Kudsk Construction, Inc. v. United States ( 2019 )


Menu:
  •       In the United States Court of Federal Claims
    No. 18-1032C
    (E-Filed: August 30, 2019)
    )
    KUDSK CONSTRUCTION, INC.,              )
    )
    Contract; RCFC 12(b)(6); Plausible
    Plaintiff,        )
    Claim for Damages Due to Delayed
    )
    Notice to Proceed; Reporting
    v.                                     )
    Requirements Not Necessarily
    )
    Incorporated into Contract by
    THE UNITED STATES,                     )
    Christian Doctrine.
    )
    Defendant.        )
    )
    William J. Braun, La Jolla, CA, for plaintiff.
    Rebecca S. Kruser, Trial Attorney, with whom were Joseph H. Hunt, Assistant
    Attorney General, Robert E. Kirschman, Jr., Director, and Deborah A. Bynum,
    Assistant Director, Commercial Litigation Branch, Civil Division, United States
    Department of Justice, Washington, DC, for defendant. MAJ Christopher A.
    Lacour, United States Army Litigation Division, Fort Belvoir, VA, of counsel.
    OPINION
    CAMPBELL-SMITH, Judge.
    This matter is before the court on defendant’s motion for partial dismissal, filed
    pursuant to Rule 12(b)(6) of the Rules of the United States Court of Federal Claims
    (RCFC), addressing a portion of Count I and all of Count IV of plaintiff’s complaint. See
    ECF No. 8. Plaintiff’s complaint, ECF No. 1, plaintiff’s response to defendant’s motion
    to dismiss, ECF No. 9, and defendant’s reply, ECF No. 16, were also considered by the
    court. Oral argument was not requested by the parties nor required by the court. For the
    reasons set forth below, defendant’s motion is DENIED.
    I.     Background 1
    Plaintiff Kudsk Construction, Inc. (Kudsk) was awarded a construction contract,
    Contract No. W9124N-09-C-0040, by the United States Army Reserve Contracting
    Center (Army) on or about September 11, 2009. ECF No. 1 at 1-2. The contract was for
    the renovation of six barracks at an Army Reserve Training Area. 
    Id. at 2.
    Approximately ten days after award, the Army notified Kudsk to suspend any work on
    the contract, because a bid protest had been filed. 
    Id. On December
    1, 2009, Kudsk was
    notified that the protest had been denied and that the work could proceed. 
    Id. Kudsk filed
    a claim on December 30, 2009, under Federal Acquisition Regulation (FAR)
    52.233-3(b)(2), for “administrative and overhead” incurred while “waiting for [a] Notice
    to Proceed.” 2 
    Id. After contract
    performance was complete, Kudsk filed a certified claim with the
    contracting officer. 
    Id. at 3.
    Two elements of that claim, which was approved in part and
    denied in part, are at issue in the motion for partial dismissal now before the court. In
    Count I of the complaint, Kudsk seeks “increased costs and unabsorbed home office
    expenses” for the period of time Kudsk was on standby, from September 11, 2009,
    through December 11, 2009, when the Notice to Proceed issued. 
    Id. at 4-5.
    This claim is
    in the amount of $66,738. 
    Id. at 5.
    In Count IV of the complaint, Kudsk asserts that on or about July 15, 2010, the
    Army directed Kudsk to comply with the reporting requirements of the American
    Recovery and Reinvestment Act of 2009 (ARRA), Pub. L. No. 111-5, Div. A, § 1512,
    123 Stat. 115, 287-88, pursuant to a regulation that was not part of this construction
    contract. ECF No. 1 at 8. Kudsk began complying with these reporting requirements
    under protest. 
    Id. at 9.
    According to Kudsk, the cost of compliance with ARRA
    reporting requirements over the period of contract performance was $6,739, and this
    amount, too, was included in plaintiff’s certified claim. 
