Fort Howard Senior Housing Associates, LLC v. United States , 2015 U.S. Claims LEXIS 665 ( 2015 )


Menu:
  •         In the United States Court of Federal Claims
    No. 10-553C
    (Filed: May 29, 2015)
    )
    FORT HOWARD SENIOR                       )
    HOUSING ASSOCIATES, LLC,                 )
    )
    Plaintiff,           )
    Enhanced-Use Lease; Department of
    )
    Veterans Affairs; Termination for Default;
    v.                                       )       Breach of Contract; Excuse; Force
    )       Majeure; Reformation; Mutual Mistake;
    THE UNITED STATES,                       )       Impossibility
    )
    Defendant.           )
    )
    Steven H. Jesser, Glenview, IL, for plaintiff.
    Sheryl Lynn Floyd, Civil Division, U.S. Department of Justice, Washington, DC,
    with whom were Joyce R. Branda, Acting Assistant Attorney General, and Robert E.
    Kirschman, Jr., Director, Commercial Litigation Branch, for defendant.
    OPINION
    FIRESTONE, Judge.
    Pending before the court is the government’s motion for summary judgment, filed
    pursuant to Rule 56 of the Rules of the United States Court of Federal Claims (“RCFC”).
    At issue is whether the Department of Veterans Affairs (“VA”) properly terminated for
    default the September 28, 2006 Enhanced-Use Lease (“Lease”) between the VA and
    plaintiff Fort Howard Senior Housing Associates, LLC (“FHSHA”) at the Fort Howard
    VA Medical Center in Baltimore County, Maryland. The Lease was executed pursuant to
    the VA’s authority under 
    38 U.S.C. §§ 8161-8167
     and gave FHSHA the right to occupy
    1
    the property for a term of 65 years, with an option to extend the Lease for 10 additional
    years. In exchange for its occupation, FHSHA was required to (1) pay consideration in
    the form of rent; (2) design, develop and construct a new 10,000 square foot Community-
    Based Outpatient Clinic (“CBOC”) within 39 months; (3) design and construct multi-use
    residences onsite in compliance with “applicable” state and local laws, codes, and
    regulations; and (4) protect, preserve, maintain, and repair the property.
    After several years, the VA became concerned about the status of the project and,
    starting in February 2009, the VA began sending notices of default to FHSHA.
    Ultimately, the VA determined that FHSHA was in default of the Lease and, on August
    17, 2009, the VA terminated the Lease for default on the primary grounds that FHSHA
    had failed to (1) commence construction of the new CBOC such that it would be
    completed with the timeframe required under the Lease,1 (2) maintain and secure the
    property, and (3) pay its proportionate share of the utility bills.
    FHSHA filed its initial complaint on August 16, 2010 and an amended complaint
    on June 29, 2012.2 In its complaint, plaintiff asserts that the VA’s termination was
    wrongful on two main grounds: (1) its failure to build the CBOC was excused by the
    force majeure clause in the Lease, and (2) the government otherwise breached the Lease
    1
    Plaintiff had not yet begun construction.
    2
    Plaintiff’s amended complaint added a new count for “tortious interference with contractual
    relationships and prospective economic advantages” and a claim for money damages based on
    costs, fees and expenses and for future development fees and profits. The court dismissed
    plaintiff’s money claims for lack of jurisdiction on September 11, 2012, on the grounds that
    plaintiff had not submitted its money claims to a contracting officer as required by the Contract
    Disputes Act, 
    41 U.S.C. §§ 7101-7109
    . Order Granting Motion to Dismiss, Fort Howard Senior
    Housing Associates, LLC v. United States, No. 10-553 (Fed. Cl. Sept. 11, 2012).
    2
    on various grounds. In its amended answer, the government counterclaimed for breach of
    the Lease and seeks $313,328.45 as the amount allegedly owed to the government under
    the Lease.
    At the heart of FHSHA’s defense to the termination is its contention that it entered
    into the Lease with the understanding that it would be able to build 1,300 housing units
    on the site and that VA’s requirement that it comply with Baltimore County zoning
    regulations—which without a variance would limit development to 550 units—made the
    project economically unviable, requiring renegotiation. FHSHA argues that Baltimore
    County’s failure to accept plaintiff’s request for an exemption from local requirements
    amounted to a force majeure event under the terms of the Lease. Plaintiff further argues
    that the VA’s insistence that plaintiff comply with local laws in connection with the
    project amounted to a breach of contract on several grounds and further excused
    FHSHA’s obligations under the Lease. Plaintiff argues that the VA, as the federal
    government, is not required to comply with local laws and regulations, and thus it was the
    VA’s insistence that plaintiff meet local zoning requirements that made the project
    economically unviable.
    Discovery in the case is now completed. The government has moved for summary
    judgment, asking the court to find that the undisputed facts establish that the termination
    for default was reasonable and proper and that plaintiff’s nonperformance is not
    excusable for any of the reasons advanced by the plaintiff. In response, FHSHA argues
    that the government’s motion should be denied on the grounds that there are genuine
    issues of material fact as to each of the government’s alleged grounds for termination for
    3
    default and that, even if the termination was correct, FHSHA has presented sufficient
    facts to show that the failure to act was excusable under the Lease. For the reasons set
    forth below, the court finds that the government is entitled to summary judgment with
    regard to the default termination for failing to build the CBOC and that the grounds
    asserted by FHSHA for its failure to act do not constitute excuses as a matter of law.
    Because FHSHA’s failure to build the CBOC within the time provided for under the
    Lease justified a termination for default and the failure cannot be excused, the court does
    not reach the alternative grounds for summary judgment set forth in the government’s
    motion.
    I.     STATEMENT OF UNDISPUTED FACTS
    The following facts are not disputed. Disputed facts relevant to FHSHA’s defense
    that its failure to perform was “excused” are discussed in connection with those claims.
    A.     The Lease
    The authority for the VA to enter enhanced-use leases (“EUL”) such as the Lease
    is set forth in 
    38 U.S.C. §§ 8161-8167
    . Pursuant to VA Handbook and Directive 7415,
    the VA Secretary assigned the Office of Asset Enterprise Management as the office
    within VA responsible for oversight of VA’s EUL program and management of
    enhanced-use projects identified as VA asset initiatives. Def.’s App’x 295-323, VA
    Handbook and Directive 7415.
    1.     Scope of the Lease
    On September 28, 2006, FHSHA and VA entered into an EUL. The Lease
    identifies that FHSHA’s role is to serve as the “master developer of the Property, with the
    4
    right and obligation to design, develop, construct, alter, operate, maintain, repair, replace,
    sublease, finance, improve and renovate the Property into the Project, and to demolish
    any existing buildings, structures and improvements on the Property, in accordance with
    the terms of this Lease.” Def.’s App’x 2. The Lease defines “Project” as “[t]he Lessee’s
    design, development, construction, demolition, alteration, operation, maintenance, repair,
    replacement, subleasing, financing, improvement, and renovation of the Property as
    provided in this Lease.” Pursuant to the Lease, the VA leased the “Property” to FHSHA
    for a term of 65 years, with a FHSHA option to extend for an additional 10-year period as
    long as an uncured Lessee Event of Default did not exist. The Lease defines “Property”
    as:
    [t]hat certain real property consisting of approximately ninety (90) acres (i)
    as described and depicted in Exhibits A, with Attachment 1 to Exhibit A,
    and E attached hereto and includes (ii) all buildings, improvements, utilities
    and infrastructure either existing or erected or placed thereon, but: (1) will
    not include the CBOC Parcel and the CBOC when the CBOC Parcel and
    CBOC revert to VA upon the completion of construction and acceptance by
    the Department, in accordance with Article 4, paragraph A.4. and (2) will
    include the ten contiguous acres for the State of Maryland Veterans Home
    described in Exhibit A, with Attachment 1 to Exhibit A, and Exhibit H in
    the event that such ten contiguous acres are added to this Lease during the
    term by amendment in accordance with Article 4.A.5 of this Lease.
    
    Id. at 7
    , Article 1. The Lease defines “CBOC” as the 10,000 square foot Community-
    Based Outpatient Clinic to be designed, developed and constructed on the Property by
    FHSHA for the VA as part of the consideration provided by FHSHA to VA under the
    Lease. 
    Id. at 4
    .
    2.     FHSHA’s Consideration
    5
    In exchange for VA leasing the Property to FHSHA, FHSHA agreed to provide
    VA consideration in the form of “Rent,” and to complete both a housing project and an
    outpatient clinic. The Lease defines “Rent” as
    [c]onsideration provided to VA for the Lease pursuant to Title 38 U.S.C.
    Section 8162 that includes discounts to veterans as described in Exhibit G,
    paragraph G.1; and in the event that discounts to veterans are not provided
    in accordance with Exhibit G, paragraph G.3, payments to VA as
    compensation for such failure to provide such discounts to veterans in
    accordance with Article 23.c.3.c.
    
    Id. at 7-8
    . Article 4 of the Lease identifies the additional items that FHSHA and VA
    agreed “constitute fair consideration for the Lease.” 
    Id. at 10
    ; 
    id. at 892
    , Infantino Dep.
    149:4-20, Jan. 23, 2014.
    Pursuant to Article 4.A.1 of the Lease, FHSHA agreed to:
    Finance, design, develop, construct, demolish, alter, operate, maintain,
    repair, replace, sublease, improve, renovate and market the Property into
    the “Project” in accordance with this Lease (including but not limited to
    Article 10 hereof), all applicable local and State laws, codes and
    ordinances, and the National Fire Protection Association (“NFPA”) 101
    Life Safety Code.
    
