Intelligent Waves, LLC v. United States ( 2017 )


Menu:
  •            In the United States Court of Federal Claims
    Nos. 17-1765C and 17-1842C
    (Filed Under Seal: December 1, 2017)
    (Reissued for Publication: December 19, 2017) *
    *************************************
    INTELLIGENT WAVES, LLC and          *
    MISSION1ST GROUP, INC.,             *
    *
    Plaintiffs,             *               Post-Award Bid Protest; Motions for a
    *               Temporary Restraining Order and
    v.                                  *               Preliminary Injunction; Likelihood of
    *               Success on the Merits; Organizational and
    THE UNITED STATES,                  *               Consultant Conflict of Interest; Evaluation
    *               of Proposals; FAR 15.305(a); Irreparable
    Defendant,              *               Injury; Balance of Harms; Public Interest;
    *               National Defense; National Security;
    and                                 *               Failure to Submit a Declaration or
    *               Affidavit Supplying Evidentiary Support
    PROFESSIONAL SOLUTIONS1, LLC,       *
    *
    Defendant-Intervenor.   *
    *************************************
    Lee Dougherty, Washington, DC, and Christian B. Nagel, Tysons, VA, for plaintiffs.
    Russel J. Upton, United States Department of Justice, Washington, DC, for defendant.
    Katherine S. Nucci, Washington, DC, for defendant-intervenor.
    OPINION AND ORDER
    SWEENEY, Judge
    In this bid protest, plaintiffs Intelligent Waves, LLC (“Intelligent Waves”) and
    Mission1st Group, Inc. (“Mission1st”) challenge the award of a five-year Indefinite Delivery
    Indefinite Quantity contract issued by the United States Defense Information Systems Agency
    (“DISA”) to defendant-intervenor Professional Solutions1, LLC (“ProSol”) for certain satellite
    communications support services. Specifically, Intelligent Waves alleges that the DISA
    *
    The court issued this Opinion and Order under seal on December 1, 2017, and directed
    the parties to submit proposed redactions. This reissued Opinion and Order incorporates the
    redactions proposed by the parties, with some nonsubstantive typographical changes. All
    redactions are indicated by a bracketed ellipsis (“[. . .]”).
    improperly evaluated the proposals submitted by Intelligent Waves and ProSol, and Mission1st
    alleges that the DISA improperly evaluated the proposals submitted by Mission1st and ProSol.
    Currently before the court are Intelligent Waves’s and Mission1st’s motions for a temporary
    restraining order and a preliminary injunction enjoining DISA from lifting a stop-work order that
    is currently in place. Because neither protestor is likely to succeed on the merits of its claim, and
    both the balance of harms and the public interest weigh in favor of defendant, the court denies
    both motions.
    I. BACKGROUND
    The Iridium constellation consists of sixty-six cross-linked satellites that operate “as a
    fully meshed network.” Administrative R. (“AR”) 346. The DISA’s Enhanced Mobile Satellite
    Services (“EMSS”) Program Office owns and manages an “EMSS-controlled satellite gateway
    that leverages the Iridium satellite constellation.” Id. The EMSS Program Office provides
    “cradle to grave” satellite communications services, including the sale and provision of EMSS
    devices, a dedicated help desk, encrypted communications, and comprehensive operation and
    maintenance of the EMSS gateway. Id. at 346-47. One of the available services is the
    Distributed Tactical Communications System (“DTCS”). Id. at 347. The DTCS functions as a
    “push-to-talk” service that allows “one-to-many voice communication.” Id. The DTCS is the
    “EMSS variant” of the Iridium commercial push-to-talk (“CPTT”) service. Id. End users of the
    EMSS Program Office services include the United States Department of Defense (“DoD”), other
    federal agencies, state and local governments, Five Eyes nations, and other sponsored
    governments and entities. 1 Id. at 346.
    The DISA reports to the DoD Chief Information Officer (“CIO”). Dep’t of Def.
    Instruction 8420.02 (Sept. 15, 2016) at 10. 2 DoD components are required to procure mobile
    satellite services via procurements managed by the DISA. Id. at 23. Waivers are allowed
    through the DoD CIO when “EMSS cannot satisfy the user requirement.” Id.
    1
    The Five Eyes nations are Australia, Canada, New Zealand, the United Kingdom, and
    the United States. Ashley S. Deeks, A (Qualified) Defense of Secret Agreements, 
    49 Ariz. St. L.J. 713
    , 741 (2016). The Five Eyes agreement is a “long-standing secret intelligence
    agreement” that “allocates electronic surveillance collection among the five states and anticipates
    a high level of coordination and intelligence sharing.” 
    Id.
    2
    Department of Defense Instruction 8420.02 is reproduced at Exhibit 1 of Intelligent
    Waves’s complaint. See ECF No. 1-1.
    -2-
    A. The Request for Proposals
    On December 2, 2016, the DISA issued Request for Proposals number HC1013-16-R-
    0014 (the “RFP”). 3 AR 59. The RFP contemplated a single five-year contract for Global
    Logistical Services Management support (“ELOG”) that would function as a follow-on effort to
    an existing contract, and was designated as a Service-Disabled Veteran-Owned Small Business
    (“SDVOSB”) set aside. 4 Id. at 59, 341, 346-47, 4038. The Performance Work Statement
    (“PWS”) was organized into eight task areas—Operational Support, Logistical and Procurement
    Support, Training Support, Program Management Support, Technical Support, Highly Qualified
    Expert/Subject Matter Expert Support, Operations Center Support, and Transition Support. Id. at
    348. Offerors were required to submit their proposals in five volumes: Executive Summary,
    Technical/Management, Price, Past Performance, and Contract Documentation. Id. at 402. As
    part of the Contract Documentation volume, offerors were directed to include an Organizational
    and Consultant Conflict of Interest (“OCCI”) Mitigation Plan or a statement that no OCCI was
    present. Id. at 408. The OCCI mitigation plan was to be “evaluated on an acceptable or non-
    acceptable basis,” and an unacceptable plan could result in not being selected for award. Id. at
    416.
    The RFP provided that the contract would be awarded to the “responsible offeror whose
    proposal [was] determined to represent the overall best value to the Government using a best
    value tradeoff evaluation process.” Id. at 409. Proposals were evaluated based on three
    factors—Technical/Management Approach, Past Performance, and Price. Id. The non-price
    factors were “significantly more important” than the price factor. Id. Technical/Management
    Approach, which was more important than Past Performance, was comprised of three subfactors
    of equal importance:
    •   Subfactor 1—Remote Mobile Telecommunications Services
    Management Expertise,
    •   Subfactor 2—Management Plan, and
    •   Subfactor 3—Sample Task Order.
