Rda Construction Corp. v. United States ( 2017 )


Menu:
  •  In the United States Court of Federal Claims
    No. 11-555 C
    Filed: July 27, 2017
    ****************************************           Accord and Satisfaction;
    *           Breach of Contract;
    *           Cardinal Change;
    *           Contract Disputes Act (“CDA”),
    *               
    41 U.S.C. §§ 7101
    –7109;
    *           False Claims Act (“FCA”),
    RDA CONSTRUCTION CORP.,                *               
    31 U.S.C. §§ 3729
    –3733;
    *           Federal Acquisition Regulations (“FAR”)
    *               52.233-1 (Disputes), 52.236-2
    *               (Differing Cite Conditions), 52.236-3
    Plaintiff,                       *               (Site Investigation and Conditions
    *               Affecting Work), 52.236-13(Accident
    v.                                     *               Prevention), 252.236-7001(Contract
    *               Drawings and Specifications), 52.249-
    THE UNITED STATES,                     *               10 (Default on Fixed-Price
    *               Construction Contract);
    *           Rule of the United States Court of
    *               Federal Claims (“RCFC”) 12(b)(1);
    Defendant.                       *           Special Plea in Fraud, 
    28 U.S.C. § 2514
    ;
    *           Tucker Act Jurisdiction over Contract
    *               Disputes, 
    28 U.S.C. § 1491
    (a)(2);
    *           United States Court of Federal Claims’
    *               Jurisdiction to Adjudicate Government
    *               Set-Offs, 
    28 U.S.C. §§ 1503
    , 2508.
    *
    ****************************************
    Cornelius J. O’Brien, Eckert Seamans Cherin & Mellott, LLC, Pittsburgh, Pennsylvania, Counsel
    for Plaintiff.
    Daniel B. Volk, United States Department of Justice, Washington, D.C., Counsel for the
    Government.
    POST TRIAL MEMORANDUM OPINION AND FINAL ORDER
    This post trial liability decision adjudicates a protracted dispute between RDA
    Construction Corp. (“RDA”) and the United States Department of the Navy, Naval Facilities
    Engineering Command (“the NAVFAC”), arising from an October 13, 2009 Contract, requiring
    RDA to demolish, remove, and construct a wharf at the Naval Station in Newport, Rhode Island
    (“Newport Naval Station”).
    To facilitate review of this Post Trial Liability Memorandum Opinion And Order, the court
    has provided the following outline:
    I.    RELEVANT FACTUAL BACKGROUND.
    A.    The Deteriorating And Dangerous Conditions At The Newport Naval Station Wharf.
    B.    On May 18, 2009, The Naval Facilities Command Issued Solicitation No. N40085-
    09-B-7002.
    C.    On June 4, 2009 and June 11, 2009, The Naval Facilities Command Conducted Two
    Site Visits Of The Newport Naval Station Wharf.
    D.    On June 30, 2009, RDA Construction Corp. Submitted A Bid.
    E.    On October 13, 2009, RDA Construction Corp. Signed Contract No. N40085-09-B-
    7002.
    F.    On November 18, 2009, The Appledore Report Was Disclosed To RDA Construction
    Corp.
    G.    On April 21, 2010, RDA Construction Corp. Filed A Certified Claim.
    H.    On May 17, 2010, The Naval Facilities Command Approved RDA Construction
    Corp.’s Baseline Schedule.
    I.    On August 31, 2010, RDA Construction Corp.’s April 21, 2010 Certified Claim Was
    Denied.
    J.    On September 20, 2010, RDA Construction Corp. Informed The Naval Facilities
    Command That Underground Obstructions Were Encountered, So Work Stopped.
    K.    On March 10, 2011, The Naval Facilities Command Instructed RDA To Submit A
    Cost Proposal To Remove The Obstructions And Continue Work.
    L.    In Late March 2011, RDA Construction Corp.’s Quality Control Manager And Site
    Safety Health Officer Quit.
    M.  On June 7, 2011 And August 19, 2011, The Naval Facilities Command Issued
    Contract Modifications 4 and 5 To The October 13, 2009 Contract.
    N.    On August 31, 2011, RDA Construction Corp. Filed A Complaint In The United
    States Court Of Federal Claims.
    O.    On September 14, 2011, RDA Construction Corp. Experienced A Third Accident At
    The Project Site.
    P.    From March 20, 2012 To November 8, 2012, The Naval Facilities Command Issued
    Contract Modifications 6–12.
    Q.    On February 21, 2013, The Naval Facility Command Terminated The October 13,
    2009 Contract.
    2
    R.    On July 3, 2013, RDA Construction Corp. Filed A Second Certified Claim.
    S.    On April 15, 2015, The Naval Facility Command’s Contracting Officer Determined
    That RDA Construction Corp. Was Liable For Liquidated Damages.
    II.    PROCEDURAL HISTORY.
    III.  DISCUSSION.
    A.    Jurisdiction.
    1.    Whether The Claims Alleged In The May 7, 2015 Second Amended Complaint
    Arise Under The Contract Disputes Act.
    2.    Whether The Claims Alleged In The May 7, 2015 Second Amended Complaint
    Were Submitted To The Contracting Officer For A Final Decision.
    a.     Regarding Counts I–IV.
    b.     Regarding Counts V–IX.
    c.     Regarding Damages.
    B.    Standing.
    C.    The Claims Alleged In RDA Construction Corp.’s May 7, 2015 Second Amended
    Complaint.
    1.    Count I: Whether The Naval Facilities Command Had A Duty To Disclose The
    Appledore Report And The Fay, Spofford & Thorndike Report.
    a.     Plaintiff’s Argument.
    b.     The Government’s Response.
    c.     Plaintiff’s Reply.
    d.     The Court’s Resolution.
    2.    Count II: Whether RDA Construction Corp. Is Entitled To An Equitable
    Adjustment Under The October 13, 2009 Contract’s Differing Site Conditions
    Clause.
    a.     Plaintiff’s Argument.
    b.     The Government’s Response.
    c.     The Court’s Resolution.
    3.    Counts III And IV: Whether The Naval Facilities Command Misrepresented
    The Condition Of The Wharf And The Purpose Of The October 13, 2009
    Contract.
    a.     Plaintiff’s Argument.
    b.     The Government’s Response.
    3
    c.     The Court’s Resolution.
    4.    Count V: Whether The Naval Facilities Command’s November 7, 2012
    Directive Was A Cardinal Change To The October 13, 2009 Contract.
    a.     Plaintiff’s Argument.
    b.     The Government’s Response.
    c.     The Court’s Resolution.
    5.    Counts VI, VII and VIII: Whether The NAVFAC Violated The Duty Of Good
    Faith And Fair Dealing.
    a.     Plaintiff’s Argument.
    b.     The Government’s Response.
    c.     The Court’s Resolution.
    i.     Regarding Price And Schedule Changes To The October 13, 2009
    Contact, Because Of The NAVFAC’s Failure To Disclose The
    Appledore Report And FST Report.
    ii.    Regarding Rescinding Approval Of RDA Construction Corp.’s
    Baseline Schedule.
    iii.  Regarding Extraction Of The Broken H-Pile Sections.
    iv.    Regarding Obstruction Drilling.
    v.     Regarding Work Suspension After The September 14, 2011 Safety
    Mishap.
    vi.    Regarding Approval Of RDA Construction Corp.’s Quality Control
    Manager And Site Safety And Health Officer.
    vii.  Regarding The Re-Inspection Of The Manitowoc 4100 Crane.
    6.    Count IX: Whether RDA Construction Corp. Was Entitled To An Extension Of
    The Contract Completion Date For Excusable Delays.
    IV.  DISCUSSION OF THE COUNTERCLAIMS ALLEGED IN THE GOVERNMENT’S
    JUNE 12, 2015 ANSWER.
    A.    Jurisdiction.
    B.    Standing.
    C.    Counterclaim I: Whether The Naval Facilities Command Is Entitled To Recover
    Liquidated Damages For The Cost Of Completing The October 13, 2009 Contract.
    1.    The Government’s Argument.
    2.    Plaintiff’s Response.
    4
    3.    The Government’s Reply.
    4.    The Court’s Resolution.
    a.    Whether RDA Was Entitled To An Extension Of The Contract
    Completion Date.
    b.    Whether The Naval Facilities Command’s February 21, 2013 Termination
    Of The October 13, 2009 Contract For Default Should Be Converted Into
    A Termination For Convenience.
    i.     Whether The February 21, 2013 Notice Of Termination Was “Fair
    And Impartial,” Pursuant To 
    48 C.F.R. § 1.602-2
    .
    ii.    Whether The Naval Facilities Command Established That RDA
    Construction Was In Default As Of The Termination Date.
    iii.  Whether The Naval Facilities Command Breached The October 13,
    2009 Contract Thereby Relieving RDA Construction Corp. Of Any
    Consequences Stemming From The February 21, 2013 Default
    Termination.
    c.    The Quantum Of Liquidated Damages That The Naval Facilities
    Command Is Entitled To Recover.
    D.    Counterclaim II: Whether RDA Construction Corp. Is Liable For Damages Under
    The Contract Dispute Act’s Anti-Fraud Provision, 
    41 U.S.C. § 7103
    (c)(2).
    1.    The Government’s Argument.
    2.    Plaintiff’s Response.
    3.    The Court’s Resolution.
    a.    Whether RDA Construction Corp.’s Crane Re-Inspection Claim Was
    “Baseless.”
    b.    Whether RDA Construction Corp.’s Crane Re-Inspection Claim Was
    “Indefensibly Inflated.”
    c.    Whether RDA Construction Corp.’s Crane Re-Inspection Claim Was
    “Premised On Affirmative Misrepresentations Of Fact.”
    E.    Counterclaim III: Whether RDA Construction Corp. Forfeited All Claims Against
    The United States Under The Special Plea In Fraud Statute, 
    28 U.S.C. § 2514
    .
    F.    Counterclaim IV: Whether RDA Construction Corp. Violated The False Claims Act.
    1.    The Government’s Argument.
    2.    Plaintiff’s Response.
    3.    The Court’s Resolution.
    5
    a.    Whether RDA Construction Corp. Falsely Certified That Its Deck
    Removal Work Complied With The October 13, 2009 Contract.
    b.    Whether RDA Construction Corp. Falsely Certified That Its Rock Fill
    Removal Work Complied With The October 13, 2009 Contract.
    i.     Regarding Rock Fill Removal.
    ii.    Regarding The Hydrographic Survey.
    c.    Whether RDA Construction Corp. Falsely Certified That It Made Timely
    Payments To Its Subcontractors.
    d.    Whether RDA Construction Corp.’s July 3, 2013 Certified Claim For
    Costs Incurred To Re-Inspect The Manitowoc 4100 Crane Was Baseless,
    Inflated And Premised On Factual Misrepresentations.
    V.    CONCLUSION.
    *       *       *
    I.     RELEVANT FACTUAL BACKGROUND.1
    A.      The Deteriorating And Dangerous Conditions At The Newport Naval Station
    Wharf.
    In 1958, the NAVFAC built a steel-reinforced concrete structure, known as the “marginal
    wharf” (“wharf”), and a metal-sheet pile bulkhead2 along 850 feet of Narragansett Bay shoreline,
    located between Piers 1 and 2 of the Newport Naval Station. PX 12 at 1–2.
    1
    The facts discussed herein were derived from evidence adduced at a trial held on
    November 16–19, 2015 and December 7–10, 2015 in Boston, Massachusetts and in January 4–6,
    2016 and July 11, 2016 in Washington, D.C. (TR at 1–2854). The witnesses for each party are
    identified in Court Exhibit A. During trial, the parties also introduced 1,463 exhibits into evidence.
    (PX 1–262; DX 1–759).
    2
    A “bulkhead” is “a retaining wall along a waterfront.” Bulkhead, MERRIAM-WEBSTER’S
    ONLINE DICTIONARY, https://www.merriam-webster.com/dictionary/bulkhead (last visited March
    22, 2017).
    6
    DX 7 at 7.
    As depicted below, the bulkhead is a seawall comprised of metal sheet-piles that were
    secured by steel rods anchored into concrete structures beneath the sea floor.
    PX 12 at 3.
    The wharf is a concrete structure, supported by 248 steel H-piles.3 DX 1 at 82–91. As
    illustrated below, each pile was encased in a concrete “jacket” from the top to below the waterline.
    3
    A “H-pile” is a steel beam with an “H”-shaped cross section and is driven into the earth
    by a pile driver. See H-Pile, MERRIAM-WEBSTER’S ONLINE DICTIONARY, https://www.merriam-
    webster.com/dictionary/H%E2%80%93pile (last visited March 22, 2017).
    7
    PX 12 at 4; DX 1 at 82–91.
    In April 2005, Appledore Marine Engineering, Inc. issued a report that was commissioned
    by the NAVFAC, titled: “Underwater Facilities Inspection And Assessment of the Newport Naval
    Station” (“the Appledore Report”). PX 12. The Appledore Report found “approximately ten
    percent of the concrete piles [supporting the wharf were] missing their fiberglass shell forms with
    failed or partially failed concrete encasement exposing the reinforcing steel and encased steel H-
    pile.” PX 12 at 15–16. The Appledore Report advised the NAVFAC that
    [b]elow the concrete jackets, the steel H-piles typically [had] advanced
    deterioration with significant loss of cross-sectional area. A Level I inspection of
    [all] the piles identified piles with buckled flanges,4 knife-edging and surface
    pitting.5 Several piles exhibit[ed] complete deterioration of the flanges . . . . Based
    on the degree of deterioration found during the Level I inspection, a special in-
    depth Level II inspection was conducted on all 248 steel H-piles including the
    removal of marine growth and steel thickness measurements.
    PX 12 at 16.
    The Appledore Report also found that the state of deteriorated H-piles “could only be
    observed during [an] underwater inspection” and was widespread i.e., forty-six percent of the H-
    piles could not safely carry any vehicular loads. PX 12 at 21, 25. Significantly, “these piles [were]
    4
    A “flange” is “a rib or rim for strength, for guiding, or for attachment to another object.”
    Flange, MERRIAM-WEBSTER’S ONLINE DICTIONARY, https://www.merriam-webster.com/
    dictionary/flange (last visited March 22, 2017).
    5
    “Pitting corrosion is a localized form of corrosion by which cavities or ‘holes’ are
    produced in the material. Pitting . . . is more difficult to detect, predict and design against [than
    uniform corrosion].” Pitting Corrosion, NATIONAL ASSOCIATION OF CORROSION ENGINEERS
    CORROSION BASICS, https://www.nace.org/Pitting-Corrosion/ (last visited March 22, 2017).
    8
    overstressed beyond their allowable load capacities simply from the weight of the [wharf.]” PX
    12 at 24. As a result, “catastrophic collapse [was] possible.” PX 12 at 25.
    In addition, the Appledore Report found that the metal-sheet pile bulkhead exhibited
    “advanced deterioration and defects.” PX 12 at 12. Where the bulkhead was accessible for
    inspection, there were “large corrosion holes . . . allowing backfill to wash through the bulkhead”
    and “[i]t [was] likely [that] portions of the bulkhead obscured from view . . . [had] similar advanced
    deterioration.” PX 12 at 12. The earth fill retained by the bulkhead between Piers 1 and 2 also
    had a large sinkhole up to eight feet wide and seven feet deep, and “sinkholes occur[ed] along the
    entire length of the . . . bulkhead.” PX 12 at 14.
    On August 29, 2008, Fay, Spofford & Thorndike, LLC (“FST”) conducted a second
    evaluation of the wharf for the NAVFAC (“the FST Report”). PX 19. The FST Report was not
    an independent evaluation, but primarily was based on information contained in the Appledore
    Report. PX 19 at 3. The FST Report found that the “overall condition of the wharf superstructure
    [was] good to fair.” PX 19 at 2. But, the FST Report “recommended that the wharf not be used
    during construction.” PX 19 at 1.
    B.      On May 18, 2009, The Naval Facilities Command Issued Solicitation No.
    N40085-09-B-7002.
    On May 18, 2009, the NAVFAC issued Solicitation No. N40085-09-B-7002 (“the
    Solicitation”) to restore the Newport Naval Station by:
           demolishing the wharf and metal-sheet pile bulkhead between Piers 1 and 2 of the
    Newport Naval Station;6
           removing underwater rock and sediment along the project site;
           constructing a new metal-sheet bulkhead; and
           constructing a parking area, storm drainage and other infrastructure, required to
    support ship berthing.
    DX 1 at 9.
    6
    The Solicitation required complete removal of the existing H-piles supporting the wharf
    and bulkhead. DX 1 at 82 (Demolition Note 3: “REMOVE PILES IN THEIR ENTIRETY”); PX
    12 at 3 (picture). In addition, bidders were instructed that during demolition, “[d]ebris shall not
    be allowed to fall into the water. Debris that does fall into the water shall be removed by the end
    of the work day.” DX 1 at 82.
    9
    The Solicitation included a set of drawings and specifications; bidders were required to
    conform contract work to the instructions listed in those documents.7 DX 1 at 35–36. The
    Solicitation warned potential bidders that
    [o]missions from the drawings or specifications or the misdescription of details of
    work that are manifestly necessary to carry out the intent of the drawings and
    specifications, or that are customarily performed, shall not relieve the Contractor
    from performing such omitted or misdescribed details of the work. The Contractor
    shall perform such details as if fully and correctly set forth and described in the
    drawings and specifications.
    DX 1 at 36 (emphasis added) (quoting 48 C.F.R. 252.236-7001(d)).
    The Solicitation also incorporated Federal Acquisition Regulation (“FAR”) 52.236-3(a),8
    requiring that potential bidders conduct their own investigations of site conditions. DX 1 at 14.
    7
    The Solicitation included thirty-eight technical drawings and specifications: (1) Title
    Sheet; (2) Locus Plan; (3) Design Loads; (4) Limit of Work Plan; (5) Demolition & Removals; (6)
    Existing Site Conditions Notes; (7) Existing Site Conditions; (8) Existing Site Conditions; (9)
    Existing Site Conditions; (10) Existing Site Conditions; (11) Existing Site Conditions; (12)
    Existing Site Conditions; (13) Hydrographic Survey Plan; (14) Soil Erosion & Sediment Control
    Plan; (15) Soil Erosion & Sediment Control Details; (16) Boring Location Plan & Logs;
    (17) Demolition Plan & Sections; (18) Rock Fill Removal Plan; (19) Demolition Details; (20) Site
    Grading, Paving & Draining Plan; (21) Sanitary Sewer Plan & Details; (22) Water Plan & Details;
    (23) Storm Sewer Plan & Details; (24) General Plan, Legend & Notes; (25) Bulkhead Plan; (26)
    Sheet Pile Plan & Elevation; (27) Sheet Pile Plan & Elevation; (28) Bulkhead Details; (29)
    Bulkhead Details; (30) Bulkhead Details; (31) Concrete Details; (32) Manhole Details; (33) Anode
    Location Plan; (34) Electrical Site Plan; (35) Bonding Locations & Details; (36) Reference
    Drawing; (37) Reference Drawing; and (38) Reference Drawing. DX 1 at 36.
    8
    FAR 52.236-3(a) provides that
    [t]he Contractor acknowledges that it has taken steps reasonably necessary to
    ascertain the nature and location of the work, and that it has investigated and
    satisfied itself as to the general and local conditions which can affect the work or
    its cost, including but not limited to (1) conditions bearing upon transportation,
    disposal, handling, and storage of materials; (2) the availability of labor, water,
    electric power, and roads; (3) uncertainties of weather, river stages, tides, or similar
    physical conditions at the site; (4) the conformation and conditions of the ground;
    and (5) the character of equipment and facilities needed preliminary to and during
    work performance. The Contractor also acknowledges that it has satisfied itself as
    to the character, quality, and quantity of surface and subsurface materials or
    obstacles to be encountered insofar as this information is reasonably ascertainable
    from an inspection of the site, including all exploratory work done by the
    Government, as well as from the drawings and specifications made a part of this
    contract. Any failure of the Contractor to take the actions described and
    10
    In addition, the Solicitation contained a release of liability for “any conclusions or
    interpretations” arising from the information provided by the NAVFAC. DX 14 at 1. This
    release included FAR 52.236-3(b) warning potential bidders that
    [t]he Government assumes no responsibility for any conclusions or interpretations
    made by the Contractor based on the information made available by the
    Government.      Nor does the Government assume responsibility for any
    understanding reached or representation made concerning conditions which can
    affect the work by any of its officers or agents before the execution of this contract,
    unless that understanding or representation is expressly stated in this contract.
    48 C.F.R. 52.236-3(b).
    Neither the Appledore Report nor the FST Report nor their findings were provided by the
    NAVFAC to potential bidders.
    C.      On June 4, 2009 and June 11, 2009, The Naval Facilities Command Conducted
    Two Site Visits Of The Newport Naval Station Wharf.
    On June 4, 2009 and June 11, 2009, the NAVFAC allowed prospective bidders to
    investigate site conditions. DX 1 at 517, 520. At the beginning of each visit, Travis J. Germano,
    a NAVFAC Construction Manager, provided bidders with a brief safety presentation and then took
    them to the site. TR at 2223 (Germano). Prospective bidders were encouraged to walk the entire
    length between Piers 1 and 2 and investigate the wharf’s conditions carefully. TR at 2225
    (Germano). They also were instructed to submit any questions in writing, so that everyone would
    have access to the same information. TR at 2223 (Germano).
    At the site, hazardous conditions around the wharf were marked by yellow sawhorses,
    orange construction fencing, and/or concrete barriers. TR at 2226 (Germano).
    acknowledged in this paragraph will not relieve the Contractor from responsibility
    for estimating properly the difficulty and cost of successfully performing the work,
    or for proceeding to successfully perform the work without additional expense to
    the Government.
    48 C.F.R. 52.236-3(a).
    11
    DX 742.10 (photograph of the wharf taken on May 19, 2008, prior to the June 4 and June 11,
    2009 site visits and RDA’s commencement of performance on February 5, 2010).
    DX 742.25 (photograph of the wharf taken on December 8, 2009, after the June 4 and June 11,
    2009 site visits, but prior to RDA’s commencement of performance on February 5, 2010).
    Exposed steel was visible where the wharf’s concrete structure showed deterioration. TR
    at 2226 (Germano).
    12
    DX 742.18 (photograph of deteriorated H-piles taken on November 29, 2009, after the June 4 and
    June 11, 2009 site visits, but prior to RDA’s commencement of performance on February 5, 2010).
    DX at 742.17 (photograph of deteriorated H-piles taken on November 29, 2009, after the June 4
    and June 11, 2009 site visits, but prior to RDA’s commencement of performance on February 5,
    2010).
    In addition, there were large sinkholes located along seventy-five percent of the bulkhead.
    TR at 2224–25 (Germano). Several bidders climbed into these sinkholes to inspect the existing
    seawall and conditions underneath the wharf. TR at 2224–25 (Germano).
    13
    DX 742.7 (photograph of sinkhole taken on May 19, 2008, prior to the June 4 and June 11, 2009
    site visits and RDA’s commencement of performance on February 5, 2010).
    An Estimator for RDA testified that he inspected the entire project site and paid special
    attention to the condition of the concrete deck and H-piles. TR at 79–80, 127–28 (Wood). But,
    RDA did not submit any questions to the NAVFAC, because RDA wanted to keep its bidding
    strategy secret. TR at 1474 (“We didn’t ask any questions because you are trying to keep your
    competitive advantage and your thought process to yourself. You are not trying to let everybody
    know what you are thinking.” (Kelley)).
    D.     On June 30, 2009, RDA Construction Corp. Submitted A Bid.
    On June 30, 2009, RDA submitted a bid for $7,162,524. DX 18 at 1. On July 7, 2009, the
    NAVFAC informed RDA that it was “the apparent low bidder” and requested that RDA provide:
    a.     Identification of the Contractor’s personnel and management to be used on this
    contract.
    b.     The Contractor’s technical and management plans for performing required services.
    c.     Description of Contractor’s facilities and equipment.
    d.     Summary of the Contractor’s experience in performing work of the type required
    by this specification.
    14
    e.       Current financial statements and data, including financial institution, point of
    contact, and phone number.
    f.       Other work presently under contract.
    g.       Prior contracts for similar work, and the names, addresses and telephone numbers
    of individuals with the organization issuing the contract who may be contacted for
    information concerning the Contractor’s performance.
    DX 22 at 1–2.
    On July 9, 2009, the NAVFAC informed RDA that its bid price “was substantially lower
    than the Government estimate” and requested that RDA “review [its] bid worksheets for . . .
    possible errors or omissions, assure [itself] that [it] fully underst[ood] the scope of work, and that
    [it] . . . include[d] . . . reasonable amounts to accomplish [the] work [required by the Solicitation].”
    DX 22 at 2. If RDA considered its bid price to be correct, RDA was instructed to provide a written
    confirmation of the price and a statement to the NAVFAC “waiv[ing] any and all claims of a bid
    mistake after award of the contract.” DX 22 at 2. After reviewing its bid, RDA informed the
    NAVFAC that “no clerical mistake was made in our calculations” and “[RDA] will honor the bid
    price and will not file any claims because of a bid mistake[.]” DX 22 at 3.
    On July 13, 2009, RDA also provided the NAVFAC with Technical And Management
    Plans stating that
    RDA plans on performing the work both from the land site and the waterside. The
    demolition of the deck and beams will be done from the land while the removal of
    the piles will be done from the water. For the driving of the sheets and the
    installation of the king piles, RDA plans to do this from the land with a barge in
    front of the work to assist in the performance. The diving crew will work off of
    floats in front of their work. All deliveries of materials will be done from land.
    RDA will self perform most of the work, but will hire qualified subcontractors for
    the specialty work, i.e. soil anchor, paving, etc. RDA will complete this project
    well ahead of 18 months as allowed in the contract.
    DX 23 at 20.
    E.       On October 13, 2009, RDA Construction Corp. Signed Contract No. N40085-
    09-B-7002.
    On September 30, 2009, the NAVFAC awarded Contract No. N40085-09-C-7002 (“the
    Contract”) to RDA. DX 1 at 536–37. On October 13, 2009, RDA signed the Contract. DX 1 at
    537. On October 15, 2009, the NAVFAC issued a Notice To Proceed. DX 29 at 1 (“[T]his letter
    constitutes your authority to commence work at the job site subject to the terms and conditions of
    the contract concerning other submittals required prior to commencing work.”). Pursuant to the
    October 13, 2009 Contract, RDA was to “complete [contract performance] within 555 days after
    receiving notice to proceed,” i.e., the completion date was set as June 26, 2011. DX 1 at 1.
    15
    F.     On November 18, 2009, The Appledore Report Was Disclosed To RDA
    Construction Corp.
    On November 12, 2009, RDA met with Mr. Germano, the NAVFAC’s Construction
    Manager, at a pre-construction conference. DX 36 at 1; DX 37 at 2. Afterwards, Michael Hartman,
    RDA’s Project Manager, and Mr. Germano toured the project site. TR at 188 (Hartman); TR at
    2253 (Germano). During the tour, Mr. Hartman informed Mr. Germano that RDA planned to
    demolish the wharf, using two excavators that would be placed side-by-side on the wharf and
    gradually work backwards from one end to the other, ripping up the concrete structure and
    removing piles as they moved along. TR at 188 (Hartman). Mr. Hartman also stated that RDA
    would leave a narrow strip on the outboard side of the wharf where the soil anchoring equipment
    would be placed while the new bulkhead was installed. TR at 2253 (Germano). At trial, Mr.
    Germano testified that he was “shocked” by RDA’s demolition plan, because the “wharf [was]
    condemned.” TR 2254 (Germano).
    On November 18, 2009, Mr. Germano provided RDA with the Appledore Report and
    restated his reservations about RDA’s demolition plan: “[F]rom [a] quick review of the document
    and drawings, [he] would significantly question the capacity of the [marginal] wharf” and “[f]rom
    a safety perspective, [he did] not believe [RDA would] be allowed to place any equipment or
    vehicles on the wharf.” PX 28 at 1.
    On November 20, 2009, RDA informed Mr. Germano that it reviewed the Appledore
    Report and was concerned that the wharf apparently was not capable of supporting a live load—a
    fact not mentioned in the Solicitation. PX 29. RDA explained that
    [i]n preparation of [its] bid[,] [RDA] included means and methods to utilize
    portions of the existing structure as a work platform for the initial selective
    demolition of the wharf structure, rip rap removal, subsequent drilling of the earth
    anchors and final demolition of the structure. Each of these work activities included
    staging equipment off the existing wharf not marine access from barge mounted
    equipment. The instability of the wharf will cause both time and cost impacts.
    PX 29.
    On December 9, 2009, the NAVFAC became concerned that the conditions described in
    the Appledore Report would adversely affect the cost of completing the wharf and requested that
    RDA provide the following information:
          Please explain in some detail exactly how you intended to utilize the existing wharf
    in performing the contract work. For example, what portions of the wharf did you
    intend to demolish at various times, what equipment did you intend to stage on the
    remaining portions of the wharf, and how did you intend to use that equipment to
    advance the project?
          Please provide a plan view drawing noting the type of equipment, locating their
    position & reach capability. Please provide a profile view drawing for both the
    16
    rock removal work and soil anchor work locating equipment position, available
    angle of drilling, and reach capability.
           Please provide your best current estimate of the cost and time impacts you will
    incur if you are required to utilize barges and temporary structures to perform the
    contract work. Please briefly explain how you arrived at your figures.
    DX 54 at 1.
    The NAVFAC also warned RDA that the December 9, 2009 letter should not be interpreted
    as accepting RDA’s characterization that the Solicitation and/or contract specifications and
    drawings were not complete. DX 54 at 2.
    On December 20, 2009, RDA responded to the NAVFAC’s December 9, 2009 letter,
    explaining that its “As-Bid Plan” was to use the existing wharf as a staging platform for a two-step
    demolition process. DX 62 at 3. During the first step, RDA planned to demolish the inboard side
    of the wharf. DX 62 at 3. This work would be performed from the wharf, by moving the
    demolition equipment backward from one end to the other. DX 62 at 3. Noncritical sections of
    the inboard wharf would be left intact to provide access to the outboard side. DX 62 at 3. Then,
    RDA would place a drill rig on the outboard portion of the wharf to complete the earth anchor
    installations required for the new bulkhead. DX 62 at 3. After installation of the earth anchors,
    RDA would demolish the outboard wharf. DX 62 at 3–4. But, in light of the Appledore Report,
    the wharf could no longer be used as a platform for demolition or construction staging. DX 62 at
    4. Therefore, that work would have to be performed from barge-mounted equipment and/or
    platforms supported by temporary piles. DX 62 at 4. And, because these structural problems were
    not disclosed in the Solicitation or during the site visit, RDA would need to spend an additional
    $1,209,905.62 to complete performance. DX 62 at 4–5; but see PX 35 at 1–2 (subcontractor
    estimate advising RDA that if the wharf demolition was performed from barges, it would cost
    RDA an additional $797,400).
    On December 23, 2009, RDA submitted a Baseline Network Analysis Schedule (“baseline
    schedule”) to the NAVFAC, compiled from its as-bid plan. DX 65 at 1; TR at 229–32 (Hartman).
    Pursuant to the October 13, 2009 Contract, “[s]ubmittal and acceptance of the [baseline schedule]
    and accurate updated schedules accompanying [RDA’s] pay requests [were] both conditions
    precedent to [the NAVFAC] processing pay request.” DX 1 at 144.
    On February 2, 2010, the NAVFAC informed RDA that the December 23, 2009 baseline
    schedule was not acceptable, because “it [did] not accurately represent the actual ‘work process
    logic,’ that is, performing the work from barge mounted equipment, in which the project will be
    completed.” DX 87 at 1. The NAVFAC also advised RDA that the February 2, 2010 letter would
    “serve as confirmation to our several phone conversations that all submitted baseline [schedules]
    to date were not approved.” DX 87 at 1. That same day, RDA submitted a revised baseline
    schedule. PX 58 at 1.
    On February 5, 2010, the NAVFAC repeated that “the multiple baseline schedules
    previously submitted . . . [were] not acceptable” (DX 95 at 1), but conditionally approved RDA’s
    February 2, 2010 baseline schedule for the limited purpose of allowing work to begin. PX 58 at 1.
    17
    The NAVFAC advised RDA that “invoicing will not be permitted until [the NAVFAC]
    complete[d] a full review of [the] schedule and accept[ed] it.” PX 58 at 1.
    On February 8, 2010, the NAVFAC informed RDA that
    [t]he [NAVFAC] is in the process of reviewing the information RDA . . . has
    provided regarding its planned method of performance of the P-469 Waterfront
    Improvement contract when it submitted its bid. The information consists of
    [RDA’s December 20, 2009] letter . . . and marked up drawings CD-101 and CD-
    501 (which include narrative inserted by RDA discussing your proposed methods).
    While we have not completed our review of this information, two of our subject
    matter experts have expressed strong reservations regarding whether your proposed
    methods were feasible even if the wharf were structurally sound[.]
    While the Navy hopes to complete its analysis of this issue in the near future and
    determine whether RDA is entitled to any adjustment to the contract price for
    adjusting its method of performance, our analysis does not excuse RDA from
    starting performance. As you are aware, your contract contains FAR Clause
    52.233-1, “Disputes.” 9
    DX 98 at 1.
    On April 1, 2010, the NAVFAC informed RDA that the July 3, 2010 revised baseline
    schedule contained thirty-four deficiencies and returned it to RDA for revisions consistent with
    the NAVFAC’s comments. DX 111 at 1.
    On April 21, 2010, RDA submitted another revised schedule that the NAVFAC also
    rejected, listing eighteen deficiencies that RDA was required to address before the baseline
    schedule could be approved. DX 121 at 2.
    G.      On April 21, 2010, RDA Construction Corp. Filed A Certified Claim.
    On April 21, 2010, RDA filed a certified a claim, requesting that the NAVFAC adjust the
    contract price by $1,948,053.86 to reflect the additional costs that RDA would incur to perform
    demolition of the wharf and construction of a new bulkhead from barge-mounted equipment. DX
    118 at 1, 4.
    H.      On May 17, 2010, The Naval Facilities Command Approved RDA
    Construction Corp.’s Baseline Schedule.
    On April 28, 2010, RDA submitted another baseline schedule for the NAVFAC’s approval.
    DX 130 at 1. On May 13, 2010, the NAVFAC rejected the April 21, 2010 submission, because it
    did not include work that the October 13, 2009 Contract required. DX 130 at 1–3. The next day,
    9
    FAR 52.233-1(i) states that “[t]he Contractor shall proceed diligently with performance
    of [the relevant] contract, pending final resolution of any request for relief, claim, appeal, or action
    arising under the contract, and comply with any decision of the [CO].” 48 C.F.R. 52.233-1(i).
    18
    RDA submitted a new revised baseline schedule, addressing the deficiencies listed in the
    NAVFAC’s May 13, 2010 rejection. DX 134 at 1. On May 17, 2010, the NAVFAC finally
    approved RDA’s baseline schedule. DX 134 at 1.
    I.      On August 31, 2010, RDA Construction Corp.’s April 21, 2010 Certified Claim
    Was Denied.
    On June 17, 2010, the NAVFAC advised RDA that the Defense Contract Audit Agency
    (“DCAA”) was performing an audit of RDA’s April 21, 2010 Certified Claim and a final decision
    would be issued on, or before, August 31, 2010. DX 151. On August 11, 2010, RDA was warned
    that the NAVFAC would deny RDA’s certified claim, if RDA continued to fail to provide the
    information requested by DCAA to complete the audit. DX 170 at 2. RDA, however, still did not
    provide the requested documents. TR at 522 (Hartman).
    On August 31, 2010, the NAVFAC CO issued a decision recognizing that the NAVFAC
    failed to disclose the Appledore Report during the bidding process, but nevertheless denied RDA’s
    certified claim, because a “reasonable contractor” who attended the June 4, 2009 and/or June 11,
    2009 site visits should have concluded that the wharf was in such poor condition that it could not
    be used as a platform for demolition and construction: “[I]t was also unreasonable for RDA to
    assume that the wharf was structurally sound in light of the fact that the entire purpose of the
    contract was to demolish the structure and build a new one.” DX 193 at 3.
    The NAVFAC CO added that
    RDA has not demonstrated its claimed damages with sufficient specificity to justify
    any payment. The Government has made several requests that RDA provide
    calculations showing that the wharf could have accommodated RDA’s proposed
    methods, such as supporting the weight and lateral forces of construction
    equipment, if it were in good condition, but RDA has never provided any such
    information.
    DX 193 at 3–4.
    J.      On September 20, 2010, RDA Construction Corp. Informed The Naval
    Facilities Command That Underground Obstructions Were Encountered, So
    Work Stopped.
    The October 13, 2009 Contract required RDA to replace the bulkhead between Pier 1 and
    Pier 2 of the Newport Naval Station. DX 1 at 9. The bulkhead was composed of king piles (i.e.,
    support beams installed intermittently along the structure) and sheet piles (i.e., a wall of
    interlocking metal sheets that mount onto the king piles). DX 1 at 100; PX 12 at 3. To replace the
    bulkhead at Newport Naval Station, RDA was required to extract the existing king and sheet piles
    and install new ones. DX 729 at 6 (Helmes Direct).
    RDA began to renovate the bulkhead from the south-end. TR at 298–99 (Hartman). On
    August 23, 2010, however, RDA informed the NAVFAC that an underground obstruction
    prevented RDA from installing additional sheet piles at the south bulkhead and requested direction
    19
    on how to proceed. DX 206 at 1. On September 20, 2010, RDA requested an equitable adjustment
    stating that the obstruction encountered was a differing site condition.10
    The NAVFAC did not immediately respond to RDA’s September 20, 2010 letter. As a
    result, RDA stopped working on the southern bulkhead and began to remove the sheet piles in the
    center bulkhead. TR at 302 (Hartman). But, it was not long before RDA encountered other
    difficulties at that location. On December 14, 2010, RDA notified the NAVFAC that “[t]he sheets
    [at the center bulkhead were] in such a deteriorated condition [that] they [could not] withstand the
    extraction process and pull[ed] apart.” DX 237 at 2. RDA also reported that it would “track all
    associated costs to perform this changed condition, and forward same to [the NAVFAC] for
    review.” DX 237 at 2.
    On January 7, 2011, RDA complained that the NAVFAC failed to acknowledge its
    December 14, 2010 letter and warned that “[a]ll work associated with the Center Bulkhead will be
    shutdown until the [NAVFAC] responds in writing as required by the [October 13, 2009
    Contract].” DX 244 at 1. Nevertheless, RDA proceeded to work on the north bulkhead. TR at
    339 (Hartman). On March 9, 2011, RDA informed the NAVFAC that it hit a second obstruction
    while installing sheet pile at the north bulkhead and requested to meet with the NAVFAC to discuss
    possible solutions. DX 283 at 2. RDA also advised the NAVFAC that “[w]e are now at a position
    where no work can proceed on either the South, Center or North Bulkheads without direction. We
    laid off all of the workers on site today and will return once we come to a mutual understanding
    on how to proceed.” DX 283 at 2.
    10
    The October 13, 2009 Contract incorporated a “differing site conditions” clause, that
    stated:
    (a) The Contractor shall promptly, and before the conditions are disturbed, give a
    written notice to the Contracting Officer of—
    (1) Subsurface or latent physical conditions at the site which differ materially
    from those indicated in this contract; or
    (2) Unknown physical conditions at the site, of an unusual nature, which differ
    materially from those ordinarily encountered and generally recognized as
    inhering in work of the character provided for in the contract.
    (b) The Contracting Officer shall investigate the site conditions promptly after
    receiving the notice. If the conditions do materially so differ and cause an increase
    or decrease in the Contractor’s cost of, or the time required for, performing any part
    of the work under this contract, whether or not changed as a result of the conditions,
    an equitable adjustment shall be made under this clause and the contract modified
    in writing accordingly.
    