    Id. at 10
    , Article 4.A.1. Pursuant to Article 4.A.2 of the Lease, FHSHA agreed to:
    [(i)] obtain all applicable local and State permits, licenses, and approvals
    (including those approvals of VA) necessary for construction and operation
    of the Permitted Uses; (ii) comply with all applicable local, State, and
    Federal requirements during operation of the Permitted Uses (including the
    applicable version of the National Fire Protection Association (NFPA) 101
    Life Safety Code); (iii) undertake its construction and operation activities
    so as to not unreasonably interfere with the operations, or otherwise deprive
    the Department of its quiet use and enjoyment of the CBOC or such other
    facilities on the Property as may be under VA possession, control, use
    and/or occupancy (“VA Facilities”) and use all reasonable and commercial
    efforts to conduct any of its construction activities involving noise, dirt, or
    other emissions that could negatively affect activities or operations of VA
    Facilities to times falling within normal business hours; and (iv) operate the
    6
    Project in accordance with existing applicable laws pertaining to a drug-
    free environment.
    
    Id.,
     Article 4.A.2. Pursuant to Article 4.A.3 of the Lease, FHSHA agreed to
    “[a]ccomplish a phased reuse and redevelopment of the Property, not to exceed three (3)
    phases, as set forth in the ‘Parcelization Plan’ in the Development Plan hereto, within one
    hundred and fifty-nine (159) months after the Effective Date . . . .” 
    Id.,
     Article 4.A.3.
    Pursuant to Article 4.A.4 of the Lease, FHSHA agreed to
    [d]esign, construct, and develop a 10,000 GSF VA Outpatient Clinic
    facility (CBOC) on a parcel of the Property (“CBOC Parcel”) . . . . Lessee
    shall complete the construction of the CBOC and obtain final acceptance
    thereof . . . no later than thirty-nine (39) months after the Effective Date . . .
    . Upon completion of construction of the CBOC and final acceptance by
    [the VA], Lessee shall, at no expense or liability to [the VA], transfer all of
    Lessee’s right, title and interest in and to the CBOC to [the VA], and
    simultaneously Lessee’s leasehold interest in the CBOC Parcel shall
    automatically revert to VA at no expense or liability to [the VA] and the
    CBOC shall cease being part of the Property.
    
    Id. at 11
    , Article 4.A.4. Article 10.H.1 further requires that, “Except for the CBOC,
    Lessee shall (i) conduct the Project Development so as to comply with all applicable
    State and local laws, codes, ordinances, permits and inspections . . . .” 
    Id. at 26
    , Article
    10.H.1.
    Articles 4.A.3 and 4.A.4 are subject to the force majeure clause, which the Lease
    defines as
    [a]ny of the following that directly cause any of Lessee’s obligations
    hereunder not to be performed in a timely manner: (1) an earthquake,
    hurricane, tornado, flood, or other similar act of God; (2) fire; (3) strikes or
    similar labor disputes provided such strike or similar dispute is beyond
    Lessee’s control and provided Lessee takes all steps reasonably possible to
    remediate such strike or similar dispute; (4) acts of the public enemy; (5)
    inability to obtain labor or materials or clear access to the Project or
    7
    unreasonable delay in approving permit applications for the Project by
    reason of acts or omissions of any governmental body not caused by
    Lessee’s actions or omissions; (6) rebellions, riots, insurrections or civil
    unrest; (7) unusually severe weather conditions that actually cause similar
    construction or development activities in the area of the Project to be
    suspended; or (8) an unknown environmental hazard or unknown hazardous
    substance (e.g., one that Lessee did not know of or have notice of by the
    Effective Date) affecting the Property.
    
    Id. at 5
    , Article 1.
    In addition to the housing project and outpatient clinic, FHSHA agreed to provide
    upkeep services for the property. Pursuant to Article 4.A.7 of the Lease, FHSHA agreed
    to “[b]e responsible for the operation, management, and maintenance of the Property in
    accordance with the provisions herein . . . .” 
    Id. at 12
    , Article 4.A.7. Pursuant to Article
    4.A.9 of the Lease, FHSHA agreed to “[b]e responsible for maintaining and securing all
    necessary access to the Property for construction and operation of the Project and
    underlying facilities.” 
    Id. at 13
    , Article 4.A.9. Pursuant to Article 4.D of the Lease,
    FHSHA agreed that, “Throughout the Term, Lessee shall maintain the Property in a good,
    clean and safe condition and shall make all repairs thereto, interior and exterior and
    structural and non-structural which are required to maintain the Property in a good, clean
    and safe condition.” 
    Id. at 15
    , Article 4.D. Pursuant to Article 4.E of the Lease, FHSHA
    agreed that, “During the Term, Lessee shall be responsible for providing or arranging for,
    at no cost or expense to VA, the infrastructure (including without limitation, all utility
    metering) for all water, gas, electricity, sewer, telephone and other utilities serving the
    Property . . . .” 
    Id.,
     Article 4.E.
    3.      Compliance with Federal, State, and Local Laws
    8
    Consistent with 
    38 U.S.C. § 8167
     (2004), Article 17.A of the Lease states, “The
    United States’ fee title interest in the Property and [the VA’s] interest in this Lease shall
    not be subject, directly or indirectly, to any State or local laws relative to taxation, fees,
    assessment or special assessments.” 
    Id. at 44
    , Article 17.A.
    Article 17.C of the Lease states, “It is understood that the intent of the parties is
    that [the VA] shall not be obligated to pay any charges, impositions, or assessments
    directly or indirectly made against the Property during the term hereof.” 
    Id.,
     Article
    17.C.
    Further, Article 33 of the Lease states:
    Unless the Lessee can demonstrate to the satisfaction of [VA] in the form
    of a written determination or written correspondence from the U.S.
    Department of Labor that the Lease or the Project is exempt therefrom,
    Lessee shall comply with the requirements of the Davis-Bacon Act, as
    amended, 40 U.S.C. Section 3141 et. seq. and the relevant rules, regulations
    and orders of the Secretary of Labor applicable thereto.
    
    Id. at 64
    , Article 33. Additionally, as discussed below, Articles 4.A.1, 4.A.2, and 10.H.1
    of the Lease set standards for the specific requirements for FHSHA’s compliance with
    local and state laws.
    4.       Representations, Warranties, and Covenants
    Pursuant to Article 6.C.1 of the Lease, FHSHA represented, warranted, and
    covenanted that “[VA] has made no representations concerning the Property’s condition,
    nor has it agreed to alter or improve the Property.” 
    Id. at 19
    , Article 6.C.1.
    Additionally, pursuant to Article 6.C.2 of the Lease, FHSHA represented,
    warranted, and covenanted that
    9
    [VA] has made no representations or warranties concerning the fitness or
    suitability for any particular use of the Property and except as provided in
    the Lease (including but not limited to provisions in Article 4 and Article 6
    pertaining the responsibility of [VA] and United States with respect to
    hazardous substances) [VA] shall not be liable for any latent or patent
    defect in such Property, nor has it agreed to alter, improve or maintain such
    Property.
    
    Id. at 20
    , Article 6.C.2.
    5.             The Development Plan
    As described in Article 10.A.1 of the Lease, “Lessee has commenced and
    completed the Development Plan which sets forth Lessee’s overall plans, including but
    not limited to planned Permitted Uses for the Parcels, for developing the Property into the
    Project pursuant to this Lease . . . .” 
    Id. at 23
    , Article 10.A.1.3 The Development Plan
    includes, amongst other items, the obligation to construct 1,300 units—including 353
    active senior units; 481 independent living units; 165 assisted living units; and 106
    skilled nursing units—and 170,000 square feet of amenities and services. 
    Id. at 98, 103
    .4
    Pursuant to Article 4.A.3 of the Lease, FHSHA was required to develop the Property in
    accordance with the Development Plan. 
    Id. at 10
    .
    Article 24.H of the Lease states, “[I]n the event of a conflict in interpretation of
    provisions of this Lease between the Development Plan at Exhibit E of this Lease, and
    Articles 1-31 or any other Exhibit of this Lease, Articles 1-31 or any other Exhibit of this
    3
    The Development Plan was attached to the Lease as Exhibit E and was never amended by the
    parties. 
    Id. at 80-187
    , Exhibit E, Development Plan.
    4
    The Development Plan did not reference the Baltimore County Land Use Regulation, which
    plaintiff contends would have limited the project to only 550 housing units. See 
    id. at 93, 971
    .
    10
    Lease shall control . . . .” 
    Id. at 54
    , Article 24.H; 
    id. at 915
    , Infantino Dep., 221:9-222:3,
    Jan. 23, 2014.
    Article 16.C.11 of the Lease states:
    [VA] and the Lessee shall cooperate by considering any and all proposed
    Lease amendments which may be requested by any proposed lender, or
    may otherwise be reasonably necessary, to implement the provisions of this
    Article; provided, however, that any such amendment shall not in any way
    affect the Term or the rent nor affect adversely in any material respect any
    rights of the Department under this Lease.
    
    Id. at 44
    , Article 16.C.11. Similarly, Article 24.T of the Lease states:
    [VA] and Lessee shall cooperate in including in this Lease by suitable
    amendment from time to time any provision which may be requested by
    any proposed lender; provided, however, that any such amendment shall
    not in any way affect the Term nor affect adversely in any material respect
    any rights of the Department under this Lease.
    
