Sekri, Inc. v. United States ( 2023 )


Menu:
  •            In the United States Court of Federal Claims
    No. 21-778
    Filed: January 31, 2023
    NOT FOR PUBLICATION*
    SEKRI, INC.,
    Plaintiff,
    v.
    UNITED STATES,
    Defendant.
    Alan M. Grayson, Windermere, FL, for the plaintiff.
    Rafique Anderson, Commercial Litigation Branch, Civil Division, U.S. Department of Justice,
    Washington, DC, for the defendant, with Nicole M. Wilmoth and Gregory M. Mathews, Defense
    Logistics Agency, of counsel.
    MEMORANDUM OPINION AND ORDER
    HERTLING, Judge
    In this pre-award bid protest, the plaintiff, SEKRI, Inc. (“SEKRI”), seeks a temporary
    restraining order and a preliminary injunction prohibiting the Defense Logistics Agency
    (“DLA”) from awarding a contract for Advanced Tactical Assault Panels (“ATAP”) to
    UNICOR, the trade name of Federal Prison Industries, Inc. (“FPI”). The plaintiff is a mandatory
    source of supply for the ATAP under the AbilityOne program, which requires federal agencies to
    procure certain goods from qualifying nonprofit agencies employing the blind or severely
    disabled. The plaintiff argues that the DLA’s set-aside of 50 percent of its ATAP requirement
    for FPI violates procurement laws and regulations. The defendant, the United States, acting
    through the DLA, opposes the plaintiff’s motion.
    *
    Despite the existence of a protective order in this case (ECF 9), this opinion is filed on the
    open record. The plaintiff has filed a motion to unseal the case and all case filings. (ECF 70.)
    Resolution of that motion has been stayed. (ECF 84.) Nonetheless, the parties’ briefs on the
    plaintiff’s motion for a preliminary injunction were filed on the open record, and the Court held
    oral argument on the open record. This opinion does not include any “source selection
    information, proprietary information, [or] confidential information.” (ECF 9 (defining protected
    information).) Accordingly, this opinion is made publicly available.
    Although the plaintiff has a colorable claim that a contract with FPI for production of half
    the ATAP is inconsistent with the law, the plaintiff has not demonstrated a likelihood of success
    on the merits. Additionally, the plaintiff has not demonstrated irreparable harm specific to the
    absence of a preliminary injunction. Accordingly, the plaintiff’s motion for a preliminary
    injunction is denied.
    I.     BACKGROUND
    This opinion assumes familiarity with the protracted history of this case. SEKRI, Inc. v.
    United States, 
    152 Fed. Cl. 742
     (2021) (“SEKRI I”); SEKRI, Inc. v. United States, 
    34 F.4th 1063
    (Fed. Cir. 2022) (“SEKRI II”); SEKRI, Inc. v. United States, __ Fed. Cl. __, No. 21-778, 
    2022 WL 17726654
     (Fed. Cl. Dec. 16, 2022) (“SEKRI III”).
    In SEKRI III, the plaintiff’s initial claims were found to be moot, but the plaintiff was
    allowed to file an amended complaint to address issues SEKRI raised during oral argument on
    the defendant’s motion to dismiss the initial and first supplemental complaint. The plaintiff’s
    pending amended complaint, styled by the plaintiff as a second supplemental complaint, but
    more properly treated as an amended complaint, alleges three claims for relief. (ECF 77.) First,
    the plaintiff alleges that the DLA’s refusal to accept SEKRI’s price is arbitrary and capricious
    and contrary to procurement law. Second, the plaintiff alleges that the DLA’s issuance of a
    solicitation to FPI for 50 percent of its ATAP requirement violates procurement law. Third, the
    plaintiff alleges that the DLA is acting in bad faith. Only the plaintiff’s second claim regarding
    the partial set-aside for FPI is relevant to its motion for a preliminary injunction.
    FPI is a government corporation employing the incarcerated to produce commodities “for
    sale to the departments or agencies of the United States.” 
    18 U.S.C. §§ 4121
    , 4122(a). FPI’s
    organic statute provides that FPI’s board of directors shall, among other things, “provide
    employment for the greatest number of those inmates in the United States penal and correctional
    institutions who are eligible to work as is reasonably possible,” “so operate the prison shops that
    no single private industry shall be forced to bear an undue burden of competition from the
    products of the prison workshops,” and “reduce to a minimum competition with private industry
    or free labor.” 
