Meridian Engineering Company v. United States ( 2019 )


Menu:
  •             In the United States Court of Federal Claims
    No. 11-492C
    (Filed: September 23, 2019)
    )
    MERIDIAN ENGINEERING                          )   Post-remand decision on claims arising out of
    COMPANY,                                      )   a contract for construction of a flood control
    )   project; accord and satisfaction; proper subject
    Plaintiff,              )   matter; inapplicability of releases to preclude
    )   relief; damages
    v.                                     )
    )
    THE UNITED STATES,                            )
    )
    Defendant.              )
    )
    Michael H. Payne, Cohen, Seglias, Pallas, Greenhall & Furman PC, Philadelphia,
    Pennsylvania, for plaintiff.
    John H. Roberson, Senior Trial Counsel, Commercial Litigation Branch, Civil Division,
    United States Department of Justice, Washington, D.C., for defendant. With him on the briefs
    were Joseph H. Hunt, Assistant Attorney General, Civil Division, and Robert E. Kirschman, Jr.,
    Director, and Allison Kidd-Miller, Assistant Director, Commercial Litigation Branch, Civil
    Division, United States Department of Justice, Washington D.C.
    OPINION AND ORDER
    LETTOW, Senior Judge.
    This contract case returns to the court on remand from the United States Court of Appeals
    for the Federal Circuit. The parties’ dispute relates to a contract between Meridian Engineering
    Company (“Meridian”) and the United States Army Corps of Engineers (“Corps”) for the
    construction of a flood control project in Nogales, Arizona, near the border with Mexico.
    Numerous issues arose during construction that ultimately led to the project’s suspension after
    partial completion. The parties’ disagreement over costs led Meridian to file suit at this court in
    2011 under the Contract Disputes Act (“CDA”), 
    41 U.S.C. §§ 7101-7109
    .
    The court conducted two trials, one held in 2014 and one in 2016, on the issues of
    liability and damages respectively. See Meridian Eng’g Co. v. United States, 
    122 Fed. Cl. 381
    (2015) (“Meridian I”) (liability); Meridian Eng’g Co. v. United States, 
    130 Fed. Cl. 147
     (2016)
    (“Meridian II”) (damages). Following these two trials, the government was held to be liable on
    some counts of the complaint and Meridian was awarded damages in the amount of $983,771.10
    plus interest. Meridian II, 130 Fed. Cl. at 172. Meridian appealed from the final judgment. See
    Meridian Eng’g Co. v. United States, 
    885 F.3d 1351
     (Fed. Cir. 2018) (“Meridian III”). The
    Federal Circuit considered numerous issues on appeal, resulting in a mixed disposition of partial
    affirmance, partial vacatur, partial reversal, and remand. See 
    id. at 1367
    . Specifically of
    relevance now, the court vacated and remanded the court’s findings in Meridian I with respect to
    Meridian’s flood-events claim (“Count 4”) and Meridian’s unpaid contract-quantities claim
    (“Count 6”) and reversed and remanded this court’s interest award in Meridian II. See 
    id.
     When
    the remanded case returned to this court, it was transferred from the originally assigned judge to
    the undersigned.
    The sole issues remaining for the court are Count 4, as to both liability and damages, and
    the interest calculation. 1 For Count 4, this court was instructed on remand “to consider whether
    the parties reached a meeting of the minds on the flood event claims in light of all of the
    evidence.” 
    Id. at 1365
     (citation omitted). Separately, the Federal Circuit instructed this court “to
    enter the correct accrual date [for interest] as January 7, 2011, and recalculate the amount of
    interest in accordance with the correct accrual date.” 
    Id.
     at 1354 n.2. A hearing was held on
    September 4, 2019 to consider these remaining issues. Additionally, the court has reviewed the
    documentary and testimonial evidence adduced and addressed at trial, and the case is now ready
    for disposition.
    FACTS 2
    On September 21, 2007, the United States Army Corps of Engineers awarded Meridian,
    an engineering and construction firm based in Tucson, Arizona, a $5.8 million contract to
    undertake and construct a flood control project for the Chula Vista Channel in Nogales, Arizona.
