Bgt Holdings LLC v. United States ( 2019 )


Menu:
  •        In the United States Court of Federal Claims
    No. 18-178C
    (E-Filed: April 5, 2019)
    )
    BGT HOLDINGS, LLC,                        )
    )     Motion to Dismiss; RCFC
    Plaintiff,            )     12(b)(6); Equitable
    )     Adjustment; Breach of
    v.                                        )     Contract; Breach of Implied
    )     Duty of Good Faith and Fair
    THE UNITED STATES,                        )     Dealing; 48 C.F.R. § 52.245-1
    )     (2012).
    Defendant.            )
    )
    Milton C. Johns, Tysons, VA, for plaintiff.
    Borislav Kushnir, Trial Attorney, with whom were Chad A. Readler, Acting Assistant
    Attorney General, Robert E. Kirschman, Jr., Director, Elizabeth M. Hosford, Assistant
    Director, Commercial Litigation Branch, Civil Division, United States Department of
    Justice, Washington, DC, for defendant.
    OPINION AND ORDER
    CAMPBELL-SMITH, Judge.
    On August 17, 2018, plaintiff BGT Holdings, LLC (BGT), filed its first amended
    complaint in which it alleges that defendant breached a contract under which plaintiff
    was to provide a gas turbine generator set to the United States Navy. See ECF No. 10.
    Defendant has moved to partially dismiss plaintiff’s amended complaint, pursuant to Rule
    12(b)(6) of the Rules of the United States Court of Federal Claims (RCFC). See ECF No.
    13. Also before the court are plaintiff’s response to defendant’s motion to dismiss, ECF
    No. 14, and defendant’s reply in support of its motion, ECF No. 15. For the following
    reasons, defendant’s motion for partial dismissal is GRANTED.
    I.     Background
    On October 27, 2014, the Navy awarded contract number N65540-15-C-0001 to
    BGT under which plaintiff was to provide a “stand-alone, complete outdoor-rated air
    cooled dual fuel LM2500 Gas Turbine Generator Set (GTGS) using GFE” (Government
    Furnished Equipment) to the Navy “at their site in Philadelphia, Pennsylvania.” ECF No.
    10 at 2.
    Under the terms of the contract, the Navy was obligated to provide certain
    equipment to plaintiff for use on the project. The relevant contract language reads as
    follows:
    4.3 Government Furnished Equipment (GFE). Listed below is the GFE
    to be provided to the Contractor for use in assembling the GTGS:
    1.     Liquid fuel LM2500PC Gas Turbine engine and power turbine
    2.     Gas Turbine enclosure with base, engine mounts and
    miscellaneous hardware (List provided in Appendix E)
    3.     Engine inlet bellmount, water wash nozzles & plenum with
    flexible interface connection
    4.     Exhaust diffuser & collector with flexible interface connection
    5.     Engine High Speed power output flexible coupling
    6.     Controls Option two (2) GFE Controller (MicroNet Plus)
    ECF No. 10-1 at 23. Plaintiff acknowledges that the Navy complied with these
    requirements “[w]ith the exception of the exhaust collector and engine mounts.” ECF
    No. 10 at 3.
    The contract incorporated a long list of provisions from the Federal Acquisition
    Regulation (FAR), including section 52.245-1, Government Property. See ECF No. 10-1
    at 45. That section reads, in relevant part:
    (d)    Government-furnished property.
    ...
    2
    (3)(i) The Contracting Officer may by written notice, at any
    time—
    (A)    Increase or decrease the amount of Government-
    furnished property under this contract;
    (B)    Substitute other Government-furnished property
    for the property previously furnished, to be
    furnished, or to be acquired by the Contractor for
    the Government under this contract; or
    (C)    Withdraw authority to use property.
    (ii) Upon completion of any action(s) under paragraph
    (d)(3)(i) of this clause, and the Contractor’s timely
    written request, the Contracting Officer shall consider
    an equitable adjustment to the contract.
    ...
    (i)    Equitable adjustment. Equitable adjustments under this clause shall
    be made in accordance with the procedures of the Changes clause.
    However, the Government shall not be liable for breach of contract
    for the following:
    ...
