Pernix Group, Inc. v. United States , 2015 U.S. Claims LEXIS 729 ( 2015 )


Menu:
  •               In the United States Court of Federal Claims
    No. 15-420 C
    (June 10, 2015)1
    * * * * * * * * * * * * * * * *
    PERNIX GROUP, INC.                *
    *
    Plaintiff,           *
    *
    FRAMACO INTERNATIONAL,            *
    INC.,                             *
    *
    Intervenor-plaintiff, *                Bid Protest; Justiciability; Protest
    *                Is Not Ripe Where the Agency
    v.                       *                Has Yet to Take a Final Action
    *                Adverse to the Protestor.
    THE UNITED STATES,                *
    *
    Defendant,           *
    *
    CADDELL CONSTRUCTION              *
    COMPANY,                          *
    *
    Intervenor-defendant. *
    * * * * * * * * * * * * * * * *
    J. Randolph MacPherson, Washington, DC, for plaintiff. Rebecca Bailey
    Jacobsen, Washington, DC, of counsel.
    Jonathan D. Shaffer, Tysons Corner, VA, for intervenor-plaintiff. Mark E.
    Hanson and Mary Pat Buckenmeyer, Tysons Corner, VA, of counsel.
    1
    / This opinion was issued under seal on May 29, 2015. Pursuant to ¶ 5 of the ordering
    language, the parties were invited to identify source selection, proprietary or confidential material
    subject to deletion on the basis that the material was protected/privileged. No redactions were
    proposed by the parties. Thus, the sealed and public versions of this opinion are identical, except
    for the publication date and this footnote.
    Sosun Bae, United States Department of Justice, with whom were Benjamin
    C. Mizer, Principal Deputy Assistant Attorney General, Robert E. Kirschman, Jr.,
    Director, Deborah A. Bynum, Assistant Director, Washington, DC, for defendant.
    Dirk Haire, Washington, DC, for intervenor-defendant. Alexa Santora,
    Sonia Tabriz, P. Sean Milani-Nia, Washington, DC, of counsel.
    __________________________
    OPINION AND ORDER
    __________________________
    Bush, Senior Judge.
    This bid protest is before the court on defendant’s and intervenor-
    defendant’s motions to dismiss brought under Rule 12(b)(1) of the Rules of the
    United States Court of Federal Claims (RCFC). These motions have been fully
    briefed. For the reasons stated below, defendant’s and intervenor-defendant’s
    motions to dismiss are granted.
    BACKGROUND2
    I.     Introduction
    Plaintiff Pernix Group, Inc. (Pernix) filed its bid protest on April 27, 2015.
    The protest seeks declaratory and injunctive relief regarding the proper
    interpretation of 22 U.S.C. § 4852(c)(2)(E) (2012) in four procurements currently
    underway under the aegis of the United States Department of State (State).
    According to the complaint, the Government Accountability Office (GAO)
    recently issued a decision advising State to interpret § 4852 in a manner that
    would eliminate Pernix from consideration in these procurements. The primary
    question before the court is whether this protest is ripe, given that State has not yet
    acted, and has not indicated how it will act, in response to GAO’s decision.
    2
    / The facts upon which the parties rely are undisputed. The court makes no findings of
    fact in this opinion other than to determine whether plaintiff’s claims are justiciable.
    2
    Caddell Construction Company (Caddell) has intervened in this protest as
    an intervenor-defendant and Framaco International, Inc. (Framaco) has intervened
    as an intervenor-plaintiff. State’s official response to the GAO decision is not due
    until June 19, 2015. The government has agreed to stay award in the procurement
    which was the focus of the GAO protest through June 12, 2015. The court
    determined that oral argument on the ripeness issue was unnecessary.
    II.   GAO and this Court Have Disagreed on the Law Governing Embassy
    Construction Projects
    A.     The Governing Statute
    State procurements for embassy construction are subject to 22 U.S.C.
    § 4852 (2012), titled “Diplomatic construction program.” Where adequate
    competition exists, contractors must be either “United States persons” or
    “qualified United States joint venture persons” in order to be eligible for such
    construction contracts. 
    Id. § 4852(a).
    Only the statutory definition of “United
    States person” is relevant to this bid protest.
    More specifically, only one element or requirement of the definition of
    “United States person” is at issue here:
    (2) the term “United States person” means a person
    which –
    ....
    (E) with respect to a construction project under
    subsection (a)(1) of this section, has achieved total
    business volume equal to or greater than the value
    of the project being bid in 3 years of the 5-year
    period before the date [of the issuance of the
    solicitation.]
    22 U.S.C. § 4852(c)(2). Thus, under the plain meaning of the statutory terms, a
    minimum business volume threshold is established which screens out ineligible
    contractors. Since 2007, however, GAO and this court have diverged as to the
    proper formula to employ in determining the “total business volume” minimum
    threshold.
    3
    B.    GAO’s Interpretation of the Total Business Volume Requirement
    In March of 2007 Caddell filed a protest at GAO concerning the award of an
    embassy construction contract. Caddell Constr. Co., B-298949.2, 2007 CPD
    ¶ 119, 
    2007 WL 1893209
    , at *3 (Comp. Gen. June 15, 2007) (“Caddell I”). In that
    protest, Caddell challenged State’s “approach of adding together 3 years of a
    company’s business receipts” to determine the total business volume of an offeror.
    
