    5 at US000001 (emphasis added). Despite the Army Corps’ attempts, on behalf of the Army, to
    extend the WVI ROE, an extension agreement was not reached. JX 6; JX 7; TR 959–60 (Gortva).
    Therefore, on November 13, 2014, the WVI ROE, and the Army’s and the EPA’s “right to enter
    in, on, over and across” the ROE Property, expired. JX 5 at US000001; TR 959–60 (Gortva).
    Nevertheless, the access road and monitoring wells, installed by the Army, remain on the Waverley
    View Property to this day. TR 1160–61 (Gortva); SVTR 19, 24.
    The WVI ROE, however, provided that,
    [a]ll tools, equipment, and other property taken upon or placed upon the [ROE
    Property] by the Government shall remain the property of the Government and may
    be removed by the Government at any time within a reasonable period, not to
    exceed thirty (30) days, after the expiration of [the WVI ROE].
    JX 5 at US000003 (emphasis added).
    Accordingly, the gravel used for the access road, as “other property taken upon or placed
    upon the [ROE Property] by the [Army],” “remain[s] the property of the [Army,]” despite
    expiration of the WVI ROE. And, although the Army was given “a reasonable period, not to
    exceed thirty (30) days, after the expiration of [the WVI ROE],” to remove the gravel access road,
    it remains on the Waverley View Property. TR 1160–61 (Gortva); SVTR 20.
    In addition, the WVI ROE provided that,
    if it appears from the monitoring results that they remain necessary for the
    continuing investigation, or for the monitoring and assessment of the need for any
    necessary response action, the monitoring wells installed by the Government shall
    59
    remain the property of the Government, and may be maintained on the land, subject
    to further extension of [the WVI ROE] by the parties.
    JX 5 at US000003 (emphasis added).
    Therefore, the Army’s continued ownership of the monitoring wells depends upon whether
    “it appears from the monitoring results that they remain necessary.” Relevant to this
    determination, the Government’s expert, Keith White,45 testified that
    [t]he available data demonstrate that the source of . . . contamination and . . . the
    vast majority of the contaminant mass occurs beneath Area B, not [the] Waverley
    View [Property]. A relatively small amount of contamination is present beneath a
    fraction of [the] Waverley View [Property], adjacent to Area B-11. Based on these
    facts, investigatory efforts and remedial efforts, will logically be focused on Area
    B-11.
    DX 136 at 3–4.
    Mr. K. White also testified, however, that “it is evident that some monitoring wells will
    likely be needed on [Phase] II [of the Waverley View Property] to complete the [Remedial
    Investigation] and potentially to monitor the effects of potential future remedial actions.” DX 136
    at 4. Mr. K. White’s opinion is consistent with statements the EPA made in its February 5, 2015
    letter, including that “much remains to be done with regard to the continuing [Remedial
    Investigation] of the groundwater plume,” and “urg[ing] WVI to continue to provide access to the
    Army to allow it to pursue its investigation of the groundwater plume that extends beneath [the
    Waverley View Property].” JX 8 at WVI00009414.
    Accordingly, as of the expiration of the WVI ROE, i.e., November 13, 2014, the monitoring
    wells “remain[ed] necessary for the continuing investigation, or for the monitoring and assessment
    of the need for any necessary response action.” JX 5 at US000003. Therefore, “the monitoring
    wells installed by the [Army] . . . remain the property of the [Army]” despite expiration of the
    WVI ROE. But, the Army’s right to maintain the monitoring wells on the ROE Property, was
    “subject to further extension of [the WVI ROE] by the parties.” JX 5 at US000003. No extension
    45
    To avoid confusion with Randy White, the court will refer to Keith White as “Mr. K.
    White.”
    At trial, the Government proffered Mr. K. White as an expert in “hydrogeology with a
    particular expertise in karst geology.” TR 1065. WVI did not object. TR 1066. Mr. K. White
    has “over 28 years’ consulting experience in evaluating the nature, extent, and transport of
    contaminants in groundwater––20 of those years focused on karst geology” and “currently leads
    [Arcadis’s] Karst Hydrology Focus Area[.]” DX 136 at 2, Appendix A. Mr. K. White’s education
    includes a Bachelor of Science (“BS”) in Geology from the State University of New York and
    Graduate Studies at Syracuse University in Containment Hydrogeology and Geochemistry and
    Advanced Hydrogeology. DX 136 at Appendix A. Therefore, the court considers Mr. K. White
    an expert in “hydrogeology with a particular expertise in karst geology.” TR 1065–66; see also
    FED. R. EVID. (“FRE”) 702.
    60
    agreement was reached, however, and the Army’s right to maintain the monitoring wells on the
    property expired with the WVI ROE, on November 13, 2014.
    Therefore, although the Army was not required to remove either the gravel access road or
    the monitoring wells, by failing to do so, the Army has, and continues to, physically occupy certain
    portions of the Waverley View Property. Such “physical occupation,” amounts to a compensable
    taking. See Stearns Co., 
    396 F.3d at 1357
     (“A physical taking occurs “when the government itself
    occupies the property or ‘requires the landowner to submit to physical occupation of its land.”)
    (internal quotations omitted); see also Huntleigh USA Corp., 
    525 F.3d at 1378
     (“A compensable
    taking . . . occurs . . . through the government's physical invasion or appropriation of private
    property[.]”).
    Having determined that the Army’s activities after expiration of the WVI ROE amounted
    to a compensable taking,46 the court must next determine whether this taking is a “permanent
    physical occupation[]” or a “temporary [physical] invasion[].” See Ark. Game & Fish Comm'n,
    
    568 U.S. at 36
    .
    As in Hendler III, “[t]here is nothing ‘temporary’ about the wells the [Army] installed on
    [WVI’s] property.” See Hendler III, 952 F.2d at 1376. More than three years have passed since
    the WVI ROE expired and more than four since the Army first began installing the wells. TR 949
    (Gortva). The four deep monitoring wells are 142 to 400 feet deep, lined with steel casings, and
    are surrounded by concrete and protective bollards at the surface. PX 86; TR 951, 1008 (Gortva).
    These wells are significant structures. Although the eleven shallow monitoring wells are less
    intrusive, they are by no means “transient [or] relatively inconsequential.” See John R. Sand &
    Gravel Co., 457 F.3d at 1357. And, in this case, all of the Army-installed monitoring wells “are
    at least as ‘permanent’ . . . as the CATV equipment in Loretto, which comprised only a few cables
    attached by screws and nails and a box attached by bolts.” See Hendler III, 952 F.2d at 1376. The
    same is true for the gravel access road which consists of several inches of stone and is “20 [to] 25
    46
    The Government insists that WVI’s Takings Clause claims are “speculat[ive]” or
    “anticipatory,” and thus “not ripe.” See, e.g., Gov’t Post-Tr. Resp. Br. at 54–56. But, by leaving
    the Army-installed gravel access road and monitoring wells on the property, the Army has, and
    continues to, physically occupy certain portions of the Waverley View Property. There is nothing
    speculative or anticipatory about the presence of these structures.
    The Government’s arguments that WVI’s claims are governed by contract law are also
    without merit. See, e.g., Gov’t Post-Tr. Resp. Br. at 56–57. As the Government acknowledges,
    the WVI ROE did not require the Army to remove the Army-installed gravel access road or
    monitoring wells. Gov’t Post-Tr. Resp. Br. 57. Instead, the WVI ROE permitted the Army to
    remove these structures, and provided a “reasonable period, not to exceed thirty (30) days” during
    which it could do so. JX 5 at US000003. Therefore, the Army’s failure to remove the gravel
    access road and the monitoring wells was not a breach of the WVI ROE, because it was not
    required by that agreement. Instead, by leaving the Army-installed gravel access road and
    monitoring wells on the Waverley View Property after the expiration of the WVI ROE, the Army
    effected a physical taking.
    61
    feet wide and hundreds of feet long.” TR 200 (Anderson); TR 953 (Gortva); see also PX 88 at A-
    14 (Image 8).
    In addition, nothing in the Army’s or the EPA’s actions “suggests that the [Army-installed
    monitoring] wells [are] a momentary excursion shortly to be withdrawn.” See Hendler III, 952
    F.2d at 1376. The deep monitoring wells are “designed to last for up to 30 years.” TR 1010
    (Gortva). And, “[u]nder the best circumstances” it may take “five years” to complete a “pilot
    study,” after which, a “full scale” remedial program could take “decades.” TR 295–99 (Thomson);
    TR 1080–82 (White). Nor do the Army’s or the EPA’s actions “disclose any indication of a
    timetable for withdrawal.” See Hendler III, 952 F.2d at 1376. As the EPA’s February 5, 2015
    letter stated, “since the full extent of the contaminated groundwater plume is not yet known, the
    Army and EPA cannot estimate the total length of time needed to address the contamination on
    WVI’s property.” JX 8 at WVI00009415 (emphasis added). In short, the Army, doesn’t know if,
    or when, it can remove the monitoring wells from the Waverley View Property.47
    The Army Corps’ September 30, 2016 letter does not provide further clarity. This letter
    states that “the Army’s rights under [the WVI ROE] are at an end . . . and the Army has no
    continuing rights with respect to the [ROE P]roperty[.]” JX 10 at WVI00009417. Although this
    is true, the gravel access road and the monitoring wells nevertheless remain on the Waverley View
    Property. TR 1160–61 (Gortva). And, the Government’s argument that the Army Corps’
    September 30, 2016 letter terminated its “rights or interest in the monitoring wells” and ended its
    physical occupation of the Waverley View Property, is without merit. Gov’t Post-Tr. Resp. Br. at
    57–58. The Army Corps cannot unilaterally burden WVI with the task of removing the gravel
    access road and the monitoring wells by announcing, after this case was filed, that it was
    terminating its ownership interests in these structures. As the court in Hendler III observed, “the
    government[,] when it has taken property by physical occupation[, may] subsequently decide to
    . . . release its interest in . . . property. Yet no one would argue that that would somehow absolve
    the government of its liability for a taking[.]” See Hendler III, 952 F.2d at 1376. Otherwise, “[a]ll
    takings [would be] ‘temporary’ . . . [because] the government can always change its mind.” Id.
    And, as the United States Supreme Court held in Arkansas Game and Fish Commission, “[o]nce
    the government's actions have worked a taking of property, ‘no subsequent action by the
    government can relieve it of the duty to provide compensation[.]’” Ark. Game & Fish Comm'n,
    