    Id. Defendant’s motion
    to dismiss asserts that the claim for unabsorbed home office
    overhead contained in Count I, and the claim for ARRA reporting costs in Count IV,
    should be dismissed for failure to state a claim upon which relief can be granted. To the
    extent that Count I also contains a claim for “increased costs” that is distinct from
    1
    The facts recounted here are taken from the complaint. The court makes no
    findings of fact in this opinion. Although the government invites the court to consider
    exhibits attached to its motion to dismiss to support the dismissal of a portion of Count I
    of the complaint, the court does not require these exhibits for its analysis. See ECF No. 8
    at 7 n.2.
    2
    All citations to the Federal Acquisition Regulation (FAR) in this opinion are to the
    2018 version of Title 48 of the Code of Federal Regulations, unless otherwise noted.
    2
    plaintiff’s unabsorbed home office overhead claim, such a claim is not addressed in
    defendant’s motion for partial dismissal. ECF No. 8 at 10-11; ECF No. 16 at 1 n.1. For
    the reasons set forth below, neither of the claims identified by defendant’s motion can be
    dismissed pursuant to RCFC 12(b)(6).
    II.    Standard of Review
    When considering a motion to dismiss brought under RCFC 12(b)(6), “[w]e must
    presume that the facts are as alleged in the complaint, and make all reasonable inferences
    in favor of the plaintiff.” Cary v. United States, 
    552 F.3d 1373
    , 1376 (Fed. Cir. 2009)
    (citing Gould Inc. v. United States, 
    935 F.2d 1271
    , 1274 (Fed. Cir. 1991)). It is well-
    settled that a complaint should be dismissed under RCFC 12(b)(6) “when the facts
    asserted by the claimant do not entitle him to a legal remedy.” Lindsay v. United States,
    
    295 F.3d 1252
    , 1257 (Fed. Cir. 2002). “To survive a motion to dismiss, a complaint must
    contain sufficient factual matter, accepted as true, to ‘state a claim to relief that is
    plausible on its face.’” Ashcroft v. Iqbal, 
    556 U.S. 662
    , 678 (2009) (quoting Bell Atl.
    Corp. v. Twombly, 
    550 U.S. 544
    , 570 (2007)).
    III.   Analysis 3
    A.     Count I – Unabsorbed Overhead Claim
    1.     Introduction
    When the government delays a construction contract, so that no direct costs are
    incurred by the contractor for a period of time, fixed home office overhead costs, which
    normally are paid proportionally through payments for the direct costs of various
    construction projects, may be “unabsorbed.” Defendant’s motion provides this
    explanation of the concept:
    A contractor recovers these indirect costs, such as home office overhead, by
    allocating a share of these costs to each contract throughout the year, with
    allocation proportional to the direct costs of each contract. When the
    Government suspends performance under the contract, the contractor ceases
    to incur direct costs. If the Government requires the contractor to be on
    standby during the suspension, so to begin work immediately or on short
    notice, then the contractor may be unable to take on replacement work and
    recover the proportional share of the home office overhead originally
    allocated to the suspended project. This unrecovered home office overhead
    3
    The court has considered all of the parties’ arguments. The court only discusses in
    this opinion the arguments that were dispositive.
    3
    is unabsorbed during the period of suspension and, under very specific
    circumstances, a contractor may be entitled to compensation.
    ECF No. 8 at 11 (internal quotations and citations omitted). Plaintiff’s Count I clearly
    contains a claim for unabsorbed home office overhead. ECF No. 1 at 4-5; see also ECF
    No. 9 at 5 (“The reasonable implication of these allegations is that KUDSK was unable to
    bid on new work to cover its overhead costs during the suspension period, and that during
    that period of time the project was unable to cover its share of overhead expenses.”).
    This type of claim is often referred to as a claim for Eichleay damages, but here it is
    better to describe plaintiff’s claim as a claim for unabsorbed overhead. See ECF No. 8 at
    11-12 (citing Eichleay Corp., ASBCA No. 5183, 60-2 BCA ¶ 2688, 
    1960 WL 538
    (July
    29, 1960)).