    Id. at *8.
    In essence, State’s interpretation of the phrase “total business volume
    equal to or greater than the value of the project being bid in 3 years of the 5-year
    period before the date [of the issuance of the solicitation],” 22 U.S.C.
    § 4852(c)(2)(E), allowed a company to meet the minimum threshold by
    aggregating three years of business receipts. Caddell I, 
    2007 WL 1893209
    , at *8.
    This approach can be described as a “cumulative” total business volume formula.
    GAO agreed with Caddell that State’s cumulative total business volume
    formula was not correct and opined:
    We think the ordinary and common meaning of these
    words is that eligible offerors will have achieved a
    business volume equal to or greater than the value of the
    project in each of 3 years within the 5-year period.
    
    Id. at *9
    (emphasis added). Thus, GAO adopted an interpretation of total business
    volume that requires that the minimum threshold be met annually for three
    individual years, not cumulatively through aggregation. GAO’s formula can
    therefore be described as an “annual” total business volume formula. After giving
    consideration to other means of statutory interpretation beyond an analysis of the
    plain text, GAO concluded:
    [W]e think the agency’s interpretation of this provision –
    looking to an entity’s highest cumulative 3-year business
    volume within the previous 5-year period – conflicts
    with the [legislative history]. In short, we find that
    [State’s] interpretation of this statute is inconsistent with
    its ordinarily understood meaning, and with the
    legislative concerns that led to the statute’s enactment.
    4
    
    Id. at *10.
    C.      The United States Court of Federal Claims Disagrees with GAO
    and Adopts the Cumulative Total Business Volume Formula
    Another bid protest filed later that year with this court raised the same issue,
    i.e., whether the total business volume threshold must be met annually, or
    cumulatively, in three of the five years before the issuance of the solicitation.
    Grunley Walsh Int’l, LLC v. United States, 
    78 Fed. Cl. 35
    (2007). There, the
    protestor had been adversely affected by State’s decision to follow Caddell I and
    to adopt an annual total business volume threshold interpretation of
    § 4852(c)(2)(E). Grunley 
    Walsh, 78 Fed. Cl. at 38
    . The court observed that for
    pure questions of law this court accords no deference to GAO opinions, and noted
    that GAO decisions are not binding on this court. 
    Id. at 39
    (citations omitted).
    Like GAO, this court began its analysis with the plain text of the statute.
    Unlike GAO, the court reached this conclusion:
    The word “total” before the term “business volume”
    indicates that the requirement is met by adding three out
    of the past five years to equal the offeror’s “total
    business volume.” If the section is read without the
    word “total,” it is completely unclear whether the three
    years are to [be] measured individually or cumulatively.
    The inclusion of the word “total” modifies the term
    “volume” and informs the reader that the volume in
    question will be, as plaintiff states, “a product of
    addition.” Measuring the three years cumulatively gives
    meaning to the word “total” and avoids a construction
    that leaves language “superfluous, void, or
    insignificant.”
    
    Id. at 40
    (quoting Duncan v. Walker, 
    533 U.S. 167
    , 174 (2001)) (footnote
    omitted). After reviewing other potential aids to statutory construction, the court
    held that the “total business volume requirement is cumulative” and sustained the
    protest. 
    Id. at 43.
    5
    D.    GAO Comments in 2009 that the Annual Total Business Volume
    Formula in Caddell I, Not the Cumulative Total Business Volume
    Formula in Grunley Walsh, is Correct
    In 2009, GAO was confronted again with the total business volume question
    in another State Department embassy construction project protest. Caddell
    Constr. Co., B-401596, 2009 CPD ¶ 187, 
    2009 WL 3031273
    (Comp. Gen. Sept.
    21, 2009) (“Caddell II”). In that protest, which also involved two of the three
    offerors participating in this protest, Caddell, relying on Caddell I, suggested that
    Framaco should have been eliminated from the competition because, among other
    reasons, it did not meet the annual total business volume requirement (as opposed
    to the cumulative total business volume requirement). 
    Id. at *3.
    GAO did not
    base its decision in Caddell II on Framaco’s failure to meet the annual total
    business volume requirement, but relied instead on other defects in Framaco’s
    qualifications. 
    Id. at *4.
    State argued before GAO that it was following Grunley Walsh and applying
    the cumulative total business volume requirement, not the annual total business
    volume requirement applied by GAO in Caddell I. Caddell II, 
    2009 WL 3031273
    ,
    at *4. GAO observed that State “recognizes that our Office reached a different
    conclusion about the meaning of this statute, [but] it urges our Office to follow the
    court’s interpretation” of § 4852(c)(2)(E) in Grunley Walsh. 
    Id. GAO disagreed
    with this suggestion:
    Then and now, we think the ordinary and common
    meaning of the words in this statute is that eligible
    offerors will have achieved a business volume equal to
    or greater than the value of the project in each of 3 years
    within the 5-year period.
    