    JX193-1. 3 During the beginning stages of the project, Meridian requested electronic drawings
    and survey files from the Corps on multiple occasions, but failed to receive them. See, e.g.,
    JX110 at 3 (requesting drawings on Oct. 29, 2007); DX726 at 4 (requesting again on Nov. 14,
    2007); PX134 (explaining that the drawings had not yet been received as of Dec. 4, 2007). The
    drawings were sent by the Corps to Meridian on December 26, 2007. See JX110 at 9. Following
    receipt of the drawings, Meridian was able to commence construction in early January 2008. See
    JX78 at 531.
    1
    As the case was being briefed on remand, the parties settled Count 6 and that Count was
    voluntarily dismissed by the plaintiff and is no longer at issue. See Notice (Sept. 19, 2019), ECF
    No. 179 (payment of $225,000 received by Meridian in settlement of Count VI); Stipulation of
    Dismissal (Sept. 20, 2019) (ECF No. 180) (parties’ stipulation that Count VI be and is dismissed
    with prejudice).
    2
    The recitation of facts constitutes the court’s principal findings of fact in accord with
    Rule 52(a) of the Rules of the Court of Federal Claims (“RCFC”). Other findings of fact and
    rulings on questions of mixed fact and law are set out in the analysis. A more complete recitation
    of facts is described in Meridian I. See 122 Fed. Cl. at 385-97.
    3
    Citations to plaintiff’s exhibits are identified as “PX___,” defendant’s exhibits are
    identified as “DX___,” and the parties’ joint exhibits are identified as “JX___.”
    2
    Initial construction continued steadily until February and March, 2008 when Meridian
    encountered subsurface flows and soil issues causing stability problems for construction. See,
    e.g., PX17; JX57. Meridian alerted the Corps to these issues, see JX57, and in response, the
    Corps issued additional requests for proposals, see, e.g., JX159, and modifications, see, e.g.,
    JX118 (referencing modification R3). 4 Problems continued to arise throughout the construction
    process, increasing the project’s scope and duration. See, e.g., PX146 at 1-6 (detailing the issues
    and revised project schedule). Additional modifications were issued by the Corps in the months
    following, including the addition of a new access ramp via Modification R6 on May 8, 2008, see
    JX121, that increased the contract price and eventually led to schedule delays, see PX389 at 18-
    19. Following further issues, the Corps issued a subsequent bilateral modification, modification
    R8, on June 5, 2008, which extended the schedule by twelve calendar days but deleted the
    additional work on the access ramp originally added in R6. See JX123. Modification R8 also
    included the following release language: “[T]his adjustment constitutes compensation in full on
    behalf of the Contractor . . . for all costs and markups directly or indirectly attributable for the
    change ordered, for all delays related thereto, for all extended overhead costs, and for
    performance of the change within the time frame stated.” JX123 at 2.
    Further modifications were issued, see, e.g., JX125, as construction continued into late
    June 2008 to the point that concrete could be poured for the channel invert, see, e.g., JX78 at
    167-69. Flooding of the work site, beginning about this same time, led to numerous delays in the
    work plan. See JX78 at 158 (“Work was stop[p]ed because of the flood and the damage[] that
    resulted from it. Additionally, Meridian is unable to proceed with their work plans for the
    weekend.”). This flooding continued to adversely affect progress on the worksite, with Meridian
    reporting incidents of continued flooding, including from July 6 to 11, 2008 and on July 14,
    2008, see PX56-61, and between August 3, 2008 and September 26, 2008, see PX62-102.
    Specifically, during the latter dates, Meridian reported that the site experienced forty-seven days
    of flooding out of fifty-four. As a partial result of these weather delays, the Corps executed
    additional modifications to the construction plan, including modification R12 on September 4,
    2008, see JX127, modification R16 on September 9, 2008, see JX131, and modification R13 on
    September 12, 2008, see JX128, which extended the construction calendar collectively by thirty-
    three days. Subsequently, on September 15, 2008, the Corps and Meridian executed bilateral
    modification R17, which addressed cost increases and schedule delays due to the late delivery of
    the survey files to Meridian. See JX132. Just as in modification R8, all of these modifications
    included the same mutual release of liability. See, e.g., JX132 at 2.
