Rudolph and Sletten, Inc. v. United States , 120 Fed. Cl. 137 ( 2015 )


Menu:
  •          In the United States Court of Federal Claims
    No. 14-647C
    (Filed: February 23, 2015)
    )
    RUDOLPH AND SLETTEN, INC., )
    )                 Contract Disputes Act (CDA), 41
    Plaintiff,   )                 U.S.C. §§ 7101-09; Motion to
    )                 Dismiss, Rule 12(b)(1); Motion for
    v.                         )                 Summary Judgment, Rule 56;
    )                 Motion Remand to the Contracting
    THE UNITED STATES,         )                 Officer, 41 U.S.C. § 7103(f)(5);
    )                 Deemed Denial of a Claim.
    Defendant.   )
    )
    Nomi L. Castle, Matthew J. Luce, Marian K. Selvaggio, Castle &
    Associates, Beverly Hills, California, for plaintiff.
    A. Bondurant Eley, Trial Attorney, Joyce F. Branda, Acting Assistant
    Attorney General, Robert E. Kirschman, Jr., Director, Steven J. Gillingham,
    Assistant Director, Commercial Litigation Branch, Civil Division, United States
    Department of Justice, Washington, D.C., for defendant.
    MEMORANDUM OPINION AND ORDER
    I.    INTRODUCTION
    Plaintiff, Rudolph and Sletten, Inc. (“R&S”), brought this action pursuant to
    the Contract Disputes Act of 1978, 41 U.S.C. §§ 7101–09 (“CDA”). The
    government moved to dismiss R&S’s complaint, or alternatively for summary
    judgment, for lack of subject-matter jurisdiction pursuant to Rules 12(b)(1) and 56
    of the Rules of the United States Court of Federal Claims (“RCFC”), arguing that
    there has been neither an actual nor a deemed final decision by the contracting
    officer. In the alternative, the government moves for remand of the case to the
    contracting officer for a final decision. For the reasons set forth below, the
    government’s motion to dismiss, or alternatively for summary judgment, is
    DENIED. The government’s motion in the alternative for remand of this case to
    the contracting officer for a final decision is GRANTED.
    -1-
    II.    FACTUAL AND PROCEDURAL BACKGROUND1
    The dispute in this case arises out of a government contract awarded to R&S
    to build the Southwest Fisheries Science Center Replacement Headquarters and
    Laboratory in La Jolla, California (“La Jolla Laboratory”).
    On May 3, 2010, the United States Department of Commerce, National
    Oceanic and Atmospheric Administration (“NOAA”), awarded R&S Contract No.
    AB1330-10-CN-0114 to construct the La Jolla Laboratory. Compl. at Ex. A.
    On August 20, 2013, R&S submitted a certified claim (“Claim 1”) to
    NOAA’s contracting officer (“the contracting officer”) seeking a compensable
    contract time extension and $26,809,003 as compensation for costs due to alleged
    government-caused delay and disruption, additional consultant costs, and extra
    work undertaken by R&S and its subcontractors. Compl. at Ex. B. NOAA
    received R&S’s certified claim on August 23, 2013. Compl. at Ex. C.
    On October 21, 2013, the contracting officer wrote to R&S advising that:
    In accordance with FAR 52.233-1(e), the Contracting Officer’s final
    decision, or a date by which a decision will be made, must be
    provided to your firm. Due to the complexity and extensive nature of
    your claim, we anticipate a final Contracting Officer’s decision to be
    issued 9 months from the date of this letter.
    App. to Def. Mot. at 19.
    On October 30, 2013, R&S submitted a second certified claim (“Claim 2”)
    to the contracting officer. App. to Def. Mot. at 1-18. This claim sought an
    additional $2,600,861 for delay-related costs and unresolved Requests for Contract
    Modifications. App. to Def. Mot. at 7.
    On November 4, 2013, R&S wrote to the contracting officer acknowledging
    receipt of the October 21, 2013 letter, but stating that the nine-month extension to
    review Claim 1 was excessive and unreasonable. App. to Def. Mot. at 20. In
    addition, R&S requested either a detailed explanation for the delay or a work plan.