    568 U.S. at 33
    .
    Neither the Army nor the EPA has entered the Waverley View Property since expiration
    of the WVI ROE (TR 1160–61 (Gortva)), however, and have no immediate or certain plans to do
    so (DX 111 at 3–5; TR 1080–83, 1085 (White); TR 1385–99 (Tesner); ECF No. 70, 95).
    Therefore, the existence of ongoing or future activities that may give rise to additional Takings
    47
    Recently, the Government has indicated that neither the Army nor the EPA has an
    immediate or certain need for the Army-installed monitoring wells on the Waverley View
    Property. DX 111 at 3–5; TR 1080–83, 1085 (White); TR 1385–99 (Tesner); ECF No. 70 (April
    3, 2017 Status Report, reporting that representatives from the Army, the EPA, the MDE, and the
    “Army’s contractors concerning the pilot project/study” met on March 30, 2017 to “discuss the
    pilot project/study,” and “confirmed that the pilot project/study would not require access to the
    Waverley View [P]roperty.”); ECF No. 95.
    62
    Clause claims is not an issue the court can resolve at this time. And, as such, the court is left with
    only those portions of the Waverley View Property that were physically occupied by the Army-
    installed gravel access road and monitoring wells.
    For these reasons, the court has determined that the Army’s activities after expiration of
    the WVI ROE on November 13, 2014 effected a permanent physical taking of those portions of
    the Waverley View Property actually occupied by the Army-installed gravel access road and
    monitoring wells.
    3.      At Trial, Plaintiff Established That It Is Entitled To Just
    Compensation.
    a.      Plaintiff’s Argument.
    WVI argues that it is entitled to “[c]ompensation for the [t]otal [l]ost [v]alue of the
    [Waverley View] Property.” Pl. Post-Tr. Br. at 44. As a practical matter, “continuing CERCLA
    operations on the [p]roperty . . . [have] taken from WVI the opportunity to make its intended use
    on [Phase] II and caused a substantial diminution in the value of [Phase] I.” Pl. Post-Tr. Br. at 44.
    This is evidenced by the fact that, “the [Army’s] physical occupation of the [p]roperty is of
    indefinite duration. . . . [E]ven after the [Army] completes its remedial investigation of the
    [p]roperty and selects a remedy — which by itself is years away — it will still likely take many
    more years beyond that to implement the remedy, and decades more to monitor the outcome.” Pl.
    Post-Tr. Br. at 44. During this time, WVI cannot develop Phase II, “so long as [the monitoring]
    wells and appurtenances remain in place, and the potential for EPA or Army intrusions and
    remedial actions remains real[,] but uncertain in their scope and duration[.]” Pl. Post-Tr. Br. at 44.
    In takings cases, “the [g]overnment must . . . compensate a property owner for the entirety
    of its loss, even when it has occupied something less than the totality of the property.” Pl. Post-
    Tr. Br. at 45. As the United States Supreme Court explained in United States v. Grizzard, 
    219 U.S. 180
     (1911), “[w]hen the part [of the property] not taken is left in such shape or condition as
    to be in itself of less value than before, the owner is entitled to additional damages on that account.”
    
    Id. at 185
    ; see also United States v. Miller, 
    317 U.S. 369
    , 376 (1943) (“If only a portion of a single
    tract is taken[,] the owner’s compensation for that taking includes any element of value arising out
    of the relation of the part of the entire tract.”); Hendler III, 952 F.2d at 1383–84 (“[O]nce a taking
    is adjudged, plaintiffs will have the opportunity to establish their severance damages, the damages
    accruing to their retained land as a result of the taking.”).
    At trial, Messrs. Dorment and Anderson and Eric Soter48 testified that the Army’s
    “occupation of . . . [Phase II] has made it impracticable for WVI to develop or sell the [Waverley
    View] Property.” Pl. Post-Tr. Br. at 24.
    48
    Mr. Soter is a principal at Rodgers Consulting, Inc., a “civil engineering, land planning,
    and surveying firm, headquartered in Germantown, Maryland” that also does work in Frederick,
    Maryland and Prince George’s County. TR 547–48. Mr. Soter previously worked for the County
    of Frederick, where he “oversaw all aspects of land development, including comprehensive
    planning and development review[.]” TR 548. At trial, WVI proffered Mr. Soter as an expert in
    63
    First, the . . . gravel [access] road[] and [the] existing well network have rendered
    obsolete WVI’s existing development plans as they pertain to [Phase] II. Second,
    the uncertainty surrounding all aspects of the [Army’s] ongoing occupation and use
    of the [p]roperty has made it foolhardy for WVI to spend the time and money to
    revise its preliminary plans for [Phase] II. Third, and perhaps most significantly,
    the uncertainty surrounding the [Army’s] occupation and use of the [p]roperty has
    destroyed any interest among buyers in purchasing the parts of the [p]roperty that
    were developed as [Phase] I.
    Pl. Post-Tr. Br. at 24.
    Because “the [Army’s] entry onto and ongoing occupation of [Phase] II has severely
    impaired the marketability of [Phase] I,” WVI asserts that it is “entitled to . . . severance damages,”
    because
    [p]otential buyers are understandably leery of investing in land adjacent to an
    ongoing CERCLA action on the same private land parcel. They are especially leery
    of doing so when the parameters of that investigation are uncertain, so that there
    exists the real — and highly visible — threat of the [Army or the EPA] someday
    demanding access to and use of the very land the potential buyers are evaluating
    for purchase. Buyers with multiple options will take their money elsewhere.
    Pl. Post-Tr. Br. at 45.
    Moreover, as a practical matter, “WVI has permanently lost the chance to make its planned
    use of [Phase] II, and [Phase] I will remain stigmatized by [the Army’s] activities on the
    [p]roperty.” Pl. Post-Tr. Br. at 46 (citing PX 88 at 73–76; PX 157 at 15). And, “[w]hen
    government action permanently deprives a landowner of the use of the landowner’s property, ‘the
    conventional method of valuation is the “before-and-after” method, i.e., the difference between
    the value of the property before and after the [taking] was imposed.’” Pl. Post-Tr. Br. at 46
    (quoting Otay Mesa Prop., L.P. v. United States, 
    670 F.3d 1358
    , 1364 (Fed. Cir. 2012)) (citing
    Bass Enters. Prod. Co. v. United States, 
    133 F.3d 893
    , 895 (Fed. Cir. 1998) (“The just
    compensation for a permanent taking is generally the fair market value of the property taken[.]”)).
    “land use planning . . . in the City of Frederick, Maryland.” TR 551. The Government objected.
    TR 551. The court does not consider Mr. Soter an expert in “land use planning . . . in the City of
    Frederick, Maryland,” because he “never worked for the City of Frederick,” which has its own
    unique “land use planning laws and regulations” and Mr. Soter never spoke “with anyone from the
    City of Frederick [before] preparing [his] report.” TR 558, 560. Instead, the court considers Mr.
    Soter’s testimony as a lay witness.
    64
    In this case, as William Harvey49 testified, that value, “including severance damages to [Phase] I,
    is $9.2 million.”50 Pl. Post-Tr. Br. at 46–47.
    WVI argues that the Government’s appraisal does not “account for the fact that the
    [Army’s] presence on the [Waverley View] Property during an ongoing Superfund NPL Site
    Remedial Investigation has rendered [Phase] II undevelopable and diminished the value of [Phase]
    I.” Pl. Post-Tr. Br. at 48. In addition, the Government’s appraisal “assume[s] that if any . . . stigma
    exists, it entirely predated the [Army’s] installation of wells and is solely the result of the
    [p]roperty’s proximity to Fort Detrick Area B.” Pl. Post-Tr. Br. at 49.
    In the alternative, if the court “determines that the [Army’s] open-ended, decades-long,
    physical occupation of the [p]roperty is a temporary taking, then it should apply the standard
    measure of damages in a temporary takings case — ‘the fair rental value of the property for the
    period of the taking.’” Pl. Post-Tr. Br. at 50 (quoting Otay Mesa Prop., 670 F.3d at 1364) (citing
    Yuba Nat. Res. v. United States, 
    904 F.2d 1577
    , 1581 (Fed. Cir. 1990) (“The usual measure of just
    compensation for a temporary taking . . . is the fair rental value of the property for the period of
    the taking.”)). In this case, “[b]ecause not even the Government can reasonably estimate the end
    date of the taking, calculating just compensation using this method requires a number of
    assumptions. Based on those assumptions, . . . the fair rental value of the property for the period
    in question is $9,080,000.” Pl. Post-Tr. Br. at 50 (citing PX 157 at 17; TR 749 (Harvey)).
    In addition, WVI states that it is “entitled to compounded interest on the $9.2 million value
    of the [p]roperty.” Pl. Post-Tr. Br. at 50. This is so, because it is well established that “something
    more than fair market value is required to make [a] property owner whole, to afford him ‘just
    compensation” when the government takes his property. Albrecht v. United States, 
    329 U.S. 599
    ,
    602 (1947). That “something more” has been “measured in terms of reasonable interest.” 
    Id.
     In
    sum, “‘just compensation’ in the constitutional sense, has been held[] . . . to be the fair market
    value at the time of taking[,] plus interest from that date to the date of payment.” Pl. Post-Tr. Br.
    at 50 (internal quotations omitted) (quoting Albrecht, 
    329 U.S. at 602
    ).
    Applying the factors set forth in Georgia-Pacific Corp. v. United States, 
    640 F.2d 328
     (Ct.
    Cl. 1980), the United States Court of Federal Claims “has repeatedly found that prudent investors
    49
    At trial, WVI proffered Mr. Harvey as an “expert appraiser.” TR 749. The Government
    did not object. TR 749. Since 1986, Mr. Harvey has severed as President of William C. Harvey
    & Associates, Inc., a real estate appraisal and brokerage firm. PX 88 at 90. Prior to that, he served
    as Vice President and Regional Manager of Legg Mason Appraisal Group from 1983 to 1986, as
    President and Director of Appraisal Service of America, Inc. from 1981 to 1983, and as a Staff
    Appraiser at Accredited Real Estate Appraisal Service, Inc. from 1977 to 1980. PX 88 at 90. Mr.
    Harvey has been qualified as an expert on “well over a hundred” occasions. TR 739. Therefore,
    the court considers Mr. Harvey an “expert appraiser.” TR 749; see also FRE 702.
    50
    This represents the difference between $13,040,000, the estimated “fair market value of
    the [Waverley View] Property prior to installation of groundwater monitoring wells,” and
    $3,840,000, the estimated “fair market value of the [p]roperty after installation of groundwater
    monitoring wells,” as determined by Mr. Harvey. Pl. Post-Tr. Br. at 32.
    65
    would collect quarterly compounded interest on their investments at a rate like the Moody’s
    Seasoned AAA Corporate Bond Index[.]” Pl. Post-Tr. Br. at 50–51 (citing Sears v. United States,
    