    Id.
     § 4122(b)(1).
    On December 15, 2022, the DLA issued a solicitation to FPI for 50 percent of the DLA’s
    ATAP requirement over a three-year ordering period. (ECF 79.) The defendant did not notify
    the plaintiff or the Court of this solicitation until January 4, 2023. (ECF 75.) On January 12,
    2023, the plaintiff filed the pending amended complaint, challenging the partial set-aside to FPI.
    (ECF 77.) On January 20, 2023, the defendant notified the plaintiff and the Court that the DLA
    anticipated awarding a contract for the procurement of the ATAP to FPI on January 31, 2023.
    (ECF 79.) The defendant noted that the DLA was unwilling to stay the award of the contract
    voluntarily while this protest was pending. Under the proposed indefinite-delivery, indefinite-
    quantity (“IDIQ”) contract, FPI would begin preparations to produce the ATAP immediately, but
    the initial delivery of the ATAP by FPI would not be due to the DLA until August 29, 2023, at
    the earliest. (ECF 85-1 at 110 ¶ 6.) The DLA would not owe FPI payment for the shipment until
    30 days after the initial delivery. (Id. at 110 ¶ 8.)
    2
    The plaintiff filed a motion for a temporary restraining order and preliminary injunction
    on January 23, 2023. (ECF 82.) The Court held a status conference on January 24, 2023, and
    the defendant filed its brief in opposition to the plaintiff’s motion and an appendix of relevant
    documents on January 30, 2023. (ECF 85, 85-1.) Oral argument on the plaintiff’s motion was
    held on January 31, 2023.
    II.    STANDARD OF REVIEW
    “A preliminary injunction is an extraordinary remedy never awarded as of right.” Winter
    v. Nat.l Res. Def. Council, Inc., 
    555 U.S. 7
    , 24 (2008). The purpose of a preliminary injunction
    in a bid protest is to preserve the status quo pending resolution of the case on the merits. See
    Cont’l Serv. Grp., Inc. v. United States, 
    722 F. App’x 986
    , 994 (Fed. Cir. 2018).
    The party seeking a preliminary injunction bears the burden of establishing four factors.
    First, the moving party must establish that it is likely to succeed on the merits. Second, the
    moving party must be likely to suffer irreparable harm absent a preliminary injunction. Third,
    the balance of equities must tip in the moving party’s favor. Fourth, a preliminary injunction
    must be in the public interest. PGBA, LLC v. United States, 
    389 F.3d 1219
    , 1228-29 (Fed. Cir.
    2004); Cont’l Serv. Grp., 722 F. App’x at 993.
    A plaintiff may not be granted preliminary relief “unless it establishes both of the first
    two factors, i.e., likelihood of success on the merits and irreparable harm.” Amazon.com, Inc. v.
    Barnesandnoble.com, Inc., 
    239 F.3d 1343
    , 1350 (Fed. Cir. 2001) (emphasis in original); see also
    Reebok Int’l Ltd. v. J. Baker, Inc., 
    32 F.3d 1552
    , 1556 (Fed. Cir. 1994) (“[I]rrespective of
    relative or public harms, a movant must establish both a likelihood of success on the merits and
    irreparable harm . . . .” (Emphasis in original)); Sumecht NA, Inc. v. United States, 
    923 F.3d 1340
    , 1348 (Fed. Cir. 2019) (upholding a decision by the Court of International Trade to deny a
    preliminary injunction based on a lack of irreparable harm even though the lower court declined
    to consider the other preliminary injunction factors). Once each of the first two criteria is met,
    no single factor is dispositive, but “the absence of an adequate showing with regard to any one
    factor may be sufficient” to deny a motion for a preliminary injunction. FMC Corp. v. United
    States, 
    3 F.3d 424
    , 427 (Fed. Cir. 1993).
    III.   DISCUSSION
    The plaintiff argues that the four factors for a preliminary injunction are met, and that the
    defendant should therefore be enjoined from awarding a contract to FPI.