    Id. at 57
    , Article 24.T.
    6.      Default
    Article 23.A of the Lease itemizes what is considered an “Event of Default” by
    Lessee. Amongst other items, Events of Default include:
    Lessee fails to pay any monetary obligation due under the provisions of this
    Lease, and such failure is not cured within the manner and time periods
    provided by Article 23.B of this Lease;
    Failure of Lessee, its assigns or sublessees, to perform or observe any
    material requirement, consideration, covenant, condition and/or
    commitment required by this Lease, and such failure is not cured within the
    manner and time periods provided for by Article 23.B of this Lease;
    [L]essee fails to complete Phase I of the Development Plan as follows: (a)
    Construct the CBOC and obtain a Certificate of Acceptance by [VA] within
    thirty-nine (39) months of the Effective Date in accordance with
    Development Plan, or (b) Complete construction and commence operation
    11
    of the LCC facilities pursuant to Phase I of the Development Plan within
    fifty-seven (57) months of the Effective Date.
    
    Id. at 49-50
    , Article 23.A. Article 23.C.1 of the Lease states:
    Upon the occurrence of a Lessee Event of Default in failing to complete
    construction of Phase 1 (including failure to complete the CBOC and
    convey title to VA), as provided in Paragraph A.6 of this Article 23, which
    either (a) continues beyond the expiration of any applicable notice and cure
    periods, or (b) is not fully cured after the end of sixty-three (63) months
    following the Effective Date, extended by a period equal to the period or
    periods of Force Majeure, if any, that prevented such completion of
    construction by such period of sixty-three (63) months, whichever event of
    clause (a) or (b) of this paragraph C.1 first occurs, VA may,
    notwithstanding Article 16 or any other provisions of this Article, terminate
    the Lease for such uncured Lessee Event of Default . . . .
    
    Id. at 50
    , Article 23.C.1. Article 23.C.2 of the Lease states:
    In the event that Lessee is in default of Article 23.A.3 of this Lease for
    failure to pay Rent to the Department, and Lessee fails to cure the default in
    accordance with Article 23.B of this Lease, the Department may,
    notwithstanding Article 16 or any other provisions of this Lease, terminate
    this Lease for such uncured Lessee Event of Default . . . .
    
    Id. at 51
    , Article 23.C.2.
    B.     VA Default Notices and Cure Letters
    Plaintiff has affirmed that, in accordance with the procedures outlined in Article
    23 of the Lease, the VA sent numerous notices of default and requests to cure to FHSHA
    when FHSHA failed to perform its obligations under the Lease. 
    Id. at 640-703
    , Default
    Notice 1; 704-09, Default Notice 2; 710-25, Default Notice 3; 726-34, Default Notice 4;
    741-50, 751-56, Requests to Cure.
    On February 11, 2009, VA sent FHSHA a its first default notice demanding that,
    within thirty days, FHSHA remit in full the sum of $126,530.00. This amount
    12
    represented the total amounts cited in five electric utility bills that the VA previously
    issued to FHSHA from September 28, 2006 through November 6, 2007, and one electric
    utility bill that the VA issued on September 22, 2008. The government attributed the
    $126,530.00 demand to Baltimore Gas & Electric utility services that were provided to,
    and thus benefitted, the leased premises, excluding the CBOC used by the VA. 
    Id. at 640-703
    , Default Notice 1.
    On February 27, 2009, in accordance with Article 7.E of the Lease, the VA sent
    FHSHA a Request for Information seeking information to help the VA determine
    FHSHA’s compliance with Articles 24.Q.1, 10.A.2, 10.A.3, 14, and 31.A of the Lease.
    On that same date, in accordance with Article 7.E of the Lease, the VA sent
    FHSHA a Request for Information seeking information about deposits FHSHA was
    collecting from veterans.
    On February 27, 2009, in accordance with Article 23.B of the Lease, the VA sent
    FHSHA a second default notice identifying that FHSHA was breaching its obligations
    and responsibilities under the following provisions of the Lease:
    a.     Article 4.A.1 – FHSHA is failing to finance, develop and maintain the
    Project as required by Article 4.A.1 of the Lease.
    b.     Article 4.A.7 – FHSHA is failing to operate, manage and maintain the
    Property as required by Article 4.A.7 of the Lease.
    c.     Article 4.A.9 – FHSHA is failing to maintain and properly secure access to
    the Property as required by Article 4.A.9 of the Lease.
    d.     Article 4.A.12 – FHSHA is failing to pay Rent as required by Article
    4.A.12 of the Lease.
    13
    e.     Article 4.D – FHSHA is failing to maintain and repair the Property as
    required by Article 4.D.
    f.     Article 6.C.8 – FHSHA has failed to provide VA unaudited income
    statements, balance sheets and cash flow statements within the time periods
    required by the Lease. In addition, FHSHA failed to notify VA of the
    lawsuit filed against FHSHA by STV Incorporated. Both of these actions
    are required by Article 6.C.8 of the Lease.
    g.     Article 12.B.1 – FHSHA is failing to manage, protect, preserve, maintain
    and repair the Property as required by Article 12.B.1 of the Lease.
    h.     Article 12.B.2 – FHSHA is failing to employ a local, designated
    representative for emergency management, protection, preservation,
    maintenance and repair as required by Article 12.B.2 of the Lease.
    i.     Article 13.A.1 and Article 13.A.4 – FHSHA has failed to maintain and
    deliver to VA a current certificate of insurance or a certified copy of each
    policy of insurance, as required by Article 13.A.1 and Article 13.A.4 and
    requested by VA on numerous occasions.
    
    Id. at 704-09
    , Default Notice 2. Default Notice 2 further stated:
    [I]n addition to remedying the aforementioned Lease breaches, FHSHA’s
    failure to make progress, including its failure to obtain financing and begin
    construction of the Project, is endangering FHSHA’s ability to complete
    Phase 1 of the Development Plan in the time required by the Lease. VA
    hereby demands assurances from FHSHA that it will complete Phase 1 of
    the Development Plan in accordance with the Lease, including construction
    and acceptance of the CBOC within thirty-nine (39) months of the
    Effective Date of the Lease . . . .
    
    Id.
     On March 3, 2009, the VA sent FHSHA a notice identifying several concerns:
    (i) FHSHA has failed to maintain the Property “in a good, clean and safe
    condition,” (ii) make timely repairs, and (iii) properly secure the Property . .
    . . VA is concerned for the safety of the veterans accessing the Property
    and the protection of VA assets. In accordance with Article 12.B.2 of the
    Lease, VA hereby notifies FHSHA that if substantial attempts to correct all
    deficiencies related to maintenance, repairs and security are not performed
    within thirty (30) days on all Parcels, VA will correct such deficiencies at
    the sole cost and expense of FHSHA . . . .
    14
    
    Id. at 759-64
    . On March 10, 2009, the VA sent FHSHA a third default notice, which
    demanded that FHSHA remit to the VA $3,101.55. 
    Id. at 710-25
    , Default Notice 3. The
    VA attributed this amount to certain Baltimore City water services and Baltimore County
    sewer services that were provided to, and thus benefitted, the portion of the Leased
    Premises, excluding the CBOC used by the VA. 
    Id.
    On March 16, 2009, FHSHA responded to the VA’s February 27, 2009 Default
    Notice 2. The response did not indicate that FHSHA would begin curing any of the
    identified defaults, with the exception of identifying a contact person and providing the
    requested income statements. The response did not provide assurances that the
    construction would be completed within the timelines set forth in the Lease.
    On April 24, 2009, the VA sent FHSHA a fourth default notice for failure to
    respond to two Requests for Information sent to FHSHA on February 27, 2009. Also on
    April 24, 2009, FHSHA sent a letter to the VA stating that FHSHA planned to respond to
    each of the letters from the VA on or before the end of May 2009. On May 13, 2009, the
    VA sent a letter to FHSHA stating:
    [I]n accordance with Article 23.B of the Lease, FHSHA is required to cure
    the defaults identified in Default Notice 1 prior to May 18, 2009 and cure
    the defaults identified in the Default Notice 2 prior to June 2, 2009. If
    FHSHA fails to cure the defaults identified in the Default Notices, VA
    intends to exercise VA’s rights under the Lease, which includes, but is not
    limited to, termination of the Lease.
    
    Id. at 735-40
    .
    C.        Termination of the Lease
    On August 17, 2009 at 3:29 pm, the VA sent a Termination for Default Notice
    15
    (“Termination Notice”) to FHSHA via email and certified mail. The effective date of the
    termination was August 17, 2009. 
    Id. at 783-866
    .
    The Termination Notice stated:
    [FHSHA] was required to cure the defaults identified in Default Notice 1
    prior to May 18, 2009 and cure the defaults identified in Default Notice 2
    prior to June 2, 2009. VA notified FHSHA that if FHSHA failed to cure the
    defaults identified in the Default Notices as required by the Lease and in the
    time periods provided in the Lease and the Default Notices, that VA will
    exercise VA’s rights under the Lease, which includes, but is not limited to,
    termination of the Lease.
    