    (3)      An increase, decrease, or substitution of Government-furnished
    property.
    48 C.F.R. § 52.245-1(d)(3)(i)-(ii) & (i)(3) (2012).
    With regard to changes that may be made to the contract terms, the contract
    provides as follows:
    (a)    Except as specified in paragraph (b) below, no order, statement, or
    conduct of Government personnel who visit the Contractor’s facilities or in
    any other manner communicates with Contractor personnel during the
    performance of this contract shall constitute a change under the “Changes”
    clause of this contract.
    3
    (b)    The Contractor shall not comply with any order, direction or request
    of Government personnel unless it is issued in writing and signed by the
    Contracting Officer, or is pursuant to specific authority otherwise included
    as a part of this contract.
    (c)    The Contracting Officer is the only person authorized to approve
    changes in any of the requirements of this contract and notwithstanding
    provisions contained elsewhere in this contract, the said authority remains
    solely the Contracting Officer’s. In the event the [C]ontractor effects any
    change at the direction of any person other than the Contracting Officer, the
    change will be considered to have been made without authority and no
    adjustment will be made in the contract price to cover any increase in charges
    incurred as a result thereof. The address and telephone number of the
    Contracting Officer is:
    John Stefano
    Naval Surface Warfare Center Carderock Division
    5001 South Broad Street
    Philadelphia, PA 19112-1403
    John.stefano@navy.mil
    (215) 897-8437
    ECF No. 10-1 at 55.
    Plaintiff alleges that “[t]he Navy informed BGT that it would not release the
    exhaust collector and the engine mounts, unless BGT provided the Navy with the cost
    savings in return, that is, a decrease in the total amount of the firm fixed price contract.”
    ECF No. 10 at 4. Plaintiff further alleges that it was instructed to address future
    correspondence to “‘Carolyn McCloskey and Suzanne Onesti directly. They will be the
    conduits to the larger Navy team. This is to ensure the right people are taking Actions.’”
    
    Id. (quoting an
    uncited source). “Ms. Onesti also emphasized the importance of
    centralized communication, telling BGT that as the Procurements Manager, she was the
    contact for ‘questions about the SOW or requirements requiring a response from the
    government, or if you need to request dimensions, drawings or specs, your email needs to
    be address[ed] to Carolyn or me, or preferably both.” 
    Id. at 4-5
    (quoting an uncited
    source). According to plaintiff “it was the usual course of performance that any decision
    by the Contracting Officer was conveyed to BGT by either Ms. Onesti or Ms.
    McCloskey.” 
    Id. at 5.
    Plaintiff also states as follows: “As the Contracting Officer for the GTGS
    program, Mr. Stefano was the person who communicated his decision to BGT no later
    than December 2, 2014 that absent cost savings, on behalf of the Navy, he would not
    4
    release the exhaust collector and engine mounts to it.” 
    Id. Plaintiff does
    not allege that
    this decision was communicated in writing and signed by the contracting officer.
    In an email dated January 16, 2015, plaintiff asked Ms. Onesti to confirm “that
    there is no charge” for the Navy’s exhaust collector. 
    Id. Ms. Onesti
    replied, as follows:
    For the Exhaust Collector, the action is for BGT to identify the costs from
    your proposal that were directly associated with buying or manufacturing
    your own Exhaust equipment. That cost would then be deducted from the
    value of the contract or applied toward future options if BGT were to use the
    GFE exhaust collector. So you actually don’t need cost data from us. If the
    cost savings are not significant enough, our Program Manager may decide
    instead to have you procure your own exhaust collector components.
    (emphasis added).
    
    Id. Several days
    later, on January 23, 2015, plaintiff sent an email to Ms. Onesti
    asking: “As we progress to the final stages of the GA, we now need the engine mounts
    and flexible coupling that the Navy is furnishing to complete those drawings. When can
    we arrange for pickup of those items?” 
    Id. In response,
    Ms. Onesti wrote, on January 26,
    2015: “Since BGT is developing their own turbine module, the mounts for the engine are
    within the scope of the enclosure design. The mounts are included in the GFE turbine
    module that was not utilized by BGT.” 