    Id. (citing Caddell
    I) (emphasis added). Nonetheless, avoiding direct conflict with
    this court’s interpretation of § 4852(c)(2)(E), GAO did not address State’s
    application of a cumulative total business volume requirement; instead, GAO
    sustained Caddell’s protest on other grounds. 
    Id. III. Protests
    of the Current Embassy Construction Procurement in Each
    Forum
    6
    A.      In 2014, Pernix and Framaco Satisfy the Cumulative Total
    Business Volume Formula and Are Prequalified for an Embassy
    Construction Contract Procurement
    Pernix and Framaco were recently judged by State to have satisfied the
    cumulative total business volume requirement in a competition for embassy
    construction in Maputo, Mozambique (the Maputo procurement). Compl. ¶¶ 14-
    15; Framaco Resp. at 4. As a result, they, along with Caddell and other offerors,
    were invited to participate in Phase II of the Maputo procurement. Compl. ¶ 17;
    Framaco Resp. at 5. In other words, these offerors had achieved “prequalification”
    for the Maputo procurement. The Prequalification Notice listing the companies
    selected to continue in the procurement was published on April 4, 2014. Compl.
    ¶ 17.
    B.      Caddell Protests the Prequalification of Pernix and Framaco at
    GAO
    Before Phase II proposals were submitted by the offerors in the Maputo
    procurement, Caddell filed a protest at GAO arguing that Pernix and Framaco
    should not have been prequalified, relying on the annual total business volume
    requirement articulated in Caddell I for one of its protest grounds. Caddell
    Constr. Co., B-411005.1, B-411005.2, 2015 CPD ¶ 132, 
    2015 WL 1874239
    (Comp. Gen. Apr. 20, 2015) (Caddell III). In its decision on that protest GAO
    noted the conflict between the Court of Federal Claims and GAO in interpreting
    the “total business volume” term of § 4852(c)(2)(E). Caddell III, 
    2015 WL 1874239
    , at *10. As in 2009, GAO found “no basis to revise our prior
    interpretation of the [law].” 
    Id. The reasons
    why GAO continues to interpret § 4852(c)(2)(E) differently
    than this court in Grunley Walsh are irrelevant to the current motions under
    review.3 By following Caddell I, GAO sustained Caddell’s challenge to
    3
    / This court, were it to reach the merits of Pernix’s protest, would be bound by neither
    Grunley Walsh nor Caddell III. Decisions in other cases before this court are not binding in this
    proceeding. See W. Coast Gen. Corp. v. Dalton, 
    39 F.3d 312
    , 315 (Fed. Cir. 1994) (“Court of
    Federal Claims decisions, while persuasive, do not set binding precedent for separate and distinct
    cases in that court.”) (citations omitted). Nor do GAO decisions create binding precedent for this
    (continued...)
    7
    Framaco’s prequalification, in part, because Framaco never achieved an annual
    total business volume of $160 million (the value of the Maputo construction
    project) although Framaco satisfied the cumulative total business volume formula.
    Caddell III, 
    2015 WL 1874239
    , at *13. GAO also sustained Caddell’s challenge
    to Pernix’s prequalification, for the sole reason that Pernix’s annual total business
    volume never reached $160 million, although Pernix, like Framaco, satisfied the
    cumulative total business volume formula. 
    Id. at *14-16.
    The GAO decision
    issued on April 20, 2015.
    C.     Pernix Files a Protest in this Court Concerning the Maputo
    Procurement and Three Others
    One week after GAO issued Caddell III, Pernix filed its bid protest in this
    court. Although State has taken no action in response to Caddell III, and has not
    publicly reacted to Caddell III, Pernix seeks an injunction and declaratory relief to
    forestall any action by State that would harm its competitive interests. Should
    State choose to follow the recommendation of GAO in Caddell III, Pernix would
    be excluded from the Maputo procurement – thus, Pernix seeks an injunction to
    preclude this occurrence. Compl. Count II, IV. Should State choose to follow the
    recommendation of GAO in Caddell III, Pernix would also lose any chance of
    winning contracts for State Department construction projects in three other
    locations: Matamoros, Mexico; Port Moresby, Papau New Guinea; and, Niamey,
    Niger. 
    Id. Count III-IV.
    Pernix seeks an injunction preventing those occurrences
    as well. 
    Id. Lastly, Pernix
    seeks declaratory relief regarding the proper
    interpretation of § 4852(c)(2)(E). 
    Id. Count I.
    D.     Motions to Dismiss
    Defendant and Caddell both argue that Pernix’s claims are not ripe, because
    State has not yet taken any action to revoke Pernix’s prequalification for the
    Maputo procurement. The government presents two additional arguments.
    According to one theory, Pernix lacks standing to bring this protest because it has
    3
    (...continued)
    court. See, e.g., Allied Tech. Grp., Inc. v. United States, 
    649 F.3d 1320
    , 1331 n.1 (Fed. Cir.
    2011) (stating that GAO decisions do not create binding precedent for the United States Court of
    Appeals for the Federal Circuit); XTRA Lease, Inc. v. United States, 
    50 Fed. Cl. 612
    , 618 (2001)
    (stating that “GAO decisions are not binding on this court”) (citation omitted).
    8
    not been prejudiced by any error committed by State. Def.’s Mot. at 7-8.
    According to another theory, even if Pernix’s protest of the Maputo procurement
    is deemed to be justiciable, Pernix should not be allowed to include the three other
    procurements in its protest. For this reason, the government argues that any of
    plaintiff’s claims related to procurements for construction in Matamoros, Port
    Moresby, and Niamey should be dismissed. 
    Id. at 8.
    The court reserves further
    discussion of these legal theories for the analysis section of this opinion.
    DISCUSSION
    I.    Standard of Review for a Ripeness Challenge to a Bid Protest
    Ripeness is a justiciability doctrine. See Fisher v. United States, 
    402 F.3d 1167
    , 1176 (Fed. Cir. 2005) (“Though justiciability has no precise definition or