    2.     Fact Issue Not Readily Resolved on a Motion to Dismiss
    Before turning to the elements of proof for unabsorbed overhead, and the question
    of whether plaintiff has stated a claim for unabsorbed overhead in this suit, the court
    notes that one of the elements of this type of claim is often fact intensive. The contractor
    must prove that while it was on standby, alternative work could not be performed during
    the delay in performance due to the contractor’s commitment to the government to return
    to the government’s project on short notice. See, e.g., P.J. Dick Inc. v. Principi, 
    324 F.3d 1364
    , 1371 (Fed. Cir. 2003) (stating that “the contractor must show that during that delay
    it was required to be ready to resume work on the contract, at full speed as well as
    immediately”) (citation omitted). The question of whether the contractor was on standby
    is more commonly addressed by this court on summary judgment than through the
    resolution of a motion to dismiss, and this factual question is not always even susceptible
    to resolution on summary judgment. See H.J. Lyness Constr., Inc. v. United States, 
    121 Fed. Cl. 287
    , 292-94, 296 (2015) (granting summary judgment in favor of the
    government because the contractor was not on standby during the period of delay), aff’d,
    652 F. App’x 972 (Fed. Cir. 2016) (table); JMR Constr. Corp. v. United States, 117 Fed.
    Cl. 436, 443-45 (2014) (denying the government’s motion for partial summary judgment
    as to the standby issue regarding the first period of delay, but granting summary
    judgment in favor of the government on the standby issue for the second period of delay);
    Redland Co. v. United States, 
    97 Fed. Cl. 736
    , 751 (2011) (granting summary judgment
    in favor of the government on the standby issue); Oak Envtl. Consultants, Inc. v. United
    States, 
    77 Fed. Cl. 688
    , 702 (2007) (denying cross motions for summary judgment, in
    part, because further fact-finding was needed to determine whether the contractor had
    been placed on standby); Ryco Constr., Inc. v. United States, 
    55 Fed. Cl. 184
    , 202 (2002)
    (denying the government summary judgment on Eichleay damages because it was “a
    triable issue whether plaintiff was on standby”). With this procedural consideration in
    mind, the court turns to the parties’ arguments regarding plaintiff’s claim for unabsorbed
    overhead in the circumstances of this contract dispute.
    3.     Precedential Guidance in Nicon Applied to This Case
    4
    According to defendant, plaintiff’s unabsorbed overhead claim is barred by the
    United States Court of Appeals for the Federal Circuit’s decision in Nicon, Inc. v. United
    States, 
    331 F.3d 878
    (Fed. Cir. 2003). ECF No. 8 at 13. The government has three
    propositions that are derived from its reading of Nicon. First, according to the
    government, no Eichleay damages can be awarded for delays that occur before a Notice
    to Proceed has issued. ECF No. 8 at 13 (citing 
    Nicon, 331 F.3d at 885
    ). Second, the
    government argues that no alternative compensation formula, different from the Eichleay
    formula, is applicable in this case, because the alternative formula permitted in Nicon can
    only be used in situations where unabsorbed overhead should be included in a
    termination for convenience settlement. 
    Id. at 14
    (relying on 
    Nicon, 331 F.3d at 888
    ;
    
    Redland, 97 Fed. Cl. at 748
    ). Third, defendant argues that Kudsk cannot show that it
    meets the strict prerequisites for an award of unabsorbed overhead, as these prerequisites
    are stated in Nicon. 
    Id. at 15
    (citing 
    Nicon, 331 F.3d at 885
    ). The court notes that
    defendant relies, to a great extent, on this court’s Redland decision for its interpretation of
    Nicon. 4 
    Id. at 11,
    14-17; ECF No. 16 at 2-8.
    a.      No Categorical Bar in Nicon Regarding Unabsorbed
    Overhead Claims for Pre-Performance Delays Caused by the
    Government
    There are two statements in Nicon which might bar unabsorbed overhead claims
    for delays that occur prior to the issuance of a Notice to Proceed. First, “[w]e agree with
    the Court of Federal Claims that constructive figures may not be substituted into the
    Eichleay formula and that use of the formula is limited to situations in which contract
    performance has begun and has been suspended by the government, causing the
    performance to take longer than originally anticipated.” 