    Progress continued on the project in the months following, with, again, further
    modifications extending the project’s scheduled completion. See, e.g., JX135 (extending the
    schedule by five calendar days as of March 13, 2009 to account for weather delays from late
    2008). Due to the delays and structural failures, however, the Corps ultimately terminated the
    project in September 2009 following a final inspection. See JX49 at 12-14.
    4
    The Modifications were referred to by the parties and in the documentation with various
    labels, e.g., “R3,” “R-3,” and R0003. For ease, the court will refer to all modifications by
    eliminating extraneous dashes and zeroes, e.g., “R3.”
    3
    Multiple disputes between the parties over costs remained. On August 24, 2009,
    Meridian submitted a final payment request to the Corps, which was eventually rejected. See
    DX572. With these disputes still outstanding, the Corps circulated internally, but never issued, a
    draft modification R33 that would have responded to Meridian’s requests for equitable
    adjustments (“REA”) regarding flood events during the 2008 monsoon season as well as sub-
    surface water flows. PX377 at 3. The draft specifically noted that, “subsurface water is an
    unpredictable element which led to delays giving partial merit to the flood REA by causing the
    contractor to be working on the channel in the early monsoon events.” PX377 at 8. At the time,
    Meridian was unaware of this draft modification. See Meridian I, 122 Fed. Cl. at 411. With no
    resolution of its claims, Meridian then submitted a Consolidated Request for Equitable
    Adjustment (“consolidated REA”) to the Corps on April 2, 2010 which contained fourteen
    counts of requests for equitable adjustment. JX177 at 1. The fourth count (“REA 4”) was a
    claim for $899,600.88 for “flood events.” JX17 at 17. On May 20, 2010, the Corps
    acknowledged receipt of the consolidated REA and stated its intent to issue a decision by
    November 30, 2010. JX189. After no decision was rendered, Meridian converted the
    consolidated REA into a certified claim on January 7, 2011. JX33 at 1.
    Again, no decision was issued by the Corps, and Meridian brought suit in this court
    alleging a right to relief under the CDA. In Meridian I, the court concluded that Meridian’s
    claim was deemed denied on March 7, 2011. Meridian I, 122 Fed. Cl. at 399; see 
    41 U.S.C. § 7103
    (f)(5). All fourteen counts were considered by the court in Meridian I, with the court ruling
    that “the [Corps] did not breach the September 21, 2007 Contract, as alleged in Counts 1-6 and
    10-13 of the May 19, 2014 Second Amended Complaint, or the implied duty of good faith and
    fair dealing, as alleged in Count 14 . . . .” 122 Fed. Cl. at 426. Counts 7-9 remained at issue until
    Meridian II, 5 where the court found that Meridian was entitled to an equitable adjustment of
    $983,771.10, plus interest accruing from January 7, 2014 until date of payment. 130 Fed. Cl. at
    172.
    Meridian subsequently appealed this decision to the Federal Circuit in Meridian III. 
    885 F.3d 1351
    . On appeal, Meridian pursued its claims against the government on all fourteen
    counts, and, additionally, it contended that the accrual date for interest as found in Meridian II
    was incorrect. See 
    id. at 1353-54
    . The government conceded liability for Counts 7-9, see 
    id. at 1354
    , and both parties agreed that the proper starting date for interest accrual should be January
    7, 2011, see 
    id.
     at 1354 n.2. 6 As to Counts 1-6 and 10-14, the Federal Circuit vacated and
    remanded the decision of the court in Meridian I for Counts 4 and 6, and affirmed the dismissal
    of the other Counts from the Meridian I decision. See 
    id. at 1367
    . Because the parties have
    reached a settlement as to Count 6, and that Count has been dismissed, see supra, at 2 n.1, only
    Count 4 remains in dispute on remand.