    scope, doctrines of standing, mootness, ripeness and political question are within
    its ambit.”) (citations omitted). A 2009 decision of this court provided a succinct
    description of the ripeness doctrine and applied that doctrine to a bid protest in
    this court:
    The justiciability doctrine of ripeness
    circumscribes the court’s review to cases that present
    realized rather than anticipated or hypothetical injuries.
    United Public Workers of America v. Mitchell, 
    330 U.S. 75
    , 89-90, 
    67 S. Ct. 556
    , 
    91 L. Ed. 754
    (1947). A claim
    for relief is not ripe for adjudication when it rests upon
    “contingent future events that may not occur as
    anticipated, or indeed may not occur at all.” Thomas v.
    Union Carbide, 
    473 U.S. 568
    , 581, 
    105 S. Ct. 3325
    , 
    87 L. Ed. 2d 409
    (1985). When reviewing an administrative
    action, the court evaluates two factors: (1) “the fitness of
    the issues for judicial decision,” and (2) “the hardship to
    the parties of withholding court consideration.” Abbott
    Labs. v. Gardner, 
    387 U.S. 136
    , 149, 
    87 S. Ct. 1507
    , 
    18 L. Ed. 2d 681
    (1967), overruled on other grounds by
    Califano v. Sanders, 
    430 U.S. 99
    , 
    97 S. Ct. 980
    , 51 L.
    Ed. 2d 192 (1977). A challenge to an administrative
    action must satisfy both factors, under Abbott
    9
    Laboratories, in order to be ripe for judicial review.
    Cedars-Sinai Medical Ctr. v. Watkins, 
    11 F.3d 1573
    ,
    1581 (Fed. Cir. 1993). Under the first factor, “an agency
    decision is not ripe for judicial review until the allegedly
    offending agency has adopted a final decision.” NSK,
    Ltd. v. United States, 
    510 F.3d 1375
    , 1384 (Fed. Cir.
    2007) (emphasis added). In turn, an agency’s decision is
    final, for the purposes of ripeness, only if it (1) “marks
    ‘the consummation of the agency’s decision-making
    process,’ i.e., it must not be merely tentative or
    interlocutory, and (2) ‘the action [is] one by which rights
    or obligations have been determined, or from which legal
    consequences will flow.’” 
    Id. at 1385
    (quoting Bennett
    v. Spear, 
    520 U.S. 154
    , 177, 
    117 S. Ct. 1154
    , 
    137 L. Ed. 2d
    281 (1997)).
    Madison Servs., Inc. v. United States, 
    90 Fed. Cl. 673
    , 678 (2009).
    The basic analytical framework presented in Madison Services is the same
    as the ripeness framework recently discussed by the United States Court of
    Appeals for the Federal Circuit.4 The Federal Circuit decision most on point,
    because of its articulation of a ripeness standard applicable to bid protests in this
    court, is Systems Application & Technologies, Inc. v. United States, 
    691 F.3d 1374
    (Fed. Cir. 2012) (SA-TECH). This precedential statement of the ripeness doctrine
    is very similar to the discussion of the doctrine presented in Madison Services:
    4
    / Because Madison Services cleaves to binding precedent of the Federal Circuit, the
    court finds the ripeness analysis in Madison Services to be far more persuasive than the ripeness
    analysis in CBY Design Builders v. United States, 
    105 Fed. Cl. 303
    (2012), a case relied upon by
    both Pernix and Framaco. The CBY Design opinion doubted whether some of the cases relied
    upon in Madison Services, such as Bennett v. Spear, 
    520 U.S. 154
    (1997), Tokyo Kikai
    Seisakusho, Ltd. v. United States, 
    529 F.3d 1352
    (Fed. Cir. 2008), and U.S. Ass’n of Imps. of
    Textiles & Apparel v. U.S. Dep’t of Commerce, 
    413 F.3d 1344
    (Fed. Cir. 2005), had “much, if
    any relevance to the question of whether a bid protest is 
    ripe.” 105 Fed. Cl. at 332
    . Yet these
    opinions, cited approvingly in Madison Services and questioned as potentially irrelevant in CBY
    Design, provide the foundational law for the Federal Circuit’s subsequent application of the
    ripeness doctrine to a bid protest. Sys. Application & Techs., Inc. v. United States, 
    691 F.3d 1374
    , 1384 (Fed. Cir. 2012).
    10
    A claim is not ripe for judicial review when it is
    contingent upon future events that may or may not occur.
    Thomas v. Union Carbide Agric. Prods. Co., 
    473 U.S. 568
    , 580-81, 
    105 S. Ct. 3325
    , 
    87 L. Ed. 2d 409
    (1985).
    The purpose of the doctrine is to prevent the courts,
    “through avoidance of premature adjudication, from
    entangling themselves in abstract disagreements over
    administrative policies, and also to protect the agencies
    from judicial interference until an administrative
    decision has been formalized and its effects felt in a
    concrete way by the challenging parties.” Abbott Labs.
    v. Gardner, 
    387 U.S. 136
    , 148-49, 
    87 S. Ct. 1507
    , 18 L.
    Ed. 2d 681 (1967), overruled on other grounds by
    Califano v. Sanders, 
    430 U.S. 99
    , 
    97 S. Ct. 980
    , 51 L.
    Ed. 2d 192 (1977). In assessing ripeness, there are two
    basic factors: “(1) the fitness of the issues for judicial
    decision[;] and (2) the hardship to the parties of
    withholding court consideration.” Abbott 
    Labs., 387 U.S. at 149
    , 
    87 S. Ct. 1507
    .
    When a party challenges government action, the
    first factor becomes a question of whether the challenged
    conduct constitutes a final agency action. See Tokyo
    Kikai Seisakusho, Ltd. v. United States, 
    529 F.3d 1352
    ,
    1363 (Fed. Cir. 2008); U.S. Ass’n of Imps. of Textiles &
    Apparel v. U.S. Dep’t of Commerce, 
    413 F.3d 1344
    ,
    1349-50 (Fed. Cir. 2005) [(Textile Importers)]. Final
    agency action hinges on two points: “First, the action
    must mark the ‘consummation’ of the agency’s
    decision-making process – it must not be of a merely
    tentative or interlocutory nature. And second, the action
    must be one by which ‘rights or obligations have been
    determined,’ or from which ‘legal consequences will
    flow.’” Bennett v. Spear, 
    520 U.S. 154
    , 177-78, 117 S.
    Ct. 1154, 
    137 L. Ed. 2d
    281 (1997) (citations omitted).
    
