Urs Energy & Construction, Inc. v. United States ( 2016 )


Menu:
  •             In the United States Court of Federal Claims
    No. 12-57 C
    (Filed April 14, 2016)
    * * * * * * * * * * * * * * * **                *
    M.K. FERGUSON COMPANY, for the                  *
    use and benefit of the secured creditors of     *
    GROUND IMPROVEMENT                              *
    TECHNIQUES, INC.; PNC BANK, N.A.;               *
    FIREMAN’S FUND INSURANCE                        *   Contracts; RCFC
    COMPANY; and R.N. ROBINSON &                    *   12(b)(1); RCFC 12(b)(6);
    SONS, INC.,                                     *   Defective Certification of
    *   Claim; Severin Doctrine;
    Plaintiffs,                   *   Allowable Contract Costs.
    *
    v.                                   *
    *
    THE UNITED STATES,                              *
    *
    Defendant.                    *
    * * * * * * * * * * * * * * * * *               *
    Robert G. Barbour, McLean, VA, for plaintiffs. Keith C. Phillips, McLean,
    VA, of counsel.
    Jeffrey A. Regner, United States Department of Justice, with whom were
    Benjamin C. Mizer, Principal Deputy Assistant Attorney General, Robert E.
    Kirschman, Jr., Director, Steven J. Gillingham, Assistant Director, Washington,
    DC, for defendant.
    ________________________________
    OPINION AND ORDER
    ________________________________
    Bush, Senior Judge.
    The court has before it the government’s motion to dismiss brought under
    Rules 12(b)(1) and 12(b)(6) of the Rules of the United States Court of Federal
    Claims (RCFC). Defendant’s motion has been fully briefed. Oral argument was
    neither requested by the parties nor required by the court. For the reasons set forth
    below, defendant’s motion is denied.
    BACKGROUND1
    Most of the relevant background for this dispute may be found in
    Ground Improvement Techniques, Inc. v. United States, 
    108 Fed. Cl. 162
     (2012)
    (GIT I), Ground Improvement Techniques, Inc. v. United States, No. 12-57C (Fed.
    Cl. May 3, 2013) (GIT II), Ground Improvement Techniques, Inc. v. United States,
    No. 12-57C (Fed. Cl. April 30, 2014) (GIT III), and Ground Improvement
    Techniques, Inc. v. United States, 618 F. App’x 1020 (Fed. Cir. 2015) (GIT IV).
    Only the facts essential to the dispute currently before the court are presented here.
    In 1995, Ground Improvement Techniques, Inc. (GIT) became the subcontractor
    for MK-Ferguson Company (MK) on a United States Department of Energy
    project in Slick Rock, Colorado (the DOE project) for the remediation of uranium
    mill tailings.2 As a result of a contract dispute, GIT eventually won a judgment
    against MK in a federal court, a portion of which remains unsatisfied. It is that
    unsatisfied portion of the judgment against MK that underlies the claim in
    plaintiffs’ amended complaint.
    In 2001, MK filed for bankruptcy under Chapter 11 of the Bankruptcy
    Code, in the United States Bankruptcy Court for the District of Nevada (the MK
    bankruptcy litigation). The unsatisfied portion of GIT’s judgment against MK,
    and post-judgment interest, were claims administered in MK’s bankruptcy. The
    bankruptcy court required MK to file a certified claim with DOE to attempt to
    satisfy GIT’s claims against MK related to the DOE project. MK did so in 2010,
    but the certification was contested as inadequate.
    1
    / This background information is drawn largely from the parties’ filings in this case and
    does not constitute fact finding by the court. The court does not reach the merits of the claim set
    forth in the amended complaint in this opinion; nor should the parties rely on any descriptive
    language in this opinion as a characterization of the nature of that claim.
    2
    / MK has undergone multiple corporate name changes, and will be referred to as MK
    even in reference to events which occurred after those name changes.
    2
    MK very recently corrected its certification of GIT’s claim to comply with
    claim certification requirements under the Contract Disputes Act of 1978, 
    41 U.S.C. §§ 7101-7109
     (2012) (CDA). Pls.’ App. Ex. 3. The type of claim
    presented in this suit is sometimes referred to as a pass-through claim, where the
    prime contractor certifies the claim of the subcontractor and sponsors that claim
    under its own name. Because GIT also went through bankruptcy, any proceeds
    from GIT’s claim will be paid to the assignees of that claim in GIT’s bankruptcy,
    usually referred to as the “Secured Parties.”3 Those assignees are indicated in the
    caption of this case by the term “secured creditors” of GIT. See Order of October
    7, 2015.
    There are three basic arguments which provide the foundation for
    defendant’s motion to dismiss presently before the court. Def.’s Mot. at 3-4. The
    government’s first jurisdictional argument essentially contends that the
    pass-through claim asserted in the amended complaint was never properly certified
    to the contracting officer and that the defects in certification are so grave that they
    cannot be cured. The government’s second argument, relying on RCFC 12(b)(1)
    and RCFC 12(b)(6) and citing Severin v. United States, 
    99 Ct. Cl. 435
     (1943),
    contends that because MK is not liable for GIT’s claim, MK cannot sponsor GIT’s
    claim before this court. In the alternative, defendant argues that the costs
    presented in MK’s pass-through claim are not allowable costs pursuant to MK’s
    contract with DOE; thus, in the government’s view, the claim set forth in the
    amended complaint fails as a matter of law.
    DISCUSSION
    I.     Standards of Review
    A.     RCFC 12(b)(1)
    In rendering a decision on a motion to dismiss for lack of subject matter
    jurisdiction pursuant to RCFC 12(b)(1), this court must presume all undisputed
    factual allegations to be true and construe all reasonable inferences in favor of the
    plaintiff. Scheuer v. Rhodes, 
    416 U.S. 232
    , 236 (1974), abrogated on other
    3
    / The term “GIT’s claim” is a shorthand reference to the pass-through claim sponsored
    by MK and presented to the DOE contracting officer. This opinion does not revisit the topic of
    the ownership of that claim, a topic which was fully explored in GIT I-IV.
    3
    grounds by Harlow v. Fitzgerald, 
    457 U.S. 800
     (1982); Reynolds v. Army & Air
    Force Exch. Serv., 
    846 F.2d 746
    , 747 (Fed. Cir. 1988). However, the plaintiff
    bears the burden of establishing subject matter jurisdiction. Alder Terrace, Inc. v.
    United States, 
    161 F.3d 1372
    , 1377 (Fed. Cir. 1998) (citing McNutt v. Gen.
    Motors Acceptance Corp. of Ind., 
    298 U.S. 178
    , 189 (1936)). To meet this burden,
    the plaintiff must establish jurisdiction by a preponderance of the evidence.
    Reynolds, 
    846 F.2d at 748
     (citations omitted).
    B.      RCFC 12(b)(6)
    It is well-settled that a complaint should be dismissed under RCFC 12(b)(6)
    “when the facts asserted by the claimant do not entitle him to a legal remedy.”
    Lindsay v. United States, 
    295 F.3d 1252
    , 1257 (Fed. Cir. 2002). When
    considering a motion to dismiss brought under RCFC 12(b)(6), “the allegations of
    the complaint should be construed favorably to the pleader.” Scheuer, 
    416 U.S. at 236
    . The court must not mistake legal conclusions presented in a complaint,
    however, for factual allegations which are entitled to favorable inferences. See,
    e.g., Papasan v. Allain, 
    478 U.S. 265
    , 286 (1986) (“[W]e are not bound to accept
    as true a legal conclusion couched as a factual allegation.”) (citations omitted).
    The court must also determine whether a complaint meets the plausibility
    standard described by the United States Supreme Court, i.e., whether it adequately
    states a claim and provides a “showing [of] any set of facts consistent with the
    allegations in the complaint.” Bell Atlantic Corp. v. Twombly, 
    550 U.S. 544
    , 563
    (2007) (Twombly) (citations omitted). “To survive a motion to dismiss, a
    complaint must contain sufficient factual matter, accepted as true, to ‘state a claim
    to relief that is plausible on its face.’” Ashcroft v. Iqbal, 
    556 U.S. 662
    , 678 (2009)
    (Iqbal) (quoting Twombly, 
    550 U.S. at 570
    ). Plausibility is a context-specific
    inquiry. See, e.g., Iqbal, 
    556 U.S. at 679
     (“Determining whether a complaint
    states a plausible claim for relief will . . . be a context-specific task that requires
    the reviewing court to draw on its judicial experience and common sense.”)