    Id.
     The Termination Notice constituted the designated VA Representative’s final
    decision that the Lease is terminated in its entirety for the following reasons:
    1.     The defaults identified in the Default Notices constitute a failure to
    pay Rent, as defined in the Lease. The failure to pay Rent is a
    material default.
    2.     FHSHA’s failure to maintain the Property and undertake the
    maintenance required by the Lease at the Property, as described in
    the Default Notices, are material breaches of the Lease and
    constitute a failure to pay Rent.
    3.     FHSHA’s failure to secure the Property, as described in Default
    Notice 2, is a material breach of the Lease and constitutes a failure to
    pay Rent.
    4.     FHSHA’s failure to maintain insurance on the Property, as described
    in Default Notice 2, is a material breach of the Lease and constitutes
    a failure to pay Rent.
    5.     FHSHA’s failure to pay for electrical utilities, as described in
    Default Notice 1, is a material breach of the Lease.
    6.     FHSHA has taken no steps to begin the actual development or
    construction of the Project. FHSHA did not respond to VA’s request
    in Default Notice 2 that FHSHA provide assurances that FHSHA
    would complete Phase 1 of the Development Plan in accordance
    with the Lease, including construction and acceptance of the CBOC
    16
    within thirty-nine (39) months of the Effective Date of the Lease.
    To date (almost thirty-six (36) months after execution of the Lease),
    FHSHA has failed to obtain financing for the Project and no lender
    has been identified and confirmed that it is ready, willing, and able
    to provide FHSHA the requisite financing to enable FHSHA to
    construct the CBOC. In addition, no plans have been submitted to
    VA or the County for review and approval. Further, FHSHA has not
    started construction of the Project. Accordingly, VA has determined
    that FHSHA will not be able to meet the deadline of thirty-nine (39)
    months after the Effective Date of the Lease (December 28, 2009)
    for construction of the CBOC in accordance with the Lease terms.
    
    Id. at 786-87
    .
    D.        FHSHA’s Obligations Regarding State and Local Approvals Under the
    Lease
    As noted above, the lease provided that FHSHA was required to undertake the
    development in a manner that satisfied all requirements of “applicable” state and local
    laws, as required by Articles 4.A.1, 4.A.2, and 10.H.1 of the Lease.
    FHSHA claims that while this was true, under the statutes governing EULs, 
    38 U.S.C. § 8166
    , local land use laws and regulations were not “applicable.” 
    38 U.S.C. § 8166
     provides:
    (a) Unless the Secretary provides otherwise, the construction, alteration,
    repair, remodeling, or improvement of the property that is the subject of the
    lease shall be carried out so as to comply with all standards applicable to
    construction of Federal buildings. Any such construction, alteration, repair,
    remodeling, or improvement shall not be subject to any State or local law
    relating to land use, building codes, permits, or inspections unless the
    Secretary provides otherwise.
    
    38 U.S.C. § 8166
    .
    Prior to execution of the Lease, the VA and FHSHA discussed the VA’s
    expectation that FHSHA comply with all applicable state and local laws. In response to a
    17
    question regarding larger issues negotiated in the Lease, Mr. Infantino, FHSHA’s
    representative,5 explained, “Obviously, the applicable word, the VA wanted to put in
    there that you comply with everything. We said, no, it’s got to be applicable because
    we’re not complying with certain local jurisdictions . . . but we resolved that by putting
    the word ‘applicable’ in.” Def.’s App’x 891-92, Infantino Dep., 141:22-142:6, Jan. 23,
    2014.
    According to FHSHA, the VA accepted FHSHA’s Development Plan which
    included the higher development density, development program, master plan, budgets,
    and economic consideration all based on 1,300 units, although County land use
    regulations would apparently allow a 550 unit density.
    Although Baltimore County never rejected FHSHA’s proposed 1,300 units as
    FHSHA never applied for a zoning variance, it is not disputed that 1,300 was not
    consistent with the Baltimore County land use regulations in place at the time.
    E.             FHSHA’s Obligation Regarding Financing
    FHSHA sought financing from Starwood Capital, who participated in Lease
    negotiations with the VA and FHSHA prior to the execution of the Lease. 
    Id. at 884-85
    ,
    Infantino Dep., 71:21-72:3, Jan. 23, 2014.
    The VA participated in multiple meetings with FHSHA’s potential lenders. In
    response to a question if the VA participated in any meetings with FHSHA’s potential
    lenders, Mr. Infantino explained, “Absolutely. They were there for the HUD and GMAC
    5
    Mr. Infantino is the chief executive manager of Ft. Howard Senior Housing Associates, LLC.
    18
    lending meetings…and they absolutely participated with Starwood . . . GMAC was
    probably two, three meetings . . . . I would have to guesstimate it was somewhere
    between 5 to 15 [meetings with Starwood]. It’s a pretty wide range, but it extended over
    a long period of time. Enough to generate $700,000 in legal fees . . . [With Enterprise,]
    we definitely had conference calls, and I’d say probably three to five conference calls, a
    series of e-mail exchanges, and we might have had one or two meetings . . . .” 
    Id.
     at 919-
    20, Infantino Dep., 240:5-241:19, Jan. 23, 2014.
    F.             Application of the Davis-Bacon Act
    Prior to execution of the Lease, FHSHA and the VA discussed that the Davis-
    Bacon Act may apply to FHSHA’s activities.6 Mr. Infantino explained, “[W]e told the
    VA during the process that Davis-Bacon doesn’t apply to the buildings we built, and they
    said they don’t know about that. They are not sure about that . . . .” 
    Id. at 912-13
    ,
    Infantino Dep., 193:18-194:2, Jan. 23, 2014.
    To resolve this ambiguity, Article 33 of the Lease was drafted to require
    compliance with the Davis-Bacon Act unless FHSHA obtained a written determination or
    written correspondence from the U.S. Department of Labor (“DOL”) that the Lease or the
    Project is exempt therefrom. 
    Id. at 64
    , Article 33; 
    id. at 891
    , Infantino Dep., 141:18-20,
    Jan. 23, 2014.
    6
    The Davis-Bacon Act sets standards for the pay of laborers and mechanics for federal contracts,
    and in particular requires that workers be paid a minimum wage determined in reference to the
    prevailing local rate. 
    40 U.S.C. §§ 3141-3142
    .
    19
    The VA remained neutral on the applicability of the Davis-Bacon Act to the
    Project, as the VA believed that the DOL, and not the VA, was the appropriate party to
    determine the applicability of this statute to the project. After FHSHA signed the Lease,
    FHSHA sought a waiver of the Davis-Bacon Act; however, on June 5, 2008, FHSHA
    informed the VA that it would no longer be seeking the waiver. 
    Id. at 867
    , Email from
    John Infantino to Erik Wishneff & Alan Hackman (June 5, 2008, 01:40 EST) (“This
    email confirms that there is no reason to cont[i]nue dialogue with Department of labor at
    this time. We will not be seeking an immediate decision on this issue.”).
    II.    DISCUSSION
    A.     Standard of Review for Summary Judgment
    Summary judgment is proper “if the movant shows that there is no genuine
    dispute as to any material fact and the movant is entitled to judgment as a matter of law.”
    RCFC 56(a); see Celotex Corp. v. Catrett, 
    477 U.S. 317
    , 322 (1986); Anderson v. Liberty
    Lobby, Inc. v. United States, 
    477 U.S. 242
    , 247 (1986). In order to defeat a motion for
    summary judgment, the nonmoving party must point to “‘specific facts showing that there
    is a genuine issue for trial.’” Celotex, 
    477 U.S. at 324
     (quoting Fed. R. Civ. P. 56(e)).
    The nonmoving party must “establish the existence of an element essential to that party’s
    case, and on which that party will bear the burden of proof at trial.” Celotex, 
    477 U.S. at 322
    . “A genuine dispute is shown to exist if sufficient evidence is presented such that a
    reasonable fact finder could decide the question in favor of the non-moving party.”
    Opryland USA Inc. v. Great American Music Show, Inc., 
    970 F.2d 847
    , 850 (Fed. Cir.
    1992) (citing Anderson, 
    477 U.S. at 248
    ). However, to the extent that actual evidence is
    20
    presented, “the evidence of the non-movant is to be believed, and all justifiable
    inferences are to be drawn in his favor.” Anderson, 
    477 U.S. at 255
    .
    B.     The Legal Standards Governing Terminations for Default and For
    Establishing That A Default is “Excused”
    In reviewing a termination for default, the court must “strike a balance between
    the judicial aversion to default terminations . . . and the fact that ‘the Government, just as
    any other party, is entitled to receive that for which it has contracted and the right to
    accept only goods that conform to the specification.’” McDonnell Douglas Corp. v.
    United States, 
    323 F.3d 1006
    , 1015 (Fed. Cir. 2003) (quoting Cascade Pac. Int’l v. United
    States, 
    773 F.2d 287
    , 291 (Fed. Cir. 1985)) (citing J.D. Hedin Constr. Co. v. United
    States, 
    187 Ct. Cl. 45
     (1969)). When a contractor challenges a default termination, the
    government bears the burden of establishing the validity of the termination. Lisbon
    Contractors, Inc. v. United States, 
    828 F.2d 759
    , 765 (Fed. Cir. 1987). These “principles
    apply with equal force where the Government has terminated a lease.” Moreland Corp.
    v. United States, 
    76 Fed. Cl. 268
    , 284 (2007) (citation omitted). Where, as here, the
    termination for default regarding construction of the CBOC involves the failure to
    perform the work, the government must establish that there was “a reasonable belief on
    the part of the contracting officer that there was ‘no reasonable likelihood that the
    [contractor] could perform the entire contract effort within the time remaining for
    contract performance.’” Lisbon, 
    828 F.2d at 765
     (quoting RFI Shield-Rooms, ASBCA
    Nos. 17374, 17991, 77-2 BCA (CCH) ¶ 12,714, 61,735) (citing Discount Co. v. United
    States, 
    554 F.2d 435
    , 441 (Ct. Cl. 1977), cert. denied, 
    434 U.S. 938
     (1977)).
    21
    Even if the government sustains its burden of showing a proper termination for
    default, the termination will be converted to a termination for convenience only if the
    delay was “excusable” under the terms of the default provision of the contract. Sauer Inc.
    v. Sec’y of the Navy, 
    224 F.3d 1340
    , 1345 (Fed. Cir. 2000). In addition, a contractor’s
    failure to perform will be excused and the termination for default converted to a
    termination for convenience if the contractor can establish that the government materially
    breached the contract. See Murdock Mach. & Engineering Co. of Utah v. United States,
    