    1
    The facts recounted in this Memorandum Opinion and Order are taken from the plaintiff’s
    complaint cited in this Memorandum Opinion and Order as (“Compl. at ___”), the defendant’s
    dispositive motion (“Def. Mot. at __”), plaintiff’s opposition thereto (“Pl. Opp. at __”),
    defendant’s reply (“Def. Rep. at __”), and the appendices to the parties’ submissions (“App. to
    ___”). Except where otherwise noted, the facts recited here are undisputed.
    -2-
    
    Id. The contracting
    officer responded on November 8, 2013, explaining the reason
    for the nine-month delay and providing R&S with a timeline for reaching a final
    decision on Claim 1 by July 15, 2014. App. to Def. Mot. at 21-22.
    On January 6, 2014, R&S filed its first lawsuit arising under the La Jolla
    contract. Rudolph & Sletten, Inc. v. United States, No. 14-14C (Fed. Cl. Jan. 6,
    2014) (“R&S I”). On May 6, 2014, the government filed a dispositive motion in
    R&S I. That motion is fully briefed and is separately pending before the Court.
    On July 8, 2014, the contracting officer informed R&S that a final decision
    on Claim 1 would not be reached by July 15, 2014 as originally estimated by the
    government, and that, instead, a final decision would be forthcoming on March 15,
    2015. App. to Def. Mot. at 40-41. The contracting officer also provided R&S with
    the following schedule for the resolution of Claim 1:
    July 31, 2014:       Approximately 35 PCOs Requiring a
    Technical Merit Letter;
    August 31, 2014:     Approximately 35 PCOs reassessing
    previously issued unilateral modifications
    and directives;
    October 15, 2014:    Approximately 35 PCOs reassessing
    previously issued unilateral modifications
    and directives;
    November 15,         Approximately 35 PCOs reassessing
    2014:                previously issued unilateral modifications
    and directive;
    January 15, 2015:    Approximately 35 PCOs pending
    evaluation;
    February 27,         Approximately 25 PCOs pending
    2015:                evaluation.
    App. to Def. Mot. at 41. R&S filed the present action regarding Claim 1 on
    July 23, 2014.
    The government moves to dismiss this case, or alternatively for summary
    judgment, for lack of jurisdiction, arguing that R&S failed to obtain a final
    decision from the contracting officer before filing its complaint. See generally
    Def. Mot. Alternatively, the government requests that the Court stay and remand
    this case to the contracting officer for a final decision, pursuant to 41 U.S.C. §
    7103(f)(5). 
    Id. at 19.
    -3-
    III.   ANALYSIS
    A.    Legal Standards
    Whether this Court possesses jurisdiction to decide the merits of a case is a
    threshold matter. Copar Pumice Co., Inc. v. United States, 
    112 Fed. Cl. 515
    , 527
    (2013) (citing PODS, Inc. v. Porta Stor, Inc., 
    484 F.3d 1359
    , 1364 (Fed. Cir.
    2007)); Steel Co. v. Citizens for a Better Env’t, 
    523 U.S. 83
    , 94–95 (1998).
    Deciding a motion to dismiss “starts with the complaint, which must be well-
    pleaded in that it must state the necessary elements of the plaintiff’s claim,
    independent of any defense that may be interposed.” Holley v. United States, 
    124 F.3d 1462
    , 1465 (Fed. Cir. 1997). As a case cannot proceed if a court lacks
    jurisdiction to hear it, the plaintiff bears the burden of establishing subject-matter
    jurisdiction and must do so by a preponderance of the evidence. Arbaugh v. Y & H
    Corp., 
    546 U.S. 500
    , 514 (2006); M. Maropakis Carpentry, Inc. v. United States,
    
    609 F.3d 1323
    , 1327 (Fed. Cir. 2010) (citing Reynolds v. Army & Air Force Exch.
    Serv., 
    846 F.2d 746
    , 748 (Fed. Cir. 1988)).
    If the Court finds it lacks subject-matter jurisdiction, it must dismiss the
    complaint. 