    SA-TECH, 691 F.3d at 1383-84
    . It is the “final agency action” or “fitness” prong
    11
    of the ripeness analysis which courts typically examine first.5
    Next, to satisfy the hardship prong of the ripeness analysis, the government
    action’s impact upon a plaintiff must be “sufficiently direct and immediate.”
    Abbott 
    Laboratories, 387 U.S. at 152
    . Abstract, avoidable or speculative harm is
    not enough to satisfy the hardship prong. E.g., Texas v. United States, 
    523 U.S. 296
    , 301-02 (1998). Being forced to wait for an agency to issue a decision is
    generally not enough to satisfy the hardship prong; the Federal Circuit has stated
    that “any business uncertainty associated with awaiting a final decision from an
    agency is different in kind and legal effect from the hardship identified in Abbott
    Laboratories and insufficient to turn a threshold agency decision into a final
    agency action ripe for review.” Textile 
    Importers, 413 F.3d at 1350
    . In the bid
    protest context, there is no measurable hardship, at the time of the protest, flowing
    from a future, hypothetical agency decision adverse to the protestor. See Texas
    Bio- & Agro-Defense Consortium v. United States, 
    87 Fed. Cl. 798
    , 806 (2009)
    (dismissing a protest on ripeness grounds and finding no hardship to the protestor
    because “these [lost business opportunities] are not hardships that would stem
    from a dismissal without prejudice [of this protest] on ripeness grounds – they are
    hardships which would be suffered if Plaintiff’s proposed site is not ultimately
    selected”) (emphasis added).
    Justiciability challenges focusing on ripeness are often brought under RCFC
    12(b)(1), as is the case here. Justiciability, however, is not the same as subject
    matter jurisdiction; ripeness and justiciability might best be described as limits on
    the exercise of jurisdiction. See Madison 
    Services, 90 Fed. Cl. at 680
    n.3
    (disagreeing with the government’s “characterization of either ripeness or
    mootness as a per se limit on the court’s jurisdiction[,]” noting “lingering
    uncertainty as to whether, and when, ripeness or mootness may operate as a limit
    upon the jurisdiction of a federal court”) (citations omitted). In its most recent
    pronouncement on this issue, the Federal Circuit distinguished between
    5
    / If it is determined that there is no final agency action to protest, the hardship prong
    appears to be of lesser importance and is sometimes omitted entirely from the court’s discussion
    of ripeness. See, e.g., Madison 
    Services, 90 Fed. Cl. at 679-80
    (dismissing a protest on ripeness
    grounds without considering hardship to the protestor, because there was no final agency action
    to protest); see also NSK Ltd. v. United States, 
    510 F.3d 1375
    , 1385 (Fed. Cir. 2007) (affirming
    the dismissal of a claim as unripe solely because the agency action was not final, without
    discussing hardship to the claimant).
    12
    justiciability (in the sense of ripeness in particular) and subject matter jurisdiction.
    See, e.g., Shinnecock Indian Nation v. United States, 
    782 F.3d 1345
    , 1348-52
    (Fed. Cir. 2015) (treating these two threshold inquiries as to whether a complaint
    should be dismissed as distinct). But see Morris v. United States, 
    392 F.3d 1372
    ,
    1375 (Fed. Cir. 2004) (stating that the Court of Federal Claims “does not have
    jurisdiction over [takings] claims that are not ripe” (citing Howard W. Heck &
    Assocs., Inc. v. United States, 
    134 F.3d 1468
    (Fed. Cir. 1998)). Nonetheless, it is
    clear that an unripe claim, like a claim outside this court’s jurisdictional ambit,
    must be dismissed without prejudice. Shinnecock Indian 
    Nation, 782 F.3d at 1350
    (citations omitted).
    II.    Analysis
    A.     Ripeness
    1.      No Final Agency Action
    There is no final action of State that is the subject of plaintiff’s requests for
    relief in the complaint. Instead, up to this point, State has simply applied the
    cumulative total business volume formula, as did this court in Grunley Walsh, and
    has prequalified both Pernix and Framaco for the Maputo procurement.6 Compl.
    ¶¶ 14-15, 17; Framaco Resp. at 4. That action, which favors plaintiff, is not being
    attacked in this lawsuit. Until and if State changes its position on the eligibility of
    Pernix for the Maputo procurement pursuant to the advice provided by GAO in
    Caddell III there is no final agency action that is ripe for review in this court.7 See
    Madison 
    Services, 90 Fed. Cl. at 679
    (“[P]laintiff’s original protest has never been
    ripe for the court’s review, because no final agency decision [regarding] the
    solicitation has ever been before the court.”).
    Framaco concedes that Pernix’s request for injunctive relief stated in the
    complaint is not ripe, but attempts to distinguish that request from Pernix’s request
    6
    / Indeed, except for a brief period between GAO’s issuance of Caddell I and this court’s
    issuance of Grunley Walsh, State appears, on this record, to have consistently preferred the
    cumulative total business volume interpretation of § 4852(c)(2)(E).
    7
    / As Caddell correctly emphasizes, this court has no jurisdiction to review GAO
    decisions such as Caddell III. Caddell Reply at 2 (citations omitted).
    13
    for declaratory relief regarding the proper interpretation of § 4852(c)(2)(E). The
    proposition advanced by Framaco is innovative but entirely unsupported by
    persuasive authority8:
    The Pernix request for injunctive relief is premature
    because the United States Department of State (“State”)
    has not decided whether to follow the Government
    Accountability Office (“GAO”) recommendation and
    Pernix and Framaco currently remain prequalified for the
    Maputo, Mozambique procurement . . . . On the other
    hand, in light of the sharp disagreement between GAO
    and this Court on a critical legal issue regarding