    Id. at 409-10. Technical/Management Approach was to be evaluated
    3
    The RFP was subsequently amended six times. AR 344. The last amendment was
    issued on January 26, 2017. Id.
    4
    The incumbent contractor is currently performing under a contract extension. See AR
    1662.
    -3-
    using a combined technical/management rating and risk rating.
    Subfactor ratings shall not be rolled up into an overall color
    rating for the technical/management factor. The combined
    technical/risk rating includes consideration of risk in conjunction
    with the strengths, weaknesses, and deficiencies in determining
    technical ratings.
    Id. at 409. The possible ratings were described as follows:
    Color        Rating                      Description
    Blue       Outstanding     Proposal meets requirements and
    indicates an exceptional approach and
    understanding of the requirements.
    Strengths far outweigh any
    weaknesses. Risk of unsuccessful
    performance is very low.
    Purple         Good         Proposal meets requirements and
    indicates a thorough approach and
    understanding of the requirements.
    Proposal contains strengths which
    outweigh any weaknesses. Risk of
    unsuccessful performance is low.
    Green      Acceptable      Proposal meets requirements and
    indicates an adequate approach and
    understanding of the requirements.
    Strengths and weaknesses are
    offsetting or will have little or no
    impact on contract performance.
    Risk of unsuccessful performance is
    no worse than moderate.
    Yellow       Marginal       Proposal does not clearly meet
    requirements and has not
    demonstrated an adequate approach
    and understanding of the
    requirements. The proposal has one
    or more weaknesses which are not
    offset by strengths. Risk of
    unsuccessful performance is high.
    Red      Unacceptable     Proposal does not meet requirements
    and contains one or more
    deficiencies. Proposal is
    unawardable.
    Id. at 414. The RFP also included relevant definitions:
    -4-
    •    Deficiency—a material failure of a proposal to meet a
    Government requirement or a combination of significant
    weaknesses in a proposal that increases the risk of unsuccessful
    contract performance to an unacceptable level.
    •    Risk—as it pertains to source selection, is the potential for
    unsuccessful contract performance. The consideration of risk
    assesses the degree to which an offeror’s proposed approach to
    achieving the technical factor or subfactor may involve the risk
    of disruption of schedule, increased cost or degradation of
    performance, the need for increased Government oversight,
    and the likelihood of unsuccessful contract performance.
    •    Significant weakness—a flaw that appreciably increases the
    risk of unsuccessful contract performance.
    •    Strength—an aspect of an offeror’s proposal that has merit or
    exceeds specified performance or capability requirements in a
    way that will be advantageous to the Government during
    contract performance.
    •    Uncertainty—any aspect of a non-cost/price factor proposal for
    which the intent of the offeror is unclear (e.g., there is more
    than one way to interpret the proposal or inconsistencies in the
    proposal indicating there may have been an error, omission, or
    mistake).
    Id. at 415.
    Past Performance was evaluated as either acceptable or unacceptable:
    Rating                          Description
    Acceptable    Based on the offeror’s performance record, the
    Government has a reasonable expectation that
    the offeror will successfully perform the
    required effort, or the offeror’s performance
    record is unknown.
    Unacceptable   Based on the offeror’s performance record, the
    Government does not have a reasonable
    expectation that the offeror will be able to
    successfully perform the required effort.
    Id.
    -5-
    The RFP also incorporated by reference several Federal Acquisition Regulation (“FAR”)
    clauses, id. at 416-22, including FAR 52.219-14, Limitations on Subcontracting, id. at 418. In
    addition, the RFP provided contact information for the DISA contracting officer. Id. at 139
    (original RFP), 423 (final amendment). Intelligent Waves, Mission1st, and ProSol, as well as
    other potential offerors, submitted questions prior to the proposal deadline, some of which were
    submitted after the question posting deadline. See, e.g., id. at 162-68 (Intelligent Waves), 169
    (Mission1st), 170-74 (ProSol), 490-92 (Mission1st), 503-05 (ProSol). Many of Intelligent
    Waves’s questions focused on proposal formatting requirements. See generally id. at 164-68.
    Intelligent Waves also commented on the evaluation criteria for past performance, suggesting
    that (1) the DISA incorporate an offeror’s “proven experience to perform work” in “austere
    environments” as contemplated by the RFP and (2) an “Acceptable” past performance rating for
    offerors with no past performance “puts the government and warfighter at risk for [un]successful
    performance on the awarded contract.” Id. at 167. Mission1st sought more information
    regarding the relative importance of factors and subfactors, price information, and proposal
    formatting. Id. at 169, 490-92. ProSol asked questions regarding security clearances,
    compliance with United States Department of State regulations, and proposal formatting
    requirements. Id. at 170-74, 503-05. The DISA responded to 106 total questions that were
    submitted by the question posting deadline. Id. at 1664. See generally id. at 4666-701
    (containing all 106 of the questions and answers).
    B. The Proposals
    Intelligent Waves, Mission1st, ProSol, and three other offerors eventually submitted
    proposals. Id. at 1665, 4048.
    In its proposal, Intelligent Waves described “Team IW” as being “comprised of
    [Intelligent Waves], prime offeror, and [. . .], significant subcontractor.” Id. at 629. The
    Technical/Management volume of Intelligent Waves’s proposal consistently referred to “Team
    IW.” See, e.g., id. at 623 (containing a list of tables and drawings). Intelligent Waves
    represented that it “ha[d] entered into a binding written agreement with our significant team
    member [. . .],” and emphasized that [. . .] was “[. . .].” Id. at 648. Two out of the three prior
    contracts on which Intelligent Waves relied in the Past Performance volume of its proposal were
    [. . .] contracts, including the [. . .]. Id. at 680. Intelligent Waves reported “N/A” for its
    organizational structure change history, and noted that [. . .] was organized in 2006 and had not
    experienced any significant organizational changes since 2009. Id. at 700.
    Intelligent Waves also included an OCCI mitigation plan as part of the Contract
    Documentation volume of its proposal. See generally id. at 761-65. Intelligent Waves stated
    that, “in order to avoid an apparent or perceived” OCCI, neither Intelligent Waves nor [. . .]
    would “provide systems engineering or technical direction[,] prepare specification or work
    statements and/or objectives for requirements[,] or[] provide evaluation services or obtain access
    to propriety information in the execution of the EMSS ELOG contract.” Id. at 761. Intelligent
    Waves acknowledged that [. . .] has “conducted historical sales of Iridium commercial devices,
    namely [CPTT] devices and ancillary items,” and therefore neither Intelligent Waves nor [. . .]
    would “pursue the sale or operational support of any current or future Iridium [CPTT] devices to
    -6-
    new customers who are eligible for Iridium airtime services under the Government’s ‘Iridium
    Flat-Fee Airtime’ (IFFA) contract . . . and the contract awarded from this solicitation . . . unless
    expressly approved by the EMSS waiver process.” Id. Since [. . .] planned to continue to
    provide support to its existing Iridium customers, such as the United States Army Central
    Command, [. . .] promised to segregate employees supporting its Iridium customers from those
    working on the EMSS ELOG contract. Id. at 762.