    Arbaugh, 546 U.S. at 514
    . In considering a motion to dismiss for lack
    of jurisdiction, the Court must “view the alleged facts in the complaint as true, and
    if the facts reveal any reasonable basis upon which the non-movant [might] prevail,
    dismissal is inappropriate.” Palafox St. Associates, L.P. v. United States, 117 Fed.
    Cl. 324, 327 (2014) (quoting Pixton v. B & B Plastics, Inc., 
    291 F.3d 1324
    , 1326
    (Fed. Cir. 2002)). The Court may also look beyond the pleadings and ‘“inquire
    into jurisdictional facts’ to determine whether jurisdiction exists.” Estes Express
    Lines v. United States, 
    108 Fed. Cl. 416
    , 420 (2013), rev’d on other grounds, 
    739 F.3d 689
    (Fed. Cir. 2014) (citing Rocovich v. United States, 
    933 F.2d 991
    , 993
    (Fed. Cir. 1991)).
    B.    The Contract Disputes Act
    The Tucker Act, 28 U.S.C. § 1491(a)(1), grants the United States Court of
    Federal Claims jurisdiction “to render judgment upon any claim against the United
    States founded either upon the Constitution, or any Act of Congress or any
    regulation of an executive department, or upon any express or implied contract
    with the United States, or for liquidated or unliquidated damages in cases not
    sounding in tort.” 28 U.S.C. § 1491(a)(1). The Tucker Act further provides that
    the Court “shall have jurisdiction to render judgment upon any claim by or against,
    or dispute with, a contractor arising under section 7104(b)(1) of title 41 [the
    Contract Disputes Act].” 
    Id. at §
    1491(a)(2).
    -4-
    For the Court to have subject-matter jurisdiction to hear a dispute under the
    CDA, the plaintiff must meet two prerequisites: (1) submit a proper claim to the
    relevant contracting officer, which must be properly certified if the amount
    requested is above $100,000, and (2) obtain a final decision on that claim. 41
    U.S.C. § 7103(a); Reflectone, Inc. v. Dalton, 
    60 F.3d 1572
    , 1575-76 (Fed. Cir.
    1995).
    Under the CDA, a contractor may obtain either an actual or a deemed final
    decision on the claim. Claude E. Atkins Enters., Inc. v. United States, 
    27 Fed. Cl. 142
    , 143 (1992). For claims over $100,000, the CDA provides that the contracting
    officer shall, within 60 days of receipt of the submitted certified claim, “(A) issue a
    decision; or (B) notify the contractor of the time within which a decision will be
    issued.” 41 U.S.C. § 7103(f)(2). The decision must be “issued within a reasonable
    time,” which is calculated by “taking into account such factors as the size and
    complexity of the claim and the adequacy of information in support of the claim
    provided by the contractor.” 41 U.S.C. § 7103(f)(3). If the contracting officer
    denies the claim within the required time period, that claim is actually denied. 
    Id. However, a
    failure to issue a decision within the required time “is deemed to be a
    decision by the contracting officer denying the claim.” 41 U.S.C. § 7103(f)(5). A
    denial, actual or deemed, authorizes an “appeal or action on the claim as otherwise
    provided in [the CDA]. The tribunal concerned may, at its option, stay the
    proceedings of the appeal or action to obtain a decision by the contracting officer.”
    
    Id. C. The
    Court Possesses Jurisdiction Over Plaintiff's Claim
    The parties do not dispute that R&S properly submitted a certified claim to
    the contracting officer and that the contracting officer did not issue a final decision
    on the claim by the government’s original deadline. Def. Mot. at 13; Pl. Opp. at 8.
    Accordingly, the question presented by this case is whether the government’s
    failure to issue a decision by the original deadline constitutes a deemed denial of
    R&S’s claim under the CDA. 41 U.S.C. § 7103(f)(5). For the reasons set forth
    below, the passage of the government’s July 15, 2014 deadline to decide plaintiff’s
    claim constitutes a deemed denial of that claim. As a result, this Court has subject-
    matter jurisdiction to consider R&S’s claim.