    124 Fed. Cl. 730
    , 735–36 (Fed. Cl. 2016)). “Between the time the [Army] entered onto WVI’s
    [p]roperty on November 21, 2013, and today, that rate has fluctuated between 4.7% and 3.3%.”
    Pl. Post-Tr. Br. at 51. Although the Government “will likely encourage the Court to adopt a lower
    rate — such as the U.S. Treasury [B]ill compounded rate of interest — . . . [the c]ourt should
    decline the Government’s invitation.” Pl. Post-Tr. Br. at 51.
    b.      The Government’s Response.
    The Government responds that WVI failed to prove that “the Army ‘has, as a practical
    matter, taken from WVI the opportunity to make its intended use of [Phase] II and caused a
    substantial diminution in the value of [Phase] I.’” Gov’t Post-Tr. Resp. Br. at 46 (quoting Pl. Post-
    Tr. Br. at 44). Specifically, “WVI . . . failed to show that any action by the [Army or the EPA]
    prevented it from moving forward with its plans to develop [Phase] II [of the Waverley View
    Property], or reduced the value of [Phase] I[.]” Gov’t Post-Tr. Resp. Br. at 46. Instead, “[t]he
    only discrete government action – the installation of . . . monitoring wells . . . pursuant to the [WVI
    ROE] – occupied a miniscule portion of [Phase] II and none of [Phase] I.” Gov’t Post-Tr. Resp.
    Br. at 46.
    In addition, WVI failed to identify any “government action that barred development of
    [Phase] II.” Gov’t Post-Tr. Resp. Br. at 47. Messrs. Dorment and Anderson both admit that “no
    one on behalf of the government told them that they could not go forward with developing [Phase]
    II or getting approvals to develop [Phase] II[,] until groundwater monitoring was completed.”
    Gov’t Post-Tr. Resp. Br. at 47 (citing TR 477 (Anderson); TR 729–30 (Dorment)). In addition,
    “the [C]ity of Frederick Planning Department testified that the presence of groundwater
    monitoring wells would not preclude final site plan approval.” Gov’t Post-Tr. Resp. Br. at 47
    (citing JX 30 at 20).
    Moreover, “[i]n none of the meetings between the parties from 2011-2013 did WVI discuss
    any preliminary plans for [Phase] II or indicate that it had plans in the short term to develop [Phase]
    II.” Gov’t Post-Tr. Resp. Br. at 47 (citing TR 956–57 (Gortva)). Nor did WVI “raise[] the issue
    of whether the wells would conflict with the preliminary site plan[,]” despite the Army’s repeated
    requests for input. Gov’t Post-Tr. Resp. Br. at 47 (citing TR 727 (Dorment)). And, despite the
    fact that the Army “notified WVI of well locations both before the first wells were installed and
    later when certain well locations needed to be [offset],” WVI never complained. Gov’t Post-Tr.
    Resp. Br. at 48 (citing DX 127; DX 139; TR 950–51, 1142–44 (Gortva)).
    WVI’s silence “about the proposed well locations – prior to filing this lawsuit – is not
    surprising in light of the fact that the buyer of [Phase] II, [and] not WVI, would be responsible for
    obtaining final site plan approval.” Gov’t Post-Tr. Resp. Br. at 48 (citing PX 29 at WVI00007847).
    WVI’s “silence is further explained by its unilateral conclusion – by at least March 2013 – that, if
    contamination were discovered through the Army’s groundwater monitoring, the Army would
    purchase [Phase] II.” Gov’t Post-Tr. Resp. Br. at 49.
    66
    If WVI had informed the Army of its development plans,51 or “responded to the Army’s
    repeated requests for feedback, the wells on [Phase] II could have been located so as not to conflict
    with the preliminary plan.” Gov’t Post-Tr. Resp. Br. at 51. As Mr. Tesner,52 “the Army’s Director
    for Restoration,” testified:
    There’s nothing . . . about the placement of the wells on the Waverley [View
    P]roperty, either there now or contemplated, that couldn’t be addressed, even
    today . . . any of the wells that are there right now could be moved, they could be
    removed. It’s not hard. It’s done all the time.
    Gov’t Post-Tr. Resp. Br. at 51 (quoting TR 1336 (Tesner)).
    Nevertheless, WVI insists, without support, that “the Army’s well-established
    environmental restoration policies and practices . . . [are] non-existent, supposedly because neither
    of the Government witnesses who testified about it could ‘identify a single Government document
    supporting [Mr. Tesner’s] contention.’” Gov’t Post-Tr. Resp. Br. at 51–52 (quoting Pl. Post-Tr.
    Br. at 27).
    In contrast to the Government’s environmental restoration expert, Mr. Tesner, WVI’s
    proffered expert, Mr. Soter, is not qualified to “provide expert testimony on the impact of
    groundwater monitoring wells on development of [Phase] II” for numerous reasons. Gov’t Post-
    Tr. Resp. Br. at 52–53 (citing TR 558, 560–62, 583–84 (Soter)).
    Were the court to determine that the Army is liable for a permanent taking, “the trial
    testimony and applicable legal standards do not support an award of just compensation in [the
    amount of $9,200,000].” Gov’t Post-Tr. Resp. Br. at 58 (citing Pl. Post-Tr. Br. at 44). Instead, as
    51
    Although “miniscule diagram[s]” of WVI’s development plans were “buried in the soils
    report Mr. Anderson mailed to the Army with his May 9, 2011 letter,” WVI never “raised the
    diagram[s] or any other reproduction of its preliminary site plan at any time during the numerous
    meetings with the Army . . . or in response to the Army’s communications about proposed well
    locations.” Gov’t Post-Tr. Resp. Br. at 34 n.6. Moreover, the “diagram[s] do[] not appear in any
    groundwater monitoring report provided to the Army. Rather, [they are] only in a soils report –
    which was not the focus of the Army’s investigation.” Gov’t Post-Tr. Resp. Br. at 34 n.6.
    52
    At trial, the Government proffered Mr. Tesner as an expert in “Army Environmental
    Restoration Program policies and practices.” TR 1295. WVI did not object. TR 1295. Mr. Tesner
    has served as the Director for Restoration in the Office of the Deputy Assistant Secretary of the
    Army for Environmental, Safety, and Occupational Health for nine years. TR 1287. In that
    position, he oversees “[l]iterally thousands” of “cleanup sites.” TR 1292–93. Previously, Mr.
    Tesner served as “Cleanup Branch Chief for Cleanup and Restoration Activities” at the Army
    National Guard for three years, where he oversaw “hundreds” of “cleanup sites,” and also as
    Project Manager for the Army Corps’ Hazardous Toxicological and Radiological Waste Branch
    for nine years. TR 1293. Therefore, the court considers Mr. Tesner an expert in “Army
    Environmental Restoration Program policies and practices.” TR 1295; see also FRE 702.
    67
    explained by the Government’s “expert appraiser, [Terrence] McPherson,53 the difference in value
    of the property with perpetual easements for the location of the wells versus without is $250,000.”
    Gov’t Post-Tr. Resp. Br. at 58 (citing DX 142 at 4). As Mr. McPherson testified, if the court finds
    a temporary taking, “the rental value for the physical occupation of the wells from November 14,
    2014 through September 30, 2016 would be $19,000.” Gov’t Post-Tr. Resp. Br. at 58 (citing DX
    142 at 3; Yuba Nat. Res., Inc. v. United States, 
    821 F.2d 638
    , 641 (Fed. Cir. 1987) (explaining that
    rental value is a proper means of just compensation for a temporary, physical taking)).
    WVI’s $13,040,000 “before” valuation of the Waverley View Property also is inconsistent
    with the Uniform Appraisal Standards for Federal Land Acquisitions (the “UASFLA”), that
    provides:
    a hypothetical condition may be used only if:
       use of the hypothetical condition is clearly required for legal purposes, for
    purposes of reasonable analysis, or for purposes of comparison;
       use of the hypothetical condition results in a credible analysis; and
       the appraiser complies with the disclosure requirements set forth in [the
    Uniform Standards of Professional Appraisal Practice (the “USPAP”)] for
    hypothetical conditions.
    Gov’t Post-Tr. Resp. Br. at 58–59 (citing THE APPRAISAL FOUNDATION, UNIFORM APPRAISAL
    STANDARDS FOR FEDERAL LAND ACQUISITIONS § 1.2.7.1 (5th ed. 2000)). Despite “undisputed
    facts” to the contrary, Mr. Harvey “assumed that before the Army installed groundwater
    monitoring wells, the [p]roperty was in pristine condition and unaffected by any environmental
    stigma.” Gov’t Post-Tr. Resp. Br. at 59. As a result,” Mr. Harvey “artificially and unreasonably
    inflate[d] the supposed value of the [p]roperty before the taking.” Gov’t Post-Tr. Resp. Br. at 60.
    WVI’s $3,840,000 “after” valuation is likewise flawed. Gov’t Post-Tr. Resp. Br. at 60–
    61. Mr. Harvey was instructed by WVI to assume that “once groundwater monitoring wells were
    installed, it was both legally and physically impossible to develop Phase II.” Gov’t Post-Tr. Resp.
    Br. at 60 (citing TR 774 (Harvey)). This assumption is contrary to the “unrebutted” testimony of
    Mr. Tesner and Joseph Gortva, Installation Restoration Manager and Hazardous Waste Manager
    for Fort Detrick (TR 904 Gortva), and is “unsupportable,” since the City of Frederick never
    53
    At trial, the Government proffered Mr. McPherson as an expert in “real estate appraisal.”
    TR 1164. WVI did not object. TR 1164. Mr. McPherson is the owner of McPherson & Associates,
    Inc., a real estate appraisal and consulting firm in Frederick, Maryland. TR 1162. He has worked
    as a “professional appraiser” for over 35 years and has acquired MAI and SRA designations. TR
    1163. Mr. McPherson has testified as an “expert appraiser” in federal and state court between
    “twenty [and] 30 times.” TR 1164. Therefore, the court considers Mr. McPherson an expert in
    “real estate appraisal.” TR 1164; see also FRE 702.
    68
    instructed WVI that it could not develop the Waverley View Property while groundwater
    monitoring wells were in place (Gov’t Post-Tr. Resp. Br. at 60).
    In addition,
    WVI admits that the Army has never told [WVI] that [it is] unable to develop [its]
    property; . . . WVI has yet to submit a development plan (or re-submit
    [RGHGAB’s] proposed plan) to the City of Fredrick; and . . . the Army has worked
    with owners of other residential developments to conduct monitoring and
    remediation activities in a manner that does not interfere with development, and
    would do so [on the Waverley View Property].
    Gov’t Post-Tr. Resp. Br. at 67–68. Instead, WVI’s decision not to develop the Waverley View
    Property represents “a business decision not to sell [Phase] II[,] based on its unsupported
    speculation that the Army would purchase . . . the [p]roperty.” Gov’t Post-Tr. Resp. Br. at 68.
    In addition, “WVI seeks an award for the value lost to the remainder of the Waverley [View
    P]roperty that was never physically occupied by the [Army], i.e., [Phase] I[,]” based on “an alleged
    reduction in value caused by the purported stigma imposed on [Phase] I.” Gov’t Post-Tr. Resp.
    Br. at 61–62. Any stigma associated with the Waverley View Property, however, “existed long
    before WVI’s purchase in 2012.” Gov’t Post-Tr. Resp. Br. at 62 (citing DX 142 at 12–15). Nor
    did the Army’s groundwater monitoring of Phase II cause WVI to lose buyers of Phase I. Gov’t
    Post-Tr. Resp. Br. at 65. Instead, each “deal” for the purchase of Phase I discussed by Mr.
    Dorment, fell through for other reasons, not the least of which was that WVI “could not
    truthfully . . . assur[e potential buyers] that [the Waverley View Property was] clean so there was
    no risk of Government intrusion on the [p]roperty.’” Gov’t Post-Tr. Resp. Br. at 65–66 (internal
    quotations omitted) (quoting Pl. Post-Tr. Br. at 29).
    Likewise, WVI’s arguments that Mr. McPherson’s appraisal is based on flawed
    assumptions “are not supported by the evidence.” Gov’t Post-Tr. Resp. Br. at 68. First, Mr.
    McPherson’s assumption that WVI “could proceed with development on [Phase] II despite the
    existence of the monitoring wells” is based on conversations with “officials at the Frederick
    Planning Office . . . confirm[ing] that the wells’ existence would not impact [WVI’s] ability to
    develop Phase [II].” Gov’t Post-Tr. Resp. Br. at 68; see also TR 1178–80 (McPherson). Second,
    Mr. McPherson assumed that “any stigma associated with the WVI property existed prior to the
    Army’s installation of the monitoring wells” because of the “comprehensive list of activities that
    he believed stigmatized the [Waverley View P]roperty at the time of its purchase in 2012, prior to
    the installation of the wells on Phase [II].” Gov’t Post-Tr. Resp. Br. at 68 (citing DX 142 at 12–
    15). In contrast, “WVI’s appraiser, Mr. Harvey, does not address why the long history of
    contamination at Fort Detrick . . . would not have placed an environmental stigma on the [Waverley
    View P]roperty.” Gov’t Post-Tr. Resp. Br. at 68. Third, “WVI’s assertion that Mr. McPherson’s
    temporary taking valuation is unreliable, because it does not consider potential future remediation
    activities . . . is legally unsupported[,]” because it is “based on potential actions . . . in the future
    [that are] unripe, speculative, and cannot form the basis for compensation in this action.” Gov’t
    Post-Tr. Resp. Br. at 68–69 (citing Pl. Post-Tr. Br. at 48).
    69
    Finally, the “proper interest rate” that the court should apply is “the rate set forth in the
    Declaration of Takings Act (the “DTA”), 
    40 U.S.C. § 3116
    , which “provides a standardized and
    uniform method for calculating delay compensation in the direct condemnation context, . . . [and]
    has been [applied] in other inverse condemnation actions.” Gov’t Post-Tr. Resp. Br. at 69 (citing
    Textainer Equip. Mgmt. Ltd. v. United States, 
    99 Fed. Cl. 211
    , 223 (Fed. Cl. 2011) (determining
    that “the DTA rate, and not the Moody's Corporate Bond Index rate” should apply to damages for
    an alleged taking of subleased containers lost by the government)); see also NRG Co. v. United
    States, 
    31 Fed. Cl. 659
    , 670 (Fed. Cl. 1994) (applying the DTA rate as “a more accurate measure
    of the economic harm . . . than the CDA interest rates” to claims for damages resulting from the
    “cancel[ation of] three mineral prospecting permits owned by plaintiffs”); Vaizburd v. United
    States, 
    67 Fed. Cl. 499
    , 504 (Fed. Cl. 2005) (explaining that “[i]n the absence of special proof that
    a rate other than [the DTA rate] is appropriate, [the court] use[s the DTA] rate” to assess interest
    on damages resulting from the government’s “deposition of sand on plaintiffs’ property”). The
    DTA rate “fully compensate[s] plaintiffs for any delay in payment and ensure[s] uniformity in
    delay compensation awards among plaintiffs in condemnation actions.” Gov’t Post-Tr. Resp. Br.
    at 69. In sum, the court has considered the DTA rate as the “default,” and “WVI has not established
    that a departure from the [DTA] rate[] . . . is warranted in this case.” Gov’t Post-Tr. Resp. Br. at
    70.
    In the alternative, “[t]o the extent that the Court finds it necessary to determine interest in
    this case through an ‘investment’ lens, the United States’ unsecured borrowing rate represents the
    return on investment that WVI has lost, at the risk WVI faced.” Gov’t Post-Tr. Resp. Br. at 70.
    In this regard, “[t]he 1-year T[reasury B]ill provides the best legal measure of interest as a
    component of just compensation.” Gov’t Post-Tr. Resp. Br. at 70.
    c.      Plaintiff’s Reply.
    WVI replies that detailed development plans for Phase II of the Waverley View Property
    were included in the 2010 CGS Site Investigation Report provided to the Army Corps with Mr.
    Anderson’s May 9, 2011 letter. Pl. Post-Tr. Reply Br. at 21. Mr. Gortva “confirmed twice during
    his cross-examination that he received and reviewed this report.” Pl. Post-Tr. Reply Br. at 21
    (citing TR 990–92, 1035–37 (Gortva)). In Mr. Dorment’s May 24, 2013 letter, he also “informed
    the Army and the EPA . . . that WVI had ‘concrete plans’ for real estate development that were
    being ‘jeopardized’ by the Government’s planned CERCLA activities on the [p]roperty.” Pl. Post-
    Tr. Reply Br. at 24 (quoting PX 10). These plans, “for which WVI had obtained preliminary
    approval from the City of Frederick . . . were public documents readily available to any interested
    person.” Pl. Post-Tr. Reply Br. at 24.
    Therefore, it is “disingenuous for the Government to claim that it would have
    accommodated WVI’s real estate development plans[,] if only it had known about them.” Pl. Post-
    Tr. Reply Br. at 24. At no time did the Army “mention . . . any such accommodation policy and
    practice in any of the multiple letters it sent to Mr. Anderson seeking access to the [Waverley
    View] Property from 2011 to 2012.” Pl. Post-Tr. Reply Br. at 24. The Government relies heavily
    and almost exclusively on the testimony of Mr. Tesner to attempt to establish the existence of a
    federal “policy” of accommodating planned real estate development in the context of a CERCLA
    investigation and remedial action. Pl. Post-Tr. Reply Br. at 27. But, Mr. Tesner’s testimony
    neither “disprove[s] a taking” nor “demonstrate[s] that WVI can develop [the Waverley View]
    70
    Property merely by asking the Army to relocate [its] groundwater monitoring wells.” Pl. Post-Tr.
    Reply Br. at 27–28. Although the Army is responsible for “thousands of contaminated sites . . .
    Mr. Tesner . . . produced just four examples of [the Army’s] alleged accommodation practice.” Pl.
    Post-Tr. Reply Br. at 28 (citing TR 1292 (Tesner)). In contrast, Mr. K White “testified that he was
    aware of no Army or EPA written policy directive to accommodate planned real estate
    development at a CERCLA remedial investigation and remedial action site.” Pl. Post-Tr. Reply
    Br. at 32 (citing TR 1097–98 (White)).
    More importantly, “[t]he EPA model order makes perfectly clear that any real estate use of
    a property that is the subject of a CERCLA action by the EPA is entirely subordinate to the EPA’s
    needs to promptly carry out a CERCLA remedial investigation and remedial action.” Pl. Post-Tr.
    Reply Br. at 33 (citing PX 6 at US000168–69, US000174 (“This Order further requires
    [r]espondent to refrain from interfering with access to the [p]roperty by [the] EPA and its
    authorized representatives for the purposes set forth herein. . . . Any such conveyance shall restrict
    the use of the [p]roperty so that the use will not interfere with activities undertaken or to be
    undertaken by [the] EPA and its representatives.”)).
    As a practical matter, Mr. Soter testified that, “accommodating the Army’s current
    groundwater wells in WVI’s very compact development would require WVI to redesign its site
    plans, at considerable effort and expense.” Pl. Post-Tr. Reply Br. at 34 (citing PX 156 at 3). The
    Government does not contest this, and “[i]ts own expert, Mr. McPherson, actually agreed with Mr.
    Soter[.]” Pl. Post-Tr. Reply Br. at 34 (citing DX 142 at 90). In addition, “[t]he Government’s
    slew of objections to Mr. Soter’s testimony go only to its weight, not its admissibility. Mr. Soter
    is well qualified to give the opinions he offered at trial.” Pl. Post-Tr. Reply Br. at 34. Despite the
    Government’s views to the contrary, Mr. Soter “does not need to have been a former employee of
    the City of Frederick to be an expert in this case.” Pl. Post-Tr. Reply Br. at 35.
    Next, the “Government criticizes Mr. Harvey for carrying out his ‘before valuation’ by
    assuming that the [Waverley View] Property was not affected by the presence of TCE and PCE[,]”
    but his assumption is consistent with the USPAP. Pl. Post-Tr. Reply Br. at 37. Mr. Harvey “relied
    on the fact that the [p]roperty had been investigated by environmental engineers, including through
    groundwater well drilling and sampling, and no hazardous substances were found on the
    [p]roperty.” Pl. Post-Tr. Reply Br. at 37–38 (citing PX 157 at 3). And, “the NFRD certification
    by the State of Maryland provided a sound basis for Mr. Harvey’s hypothetical assumption [and]
    . . . did not result in an inflated valuation of the [Waverley View] Property, as the Government
    erroneously suggests.” Pl. Post-Tr. Reply Br. at 38. In fact, Mr. Harvey’s appraisal is “directly in
    line with the range of appraisals by Mr. McPherson and other appraisers from late 2012 through
    2015.” Pl. Post-Tr. Reply Br. at 39. Therefore, “[t]he Government’s attack on Mr. Harvey’s
    assumption that it was impossible to develop [Phase] II of the [Waverley View] Property for the
    foreseeable future is baseless.” Pl. Post-Tr. Reply Br. at 41. To the contrary, “[t]he . . . 15 wells
    on the [Waverley View] Property are physical impediments to its development, have been since
    November 2013, and will be as long as they are present.” Pl. Post-Tr. Reply Br. at 41. Moreover,
    “[n]o rational home builder, given a choice of other properties on the market, would be willing to
    step into this quagmire, subject to the unretracted EPA letters of February 2013 and February 2015
    threatening CERCLA liability[.]” Pl. Post-Tr. Reply Br. at 41. As Mr. Harvey testified, “‘[g]iven
    that the EPA already raised the risk of CERCLA-related liability to an owner of the subject
    property, the risks . . . include market resistance or stigma.’” Pl. Post-Tr. Reply Br. at 44 (quoting
    71
    PX 157 at 15). “[M]arket resistance” was “borne out by the actual experience of the real estate
    market,” as interest in the Waverley View Property “dissipated” by 2014, despite several
    developers expressing interest in early 2013. Pl. Post-Tr. Reply Br. at 44. Other than the
    “Nusbaum Company, which proceeded with the HUD-financed, tax credit apartment complex on
    a portion of [Phase] I[,]” there have been no other offers for any other part of the [p]roperty, despite
    an increasingly improved market for real estate development since 2013.” Pl. Post-Tr. Reply Br.
    at 44–45.
    The Government’s suggestion that “WVI is seeking just compensation based on an inflated
    [‘]before’ value of the property, given its $4 million stated purchase price in RGHGAB’s
    bankruptcy[,]” is unfounded. Pl. Post-Tr. Reply Br. at 45. In fact, “the bankruptcy sale price . . .
    reflected several unusual factors, including[:] (1) the depressed value of the [Waverley View]
    Property during the Great Recession . . . , and (2) the $10,250,000 in debt carried by RGHGAB[.]”
    Pl. Post-Tr. Reply Br. at 45. As Mr. Harvey testified, because the “bankruptcy sale, [w]as ‘a forced
    sale between related parties that were atypically motivated by duress[,] . . . [it] does not provide a
    meaningful indication of fair market value[.]’” Pl. Post-Tr. Reply Br. at 45 (quoting PX 88 at 28).
    In addition, the Government’s objection “to the severance damage analysis conducted by Mr.
    Harvey, which reduced the value of the remainder of the [Waverley View] Property, the [Phase] I
    area, by 28%” is unfounded. Pl. Post-Tr. Reply Br. at 46 (citing Gov’t Post-Tr. Resp. Br. at 61).
    When the Army entered Phase II, it “effectively announc[ed] to the real estate market that [Phase]
    II is now a CERCLA remedial investigation site, [thereby] . . . adverse[ly] impact[ing] . . . the
    remainder of the larger 92-acre parcel.” Pl. Post-Tr. Reply Br. at 47. This was “borne out by Mr.
    Harvey’s analysis. . . . On the other hand, Mr. McPherson did not perform any severance damage
    analysis and conclusorily states that any stigma associated with the [Waverley View] Property
    predates the [Army’s] entry onto it.” Pl. Post-Tr. Reply Br. at 47–48. In sum, Mr. Harvey’s
    appraisal and valuation conclusions regarding severance damages “are unrebutted by Mr.
    McPherson. The same is true of Mr. Harvey’s overall conclusions on value.” Pl. Post-Tr. Reply
    Br. at 51.
    Moreover, Mr. McPherson’s appraisal is “fatally flawed[,]” because it is “based on [the]
    entirely unsupported assumption[] that the Army will readily move the CERCLA wells (and any
    remedial structures) upon request.” Pl. Post-Tr. Reply Br. at 51. Mr. McPherson did not
    “interview a single EPA official to evaluate th[is] assumption” and Mr. McPherson does not have
    any “experience conducting an appraisal at a CERCLA [NPL] site, subject to control by the EPA.”
    Pl. Post-Tr. Reply Br. at 52 (citing TR 1181–83 (McPherson)).
    Finally, although the Government argues that “the measure of just compensation should be
    uniform as between direct takings cases and inverse condemnation cases[,] . . . the purpose of
    awarding interest as part of just compensation in a takings case is to put the property owner in ‘as
    good a position pecuniarily as he would have occupied if the payment had coincided with the
    appropriation.’” Pl. Post-Tr. Reply Br. at 52–53 (quoting Kirby Forest Indus. v. United States,
    