    Regarding Count 4 concerning flood events, the Federal Circuit concluded that the
    court’s analysis in Meridian I was insufficient. Id. at 1362. In Meridian I, the court had ruled
    5
    Count 7 concerned “Suspension of work,” Count 8 related to “Channel Fill,” and Count
    9 was based on “Interest Protection.” See Meridian III, 885 F.3d at 1354.
    6
    The court today adjusts the proper interest accrual date. See infra, at 9.
    4
    that Meridian’s claim was barred by the defense of accord and satisfaction due to the releases
    present in both modification R8 and modification R17. 122 Fed. Cl. at 411-12. Meridian had
    argued that the parties continued to consider the flood-damage claim despite the releases, such
    that there was no meeting of the minds between the parties as required for accord and
    satisfaction. Id. at 412. In support of this contention, Meridian argued that the draft modification
    R33 included the Corps’ estimate of money owed by the Corps to Meridian for flood damage. Id.
    Nonetheless, the court had concluded in Meridian I that because Meridian was unaware of the
    draft modification R33 prior to discovery, the releases in R8 and R17 were effective to preclude
    the claim. Id.
    In vacating and remanding that decision, the Federal Circuit clarified on appeal that the
    standard for acceptance vel non of a claim when presented with an accord and satisfaction
    defense does not require evidence of proposed modifications negotiated between the parties.
    Meridian III, 885 F.3d at 1364. Instead, as the court noted, “Our precedent on the meeting of the
    minds inquiry accepts a wide range of evidence in its fact-specific consideration” of meeting of
    the minds, id. at 1365, and particularly that it was necessary to take into account “additional
    evidence on record showing that the [g]overnment directed Meridian to submit revised estimates
    for the flood claim on multiple occasions after the execution of the bilateral modifications [that
    contained the releases],” id. at 1364. The court of appeals also questioned whether the “subject
    matter” of the releases applied to the flood-damage claim, i.e., whether “the subject matter of the
    modification [and attendant release] is the same as that of the disputed claim.” Id. at 1364 n.12.
    Consequently, the court ordered that “[o]n remand, the Court of Federal Claims shall consider
    meeting of the minds and proper subject matter.” Id.
    STANDARDS FOR DECISION
    Accord and satisfaction refers to the “discharge [of a claim] by the rendering of some
    performance different from that which was claimed as due and the acceptance of such substituted
    performance by the claimant as full satisfaction of his claim.” Brock & Blevins Co. v. United
    States, 
    343 F.2d 951
    , 955 (Ct. Cl. 1965) (quoting 6 Corbin, Contracts § 1276 (1962)). To
    establish the affirmative defense of accord and satisfaction, four elements must be present: “(1)
    proper subject matter; (2) competent parties; (3) a meeting of the minds of the parties; and (4)
    consideration.” Holland v. United States, 
    621 F.3d 1366
    , 1382 (Fed. Cir. 2010) (citing
    O’Connor v. United States, 
    308 F.3d 1233
    , 1240 (Fed. Cir. 2002)); see also Sikorsky Aircraft
    Corp. v. United States, 
    105 Fed. Cl. 657
    , 674 (2012).
    ANALYSIS
    I. Count 4: Flood Event Liability
    The court is first charged on remand with determining whether the government is liable
    to Meridian for flood-event damages suffered during the 2008 monsoon season. Meridian argues
    that it is entitled to recover damages in connection with the flood events in a total of
    $921,620.69, plus interest. Pl.’s Br. on Remand (“Pl.’s Br.”) at 16, ECF No. 157. In opposition,
    the government asserts that this claim should be barred under the defense of accord and
    satisfaction, or alternatively, that the contract assigned the risk of flooding to Meridian. Def.’s
    5
    Resp. to Pl.’s Br. on Remand (“Def.’s Opp’n”) at 18, 31, ECF No. 172. Because the court
    concludes that the government’s arguments of accord and satisfaction and assignment of risk are
    unconvincing, the court finds the government liable for flood-event damages under Count 4.