    Id. In late
    January 2015, after the Navy and plaintiff failed to agree on “cost savings”
    related to the GFE, “the Navy informed BGT that it had reutilized the GFE exhaust
    collector and engine mounts as fleet assets, and they were no longer available to BGT
    through the contract.” 
    Id. at 5-6.
    Plaintiff acknowledges that the contracting officer, Mr.
    John Stefano, “had the authority to ‘decrease the amount of Government-furnished
    property under this contract.’” 
    Id. at 6
    (citing FAR 52.245-1(d)(3)(i)(A)). Plaintiff
    alleges that Mr. Stefano was the only person authorized to make such a decision, see 
    id., but states
    that Ms. Onesti, not Mr. Stefano, communicated the decision to plaintiff, see 
    id. at 9.
    In early 2015, plaintiff provided several progress reports to the Navy that included
    discussion of the “issue of cost savings in exchange for the use of the exhaust collector
    and engine mounts.” 
    Id. at 7.
    Plaintiff alleges that the contracting officer received these
    reports, and as such, “knew or should have known that BGT was confronted with the
    decision of whether to use the Navy’s GFE and provide it with a ‘cost savings to the
    project,’ or procure its own equipment in place of the GFE.” 
    Id. 5 In
    April 2015, because the Navy had refused to provide the GFE, plaintiff
    “purchased both an exhaust collector and engine mounts in the commercial market,”
    which were “identical” to the equipment that would have been provided by the Navy
    under the contract. 
    Id. at 6
    . Plaintiff purchased the equipment because it “was
    contractually obligated to manufacture a Gas Turbine Generator Set,” and it is impossible
    to do so “without incorporating both an exhaust collector and engine mounts.” 
    Id. The Navy
    accepted delivery of the GTGS from plaintiff, and made its final
    payment on the contract in December 2016. See 
    id. at 10.
    Plaintiff had submitted a
    claim to the contracting officer including a request for an equitable adjustment in the
    amount of $610,775 as a result of the Navy’s GFE decision, on November 1, 2016. See
    
    id. On May
    30, 2017, the contracting officer denied plaintiff’s claim as to the GFE. See
    
    id. In its
    amended complaint, plaintiff alleges five counts: (1) “Count I. Constructive
    Change—Equitable Adjustment for the Cost of Exhaust Collector and Engine Mounts,”
    
    id. at 3-11;
    (2) “Count II. Breach of Contract (Failure to provide GFE),” 
    id. at 11;
    (3)
    “Count III. Breach of Duty of Good Faith and Fair Dealing (Failure to provide GFE),”
    
    id. at 11-12;
    (4) “Count IV. Constructive Change—Equitable Adjustment—Increased
    Cost of Water Treatment Plant,” 
    id. at 12-14;
    and (5) “Count V. Equitable Adjustment—
    Costs Resulting from Delay Within the Control of the Government,” 
    id. at 14-16.
    In its
    motion for partial dismissal, ECF No. 13, defendant moves to dismiss the first three of
    these counts for failure to state a claim upon which relief can be granted, pursuant to
    RCFC 12(b)(6). 1
    II.    Legal Standards
    A complaint should be dismissed under RCFC 12(b)(6) “when the facts asserted
    by the claimant do not entitle him to a legal remedy.” Lindsay v. United States, 
    295 F.3d 1252
    , 1257 (Fed. Cir. 2002). To survive a motion to dismiss, a complaint must contain
    factual allegations that are “enough to raise a right to relief above the speculative level.”
    Bell Atl. Corp. v. Twombly, 
    550 U.S. 544
    , 545 (2007). The basis for relief “requires
    more than labels and conclusions, and a formulaic recitation of the elements of a cause of
    action will not do.” 
    Id. at 555
    (citations omitted). However, “[i]n ruling on a RCFC
    12(b)(6) motion to dismiss, the court must accept as true the complaint’s undisputed
    factual allegations and should construe them in a light most favorable to plaintiff.”
    1
    Plaintiff alleges additional facts relevant to portions of the amended complaint not
    at issue in defendant’s motion for partial dismissal. See ECF No. 10 at 12-16 (detailing
    facts relevant to Counts IV and V). As such, the court has not recited those facts in this
    opinion.
