Fox Logistics and Construction Company v. United States ( 2019 )


Menu:
  •           In the United States Court of Federal Claims
    No. 18-1395C
    (Filed: September 25, 2019)
    *************************************
    *
    FOX LOGISTICS AND CONSTRUCTION *
    COMPANY,                            *                    Third-Party Beneficiary; Implied-
    *                    In-Fact Contract; Duty of Good
    Plaintiff,      *                    Faith and Fair Dealing; Privity of
    *                    Contract; Tucker Act; 28 U.S.C. §
    v.                                 *                    1491; Subject-Matter Jurisdiction;
    *                    RCFC 12(b)(1).
    THE UNITED STATES,                  *
    *
    Defendant.      *
    *
    *************************************
    Hal A. Emalfarb, Emalfarb, Swan & Bain, Highland Park, Illinois, for Plaintiff Fox
    Logistics and Construction Company.
    Michael D. Snyder, with whom was Joseph H. Hunt, Assistant Attorney General, Robert
    E. Kirschman, Jr., Director, Commercial Litigation Branch, Steven J. Gillingham,
    Assistant Director, Commercial Litigation Branch, U.S. Department of Justice,
    Washington, D.C., and Rhonda Sumpter, United States Air Force, Joint Base Andrews,
    Maryland, for Defendant.
    OPINION AND ORDER
    WHEELER, Judge.
    In this case, plaintiff Fox Logistics and Construction Co. (“Fox”) alleges that it was
    a third-party beneficiary of a contract between Lakeshore Engineering Services, Inc.
    (“Lakeshore”) and the Department of the Air Force. In the alternative, Fox claims that it
    had an implied-in-fact contract with the Air Force. In either event, Fox alleges that the Air
    Force breached its duty of good faith and fair dealing.
    Fox’s claims are related to a construction contract between the Government and
    Lakeshore for the construction of Shindand Air Base in Afghanistan. Fox was one of
    Lakeshore’s subcontractors on the project, and alleges that it is owed approximately $11.7
    million in damages for unpaid work and other costs associated with the construction of the
    base.
    Now before the Court is the Government’s motion to dismiss this case for lack of
    subject-matter jurisdiction. For the reasons that are discussed below, the Court STAYS
    consideration of the Government’s motion to dismiss, pending completion of limited
    discovery on the issue of the Court’s jurisdiction over this case.
    Background
    In April of 2006, the Air Force awarded Lakeshore a contract for heavy engineering
    repair and construction work at Shindand Air Base in Afghanistan. Compl. ¶ 5. The Air
    Force waived the usual bond requirements for the project because the base was located in
    a war zone. Id. ¶ 6. On August 23, 2012, the Air Force issued Task Order FA8903-06-D-
    8505-0042 (“TO 42”) to Lakeshore for infrastructure work on the air base. Id. ¶ 7.
    Lakeshore hired Fox as a subcontractor responsible for the TO 42 construction on October
    12, 2012. Id. ¶ 8.
    By May of 2013, Lakeshore was behind on both construction and payments to its
    subcontractors. See id. ¶¶ 10-11. Between May 2013 and January 2014, the Air Force
    issued three Show Cause Notices to Lakeshore, requesting that Lakeshore provide
    assurances that it was willing and able to complete TO 42. Id. ¶¶ 10-13. Each of these
    Show Cause Notices resulted in part from Lakeshore’s inability to pay its subcontractors.
    See id. Some subcontractors, including Fox, refused to continue work on Lakeshore’s
    projects until they were paid. E.g., Dkt. 15-1 at 3. The third Show Cause Notice, issued
    by Contracting Officer Captain Rebecca Ban on January 7, 2014, warned Lakeshore that
    unless it “submit[ted] acceptable assurances within ten . . . days” TO 42 could be terminated
    for default. Compl. ¶ 13.