    prequalification that impacts numerous State
    procurements in a manner that materially prejudices and
    harms Pernix, Framaco and similarly situated offerors,
    Pernix’s request for declaratory judgment is ripe for
    consideration by the Court.
    Framaco Resp. at 1-2. The court finds no distinction, however, between requests
    for declaratory or injunctive relief in determining the ripeness of this bid protest.
    The test for ripeness stated in Abbott Laboratories and SA-TECH applies to
    requests for declaratory judgments as well as to requests for injunctive relief. See
    Abbott 
    Laboratories, 387 U.S. at 138
    (reviewing the ripeness of an action
    requesting both declaratory and injunctive relief). The court notes that the
    underlying bid protest in SA-TECH requested both declaratory and injunctive
    relief, but this court chose to offer only injunctive relief because the two types of
    relief would provide the same functional relief to the protestor. See Sys.
    Application & Techs., Inc. v. United States, 
    100 Fed. Cl. 687
    , 720 (2011)
    (“Because the practical effect of this requested [declaratory] relief is to prevent the
    Army from taking the proposed corrective action, it is ‘tantamount to a request for
    injunctive relief.’ Thus, the court will limit its discussion to SA-TECH’s request
    for the entry of a permanent injunction prohibiting the Army from undertaking its
    8
    / Framaco relies on CBY Design for its ripeness analysis. Framaco Resp. at 7. As stated
    previously, the ripeness analysis presented in CBY Design diverges from Federal Circuit
    precedent and is unhelpful here. See supra note 4.
    14
    proposed corrective action.” (quoting PGBA, LLC v. United States, 
    389 F.3d 1219
    ,
    1228 (Fed. Cir. 2004))). Because the two forms of relief are functionally
    indistinguishable in this type of bid protest, e.g., 
    PGBA, 389 F.3d at 1228
    , Pernix
    cannot present an unripe claim for injunctive relief but simultaneously present a
    ripe claim for declaratory relief. Pernix’s request for declaratory relief, like its
    request for injunctive relief, has no final agency action at its base and must be
    dismissed as unripe.
    Only one other issue raised by the parties merits discussion in the court’s
    review of the “fitness” prong of the ripeness analysis. Plaintiff relies on two
    Federal Circuit opinions which discuss the breadth of this court’s bid protest
    jurisdiction in an effort to show that its protest is ripe. See Pl.’s Resp. at 5 (citing
    Distributed Solutions, Inc. v. United States, 
    539 F.3d 1340
    (Fed. Cir. 2008);
    RAMCOR Servs. Grp., Inc. v. United States, 
    185 F.3d 1286
    (Fed. Cir. 1999)).
    Neither of those opinions addressed the ripeness doctrine, and further, as
    defendant points out, the bid protest scenarios in RAMCOR and Distributed are
    readily distinguishable from the procurements at issue here. See Def.’s Reply at
    1-2 (“But plaintiff fails to note the key distinction between those cases and the
    present action, which is that, in both of the cited cases, the Federal Circuit
    contemplated jurisdiction over actual decisions and alleged violations by the
    Government, not hypothetical ones.”) (citations omitted). There is no aid for
    Pernix’s ripeness contentions in either of these Federal Circuit opinions.
    For all of the above-stated reasons, the court finds that Pernix’s protest is
    not fit for adjudication because there is no final agency action for this court to
    review. This finding is strong evidence that this protest is not ripe and is not
    justiciable. See supra note 5. The court turns to the second ripeness factor, the
    hardship prong, to confirm that dismissal of this protest without prejudice is
    warranted.
    2.     No Hardship at This Juncture
    According to plaintiff, participation in Phase I and Phase II of an embassy
    construction contract procurement “requires prospective and actual offerors to
    incur substantial costs.” Pl.’s Resp. at 3. There appears to be no dispute that
    Pernix has invested heavily in the competitions at issue in this suit, and that
    uncertainty regarding the eligibility of Pernix for the Maputo procurement, and
    15
    uncertainty regarding its eligibility for the other State procurements noted in the
    complaint, has an impact on the company. See 
    id. Ex. 1
    ¶ 6 (“The lack of clarity
    regarding the legal standard for how to qualify contractors under the ‘total
    business volume’ requirement is significantly impacting our company’s resources,
    and will continue to do so until a final interpretation of the [statute] is achieved.”).
    The parties dispute, however, whether the costs of such uncertainty satisfy the
    hardship prong of the ripeness analysis. Compare Framaco Resp. at 8 (stating that
    the “substantial harm” to Pernix shows that “the second factor, hardship,
    overwhelmingly weighs in favor of ripeness”) and Pl.’s Resp. at 9 (“With respect
    to the ‘hardship prong’ of the ripeness inquiry, the facts . . . show that it would be
    the Court’s failure to act that would create hardship.”), with Def.’s Reply at 3-4
    (“[A]lthough Pernix and Framaco assert hardship and injury to bolster their
    arguments of both ripeness and standing, all such hardship or injury is speculative
    and contingent upon State’s acceptance of the GAO’s recommendation, an action
    that has not occurred yet and may not occur at all. . . . [B]ecause State could
    decide to reject the GAO’s recommendation and keep Pernix and Framaco as
    qualified participants, Pernix and Framaco cannot reasonably claim that they have
    already been injured . . . .”) and Caddell Mot. at 4 (“In essence, Pernix has not
    been harmed and shows no probability that it will be imminently harmed.”).
    As noted earlier in this opinion, the ripeness doctrine protects “agencies
    from judicial interference until an administrative decision has been formalized and
    its effects [are] felt in a concrete way by the challenging parties.” Abbott
    