    6
    Bristol Bay Area Health Corp. v. United States, 
    110 Fed. Cl. 251
    , 259 (2013) (citing
    Gould, Inc. v. United States, 
    935 F.2d 1271
    , 1274 (Fed. Cir. 1991)).
    III.   Analysis
    A.     Plaintiff Is Not Entitled to Equitable Adjustment
    In the first count of the amended complaint, plaintiff seeks an equitable adjustment
    in the amount of the expense it incurred to purchase the exhaust collector and engine
    mounts that defendant did not provide. See ECF No. 10 at 3-11. “Equitable adjustments
    are corrective measures that make a contractor whole when the Government modifies a
    contract.” Int’l Data Prods. Corp. v. United States, 
    492 F.3d 1317
    , 1325 (Fed. Cir. 2007)
    (citing Ets-Hokin Corp. v. United States, 
    190 Ct. Cl. 668
    , 674 (1970); see also Aydin
    Corp. v. Widnall, 
    61 F.3d 1571
    , 1577 (Fed. Cir. 1995) (“Where it requires a constructive
    change in a contract, the Government must fairly compensate the contractor for the costs
    of the change.”). In order to be effective, such modifications must be made by an agent
    with actual authority to bind the government. See Winter v. Cath-dr/balti, Joint Venture,
    
    497 F.3d 1339
    , 1344 (Fed. Cir. 2007) (“Where a party contracts with the government,
    apparent authority of the government’s agent to modify the contract is not sufficient; an
    agent must have actual authority to bind the government.”) (citing Trauma Serv. Grp. v.
    United States, 
    104 F.3d 1321
    , 1325 (Fed. Cir. 1997)).
    The contract at issue incorporates the “Government Property” FAR provision. See
    ECF No. 10-1 at 45 (incorporating 48 C.F.R. § 52.245-1). That provision specifies that
    “equitable adjustments under this clause shall be made in accordance with the procedures
    of the Changes clause” of the contract. 48 C.F.R. § 52.245-1(i). The changes clause, in
    turn, provides:
    (a)    Except as specified in paragraph (b) below, no order, statement, or
    conduct of Government personnel who visit the Contractor’s facilities or in
    any other manner communicates with Contractor personnel during the
    performance of this contract shall constitute a change under the “Changes”
    clause of this contract.
    (b)    The Contractor shall not comply with any order, direction or request
    of Government personnel unless it is issued in writing and signed by the
    Contracting Officer, or is pursuant to specific authority otherwise included
    as a part of this contract.
    (c)    The Contracting Officer is the only person authorized to approve
    changes in any of the requirements of this contract and notwithstanding
    provisions contained elsewhere in this contract, the said authority remains
    7
    solely the Contracting Officer’s. In the event the [C]ontractor effects any
    change at the direction of any person other than the Contracting Officer, the
    change will be considered to have been made without authority and no
    adjustment will be made in the contract price to cover any increase in charges
    incurred as a result thereof. The address and telephone number of the
    Contracting Officer is:
    John Stefano
    Naval Surface Warfare Center Carderock Division
    5001 South Broad Street
    Philadelphia, PA 19112-1403
    John.stefano@navy.mil
    (215) 897-8437
    ECF No. 10-1 at 55. This provision establishes Mr. Stefano as the agent with actual
    authority to change the contract on defendant’s behalf, so long as any change is in writing
    and signed.
    As an initial matter, plaintiff has not stated a claim that demonstrates its
    compliance with this contract term. Plaintiff makes much of its allegation that the
    contracting officer “made the decision to withdraw the GFE from the Contract.” ECF
    No. 14 at 14; see also ECF No. 10 at 9. In support of this assertion, plaintiff repeatedly
    cites to seven paragraphs of its amended complaint, which read, as follows:
    23.    As the Contracting Officer for the GTGS program, Mr. Stefano was
    the person who communicated his decision to BGT no later than December
    2, 2014 that absent cost savings, on behalf of the Navy, he would not release
    the exhaust collector and engine mounts to it.
