Meltech Corporation, Inc. v. United States ( 2023 )


Menu:
  •    In the United States Court of Federal Claims
    NOT FOR PUBLICATION
    No. 21-1532C
    (Filed: February 13, 2023)
    )
    MELTECH CORPORATION, INC.,                 )
    )
    Plaintiff,                )
    )
    v.                                )
    )
    UNITED STATES,                             )
    Defendant.                 )
    )
    Leonard A. Sacks, Leonard A. Sacks & Associates, P.C., Rockville, MD, for plaintiff.
    Fred A. Mendicino, Faughnan Mendicino PLLC, Dulles, VA, Of Counsel.
    Matthew J. Carhart, Trial Attorney, Commercial Litigation Branch, Civil Division,
    U.S. Department of Justice, Washington DC, for defendant, with whom on the
    briefs were Brian M. Boynton, Principal Deputy Assistant Attorney General,
    Patricia M. McCarthy, Director, Deborah A. Bynum, Assistant Director, Commercial
    Litigation Branch, Civil Division, U.S. Department of Justice, Washington DC.
    Adam J. Kwiatkowski, Assistant District Counsel, U.S. Army Corps of Engineers,
    Baltimore, MD, Of Counsel.
    TRANSFER ORDER
    On or about September 29, 2014, the United States Army Corps of Engineers
    (USACE) awarded plaintiff Meltech Corporation, Inc. a $10.5 million design-build
    contract to renovate military barracks located in Fort Meade, Maryland. In the
    course of contract performance, Meltech submitted three certified claims dated
    August 31, 2017, April 9, 2020, and June 9, 2021. The contracting officer denied
    the certified claims on July 6, 2018, July 2, 2020, and July 12, 2021, respectively.
    Meltech appealed the denials of the first and third certified claims to the Armed
    Services Board of Contract Appeals (ASBCA or Board). Meltech appealed the
    denial of the second certified claim to this Court. On January 27, 2023, the Court
    directed the parties to show cause why this case should not be transferred to the
    ASBCA pursuant to 
    41 U.S.C. § 7107
    (d). 1 See ECF No. 17. Both parties timely
    responded on February 9, 2023. See ECF Nos. 17–18. For the reasons set forth
    below, transfer of this action is in the interest of justice.
    Relevant here, the first certified claim seeks reimbursement of $350,978
    and a 150-day contract extension for an alleged differing site condition involving
    the structural integrity of the military barracks’ existing concrete. Through
    discovery in the ASBCA proceedings, Meltech claims to have uncovered evidence
    demonstrating the USACE possessed–but failed to disclose–superior knowledge
    regarding the structural condition of the subject site. Accordingly, on January 10,
    2020, Meltech sought to amend its ASBCA complaint to add claims of superior
    knowledge and breach of good faith and fair dealing. On June 11, 2020, the Board
    denied Meltech’s motion to pursue the additional causes of action citing Meltech’s
    failure to present them in the August 31, 2017 certified claim to the contracting
    officer.
    In the interim, on April 9, 2020, Meltech filed the second certified claim
    with the contracting officer based on the USACE’s alleged withholding of superior
    knowledge. Although the phrase “good faith and fair dealing” does not appear in
    Meltech’s second certified claim, in describing its “simple claim” (notably singular),
    Meltech explains the contractor “suffered damages based on the USACE[’s] failure
    to disclose its superior knowledge or to allow Meltech to perform destructive testing
    for many months without good cause.” See ECF No. 1-2 at 1 (emphasis added). In
    the April 9, 2020 certified claim, Meltech claimed entitlement to the same amount
    of increased costs included in the first certified claim (i.e., $350,978), but extended
    the claimed government-caused delay from 150 days to 283 days. See 
    id.
     As noted
    above, the contracting officer denied the second certified claim on July 2, 2020.
    Rather than appeal the contracting officer’s July 2, 2020 decision to the
    ASBCA within the agency board’s 90-day statutory deadline, see 
    41 U.S.C. § 7104
    (a), Meltech filed the instant suit on July 1, 2021, i.e., one day shy of the
    Court’s one-year statutory deadline. See 
    id.
     § 7104(b)(3). In the complaint filed
    in this Court, Meltech asserts alternative theories of recovery based on USACE’s
    alleged withholding superior knowledge and the agency’s alleged breach of
    good faith and fair dealing. Meltech seeks $2.4 million in damages–an amount
    not included in either of Meltech’s certified claims.
