Davis Wetlands Bank, LLC v. United States , 78 ERC (BNA) 1266 ( 2013 )


Menu:
  •      In the United States Court of Federal Claims
    No. 13-268 C
    Filed: December 16, 2013
    ****************************************                                         Clean Water Act, 33 U.S.C. § 1344
    *                                            (permits for dredged or fill
    DAVIS WETLANDS BANK, LLC,              *                                            material);
    *                                         Jurisdiction;
    Plaintiff,                       *                                         Motion to Dismiss, RCFC 12(b)(1)
    *                                            and 12(b)(6);
    v.                                     *                                         Regulatory instrument;
    *                                         33 C.F.R. § 332.8(o)(3) (credits
    THE UNITED STATES,                     *                                            issued re: wetlands mitigation);
    *                                         60 Fed. Reg. 58,605-02, 58,606
    Defendant.                       *                                            (Nov. 28, 1995) (Federal
    *                                            Guidance for the Establishment,
    *                                            Use and Operation of Mitigation
    ****************************************                                            Banks).
    Douglas E. Kahle, Wolcott Rivers Gates, Virginia Beach, Virginia, Counsel for Plaintiff.
    Meen Geu Oh, United States Department of Justice, Civil Division, Washington, D.C., Counsel
    for Defendant.
    MEMORANDUM OPINION AND ORDER
    BRADEN, Judge.
    I.            RELEVANT FACTUAL BACKGROUND.1
    On November 4, 1998, Davis Wetlands Bank, LLC (“the Bank”), the United States Army
    Corps of Engineers (“the Army Corps”), the United States Fish & Wildlife Service (“USFWS”),
    and the Virginia Department of Environmental Quality (“VDEQ”), established a wetlands
    1
    The relevant facts discussed herein were derived from the April 15, 2013 Complaint and
    attached exhibits: (1) Federal Guidance for the Establishment, Use and Operation of Mitigation
    Banks (“Ex. A”); (2) Umbrella Memorandum of Agreement Between Bank Sponsor, U.S. Army
    Corps of Engineers, et al. to Establish a Procedure for Compensation for Wetland Habitat Losses
    in Southeastern Virginia in the Davis Wetland Bank, LLC and for the Development and Use of
    Such Bank (“Ex. B”); (3) Site-Specific Plan for the Davis Wetland Bank, Chesapeake, Virginia
    (“Ex. C”); (4) a 2001 amendment to the Umbrella Agreement (“Ex. D”); (5) an August 24, 2012
    email between the Bank, the Army Corps, the USFWS and the VDEQ (“Ex. E”); and a
    November 21, 2012 letter from William T. Walker, Chief, Regulatory Branch, Department of the
    Army, Norfolk District Corps of Engineers, to Mr. Douglas Davis, Davis Environmental
    Consultants, Inc. and Mr. Emil A. Viola, Great Dismal Swamp Restoration Bank, LLC (“Ex. F”).
    mitigation bank,2 pursuant to an Umbrella Memorandum of Agreement (“Umbrella
    Agreement”). Compl. ¶¶ 1, 19, Ex. B. The Umbrella Agreement “establish[ed] general
    provisions for the design, development, construction, use and monitoring of a compensatory
    wetland bank . . . and . . . a procedure for providing off-site compensation for unavoidable
    wetland impacts (primarily) in Southeastern Virginia.” Compl. Ex. B at 1.
    On November 24, 1998, a Site-Specific Plan for the Davis Wetland Bank (“Site-Specific
    Plan”) was implemented, that was revised on March 31, 1999. Compl. ¶ 20 & Ex. C. That plan
    required the Bank to “block[] the drainage discharge from the site to increase the hydrology” and
    “plant[] thousands of tree seedlings.” Compl. ¶ 28. On September 26, 2001, the signatories
    amended the Umbrella Agreement.3 Compl. ¶ 21 & Ex. D.
    Under the Final Agreement, the Bank committed to restore agricultural and forested areas
    to wetlands and preserve existing wetlands, as well as provide financial assurance for the Bank’s
    performance. Compl. ¶ 23 & Ex. B at 5. In exchange, the Army Corps agreed to issue the Bank
    one wetland credit per 1.00 acre of restored cropland, 0.50 acres of restored previously-drained
    forest; or 7.5 acres of existing wetlands.4 Compl. Ex D. The Bank could then “sell credits to
    third parties as compensation mitigation for unavoidable impacts to wetlands that were
    permitted, pursuant to Section 404 [33 U.S.C. § 1344] of the [Clean Water Act].” Compl. ¶ 25.