    ...
    25.    On January 16, 2015, Ms. Onesti replied:
    For the Exhaust Collector, the action is for BGT to identify the costs from
    your proposal that were directly associated with buying or manufacturing
    your own Exhaust equipment. That cost would then be deducted from the
    value of the contract or applied towards future options if BGT were to use
    the GFE exhaust collector. So you actually don’t need cost data from us. If
    the cost savings are not significant enough, or Program Manager may decide
    instead to have you procure your own exhaust collector components.
    (emphasis added).
    8
    ...
    28.     In late January 2015, after the Navy and BGT were unable to come to
    agreement on “cost savings” in exchange for the GFE, the Navy informed
    BGT that it had reutilized the GFE exhaust collector and engine mounts as
    fleet assets, and they were no longer available to BGT through the contract.
    29.     As the Contracting Officer, Mr. Stefano had the authority to “decrease
    the amount of Government-furnished property under this contract.” Contract
    p. 44 (incorporating FAR 52.245-1(d)(3)(i)(A)). Put another way, every item
    of GFE listed in the Contract, including the exhaust collector and engine
    mounts, was under the control of Mr. Stefano for use only in this Contract.
    In order for the Navy to reutilize any GFE for a purpose other than Contract
    N65540-15-C-0001, Mr. Stefano’s permission was necessary.
    ...
    39.    Mr. Stefano made the decision to decrease the amount of GFE in the
    contract no later than when he permitted the exhaust collector and engine
    mounts to be withdrawn from the contract and reutilized as fleet assets.
    40.   Within the GTGS program, Mr. Stefano was also referred to as the
    “Program Manager.”
    41.    In his position as Contracting Officer, Mr. Stefano directed and
    controlled the actions of both Ms. Onesti and Ms. McCloskey within the
    GTGS program.
    ECF No. 10 at 5-7.
    Nowhere in these allegations, or elsewhere in its amended complaint, does
    plaintiff allege that the change to the contract regarding GFE was “in writing and signed
    by the Contracting Officer,” as required by the express terms of the contract. ECF No.
    10-1 at 55. The contract also provides that absent compliance with the foregoing
    requirement, “the change will be considered to have been made without authority and no
    adjustment will be made in the contract price to cover any increase in charges incurred as
    a result thereof.” 
    Id. Plaintiff is
    bound by the terms of the contract, and cannot state a
    claim for equitable adjustment, unless it presents a viable defense to the contract. See
    Forest Envtl. Servs. Co. v. United States, 
    5 Cl. Ct. 774
    , 777 (1984) (“It is well settled that
    a party to a contract will be bound by the terms thereof, unless there exists some defense
    to the contract, i.e., fraud, duress, or unless the contract is found to be unreasonable,
    9
    unconscionable or contrary to public policy, or it produces an egregious, unfair or
    unreasonable result.”).
    Plaintiff does not present a defense to the enforceability of the contract as a whole,
    but instead claims that it is entitled to an equitable adjustment for the cost of the exhaust
    collector and engine mounts, even absent compliance with the change provision in the
    contract, on the theories of ratification and waiver. With regard to ratification, plaintiff
    alleges that “Contracting Officer Stefano ratified Ms. Onesti’s decision to decrease the
    GFE under the contract when he permitted the GFE exhaust collector and engine mounts
    to be withdrawn from the contract and reutilized as fleet assets.” See ECF No. 10 at 8.
    In addition, after citing caselaw related to the issue waiver, plaintiff alleges that:
    In giving permission for GFE that was included in the contract to be
    withdrawn from the contract and instead reutilized for other Navy purposes,
    without issuing a formal written change order, Mr. Stefano intended to make
    a change to the contract without relying on its right to do so only by written
    notice.
    
    Id. Defendant disagrees,
    and argues that the theories of ratification and waiver are
    unavailable to plaintiff.
    Defendant contends that plaintiff has contracted away its ability to make an
    argument for ratification in these circumstances. Specifically, defendant asserts that
    plaintiff “agreed ‘not [to] comply with any order, direction or request of Government
    personnel unless it is issued in writing and signed by the Contracting Officer,’” and that
    “‘any change at the direction of any person other than the Contracting Officer . . . will be
    considered to have been made without authority.’” ECF No. 13 at 16 (quoting ECF No.