    Shortly after the complaint was filed in this Court, the parties jointly
    requested a nearly year-long stay to allow the ASBCA to resolve Meltech’s appeals,
    representing: “In light of the factual overlap between the case before the [ASBCA]
    and the case before this Court, the parties expect that the board’s decision will
    likely narrow the factual issues that this Court must decide, if the board’s decision
    does not dispose of the case entirely.” See ECF No. 5 at 3; accord ECF No. 7 at 1
    (“As the parties previously explained, Meltech is currently pursuing claims before
    1This case was transferred to the undersigned for adjudication on January 4, 2023, pursuant to
    Rule 40.1(b) of the Rules of the United States Court of Federal Claims. See ECF Nos. 14–15.
    2
    the Armed Services Board of Contract Appeals that overlap with the claims it
    brought before this Court.”). The stay remained in effect until June 14, 2022; the
    following day, the Court granted the parties’ joint request for a briefing schedule
    on defendant’s motion to dismiss. See ECF Nos. 9–10.
    On September 15, 2022, defendant moved to dismiss Meltech’s complaint or,
    in the alternative, to stay this case pending final disposition of the ASBCA appeals.
    See ECF No. 11. Defendant argues Meltech’s allegations constitute impermissible
    claim splitting. At a minimum, defendant seeks to dismiss Meltech’s claims insofar
    as they allege a breach of good faith and fair dealing and request damages in excess
    of $350,978 due to Meltech’s failure to present the issues to the contracting officer.
    Defendant alternatively requests that the Court stay this matter until the Board
    proceedings conclude and then dismiss the complaint based on issue preclusion.
    See id. at 46 (“It is unnecessary to expend resources litigating this case when the
    case may be substantially narrowed, if not entirely dispose of, by the board’s final
    judgment.”). Although disagreeing with defendant’s position regarding issue
    preclusion, Meltech does not oppose a stay and “agrees that a final decision by the
    Board would limit the scope of disputed facts and shorten the overall duration of
    any future proceedings before this Court.” See ECF No. 12 at 36.
    Title 41, United States Code, Section 7107(d) provides:
    If 2 or more actions arising from one contract are filed in the
    United States Court of Federal Claims and one or more agency boards,
    for the convenience of parties or witnesses or in the interest of justice,
    the United States Court of Federal Claims may order the consolidation
    of the actions in that court or transfer any actions to or among the
    agency boards involved.
    
    41 U.S.C. § 7107
    (d). Although not conclusively decided, the weight of authority
    strongly suggests Meltech’s timely appeal to this Court vests derivative jurisdiction
    in the ASBCA to adjudicate the merits of Meltech’s April 9, 2020 certified claim
    following a § 7107(d) transfer. See Glenn v. United States, 
    858 F.2d 1577
    , 1580–81
    (Fed. Cir. 1988); Southwest Marine, Inc. v. United States, 
    680 F. Supp. 327
    , 329–30
    (N.D. Ca. 1988); see, e.g., also Suffolk Constr. Co., Inc. v. Gen. Servs. Admin.,
    CBCA 4377, 
    16-1 BCA ¶ 36,476
    ; but see Nova Grp./Tutor-Saliba v. United States,
    
    127 Fed. Cl. 591
    , 595–96 (2016). Nothing in § 7107(d) limits this Court’s transfer
    authority to complaints filed within 90 days of the contracting officer’s decision.
    See Glenn, 858 F.3d at 1581 (predecessor statute did not limit Court of Federal
    Claims’ transfers to complaints filed within 90 days of contracting officer’s decision).
    In assessing whether the transfer of this action to the ASBCA under
    § 7107(d) would facilitate the just and efficient resolution of the underlying
    disputes, the Court traditionally considers the following factors:
    3
    (1) Whether the dispute before the board and the court concern the
    same contract; (2) whether the claims before the court and the board
    duplicate claims or have overlapping and related issues; (3) whether
    plaintiff initially chose to appeal its claims before a court or a board;
    (4) whether one forum or the other has already made significant
    progress on the claims; (5) whether concurrent resolution would result
    in an inefficient allocation of the court’s, board’s, or party’s resources;
    (6) whether separate forums would reach inconsistent results.