    In the Technical/Management volume of its proposal, Mission1st provided a management
    plan touting its [. . .]. Id. at 525. See generally id. at 533-40 (containing Mission1st’s
    management plan). Mission1st reported that [. . .] provided a subcontractor management plan.
    Id. at 535. In its staffing plan, Mission1st averred that it had a thirteen-year history of
    “successfully recruit[ing] and retain[ing] hundreds of personnel on DoD contracts at locations
    worldwide,” including [. . .] currently operating throughout the Middle East who have satellite
    communications experience and technical certifications. Id. at 535-36. Mission1st also
    highlighted its “proven ability to quickly grow and shrink [its] staff in response to changing work
    conditions.” Id. at 538.
    In discussing its past performance, Mission1st indicated that it has supported “hundreds
    of projects for DoD software and systems,” and noted that it was then the prime contractor for
    various communications and infrastructure support, information technology services, and
    professional engineering services contracts. Id. at 577. According to Mission1st, the three
    contracts listed in the Past Performance volume of its proposal “cover[ed] every aspect of the
    EMSS ELOG PWS.” Id.; see also id. ([. . .]).
    In its proposal, ProSol declared that it has “fifteen years of technical and recent
    operational experience supporting warfighters around the world” in addition to its Top Secret
    facility clearance that makes it “capable of independently executing every aspect of the
    EMSS/ELOG program requirements.” Id. at 877. ProSol emphasized its “partnership with
    Marshall Communications Corporation [(“Marshall”)],” which ProSol described as a “best-in-
    class” DISA field service representative provider with “Remote Mobile Telecommunications
    Services Management” experience fulfilling “nearly the exact requirements as the ELOG
    Program.” Id. ProSol noted that Marshall is a Veteran-Owned Small Business. Id. In the
    Technical/Management Approach volume of its proposal, ProSol described its experience
    working with the DISA to provide logistics, operations and maintenance, warranty, help desk,
    technical support, and training services in the Middle East and elsewhere. Id. at 887. With
    respect to its organizational structure, ProSol explained that ProSol and Marshall would “execute
    a comparable amount of work,” with the exception that ProSol would exclusively perform
    program management functions, because ProSol and Marshall was a “well-balanced team” with
    respect to technical knowledge and experience. Id. at 896. ProSol noted, however, that it would
    perform a majority of the “direct labor activities” itself, consistent with the set aside. Id.; see
    also id. at 3790 (“As a SDVOSB and in compliance with FAR part 52.219-14, ProSol will
    perform at least 51% of the Labor on this contract.”).
    -7-
    ProSol listed three contracts in the Past Performance volume of its proposal: (1) a $15.6
    million contract between ProSol and the United States Marine Corps for communications,
    systems, and technology support, id. at 955; (2) a $43.3 million contract between Marshall and
    the United States Navy to provide operational, logistical and procurement, technical, and subject
    matter support to the DISA in the Middle East and elsewhere, id. at 958; and (3) $2 million in
    subcontracts between ProSol and the United States Department of Homeland Security to provide
    logistics, help desk, project management, training, communications, and subject matter expert
    services, id. at 963.
    C. Discussions
    After all of the proposals were submitted, the results of initial evaluations were as
    follows:
    Intelligent
    Mission1st           ProSol
    Waves
    Technical/Management Approach
    Subfactor 1     Marginal       Unacceptable        Outstanding
    Subfactor 2     Marginal           Good            Outstanding
    Subfactor 3    Acceptable        Acceptable        Outstanding
    Past Performance
    Acceptable        Acceptable        Acceptable
    Price
    [. . .]          [. . .]        $32,953,522
    Id. at 1670. The contracting officer recommended holding discussions and keeping all six
    offerors in the competitive range because each offeror had a “reasonable chance of being
    selected for award following discussions.” Id. at 1669. Upon approval of the Source Selection
    Authority, evaluation notices (“ENs”) were issued as follows:
    •   Intelligent Waves—five ENs (two technical in nature, one
    regarding OCCI, and two with respect to price);
    •   Mission1st—six ENs (four technical and two price); and
    •   ProSol—one EN (technical).
    Id. at 1673.
    Two rounds of discussions were held. The first round of ENs was transmitted on June
    16, 2017. Id. at 1677 (Intelligent Waves), 1739 (Mission1st), 1756 (ProSol). The second round
    of ENs was transmitted on August 16, 2017. Id. at 2499 (Intelligent Waves), 2533 (Mission1st),
    2542 (ProSol).
    -8-
    During the first round of discussions, the contracting officer sent an EN to Intelligent
    Waves in which he observed that [. . .], Intelligent Waves’s major subcontractor, “sells and
    supports substantial commercial Iridium products and airtime, especially in the Middle East, and
    those products and services essentially compete with the EMSS Program,” and that Intelligent
    Waves “did not demonstrate knowledge of mobile systems and devices . . . outside of [its]
    partnership with [. . .].” Id. at 1680. He noted that [. . .]’s status as a seller of Iridium products
    “increase[d] the risk of non-objective expertise and support being provided” on the EMSS ELOG
    contract. Id. at 1681. He then explained that the proposed firewall among [. . .] employees was
    insufficient because “the impaired objectivity pertains [to] [. . .] as an organization,” not to
    individual groups of employees. Id. at 1683; see also id. at 1689-93 (discussing the insufficiency
    of Intelligent Waves’s OCCI mitigation plan). The contracting officer noted that [. . .] was not
    an Iridium reseller [. . .]. Id.
    Intelligent Waves submitted an updated OCCI mitigation plan in response to this EN. Id.
    at 2141. However, the contracting officer remained concerned that the updated OCCI mitigation
    plan failed to adequately address the concern regarding [. . .]’s “impaired objectivity.” Id. at
    2506, 2517-18. Specifically, as reflected in a subsequent EN sent to Intelligent Waves, the
    contracting officer remarked that part of the updated mitigation plan involved utilizing only
    Intelligent Waves direct employees to perform certain PWS activities, which was problematic for
    the DISA because those activities “are integrated into larger task order requirements . . . and
    cannot reasonably be segregated without imposing a substantial burden on the government that
    elevates the risk of unsuccessful performance.” Id. at 2507. Further, the contracting officer
    noted that the determination of Intelligent Waves that commercial Iridium CPTT services did not
    compete with EMSS DTCS services ran contrary to the DISA’s view. Id. at 2510. He also
    stated that Intelligent Waves failed to address how [. . .]’s legacy customers would be dealt with.