    873 F.2d 1410
    , 1413 (Fed. Cir. 1989) (citing Malone v. United States, 
    849 F.2d 1441
    ,
    1446 (Fed. Cir. 1988)).
    Tested by these standards, the court now turns to the questions of whether the
    government’s decision to terminate the Lease for default was justified and if so whether,
    as the government argues, the plaintiff’s claims of “excuse” fail as a matter of law.
    C.     The Termination for Default Regarding Construction of the CBOC
    The following facts are not disputed. FHSHA did not begin construction of the
    CBOC by the time that the termination for default was issued. Under the terms of the
    Lease, failing to construct the CBOC in accordance with the Lease terms would be
    grounds for default unless the time for constructing the CBOC was extended by
    agreement or due to a force majeure event. However, it is undisputed that the time for
    constructing the CBOC was not extended by agreement. Further, it is also undisputed
    that when the VA, in accordance with the Lease, sent a cure letter to FHSHA on May 13,
    2009 asking FHSHA to provide assurances that it could comply with Lease and construct
    the CBOC in accordance with the Lease terms, FHSHA failed to respond by the date
    22
    provided. When the VA had not heard from FHSHA, it began its initial steps to
    terminate the Lease for default. Finally, it is not disputed that, although FHSHA
    responded to some of the VA’s concerns in a letter it sent to the VA on August 17, 2009,
    FHSHA did not commit to constructing the CBOC in accordance with the schedule set
    forth in the Lease and the notice of termination for default was sent on that same day.
    In light of these undisputed facts, the court finds that the termination for default
    based on FHSHA’s failure to timely construct the CBOC was justified under the terms of
    the Lease. Under the undisputed facts as laid out above, FHSHA was unable to construct
    the CBOC by the date required by the Lease. Indeed, FHSHA had not begun
    construction. Accordingly, unless, as FHSHA argues, there are disputed issues of fact
    which if proven would establish that FHSHA’s failure to perform was excused by a force
    majeure event,7 as provided for in the Lease or by a material breach of the lease by the
    VA, it will be affirmed.
    1.             As a Matter of Law, the VA Did Not Breach Its Duty to
    Cooperate or Violate Any Implied Warranties by Requiring
    Compliance with State and Local Land Use Laws and Taxes.
    FHSHA contends that the VA breached its duty to cooperate and violated implied
    warranties in two ways: (1) by requiring FHSHA to comply with state and local land use
    and construction requirements and state and local taxes, and (2) by then failing to assist
    FHSHA to resolve issues that arose out of FHSHA’s obligations to comply with local
    7
    At oral argument, counsel for plaintiff conceded that, if there was no force majeure event, then
    there is no dispute that FHSHA materially breached the lease.
    23
    zoning laws. According to plaintiff, these actions excuse its failure to begin construction
    on the CBOC. Plaintiff recognizes that the Lease states that FHSHA would comply with
    “applicable local and State laws, codes and ordinances,” but argues that the Federal
    government’s exemption from such laws means that none of the state or local
    requirements or taxes are “applicable.”
    The government argues that it did not breach its duty to cooperate or violate any
    implied warranties because the VA, in the terms of the Lease, exercised its statutory
    authority to require such compliance. The government argues that the version of 
    38 U.S.C. § 8166
    (a)8 in effect at the time the parties entered into the Lease gave the VA the
    “discretion” to require a lessee that enters into an EUL to comply with state or local
    requirements relating to land use, building codes, permits or inspections and thus the VA
    was entitled to require compliance with state and local laws and regulations.
    Specifically, the government relies on the second sentence of § 8166(a), contending that
    it expressly states that any construction, alteration, repair, remodeling, or improvement”
    is not subject to state or local “land use, building codes, permits, or inspections unless the
    Secretary provides otherwise.” 
    38 U.S.C. § 8166
    (a) (emphasis added). The government
    8
    The version of 
    38 U.S.C. § 8166
    (a) in effect at the time the parties entered into the Lease states:
    Unless the Secretary provides otherwise, the construction, alteration, repair,
    remodeling, or improvement of the property that is the subject of the lease shall be
    carried out so at to comply with all standards applicable to construction of Federal
    Buildings. Any such construction, alteration, repair, remodeling, or improvement
    shall not be subject to any State or local law relating to land use, building codes,
    permits, or inspections unless the Secretary provides otherwise.
    
    38 U.S.C. § 8166
    (a) (2004).
    24
    argues that the Lease by its terms demonstrates that the Secretary of the VA did not
    exempt FHSHA from complying with state and local laws, instead stating in Articles
    4.A.1, 4.A.2, and 10.H.1 that FHSHA is subject to all applicable laws. According to the
    government, “applicable” laws include the local Baltimore County zoning requirements.
    The court agrees with the government. While the VA does have discretion under
    