    On January 17, 2014, Lakeshore responded to the third Show Cause Notice. Id. ¶
    14. In its response, Lakeshore proposed creating a “designated holding account” into
    which the Air Force could deposit the funds for three task orders Lakeshore was working
    on, including TO 42. Dkt. 29-1 at 1. (In their course of dealing, the parties sometimes
    referred to the designated holding account as the “special account.” See, e.g., Compl. ¶
    21.) Lakeshore gave designated Air Force personnel view-only access to the account, so
    that they could monitor how funds were distributed from it. Id. ¶ 18.
    In a February 7, 2014 memorandum, Captain Ban agreed to Lakeshore’s proposal.
    Id. Captain Ban informed Lakeshore that future invoices must include “subcontractor
    payment certifications” and that Lakeshore must pay its subcontractors as soon as it
    received money from the Air Force. Id. Additionally, the Air Force required Lakeshore
    to create payment plans for each subcontractor for which it was in arrears. Id. These
    2
    payment plans had to be signed by the subcontractor, include the amounts owed to the
    subcontractor, detail the amount that Lakeshore would actually be paying to the
    subcontractor, and include the date by which Lakeshore intended to pay all of the money
    it owed to the subcontractor. Id. Captain Ban also said that Lakeshore would not “be
    allowed to retain funds for their own in-country expenses” other than money necessary for
    “life support and security.” Id. Finally, Captain Ban warned Lakeshore that the Air Force
    would be monitoring the transactions out of the designated holding account, and that “[i]f
    at any time, transactions d[id] not occur in accordance with the approved subcontractor
    payment certification” the task order would “be immediately terminated for default.” Id.
    Lakeshore contacted Mushtaq Habibi, Fox’s Director General, to explain these
    requirements, and obtain his consent to Lakeshore’s payment plan for Fox. See Dkt. 26-9
    at 56-57. After consulting by email with two Air Force officers, Mr. Habibi consented to
    the payment plan. Id. at 56-57, 65, 67.
    At first, the new plan appeared to be working. Between February and May of 2014,
    Lakeshore paid Fox $4,052,085.01. See Compl. ¶ 27. Unfortunately, on May 1, 2014,
    Lakeshore abandoned TO 42. Id. ¶ 28. The next day it filed for bankruptcy in the United
    States. Id. ¶ 29. At the time it declared bankruptcy, Lakeshore still owed Fox more than
    $3,000,000. Id. ¶ 47. Fox has incurred more than $8,000,000 in uncompensated expenses
    since then. Id. Fox attempted to recover the money it was owed during Lakeshore’s
    bankruptcy proceeding, but was unsuccessful. See id. ¶ 31. Fox then filed a certified claim
    with Captain Ban, asking to be paid the money it was owed under TO 42. Id. ¶ 31. Captain
    Ban denied Fox’s claim on October 24, 2017. Id. ¶ 32.
    On September 13, 2018, Fox filed this suit. On April 15, 2019, the Government
    filed a motion to dismiss Fox’s complaint for lack of subject-matter jurisdiction under Rule
    12(b)(1) of the Rules of the United States Court of Federal Claims (“RCFC”). Fox filed a
    response to the motion to dismiss on June 28, 2019, and the Government filed its reply on
    August 6, 2019. The Court heard oral argument on the motion on September 4, 2019.
    Discussion
    A. Standard of Review
    Whether the Court has jurisdiction to decide the merits of a case is a threshold
    matter. See PODS, Inc. v. Porta Stor, Inc., 
    484 F.3d 1359
    , 1365 (Fed. Cir. 2007). When
    deciding a Rule 12(b)(1) motion to dismiss, a court must assume all the undisputed facts
    in the complaint are true and draw reasonable inferences in the non-movant’s favor.