    Laboratories, 387 U.S. at 148-49
    . In the dispute discussed in Abbott
    Laboratories, the issue was ripe because the Commissioner of Food and Drugs
    had construed a statute in a manner adverse to the plaintiffs, whereas here, State
    has not yet acted to construe § 4852(c)(2)(E) in a manner adverse to Pernix.
    Pernix has not yet “felt [the effects of a final agency action] in a concrete way.”
    Abbott 
    Laboratories, 387 U.S. at 148
    . Nor has Pernix suffered “sufficiently direct
    and immediate” effects of any final agency action. 
    Id. at 152.
    Under Abbott
    Laboratories, Pernix has not satisfied the hardship prong of the ripeness analysis.
    The general rule is that the hardship prong of the ripeness test cannot be
    satisfied by contingent or speculative harm. Texas v. United 
    States, 523 U.S. at 301-02
    ; Texas Bio- & 
    Agro-Defense, 87 Fed. Cl. at 806
    . As defendant notes, this
    rule prevents courts from issuing advisory opinions on abstract legal questions.
    See Def.’s Mot. at 6 (citing cases); Def.’s Reply at 2-3 (same). Here, any hardship
    16
    to Pernix flowing from Caddell III is still speculative and contingent, and the
    hardship prong of the ripeness inquiry under Texas v. United States is not
    satisfied.
    A similar result is obtained when this case is compared to Federal Circuit
    precedent. In SA-TECH, the decision most on point, the hardship prong of the
    ripeness inquiry was satisfied because the United States Army had made a final
    decision affecting SA-TECH’s competitive advantages in an ongoing
    procurement:
    With respect to the hardship element of the ripeness
    analysis, the Army asserts that SA-TECH has not
    suffered a hardship because the “announced intention to
    implement corrective action is an intermediate step of a
    single procurement process, and the continuation of that
    process, while SA-TECH remains in contention, is not a
    hardship.” Appellant’s Br. 26. As discussed above, this
    approach ignores the competitive hardships SA-TECH
    suffers as a result of the Army’s arbitrary decision to
    recompete the 
    contract. 691 F.3d at 1385
    . Thus, in SA-TECH, the Army had committed to a decision
    adverse to the protestor, whereas here, State has made no such commitment.
    Under SA-TECH, Pernix has not satisfied the hardship prong of the ripeness
    analysis.
    Finally, the court finds Textile Importers to be instructive. At issue there
    was the government’s decision to consider twelve petitions from domestic textile
    producers requesting that the United States consult with China about certain
    textile imports, a course of action which might have led to import restrictions
    against those Chinese imports. A suit filed by an association of textile importers
    to enjoin the consideration of those twelve petitions was found to be unripe. The
    Federal Circuit provided this analysis focusing on the hardship prong of the
    ripeness inquiry:
    In this case, the Association cites a number of actions
    taken by its members allegedly in response just to [the
    17
    government’s] decision to consider the twelve petitions.
    These actions were based on the businesses’ perceived
    uncertainty concerning whether, when, and to what
    extent import relief might be imposed in the future, but
    not on any legally binding requirement presently
    imposed by . . . the government. In contrast, Abbott
    Laboratories involved a mandatory regulation with
    binding legal effect that was issued after formal notice
    and comment and that was utterly unambiguous. Thus,
    following [Federal Trade Commission v. Standard Oil
    Co. of California, 
    449 U.S. 232
    (1980)], we hold that
    any business uncertainty associated with awaiting a final
    decision from an agency is different in kind and legal
    effect from the hardship identified in Abbott
    Laboratories and insufficient to turn a threshold agency
    decision into a final agency action ripe for review.
    Textile 
    Importers, 413 F.3d at 1350
    . Here, there is no “legally binding
    requirement” issued by State that harms Pernix – under Textile Importers, Pernix
    has not satisfied the hardship prong of the ripeness inquiry. 
    Id. As in
    Textile
    Importers, “any business uncertainty associated with awaiting a final decision
    from an agency is different in kind and legal effect from the hardship identified in
    Abbott Laboratories and insufficient” to establish ripeness. 
    Id. At this
    juncture,
    there is no hardship to Pernix so as to render this bid protest ripe and justiciable.
    B.     Standing
    Both the government and Caddell assert that plaintiff lacks standing to bring
    this protest. Def.’s Mot. at 7-8 & n.1; Def.’s Reply at 3-4; Caddell Reply at 6-8.
    Having considered the precedential Federal Circuit decisions relied upon by the
    parties, the court is not convinced that the facts in the bid protests underlying
    those decisions are sufficiently analogous to this case. The court therefore
    declines to extend various Federal Circuit pronouncements on bid protest standing
    to the somewhat unusual circumstances of this case.
    Here, Pernix’s protest challenges a hypothetical elimination from
    competition that has not yet occurred. That challenge is clearly barred on ripeness
    18
    grounds. The court therefore sees no reason to reach or address the parties’ rather
    convoluted arguments regarding Pernix’s standing to bring its unripe protest. See,
    e.g., Sinochem Int’l Co. v. Malaysia Int’l Shipping Corp., 
    549 U.S. 422
    , 431
    (2007) (“[A] federal court has leeway to choose among threshold grounds for
    denying audience to a case on the merits.”) (citations and internal quotations
    omitted); Shinnecock Indian 
    Nation, 782 F.3d at 1353
    (affirming this court’s
    dismissal of a suit on ripeness grounds but vacating this court’s alternative holding
    that the suit should also be dismissed for lack of subject matter jurisdiction).
    C.     Multiple Procurement Protest
    Because Pernix’s bid protest is not ripe, the threshold issue of justiciability
    requires dismissal of this suit. The court therefore need not address defendant’s
    and Caddell’s alternative argument that four procurements cannot be addressed in
    a single protest. The court notes, however, that there have been instances in which
    this court has considered challenges to multiple procurements within a single
    protest. E.g., Bannum, Inc. v. United States, 
    60 Fed. Cl. 718
    , 722 & n.6 (2004);
    MCS Mgmt., Inc. v. United States, 
    48 Fed. Cl. 506
    , 509 (2001).
    CONCLUSION
    For the foregoing reasons, it is hereby ORDERED that:
    (1)    Defendant’s Motion to Dismiss, filed May 5, 2015, is GRANTED;
    (2)    Intervenor-Defendant Caddell’s Motion to Dismiss, filed May 5,
    2015, is GRANTED;
    (3)    Plaintiff Pernix’s Motion for Declaratory Judgment, and Preliminary
    and Permanent Injunction, filed April 27, 2015, is DENIED as moot;
    (4)    The Clerk’s Office is directed to ENTER final judgment in favor of
    defendant and intervenor-defendant, DISMISSING the complaint
    without prejudice;
    (5)    On or before June 10, 2015, counsel for the parties shall CONFER
    and FILE with the Clerk’s Office a redacted copy of this opinion,
    19
    with any material deemed proprietary marked out and enclosed in
    brackets, so that a copy of the opinion can then be prepared and made
    available in the public record of this matter; and
    (6)   Each party shall bear its own costs.
    /s/Lynn J. Bush
    LYNN J. BUSH
    Senior Judge
    20
    