    (citation omitted).
    II.   Analysis
    A.     A Defective Certification Has Been Cured
    1.     MK’s Certification of the Pass-Through Claim
    4
    As ordered by the judge in the MK bankruptcy litigation, MK certified
    GIT’s subcontractor claim on October 22, 2010 and provided that certification,
    with supporting documents, to the contracting officer on the DOE project. That
    certification statement contains the following language:
    Attached please find the referenced subcontractor claim
    and supporting documents.
    As compelled by the Order being submitted herewith and
    the terms of the previous Order of the Court granting
    relief from the [bankruptcy] stay, I certify that the claim
    is made consistent with the Court’s Orders; and that I am
    duly authorized to certify the claim on behalf of the
    contractor.
    Am. Compl. Ex. 4 at 26. The claim amount was for $9,842,711.83. Id. at 27.
    There is no real dispute that an effective certification for a nine million
    dollar claim must include four elements prescribed by the CDA. The contractor
    must certify that:
    (A) the claim is made in good faith;
    (B) the supporting data are accurate and complete to the
    best of the contractor’s knowledge and belief;
    (C) the amount requested accurately reflects the contract
    adjustment for with the contractor believes the Federal
    Government is liable; and
    (D) the certifier is authorized to certify the claim on
    behalf of the contractor.
    
    41 U.S.C. § 7103
    (b). Only the last of those four elements is clearly present in the
    certification letter provided by MK on October 22, 2010. Unless the court orders
    issued by the bankruptcy court could relieve MK of its certification burden, it is
    clear that the October 22, 2010 certification is not sufficient under the CDA.
    The court need not decide whether such a certification under court order, or
    a subsequent certification under court order submitted in MK’s name but not
    authorized by MK, could ever be sufficient to certify a CDA claim. MK, on
    December 22, 2015, provided a second certification to the contracting officer
    5
    which stated, in relevant part, that:
    On behalf of URS Energy & Construction, Inc.,
    successor to Morrison Knudson Company d/b/a MK
    Ferguson Company, I hereby certify that the
    pass-through claim of Ground Improvement
    Technologies, Inc. for the judgment amount of
    $9,842,711.83, plus interest from August 16, 2006, is
    made in good faith; that the supporting data are accurate
    and complete to the best of my knowledge and belief;
    that the amount requested accurately reflects the contract
    adjustment for which the contractor believes the
    Government is liable; and that I am duly authorized to
    certify the claim on behalf of URS Energy &
    Construction, Inc.
    Pls.’ App. at 22. The December 22, 2015 certification submitted by MK contains
    all four elements required by the CDA.
    Defendant does not argue that the December 22, 2015 certification is itself
    defective. In the court’s view, the December 22, 2015 certification cures the
    defects in MK’s October 22, 2010 certification. The submission of a corrected
    and proper certification normally ends the court’s inquiry into the certification
    issue because it is well-established that a defective certification can be corrected at
    any time before this court enters a judgment in a contractor’s suit under the CDA.
    See, e.g., 
    41 U.S.C. § 7103
    (b)(3) (“A defect in the certification of a claim does not
    deprive a court or an agency board of jurisdiction over the claim. Prior to the
    entry of a final judgment by a court or a decision by an agency board, the court or
    agency board shall require a defective certification to be corrected.”);
    M. Maropakis Carpentry, Inc. v. United States, 
    609 F.3d 1323
    , 1329 (Fed. Cir.
    2010) (“[W]hile technical compliance with certification is not a jurisdictional
    prerequisite to litigation of a contractor’s claim under the CDA, it is a requirement
    to the maintenance of such an action.”) (citations omitted); James M. Ellett
    Constr. Co. v. United States, 
    93 F.3d 1537
    , 1546 (Fed. Cir. 1996) (noting that after
    late 1992 “certification of [a CDA claim is] not a jurisdictional prerequisite”).
    The government does not accept this interpretation of the effectiveness of
    the December 22, 2015 certification, however. Defendant asserts that the October
    6
    22, 2010 certification was not a certification at all, and thus does not benefit from
    the rule that a defective certification can later be corrected. See Def.’s Mot. at 15
    (“Plaintiff[s’] claims are not merely defectively certified, they are not certified at
    all.”). This is a plausible but ultimately unsuccessful argument.
    The government’s “failure to certify” argument is constructed upon a
    number of contentions. First, relying on a provision of the Federal Acquisition
    Regulation (FAR), 
    48 C.F.R. § 33.201
     (2010), defendant characterizes the October
    22, 2010 certification as a “failure to certify,” rather than as a defective
    certification. Def.’s Mot. at 15; see also FAR 33.201 (“Failure to certify shall not
    be deemed to be a defective certification.”). Second, the government suggests that
    jurisdiction in this court cannot lie where MK failed to certify the pass-through
    claim, relying principally on Scan Tech Security, L.P. v. United States, 
    46 Fed. Cl. 326
     (2000). Third, defendant argues that MK lacked the necessary intent to certify
    the pass-through claim’s accuracy and merit, thus rendering its October 22, 2010
    certification not merely defective, but incurable. See Def.’s Reply at 3 (“MK’s
    failure to certify is not susceptible to being cured, because its refusal to provide
    three of the four required certifications is not a mere defect.”) (citing Scan Tech,
    46 Fed. Cl. at 335). These arguments are not persuasive, for the following
    reasons.4
    2.      “Failure to Certify” Not Precisely Defined
    4
    / Although defendant frames this inquiry as a question of jurisdiction, the court believes
    such an approach to be questionable in light of precedent binding on this court. See, e.g., Engage
    Learning, Inc. v. Salazar, 
    660 F.3d 1346
    , 1356 (Fed. Cir. 2011) (“[B]ecause these allegations [in
    the complaint] are non-frivolous assertions of the existence of a contract under the [CDA], the
    [board of contract appeals] may not decline to consider them on jurisdictional grounds.”); Fisher
    v. United States, 
    402 F.3d 1167
    , 1175-76 (Fed. Cir. 2005) (“Assuming that the Court of Federal
    Claims has taken jurisdiction over the cause as a result of the initial determination that plaintiff’s
    cause rests on a money-mandating source, the consequence of a ruling by the court on the merits,
    that plaintiff’s case does not fit within the scope of the source, is simply this: plaintiff loses on
    the merits for failing to state a claim on which relief can be granted.”); Do-Well Mach. Shop, Inc.
    v. United States, 
    870 F.2d 637
    , 639 (Fed. Cir. 1989) (“The presence of a valid defense, however,
    does not oust a tribunal of jurisdiction unless, of course, the defense is jurisdictional.”). Here, in
    light of these authorities, the court is not persuaded that an inquiry into whether a particular
    certification of a CDA claim was defective (and thus curable) or incurably deficient is indeed
    jurisdictional. In any event, the government does not prevail on this issue under either RCFC
    12(b)(1) or 12(b)(6).
    7
    Neither the regulation cited by defendant nor the CDA itself contains
    illuminating language which explains the difference between submitting a
    defective certification and “failing” to submit a certification. Both parties cite to
    legislative history of the CDA which indicates that the 1992 amendment of the
    CDA sought to prevent “[w]asteful and esoteric litigation” over the certification of
    CDA claims. H.R. Rep. 102-1006, at 28 (1992). The bill before Congress also
    apparently attempted to favor technically deficient certifications (“the result of
    innocent mistake or inadvertence”) over certifications which were “made
    fraudulently, in bad faith, or with reckless or grossly negligent disregard of the
    Contract Disputes Act or applicable regulations,” id. at 28-29, although this
    particular concern is not explicitly stated in the final amendment of the statute, 
    41 U.S.C. § 7103
    (b)(3). The court notes that the governing statute, 
    41 U.S.C. § 7103
    (b)(3), and the text of the regulation, FAR 33.201, even if these authorities
    were interpreted to incorporate every statement in the legislative history cited by
    the parties, do not, by any means, address every type of imperfect certification.
    Courts and contract appeals boards have attempted to apply the statute and
    regulation to diverse fact patterns, but the court has searched in vain for a case on
    all fours with the facts of this case.