    48 C.F.R. § 52.236-2
    (a)–(b).
    20
    K.     On March 10, 2011, The Naval Facilities Command Instructed RDA To
    Submit A Cost Proposal To Remove The Obstructions And Continue Work.
    On March 10, 2011, RDA was advised that
    [t]he [NAVFAC] received [RDA’s] cost proposal on 17 February 2011 regarding
    removal of the obstructions. Additional back-up information was requested from
    RDA on 4 March 2011[.] . . . [RDA’s] proposal cannot be analyzed until this
    information is received.
    RDA is claiming that they are unable to remove the existing sheet piles . . . [.] As
    stated on drawing CD-501, Note 1, ‘if sheets cannot be extracted, cut sheet along
    knuckle from top of sheet to ground line, then continue to extract using a vibratory
    hammer.’ During a site visit on 8 March, the [NAVFAC] observed that while trying
    to remove the existing sheets, RDA did not cut to the ground line but rather to the
    waterline. For this reason, the [NAVFAC] disagrees that RDA has encountered a
    differing site condition.
    Please be advised that RDA is currently in default of the contract. If RDA disagrees
    with the [NAVFAC’s] response to these issues, RDA’s remedy is to utilize the
    [CDA], which is incorporated into the contract via FAR 52.233-1. Pursuant to that
    clause, ‘the contractor shall proceed diligently with performance of this contract . .
    . and comply with any decision of the [CO],’ even though it is pursuing claims
    under the [CDA]. . . . Any future abandonment of the project by RDA will be
    considered a material breach[.]
    DX 274 at 1–2.
    On March 11, 2011, RDA responded that its work force would return to the site on March
    14, 2011, but the decision to stop work “should not be construed as Project abandonment[,] but
    rather a short period of time to coordinate and plan for the most recent developments experience
    on the Project.” DX 276 at 1.
    On March 16, 2011, RDA informed the NAVFAC of another obstruction at the north
    bulkhead that was encountered, renewed complaints that obstructions at the bulkhead were
    differing site conditions, and requested a meeting to discuss “various options and hopefully come
    to terms with a solution.” DX 283 at 3.
    L.     In Late March 2011, RDA Construction Corp.’s Quality Control Manager
    And Site Safety Health Officer Quit.
    In late March 2011, RDA’s Site Safety Health Officer (“SSHO”) and Quality Control
    Manager (“QC”) quit after RDA experienced two accidents on site. DX 174; DX 262; TR at 1180–
    81 (Mr. Rachupka), 1368 (Kelley). Thereafter, from March 31–May 5, 2011, RDA sent numerous
    letters to the NAVFAC requesting that Ray Morisette, Peter Meomartino, Lynda Amarantes,
    Michael Rand, and Richard DiRamio be approved as QCs and SSHOs. DX 307–13, 316, 319–20,
    322–26. On May 9, 2011, the NAVFAC approved Mr. Morrissette to serve both as the QC and
    21
    SSHO, but denied RDA’s other proposed personnel, because their “resumes and certificates” did
    not meet contract requirements. DX 327 at 1.
    M.      On June 7, 2011 And August 19, 2011, The Naval Facilities Command Issued
    Contract Modifications 4 and 5 To The October 13, 2009 Contract.
    On April 4, 2011, the NAVFAC requested that RDA submit a cost proposal for “a
    pneumatic percussive air-track drill rig to penetrate through the reported obstructions [at the south
    bulkhead and north bulkhead],” but cautioned that “this is an inquiry only and is not to be construed
    as authority to proceed with the work.” DX 293 at 1. On April 12, 2011, RDA provided the
    NAVFAC with that proposal. DX 298 at 1. On April 14, 2011, the NAVFAC asked for more
    information and “to provide an approximate number of days [RDA] thought it might take to drill
    through the obstructions so [the NAVFAC could] put an estimated number of days in the
    modification[.]” DX 299 at 1. On April 22, 2011, RDA provided that information. DX 304 at 1.
    On June 7, 2011, the NAVFAC executed Modification 411 as an equitable adjustment to
    the October 13, 2009 Contract, “to incorporate changes required by obstructions encountered
    during installation of sheet piles.” DX 1 at 587. Modification 4 required RDA to drill through the
    obstructions at the south and north bulkheads, extended the contract completion date by forty-four
    days, i.e., from June 26 to August 9, 2011, and increased the contract price by $290,180. DX 1 at
    588. Modification 4 also required that “[a]cceptance of this modification by the Contractor
    constitutes an accord and satisfaction and represents payment in full for both time and money and
    for any and all costs, impact effect, and for delays and disruptions arising out of, or incidental to,
    the work as herein revised.” DX 1 at 588 (emphasis added).12
    On June 28, 2011, Ray Morrissette had a heart attack. DX 347 at 1; PX 138 at 1; TR at
    659 (Wallis), 1157–58 (Rachupka), 1373 (Kelley). Because the October 13, 2009 Contract
    required RDA to “[p]rovide a Site Safety and Health Officer (SSHO) at the work site at all times,”
    RDA had to stop work, pending Ray Morrissette’s recovery or the appointment of another SSHO.
    DX 1 at 192; DX 347 at 1; DX 350 at 1. On June 29, 2011, RDA re-proposed Lynda Amarantes
    11
    Modifications 1–3 made administrative changes to the October 13, 2009 Contract. On
    November 4, 2009, the NAVFAC executed Modification 1 designating the Facilities Engineering
    Acquisition Division team at Newport Naval Station as the Administrative Contracting Officer
    and set the liquidated damages amount at $3,531.56 for each calendar day of delay until the work
    is completed. DX 1 at 581. On January 27, 2010, the NAVFAC executed Modification 2
    providing that payment to RDA would be made by the Defense Finance and Accounting Service.
    DX 1 at 583. On April 15, 2010, Modification 3 changed the contract completion date from April
    11, 2011 to June 26, 2011, “due to [an] Option exercised at time of award (which allowed for an
    additional 65 days for contract completion if exercised).” DX 1 at 586.
    12
    The effect of the accord and satisfaction clause was to absolve the NAVFAC from any
    liability relating to the non-disclosure of the Appledore Report and the FST Report prior to
    executing the October 13,2 009 Contract, including RDA’s April 21, 2010 Certified Claim.
    22
    for the QC and SSHO positions. DX 345 at 1; DX 346 at 1. On June 30, 2011, RDA also re-
    proposed Michael Rand for the QC position. DX 348 at 1.
    On July 13, 2011, the NAVFAC responded that Lynda Amarantes was not qualified to
    serve as a QC or SSHO. DX 356 at 1. On July 27, 2011, RDA advised the NAVFAC that Ray
    Morrissette was “cleared by his cardiologist to return to work,” but was required to “attend [a
    cardiac rehabilitation program] on Mondays, Wednesdays, [and] Fridays.” DX 366 at 1. RDA
    proposed that Michael Rand act as QC and SSHO, when Ray Morrissette was absent. DX 366
    at 1.
    On August 9, 2011, RDA informed the NAVFAC that it began drilling through the
    obstructions on July 17, 2011, but work was still in progress. DX 372 at 1. The August 9, 2011
    letter also advised that
    [t]o date [RDA has] experienced conditions which were not anticipated in the scope
    of additional work. Several iterations of obstruction drilling, attempted driving of
    permanent sheets and then more drilling has occurred several times. Unanticipated
    additional obstruction drilling at the Center Bulkhead . . . , extraction of existing
    sheet pile at the North Bulkhead . . . causing adjacent King Piles to move outboard.
    In general RDA has worked out of planned sequence causing our Obstruction Drill
    Crew and Pile Driving Crew to experience inefficiencies in production.
    DX 372 at 1.
    On August 19, 2011, the NAVFAC issued Modification 5 to the October 13, 2009 Contract,
    extending the contract end-date from August 9 to August 16, 2011, and increased the contract price
    by $41,055. DX 1 at 592. Modification 5 also included an accord and satisfaction clause. DX 1
    at 592.
    N.      On August 31, 2011, RDA Construction Corp. Filed A Complaint In The
    United States Court Of Federal Claims.
    On August 31, 2011, RDA filed a Complaint in the United States Court of Federal Claims,
    alleging that: (1) the Government violated its duty to disclose material information regarding the
    nature of the work required by the October 13, 2009 Contract; (2) under the differing site
    conditions clause of the October 13, 2009 Contract, RDA is entitled to recover costs attributable
    to site conditions that differed materially from the conditions disclosed in the contract documents;
    and (3) the NAVFAC affirmatively and intentionally misrepresented the conditions of the wharf.
    ECF No. 1, 8/31/11 Compl. at ¶¶ 49–50, 52–53, 55–56 (“8/31/11 Compl.”). On that same day,
    RDA Construction Corp. v. United States, No. 11-555, was assigned to the Honorable Francis M.
    Allegra. ECF No. 3.
    O.      On September 14, 2011, RDA Construction Corp. Experienced A Third
    Accident At The Project Site.
    On September 14, 2011, RDA had an accident at the Newport Naval Station involving a
    Manitowoc 4100W crane, but no one was injured. DX 398 at 1. On September 27, 2011, RDA
    was informed that its safety record was unacceptable, because “neither the SSHO/QC Manager
    23
    nor the Superintendent [was] on site when the accident occurred.” DX 413 at 1. The NAVFAC
    also warned RDA that
    [i]f the Government observes any unsafe conditions at the project site in the future,
    or if any future incidents occur, we plan to vigorously enforce the contract’s
    remedies for such matters. Specifically, the contract permits the Government to
    stop all work on the project until all safety concerns have been remedied. Under
    the contract, such a stoppage would not entitle RDA to any type of monetary
    adjustment nor any extension of the contract’s completion date. The contract
    specifications also permit the Government to demand the removal of your
    superintendent and/or SSHO due to their failure to enforce safety requirements and
    stop all work until suitable replacements are identified and onsite. And, if such
    stoppages result in RDA failing to make sufficient progress on the contract, the
    Government will be entitled to terminate the contract for default.
    DX 413 at 1–2.
    On September 28, 2011, RDA responded that it did not “take the events surrounding the
    incident on September 14, 2011 lightly and intend[ed] to address the situation . . . to the
    [NAVFAC’s] satisfaction.” DX 415 at 1. To that end, RDA proposed “an internal review of the
    contract requirements regarding the SSHO” and promised that “[t]he approved SSHO or his
    approved designee will be on site during all work activities,” “[p]rior to a scheduled absence by
    the SSHO upcoming safety and QC inspections will be completed,” and “[i]f there are any QC
    and/or safety requirements that have to be addressed or if there are multiple work activities being
    performed during the SSHO’s absence then RDA’s President, Gene Kelley will provide the
    additional oversight.” DX 415 at 2.
    On October 11, 2011, RDA proposed that Mark Wallis be approved as the alternate SSHO
    so that he could serve as SSHO, when Ray Morrissette was not present at the project site. DX 426
    at 1. On October 19, 2011, RDA also submitted Mark Wallis as an alternate QC. DX 436 at 1.
    On January 19, 2012, the NAVFAC rejected RDA’s proposal to use Mark Wallis as a QC, because
    of
    certain prior actions he has taken that have demonstrated a total disregard for
    necessary safety and environmental concerns. For example, Wallis recently
    ignored Navy guidance by failing to use any preventive measures to prevent or
    mitigate a release of fuel during the recovery operation of the sunken push boat [on
    January 12, 2012]. Although the need for such measures was explicitly discussed
    during the critical lift meeting on [January 11, 2012] and mentioned again prior to
    the critical lift on [January 12, 2012], RDA did not exercise necessary steps to
    prevent or contain a spill.
    As a result of RDA’s failure, a fuel spill occurred during the lift and Naval Station
    Newport had to report a second release of fuel from RDA’s boat into Narragansett
    Bay to the RI Department of Environmental Management and US Coast Guard.
    This recent spill was the second release of fuel into Narragansett Bay by RDA in
    the past month (first release occurred on [December 29, 2011] when attempting to
    24
    recover the sunken push boat). Despite having experienced the prior spill, and
    despite the Navy’s guidance to RDA to have spill kits available to respond if
    additional fuel was released into the water, RDA did not utilize any preventive
    measures prior to lifting the boat from the water. The Navy finds this lack of care
    on the part of RDA and Wallis to be completely unacceptable.
    DX 485 at 1–2. The NAVFAC also denied RDA’s request to use Mark Wallis as an SSHO. DX
    486 at 1.
    On January 20, 2012, RDA proposed Peter Brewer to replace Ray Morrissette as the SSHO.
    DX 487 at 1. On January 24, 2012, RDA requested that the NAVFAC reconsider Mark Wallis as
    RDA’s QC. DX 489 at 1. On January 27, 2012, the NAVFAC approved Peter Brewer as RDA’s
    SSHO, but again rejected Mark Wallis, insisting that “a different, qualified individual [] fill the
    QC position before [RDA could] resume work on the project.” DX 491 at 1. On the same day,
    RDA requested approval of Gerald Smith as QC. DX 493 at 1. On February 13, 2012, the
    NAVFAC approved Gerald Smith as RDA’s QC. PX 156 at 2.
    P.      From March 20, 2012 To November 8, 2012, The Naval Facilities Command
    Issued Contract Modifications 6–12.
    On March 20, 2012, the NAVFAC executed Modification 6, granting RDA a $34,401
    equitable adjustment to remove the H-piles, sheet piles, and creosoted timber that were not shown
    on the contract drawings and extended the contract completion date from August 16, 2011 to
    August 17, 2011. DX 1 at 594. Modification 6 also contained an accord and satisfaction clause.
    DX 1 at 594.
    On April 13, 2012, the NAVFAC issued Modification 7, requiring RDA to perform
    additional drilling through the obstructions at the south bulkhead with a construction monitor
    onsite to observe the drilling operations. DX 1 at 597. The contract completion date also was
    extended by seventy-one days, i.e., from August 17, 2011 to October 27, 2011, and the total cost
    of the contract was increased by $63,959.23. DX 1 at 597.
    On June 6, 2012, the NAVFAC executed Modification 8, extending the contract
    completion date to November 13, 2011 and the total cost by $95,314, to add a corrosion protection
    system on the tie rods for the deck fitting bases and attach all landside anodes to new sheet piles.
    Modification 8 also included an accord and satisfaction clause. DX 1 at 601.
    On August 17, 2012, the NAVFAC issued Modification 9, extending the contract
    completion date to February 14, 2012 and increasing the contract price by $351,423, for additional
    drilling through the obstructions at the south and north bulkheads. DX 1 at 604.
    On September 4, 2012, the NAVFAC published Modification 10, granting RDA a $69,280
    equitable adjustment for the time, labor, material and equipment costs that RDA incurred to drill
    through the obstructions at the south bulkhead. DX 1 at 607–08. Modification 10 also extended
    the contract completion date to June 15, 2012 for delays when RDA did not have an approved
    SSHO and QC. DX 1 at 608.
    25
    On September 19, 2012, the NAVFAC executed Modification 11, decreasing the contract
    completion date to June 12, 2012 and deducting $2,504 from the contract price, because RDA used
    a method to drill through the obstructions at the north bulkhead that was less expensive than
    originally anticipated. DX 1 at 611–12.
    On November 8, 2012, the NAVFAC executed Modification 12, extending the contract
    completion day to October 5, 2012, and increasing the contract price by $299,165, for additional
    work required to drill through obstructions at the north bulkhead. DX 1 at 614–15.
    Q.      On February 21, 2013, The Naval Facility Command Terminated The October
    13, 2009 Contract.
    On November 7, 2012, the NAVFAC directed RDA to remove several piles from the bay
    floor that broke below the mud-line. DX 626 at 1. On January 18, 2013, RDA complained that
    the NAVFAC’s repeated failure to adjust the October 13, 2009 Contract for unforeseen conditions
    and November 7, 2012 directive constituted a cardinal change. DX 626 at 2. Therefore, RDA
    refused to comply with the NAVFAC’s instructions. DX 626 at 2.
    On November 28, 2012, J. P. Riley Crane Consultants (“J.P. Riley”), an independent crane
    inspector, conducted an annual inspection of the Manitowoc 4100W crane and presented RDA
    with a Crane Inspection Certificate, but also issued a Deficiency Report citing five items that
    needed repair. DX 677 at 3, 6. RDA was instructed to sign the Deficiency Report and return it to
    J.P. Riley, ten days after the repairs were made. DX 677 at 6. On December 13, 2012, an RDA
    employee signed the Report. DX 677 at 6.
    On January 9, 2013, RDA provided the NAVFAC with the November 28, 2012 Crane
    Inspection Certificate and signed Deficiency Report. DX 677 at 17. But, on January 10, 2013, a
    NAVFAC official sent an e-mail to RDA stating there was no “mention when the crane was re-
    inspected by J[.]P[.] Riley confirming the adequacy of repairs so that it could be placed back into
    service.” DX 677 at 18. The email also stated that, according to the United States Army Corps of
    Engineer Safety And Health Requirements Manual EM 385-1-1 (2008) (the “EM 385-1-1”): “a
    written report is required confirming the adequacy of repairs.” DX 677 at 18. Subsequently, the
    NAVFAC and RDA argued about whether the EM 385-1-1 required J.P. Riley to re-inspect the
    crane after the repairs were completed, or if an RDA mechanic could perform the re-inspection.
    DX 677 at 17–27.
    On January 14, 2013, the NAVFAC issued a letter, pursuant to FAR 52.236–13,13
    directing RDA “to have the Manitowoc 4100 crane inspected by an independent, third-party that
    13
    In demolition contracts, FAR 52.236–13 provides that “the Contractor shall comply with
    all pertinent provisions of the latest version of U.S. Army Corps of Engineers Safety and Health
    Requirements Manual, EM 385–1–1, in effect on the date of the solicitation,” and
    [if the] Contracting Officer becomes aware of any noncompliance with these
    requirements or any condition which poses a serious or imminent danger to the
    health or safety of the public or Government personnel, the Contracting Officer
    shall notify the Contractor orally, with written confirmation, and request
    26
    specializes in performing crane inspection” and stating that “RDA is not permitted to use the
    Manitowoc 4100 crane . . . until such an independent inspection has been completed.” DX 677 at
    28. The letter also instructed that the NAVFAC personnel were to be present for the re-inspection.
    DX 677 at 28.
    On January 16, 2013, J.P. Riley re-inspected the crane in the presence of Craig Rachupka,
    NAVFAC’s Construction/Project Manager. DX 625 at 1. At the re-inspection, RDA agreed to
    make the necessary repairs and submit to a third re-inspection. DX 625 at 2. The NAVFAC also
    instructed RDA to keep the crane out of service until that time. DX 677 at 60. Afterward, RDA
    sent the NAVFAC additional letters about whether FAR 52.236–13 and the EM 385-1-1 gave the
    NAVFAC authority to keep RDA’s Manitowoc 4100 crane out of service. DX 677 at 60, 104,
    106, 118–121.
    On January 31, 2013, the NAVFAC instructed RDA to show cause why the October 13,
    2009 Contract should not be terminated for default, pursuant to FAR 52.249-10,14 because
    immediate initiation of corrective action . . . . If the Contractor fails or refuses to
    promptly take corrective action, the Contracting Officer may issue an order
    stopping all or part of the work until satisfactory corrective action has been taken.
    The Contractor shall not be entitled to any equitable adjustment of the contract
    price or extension of the performance schedule on any stop work order issued
    under this clause.
    
    48 C.F.R. § 52.236
    –13 (c), (d).
    14
    FAR 52.249-10 states, in relevant part,
    (a) If the Contractor refuses or fails to prosecute the work or any separable part,
    with the diligence that will insure its completion within the time specified in this
    contract including any extension, or fails to complete the work within this time, the
    Government may, by written notice to the Contractor, terminate the right to proceed
    with the work (or the separable part of the work) that has been delayed. In this
    event, the Government may take over the work and complete it by contract or
    otherwise, and may take possession of and use any materials, appliances, and plant
    on the work site necessary for completing the work. The Contractor and its sureties
    shall be liable for any damage to the Government resulting from the Contractor’s
    refusal or failure to complete the work within the specified time, whether or not the
    Contractor’s right to proceed with the work is terminated. This liability includes
    any increased costs incurred by the Government in completing the work.
    (b) The Contractor’s right to proceed shall not be terminated nor the Contractor
    charged with damages under this clause, if—
    (1) The delay in completing the work arises from unforeseeable causes beyond
    the control and without the fault or negligence of the Contractor.
    48 C.F.R. 52.249-10.
    27
    the contract’s [amended] completion date passed almost four months ago, on 5
    October 2012. Since that date, the Navy ha[d] refrained from terminating RDA . . .
    under the default clause in hopes that RDA would make significant progress
    towards completion, thereby mitigating its potential damages.
    RDA’s continued failure to make progress towards completion of this project,
    however, require[d] the Navy to reconsider its position regarding termination.
    RDA . . . made only limited progress on any contract work for over a month and at
    least two of its major pieces of equipment . . . [were] currently broken, [creating]
    significant concerns regarding RDA’s ability, and desire, to achieve progress in the
    future. RDA . . . also . . . repudiated its duty to perform . . . the extraction of H-
    piles broken during earlier removal attempts.
    DX 636 at 1.
    On February 1, 2013, RDA insisted that “progress ha[d] been limited due to obstructions,
    and the [G]overnment’s failure to act in good faith and to utilize the partnering agreement to get
    this project done.” DX 637 at 1.
    On February 21, 2013, a NAVFAC CO terminated the October 13, 2009 Contract for
    default, citing RDA’s failure to perform the necessary contract work and complete the project in a
    timely manner. DX 650 at 1. In addition, RDA was advised that the NAVFAC intended to issue
    a contract modification assessing liquidated damages against RDA. DX 650 at 3. On that date,
    the NAVFAC also contacted RDA’s surety, Great American Insurance Company (“GAIC”),
    demanding that GAIC complete the October 13, 2009 Contract. DX 653 at 1, 11. Subsequently,
    GAIC conducted two underwater surveys of the project site. DX 689; DX 698. Both surveys
    showed that RDA left substantial amounts of debris around the footprint of the demolished wharf.
    DX 689 at 1; DX 698 at 4.
    As a result, on March 18, 2013, RDA filed a Certified Claim stating:
    [p]lease find attached our costs associated with your direction to re-inspect the
    Manitowoc 4100W crane . . . . As RDA believes that NAVFAC direction to re-
    inspect the crane to be unreasonable and exceed contract requirements we are
    hereby filing our Notification of Claim.
    DX 677 at 114–15.
    R.      On July 3, 2013, RDA Construction Corp. Filed A Second Certified Claim.
    On July 3, 2013, RDA filed a second certified claim alleging that the NAVFAC: delayed
    contract performance (DX 691 at 19–29); failed to award RDA time extensions for delays caused
    by the NAVFAC (DX 691 at 21); unilaterally modified the October 13, 2009 Contract (DX 691 at
    21–25); and wrongfully terminated the October 13, 2009 Contract (DX 691 at 30). This conduct
    breached the October 13, 2009 Contract and entitled RDA to recover $1,625,258 in unanticipated
    costs and $718,059 in lost profits. DX 691 at 9, 30–31. The July 3, 2013 Certified Claim also
    alleged that RDA was not liable for liquidated damages, but entitled to recover $294,705 that the
    NAVFAC wrongfully withheld from RDA. DX 691 at 13, 31.
    28
    On September 26, 2013, the NAVFAC CO determined that RDA’s July 3, 2013 Certified
    Claim failed to identify a specific basis for each of the claimed items and was invalid. DX 695 at
    2. The CO also determined that, even if the July 3, 2013 Certified Claim was valid, the NAVFAC
    was only liable for PCO 46, “Revised Base Access Requirements.” DX 695 at 2. In a separate
    letter, also dated September 26, 2013, the NAVFAC CO decided that RDA was entitled to
    $11,162.99, because the NAVFAC changed policies regarding base access, causing RDA to incur
    the cost of “new access badges for its employees[.]” DX 696 at 1.
    On December 20, 2013, the NAVFAC entered into a Tender Agreement with RDA’s
    surety, GAIC. DX 700. Under the Agreement, GAIC tendered Haskell Company (“Haskell”) to
    complete the October 13, 2009 Contract for $4,707,353. DX 700 at 4. The NAVFAC would pay
    Haskell the remaining contract balance of $1,932,415.76 and GAIC would cover the remaining
    $2,774,937.24. DX 700 at 4.
    On March 4, 2014, Haskell and the NAVFAC executed a contract for completion of the
    remaining work under RDA’s October 13, 2009 Contract. DX 702 at 2. Haskell’s March 4, 2014
    Contract had a completion date of November 30, 2014. DX 702 at 6.
    S.      On April 15, 2015, The Naval Facility Command’s Contracting Officer
    Determined That RDA Construction Corp. Was Liable For Liquidated
    Damages.
    On April 15, 2015, the NAVFAC CO also determined that RDA was liable for $2,581,161
    in liquidated damages. DX 711 at 1. The CO, however, credited RDA $11,162.99 for PCO 46
    and $294,705 for outstanding compensation that the NAVFAC withheld from RDA as partial
    payment of the assessed liquidated damages. DX 711 at 1. As a result, the CO determined that
    RDA owed the NAVFAC $2,275,293.01 in liquidated damages. DX 711 at 1.
    II.    PROCEDURAL HISTORY.
    After three years of discovery before Judge Allegra, on May 7, 2015, RDA filed a Second
    Amended Complaint (“5/7/15 Sec. Am. Compl. at ¶¶ 1–134”), alleging that:
    (1)     the NAVFAC breached its duty to disclose material information regarding the
    extreme deterioration of the Wharf, that was known by the NAVFAC and
    unavailable to RDA (“Count I”);
    (2)     RDA encountered latent site conditions that materially differed from the conditions
    described in the Contract (“Count II”);
    (3)     the NAVFAC knew that the site conditions materially differed from the condition
    described in the Contract, but negligently and/or intentionally withheld that
    information (“Count III”);
    (4)     the NAVFAC affirmatively misrepresented the purpose of the Contract and the
    actual conditions of the Wharf (“Count IV”);
    (5)     the NAVFAC breached the Contract (“Count V”);
    29
    (6)    the CO’s administration of contract work was arbitrary and capricious (“Count
    VI”);
    (7)     the NAVFAC acted “willfully, intentionally, and in bad faith,” when it withheld
    decisions, created obstructions, failed to timely approve requests for information
    and changes, and wrongfully terminated the Contract (“Count VII”);
    (8)    the NAVFAC breached the Covenant of Good Faith and Fair Dealing (“Count
    VIII”); and
    (9)    the CO’s determination that the NAVFAC was entitled to liquidated damages for
    delays caused by RDA and to retain $294,705 in partial payment thereof, was
    “improper, unjustifiable, unsupported by the contract documents, and in bad faith”
    (“Count IX”).
    ECF No. 44, 5/7/15 Sec. Am. Compl. at ¶¶ 95–96, 98–99, 101–04, 106–07, 109–14, 116–18, 120–
    22, 124–27, 129–34.
    On June 12, 2015, the Government filed an Answer to RDA’s May 7, 2015 Second
    Amended Complaint (“6/12/15 Gov’t Answer”) asserting three affirmative defenses: (1) part, or
    all, of RDA’s claims are barred by release, waiver, accord and satisfaction, or estoppel; (2) RDA
    assumed the risk that its site investigation, as well as its chosen means and methods during
    performance, would be inadequate; and (3) to the extent RDA is entitled to any recovery, it must
    be offset by amounts that RDA owes the NAVFAC. ECF No. 46, 6/12/15 Gov’t Answer at ¶¶
    136–38.
    In addition, the June 12, 2015 Answer contained four counterclaims, alleging that the
    Government is entitled to:
    (1)    $2,275,293.01 in liquidated damages, because RDA failed to finish performance of
    the October 13, 2009 Contract by the completion date (“Counterclaim I”);
    (2)    $82,974.70, under the CDA’s anti-fraud provision, 
    41 U.S.C. § 7103
    (c)(2), because
    RDA misrepresented facts related to items claimed in the July 3, 2013 Certified
    Claim (“Counterclaim II”);
    (3)    forfeiture of RDA’s July 3, 2013 Certified Claim, pursuant to 
    28 U.S.C. § 2514
    ,
    because that claim contained false statements (“Counterclaim III”); and
    (4)    $231,000, under the False Claims Act, 
    31 U.S.C. §§ 3729
    –3733, because RDA
    knowingly submitted twenty invoices to the NAVFAC that contained false
    representations (Counterclaim IV”).
    6/12/15 Gov’t Answer ¶¶ 174–90.
    *      *       *
    30
    On June 23, 2015, this case was reassigned to the undersigned judge. ECF Nos. 47–48.
    On July 14, 2015, the court issued an Order, setting the deadline for RDA’s Answer to the
    Government’s June 2, 2015 Counterclaims for July 24, 2015. ECF No. 50. In addition, the court
    set a trial date to be held in Boston, Massachusetts commencing on November 16, 2015. ECF
    No. 50.
    On July 24, 2015, RDA filed an Answer to the counterclaims alleged in the Government’s
    June 12, 2015 Answer (“7/24/15 Pl. Answer”), asserting ten affirmative defenses:
    (1)     The Government’s counterclaims fail to state a claim upon which relief can be
    granted (“Affirmative Defense I”);
    (2)     the Government is estopped from recovering damages from RDA (“Affirmative
    Defense II”);
    (3)     the Government’s counterclaims are barred by the principle of waiver
    (“Affirmative Defense III”);
    (4)     the Government’s counterclaims are barred by the doctrine of unclean hands
    (“Affirmative Defense IV”);
    (5)     the Government’s counterclaims are based on statements or conduct that the
    NAVFAC approved or ratified (“Affirmative Defense V”);
    (6)     to the extent that any of the circumstances alleged by the Government occurred, the
    Government is barred from recovery, because these facts were caused by the
    NAVFAC (“Affirmative Defense VI”);
    (7)     the NAVFAC did not rely upon the misrepresentations alleged in the Government’s
    counterclaims (“Affirmative Defense VII”);
    (8)     the Government did not plead any fraud counterclaim with specificity, as required
    by law (“Affirmative Defense VIII”);
    (9)     the Government’s counterclaims are barred, because RDA did not knowingly
    submit any false claims to the NAVFAC for payment or approval (“Affirmative
    Defense IX”); and
    (10)    the Government’s counterclaims are barred, because RDA never made an
    actionable misrepresentation, nor did it knowingly make any false statement, record
    or other representation material to any claim (“Affirmative Defense X”).
    ECF No. 51, 7/24/15 Pl. Answer at 6–8.
    In addition, RDA “reserve[d] the right to prove such other and further affirmative defenses
    as are disclosed in discovery . . . and through evidence offered at the trial of this action.” 7/24/15
    Pl. Answer at 8.
    31
    On September 21, 2015, the parties filed a Joint Status Report requesting a pretrial
    schedule. ECF No. 53. On September 29, 2015, the parties filed their respective Preliminary
    Witness Lists. ECF Nos. 54–55. On October 7, 2015, the court issued a Scheduling Order, setting
    an Initial Pretrial Conference for October 21, 2015. ECF No. 58.
    On October 16, 2015, the Government filed a Motion To Dismiss (“Gov’t Mot.”), pursuant
    to Rule of the United States Court of Federal Claims (“RCFC”) 12(b)(1), arguing that, under the
    Contract Disputes Act, 
    41 U.S.C. §§ 7101
    –09, the court does not have jurisdiction to adjudicate
    claims alleged in the May 7, 2015 Second Amended Complaint, because it did not identify the
    relief sought by RDA. ECF No. 59. Specifically, paragraph ninety-two of the Second Amended
    Complaint (ECF No. 59 at 6–7) includes six items that RDA failed to submit to the NAVFAC CO
    in a certified claim or that contradicted the RDA’s certified claim. ECF No. 59 at 7–9.
    On November 3, 2015, the Government filed a Witness List. ECF No. 60. On November
    4, 2015, RDA filed a Witness List. ECF No. 61. That same day, the court issued a Pre-Trial
    Scheduling Order, stating that the court would resume trial from November 16, 2015 to November
    19, 2015. ECF No. 62. On November 10, 2015, the parties filed their respective Exhibit Lists.
    ECF Nos. 63–67. On November 11, 2015, RDA filed a Response to the Government’s October
    16, 2015 Motion To Dismiss (“Pl. Resp.”), arguing that the court has jurisdiction to adjudicate all
    the claims alleged in the May 7, 2015 Second Amended Complaint, because RDA submitted each
    of these claims to the NAVFAC CO prior to filing the May 7, 2015 Second Amended Complaint
    in the United States Court of Federal Claims. ECF No. 68, Pl. Resp. at 1. On November 12, 2015,
    the court issued an Order denying the October 16, 2015 Motion To Dismiss, pending trial. ECF
    No. 69. The same day, the Government filed a Pre-Trial Brief. ECF No. 70. On November 15,
    2015, RDA filed a Revised Exhibit List. ECF No. 71.
    On November 16–19, 2015, the court presided over trial in Boston, Massachusetts (TR at
    1–1141). ECF Nos. 73, 75, 77, 79. On December 4, 2015, RDA filed a Consent Motion For Leave
    To File Deposition Transcripts Of Jonathan Peters And Marc Nicolazzo that the court granted.
    ECF Nos. 80. On December 5, 2015, RDA filed the deposition testimony of Jonathan Peters and
    Marc Nicolazzo. ECF Nos. 81–84. On December 7–10, 2015 the court resumed trial in Boston,
    Massachusetts (TR at 1142–2470). ECF Nos. 87, 89, 91, 93. The court also instructed the
    Government to produce several documents for which the Government claimed privilege for in
    camera review. TR at 1257. On December 17, 2015, the Government filed a Notice Of In Camera
    Submission. ECF No. 85. On January 4–6, 2016, the court resumed trial in Washington, D.C.
    ECF Nos. 97, 99, 101; TR at 2471–2759.
    On March 4, 2016, the parties filed a Joint Status Report. ECF No. 102. Therein, RDA
    explained that, during trial, the Government raised concerns that some of RDA’s damages claims
    were not supported by financial records. ECF No. 102 at 1. In response, RDA engaged an
    accountant to analyze company records and prepare an expert report on RDA’s damages. ECF
    No. 102 at 1. RDA requested that the court schedule a hearing to conclude the trial and allow
    RDA leave to file a Third Amended Complaint. ECF No. 102 at 2–3. The Government agreed
    that the court should schedule a date to conclude the trial, but opposed RDA’s motion. ECF No.
    102 at 3–4. On March 16, 2016, the court issued an Order, instructing the parties that trial would
    resume on July 11–12, 2016. ECF No. 103. On July 8, 2016, RDA filed a Motion To Bifurcate.
    ECF No. 104. On July 11, 2016, trial resumed in Washington D.C. ECF No. 108, (TR at 2760–
    32
    854). At that time, the court instructed the parties to draft a proposed scheduling order to conclude
    the case. TR at 2852. On July 12, 2016, the court denied RDA’s July 8, 2016 Motion To Bifurcate.
    On July 18, 2016, the court issued a Scheduling Order, instructing RDA to provide the
    Government with an expert report from RDA’s accountant, Michael Brander, by July 30, 2016.
    ECF No. 106. In addition, the court instructed the parties to file a Joint Status Report, proposing
    a schedule for further proceedings, by August 12, 2016. ECF No. 106.
    On August 12, 2016, the parties filed a Joint Status Report, in which they proposed
    different schedules. ECF No. 109. RDA proposed that the court re-open discovery on damages;
    the Government requested that the court conclude the trial and issue a post-trial briefing schedule.
    ECF No. 109 at 1–2, 4.
    On August 16, 2016, the court convened a Status Conference, wherein the court stated that,
    “in light of the parties’ disputed issues [over damages,] . . . the Court has decided to . . . bifurcate
    [this case] and [first] issue a liability decision.” ECF No. 113, 8/16/2016 TR at 11. On August
    19, 2016, the parties filed a Joint Status Report, representing that
    the parties agree that the most efficient way to proceed at this point will be to
    bifurcate plaintiff’s damages case and proceed with briefing as to liability regarding
    plaintiff’s claims. This briefing would also include post-trial briefing on
    defendant’s counterclaims, for which there is no need for bifurcation, such that
    briefing on defendant’s counterclaims would address both liability and quantum.
    ECF No. 110. That same day, the court issued a Briefing Schedule, instructing the parties to submit
    Post-Trial Briefs by October 5, 2016; any Post-Trial Response Briefs were due by November 4,
    2016. ECF No. 111.
    On October 18, 2016, RDA filed an Unopposed Motion To Modify The Briefing Schedule.
    ECF No. 118. On October 19, 2016, the court granted the October 18, 2016 Motion. ECF No.
    119. Pursuant to the modified briefing schedule, on November 8, 2016, the parties filed Post-Trial
    Briefs (“Pl. PT Br.” and “Gov’t PT Br.”). ECF Nos. 120–21. On January 23, 2017, the parties
    filed Post-Trial Response Briefs (“Pl. PT Resp.” and “Gov’t PT Resp.”). ECF Nos. 129–30.
    On April 18, 2017, the court instructed the parties to file a Draft Order, identifying all of
    the Exhibits and Demonstratives admitted into evidence in this case. On May 17, 2017, the parties
    submitted the Draft Order, attached hereto as Court Exhibit A.
    III.   DISCUSSION.
    A.      Jurisdiction.
    The Tucker Act authorizes the United States Court of Federal Claims with jurisdiction to
    adjudicate any claim that: (1) arises under the Contract Disputes Act (“CDA”), 
    41 U.S.C. §§ 7101
    –
    7109; and (2) has been submitted to the relevant CO for a final decision. See 28 U.S.C. 1491(a)(2)
    (“The [United States] Court of Federal Claims shall have jurisdiction to render judgment upon any
    claim by or against, or dispute with, a contractor arising under section 7104(b)(1) of title 41 . . .
    on which a decision of the [CO] has been issued[.]”).
    33
    1.      Whether The Claims Alleged In The May 7, 2015 Second Amended
    Complaint Arise Under The Contract Disputes Act.
    A claim “arises under” the CDA if it is based on
    any express or implied contract . . . made by an executive agency for-- (1) the
    procurement of services, other than real property in being; (2) the procurement of
    services; (3) the procurement of construction, alteration, repair, or maintenance of
    real property; or (4) the disposal of personal property.
    