    Id. at 2510, 2517. Ultimately, the contracting officer advised that it was “unacceptable to the
    Government” for a contractor to [. . .]. Id. at 2518. Intelligent Waves responded to this EN with
    another updated OCCI mitigation plan. Id. at 2805-06.
    D. Evaluation of Proposals
    After the second round of discussions, the revised proposals were evaluated. During its
    evaluation, the evaluation team determined that Intelligent Waves did not resolve any of its non-
    price ENs, id. at 4154, 4161, and that Mission1st resolved all of its non-price ENs, id. at 4150-
    52. The final evaluations were as follows:
    -9-
    Intelligent
    Mission1st            ProSol
    Waves
    Technical/Management Approach
    Subfactor 1     Marginal         Acceptable         Outstanding
    Subfactor 2     Marginal           Good             Outstanding
    Subfactor 3    Acceptable        Acceptable         Outstanding
    Past Performance
    Acceptable        Acceptable         Acceptable
    Price
    [. . .]          [. . .]         $30,295,442
    Id. at 4128-29, 4203.
    The evaluation team assigned the following strengths and weaknesses with respect to the
    Technical/Management Approach factor:
    Intelligent
    Mission1st             ProSol
    Waves
    Technical/Management Approach
    7 strengths
    Subfactor 1          [. . .]          [. . .]
    0 weaknesses
    8 strengths
    Subfactor 2          [. . .]          [. . .]
    0 weaknesses
    1 strength
    Subfactor 3          [. . .]          [. . .]
    0 weaknesses
    Id. at 4134-40 (ProSol), 4149-53 (Mission1st), 4153-63 (Intelligent Waves). With respect to the
    Past Performance factor the evaluation team noted that all three of ProSol’s past performance
    references returned questionnaires, and each of ProSol’s three prior contracts were deemed
    recent, relevant, and to have an acceptable quality of performance. Id. at 4169-74. Intelligent
    Waves also had all three past performance contracts rated as recent, relevant, and having an
    acceptable quality of performance. Id. at 4195. Mission1st similarly had all three past
    performance contracts rated as recent and relevant, but only one was deemed to have an
    acceptable quality of performance (with the remaining two unknown). Id. at 4189-90.
    Ultimately, the evaluation team recommended that ProSol be awarded the contract. Id. at
    4122, 4203. Specifically, in comparing ProSol’s and Mission1st’s proposals, the evaluation team
    determined that ProSol’s approach under subfactor 1 had “numerous technical advantages over
    that of [Mission1st],” id. at 4211; that ProSol’s “proposed organizational structure [was] superior
    to [Mission1st’s]” under subfactor 2, id. at 4212; and that ProSol’s sample task order under
    subfactor 3 “contained advantages” over Mission1st, id. at 4213. The evaluation team further
    found that there was “no advantage to either proposal under the past performance factor,” but
    ProSol’s “numerous strengths that benefit the Government in various ways that [Mission1st’s]
    proposal is lacking” and concomitant lower risk of unsuccessful performance outweighed
    Mission1st’s slight price advantage. Id. at 4214.
    -10-
    Then, in comparing the proposals of ProSol and Intelligent Waves, the evaluation team
    determined that “[t]he relative merits of ProSol’s proposed approach to subfactor 1 [were]
    technically superior to the relative merits of [Intelligent Waves’s] proposed approach,” id. at
    4219; that “ProSol’s proposed organization structure and proposed cost management plan [were]
    superior to those of [Intelligent Waves] with strengths in [ProSol’s] approach for recruiting and
    retaining personnel, . . . subcontract management, organizational structure methodology, and . . .
    flexibility and performance” under subfactor 2, id. at 4220; and that ProSol’s sample task order
    under subfactor 3 was “exceptional” and thus “superior” to the adequate sample task order
    submitted by Intelligent Waves, id. The evaluation team referred to [. . .]’s involvement as
    “present[ing] a risk of impaired objectivity in [Intelligent Waves’s] performance of the contract,”
    but noted that “[e]ven if these weaknesses related to . . . utilizing [. . .] as a subcontractor were
    completely mitigated, ProSol’s technical advantages . . . outweigh[ed Intelligent Waves’s] price
    advantage.” Id. at 4221.
    E. The Source Selection Decision and Contract Award
    After reviewing the evaluation team’s report, the Source Selection Authority determined
    that ProSol’s proposal “offer[ed] the best value” to the DISA. Id. at 4413; accord id. at 4501.
    The Source Selection Authority observed that ProSol’s approach was “free of weaknesses and
    deficiencies,” “contain[ed] sixteen strengths and no weaknesses,” and was “technically superior
    to all other offerors.” Id. at 4501. Therefore, the Source Selection Authority explained, ProSol’s
    “technical superiority” outweighed the lower prices proposed by Intelligent Waves and
    Mission1st. Id. Because ProSol’s price was “balanced, complete, and fair and reasonable” and
    ProSol “met all administrative requirements of the RFP,” the contracting officer was directed to
    award the ELOG contract to ProSol. Id.
    The ELOG contract was officially awarded to ProSol on October 20, 2017. Id. at 4299.
    Both Intelligent Waves and Mission1st had been notified, three days prior to the official award,
    of their non-selection and that ProSol was determined to represent the overall best value. Id. at
    4090 (Intelligent Waves), 4101 (Mission1st). Both Intelligent Waves and Mission1st received
    written debriefings on October 20, 2017. See generally id. at 4286-90 (Intelligent Waves), 4295-
    97 (Mission1st). The contracting officer answered follow-up questions submitted by Mission1st
    on October 24, 2017. See id. at 4515-16.
    F. Procedural History
    Mission1st filed a protest at the Government Accountability Office (“GAO”) on October
    25, 2017. See generally id. at 4521-29. Mission1st argued that the DISA improperly evaluated
    ProSol’s proposal because (1) ProSol did not have the expertise to meet the requirements for
    subfactor 1 of the Technical/Management Approach factor, (2) Mission1st should have received
    an “Outstanding” rating for subfactor 2, (3) ProSol does not have sufficient experience to
    warrant an “Acceptable” past performance rating and thus Mission1st should have been rated “at
    least equivalent” to ProSol with respect to its overall technical capability, and (4) ProSol would
    be unable to adhere to the limitation on subcontracting clause contained in the RFP. Id. at 4524-
    28. Pursuant to FAR 52.233-3, a stop-work order was issued on October 30, 2017. Id. at 4558.
    -11-
    ProSol filed a motion for summary dismissal of the protest on November 13, 2017. Id. at 4577-
    80. The DISA then filed a motion to dismiss the protest on November 15, 2017, id. at 4621,
    arguing generally that Mission1st’s protest grounds were “untimely, speculative, and fail[ed] to
    state a valid basis of protest,” id. at 4623.