    Acevedo v. United States, 
    824 F.3d 1365
    , 1368 (Fed. Cir. 2016). Further, the plaintiff
    bears the burden of establishing facts sufficient to invoke this Court’s jurisdiction by a
    preponderance of the evidence. Reynolds v. Army & Air Force Exch. Serv., 
    846 F.2d 746
    ,
    748 (Fed. Cir. 1988). In determining whether a plaintiff has met this burden, courts may
    3
    look “beyond the pleadings and ‘inquire into jurisdictional facts’ in order to determine
    whether jurisdiction exists.” Lechliter v. United States, 
    70 Fed. Cl. 536
    , 543 (2006)
    (quoting Rocovich v. United States, 
    933 F.2d 991
    , 993 (Fed. Cir. 1991)). When
    jurisdictional facts are in dispute, jurisdictional discovery is appropriate. Hopi Tribe v.
    United States, 
    113 Fed. Cl. 43
    , 50 (2013) (citing Samish Indian Nation v. United States,
    No. 2-1383L, 
    2006 WL 5629542
    , at *4-6 (Fed. Cl. 2006); E. Trans-Waste of Md., Inc. v.
    United States, 
    27 Fed. Cl. 146
    , 148 n.1 (1992)).
    B. Plaintiff’s Claims
    For this Court to have jurisdiction over a breach of contract claim against the United
    States, there must be privity of contract between the plaintiff and the Government. Cent.
    Transp. Int’l, Inc. v. United States, 
    63 Fed. Cl. 336
    , 338 (2004). “Absent privity . . . there
    has been no waiver of sovereign immunity” and the Court does not have jurisdiction over
    the claim. 
    Id.
     However, a plaintiff need not be in direct privity; status as a third-party
    beneficiary to a contract with the Government will suffice to give the Court jurisdiction.
    See Anderson v. United States, 
    344 F.3d 1343
    , 1352 (Fed. Cir. 2003). The Court also has
    jurisdiction to hear claims relating to implied-in-fact contracts with the Government. 
    Id.
    at 1351 n.2 (citing Maher v. United States, 
    314 F.3d 600
    , 603 n.1 (Fed. Cir. 2002)).
    In its complaint, Fox asserts that it was a third-party beneficiary of the contract
    between Lakeshore and the Government. In the alternative, Fox claims that it had an
    implied-in-fact contract with the Government. Either theory, if supported by a
    preponderance of the evidence, would give the Court jurisdiction to hear Fox’s claims. 1
    See Turping v. United States, 
    913 F.3d 1060
    , 1065 (Fed. Cir. 2019).
    1. Third-Party Beneficiary
    It is not easy for a plaintiff to prove that it is a third-party beneficiary of a contract.
    The third party is “entitled to a benefit promised in a contract . . . only if the contracting
    parties so intend.” Astra USA, Inc. v. Santa Clara County, 
    563 U.S. 110
    , 117 (2011). The
    parties’ intent to benefit the third party can be either “express or implied,” but it must be
    “fairly attributable to the contracting officer.” G4S Technology LLC v. United States, 
    779 F.3d 1337
    , 1340 (Fed. Cir. 2015) (quoting Glass v. United States, 
    258 F.3d 1349
    , 1354
    (Fed. Cir. 2001); Flexfab, L.L.C. v. United States, 
    424 F.3d 1254
    , 1263 (Fed. Cir. 2005)).
    The parties to the contract must intend to benefit the third party directly; incidental benefits
    1
    In its complaint, Fox also alleges a third claim for relief: that the Government breached the
    implied duty of good faith and fair dealing it owed to Fox as a third-party beneficiary of the
    contract between the Government and Lakeshore. Compl. ¶¶ 62-63. For the reasons discussed
    more fully below, this claim is derivative of Fox’s third-party beneficiary claim. Since the Court
    has STAYED consideration of the Government’s motion to dismiss the third-party beneficiary
    claim, it also STAYS consideration of the motion to dismiss Fox’s claim for breach of the implied
    duty of good faith and fair dealing.