    It is obvious that a complete failure to submit any certification whatsoever
    for a CDA claim seeking more than $100,000 is a “failure to certify” and this
    failure cannot qualify as a defective certification which may be cured. See, e.g.,
    Estes Express Lines v. United States, 
    123 Fed. Cl. 538
    , 550 (2015) (dismissing a
    CDA claim for lack of jurisdiction in part because the contractor conceded that it
    had not submitted any certification of its large claim), appeal docketed, No. 16-
    1298 (Fed. Cir. Dec. 9, 2015). Under less obvious, but understandable,
    circumstances the Armed Services Board of Contract Appeals has repeatedly held
    that a failure to sign a certification also constitutes a failure to certify a CDA claim
    under FAR 33.201. See, e.g., Tokyo Co., 
    ASBCA No. 59059
    , 
    14-1 BCA ¶ 35,590
    (Apr. 23, 2014) (“Thus, the altogether lack of a signature on a certification is not a
    defect that can be cured under FAR 33.201 such that we can retain jurisdiction.”)
    (citations omitted). There is also a line of decisions from the contract appeals
    boards that assesses the contractor’s knowledge of proper certification language,
    or weighs evidence of the contractor’s intent to be bound by its certification. E.g.,
    Walashek Indus. & Marine, Inc., 
    ASBCA No. 52166
    , 
    00-1 BCA ¶ 30,728
     (Jan. 6,
    2000); Keydata Sys., Inc., GSBCA No. 14281-TD, 
    97-2 BCA ¶ 29,330
     (Oct. 10,
    1997); Prod. Corp., 
    ASBCA No. 49122
    -812, 
    96-1 BCA ¶ 28,053
     (Nov. 6, 1995).
    8
    None of these board decisions were discussed by the parties.5 Because the facts
    underlying each of these board decisions appear to vary greatly, and because the
    decisions of the appeals boards are not binding on this court, the court finds little
    assistance in these board decisions for the analysis required in this case.
    3.      “Failure to Certify” Cases Decided by This Court
    Defendant relies principally on Scan Tech for the proposition that MK did
    not certify its claim in 2010 as required by the CDA, thus depriving this court of
    jurisdiction over the claim presented in plaintiffs’ amended complaint. Def.’s
    Mot. at 14 (citing Scan Tech, 46 Fed. Cl. at 334). Scan Tech, however, is
    inapposite. Two documents in Scan Tech, a “cost or pricing data” form submitted
    to the contracting officer and a letter sent to the contracting officer over two years
    later, were deemed by the court to have fallen short of the “defective certification”
    benchmark. 46 Fed. Cl. at 335-38. The form was a “Contract Pricing Proposal
    Cover Sheet” which bears no resemblance to the letter submitted by MK on
    October 22, 2010. Id. at 329. The second document was a letter from a company
    official which enclosed some invoices which he stated were “as complete an
    assembly as possible.” Id. Unlike MK’s October 22, 2010 certification, this letter
    did not explicitly attempt to certify a CDA claim. Id. The court in Scan Tech
    found that neither of these documents was a “defective certification” because each
    reflected “a complete disregard of the CDA’s certification requirement.” Id. at
    338.
    This court’s interpretation of CDA certification requirements in Scan Tech,
    although persuasive, is not binding on this court. See, e.g., W. Coast Gen. Corp. v.
    Dalton, 
    39 F.3d 312
    , 315 (Fed. Cir. 1994) (“Court of Federal Claims decisions,
    while persuasive, do not set binding precedent for separate and distinct cases in
    5
    / In its reply brief, defendant, for the first time, indirectly alludes to the line of decisions
    from the boards of contract appeals which distinguishes between defective certifications and
    “failure to certify” scenarios. See Def.’s Reply at 4-5 (citing URS Energy & Constr., Inc., CBCA
    No. 2589, 
    12-1 BCA ¶ 35,055
     (May 30, 2012)). To the extent that the analysis in this board
    decision cited by the government is properly before the court, the court does not find it
    persuasive under the facts of this case. As explained in the following section of this opinion,
    MK’s pass-through claim certification was made under orders from a bankruptcy court, and this
    special circumstance must be considered when such a CDA certification is challenged. The
    board decision cited in the government’s reply brief does not consider this crucial issue,
    apparently because judicial orders were not at issue in that appeal.
    9
    that court.”) (citations omitted). The court in Scan Tech appropriately relied on
    the FAR, which provides the following guidance:
    Defective certification means a certificate which alters or
    otherwise deviates from the language in [FAR] 33.207(c)
    or which is not executed by a person authorized to bind
    the contractor with respect to the claim. Failure to
    certify shall not be deemed to be a defective certification.
    FAR 33.201. The remainder of that court’s analysis, however, applies caselaw to
    the facts before it in Scan Tech, which involved neither a bankrupt prime
    contractor under orders from a bankruptcy court, nor an explicit statement of
    certification, which is the case here. Because the court in Scan Tech did not
    confront facts similar to the instant case, this court cannot agree with the
    government that Scan Tech compels a finding that “MK’s failure to certify is not
    susceptible to being cured, because its refusal to provide three of the four required
    certifications is not a mere defect.” Def.’s Reply at 3.
    The other cases cited by the government for its “failure to certify” argument
    are just as unavailing as Scan Tech. In CSX Transportation, Inc. v. United States,
    
    123 Fed. Cl. 244
     (2015), the court held that the submission of a standard claim
    form for damage to property, often used to lodge tort claims against the federal
    government, could indeed constitute a claim under the CDA. 
    Id. at 251
    . Because
    the claim exceeded the $100,000 threshold, however, certification was required
    under 
    41 U.S.C. § 7103
    . 
    Id. at 251-52
    . The standard form’s certification language
    did not resemble the language required for CDA certification set forth in 
    41 U.S.C. § 7103
    (b). 
    Id. at 252
    . The court therefore ruled that the plaintiff’s certification on
    the standard claim form was a failure to certify, not a defective certification. 
    Id.
    As in Scan Tech, the certification inquiry in CSX did not involve a bankruptcy
    court order or a letter whose sole purpose was to certify a subcontractor claim.
    For this reason, the analysis in CSX is distinguishable from the analysis required in
    this case.
    Finally, defendant, in its reply brief, relies upon another decision of this
    court, Sam Gray Enterprises, Inc. v. United States, 
    32 Fed. Cl. 526
    , 530 (1995),
    without explaining how the holding in that case supports its “failure to certify”
    argument. Def.’s Reply at 4. The communications between the businessman and
    the United States Air Force in that case did not include a CDA claim or a CDA
    10
    claim certification. Sam Gray, 32 Fed. Cl. at 529-30. Instead, the businessman’s
    letters and facsimiles presented requests for widely-varying amounts of money,
    and a statement that the contractor “in good faith” had to borrow “approximately
    Two Million Dollars” to provide housing to federal contractors in the Bahamas.
    Id. The “coincidental” usage of the term “good faith” was held to “bear[] so little
    resemblance to the broadest possible reading of the [CDA] certification
    requirement that the court [found] that [the] plaintiff never made any attempt to
    certify his claim and that his allegation [was] merely an after-the-fact attempt to
    ameliorate his error.” Id. at 530. The facts in Sam Gray in no way resemble the
    facts of this case. The court cannot rely on the cases cited by the government to
    hold that MK failed to certify the pass-through claim submitted on October 22,
    2010.
    4.     Precedential Cases Discussing CDA Certification
    Requirements
    In the instant case the inquiry into certification requires consideration of the
    particular facts under which the October 22, 2010 certification was made by MK,
    and a review of analogous cases. Most relevant to this case, both in the court’s
    view and as demonstrated by the parties’ recitation of facts in their briefs, are the
    following circumstances: (1) MK’s claim is a pass-through claim; (2) MK’s
    October 22, 2010 certification of the claim was made under orders of the
    bankruptcy court; and, (3) MK’s certification employed language specified by the
    bankruptcy court. See Def.’s Mot. at 9 (noting that MK’s October 22, 2010
    certification “utilized the language from the bankruptcy court’s August 4, 2010
    order”). For guidance, the court turns first to two precedential decisions of the
    United States Court of Appeals for the Federal Circuit which discuss the
    certification of pass-through claims. The court then turns to a dispute which
    proceeded from a contract appeals board to the Federal Circuit, and in which a
    bankruptcy court’s order influenced a prime contractor’s certification of a pass-
    through claim.
