White Buffalo Construction, Inc. v. United States , 2015 U.S. Claims LEXIS 985 ( 2015 )


Menu:
  •           In the United States Court of Federal Claims
    Nos. 99-961C, 00-415C, and 07-738C
    (Consolidated)
    (Filed: August 3, 2015)
    ***************************************
    *
    WHITE BUFFALO CONSTRUCTION, INC., *
    *
    Construction Contract for Road
    Plaintiff,        *
    Repairs in National Forest; Default
    *
    Termination Converted to Termination
    v.                                    *
    for Convenience of the Government;
    *
    Correction of Damages Following
    THE UNITED STATES,                    *
    Remand.
    *
    Defendant.        *
    *
    ***************************************
    Richard E. Alexander, Stoel Rives, LLP, Portland, Oregon, for Plaintiff.
    Heidi L. Osterhout, with whom were Benjamin C. Mizer, Principal Deputy Assistant
    Attorney General, Robert E. Kirschman, Jr., Director, and Steven J. Gillingham, Assistant
    Director, Commercial Litigation Branch, Civil Division, U.S. Department of Justice,
    Washington, D.C., for Defendant.
    OPINION AND ORDER ON REMAND
    WHEELER, Judge.1
    In the fall of 1998, the Federal Highway Administration (“FHA”) contracted with
    Plaintiff White Buffalo Construction, Inc. (“White Buffalo”) to repair damaged roads in
    the Siskiyou National Forest, located in southwestern Oregon. In December 1998, the FHA
    terminated the contract for default. White Buffalo filed suit in this Court on November 30,
    1999, challenging the default termination, and seeking conversion to a termination for the
    convenience of the Government. White Buffalo filed a second suit on July 14, 2000
    seeking the return of liquidated damages paid by White Buffalo’s surety. Prior to trial in
    these cases, the FHA, with authorization from the Department of Justice, converted White
    Buffalo’s termination for default into a termination for convenience based on evidence
    1
    On June 5, 2015, Judge Wheeler received this case by transfer from Judge Lawrence J. Block.
    reviewed during trial preparation. White Buffalo maintained its 1999 and 2000 lawsuits,
    however, arguing that the conversion deprived it of relief under the Equal Access to Justice
    Act (“EAJA”), 28 U.S. § 2414, through which White Buffalo could have obtained
    attorneys’ fees. On October 22, 2007, White Buffalo filed a third lawsuit, to obtain lost
    profits on uncompleted work due to the FHA’s alleged bad faith conduct and to challenge
    the amount of the termination settlement with the FHA.
    This Court, with Senior Judge Loren A. Smith presiding, conducted a trial and
    issued a decision on September 22, 2011, finding that the 1999 and 2000 cases were moot
    due to the FHA’s conversion of the termination for default into a termination for
    convenience. The Court did not, however, dismiss those cases in its judgment. The Court
    also found that the FHA did not act in bad faith toward White Buffalo, and thus the Court
    awarded no lost profits for uncompleted work. The Court did award $353,237.36 plus
    interest to be paid on White Buffalo’s termination for convenience claim. However, the
    Court failed to include $29,528.00 in subcontractor damages in its final calculation due to
    a mathematical error. See White Buffalo Constr., Inc. v. United States, 
    101 Fed. Cl. 1
    (2011).
    White Buffalo filed a notice of appeal of these consolidated cases on January 6,
    2012. On November 1, 2013, the U.S. Court of Appeals for the Federal Circuit issued its
    decision affirming in part, vacating in part, and remanding the case to this Court with
    directions. White Buffalo Constr., Inc. v. United States, 546 Fed. App’x 952 (Fed. Cir.
    2013). On December 23, 2013, the Federal Circuit issued its mandate to this Court, with
    instructions to dismiss the 1999 and 2000 cases as moot, and to determine whether to award
    the missing $29,528.00 in damages.
    The parties have agreed in a July 24, 2015 joint status report that the $29,528.00 in
    subcontractor damages were actually awarded by this Court but were not added to the
    original judgment. The Court therefore awards the missing $29,528.00 in damages in case
    number 07-738C, and dismisses the cases docketed as 99-961C and 00-415C as moot. The
    $29,528.00 in subcontractor damages should be added to the $352,237.36 previously
    awarded for a corrected total of $381,765.36, with interest to be recalculated by the parties
    in accordance with applicable law. The Clerk is directed to issue an amended judgment
    reflecting this ruling.
    IT IS SO ORDERED.
    s/ Thomas C. Wheeler
    THOMAS C. WHEELER
    Judge
    2
    

Document Info

Docket Number: 99-961C, 00-415C, and 07-738C

Citation Numbers: 122 Fed. Cl. 594, 2015 U.S. Claims LEXIS 985, 2015 WL 4607902

Judges: Thomas C. Wheeler

Filed Date: 8/3/2015

Precedential Status: Precedential

Modified Date: 10/19/2024