    41 U.S.C. § 7102
    (a).
    The May 7, 2015 Second Amended Complaint alleges nine claims that are based on the
    October 13, 2009 Contract between the NAVFAC and RDA to improve a wharf at Newport Naval
    Station. Sec. Am. Compl. at ¶¶ 1–134. For this reason, the court has determined that the claims
    alleged in the May 7, 2015 Second Amended Complaint arise under the CDA.
    2.      Whether The Claims Alleged In The May 7, 2015 Second Amended
    Complaint Were Submitted To The Contracting Officer For A Final
    Decision.
    The CDA provides that “[e]ach claim by a contractor against the Federal Government
    relating to a contract shall be submitted to the [CO] for a decision.” 41 U.S.C § 7103(a)(1)
    (emphasis added). For this reason, the United States Court of Appeals for the Federal Circuit has
    held that CDA “jurisdiction . . . requires both a valid claim and a [CO’s] final decision on that
    claim.” M. Maropakis Carpentry, Inc. v. United States, 
    609 F.3d 1323
    , 1327 (Fed. Cir. 2010).
    The CDA, however, does not define the term “claim.” Id at 1327. Therefore, the court
    “look[s] to the FAR implementing the CDA for the definition [of that term].” 
    Id.
     (citing
    Reflectone, Inc. v. Dalton, 
    60 F.3d 1572
    , 1575 (Fed. Cir. 1995) (en banc)). According to the FAR,
    a “claim” is “a [non-routine,] written demand or written assertion by one of the contracting parties
    seeking, as a matter of right, the payment of money in a sum certain, the adjustment or
    interpretation of contract terms, or other relief arising under or relating to the contract.” 
    48 C.F.R. § 52.233-1
    .
    A claim under the CDA also must contain “a clear and unequivocal statement that gives
    the [CO] adequate notice of the basis and amount of the claim.” Contract Cleaning Maint., Inc. v.
    United States, 
    811 F.2d 586
    , 592 (Fed. Cir. 1997). A claim also must “indicate to the [CO] that
    the [plaintiff] is requesting a final decision.” See M. Maropakis Carpentry, 
    609 F.3d at 1327
    . In
    addition,
    [f]or claims of more than $100,000 made by a contractor, the contractor shall certify
    that--
    (A) the claim is made in good faith;
    (B) the supporting data are accurate and complete to the best of the contractor’s
    knowledge and belief;
    34
    (C) the amount requested accurately reflects the contract adjustment for which
    the contractor believes the Federal Government is liable; and
    (D) the certifier is authorized to certify the claim on behalf of the contractor.
    
    41 U.S.C. § 7103
    (b)(1).
    If a the plaintiff submits a valid CDA claim, the CO has sixty days to issue a decision or
    notify the plaintiff of the time within which a decision will be issued. See 
    41 U.S.C. §§ 7103
    (f)(1)–
    (2). The CO’s failure “to issue a decision on a claim within the required time period is deemed to
    be a decision by the [CO] denying the claim and authoriz[ing] an appeal or action on the claim[.]”
    
    41 U.S.C. § 7103
    (f)(5).
    In addition, “[a]n action brought before the [United States] Court of Federal Claims under
    the CDA must be ‘based on the same claim previously presented to and denied by the [CO].’”
    Scott Timber Co. v. United States, 
    333 F.3d 1358
    , 1365 (Fed. Cir. 2003) (quoting Cerberonics,
    Inc. v. United States, 
    13 Cl. Ct. 415
    , 417 (1987)). “This standard, however, does not require rigid
    adherence to the exact language or structure of the original administrative CDA claim [when
    different claims] arise from the same operative facts, [and] claim essentially the same relief, and
    merely assert differing legal theories for that recovery.” Scott Timber, 
    333 F.3d at 1365
    .
    a.     Regarding Counts I–IV.
    On April 21, 2010, prior to filing this lawsuit, RDA submitted a certified claim to the
    NAVFAC CO requesting an equitable adjustment for costs that RDA did not anticipate, because
    the NAVFAC failed to disclose the Appledore Report and FST Report. DX 118 at 1–3. The April
    21, 2010 Certified Claim specified that the equitable adjustment was related to “the 2005 Marginal
    Wharf Inspection Report,” i.e., the Appledore Report (DX 118 at 1), and provided a detailed
    breakdown of the costs RDA sought to recover (DX 118 at 4–5), providing the NAVFAC CO
    “adequate notice of the basis and amount of the claim.” Contract Cleaning, 811 F.2d at 592. On
    August 31, 2010, the NAVFAC CO denied RDA’s April 21, 2010 Certified Claim.
    Counts I–IV of the May 7, 2015 Second Amended Complaint allege that RDA is entitled
    to damages for the NAVFAC’s failure to disclose that the Newport Naval Station wharf could not
    support the weight of construction equipment under four different legal theories: (1) the NAVFAC
    violated its duty to disclose “superior knowledge” regarding the wharf’s deteriorated condition;
    (2) the October 13, 2009 Contract’s differing site conditions clause entitles RDA to an equitable
    adjustment; (3) the NAVFAC affirmatively misrepresented the condition of the Newport Naval
    Station wharf; and (4) the NAVFAC misrepresented the purpose of the project. 5/7/15 Sec. Am.
    Compl. at ¶¶ 94–107.
    The April 21, 2010 Certified Claim and Counts I–IV of the May 7, 2015 Second Amended
    Complaint “assert differing legal theories for . . . recovery.” Scott Timber, 
    333 F.3d at 1365
    . But,
    they “arise from the same operative facts, [and] claim essentially the same relief.” 
    Id.
     Therefore,
    Counts I–IV of the May 7, 2015 Second Amended Complaint are “based on the same claim
    previously presented to and denied by the [CO].” 
    Id.
    35
    For these reasons, the court has determined that it has jurisdiction to adjudicate Counts I–
    IV of the May 7, 2015 Second Amended Complaint.
    b.      Regarding Counts V–IX.
    On July 3, 2013, RDA submitted a second Certified Claim to the NAVFAC CO alleging
    that the NAVFAC: delayed contract performance (DX 691 at 19–29); failed to award RDA time
    extensions for delays caused by the NAVFAC (DX 691 at 21); unilaterally modified the October
    13, 2009 Contract (DX 691 at 21–25); and wrongfully terminated the October 13, 2009 Contract
    (DX 691 at 30). This conduct breached the October 13, 2009 Contract and entitled RDA to recover
    $1,625,258 in unanticipated costs and $718,059 in lost profits. DX 691 at 9, 30–31. The July 3,
    2013 Certified Claim also alleged that RDA was not liable for liquidated damages and owed
    $294,705 that the NAVFAC withheld in partial payment of those liquidated damages. DX 691 at
    13, 31. The court has determined that the July 3, 2013 Certified Claim properly was submitted to
    the CO for a final decision and provided notice of the basis and amount of the claim alleged. See
    Contract Cleaning, 811 F.2d at 592. On September 26, 2013, the CO denied the July 3, 2013
    Certified Claim. DX 695.
    Count V of the May 7, 2015 Second Amended Complaint alleges that the NAVFAC
    breached the October 13, 2009 Contract by: causing unnecessary delays, imposing requirements
    on RDA beyond the terms of the contract; failing to compensate RDA for the time and cost of
    changes to the project; failing to conduct “partnering sessions,” and wrongfully terminating the
    October 13, 2009 Contract. 5/7/15 Sec. Am. Compl. at ¶¶ 111–14. Based on the same operative
    facts as Count V, Counts VI–IX allege that the NAVFAC’s administration and ultimate
    termination of the October 13, 2009 Contract was arbitrary and capricious and violated the
    NAVFAC’s duty of good faith and fair dealing. 5/7/15 Sec. Am. Compl. at ¶¶ 115–27.
    The July 3, 2013 Certified Claim and Counts V–IX of the May 7, 2015 Second Amended
    Complaint arise from the same operative facts and seek essentially the same relief. Therefore,
    Counts V–IX are “based on the same claim[s] previously presented to and denied by the [CO].”
    Scott Timber, 
    333 F.3d at 1365
    .
    For these reasons, the court has determined that it has jurisdiction to adjudicate Counts V–
    IX of the May 7, 2015 Second Amended Complaint.
    c.      Regarding Damages.
    On October 16, 2015, the Government filed a Motion To Dismiss for lack of subject matter
    jurisdiction, pursuant to RCFC 12(b)(1). Gov’t Mot. at 1. Therein, the Government argued that
    paragraph ninety-two of the May 7, 2015 Second Amended Complaint contained a table,
    identifying the components of RDA’s total damages, but RDA did not properly submit some of
    those components to the NAVFAC CO. Gov’t Mot. at 7–9. On November 12, 2015, the court
    denied the October 16, 2015 Motion To Dismiss, pending trial in this case. ECF No. 69.
    On November 8, 2016, after trial concluded, the Government filed a Post Trial Brief
    arguing that “[a]t trial, it remained RDA’s burden to prove that the [c]ourt ha[d] jurisdiction to
    grant the relief [RDA] seeks in its [May 7, 2015] second amended complaint.” Gov’t PT Br. at
    74; see also Fanning, Phillips, Molnar v. West, 
    160 F.3d 717
    , 720 (Fed. Cir. 1998) (“Federal courts
    36
    are not courts of general jurisdiction[.] We therefore have a special obligation to satisfy ourselves
    of our own jurisdiction.” (internal citations omitted)).
    The components listed in paragraph ninety-two of the May 7, 2015 Second Amended
    Complaint are not separate claims; instead, they specify the amount of damages requested under
    Counts I–VIII. Because the court has jurisdiction to adjudicate the subject matter of Counts I–
    VIII, the court has determined that it also has jurisdiction to determine any damages arising from
    those claims.
    B.      Standing.
    The United States Supreme Court has held that “the question of standing is whether the
    litigant is entitled to have the court decide the merits of the dispute or of particular issues.”
    Warth v. Seldin, 
    422 U.S. 490
    , 498 (1975). Standing must be determined “as of the
    commencement of suit[.]” Rothe Dev. Corp. v. Dep’t of Def., 
    413 F.3d 1327
    , 1334 (Fed. Cir. 2005)
    (quoting Lujan v. Defs. of Wildlife, 
    504 U.S. 555
    , 570 n.5 (1992)). “The party invoking federal
    jurisdiction bears the burden of establishing [standing].” Lujan, 
    504 U.S. at 560
    . The United States
    Supreme Court held in Friends of the Earth, Inc. v. Laidlaw Envtl. Serv., Inc., 
    528 U.S. 167
     (2000),
    that to establish standing
    a plaintiff must show (1) it has suffered an ‘injury in fact’ that is (a) concrete and
    particularized and (b) actual or imminent, not conjectural or hypothetical; (2) the
    injury is fairly traceable to the challenged action of the defendant; and (3) it is
    likely, as opposed to merely speculative, that the injury will be redressed by a
    favorable decision.
    
    Id.
     180–81.
    In addition, “[t]o have standing to sue the sovereign on a contract claim, a plaintiff must
    be in privity of contract with the United States.” Anderson v. United States, 
    344 F.3d 1343
    , 1351
    (Fed. Cir. 2003). In other words, the contract in question must be between the plaintiff and the
    Government. See Ransom v. United States, 
    900 F.2d 242
    , 244 (Fed. Cir. 1990) (“To maintain a
    cause of action pursuant to the Tucker Act that is based on a contract, the contract must be between
    the plaintiff and the [G]overnment.”).
    The May 7, 2015 Second Amended Complaint alleges that RDA suffered monetary injury
    that is concrete, particularized, and fairly traceable to the NAVFAC’s actions. And, any financial
    injury established by RDA can be redressed by a monetary award. Moreover, it is undisputed that
    RDA was a signatory and intended beneficiary of the October 13, 2009 Contract. 5/7/15 Sec. Am.
    Compl. at ¶ 5 (“On or about September 14, 2009, RDA entered contract No. N40085-09-C-7002
    P469 . . . with the Government[.]”); 6/12/15 Gov’t Answer at ¶ 5 (“Admits the allegations
    contained in paragraph 5[.]”). Therefore, RDA is in privity of contract with the Government.
    For these reasons, the court has determined that RDA has standing to seek an adjudication
    of the claims alleged in the May 7, 2015 Second Amended Complaint.
    37
    C.      The Claims Alleged In RDA Construction Corp.’s May 7, 2015 Second
    Amended Complaint.
    1.      Count I: Whether The Naval Facilities Command Had A Duty To
    Disclose The Appledore Report And The Fay, Spofford & Thorndike
    Report.
    a.      Plaintiff’s Argument.
    RDA argues that, under the “superior knowledge doctrine,” a contracting agency has an
    “implied duty” to advise contractors of “otherwise unavailable information regarding some novel
    matter affecting the contract that is vital to its performance.” Pl. PT Br. at 47 (quoting Scott Timber
    Co., 692 F.3d at 1373). In this case, the NAVFAC violated the duty to disclose, because:
    (1)     the Appledore Report concluded that the wharf could not support the weight of
    demolition equipment, a fact that would and did affect the cost and duration of
    performance (Pl. PT Br. at 48);
    (2)     the NAVFAC was aware of the wharf’s deterioration and knew that this condition
    could only be observed during an underwater inspection (Pl. PT Br. at 48–49);
    (3)     the Solicitation did not mention that the wharf, supporting H-piles and bulkhead
    were in poor condition; instead the specification stated that RDA could locate
    demolition equipment throughout the wharf (Pl. PT Br. at 49); and
    (4)     the NAVFAC did not advise RDA about the existence of the Appledore Report or
    the FST Report or conclusions therein until after the parties had signed the October
    13, 2009 Contract (Pl. PT Br. at 48).
    In sum, the NAVFAC’s violation of the implied duty to disclose the Appledore Report and
    FST Report was a material breach of the October 13, 2009 Contract that adversely affected RDA’s
    ability to perform. Pl. PT Br. at 50. Therefore, the court should convert the NAVFAC’s February
    21, 2013 decision to terminate the October 13, 2009 Contract for default to a termination for
    convenience.
    b.       The Government’s Response.
    The Government responds that it had no duty to disclose either the Appledore Report or
    FST Report, nor did the Solicitation mislead RDA about the conditions of the Newport Naval
    Station wharf and, in any event, RDA was on notice to inquire about those conditions. Gov’t PT
    Br. at 76. The Solicitation informed RDA that, since the wharf was constructed in the 1950s RDA
    was on notice that the wharf, “was likely not in good condition.” Gov’t PT Br. at 77. In addition,
    structural problems were identified in Solicitation documents and apparent during the June 4, 2009
    and June 11, 2009 site visits. Gov’t PT Br. at 77 (citing DX 729 at 5 (Helmes Direct) (“Contract
    Drawings showing the existing bulkhead identify a number of sinkholes which clearly indicate an
    unstable condition[.]”)). Moreover, during the bidding process, RDA did not ask the NAVFAC
    any questions about the condition of the wharf. Gov’t PT Br. at 77 (citing TR at 1474 (Kelley)).
    38
    Nor did RDA perform an independent analysis of the wharf’s load capacity by a professional
    engineer that would have revealed
    (1) that the wharf deck slab would have been unable to safely accommodate the
    loads of even a very lightweight excavator, (2) that the wharf structure would have
    collapsed under its own weight once the restraint provided by the connection to the
    landside was removed, and (3) that the existing steel sheet pile wall would have
    failed as the rip rap was removed, which had to occur before the king piles for the
    new bulkhead wall could be installed.
    Gov’t PT Br. at 77–78 (citing DX 728 (Cohen Direct)).
    More importantly, RDA’s plan to perform parts of the bulkhead construction from the
    wharf was inconsistent with the Solicitation’s instruction that the wharf must be completely
    demolished before work could commence on the bulkhead. Gov’t PT Br. at 78 (citing DX 1 at 83
    (“CONCRETE APRON & PILES TO BE DEMOLISHED PRIOR TO REMOVAL OF ROCK
    FILL.”); and DX 1 at 414 (“Any excavation [of rock fill] required within the area where sheet
    pilings are to be installed shall be completed prior to placing sheet pilings.”)).
    c.      Plaintiff’s Reply.
    RDA replies that the severe structural deterioration of the wharf and bulkhead were not
    apparent during the June 4 and June 11, 2009 site visits. Pl. PT Resp. at 3–4. The wharf showed
    some signs of wear-and-tear, but was well-preserved for its age. Pl. PT Resp. at 3.
    In addition, RDA’s demolition plan was consistent with the Solicitation. Pl. PT Br. at 8.
    Although the Solicitation required RDA to demolish sections of the wharf, before removing the
    rip rap beneath, it did not necessarily require RDA to demolish the entire wharf before
    commencing any rip rap removal. Pl. PT Resp. at 9. Moreover, the Solicitation did not expressly
    prohibit RDA from placing equipment on the wharf. Pl. PT Resp. at 9. Therefore, RDA’s plan to
    demolish the inboard portion of the wharf using equipment located on the wharf, did not conflict
    with the Solicitation. Pl. PT Resp. at 9.
    Furthermore, it is undisputed that the NAVFAC knew about the Appledore Report and FST
    Report before issuing the Solicitation and understood their importance to the cost of the project.
    Pl. PT Resp. at 8. But, the NAVFAC did not include or refer to either report or their findings in
    the Solicitation. Pl. PT Resp. at 8. This was a conscious attempt to mislead prospective bidders.
    Pl. PT Resp. at 10.
    d.      The Court’s Resolution.
    It is well established that “the contractor in a fixed-price contract assumes the risk of
    unexpected costs.” ITT Arctic Servs., Inc. v. United States, 
    524 F.2d 680
    , 691 (Ct. Cl. 1975); see
    also Helene Curtis Indus., Inc. v. United States, 
    312 F.2d 774
    , 778 (Ct. Cl. 1963) (“Where the
    Government . . . has no duty to disclose information, and does not improperly interfere with
    performance, the fixed-price contractor of course bears the burden of unanticipated increases in
    cost[.]”). Under the superior knowledge doctrine, however, the Government has “an implied duty
    to disclose to a contractor otherwise unavailable information regarding some novel matter
    39
    affecting the contract that is vital to its performance.” Giesler v. United States, 
    232 F.3d 864
    , 876
    (Fed. Cir. 2000).
    A contracting agency violates the implied duty to disclose “superior knowledge” if:
    (1) a contractor undertakes to perform [the contract] without vital knowledge of a
    fact that affects performance costs or duration, (2) the government was aware the
    contractor had no knowledge of and had no reason to obtain such information,
    (3) any contract specification supplied misled the contractor or did not put it on
    notice to inquire, and (4) the government failed to provide the relevant information.
    Hercules Inc. v. United States, 
    24 F.3d 188
    , 196 (Fed. Cir. 1994). The plaintiff bears the burden
    of establishing each element by “specific evidence.” See GAF Corp. v. United States, 
    932 F.2d 947
    , 949 (Fed. Cir. 1991).
    Regarding the first and fourth elements, Mr. Hartman, RDA’s Project Manager, and Mr.
    Wood, RDA’s Estimator, testified that RDA was unaware of any load restrictions on the wharf
    until November 2009, approximately one month after the parties executed the October 13, 2009
    Contract. TR at 106–07 (Wood); TR at 188–89 (Hartman). Mr. Germano, the NAVFAC
    Construction Manager, confirmed that the NAVFAC did not disclose that the wharf was subject
    to severe load restrictions until November 18, 2009. TR at 2256–60 (Germano). Therefore, the
    court finds that RDA undertook to perform the October 13, 2009 Contract without “vital
    knowledge” of a fact that affected performance costs and duration. See Hercules, 
    24 F.3d at 196
    (element one). And, the NAVFAC failed to provide that information before contract formation.
    See Hercules, 
    24 F.3d at 196
     (element four).
    Regarding the second element, RDA argues that bidders only could have learned of the
    wharf’s load restriction from: (1) the Solicitation; or (2) the June 4 and June 11, 2009 site visits.
    Pl. PT Resp. at 8. The NAVFAC knew that the Solicitation did not provide a load restriction for
    the wharf. Pl. PT Br. at 48. The NAVFAC also knew that the deterioration jeopardizing the
    wharf’s structural integrity “could only be observed during [an] underwater investigation.” Pl. PT
    Br. at 48 (quoting PX 12 at 21 (Appledore Report)).
    RDA’s argument assumes that bidders could only ascertain that the wharf was subject to a
    load restriction by directly observing the wharf’s subsurface deterioration. But, this assumption is
    rebutted by evidence showing that there were other indicia of the wharf’s limited load capacity
    visible during the June 4 and June 11, 2009 site visits. For example, orange sawhorses and concrete
    barriers lining the perimeter of the wharf indicated that vehicles could not drive there. In addition,
    large sinkholes running along most of the wharf and bulkhead suggested that the land around the
    wharf was not stable. DX 729 at 5, 8 (Helmes Direct).
    40
    DX 742.10 (photograph of the wharf taken on May 19, 2008, prior to the June 4 and June 11, 2009
    site visits);
    DX 742.15 (photograph of the wharf taken on June 20, 2008, prior to the June 4 and June 11, 2009
    site visits);
    41
    DX 742.14 (photograph of sinkhole taken on May 30, 2008, prior to the June 4 and June 11, 2009
    site visits); DX 742.6 (photograph of sinkhole taken on May 19, 2008).
    Therefore, although the NAVFAC was aware that RDA had no knowledge of the
    Appledore Report or the FST Reports prior to submitting a bid, the court finds that, from the
    physical condition of the wharf visible on inspection, a contractor would have “reason to obtain
    [additional] information,” such as an independent engineer report or an underwater investigation.
    See Hercules, 
    24 F.3d at 196
     (element two). Accordingly, RDA’s superior knowledge claim fails
    under the second element.
    Regarding the third element, RDA argues that the Solicitation affirmatively misrepresented
    that the wharf could support the weight of cranes and excavators by instructing prospective
    contractors to “[l]ocate demolition equipment throughout the structure and remove materials so as
    to not impose excessive loads to framing.” DX 1 at 291. RDA interprets “demolition equipment”
    to include heavy machines like cranes and excavators. Pl. PT Br. at 49. The Solicitation, however,
    does not define that term. Instead, the Solicitation incorporates the American Society of Safety
    Engineer’s 2006 Safety and Health Program Requirements for Demolition Operations (“ASSE
    A10.6”) (DX 1 at 288), which states that the type of demolition equipment that each structure can
    withstand should be determined by the contractor (ASSE A10.6 at §§ 4.1, 5.8).
    The United States Court of Appeals for the Federal Circuit has held that “various contract
    provisions must be read as part of an organic whole, according reasonable meaning to all of the
    contract terms. Such interpretation must assure that no contract provision is made inconsistent,
    superfluous, or redundant.” See Lockheed Martin IR Imaging Sys., Inc. v. West, 
    108 F.3d 319
    , 322
    42
    (Fed. Cir. 1997) (internal citations omitted). In this case, Section 4.1 of the ASSE A10.6, which
    was part of the Solicitation, provides that “[p]rior to starting demolition operations, a written
    engineering survey of the structure shall be made by a qualified person to determine the type and
    condition of the framing, floors and walls so that action can be taken, if needed, to prevent
    premature collapse of any portion of the structure.” ASSE A10.6 at § 4.1 (emphasis added).
    Similarly, Section 5.8 of the ASSE A10.6 cautions that “[t]he use of equipment and storage of
    materials and debris on any floor shall not exceed the allowable floor loads.” ASSE A10.6 at §
    5.8 (emphasis added). Both of these industry standards require that bidders conduct engineering
    due diligence to ensure the load capacity of the relevant structure before placing equipment there.
    RDA also argues that the Solicitation’s failure to provide load restrictions for the wharf
    misled prospective bidders to assume that the wharf was not subject to any significant restrictions
    and could support the weight of heavy construction equipment. Pl. PT Br. at 48–49. Mr. Wood
    testified that, if the Solicitation does not specify the load capacity of a certain structure, it is safe
    to “use [that structure] for its intended purpose.” TR at 106 (Wood). Mr. Wood’s view, however,
    was rebutted by the expert testimony of Philip Helmes, P.E., who observed that, when “[t]he
    Contract Documents do not indicate or provide any safe load limits for the existing structure, . . .
    a responsible contractor would be expected to seek additional information . . . prior to developing
    a work method based on imposing significant loads on the wharf.” DX 729 at 6 (Helmes Direct).
    Mr. Helmes also testified that without “a pre-bid engineer’s assessment . . ., the alleged assumption
    that the bulkhead could support the load from RDA’s intended equipment had no basis and was a
    poor assumption.” DX 729 at 6 (Helmes Direct). There is no evidence that any of the contractors
    were precluded from having an independent professional engineer present during the site visits or
    from conducting an underwater investigation. Therefore, the Solicitation’s instruction to “[l]ocate
    demolition equipment throughout the structure” and the Solicitation’s failure to provide an express
    load restriction for the wharf did not represent that the wharf could withstand heavy construction
    equipment. See Hercules, 
    24 F.3d at 196
     (element three).
    But, even if the Solicitation could be construed as misleading bidders about the wharf’s
    load capacity, RDA’s superior knowledge claim still fails under the third factor, because the
    Solicitation provided bidders with specific notice to inquire about the wharf’s condition. DX 1 at
    34 (incorporating 
    48 C.F.R. § 52.236-3
    (a)).15 RDA justifies the failure to conduct an independent
    inspection, explaining that most of the deterioration affecting the wharf could not be observed
    from the deck’s surface. TR at 189–90 (Hartman). FAR 52.236-3(a), however, requires bidders
    to verify both the surface and subsurface condition of the wharf, relying on: “an inspection of the
    site;” “all exploratory work done by the Government;” and “the drawings and specification made
    15
    FAR 52.236-3(a) requires that:
    The Contractor . . . acknowledges that it has satisfied itself as to the character,
    quality, and quantity of surface and subsurface materials . . . insofar as this
    information is reasonably ascertainable from an inspection of the site, including all
    exploratory work done by the Government, as well as from the drawings and
    specifications made a part of this contract.
    