    A. Accord and Satisfaction
    Two of the necessary elements for accord and satisfaction are in dispute in this case: (1)
    what the proper subject matter of the releases are; and (2) whether the parties came to a meeting
    of the minds on the scope of the releases. After addressing the issue of the proper subject matter
    of the releases in modification R8 and modification R17, the court will examine whether the
    parties came to a meeting of the minds that the releases set out in those modifications
    “constituted full and complete satisfaction of all obligations and liabilities,” Holland, 
    621 F.3d at 1383
    , for all flood-events claims.
    1. Proper subject matter.
    At issue is whether the release language from modifications R8 and R17 encompasses
    Meridian’s claims for flood-event damages. Both modification R8, dated June 5, 2008, and
    modification R17, dated September 15, 2008, contain the same mutual release of liability. The
    specific text is:
    It is understood and agreed that pursuant to the above, the contract time is
    extended the number of calendar days stated, and the contract price is increased as
    indicated above, which reflects all credits due the Government and all debits due
    the Contractor. It is further understood and agreed that this adjustment constitutes
    compensation in full on behalf of the Contractor and its Subcontractors and
    Suppliers for all costs and markups directly or indirectly attributable for the
    change ordered, for all delays related thereto, for all extended overhead costs, and
    for performance of the change within the time frame stated.
    JX123 at 2; JX132 at 2. Modification R8 was specifically described as “a definitization of
    modification R00006,” JX123 at 2, which had added the new access ramp, while modification
    R17 addressed “delay as it pertains to project drawings and survey issues,” JX132 at 2.
    Meridian argues that each of these releases speaks only to specific costs associated with
    the explicit purposes listed in the modifications, that is, the costs of the new access ramp and the
    survey drawing delays. See Pl.’s Br. at 22. The government, on the other hand, suggests a
    broader reading of the release language that would include the release of all flood-event damage
    claims, past and future, arguing that these are encompassed within the related-costs language of
    the release. See Def.’s Opp’n at 25-26. The court agrees with Meridian.
    While the release language specifies release for “all costs and markups directly or
    indirectly attributable for the change ordered” and “for all delays related thereto,” see JX123 at
    2; JX132 at 2, flood-event damage claims arising in the future are simply too attenuated from the
    access ramp and survey delays to be within the subject matter of these releases. Notably, the
    6
    execution dates of both of the modifications, but particularly that of R8, pre-date a significant
    portion of the days when the site experienced flooding. See id.; see also PX62-102 (noting
    significant flooding at the work site between August 3, 2008 and September 26, 2008); Hr’g Tr.
    10:4-7 (Sept. 4, 2019) (“There were approximately 14 flood events during that monsoon season
    of 2008 and they occurred between June 27th and December 19th of 2008.”). The releases do not
    explicitly cover flood damage that had not yet occurred and whose scope was not predicted.
    In support of its position, the government argues that the flood-event damage was
    suffered as at least an indirect result of the delays incurred from these modifications, R8 and
    R17, because these delays forced Meridian to work during the area’s extended monsoon season,
    the ultimate cause of the site’s flooding. Def.’s Opp’n at 27. This argument, however, is
    unconvincing. The project’s overall progress in 2008 was slowed as a result of numerous causes,
    including additional modifications to the scope of the work and differing site conditions such as
    sub-surface water flows and softer-than-anticipated soils. Thus, no accurate line of causation can
    be drawn between the two causes of delay at issue here, the definitization of the new access ramp
    and the survey delays, and the several other incidents and modifications which delayed the
    project and pushed completion of the crucial channel invert work into monsoon season.
    The facts at hand can also be distinguished from those of the cases the government uses
    to support its broad reading of the release language at issue. For example, in King Fisher Marine
    Serv., Inc. v. United States, 
    16 Cl. Ct. 231
     (1989), while the court did find that the release
    language barred all claims arising from a FO-2 change order, ultimately, the court limited its
    reading of the language by applying the notion that “King Fisher’s entire claim is based on the
    FO-2 change order.” 