    In the meantime, on November 9, 2017, Intelligent Waves filed the instant protest in this
    court, arguing generally that the DISA improperly evaluated Intelligent Waves’s and ProSol’s
    proposals, and further arguing that the DISA’s determination regarding the insufficiency of
    Intelligent Waves’s OCCI mitigation plan was arbitrary and capricious because it followed a
    plan [. . .]. Compl. ¶¶ 3-4. Intelligent Waves explained that (1) ProSol’s “lack of demonstrated
    ‘expertise’” precluded ProSol from receiving an “Outstanding” rating under subfactor 1 of the
    Technical/Management Approach factor, id. ¶ 69, (2) Intelligent Waves “itself” had the requisite
    experience to perform under subfactor 1 and thus its assessment of a weakness was improper, id.
    ¶¶ 73, 77, and (3) ProSol lacked the requisite experience to receive an “Outstanding” rating
    under subfactor 2, id. ¶ 84.
    On November 16, 2017, the DISA requested that the GAO dismiss Mission1st’s protest
    pursuant to 
    4 C.F.R. § 21.11
    (b) because the protest concerned the same procurement as the
    instant bid protest. AR 4706. Mission1st opposed DISA’s dismissal, id. at 4741-42, while
    ProSol agreed that the GAO protest should be dismissed, id. at 4743. The GAO issued a
    dismissal order on November 21, 2017, explaining that the GAO would not entertain protests
    “where the matter involved is the subject of litigation before a court of competent jurisdiction . . .
    [e]ven where the specific issues before the court are not the same as those raised [at the GAO]
    . . . if there is a reasonable possibility that the court’s disposition of the matter [would] render a
    decision by [the GAO] academic,” and that the Intelligent Waves complaint in this court called
    into question ProSol’s expertise and capabilities and the reasonableness of the DISA’s
    evaluation. Id. at 4746-47.
    On November 28, 2017, Mission1st filed its complaint in this court, asserting the same
    claims that it presented to the GAO. That case was transferred to the undersigned and
    consolidated with this case on November 29, 2017. Because the DISA indicated that it would lift
    its stop-work order on December 1, 2017, see Def.’s Opp’n to Pls.’ Mots. for Emergency
    Injunctive Relief (“Def.’s Opp’n”) Attach. 3, ECF 29-1, Intelligent Waves and Mission1st filed
    motions for a temporary restraining order and a preliminary injunction. Defendant responded on
    November 30, 2017, and the court heard oral argument on December 1, 2017.
    II. STANDARD OF REVIEW
    The United States Court of Federal Claims (“Court of Federal Claims”) possesses
    “jurisdiction to render judgment on an action by an interested party objecting to . . . the award of
    a contract or any alleged violation of statute or regulation in connection with a procurement or a
    proposed procurement,” 
    28 U.S.C. § 1491
    (b)(1) (2012), and may “award any relief that the court
    considers proper, including declaratory and injunctive relief except that any monetary relief shall
    be limited to bid preparation and proposal costs,” 
    id.
     § 1491(b)(2). In bid protests, the Court of
    Federal Claims reviews the challenged agency action pursuant to the standards set forth in 5
    -12-
    U.S.C. § 706. Id. § 1491(b)(4). Although section 706 contains several standards, “the proper
    standard to be applied in bid protest cases is provided by 
    5 U.S.C. § 706
    (2)(A): a reviewing
    court shall set aside the agency action if it is ‘arbitrary, capricious, an abuse of discretion, or
    otherwise not in accordance with the law.’” Banknote Corp. of Am. v. United States, 
    365 F.3d 1345
    , 1350 (Fed. Cir. 2004); accord Per Aarsleff A/S v. United States, 
    829 F.3d 1303
    , 1309
    (Fed. Cir. 2016). The “arbitrary and capricious” standard is “highly deferential” and requires
    courts to sustain agency actions that demonstrate “rational reasoning and consideration of
    relevant factors.” Advanced Data Concepts, Inc. v. United States, 
    216 F.3d 1054
    , 1058 (Fed.
    Cir. 2000). In other words, reviewing courts conduct a “rational basis” review of the agency
    action at issue, rather than an “independent de novo assessment.” Turner Constr. Co., Inc. v.
    United States, 
    645 F.3d 1377
    , 1384-85 (Fed. Cir. 2011) (internal quotation marks omitted).
    Rule 65 of the Rules of the United States Court of Federal Claims guides the court in
    awarding preliminary injunctive relief. Preliminary injunctive relief is “an extraordinary and
    drastic remedy.” Mazurek v. Armstrong, 
    520 U.S. 968
    , 972 (1997) (per curiam) (internal
    quotation marks omitted); accord FMC Corp. v. United States, 
    3 F.3d 424
    , 427 (Fed. Cir. 1993);
    Akal Sec., Inc. v. United States, 
    87 Fed. Cl. 311
    , 316 (2009). A protestor “seeking a preliminary
    injunction must establish that [it] is likely to succeed on the merits, that [it] is likely to suffer
    irreparable harm in the absence of relief, that the balance of equities tips in [its] favor, and that
    an injunction is in the public interest.” Winter v. Nat. Res. Def. Council, Inc., 
    555 U.S. 7
    , 20
    (2008); accord Amidon, Inc. v. United States, 
    124 Fed. Cl. 517
    , 522 (2015). None of the four
    factors, taken individually, is dispositive, and a “weakness of the showing regarding one factor
    may be overborne by the strength of the others.” FMC Corp., 
    3 F.3d at 427
    . Conversely, “the
    absence of . . . any one factor may be sufficient” to deny preliminary injunctive relief. Id.; see
    also Wind Tower Trade Coal. v. United States, 
    741 F.3d 89
    , 100 (Fed. Cir. 2014) (“[A] showing
    on one preliminary injunction factor does not warrant injunctive relief in light of a weak showing
    on other factors.”); Atlanta Pharma AG v. Teva Pharm. USA, Inc., 
    566 F.3d 999
    , 1005 (Fed. Cir.