    4
    are not enough. See 
    id. at 1341
    ; Glass, 
    258 F.3d at 1354
    . The Government’s intention to
    benefit a third party can be established by circumstantial evidence. G4S, 779 F. 3d at 1341.
    There is a thin line between a contract that directly benefits a third party and one
    that does not. This is especially true because “the government’s conduct should be
    evaluated in the context of its responsibility to protect the public interest.” Id. The cases
    that evaluate this issue often turn on fine distinctions, such as the method used to pay the
    third party. For instance, in D & H Distributing Co. v. United States, the Federal Circuit
    held that a subcontractor was a third-party beneficiary to a contract because the
    Government made payments into an account held jointly by the prime contractor and the
    subcontractor. 
    102 F.3d 542
    , 546-48 (Fed. Cir. 1996). Similarly, in J.G.B. Enters., Inc. v.
    United States, the Circuit held that the contract created a direct benefit because the
    Government’s “payments to the prime contractor were held in escrow for the third-party
    subcontractor.” 
    497 F.3d 1259
    , 1260, 1261 n.1 (Fed. Cir. 2007). In contrast, the Circuit
    found that there was no direct benefit in G4S Technology LLC v. United States, because
    in that case payment was made directly to the prime contractor’s general fund, even though
    the Government knew that the prime contractor owed subcontractors money for work done
    on the contract. 779 F.3d at 1342.
    The Federal Circuit’s decision in G4S illustrates how fact intensive the inquiry into
    whether a contract directly benefits a third party is. In that decision, the court considered
    each of the government’s public and private statements about the contract, as well as the
    specific details of how the subcontractor was paid. See id. at 1338-43. Only after
    considering the complete factual record before it did the Circuit conclude that the
    subcontractor, G4S, did not directly benefit from the contract because the Government did
    not “provide[] guarantees directly to G4S” or “arrange[] to pay G4S itself.” Id. at 1343.
    This Court, too, recognized the need to fully develop the factual record in G4S.
    Initially, the Government filed a motion to dismiss for lack of subject-matter jurisdiction,
    based on what it claimed was the lack of privity between itself and G4S. See G4S Tech.
    LLC v. United States, 
    114 Fed. Cl. 662
    , 668 (2014). Judge Firestone determined “that G4S
    had raised a non-frivolous claim,” and ruled that the Court had jurisdiction over the case if
    G4S was a third-party beneficiary of the contract between the Government and the prime
    contractor. See G4S, 779 F.3d at 1339-40; G4S, 114 Fed. Cl. at 668. Accordingly, she
    “ordered discovery on the limited issue of whether G4S could establish a contractual right
    to recovery against the United States.” G4S, 114 Fed. Cl. at 668.
    Judge Firestone’s reasoning is persuasive in this case. Like G4S, Fox raises non-
    frivolous claims in its complaint. It is undisputed that the Government was concerned
    about Lakeshore’s repeated failures to pay its contractors. See Dkt. 26-1 at 1. As counsel
    to Fox acknowledged during oral argument, the original contract between Lakeshore and
    the Government was not intended to directly benefit Fox or any other subcontractor.
    However, Fox argues that the Government modified its contract with Lakeshore in March
    5
    of 2014 with the intention of specifically benefitting Fox. Compl. ¶ 45. To support this
    contention, Fox cites Captain Ban’s February 7, 2014 memorandum to Lakeshore
    approving the creation of the holding account and specifying how the funds from the
    account were to be distributed. Id. ¶ 40. Fox claims that Captain Ban used this
    memorandum “to modify TO 42” with the “intent[] to protect and benefit Fox.” Id.
    Fox provides some objective evidence to support this claim. For instance, Mr.
    Habibi says that he relied “on the verbal and written statements of Contracing [sic]
    Officer’s Representatives Capt. Benjamin Knost, Maj. Karlo Jajliardo, Lt. Col. Greg Reich,
    and Lt. Col. Michael Greer,” who apparently told him that the Government “would take
    appropriate measures to directly pay Fox . . . thereby bypassing the cash flow problems
    Lakeshore [faced].” Dkt. 26-8 at 6. Major Jajliardo later sent Mr. Habibi another email,
    in which he asked for updated information on how much money Lakeshore owed Fox. Id.