    The Final Agreement also required that the Bank provide the Army Corps with an annual
    report for seven years.5 Compl. Ex. C. At the end of the first 5-year monitoring period, “the
    2
    Federal guidelines define wetlands mitigation banking as:
    [W]etland restoration, creation, enhancement, and in exceptional circumstances,
    preservation undertaken expressly for the purpose of compensating for
    unavoidable wetland losses in advance of development actions, when such
    compensation cannot be achieved at the development site or would not be as
    environmentally beneficial. It typically involves the consolidation of small,
    fragmented wetland mitigation projects into one large contiguous site. Units of
    restored, created, enhanced or preserved wetlands are expressed as “credits”
    which may subsequently be withdrawn to offset “debits” incurred at a project
    development site.
    Federal Guidance for the Establishment, Use and Operation of Mitigation Banks, 60 FED. REG.
    58,605-02, 58,606 (Nov. 28, 1995).
    3
    Hereinafter, the court will refer to the Umbrella Agreement, amendments thereto, and
    the Site-Specific Plan as the “Final Agreement.”
    4
    “The number of credits must reflect the difference between pre- and post-compensatory
    mitigation project site conditions, as determined by a functional or condition assessment or other
    suitable metric.” 33 C.F.R. § 332.8(o)(3).
    5
    An annual report was required for the first five years, but was extended to seven years,
    under the Site-Specific Plan. Compl. ¶¶ 26–27, Ex. B at 11, & Ex. C at 4.
    2
    credit composition [would] be reevaluated and may be adjusted to reflect maturation of the
    restored or created wetlands.” Compl. Ex. B. On October 30, 2001, the Army Corps agreed to
    issue the Bank 389.9 credits, “subject to the success of [the Bank’s] restoration and creation
    efforts.”6 Compl. ¶ 39 & Ex. D.
    The Army Corps, however, suspended the performance of the wetlands bank from June
    16, 2006 to September 8, 2009, because of “a temporary property ownership dispute.” Compl. ¶
    29. During that time, the Bank continued to monitor and report on the restoration activities and,
    in 2009, provided a final progress report to the Army Corps. Compl. ¶¶ 30–31.
    Sometime in 2012, the Bank requested that the Army Corps issue an additional 139.5
    credits to reflect the development of certain agricultural fields into mature forested wetlands.
    Compl. ¶ 47. On August 24, 2012, however, the Army Corps denied that request. Compl. ¶ 49,
    Ex. E, & Ex. F.
    II.           PROCEDURAL HISTORY.
    On April 15, 2013, the Bank filed a Complaint in the United States Court of Federal
    Claims alleging that the Army Corps’ refusal to adjust credit composition to reflect the
    maturation of the restored agricultural fields into forested wetlands violated
    33 C.F.R. § 332.8(o)(3), and breached the Final Agreement. Compl. ¶¶ 50–53. Accordingly, the
    Bank seeks alleged damages for the Army Corps’ refusal to issue the additional 139.5 credits, in
    the amount of $1,395,000. Compl. ¶ 53.
    On July 24, 2013, the Government filed a Motion To Dismiss. On August 23, 2013, the
    Bank filed a Response. On September 6, 2013, the Government filed a Reply.
    III.          DISCUSSION.
    A.             Jurisdiction.
    The United States Court of Federal Claims has “jurisdiction to render judgment upon any
    claim against the United States founded either upon the Constitution, or any Act of Congress or
    any regulation of an executive department, or upon any express or implied contract with the
    United States, or for liquidated or unliquidated damages in cases not sounding in tort.” 28 U.S.C.
    6
    The total 389.9 credits consists of:
    (i)            139.5 credits for planting trees and restoring hydrology to 139.5 acres of
    agricultural fields;
    (ii)           226 credits for restoring the 113 acres of restored previously-drained
    forest; and
    (iii)          24.4 credits for preserving 182.7 acres of existing wetlands.
    Compl. ¶ 39.
    3
    § 1491(a)(1). The Tucker Act, however, is only a “jurisdictional statute; it does not create any
    substantive right enforceable against the United States for money damages.” United States v.