    Nicon, 331 F.3d at 884
    .
    Similarly, the Federal Circuit reaffirmed this aspect of its holding: “The Court of Federal
    Claims was therefore correct in concluding that the Eichleay formula is only applicable in
    situations in which contract performance has begun.” 
    Id. The court
    notes, however, that
    each of these statements categorically limits the use of the Eichleay formula to delays that
    occur after a Notice to Proceed has issued, but neither of these statements addresses the
    question of whether unabsorbed overhead might be available if the quantum of the claim
    were calculated in some other way. 5
    4
    Decisions of this court do not establish binding precedent for this case. E.g.,
    W. Coast Gen. Corp. v. Dalton, 
    39 F.3d 312
    , 315 (Fed. Cir. 1994).
    5
    It should be noted that the Armed Services Board of Contract Appeals (ASBCA),
    in one decision, has interpreted the holding in Nicon to apply only to situations where the
    delay occurred before performance began and where the contract was never performed.
    See Alderman Bldg. Co., ASBCA No. 58082, 15-1 BCA ¶ 35841, 
    2014 WL 7260695
    (Dec. 9, 2014) (suggesting that the Eichleay formula still applies to pre-performance
    delays where contract performance later occurred, if the prerequisite elements to support
    5
    In Redland, this court interpreted those statements from the Federal Circuit, which
    limited the use of the Eichleay formula, as a ban on the availability of unabsorbed
    overhead for delays occurring before contract performance had 
    begun. 97 Fed. Cl. at 747-48
    (citing 
    Nicon, 331 F.3d at 884
    -85, 888). Here, the court prefers to adhere strictly
    to the text of Nicon. Plaintiff cannot benefit from the Eichleay formula, but there is no
    holding in Nicon which categorically bars plaintiff from recovering unabsorbed overhead
    for the three-month delay before the Army issued its Notice to Proceed. 6
    Indeed, the viability of a claim for unabsorbed overhead brought by a contractor
    who is prevented from starting construction is one of the primary holdings in 
    Nicon. 331 F.3d at 881
    (“We . . . remand for further proceedings to determine if Nicon may recover
    unabsorbed overhead damages as part of its termination for convenience settlement by
    some other method of allocation”); 
    id. at 884
    (“However, [just because the Eichleay
    formula is inapplicable] does not mean that a contractor, who is required to remain on
    standby because of a government-caused delay but is never allowed to begin
    performance, may not receive some of its unabsorbed home office overhead as part of its
    termination for convenience settlement by some other method of allocation.”); 
    id. at 886
    (“Even if there is no date set in the contract by which a notice to proceed must issue,
    there is an implied obligation on the part of the government to issue the notice to proceed
    within a reasonable time.” (citing Ross Eng’g Co. v. United States, 
    92 Ct. Cl. 253
    (1940)); 
    id. at 888
    (“[I]n situations in which contract performance has not yet begun, but
    the government terminates the contract for convenience after a period of delay, the
    contractor is not left without a remedy. The contractor may recover unabsorbed overhead
    costs as part of its termination for convenience settlement if a reasonable method of
    allocation can be determined on the facts of the case and the contractor can otherwise
    satisfy the strict prerequisites for recovery of unabsorbed overhead costs.”). Thus, the
    Federal Circuit allowed a claim for unabsorbed overhead to be litigated, where
    performance had not begun and the contract was terminated for the convenience of the
    government. In the court’s view, the text of the Nicon decision does not include a
    categorical bar on claims for unabsorbed overhead based on delays that occur before a
    Notice to Proceed is issued, and respectfully disagrees with the Redland decision on this
    point.
    b.     Alternative Formulas Not Necessarily Barred by Nicon
    There are two plausible readings of Nicon regarding the use of alternative
    formulas, other than the Eichleay formula, to support an unabsorbed overhead claim.
    a claim for Eichleay damages are met (citing 
    Nicon, 331 F.3d at 888
    )). In the court’s
    view, this reading of Nicon is not persuasive. See infra note 7.