    Id. at 237
    . Here, unlike in King Fisher, the claim for flood-event damages
    is not obviously within the purview of either the ramp access or the survey delays specifically
    addressed by the modifications. Contrastingly, as with King Fisher, in John Massman
    Contracting Co. v. United States, 
    23 Cl. Ct. 24
     (1991), the claims brought by the plaintiff were
    for compensation resulting from schedule extensions due to modifications that included release
    language similar to that at issue here, see 
    id. at 28
    , but the money sought by Massman was for
    delays and damages that were explicitly encompassed by the subject matter of the modifications.
    For example, Massman sought damages and costs from high river flows; modification P10,
    which contained the release language, “granted plaintiff a 295 calendar day extension because of
    high river flows.” 
    Id. at 27-28
     (emphasis added). Again, modifications R8 and R17 related to an
    access ramp and survey delays, not flood-event damages. Accordingly, the connection between
    the claim and the explicit subject of the release does not correlate as it did in King Fisher and
    Massman.
    2. Meeting of the minds.
    Although the court today finds that flood-event damages are not encompassed within the
    subject matter of the R8 and R17 releases, the court also concludes that the defense of accord and
    satisfaction is barred here because it finds there was no meeting of the minds between the parties
    as to the flood-event damages claim. As explained by the Federal Circuit in Community
    Heating, “[C]ourts may refuse to bar a claim based upon the defense of accord and satisfaction
    where the parties continue to consider the claim after execution of a release” because this
    conduct is evidence that there was no meeting of the minds between the parties that the release
    7
    language would constitute an abandonment of the plaintiff’s earlier claim. See Community
    Heating & Plumbing Co., Inc. v. Kelso, 
    987 F.2d 1575
    , 1581 (Fed. Cir. 1993) (citing Winn-
    Senter Constr. Co. v. United States, 
    75 F. Supp. 255
     (Ct. Cl. 1948)). Ultimately, the court
    concludes today that there was no meeting of the minds here because the flood-event damages
    claim continued to be negotiated after the releases were issued, as evidenced by draft
    modification R33, the government’s request for and Meridian’s subsequent submission of an
    REA including a claim for flood events, and the government’s subsequent consideration of that
    REA. See, e.g., Community Heating, 
    987 F.2d at 1581
     (emphasizing that the Navy continued to
    negotiate and audit the claims thereby barring an accord and satisfaction defense); A & K
    Plumbing & Mech., Inc. v. United States, 
    1 Cl. Ct. 716
    , 723 (1983), aff’d, 
    795 F.2d 1011
     (Fed.
    Cir. 1986) (concluding that each party’s consideration of the merits of the claim required that the
    release not be construed as a bar to plaintiff’s claim).
    In this case, there is evidence that both parties considered the merits of the flood-event
    damages claim after the execution of modifications R8 and R17. Following the execution of the
    modifications, in June and September 2008 respectively, Meridian sent a letter to the Corps
    requesting equitable compensation for flood-event damage. See PX377 at 7 (referencing an REA
    sent on December 22, 2008 regarding flood damage on site). The Corps responded to this REA
    with a letter, dated January 22, 2009, finding that after an initial consideration on the merits, it
    found no merit. Def.’s Opp’n, Ex. B at 1. Meridian, still seeking final resolution on its flood-
    events REA in addition to others, filed a consolidated REA on April 2, 2010, see JX177, with the
    Corps, responding to their request to do so, id.; see also Hr’g Tr. 857:18-858:12 (Jan. 29, 2014).
    In August 2010, the Corps internally circulated draft modification R33, which noted that the
    Corps’ initial response to the flood REA came with “a request for additional information” from
    Meridian, and noted that the flood REA now garnered “partial merit.” P377 at 7-8. While this
    modification was never issued, and although Meridian did not learn of this document until
    discovery was had in this case, the draft of this document and its internal circulation are enough
    to show continued consideration by the Corps of Meridian’s claim.
    Further in support of this conclusion, the Corps responded to the consolidated REA,
    which contained the renewed REA for flood events, with a letter on May 20, 2010,
    acknowledging the receipt of the REAs and committing to issue a final decision by November
    30, 2010 on the claims. See JX189. The record, therefore, contains sufficient evidence that there
    was no “intent on the part of either party that the release[s] ha[d] [the] effect” of barring the
    plaintiff’s claims. A & K Plumbing, 1 Cl. Ct. at 723.