    Testan, 
    424 U.S. 392
    , 398 (1976). Therefore, in order to pursue a substantive right, a plaintiff
    must identify and plead an independent contractual relationship, constitutional provision, federal
    statute, and/or executive agency regulation that provides a substantive right to money damages
    for the court to have jurisdiction. See Todd v. United States, 
    386 F.3d 1091
    , 1094 (Fed. Cir.
    2004) (“[J]urisdiction under the Tucker Act requires the litigant to identify a substantive right for
    money damages against the United States separate from the Tucker Act.”); see also Fisher v.
    United States, 
    402 F.3d 1167
    , 1172 (Fed. Cir. 2005) (en banc) (“The Tucker Act . . . does not
    create a substantive cause of action; in order to come within the jurisdictional reach and the
    waiver of the Tucker Act, a plaintiff must identify a separate source of substantive law that
    creates the right to money damages. In the parlance of Tucker Act cases, that source must be
    ‘money-mandating.’”).
    B.      Standard Of Review For A Motion To Dismiss Pursuant To RCFC 12(b)(1).
    A challenge to the United States Court of Federal Claims’ “general power to adjudicate in
    specific areas of substantive law . . . . is properly raised by a [Rule] 12(b)(1) motion[.]”
    Palmer v. United States, 
    168 F.3d 1310
    , 1313 (Fed. Cir. 1999); see also Rules of the United
    States Court of Federal Claims (“RCFC”) 12(b)(1) (allowing a party to assert, by motion, “lack
    of subject-matter jurisdiction”). When considering whether to dismiss an action for lack of
    subject matter jurisdiction, the court is “obligated to assume all factual allegations of the
    complaint to be true and to draw all reasonable inferences in plaintiff’s favor.” Henke v. United
    States, 
    60 F.3d 795
    , 797 (Fed. Cir. 1995).
    Nonetheless, the plaintiff bears the burden of establishing jurisdiction by a preponderance
    of the evidence. See Reynolds v. Army & Air Force Exch. Serv., 
    846 F.2d 746
    , 748 (Fed. Cir.
    1988) (“[O]nce the [trial] court’s subject matter jurisdiction [is] put in question . . . [the plaintiff]
    bears the burden of establishing subject matter jurisdiction by a preponderance of the
    evidence.”).
    C.      Standard Of Review For A Motion To Dismiss Pursuant To RCFC 12(b)(6).
    A challenge to the United States Court of Federal Claims’ “[ability] to exercise its
    general power with regard to the facts peculiar to the specific claim . . . is raised by a [Rule]
    12(b)(6) motion[.]” 
    Palmer, 168 F.3d at 1313
    ; see also RCFC 12(b)(6) (“Every defense to a
    claim for relief in any pleading must be asserted in the responsive pleading . . . . But a party may
    assert the following defenses by motion: . . . (6) failure to state a claim upon which relief can be
    granted[.]”).
    When considering whether to dismiss an action for failure to state a claim, the court must
    assess whether “a claim has been stated adequately” and then whether “it may be supported by
    [a] showing [of] any set of facts consistent with the allegations in the complaint.” Bell Atl. Corp.
    v. Twombly, 
    550 U.S. 544
    , 563 (2007). The plaintiff’s factual allegations must be substantial
    enough to raise the right to relief “above the speculative level,” accepting all factual allegations
    in the complaint as true and making all reasonable inferences in favor of the plaintiff. 
    Id. at 555.
    4
    D.      Issues Raised In The Government’s July 24, 2013 Motion To Dismiss.
    1.      Whether The Court Has Jurisdiction To Adjudicate Breach Of
    Contract Claims Arising From The Final Agreement.
    a.      The Government’s Argument.
    The Government advances two arguments in support of the Motion To Dismiss, pursuant
    to RCFC 12(b)(1). First, the court does not have jurisdiction to adjudicate the claims alleged in
    the April 15, 2013 Complaint under the Tucker Act, because the Final Agreement is not a
    contract. Gov’t Mot. 6–8. Second, the court does not have jurisdiction, because the Final
    Agreement does not contemplate money damages as a remedy. Gov’t Mot. 8–10.
    A clear indication of intent to contract must be found before concluding a contract has
    been formed. Gov’t Mot. 6 (citing D & N Bank v. United States, 
    331 F.3d 1374
    , 1378 (Fed. Cir.