    467 U.S. 1
    , 10 (1984)) (citing Gov’t Post-Tr. Resp. Br. at 69). “[A]n award of less than the
    Moody’s AAA Corporate Bond Index rate will not fulfill that purpose.” Pl. Post-Tr. Reply Br. at
    53 (citing Pl. Post-Tr. Br. at 50–52). In addition, “WVI’s position is entirely consistent with the
    cases on which the Government relies.” Pl. Post-Tr. Reply Br. at 53.
    72
    d.      The Government’s Sur-Reply.
    The Government adds that WVI’s “reticence” regarding its development plans “becomes
    clear in the context of WVI’s admission at trial that, in March 2013, it made a business decision
    to stop marketing [Phase] II based on Mr. Anderson’s speculation that the Army would buy the
    property if contamination was found.” Gov’t Post-Tr. Sur-Reply Br. at 21. And, even if WVI sold
    Phase II, “it planned to require the purchaser to obtain final site plan approval. Thus, if the site
    plan was going to change – and it did not have to – any attendant expense would be borne by the
    purchaser, not WVI.” Gov’t Post-Tr. Sur-Reply Br. at 21.
    Mr. Tesner “unequivocally [testified] that the Army not only would have accommodated
    WVI’s development plans in 2013-14, it would do so today – if WVI were interested in developing
    [Phase] II[, of the Waverley View Property]” and “WVI offers no evidence to the contrary.” Gov’t
    Post-Tr. Sur-Reply Br. at 22 (citing TR 1418 (Tesner)). Mr. Tesner “has been responsible for
    ‘literally thousands’ of active cleanup sites under a variety of different programs,” and “[t]he four
    examples he provided are illustrative of how the Army’s general policy is applied in practice.”
    Gov’t Post-Tr. Sur-Reply Br. at 22 (citing TR 1292 (Tesner)). These examples were not exhaustive
    and the Government was “not required to introduce further cumulative evidence of how the policy
    and practices have been applied to specific sites.” Gov’t Post-Tr. Sur-Reply Br. at 22.
    Failing to “produce a witness to testify that the policies Mr. Tesner has developed and
    worked with . . . [do] not exist, WVI attempts to rely upon an EPA Model Administrative Access
    Order as the ‘only’ federal policy that ‘addresses how real estate development and use is to be
    addressed in the context of a CERCLA remedial investigation[.]” Gov’t Post-Tr. Sur-Reply Br. at
    26 (quoting Pl. Post-Tr. Reply Br. at 26). In this case, however, “no administrative access order
    was even sought, much less entered, [and] . . . Mr. Tesner’s testimony that [the] EPA’s policy and
    practice of accommodating private real estate development is the same as the Army’s is
    unrebutted.” Gov’t Post-Tr. Sur-Reply Br. at 26.
    Mr. Harvey’s appraisal was “based on a proposition that a non-public right of access
    agreement and resulting installation of a dozen small monitoring wells stigmatized the [Waverley
    View] Property.” Gov’t Post-Tr. Sur-Reply Br. at 28. But, Mr. Harvey fails to consider “that it
    had been publicly known for years that the [p]roperty abutted a superfund site where various
    chemical warfare waste products had been disposed.” Gov’t Post-Tr. Sur-Reply Br. at 28. And,
    Mr. Harvey “pretends there was no environmental stigma associated with the [p]roperty prior to
    the date of alleged taking . . . based primarily on the . . . 2004 NFRD, which does not itself show
    a ‘clean’ property.” Gov’t Post-Tr. Sur-Reply Br. at 28. Moreover, in 2011,
    more than a year before WVI purchased the [Waverley View] Property, the Army
    informed [Messrs.] Anderson and Mr. Dorment that: (1) groundwater monitoring
    results from wells just across the boundary between Fort Detrick and Waverley
    View [Phase] II showed high levels of contamination; (2) contamination had likely
    migrated to WVI’s property; and (3) the Army felt strongly that it needed to conduct
    groundwater monitoring on WVI’s [p]roperty to determine the extent of any
    contamination.
    Gov’t Post-Tr. Sur-Reply Br. at 28–29.
    73
    Therefore, it was “unreasonable for Mr. Harvey to rely on the 2004 NFRD to assume that
    the property did not suffer any pre-existing environmental stigma in 2012 due to its location
    adjacent to Ft. Detrick.” Gov’t Post-Tr. Sur-Reply Br. at 29. In addition, although “WVI bears
    the burden of proving severance damages,” WVI “continues to fail to show that Mr. Harvey’s
    severance damages analysis is factually or legally supported.” Gov’t Post-Tr. Sur-Reply Br. at 30.
    Moreover, arguments similar to those underlying WVI’s claim for severance damages were
    rejected by the United States Court of Appeals for the Federal Circuit in Hendler v. United States,
    