    10-1 at 55) (emphasis added by defendant). This contract language, according to
    defendant, is fundamentally at odds with the theory of ratification because plaintiff
    “agreed that the contracting officer must personally issue and sign a written directive
    before such a directive becomes binding on the Government.” 
    Id. Defendant makes
    a similar argument with respect to plaintiff’s theory that
    defendant waived the right to enforce the requirements of the changes clause:
    Because Mr. Stefano’s approval was required for the withdrawal of GFE, and
    because the alleged withdrawal occurred without a written directive from
    him, BGT claims that Mr. Stefano must have intended to modify the
    Contract’s GFE provision without a written directive. In essence, BGT
    argues that contract modification by an unauthorized agent constitutes a
    presumptive waiver precisely because someone else had sole authority to
    make the modification.
    10
    
    Id. (citations omitted).
    Allowing a waiver theory under such circumstances, in
    defendant’s view, would “nullify the well-settled principle that only Government agents
    with authority can bind the Government.” 
    Id. And following
    this theory to its logical
    conclusion, “if permission by authorized Government personnel could be assumed
    whenever unauthorized personnel take action, the actions of unauthorized personnel
    would always bind the Government.” 
    Id. at 17.
    In order to effectively waive a right to which a party would otherwise be entitled,
    it must do so “knowingly and voluntarily.” Minesen Co. v. McHugh, 
    671 F.3d 1332
    ,
    1340 (Fed. Cir. 2012). Plaintiff acknowledges as much in its response, stating that
    “[w]aiver requires only that the party waiving [a] right do so ‘voluntarily’ and
    ‘knowingly’ based on the facts of the case.” See ECF No. 14 at 14 (quoting Seaboard
    Lumber Co. v. United States, 
    903 F.2d 1560
    , 1563 (Fed. Cir. 1990)). Plaintiff claims it
    did not knowingly or intentionally relinquish its right to assert the defenses of ratification
    and waiver, and therefore, the contract language should not be read to have that effect.
    See ECF No. 14 at 12-14. Plaintiff also argues that “[n]othing in the Contract at issue in
    this case ‘spell[s] out’ legal theories precluded by contract, and BGT certainly does argue
    that it never waived such rights.” 
    Id. (quoting an
    uncited source).
    It strains credulity, however, for plaintiff to claim that it was unaware that the
    specific contract language at issue here precludes its arguments relating to ratification and
    waiver. As noted above, the changes clause in the contract states that plaintiff “shall not
    comply with any order, direction or request” from anyone other than the contracting
    officer, and puts plaintiff on notice that if “the contractor effects any change at the
    direction of any person other than the Contracting Officer, the change will be considered
    to have been made with no authority and no adjustment will be made in the contract price
    to cover any increase in charges incurred as a result thereof.” ECF No. 10-1 at 55.
    The language of the changes clause is both unambiguous and diametrically opposed to
    plaintiff’s theories. Indeed, this contract provision, which plaintiff knew was part of the
    contract, guards against the very conduct plaintiff now seeks to justify.
    In addition, plaintiff makes no allegation in its amended complaint that its decision
    to enter into the subject contract was not voluntary. As such, plaintiff was contractually
    obligated to refrain from complying with Ms. Onesti’s attempted modification, absent
    written and signed direction from Mr. Stefano. Plaintiff has not alleged that it sought,
    much less obtained, such written consent to the GFE modification.
    For these reasons, plaintiff’s claim for an equitable adjustment must be dismissed.
    11
    B.     The Express Terms of the Contract Preclude Plaintiff’s Claim for Breach
    of Contract
    In the second count of the amended complaint, plaintiff alleges that defendant
    breached its contractual duties in two respects: (1) by failing to “provide the GFE to
    Plaintiff according to the plain terms of the Contract,” and (2) by refusing to allow an
    equitable adjustment for the undelivered GFE. ECF No. 10 at 11. Neither of these
    claims is valid.