    The government argues in its motion that the Court lacks subject-matter
    jurisdiction to consider R&S’s claim because there has not been a deemed denial of
    the claim by the contracting officer. Specifically, the government maintains that
    the contracting officer in this case properly and timely extended the deadline for
    issuing a final decision on R&S’s claim until March 15, 2015, once the
    -5-
    government determined that it would not meet its original deadline. Def. Mot. at
    13-14. The government further maintains that because the new deadline set by the
    contracting officer is reasonable, R&S’s claim before this Court is premature and
    jurisdictionally barred. Def. Mot. at 13. For the reasons discussed below, the
    Court disagrees.
    The CDA contains specific requirements regarding the timing for reaching a
    decision on a claim. Section 7103(f)(2) of the CDA provides that: “A contracting
    officer shall, within 60 days of receipt of a submitted certified claim over
    $100,000-- (A) issue a decision; or (B) notify the contractor of the time within
    which a decision will be issued.” 41 U.S.C. § 7103(f)(2) (emphasis added). The
    plain language of the statute requires that the contracting officer either make a
    decision within 60 days, or set a firm deadline for issuing a final decision within 60
    days of receiving a claim. Id.2
    Although the meaning of section 7103(f)(2) has not often been addressed by
    the courts, the relevant case law supports the view that section 7103(f)(2) gives the
    government the right to extend the deadline for issuing a final decision only once
    and that the deadline must be set during the initial 60-day period.3 In Claude E.
    Atkins, the Court held that a contractor may “treat the passage of the due date
    specified in the initial sixty days as a deemed decision even if the contracting
    officer attempts to further extend the due date.” Claude E. 
    Atkins, 27 Fed. Cl. at 145
    . Similarly, the United States District Court for the District of Columbia
    recently held that a contracting officer is permitted only a single extension under
    the CDA. Tuba City Reg’l Health Care Corp. v. United States, et al., No. 13–639,
    2
    This reading of section 7103(f)(2) is reinforced by the statute’s remaining provisions: Section
    7103(f)(3) places a reasonableness limitation on section 7103(f)(2)(B) and prevents the
    contracting officer from setting a final decision date far in the future. If the contracting officer
    does set an unreasonable decision date, section 7103(f)(4) allows the contractor to ask a court to
    direct the contracting officer to issue a decision within a specified period of time. 41 U.S.C. §
    7103(f)(4). If the contracting officer fails to comply with any of the timeliness provisions in the
    CDA, section 7103(f)(5) permits the contractor to interpret the delay as a deemed denial. 41
    U.S.C. § 7103(f)(5).
    3
    The Court has also addressed this issue in dicta on two other occasions: In AFD Fund v. United
    States, 
    61 Fed. Cl. 540
    , 542 n.1 (2004), the Court found that a plaintiff may treat “the passage of
    [the final decision date set by the contracting officer] without a final decision as a deemed
    denial . . . . .” Similarly in Boeing Co. v. United States, 
    26 Cl. Ct. 257
    , 259-60 (1992), the Court
    found that a fixed final decision date is required and if the “claim is substantial and will require a
    long period of time to address, then the contracting officer's only option is to fix a date far
    enough into the future to assure a complete evaluation.”
    -6-
    
    2014 WL 1648215
    (D.D.C Apr. 25, 2014). In Tuba City, the district court
    confronted facts similar to this case: the contracting officer in that case extended
    the deadline for a final decision multiple times and the contractor filed an action in
    court arguing that its claim had been deemed denied. Tuba City, 
    2014 WL 1648215
    , at *2. In that case, the court determined that the CDA allows the
    contracting officer to pick its own deadline beyond the 60-day period. 
    Id. at *3.
    But, “[o]nce picked . . . that deadline is firm” and failure to meet that deadline
    results in a deemed denial of the claim. 
    Id. The Claude
    E. Atkins and Tuba City decisions are instructive here. In this
    case, the contracting officer set a deadline of July 15, 2014 for issuing a final
    decision on R&S’s claim. That deadline passed without the contracting officer
    reaching a decision. Although the contracting officer did seek to extend the
    deadline again before the first extension expired, no language in the CDA provides
    the government with the right to a second extension. As a result, R&S may treat
    the contracting officer’s failure to reach a decision by the government’s July 15,
    2014 deadline as a deemed denial of its claim. See 41 U.S.C. § 7103(f)(2); Claude
    E. 