    175 F.3d 1374
     (Fed. Cir. 1999) (“Hendler VI”). Gov’t Post-Tr. Sur-Reply Br. at 30 (citing Hendler
    VI, 
    175 F.3d at 1383
    ). That is the situation in this case, as WVI argued that the Waverley View
    Property was unmarketable or at least greatly depreciated because of the access order, as it would
    significantly interfere with development. Gov’t Post-Tr. Sur-Reply Br. at 30 (citing Hendler VI,
    
    175 F.3d at 1384
    ).
    e.      Plaintiff’s Sur-Reply.
    WVI adds that Mr. Harvey considered any and all environmental stigma from Fort Detrick
    in assessing the ‘before’ valuation of the [Waverley View] Property.” Pl. Post-Tr. Sur-Reply Br.
    at 21 (quoting Gov’t Post-Tr. Sur-Reply Br. at 28). Moreover, “Mr. Harvey’s reliance on the
    [2004] NFRD was entirely appropriate and well-founded[.]” Pl. Post-Tr. Sur-Reply Br. at 22.
    And, “[a]s of the date of his ‘before’ valuation, only the Army’s ‘suspicion’ weighed against the
    [2004] NFRD.” Pl. Post-Tr. Sur-Reply Br. at 22.
    In addition, “Mr. McPherson’s testimony is consistent with Mr. Harvey’s analysis, given
    that Mr. McPherson could not identify even a single property anywhere that had proceeded with
    development during the remedial investigation stage of a CERCLA investigation at an NPL site.”
    Pl. Post-Tr. Sur-Reply Br. at 23 (citing TR 1270–71 (McPherson)). And, “Mr. Harvey’s appraisal
    conclusion that [a] diminution in value of $9.2 million [was] caused by the [Army’s] permanent
    taking . . . is strongly supported by the practical reality that no other purchasers have come forth
    to purchase any part of the [p]roperty, except [a] minor portion of . . . [Phase I.]” Pl. Post-Tr. Sur-
    Reply Br. at 23.
    In sum, the parties can “debate forever whether WVI should have offered, or the
    Government should have asked for, more detailed development plans[,]” however, “[t]his case has
    never been merely about whether any particular well locations interfere, in the short run, with
    WVI’s current development plan.” Pl. Post-Tr. Sur-Reply Br. at 24–25. Instead, “[i]t is — and
    always has been — about the paralyzing uncertainty created by the [Army’s] ongoing, evolving,
    and indefinite occupation of the [Waverley View] Property.” Pl. Post-Tr. Sur-Reply Br. at 25.
    And, “[t]here is no evidence that a slight repositioning of the [Army’s monitoring] wells . . . spells
    the difference between a taking and a feasible new real estate development plan.” Pl. Post-Tr. Sur-
    Reply Br. at 25.
    Moreover, the Government’s contention that “WVI did not object to the proposed well
    locations[,] because WVI ‘simply took [Phase] II off the market[,]’ . . . is simply false.” Pl. Post-
    Tr. Sur-Reply Br. at 25 (quoting Gov’t Post-Tr. Sur-Reply Br. at 19, 21). Instead, “the record
    shows that all but one prospective purchaser of the [Waverley View] Property disappeared upon
    the [Army’s] entry onto the [p]roperty.” Pl. Post-Tr. Sur-Reply Br. at 27. And, “[a]lthough WVI
    74
    continued to market the [p]roperty, no other purchasers materialized.” Pl. Post-Tr. Sur-Reply Br.
    at 27.
    WVI insists that Mr. Soter “is unquestionably qualified to testify” about: “(1) the import
    of obtaining [p]reliminary [p]lan approval in the City of Frederick; (2) the impact of wells and
    remedial activities on site development plans; and (3) the time, cost, and uncertainty associated
    with obtaining re-approval for new or altered site development plans.” Pl. Post-Tr. Sur-Reply Br.
    at 27. As “[t]he Government’s appraisal expert, Mr. McPherson, testified . . . [p]reliminary [p]lan
    approval by the City of Frederick is a valuable entitlement.” Pl. Post-Tr. Sur-Reply Br. at 28. Mr.
    Soter and Mr. McPherson “also agreed that the Government’s current well network on the
    [p]roperty interferes with [WVI’s] Preliminary Plan.” Pl. Post-Tr. Sur-Reply Br. at 28. And, as
    Mr. McPherson “conceded[,] . . . applying a buffer of 50 feet around each well, to allow for testing
    and maintenance, will ‘result in the loss of four units [of 293 planned units] and possibl[y]
    redesigning the remaining ten units resulting in additional design costs.’” DX 142 at 92 (emphasis
    added). Moreover, “[n]o reasonable developer would spend millions of dollars redesigning and
    seeking approval for a new [p]reliminary [p]lan . . . while the Army and [the] EPA are considering
    installation of additional wells for the [R]emedial [I]nvestigation[.]” Pl. Post-Tr. Sur-Reply Br. at
    28.
    f.         The Court’s Resolution.
    i.        Governing Precedent.
    The hallmark of a physical taking is government occupation of real property. See, e.g.,
    Loretto, 
    458 U.S. at 427
     (“[W]here real estate is actually invaded . . . so as to effectually destroy
    or impair its usefulness, it is a taking, within the meaning of the Constitution.”) (internal quotations
    omitted). And, it is well established that “a physical taking is defined by the government's
    corporeal violation of private property.” Bassett, New Mexico LLC v. United States, 
    55 Fed. Cl. 63
    , 74 (Fed. Cl. 2002). “In cases of a partial physical taking as that here, [however,] just
    compensation under the [T]akings [C]lause of the Constitution includes ‘not only the market value
    of that part of the tract appropriated, but the damage to the remainder resulting from that taking[.]’”
    Hendler VI, 
    175 F.3d at 1383
     (quoting Grizzard, 
    219 U.S. at 183
    ); see also Bassett, New Mexico
    LLC, 55 Fed. Cl. at 74 (noting that the United States Court of Federal Claims has “recognized the
    possibility of compensable stigmatic injuries that extend beyond the tangible aspects of a physical
    taking”). Plaintiffs, however, “bear the burden of proving [such] severance damages.” Hendler
    VI, 
    175 F.3d at 1383
    . And, “[t]he guiding principle of just compensation, [remains] . . . that the
    owner of the . . . property ‘must be made whole but is not entitled to more.’” United States v.
    564.54 Acres of Land, 
    441 U.S. 506
    , 516 (1979) (emphasis omitted) (quoting Olson v. United
    States, 
    292 U.S. 246
    , 255 (1934) (“[A property owner] is entitled to be put in as good a position
    pecuniarily as if his property had not been taken. He must be made whole but is not entitled to
    more. It is the property and not the cost of it that is safeguarded by state and Federal
    Constitutions.”).
    WVI contends that the Army’s permanent physical taking had an adverse economic impact
    on the entire Waverley View Property. WVI claims that the Army’s investigative activities
    produced two linked effects flowing from the Army’s physical occupation. The first effect was
    preventing WVI from developing Phase II of the Waverley View Property. The second effect was
    75
    the diminution of the Waverley View Property’s overall market value due to the stigma associated
    with the Army’s ongoing physical presence, uncertainty of future investigative or remedial action,
    and the threat of CERCLA liability.
    ii.     Plaintiff Failed To Establish That The Taking Of Certain
    Portions Of The Waverley View Property Prohibited
    The Development Or Sale Thereof.
    WVI maintains that the presence of the Army-installed monitoring wells on the Waverley
    View Property and the ongoing “uncertainty” surrounding the potential for future investigative or
    remedial action by the Army or the EPA effectively prohibits the development and sale of the
    entire property. The Government counters that the presence of the Army-installed monitoring
    wells does not inhibit development of the property and that any future investigative or remedial
    action is “speculative” as neither the EPA nor the Army have reentered the property since
    expiration of the WVI ROE, and have no immediate or certain plans to do so.
    The Government is correct about the speculative nature of WVI’s contention that the EPA
    or the Army would restrict or oppose development of the Waverley View Property. Instead, the
    decision not to pursue further development of Phase II of the Waverley View Property represents
    an informed and calculated business decision (TR 454–55 (Dorment); TR 579 (Soter)), or in Mr.
    Dorment’s own words, “opportunity in crisis” (JX 22 at WVI00008413).
    At trial, Mr. Dorment testified that, despite his “impression” to the contrary (TR 729
    (Dorment)), neither the Army nor the EPA “told [WVI] that it was prohibited from developing
    [the] property because of groundwater monitoring” (TR 728–29 (Dorment); see also TR 477
    (Anderson) (agreeing that “no one from the Government has told [WVI], in words or substance,
    ‘[WVI] cannot go forward with development or getting approvals to develop Phase [II] until the
    groundwater monitoring has been completed’”); TR 576 (Soter)). In fact, WVI did not ask the
    Army or the EPA if it could proceed with development of Phase II or even “express[] concern that
    installation of [monitoring] wells on [Phase II] would prevent [it] from developing [the property].”
    TR 940, 947–48 (Gortva); see also DX 126; TR 445 (Anderson). Nor did WVI “investigate to
    determine whether other developers had been allowed to complete developments while remedial
    investigations were occurring.” TR 472 (Anderson). In addition, the City of Frederick did not
    inform WVI that it “was prohibited from developing its property because of groundwater
    monitoring.” TR 728 (Dorment). And, WVI did not ask the City of Frederick what “the effect of
    groundwater monitoring wells might be on approvals for Phase [II].” TR 471 (Anderson). If WVI
    had made such an inquiry, however, it would have learned that the presence of groundwater
    monitoring wells on the property would not have precluded approval of the Final Site Plan for
    Phase II. JX 30 at 19–20.54
    In any event, WVI took none of the steps necessary to begin developing Phase II. For
    example, in late 2008, WVI’s predecessor-in-interest, RGHGAB, withdrew its Final Site Plan for
    54
    The court’s review of CERCLA and the Maryland Code, did not reveal any legal duty
    on the part of the Army, the EPA, or the MDE to inform or advise WVI of the effects of
    investigation or remedial activities on developing the Waverley View Property.
    76
    Phase II. JX 20; PX 120; PX 156 at 6. Although the Planning Commission provided “review
    comments” to RGHGAB, WVI never addressed these comments or resubmitted the plan for
    approval (JX 20; PX 120; PX 156 at 6; TR 470 (Anderson)), despite approval being a necessary
    step toward development (JX 30 at 12–13; PX 156 at 3). Instead, subsequent promotional
    materials concerning the Waverley View Property, provided that “[f]inal plan approval [of Phase
    II] will be necessary and will need to be completed by the purchaser[.]” PX 29 at WVI00007847.
    Nor did WVI complete each of the “required” improvements upon which approval of RGHGAB’s
    PND Master Plan was conditioned. See SVTR 36–37. In fact, other than executing the January
    2013 Deferral Agreement, that “reduc[ed WVI’s] up-front financial outlay” requirement by “$2
    million” (TR 175–76, 471 (Anderson)), the record does not evidence any other material efforts
    taken by WVI to develop Phase II.
    Moreover, WVI did not present the Army or the EPA with a copy of its plans to develop
    Phase II before signing the WVI ROE (TR 1040 (Gortva)),55 nor did WVI inform either agency of
    any plans to develop Phase II in the “near term” (TR 956–57 (Gortva)). WVI also did not object
    to the proposed location of “drilling areas,” as shown in the map included with the WVI ROE (TR
    956 (Gortva); TR 1310 (Tesner); see also JX 5 at US000006), no did it indicate that any “well
    locations conflicted with [its] plans for [Phase II]” (TR 956 (Gortva); see also TR 948 (Gortva)).
    In addition, “[WVI] never asked the [Army or the EPA] about where it would locate [the
    monitoring] wells[,]” and “never asked the [Army or the EPA] to move a [monitoring] well
    location” to accommodate development plans for Phase II. TR 727–28 (Dorment). And, despite
    the Army’s attempt to obtain feedback from WVI about the proposed offset locations of
    monitoring wells (TR 950–51, 1142–44 (Gortva); see also DX 127), the Army never received a
    response. (TR 951 (Gortva)).56
    55
    WVI’s argument that it provided the Army with detailed development plans for Phase II
    in the 2010 CGS Site Investigation Report included with Mr. Anderson’s May 9, 2011 letter, is
    not evidenced in the trial record. Pl. Post-Tr. Reply Br. at 20–26. Prior to “filing this lawsuit,”
    WVI did not inform the Army that any plans existed regarding WVI’s development of Phase II.
    TR 727 (Dorment); see also TR 962–63, 1040 (Gortva). Instead, WVI contends that the Army
    should have presumed the significance of the plans included in the 2010 CGS Site Investigation
    Report, although they predated WVI’s ownership of the Waverley View Property by more than
    two years, and were included in a report prepared for RGHGAB, not WVI. PX 150 at PL002157–
    58 (Figures 1 and 2 are dated “10/27/10” and “10/24/10,” respectively). Moreover, even assuming
    that the Army was aware of these plans, as Mr. Gortva testified,
    there [are] no GPS coordinates. There is no way to fix [the plans relative to] . . .
    the ground. There [are] no utilities on [the plans]. There is nothing to indicate
    [these are] exact plan[s], [or] more than . . . conceptual drawings of the proposed
    locations of the homes. Nothing on [the plans] would indicate . . . that this is a true
    engineering design plan of where exactly the houses will be built.”
    TR 993 (Gortva); see also TR 147 (Anderson) (testifying that the plans were “small scale”).
    56
    WVI argues that the presence of the Army-installed monitoring wells prohibited
    development of Phase II (Pl. Post-Tr. Sur-Reply Br. at 27–29), despite the continuing presence of
    77
    For these reasons, WVI’s contention that either the EPA or the Army would restrict or
    oppose development of the Waverley View Property is not supported in the record. Instead, the
    trial record reflects examples of several projects in which the Army located and/or relocated
    monitoring wells to accommodate development (TR 1320–1334 (Tesner); DX 119 (describing the
    Army’s interactions with a developer in Ramsey County, Minnesota); DX 120 (showing
    monitoring wells installed at Cameron Station in Alexandria, Virginia)). The court does not view
    that testimony, however, as evidencing a policy mandating the Army or the EPA to accommodate
    development. In any event, the extent to which any of the Army’s or the EPA’s activities have, or
    will, interfere with development of the Waverley View Property is unknown at this time, as WVI
    has yet to take the steps necessary to do so. Although WVI may view this “uncertainty” as
    prohibitive, it is a risk WVI accepted when it purchased the Waverley View Property.
    For these reasons, the court has determined that Plaintiff failed to establish at trial that the
    Army’s taking of certain portions of the Waverley View Property prohibited or interfered with
    development of the Waverley View Property.
    iii.    Plaintiff Failed To Establish That Any Stigma Attached
    To The Waverley View Property Was Caused By The
    Government’s Activities Thereon.
    The court has “recognized the possibility of compensable stigmatic injuries that extend
    beyond the tangible aspects of a physical taking.” Bassett, New Mexico LLC, 55 Fed. Cl. at 74;
    see also Hendler v. U.S., 
    38 Fed. Cl. 611
    , 625 (Fed. Cl. 1997) (“Moreover, if fear of a hazard
    would affect the price a knowledgeable and prudent buyer would pay to a similarly well-informed
    seller, diminution in value caused by that fear may be recoverable as part of just compensation.”
    (internal citations and quotation marks omitted)). And, “‘stigma’ amounts to considerably more
    than a mental attitude on the part of buyers. It is based upon a very real possibility that any
    commercial activity on the property might lead to regulatory prohibition or real physical danger.”
    Bassett, New Mexico LLC, 55 Fed. Cl. at 74.
    As a threshold matter, the court does not consider the aforementioned non-precedential
    cases, recognizing stigma as a cognizable basis for a Takings Clause claim, persuasive, because
    such a theoretical basis for recovery is speculative and implicates Due Process concerns. In any
    its own CGS-installed monitoring wells on the property (see SVTR 22; see also PX 76). CGS-
    installed monitoring wells GW-1 and GW-3, however, are located within the planned development