    II. Assumption of Risk
    The government alternatively suggests that that Meridian’s claim for flood-event
    damages fails because the contract assigned the risk of flooding on the site to Meridian. Def.’s
    Opp’n at 31. This argument is attended by irony—in one sense, the government seeks to suggest
    that the flood-events damage directly resulted from the delays caused by modifications R8 and
    R17 (thus seeking to put them within the release language), and yet also suggests that the flood
    damage from monsoon season was the sheer result of poor planning on Meridian’s part. See
    Def.’s Opp’n at 31-34 (“Meridian’s flood[-]event damages claim also fails because Meridian
    chose to work in the river channel during monsoon season.”). The government’s argument is
    8
    unavailing. Meridian’s initial construction schedule planned for a completion of the channel
    invert work, a necessary step in protecting the site from flooding, to be completed by late June
    2008. See Pl.’s Br. at 16-17; Hr’g Tr. 8:3-7 (Sept. 4, 2019). As previously noted, many issues
    arose in the project’s early stages that led to cumulative substantial delay, including those caused
    by the government’s failure timely to provide the survey files. These delays, in turn, pushed the
    channel invert work’s completion well into monsoon season. The government cannot now claim
    that Meridian assumed the risk of flooding from monsoon season when the government was
    largely responsible for Meridian’s inability to complete the project prior to the beginning of
    monsoon season. See, e.g., Merritt-Chapman & Scott Corp. v. United States, 
    528 F.2d 1392
    ,
    1398-99 (Ct. Cl. 1976) (finding that government-caused delays which pushed the contractor to
    work during heavy rainfall were compensable). Simply put, the government cannot escape
    liability for flood damages when the government is responsible for causing the contractor to be
    working during the flood-prone season.
    III. Count 4: Flood-Event Damages
    Because the court concluded in Meridian I that the government was not liable to
    Meridian for flood-event damages, see 122 Fed. Cl. at 412, the court never addressed the issue of
    damages for Count 4 in Meridian II, see 130 Fed. Cl. at 172. The court today finds the
    government liable for flood-event damages under Count 4. Therefore, the court must determine
    the proper amount due.
    Meridian, on remand, sought damages in the amount of $921,620.69, plus interest. Pl.’s
    Br. at 16. The government disputed $48,017 of this sum, arguing for damages in the amount of
    $873,603.69, plus interest. See Joint Stipulations of Fact (“Joint Stip.”) at 85, ECF No. 141.
    Meridian has now conceded and agrees to the government damages calculation of $873,603.69,
    plus interest. Hr’g Tr. 58:16-25; 59:9-15 (Sept. 4, 2019). Therefore, the court finds that
    Meridian is entitled to damages for flood events under Count 4 in that amount.
    IV. Interest Calculation: Counts 4, 7-9
    On remand, this court has also been charged with recalculating the damages based on the
    proper interest accrual starting date. Meridian III, 885 F.3d at 1354 n.2. This interest must be re-
    calculated with regard to Counts 7-9 in accordance with the damages awarded in Meridian II,
    and calculated now for the first time with regard to Count 4.
    Under 
    28 U.S.C. § 2516
    (a), Meridian is entitled to interest on both of its claims.
    Pursuant to 
    41 U.S.C. § 7109
    (b), “[i]nterest shall accrue and be paid at a rate which the Secretary
    of the Treasury shall specify as applicable for each successive 6-month period.” As noted in
    Meridian III, the proper interest accrual start date is January 7, 2011, 885 F.3d at 1354 n.2, not
    January 7, 2014 as originally stated in Meridian II, 130 Fed. Cl. at 171. The applicable interest
    rates, as determined by the Secretary of the Treasury for the periods at issue are as follows:
    (1) January 7, 2011-June 30, 2011: 2.625%. 
    75 Fed. Reg. 82,146
     (Dec. 29, 2010).
    (2) July 1, 2011-December 31, 2011: 2.5%. 
    76 Fed. Reg. 38,742
    -43 (July 1, 2011).