    A seminal case, with a long procedural history not of interest here, is
    United States v. Turner Constr. Co., 
    827 F.2d 1554
     (Fed. Cir. 1987). Turner, the
    prime contractor, offered two certifications of a pass-through claim originating
    from its subcontractor Johnson, but also advised the contracting officer, as
    required under its master contract, as to the merits of the claim. Turner, 
    827 F.2d at 1556-57
    . One of these advisory reports was negative, suggesting that the
    11
    agency deny the claim, while a later advisory suggested that Turner could only
    provide factual background and no longer offered any legal advice as to whether
    the claim should be denied or granted. 
    Id. at 1557
    . Although Turner’s second
    certification conformed perfectly with CDA requirements, the government
    attempted to invalidate the certification because Turner had once recommended
    denial of the very claim it later certified. The Federal Circuit disagreed with the
    government’s overly rigorous interpretation of the CDA’s claim certification
    requirement.
    The court’s analysis of the validity of Turner’s second certification is
    instructive:
    The government . . . argues . . . that the certification must
    not only be submitted in good faith but must reflect the
    prime contractor’s own belief that the submitted claim
    reflects the amount owed by the government and that to
    allow the prime to substitute the subcontractor’s belief
    for its own in making a certification would make a sham
    of the certification requirement, regardless of the merits
    of the submitted claim, and would render meaningless
    the prohibition against direct appeals by subcontractors.
    Under the facts of the present case, we do not find this
    argument persuasive.
    As explained by Turner in its October 10, 1980 letter
    . . . , its recommendation to deny the claim was beyond
    its expertise and was the result of an erroneous view of
    what was required of it under the terms of the contract.
    We agree that the recommendation as to the ultimate
    resolution of the claim was beyond its proper role. We
    further agree with the board in [Turner Constr. Co. ex
    rel. Industrotech Constructors, Inc., 
    ASBCA No. 25447
    ,
    
    84-1 BCA ¶ 16,996
     (Nov. 25, 1983)] that the
    certification requirement requires not that the prime
    contractor believe the subcontractor’s claim to be certain,
    but that the prime contractor believe that there is good
    ground for the claim. Thus, how the prime contractor
    itself would resolve the dispute should not be relevant to
    12
    the certification issue; the prime contractor should not,
    through the requirement that it certify subcontractor
    claims, be used as a substitute for the contracting officer
    or the board [of contract appeals] in the determination of
    the merits of the submitted claims under the CDA.
    The government does not dispute that Turner’s
    certification of August 13, 1980, simultaneously
    encompassed all of the statutory elements needed for
    certification. It was unequivocal and replaced the
    ineffective qualified certification submitted by Turner on
    May 19, 1980. To require more by allowing the
    contracting officer the discretion to look beyond
    certification language which complies with the statute
    would necessarily require an examination of the
    underlying basis and merits of the claim in order to
    determine the validity of the certification. Since a proper
    certification is a precursor to jurisdiction under the CDA,
    invalidating certifications as a result of such
    examinations would prevent the contracting officer, the
    board, or this court from employing the provisions of the
    CDA on any aspect of the claim. This is contrary to the
    overall goal of Congress that the CDA be used to resolve
    all disputes and claims arising from contracts with
    government agencies . . . .
    Turner, 
    827 F.2d at 1561
     (citation to legislative history omitted). The Federal
    Circuit also opined at length on the topic of pass-through claims, and the role of
    the sponsor of those claims:
    As a result of the terms of the contract and the provisions
    of the CDA, Turner found itself in an unexpected,
    confusing, and potentially conflicting position with
    respect to its subcontractors and the administration of its
    duties toward the government under the contract. In
    practical effect, Turner found itself in the position of
    having to review and certify the data and legal theories
    underlying the subcontractor’s claims while also
    13
    providing the data and basis for the government’s
    defense of the same claims. We believe that Turner’s
    actions under the facts of this case more than represent a
    good faith effort to balance and comply with the
    competing concerns confronting it.
    Given the nature of this court’s day-to-day business, we
    do not find it at all surprising for there to be at least
    facially proper grounds factually and legally supporting
    each side in a nonfrivolous dispute. Nor do we find
    hopelessly irreconcilable the awkward requirement that
    the prime contractor both certify the claims of its
    subcontractors and provide the government with facts
    and theories with which to defend those claims. In fact,
    this accords with the government’s argument that the
    contractor is now required under the CDA “to disclose
    any facts which would undermine [its] claims.”
    However, we believe that the resolution of the alternative
    arguments presented in a claim arising out of a
    government contract is properly made in accordance with
    the provisions of the CDA, and should not be the
    responsibility of the prime contractor as a prerequisite to
    certification of its subcontractor’s claim.
    
    Id. at 1559
     (citation to legislative history omitted). Although Turner’s
    certification, unlike MK’s October 22, 2010 certification in this case, contained all
    of the required elements for a CDA certification, the Turner decision provides
    several key insights into the certification of pass-through claims.
    First, the CDA “certification requirement requires not that the prime
    contractor believe the subcontractor’s claim to be certain, but that the prime
    contractor believe that there is good ground for the claim.” Turner, 
    827 F.2d at 1561
    . Second, the Federal Circuit requires that the sponsor of a pass-through
    claim make “a good faith effort to balance and comply with the competing
    concerns confronting it.” 
    Id. at 1559
    . Third, it is not the role of the prime
    contractor to adjudicate the pass-through claim, but to certify and present the pass-
    through claim to the contracting officer if good ground for the claim exists. 
    Id.
     A
    few years later, the Federal Circuit had another opportunity to examine a
    14
    certification of a pass-through claim in Transamerica Insurance Corp. ex rel.
    Stroup Sheet Metal Works v. United States, 
    973 F.2d 1572
     (Fed. Cir. 1992),
    overruled in part on other grounds by Reflectone, Inc. v. Dalton, 
    60 F.3d 1572
    (Fed. Cir. 1995) (en banc).
    The prime contractor in Transamerica was Bodenhamer Building
    Corporation (BBC). BBC sponsored a claim for its subcontractor Stroup,
    providing a certification which complied with the language required by the CDA,
    but also attaching a cover letter containing qualifying statements:
    [T]his claim is being filed by our subcontractor and
    inasmuch as they do not have contract privity with you,
    we are acting as a conduit on their behalf in this matter.
    We do not have access to their books and records and,
    therefore, cannot make any statement with respect to the
    amount of their claim. However, we have no reason to
    believe that their cost figures and delay estimates are
    incorrect.
    Transamerica, 
    973 F.2d at 1580
     (quotations removed). The United States Claims
    Court deemed BBC’s certification to be defective because of the qualifying
    language in the cover letter. 
    Id. at 1579
    .
    The Federal Circuit disagreed. Following Turner, the court stated that “the
    language of BBC’s September 1, 1988 cover letter, which the Government alleges
    [impermissibly] qualified BBC’s certification, is perfectly consistent with th[e]
    standard set out in Turner.” Transamerica, 
    973 F.2d at 1580
    . The court
    specifically relied on the “good ground” language in Turner which describes the
    level of belief required for the sponsor of a pass-through claim, and also found that
    BBC’s cover letter and enclosed certification were in substantial compliance with
    the CDA. 
    Id. at 1580-81
    . Transamerica thus reinforces the “good ground”
    standard set forth in Turner, and also allows the prime contractor some leeway in
    qualifying its support for a pass-through claim, at least in some circumstances.
    See, e.g., George Hyman Constr. Co. v. United States, 
    30 Fed. Cl. 170
    , 176 n.11
    (1993) (citing Transamerica, 
    973 F.2d at 1580
    , for the proposition that a prime
    contractor “is permitted to qualify its certification of the claim under the CDA by
    relying on the subcontractor’s representations”), aff’d, 
    39 F.3d 1197
     (Fed. Cir.
    1994).