    of Phase II, and appear to interfere with the planned residential development of the property.
    Compare PX 76, with DX 142 at 91. In light of the Army’s history of locating and/or relocating
    monitoring wells to accommodate development (TR 1320–1334 (Tesner); DX 119 (describing the
    Army’s interactions with a developer in Ramsey County, Minnesota); DX 120 (showing
    monitoring wells installed at Cameron Station in Alexandria, Virginia)), WVI fails to explain why
    the Army-installed monitoring wells present a significant challenge to development, but the CGS-
    installed monitoring wells do not. Moreover, WVI also fails to explain why the presence of the
    Army-installed monitoring wells present a barrier to planning approval by the City of Frederick,
    but the CGS-installed monitoring wells do not. In fact, in 2004 and 2006, despite the presence of
    numerous CGS-installed monitoring wells, the Planning Commission approved both the PND
    Master Plan and the Final Site Plan for Phase I. JX 20; PX 120; PX 156 at 5; TR 112 (Anderson).
    78
    event, whatever stigma may be attached to the Waverley View Property, predated WVI’s
    ownership of the property and the Government’s taking of certain portions of the Waverley View
    Property.
    On November 15, 2012, when WVI purchased the Waverley View Property, the following
    information was publicly known: (1) Phase II of the Waverley View Property lies directly adjacent
    to the Fort Detrick Area B-11 disposal pits (PX 70); (2) in October 1992, the MDE discovered
    contamination in “residential wells in the vicinity of Fort Detrick Area B” (PX 24 at PL004078);
    (3) on November 13, 1997, the Army publicly reported that contamination likely migrated from
    Area B-11 onto the Waverley View Property (DX 128 at 19–20; TR 920 (Gortva)); (4) on April 8,
    2009, Fort Detrick Area B Groundwater was listed on the NPL as a CERCLA Superfund site, and
    the Area B-11 Chemical Waste Disposal Pits were identified as a “source area” (PX 65 at 2); (5)
    in early 2010, the Kristen Renee Foundation launched a public campaign “to research and
    investigate the findings associated with Fort Detrick ‘Area B’ groundwater” (DX 142 at 14); (6)
    on October 8, 2011, The Baltimore Sun published an article about contamination at Fort Detrick
    and concerns for the surrounding community (DX 41 at WVI00006709–12); (7) Mr. White and
    “more than 100 fellow plaintiffs” filed a “mass tort lawsuit” against the Army (DX 41 at
    WVI00006709); (8) beginning in 2011, the Army publicly distributed a “Project Overview”
    reaffirming its suspicion that contamination had migrated onto the Waverley View Property (TR
    930–31 (Gortva); see also JX 15 at US002781; TR 762–63 (Harvey)); and (9) in 2011 and 2012,
    the Army began requesting permission to investigate properties around Fort Detrick (TR 924
    (Gortva)).
    Moreover, WVI had the following additional information when it purchased the Waverley
    View Property in 2012: (1) on October 4, 2001, WLGA reported that “1,1,1 [t]richloroethane,
    tetrachloroethene, and trichloroethene were detected [on the Waverley View Property] in
    September/October 2001” (PX 151 at 1); (2) on March 10, 2011, and continuing until WVI
    purchased the property, the Army sought access to the Waverley View Property as a “critical”
    component of its “site investigation activities for the Fort Detrick Area B Groundwater Remedial
    Investigation” (JX 3 at WVI00009453; see also, e.g., PX 7; DX 16; DX 17; DX 22; TR 150–51
    (Anderson)); (3) on November 16, 2011, the Army Corps informed Messrs. Dorment and
    Anderson of “significantly elevated” levels of contaminants found less than 20 feet from the
    Waverley View Property (TR 926–27 (Gortva)); (4) on February 7, 2012, the Army Corps
    informed WVI’s predecessor-in-interest, RGHGAB, that the Waverley View Property was
    “critical to achieving [its] project goals and no viable alternative locations exist” (JX 3 at
    WVI00009453 (emphasis added)); (5) on September 6, 2012, the MDE informed RGHGAB that
    it was not willing to issue a “‘comfort letter’ . . . stat[ing] that there would be no known health risk
    if the property were to be developed under the constraints of the [2004] NFRD (essentially no
    groundwater use)” because of the “unknown . . . extent of groundwater contamination associated
    with Area B” (DX 33 at US000157); and (6) on November 8, 2012, the Army Corps again
    informed Mr. Anderson that the Waverley View Property was “critical for the completion of [the
    Army’s] efforts” (PX 7 at WVI0008362).
    Therefore, WVI’s reliance upon the 2004 NFRD was misplaced. Pl. Post-Tr. Br. at 5
    (explaining that WVI “understood the [2004] NFRD to be the ‘gold standard’ of assurances that
    environmental constraints would not impede development of the [Waverley View P]roperty”
    (quoting TR 143 (Anderson))). The 2004 NFRD was not a guarantee that the Waverley View
    79
    Property was free of contaminants, and RGHGAB was well aware of this when the MDE refused
    to issue a “comfort letter” because of the “unknown . . . extent of groundwater contamination
    associated with Area B.” DX 33 at US000157. And, to the extent the 2004 NFRD provided any
    assurances, it was only as reliable as the information submitted by RGHGAB in the 2004 Site
    Characterization Report. But, as WVI’s expert, Dr. Matthew Tonkin,57 testified, despite CGS’s
    conclusion that “[n]o contaminants of potential concern . . . were identified” (PX 151 at 15), “it
    [was] possible that there were contaminants [on the Waverley View Property] that just hadn't been
    located” (TR 505 (Tonkin)). Therefore, WVI’s reliance on the 2004 NFRD when it purchased the
    property, was unreasonable, particularly in light of the Army’s well-known suspicion that
    contamination had migrated onto the Waverley View Property. JX 15 at US002781; DX 128 at
    19–20; TR 920, 930–31 (Gortva).
    Likewise, the threat of future investigative or remedial action was known to the public
    when WVI purchased the property, and so was the threat of CERCLA liability. The EPA’s
    CERCLA authority predated WVI’s ownership of the Waverley View Property by more than three
    and a half years. And, at that time, it was a matter of public knowledge that the Army intended to
    investigate properties around Fort Detrick (TR 924 (Gortva)), especially the Waverley View
    Property (JX 15 at US002781; DX 128 at 19–20; TR 920, 930–31 (Gortva)). In addition, Mr.
    Dorment was aware of the Army’s interest in gaining access to the Waverley View Property,
    because it was a “critical” component of the Army’s Remedial Investigation. JX 3 at
    WVI00009453.
    As a practical matter, the only material difference between the Waverley View Property on
    November 15, 2012 and today, is the physical presence of the Army-installed monitoring wells on
    Phase II of the property. Although, WVI voluntarily consented to the installation of these
    monitoring wells, WVI insists that they stigmatize the entire property and “represent a problem
    . . . in the competitive marketplace.” TR 708 (Dorment). In 2004, however, RGHGAB engaged
    CGS to “determine the on-site extent . . . of contamination as a direct result of potential off-site
    migration from the adjacent Fort Detrick Military Reservation[.]” PX 151 at 1. Thereafter, CGS
    installed seven groundwater monitoring wells on the property. PX 151 at 1. These groundwater
    monitoring wells were installed “to depths of about 115 feet below ground surface” (PX 155 at 5),
    and “were constructed of 6-inch diameter steel casing,” except for GW-7 which “was constructed
    of 4-inch diameter . . . PVC [pipe]” (PX 151 at 2–3; see also PX 88 at A-14 (Image 7). And, as of
    the court’s December 1, 2017 site visit to the Waverley View Property, at least some of the CGS-
    57
    At trial, WVI proffered Mr. Tonkin as an expert “hydrogeologist with expertise in the
    area of CERCLA investigation, remedial investigations, feasibility studies, and remedial actions.”
    TR 501. The Government did not object. TR 501. Mr. Tonkin has been the President of SSPA
    for the past four years and a Principal Hydrogeologist with SSPA for the past 20. TR 498. His
    education includes a Doctor of Philosophy in Civil Engineering from the University of
    Queensland, Australia, a Master of Science in Hydrogeology and a BS in Applied Geology from
    Birmingham University. PX 66. Mr. Tonkin has worked on “about 25 or 26” projects with the
    EPA, and the “majority of those were . . . CERCLA sites . . . involving remedial investigations and
    feasibility studies[.]” TR 499. Therefore, the court considers Mr. Tonkin an expert
    “hydrogeologist with expertise in the area of CERCLA investigation, remedial investigations,
    feasibility studies, and remedial actions.” TR 1065–66; see also FRE 702.
    80
    installed monitoring wells remain on Phase II, nearly fourteen years after CGS completed its
    investigation. SVTR 22; see also PX 76. The CGS-installed monitoring wells are clearly visible,
    and project several feet above ground. PX 88 at A-14 (Image 7). Therefore, whatever stigma may
    be attached to the Waverley View Property because of the presence of monitoring wells was well
    established by the presence of the CGS-installed monitoring wells and predated the presence of
    the Army-installed monitoring wells by nearly a decade.
    For these reasons, the court has determined that any stigma attached to the Waverley View
    Property predated WVI’s ownership and was not caused by the Army’s or the EPA’s activities on
    the property.
    iv.     Plaintiff Is Entitled To $1.06 Per Square Foot Of The
    Waverley View Property Physically Occupied By The
    Army-Installed Monitoring Wells And Gravel Access
    Road.
    “The guiding principle of just compensation, . . . is that the owner of the . . . property ‘must
    be made whole but is not entitled to more.’” 564.54 Acres of Land, 
    441 U.S. at 516
     (quoting
    Olson, 
    292 U.S. at 255
     (“[A property owner] is entitled to be put in as good a position pecuniarily
    as if his property had not been taken. He must be made whole but is not entitled to more. It is the
    property and not the cost of it that is safeguarded by state and Federal Constitutions.”). Because
    of “serious practical difficulties in assessing the worth an individual places on particular property
    at a given time,” however, the United States Supreme Court has recognized the need to determine
    “just compensation” through “a relatively objective working rule.” Id. at 511. Thus, just
    compensation for a permanent taking is “generally” determined by the fair market value of the
    property taken. See Bass Enters. Prod. Co., 
    133 F.3d at 895
    ; see also Bauman v. Ross, 
    167 U.S. 548
    , 574 (1897) (defining “just compensation” as “the value of [property that the owner] has been
    deprived of, and no more”). “Under this standard, the owner is entitled to receive what a willing
    buyer would pay in cash to a willing seller at the time of the taking.” 564.54 Acres of Land, 
    441 U.S. at 511
    . But, “the quantum of damages” must “be shown to a reasonable approximation,” i.e.,
    “estimated with a fair degree of accuracy.” Ark. Game & Fish Comm'n v. United States, 
    736 F.3d 1364
    , 1379 (Fed. Cir. 2013) (on remand) (internal quotations and citations omitted).
    Although the parties argue at length about the appropriate amount of just compensation,
    they are based on the fair market value of the Waverley View Property before and after installation
    of the Army’s monitoring wells. Just compensation, however, is measured as of the “time of the
    taking.” 564.54 Acres of Land, 
    441 U.S. at 511
    . And, the taking in this case, did not occur until
    expiration of the WVI ROE, i.e., November 13, 2014. But, WVI’s expert, Mr. Harvey, determined
    “the fair market value of the Waverley View Property before and after November 21, 2013” (PX
    157 at 10); the Government’s expert, Mr. McPherson, determined the same as of May 10, 2013
    (DX 142 at 2). As such, each parties’ valuation was based on the incorrect period of time.
    In addition, Mr. Harvey, testified that the fair market value of the Waverley View Property
    before and after installation of the Army’s monitoring wells was $13,040,000 and $3,840,000,
    respectively. PX 157 at 17. These valuations, however, are not supported by the record. For
    example, Mr. Harvey based his “before” valuation on numerous incorrect assumptions, including:
    (1) that the Waverley View Property was not contaminated by TCE or PCE (PX 88 at 12; see also
    81
    PX 76 (Figures 11A and 11B); TR 355–56 (Thomson); TR 765 (Harvey); TR 954–55 (Gortva));
    and (2) that the value of the Waverley View Property was not affected by the well-known history
    of contamination of Area B (PX 157 at 13–16). These assumptions are inconsistent with the
    record, particularly with the Army’s discovery of TCE and PCE on Phase II of the Waverley View
    Property before expiration of the WVI ROE. PX 76 (Figures 11A and 11B); TR 355–56
    (Thomson); TR 954–55 (Gortva)). Mr. Harvey also mistakenly assumed that WVI “entered into
    the [WVI] ROE under coercion due to the Army’s and [the] EPA’s threat of CERCLA liability[.]”
    PX 88 at 29. To the contrary, as determined by the court, WVI voluntarily consented to the terms
    of that agreement. As to Mr. Harvey’s “after” valuation, he incorrectly assumed that development
    of Phase II was “not legally permissible [or] physically possible for the foreseeable future[.]” PX
    88 at 11; see also TR 774 (Harvey). This is inconsistent with the court’s determination that neither
    the Army nor the EPA prohibited or interfered with development of the Waverley View Property.
    Mr. McPherson, on the other hand, testified that the fair market value of the Waverley
    View Property before and after installation of the Army’s monitoring wells was $11,000,000 and
    $10,750,000, respectively. PX 157 at 17. Mr. McPherson’s “after” valuation, however, was based
    on the presence of “hypothetical perpetual easements [that] would enable the [Army] to access and
    sample [the Army-installed] monitoring wells[.]” DX 142 at 90; see also DX 142 at 90–94. But,
    the presence of such easements is inconsistent with the fact that neither the Army nor the EPA has
    any immediate need or plans to enter the Waverley View Property again. DX 111 at 3–5; TR
    1080–83, 1085 (White); TR 1385–99 (Tesner); ECF No. 70, 95. As to Mr. McPherson’s “before”
    valuation, although he considered preexisting stigma (DX 142 at 12–150), his valuation
    nevertheless represents the “unimpaired value”58 of the Waverley View Property (DX 142 at 7
    (“The values estimated in my report are based on the assumption that the property is not negatively
    affected by the existence of hazardous substances or detrimental environmental conditions. The
    appraiser[] is not an expert in the identification of hazardous substances or detrimental
    environmental conditions. The property has had significant environment assessments and reports.
    The unimpaired value is being estimated.”)). Again, however, this is inconsistent with the Army’s
    discovery of TCE and PCE on Phase II of the Waverley View Property before expiration of the
    WVI ROE. PX 76 (Figures 11A and 11B); TR 355–56 (Thomson); TR 954–55 (Gortva)).
    Despite the errors in each parties’ valuation, the court has determined that Mr. McPherson’s
    “before” valuation of $11,000,000 provides the best basis from which the court can extrapolate a
    proper valuation of the property as of November 13, 2014.59 See Otay Mesa Prop., L.P. v. United
    States, 
    779 F.3d 1315
    , 1324, 1326 (Fed. Cir. 2015) (holding that “nothing [is] inappropriate with
    . . . looking at the evidence as a whole and using [the court’s] own methodology to calculate a
    damages award[,]” because the “court is not necessarily stuck with the ‘stark choice’ of accepting
    or rejecting a party's valuation . . . [as it] ‘is responsible for deciding what evidence to credit or
    reject and what result to reach’”) (quoting Precision Pine & Timber, Inc. v. United States, 596
    58
    Mr. McPherson defines “unimpaired value” as “[t]he market value of a contaminated
    property developed under the hypothetical condition that the property is not contaminated.” DX
    142 at 18.
    59
    Unlike Mr. Harvey’s “before” valuation, Mr. McPherson’s “before” valuation accounts
    for preexisting stigma attached to the Waverley View Property.
    