    A.      Likelihood of Success on the Merits
    The facts giving rise to this dispute and the application of law to those facts are not
    entirely clear. The plaintiff has demonstrated that it has a colorable claim that the defendant has
    acted illegally but has not shown a likelihood of success.
    The plaintiff argues that it will succeed on the merits because the award of a contract to
    FPI for the ATAP is unlawful. The plaintiff argues that FPI’s board of directors has not decided
    to produce the ATAP, and that in the absence of such a board decision, the production of the
    3
    ATAP by FPI would violate 
    18 U.S.C. § 4122
    (b)(4). The plaintiff argues that the board of
    directors has also failed to follow mandatory procedures for producing a new product, including
    providing notice to affected private vendors, advising affected trade associations, and soliciting
    comments. See 
    18 U.S.C. § 4122
    (b)(4)-(5). The plaintiff argues further that, although FPI
    generally has priority in mandatory-source procurements over nonprofits like SEKRI, FPI’s
    priority is implicitly conditioned on the government’s compliance with relevant statutes and
    regulations. Cf. 
    41 U.S.C. § 8504
    (b) (providing that FPI has priority only regarding products
    “required under 4124 of title 18 to be procured from that industry”). As the only other
    mandatory source for the ATAP, the plaintiff argues that it has been prejudiced by the DLA and
    FPI’s violation of those procedures.
    The defendant argues that the statutory process described by SEKRI applies only when a
    new product code and not an individual item is introduced to the FPI Schedule. The defendant
    argues that the ATAP falls under the long-standing product code 8465 “as a type of
    organizational clothing and individualized equipment.” (ECF 85 at 16.) The defendant also
    explains that the first contract between SEKRI and the Army was to develop the ATAP as a
    prototype. That contract was for a service (research), not a product. Because the contract for the
    initial production of ATAP was performed under a service contract, SEKRI had priority over
    FPI. See FAR 8.704(a). Once SEKRI developed and produced the prototype and follow-ons of
    the ATAP, subsequent production of the ATAP would occur pursuant to a contract for goods,
    under which FPI has priority over SEKRI. See 
    id.
     The defendant points to documents revealing
    that in September 2018 FPI waived its priority for 50 percent of the Army’s ATAP requirements
    for a period of five years or until 120,000 ATAP units were produced annually. The defendant
    argues that the DLA’s set-aside of 50 percent of its ATAP requirement to FPI is therefore lawful.
    Although other issues are relevant to the dispute, the outcome of the case hinges to a
    large degree on the interpretation of the term “product,” as used in 
    18 U.S.C. § 4122
    (b). Under
    that section, FPI’s board of directors must take several required steps before deciding to allow
    FPI to produce a new “product.”
    The term “product” appears undefined by the statute. The defendant argues that
    “product” means an entire category of items, so long as the items pertain to the same four-digit
    code. The defendant argues that the FPI decided on that approach in a regulation. Product
    Development and Production: Public Involvement Procedures, 
    62 Fed. Reg. 11,465
    , 11,469
    (FPI March 12, 1997).
    The defendant’s argument poses three analytical problems. First, the plaintiff argues that
    the code 8465 includes diverse items such as snowshoes, skis, and swords without scabbards.
    These items are so diverse that it strains credulity that they would not be different “products”
    under 
    18 U.S.C. § 4122
    (b). Second, the definition of “product” in the Federal Register does not
    necessarily support the defendant’s argument. FPI explained: “[A]n item may be considered
    separate from another product in the same 4-digit FSC category, if its function differs
    substantially.” 62 Fed. Reg. at 11,470. The ATAP is functionally different from skis, for
    example. Third, the defendant must show that FPI’s definition of “product” aligns with FPI’s
    organic statute. The plaintiff’s interpretation of the term “product” as meaning an “item” is
    colorable at this stage of the litigation.
    4
    Other facts, however, will be relevant to the dispute. For example, the validity of
    AbilityOne’s finding that SEKRI could meet only 50 percent of the Army’s requirement in 2019
    is uncertain. Whether FPI fully or partially waived its priority, and the extent of that waiver, also
    requires further factual development and legal analysis that cannot be undertaken under the tight
    timeline required for resolution of this motion. Although this case has been ongoing for more
    than two years, the facts giving rise to the plaintiff’s current claims are novel.