    First, for the reasons explained above, plaintiff’s claim that it was entitled to an
    equitable adjustment is unfounded. As such, defendant could not have breached the
    contract by rejecting plaintiff’s request. And second, even assuming that an authorized
    government agent modified the contract by declining to provide the exhaust collector and
    engine mounts, plaintiff’s claim that such a modification breached the contract is
    explicitly barred by its terms.
    The contract incorporates FAR section 52.245-1, titled “Government Property,”
    see ECF No. 10-1 at 45, which reads, in relevant part:
    (i)    Equitable adjustment. Equitable adjustments under this clause shall
    be made in accordance with the procedures of the Changes clause.
    However, the Government shall not be liable for breach of contract
    for the following:
    ...
    (3)    An increase, decrease, or substitution of Government-furnished
    property.
    48 C.F.R. § 52.245-1(i)(3) (emphasis added).
    Clauses that limit the government’s liability have not uniformly been enforced in
    all circumstances. Of particular concern are cases in which the limitations at issue do not
    “disavow claims outright,” but instead seek to narrow a contractor’s recovery. Blue Lake
    Forest Prods., Inc., v. United States, 
    86 Fed. Cl. 366
    , 380 n.21 (2009); 
    id. at 378-79
    (discussing cases in which the United States Court of Appeals for the Federal Circuit,
    along with this court and its predecessors, have declined to enforce clauses limiting the
    amount of the government’s liability “where the Government’s own unreasonable
    conduct caused a delay or suspension”).
    Limitations clauses have been enforced, however, when those clauses are
    sufficiently explicit and direct. In Wells Brothers Co. v. United States, 
    254 U.S. 83
                                                 12
    (1920), the contractor sought damages for an alleged construction delay caused by the
    government. The clause limiting the government’s liability stated that “no claim shall be
    made or allowed to the contractor for any damages which may arise out of any delay
    caused by the United States.” 
    Id. at 85.
    The Supreme Court of the United States upheld
    the provision, explaining that its language “cannot be treated as meaningless and futile
    and read out of the contract” and found that “its plain meaning is fatal to [Wells
    Brothers’] claim.” 
    Id. at 86-87.
    See also George A. Fuller Co. v. United States, 69 F.
    Supp. 409, 412 (Ct. Cl. 1947) (acknowledging the force of Wells Brothers with regard to
    cases in which the contract language at issue includes “express provisions . . . exempting
    the Government from liability” for delay damages); Dept. of Nat. Res. and Conservation
    of State of Montana v. United States, 
    1 Cl. Ct. 727
    , 734 (1983) (stating that “it is required
    that where the government intends to exculpate itself from liability for its breach of
    contract, it must manifest that intent in clear, direct and express language”).
    It is difficult for the court to conceive of clearer exculpatory language than the
    clause at issue in this case. When it entered into the contract to provide the Navy with a
    GTGS, plaintiff agreed that “the Government shall not be liable for breach of contract for
    . . . [a]n increase, decrease, or substitution of Government-furnished property.” 48 C.F.R.
    § 52.245-1(i)(3). But rather than address this language or any relevant caselaw directly,
    plaintiff confines its response to an argument that the decision to withdraw GFE was a
    cardinal change, and thus, a material breach of the contract. See ECF No. 14 at 17-18.
    The court need not resolve whether the cardinal change doctrine could, in theory, apply to
    a case in which the government does not provide GFE as contemplated by the contract.
    The materiality of any alleged breach decidedly does not affect the outcome in this case
    since a claim for breach of contract is not a remedy available to plaintiff.
    Because the unambiguous terms of the contract clearly preclude claims for breach
    in the present circumstances, the second count of plaintiff’s amended complaint must be
    dismissed.
    C.     Breach of the Implied Duty of Good Faith and Fair Dealing
    Plaintiff makes a claim for breach of the implied duty of good faith and fair
    dealing in the third count of its amended complaint. See ECF No. 10 at 11-12. Plaintiff
    alleges that “Defendant targeted its actions specifically toward Plaintiff to drive up
    Plaintiff’s costs to perform.” 
    Id. at 12.