    6
    The court notes that the interpretation of Nicon presented in Redland has not been
    cited in later decisions on the topic of claims for unabsorbed overhead.
    6
    Relying on Redland, the government argues that in Nicon, alternative formulas were only
    approved for use in the circumstance where a pre-performance delay was followed by a
    termination for convenience before performance could occur. 7 ECF No. 8 at 14 (citing
    
    Redland, 97 Fed. Cl. at 748
    ); ECF No. 16 at 3-4 (citing 
    Redland, 97 Fed. Cl. at 747
    ).
    One could also read Nicon as creating an exception which allows for the use of
    alternative formulas in the context of pre-performance delays followed by a termination
    for convenience, and leaving open the possibility that this exception could be extended to
    other pre-performance delay scenarios.
    This court’s decision in Redland notes that using alternative formulas to show
    unabsorbed overhead for anything other than a termination for convenience settlement
    would be an extension of Nicon. See 
    Redland, 97 Fed. Cl. at 748
    (stating that “the court
    need not decide whether Nicon’s holding can be extended to other situations”). The court
    has not found any binding precedent on this topic. In the absence of binding precedent as
    to the possible extension of the exception created by the Nicon decision for alternatives to
    the Eichleay formula, the court cannot state that Kudsk’s unabsorbed overhead claim is
    foreclosed as a matter of law by the Nicon decision.
    c.     Nicon’s Strict Prerequisites for Unabsorbed Overhead Claims
    Involve Disputed Facts
    As the Federal Circuit’s most recent pronouncement on unabsorbed overhead
    claim prerequisites, Nicon provides binding precedent that must be applied in this case. 8
    7
    In Alderman, the ASBCA also construed the Nicon exception, allowing alternative
    formulas to support a claim for unabsorbed overhead, as a narrow one that only applies to
    termination for convenience cases. See Alderman, 
    2014 WL 7260695
    (asserting that the
    Nicon “court stressed that its holding did not extend to cases in which ‘performance of
    the contract does eventually occur or resume after the government-caused delay’”
    (quoting 
    Nicon, 331 F.3d at 883
    ) (emphases added)). But that quote in Alderman is not
    the holding of Nicon. The full sentence in Nicon, which is only partially quoted by the
    ASBCA, is not a holding but a description of other cases which are distinguishable
    because they arose from different facts: “In the typical cases dealing with the application
    of the Eichleay formula, performance of the contract does eventually occur or resume
    after the government caused 
    delay.” 331 F.3d at 883
    . The clear holding in Nicon is
    found, instead, in this statement: “the Eichleay formula is only applicable in situations in
    which contract performance has begun.” 
    Id. at 884.
    8
    This type of unabsorbed overhead claim is the subject of “long standing” guidance
    in binding precedent, Capital Elec. Co. v. United States, 
    729 F.2d 743
    , 747 (Fed. Cir.
    1984), and the Nicon decision must be presumed to correctly apply this entire body of
    precedent, see Johnston v. IVAC Corp., 
    885 F.2d 1574
    , 1579 (Fed. Cir. 1989) (“Where
    conflicting statements . . . appear in our precedent, the panel is obligated to review the
    cases and reconcile or explain the statements, if possible.”); see also P.J. Dick, 
    324 F.3d 7
    The three prerequisites are as follows: (1) “there must have been a government-caused
    delay of uncertain duration”; (2) “[t]he contractor must also show that the delay extended
    the original time for performance or that, even though the contract was finished within
    the required time period, the contractor incurred additional costs because he had planned
    to finish earlier”; and (3) “the contractor must have been on standby and unable to take
    on other work during the delay period.” 
    Nicon, 331 F.3d at 883
    (citations omitted). The
    government appears to concede that the complaint alleges a government-caused delay of
    uncertain duration. ECF No. 8 at 15.