    The facts most crucial to the plaintiff’s claims and the legal implications of these facts
    remain insufficiently developed to conclude that the plaintiff is likely to prevail on the merits of
    its claim. The plaintiff’s arguments regarding the legality of a contract to FPI are colorable and
    may prevail, but they do not yet rise to the threshold of a showing of being likely to succeed. It
    is the plaintiff’s burden to demonstrate likelihood of success on the merits, and, on this uncertain
    record, the plaintiff has not done so.
    B.      Irreparable Harm
    Even assuming, for the sake of argument, that the plaintiff had demonstrated that it is
    likely to succeed on the merits of its claim, it must also demonstrate that it would suffer
    irreparable harm if its request for a preliminary injunction is denied. The plaintiff cannot do so.
    The plaintiff argues that the record and previous opinions in this case already establish
    irreparable injury to SEKRI. Furthermore, the plaintiff argues that any funds that are obligated
    to FPI will not go to SEKRI if the contract to FPI is ultimately enjoined on the merits. (ECF 82
    at 18-19.)
    The defendant argues that SEKRI will not be irreparably injured by the absence of a
    preliminary injunction. The defendant argues that in the event the contract to FPI is ultimately
    enjoined and SEKRI is found to be the only lawful mandatory source of the ATAP, SEKRI
    would suffer neither loss of profits nor delay in award of the contract stemming from the initial
    award of the contract to FPI.1
    In Timberline Helicopters, Inc. v. United States, Chief Judge Kaplan explained that
    irreparable harm in the preliminary-injunction context typically includes either the loss of profits
    while a protest is pending or the loss of an opportunity to compete fairly. 
    140 Fed. Cl. 117
    , 121
    (2018). The plaintiff in this case would suffer neither type of harm if its motion for a
    preliminary injunction is denied. The DLA’s process for procuring the ATAP from SEKRI will
    proceed regardless of the existence of a preliminary injunction on the FPI contract award, so
    SEKRI does not stand to lose profits because of the pending protest. SEKRI also will not lose
    the opportunity to compete fairly because it is a mandatory source of supply for the ATAP
    outside of the competitive-procurement process. See SEKRI II, 34 F.4th at 1072.
    1
    Although largely absent from the defendant’s brief, these arguments were raised in the
    status conference held on January 24, 2023, and at oral argument held on January 31, 2023.
    5
    In a signed statement in the appendix to the defendant’s brief, the DLA contracting
    officer explained that the DLA would not obligate funding beyond the guaranteed minimum
    amount or guaranteed minimum quantity on the FPI contract. (ECF 85-1 at 110 ¶ 4); see FAR
    16.501-2(b)(3). The minimum quantity on the contract contemplated by the DLA is 9,750
    ATAP units. (ECF 85-1 at 110 ¶ 5.) Assuming a delivery order is placed on January 31, 2023,
    FPI’s delivery of the 9,750 ATAP units will not be due until August 29, 2023. (Id. at 110 ¶¶ 5-
    6.) The DLA contracting officer avers that FPI’s contract will contain FAR 52.249-2 and that
    the DLA will thus “retain the right to terminate FPI’s contract for convenience should the Court
    find that DLA’s award to FPI was improper.” (Id. at 111 ¶ 9.) The “DLA will then de-obligate
    funds under the terminated FPI contract and re-obligate the funds for a new contract to SEKRI or
    another contractor, as appropriate.” (Id.) In support of this assertion, the DLA employee quotes
    a Department of Defense regulation that provides:
    [W]here contract award is determined to be invalid as a result of a
    bid protest and the contract is terminated for convenience,
    appropriations charged for the original contract may be obligated for
    a replacement contract if it is awarded without undue delay after
    termination of the original contract. Any award within 100 days of
    termination necessarily is award without undue delay because 31
    U.S.C. 1558 statutorily extends the availability of appropriations for
    such period following the final ruling on a bid protest.
    (Id. at 111 ¶ 10 (quoting Department of Defense Financial Management Regulations Volume 3,
    Chapter 8, paragraph 081303, provision 13.3.4).)