    Plaintiff also claims that “Defendant specifically
    refused to provide the contractually required GFE to frustrate and inhibit Plaintiff’s
    ability to complete the performance of its contractual obligations.” 
    Id. As the
    Federal Circuit has explained, the implied duty of good faith and fair
    dealing “imposes obligations on both contracting parties that include the duty not to
    interfere with the other party’s performance and not to act so as to destroy the reasonable
    13
    expectations of the other party regarding the fruits of the contract.” Centex Corp. v.
    United States, 
    395 F.3d 1283
    , 1304 (Fed. Cir. 2005). The Federal Circuit has also held
    that “a party to a contract cannot use an implied duty of good faith and fair dealing to
    ‘expand [another] party’s contractual duties beyond those in the express contract or create
    duties inconsistent with the contract’s provisions.’” Agility Pub. Warehousing Co. KSCP
    v. Mattis, 
    852 F.3d 1370
    , 1384-85 (Fed. Cir. 2017) (quoting Metcalf Constr. Co. v.
    United States, 
    742 F.3d 984
    , 994 (Fed. Cir. 2014)). Put another way, parties “cannot rely
    on the implied covenant of good faith and fair dealing to change the text of their
    contractual obligations.” Century Expl. New Orleans LLC v. United States, 
    745 F.3d 1168
    , 1179 (Fed. Cir. 2014).
    Here, plaintiff alleges that defendant’s “refus[al] to provide the contractually
    required GFE” was a breach of its implied duty of good faith and fair dealing. See ECF
    No. 10 at 12. Under the terms of the contract, defendant was obligated to provide a list of
    GFE, including a “Gas Turbine enclosure with base, and engine mounts and
    miscellaneous hardware,” and an “exhaust diffuser & collector with flexible interface
    connection.” ECF No. 10-1 at 23. Plaintiff alleges that defendant did not provide either
    the engine mounts or the exhaust collector. See ECF No. 10 at 3.
    Plaintiff’s claim for a breach of the implied duty of good faith and fair dealing
    founders, however, upon consideration of FAR 52.245-1, which was incorporated by
    explicit reference into the contract. The contracting officer was specifically permitted,
    “by written notice, at any time [to] . . . [i]ncrease or decrease the amount of Government-
    furnished property under this contract,” or to “[w]ithdraw authority to use property.” 48
    C.F.R. § 52.245-1(d)(3)(i)(A), (C). In addition, FAR 52.245-1 states that “the
    Government shall not be liable for breach of contract for . . . [a]n increase, decrease, or
    substitution of Government-furnished property.” 48 C.F.R. § 52.245-1(i)(3).
    In seeking to recover for defendant’s alleged breach of its implied duty of good
    faith and fair dealing, plaintiff asks the court to find that defendant’s alleged decision to
    decrease the amount of, or withdraw use of, certain GFE interfered with its contract
    performance in an impermissible manner. Reaching this conclusion would require the
    court to “change the text of [defendant’s] contractual obligations,” in contravention of
    Federal Circuit precedent. Century 
    Expl., 745 F.3d at 1179
    . The court accepts as true
    plaintiff’s allegation that defendant did not provide the engine mounts or exhaust
    collector. But in so doing, the defendant exercised a right given to it by the express terms
    of the contract, and therefore could not have breached a contrary duty implied in the
    contract. As such, the court cannot conclude that plaintiff has sufficiently alleged a claim
    for defendant’s breach of its implied duty of good faith and fair dealing.
    14
    IV.    Conclusion
    For the foregoing reasons, defendant’s motion for partial dismissal, ECF No. 13, is
    GRANTED.
    Pursuant to RCFC 54(b), there being no just reason for delay, and for the reasons
    stated in this opinion, the clerk’s office is directed to ENTER final judgment in favor of
    defendant, DISMISSING Counts I, II, and III of plaintiff’s amended complaint, with
    prejudice.
    Defendant is directed to FILE its answer or otherwise respond to the remaining
    counts, Counts IV and V, of plaintiff’s amended complaint, on or before May 6, 2019.
    IT IS SO ORDERED.
    s/Patricia E. Campbell-Smith
    PATRICIA E. CAMPBELL-SMITH
    Judge
    15