    82 F.3d 817
    , 832 (Fed. Cir. 2010)); see also Kimball Laundry Co. v. United States, 
    338 U.S. 1
    , 20
    (1949) (holding that, in determining compensation due, a court exercises its reasonable judgment,
    “with the aid of all relevant data to find an amount representing value to any normally situated
    owner or purchaser of the interests taken”); Seravalli v. United States, 
    845 F.2d 1571
    , 1575 (Fed.
    Cir. 1988) (“We are unwilling to restrict the trial courts to any single basis for determining fair
    market value. Those courts necessarily must have considerable discretion to select the method of
    valuation that is most appropriate in the light of the facts of the particular case. It may be a single
    method or some combination of different methods.”).
    In this case, the court must first account for the fact that Mr. McPherson’s valuation was
    determined as of May 10, 2013, approximately a year and a half before the taking occurred on
    November 13, 2014. DX 142 at 2. As Mr. McPherson testified, properties in Frederick, Maryland
    appreciated in value by 3 percent between May 10, 2013 and November 13, 2014. TR 1209–10
    (McPherson); see also DX 142 at 20, 88. Appreciating Mr. McPherson’s “before” valuation by 3
    percent during this period, yields an unimpaired value of approximately $11,500,000 for the
    Waverley View Property as of November 13, 2014.
    Next, the court must account for the presence of TCE and PCE on the Waverley View
    Property. Mr. Harvey testified that the presence of TCE and PCE negatively impacts a property’s
    fair market value by an average of 72%. PX 88 at 75. Applying this reduction to the court’s
    valuation would yield a value of $3,220,000 as an estimate of the Waverley View Property’s
    impaired value as of November 13, 2014.
    The court must next apportion value between Phase I and Phase II of the property. Based
    on Mr. McPherson’s “before” valuation of $11,000,000, he determined that the “contributory
    values” of Phase I and Phase II were $7,400,000 and $3,600,000, respectively. DX 142 at 87–89.
    Apportioning the court’s valuation of $3,220,000 using this same ratio, yields an impaired value
    of approximately $1,050,000 for Phase II of the Waverley View Property, as of November 13,
    2014.
    Phase II consists of approximately 23 acres (DX 142 at 40, 42, 92 (describing “Expansion
    Parcel A (Phase II)” as 22.81639 acres, or 993,882 square feet, in size); see also PX 88 at 25).
    Therefore, the court has determined that Phase II of the Waverley View Property was worth $1.06
    per square foot on November 13, 2014 ($1,050,000/993,882 square feet, yields $1.0564 per square
    foot). Accordingly, WVI is entitled to $1.06 per square foot for the property physically occupied
    by the Army-installed monitoring wells and gravel access road, including a reasonable square
    footage to accommodate development around the monitoring wells. Neither party, however,
    provided the court with an estimate of the square footage of property physically occupied by the
    Army-installed monitoring wells and gravel access road. Therefore, the court is unable to
    determine damages at this time.
    IV.     CONCLUSION.
    For these reasons, the court has determined that the Army’s activities after expiration of
    the WVI ROE effected a permanent physical taking of those portions of the Waverley View
    Property occupied by the Army-installed monitoring wells and gravel access road. Accordingly,
    WVI is entitled to $1.06 per square foot of property physically occupied by the Army-installed
    83
    monitoring wells and gravel access road. Neither party, however, has provided the court with an
    estimate of the square footage of property physically occupied by the Army-installed monitoring
    wells and gravel access road, including a reasonable square footage to accommodate development
    around the monitoring wells. Accordingly, the parties are directed to provide the court with this
    information on or before February 23, 2018.
    All other pending motions are denied as moot.
    IT IS SO ORDERED.
    s/ Susan G. Braden
    SUSAN G. BRADEN
    Chief Judge
    84
    