    38 U.S.C. § 8166
    (a) to determine whether it must comply with state and local law, it is
    clear that the VA required compliance under the terms of the Lease. The Lease states:
    Lessee hereby agrees to the following, all of which shall constitute fair
    consideration for this Lease:
    1. Finance, design, develop, construct, demolish, alter, operate, maintain,
    repair, replace, sublease, improve, renovate and market the Property into the
    “Project” in accordance with this Lease (including but not limited to Article
    10 hereof), all applicable local and State laws, codes and ordinances, and the
    National Fire Protection Association (“NFPA”) 101 Line Safety Code.
    2. During the Term of the Lease: (i) obtain all applicable local and State
    permits, licenses, and approvals (including those approvals of VA) necessary
    for construction and operation of the Permitted Uses; . . .
    Def.’s App’x 10, Articles 4.A.1, 4.A.2. Plaintiff argues that the use of “applicable”
    allows FHSHA to avoid compliance: as § 8166 generally exempts the government, none
    of the laws are applicable. However, such a reading of the Lease would render these
    terms mere surplussage, which is disfavored. E.g. Metric Constructors, Inc. v. Nat’l
    Aeronautics & Space Admin., 
    169 F.3d 747
    , 753 (Fed. Cir. 1999) (“Courts prefer, for
    example, an interpretation of a contract that gives effect to all its terms and leaves no
    provision meaningless.” (citing United States v. Johnson Controls, Inc., 
    713 F.2d 1541
    ,
    1555 (Fed. Cir. 1983))). Instead, it is clear that these terms unambiguously state that
    25
    state and local laws are relevant to the project. Plaintiff’s contention that “applicable”
    should be read to mean “none” is simply inconsistent with the plain language of the lease
    and must be rejected. Accordingly, the VA’s later insistence that FHSHA comply with
    state and local laws was not a breach of the lease, but rather entirely consistent with it.
    In addition, contrary to FHSHA’s contention, nothing in 
    38 U.S.C. § 8167
    suggests that the VA breached any duty in connection with state and local tax obligations
    under the Lease. Under 
    38 U.S.C. § 8167
    , the United States’ interest in and use of the
    property “shall not be subject . . . to any State or local laws relative to taxation, fees,
    assessments, or special assessments, except that sales taxes [shall be] charged in
    connection with any construction, alteration, repair, remodeling or improvement project
    carried out under the lease.” 
    38 U.S.C. § 8167
     (1991). This exemption, however, did not
    extend to FHSHA’s interest in the property. The Lease expressly required that FHSHA
    pay and discharge, . . . prior to delinquency, all taxes, general and special
    assessments, and other charges of every description that during the term of
    this Lease may be levied or assessed against the Property and all interests
    therein and all improvements and other property thereon, whether
    belonging to [the VA] or the Lessee.
    Def.’s App’x 44, Article 17.B. Accordingly, if a state or local government imposed taxes
    on FHSHA’s interest in the property, FHSHA was obligated to pay such taxes and the
    VA did not have the power under § 8167 to exempt FHSHA from paying state or local
    taxes.
    Given the plain language of the subject Lease provisions, the court finds as a
    matter of law that the VA did not breach a duty of good faith and fair dealing or violate
    any implied warranties when it (1) required in the Lease that FHSHA comply with state
    26
    and local land use, building code, permit, and inspection laws, notwithstanding that 
    38 U.S.C. § 8166
    (a) permitted the VA to exempt itself from those requirements; or (2)
    declined to interpret 
    38 U.S.C. § 8167
     to permit the VA to exempt FHSHA from paying
    state and local taxes. In such circumstances, the VA did not have an obligation to work
    with FHSHA to help FHSHA avoid its legal obligations. Plaintiff has provided no legal
    basis for this court to find that the parties’ agreement to cooperate required the VA to
    assist FHSHA in avoiding its responsibilities under the terms of the Lease. For those
    reasons, the court finds that the VA acted in accordance with its rights under the law and
    did not breach the Lease.
    2.     The VA Did Not Breach the Lease by Concluding that Baltimore
    County Zoning Rules Were “Applicable” Under the Lease.
    FHSHA further contends that the VA breached its Lease with FHSHA by
    requiring compliance with state and local laws that limited development to 550 units
    because the VA knew that if FHSHA had to comply with all local land use rules it would
    not be able to build the 1,300 units identified in the Development Plan attached to the
    Lease. FSHSA argues that, by approving the Development Plan, the VA must not have
    intended that Baltimore County’s 550-unit limit was an “applicable” requirement under
    the Lease.
    The government argues that FHSHA’s argument fails as a matter of law because
    the term “applicable” in Article 4.A.2 of the Lease plainly meant that FHSHA would be
    required to comply with all of state and local rules that “apply” to the Project, and
    nothing in the Lease suggested that Baltimore County’s density zoning rules were not
    27
    “applicable.” With regard to FHSHA’s contention that the VA would not have intended
    to make a 550-unit local zoning limit “applicable,” the government argues that, by its
    terms, the Lease took precedence over the Development Plan.9 Moreover, the
    government argues that both the Lease and the Development Plan state that “FHSHA will
    obtain all applicable local and State permits, licenses, and approvals (including those
    approvals of VA) necessary for construction and operation.” Def.’s App’x 10, Article
    4.A.2; 
    id. at 93
    , Development Plan.
    As noted above, the court agrees with the government that the Lease is not
    ambiguous with regard to the use of “applicable.” There is no dispute that the housing
    project was to be built in Baltimore County. In such circumstances, because the project
    was in Baltimore County, Baltimore County’s zoning rules were applicable and therefore
    FHSHA was required to comply with them. There is nothing in the Lease or
    Development Plan that puts this reading of the Lease into question. Thus, the VA did
    not, as a matter of law, breach the lease by requiring FHSHA to comply with local zoning
    laws with regard to the density limit on housing units.
    To the extent that FHSHA contends that the VA breached the contract by failing to
    disclose or discuss Baltimore County’s density limit in advance of FHSHA signing the
    9
    Specifically, the government refers to Article 24.H, which states in relevant part:
    All Exhibits attached to [the] Lease are fully a part of [the] Lease. In the event of
    a conflict in interpretation of provisions of [the] Lease between the Development
    Plan at Exhibit E of [the] Lease, and Articles 1-31 or any other Exhibit of [the]
    Lease, Articles 1-31 or any other Exhibit of [the] Lease shall control.
    Def.’s App’x 54, Article 24.H.
    28
    Lease, the argument also fails as a matter of law. The government acknowledges that
    under the “superior knowledge” doctrine it could be liable for a breach if “the
    government owes a duty to disclose critical information to a contractor that is necessary
    to prevent the contractor from unknowingly pursuing a ruinous course of action.”
    McDonnell, 
    323 F.3d at 1020
     (quoting McDonnell Douglas Corp. v. United States, 
    182 F.3d 1319
    , 1329 (Fed. Cir. 1999) (internal quotation marks omitted)). FHSHA, however,
    fails to provide any factual support for its allegations that the VA knew in advance of
    signing the Lease with FHSHA that Baltimore County had zoning restrictions which
    would have limited the number of units that could have built on the site. To the contrary,
    the undisputed evidence shows that the VA did not learn about Baltimore County’s
    zoning restrictions until FHSHA informed the VA after the Lease was signed. Def.’s
    Supp. App’x 1253, Hackman Decl. ¶ 14. In such circumstances, the VA lacked the
    knowledge necessary to create a duty and FHSHA’s claim of breach based on a “superior
    knowledge” claim also fails as a matter of law.
    3.     FHSHA’s Various Force Majeure Claims Fail As a Matter of
    Law.
    Under the Force Majeure Clause of the Lease, FHSHA’s delay in completing the
    CBOC could be excused
    if [a]ny of the following that directly cause any of Lessee’s obligations
    hereunder not to be performed in a timely manner: (1) an earthquake,
    hurricane, tornado, flood, or other similar act of God; (2) fire; (3) strikes or
    similar labor disputes provided such strike or similar dispute is beyond
    Lessee’s control and provided Lessee takes all steps reasonably possible to
    remediate such strike or similar dispute; (4) acts of the public enemy; (5)
    inability to obtain labor or materials or clear access to the Project or
    unreasonable delay in approving permit applications for the Project by
    29
    reason of acts or omissions of any governmental body not caused by
    Lessee’s actions or omissions; (6) rebellions, riots, insurrections or civil
    unrest; (7) unusually severe weather conditions that actually cause similar
    construction or development activities in the area of the Project to be
    suspended; or (8) an unknown environmental hazard or unknown hazardous
    substance (e.g., one that Lessee did not know of or have notice of by the
    Effective Date) affecting the Property.
    Def.’s App’x 5, Article 1 (emphasis added). FHSHA contends that various governmental
    bodies delayed processing certain of FHSHA’s applications, agreements, and related
    documents and that, pursuant to the force majeure provisions in the Lease, these delays
    excuse FHSHA’s failure to complete the CBOC on time.
    Specifically, FHSHA contends that (1) the VA delayed in assisting FHSHA to
    secure an opinion letter from the DOL as to the applicability of Davis-Bacon wages with
    regard to its employees at the site, and (2) Baltimore County, the Maryland State Historic
    Preservation Office, and the VA failed to act promptly on the applications FHSHA
    submitted to these organizations in connection with this project. The government
    contends that none of the delays identified by FHSHA constitute a force majeure event.
    For the reasons that follow, the court agrees.
    a.     VA and DOL’s Actions with Respect to the Davis-Bacon
    Act Did Not Excuse FHSHA’s Failure to Timely Perform
    Under the Force Majeure Provisions of the Lease.
    Regarding Davis-Bacon wage requirements, FHSHA is unable to demonstrate that
    any of the VA’s or DOL’s actions in connection with FHSHA’s effort to waive such
    requirements amounts to a force majeure event. First, Subsection 3 of the definition
    states that a force majeure event includes “strikes or similar labor disputes provided such
    strike or similar dispute is beyond Lessee’s control and provided Lessee takes all steps
    30
    reasonably possible to remediate such strike or similar dispute.” Def.’s App’x 4, Article
    1. However, FHSHA has not presented any evidence to show that there were any strikes
    or similar labor disputes that prevented FHSHA from constructing the CBOC in a timely
    fashion.
    Second, FHSHA’s allegations regarding VA’s failure to help FHSHA from
    obtaining an opinion letter from DOL as to the applicability of the Davis-Bacon Act do
    not constitute a force majeure event. The Lease expressly provides that the Davis-Bacon
    Act is applicable to FHSHA’s construction on the Fort Howard site unless FHSHA
    obtains an exemption. The Lease provides:
    [u]nless the Lessee can demonstrate to the satisfaction of the Department in
    the form of a written determination or written correspondence from the U.S.
    Department of Labor that the Lease or the Project is exempt therefrom,
    Lessee shall comply with the requirements of the Davis-Bacon Act, as
    amended, 40 U.S.C. Section 3141 et. seq. and the relevant rules, regulations
    and orders of the Secretary of Labor applicable thereto.
    Id. at 64, Article 33.
    The VA told FHSHA prior to finalizing the Lease that the VA was unsure as to
    whether DOL would grant a waiver. Id. at 912-13, Infantino Dep. 193:18-194:2, Jan. 23,
    2014. Thus, FHSHA took the risk that it might not receive a waiver when it signed the
    Lease. Moreover, FHSHA informed the VA that, as of June 5, 2008, it would no longer
    seek a waiver from the Davis-Bacon requirements. Id. at 867, Email from John Infantino
    to Erik Wishneff & Alan Hackman (June 5, 2008, 01:40 EST) (“This email confirms that
    there is no reason to cont[i]nue dialogue with Department of labor at this time. We will
    not be seeking an immediate decision on this issue.”).
    31
    Finally, there is no evidence showing that any delay related to Davis-Bacon
    requirements interfered with FHSHA’s ability to complete the CBOC by the date
    required in the Lease. For all of these reasons, there is no basis for the court to find that
    the VA and DOL’s actions regarding Davis-Bacon Act compliance could as a matter of
    law excuse FHSHA’s failure to meets its obligations with regard to the CBOC.
    b.             FHSHA Is Unable To Establish That The Timing Of The
    VA’s And The State And Local Government’s Responses
    To FHSHA’s Applications Constituted Force Majeure
    Events.
    Regarding prompt responses from the VA and state and and local governments,
    FHSHA contends that the failure of the VA and various state and local governmental
    bodies to act timely with regard to FHSHA’s submissions constituted force majeure
    events under the definition of force majeure the Lease. In response, the government
    argues that the undisputed facts establish that none of the actions by the VA or state and
    local governments actually prevented FHSHA from moving forward with its
    responsibilities under the Lease.
    First, FHSHA argues that the VA delayed its actions by failing to timely approve
    changes to construction plans. The government correctly argues that this argument fails
    as a matter of law. Under Article 10.A.3 of the Lease, FHSHA was authorized to
    proceed with any construction plan changes if the VA failed to act within 20 days of
    FHSHA’s submission of a request for changes.10 In such circumstances, FHSHA cannot
    10
    The Lease provides:
    VA’s failure to respond within twenty (20) business days to such submission of
    any plat, plan, specification or application (or, if the response is disapproval, to
    32
    show that the VA unreasonably delayed FHSHA by failing to approve changes to the
    construction plans.11
    Second, FHSHA argues that delays in the approval of the Programmatic
    Agreement—which was made between FHSHA, the State of Maryland Historic
    Preservation Office, and VA—also amounted to a force majeure event that should excuse
    FHSHA’s failure to timely construct the CBOC. Again, FHSHA’s argument fails as a
    matter of law.
    The Lease provides that the Lessee and VA were required to comply with the
    provisions of the National Historic Preservation Act and the Archeological Resources
    Protection Act, 
    16 U.S.C. §§ 470
    -470mm (“NHPA and ARPA”), and to abide by any
    agreements the parties entered into with respect to NHPA and ARPA either prior to or
    during the terms of the Lease. Def.’s App’x 20, Article 6.C.5. The parties’ undisputed
    identify the defects with such specificity that Lessee can correct them) shall be
    deemed unreasonable for purposes of this Article 10.A and the Department’s
    consent thereto shall be deemed given.
    Def.’s App’x 24, Article 10.A.3.
    11
    In his affidavit and declaration attached to plaintiff’s response, Mr. Infantino made several
    allegations regarding the VA’s conduct: (1) that the VA failed to provide a legal description for
    the CBOC site; (2) that the VA failed to approve an Updated Schematic CBOC Plan,
    Design/Build Process Agreement, or Final Schematic CBOC Plan in writing; (3) that the VA
    refused to amend the CBOC plan to be within the 10,000 ground square feet standard in the
    Lease; (4) that the VA did not consider or approve requests to relocate the CBOC; and (5) that
    the VA failed to provide a scaled-down program necessary to prepare a Final Schematic CBOC
    Plan. Pl.’s Am. Mot. for Summ. J., Ex. B, Infantino Aff. ¶¶ 28-37; 
    id.,
     Ex. D, Infantino Supp.
    Aff. ¶¶ 23-35. In addition to the provisions of the Lease allowing FHSHA to consider
    submissions to be approved by the VA after 20 days, the court finds that plaintiff has provided
    no support for the allegations in those declarations. Such uncorroborated statements cannot
    defeat a motion for summary judgment. Impresa Construzioni Geom. Domenico Garufi v.
    United States, 
    61 Fed. Cl. 175
    , 181 (2004) (citations omitted).
    33
    facts show that the government representatives had negotiated a draft Programmatic
    Agreement pursuant to 
    16 U.S.C. § 470
    , and were prepared to sign the agreement, but
    FHSHA did not sign the Agreement. Def.’s Supp. App’x 1253, Hackman Decl. ¶¶ 16-
    19. Rather, on January 6, 2009, after the VA had sent a copy of the Agreement to
    FHSHA, the VA received a question from FHSHA12 which appears to have been
    previously answered by the VA on June 27, 2008.13 For whatever reason, however,
    FHSHA never executed the Programmatic Agreement, and thus it was not executed. 
    Id.
    Because the undisputed evidence shows that FHSHA contributed to any delay by failing
    to sign the Agreement, FHSHA cannot establish that the government’s delay was a force
    majeure event under the terms of the Lease. Under the Lease, a qualifying unreasonable
    delay could not be “caused by Lessee’s actions or omissions,” Def.’s App’x 5, Article 1,
    and therefore FHSHA’s contribution to the delay prevents it from constituting a force
    12
    On January 6, 2009, Mr. Erik Wishneff of Federal Development sent an email to Mr. Alan
    Hackman, VA, to ask whether, “if the PA was terminated that it would not trigger a default under
    the Lease and that [FHSHA] would simply have to go through the statutory Section 106
    process.” Def.’s Supp. App’x 1195, Email from Erik Wishneff to Alan Hackman & John
    Infantino (Jan. 6, 2009, 15:05 EST).
    13
    On June 27, 2008, Mr. Hackman responded to Mr. Wishneff’s June 23, 2008 email message:
    You have asked for clarification as to whether VA would consider FHSHA in
    default of the EUL if a party terminates the PA. We do not believe that VA would
    find FHSHA in default of the EUL because the PA is terminated by a party.
    Should the PA be terminated by a party, VA would, in that event, expect FHSHA
    to comply with Section 106 of the NHPA. While the PA is effective, however,
    FHSHA would be required to comply with the PA terms in accordance with
    Article 6.C.5 of the EUL.
    Def.’s Supp. App’x 1165, Email from Alan Hackman to Erik Wishneff & James Wagner (June
    27, 2008, 12:06 EST).
    34
    majeure event.
    Third, FHSHA argues that Baltimore County’s failure to approve the Entitlement
    Memorandum of Understanding (“Entitlement MOU”)14 that it submitted in 2006 asking
    for an exemption from county jurisdiction over development of the Fort Howard site was
    a force majeure event. According to FHSHA, the county delayed taking any action on the
    Entitlement MOU until the State of Maryland adopted statewide legislation addressing
    federal EUL and base realignment and closure projects. FHSHA further contends that,
    because state and federal agencies took such a long time to address FHSHA’s
    applications and documents in connection with the Entitlement MOU, the VA should
    have afforded FHSHA additional time to complete its work.
    The government argues that FHSHA cannot establish a force majeure event based
    on Baltimore County’s failure to waive its jurisdiction over the Project because FHSHA
    was required under the Lease to comply with County requirements or seek a modification
    of the requirements. Here, the government argues, it is undisputed that FHSHA never
    submitted a formal permit application to Baltimore County requesting approval for 1,300
    units or otherwise asking the County to modify the zoning restrictions that limited to 550
    the number of units that could be built at the Fort Howard site.
    The court again agrees with the government. As an initial matter, as discussed
    above, the Lease clearly states that FHSHA itself was required to take the necessary steps
    14
    FHSHA had submitted an Entitlement MOU to Baltimore County that provided the County
    only with review authority over the Ft. Howard project. Pl.’s Am. Mot. for Summ. J., Ex. B,
    Infantino Aff. ¶ 84.
    35
    to “obtain all applicable local and State permits, licensees, and approvals . . . necessary
    for construction and operation of the Permitted Uses [of the Fort Howard site].” Def.’s
    App’x 10, Article 4.A.2. As this responsibility rested solely with FHSHA, the County’s
    refusal to waive jurisdiction cannot be a force majeure event, as it is “caused by Lessee’s
    actions or omissions.” 
    Id. at 5
    , Article 1.
    In this connection, however, it is important to note that while FHSHA needed a
    waiver of County requirements in order to build the desired number of housing units, it is
    undisputed that FHSHA did not need County approval to build the CBOC because it was
    a “federal” building to which no state or local zoning restrictions applied. See 
    id. at 26
    ,
    Article 10.H.1. There is no evidence that the state or local government failed to act with
    regard to any request in connection with construction of the CBOC. Accordingly, the
    court must reject FHSHA’s contention that it could not build the CBOC unless it
    obtained an exemption from all local requirements from Baltimore County. FHSHA
    argues that the uncertainties regarding the housing units prevented it from being able to
    construct the CBOC because its financing was based on building 1,300 units. However,
    the Lease plainly provided that FHSHA had 39 months to build the CBOC and thus it had
    over 3 years to deal with the County and the VA to work out issues regarding the CBOC.
    The fact that FHSHA elected to seek an exemption from County rules rather than to seek
    a variance from them is, as discussed above, a risk that FHSHA alone bore under the
    36
    Lease.15 The County’s decision not to exempt FHSHA from local zoning requirements
    and any delay in making that decision is not a force majeure event that prevented
    construction of the CBOC.
    4.             VA Did Not Breach Its Duty Of Good Faith And Fair Dealing By
    Failing To Discuss Possible Lease Modifications With Potential
    Lenders After The Parties Signed The Lease.
    FHSHA next contends that the VA breached its duty of good faith and fair dealing
    by refusing to discuss possible lease modifications with lenders after the Lease was
    signed. The government argues that this argument fails because the Lease expressly
    provides that VA is not required to accept a proposed modification which “in any way
    affect[s] the Term or the rent [or] affect[s] adversely in any material respect any rights of
    the Department under [the] Lease.” Def.’s App’x 44, Article 16.C.11.
    There is no dispute that the VA made construction of the CBOC a material term of
    the Lease. As a matter of law, the government could not breach the duty of good faith
    and fair dealing on the grounds that the government refused to eliminate or change the
    CBOC identified in the Lease after FHSHA learned that it would have to comply with
    local zoning rules for the housing units.
    5.             FHSHA Is Unable To Establish That It Is Entitled to
    Reformation of the Lease Based on Mutual Mistake.
    FHSHA next argues that its failure to construct the CBOC should be excused
    because the parties were mutually mistaken regarding two facts underlying their Lease.
    15
    FHSHA agrees that it did not “undertake local zoning,” the process of obtaining a local zoning
    variance. Pl.’s Am. Mot. for Summ. J., Ex. B, Infantino Aff. ¶ 98. According to Mr. Infantino,
    “the process to undertake local zoning could have lasted years . . . .” 
    Id.
    37
    First, FHSHA argues that the parties were mutually mistaken in their belief that the
    County would approve FHSHA’s construction of 1,300 housing units at Fort Howard
    under the Lease. Second, FHSHA argues that the parties were mutually mistaken in their
    understanding that “Baltimore County [would] not have authority to issue permits but
    [would] be given [only] a courtesy review of site plans.” Compl. ¶ 67.
    To establish a mutual mistake of fact, FHSHA must show:
    (1) the parties to the contract were mistaken in their belief regarding a fact;
    (2) that mistaken belief constituted a basic assumption underlying the
    contract;
    (3) the mistake had a material effect on the bargain; and
    (4) the contract did not put the risk of the mistake on the party seeking
    reformation.
    Dairyland Power Co-op v. United States, 
    16 F.3d 1197
    , 1202 (Fed. Cir. 1994) (citing
    Atlas Corp. v. United States, 
    895 F.2d 745
    , 750 (Fed. Cir. 1990)). The government
    argues that FHSHA was obligated to comply with Baltimore County density
    requirements and thus bore the risk of the County not approving the construction of 1,300
    units at the Fort Howard site. In such circumstances, the government argues, FHSHA
    cannot rely on reformation of the Lease as a basis for finding that its failure to construct
    the CBOC was excused.
    The court agrees with the government. As discussed above, although the
    Development Plan provided that FHSHA intended to build 1,300 units, the Lease
    expressly provided that the Lease, not the Development Plan, controlled and stated that
    the VA did not represent or warrant that the Fort Howard site would be suitable for any
    particular purpose. Def.’s App’x 54, Article 24.H. Thus, the Development Plan’s
    38
    statement that the proposed site was in keeping with Baltimore County’s intent for the
    area is not relevant. Because, as discussed above, the Lease required FHSHA to comply
    with state and local requirements associated with the development and construction of the
    project, FHSHA was required to obtain county approval to build the full 1,300 units, and
    thus assumed the risk that it would not be able to obtain such approval when it signed the
    Lease. Accordingly, there was no mutual mistake. In such circumstances, the court finds
    that FHSHA cannot establish that it is legally entitled to reformation of the Lease.
    6.     FHSHA Cannot Establish that Performance Under The Lease
    Was Either Impossible Or Commercially Impracticable As A
    Matter of Law.
    As discussed throughout this opinion, at the heart of FHSHA’s defense to the
    termination of default is its contention that it was economically impossible to meet its
    obligations under the Lease unless it was permitted to construct 1,300 housing units on
    the Fort Howard site. According to FHSHA, 550 total housing units would not generate
    a sufficient income stream to begin construction or satisfy other Lease obligations, while
    1,300 housing units would. FHSHA therefore argues that its failure to construct the
    CBOC must be excused as impracticable. The government argues in response that
    plaintiff has failed to carry its burden of introducing disputed facts to show impossibility
    or impracticability and thus its argument fails as a matter of law.
    The doctrines of impossibility and impracticability “have merged over time, as
    courts have construed the term ‘impossibility’ to include ‘impracticability.’” Short Bros.,
    PLC v. United States, 
    65 Fed. Cl. 695
    , 782-83 (2005) (citing Seaboard Lumber Co. v.
    39
    United States, 
    308 F.3d 1283
    , 1294 (Fed. Cir. 2002)). The Supreme Court has
    reformulated the common law doctrine of impossibility as follows:
    [W]here, after a contract is made, a party’s performance is made
    impracticable without his fault by the occurrence of an event the non-
    occurrence of which was a basic assumption on which the contract was
    made, his duty to render that performance is discharged, unless the
    language or the circumstances indicate the contrary.
    United States v. Winstar Corp., 
    518 U.S. 839
    , 904 (1996) (quoting Restatement (Second)
    of Contracts § 261 (1981)). For a plaintiff to prevail upon a defense of impossibility, the
    plaintiff must “show that (i) a supervening event made performance impracticable; (ii)
    the non-occurrence of the event was a basic assumption upon which the contract was
    based; (iii) the occurrence of the event was not [the plaintiff’s] fault; and (iv) [the
    plaintiff] did not assume the risk of occurrence.” Seaboard, 
    308 F.3d at 1294
     (citation
    omitted).
    Essentially, “[t]he Restatement requires plaintiff to show that the cause of the
    impracticability was a fact, the non-existence of which was a basic assumption of the
    contract.” Short, 65 Fed. Cl. at 785. This assumes that “the parties will have bargained
    with respect to any risks that are both within their contemplation and central to the
    substance of the contract.” Winstar, 
    518 U.S. at 905
    . “[N]o impossibility defense will lie
    where the ‘language or the circumstances’ indicate allocation of the risk to the party
    seeking discharge.” Seaboard, 
    308 F.3d at 1295
     (citations omitted). For example, a
    contractor that enters into a fixed-price contract for the purchase of timber bears the risk
    that the market price will drop. 
    Id.
     Under such circumstances, “because the non-
    occurrence of a market slump was not a basic assumption of both parties and [the
    40
    contractor] bore the risk, [the contractor’s] impossibility defense fails as a matter of law.”
    