    48 C.F.R. § 52.236-3
    (a) (emphases added).
    43
    a part of this contract.” 
    48 C.F.R. § 52.236-3
    (a). Therefore, RDA was on notice to inquire about
    the subsurface conditions of the wharf that were not visible during its site visit. See Hercules, 
    24 F.3d at 196
     (element three).
    For these reasons, the court has determined that the NAVFAC did not have a duty to
    disclose the Appledore Report and FST Report prior to accepting RDA’s bid and entering into the
    October 13, 2009 Contract. Accordingly, Count I of the May 7, 2015 Second Amended Complaint
    is dismissed.
    2.      Count II: Whether RDA Construction Corp. Is Entitled To An
    Equitable Adjustment Under The October 13, 2009 Contract’s
    Differing Site Conditions Clause.
    a.      Plaintiff’s Argument.
    RDA argues that the actual deteriorating condition of the wharf and bulkhead was a “type
    1” differing site condition,16 for which RDA is entitled to an equitable adjustment. RDA adds that
    a reasonable person would interpret the Solicitation to allow a contractor to perform work from
    the wharf and the land parallel to the wharf. Pl. PT Br. at 55. RDA’s Estimator testified that, if
    there was a restriction on the wharf’s capacity there would be a corresponding note; if there was
    no note, the structure was usable for its intended purpose. TR at 106 (Mr. Wood). RDA’s
    Construction Manager also testified that, in his experience, load restrictions always are provided
    to bidders. TR at 191–92, 209 (Hartman). In this case, the Solicitation expressly allowed bidders
    to place demolition equipment on the wharf, but to “[l]ocate demolition equipment throughout the
    structure.” DX 1 at 291. In addition, the Solicitation instructed bidders to assume that thirty holes
    in the bulkhead would need repair. Pl. PT Br. at 55 (citing DX 1 at 107). But, RDA’s Engineering
    Consultant testified that this amount of deterioration ordinarily would not prohibit a contractor
    from demolishing the wharf from the landside of the bulkhead or from the wharf deck. TR at 827–
    28 (Martel).
    RDA adds that the actual condition of the existing bulkhead and wharf were not reasonably
    foreseeable, based on the Solicitation and site visits. Pl. PT Br. at 55. RDA’s President, RDA’s
    Estimator, and RDA’s Project Manager “testified credibly that the observable condition of the
    wharf provided no indication that RDA would be unable to employ conventional means to
    demolish and construct this project from the existing structure and from the landside of the
    bulkhead.” Pl. PT Br. at 55.
    In sum, RDA reasonably relied on the Solicitation’s representation about the wharf’s
    condition. Pl. PT Br. at 55 (“RDA’s cost estimate, including its estimate as to the duration of the
    work on this Project, were based on its thorough review of the contract documents and its visual
    inspection of the facility.”). But, the actual conditions of the wharf and bulkhead differed
    16
    The October 13, 2009 Contract includes a “differing site conditions” clause. DX 1 at
    545 (incorporating 
    48 C.F.R. § 52.236-2
    ). “Type 1” differing site conditions are “[s]ubsurface or
    latent physical conditions at the site which differ materially from those indicated in this
    contract[.]” 
    48 C.F.R. § 52.236-2
    (a)(1) (emphasis added).
    44
    materially from the conditions represented in the Solicitation requiring RDA to shift operations to
    the water and incur the cost of deploying a barge for the duration of the project. Pl. PT Br. at 56.
    b.      The Government’s Response.
    The Government responds that RDA did not establish each element of its differing site
    conditions claim. Gov’t PT Resp. at 17.
    c.      The Court’s Resolution.
    To receive an equitable adjustment for a “type 1” differing site condition, a contractor must
    establish that: (1) “a reasonable contractor reading the contract documents as a whole would
    interpret them as making a representation about the site conditions;” (2) “the actual site conditions
    were not reasonably foreseeable to the contractor, with the information available to the particular
    contractor outside the contract documents;” (3) “the particular contractor in fact relied on the
    contract representation;” and (4) “the conditions differed materially from those represented, and
    the contractor suffered damages as a result.” Int’l Tech. Corp. v. Winter, 
    523 F.3d 1341
    , 1348–49
    (Fed. Cir. 2008).
    As to the first element, the United States Court of Appeals for the Federal Circuit has held
    that there cannot be a differing site condition, “unless the contract [affirmatively] indicated what
    that condition would be.” Comtrol, Inc. v. United States, 
    294 F.3d 1357
    , 1363 (Fed. Cir. 2002).
    Whether the contract indicates a particular site condition is a question of contract interpretation,
    requiring the court to “place itself into the shoes of a reasonable and prudent contractor and decide
    how such a contractor would act in interpreting the contract documents.” H.B. Mac, Inc. v. United
    States, 
    153 F.3d 1338
    , 1345 (Fed. Cir. 1998).
    In this case, the Solicitation instructed the contractor to “[l]ocate demolition equipment
    throughout the structure and remove materials so as to not impose excessive loads to framing.”
    DX 1 at 291. RDA argues that this clause affirmatively represented that the wharf could support
    the weight of heavy demolition equipment, such as cranes and excavators. But, other provisions
    of the Solicitation clarified that the contractor was responsible for evaluating each structure to
    determine what type of demolition equipment it could safely withstand. DX 1 at 288 (citing ASSE
    A10.6 § 4.1 (“Prior to starting demolition operations, a written engineering survey of the structure
    shall be made by a qualified person to determine the type and condition of the framing, floors and
    walls so that action can be taken, if needed, to prevent premature collapse of any portion of the
    structure.”) and ASSE A10.6 § 5.8 (“The use of equipment and storage of materials and debris on
    any floor shall not exceed the allowable floor loads.”)). Therefore, the Solicitation did not
    represent that the wharf could support the weight of any demolition equipment, only that the weight
    needed to be balanced throughout the surface of the relevant structure and the concentration of
    heavy equipment on one area of a particular structure could cause it to collapse.
    Moreover, RDA argues that the Solicitation’s failure to provide a load restriction for the
    wharf would lead a reasonable contractor to conclude that the wharf could bear the weight of heavy
    construction equipment. Pl. PT Br. at 54–55. RDA’s Estimator testified that, in his experience,
    “if there is a [load] restriction [associated with a structure], there would be a note [in the
    Solicitation].” TR at 106 (Wood). The absence of a note led him to conclude that “[RDA] could
    45
    utilize the [wharf] to work off of.” TR at 107 (Wood). But, Mr. Wood’s testimony was
    contradicted by RDA’s Project Manager, who testified that he did not draw any conclusion about
    the absence of load restrictions on the wharf, until he read the Appledore Report. TR at 191
    (Hartman). The Government also rebutted Mr. Wood with expert testimony that advised: “a
    prudent contractor would have requested more information regarding the [wharf’s] Safe Load
    Limit” and “[i]t was not reasonable for RDA to assume that the existing structure could support
    heavy construction equipment.” DX 729 at 5 (Helmes Direct). DX 742.6 (photograph of sinkhole
    taken on May 19, 2008, prior to the June 4 and June 11, 2009 site visits.)
    In addition, the Solicitation required prospective bidders to satisfy themselves of “the
    character, quality, and quantity of surface and subsurface materials . . . insofar as this information
    was reasonably ascertainable from an inspection of the site[.]” DX 1 at 34 (incorporating 
    48 C.F.R. § 52.236-3
    (a)). Photographs of the wharf taken prior to RDA’s June 4 and June 11, 2009 site visits
    show orange sawhorses and concrete barriers, cordoning off the wharf. DX 742.14 (photograph
    of wharf taken on May 20, 2008, prior to the June 4 and June 11, 2009 site visits); DX 742.15
    (photograph of wharf taken on June 20, 2008, prior to the June 4 and June 11, 2009 site visits). A
    reasonable and prudent contractor could see that the wharf could not safely bear the weight of
    vehicular traffic, much less heavy construction equipment, regardless of the Solicitation’s silence
    about that issue. Therefore, a reasonable contractor would read the Solicitation, including
    accompanying drawings, the ASSE A10.6 industry standards and observation of the wharf’s
    condition during two site visits, to warrant further investigation into whether the wharf and
    bulkhead could safely bear the weight of demolition equipment.
    RDA counters that a reasonable contractor would interpret the Solicitation’s disclosure of
    thirty holes in the bulkhead as a representation that the bulkhead and wharf had no other significant
    deterioration. But, a statement that the bulkhead contained some deterioration did not
    affirmatively represent that the bulkhead contained only that amount of deterioration. See, Int’l
    Tech. Corp., 523 F.3d at 1350 (“[T]his court [has] held that contract documents stating ‘[h]ard
    material . . . may be encountered’ did not represent that only hard material would be encountered.”
    (quoting Comtrol, 
    294 F.3d at 1362
    )). Moreover, the Government’s construction project
    development practices expert testified that the contract drawings “showing the existing bulkhead[,]
    identify a number of sinkholes which clearly indicate an unstable condition[.]” DX 729 at 6
    (Helmes Direct).
    For these reasons, the court has determined that, as a matter of law, RDA is not entitled to
    an equitable adjustment under the October 13, 2009 Contract’s differing site conditions clause.
    See Comtrol, 
    294 F.3d at 1363
     (“A contractor is not eligible for an equitable adjustment for a Type
    I differing site condition unless the contract indicated what that condition would be.”).
    In the alternative, RDA raises a “defective specification claim” under Count II. Pl PT Br.
    at 56. But, the United States Court of Appeals for the Federal Circuit has held that:
    Although differing site conditions and defective specifications claims are distinct
    in theory, they collapse into a single claim . . . where the alleged defect in the
    specification is the failure to disclose the alleged differing site condition. Where
    the differing site conditions claim and the defective specifications claim are so
    46
    intertwined as to constitute a single claim, that claim will be governed by the
    specific differing site conditions clause and the cases under that clause.
    Comtrol, 
    294 F.3d at 1362
     (emphases added).
    In this case, RDA’s defective specification claim arises from the NAVFAC’s alleged
    failure to disclose that the wharf could not support the weight of demolition equipment, i.e., the
    same condition that RDA argues entitles it to an equitable adjustment under the October 13, 2009
    Contract’s differing site conditions clause. Pl. PT Br. at 56–57. Therefore, RDA’s defective
    specification and differing site conditions allegations constitute a single claim governed by the
    October 13, 2009 Contract’s differing site conditions clause and precedent regarding the same.
    Since the court has determined that RDA is not entitled to relief under the differing site conditions
    theory, RDA also is not entitled to relief under a defective speculation theory. Accordingly,
    Count II of the May 7, 2015 Second Amended Complaint is dismissed.
    3.      Counts III And IV: Whether The Naval Facilities Command
    Misrepresented The Condition Of The Wharf And The Purpose Of The
    October 13, 2009 Contract.
    a.      Plaintiff’s Argument.
    Counts III and IV are a variation of Count II, the gravamen of which is that the Solicitation
    affirmatively represented that the contractor could locate demolition equipment on the wharf. Pl.
    PT Resp. at 11 (citing DX 1 at 291). In addition, the absence of a load restriction in the Solicitation,
    indicated that the relevant structure could be used for its intended purpose. Pl. PT Resp. at 11
    (citing TR at 104–07 (Mr. Wood)); TR at 191–92 (Hartman). Accordingly, RDA reasoned that
    “[t]hese express representations, together with the NAVFAC’s failure to provide the Appledore
    Report and the [FST Report], constitute clear misrepresentations of material fact regarding the
    manner in which the work [was] to be performed and the condition of the wharf that RDA
    reasonably relied upon in submitting its bid for this project.” Pl. PT Resp. at 11–12.
    b.      The Government’s Response.
    The Government responds that the Solicitation did not misrepresent that the wharf could
    bear the weight of demolition equipment. Gov’t PT Br. at 77. Nor has RDA proffered any pre-
    award evidence to show that it intended to work from the wharf. Gov’t PT Br. at 76. Therefore,
    even if the Solicitation misrepresented that the wharf could support demolition equipment, RDA
    failed to demonstrate that it relied on any such misrepresentation. Gov’t PT Br. at 76. In fact, a
    reasonable contractor would not have relied on a representation that a seventy year-old wharf, with
    obvious signs of deterioration, could support the weight of heavy construction equipment, without
    further investigation. Gov’t PT Br. at 77–79.
    c.      The Court’s Resolution.
    The United States Court of Appeals for the Federal Circuit has held that, “for a contractor
    to prevail on a claim of misrepresentation, the contractor must show that the Government made an
    erroneous representation of a material fact that the contractor honestly and reasonably relied on to
    the contractor’s detriment.” T. Brown Constructors, Inc. v. Pena, 
    132 F.3d 724
    , 729 (Fed. Cir.
    47
    1997). This is the same legal standard that applies to type 1 differing site conditions claims. See
    Int’l Tech., 523 F.3d at 1348 (“A misstatement as to site conditions in a government contract can
    support a claim for breach of contract. The same requirements apply whether the contractor asserts
    such a common law breach claim or a Type I claim under the Differing Site Conditions clause[.]”).
    Again, whether a Solicitation makes an erroneous representation is a question of contract
    interpretation, requiring the court to “place itself into the shoes of a reasonable and prudent
    contractor[.]” H.B. Mac, 
    153 F.3d at 1345
    .
    In this case, RDA argues that the Solicitation misrepresented that the wharf could safely
    bear the weight of demolition equipment, because it: (1) failed to disclose the Appledore Report
    and FST Report prior to the contract award (Pl. PT Resp. at 11); (2) did not provide a load
    restriction for the wharf or bulkhead (Pl. PT Resp. at 11); and (3) instructed contractors to “[l]ocate
    demolition equipment throughout the structure” (Pl. PT Resp. at 11 (quoting DX 1 at 291)). As
    discussed previously, the court finds that a reasonable and prudent contractor would not interpret
    the Solicitation as a whole to affirmatively represent that the conditions of the wharf could support
    demolition equipment.
    For these reasons, the court has determined that RDA did not satisfy the requisite elements
    of misrepresentation. Accordingly, Count III and Count IV of the May 7, 2015 Second Amended
    Complaint are dismissed.
    4.      Count V: Whether The Naval Facilities Command’s November 7, 2012
    Directive Was A Cardinal Change To The October 13, 2009 Contract.
    a.      Plaintiff’s Argument.
    Count V alleges that the NAVFAC’s November 7, 2012 “directive” to extract broken H-
    piles from beneath the sea floor was a cardinal change, because it substantially altered the
    magnitude, cost, and type of work required by the October 13, 2009 Contract. Pl. PT Br. at 40–
    41.
    At the time of RDA’s bid, without the benefit of the Appledore Report, RDA planned to
    use a vibratory hammer to shake and remove the H-piles in one piece from the sea floor. Pl. PT
    Br. at 40. Because the H-piles were deteriorated beyond what was expected, all of the piles that
    RDA attempted to remove broke. Pl. PT Br. at 41. After trial and error, RDA discovered a method
    to extract the broken piles, but it was costlier than RDA originally anticipated for pile-removal.
    Pl. PT Br. at 41. In fact, the company that assumed completion of the project estimated that
    removing all of the broken H-piles would cost over $5 million. Pl. PT Br. at 41 (citing 11/05/15
    Dep. of Jonathan Peters at 321, 323). In addition, the NAVFAC’s November 7, 2012 “directive”
    would have extended the October 13, 2009 Contract’s duration by months, as established, since
    Haskell worked to remove all of the H-piles “throughout 2014 and [October] 2015.” Pl. PT Br. at
    42.
    b.      The Government’s Response.
    The Government responds that the October 13, 2009 Contract required RDA to “remove
    piles in their entirety.” DX 1 at 82. Although it became very expensive to remove the H-piles, the
    added expense was RDA’s fault, because “RDA intentionally broke the piles off, having proposed
    48
    and obtained approval for this . . . method in its demolition plan.” Gov’t PT Br. at 65 (citing DX
    108 at 5) (emphasis added). Therefore, the NAVFAC’s November 7, 2012 directive did not
    significantly change: (1) the magnitude of work to be performed; (2) the nature of the work
    contemplated in the October 13, 2009 Contract; or (3) the cost of performance. And, the
    November 7, 2012 directive did not constitute a cardinal change. Gov’t PT Br. at 66.
    c.      The Court’s Resolution.
    As a matter of law, the cardinal change doctrine may be invoked where,
    the [contracting agency] effects an alteration in the work so drastic that it effectively
    requires the contractor to perform duties materially different from those originally
    bargained for. By definition, then a cardinal change is so profound that it is not
    redressable under the contract, and thus renders the government in breach.
    Allied Materials & Equip. Co. v. United States, 
    569 F.2d 562
    , 563–64 (Ct. Cl. 1978) (emphasis
    added).
    As with other breach of contract claims, the cardinal change doctrine has a causation
    requirement. See Rolin v. United States, 
    160 F. Supp. 264
    , 268 (Ct. Cl. 1958) (“[T]he
    Government’s financial obligation to anyone who has furnished materials or services to the
    Government under a contract is to be found within the four walls of the contract, unless the
    Government has caused its contractor to incur unforeseen expenses in performing the contract.”
    (emphasis added)). In other words, a plaintiff cannot prevail on a breach of contract claim, simply
    because unforeseen circumstances changed the amount, or difficulty, of the contract work. See
    United States v. Spearin, 
    248 U.S. 132
    , 135–36 (1918) (“Where one agrees to do, for a fixed sum,
    a thing possible to be performed, he will not be excused or become entitled to additional
    compensation, because unforeseen difficulties are encountered.” (internal citations omitted)).
    Instead, the plaintiff must demonstrate that the Government caused the underlying change.
    “[A] cardinal change is principally a question of fact[.]” Allied Materials, 569 F.2d at 565.
    “Each case must be analyzed on its own facts and circumstances giving just consideration to the
    magnitude and quality of the changes ordered and their cumulative effect upon the project as a
    whole.” Gen. Dynamics Corp. v. United States, 
    585 F.2d 457
    , 462 (Ct. Cl. 1978). Since a cardinal
    change constitutes a breach of contract, the plaintiff bears the burden of proof. See Stockton E.
    Water Dist. v. United States, 
    583 F.3d 1344
    , 1360 (Fed. Cir. 2009).
    The October 13, 2009 Contract expressly required RDA to “remove piles in their entirety.”
    DX 1 at 82. The November 7, 2012 instruction did not change this requirement in any way, stating,
    “[all] remaining H-piles . . . will have to be removed in their entirety[.]” PX 96 at 1. In other
    words, the NAVFAC did not cause any change to the contract requirements. Nevertheless, RDA
    insists that the NAVFAC’s November 7, 2012 directive constituted a cardinal change, because
    RDA did not expect the piles to break during the extraction process. But, due to latent
    deterioration, virtually all of the piles snapped below the sea floor. Pl. PT Br. 40–41. Removal of
    the broken pile stubs required RDA to use extraction methods that were far more expensive than
    it originally anticipated. Pl. PT Br. 41. Under these circumstances, the NAVFAC’s enforcement
    49
    of the contractual requirement that all piles must be removed in their entirety was a cardinal
    change. Pl. PT Br. at 40–42.
    RDA’s cardinal change claim fails, because the record contradicts RDA’s assertion that it
    did not expect the piles to break during the extraction process. On March 29, 2010, RDA submitted
    a demolition plan to the NAVFAC advising that,
    the combination pile cap and support pile will be extracted with the crane. . . . In
    most cases under the load of the extraction process the pile will break between the
    mud line and existing pile jacket due to advanced pile section loss[.] . . . The
    resulting bottom pile section remaining will be extracted with the Manitowoc 4100
    crane and a dive assist crew[.]
    DX 108 at 4–5 (emphasis added). The March 29, 2010 plan was submitted before RDA began
    pile removal. DX 1 at 287, 290 (stating that approval of the demolition plan was required prior to
    beginning work). Therefore, the evidence shows that, prior to removing any piles, RDA knew that
    its extraction method would cause most piles to break.
    For these reasons, the court has determined that RDA did not prove that the NAVFAC
    caused any change to the contract work or the circumstances affecting that work, let alone a
    cardinal change that required RDA to perform duties materially different from those bargained for
    by the parties. See Allied Materials, 569 F.2d at 563–64. Accordingly, Count V of the May 7,
    2015 Second Amended Complaint is dismissed.
    5.     Counts VI, VII and VIII: Whether The NAVFAC Violated The Duty
    Of Good Faith And Fair Dealing.
    a.      Plaintiff’s Argument.
    RDA argues that the NAVFAC breached the duty of good faith and fair dealing by: (1) not
    promptly and fairly adjusting the contract for changes in price and schedule, resulting from new
    information contained in the Appledore Report and FST Report about the wharf’s ability to carry
    demolition equipment; (2) rescinding the NAVFAC’s conditional approval of RDA’s baseline
    schedule; (3) failing to provide instructions on how to remove the broken H-piles; (4) failing to
    authorize drilling that was required to bypass unanticipated obstructions blocking all progress on
    the project; (5) directing RDA to commence obstruction drilling before processing a contract
    modification for that work, then failing to compensate RDA for the additional drilling work; (6)
    directing RDA to remove all broken piles embedded in the sea floor, despite knowing that “such
    work was not necessary, was impractical to perform, and would cause RDA to incur prohibitive
    expense and further prolonged delay”; (7) shutting down the project in September 2011, based on
    “exaggerated safety concerns and maintaining such [a] shutdown for an unreasonable long period
    of time”; (8) failing to act on RDA’s SSHO and QC proposals for months and then denying those
    proposals on “insubstantial or erroneous grounds”; and (9) demanding re-inspection of RDA’s
    crane in January 2013, violating the October 13, 2009 Contract and prior practice. Pl. PT Br. at
    58–61.
    50
    b.      The Government’s Response.
    The Government responds that the NAVFAC properly did not adjust the contract for
    changes in price and schedule, due to unanticipated site conditions. Moreover, the NAVFAC was
    “overly generous” in granting RDA numerous modifications to the October 13, 2009 Contract and
    any delay in granting such modifications is remediable under the Disputes Clause, not as a breach
    of contract. Gov’t PT Resp. at 20.
    Specifically, the NAVFAC did not breach the duty of good faith and fair dealing by
    insisting that RDA’s baseline schedule include all of the contract work and enforcing the
    contractual requirement that RDA remove all of the H-piles in their entirety. Gov’t PT Resp. at
    2–9, 20.
    Nor did the NAVFAC breach the duty of good faith and fair dealing when it allegedly
    refused to instruct RDA on how to remove H-piles that broke beneath the mudline and failed to
    authorize drilling to bypass obstructions at the south and north bulkheads in a timely manner, since
    the October 13, 2009 Contract did not require the NAVFAC to provide instructions other than
    those contained in the Solicitation and RDA was free to drill through obstructions, without any
    NAVFAC authorization. Gov’t PT Resp. at 35.
    Nor did the NAVFAC breach the duty of good faith and fair dealing by enforcing the
    October 13, 2009 Contract’s safety requirements, particularly after RDA experienced a third
    accident onsite. Gov’t PT Resp. at 21. In fact, the NAVFAC reasonably exercised its discretion
    in rejecting several RDA candidates for the QC and SSHO positions who did not have the
    necessary qualifications. Gov’t PT Resp. at 20, 25–29, 32–33, 43–44.
    In addition, the NAVFAC’s decision to request a crane re-inspection in January 2013 was
    consistent with the October 13, 2009 Contract and did not violate the duty of good faith and fair
    dealing. Gov’t PT Resp. at 22.
    c.      The Court’s Resolution.
    “Every contract imposes upon each party a duty of good faith and fair dealing in its
    performance and enforcement.” Metcalf Const. Co. v. United States, 
    742 F.3d 984
    , 990 (Fed. Cir.
    2014) (quoting RESTATEMENT (SECOND) OF CONTRACTS § 205 (1981)(“RESTATEMENT”)) (internal
    quotation marks omitted). “Failure to fulfill that duty constitutes a breach of contract[.]” Id.
    (quoting RESTATEMENT § 235)). But, the duty of good faith and fair dealing does not “expand a
    party’s contractual duties beyond those in the express contract or create duties inconsistent with
    the contract’s provisions.” Precision Pine & Timber, Inc. v. United States, 
    596 F.3d 817
    , 831
    (Fed. Cir. 2010). For this reason, “an act will not be found to violate the duty [of good faith and
    fair dealing] . . . if such a finding would be at odds with the terms of the original bargain, whether
    by altering the contract’s discernible allocation of risks and benefits or by conflicting with a
    contract provision.” Metcalf, 742 F.3d at 991.
    In essence, the covenant of good faith and fair dealing “imposes obligations on both
    contracting parties that include the duty not to interfere with the other party’s performance and not
    to act so as to destroy the reasonable expectations of the other party regarding the fruits of the
    contract.” Centex Corp. v. United States, 
    395 F.3d 1283
    , 1304 (Fed. Cir. 2005). The Government
    51
    may breach this duty if it acts unreasonably under the circumstances. See C. Sanchez & Son, Inc. v.
    United States, 
    6 F.3d 1539
    , 1542 (Fed. Cir. 1993) (“The government must avoid actions that
    unreasonably cause delay[.]”); see also Commerce Int’l Co. v. United States, 
    338 F.2d 81
    , 86 (Ct.
    Cl. 1964) (holding that actions that cause a “breach of [the] obligation of reasonable cooperation”
    depend upon the “particular contract, its context, and its surrounding circumstances”).
    i.      Regarding Price And Schedule Changes To The October
    13, 2009 Contact, Because Of The NAVFAC’s Failure To
    Disclose The Appledore Report And FST Report.
    First, RDA argues that the NAVFAC breached the duty of good faith and fair dealing when
    it failed to “promptly and fairly adjust the contract for changes in price and schedule necessitated
    by the belated disclosure of material information [in the Appledore Report and FST Report]
    concerning actual Project conditions.” Pl. PT Br. at 58. But, as discussed in sections of this Post
    Trial Memorandum Opinion and Final Order addressing Counts I–V, RDA was not entitled to an
    equitable adjustment, because, as a matter of law, the NAVFAC did not have a duty to disclose
    the Appledore Report and FST Report, and the Solicitation did not misrepresent the condition of
    the wharf.
    Therefore, the court has determined that the NAVFAC did not breach the duty of good
    faith and fair dealing by refusing to adjust the October 13, 2009 Contract to compensate RDA for
    price and schedule changes as a result of not disclosing the Appledore Report and FST Report
    during the bidding process.
    ii.     Regarding Rescinding Approval Of RDA Construction
    Corp.’s Baseline Schedule.
    Second, RDA argues that the NAVFAC violated the covenant of good faith and fair dealing
    by “[a]pproving RDA’s impacted schedule to permit work to begin[,] then rescinding such
    schedule approvals upon which depended RDA’s ability to be timely paid for work commenced
    in reliance thereon.” Pl. PT Br. at 59. The record shows that, on February 5, 2010, the NAVFAC
    conditionally approved RDA’s baseline schedule for the limited purpose of allowing work to
    begin. PX 58 at 1. But, there is no evidence that the February 5, 2010 conditional approval was
    ever rescinded. In addition, the record evidence contradicts RDA’s assertion that, based on the
    February 5, 2010 conditional approval, RDA reasonably expected to invoice the work it
    performed. In fact, the February 5, 2010 conditional approval expressly stated that RDA could
    begin work, but the NAVFAC would not process RDA’s invoices until the NAVFAC completed
    a full review of RDA’s proposed baseline schedule. PX 58 at 1.
    52
    PX 58 at 1.
    It appears that RDA also contends that the NAVFAC breached its duty of good faith and
    fair dealing by allowing work to begin on February 5, 2010, but delaying approval of the baseline
    schedule necessary for payment until May 17, 2010, forcing RDA to work without payment for
    three months. The record, however, shows that RDA was responsible for most of the delay:
          On April 1, 2010, the NAVFAC informed RDA that its proposed baseline schedule
    contained thirty-four deficiencies. DX 111 at 2–3.
          On April 21, 2010, RDA submitted a revised baseline schedule. DX 121 at 1.
          On April 22, 2010, the NAVFAC rejected RDA’s revised baseline schedule,
    because it contained many of the same deficiencies identified in the April 1, 2010
    rejection and a few new deficiencies. DX 121 at 2.
          On April 28, 2017, RDA submitted a second revised baseline schedule. DX 130
    at 1.
          On May 13, 2010, the NAVFAC rejected RDA’s second revised schedule, because
    RDA still did not correct many of the deficiencies identified in the April 1, 2010
    and April 21, 2010 rejections. DX 130 at 2–3.
          On May 14, 2010, RDA finally submitted a baseline schedule that addressed all of
    the NAVFAC’s concerns. DX 134 at 1.
          Three days later, the NAVFAC approved the May 13, 2010 baseline schedule. DX
    134 at 1.
    53
    Therefore, the court has determined that the NAVFAC did not violate the duty of good
    faith and fair dealing by rescinding the February 5, 2010 conditional approval of RDA’s baseline
    schedule, nor did the NAVFAC cause any delay to the final approval of that schedule.
    iii.   Regarding Extraction Of The Broken H-Pile Sections.
    Third, RDA argues that the NAVFAC violated the duty of good faith and fair dealing by
    refusing to help RDA develop a plan for extracting the H-piles that broke off beneath the mudline
    or, alternatively, waiving RDA’s obligation to remove the piles in their entirety. Pl. PT Br. at 59.
    The October 13, 2009 Contract, however, expressly stated that RDA must formulate a plan to
    “remove all piles in their entirety.” DX 1 at 82, 290. In other words, the October 13, 2009 Contract
    allocated the risks associated with formulating and executing a pile removal plan to RDA. A
    finding that the NAVFAC’s failure to help RDA develop a removal plan, or otherwise waive
    RDA’s obligation to “remove all piles in their entirety[,]” breached the October 13, 2009 Contract
    would force the NAVFAC to incur the costs of carrying out those activities. Accordingly, such a
    determination would transfer to the NAVFAC risks that the October 13, 2009 Contract allocated
    to RDA.
    Therefore, the court has determined that the NAVFAC did not violate the duty of good
    faith and fair dealing by refusing to waive the contractual requirement that RDA remove all of the
    H-pile sections or to assist RDA in doing so.
    iv.    Regarding Obstruction Drilling.
    Fourth, RDA argues that the NAVFAC violated the duty of good faith and fair dealing by
    failing to timely authorize obstruction drilling at the bulkhead, causing the project to come to a
    standstill. Pl. PT Br. at 59–60 (citing PX 83 at 2). RDA, however, fails to identify any contract
    provision that required the NAVFAC to authorize such work.
    Moreover, the record shows that this delay was caused by RDA’s refusal to drill through
    the obstructions without first receiving an equitable adjustment. On March 9, 2011, RDA’s Project
    Manager advised the NAVFAC that “RDA will not continue to perform work on [the bulkhead]
    without . . . a Contract Modification.” DX 273 at 1. Similarly, on August 16, 2012, RDA’s
    President informed the NAVFAC, “I believe that [i]t is in RDA’s and the Navy’s best interest to
    hold off on the obstruction drilling . . . until we reach an agreement on a unilateral modification.”
    DX 570 at 1. In short, RDA voluntarily stopped contract performance, hoping that the NAVFAC
    would modify the contract price and schedule to account for obstructions at the bulkhead. RDA
    pursued this strategy, despite the October 13, 2009 Contract’s instruction that “[a] Contractor shall
    proceed diligently with performance of this contract, pending final resolution of any request for
    relief, claim, appeal, or action arising under the contract[.]” DX 1 at 14 (incorporating 
    48 C.F.R. § 52.233-1
    (i)).
    Conversely, RDA argues that the NAVFAC violated the duty of good faith and fair dealing
    by “[d]irecting RDA to commence obstruction drilling in February 2012, in advance of processing
    a contract modification, then failing to take any steps to compensate RDA for all such extra work
    through termination the following February.” Pl. PT Br. at 60. But, RDA did not proffer any
    evidence that the NAVFAC ordered RDA to commence obstruction drilling in February 2012. To
    54
    the contrary, RDA appears to recognize that “[i]n February 2012 . . . RDA proceeded with the
    second round of obstruction drilling in advance of receiving formal authorization.” Pl. PT Br. at
    25 (emphasis added).17
    17
    During the trial of this case the court questioned Mr. Rachupka, the NAVFAC’s CO,
    about a related issue: a May 10, 2012 request for equitable adjustment that remained pending for
    ten months. TR at 2134–35 (Rachupka). Mr. Rachupka conceded that the NAVFAC’s delay was
    unfair to RDA:
    [THE COURT]: Was there an occasion where you had an outstanding change order
    for ten months? . . .
    [MR. RACHUPKA]: We did have, as I explained earlier this week in testimony,
    the change order that is being questioned right now where there were inaccuracies
    related to the amount of money being sought by RDA. If you remember our
    conversation about the double dipping --
    [THE COURT]: Right.
    [MR. RACHUPKA]: -- that is specifically what Mr. O’Brien is referring to.
    [THE COURT]: What I am saying is you didn’t get it resolved because you didn’t
    get the information from RDA?
    [MR. RACHUPKA]: As you have seen, there has been a myriad of issues. It’s one
    of those things that we never got to sit down and address and work out.
    [THE COURT]: In ten months?
    [MR. RACHUPKA]: That is correct, Your Honor.
    [THE COURT]: And was that because you didn’t try?
    [MR. RACHUPKA]: I had, I had done -- I believe I did some evaluation but never
    completed it.
    [THE COURT]: I’m sorry?
    [MR. RACHUPKA]: I probably did some evaluation as to the cost proposals but
    never completed it.
    [THE COURT]: Do you think that was fair to the contractor?
    [MR. RACHUPKA]: I wouldn’t say it is fair but --
    55
    Therefore, the court has determined that the NAVFAC did not violate the duty of good
    faith and fair dealing by failing to award RDA an equitable adjustment prior to commencing
    obstruction drilling in February 2012 or withholding payment for that work.
    v.      Regarding Work Suspension After The September 14,
    2011 Safety Mishap.
    Fifth, RDA argues that the NAVFAC violated the duty of good faith and fair dealing when
    it suspended work, following an accident on September 14, 2011. Pl. PT Br. at 61. The September
    14, 2011 accident was RDA’s third safety incident. DX 413 at 1. The first accident occurred on
    August 10, 2010 and resulted in the injury of an RDA worker. DX 174 at 1. The second accident
    took place on February 22, 2011, when a vibratory hammer hit an employee breaking several of
    his ribs. DX 261 at 9. Moreover, RDA’s QC and SSHO (safety officers) were not at the project
    site when the September 14, 2011 accident occurred. DX 413 at 1. In light of RDA’s repeated
    failure to satisfy its contractual obligation to maintain a safe work site and have safety officers
    supervise all work (DX 1 at 192), and the NAVFAC’s authority to stop work pending the
    investigation of a safety incident (DX 1 at 193), the court finds that it was reasonable for the
    NAVFAC to require a thorough investigation of the September 14, 2011 accident.
    Therefore, the court has determined that the NAVFAC did not violate the duty of good
    faith and fair dealing by suspending work to investigate why RDA repeatedly experienced
    accidents that risked injury to individuals and damage to equipment at the Newport Naval Station.
    vi.     Regarding Approval Of RDA Construction Corp.’s
    Quality Control Manager And Site Safety And Health
    Officer.
    Sixth, RDA argues that the NAVFAC violated the duty of good faith and fair dealing when
    it failed to evaluate RDA’s QC and SSHO candidates in a timely manner and denied several of
    those candidates on “insubstantial or erroneous grounds.” Pl. PT Br. at 60–61. These delays
    forced RDA to stop work, because the October 13, 2009 Contract required RDA to “[p]rovide a
    [SSHO] at the work site at all times.” DX 1 at 192. The record, however, shows that the NAVFAC
    evaluated candidates in a reasonable time and promptly approved personnel that satisfied the
    October 13, 2009 Contract’s experience and certification requirements. DX 1 at 192–93
    (minimum qualifications for SSHO), 217–18 (minimum qualifications for QC). In fact, the
    [THE COURT]: I didn’t hear you. Would you please stop doing that[?]
    [MR. RACHUPKA]: So I would not say it is fair. No, I wouldn’t say that.
    TR at 2134–35 (Rachupka).
    RDA, however, did not argue that the NAVFAC’s failure to timely address the May 10,
    2012 request violated the duty of good faith and fair dealing in the November 8, 2016 Post Trial
    Brief. Therefore, the court does not address this issue. See Novosteel SA v. U.S., Bethlehem Steel
    Corp., 
    284 F.3d 1261
    , 1274 (Fed. Cir. 2002) (holding that a party waives an argument when it fails
    to raise that argument in its principal brief).
    56
    NAVFAC approved Mr. Morrissette as QC and SSHO within five days (DX 327 at 1), Mr. Brewer
    as SSHO in seven days (DX 491 at 1), and Mr. Smith as QC in eighteen days (PX 156 at 2).
    To the extent that delays occurred in the approval of RDA’s candidates for the QC and
    SSHO roles, the record shows that RDA repeatedly submitted candidates that did not meet the
    contractual requirements for those roles. From March 31–May 2, 2011, RDA requested that the
    NAVFAC approve Mr. Meomartino, Ms. Amarantes, Mr. Rand, and Mr. DiRamio as QCs and
    SSHOs. DX 306–13, 316, 319–20. On May 9, 2011, the NAVFAC rejected all of these candidates,
    because they did not have the experience and/or certifications required by the October 13, 2009
    Contract. DX 327 at 1–13. After Mr. Morrissette, the QC and SSHO from May 9, 2011 to late
    January 2012, had a heart attack on June 28, 2011, it became necessary for RDA to hire an
    alternative QC and SSHO on site. Instead of proposing a new candidate, RDA requested that the
    NAVFAC reconsider Ms. Amarantes and Mr. Rand. DX 345 at 1; DX 346 at 1; DX 348 at 1.
    Because RDA did not indicate that either candidate had acquired the necessary experience and/or
    certifications after they were first rejected, the NAVFAC rejected them a second time. DX 356
    at 1 (rejecting Ms. Amarantes); DX 357 at 1 (rejecting Mr. Rand).
    Moreover, the NAVFAC did not deny RDA’s QC and SSHO candidates on insubstantial
    grounds. The October 13, 2009 Contract required QC candidates to have the following
    qualifications:
    a minimum of 10 years combined experience in the following positions: Project
    Superintendent, QC Manager, Project Manager, Project Engineer or Construction
    Manager on similar size and type construction contracts which included the major
    trades that are part of this Contract. The individual must have at least two years
    experience as a QC Manager. The individual must be familiar with the
    requirements of, and have experience in the areas of hazard identification, safety
    compliance, and sustainability.
    In addition to the above experience and education requirements, the QC Manager
    must have completed the course entitled “Construction Quality Management
    (CQM) for Contractors.”
    DX 1 at 217.
    The October 13, 2009 Contract also required that SSHO have specific qualifications,
    including:
    [a] minimum of 10 years safety work of a progressive nature with at least 5 years
    of experience on similar projects. 30-hour OSHA construction safety class or
    equivalent within the last 5 years. An average of at least 24 hours of formal safety
    training each year for the past 5 years with training for competent person status for
    at least the following 4 areas of competency: Excavation; Hazardous energy; Health
    hazard recognition, evaluation and control of chemical, physical and biological
    agents; Personal protective equipment and clothing to include selection, use and
    maintenance.
    DX 1 at 192.
    57
    The NAVFAC denied Mr. Meomartino as QC and SSHO, because his resume did not
    indicate: (1) ten years of experience on projects of comparable size; (2) familiarization with United
    States Army Corp of Engineers safety guidelines; (3) completion of the “Construction Quality
    Management (CQM) for Contractors” course; (4) completion of thirty-hour OSHA construction
    safety class within the last five years; and (5) twenty-four hours of formal safety training each year
    for the past five years. DX 327 at 3–4.
    Ms. Amarantes’ background did not satisfy the contract requirements either, because her
    resume did not indicate: (1) ten years of combined experience as Project Superintendent, QC,
    Project Manager, Project Engineer or Construction Manager on projects of comparable size; (2)
    any experience as QC; (3) five years of safety work on similar projects; and (4) training for
    excavation, hazardous energy or personal protective equipment. DX 327 at 5–6. In addition, the
    NAVFAC noted that Ms. Amarantes did not provide documentation for fourteen hours of the
    formal safety training included on her resume. DX 327 at 6.
    Similarly, Mr. Rand’s resume did not indicate: (1) ten years of combined experience as
    Project Superintendent, QC, Project Manager, Project Engineer or Construction Manager; (2) any
    experience as QC; (3) any experience applying the United States Army Corp of Engineers safety
    guidelines; (4) completion of the “Construction Quality Management (CQM) for Contractors”
    course; (5) ten years of experience in safety work of a progressive nature; and (6) twenty-four
    hours of formal safety training each year for the past five years. DX 327 at 7–8.
    Mr. DiRamio also was denied as QC and SSHO, because he: (1) did not complete the
    “Construction Quality Management (CQM) for Contractors” course; (2) only had seventeen
    months of experience in safety work; (3) did not complete the thirty-hour OSHA construction
    safety class within the past five years; and (4) did not provide proof of any formal safety training
    in the last five years. DX 327 at 10–11.
    And, the NAVFAC also denied Mr. Wallis for the SSHO position, because his resume did
    not: (1) demonstrate ten years of experience in safety work; (2) provide certificates showing
    completion of the thirty-hour OSHA construction safety class; (3) indicate he had taken an average
    of twenty-four hours of formal safety training each year for the past five years; and (4) demonstrate
    competent person status in hazardous energy, health hazard recognition, or personal protective
    equipment. DX 486 at 1. Likewise, Mr. Wallis was denied the QC position, because in his past
    performance he failed to follow Navy guidelines during the recovery of a sunken RDA boat,
    leading to a fuel spill. DX 485 at 1. The NAVFAC considered this accident in finding that he was
    not competent to perform the role of QC. DX 485 at 1.
    Therefore, the court has determined that the NAVFAC did not unreasonably delay the
    evaluation of RDA’s candidates for the QC and SSHO positions or deny those candidates on
    insubstantial grounds.
    vii.    Regarding The Re-Inspection Of The Manitowoc 4100
    Crane.
    RDA also argues that the NAVFAC violated the duty of good faith and fair dealing by
    “[d]emanding re-inspection of RDA’s crane in January 2013, violating both the applicable contract
    58
    standards (EM-385) and prior practice, resulting in prolonged, expensive repairs during which time
    RDA was unable to use this equipment.” Pl. PT Br. at 61. RDA’s argument is based on a
    disagreement with the NAVFAC regarding whether an independent crane inspector was required
    to perform a second inspection of the Manitowoc 4100 Crane to ensure that RDA had properly
    repaired deficiencies that the crane inspector had identified during a previous inspection. DX 677
    at 60, 104, 106.
    The October 13, 2009 Contract incorporates the 2003 United States Army Corps of
    Engineers’ Safety and Health Requirements, EM 385-1-1 (“EM 385-1-1”). DX 1 at 192. The EM
    385-1-1 states that “[a]ll equipment shall be shut down and positive means taken to prevent its
    operation while repairs or manual lubrications are being done.” EM 385-1-1 at ¶ 16.A.08b. In
    addition, “[l]oad performance tests shall be conducted . . . [b]efore initial use of cranes in which a
    load bearing . . . or load controlling part or component, brake, travel component, or clutch have
    been altered, replaced, or repaired[.]” EM 385-1-1 at ¶ 16.C.13c(2)(a). “A qualified person shall
    conduct [the] performance tests” (EM 385-1-1 at ¶ 16.C.13a (emphasis added)) and “[w]ritten
    reports of the performance test, showing test procedures and confirming the adequacy of repairs
    or alterations, shall be maintained with the crane” (EM 385-1-1 at ¶ 16.C.13c).
    On November 28, 2012, J.P. Riley inspected RDA’s Manitowoc 4100 Crane and found
    inter alia that the crane’s brakes must be adjusted and/or repaired. DX 677 at 13. According to
    the EM 385-1-1, the deficiencies required RDA to take the crane out of service while the repairs
    were being made (EM 385-1-1 at ¶ 16.A.08b) and a qualified person to conduct a load performance
    test on the crane before it could be placed back into service (EM 385-1-1 at ¶¶ 16.C.13a,
    16.C.13c(2)(a)). After RDA informed the NAVFAC that it had repaired all of the deficiencies
    identified by J.P. Riley, including the break adjustments, the NAVFAC instructed that the crane
    must remain out of service until J.P. Riley conducted a re-inspection and load performance test on
    the crane. DX 625 at 6; DX 677 at 28–29. RDA argues that this request was not in good faith,
    because nothing in the October 13, 2009 Contract required RDA to hire J.P. Riley to conduct the
    re-inspection and performance test, instead of another qualified person. DX 625 at 3–6.
    RDA requested that Steve Watt, one of RDA’s mechanics, conduct the re-inspection and
    performance test, but failed to provide any evidence that Mr. Watt was a “qualified person” under
    EM 385-1-1. DX 625 at 3–4. In fact, when the NAVFAC asked RDA for Mr. Watt’s resume, Mr.
    Kelley responded:
    [o]nce again[,] Steve Watt has demonstrated to me . . . that he is qualified to inspect
    the recommended repairs to this crane. I do not and will not have you dictate to me
    what you believe the standard to be. You are wrong. Neither OSHA nor the em385
    require what you are asking. You are overstepping your authority. [Mr. Watt] has
    extensive knowledge and experience working on these cranes as my employee for
    nearly 20 years, and that makes him qualified. I have been in in the marine and
    crane business all my working life I have the extensive knowledge, training and the
    experience to make the determination regarding Steve’s qualifications[.] I have
    gone thru dozens and dozens of crane inspections and OSHA inspections. RDA is
    complying with our contract.
    DX 625 at 3.
    59
    In addition, RDA had a contractual duty to maintain a safe work environment. But, by the
    end of 2012, RDA had experienced three safety mishaps, including one crane accident. DX 398
    at 1. In light of RDA’s questionable safety record, it was reasonable for the NAVFAC to require
    that RDA either: (1) prove that Mr. Watt was qualified to inspect the crane and conduct
    performance tests; or (2) hire a third-party crane inspector to conduct the re-inspection and tests.
    RDA also argues that the October 13, 2009 Contract did not require the crane to be re-
    inspected at all. Pl. PT Br. at 31. But, the EM 385-1-1 expressly requires a “[w]ritten report[] . .
    . confirming the adequacy of repairs or alterations.” EM 385-1-1 at ¶ 16.C.13c. In addition, it is
    undisputed that a qualified person had to conduct a load performance test on the crane, and that
    RDA had not conducted such a test when the NAVFAC requested that the crane be taken out of
    service. In fact, RDA’s response to this request stated that,
    [t]he referenced sections of EM-385-1-1 require that a written report documenting
    the tests be maintained before initial use of the 4100W as the brakes have been
    repaired. This documentation will be provided as soon as the Operational Test has
    been completed.
    DX 625 at 6. In other words, the NAVFAC had a contractual right to take the crane out of service
    until a qualified person conducted a re-inspection and performance test on the crane, and did not
    act unreasonably when it exercised that right.
    Therefore, the court has determined that the NAVFAC did not violate the duty of good
    faith and fair dealing by taking RDA’s Manitowoc 4100 crane out of service.
    In sum, the court has determined that the NAVFAC did not violate the duty of good faith
    and fair dealing in its administration of the October 13, 2009 Contract. Accordingly, Count VI–
    VIII of the May 7, 2015 Second Amended Complaint are dismissed.
    6.      Count IX: Whether RDA Construction Corp. Was Entitled To An
    Extension Of The Contract Completion Date For Excusable Delays.
    The May 7, 2015 Second Amended Complaint contains a “ninth cause of action.” 5/7/2015
    Sec. Am. Compl. at ¶¶ 128–34. The so-called “ninth cause of action,” however, asserts an
    affirmative defense. Specifically, it alleges that the NAVFAC is not entitled to recover liquidated
    damages for RDA’s failure to complete performance of the October 13, 2009 Contract by the
    modified completion date, i.e., October 5, 2012, because the NAVFAC was required to extend the
    completion date by 313 days for excusable delays. 5/7/2015 Sec. Am. Compl. at ¶¶ 132–34.
    Because the “ninth cause of action” is, in fact, an affirmative defense to the NAVFAC’s
    counterclaim for liquidated damages, i.e., Counterclaim I, the court addresses this issue in its
    discussion of the NAVFAC’s counterclaims. See M. Maropakis Carpentry, 
    609 F.3d at 1330
    (characterizing allegation that plaintiff was entitled to adjustment of the contract completion date
    for excusable delays as an affirmative defense).
    60
    IV.     DISCUSSION OF   THE      COUNTERCLAIMS                             ALLEGED          IN      THE
    GOVERNMENT’S JUNE 12, 2015 ANSWER.
    A.      Jurisdiction.
    The United States Court of Federal Claims has “jurisdiction to render judgment upon any
    set-off or demand by the United States against any plaintiff in such court.” 
    28 U.S.C. § 1503
    .
    Likewise, the court has jurisdiction to adjudicate “any setoff, counterclaim, claim for damages, or
    other demand [that] is set up on the part of the United States against any plaintiff making claim
    against the United States[.]” 
    28 U.S.C. § 2508
    . The court’s jurisdiction to adjudicate Government
    counterclaims, however, is subject to the prerequisite that the court have jurisdiction to adjudicate
    an underlying claim against the Government in the same case. See Mulholland v. United States,
    