    The defendant’s showing regarding the process for de-obligating and re-obligating funds
    undercuts the plaintiff’s claim of irreparable harm. If the FPI contract is enjoined on the merits,
    the funds available to SEKRI to produce 100 percent of the ATAP would not be diminished.
    SEKRI can therefore show no injury due to the absence of a preliminary injunction.
    Accordingly, the plaintiff does not stand to suffer a loss in profits specific to the absence of a
    preliminary injunction.
    A preliminary injunction also would not affect the timing of a potential contract award to
    SEKRI for the ATAP. The preliminary injunction of the FPI contract award would not mandate
    the award of a comparable contract to SEKRI; it would only halt the award to FPI. See Citizant,
    Inc. v. United States, 
    142 Fed. Cl. 260
    , 274 (2019) (“As an initial matter, the court cannot direct
    the government to award a contract to a specific offeror.”) The defendant has indicated that the
    procurement process currently ongoing between SEKRI and the DLA will proceed on its own
    track according to its own timing independent of the procurement process between the DLA and
    FPI. That procurement has stalled, however, due to the parties’ disagreement over the approved
    unit price of the ATAP, giving rise to a claim included in the plaintiff’s current complaint but not
    at issue in the plaintiff’s motion for preliminary relief.
    A preliminary injunction barring award of the contract to FPI at this stage of the litigation
    would therefore put SEKRI in no better or worse position if the contract award to FPI is
    ultimately permanently enjoined on the merits.
    6
    SEKRI compellingly argues that it will suffer irreparable harm if the FPI contract is not
    permanently enjoined. The defendant does not contest the plaintiff’s assertion that if the DLA
    acts unlawfully to deprive it of the contract to produce the ATAP, SEKRI stands to lose
    substantial investments to support that production, including the loss of more than 75 severely
    disabled employees who would have few, if any, similar work opportunities. See SEKRI III,
    
    2022 WL 17726654
    , at *16 n.10 (quoting ECF 46-1 at ¶ 12).
    SEKRI may face those harms, however, irrespective of whether a preliminary injunction
    issues. Enjoining an award to FPI would not mandate award of a contract to SEKRI. It is
    unlikely that enjoining the FPI award would cause the DLA to award 100 percent of its
    requirement to SEKRI immediately because the parties cannot currently agree to a price.
    To demonstrate irreparable harm for the purposes of a preliminary injunction, a plaintiff
    must show harm particular to the absence of a preliminary injunction. See Cont’l Serv. Grp., 722
    F. App’x at 993. As Judge Wheeler once explained, a preliminary “injunction is not intended to
    prevent all harm that could befall a plaintiff during a pending litigation, but only that harm that
    could stem from failing to preserve the status quo while the case is pending.” Navient Sols., LLC
    v. United States, 
    141 Fed. Cl. 181
    , 184 (2018). The plaintiff’s arguments about irreparable harm
    absent a permanent injunction thus do not apply at this stage of the litigation.
    Because SEKRI is unable to demonstrate that it would suffer irreparable harm in the
    absence of a preliminary injunction, its motion for such an injunction cannot be granted.
    Amazon.com, 
    239 F.3d at 1350
    ; Reebok, 
    32 F.3d at 1556
    ; Sumecht, 
    923 F.3d at 1348
    .
    IV.    CONCLUSION
    Although the plaintiff’s legal argument is colorable, the plaintiff has not met its burden to
    demonstrate that it is likely to succeed on the merits. Moreover, even if the plaintiff had met its
    burden on that point, the plaintiff cannot demonstrate irreparable harm in the absence of a
    preliminary injunction. Because the first two factors for a preliminary injunction are not clearly
    met, other factors need not be addressed. See Amazon.com, 
    239 F.3d at 1350
    . Accordingly, the
    plaintiff’s motion for a preliminary injunction is DENIED.
    7
    The Court ADOPTS the following schedule for further proceedings:
    February 10, 2023:            The defendant shall file the administrative record;
    February 24, 2023:            The parties shall file cross-motions for judgment on the
    administrative record and the defendant shall file any
    motion to dismiss;
    March 7, 2023:                The parties shall file cross-response briefs.
    The Court will consult with the parties regarding a date for oral argument at a later time.
    It is so ORDERED.
    s/ Richard A. Hertling
    Richard A. Hertling
    Judge
    8