    As to the second and third prerequisites, plaintiff argues that the complaint
    proffers sufficient facts for these elements, or, in the alternative, that leave to amend the
    complaint should be given to set forth adequate facts in support of these elements. ECF
    No. 9 at 5-6. As a threshold matter, the court notes that the parties dispute whether
    plaintiff’s contract was completed on time. ECF No. 1 at 3; ECF No. 7 at 2 (answer).
    The parties also hotly dispute whether plaintiff was on standby from September 11, 2009,
    through December 11, 2009. ECF No. 8 at 16-17; ECF No. 9 at 5-6; ECF No. 16 at 6-7.
    In this regard, plaintiff has alleged that its bonding capacity, strained by the government’s
    project, would not allow it to take on other work while it was on standby. ECF No. 1 at
    4.
    The court concludes that the complaint contains a plausible unabsorbed overhead
    claim in Count I, under Nicon. 9 Both parties intend to file motions for summary
    judgment at the close of discovery. See ECF No. 17 at 2 (joint preliminary status report).
    Whether plaintiff’s unabsorbed overhead claim will survive cross-motions for summary
    judgment is a question the court reserves for further inquiry. Plaintiff may seek leave, at
    its option, to amend its complaint in light of the court’s holdings in this opinion regarding
    Count I.
    B.     Count IV – ARRA Reporting Requirements
    at 1372 (looking to the Federal Circuit’s “later decisions” for guidance on the standby
    prerequisite for unabsorbed overhead claims).
    9
    Plaintiff relies upon Interstate General Government Contractors, Inc. v. West, 
    12 F.3d 1053
    (Fed. Cir. 1993), as support for the viability of an unabsorbed overhead claim
    based on pre-performance delay, and as support for recovery through FAR 52.233-3.
    ECF No. 9 at 3-4. The court agrees that Interstate, when read in conjunction with the
    majority’s opinion in Nicon, adds plausibility to plaintiff’s claim in Count I. The court
    notes, too, that Interstate contains seminal guidance regarding the elements of proof for
    an unabsorbed overhead claim, as evidenced by extensive citations to Interstate in both
    Nicon and P.J. Dick. To the extent that defendant’s reply brief could be read to conclude
    that Interstate is no longer good law, the court would disagree. ECF No. 16 at 5.
    8
    According to Count IV of the complaint, Kudsk “incurred administrative costs
    preparing and submitting ARRA reports to the Contracting Officer along with its monthly
    payment applications.” ECF No. 1 at 9. Plaintiff views these costs as flowing from a
    unilateral change to the contract for which the government must pay. 
    Id. The government
    argues that ARRA reporting requirements must be incorporated into the
    contract through the Christian doctrine and that the Army owes nothing to Kudsk for the
    costs of compliance with these requirements. See ECF No. 8 at 19, 22-25 (citing G. L.
    Christian & Assocs. v. United States, 
    320 F.2d 345
    (Ct. Cl. 1963) (Christian II); G. L.
    Christian & Assocs. v. United States, 
    312 F.2d 418
    (Ct. Cl. 1963) (Christian I). It is not
    clear to the court, however, that the Christian doctrine applies to ARRA reporting
    requirements in the circumstances of this case.
    1.     Christian Doctrine Overview
    Generally, “under the Christian doctrine, a court may insert a clause into a
    government contract by operation of law if that clause is required under applicable
    federal administrative regulations.” K-Con, Inc. v. Sec’y of Army, 
    908 F.3d 719
    , 724
    (Fed. Cir. 2018) (citation omitted). “For a court to incorporate a clause into a contract
    under the Christian doctrine, it generally must find (1) that the clause is mandatory; and
    (2) that it expresses a significant or deeply ingrained strand of public procurement
    policy.” 
    Id. (citation omitted).
    The first prong of the doctrine is satisfied if the clause is
    mandatory, i.e., if the clause is required by statute or regulation. 