    The Major “stress[ed] how importation this info [was],” and implied that it would be
    applied to “useful purposes.” Id.; see also Dkt. 26-9 at 47.
    Mr. Habibi understood these and other actions by the Government to indicate that it
    had assented to his demand that the Government control Lakeshore’s holding account
    before Fox would go back to work—that is, that the Government intended to directly
    benefit Fox. Dkt. 26-8 at 7-8; Dkt. 26-9 at 44, 52. Fox alleges throughout its complaint
    that Captain Ban was aware of and specifically authorized communications between Air
    Force officers and Fox. E.g., Compl. ¶¶ 23, 26, 37-38.
    The Government maintains that it never modified its contract with Lakeshore, and
    that if it did, it did not do so with the express intention of benefitting Fox. In support of
    this contention, the Government provided as Exhibit A to its motion to dismiss the
    declaration of Lara Schoenenberger, 2 a project manager for the Air Force who oversaw
    Lakeshore’s work on TO 42. See Dkt. 15-1 at ¶¶ 7, 10, 12. However, Ms. Schoenenberger
    was neither the contracting officer nor one of the Air Force officers that directly contacted
    Fox. She therefore is not able to deny that Captain Ban intended to directly benefit Fox or
    that Captain Ban was aware of and authorized the communications between the Air Force
    officers and Fox.
    It may well be that after the factual record is more fully developed, Fox is unable to
    demonstrate that it is a third-party beneficiary of the contract between Lakeshore and the
    Government. However, Fox has raised a non-frivolous claim that it is a third-party
    beneficiary and is entitled to additional discovery on this point. Therefore, the
    2
    In a motion filed with the Court on September 13, 2019, Fox moved to exclude eleven paragraphs
    of Ms. Schoenenberger’s declaration, or in the alternative for the Court to hold a hearing to
    supplement the evidentiary record before the Court ruled on the Government’s motion to dismiss.
    Dkt. 31 at 13-14. Given the Court’s decision to STAY consideration of the Government’s motion
    to dismiss until after the completion of jurisdictional discovery, Fox’s motion is DENIED as moot.
    6
    Government’s motion to dismiss Count One of Fox’s complaint is STAYED pending the
    completion of jurisdictional discovery.
    2. Implied-In-Fact Contract
    Implied-in-fact contracts with the Government are also difficult to prove. Implied-
    in-fact contracts are contracts inferred by a court when “the light of the surrounding
    circumstances” demonstrates a meeting of the minds between the parties, even if the
    agreement was never formalized. Turping v. United States, 
    913 F.3d 1060
    , 1065 (Fed. Cir.
    2019) (quoting Hanlin v. United States, 
    316 F.3d 1325
    , 1328 (Fed. Cir. 2003). In order to
    establish an implied-in-fact contract, the plaintiff must demonstrate the same elements
    needed for an express contract. 
    Id.
     Specifically, the plaintiff must prove “(1) mutuality of
    intent, (2) consideration, (3) an unambiguous offer and acceptance, and (4) ‘actual
    authority’ on the part of the Government’s representative to bind the Government in
    contract.” 
    Id.
     (quoting Hanlin, 
    316 F.3d at 1328
    ). Plaintiffs must prove “by objective
    evidence, the existence of an offer and a reciprocal acceptance” in order to show the
    “mutuality of intent” necessary for the formation of an implied-in-fact contract. 
    Id.
    As both parties have acknowledged, the Court must contemplate similar facts when
    considering Fox’s third-party beneficiary and implied-in-fact contract claims. See Compl.