    9
    (3) January 1, 2012-June 30, 2012: 2.0%. 
    76 Fed. Reg. 82,350
     (Dec. 30, 2011).
    (4) July 1, 2012-December 31, 2012: 1.75%. 
    77 Fed. Reg. 38,888
     (June 29, 2012).
    (5) January 1, 2013-June 30, 2013: 1.375%. 
    77 Fed. Reg. 76,624
     (Dec. 28, 2012).
    (6) July 1, 2013-December 31, 2013: 1.75%. 
    78 Fed. Reg. 39,063
     (June 28, 2013).
    (7) January 1, 2014-June 30, 2014: 2.125%. 
    79 Fed. Reg. 424
     (Jan. 3, 2014).
    (8) July 1, 2014-December 31, 2014: 2.0%. 
    79 Fed. Reg. 37,391
     (July 1, 2014).
    (9) January 1, 2015-June 30, 2015: 2.125%. 
    79 Fed. Reg. 78,950
    -51 (Dec. 31, 2014).
    (10) July 1, 2015-December 31, 2015: 2.375%. 
    80 Fed. Reg. 39,482
    -83 (Jan. 9, 2015).
    (11) January 1, 2016-June 30, 2016: 2.5%. 
    80 Fed. Reg. 81,880
     (Dec. 31, 2015).
    (12) July 1, 2016-December 31, 2016: 1.875%. 
    81 Fed. Reg. 44,088
     (July 6, 2016).
    (13) January 1, 2017-June 30, 2017: 2.5%. 
    82 Fed. Reg. 910
     (Jan. 4, 2017).
    (14) July 1, 2017-December 31, 2017: 2.375%. 
    82 Fed. Reg. 34,348
     (July 24, 2017).
    (15) January 1, 2018-June 30, 2018: 2.625%. 
    83 Fed. Reg. 3,052
     (Jan. 22, 2018).
    (16) July 1, 2018-December 31, 2018: 3.5%. 
    83 Fed. Reg. 47,970
     (Sept. 21, 2018).
    (17) January 1, 2019-June 30, 2019: 3.625%. Bureau of the Fiscal Serv., Interest Rates,
    Prompt Payment, https://www.fiscal.treasury.gov/prompt-payment/rates.html (last visited
    Sept. 16, 2019).
    (18) July 1, 2019-September 19, 2019: 2.625%. Bureau of the Fiscal Serv., Interest Rates,
    Prompt Payment, https://www.fiscal.treasury.gov/prompt-payment/rates.html (last visited
    Sept. 16, 2019).
    Further interest will be due at the rate specified by the Treasury until the judgment has been paid.
    Meridian was awarded pre-interest damages of $983,771.10 in Meridian II, 130 Fed. Cl.
    at 171, and has today been awarded pre-interest damages of $873,603.69, for a total of
    $1,857,374.79. Meridian is entitled to simple interest on this total amount. 
    42 C.F.R. § 52.233
    -
    1(h). Simple interest is calculated with the formula I=Prt, where “I” is the interest, “P” is the
    principal, “r” is the interest rate, and “t” is the unit of time. As of September 19, 2019, the
    government owes a total of $377,982.13 in interest. The following table contains a more detailed
    calculation:
    10
    CONCLUSION
    For the reasons stated, the court finds the government liable to Meridian for Count 4,
    flood-event damages. Pursuant to Meridian III, the government is also liable for Count 7,
    suspension of work, Count 8, channel fill, and Count 9, interest protection. See 885 F.3d at
    1354. Meridian is entitled to damages in the amount of $873,603.69 for Count 4 and $983,771.10
    for Counts 7-9, totaling to damages in the amount of $1,857,374.79, plus interest, pursuant to 
    41 U.S.C. § 7109
    (b). Interest will accrue from January 7, 2011 until the date of payment. As of
    September 19, 2019, the government owed Meridian $377,982.13 in interest. The clerk is
    directed to enter final judgment in accord with this disposition.
    No costs.
    It is so ORDERED.
    s/ Charles F. Lettow
    Charles F. Lettow
    Senior Judge
    11