    Avant Assessment, LLC v. United States, 
    134 Fed. Cl. 323
    , 332–33 (2017)
    (quoting Morse Diesel Int’l, Inc. v. United States, 
    66 Fed. Cl. 801
    , 804 (2005)
    (citing Giuliani Contracting Co. v. United States, 
    21 Cl. Ct. 81
    , 83 (1990))).
    There is no serious debate that these factors support transferring this action
    to the ASBCA.
    Meltech’s appeals to the ASBCA and the complaint filed in this Court
    concern the same contract. As outlined above, the claims before the Court
    overlap with and relate to the issues pending before the Board (i.e., USACE’s
    representations regarding the structural integrity of the military barracks’
    existing concrete). Regarding the initial choice of forum, prior to commencing
    this action, Meltech sought to litigate its superior knowledge and breach of
    good faith and fair dealing claims in the ASBCA by amending its complaint.
    It was during the pendency of that motion, opposed by the government, that
    Meltech filed the April 9, 2020 certified claim at issue in this case.
    Turning to comparative progress, the Board has devoted substantial
    resources and made significant progress in the related appeals, including
    overseeing extensive discovery and conducting hearings, with post-hearing
    briefing presently underway. A search of the ASBCA website reveals fifteen
    (15) consolidated appeals filed by Meltech under the same USACE contract
    at issue here. See Meltech Corp., ASBCA Nos. 61706 & 61768, at *1 & n.1
    (Dec. 17, 2021). In contrast, at the parties’ joint request, the proceeding
    before this Court has been effectively stayed since its filing to allow the
    related Board proceedings to conclude. Indeed, defendant’s pending motion
    to dismiss or continue to stay these proceedings is also predicated on the
    parallel ASBCA proceedings. To allow concurrent or consecutive adjudication
    of intricately related claims before the Board and the Court would constitute
    an inefficient use of judicial resources and risk inconsistent results. Transfer
    of this case to the ASBCA alleviates these concerns.
    In arguing against transfer, defendant cites Meltech’s failure to
    include its good faith and fair dealing contention and request for damages
    in excess of $350,978 in its April 9, 2020 certified claim. Upon this premise,
    defendant maintains that the Court and the Board similarly lack jurisdiction
    over these claims and, as such, a transfer would be futile. Without endorsing
    the argument or deciding the issue, it remains to be determined whether
    4
    Meltech’s April 9, 2020 certified claim sufficiently noticed a good faith and
    fair dealing assertion. As for the potential limitation on damages, the issue is
    secondary to a liability finding. On both counts, the ASBCA stands in a
    better position to assess Meltech’s claims given the extensive proceedings
    already conducted before the Board.
    In turn, Meltech argues that the proceedings before the ASBCA have
    progressed too far for the issues raised in this action to effectively catch up.
    Meltech’s contention highlights the institutional knowledge advantage the
    Board possesses over the Court regarding the USACE contract at issue
    and the arguments presented by the parties. Finally, citing Nova Grp./
    Tutor-Saliba, Meltech avers that a § 7107(d) transfer risks forfeiting the
    claims included in the contractor’s April 9, 2020 certified claim. The Court
    finds the argument unpersuasive. As noted above, in Glenn, the Federal
    Circuit sanctioned the transfer of actions filed in this Court between 91 days
    and one year of the contracting officer’s decision under the predecessor
    statute to § 7107(d), vesting the Board with derivative jurisdiction. See 
    858 F.2d at
    1580–81. Moreover, as in Glenn, the issues pending before the Court
    and the Board are interrelated, meriting transfer and consolidation.
    For the foregoing reasons,
    (1) Defendant’s Motion to Dismiss (ECF No. 11) is DENIED as Moot;
    (2) This matter is TRANSFERRED to the Armed Services Board of Contract
    Appeals pursuant to 
    41 U.S.C. § 7107
    (d); and
    (3) The Clerk of Court is directed to TRANSFER this case to the Armed Services
    Board of Contract Appeals by mailing a certified copy of this order and a copy of
    the docket sheet in this matter to:
    Armed Services Board of Contract Appeals
    Skyline 6 – Room 703
    5109 Leesburg Pike
    Falls Church, VA 22041-3208
    It is so ORDERED.
    s/ Armando O. Bonilla
    Armando O. Bonilla
    Judge
    5