    ¶ 49; Dkt. 15 at 21. As with its third-party beneficiary claim, Fox raises a non-frivolous
    claim that the contracting officer intended to enter into a contract with it.
    The Government asserts that Fox’s claim for breach of an implied-in-fact contract
    should be dismissed because Fox cannot show “mutuality of intent, an unambiguous offer
    and acceptance, or an exercise of actual authority on the part of . . . the contracting officer.”
    Dkt. 15 at 21. In contrast, Fox claims that Captain Ban’s February 7, 2014 memorandum
    to Lakeshore approving the creation of the holding account and specifying how the funds
    from the account were to be distributed created the implied-in-fact contract between the
    Government and Fox. The Government, Fox says, “manifested its intent to accept Fox’s
    offer to return to work in exchange for the [Government] . . . taking steps to protect and
    compensate Fox.” Compl. ¶ 56.
    Fox points to at least some objective evidence to support its claims. As discussed
    more fully above, Mr. Habibi says that he had extensive verbal and written communications
    with Contracting Officer’s Representatives who assured him that the Government was
    taking steps to ensure that Fox was paid for its work. Dkt. 26-8 at 6. Fox asserts that these
    communications were specifically authorized by Captain Ban, the Contracting Officer.
    Compl. ¶¶ 23, 26, 37-38. Fox has provided the Court with a number of emails that partially
    corroborate its version of events. The Government disputes Fox’s account, but ultimately
    it fails to fully refute it. Without sworn statements from Captain Ban or her Representatives
    specifically denying Fox’s assertion that Captain Ban intended to contract with Fox, the
    Court must take Fox’s allegations—supported by some evidence—as true.
    7
    On this claim, too, Fox may ultimately be unable to prove that the Court has
    jurisdiction. However, Fox has raised a non-frivolous claim that it had an implied-in-fact
    contract with the Government, and is entitled to more fully develop the factual record
    before the Court rules on the Government’s motion to dismiss. Therefore, the
    Government’s motion to dismiss Count Two of Fox’s complaint is STAYED pending the
    completion of jurisdictional discovery.
    3. Breach of the Implied Duty of Good Faith and Fair Dealing
    In its complaint, Fox also alleges a third claim for relief: that the Government
    breached the implied duty of good faith and fair dealing it owed to Fox as a third-party
    beneficiary of the contract between the Government and Lakeshore. Compl. ¶¶ 62-63. The
    Federal Circuit has held that “[e]very contract, including one with the federal government,
    imposes upon each party an implied duty of good faith and fair dealing in its performance
    and enforcement.” Dobyns v. United States, 
    915 F.3d 733
    , 739 (Fed. Cir. 2019). However,
    the implied duty “cannot expand a party’s contractual duties beyond those in the express
    contract.” 
    Id.
     (quoting Precision Pine & Timber, Inc. v. United States, 
    596 F.3d 817
    , 831
    (Fed. Cir. 2010)). Therefore, if Fox was not an intended third-party beneficiary of the
    contract between the Government and Lakeshore, it cannot recover for a breach of the
    implied duty of good faith and fair dealing. The Court has STAYED consideration of the
    Government’s motion to dismiss Fox’s third-party beneficiary claim, so it will not address
    whether Fox’s implied duty claim should be dismissed at this time.
    The Government’s motion to dismiss Count Three of Fox’s complaint is therefore
    also STAYED pending the completion of jurisdictional discovery.
    Conclusion
    For these reasons, the Government’s motion to dismiss is STAYED pending the
    completion of limited discovery on the issue of jurisdiction. Additionally, Fox’s motion to
    exclude portions of Ms. Schoenenberger’s declaration is DENIED as moot. The parties
    shall file a joint status report no later than Friday, October 11, 2019, proposing a schedule
    for jurisdictional discovery, and for supplemental briefing following the completion of
    discovery.
    IT IS SO ORDERED.
    s/ Thomas C. Wheeler
    THOMAS C. WHEELER
    Judge
    8