    361 F.2d 237
    , 245 (Ct. Cl. 1966). Therefore, if the court dismisses a claim alleged by plaintiff
    against the Government for lack of subject-matter jurisdiction, the court must also dismiss the
    Government’s counterclaims. 
    Id.
    Because the court has determined that it has jurisdiction to adjudicate Counts I–VIII of
    RDA’s May 7, 2015 Second Amended Complaint, the court also has jurisdiction to adjudicate the
    counterclaims alleged in the Government’s June 12, 2015 Answer. See Computer Wholesale
    Corp. v. United States, 
    214 Ct. Cl. 786
    , 788 (1977) (“If plaintiff had pleaded a proper claim,
    defendant would be able to claim a setoff or counterclaim for the liquidated damages under 
    28 U.S.C. § 1503
     or § 2508.”); see also Martin J. Simko Const., Inc. v. United States, 
    852 F.2d 540
    ,
    547 (Fed. Cir. 1988) (“The Claims Court has jurisdiction to hear government counterclaims
    asserted under the False Claims Act.”); Daff v. United States, 
    78 F.3d 1566
    , 1573 (Fed. Cir. 1996)
    (“[T]he court had jurisdiction with respect to . . . the government’s . . . fraud claims.”).
    B.      Standing.
    The June 12, 2015 Answer alleges that the Government is entitled to recover liquidated
    damages for RDA’s breach of the October 13, 2009 Contract and penalties, under the CDA and
    False Claims Act, for fraudulent claims that RDA submitted to the NAVFAC. 6/12/15 Gov’t
    Answer ¶¶ at 174–90. Therefore, the June 12, 2015 Answer alleges that the Government has
    suffered economic injury that is concrete, particularized, and fairly traceable to RDA’s actions.
    See Friends of the Earth, 
    528 U.S. at 180
     (“[To establish standing,] plaintiff must show . . . it has
    suffered an ‘injury in fact’ that is . . . concrete and particularized . . . [and] fairly traceable to the
    challenged action[.]”). In addition, any financial injury established by the Government can be
    redressed by a monetary award. See 
    id. at 181
     (holding that, to establish standing, alleged injury
    can “be redressed by a favorable decision”).
    For these reasons, the court has determined that the Government has standing to seek an
    adjudication of the counterclaims alleged in the June 12, 2015 Answer.
    61
    C.      Counterclaim I: Whether The Naval Facilities Command Is Entitled To
    Recover Liquidated Damages For The Cost Of Completing The October 13,
    2009 Contract.
    1.     The Government’s Argument.
    The Government’s June 12, 2015 Answer alleges that the NAVFAC is entitled to recover
    $3,531.26 in liquidated damages for each calendar day between the contract completion date and
    the date the contract work was actually completed. 6/12/15 Gov’t Answer at ¶¶ 174–76. In
    addition, the Government argues that such liquidated damages continued to accrue after the
    October 13, 2009 Contract was terminated, because, at that time, RDA was in default for:
    (1) violating the False Claims Act (“FCA”), 
    31 U.S.C. §§ 3729
    –3733 (Gov’t PT Br. at 42–44); (2)
    failing to timely complete the project (Gov’t PT Br. at 44–51); (3) not making progress toward
    completion (Gov’t PT Br. at 51–56); (4) failing to provide adequate assurances in response to the
    NAVFAC’s January 31, 2013 Show Cause Notice (Gov’t PT Br. at 56–59); (5) repudiating a
    fundamental contract requirement to remove all the H-piles in their entirety (Gov’t PT Br. at 59–
    67); and (6) not complying with a number of contract provisions, including removal of demolition
    debris from the bay, completion of rip removal and installation of sheet piles and soil anchors
    (Gov’t PT Br. at 67–69).
    In total, the Government argues that the NAVFAC is entitled to recover $2,514,072 for
    712 days of delay.18 Gov’t PT Br. at 69. After subtracting $294,705 that the NAVFAC retained
    in payments owed to RDA and an $11,162.99 equitable adjustment to the October 13, 2009
    Contract for unforeseen costs, the NAVFAC is owed $2,208,204.01. Gov’t PT Br. at 69.
    2.     Plaintiff’s Response.
    RDA responds that the Government did not prove by a preponderance of the evidence that
    the NAVFAC’s February 21, 2013 default termination of the October 13, 2009 Contract was
    justified. Pl. PT Resp. at 12 (citing Lisbon Contractors, Inc. v. United States, 
    828 F.2d 759
    , 765
    (Fed. Cir. 1987)). Under FAR 1.602-2(b), COs must “[e]nsure that contractors receive impartial,
    fair, and equitable treatment.” Pl. PT Resp. at 13. This obligation requires that the CO “take
    ownership of all determinations included in the final [CO’s] opinion.” Pl. PT Resp. at 14 (quoting
    CEMS, Inc. v. United States, 
    65 Fed. Cl. 473
    , 479 (2005) (internal quotation marks omitted)). Ms.
    Kahler, the NAVFAC’s Acquisition Director/Chief of the Contracting Office, violated this
    obligation, because she issued the February 21, 2013 Notice of Termination without knowledge
    of, and relying on incorrect information about, the NAVFAC’s administration of the October 13,
    2009 Contract. Pl. PT Resp. at 14–15.
    18
    The Government calculates the amount of delay by adding: (1) the 441 days that elapsed
    between RDA’s final contract completion date of October 5, 2012 and the December 20, 2013
    execution of the Tender Agreement between the NAVFAC and RDA’s surety; and (2) the 271
    days between the execution of the completion contract between the NAVFAC and Haskell and the
    Haskell contract’s original completion date of November 30, 2014. Gov’t PT Br. at 69.
    62
    In addition, RDA argues that the NAVFAC was not justified in terminating the October
    13, 2009 Contract for failure to complete work by the contract completion date, because RDA was
    entitled to a 313-day extension of time for excusable delays. Pl. PT Resp. at 17. Nor could RDA’s
    alleged lack of progress justify the February 21, 2013 default termination, because the NAVFAC
    contributed to RDA’s lack of progress by: (1) refusing to approve obstruction drilling for long
    periods of time; (2) requiring re-inspection of the Manitowoc 4100 crane in violation of the
    October 13, 2009 Contract; and (3) forcing RDA to deplete its resources dealing with conditions
    that the NAVFAC knew about from the Appledore Report and FST Report, but did not disclose to
    bidders during the procurement process. Pl. PT Resp. at 20–23. “It is simply not reasonable for
    NAVFAC to point to conditions which it had a role in creating as justification for default
    termination[.]” Pl. PT Resp. at 22.
    Moreover, the NAVFAC was not justified in terminating the October 13, 2009 Contract on
    the basis that RDA failed to provide adequate assurances in response to the NAVFAC’s January
    31, 2013 Show Cause Notice. Pl. PT Resp. at 23. In response to the January 31, 2013 Show Cause
    Notice, “RDA explained the major impediments to completing the project, which were all
    NAVFAC’s responsibility, and stated unambiguously that ‘RDA will continue to work diligently
    to complete the work.’ RDA is unsure what further assurance could be provided.” Pl. PT Resp.
    at 23 (internal citations omitted).
    RDA also responds that it did not repudiate any obligation under the October 13, 2009
    Contract. Pl. PT Resp. at 23. Although the NAVFAC insisted that RDA remove all of the broken
    H-piles from below the sea floor, those instructions constituted a cardinal change. Pl. PT Br. at
    23. Therefore, RDA was not contractually obligated to perform that work. Pl. PT Br. at 23.
    Moreover, the NAVFAC was not justified in terminating the October 13, 2009 Contract on the
    basis that RDA did not comply with its contractual obligation to: (1) remove all of the debris that
    fell into the bay during wharf demolition; (2) complete rip rap removal; and (3) install sheet piles
    and soil anchors. Pl. PT Resp. at 23–29. First, RDA removed virtually all of the debris from the
    bay, and planned to remove the negligible amount remaining once the rest of the contract work
    was complete. Pl. PT Resp. at 23–25. Second, RDA removed all the rip rap within twenty feet of
    the bulkhead, as required by the October 13, 2009 Contract. Pl. PT Resp. at 27. Any additional
    rip rap was beyond the October 13, 2009 Contract’s scope. Pl. PT Resp. at 27. Third, RDA’s
    failure to complete the installation of sheet piles and soil anchors at the bulkhead was caused by
    unforeseen obstructions and the NAVFAC’s delay in approving work to drill through those
    obstructions. Pl. PT Resp. at 29.
    But, even if the Government did demonstrate that the February 21, 2013 default termination
    was justified, “a contractor’s failure to perform will be excused and the termination for default
    converted to a termination for convenience if the contractor can establish that the government
    materially breached the contract.” Pl. PT Br. at 37 (quoting Fort Howard Senior Hous. Assocs.,
    LLC v. United States, 
    121 Fed. Cl. 636
    , 649 (2015)). In this case, the NAVFAC breached the
    63
    October 13, 2009 Contract by: (1) effecting a cardinal change when it instructed RDA to remove
    all the H-piles in their entirety (Pl. PT Br. at 38); (2) failing to timely authorize obstruction drilling
    at the bulkhead (Pl. PT Br. at 42); (3) failing to disclose the Appledore Report and FST Report
    during the procurement process (Pl. PT Br. at 47–56); (4) including a defective specification in the
    October 13, 2009 Contract (Pl. PT Br. at 56); and (5) violating the duty of good faith and fair
    dealing (Pl. PT Br. at 57–61). Therefore, the court must convert the February 21, 2013 termination
    for default into a termination for convenience. Pl. PT Br. at 37–38.
    3.      The Government’s Reply.
    The Government replies that “[n]one of RDA’s arguments rebut [the Government’s]
    showing that RDA was in default at the time of the termination.” Gov’t PT Resp. at 2. First, RDA
    was not excused from removing the H-piles in their entirety, because that contractual requirement
    was included in the original contract and never changed. Gov’t PT Resp. at 2–9. In addition, RDA
    did not demonstrate that it was entitled to a 313-day extension of the contract completion date for
    work that RDA performed to drill through obstructions at the bulkhead. Although RDA’s
    scheduling expert, Mr. Mitchell, testified that the project experienced a total of 821 calendar days
    of delay, he did not offer any opinion as to the causes of the delay. Gov’t PT Resp. at 37. And,
    RDA failed to provide any evidence that the obstructions forced RDA to halt all contract work.
    Gov’t PT Resp. at 35.
    The Government adds that the NAVFAC’s failure to disclose the Appledore Report and
    FST Report was not a material breach of the October 13, 2009 Contract. Gov’t PT Resp. at 15.
    But, even if it was, “a party facing a material breach must choose between continuing to perform
    the contract or ceasing performance and asserting a breach[.] . . . Failure to [cease performance]
    results in waiver of any right to treat the alleged breach as having terminated the contract.” Gov’t
    PT Resp. at 15. In this case, RDA discovered that the NAVFAC withheld the Appledore Report
    and FST Report on November 18, 2009, but continued to perform on the October 13, 2009 Contract
    until February 14, 2013. “RDA cannot now [] claim that its 2013 default was excused by its
    November 2009 receipt of the Appledore [R]eport[.]” Gov’t PT Resp. at 16.
    The Government also replies that RDA was not excused from performing on the October
    13, 2009 Contract by any alleged constructive change or differing site condition. Gov’t PT Resp.
    at 16–17. “[C]ontingencies contemplated by various contract clauses are remediable under those
    clauses of the contract, not as a breach of the contract.” Gov’t PT Resp. at 17 (quoting Triax-
    Pac. v. Stone, 
    958 F.2d 351
    , 354 (Fed. Cir. 1992)). The October 13, 2009 Contract included a
    Changes Clause and differing site conditions clause. Gov’t PT Resp. at 17. Therefore, any change
    in work or differing site condition that RDA encountered would be remediable as an equitable
    adjustment and not as a breach of contract. Gov’t PT Resp. at 17.
    Likewise, RDA was not excused from performing work under the October 13, 2009
    Contract by alleged defects in the specification, because such defects are remediable as equitable
    adjustments. Gov’t PT Resp. at 18. Alternatively, RDA failed to prove any of the elements of a
    defective specification claim; RDA did not demonstrate that the specification contained any errors
    or that RDA was actually misled by information contained in the specification. Gov’t PT Resp. at
    64
    18. Finally, the Government replies that the NAVFAC never breached the covenant of good faith
    and fair dealing. Gov’t PT Resp. at 19–22.
    4.     The Court’s Resolution.
    The October 13, 2009 Contract includes the following liquidated damages provision:
    (a) If the Contractor fails to complete the work within the time specified in the
    contract, the Contractor shall pay liquidated damages to the Government in the
    amount of [$3,531] for each calendar day of delay until the work is completed or
    accepted.
    (b) If the Government terminates the Contractor’s right to proceed, liquidated
    damages will continue to accrue until the work is completed. These liquidated
    damages are in addition to excess costs of repurchase under the [t]ermination
    clause.
    DX 1 at 17, 586 (incorporating 
    48 C.F.R. § 52.211-12
    ).
    Although FAR 52.211-12(b) does not distinguish between terminations for default and
    terminations for the convenience of the Government, the United States Court of Appeals for the
    Federal Circuit’s predecessor held that the Government cannot recover prospective liquidated
    damages when it terminates a contract for its own convenience. See John A. Johnson Contracting
    Corp. v. United States, 
    132 Ct. Cl. 645
    , 661 (1955) (“The plaintiff’s . . . work was, in fact,
    terminated for the convenience of the Government. The Government had, therefore, no right under
    the contract to charge the plaintiff with the excess costs of having [the work] completed[.]”); see
    also Timberland Paving & Const. Co. v. United States, 
    8 Cl. Ct. 653
    , 662 (1985) (“Where a
    termination for default is . . . in the contemplation of the law one for the convenience of the
    government, neither liquidated damages for any period following the termination nor common law
    damages for a breach may properly be assessed against a government contractor.”). In addition,
    the October 13, 2009 Contract provides that “[i]f, after termination, it is determined that the
    Contractor was not in default, or that the default was excusable, the rights and obligations of the
    parties shall be the same as if the termination had been issued for the convenience of the
    Government.” DX 1 at 15 (incorporating 
    48 C.F.R. § 52.249-10
    (c)). Therefore, if the Contractor
    was not in default, or the default was excusable, the Government cannot recover liquidated
    damages under FAR 52.211-12(b).
    In this case, the Government has proffered undisputed evidence that RDA did not
    substantially complete the October 13, 2009 Contract by the modified completion date, i.e.,
    October 5, 2012. RDA, however, argues that it is not liable for any liquidated damages, because
    the NAVFAC should have extended the contract completion date by 313 days to account for
    excusable delays. In the alternative, RDA argues that it is not liable for liquidated damages that
    accrued after the NAVFAC’s February 21, 2013 Notice Of Termination, because RDA did not
    default on the October 13, 2009 Contract.
    65
    a.      Whether RDA Was Entitled To An Extension Of The Contract
    Completion Date.
    “[A] party asserting that liquidated damages were improperly assessed bears the burden of
    showing the extent of the excusable delay to which it is entitled.” Sauer Inc. v. Danzig, 
    224 F.3d 1340
    , 1347 (Fed. Cir. 2000). Specifically, the party asserting the excusable delay, must show that:
    (1) the delay resulted from “unforeseeable causes beyond the control and without the fault or
    negligence of the [party]”; and (2) the party “took reasonable action to perform the contract
    notwithstanding the occurrence of such excuse.” 
    48 C.F.R. § 52.249-10
    (b)(1); see also
    International Elecs. Corp. v. United States, 
    646 F.2d 496
    , 510 (Ct. Cl. 1981).
    Regarding the first element, RDA argues that most of the excusable delay was caused by
    “unforeseen obstructions that prevented RDA from installing [sheet piles at the bulkhead].” Pl.
    PT Br. at 21. Although these obstructions may have been “unforeseen,” RDA failed to demonstrate
    that they were “beyond the control and without [RDA’s] fault or negligence.” 
    48 C.F.R. § 52.249
    -
    10(b)(1) (emphasis added). The Government proffered the expert opinion of Mr. Helmes, P.E.,
    that, “[t]he difficulties RDA encountered installing the sheet pile return walls were largely a result
    of RDA’s failure to properly complete its predecessor activities, which involve[d] removal of piles
    and all the required rock fill.” DX 729 at 25 (emphasis added) (Helmes Expert Report). RDA,
    however, did not present any evidence to rebut Mr. Helmes’ opinion. At trial, RDA proffered two
    witnesses with experience in construction scheduling—Mr. Mitchell and Mr. Sivalogan—to testify
    that RDA’s progress on the October 13, 2009 Contract was delayed. But, neither witness addressed
    what caused the obstructions. See, e.g., TR at 1810 (Mitchell) (“[THE GOVERNMENT’S
    COUNSEL]: What about causation? You didn’t determine the cause of each of the delays you
    identified, correct? [MR. MITCHELL]: That’s correct.”).
    Regarding the second element, RDA failed to demonstrate that it “took reasonable action
    to perform the [October 13, 2009 Contract] notwithstanding the [obstructions].” International
    Elecs. Corp., 646 F.2d at 510. RDA argues that it is entitled to a 313-day extension of the contract
    completion date, because RDA was forced to stop all contract work pending the NAVFAC’s
    approval of obstruction drilling. Pl. PT Resp. at 18–19. RDA, however, does not cite a single
    piece of evidence that supports its assertion that obstruction drilling could not begin without the
    NAVFAC’s authorization. To the contrary, the October 13, 2009 Contract expressly required
    RDA to begin drilling pending a formal modification. DX 1 at 14 (incorporating 
    48 C.F.R. § 52.233-1
    (i) (“The Contractor shall proceed diligently with performance of this contract, pending
    final resolution of any request for relief, claim, appeal, or action arising under the contract, and
    comply with any decision of the Contracting Officer.”)). And, RDA’s November 11, 2016 Post
    Trial Brief admits that, on at least one occasion, “RDA proceeded with . . . obstruction drilling in
    advance of receiving formal authorization.” Pl. PT Br. at 25 (emphasis added).
    In addition, the record evidence shows that RDA stopped contract performance voluntarily,
    because it hoped to secure a contract modification that fully compensated RDA for the necessary
    obstruction drilling before it performed such work. Indeed, RDA’s Project Manager advised the
    NAVFAC that “RDA will not continue to perform work on [the bulkhead] without . . . a Contract
    Modification.” DX 273 at 1. Similarly, RDA’s President stated: “I believe that [i]t is in RDA’s
    and the Navy’s best interest to hold off on the obstruction drilling . . . until we reach an agreement
    on a unilateral modification.” DX 570 at 1.
    66
    For these reasons, the court has determined that RDA was not entitled to an extension of
    the October 13, 2009 Contract’s completion date for excusable delays.
    b.         Whether The Naval Facilities Command’s February 21, 2013
    Termination Of The October 13, 2009 Contract For Default
    Should Be Converted Into A Termination For Convenience.
    i.       Whether The February 21, 2013 Notice Of Termination
    Was “Fair And Impartial,” Pursuant To 
    48 C.F.R. § 1.602-2
    .
    As an initial matter, RDA argues that The CO’s February 21, 2013 default-termination
    decision should be set aside—regardless of the merits—because the decision was not a fair and
    impartial “product of [her] personal and independent judgment.” Pl. PT Resp. at 14 (quoting N.
    Star Alaska Hous. Corp. v. United States, 
    76 Fed. Cl. 158
    , 209 (2007)).
    Under the CDA, “[e]ach claim by the Federal Government against a contractor relating to
    a contract shall be the subject of a written decision by the contracting officer.” 
    41 U.S.C. § 7103
    (a)(3). In addition, the CO’s decision must be “fair and impartial.” 
    48 C.F.R. § 1.602-2.19
    And, although there is no “implied prohibition against [the CO] first obtaining or even agreeing
    with the views of others,” Pac. Architects & Eng’rs, Inc. v. United States, 
    491 F.2d 734
    , 744 (Ct.
    Cl. 1974), a CO’s default termination decision must be the result of her personal and independent
    judgment, such that “a decision by someone else is a nullity.” N.Y. Shipbuilding v. United States,
    
    385 F.2d 427
    , 439 (Ct. Cl. 1967).
    On February 21, 2013, the CO issued a written decision providing her reasons for
    terminating the contract for default, i.e., RDA failed to complete the project by its contract
    completion date, and also affirmatively repudiated the contractual requirement to remove broken
    H-piles. DX 650 at 1–4. RDA argues that this decision demonstrates a “clear lack of
    independence,” however, because the CO: (1) lacked technical construction knowledge; (2) relied
    on the advice of the field staff, including Mr. Germano, the Supervisory General Engineer for
    19
    FAR 1.602-2 provides, in relevant part, that:
    Contracting officers are responsible for ensuring performance of all necessary
    actions for effective contracting, ensuring compliance with the terms of the
    contract, and safeguarding the interests of the United States in its contractual
    relationships. In order to perform these responsibilities, contracting officers should
    be allowed wide latitude to exercise business judgment. Contracting officers
    shall—
    ...
    (b) Ensure that contractors receive impartial, fair, and equitable treatment; and
    (c) Request and consider the advice of specialists in audit, law, engineering,
    information security, transportation, and other fields, as appropriate.
    
    48 C.F.R. § 1.602-2
    .
    67
    NAVFAC, and Mr. Rachupcka, the Construction Project Manager for NAVFAC; and (3) did not
    adopt RDA’s arguments with respect to the removal of the H-piles. Pl. PT Resp. at 14–15.
    In fact, that the CO did not have specialized construction knowledge, does not mean that
    her decision was not independent. As the FAR makes clear, COs are specialists in contract
    administration that “should be allowed wide latitude to exercise business judgment” in their
    dealings with contractors. 
    48 C.F.R. § 1.602-2
    . The FAR also recognizes that COs are not experts
    in other subject matter and states that they should “request and consider the advice of specialists
    in audit, law, engineering, information security, transportation, and other fields, as appropriate,”
    “[s]ecure assistance from legal and other advisors,” and “coordinate with the contract
    administration office or contracting office, as appropriate.” 
    48 C.F.R. §§ 1.602-2
    (c), 33.211. It
    was for this reason that the CO relied on the advice of Mr. Germano and Mr. Rachupka, who had
    specialized construction knowledge and were involved in the day-to-day management of the
    October 13, 2009 contract. That she relied on this advice does not render her decision non-
    independent, despite RDA’s arguments to the contrary.
    RDA cites to several cases where the United States Court of Federal Claims found a CO’s
    decision to be lacking independent judgment, but those cases are distinguishable. In Fireman’s
    Fund Ins. Co. v. United States, 
    92 Fed. Cl. 598
     (2010), the CO did not review a claim decision,
    prepared by counsel, before signing it. 
    Id.
     at 697–98. Similarly, in CEMS, Inc. v. United States,
    
    65 Fed. Cl. 473
     (2005), the CO “releas[ed] authority to subordinates and remain[ed] remarkably
    detached from the decision-making process,” and denied claims “in which even government error
    or changes were acknowledged.” 
    Id.
     at 479–80. Likewise in North Star Alaska Housing Corp. v.
    United States, 
    76 Fed. Cl. 158
     (2007), the CO gave in to pressure from other Government officials
    to abdicate his responsibility to be impartial and agreed to support contract interpretations made
    by officials, who were openly contemptuous of the contractor. 
    Id.
     at 210–11.
    In this case, the CO’s testimony shows no abdication of responsibility. Before making the
    default-termination decision, the CO reviewed the contract documents, the contract modifications,
    and letters sent by RDA, wherein RDA claimed entitlement to increased costs and time to complete
    the project. TR at 2498 (Kahler).20 The CO then sent the January 31, 2013 Show Cause Letter,
    affording RDA an opportunity to explain why the contract should not be terminated for default.
    DX 636 at 1–2. But, the CO was not persuaded by RDA’s February 1, 2013 Response, because
    RDA did not address her concerns in sufficient detail nor express urgency in getting the project
    done. TR at 2503 (Kahler). In addition, RDA’s February 1, 2013 Response reiterated RDA’s
    earlier position, as expressed in RDA’s January 18, 2013 Letter, that RDA would not conduct any
    work related to H-pile removal without a change order. TR 2503–04 (Kahler); see also DX 637
    at 1–2 (1/18/13 RDA letter). Based upon this record, the court finds that the CO used her
    20
    RDA also asserts that Ms. Kahler’s termination decision is defective because she did not
    review the claim file associated with RDA’s April 21, 2010 Certified Claim. Pl. PT Resp. at 14.
    But, Ms. Kahler testified that she did not review that claim file because a final decision on that
    Certified Claim was issued by a NAVFAC CO on August 31, 2010. TR at 2606 (Kahler); see also
    DX 193 at 1–4 (8/31/10 Certified Claim denial decision).
    68
    independent judgment in deciding that RDA was in default, and she did not abdicate her decision-
    making responsibility.
    RDA also asserts that the CO’s default-termination decision was flawed because: she did
    not understand that removal of the H-piles would entail considerable cost; she was not aware that
    FST recommended that the H-piles be cut; and she mistakenly was informed by the Government’s
    counsel that RDA intentionally broke H-piles. Pl. PT Resp. at 15. But, RDA’s argument does not
    establish that the CO did not use independent decision-making. And, as previously explained, the
    H-pile removal was required by the express terms of the October 13, 2009 contract. DX 1 at 82
    (Demolition Note 3: “REMOVE PILES IN THEIR ENTIRETY”); PX 12 at 3 (picture). Moreover,
    the record evidences that RDA did in fact intentionally cut the H-piles, pursuant to RDA’s March
    29, 2010 removal plan. DX 108 at 3–4.
    For these reasons, the court has determined that the February 21, 2013 default-termination
    should not be set aside based upon a lack of independence or fairness on the part of the CO.
    ii.     Whether The Naval Facilities Command Established
    That RDA Construction Was In Default As Of The
    Termination Date.
    The October 13, 2009 Contract includes a default provision that allows the Government to
    terminate the Contract for default if “the Contractor refuses or fails to prosecute the work or any
    separable part, with the diligence that will insure its completion within the time specified in this
    contract including any extension, or fails to complete the work within this time[.]” DX 1 at 15
    (incorporating 
    48 C.F.R. § 52.249-10
    (a)). In addition, the October 13, 2009 Contract’s default
    clause states that the Government retains “any other rights and remedies provided by law[.]” DX
    1 at 15 (incorporating 
    48 C.F.R. § 52.249-10
    (d)). This includes the right to terminate the October
    13, 2009 Contract upon a material breach or repudiation of a contract requirement. See Dow Chem.
    Co. v. United States, 
    226 F.3d 1334
    , 1346 (Fed. Cir. 2000) (“A material breach, or repudiation,
    gives rise to a right to exercise a termination provision in a contract[.]”); see also Cities Serv.
    Helex, Inc. v. United States, 
    543 F.2d 1306
    , 1313 (Ct. Cl. 1976) (“A material breach . . . gives the
    injured party the right to end the agreement[.]”).
    The Government bears the burden of proving that a termination for default was justified.
    See Lisbon Contractors, Inc. v. United States, 
    828 F.2d 759
    , 765 (Fed. Cir. 1987) (“[W]e conclude
    that the government should bear the burden of proof with respect to the issue of whether
    termination for default was justified[.]”). The Government satisfies this burden if it can
    demonstrate that “there was an existing ground for a default-termination, regardless of whether
    that ground was known to the contracting officer at the time of the termination.” Empire Energy
    Mgmt. Sys., Inc. v. Roche, 
    362 F.3d 1343
    , 1357 (Fed. Cir. 2004); see also Kelso v. Kirk Bros.
    Mech. Contractors, Inc., 
    16 F.3d 1173
    , 1175 (Fed. Cir. 1994) (“This court sustains a default
    termination if justified by the circumstances at the time of termination, regardless of whether the
    Government originally removed the contractor for another reason.”).
    Here, the Government argues that RDA defaulted on the October 13, 2009 Contract,
    because RDA failed to complete performance by the contract completion date, i.e., October 5,
    2012. RDA does not dispute that it had not completed performance of the October 13, 2009
    69
    Contract by October 5, 2012. In fact, Mr. Sivalogan, a construction scheduling consultant
    employed by RDA, testified that as of November 8, 2012, one month after the completion date,
    RDA required 198 days to complete the October 13, 2009 Contract. TR at 957 (Sivalogan).
    Instead, RDA argues that it was not in default, because it was entitled to a 313-day extension of
    the completion date for excusable delays. For the reasons provided above, however, RDA has
    failed to demonstrate any excusable delays.
    Alternatively, the Government argues that RDA repudiated the October 13, 2009
    Contract’s requirement to remove all of the H-piles in their entirety. “At common law, anticipatory
    repudiation of a contract required an unambiguous and unequivocal statement that the obligor
    would not or could not perform the contract.” Danzig v. AEC Corp., 
    224 F.3d 1333
    , 1337 (Fed.
    Cir. 2000). Under modern Government contract law, however,
    anticipatory repudiation includes cases in which reasonable grounds support the
    obligee’s belief that the obligor will breach the contract. In that setting, the obligee
    ‘may demand adequate assurance of due performance’ and if the obligor does not
    give such assurances, the obligee may treat the failure to do so as a repudiation of
    the contract.
    
    Id.
     at 1337–38 (emphasis added) (quoting Restatement (Second) of Contracts § 251 (1981)).
    On November 7, 2012, the NAVFAC rejected a request from RDA to waive the October
    13, 2009 Contract’s requirement to “remove all piles in their entirety.” PX 99 at 1. On January
    18, 2013, RDA informed the NAVFAC that RDA would not remove any additional piles, unless
    the NAVFAC provided an equitable adjustment of $1,096,858.26 and three months to perform that
    work. DX 626 at 2. On January 31, 2013, in response to RDA’s January 18, 2013 letter, the
    NAVFAC ordered RDA to show cause why the October 13, 2009 Contract should not be
    terminated on the basis that RDA repudiated its contractual obligation to remove all of the H-piles.
    DX 636 at 1. On February 1, 2013, RDA responded to the NAVFAC’s Show Cause Letter stating
    that its position with regard to the H-piles remained the same, i.e., RDA would not perform the
    work, without an equitable adjustment. DX 637 at 2. On February 21, 2013, RDA terminated the
    October 13, 2009 Contract for default, citing anticipatory repudiation as one of the grounds. DX
    650 at 2–3.
    This sequence of events demonstrates that RDA’s conduct leading up to the January 31,
    2013 Show Cause Letter provided reasonable grounds for the NAVFAC to believe that RDA
    would not remove the H-piles in their entirety and thereby breach the October 13, 2009 Contract.
    Accordingly, the NAVFAC had a reasonable basis to “demand adequate assurance” that RDA
    would remove the remaining piles. RDA’s February 1, 2013 Response to the January 31, 2013
    Show Cause Letter clearly failed to provide such assurances, as it plainly stated that RDA would
    not perform the remaining work. DX 637 at 2.
    70
    For these reasons, the court has determined that the NAVFAC’s February 21, 2013 default
    termination of the October 13, 2009 Contract was justified.21
    iii.    Whether The Naval Facilities Command Breached The
    October 13, 2009 Contract Thereby Relieving RDA
    Construction Corp. Of Any Consequences Stemming
    From The February 21, 2013 Default Termination.
    A material breach of contract by the Government, “provides [the contractor] with a legal
    right to avoid the contract, discharges [the contractor’s] duty to perform, and relieves [the
    contractor] of the default termination and its consequences.” Malone v. United States, 
    849 F.2d 1441
    , 1446 (Fed. Cir. 1988). Here, RDA argues that it is relieved of the February 21, 2013 default
    termination and its consequences, because the NAVFAC breached the October 13, 2009 Contract
    by:
    (1)     effecting a cardinal change to the October 13, 2009 Contract (Pl. PT Br. at 38);
    (2)     failing to timely authorize obstruction drilling at the bulkhead (Pl. PT Br. at 42);
    (3)     failing to disclose the Appledore Report and FST Report during the procurement
    process (Pl. PT Br. at 47–56);
    (4)     including a defective specification in the October 13, 2009 Contract (Pl. PT Br. at
    56); and
    (5)     violating the duty of good faith and fair dealing (Pl. PT Br. at 57–61).
    The court has addressed all of RDA’s breach of contract arguments in its discussion of
    Counts I–VIII of the May 7, 2015 Second Amended Complaint, and has determined that the
    NAVFAC did not breach the October 13, 2009 Contract. Therefore, RDA is not relieved of the
    February 21, 2013 default termination and its consequences.
    In sum, the court has determined that RDA is liable for liquidated damages.
    21
    The Government provides six alternative grounds for the court to find that the
    NAVFAC’s February 21, 2013 default termination was justified. Gov’t PT Br. at 42. But, to
    demonstrate that a default termination was justified, the Government only needs to show that
    “there was an existing ground . . . at the time of the termination.” Empire Energy, 
    362 F.3d at 1357
    . In other words, the Government only needs to succeed on one of its six alternative
    arguments. Here, the court has considered the Government’s two strongest grounds in support of
    the February 21, 2013 default termination and has determined that either ground was sufficient to
    justify termination. For this reason, the court does not find it necessary to address the
    Government’s four other grounds.
    71
    c.     The Quantum Of Liquidated Damages That The Naval
    Facilities Command Is Entitled To Recover.
    The Government argues that it is entitled to recover liquidated damages for 712 days of
    delay. RDA responds that the October 13, 2009 Contract’s completion date should be extended
    by 313 days for excusable delays, but otherwise does not dispute the amount claimed by the
    Government. The court, however, previously rejected RDA’s excusable-delay argument.
    Therefore, the court has determined that the NAVFAC is entitled to liquidated damages for 712
    days of delay.
    The October 13, 2009 Contract provides that “the Contractor shall pay liquidated damages
    to the Government in the amount of [$3,531] for each calendar day of delay[.]” DX 1 at 17, 586.
    Applying the $3,531 daily rate, the NAVFAC is entitled to a total of $2,514,072 in liquidated
    damages. This amount is offset by the NAVFAC’s retention of $305,867.99 in payments owed to
    RDA. DX 711 at 1. Accordingly, RDA owes the NAVFAC $2,208,204.01 in liquidated damages.
    D.       Counterclaim II: Whether RDA Construction Corp. Is Liable For Damages
    Under The Contract Dispute Act’s Anti-Fraud Provision, 
    41 U.S.C. § 7103
    (c)(2).
    The Government’s June 12, 2015 Answer alleges that RDA is liable for $82,974.70 in
    damages for violating the CDA’s anti-fraud provision, 
    41 U.S.C. § 7103
    (c)(2).22 6/12/15 Gov’t
    Answer ¶¶ 177–182.
    1.     The Government’s Argument.
    On November 28, 2012, J.P. Riley inspected a Manitowoc 4100 crane that RDA was using
    and noted several items that needed repair. DX 677 at 3. On January 14, 2013, the NAVFAC
    directed RDA to take the crane out of service for a re-inspection. DX 677 at 28. On January 16,
    2013, J.P. Riley conducted a second inspection and issued a Deficiency/Recommendation Report,
    finding that several problems identified in the November 28, 2012 report were not addressed and
    noting that “any Deficiency . . . Shall be repaired or defective parts be replaced before continued
    use.” DX 677 at 52.
    22
    The CDA, in relevant part, provides:
    [i]f a contractor is unable to support any part of the contractor’s claim and it is
    determined that the inability is attributable to a misrepresentation of fact or fraud
    by the contractor, then the contractor is liable to the Federal Government for an
    amount equal to the unsupported part of the claim plus all of the Federal
    Government’ s costs attributable to reviewing the unsupported part of the claim.
    Liability under this paragraph shall be determined within 6 years of the commission
    of the misrepresentation of fact or fraud.
    
    41 U.S.C. § 7103
    (c)(2).
    72
    On March 18, 2013, RDA sent a letter to the NAVFAC, certifying a claim for $82,974.70
    in additional costs and requesting a 112-day contract time extension in order to comply with the
    NAVFAC’s January 14, 2013 directive. Gov’t PT Br. at 37–39; see also DX 677 at 114–15
    (3/18/13 certified claim).
    The Government contends that this claim was without merit, because “[t]here is no basis
    to hold [the NAVFAC] liable for RDA’s inability to keep its crane in safe operating condition.”
    Gov’t PT Br. at 37. Indeed, RDA’s witnesses had no explanation for claiming an “indefensibly
    inflated” $82,974.40 in costs. Gov’t PT Br. at 70–71.
    The Government also argues that the March 18, 2013 Certified Claim included two
    “blatantly false statements,” i.e., that: (1) RDA’s “mechanics made [the] noted repairs” after the
    crane was first inspected on November 28, 2012; and (2) that “[J.P. Riley] did not take the crane
    out of service [after the November 28, 2012 inspection] or at any point thereafter.” Gov’t PT Br.
    at 37 (citing DX 677 at 114–15). RDA, however, did not make all of the noted repairs and “fully
    understood” that the crane inspector took the crane out of service after the January 16, 2013 re-
    inspection. Gov’t PT Br. at 37–38.
    The March 18, 2013 Certified Claim for crane re-inspection and repair costs subsequently
    was incorporated as PCO 47 in the July 3, 2013 Certified Claim (DX 691 at 30), which was in turn
    incorporated into the May 7, 2015 Second Amended Complaint (5/7/15 Sec. Am. Compl. at ¶ 92).
    As a matter of law, the Government is entitled to an “amount equal to the unsupported part of [a]
    claim.” 
    41 U.S.C. § 7103
    (c)(2). Since the $82,974.70 claimed in the May 7, 2015 Second
    Amended Complaint is attributed solely to RDA’s fraudulent activity, the Government is owed
    $82,974.70 in damages. Gov’t PT Br. at 69, 72 (citing 
    41 U.S.C. § 7103
    (c)(2)).
    2.      Plaintiff’s Response.
    RDA responds that the Government cannot establish the requisite scienter for liability
    under the CDA, because the NAVFAC “injected itself into the crane inspection and re-inspection
    process and, hence, had full knowledge at all times of the status of the inspections and whether the
    crane had been taken out of service.” Pl. PT Resp. at 47. “Back and forth correspondence”
    establishes that the NAVFAC was aware of all issues regarding repairs and re-inspections;
    therefore RDA could not have acted with intent to defraud. Pl. PT Resp. at 45–47.
    With respect to whether RDA violated the CDA, by submitting an “indefensibly inflated”
    claim, RDA responds that its claim was made in good faith. Pl. PT Resp. at 47 (citing Horn &
    Assoc., Inc., v. United States, 
    123 Fed. Cl. 728
    , 783 (2015) (determining that a certified claim did
    not violate the CDA, when the contractor mislabeled costs as “actual costs incurred,” so the
    contractor acted in good faith and did not submit certified claim to obtain “leverage” against the
    Government)).
    3.      The Court’s Resolution.
    Under the CDA’s anti-fraud provision, a contractor that is “unable to support any part of
    the contractor’s claim” as a result of “misrepresentation of fact or fraud” is liable to the
    Government for an amount equal “to the unsupported part of the claim plus all of the Federal
    Government’s costs attributable to reviewing the unsupported part of the claim.” 
    41 U.S.C. § 73
    7103(c)(2). A “misrepresentation of fact” is “a false statement of substantive fact, or conduct that
    leads to a belief of a substantive fact material to proper understanding of the matter in hand, made
    with intent to deceive or mislead.” 
    41 U.S.C. § 7101
    (9); see also Commercial Contractors, Inc. v.
    United States, 
    154 F.3d 1357
    , 1362 (Fed. Cir. 1998) (“To recover under the CDA, the government
    is required to establish that the contractor made false or fraudulent statements in its submitted
    claim with an intent to deceive or mislead the government.” (emphasis added)); see also Daewoo
    Engineering & Const. Co. v. United States, 
    557 F.3d 1332
    , 1335 (Fed. Cir. 2009) (“The
    [G]overnment must establish this falsity and intent by a preponderance of the evidence.”). In short,
    to establish a violation of the CDA, the Government must prove: (1) falsity, (2) materiality, and
    (3) intent to defraud. See 
    41 U.S.C. §§ 7101
    (9), 7103(c)(2).
    In this case, the Government asserts that RDA’s claim for crane re-inspection costs is
    fraudulent because it was: (1) “baseless”; (2) “indefensibly inflated”; and (3) “premised on
    misrepresentations of fact.” Gov’t PT Br. at 37, 70–71. The court will address each of these
    arguments in turn.
    a.      Whether RDA Construction Corp.’s Crane Re-Inspection
    Claim Was “Baseless.”
    The Government argues that RDA’s claim for crane re-inspection costs and repair of the
    Manitowoc 4100W crane is fraudulent, because RDA lacked any “colorable basis to demand
    compensation” from the NAVFAC. Gov’t PT Br. at 71. But, RDA’s March 18, 2013 Certified
    Claim, July 3, 2013 Certified Claim and May 7, 2015 Amended Complaint are rooted in a long-
    running dispute about whether the NAVFAC acted within its authority, when it ordered the crane
    to be taken out of service. DX 677 at 114–115; see also Pl. PT Br. at 31, 61, 64 (arguing that the
    NAVFAC did not have any contractual basis for requiring the crane to be re-inspected and RDA
    incurred costs as a result).
    The fact that RDA and the Government disagree about whether the NAVFAC acted
    properly does not render RDA’s claim fraudulent. The Government cites to the United States
    Court of Appeals for the Federal Circuit’s holding in Daewoo for the proposition that “[i]t is well
    established that a baseless certified claim is a fraudulent claim.” 
    557 F.3d at 1339
    ; see also 
    id.
     at
    1339–40 (“For instance . . . if a party knows that its claim that it is entitled to funds under a letter
    of credit ‘has no plausible or colorable basis,’ then the party’s ‘effort to obtain the money is
    fraudulent.’” (quoting Itek Corp. v. First Nat’l Bank of Boston, 
    730 F.2d 19
    , 25 (1st Cir. 1984)).
    RDA’s claim, however, was not “baseless,” in the manner of the contractor’s claim in Daewoo.
    In that case, a contractor submitted an inflated claim as a “negotiating ploy” and did not honestly
    believe that the Government owed it the amounts claimed. See Daewoo, 
    557 F.3d at 1339
     (quoting
    Daewoo Engineering v. United States, 
    73 Fed. Cl. 547
    , 588, 589 (2006)). In this case, the
    Government did not proffer any evidence that RDA certified this claim as a “negotiating ploy” or
    otherwise did not honestly believe that the NAVFAC acted improperly.
    For these reasons, the court has determined that RDA’s re-inspection claim was not
    “baseless.”
    74
    b.     Whether RDA Construction Corp.’s Crane Re-Inspection
    Claim Was “Indefensibly Inflated.”
    Next, the Government argues that RDA’s $82,974.70 claim for crane re-inspection costs
    was fraudulent, because “RDA’s witnesses had no explanation for the amount claimed, [that] was
    indefensibly inflated.” Gov’t PT Br. at 71. Specifically, the Government cites the following
    testimony of RDA’s Project Manager, Mark Wallis:
    [THE GOVERNMENT’S COUNSEL]: Can you explain to me how you calculated
    [the $82,974.70?] It might be on the same sheet, [DX] 657.14.
    [MR. WALLIS]: It is. The bottom, it’s the bottom amount on total cost, Line 14.
    [THE GOVERNMENT’S COUNSEL]: Look at rental equipment on Line 5.
    $52,823. It’s not rental equipment, right?
    [MR. WALLIS]: No, it isn’t.
    [THE GOVERNMENT’S COUNSEL]: It’s actually owned equipment?
    [MR. WALLIS]: Correct.
    [THE GOVERNMENT’S COUNSEL]: Where does that number come from?
    [MR. WALLIS]: Worksheet one.
    [THE GOVERNMENT’S COUNSEL]: Worksheet one on DX 657.15, can you
    explain the calculation for the 4100 crane?
    [MR. WALLIS]: 640 at the 82.63.
    [THE GOVERNMENT’S COUNSEL]: How did you get 640 hours? Based on a
    40–hour workweek?
    [MR. WALLIS]: Yes. I believe so, yes.
    [THE GOVERNMENT’S COUNSEL]: If you divide 640 by 40, how many weeks
    are you talking about? . . .
    [MR. WALLIS]: 16.
    [THE GOVERNMENT’S COUNSEL]: 16 weeks?
    [MR. WALLIS]: Wait a minute. 16.
    [THE GOVERNMENT’S COUNSEL]: 16 weeks, roughly four months?
    [MR. WALLIS]: Correct.
    75
    [THE GOVERNMENT’S COUNSEL]: What date are we going to start that four
    months on? Would it be December 13, 2012, from DX 657.14?
    [MR. WALLIS]: Well according to what it says on the verbiage at the bottom, it
    would be starting December 13.
    [THE GOVERNMENT’S COUNSEL]: So if you start December 13, 2012, and run
    about four months, where do you get to?
    [MR. WALLIS]: Beyond that. Middle of April.
    [THE GOVERNMENT’S COUNSEL]: Why did you claim 640 for the crane?
    [MR. WALLIS]: I can’t answer that because I don’t have — I can’t answer that.
    TR at 796–97.
    As this testimony demonstrates, the cost data submitted with RDA’s March 18, 2013 claim
    was both confusing and incorrect. Specifically, RDA requested a time extension of “80 work days
    or 112 calendar days . . . based on the number of shifts that the Manitowoc 4100W was [not in
    service] from December 13, 2012[, i.e., the date] when all repairs had been completed[,] until
    February 28, 2013 when the re-inspection [was] completed.” PX 148 at 14; DX 657 at 14 (same).
    Eighty work days at eight hours equals 640 hours; RDA multiplied this figure by the Manitowoc
    4100W crane’s hourly “Standby Rate” of $82.63, to arrive at a total idle equipment cost of
    $52,883.20. PX 148 at 14–15; DX 657 at 14–15. This figure was added together with labor costs,
    overhead, a bond premium, and $5740.00 in unspecified sub-contractor costs to reach a total of
    $82,974.70. PX 148 at 14; DX 657 at 14.
    The record supports RDA’s assertion that the repairs were made to the crane on December
    13, 2012. DX 677 at 13. But, RDA’s calculations are incorrect, because there were only 77
    calendar days between December 13, 2012 and February 28, 2013, and not all were “work days.”
    An incorrect and confusing claim, however, is not necessarily fraudulent. In order to demonstrate
    that the March 18, 2013 claim was submitted in violation of the CDA, the Government must
    establish by preponderant evidence that RDA acted with intent to deceive or mislead. See Daewoo,
    