Document Info

Docket Number: 15-371

Judges: Susan G. Braden

Filed Date: 1/5/2018

Precedential Status: Precedential

Modified Date: 1/5/2018

Authorities (39)

donald-k-anderson-angel-cortina-jr-and-patricia-b-wallace-and-david , 344 F.3d 1343 ( 2003 )

Armstrong v. United States , 80 S. Ct. 1563 ( 1960 )

National Board of Young Men's Christian Assns. v. United ... , 89 S. Ct. 1511 ( 1969 )

United States v. 564.54 Acres of Monroe and Pike County Land , 99 S. Ct. 1854 ( 1979 )

Phillips v. Washington Legal Foundation , 118 S. Ct. 1925 ( 1998 )

The Stearns Company, Ltd. v. United States , 396 F.3d 1354 ( 2005 )

North Star Steel Co. v. United States , 477 F.3d 1324 ( 2007 )

Arkansas Game & Fish Commission v. United States , 133 S. Ct. 511 ( 2012 )

Yuba Natural Resources, Inc. And Placer Service Corporation ... , 821 F.2d 638 ( 1987 )

Yee v. City of Escondido , 112 S. Ct. 1522 ( 1992 )

the-national-board-of-the-young-mens-christian-associations-the , 396 F.2d 467 ( 1968 )

Henry Hendler, Paul Garrett and Tillie Goldring as Trustees ... , 175 F.3d 1374 ( 1999 )

United States v. Miller , 63 S. Ct. 276 ( 1943 )

Nvt Technologies, Inc. v. United States , 370 F.3d 1153 ( 2004 )

bass-enterprises-production-company-perry-r-bass-inc-lee-m-bass-inc , 133 F.3d 893 ( 1998 )

Albrecht v. United States , 329 U.S. 599 ( 1947 )

Lujan v. Defenders of Wildlife , 112 S. Ct. 2130 ( 1992 )

Bauman v. Ross , 17 S. Ct. 966 ( 1897 )

Tahoe-Sierra Preservation Council, Inc. v. Tahoe Regional ... , 122 S. Ct. 1465 ( 2002 )

Schooner Harbor Ventures, Inc. v. United States , 569 F.3d 1359 ( 2009 )

View All Authorities »