    2009) (“[A] movant must establish the existence of both of the first two factors to be entitled to a
    preliminary injunction.”). The award of preliminary injunctive relief is within the discretion of
    the court. FMC Corp., 
    3 F.3d at 427
    . “When injunctive relief is warranted, it will only be issued
    upon a showing by a preponderance of the admissible evidence.” Textron, Inc. v. United States,
    
    74 Fed. Cl. 277
    , 287 (2006).
    III. ANALYSIS
    As an initial matter, the court finds that it has jurisdiction over the instant protests
    because both Intelligent Waves and Mission1st have made nonfrivolous allegations that the
    DISA improperly evaluated proposals. See Distributed Sols., Inc. v. United States, 
    539 F.3d 1340
    , 1345 n.1 (2008) (“A non-frivolous allegation of a statutory or regulatory violation in
    connection with a procurement or proposed procurement is sufficient to establish jurisdiction.”).
    Further, both Intelligent Waves and Mission1st have standing as “interested parties” because
    each submitted a proposal and was determined to be in the competitive range. See CACI, Inc.-
    Fed. v. United States, 
    719 F.2d 1567
    , 1575 (Fed. Cir. 1983) (finding that a protestor “within the
    ‘zone of active consideration’” had “standing to challenge the proposed award”).
    -13-
    A. Likelihood of Success on the Merits
    To prevail on their motions for a preliminary injunction, either Intelligent Waves or
    Mission1st must establish that it is likely to succeed on the merits of its protest. Under the
    applicable standard of review, the court
    may set aside a procurement action if (1) the procurement official’s
    decision lacked a rational basis; or (2) the procurement procedure
    involved a violation of regulation or procedure. A court reviews a
    challenge brought on the first ground to determine whether the
    contracting agency provided a coherent and reasonable explanation
    of its exercise of discretion, and the disappointed bidder bears a
    heavy burden of showing that the award decision had no rational
    basis. When a challenge is brought on the second ground, the
    disappointed bidder must show a clear and prejudicial violation of
    applicable statutes or regulations.
    Centech Grp., Inc. v. United States, 
    554 F.3d 1029
    , 1037 (Fed. Cir. 2009) (citations and internal
    quotation marks omitted).
    If the court finds that “the government acted without rational basis or contrary to law
    when evaluating bids and awarding the contract,” it must then “determine, as a factual matter,
    whether the bid protester was prejudiced by that conduct.” Bannum, Inc. v. United States, 
    404 F.3d 1346
    , 1351 (Fed. Cir. 2005). A bid protester demonstrates prejudice by “show[ing] that
    there was a ‘substantial chance’ it would have received the contract award” absent the error
    found by the court. 
    Id. at 1353
    ; see also Linc Gov’t Servs., LLC v. United States, 
    96 Fed. Cl. 672
    , 695-97 (2010) (distinguishing “allegational prejudice” required to establish standing from
    the “prejudicial error” required to prevail on the merits).
    The court finds that neither Intelligent Waves nor Mission1st is likely to succeed on the
    merits of their protests.
    The gravamen of Intelligent Waves’s protest is that the DISA’s determination that [. . .]’s
    Iridium sales presented an OCCI weakness was “arbitrary, capricious, and lack[ed] a rational
    basis.” Intelligent Waves Mem. Supp. Mot. TRO & Mot. Prelim. Inj. (“Intelligent Waves
    Mem.”) 20, ECF No. 24. A conflict of interest arises when a contractor “will evaluate its own
    offers for products or services, or those of a competitor, without proper safeguards to ensure
    objectivity to protect the Government’s interests.” FAR 9.505-3. At oral argument, counsel for
    Intelligent Waves stressed that there is no competition between Iridium CPTT and EMSS DTCS
    because the DoD CIO, who oversees the DISA, has the authority to grant waivers allowing DoD
    agencies to procure Iridium CPTT services, and, in any event, the DoD components are not in
    competition with one another because they fall under the same umbrella.
    -14-
    Intelligent Waves’s argument concerning OCCI is unavailing. First, the DoD as a whole
    is not considered one agency. DoD departments are the separate military departments (Army,
    Navy, and Air Force—the Marine Corps is part of the Navy), and the various “defense agencies”
    include the DISA, the Defense Intelligence Agency, the National Geospatial-Intelligence
    Agency, the National Security Agency, the United States Special Operations Command, the
    Defense Logistics Agency, and others. See Defense Federal Acquisition Regulation Supplement
    202.101. Thus, various components of the DoD are considered separate agencies. Second, it is
    well within the DISA’s discretion to determine that Iridium CPTT and EMSS DTCS are
    competing services. This determination is logical because both services “offer similar capability
    . . . to the same customer markets,” AR 4435, and the DISA is free to prefer one over the other,
    as it has consistently done. Third, that [. . .] is currently [. . .] is of no moment with respect to the
    OCCI issue because (1) [. . .] did not become an Iridium reseller until after it [. . .] and (2) the
    DISA is free to institute new requirements in new procurements. Fourth, Intelligent Waves
    received multiple ENs regarding its OCCI weakness and failed to adequately address the DISA’s
    concerns. The DISA explained its rationale at length in the ENs, in the technical evaluation, in
    the source selection document, and in the debriefing. Simply put, Intelligent Waves cannot
    overcome its “heavy burden,” Impresa Construzioni Geom. Domenico Garufi v. United States,
    
    238 F.3d 1324
    , 1332-33 (Fed. Cir. 2001), of demonstrating that the DISA’s determination lacked
    a rational basis.
    Finally, even if the DISA erred in finding that [. . .]’s participation gave rise to an OCCI
    and thus one or more weaknesses, there is no prejudicial error because the DISA found that
    ProSol’s proposal was technically superior to Intelligent Waves’s proposal notwithstanding the
    various issues concerning [. . .] and the OCCI. The OCCI only concerned subfactors 1 and 2.
    Even if Intelligent Waves had also received fifteen total strengths across those two subfactors
    (like ProSol) instead of [. . .], ProSol was still rated “Outstanding” for subfactor 3, compared to
    Intelligent Waves’s “Acceptable” rating, based on the sample task orders.