    Id.
    The government argues that FHSHA’s commercial impracticability defense fails
    as a matter of law because FHSHA assumed the risk of occurrence. See Seaboard, 
    308 F.3d at 1295
    . As discussed above, the court agrees that the Lease required FHSHA to
    obtain Baltimore County’s approval for the development of the property. If FHSHA
    knew that it would have to construct 1,300 units rather than 550 units to make the Lease
    viable, FHSHA was required at a minimum to try to get permission from the County to
    build more than 550 units. The undisputed facts show, however, that FHSHA never
    sought a variance from Baltimore County. To the contrary, FHSHA decided not to seek a
    variance, but instead sought only an exemption from local land use rules. See supra n.
    15. A request for an exemption is not the same as seeking to comply with local land use
    requirements through the variance process or otherwise. Because FHSHA bore the risk
    under the Lease for complying with Baltimore County’s density requirements and failed
    to even attempt to comply with Baltimore County’s zoning code, it cannot show that its
    failure to construct the CBOC should be excused because it could not finance the project.
    FHSHA simply failed to fulfill its obligations under the Lease. As such, the court finds
    that FHSHA’s impossibility defense fails as a matter of law.16
    16
    The final count in FHSHA’s amended complaint seeks compensation for “Tortious
    Interference with Contractual Relations and Prospective Economic Advantages.” Compl. Count
    VI. FHSHA contends that “VA had a contractual relationship with FHSHA, with the probability
    of future economic benefit to FHSHA, and breached such contract in the manners set forth
    above.” Compl. ¶ 81. FHSHA contends that the VA’s decision to terminate the Lease is a
    breach of contract and therefore is improper, arbitrary, capricious, and an abuse of discretion.
    41
    III.          CONCLUSION
    For the foregoing reasons, the government’s motion for summary judgment is
    GRANTED. The parties shall file a joint status report by July 6, 2015 setting forth a
    schedule for resolving the government’s counterclaim, which is now the sole remaining
    issue in this case.
    IT IS SO ORDERED.
    s/Nancy B. Firestone
    NANCY B. FIRESTONE
    Judge
    Compl . ¶¶ 50, 57, 63, 74, 79. While this court typically lacks jurisdiction over cases sounding
    in tort, 
    28 U.S.C. § 1491
    (a), claims are within its jurisdiction where they arise from an alleged
    breach of contract. Awad v. United States, 
    301 F.3d 1367
    , 1372 (Fed. Cir. 2002); see also Wood
    v. United States, 
    961 F.2d 195
    , 198 (Fed. Cir. 1992) (“If an action arises ‘primarily from a
    contractual undertaking,’ jurisdiction lies in the [Court of Federal Claims] ‘regardless of the fact
    that the loss resulted from the negligent manner in which defendant performed its contract.’”
    (quoting San Carlos Irrigation and Drainage Dist. v. United States, 
    877 F.2d 957
    , 960 (Fed. Cir.
    1989))). However, for all of the reasons set forth above, the court has found that the VA did not
    breach its contract with FHSHA. Where there is no breach, FHSHA’s claim for tortious
    interference fails and must also be dismissed.
    42
    