    15
    Finally, the court turns to a contract appeals board decision, and the
    subsequent reversal of that decision by the Federal Circuit, which concerned a
    pass-through claim sponsored, at the insistence of a bankruptcy court, by a prime
    contractor. Arnold M. Diamond, Inc., 
    ASBCA No. 40885
    , 
    93-2 BCA ¶ 25,680
    ,
    
    1992 WL 398328
     (Dec. 31, 1992) (Diamond I), rev’d, 
    25 F.3d 1006
     (Fed. Cir.
    1994) (Diamond II). The contracting agency was the United States Navy, the
    prime contractor was Arnold M. Diamond, Inc. (Diamond), and the subcontractor
    was Perth Amboy Iron Works, Inc. (PAI). The subcontractor’s claim against the
    Navy was valued at approximately two million dollars, by PAI, although Diamond
    communicated to PAI that the prime contractor believed the claim was only worth
    $44,000 and warned PAI about procurement fraud:
    On 13 January 1987, [Diamond] sent to PAI its analysis
    of PAI’s claim. Of the total claim of $1,902,570,
    [Diamond] concluded that PAI was entitled to recover
    approximately $44,000. In whole sections of PAI’s
    claim document [Diamond] added the notation ‘do not
    concur.’ [Diamond] also advised PAI of the CDA
    certification requirements and forwarded to PAI
    educational treatises pertaining to the subject of
    procurement fraud investigations.
    Diamond I, 
    1992 WL 398328
    .
    Diamond submitted PAI’s claim to the Navy two months later with no CDA
    certification from Diamond and this language in Diamond’s cover letter:
    We are submitting this claim to you because we are
    obligated to honor the request of our Subcontractor,
    Perth Amboy Iron Works, Inc. This claim is submitted
    without comment, verification or mark up for [Diamond]
    ....
    
    Id.
     The Navy rejected the pass-through claim because it was not certified by
    Diamond. PAI went into bankruptcy, whereupon Diamond attempted to convince
    the bankruptcy court that PAI’s two million dollar claim was abandoned because it
    had not been properly certified (by PAI). Under orders from the bankruptcy court
    to issue a proper CDA certification, PAI issued “a properly worded” CDA
    16
    certification of its claim, and continued to assert the same amount for that claim.
    Diamond demanded a response from PAI to Diamond’s highly critical analysis of
    PAI’s claim for approximately two million dollars, and requested “documentation
    which would justify and support the claim.” 
    Id.
     No documentation from PAI was
    received by Diamond.
    Diamond then renewed its request to the bankruptcy court that it find PAI’s
    two million dollar claim to have been abandoned. The bankruptcy court held a
    hearing. The colloquy between the bankruptcy judge, Mr. Christopher M.
    Houlihan (Diamond’s counsel), and Mr. Samuel Z. Gdanski (Special Counsel
    relied upon for his expertise in government contract law) is reproduced in relevant
    part here:
    Mr. Houlihan: There’s no problem with [PAI’s]
    certification [language], your Honor. The problem is
    with the amount. When the claim was originally
    certified back in December of 1986 it contained a
    qualification. At that time Diamond asked PAI to certify
    the claim without qualification. A response came back
    in January of ’87 saying we can’t certify it exactly that
    way, to do so would be perjury. At that time in June, on
    June 13th of 1987 . . . Diamond did a very lengthy
    analysis of the PAI claim. It stated that the value of the
    claim was about $44,000, substantially less than the
    million nine. We’ve asked for a response to that and we
    have never received a response to that. In response to
    the Court’s order of October 24th of 1988, PAI gave us a
    certification for the exact same amount of $1.9 million.
    Now, your Honor, as you’re aware Diamond as the
    contractor is the one who has to certify the claim to the
    Navy.
    ....
    The Court: Are you suggesting to me that you have the
    authority and the right to decide what claim is going to
    be submitted by [PAI] to the Government?
    Mr. Houlihan: No, your Honor. I’m not suggesting that.
    What I am saying is that we face criminal and personal
    rather, civil penalties if we certify a claim which is false
    17
    and if we believe and we have put in writing that we
    believe a claim is worth $44,000 and we certify a million
    nine claim, I think it’s going to raise some serious
    questions and put us in jeopardy. [We’d] be happy to
    certify the million nine claim, your Honor, if we could
    get some back up on it. . . .
    ....
    The Court: Well, what would you suggest I do, Mr.
    Gdanski?
    Mr. Gdanski: That you order –
    The Court: That I order [Diamond] to certify something
    that they don’t feel in good faith they can certify?
    Mr. Gdanski: Yes. They’ve got the caveat. They’ve got
    the defense, the explanation. It’s on the record that they
    dispute the merits of the claim. If they want to do that
    with a cover letter, they can do that. Or in the absence,
    your Honor, of your office ruling substantively on the
    issue we could elevate this to the Armed Services Board
    of Contract Appeals and let them rule on this.
    ....
    Mr. Houlihan: . . . If the Court ordered Diamond to
    certify the claim, Diamond would do it and we could go
    to the Navy and say that we have been ordered by the
    United States Bankruptcy Court to certify this claim for a
    million nine and we would do that.
    The Court: You think I have a right to order you to
    certify something that you don’t feel that you can do in
    good faith?
    Mr. Houlihan: Well, your Honor, it is an asset of the
    bankrupt’s estate and it would be in the interest of the
    creditors to pursue this claim, if it is a valid claim and we
    would have the security of a court order. We have
    brought to the Court’s attention our difficulties with the
    claim and if your Honor decided that we should proceed,
    we would follow your order immediately.
    The Court: It is so ordered. The motion for an order
    declaring the claim abandoned is denied and Arnold M.
    Diamond, Inc. is hereby ordered to submit the -- to
    18
    certify the claim of PAI, together with Diamond’s other
    claim or claims and submit same to the Government for
    review. I’m satisfied that on a basis of the review of the
    statute and the pleadings it appears to me that there is a
    basis, a good faith basis for certifying the claim and I’m
    going to order and direct Diamond to do so.
    Diamond I, 
    1992 WL 398328
    . Diamond then complied with the court’s order and
    certified PAI’s claim for approximately two million dollars, and included the
    prime contractor’s mark-up on that claim. 
    Id.
     Diamond did not mention within its
    certification that its CDA certification of the pass-through claim was submitted in
    compliance with the order of the bankruptcy court.
    The Navy denied the pass-through claim in its entirety, and Diamond sought
    review of that decision before the Armed Services Board of Contract Appeals
    (ASBCA or board). The board acknowledged that Diamond’s certification of the
    pass-through claim “contain[ed] the language required by the CDA.” Diamond I,
    
    1992 WL 398328
    . The board cited Turner, but noted that, unlike the
    circumstances of Turner, “[i]n this appeal[] we confront the unique, undisputed
    factual situation in which the prime contractor has itself attacked the claim it later
    certified, and certified the claim only after receiving a court order to do so.”
    Diamond I, 
    1992 WL 398328
    .
    In the face of strong evidence that Diamond did not believe in the validity
    of PAI’s two million dollar claim, the ASBCA held that Diamond’s certification
    was not valid. The board stated that:
    Honesty with a subcontractor or the baring of one’s soul
    to the Bankruptcy Court is not the good faith envisioned
    by the CDA certification requirement. The claim must
    be submitted to the Government in good faith. There is
    more than ample evidence that was not done in this case.
    Diamond I, 
    1992 WL 398328
    . The ASBCA also commented that the board was
    “unprepared to attach unwarranted importance to a [bankruptcy] court order which
    is violative of a statute [(the CDA)] over which we have province.” 
    Id.
     After
    Diamond’s motion for reconsideration was denied, Diamond appealed the board’s
    decision to the Federal Circuit.
    19
    The Federal Circuit largely adopted the board’s factual findings, but noted
    that Diamond’s CDA certification of PAI’s claim had been accompanied by a
    letter notifying the Navy of the bankruptcy court’s order, and that a copy of the
    court order was attached to that letter. Diamond II, 
    25 F.3d at 1009
    . The court
    then proceeded to rule upon Diamond’s CDA certification. The court’s thorough
    discussion of pass-through claims, bankruptcy court orders and the effect of such
    orders on CDA certification is instructive. The Federal Circuit first noted that
    Diamond met its obligations as a prime contractor under the CDA:
    The Board’s findings of fact demonstrate that Diamond
    complied fully with the congressional mandate to review
    and manage the claim of its subcontractor. Ironically,
    however, the data that Diamond developed in its analysis
    of PAI’s claim, as well as Diamond’s representations to
    the Bankruptcy Court, were used by the Government in
    persuading the Board to dismiss Diamond’s appeal. The
    Board concluded that Diamond did not consider that
    there was good ground for the claim it had submitted
    [o]n behalf of its subcontractor and consequently, that
    the claim was not submitted in good faith.