    557 F.3d at 1335
     (“The [G]overnment must establish . . . falsity and intent by a preponderance of
    the evidence.”).
    At trial, Mr. Kelley, RDA’s President, testified that the 640 hour/80 work day figure was a
    “mistake,” and admitted that it was impossible for 112 days to have passed between December 13,
    2012, and February 28, 2013. TR at 1691–92 (Kelley). Mr. Kelley also testified that the work
    associated with RDA’s broken-down “CAT 375” excavating machine may have been erroneously
    charged to the March 18, 2013 claim. TR at 1693 (Kelley) (“No, it’s clearly inaccurate with the
    date and there was also some other issues with that once we started to dig into it. . . . . There were
    like some issues that were charged to it that shouldn’t have been charged to it . . . [including] some
    work on the 375[.]”). But, Mr. Kelley maintained that the claim was submitted in good faith and
    he and Mr. Wallis believed that RDA was entitled to those costs, when the certified claims were
    submitted to the NAVFAC. TR at 1694 (Kelley) (“I still stand that I in good faith was trying to
    76
    certify that claim . . . . I relied on the people in good faith that we weren’t defrauding anybody . .
    . . We feel strongly that we’re entitled to these numbers.”).
    The United States Court of Appeals for the Federal Circuit has held that a contractor may
    violate the CDA, if a claim is based on a “baseless calculation.” Daewoo, 577 F.3d at 1339. But,
    Mr. Kelley’s and Mr. Wallis’s testimony is substantially different than the evidence in Daewoo.
    See id. at 1335. In that case, the contractor’s witnesses gave false testimony and were found to be
    not credible. See Daewoo, 73 Fed. Cl. at 569–570. In addition, the testimony about the calculation
    of the certified claim in that case “left no doubt that [the claim] was unsupportable and was pursued
    by [the contractor] with fraudulent intent.” Id. at 574 n.45 (emphasis added).
    In the judgment of the court, Mr. Kelley and Mr. Wallis admitted and credibly explained
    that the March 18, 2013 claim was incorrect, but was not submitted with an intent to mislead or
    deceive the NAVFAC. The Government has not offered preponderant evidence to the contrary.
    For these reasons, the court has determined that RDA did not submit an “indefensibly
    inflated” claim.
    c.      Whether RDA Construction Corp.’s Crane Re-Inspection
    Claim Was “Premised On Affirmative Misrepresentations Of
    Fact.”
    In addition, the Government argues that RDA’s March 18, 2013 Certified Claim was
    fraudulent, because it included “affirmative misrepresentations of fact regarding whether the
    repairs had been made after the first inspection and whether the crane inspector took the crane out
    of service.” Gov’t PT Br. at 71. Specifically, the March 18, 2013 Certified Claim included the
    following statements that the Government alleges were false, material, and made with the intent
    to defraud:
    (1) On November 28, 2012[,] we performed the “Annual Crane Inspection” on our
    Manitowoc 4100W. The inspection was performed by J.P. Riley and both an
    annual crane inspection sticker and deficiency report were issued by the crane
    inspector. RDA’s mechanics made the noted repairs and the deficiency report was
    signed and returned to J.P. Riley as required on his inspection report to indicate that
    the deficiencies had been addressed.
    (2) In completing the annual [crane] inspection on November 28, 2012 J.P. Riley issued
    a certification. Furthermore, it is important to acknowledge that as a qualified
    inspector J.P. Riley did not take the crane out of service at this point [i.e., November
    77
    28, 2012] or at any point thereafter. NAVFAC interpreted the relevant documents
    and specification and directed RDA not to use the crane until it was re-inspected.
    DX 677 at 114–15 (emphasis added).23
    The statement that RDA’s mechanics made the repairs identified by J.P. Riley after the
    November 28, 2012 inspection, but prior to the NAVFAC taking the crane out of service and J.P.
    Riley’s second re-inspection, in fact, was false, because one of the noted “Deficiencies” was not
    repaired. The November 28, 2012 Deficiency Report listed the following deficiencies:
    (1) “Hydraulic leaks”; (2) “Fire Extinguisher”; (3) “Brake Adjustments”; (4) “Wipers”; and (5)
    “Hook Rollers Need Adjustments.”               DX 677 at 6.            The January 16, 2013
    Deficiency/Recommendation Report listed the following deficiencies: (1) “Fire Extinguisher
    (2ND time on reinspection)24”; (2) “Paint/Corrosion Control (Boom Heal [sic])”; (3) “Hydraulic
    leaks (lower side at Pumps)”; (4) “Travel Locks (Left Side)”; and (5) “Lattice Members (10ft
    section near picture window).” DX 677 at 52 (emphasis added). Thus, although the March 18,
    2013 letter states that RDA’s mechanics made the noted repairs, there was one repair that was not
    made—a fire extinguisher was not installed.25
    With respect to the second statement, RDA is correct that J.P. Riley did not take the crane
    out of service on November 28, 2012. DX 677 at 3.26 But the latter part of the statement—that
    23
    The CDA defines a “misrepresentation of fact” as a “a false statement of substantive
    fact [that] leads to a belief of a substantive fact material to proper understanding of the matter in
    hand, made with intent to deceive or mislead.” 
    41 U.S.C. § 7101
    (9).
    24
    The Re-Inspection Deficiency/Recommendation Report, however, noted that the fire
    extinguisher was replaced on the same day that the inspection was conducted. DX 677 at 52.
    25
    The November 28, 2012 Deficiency Report and January 16, 2013 Deficiency/
    Recommendation Reports both noted “hydraulic leaks” in need of repair. DX 677 at 6, 52. The
    January 16, 2013 Deficiency/Recommendation Report, however, does not state that the hydraulic
    leaks found on January 16, 2013 were the same as the hydraulic leaks found on November 28,
    2012. DX 677 at 52. At trial, both Mr. Wallis, Construction Manager for RDA, and Mr. Kelley,
    President of RDA, credibly testified that the leaks could have been located at different points on
    the crane. TR at 792 (Wallis) (“The oil leaks are inconclusive, whether they were the same oil
    leaks on both times. It’s an old machine.”); see also TR at 1708–09 (Kelley) (“I would only think
    that the fire extinguisher was the same deficiency . . . . . When we go to the other one [the
    Deficiency/Recommendation Report is] more specific, to the right side of the pump.”). Mr.
    Rachupka, the NAVFAC’s Construction Manager, was present at the second re-inspection, and
    recorded that hydraulic leaks remained a problem. DX 625 at 1. But, at trial, Mr. Rachupka
    testified that he “couldn’t say for certain” whether these were the same leaks, because he was not
    present at the first inspection, and only assumed that the leaks were the same. TR at 2184
    (Rachupka).
    26
    Although J.P. Riley issued a “Deficiency Report,” that noted five deficiencies, this
    Report did not take the crane out of service. DX 677 at 6. The November 28, 2012 Deficiency
    Report only instructed RDA that all of the noted deficiencies required repair and that the Report
    78
    J.P. Riley did not take the Manitowoc 4100W crane out of service “at any point thereafter,” was
    false. On January 14, 2013, the NAVFAC took the crane out of service until J.P Riley
    “perform[ed] a re-inspection of the crane now that that the repairs have been made.” DX 677 at
    17. It was not until January 16, 2013 that J.P. Riley conducted a second inspection and issued a
    second Deficiency/Recommendation Report that actually took the crane out of service until certain
    repairs were made: “any Deficiency . . . Shall be repaired or defective parts be replaced before
    continued use.” DX 677 at 52.27
    Although the aforementioned statements were false, they were not of the character or
    quality that falsely “leads to a belief of a substantive fact material to proper understanding of the
    matter in hand” nor were they made with “intent to deceive.” 
    41 U.S.C. § 7101
    (9). RDA’s March
    18, 2013 claim letter was submitted to bring the dispute about the Manitowoc crane to a head.
    On January 16, 2013, Mr. Rachupka arrived for the re-inspection and saw that the missing
    fire extinguisher was not replaced. DX 625 at 1. But, the fire extinguisher was replaced shortly
    thereafter. DX 625 at 1. More importantly, Mr. Rachupka’s summary of the re-inspection
    demonstrates that the NAVFAC decided to keep the Manitowoc 4100W crane out of service,
    because: (1) the EM-385-1-1 required a qualified person to perform a load test after the crane’s
    brakes were repaired, but a load test could not be conducted on January 16, 2013, because of
    missing equipment; and (2) new defects were found during the re-inspection would require another
    re-inspection.28 DX 625 1–2. In other words, while RDA’s statement regarding its repairs was
    false, it was immaterial to the NAVFAC’s approach to RDA’s crane. The crane was taken out of
    service and remained out of service, because of the NAVFAC’s interpretation of the EM-385-1-1,
    and not because of J.P. Riley’s November 28, 2012 inspection and deficiency report. For these
    reasons, RDA’s statements, although inaccurate, could not have misled the Government into
    forming a false belief about a “substantive fact material to the proper understanding of the matter
    in hand.” 
    41 U.S.C. § 7101
    (9).
    For these reasons, the court has determined that, although the March 18, 2013 claim was
    confusing and incorrect, as Mr. Kelley and Mr. Wallis testified, it was not made with the intent to
    mislead or deceive the NAVFAC.
    should be signed and returned to J.P. Riley, within ten days of the repairs being made. DX 677 at
    6
    27
    In context, however, RDA’s statement can also be read as “J.P. Riley did not take the
    crane out of service on November 28, 2012, or at any point thereafter, until the NAVFAC’s January
    14, 2013 order taking the crane out of service.”
    28
    Specifically, Mr. Rachupka found that the crane’s boom lacing had to be replaced, so an
    additional load test would have to be conducted. DX 625 at 1. In addition, one of the cranes’
    tracks would not “lock” to allow proper turning. DX 625 at 1. RDA’s repair to the track’s locking
    mechanism would require an additional performance test. DX 625 at 1.
    79
    E.        Counterclaim III: Whether RDA Construction Corp. Forfeited All Claims
    Against The United States Under The Special Plea In Fraud Statute, 
    28 U.S.C. § 2514
    .
    The Government’s June 12, 2015 Amended Answer alleges that RDA’s July 3, 2013
    Certified Claim should be forfeited under the Special Plea in Fraud, 
    28 U.S.C. § 2514.29
     6/12/15
    Gov’t Answer ¶¶ 183–84. To establish a violation of the Special Plea in Fraud statute, the
    Government must show by “clear and convincing evidence that the contractor knew that its
    submitted claims were false, and that it intended to defraud the government by submitting those
    claims.” Veridyne Corp. v. United States, 
    758 F.3d 1371
    , 1367–77 (Fed Cir. 2014) (quoting
    Daewoo, 
    557 F.3d at 1341
    ). As a matter of law, however, proof of “negligence and ineptitude”
    does not evidence intent to defraud under the Special Plea in Fraud statute. See Miller v. United
    States, 
    213 Ct. Cl. 59
    , 69 (1977) (holding that a contractor’s “confused and incorrect” invoices,
    although evident of a “pattern of carelessness and slothfulness,” did not rise to the level of
    deliberate fraud.). In other words, the Government must prove three elements: (1) falsity; (2)
    knowledge of falsity; and (3) actual intent to defraud.
    The Government argues that the July 3, 2013 Certified Claim incorporates RDA’s earlier
    March 18, 2013 claim letter, and is fraudulent for the reasons previously addressed, i.e., it was: (1)
    “baseless”; (2) “inexplicably inflated”; and (3) “premised on misrepresentations of fact.” Gov’t
    PT Br. at 72–73.
    For the reasons previously discussed, the court has determined that the Government failed
    to establish even by a preponderance of the evidence that the March 18, 2013 Certified Claim was
    submitted with an intent to defraud, much less section 2514’s heightened “clear and convincing”
    evidentiary standard.
    29
    The Special Plea in Fraud Statute provides:
    A claim against the United States shall be forfeited to the United States by any
    person who corruptly practices or attempts to practice any fraud against the United
    States in the proof, statement, establishment, or allowance thereof.
    In such cases the United States Court of Federal Claims shall specifically find such
    fraud or attempt and render judgment of forfeiture.
    
    28 U.S.C. § 2514
    .
    80
    F.        Counterclaim IV: Whether RDA Construction Corp. Violated The False
    Claims Act.
    1.     The Government’s Argument.
    The Government argues that RDA violated the False Claims Act (“FCA”), 
    31 U.S.C. §§ 3729
    –3733,35 by submitting: (1) invoices that falsely certified that RDA’s concrete deck removal
    work complied with the October 13, 2009 Contract specifications (Invoices 2–21); (2) invoices
    that falsely certified that RDA’s rock fill removal work complied with the October 13, 2009
    Contract specifications (Invoices 5–21); (3) invoices that falsely certified that RDA made timely
    payments to its subcontractors and suppliers (Invoices 2 through 21); and (4) a July 3, 2013
    Certified Claim for crane re-inspection costs that was baseless, inflated and premised on factual
    misrepresentations. Gov’t PT Br. at 27, 29, 36–37.
    2.     Plaintiff’s Response.
    First, RDA responds that it did not defraud the FCA by submitting invoices for concrete
    deck removal, because the NAVFAC paid those invoices in full despite knowing that RDA’s work
    did not comply with the October 13, 2009 Contract’s specifications. Pl. PT Resp. at 36–39.
    Second, RDA responds that it did not violate the FCA by submitting invoices for rock fill
    removal, because RDA’s work satisfied the October 13, 2009 Contract’s requirements. Pl. PT
    Resp. at 39–40. To the extent that RDA’s rock fill removal did not satisfy all of the contract
    requirements, however, that failure does not constitute fraud, because it was premised on a
    reasonable interpretation of ambiguous contract terms. Pl. PT Resp. at 39–40. Moreover, the
    NAVFAC knew of the deficiencies in rock fill removal at the time that RDA submitted the
    challenged invoices, but nevertheless compensated RDA for that work. Therefore, the NAVFAC
    was not defrauded by the submission of those invoices. Pl. PT Resp. at 41, 43.
    35
    The False Claims Act, in relevant part, provides:
    (a) Liability for certain acts.--
    (1) In general. . . . [A]ny person who--
    (A) knowingly presents, or causes to be presented, a false or fraudulent
    claim for payment or approval;
    (B) knowingly makes, uses, or causes to be made or used, a false record or
    statement material to a false or fraudulent claim[,] . . .
    is liable to the United States Government for a civil penalty of not less than
    $5,000 and not more than [$11,000], plus 3 times the amount of damages
    which the Government sustains because of the act of that person.
    
    31 U.S.C. § 3729
    (a).
    81
    RDA also responds that it did not violate the FCA by falsely certifying that it made timely
    payments to its subcontractors and suppliers, because RDA’s misrepresentation was not material
    to the NAVFAC’s decision to pay the challenged invoices. Pl. PT Resp. at 44.
    Finally, RDA responds that the July 3, 2013 Certified Claim for crane re-inspection costs
    did not amount to fraud, because the NAVFAC had full knowledge of the facts underlying this
    dispute. Pl. PT Resp. at 45–46. Moreover, the July 3, 2013 Certified Claim was not inflated. Pl.
    PT Resp. at 46. At most, RDA made a good faith mistake in calculating damages. Pl. PT Resp.
    at 46.
    3.      The Court’s Resolution.
    To establish a violation of the FCA, the Government must demonstrate that:
    (1)     the contractor presented or caused to be presented to an agent of the United
    States a claim for payment;
    (2)     the claim was false or fraudulent; [and]
    (3)     the contractor knew the claim was false or fraudulent[.]
    Young-Montenay, Inc. v. United States, 
    15 F.3d 1040
    , 1043 (Fed. Cir. 1994).
    The FCA defines “know” or “knowing” as “actual knowledge of the information,”
    “deliberate ignorance of the truth or falsity of the information,” or “reckless disregard of the truth
    or falsity of the information.” 
    31 U.S.C. § 3729
    (b)(1)(A). Under the FCA, knowledge does not
    require “specific intent to defraud[.]” 
    31 U.S.C. § 3729
    (b)(1)(B).
    In addition, the United States Supreme Court has held that an alleged “misrepresentation
    about compliance with a statutory, regulatory, or contractual requirement must be material to the
    Government’s payment decision in order to be actionable under the [FCA].” Universal Health
    Services, Inc. v. United States, 
    136 S. Ct. 1989
    , 2002 (2016). When evaluating materiality under
    the FCA,
    the Government’s decision to expressly identify a provision as a condition of
    payment is relevant, but not automatically dispositive. Likewise, proof of
    materiality can include, but is not necessarily limited to, evidence that the defendant
    knows that the Government consistently refuses to pay claims in the mine run of
    cases based on noncompliance with the particular statutory, regulatory, or
    contractual requirement. Conversely, if the Government pays a particular claim in
    full despite its actual knowledge that certain requirements were violated, that is
    very strong evidence that those requirements are not material. Or, if the
    Government regularly pays a particular type of claim in full despite actual
    knowledge that certain requirements were violated, and has signaled no change in
    position, that is strong evidence that the requirements are not material.
    
    Id.
     at 2003–04 (emphasis added).
    82
    “In any action brought under [the FCA], the United States shall be required to prove all
    essential elements of the cause of action, including damages, by a preponderance of the evidence.”
    
    31 U.S.C. § 3731
    (d).
    a.      Whether RDA Construction Corp. Falsely Certified That Its
    Deck Removal Work Complied With The October 13, 2009
    Contract.
    The Government argues that on May 18, 2010 RDA submitted an invoice for deck
    demolition that violated the FCA by falsely certifying that RDA’s demolition work complied with
    the October 13, 2009 Contract’s specifications. Gov’t PT Br. at 29–32 (citing DX 80 at 26).
    Specifically, the Government argues that RDA did not comply with the contractual requirement
    that “DEMOLITION DEBRIS SHALL NOT BE ALLOWED TO FALL INTO THE WATER,”
    and that any “DEBRIS THAT FALLS INTO THE WATER SHALL BE REMOVED BEFORE
    THE END OF THE WORK DAY.” DX 1 at 82. The Government adds that, because RDA never
    removed the debris, the nineteen invoices RDA submitted after May 18, 2010 also violated the
    FCA. Gov’t PT Br. at 31–32.
    The parties agree that RDA: (1) presented Invoices 2–21 to the NAVFAC; (2) failed to
    remove all of the debris as required by the October 13, 2009 Contract; and (3) knew that it had not
    complied with all of the requirements of the October 13, 2009 Contract. RDA, however, argues
    that its misrepresentation did not violate the FCA, because it was not “material . . . to the
    Government’s payment decision[.]” Universal Health Services, 136 S. Ct. at 2002. The court
    agrees.
    The United States Supreme Court has stated that “if the Government pays a particular claim
    in full despite its actual knowledge that certain requirements were violated, that is very strong
    evidence that those requirements are not material.” Id. at 2003. In this case, the NAVFAC did
    just that. On May 18, 2010, RDA submitted its first invoice for deck demolition work. DX 80 at
    1. The NAVFAC received that invoice two days later. DX 80 at 1. On May 25, 2010, the
    NAVFAC wrote to RDA stating that “RDA has been performing demolition since mid March 2010
    and only as of last week did you start removing the debris. Everyone has observed that RDA
    allowed the significant accumulation of construction demolition debris on your site without
    disposing of it as you went along[.]” DX 140 at 1 (emphasis added). The May 25, 2010 letter
    demonstrates that the NAVFAC had contemporary knowledge of RDA’s failure to remove the
    demolition debris that fell into the Narragansett Bay. The NAVFAC, however, nevertheless
    compensated RDA for the deck removal work included in the May 18, 2010 Invoice and all
    subsequent invoices. Gov’t PT Br. at 30 (“RDA invoiced for and received the full $100,000
    allotted for disposal of the concrete from the demolition of the wharf.”), 50 (“RDA had the
    opportunity to invoice, and was paid, for all work satisfactorily performed through the
    termination[.]”).
    For these reasons, the court has determined that RDA’s misrepresentation regarding the
    debris that fell into the Narragansett Bay was not material to the Government’s payment decision.
    83
    b.         Whether RDA Construction Corp. Falsely Certified That Its
    Rock Fill Removal Work Complied With The October 13,
    2009 Contract.
    Next, the Government argues that RDA’s September 28, 2010 Invoice (Invoice 5) violated
    the FCA by falsely certifying that RDA: (1) completed all of the rock fill removal work required
    by the October 13, 2009 Contract; and (2) submitted a hydrographic survey of the project site
    within seven days of completing rock fill removal. Gov’t PT Br. at 32–33.
    i.       Regarding Rock Fill Removal.
    The Government has satisfied the first two elements of FCA liability. First, the
    Government has demonstrated that, on September 28, 2010, RDA submitted an invoice claiming
    payment for all of the rock fill removal work required by the October 13, 2009 Contract. DX 210
    at 3.
    Second, the Government established that the September 28, 2010 Invoice misrepresented
    that RDA completed the rock fill removal. During trial, Lawrence Ahearn, the superintendent of
    the completion contract awarded to Haskell after RDA was terminated, testified that RDA failed
    to remove rock fill throughout the project site:
    [THE GOVERNMENT’S COUNSEL]: Now, [Haskell] also removed significant
    quantities of rockfill and riprap?
    [MR. AHEARN]: Correct. . . .
    [THE GOVERNMENT’S COUNSEL]: Would it be fair to say you removed several
    truckloads of rockfill and riprap?
    [MR. AHEARN]: Yeah. Rock, probably 30 truckloads.
    [THE GOVERNMENT’S COUNSEL]: And did you encounter the rockfill across
    the entire length of the project?
    [MR. AHEARN]: Yes. It was heavier in some areas than others.
    TR at 1122–23 (emphases added) (Ahearn).
    RDA does not dispute that it failed to remove all of the rock fill from the project site.
    Instead, RDA asserts that it was impossible to excavate all of the rock fill without some material
    falling back into the Narragansett Bay. Pl. PT Br. at 41. The material that fell back into the water
    frequently rolled outside of the “limits of excavation.” Pl. PT Br. at 41. According to RDA,
    “[c]hasing those rocks . . . was not part of [the October 13, 2009] Contract.” Pl. PT Br. at 41. But,
    RDA does not cite, and the court is unable to identify, any provision of the October 13, 2009
    Contract that supports this argument. Therefore, the court has determined that the Government
    satisfied the second element of its FCA claim. See Young-Montenay, 
    15 F.3d at 1043
    .
    84
    The Government, however, failed to establish the third element of FCA liability. Here, the
    Government argues that RDA had “actual knowledge” of the September 28, 2010 Invoice’s
    misrepresentations. Gov’t PT Br. at 33. Specifically, the Government argues that RDA knew its
    rock fill removal work was incomplete when it submitted the September 28, 2010 Invoice, because
    RDA composed a draft schedule narrative the following month that stated, “the last pieces of the
    rip-rap . . . were removed by October 22, 2010.” DX 220 at 1 (emphasis added). The draft
    narrative also contained a comment from Mr. Sivalogan, RDA’s scheduling consultant, advising:
    “check this [date]. This is the date included in the schedule. If this date is incorrect, then [I]
    suggest we . . . do not mention dates here.” DX 220 at 1. The final schedule narrative does not
    contain the October 22, 2010 date. DX 219 at 4.
    The Government asserts that RDA’s removal of the October 22, 2010 date from the final
    schedule narrative is an admission that the rock fill work remained incomplete on October 22,
    2010, i.e., one month after RDA submitted the September 28, 2010 Invoice. But, the logic of this
    conclusion is flawed. Based on Mr. Sivalogan’s comment, RDA’s exclusion of the October 22,
    2010 date only suggests that RDA believed that the October 22, 2010 completion date was
    incorrect; it does not, however, provide any insight into whether RDA believed the work was
    completed before or after that date. In other words, the absence of a completion date in the final
    schedule narrative equally supports two conclusions: (1) RDA believed that it completed the work
    some time before October 22, 2010 and possibly before it submitted the September 28, 2010
    Invoice; or (2) RDA believed the work remained unfinished as of October 22, 2010. Therefore,
    the Government did not prove by a preponderance of the evidence, i.e., that it is more likely than
    not, that RDA knew its rock fill work was incomplete when it submitted the September 28, 2010
    Invoice.
    For these reasons, the court has determined that RDA is not liable under the FCA for falsely
    certifying that it completed rock fill removal on, or before, September 28, 2010.
    ii.     Regarding The Hydrographic Survey.
    The Government also argues that the September 28, 2010 Invoice falsely certified
    compliance with all of the October 13, 2009 Contract’s requirements related to rock fill removal,
    because RDA did not submit a hydrographic survey of the project site within seven days of
    completing that work. Here, the parties do not dispute that the first three elements of FCA liability
    are satisfied. RDA, however, argues that the Government’s FCA claim is not actionable, because
    the relevant misrepresentation was immaterial to the Government’s payment decision. Pl. PT
    Resp. at 43. The court agrees.
    “[I]f the Government pays a particular claim in full despite its actual knowledge that certain
    requirements were violated, that is very strong evidence that those requirements are not material.”
    Universal Health Services, 136 S. Ct. at 2003. In this case, the September 28, 2010 Invoice
    represented that RDA completed rock fill removal on July 21, 2010. DX 210 at 3. The NAVFAC
    did not receive a hydrographic report by July 28, 2010. And, it was well known that RDA did not
    plan on submitting a hydrographic report until the project was complete. In fact, Mr. Kelley,
    RDA’s President, testified that “[it] was common knowledge among[] [everyone], the Navy
    included, that we were going to go back at the end of the project, [to] do a final hydrographic
    survey.” TR at 1543 (Kelley). Nonetheless, the NAVFAC paid RDA the full amount of the
    85
    September 28, 2010 Invoice minus a ten percent penalty for falling 125 days behind schedule. DX
    210 at 1. Therefore, the court finds that RDA’s misrepresentation regarding the hydrographic
    survey was not material to the Government’s payment decision.
    For these reasons, the court has determined that RDA is not liable under the FCA for falsely
    certifying that it submitted a hydrographic survey of the project site within seven days of
    completing rock fill removal.
    c.     Whether RDA Construction Corp. Falsely Certified That It
    Made Timely Payments To Its Subcontractors.
    The Government also argues that RDA falsely certified compliance with the Prompt
    Payment Act, 
    31 U.S.C. § 3905
    ,36 in its May 18, 2010 Invoice (Invoice 2), because RDA failed to
    pay several of its subcontractors within seven days of receiving payment from the NAVFAC.
    Gov’t PT Br. at 34–35.
    Here, the Government has demonstrated that RDA presented a May 18, 2010 Invoice to
    the NAVFAC. DX 80 at 1. The Government has also established that the May 18, 2010 Invoice
    misrepresented that RDA paid its subcontractors on time, pursuant to the Prompt Payment Act. In
    fact, RDA’s President testified that, two years after the October 13, 2009 Contract was terminated,
    RDA still owed money to several subcontractors:
    [THE GOVERNMENT’S COUNSEL]: And RDA owes [] money to Hub [a
    subcontractor] regardless of whether it prevails in this case or not, right?
    [MR. KELLEY]: Yes.
    [THE GOVERNMENT’S COUNSEL]: There are other subcontractors or suppliers
    for the P-469 project that RDA also owes money to, right?
    [MR. KELLEY]: There was a few.
    36
    The Prompt Payment Act, in relevant part, provides:
    (b) Each construction contract awarded by an agency shall include a clause that
    requires the prime contractor to include in each subcontract for property or services
    entered into by the prime contractor and a subcontractor (including a material
    supplier) for the purpose of performing such construction contract—
    (1) a payment clause which obligates the prime contractor to pay the
    subcontractor for satisfactory performance under its subcontract within 7 days
    out of such amounts as are paid to the prime contractor by the agency under
    such contract[.]
    