Document Info

Docket Number: 10-553C

Citation Numbers: 121 Fed. Cl. 636, 2015 U.S. Claims LEXIS 665, 2015 WL 3451759

Judges: Nancy B. Firestone

Filed Date: 5/29/2015

Precedential Status: Precedential

Modified Date: 10/19/2024

Authorities (18)

McDonnell Douglas Corporation, and General Dynamics ... , 323 F.3d 1006 ( 2003 )

United States v. Winstar Corp. , 116 S. Ct. 2432 ( 1996 )

Emily Malone D/B/A Precision Cabinet Company v. The United ... , 849 F.2d 1441 ( 1988 )

Lisbon Contractors, Inc. v. The United States , 828 F.2d 759 ( 1987 )

Cascade Pacific International v. The United States , 773 F.2d 287 ( 1985 )

Celotex Corp. v. Catrett, Administratrix of the Estate of ... , 106 S. Ct. 2548 ( 1986 )

Sauer Incorporated v. Richard J. Danzig, Secretary of the ... , 224 F.3d 1340 ( 2000 )

Anderson v. Liberty Lobby, Inc. , 106 S. Ct. 2505 ( 1986 )

McDonnell Douglas Corporation, Plaintiff-Cross and General ... , 182 F.3d 1319 ( 1999 )

San Carlos Irrigation and Drainage District v. The United ... , 877 F.2d 957 ( 1989 )

Opryland USA Inc. v. The Great American Music Show, Inc. , 970 F.2d 847 ( 1992 )

The United States v. Johnson Controls, Inc. , 713 F.2d 1541 ( 1983 )

Seaboard Lumber Company and Capital Development Company v. ... , 308 F.3d 1283 ( 2002 )

atlas-corporation-kerr-mcgee-chemical-corporation-quivira-mining-company , 895 F.2d 745 ( 1990 )

Metric Constructors, Inc. v. National Aeronautics and Space ... , 169 F.3d 747 ( 1999 )

Dairyland Power Cooperative v. United States , 16 F.3d 1197 ( 1994 )

Adnan Awad, and Lynn Awad v. United States and Allen ... , 301 F.3d 1367 ( 2002 )

Michael R. Wood v. The United States, U.S. Customs Service, ... , 961 F.2d 195 ( 1992 )

View All Authorities »