    Intelligent Waves also contends that the DISA “failed to adhere to the evaluation
    requirements stated in the [RFP] when it found that ProSol warranted an outstanding rating under
    Subfactor 1.” Intelligent Waves Mem. 27. It is axiomatic that proposals must be evaluated in a
    manner that is “reasonable and consistent with the evaluation criteria and applicable statutes and
    regulations,” and that the “merit of competing proposals is primarily a matter of agency
    discretion.” E.W. Bliss Co. v. United States, 
    77 F.3d 445
    , 449 (Fed. Cir. 1996) (internal
    quotation marks omitted); accord FAR 15.305(a) (providing that government agencies must
    “evaluate competitive proposals and then assess their relative qualities solely on the factors and
    subfactors specified in the solicitation”). Intelligent Waves provides no support for its argument
    that the DISA did not follow the evaluation criteria set forth in the RFP beyond its averment that
    ProSol’s experience was “insufficient to demonstrate ‘expertise’ in providing support in remote,
    hostile locations.” Intelligent Waves Mem. 29. Intelligent Waves appears to argue that ProSol
    cannot rely on the experience of its subcontractor partner to meet the experience requirement,
    which runs counter to Intelligent Waves’s assertions that the experience of its own subcontractor
    partner is relevant to capability determinations. Intelligent Waves cannot have it both ways.
    “After all, in the law, what is sauce for the goose is normally sauce for the gander.” Heffernan v.
    City of Paterson, 
    136 S. Ct. 1412
    , 1418 (2016). Regardless, the DISA provided detailed
    -15-
    explanations of the relevant experience that ProSol brings to the table. Further, even if ProSol
    had been rated lower than “Outstanding” for subfactor 1 of the Technical/Management Approach
    factor, it was rated “Outstanding” in the remaining technical subfactors with myriad strengths.
    Thus, if the OCCI-related issues discussed above were set aside and Intelligent Waves received
    “Outstanding” ratings for subfactors 1 and 2, ProSol still would have been rated technically
    superior. 5
    Mission1st similarly avers that the DISA improperly assigned ProSol an “Outstanding”
    rating in subfactor 1 because “ProSol has no experience performing computer facilities
    management services on federal contracts of significant size and extremely limited experience in
    the geographic region or battlefield environment(s) as required by the [RFP].” Mission1st Mem.
    Supp. Mot. Injunctive Relief (“Mission1st Mem.”) 9, ECF No. 26. Mission1st’s argument
    concerning ProSol’s subfactor 1 rating fails for the same reason that Intelligent Waves’s
    argument regarding subfactor 1 failed—the DISA sufficiently explained the relevant experience
    that ProSol brings to the table, with or without its subcontractor partner.
    Mission1st also posits that it should have received an “Outstanding” rating for subfactor
    2, rather than a “Good” rating, because it was assessed [. . .] that were described as
    “outstanding,” see AR 4295-96, and [. . .]. Mission1st’s reasoning reflects an improper
    application of the stated evaluation criteria. A “Good” rating was assigned to subfactors with
    strengths that “outweigh[ed]” any weaknesses, while an “Outstanding” rating was assigned when
    strengths “far outweigh[ed]” any weaknesses. In other words, Mission1st’s [. . .] in subfactor 2
    did not necessarily compel an “Outstanding” rating for that subfactor, as outstanding as those
    individual strengths may have been. Therefore, the DISA did not improperly rate Mission1st’s
    proposal as “Good” for subfactor 2. But even if Mission1st had been assigned an “Outstanding”
    rating, ProSol’s “Outstanding” rating—with eight strengths compared to [. . .]—likely would
    have carried more weight in the DISA’s overall best value determination. Thus, if ProSol had
    received a lower rating for subfactor 1, and Mission1st had received a higher rating for subfactor
    2, it would not have been unreasonable for the DISA to determine that ProSol provided a
    technically superior proposal.
    With respect to past performance, Mission1st asserts that ProSol was undeserving of its
    “Acceptable” rating. Mission1st invokes FAR 15.305(a)(2)(iv), which states that “an offeror
    without a record of relevant past performance or for whom information on past performance is
    not available . . . may not be evaluated favorably or unfavorably.” Mission1st avows that the
    lack of a neutral past performance rating, in contravention to the FAR, “improperly allowed the
    [DISA] to assign a favorable rating to offerors with no past performance.” Mission1st Mem. 12.
    Mission1st’s argument here fails for two reasons. First, Mission1st did not raise this argument in
    a pre-award protest. Contractors who have the opportunity to object to the terms of a
    solicitation, but fail to do so, are precluded from later raising such objections in a bid protest.
    Blue & Gold Fleet, L.P. v. United States, 
    492 F.3d 1308
    , 1313 (Fed. Cir. 2007); see also Per
    Aarsleff A/S, 829 F.3d at 1313. Second, even if there should have been a neutral rating available
    5
    Intelligent Waves contends only that it “would have received either Good or
    Acceptable ratings under [subfactors 1 and 2].” Intelligent Waves Mem. 27.
    -16-
    for past performance, it likely would not have changed the results. ProSol provided three past
    performance references, all of which were deemed recent, relevant, and of acceptable quality. It
    was therefore reasonable for ProSol to have been given an “Acceptable” rating on the Past
    Performance factor.
    Mission1st’s final assignment of error relates to the limitations on subcontracting. FAR
    52.219-14(c)(1) provides that “[a]t least 50 percent of the cost of contract performance incurred
    for personnel shall be expended for employees of the concern.” While Mission1st correctly
    states the law, it fails to recognize that ProSol’s proposal does not violate the limitations on
    subcontracting. ProSol demonstrated that it is acutely aware of the limitations on subcontracting,
    and proposed to perform a majority of the contract work.
    In sum, neither Intelligent Waves nor Mission1st is likely to succeed in demonstrating
    that the DISA’s decision to award the EMSS ELOG contract to ProSol was arbitrary, capricious,
    an abuse of discretion, or otherwise contrary to law. Nevertheless, for the sake of completeness,
    the court addresses the remaining factors for establishing the need for injunctive relief:
    irreparable injury, the balance of harms, and the public interest.
    B. Irreparable Injury
    With respect to irreparable injury, a protestor “must show that without a preliminary
    injunction it will suffer irreparable harm before a decision can be rendered on the merits.” Akal
    Sec., 87 Fed. Cl. at 311; accord IBM Corp. v. United States, 
    118 Fed. Cl. 677
    , 683-84 (2014).
    Intelligent Waves avers, through its counsel (without a supporting affidavit or declaration), that it
    will lose the opportunity to compete for the EMSS ELOG contract, expected profits from
    performing the contract, and “the experience in performing this complex, global contract that
    [Intelligent Waves] could apply toward its future proposals for other government work,” if it
    does not receive injunctive relief because it “cannot recover these financial and experiential
    losses” without such relief. Intelligent Waves Mem. 30. Mission1st also avers, through its
    counsel (without a supporting affidavit or declaration), that it will “suffer irreparable harm if an
    injunction is not granted, because the only other available relief—the potential for recovery of
    bid preparation costs—will not compensate Mission1st for the loss of valuable business on the
    Solicitation.” Mission1st Mem. 17. Neither Intelligent Waves nor Mission1st has provided the
    court with the evidence necessary to carry its burden. See Gemtron Corp. v. Saint-Gobain Corp.,
    
    572 F.3d. 1371
    , 1380 (Fed. Cir. 2009) (observing that “unsworn attorney argument . . . is not
    evidence”).