Document Info

Docket Number: 15-420 C

Citation Numbers: 121 Fed. Cl. 592, 2015 U.S. Claims LEXIS 729, 2015 WL 3616114

Judges: Lynn J. Bush

Filed Date: 6/10/2015

Precedential Status: Precedential

Modified Date: 10/19/2024

Authorities (18)

Califano v. Sanders , 97 S. Ct. 980 ( 1977 )

Texas v. United States , 118 S. Ct. 1257 ( 1998 )

Sinochem International Co. v. Malaysia International ... , 127 S. Ct. 1184 ( 2007 )

Pgba, LLC v. United States, and Wisconsin Physicians ... , 389 F.3d 1219 ( 2004 )

Thomas v. Union Carbide Agricultural Products Co. , 105 S. Ct. 3325 ( 1985 )

Bennett v. Spear , 117 S. Ct. 1154 ( 1997 )

Nsk Ltd. v. United States , 510 F.3d 1375 ( 2007 )

West Coast General Corporation v. John H. Dalton, Secretary ... , 39 F.3d 312 ( 1994 )

Howard W. Heck, and Associates, Inc. v. United States , 134 F.3d 1468 ( 1998 )

Ramcor Services Group, Inc. v. United States , 185 F.3d 1286 ( 1999 )

Robert E. Morris and Carol L. Morris v. United States , 392 F.3d 1372 ( 2004 )

cedars-sinai-medical-center-warren-s-grundfest-md-james-s-forrester , 11 F.3d 1573 ( 1993 )

Distributed Solutions, Inc. v. United States , 539 F.3d 1340 ( 2008 )

Tokyo Kikai Seisakusho, Ltd. v. United States , 529 F.3d 1352 ( 2008 )

Duncan v. Walker , 121 S. Ct. 2120 ( 2001 )

Abbott Laboratories v. Gardner , 87 S. Ct. 1507 ( 1967 )

Federal Trade Commission v. Standard Oil Co. , 101 S. Ct. 488 ( 1980 )

U.S. Ass'n of Importers of Textiles & Apparel v. United ... , 413 F.3d 1344 ( 2005 )

View All Authorities »