    Id. The second
    prong
    often examines how long a particular practice or policy has been in existence. See 
    id. at 726
    (noting that the bonding requirement discussed in that case had been a feature of
    government construction contracts since 1935). A court may also consider whether the
    policy or practice serves a vital purpose in protecting the government from excessive
    contract payments. See, e.g., Gen. Eng’g & Mach. Works v. O’Keefe, 
    991 F.2d 775
    , 780
    (Fed. Cir. 1993) (General Engineering) (incorporating into a government contract an
    omitted, mandatory clause because, in part, it “discourages the unnecessary and wasteful
    spending of government money”).
    2.     Christian Doctrine Prong One: Whether ARRA Reporting
    Requirements Were Mandatory for Plaintiff’s Contract
    The inquiry into the first prong of the Christian doctrine, as it might apply to
    plaintiff’s construction contract, focuses, first, on regulatory language. As defendant
    argues, the relevant FAR provisions were phrased in terms that were mandatory in nature,
    so that contractors benefiting from ARRA funds were required to submit reports which
    tracked the expenditure of ARRA funds in various ways. See ECF No. 8 at 21-22 (citing
    Federal Register for amendments to the FAR addressing ARRA reporting requirements,
    such as former provisions, specifically FAR 4.1500, FAR 4.1501(c), FAR 4.1502, and
    FAR 52.204-11, which are no longer contained in the current FAR); see also FAR Case
    2009-009, American Recovery and Reinvestment Act of 2009 (the Recovery Act)--
    Reporting Requirements, 74 Fed. Reg. 14639, 14644-46 (Mar. 31, 2009)). Thus, there
    9
    appears to be no real dispute that under the version of the FAR that was applicable when
    Kudsk entered into its contract with the Army, ARRA reporting requirements were
    established in the FAR as mandatory. This determination does not end the inquiry,
    however.
    It is not clear from the record that Kudsk’s contract with the Army, Contract No.
    W9124N-09-C-0040, was funded in whole or in part by ARRA funds. The complaint
    alleges that the contracting officer informed Kudsk it should begin submitting ARRA
    reports in July 2010, approximately ten months after contract award and approximately
    seven months after Kudsk received the Notice to Proceed with contract performance.
    ECF No. 1 at 8. Nowhere in defendant’s answer, motion to dismiss, or reply brief,
    however, does the government affirmatively state that Contract No. W9124N-09-C-0040
    was funded in whole or in part with ARRA funds. Instead, defendant merely asserts that
    “Kudsk does not allege that its contract was not funded through the ARRA, or any other
    reason why the ARRA reporting requirements would not be applicable.” ECF No. 8 at
    25. Thus, defendant’s argument that ARRA reporting was mandatory for Contract No.
    W9124N-09-C-0040 is not supported by any evidence that ARRA funding for this
    contract triggered the mandatory reporting requirements set forth in the FAR at that time.
    Nor has defendant alleged that Kudsk was on notice that its contract was funded in
    whole or in part by ARRA funds. Indeed, the most obvious, and mandatory, provision of
    such notice would have been the inclusion of FAR 52.204-11 setting forth ARRA
    reporting requirements with which Kudsk would need to comply. See ECF No. 8 at
    21-22 (arguing that at this time FAR 4.1502 required contracting officers to insert FAR
    52.204-11 into all solicitations funded in whole or in part by ARRA). Plaintiff’s
    complaint states that FAR 52.204-11 was not included in Contract No.
    W9124N-09-C-0040, and that Kudsk refused to sign a bilateral modification that would
    have inserted this clause into the contract after performance had begun. ECF No. 1 at
    8-9. Defendant accepts this allegation in the complaint as true for the purposes of its
    motion to dismiss. ECF No. 8 at 23. Further, the government does not contend that
    notice of ARRA funding for Contract No. W9124N-09-C-0040 was provided to Kudsk
    by some other means.
    Lack of notice, on this record, undermines defendant’s argument that Kudsk
    cannot escape the incorporation of FAR 52.204-11 into its contract. Defendant argues
    that Kudsk was aware, or should have been aware, of ARRA reporting requirements.