    
    Id.
     (footnoted omitted).
    The Federal Circuit then discussed bankruptcy proceedings and the
    authority of bankruptcy courts, and concluded that a bankruptcy court’s orders are
    entitled to significant deference in government contract disputes when the prime
    contractor and subcontractor are within the bankruptcy court’s jurisdiction.
    Diamond II, 
    25 F.3d at 1010
    . The court then applied that deference to the issue of
    the “good faith” of the sponsor of a pass-through claim, noting, first, that the “term
    ‘good faith’ is not defined in the CDA.” 
    Id.
     The Federal Circuit borrowed a
    definition of good faith from an en banc decision of the Supreme Court of
    California:
    The phrase “good faith” in common usage has a
    well-defined and generally understood meaning, being
    ordinarily used to describe that state of mind denoting
    honesty of purpose, freedom from intention to defraud,
    and, generally speaking, means being faithful to one’s
    20
    duty or obligation.
    
    Id.
     (quoting People v. Nunn, 
    46 Cal. 2d 460
    , 468, 
    296 P.2d 813
    , 818 (1956) (en
    banc)).
    Applying deference and this definition of good faith, the Federal Circuit
    approved of Diamond’s CDA certification:
    It is clear from the record in this case that Diamond had
    no intention either to defraud or deceive the Navy. To
    the contrary, the Board’s findings of fact show that in its
    direct dealing with PAI and in the Bankruptcy Court,
    Diamond took every measure that could reasonably have
    been expected of a prime contractor, under the
    circumstances, to obtain PAI’s support and justification
    for its claim in an amount which Diamond felt it could
    conscientiously certify. Alternatively, Diamond
    petitioned the Bankruptcy Court to relieve Diamond of
    its obligation to certify PAI’s claim. Instead of obtaining
    the relief it sought, Diamond was ordered to certify the
    claim by the Bankruptcy Court. Diamond complied with
    the order and notified the contracting officer that it had
    certified the claim because it was required to do so by
    order of the Bankruptcy Court. When one contrasts the
    Board’s conclusion of law with its findings of fact, the
    question that arises is: “What other course could a
    reasonable contractor have taken in the circumstances to
    show that it acted in good faith?” Significantly, the
    Board in its opinion stated: “We agree that appellant’s
    actions, for the most part, demonstrate a conscientious
    effort to meet its ethical, contractual, and statutory
    obligations.” Nevertheless, the Board held that Diamond
    had not acted in good faith.
    This court agrees with Diamond’s contention that it acted
    in the reasonable belief that there was no viable
    alternative to the course of action it followed in this case.
    First, Diamond’s efforts to file its own properly certified
    21
    claim came to naught. Second, Diamond was obligated
    both by . . . the CDA and the Order of the Bankruptcy
    Court to certify the subcontractor’s claim. If it had
    refused to do so, Diamond would have exposed itself to a
    suit for damages by PAI without any right of
    reimbursement. Third, there was a possibility that if it
    had disobeyed the order of the Bankruptcy Court,
    Diamond would have been cited by that court for civil
    contempt.
    Diamond II, 
    25 F.3d at 1010-11
     (footnote omitted). Finding good faith in
    Diamond’s CDA certification, the court reversed the ASBCA and remanded for
    further proceedings.
    It is important to note that the Diamond II decision distinguished Turner,
    not because the “good ground” standard of belief in the validity of a
    subcontractor’s claim is too low for the factual scenario of Diamond II, but
    because “good ground” may actually be too high a standard of belief for a court-
    ordered CDA certification:
    We recognize that in [Turner], this court held that while
    the certification provision does not require the prime
    contractor to believe that the subcontractor is entitled to
    recover on the claim, it is necessary that the prime
    believe that there is good ground for the subcontractor’s
    claim. However, that case is factually distinguishable,
    because in Turner, unlike the situation in this case, the
    prime contractor was not required by a court of
    competent jurisdiction to certify the subcontractor’s
    claim in spite of the prime’s belief that there was not
    good ground for most of the amount claimed by the
    subcontractor.
    Diamond II, 
    25 F.3d at
    1009 n.2. Thus, Diamond II considers the CDA
    certification of a pass-through claim which results from a bankruptcy court order
    to be a special type of CDA certification, and one which may, in certain
    circumstances, be held to less-stringent standards than those set forth in Turner
    22
    and Transamerica, for example. Compliance with a bankruptcy court order
    appears to be enough to satisfy the good faith requirement, in the circumstances of
    Diamond II, which are very similar to the circumstances of MK’s October 22,
    2010 certification of GIT’s claim.
    5.     MK’s October 22, 2010 Certification Constitutes a
    Defective Certification, Not a Failure to Certify
    Having considered Diamond II, the precedential case most on point, and the
    holdings of Turner and Transamerica, the court notes first that in each of these
    three cases, the prime contractor provided a certification with language containing
    the elements required by the CDA, along with the pass-through claim. Here,
    MK’s conforming certification was not delivered to the contracting officer until
    December 22, 2015, after plaintiffs’ amended complaint was filed in this court. In
    addition, none of these precedential decisions applied the 1992 amendment to the
    CDA to the cases before them. Acknowledging these distinctions, the court does
    not believe the holdings of these precedential cases can be extended to find that
    MK’s October 22, 2010 certification, by itself, was a valid certification under the
    CDA.
    Nevertheless, the court does consider these three precedential cases to
    controvert the “failure to certify” challenge raised by defendant. Defendant argues
    that MK’s October 22, 2010 certification is fatally undermined by MK’s
    representations to the bankruptcy court that MK had legitimate concerns as to the
    amount claimed by GIT. Def.’s Reply at 7. The holding in Diamond II, however,
    shows that compliance with a bankruptcy court’s order can be sufficient to show
    that, despite expressed reservations, the prime contractor’s sponsorship is made in
    good faith. The holding in Turner shows that certainty as to a subcontractor’s
    claim is not required, just a belief that the claim has “good ground.” The
    Transamerica holding permits the prime contractor to express qualified support
    for a pass-through claim. In light of these authorities, the court cannot conclude
    that MK’s October 22, 2010 certification was a complete failure to certify GIT’s
    claim. Instead, under Diamond II, Turner and Transamerica, it was a defective
    certification, and that defective certification was cured on December 22, 2015.
    This court is not deprived of jurisdiction, nor does plaintiffs’ amended complaint
    fail to state a claim upon which relief may be granted because of the manner of
    MK’s certification of GIT’s claim.
    23
    B.     MK Remains Liable to GIT as a Result of the MK Bankruptcy
    Litigation
    The court turns now to the government’s argument which relies on the
    Severin doctrine, a doctrine named for a 1943 opinion issued by the Court of
    Claims. According to this doctrine, a prime contractor may not sponsor a pass-
    through claim unless it remains liable to its subcontractor on the underlying claim.
    See Severin, 99 Ct. Cl. at 443 (“If [the prime contractor] plaintiffs had proved that
    they, in the performance of their contract with the Government became liable to
    their subcontractor for the damages which the latter suffered, that liability, though
    not yet satisfied by payment, might well constitute actual damages to plaintiffs,
    and sustain their suit.”). In this case, defendant argues that because “MK obtained
    a discharge of its liability to GIT in bankruptcy, . . . MK is not liable to GIT or the
    secured parties for the claims asserted in this litigation [and MK] cannot sponsor
    the secured parties’ claims under the Severin doctrine.” Def.’s Mot. at 25-26.
    The Severin doctrine has evolved since 1943. See, e.g., United States v.
    Johnson Controls, Inc., 
    713 F.2d 1541
    , 1552 n.8 (Fed. Cir. 1983) (“In subsequent
    cases, the application of the Severin doctrine has been narrowly construed.”)