    31 U.S.C.A. § 3905
    (b)(1).
    86
    TR at 1535 (Kelley). Mr. Kelley’s testimony also demonstrates that RDA had actual knowledge
    that its Prompt Payment Act certifications were false. TR at 1535.
    Nevertheless, the Government has not established FCA liability, because it failed to prove
    by a preponderance of the evidence that RDA’s false certification of compliance with the Prompt
    Payment Act was material to the NAVFAC’s decision to pay the May 18, 2010 Invoice. The
    Government must “prove all essential elements of [an FCA] cause of action . . . by a preponderance
    of the evidence.” 
    31 U.S.C. § 3731
    (d). One such element is whether the relevant
    misrepresentation was material to the Government’s payment decision. See Universal Health
    Servs., 136 S. Ct. at 2002 (“[A] a misrepresentation about compliance with a statutory, regulatory,
    or contractual requirement must be material to the Government’s payment decision in order to be
    actionable under the False Claims Act.”). In this case, however, the Government failed to present
    any evidence to prove that compliance with the Prompt Payment Act was material to the
    NAVFAC’s decision to pay the May 18, 2010 Invoice. In fact, the Government’s post-trial briefs
    do not mention materiality at all. Therefore, the Government failed to satisfy its burden of proof
    with regard to an essential element of its FCA claim. See, e.g., Cox v. Merit Sys. Prot. Bd., 
    817 F.2d 100
    , 101 (Fed. Cir. 1987) (“Because [the plaintiff] . . . offered no evidence in support of his
    assertion . . ., he failed to carry his burden of proof[.]”).
    For these reasons, the court has determined that RDA is not liable under the FCA for falsely
    certifying compliance with the Prompt Payment Act.
    d.      Whether RDA Construction Corp.’s July 3, 2013 Certified
    Claim For Costs Incurred To Re-Inspect The Manitowoc 4100
    Crane Was Baseless, Inflated And Premised On Factual
    Misrepresentations.
    The Government also argues that RDA violated the FCA by submitting a July 3, 2013
    Certified Claim for crane inspection costs that was “baseless,” “inexplicably inflated,” and
    “premised on misrepresentations of fact.” Gov’t PT Br. at 37. Specifically, the Government
    argues that RDA claimed an equitable adjustment for delays incurred when the NAVFAC took its
    crane out of service pending repair of five deficiencies identified in a November 28, 2012
    inspection. Gov’t PT BR. at 37. In an attempt to recover some of its losses, RDA misrepresented
    the underlying facts, falsely stating that the inspector never took the crane out of service. Gov’t
    PT Br. at 37–38. And, claimed an equitable adjustment that exceeded the total amount of working
    hours between the inspection and RDA’s default termination. Gov’t PT Br. 38–39.
    Here, the Government has satisfied the first three elements of its FCA counterclaim. First,
    the Government has demonstrated that RDA submitted an equitable adjustment claim to recover
    costs incurred while its crane was out service. The July 3, 2013 Certified Claim incorporates a
    March 18, 2013 Certified Claim where RDA requested “compensation for . . . the time associated
    with the crane being out of service as directed by NAVFAC.” DX 691 at 1 (incorporating DX 663
    at 7). The March 18, 2013 Certified Claim justified its request, in part, by arguing that “[the crane]
    inspector . . . did not take the crane out of service at this point or any point thereafter.” DX 663 at
    7.
    87
    Second, the Government has demonstrated that RDA’s assertion that the inspector did not
    take the crane out of service was false. At trial, Mr. Wallis, RDA’s project manager at the time of
    the crane inspection, testified as follows:
    [THE GOVERNMENT’S COUNSEL]: [The March 18, 2013 Certified Claim
    includes] a sentence that says, ‘Furthermore, it is important to acknowledge that as
    a qualified inspector J.P. Riley did not take the crane out of service at this point or
    at any point thereafter.’
    [THE COURT]: Is that a true statement or not? You signed the letter.
    [Mr. Wallis]: Based on the information that I see now, no. Based on the information
    I have been pointed out to, I would say . . . it was taken out of service.
    [THE COURT]: So you were misinformed when you wrote the letter?
    [THE WITNESS]: Yes.
    TR at 790 (Wallis).
    Third, the Government has demonstrated that RDA knew that it misrepresented the
    inspector’s decision to take the crane out of service. Indeed, on January 18, 2013, the crane
    inspector submitted a Deficiency Report that identified five deficiencies on the crane and
    instructed RDA that “any [d]eficiencies [must] be repaired . . . before continued use.” DX 677 at
    59. On January 23, 2013, RDA acknowledged receipt of the Deficiency Report and responded,
    “[w]e do not believe that the equipment should be taken out of service until the deficiencies . . .
    have been corrected.” DX 677 at 56. The January 23, 2013 letter shows that RDA had actual
    knowledge that the inspector took its crane out of service before RDA submitted the March 18,
    2013 Certified Claim or July 3, 2013 Certified Claim.
    The Government, however, has failed to establish that RDA’s misrepresentation of the
    underlying facts was material to the NAVFAC’s payment decision. Although RDA’s statement
    that “[the crane] inspector . . . did not take the crane out of service” (DX 663 at 7) may have
    affected the NAVFAC’s decision to equitably adjust the October 13, 2009 Contract, the
    Government did not address the issue of materiality during trial or in its post-trial briefs.
    Therefore, the court has determined that the Government failed to carry its burden of proof with
    regard to this element of FCA liability. See, e.g., Cox, 
    817 F.2d at 101
     (“Because [the plaintiff] .
    . . offered no evidence in support of his assertion . . ., he failed to carry his burden of proof[.]”).
    Similarly, the Government did not address whether the NAVFAC’s decision to pay the
    July 3, 2013 Certified Claim was affected by miscalculations in the requested damages. Therefore,
    the Government also failed to prove that the “inexplicably inflated” damages contained in the July
    3, 2013 Certified Claim were material.
    For these reasons, the court has determined that RDA’s July 13, 2013 Certified Claim did
    not violate the FCA.
    88
    V.     CONCLUSION.
    For these reasons, the court has determined that the NAVFAC did not breach the October
    13, 2009 Contract, as alleged in Counts I, III–VIII of the May 7, 2015 Second Amended
    Complaint. The court has also determined that RDA is not entitled to an equitable adjustment of
    the October 13, 2009 Contract, as alleged in Count II, or remission of withheld payments, as
    alleged in Count IX.
    Regarding the Government’s counterclaims, the court has determined that the NAVFAC is
    entitled to recover $2,208,204.01 in liquidated damages, as alleged in Counterclaim I of the
    Government’s June 12, 2015 Answer. But, RDA did not defraud the NAVFAC, as alleged in
    Counterclaims II–IV.
    The Clerk of Court is directed to enter judgment in accordance with this disposition.
    IT IS SO ORDERED.
    s/ Susan G. Braden
    SUSAN G. BRADEN
    Chief Judge.
    89
    Court Exhibit A
    Court Exhibit A identifies the transcripts, trial exhibits, demonstrative exhibits, and
    witnesses whose testimony comprises the record of trial held in this matter between November 16,
    2015 and July 11, 2016.
    I.       TRANSCRIPTS.
    The trial record includes the following transcripts:
    Description                                Date         Docket Reference
    Trial Transcript Vol. 1                           Nov. 16, 2015        ECF No. 73
    Trial Transcript Vol. 2                           Nov. 17, 2015        ECF No. 75
    Trial Transcript Vol. 3                           Nov. 18, 2015        ECF No. 77
    Trial Transcript Vol. 4                           Nov. 19, 2015        ECF No. 79
    Trial Transcript Vol. 5                           Dec. 7, 2015         ECF No. 87
    Trial Transcript Vol. 6                           Dec. 8, 2015         ECF No. 89
    Trial Transcript Vol. 7                           Dec. 9, 2015         ECF No. 91
    Trial Transcript Vol. 8                           Dec. 10, 2015        ECF No. 93
    Trial Transcript Vol. 9                           Jan. 4, 2016         ECF No. 97
    Trial Transcript Vol. 10                          Jan. 5, 2016         ECF No. 99
    Trial Transcript Vol. 11                          Jan. 6, 2016         ECF No. 101
    Trial Transcript Vol. 12                          July 11, 2016        ECF No. 108
    Peters Deposition Transcript Vol. 1               Oct. 23, 2015        ECF No. 81-1
    Peters Deposition Transcript Vol. 2               Oct. 23, 2015        ECF No. 82
    Peters Deposition Transcript Vol. 3               Nov. 5, 2015         ECF No. 83
    Nicolazzo Deposition Transcript                   Oct. 28, 2015        ECF No. 84
    II.      TRIAL EXHIBITS.
    The following exhibits were admitted unless otherwise noted.
    A.     Exhibits Offered By Plaintiff.
    PX 001    Solicitation, Offer, and Award (Construction, Alteration, or Repair)
    PX 002    NAVFAC Mid Atlantic Solicitation, Offer, and Award
    PX 003    Cost Detail Estimate
    PX 004    Abstract of Offers – Construction
    PX 005    Amendment of Solicitation/ Modification of Contract executed 6/30/2009 re
    potential bidders
    PX 006    Amendment of Solicitation / Modification of Contract executed 7/7/2011 re
    Obstructions Encountered During Installation of Sheet Piles
    PX 007    Drawing Set for P-469 Waterfront Improvements, Naval Station Newport, RI
    PX 008    Contract Modifications Issued to RDA Construction
    PX 009    NAVFAC Specifications for Work Order No. 794165, Waterfront Improvements at
    Naval Station, Newport, R.I.
    1
    PX 010   E-mail dated 8/17/2015 with attachment re P469 Waterfront Project Waterside Work
    Estimate Summary Sheet
    PX 012   NAVFAC Underwater Facilities Inspection & Assessments by Appledore Marine
    Engineering, Inc. dated April, 2005
    PX 013   Unified Facilities Guide Specifications, UFGS-02 41 00, October 2006
    PX 014   United Facilities Guide Specifications July 2013
    PX 015   Kickoff Meeting Minutes dated 5/15/2008
    PX 016   Order for Supplies or Services executed 5/27/2008
    PX 017   Report dated 7/22/2008 from FST Engineers to NAVFAC re Charrette Inbrief
    PX 018   E-mail dated 8/27/2008 from David Anderson to Cynthia De Jong re Record of
    Telephone Call August 27, 2008
    PX 019   Existing Wharf Evaluation dated 8/29/2008 by FST, LLC
    PX 020   Letter dated 2/2/2009 from Travis Germano to Michael Hartman re Submission of
    Baseline Schedule - Letter of Concern
    PX 021   Letter dated 2/8/2009 [sic] from Karen Sampson to Michael Hartman re Review of
    Letter RDA-002
    PX 022   Pre-bid photographs of Wharf
    PX 023   Letter dated 6/26/2009 from NASDI to Gene Kelley re: Pier Demolition Proposal
    PX 024   Memorandum dated 6/30/2009 from Hub Foundation Co., Inc. to American Bridge
    Company, Attn: Estimating re Proposal
    PX 025   Letter dated 7/30/2009 from William Reagan to Bruce Wood re Waterfront
    Improvements at Naval Station Newport RI
    PX 026   E-mail dated 10/2/2009 with attachment from Drew Floyd to Mike Hartman re Drill
    rig - platform schematic
    PX 027   E-mail from Sivalogan to Hartman dated 11/11/2009
    PX 028   E-mail dated 11/18/2009 from Germano dated 11/18/2009 enclosing Appledore
    Report
    PX 029   Letter RDA - 001 from Michael Hartman to Travis Germano re E-mail
    Correspondence from Travis Germano Dated 11/18/09
    PX 030   Letter RDA - 002 dated 11/20/2009 from Michael Hartman to Nancy Van Gelder re
    NAVFAC Response Letter Dated December 9, 2009
    PX 031   E-mail chain dated 11/24/2009 from Travis Germano to Frank Stich, David
    Anderson and Boris Shilman re P-469 2005 Waterfront Marginal Wharf Inspection
    Report
    PX 032   E-mail chain dated 11/24/2009 from Frank Stich to Boris Shilman re Change
    Notification Deficient Wharf Letter
    PX 033   E-mail chain dated 12/2/2009 from Boris Shilman to Frank Stich re Change
    Notification Deficient Wharf
    PX 034   Letter dated 12/9/2009 from Karen Sampson to Michael Hartman re RDA Letter of
    20 Nov 2009
    PX 035   Draft Letter dated 12/16/2009 from NASDI to Michael Hartman re Demolition from
    Barges Estimated Cost and Time Impacts
    PX 036   Letter dated 12/18/2009 from NASDI to Michael Hartman re: Newport Pier Deck
    Demolition Proposal
    2
    PX 037   E-mail chain dated 12/28/2008 with attachment from Mike Hartman to Nancy Van
    Gelder re: Response to NAVFAC letter dated 12/9/09
    PX 038   Demo Plan Calculations dated 2/22/2010 by Martel Engineering, Inc.
    PX 039   Letter RDA - 008 dated 2/25/2010 with attachment from Michael Hartman to Karen
    Sampson re Letter dated February 8, 2010
    PX 040   E-mail dated 4/21/2010 with attachment from Mike Hartman to Karen Sampson re
    Claim Certification Request
    PX 041   Letter from Rachupka to Hartman dated 5/17/2010
    PX 042   Letter RDA - 018 dated 5/24/2010 from Michael Hartman to Karen Sampson re
    Demolition Claim due to 2005 Marginal Wharf Inspection Report
    PX 043   E-mail dated 5/24/2010 from Mike Hartman to Karen Sampson re Update on
    Demolition Issues
    PX 044   Letter RDA - 018 dated 5/24/2010 from Michael Hartman to Karen Sampson re
    Demolition claim due to 2005 Marginal Wharf Inspection Report
    PX 045   Letter dated 5/25/2010 from Karen Sampson to Michael Hartman re Response to
    5/24/2010 claim letter
    PX 046   Letter RDA - 022 with attachments dated 7/8/2010 from Michael Hartman to Karen
    Sampson
    PX 047   Letter RDA - 021A dated 7/12/2010 from Michael Hartman to Karen Sampson re
    Additional Known Impacts due to 2005 Marginal Wharf Inspection Report
    PX 048   Letter dated 8/31/2010 from Department of The Navy re Review of Certified Claim
    4/19/2010
    PX 049   Letter RDA - 043 dated 11/19/2010 from Michael Hartman to Craig Rachupka re
    Cost Impacts Drilling King Piles from Barge
    PX 050   Letter dated 6/14/2011 from Eugene Kelley to The Hon. Stephen F. Lynch re RDA
    Contract Dispute with U.S. Navy
    PX 051   Memorandum dated 2/22/2012 from Marc Nicolazzo to File re P-469 - Con Phase
    Site Visit
    PX 052   E-mail dated 3/5/2012 from Travis Germano to Ansley Marr re P-469 Field Memo
    for Feb 22
    PX 053   E-mail chain dated 8/6/2012 from Erick Cooper to Craig Rachupka re P-469
    Waterfront Improvements
    PX 054   Summary of Monetary Claim for Work Impacted by the Appledore Report
    PX 055   P-469 Waterfront Improvement Turnover Sheet
    PX 056   E-mail Sivalogan to Hartman dated 1/19/2010
    PX 057   E-mail from Germano to Hartman dated 1/27/2010
    PX 058   Transmittal #016b dated 2/2/2010 from RDA to Germano conditionally approving
    construction schedule
    PX 059   Rachupka Letter dated 5/13/2010
    PX 060   Invoice 6A with certification dated 11/29/2010
    PX 061   Letter dated 11/19/2010 from Michael Hartman to Craig Rachupka re Obstructions
    Preventing Completion of S. Bulkhead Sheet Pile
    PX 062   Letter RDA-045 with attachment dated 12/14/2010 from Michael Hartman to Craig
    Rachupka re Deteriorated Condition of Existing Sheet Pile
    3
    PX 063   E-mail chain dated 3/9/2011 from David Anderson re Continual Problems
    w/Obstructions & Deteriorated Existing Sheets
    PX 064   Letter dated 3/10/2011 from Karen Sampson to Michael Hartman re Response to
    Letter RDA-053
    PX 065   Letter dated 3/10/2011 from Karen Sampson to Gene Kelley re Response to RDA-
    053
    PX 066   Letter RDA - 055 from Michael Hartman to Karen Sampson re Additional Response
    to Government Letter Ser FEAD/L6211 dated 3/10/2011
    PX 067   E-mail chain dated 5/11/2011 from Craig Rachupka to Erick Cooper re P-469 Funds
    Request for 2 Critical Path Mods
    PX 068   Amendment of Solicitation/ Modification of Contract executed 7/7/2011 re
    obstructions encountered during installation of sheet piles
    PX 069   Amendment of Solicitation/ Modification of Contract executed 8/19/2011 re
    differing site conditions
    PX 070   Letter dated 1/27/2012 from Karen Sampson to Eugene Kelley
    PX 071   Amendment of Solicitation/ Modification of Contract executed 4/13/2012 re revised
    drill pattern and additional time and materials
    PX 072   E-mail chain dated 8/14/2012 from Gene Kelley to Karen Sampson re Additional
    Construction Drilling
    PX 073   Amendment of Solicitation/ Modification of Contract executed 8/17/2012 re drill
    obstruction at north and south bulkheads
    PX 074   E-mail chain dated 8/17/2012 from Boris Shilman to Travis Germano re P-469,
    Obstruction Drilling (Mod 9)
    PX 075   E-mail chain dated 8/20/2012 from Karen Sampson to Jeffrey Welch re
    modifications
    PX 076   Amendment of Solicitation/ Modification of Contract
    PX 077   E-mail chain dated 11/13/2012 from Gerard Montani re Completion Date for the
    Marginal Wharf
    PX 078   E-mail dated 11/27/2012 from Mark Wallis to Travis Germano dated 11/27/2012 re
    Additional Drilling
    PX 079   E-mail dated 1/10/2013 from Erin Sanders to Ryan Tibbets re P-469 Status
    PX 080   E-mail chain dated 1/23/2013 from Erick Cooper re P-469 North Bulkhead - Work
    Point 7A & Return Wall
    PX 081   E-mail chain dated 1/29/2013 from Craig Rachupka to Travis Germano re Financial
    Status
    PX 082   Letter RDA-173 from Mark Wallis to Craig Rachupka re Letter RDA-135 dated
    5/10/2012, Contract Modification P00009
    PX 083   Letter RDA-184 with attachments dated 4/1/2013 re Additional Cost of Delayed
    Issue of Contract Modifications
    PX 084   E-mail chain from Karen Sampson re Notice of Claim PCO-50 Delayed Issue of
    Contract Modifications
    PX 085   Time Line #2 - Obstruction Drilling
    PX 086   Pre-Negotiation Memo re Extension of Bulkhead at WP 5 and WP 7
    PX 087   Monthly Schedule Narrative Update 21
    PX 089   Letter RDA-025 dated 7/26/2010 from Michael Hartman to Karen Sampson
    4
    PX 090   E-mail chain dated 8/4/2010 from Don Harvie to Craig Rachupka re Letter on Pile
    Pulling - Follow up
    PX 091   Letter RDA-058 dated 4/4/2011 from Eugene Kelley to Craig Rachupka
    PX 092   Draft Letter RDA-146 dated 6/14/2012 revised 8/10/2012 re Outstanding Contract
    Issues
    PX 093   Opinion of Cost for Deductions with attachment dated 8/24/2012
    PX 094   Letter RDA-155 with attachment dated 9/17/2012 from Mark Wallis to Craig
    Rachupka re Outstanding Contract Issues
    PX 095   E-mail chain dated 11/6/2012 with attachment from Craig Rachupka to Karen
    Sampson re H Pile Extraction Letter 10-12-12
    PX 096   Letter dated 11/7/2012 with attachment from Karen Sampson to Gene Kelley re
    Letter RDA-098
    PX 097   Letter RDA-168 with attachment dated 1/18/2013 from Mark Wallis to Karen
    Sampson re Pile Extraction Variance
    PX 098   E-mail dated 1/23/2013 from Craig Rachupka to Erick Cooper re Atty Client Priv P-
    469 H-Pile Issue
    PX 099   E-mail dated 1/23/2013 from Travis Germano re Meeting Announcement and
    Agenda
    PX 100   E-mail from Louis Vinciguerra to Jonathan Peters dated 1/28/2013 re: potential
    impact of delays
    PX 101   E-mail dated 1/29/2013 from Travis Germano re P- 469 Financial Position?
    PX 102   Remaining Scope P469 dated 1/30/2013
    PX 103   FST remaining scope dated 2/11/2013
    PX 104   Memo of Meeting on 3/7/2013
    PX 105   Remaining Scope 3/13/13 w/ notes
    PX 106   E-mail with attachment from Peters to Ahearn dated 3/25/2013 re Project
    Preliminary Scope Narrative
    PX 107   Completion Drawings 3/28/2013 with notes
    PX 108   Cost Estimate Summary 3/29/2013
    PX 109   E-mail dated 4/2/2013 with attached drawing set from Craig Rachupka to Jonathan
    Peters
    PX 110   E-mail from Anderson to U.S. Navy dated 4/2/2013
    PX 111   Time Line #1 dated 5/8/2013 re Pile Variance Request
    PX 112   E-mail dated 6/16/2014 from Craig Rachupka re RFI-022 existing Water-Side Steel
    Piles Cutoff Request
    PX 113   Haskell RFI 22
    PX 114   E-mail dated 6/26/2014 from Craig Rachupka to Jonathan Peters with attachment re
    Responses to RFI’s 21 & 22
    PX 115   E-mail chain dated 1/16/2015 from Jonathan Peters to Travis Germano re Meeting
    Today
    PX 116   E-mail from Jonathan Peters to Craig Rachupka and others dates 1/19/2015 re
    Meeting Requests
    PX 117   E-mail from Jonathan Peters to Charles Bateh dated 1/21/2015 re 469 Work this
    week
    PX 118   E-mail chain dated 1/23/2015 from Robert Wadsworth re: P-469 H Pile Removal
    5
    PX 119   E-mail from Jonathan Peters to Garrett Sigler dated 5/13/2015 re P469 Water-side
    work
    PX 120   E-mail from Jonathan Peters to Craig Rachupka and others dated 6/16/2015 re P469
    Waterfront Improvements: Pile Extraction
    PX 121   E-mail from Jonathan Peters to Craig Rachupka dated 7/8/2015 re Waterside Work
    PX 122   Memorandum dated 7/10/2015 from Larry Ahearn to Jonathan Peters
    PX 123   Letter with attachments from Jonathan Peters to Leslie Brazil dated 7/16/2015
    PX 124   E-mail with attached photographs from Jonathan Peters to Craig Rachupka and
    others dated 7/17/2015 re GAIC’s approval of Contractor’s June, 2015 payment
    request for Water-Side Work
    PX 125   E-mail with attachment dated 8/10/2015 from Reagan Construction Corp. to
    Jonathan Peters re P-469 Pile Extraction Log 8-11-15
    PX 126   Haskell spreadsheet re estimate to complete extraction dated 8/14/2015
    PX 127   Letter dated 8/17/2015 from Shannon Reagan to Jonathan Peters re quote
    PX 128   E-mail change from Jonathan Peters to David Nimmich, Esq. dated 8/27/2015
    PX 129   Mutual Release Agreement between Great American Insurance Company, Haskell
    Co. and the United States of America
    PX 130   Color Photo of rusted pile
    PX 131   Color Photo of rusted pile
    PX 132   Color Photograph of rusty piece of pile
    PX 133   Color Photograph of cut pile with angles attached
    PX 134   Color Photograph of drilled and anchored rock
    PX 135   Color Photograph of crane hoist
    PX 136   RDA Construction Pile Installation Log
    PX 137   Letter RDA-066A with attachments dated 5/5/2011 from Eugene Kelley to Craig
    Rachupka re Approval for Alternate Safety Supervisor SSHO
    PX 138   Letter RDA-077 from Eugene Kelley to Kimberly Choplin dated 7/7/2011 re
    Approval of Lynda Amarantes as SSHO/QC Manager
    PX 139   Letter RDA-094 from Eugene Kelley to Craig Rachupka re Alternate Quality
    Control Manager
    PX 140   E-mail dated 1/4/2012 from Mark Wallis to Craig Rachupka re Recovery of Proud
    Mary
    PX 141   Letter RDA-106 dated 1/6/2012 from Mark Wallis to Craig Rachupka re Notice of
    Delay - Recovery of Push Boat
    PX 142   Letter dated 1/19/2012 from Kimberly Choplin to Gene Kelley re Mark Wallis as
    QC Manager
    PX 143   Letter dated 1/23/2012 with attachment from Kim Choplin to Gene Kelley re letter
    of 1/6/2012, sunken push boat
    PX 144   Letter RDA-119 dated 2/2/2012 from Mark Wallis to Craig Rachupka re Notice of
    Delay - Delayed Response to Rejection of Mark Wallis as QC Manager
    PX 145   Letter dated 6/7/2012 from Mark Wallis to Craig Rachupka with attached Additional
    Overhead Due to Delayed Response to QCM Approval
    PX 146   E-mail dated 8/3/2012 from Craig Rachupka to Stephen Ericson re: Photos of
    Existing Bulkhead at Rip Rap Areas
    6
    PX 147   Letter dated 1/31/2013 from Karen Sampson to Eugene Kelley re Letter RDA-169
    PX 148   Letter RDA-178 with attachments dated 3/18/2013 from Mark Wallis to Karen
    Sampson re Notice of Claim PCO-047, Additional Cost for Manitowoc 4100W Re-
    Inspection [Depex. 181]
    PX 149   Letter RDA-176 with attachments dated 3/20/2013 from Mark Wallis to Karen
    Sampson re Notice of Claim PCO-045
    PX 150   Letter RDA-179 with attachments dated 3/20/2013 from Eugene Kelley to Karen
    Sampson re Additional Cost for Delayed Response to RFI-26
    PX 151   Letter RDA-181 dated 3/22/2013 from Eugene Kelley to Karen Sampson re Revised
    Notice of Claim Letters
    PX 152   Time Line #3 dated 5/15/2013 re Annual Crane Inspection
    PX 153   Time Line #4 re Delayed Rejection of SSHO
    PX 154   Time Line #5 dated 5/19/2013 re Delayed Response to RFI-26
    PX 155   Time Line #6 dated 5/19/2013 re Revised Base Access - RapidGate
    PX 156   Time Line #7 dated 5/22/2013 re Delayed Approval of QCM
    PX 157   Time Line #8 dated 5/23/2013 re Delayed Recovery of Proud Mary
    PX 158   Letter dated 5/24/2013 from Kimberly Kahler to Eugene Kelley re Certified Claims
    PX 159   Time Line #9 dated 5/24/2013 re Interference Batter Piles vs. Soil Anchors
    PX 160   Time Line #10 dated 5/28/2013 re Revised Closure Details at Workpoints
    PX 161   Time Line #11 re Delayed Approval of SSHO / QCM
    PX 162   Letter RDA-191 with attachments dated 7/3/2013 from Eugene Kelley to Kimberly
    Kahler
    PX 163   Letter dated 9/26/2013 from Kimberly Kahler to Eugene Kelley re 7/3/2013 Claim
    PX 164   Plaintiff RDA Construction Corporation’s Answers and Objections to Defendant’s
    Third Set of Interrogatories
    PX 165   Equipment Rental Rates, November 2009
    PX 166   Letter re RDA-089
    PX 167   Letter dated 6/20/2012 signed by Karen Sampson to Gene Kelley re Receipt of
    Updated Construction Schedule
    PX 168   Letter dated 1/31/2013 from Kimberly Kahler to Eugene Kelley re Show Cause
    Letter
    PX 169   Letter dated 2/1/2013 from Eugene Kelley to Kimberly Kahler re Show Cause Letter
    PX 170   Draft Letter dated 7/31/2012 from Karen Sampson to Gene Kelley re updated
    construction schedule
    PX 171   E-mail dated 10/11/2012 from Craig Rachupka to Travis Germano re Forbearance
    Letter for Updated Schedule 9/17/12
    PX 172   E-mail from Craig Rachupka to Robert Wadsworth dated 12/5/2012 re Forbearance
    Letter for Updated Schedule 9/17/12
    PX 173   E-mail chain dated 12/5/2012 from Craig Rachupka to Robert Wadsworth re
    Forbearance Letter for Updated Schedule 7/26/12
    PX 174   E-mail dated 1/17/2013 from Craig Rachupka to Robert Wadsworth re Forbearance
    Letter for Updated Schedule
    PX 175   E-mail dated 1/9/2013 from Karen Sampson to Craig Rachupka re Negotiation
    Meeting on Tuesday, 15 Jan 13 at 1300 hrs.
    7
    PX 176   Letter with attachments dated 2/21/2013 from Kimberly Kahler to Eugene Kelley re
    Notice of Termination
    PX 177   E-mail chain dated 5/23/2012 from Craig Rachupka to Travis Germano re P-469
    Waterfront Improvements Project
    PX 178   E-mail chain from Daniel Sullivan re Newport Marginal Wharf - Descoping Items
    PX 179   E-mail chain dated 7/2/2012 from Gerard Montani re Pier 2 Load Capacity Study
    PX 180   E-mail dated 8/3/2012 with attached photographs from Travis Germano to Gerard
    Montani re Photos of Existing Bulkhead at Rip Rap Areas for P-469
    PX 181   Letter dated 8/28/2012 from Karen Sampson to Gene Kelly re Cost Proposal
    PX 182   Letter RDA-184 dated 8/31/2012 with attachments from Mark Wallis to Karen
    Sampson re RFP-010 Letter
    PX 183   E-mail dated 8/21/2012 from Erick Cooper re Deletion of Scope
    PX 184   E-mail chain dated 8/24/2012 from David Anderson re Deletion of Work Estimates
    PX 185   Tender Agreement executed 12/20/2013
    PX 186   Memorandum dated 7/30/2014 from Jeff Welch to Jonathan Peters re P-469
    Completion Contract
    PX 187   E-mail chain with attachments dated 4/2/2013 from Craig Rachupka to Leonard
    Topp re Scope of Work to Complete P-469 4/2/13
    PX 188   E-mail with attachment dated 4/2/2013 from Craig Rachupka to Jonathan Peters re
    P-469 Scope of Work to Complete Remaining Work & Deficiencies
    PX 189   Letter dated 7/29/2014 from Jonathan Peters to Kimberly Kahler and Garrett Sigler
    re delays
    PX 190   E-mail chain from David Nimmich, Esq. with attachment dated 3/14/2013 re Scope
    of Work to Complete Project & Haskell Contact Info
    PX 191   E-mail dated 2/14/2013 from Craig Rachupka to John Lambalot re P-469 RDA
    Resuming Obstruction Drilling Ops at WP7 [Depex. 256]
    PX 192   E-mail chain from Craig Rachupka to Travis Germano re Forbearance Letter for
    Updated Schedule 9/17/2012
    PX 193   E-mail chain dated 12/5/2012 from Craig Rachupka to Robert Wadsworth re
    Forbearance Letter for Updated Schedule 9-17-12
    PX 194   E-mail chain dated 12/5/2012 from Craig Rachupka to Robert Wadsworth re
    Forbearance Letter for Updated Schedule 7-26-12
    PX 195   E-mail dated 1/17/2013 from Craig Rachupka to Robert Wadsworth re Forbearance
    Letter for Updated Schedule
    PX 196   E-mail chain dated 1/29/2013 from David Greenfield to Keith Barbish re P-469
    USCG Contact Info
    PX 197   E-mail chain with attachment dated 2/7/2013 from L Tanya Simms re Final Minutes
    of Coordination Meeting
    PX 198   Letter dated 2/21/2013 from Kimberly Kahler to Jeff Woodward re Notice of
    Termination
    PX 199   Letter dated 5/24/2013 from Kimberly Kahler to Garrett Sigler re Tender Agreement
    PX 200   Solicitation, Offer and Award executed 3/4/2014
    PX 201   E-mail chain dated 6/6/2013 from David Nimmich, Esq. to Garrett Sigler and
    Kimberly Kahler re Updated Tender Agreement
    8
    PX 202   E-mail chain dated 9/26/2013 from Craig Rachupka re Underwater Survey
    Performed by Semper Diving
    PX 203   Letter with attachment dated 5/14/2014 from Hindshaw & Culbertson, LLP to
    Daniel B. Volk, Esq. re Tender Agreement
    PX 204   E-mail chain dated 7/10/2014 from David Nimmich, Esq. re P-469 Schedule
    PX 205   E-mail dated 7/18/2014 from David L. Nimmich, Esq. to Garrett Sigler re Water-
    side Work
    PX 206   E-mail dated 7/31/2014 with attachment from Jonathan Peters re P-469 Waterfront
    Improvements: Notice Letter and Alternative Debris Removal Discussion Letter
    PX 207   Demolition debris photograph dated 4/16/20104
    PX 208   Demolition debris photograph dated 5/10/2010
    PX 209   E-mail from Garrett Sigler to Jonathan Peters dated 8/1/2013 attaching RDA
    Demolition Photos
    PX 210   E-mail from Garrett Sigler to Jonathan Peters dated 8/1/2013 attaching RDA Sawcut
    and debris photos
    PX 211   Waterside Agreement dated 12/20/2013
    PX 212   E-mail dated 6/27/2014 from Jonathan Peters to Craig Rachupka with attachment re
    Waterside Work Agreement
    PX 213   Letter dated 7/28/2014 from Larry Ahearn to Jonathan Peters re discussion of
    removal methods for P469 project
    PX 214   E-mail with attached drawing from Jonathan Peters to Craig Rachupka dated
    8/14/2014 re P469 Rock and Sediment removal plan
    PX 215   Letter from Jonathan Burwood, Esq. to David Nimmich, Esq., Esq. dated 11/3/2014
    PX 216   E-mail dated 1/20/2015 from Jonathan Peters to David Nimmich, Esq. re Water-Side
    Agreement Billing Summary and Backup through 12/30/2014
    PX 217   E-mail from Peters to Rachupka dated 2/13/2015 enclosing photographs of Pile 30B
    PX 218   E-mail dated 8/18/2015 from Gregory Koger, Esq. to Jonathan Burwood, Esq.
    PX 219   Letter with attachments dated 8/24/2015 from Jonathan Burwood, Esq. to David
    Nimmich, Esq.
    PX 220   Letter dated 8/28/2015 from Reagan Construction Corp to The Haskell
    Company
    PX 221   E-mail chain including 8/27/2015 communication from Jonathan Peters to David
    Nimmich, Esq.
    PX 222   Letter dated 9/4/2015 from The Reagan Company to The Haskell
    Company
    PX 223   Letter dated 9/8/2015 from Jonathan Peters to David Nimmich, Esq. and Jonathan
    Burwood, Esq.
    PX 224   E-mail dated 9/9/2015 from David Nimmich, Esq. to Gregory Koger, Esq.
    PX 225   E-mail dated 9/14/2015 from Jonathan Peters to The Reagan Company
    PX 226   Letter dated 9/18/2015 from Reagan Construction Corp to The Haskell Company
    PX 227   Letter dated 9/22/2015 from Reagan Construction Corp to The Haskell Company
    PX 228   Subcontract modification dated 10/6/15
    PX 229   Haskell Debris Log
    PX 230   Haskell’s log of soil piles A & D
    9
    PX 231  Soil Export Log, Catlano Construction, Inc., Spreadsheet
    PX 232  Rachupka to D. Anderson dated 5/31/2012
    PX 233  Scope of Work Cost Estimate dated 3/29/2013
    PX 234  Time Line #12 dated 5/30/2013 re Termination Cost and Demobilization
    PX 235  RDA’s Claim Related to NAFAC’s Wrongful Termination and Breach of Contract
    Narrative dated 7/3/2013 with attached Appendices, Summaries and Support
    Documents
    PX 236 Letter dated 7/16/2015 from Jonathan Peters of Haskell to Leslie Brazil
    PX 238 SureTrack Project Manager Scheduling Report RB21 dated 2/5/2013
    PX 239 RDA Construction Cost Report Summary
    PX 240 RDA Construction Cost Report
    PX 241 RDA Construction Daily Production Reports
    PX 242 Original Baseline Schedule
    PX 243 Adjusted Baseline Schedule
    PX 244 Impact Baseline Schedule
    PX 247 RDA Construction RFI’s
    PX 248 RFI Log
    PX 249 P469 Waterfront Improvement Project Submittal Register
    PX 253a RDA Construction Photographs
    PX 255 Letter dated 8/24/2015 from Jonathan Burwood, Esq. to David Nimmich, Esq. and
    Gregory Koger, Esq. re Settlement Communication
    PX 256 Judgment in the matter of Great American Insurance Company v RDA Construction
    filed 9/3/2015
    PX 2571 E-mail dated 9/21/2010 from Craig Rachupka to Frank Stich re: P-469 M-1 Mod
    Work Costs with attached spreadsheet
    PX 2582 Spreadsheet titled: Costs Associated with P-469 Wharf Work at M-1
    PX 2593 E-mail from Craig Rachupka to Frank Stich dated 9/21/2010 at 5:05 p.m. re: P-469
    M-1 Mod Work Costs
    PX 261* Expert Report of Thomas E. Mitchell, P.E. including attached Curriculum Vitae and
    Exhibits
    PX 261* Franklin M. Grynkewicz, P.E. Curriculum Vitae
    PX 262 Franklin M. Grynkewicz, P.E., Export Report
    ECF-81 Deposition of Jonathan Peters (Vol. I) and exhibits 377 through 404 filed 12/5/2015
    1  PX 257, 258, and 259 were not admitted during trial. These three exhibits were offered
    by plaintiff for impeachment. Trial Tr. 1294:4-5. Defendant objected to their admission as
    substantive evidence. Trial Tr. 1294:11-14. The court deferred its ruling pending further
    discussion in post-trial briefing. Trial Tr. 1294:17-20. Neither the objection nor these exhibits
    were addressed in post-trial briefing.
    2   See note regarding PX 257.
    3   See note regarding PX 257.
    10
    ECF-82    Deposition of Jonathan Peters (Vol. II) and exhibits 405 through 432 filed 12/5/2015
    ECF-83    Deposition of Jonathan Peters (Vol. III) and exhibits 700 through 715 filed
    12/5/2015
    *Expert Report of Thomas E. Mitchell, P.E. and Curriculum Vitae of Franklin M. Grynkewicz,
    P.E. were inadvertently both filed on record as PX 261.
    B.     Exhibits Offered By Defendant
    DX 001    Contract No. N40085-09-C-7002
    DX 002    Contractor Production Reports
    DX 003    Haley & Aldrich Reports - King Pile Installation
    DX 004    Haley & Aldrich Reports - Obstruction Drilling
    DX 005    Haley & Aldrich Reports - Soil Anchors
    DX 006    Haley & Aldrich Reports - Soil Anchors & Obstruction Drilling
    DX 007    FST Engineers/NAVFAC Charrette Inbrief Report
    DX 008    Base Access Master List
    DX 009    Base Access Master List
    DX 010    Sign In Sheet for First Site Visit
    DX 011    Sign In Sheet for Second Site Visit
    DX 012    NASDI Proposal
    DX 013    Moretrench Proposal
    DX 014    Testa Proposal
    DX 015    RDA Bid Calculations
    DX 016    RDA Subcontractor Quotes Comparison
    DX 017    HUB Foundations Proposal
    DX 018    Abstract of Offers
    DX 019    Bid Opening Sign In Sheet
    DX 020    Bid Opening Statement
    DX 021    Government Estimate
    DX 022    Navy Letter to RDA
    DX 023    RDA Letter with Pre-Award Survey Information
    DX 024    RDA Construction Equipment Detail
    DX 025    Bid Extension
    DX 026    Navy Letter to RDA
    DX 027    Moretrench Email to RDA
    DX 028    Moretrench Email to RDA
    DX 029    Notice to Proceed
    DX 030    Email Attaching Cost Breakdown
    DX 031    Navy Email Requesting Site Plan
    DX 032    Email re Pre-Construction Meeting
    DX 033    Construction Site Plan
    11
    DX 034   Email re Schedule Narrative
    DX 035   Email re Draft Schedule
    DX 036   Pre-Construction Meeting Sign-In Sheet
    DX 037   Pre-Construction Agenda & Meeting Minutes
    DX 038   Email re Draft Schedule
    DX 039   Pre-Construction Meeting Agenda and Minutes
    DX 040   Work in Process Draft Schedule
    DX 041   Navy email re Structural Report of Existing Wharf
    DX 042   Emails re 2005 marginal wharf inspection report
    DX 043   Letter No. RDA-001
    DX 044   Email re Schedule
    DX 045   Stich Exhibit 168
    DX 046   FST Letter to Navy
    DX 047   Approval of Scheduler
    DX 048   Navy to RDA re Approval of Scheduler
    DX 049   Navy to RDA re Scheduler Qualifications
    DX 050   RDA Draft Baseline Schedule
    DX 051   RDA Schedule RN00 Draft
    DX 052   RDA Schedule Narrative
    DX 053   RDA to Navy re List of Contractors & Subcontractors
    DX 054   Navy Letter to RDA
    DX 055   Email re Baseline Schedule Challenges
    DX 056   RDA Cost Estimate
    DX 057   RDA & Navy email re Marginal Wharf Issue
    DX 058   NASDI Letter to RDA
    DX 059   RDA Cost Detail
    DX 060   NASDI Letter to RDA
    DX 061   Email re Schedule
    DX 062   Letter No. RDA-002
    DX 063   Invoice No.1
    DX 064   RDA Schedule Narrative
    DX 065   RDA Schedule RN00
    DX 066   RDA Schedule RN00 Tabular Print
    DX 067   Email re SureTrak
    DX 068   RDA Original Mod Pricing Calculations
    DX 069   Email re CPM Cost Loading
    DX 070   Letter No. RDA-003
    DX 071   Email Attaching Schedule with SOV
    DX 072   Email re Final Touches CPM
    DX 073   RDA email re final touches RN00
    DX 074   RDA Schedule Activity ID Report
    12
    DX 075   Letter No. RDA-004
    DX 076   Letter No. RDA-005
    DX 077   HUB Foundation Subcontract Agreement
    DX 078   Moretrench Subcontract Agreement
    DX 079   Email re Updated Schedule
    DX 080   Invoice No. 2
    DX 081   Email re RDA Schedule
    DX 082   Email re Revised CPM
    DX 083   Email re Baseline Schedule
    DX 084   Email re Baseline Schedule
    DX 085   Email re Baseline Schedule
    DX 086   Email re Submittal Review Time
    DX 087   Navy Letter to RDA
    DX 088   Draft Navy Letter (Not Sent)
    DX 089   RDA Schedule Narrative
    DX 090   RDA Schedule Activity ID Report
    DX 091   Email re CPM
    DX 092   Letter No. RDA-006
    DX 093   Letter No. RDA-009
    DX 094   Navy Letter to RDA
    DX 095   Navy Letter to RDA re Baseline Schedule
    DX 096   NAVFAC email re NAS under review
    DX 097   Conditional Schedule Approval
    DX 098   Navy Letter to RDA on Waterfront Improvement
    DX 099   Letter No. RDA-007
    DX 100   RDA Email to Martel
    DX 101   Demolition Plan Submittal
    DX 102   Martel Calculations
    DX 103   Revised Martel Calculations
    DX 104   Letter No. RDA-008
    DX 105   Purchase Order
    DX 106   Demolition Plan Submission
    DX 107   Navy Letter to RDA
    DX 108   Demolition Plan Submission
    DX 109   Request for Proposal
    DX 110   Letter No. RDA-010
    DX 111   Navy Letter to RDA Returning Schedule For Revision
    DX 112   Navy Letter to RDA re Asbestos Abatement Plan
    DX 113   Email re Schedule
    DX 114   Email re Schedule
    DX 115   Email re Cost Loading CPM
    13
    DX 116   Email re Invoicing Procedures
    DX 117   Letter No. RDA-011
    DX 118   Letter No. RDA-012A
    DX 119   Navy Letter to RDA re Wales
    DX 120   Navy Letter to RDA re King Pile Connectors
    DX 121   Navy Letter to RDA re Schedule Submission
    DX 122   Email re Schedule
    DX 123   Letter No. RDA-013
    DX 124   Letter No. RDA-014
    DX 125   Letter No. RDA-015
    DX 126   Email re Cost Loading Mix Up
    DX 127   Navy Letter to RDA re King Pile Connectors
    DX 128   Navy Letter to RDA re Wales
    DX 129   Letter No. RDA-017
    DX 130   Navy Letter to RDA Returning Schedule For Revision
    DX 131   Baseline Schedule Transmittal 016F RA0A
    DX 132   Baseline Schedule Transmittal 016F RA0A Classic Layout
    DX 133   Baseline Schedule Transmittal 016F RA0A Pred Succ Rpt
    DX 134   Navy Letter to RDA Accepting Baseline Schedule
    DX 135   Transmittal 16g Schedule Update
    DX 136   Navy Letter to RDA re Interlock Connectors
    DX 137   Letter No. RDA-018
    DX 138   Letter No. RDA-019
    DX 139   Navy Letter to RDA re Recent Submittals
    DX 140   Navy Letter to RDA re Demolition
    DX 141   Letter No. RDA-016
    DX 142   Navy Letter to RDA re Interlock Connectors
    DX 143   Navy Letter to RDA re PZ 90 degree Corners
    DX 144   RDA Email to Navy re Job Progress Update
    DX 145   Navy Letter to RDA re Job Progress Update
    DX 146   Letter No. RDA-020
    DX 147   Navy Letter to RDA re Updated Construction Schedule
    DX 148   Navy Letter to RDA re Log Report & Schedule Narrative
    DX 149   Navy Letter to RDA re FST Drawings & Elevated Wale
    DX 150   Navy Letter to RDA re Updated Construction Schedule
    DX 151   Navy Letter to RDA re Receipt of Claim
    DX 152   Letter No. RDA-021
    DX 153   Letter No. RDA-024 & RDA-023
    DX 154   Invoice No. 3
    DX 155   Letter No. RDA-022
    DX 156   Email Attaching Kelley Certs & SCUBA AHA
    14
    DX 157   Letter No. RDA-021A
    DX 158   Navy Letter to RDA re Updated Schedule
    DX 159   Navy Letter to RDA re Dig Safe Permit
    DX 160   FST Memo re Site Visit
    DX 161   Letter No. RDA-025
    DX 162   FST Memo re Letter No. RDA-022
    DX 163   Email re King Pile & Soil Anchor Activity Schedule
    DX 164   Letter No. RDA-026
    DX 165   Letter No. RDA-027
    DX 166   Invoice No. 4
    DX 167   Letter No. RDA-028
    DX 168   QC/Production Meeting #1
    DX 169   CorrTech Letter to RDA re Anodes
    DX 170   DCAA Letter to RDA re Access to Records
    DX 171   FST Letter to Navy re Anodes
    DX 172   Email re King Pile Installation Schedule
    DX 173   PWD Newport FEAD Safety Assist Visit Outbrief
    DX 174   Navy Letter to RDA re Safety Mishap
    DX 175   Navy Letter to RDA re Underwater QC Team at SBH
    DX 176   RFI 12
    DX 177   Email re Obstructions
    DX 178   Letter No. RDA-029
    DX 179   Letter No. RDA-030
    DX 180   Non-Compliance Notice No. 1
    DX 181   Email re Obstructions at SBH
    DX 182   QC/Production Meeting #2
    DX 183   Email re Obstructions
    DX 184   Email re Obstructions
    DX 185   Email re Obstructions
    DX 186   Navy Letter to RDA re Safety Mishap
    DX 187   Navy Letter to RDA re Safety Inspection
    DX 188   Navy Letter to RDA re Underwater QC Team
    DX 189   Navy Letter to RDA re Letter No. RDA-027
    DX 190   Email re FST Field Consultation Days
    DX 191   Letter No. RDA-031
    DX 192   QC/Production Meeting #3
    DX 193   Contracting Officer’s Final Decision
    DX 194   Navy Letter to RDA re Updated Schedule
    DX 195   RDA Letters re Personnel
    DX 196   QC/Production Meeting #4
    DX 197   Cost Breakdown
    15
    DX 198   Cost Breakdown
    DX 199   Navy Letter to RDA re Personnel
    DX 200   QC/Production Meeting #5
    DX 201   Letter No. RDA-032
    DX 202   RDA email re Addl Piles Pulled SBH
    DX 203   Navy Letter to RDA re Safety Mishap
    DX 204   Letter No. RDA-033
    DX 205   Letter No. RDA-034
    DX 206   Letter No. RDA-035
    DX 207   QC/Production Meeting #6
    DX 208   Email re Job Cost System
    DX 209   QC/Production Meeting #7
    DX 210   Invoice No. 5A
    DX 211   Letter No. RDA-036
    DX 212   QC/Production Meeting #10
    DX 213   QC/Production Meeting #9
    DX 214   Email re Schedule for Field Observation
    DX 215   FST Consultation Response re SBH and RFI 12
    DX 216   FST Letter re Obstructions
    DX 217   Navy Letter to RDA Acknowledging Updated Schedule
    DX 218   QC/Production Meeting #11
    DX 219   Invoice No. 6A
    DX 220   Draft Monthly Schedule Narrative Update#5
    DX 221   QC/Production Meeting #12
    DX 222   Letter No. RDA-037
    DX 223   Navy Letter to RDA Acknowledging Receipt of Schedule
    DX 224   Letter No. RDA-038
    DX 225   Letter No. RDA-039
    DX 226   Letter No. RDA-040
    DX 227   QC/Production Meeting #16
    DX 228   Letter No. RDA-041
    DX 229   Letter No. RDA-042
    DX 230   Letter No. RDA-043
    DX 231   Letter No. RDA-044
    DX 232   Email with Bond Information Request
    DX 233   FST to Navy re Soil Anchors 50 & 52
    DX 234   FST Letter re RFI 18A
    DX 235   FST Letter re RFI 22
    DX 236   Invoice No. 7
    DX 237   Letter No. RDA-045
    DX 238   Moretrench Soil Anchor Submittal
    16
    DX 239   Email with Photos of Ripped Sheets at WP5
    DX 240   Underwater QC Inspection Report
    DX 241   Email re Letter No. RDA-045
    DX 242   QC/Production Meeting #19
    DX 243   Letter No. RDA-046
    DX 244   Email re Letter No. RDA-045
    DX 245   QC/Production Meeting #20
    DX 246   QC/Production Meeting #21
    DX 247   RI Tax Notices
    DX 248   Email re PCO-015
    DX 249   Email re Conference Call re SBH Sheets
    DX 250   QC/Production Meeting #22
    DX 251   Disapproved Tieback Submittal
    DX 252   Navy Letter to RDA re Soil Disposal
    DX 253   QC/Production Meeting #23
    DX 254   QC/Production Meeting #24
    DX 255   Hub Work Chronology
    DX 256   QC/Production Meeting #25
    DX 257   Navy Letter to RDA re Underwater QC Inspections
    DX 258   Navy Letter to RDA re Two Week Look Ahead
    DX 259   Letter No. RDA-048
    DX 260   RFI 24
    DX 261   Analysis on Mishap Presentation
    DX 262   Navy Letter to RDA re Safety Mishap
    DX 263   Invoice No. 8B
    DX 264   Letter No. RDA-049
    DX 265   Letter No. RDA-050
    DX 266   Non-Compliance Notice No. 2
    DX 267   Letter No. RDA-051
    DX 268   Letter No. RDA-052
    DX 269   RDA Safety Meeting
    DX 270   FST Letter re RFI 24
    DX 271   Email re RDA-053
    DX 272   RDA Email re Obstructions and Deteriorated Sheets
    DX 273   Letter No. RDA-053
    DX 274   Navy Letter to RDA re Letter No. RDA-053
    DX 275   RDA Email re Government letter
    DX 276   Letter No. RDA-054
    DX 277   QC/Production Meeting #28
    DX 278   QC/Production Meeting #28
    DX 279   Navy Letter to RDA re Safety Action Plan
    17
    DX 280   Navy Letter to RDA re Revised Organization Chart
    DX 281   Navy Letter to RDA re Request for Backup Information
    DX 282   Letter No. RDA-055
    DX 283   Letter No. RDA-056
    DX 284   QC/Production Meeting #29
    DX 285   QC/Production Meeting #29
    DX 286   Non-Compliance Notice No. 3
    DX 287   QC/Production Meeting #30
    DX 288   QC/Production Meeting #30
    DX 289   Non-Compliance Notice No. 4
    DX 290   Letter No. RDA-057
    DX 291   Email re Obstructions
    DX 292   Email Requesting Cost Proposal
    DX 293   Navy Letter to RDA Requesting Cost Proposal
    DX 294   Letter No. RDA-058
    DX 295   QC/Production Meeting #31
    DX 296   QC/Production Meeting #31
    DX 297   QC/Production Meeting #31
    DX 298   Letter No. RDA-059
    DX 299   Email re Cost Proposal
    DX 300   QC/Production Meeting #31
    DX 301   Navy Letter to RDA re Obstructions
    DX 302   Navy Letter to RDA Requesting Cost Proposal
    DX 303   Email re RFP Letters
    DX 304   Letter No. RDA-059A
    DX 305   Documents re PCO-025
    DX 306   Letter No. RDA-065
    DX 307   Letter No. RDA-052A
    DX 308   Letter No. RDA-057A
    DX 309   Letter No. RDA-060
    DX 310   Letter No. RDA-061
    DX 311   Letter No. RDA-062
    DX 312   Letter No. RDA-063
    DX 313   Letter No. RDA-064
    DX 314   QC/Production Meeting #32
    DX 315   QC/Production Meeting #32
    DX 316   Letter No. RDA-066
    DX 317   Invoice No. 9
    DX 318   FST Letter to Navy re Cutoff Wall Variance
    DX 319   Letter No. RDA-067
    DX 320   Letter No. RDA-067A
    18
    DX 321   QC/Production Meeting #33
    DX 322   Letter No. RDA-068
    DX 323   Letter No. RDA-069
    DX 324   Letter No. RDA-066A
    DX 325   Letter No. RDA-068A
    DX 326   Letter No. RDA-069A
    DX 327   Navy Letter to RDA re Proposed Personnel
    DX 328   RDA-071
    DX 329   QC/Production Meeting #34
    DX 330   QC/Production Meeting #35
    DX 331   QC/Production Meeting #35
    DX 332   Cost Worksheet re Obstruction Drilling
    DX 333   QC/Production Meeting #35
    DX 334   QC/Production Meeting #36
    DX 335   QC/Production Meeting #36
    DX 336   QC/Production Meeting #37
    DX 337   QC/Production Meeting #37
    DX 338   Mod P00004 Drawings
    DX 339   Letter No. RDA-072
    DX 340   QC/Production Meeting #38
    DX 341   QC/Production Meeting #38
    DX 342   Letter No. RDA-070
    DX 343   QC/Production Meeting #39
    DX 344   QC/Production Meeting #40
    DX 345   Letter No. RDA-073
    DX 346   Letter No. RDA-074
    DX 347   Email re Obstruction Drilling Schedule
    DX 348   Letter No. RDA-075
    DX 349   QC/Production Meeting #39
    DX 350   Letter No. RDA-076
    DX 351   Letter No. RDA-077
    DX 352   HUB Foundation Work Chronology
    DX 353   QC/Production Meeting #43
    DX 354   QC/Production Meeting #43
    DX 355   QC/Production Meeting #44
    DX 356   Navy Letter to RDA re Personnel
    DX 357   Letter No. RDA-061A
    DX 358   Email re Tentative RDA Construction Schedule
    DX 359   QC/Production Meeting #44
    DX 360   QC/Production Meeting #45
    DX 361   Letter No. RDA-078
    19
    DX 362   FST Letter re Landside Anodes
    DX 363   QC/Production Meeting #45
    DX 364   QC/Production Meeting #46
    DX 365   Email re Three Week Schedule
    DX 366   RDA Letter to Navy
    DX 367   FST Site Sketch for CBH WP5a
    DX 368   QC/Production Meeting #46
    DX 369   QC/Production Meeting #46
    DX 370   QC/Production Meeting #47
    DX 371   Navy Letter to RDA re Tie Rods
    DX 372   Letter No. RDA-079
    DX 373   QC/Production Meeting #47
    DX 374   QC/Production Meeting #47
    DX 375   QC/Production Meeting #48
    DX 376   Letter No. RDA-080
    DX 377   Time Impact Analysis Narrative
    DX 378   Email re Current Issues
    DX 379   Obstruction Drilling Change Order Work History
    DX 380   RDA Monthly Schedule Narrative Update #9
    DX 381   Invoice No. 10
    DX 382   FST Letter re Sheet Pile 100B
    DX 383   QC/Production Meeting #48
    DX 384   QC/Production Meeting #49
    DX 385   QC/Production Meeting #49
    DX 386   Narrative re Obstructions at WP7a
    DX 387   QC/Production Meeting #49
    DX 388   QC/Production Meeting #49
    DX 389   QC/Production Meeting #50
    DX 390   Letter No. RDA-081
    DX 391   Email re Rev Drill Mount
    DX 392   QC/Production Meeting #50
    DX 393   QC/Production Meeting #51
    DX 394   QC/Production Meeting #50
    DX 395   Email re WP 7a Obstructions
    DX 396   Email re Crane Accident and SBH Obstructions
    DX 397   Email re Initial Lessons Learned
    DX 398   Safety Lesson Learned: Accident Abstract
    DX 399   Email re Crane Capacity
    DX 400   Email re Navy Site Visit
    DX 401   Email re Crane Accident Report
    DX 402   Details of Accident
    20
    DX 403   Crane Accident Report
    DX 404   FST Letter to Navy with Estimate of FST Consultation Time
    DX 405   Non-Compliance Notice Nos. 5-8
    DX 406   QC/Production Meeting #52
    DX 407   Letter No. RDA-082
    DX 408   Letter No. RDA-083
    DX 409   Negotiation Memorandum
    DX 410   Letter No. RDA-084
    DX 411   QC/Production Meeting #52
    DX 412   QC/Production Meeting #53
    DX 413   Navy Letter to RDA re Safety Incident
    DX 414   Email re Crane Inspection
    DX 415   Letter No. RDA-085
    DX 416   Letter No. RDA-047 Revised
    DX 417   Letter No. RDA-086
    DX 418   QC/Production Meeting #53
    DX 419   QC/Production Meeting #54
    DX 420   QC/Production Meeting #54
    DX 421   Letter No. RDA-087
    DX 422   Letter No. RDA-088
    DX 423   Navy Letter to RDA re Base Access System
    DX 424   QC/Production Meeting #55
    DX 425   QC/Production Meeting #54
    DX 426   Letter No. RDA-089
    DX 427   Letter No. RDA-090
    DX 428   Letter No. RDA-091
    DX 429   Letter No. RDA-092
    DX 430   Navy Letter to RDA re Crane Repair
    DX 431   Non-Compliance Notice No. 9
    DX 432   QC/Production Meeting #56
    DX 433   QC/Production Meeting #55
    DX 434   Letter No. RDA-093
    DX 435   Letter No. RDA-097
    DX 436   Letter No. RDA-094
    DX 437   Letter No. RDA-095
    DX 438   Letter No. RDA-096
    DX 439   Letter No. RDA-099
    DX 440   QC/Production Meeting #56
    DX 441   QC/Production Meeting #56
    DX 442   QC/Production Meeting #57
    DX 443   Navy Letter to RDA re Personnel
    21
    DX 444   Email re Crane Inspection
    DX 445   Martel to RDA re Removal of Modification to Crane
    DX 446   Email re Tie Back Drilling Schedule
    DX 447   QC/Production Meeting #57
    DX 448   QC/Production Meeting #58
    DX 449   Email attaching Soil Anchor Activity Plan
    DX 450   Email re Revisions to Soil Anchor Schedule
    DX 451   QC/Production Meeting #58
    DX 452   QC/Production Meeting #58
    DX 453   Letter No. RDA-098
    DX 454   Letter No. RDA-100
    DX 455   QC/Production Meeting #59
    DX 456   QC/Production Meeting #59
    DX 457   QC/Production Meeting #59
    DX 458   Invoice No. 11
    DX 459   Letter No. RDA-101
    DX 460   Letter No. RDA-102
    DX 461   Terralogic Proposal
    DX 462   Navy Letter to RDA re Letter No. RDA-100
    DX 463   Navy Letter to RDA re Letter No. RDA-102
    DX 464   Email re RevDrill
    DX 465   FST Memo re Soil Anchors
    DX 466   Revised Terralogic Proposal
    DX 467   QC/Production Meeting #60
    DX 468   QC/Production Meeting #61
    DX 469   Email re Change From RevDrill to Casagrande
    DX 470   Letter No. RDA-103
    DX 471   Letter No. RDA-104
    DX 472   Coast Guard Notice re Oil Pollution Incident
    DX 473   Non-Compliance Notice No. 10
    DX 474   Email re Recovery of Proud Mary
    DX 475   Letter No. RDA-106
    DX 476   Letter No. RDA-107
    DX 477   QC/Production Meeting #60
    DX 478   QC/Production Meeting #61
    DX 479   Letter No. RDA-108
    DX 480   Non-Compliance Notice No. 11
    DX 481   Non-Compliance Notice No. 13
    DX 482   QC/Production Meeting #62
    DX 483   QC/Production Meeting #63
    DX 484   QC/Production Meeting #62
    22
    DX 485   Navy Letter to RDA re Personnel
    DX 486   Navy Letter to RDA re Personnel
    DX 487   Letter No. RDA-110
    DX 488   Navy Letter to RDA re Boat Recovery
    DX 489   Letter No. RDA-109
    DX 490   Non-Compliance Notice No. 12
    DX 491   Navy Letter to RDA
    DX 492   Letter No. RDA-112
    DX 493   Letter No. RDA-114
    DX 494   Letter No. RDA-115
    DX 495   Letter No. RDA-116
    DX 496   Letter No. RDA-117
    DX 497   Letter No. RDA-118
    DX 498   Letter No. RDA-119
    DX 499   Letter No. RDA-111
    DX 500   Letter No. RDA-113
    DX 501   Letter No. RDA-122
    DX 502   Letter No. RDA-123
    DX 503   Letter No. RDA-123 REV
    DX 504   MA Dept. of Revenue Letter and Attachments
    DX 505   Letter No. RDA-124
    DX 506   QC/Production Meeting #64
    DX 507   Letter No. RDA-125
    DX 508   Letter No. RDA-126
    DX 509   Letter No. RDA-128
    DX 510   Letter No. RDA-129
    DX 511   Letter No. RDA-130
    DX 512   Letter No. RDA-132
    DX 513   Letter No. RDA-134
    DX 514   QC/Production Meeting #65
    DX 515   QC/Production Meeting #65
    DX 516   Invoice No. 12
    DX 517   QC/Production Meeting #65
    DX 518   QC/Production Meeting #65
    DX 519   Letter No. RDA-131
    DX 520   Email re RFI 31
    DX 521   Invoice No. 13
    DX 522   QC/Production Meeting #65
    DX 523   Letter No. RDA-132REV
    DX 524   QC/Production Meeting #65
    DX 525   QC/Production Meeting #71
    23
    DX 526   Invoice No. 014
    DX 527   QC/Production Meeting #73
    DX 528   Letter No. RDA-135
    DX 529   Letter No. RDA-136
    DX 530   Letter No. RDA-137
    DX 531   Letter No. RDA-138
    DX 532   Letter No. RDA-139
    DX 533   Letter No. RDA-140
    DX 534   Letter No. RDA-141
    DX 535   Email re RDA PCOs
    DX 536   Letter No. RDA-142
    DX 537   QC/Production Meeting #73
    DX 538   Non-Compliance Notice No. 14
    DX 539   Non-Compliance Notice No. 15
    DX 540   Contractor’s Invoice No. 015
    DX 541   Letter No. RDA-143
    DX 542   Letter No. RDA-144
    DX 543   Letter No. RDA-145
    DX 544   Letter No. RDA-146
    DX 545   Letter No. RDA-147
    DX 546   QC/Production Meeting #73
    DX 547   Letter No. RDA-148
    DX 548   Navy Letter to RDA Acknowledging Receipt of Schedule
    DX 549   QC/Production Meeting #74
    DX 550   Letter No. RDA-149
    DX 551   Request for Proposal
    DX 552   QC/Production Meeting #75
    DX 553   QC/Production Meeting #76
    DX 554   QC/Production Meeting #77
    DX 555   Letter No. RDA-150
    DX 556   Letter No. RDA-151
    DX 557   Invoice No. 16
    DX 558   Email re Obstruction Drilling
    DX 559   Email re Drill Patterns Recommended by FST
    DX 560   Email re Drilling Through Obstructions For A Third Time
    DX 561   QC/Production Meeting #79
    DX 562   QC/Production Meeting #79
    DX 563   Email re Drilling Rates
    DX 564   QC/Production Meeting #82
    DX 565   QC/Production Meeting #82
    DX 566   QC/Production Meeting #79
    24
    DX 567   Email re Obstruction Drilling
    DX 568   Letter No. RDA-152
    DX 569   Letter No. RDA-156
    DX 570   Email re Obstruction Drilling
    DX 571   Email re PCO-027
    DX 572   Email re Obstruction Drilling
    DX 573   QC/Production Meeting #83
    DX 574   QC/Production Meeting #83
    DX 575   Request for Proposal
    DX 576   Letter No. RDA-154
    DX 577   QC/Production Meeting #84
    DX 578   QC/Production Meeting #84
    DX 579   Invoice No. 17
    DX 580   QC/Production Meeting #85
    DX 581   QC/Production Meeting #85
    DX 582   QC/Production Meeting #85
    DX 583   Negotiation Memorandum
    DX 584   Email re Modification
    DX 585   Letter No. RDA-155
    DX 586   QC/Production Meeting #86
    DX 587   QC/Production Meeting #86
    DX 588   QC/Production Meeting #88
    DX 589   Letter No. RDA-157
    DX 590   Email re Dredging
    DX 591   QC/Production Meeting #88
    DX 592   QC/Production Meeting #88
    DX 593   QC/Production Meeting #88
    DX 594   Invoice No. 18
    DX 595   Email re Jim Souza
    DX 596   QC/Production Meeting #89
    DX 597   Letter No. RDA-158
    DX 598   QC/Production Meeting #90
    DX 599   QC/Production Meeting #90
    DX 600   Letter No. RDA-159
    DX 601   QC/Production Meeting #91
    DX 602   Letter No. RDA-160
    DX 603   QC/Production Meeting #93
    DX 604   Letter No. RDA-161
    DX 605   SMC Existing Site Survey
    DX 606   QC/Production Meeting #94
    DX 607   Contractor’s Invoice No. 019
    25
    DX 608   QC/Production Meeting #95
    DX 609   QC/Production Meeting #95
    DX 610   Letter No. RDA-164
    DX 611   Letter No. RDA-161A
    DX 612   QC/Production Meeting #96
    DX 613   QC/Production Meeting #96
    DX 614   Letter No. RDA-163
    DX 615   QC/Production Meeting #97
    DX 616   Non-Compliance Notice No. 16
    DX 617   QC/Production Meeting #98
    DX 618   QC/Production Meeting #98
    DX 619   Letter No. RDA-165
    DX 620   Invoice No. 020
    DX 621   QC/Production Meeting #99
    DX 622   QC/Production Meeting #99
    DX 623   Letter No. RDA-167
    DX 624   Letter No. RDA-168
    DX 625   Email re Crane Re-Inspection
    DX 626   Letter No. RDA-166
    DX 627   Letter No. RDA-169
    DX 628   Email re Return Wall
    DX 629   Navy Letter to RDA Acknowledging Receipt of Schedule
    DX 630   Letter No. RDA-170
    DX 631   Email re Crane inspection issue
    DX 632   QC/Production Meeting #100
    DX 633   QC/Production Meeting #100
    DX 634   QC/Production Meeting #100
    DX 635   QC/Production Meeting #100
    DX 636   Show Cause Notice
    DX 637   Response to Show Cause Notice
    DX 638   Email re CAT375 Status
    DX 639   QC/Production Meeting #101
    DX 640   QC/Production Meeting #101
    DX 641   Email re Soil Anchor Records
    DX 642   QC/Production Meeting #102
    DX 643   QC/Production Meeting #102
    DX 644   Contractor’s Invoice No. 021
    DX 645   Letter No. RDA-171
    DX 646   Letter No. RDA-172
    DX 647   Email re Status of Equipment
    DX 648   Letter No. RDA-173
    26
    DX 649   Email re Equipment Status
    DX 650   Notice of Termination
    DX 651   Letter No. RDA-175
    DX 652   Performance Evaluation
    DX 653   Email w/ attachments re Termination for Default
    DX 654   Letter No. RDA-174
    DX 655   FST Meeting Memo
    DX 656   Email re Demobilization
    DX 657   Letter No. RDA-178
    DX 658   Letter No. RDA-182
    DX 659   Email re Demobilization
    DX 660   Email re Inspection
    DX 661   Letter No. RDA-177
    DX 662   Letter No. RDA-179
    DX 663   Letter No. RDA-181
    DX 664   Email re Invoices
    DX 665   Letter No. RDA 180
    DX 666   Email re Correction re Invoice Amounts Paid
    DX 667   RDA Notes
    DX 668   Letter No. RDA-184
    DX 669   Letter No. RDA-185
    DX 670   Letter No. RDA-186
    DX 671   Letter No. RDA-187
    DX 672   Letter No. RDA-188
    DX 673   Letter No. RDA-189
    DX 674   Letter No. RDA-190
    DX 675   RDA Memo #1: Time Line Pile Variance Request
    DX 676   RDA Memo #2: Time Line Obstruction Drilling
    DX 677   RDA Memo #3: Time Line Annual Crane Inspection
    DX 678   RDA Memo #4: Time Line Delayed Rejection of SSHO
    DX 679   RDA Memo #5: Time Line Delayed Response to RFI-26
    DX 680   RDA Memo #6: Time Line RapidGate
    DX 681   RDA Memo #7: Time Line Delayed Approval of QCM
    DX 682   RDA Memo #8: Time Line Delayed Recovery of Proud Mary
    DX 683   RDA Memo #9: Time Line Interference Batter Piles
    DX 684   Email Attaching Navy Letter re Claim Submission
    DX 685   RDA Memo #10: Time Line Revised Closure Details
    DX 686   RDA Memo #11: Time Line Delayed Approval of SSHO/QCM
    DX 687   RDA Memo #12: Time Line Termination Cost & Demobilization
    DX 688   IRS Notice of Levy
    DX 689   Email re Dive Results
    27
    DX 6904      Coastal Diving Report
    DX 691       Letter No. RDA-191
    DX 692       Email re Hydrographic Surveys
    DX 693       Email re Completion Proposal
    DX 694       Email re debris negotiation with GAIC
    DX 695       Navy Letter to RDA
    DX 696       Navy Letter to RDA
    DX 697       Email re Semper Diving Initial Survey
    DX 698       Semper Dive Report
    DX 699       Email re Bond
    DX 700       Tender Agreement
    DX 701       Email re Receipt of Surety Check
    DX 702       Completion Contract Award to Haskell
    DX 703       Job Cost Report - Detailed
    DX 704       Email re Latent Defect
    DX 705       Email re Schedule of Prices
    DX 706       Email re Proposed H-Pile Extraction Plan
    DX 707       Email re Proposed H-Pile Extraction Plan
    DX 708       Depth Survey
    DX 709       Job Cost Report - Summary
    DX 710       Multi-Beam Side-Scan Survey
    DX 711       Contracting Officer’s Final Decision
    DX 7135      Email & attachments re Pile Extraction Log
    DX 714       RI Exempt Purchase Certificate
    DX 715       RDA Sketch
    DX 716       RDA Sketch
    DX 717       Calculations From Interrogatory Responses
    DX 718       Navy Modification File P00004
    DX 719       Navy Modification File P00005
    DX 720       Navy Modification File P00006
    DX 721       Navy Modification File P00007
    DX 722       Navy Modification File P00008
    DX 723       Navy Modification File P00009
    DX 724       Navy Modification File P00010
    DX 725       Navy Modification File P00011
    4 During trial, RDA asserted hearsay objections regarding DX 690, 697, and 698, and those
    objections are preserved as reflected in the transcript. Trial Tr. 2024:2 to 2032:12. The court
    overruled the objections under the residual hearsay exception. Trial Tr. 2031:22 to 2032:12.
    5   DX 712 was withdrawn. Trial Tr. 1664:12-13.
    28
    DX 726   Navy Modification File P00012
    DX 727   Expert Report of Nancy Byrne
    DX 728   Expert Report of James Cohen
    DX 729   Expert Report of Philip Helmes
    DX 730   Expert Report of John McGrath
    DX 731   Expert Report of Scott Richter
    DX 732   Komatsu PC800 Spec Sheet
    DX 733   Manitowoc 4100W Spec Sheet
    DX 734   Kelley Journal Notes
    DX 735   GAIC Payment Bond Claims File
    DX 736   RDA Job Cost Report Used By LMHS
    DX 737   Calculations Accompanying Responses to Defendant’s Third Set of Interrogatories
    DX 738   USACE EP 1110-1-8, Vol. 1
    DX 739   EM 385-1-1 Safety Manual (2003)
    DX 740   EM 385-1-1 Safety Manual (2008)
    DX 741   Certified Payrolls
    DX 742   Project Photographs
    DX 743   Haskell Trucking Records
    DX 744   Haskell Trucking Records
    DX 745   RDA Schedule Files
    DX 746   Assorted PCO Documents and Notes
    DX 747   RDA Equipment Rate Calculations
    DX 748   Email Attaching Notice to Proceed
    DX 749   GAIC Underwriting Memorandum and Associated Documents
    DX 750   Grynkewicz Deposition Exhibit No. 1 (Resume)
    DX 751   Grynkewicz Deposition Exhibit No. 2 (Report)
    DX 752   Grynkewicz Deposition Exhibit No. 3 (Unified Facilities Criteria)
    DX 753   Grynkewicz Deposition Exhibit No. 4 (Manual for Bridge Evaluation)
    DX 754   Grynkewicz Deposition Exhibit No. 5 (Annotated Drawing CD-101)
    DX 755   ASCE7-10
    DX 756   ASCE 37-02
    DX 757   AASHTO Construction Handbook for Bridge Temporary Works
    DX 758   AASHTO - Guide Design Specifications for Bridge Temporary Works
    DX 759   ACI 318
    29
    III.   DEMONSTRATIVE EXHIBITS.
    Although not offered or received as substantive evidence, Trial Tr. 1823:5, the following
    demonstrative exhibits were presented during trial:
    A.      Demonstrative Exhibits Presented By Plaintiff.
    Plaintiff’s Demonstrative Exhibit No. 1: Timeline of drilling modifications
    Plaintiff’s Demonstrative Exhibit No. 2: Hartman Drawing
    Plaintiff’s Demonstrative Exhibit No. 3: Sketch of P-469 Site
    B.      Demonstrative Exhibits Presented By Defendant.
    Defendant’s Demonstrative Exhibit No. 1: Opening Statement Visual Aid
    Defendant’s Demonstrative Exhibit No. 2: Location Graphic
    Defendant’s Demonstrative Exhibit No. 3: Summary Chronology
    Defendant’s Demonstrative Exhibit No. 4: Visual Aid for Expert Testimony of John McGrath
    IV.    WITNESSES.
    Trial witnesses are listed below in order of their first appearance, along with the title of the
    position held during the time period covered by their testimony. The two witnesses whose
    deposition testimony was admitted in lieu of live testimony, by consent of the parties and with
    leave of the court, appear at the end of the list. The witnesses listed below were not proffered as
    expert witnesses unless specifically noted:
    1.      Bruce Wood
    Estimator
    RDA Construction Corp.
    2.      Michael Hartman
    Project Manager
    RDA Construction Corp.
    3.      Mark Wallis
    Project Manager
    RDA Construction Corp.
    4.      Michael Martel, P.E.
    Engineering Consultant to RDA Construction Corp.
    Martel Engineering, Inc.
    30
    5.      David P. Anderson, P.E.
    Project Manager
    Fay, Spofford & Thorndike, LLC
    6.      Sivalingam Sivalogan
    Construction Scheduling
    exPertcon, Inc.
    7.      Lawrence A. Ahearn
    Vice President
    Reagan Construction Corporation
    8.      Craig J. Rachupka
    Civil Engineer
    Facilities Engineering and Acquisition Division, Naval Station Newport
    9.      Eugene Kelley
    President
    RDA Construction Corp.
    10.     Thomas Mitchell, P.E. (expert witness)
    Urban Engineers, Inc.
    Mr. Mitchell was proffered as an expert in construction scheduling.   6   TR at
    1822.
    11.     James Michael Souza
    Pile Driver Foreman
    RDA Construction Corp.
    12.     Travis Germano, P.E.
    Supervisory General Engineer
    Facilities Engineering and Acquisition Division, Naval Station Newport
    13.     Nancy Byrne (expert witness)
    Hydrographer
    Hydro Data, Inc.
    6 RDA proffered Thomas Mitchell, P.E., as an expert in construction scheduling. TR at
    1822. Mr. Mitchell is the General Manager and Vice President of Urban Engineers. TR at 1782.
    Mr. Mitchell received a Master’s degree in civil engineering from Villanova. TR at 1783–84.
    And, has approximately thirty years of experience in scheduling analysis, including thirteen years
    with the United States Army Corps of Engineers. TR at 1784–85. The Government did not object
    to Mr. Mitchell’s qualifications. TR at 1804. Accordingly, the court has determined that Mr.
    Mitchell is an expert in his respective field and qualified to testify as such. See Fed. R. Ev. 702.
    31
    Ms. Byrne was proffered as an expert in hydrographic and geotechnical surveying. 7
    TR at 2446.
    14.     Lieutenant Commander Robert Wadsworth, P.E.
    Director
    Facilities Engineering and Acquisition Division, Naval Station Newport
    15.     Kimberly R. Kahler
    Chief of the Contracting Office
    Naval Facilities Engineering Command, Mid-Atlantic
    16.     John McGrath (expert witness)
    Managing Director
    Beacon Group, LLC
    Mr. McGrath was proffered as an expert in critical path method scheduling and
    delay analysis.8 TR at 2532.
    17.     Philip Helmes, P.E. (expert witness)
    President
    Helmes&Co
    7 The Government proffered Nancy Byrne as an expert in hydrographic and geotechnica l
    surveying. TR at 2446. Ms. Byrne is the owner of Hydro Data, a company that performs
    hydrographic surveys, geophysical surveys, and oceanographic investigations. TR at 2442. Ms.
    Byrne has a Bachelors in Music from the University of Hartford, and a Bachelors in Earth Science
    and Geology from the University of Connecticut. TR at 2444. The American Congress of
    Surveying and Mapping has recognized Ms. Byrne as a Certified Hydrographer. TR at 2445. RDA
    did not object to Ms. Byrne’s qualifications. TR at 2459. Accordingly, the court has determined
    that Ms. Byrne is an expert in her respective field and qualified to testify as such. See Fed. R. Ev.
    702.
    8 The Government proffered John McGrath as an expert in critical path method scheduling
    and delay analysis. TR at 2532. Mr. McGrath received a Bachelor of Science in Aerospace
    Engineering and Masters in Business Administration from the University of Colorado at Boulder.
    TR at 2525–26. He has twenty-three years of experience in construction scheduling. TR at 2531.
    And, has been qualified as an expert in six cases before the United States Court of Federal Claims.
    TR at 2531–32. RDA did not object to Mr. McGrath’s qualifications. Accordingly, the court has
    determined that Mr. McGrath is an expert in his respective field and qualified to testify as such.
    See Fed. R. Ev. 702.
    32
    Mr. Helmes was proffered as an expert in construction project development
    practices, estimating, and management. 9 TR at 2582.
    18.     James Cohen, P.E. (expert witness)
    Associate Principal
    Weidlinger Associates, Inc.
    Mr. Cohen was proffered as an expert in structural collapse and forensic
    engineering.10 TR. 2703–04.
    19.     Scott M. Richter, CPA (expert witness)
    Director, Financial Investigations and Dispute Advisory
    RSM US LLP
    Mr. Richter was proffered as an expert in accounting and forensic accounting.11 TR
    at 2757.
    9   RDA proffered Philip Helmes, P.E., as an expert in construction project development
    practices, estimating, and management. TR at 2582. Mr. Helmes received a Bachelor of Science
    in Structural Civil Engineering from Syracuse University in 1976, and a Masters in Business
    Administration from the University of Connecticut in 1981. TR at 2573–74. Mr. Helmes has
    thirty-five years of experience as a Professional Engineer, with licenses in ten states. TR at 2574.
    He is also the President of Helmes & Co., a consulting practice that specializes in strusctural
    engineering and geotechnical foundation work. TR at 2572–75. The Government did not object
    to Mr. Helmes’s qualifications. TR at 2601. Accordingly, the court has determined that Mr.
    Helmes is an expert in his respective field and qualified to testify as such. See Fed. R. Ev. 702.
    10 The Government proffered James Cohen, P.E., as an expert in structural collapse and
    forensic engineering. TR at 2703–04. Mr. Cohen has a Bachelor of Science from the College of
    Civil Engineering at Cornell University, and a Masters in Concrete Structures from the Imperial
    College of Science and Technology in London. TR at 2695. He became a Professional Engineer
    in 1985. TR at 2694. And, currently serves as the Senior Vice President for Thornton Tomasetti.
    TR at 2698. RDA did not object to Mr. Cohen’s qualifications. TR at 2704. Therefore, the court
    has determined that Mr. Cohen is an expert in his respective field and qualified to testify as such.
    See Fed. R. Ev. 702.
    11  The Government proffered Scott M. Richter, CPA as an expert in accounting and
    forensic accounting. Trial Tr. 2757. Mr. Richter is a litigation support consultant with RSM US.
    TR at 2756. In 1989, Mr. Richter received his undergraduate degree in Business Administra tio n
    from Northeastern University in Boston. In 1991, he became a Certified Public Accountant. TR
    at 2756. Mr. Richter is also a Certified Fraud Examiner. TR at 2757. RDA did not object to Mr.
    Richter’s qualifications. TR at 2757. Accordingly, the court has determined that Mr. Richter is
    an expert in his respective field and qualified to testify as such. See Fed. R. Ev. 702.
    33
    20.    Franklin M. Grynkewicz (expert witness)
    FCC Consulting
    Mr. Grynkewicz was proffered as an expert in civil engineering and safe
    demolition practices.12 TR at 2771.
    21.    Jonathan Peters
    Project Manager
    The Haskell Company
    22.    Marc Nicolazzo
    Senior Engineer
    Fay Spofford Thorndike
    12 RDA proffered Franklin M. Grynkewicz as an expert in civil engineering and safe
    demolition practices. TR at 2771. Mr. Grynkewicz received his first degree in geophysics from
    the University of East Anglia in the in 1976, and his Masters in Civil Engineering from
    Northeastern University in 1984.          TR at 276667.         He has been working as a
    geotechnical/geostructural engineer since 1979. TR at 2767. The Government did not object to
    Mr. Grynkewicz’s qualifications. TR at 2771. Therefore, the court has determined that Mr.
    Grynkewicz is an expert in his respective field and qualified to testify as such. See Fed. R. Ev.
    702.
    34
    