    ECF No. 8 at 25 (citing General 
    Engineering, 991 F.2d at 780
    ). But unless Kudsk was on
    notice that its contract, Contract No. W9124N-09-C-0040, used ARRA funds and thus
    would be subject to ARRA reporting requirements, its awareness, or presumed
    awareness, of ARRA reporting requirements in the FAR would be immaterial.
    To restate the court’s analysis regarding prong one of the Christian doctrine
    inquiry, the court agrees with defendant that ARRA reporting requirements were
    mandatory. However, the record does not establish that Contract No.
    10
    W9124N-09-C-0040 was funded in whole or in part with ARRA funds, or that plaintiff
    was on notice that it was entering into a contract subject to ARRA reporting
    requirements. Given the current state of the record before the court, prong one of the
    Christian doctrine has not been satisfied. In other words, defendant has not shown that
    FAR 52.204-11 was a mandatory contract clause that should be incorporated into
    Contract No. W9124N-09-C-0040 pursuant to the Christian doctrine.
    3.     Christian Doctrine Prong Two: Whether ARRA Reporting
    Requirements Expressed a Deeply Ingrained Public Procurement
    Policy
    The government does not fare any better when the court examines, under prong
    two, the public policies expressed in ARRA reporting requirements. Plaintiff notes that
    ARRA reporting requirements only remained part of federal government procurement
    policy for about five years, beginning with 2009, the year Kudsk entered into this
    contract with the Army. ECF No. 9 at 7. Indeed, it is difficult to see a parallel between
    the venerable procurement policy discussed in Christian I—the right for the government
    to terminate a contract for convenience, which has been consistently protected since
    World War II—or the bonding requirement in K-Con, which has been in place since
    1935. 
    K-Con, 908 F.3d at 726
    ; Christian 
    I, 312 F.2d at 426
    . The court must agree with
    plaintiff that ARRA reporting requirements, which were newly-minted to track the effects
    of a specific economic stimulus package, were not the expression of a deeply ingrained
    federal procurement policy.
    Defendant argues, nonetheless, that ARRA reporting requirements were similar to
    other contract clauses incorporated into procurement contracts by the Christian doctrine,
    because these requirements discouraged “‘unnecessary and wasteful spending of
    government money,’” and thus satisfied the significant and deeply ingrained procurement
    policy prong of the doctrine. ECF No. 16 at 10 (quoting General 
    Engineering, 991 F.2d at 780
    ). The government’s argument is colorable, in that some of the various ARRA
    reporting requirements could, indeed, help identify wasteful government spending. But
    the focus of ARRA reporting requirements, as evidenced by the expiration of these
    reporting requirements after five years, appears to have been on ensuring accountability
    to the American public with respect to a massive and time-limited effort to leverage this
    country out of an economic recession. See ECF No. 8 at 19-21 (describing the purposes
    of ARRA). ARRA reporting requirements were not, therefore, analogous to the contract
    clauses expressing deeply ingrained and significant procurement policies incorporated
    into the contracts discussed in Christian I, K-Con, or General Engineering.
    Based on its review of the record now before the court, neither prong of the
    Christian doctrine analysis supports the incorporation of ARRA reporting requirements
    into plaintiff’s contract. Count IV, in consequence, survives defendant’s motion to
    dismiss.
    11
    IV.   Conclusion
    Both Count I and Count IV of the complaint contain plausible claims. On or
    before September 20, 2019, if desired, plaintiff may move to amend its complaint in
    light of the court’s holdings in this opinion regarding Count I. Any such motion must
    present the proposed amended complaint as an attachment to the motion and must also
    state the government’s position on the motion.
    In accordance with the foregoing, defendant’s motion for partial dismissal, ECF
    No. 8, is DENIED. On or before September 20, 2019, the parties are directed to FILE a
    joint status report proposing the next steps in this litigation. In addition, should this
    decision require the parties to request leave to amend the discovery schedule in this
    matter, see ECF No. 18 (order), the parties shall do so by filing an appropriate joint
    motion with the court.
    IT IS SO ORDERED.
    s/Patricia E. Campbell-Smith
    PATRICIA E. CAMPBELL-SMITH
    Judge
    12