    Atkins, 27 Fed. Cl. at 145
    .
    The government incorrectly argues that the contracting officer had the right
    to further extend the deadline for issuing a final decision in this case because
    R&S’s claim is complex. Def. Mot. at 16-17. Section 7103(f)(3) of the CDA
    requires that, at the outset, the government calculate the deadline for issuing a final
    decision “taking into account such factors as the size and complexity of the claim
    and the adequacy of information in support of the claim provided by the
    contractor.” 41 U.S.C. § 7103(f)(3). Moreover, in Claude E. Atkins, the Court
    held that even if the claim is complex, the contracting officer “must choose, within
    the sixty days, a reasonable due date that he will be able to meet.” Claude E.
    
    Atkins, 27 Fed. Cl. at 146
    . There is “no exception to the § 7103(f) timing
    requirements for complex claims.” Tuba City, 
    2014 WL 1648215
    , at *3. For this
    reason, when faced with a complex claim, the contracting officer here should have
    picked a deadline that afforded plenty of time to evaluate R&S’s claim. 
    Id. The government
    also relies upon several Board of Contract Appeals cases to
    support its argument that the contracting officer properly extended the deadline for
    a final decision on R&S’s claim.4 But, a plain reading of section 7103(f)(2)
    4
    In Appeal of Robert Augustine & Sons, Inc., VABCA No. 3079, 
    1989 WL 146843
    (V.A.B.C.A.
    Nov. 22, 1989), the Veterans Board of Contract Appeals (“VABCA”) held that the claim in the
    case was deemed denied, but stated, in dictum, that the contracting officer need only provide a
    “good faith estimate” for when a decision would be rendered and that the estimate could be
    -7-
    demonstrates that the government must set a firm deadline within the initial 60-day
    period, and if that deadline is not met, the contractor may choose to treat any
    further extension of the deadline as a deemed denial of its claim. See 41 U.S.C. §
    7103(f)(2); Claude E. 
    Atkins, 27 Fed. Cl. at 145
    .
    Because section 7103(f)(2) requires that the contracting officer issue a final
    decision within the initial deadline set by the government, R&S may treat the
    elapse of the government’s July 15, 2014 deadline in this case as a deemed denial
    of its claim. 
    Id. The Court,
    accordingly, possesses subject-matter jurisdiction to
    consider R&S’s claim.
    D.      Stay of Proceedings
    As an alternative to dismissal of this case, the government requests that the
    Court stay and remand this case to the contracting officer for a final decision. Def.
    Mot. at 17-18. R&S opposes this request. Pl. Opp. at 2. As this Court possesses
    subject-matter jurisdiction over R&S’s claim, the Court has discretion to issue a
    stay order “to obtain a decision by the contracting officer.” 41 U.S.C. §
    7103(f)(5).5 “[W]hen the Court does possess jurisdiction over a claim based upon
    extended if reasonable. In Appeal of Chester P. Schwartz, Gary A. Mosko, and Stanley H.
    Marks, VABCA No. 2975, 
    1989 WL 156822
    (V.A.B.C.A. Dec. 8, 1989), the VABCA held that
    the claim in the case was deemed denied, but stated, in dictum, that a “good faith estimate” was
    all that was required. In Appeal of Suh’dutsing Techs., ASBCA No. 58760, 
    2014 WL 1909252
    ,
    (A.S.B.C.A. Apr. 28, 2014), the Armed Services Board of Contract Appeals held that the claim
    in the case was deemed denied because the contracting officer did not issue a fixed date for
    reaching a decision on the claim.
    5
    In their Joint Status Report filed with the Court on February 5, 2015, the parties assert that the
    contracting officer has no jurisdiction to issue a final decision on R&S’s claim while this
    litigation is pending. See February 5, 2015 Joint Status Report at 4, 7. In Sharman Co. v. United
    States, the Court of Appeals for the Federal Circuit held that “[o]nce a claim is in litigation, the
    Department of Justice gains exclusive authority to act in the pending litigation. . . . That
    exclusive authority divests the contracting officer of his authority to issue a final decision on the
    claim.” See Sharman Co. v. United States, 
    2 F.3d 1564
    , 1571 (Fed. Cir. 1993) (citations
    omitted), overruled on other grounds by Reflectone, Inc. v. Dalton, 
    60 F.3d 1572
    . However,
    Sharman did not address circumstances where the Court has determined that it possesses
    jurisdiction and seeks to remand a case to the contracting officer pursuant to section 7103(f)(5).