Document Info

Docket Number: 11-555 C

Judges: Susan G. Braden

Filed Date: 7/27/2017

Precedential Status: Precedential

Modified Date: 11/7/2024

Authorities (40)

donald-k-anderson-angel-cortina-jr-and-patricia-b-wallace-and-david ( 2003 )

H.B. Mac, Inc. v. United States ( 1998 )

C. Sanchez and Son, Incorporated v. United States ( 1993 )

William A. Ransom and Robert D. Nesen v. The United States ( 1990 )

Young-Montenay, Inc. v. United States ( 1994 )

Charles W. Daff, Trustee in Bankruptcy for Triad ... ( 1996 )

Reflectone, Inc. v. John H. Dalton, Secretary of the Navy ( 1995 )

admiral-frank-b-kelso-ii-acting-secretary-of-the-navy-v-kirk-brothers ( 1994 )

Daewoo Engineering and Const. Co., Ltd. v. United States ( 2009 )

Helene Curtis Industries, Inc. v. The United States ( 1963 )

Commercial Contractors, Inc. v. United States ( 1998 )

Emily Malone D/B/A Precision Cabinet Company v. The United ... ( 1988 )

Stockton East Water District v. United States ( 2009 )

New York Shipbuilding Corporation v. The United States ( 1967 )

James E. Cox v. Merit Systems Protection Board ( 1987 )

Empire Energy Management Systems, Inc. v. James G. Roche, ... ( 2004 )

Lisbon Contractors, Inc. v. The United States ( 1987 )

Lockheed Martin Ir Imaging Systems, Inc. v. Togo D. West, ... ( 1997 )

Hercules Incorporated v. The United States, Wm. T. Thompson ... ( 1994 )

Warth v. Seldin ( 1975 )

View All Authorities »