    (citation omitted); Seger v. United States, 
    469 F.2d 292
    , 300 (Ct. Cl. 1972) (“It is
    time to put the Severin rule to rest insofar as subcontractor claims are asserted as
    an equitable adjustment under the provisions of a prime contract with the
    Government.”) (footnote omitted). Among the limitations on the modern Severin
    doctrine are two that are applicable in this case: (1) the burden is on the
    government to prove that the prime contractor is no longer liable to its
    subcontractor on the pass-through claim; and (2) the Severin doctrine generally
    requires an “‘an iron-bound release or contract provision immunizing the prime
    contractor completely from any liability to the sub.’” E.R. Mitchell Constr. Co. v.
    Danzig, 
    175 F.3d 1369
    , 1370-71 (Fed. Cir. 1999) (citations omitted).
    The parties have not cited to any cases providing precedent binding on this
    court which analyze the liability of a bankrupt prime to its subcontractors for
    purposes of applying the modern Severin doctrine to pass-through claims. Both
    parties rely on J. L. Simmons Co. v. United States, 
    304 F.2d 886
     (Ct. Cl. 1962), as
    providing some guidance. The court agrees that J. L. Simmons is helpful because
    it shows that anything less effective than an “iron-bound release or contract
    provision” is insufficient for the Severin doctrine to block a pass-through suit.
    The analysis in J. L. Simmons also provides an analytical framework which, in the
    24
    court’s view, compels a rejection of the government’s Severin doctrine challenge
    to the amended complaint in this case.
    The subcontracts between J. L. Simmons and its subcontractors contained
    “releases” which permitted two means for resolving the subcontractors’ claims
    against the prime contractor. J. L. Simmons, 
    304 F.2d at 888
    . If the prime’s pass-
    through suit was successful, the prime would pay out the proceeds to its
    subcontractors. 
    Id.
     If, however, the pass-through suit failed, the prime’s liability
    was extinguished. 
    Id.
     The court described this arrangement as falling into a
    middle ground between liability and no liability: “Lying between these extremes
    are those cases involving situations wherein the prime contractor has agreed to
    reimburse its subcontractor for damages it has suffered at the hands of the
    Government, but only as and when the former receives payment for them from the
    Government.” 
    Id. at 889
    . The court noted that this middle ground of liability was
    enough to escape dismissal of a pass-through claim under the Severin doctrine. 
    Id.
    (citing cases). Ruling for J. L. Simmons, the court provided an analytical
    framework for deciding when a prime contractor retains at least an “implicit”
    liability to its subcontractors:
    In our view, defendant . . . misconceives the over-all
    tenor of the releases. Although the language used may
    be somewhat inartistic, we think that, taken as a whole,
    the releases do recognize an existing liability on the part
    of plaintiff for these claims. We have indicated that
    plaintiff’s liability is not expressly negated in any event.
    Rather, the releases simply purport to set forth the
    manner in which plaintiff’s liability is to be
    extinguished. Certainly implicit, at least, in these
    provisions would seem to be a recognition on the part of
    the parties that plaintiff is liable for these claims.
    Otherwise, there would be no reason for the parties to go
    to the trouble of providing a method for extinguishing a
    nonexisting liability. Consequently, we have here a
    situation where plaintiff’s liability for these claims was
    recognized and expressly preserved at the time the
    releases were entered into.
    Moreover, it is apparent that, insofar as they relate to
    25
    these particular claims, the releases are clearly
    conditional or contingent in nature. They become
    operable only if and when plaintiff prosecutes these very
    claims against the Government to a final judgment.
    Even then, if the claims are found meritorious, plaintiff’s
    liability is not extinguished until actual payment is made
    to the subcontractors. Thus, the releases neither
    exonerate plaintiff from liability ab initio nor
    subsequently, but do impose certain obligations on
    plaintiff which it must fulfill before its duty to reimburse
    these subcontractors for the damage allegedly caused by
    the Government is extinguished. It is apparent, then, that
    plaintiff is presently subject to liability on these claims
    and will continue to be so until liability is extinguished
    in accord with the method agreed to by the parties.
    
    Id. at 890
    .
    The court must follow J. L. Simmons, and finds a strong parallelism between
    the implicit liability described in that case and the implicit liability of MK in the
    MK bankruptcy litigation. Instead of releases written into its subcontracts, MK’s
    liability is established by the bankruptcy court’s jurisdiction over MK and that
    court’s order requiring MK to submit a CDA certification. Even though post-
    bankruptcy MK, just like J.L. Simmons, may not be required to pay anything to
    satisfy its subcontractor’s claim, MK still has “certain obligations . . . which it
    must fulfill before its duty to reimburse [its] subcontractor[] . . . is extinguished.”
    J.L. Simmons, 
    304 F.2d at 890
    . As was the case for J.L. Simmons, if MK prevails
    in this suit, the proceeds must be paid by post-bankruptcy MK to the owners of
    GIT’s claim.6 Under this authority, the court finds that defendant failed to meet its
    burden to prove that MK is not liable to GIT and that the Severin doctrine bars
    MK’s pass-through claim.
    The parties also dispute whether this case should be distinguished from or
    6
    / MK is only a nominal plaintiff for the benefit of the assignees of GIT’s claim. See
    Def.’s App. at 71 (noting that defendant’s counsel wishes to ensure that MK is correctly
    identified by its current corporate name so that it can receive any monetary judgment issued in
    this case).
    26
    governed by the analysis set forth in Brazier Forest Products, Inc. v. United
    States, 
    11 Cl. Ct. 468
     (1987). The court relies on Brazier for the limited purpose
    of establishing that a bankrupt prime may, in certain circumstances, sponsor a
    pass-through claim despite the Severin doctrine. For the same limited purpose, the
    court notes that a bankrupt prime contractor was nonetheless able to sponsor a
    pass-through claim in International Technology Corp., 
    ASBCA No. 54136
    , 
    04-1 BCA ¶ 32,607
     (Apr. 27, 2004). That pass-through claim eventually failed on the
    merits, but it did not fall prey to the Severin doctrine. See id. n.1; see also Int’l
    Tech. Corp. v. Winter, 
    523 F.3d 1341
    , 1344 n.1 (Fed. Cir. 2008). The court must
    reject defendant’s Severin doctrine challenge to the amended complaint because
    the government has not met its burden to prove that the modern Severin doctrine
    bars MK’s pass-through claim.
    C.      GIT’s Claim is Plausibly an Allowable Cost under the DOE
    Contract
    Having confirmed its jurisdiction over this suit, and having rejected
    defendant’s arguments regarding the certification of MK’s pass-through claim and
    MK’s liability for that claim, the court turns to the government’s RCFC 12(b)(6)
    argument disputing the “allowability” of the cost of the pass-through claim under
    MK’s contract with DOE. The government contends that “the claimed costs [in
    GIT’s claim] are not allocable or allowable under the contract between MK and
    DOE because MK never incurred the costs, and has no liability for the costs.”
    Def.’s Mot. at 2; see also Def.’s Reply at 12 (arguing that any lingering liability
    from MK’s bankruptcy “does not establish that MK has incurred or will incur the
    cost of [GIT’s] claim”). This argument relies on two authorities, a FAR provision
    alleged in the amended complaint to be part of MK’s contract with DOE, and an
    inapposite citation from a decision of the Civilian Board of Contract Appeals
    adjudicating DOE’s reimbursement liability for another aspect of the litigation
    between MK and GIT. Neither of these authorities convinces the court that MK’s
    pass-through claim is not plausible.
    The FAR provision cited by defendant is FAR 31.201-1, 
    48 C.F.R. § 31.201-1
     (1984).7 In relevant part, it states:
    7
    / Defendant cites to the “1983” version of the FAR for the language quoted here. Def.’s
    Mot. at 27. To the extent that there was a 1983 version of the FAR, it did not take effect until
    (continued...)
    27
    The total cost of a contract is the sum of the allowable
    direct and indirect costs allocable to the contract,
    incurred or to be incurred . . . .
    
    Id.
     The government focuses on the “incurred or to be incurred” language of the
    regulation, and again argues, just as it did in its Severin doctrine argument, that
    MK has not incurred and will never incur the costs of the pass-through claim
    because of its discharge of GIT’s claim in the MK bankruptcy litigation. For this
    reason, the government argues that “MK’s liability for the GIT judgment . . .
    [cannot] be charged to the [DOE] contract as an allowable cost.” Def.’s Mot. at
    29.