    
    Id. Rather, as
    discussed above, the CDA explicitly grants the Court the authority to “retrocede
    authority to the contracting officer” when the Court “posses[es] jurisdiction over a claim based
    on a deemed denial.” United Partition Sys., Inc. v. United States, 
    59 Fed. Cl. 627
    , 643 (2004);
    see also RCFC Rule 56.2(a)(1) (allowing the Court to remand matters within its jurisdiction to an
    administrative or executive body or official).
    -8-
    a deemed denial, it is specifically granted discretion to retrocede authority to the
    contracting officer [by the CDA].” United Partition Sys., Inc. v. United States, 
    59 Fed. Cl. 627
    , 643 (2004). Thus, the Court may stay and remand this case to the
    contracting officer in order to “obtain a final decision when the Court believes that
    such a decision would be beneficial to the parties and assist resolution of the
    matter.” 
    Id. at 641-642.
    The government argues in its motion that a stay and remand of this case is
    warranted because the contracting officer has already devoted substantial resources
    to reviewing R&S’s claim. Def. Mot. at 18. The government further asserts that
    the ongoing review of R&S’s claim has “great potential to identify significant
    areas of agreement between R&S and the Government that could substantially
    narrow the issues truly in dispute between the parties.” 
    Id. Because the
    contracting officer has already committed significant resources towards analyzing
    R&S’s claim, a stay until the contracting officer issues a decision will promote
    judicial economy.6 The government has represented to the Court that the
    contracting officer’s review is expected to be completed by March 15, 2015. See
    Def. Mot. at 18; Def. Reply at 9; February 5, 2015 Joint Status Report. Given this
    expectation, a short stay would not work an undue hardship on the parties. As a
    remand of this case to the contracting officer for a decision would be beneficial to
    the resolution of this matter, the Court will stay proceedings in this case until after
    the issuance of the decision, which shall be no later than 30 days from the filing of
    this Memorandum Opinion and Order.
    IV.    CONCLUSION
    For the foregoing reasons, the government’s failure to reach an actual
    decision on R&S’s claim within the time initially specified by the contracting
    officer constitutes a deemed denial of that claim under the CDA. R&S may appeal
    the deemed denial of its claim in this Court under the CDA. Accordingly, the
    government’s motion to dismiss, or alternatively for summary judgment, is
    DENIED.
    6
    While the Court believes a decision from the contracting officer will be beneficial to this case,
    the contracting officer’s findings of facts are not binding upon the parties and are not entitled to
    any deference. The Court conducts its review de novo. Wilner v. United States, 
    24 F.3d 1397
    ,
    1401 (Fed. Cir. 1994).
    -9-
    Because the government has completed much of the work needed to review
    R&S’s claim and a decision by the contracting officer on that claim is imminent,
    the Court exercises its discretion under the CDA to stay these proceedings to
    obtain a final decision by the contracting officer. The government’s motion for
    remand to the contracting officer for a final decision is, therefore, GRANTED.
    The case is STAYED 30 days from the filing of this Memorandum Opinion and
    Order and REMANDED to the contracting officer for a decision, which shall be
    issued no later than 30 days from the filing of this Memorandum Opinion and
    Order.
    The parties are instructed to file a joint status report on or before 45 days
    from the filing of this Memorandum Opinion and Order advising the Court of their
    views on how this matter should proceed, which shall include a proposed schedule
    for discovery and a discussion of whether this case should be consolidated with
    Rudolph & Sletten, Inc. v. United States, No. 14-14C (Fed. Cl. filed Jan. 6, 2014).
    The parties shall bear their own costs.
    IT IS SO ORDERED.
    s/ Lydia Kay Griggsby
    LYDIA KAY GRIGGSBY
    Judge
    - 10 -