    For the sake of argument, however, the court will proceed with its analysis as if
    Intelligent Waves and Mission1st had submitted evidentiary support for their claims. The Court
    of Federal Claims has recognized that a lost opportunity to compete for a contract—and the
    attendant inability to obtain the profits expected from the contract—can constitute an irreparable
    injury. See, e.g., Akal Sec., 87 Fed. Cl. at 819; Heritage of Am., LLC v. United States, 
    77 Fed. Cl. 66
    , 78 (2007); Overstreet Elec. Co. v. United States, 
    47 Fed. Cl. 728
    , 743 (2000).
    -17-
    Absent preliminary injunctive relief, the stop-work order will be lifted on December 1,
    2017, and both Intelligent Waves and Mission1st will likely have permanently lost the
    opportunity to perform under the contract. No adequate remedy exists to make up for this
    potential loss of business or competitive advantage; were they to be awarded, bid preparation and
    protest costs would be wholly insufficient. Accordingly, both Intelligent Waves and Mission1st
    will likely be irreparably injured absent injunctive relief.
    C. Balance of Harms
    In addition to considering whether a protestor would suffer an irreparable injury absent
    injunctive relief, “[t]he court must balance the harm plaintiff would suffer without preliminary
    relief against the harm that preliminary relief would inflict on defendant and defendant-
    intervenor. Generally, if the balance tips in favor of defendant, a preliminary injunction is not
    appropriate.” Akal Sec., 87 Fed. Cl. at 320 (citation omitted); accord Reilly’s Wholesale
    Produce v. United States, 
    73 Fed. Cl. 705
    , 715 (2006). The court has already presumed, for
    argument’s sake, that Intelligent Waves and Mission1st will likely suffer an irreparable injury in
    the absence of preliminary injunctive relief. Intelligent Waves contends that the “DISA can
    maintain the services needed through a brief extension to [. . .] during the pendency of this
    protest.” Intelligent Waves Mem. 30-31. Mission1st similarly argues that the DISA can “easily
    extend its current contract with [. . .].” Mission1st Mem. 18. Meanwhile, defendant explains
    that issuing a temporary restraining order or a preliminary injunction would [. . .]. Def.’s Opp’n
    32, ECF No. 29. Under a bridge contract, [. . .] would be [. . .]. Id. at 32-33. Indeed, unlike
    Intelligent Waves and Mission1st, defendant attached a declaration from the supervisory
    program manager for the DISA on the incumbent contract detailing the harm that the government
    would suffer if injunctive relief were to issue. Id. at 32.
    On one hand, the court assumes (for sake of argument) that the protestors will likely
    suffer irreparable harm absent such relief. On the other hand, the harm to the government—as
    supported by declaration—would not be insubstantial, as Intelligent Waves and Mission1st
    proclaim. Because the protestors are unlikely to succeed on the merits, the balance of harms
    weighs in defendant’s favor.
    D. Public Interest
    Finally, when “employing the extraordinary remedy of injunction,” a court “should pay
    particular regard for the public consequences” of doing so. Weinberger v. Romero-Barcelo, 
    456 U.S. 305
    , 312 (1982). It is undisputed that “the public interest in honest, open, and fair
    competition in the procurement process is compromised whenever an agency abuses its
    discretion in evaluating a contractor’s bid.” Overstreet, 47 Fed. Cl. at 744; accord Bona Fide
    Conglomerate, Inc. v. United States, 
    96 Fed. Cl. 233
    , 242 (2010) (noting the “overriding public
    interest in preserving the integrity of the procurement process”). However, there is also a
    “public interest in minimizing disruption [to the agency].” Heritage of Am., 77 Fed. Cl. at 78,
    quoted in Akal Sec., 87 Fed. Cl. at 321; accord Aero Corp., S.A. v. United States, 
    38 Fed. Cl. 237
    , 242 (1997) (“[A] procuring agency should be able to conduct procurements without
    excessive judicial infringement upon the agency’s discretion.”).
    -18-
    Both Intelligent Waves and Mission1st highlight the public interest in fair procurements.
    In addition, Mission1st suggests that the public interest is served by “reducing any risk to the
    ultimate consumers of the Contract services [due to] ProSol’s inexperience” because “[t]hese
    communications systems constitute a vital lifeline required both for mission accomplishment of
    national security objectives, for the safety of their users and to disseminate critical real-time
    intelligence to battlefield commanders and operators in conflict zones.” Mission1st Mem. 19.
    Intelligent Waves remarks, in discussing the balance of hardships, that any “national defense and
    security concerns in this case are limited” because of the DISA’s ability to extend the contract.
    Intelligent Waves Mem. 30-31. Defendant highlights the public interest in avoiding undue
    interference with procurements, and agrees with Mission1st that the procurement “implicates
    national defense and national security interests.” Def.’s Opp’n 34 (relying on Mission1st Mem.
    19). Defendant specifies that both the incumbent contract and the contract at issue in this protest
    involve “mission critical operations support for Special Forces and others performing critical
    military functions.” Id. at 35.
    The court agrees with Mission1st and defendant that there is a significant public interest
    in ensuring the safety of people and property. This interest is endangered when the federal
    government lacks confidence that its contractor can provide the necessary support. The DISA
    has reasonably placed its confidence in ProSol, and is understandably reticent to award a sole-
    source bridge contract to a contractor that was not selected for the follow-on effort and competes
    with the services at issue here. Accordingly, the public interest weighs in defendant’s favor.
    IV. CONCLUSION
    The court has considered all of the parties’ arguments. To the extent not discussed
    herein, they are unpersuasive, without merit, or are unnecessary for resolving the matters
    currently before the court.
    Neither Intelligent Waves nor Mission1st are likely to succeed on the merits of their
    protests. Although both protestors may be irreparably harmed absent an injunction, the balance
    of harms and the public interest weigh in favor of the defendant.
    Therefore, the court DENIES Intelligent Waves’s motion for a temporary restraining
    order and a preliminary injunction and DENIES Mission1st’s motion for a temporary restraining
    order and a preliminary injunction. The parties shall, consistent with the court’s November 27,
    2017 scheduling order, file a joint status report suggesting a schedule for further proceedings no
    later than Monday, December 11, 2017.
    [. . .]
    IT IS SO ORDERED.
    s/ Margaret M. Sweeney
    MARGARET M. SWEENEY
    Judge
    -19-