    The government fails to cite a single case which interprets the scope and
    meaning of FAR 31.201-1, in general, or which interprets this regulation
    specifically in terms of a bankruptcy discharge. The court thus has nothing more
    than the government’s ipse dixit assertion that an unsatisfied judgment that is part
    of a prime contractor’s bankruptcy estate cannot be allowable to a cost
    reimbursement contract under FAR 31.201-1.8 Under the standard of review
    required by RCFC 12(b)(6), and in the face of such a lack of persuasive authority,
    the court cannot conclude that MK’s pass-through claim is not at least plausibly
    allowable under MK’s contract with DOE.
    The government fares no better with its reliance on URS Energy &
    Construction, Inc., CBCA No. 2260,
    12-2 BCA ¶ 35,094
     (June 29, 2012). The
    decision in URS Energy focused on a liability of MK that was not discharged in
    the MK bankruptcy litigation, i.e., MK’s liability to its surety “Federal”:
    7
    (...continued)
    April 1, 1984. See Establishing the Federal Acquisition Regulation, 
    48 Fed. Reg. 42,102
    , 42,102
    (Sept. 19, 1983). The contract between MK and DOE was entered into in 1983. Am. Compl.
    ¶ 7. The text of FAR 31.201-1 is available in the 1984 edition of the Code of Federal
    Regulations.
    8
    / The contract provisions governing allowable costs actually set forth in MK’s contract
    with DOE are not before the court. Although the government may be correct that MK’s contract
    included essentially the same language as FAR 31.201-1, as alleged in plaintiffs’ amended
    complaint, the foundation for defendant’s “allowable costs” argument is far from solid. See
    supra note 7.
    28
    In this appeal, [MK] seeks reimbursement only for the
    amount it was obligated to pay Federal, as surety, as part
    of its indemnity obligation. Because [MK]’s
    indemnification obligation was not discharged during the
    bankruptcy, the bankruptcy does not, in any way, affect
    the outcome of the case.
    Id. The board of contract appeals in URS Energy nowhere discusses the
    allowability of a claim that was discharged in bankruptcy, under FAR 31.201-1 or
    any other regulation. Simply put, the board did not discuss or make any findings
    as to the effect of a bankruptcy discharge on the allowability of contract costs.
    The government’s contention that MK’s pass-through claim is not plausible under
    FAR 31.201-1 and URS Energy is not persuasive.
    D.    Remand for a Contracting Officer’s Decision on the Merits of
    MK’s Pass-Through Claim
    The court raises an issue sua sponte regarding further proceedings in this
    case. Normally, having dismissed all of the government’s challenges to a
    complaint, the court would require an answer to the complaint. Here, however, the
    DOE contracting officer never reached the merits of MK’s pass-through claim due
    to a defective certification that was only corrected very recently. In somewhat
    analogous circumstances, this court remanded a CDA claim to a federal agency for
    a decision on the merits of that claim:
    Once the court determines that a case is within its
    jurisdiction, it has juridical power to enter an order
    remanding the case to another body, either at the request
    of a party or on its own motion. The Tucker Act grants
    this court “the power to remand appropriate matters to
    any administrative or executive body or official with
    such direction as it may deem proper and just.” 
    28 U.S.C. § 1491
    (a)(2). When the factual record before the
    court is incomplete or additional agency proceedings or
    action are necessary, a remand may be appropriate. Both
    deficiencies exist here. [The agency] did not act on a
    number of Rollock’s claims, and, when it did act, it left
    salient matters unresolved. [The agency] should further
    29
    develop the factual record and definitively act on
    Rollock’s claims.
    Rollock Co. v. United States, 
    115 Fed. Cl. 317
    , 334 (2014) (citations omitted).
    In another recent case, a contracting officer delayed the issuance of his final
    decision on a CDA claim too long and the contractor brought suit in this court
    under a “deemed denial” theory. Rudolph & Sletten, Inc. v. United States, 
    120 Fed. Cl. 137
     (2015). This court found that it had jurisdiction over the cause, but
    remanded the claim to the contracting officer for a final decision on the merits. Id.
    at 143. The court cited 
    41 U.S.C. § 7103
    (f)(5) for its authority to do so. Under
    the same statutory authority the boards of contract appeals also will stay
    proceedings, in some circumstances, to allow a contracting officer’s decision to
    issue on the merits of a CDA claim. See, e.g., Brad West & Assocs., Inc., CBCA
    No. 3879, 
    14-1 BCA ¶ 35,744
     (Sept. 18, 2014) (noting in the procedural history of
    that case that the board had “directed [the agency] to issue a [contracting officer’s]
    decision within thirty days, or advise the Board as to why such a decision could
    not be issued”); Lobar, Inc., 
    ASBCA No. 59178
    , 
    14-1 BCA ¶ 35,584
     (Apr. 18,
    2014) (“We conclude that the issuance of a CO’s decision will better enable the
    parties to potentially settle this appeal and therefore grant the motion to stay
    proceedings until 12 May 2014 to issue a CO’s decision.”).
    The court believes that there is ample reason for a remand to DOE in this
    case. First, the defective certification has been cured, thus removing the reason
    the contracting officer gave for refusing to consider MK’s pass-through claim.
    Am. Compl. ¶ 24. Second, the factual underpinnings of the pass-through claim are
    interwoven with proceedings before a number of federal courts and the Civilian
    Board for Contract Appeals. These complex facts need to be analyzed in the
    context of the DOE project and contract documents. The DOE contracting officer
    is best situated to undertake this review in the first instance. Third, the type of
    underlying claim presented here is rather unusual, in that it is founded on a
    partially-satisfied judgment issued by a district court. DOE must render a decision
    on this unusual claim in light of its own interpretation of relevant law and relevant
    contract provisions.
    For all of the above reasons, the court will remand MK’s pass-through claim
    to DOE. In order for this process to function smoothly, the court solicits the
    parties’ input into an appropriate remand order. The instructions to DOE cannot
    30
    dictate any particular outcome, as such an order would exceed this court’s remand
    authority. See, e.g., Todd Constr., L.P. v. United States, 
    88 Fed. Cl. 235
    , 245
    (2009) (“The common theme running through these [remand] cases is that the
    remand does not mandate a particular factual determination, but directs the
    agency’s attention to matters the court believes require further action to create an
    adequate record for the agency’s decision.”). However, the parties may be able to
    suggest the appropriate period of time for such a remand and other requirements
    that would help this litigation proceed more efficiently from this point forward.
    Once the court has received a jointly-drafted proposed remand order from the
    parties, the court will remand MK’s pass-through claim to DOE’s contracting
    officer for the issuance of a final decision on that claim.
    CONCLUSION
    For the foregoing reasons, defendant’s motion to dismiss is denied. The
    court agrees with defendant, however, that the caption of this case should be
    modified to reflect the correct corporate name of the current prime contractor with
    DOE, URS Energy & Construction, Inc., the successor to MK and the sponsor of
    the claim set forth in the amended complaint. See Def.’s Mot. at 3. The parties
    should substitute “URS Energy & Construction, Inc.” for “M.K. Ferguson
    Company” in the caption of this case from this point going forward. The next
    procedural step in this case will be to remand plaintiffs’ claim to DOE. The court
    stays all other proceedings in this case until further order of the court.
    Accordingly, it is hereby ORDERED that
    (1)   Defendant’s Motion to Dismiss the First Amended Complaint,
    filed November 16, 2015, is DENIED;
    (2)   The Clerk’s Office is directed to CORRECT the docket to
    show the following four named plaintiffs and ALL FUTURE
    FILINGS by the parties shall reflect this change: URS
    ENERGY & CONSTRUCTION, INC., for the use and benefit
    of the secured creditors of GROUND IMPROVEMENT
    TECHNIQUES, INC.; PNC BANK, N.A.; FIREMAN’S FUND
    INSURANCE COMPANY; and, R.N. ROBINSON & SONS,
    INC.;
    31
    (3)   The Clerk’s Office is directed to SUSPEND all proceedings in
    this case until further order of the court; and,
    (4)   Defendant shall FILE a Notice containing the parties’
    proposed remand order to DOE on or before May 6, 2016.
    /s/Lynn J. Bush
    LYNN J. BUSH
    Senior Judge
    32