    2003)). The Government, however, insists that the Final Agreement was not a contract but “a
    regulatory instrument,” the purpose of which was to “establish general provisions for the design
    [and] development . . . of a compensatory wetland bank[.]” Gov’t Mot. 7. The Army Corps’
    actions to “effectuate regulatory proclamations” and “exercise the Government’s sovereign
    function does not signify intent to contract.” Gov’t Mot. 6 (citing Anderson v. United States, 
    344 F.3d 1343
    , 1357 (Fed. Cir. 2003); D & N 
    Bank, 331 F.3d at 1378
    ).
    More specifically, the Government contends that the Army Corps’ role in the Final
    Agreement was in the nature of a regulator and supervisor, i.e. to verify “the geographic
    parameters of the proposed mitigation bank, . . . over[see] . . . the project, establish criteria that
    [the Bank] must follow to obtain credits, adjudge the suitability for a particular compensation
    proposal or compensation site, determine appropriate credit composition ratios, and generally
    inform [the Bank of non-compliance].” Gov’t Mot. 7 (internal citations and quotations omitted).
    As such, the Army Corps was not a party to the Final Agreement, but the regulation. Gov’t Mot.
    7 (citing Hearts Bluff Game Ranch, Inc. v. United States, 
    669 F.3d 1326
    , 1331 (Fed. Cir. 2012)
    (“The mitigation bank program is run exclusively by the [Army] Corps, subject to its pervasive
    control, and no landowner can develop a mitigation bank absent [its] approval.”)). And, the Final
    Agreement is a “regulatory arrangement[],” not a contract. Gov’t Mot. 8. In fact, the
    Government suggests that the court should view the Final Agreement as a permit. Gov’t Reply
    1–2 (citing Hearts Bluff Game 
    Ranch, 669 F.3d at 1331
    (referring to an application to establish a
    mitigation bank as a “permit”); United States v. Smith, 
    39 F.2d 851
    , 856 (1st Cir. 1930) (“In
    general, a license is not a contract.”); BLACK’S LAW DICTIONARY (9th ed. 2009) (defining
    “permit” as a “license”)).
    Only in “exceptional circumstances” may a court construe a permit to be a contract.
    Gov’t Reply 3 (citing Son Broadcasting, Inc. v. United States, 
    52 Fed. Cl. 815
    (2000) (finding
    that a Special Use Permit, together with an incorporated Site Plan, concerning the development
    of mountaintop broadcasting towers in a national forest was a contract)). In this case, the Final
    Agreement, unlike a contract, limits transferability. Gov’t Reply 4 (citing Hage v. United States,
    
    35 Fed. Cl. 147
    , 166–67 (1996) (stating that nontransferability weighs in favor of finding a
    permit to be a license, not a contract)). The Army Corps also maintained a “unilateral right to
    suspend activity under the [Final Agreement],” if the Army Corps determined that the Bank did
    5
    not meet certain requirements. Gov’t Reply 4 (citing 
    Hage, 35 Fed. Cl. at 166
    –67). In addition,
    the Final Agreement affords the Army Corps “the right to inspect, oversee, penalize, and
    generally manage and police, while [the Bank] is given little, if any, commensurate rights and
    privileges.” Gov’t Reply 4 (citing Meadow Green-Wildcat Corp. v. Hathaway, 
    936 F.2d 601
    ,
    604 (1st Cir. 1991) (treating a permit as a contract, where the terms did not grant “some special
    advantage” to the Government)); see also Gov’t Reply 5–7 (arguing that the Final Agreement
    includes no reciprocal obligations by the Army Corps). In other words, this is not a case where
    the permittee’s substantial capital investments create an inference of intent to contract, because
    “the only security offered . . . is . . . a staggered release of credits upon approval by the [Army]
    Corps for [the Bank] achieving various benchmarks in the creat[ed] wetlands.” Gov’t Reply 7–9.
    In the alternative, assuming arguendo that the Final Agreement is a contract, it does not
    contemplate the remedy of monetary damages, because the words “money” or “damage” are not
    included in the Final Agreement. Gov’t Mot. 8 (citing D & N 
    Bank, 331 F.3d at 1378
    (“[T]he
    intent to contract . . . is implausible because none of the documents . . . mentions goodwill or the
    accounting treatment thereof.”). Instead, in this case, the Bank attempts to transform its demand
    for additional credits into a demand for money damages. Gov’t Mot. 10. The only relief
    contemplated by the Final Agreement is “nonmonetary,” namely “credit adjustments under the
    Disputes Resolution Clause.” Gov’t Reply 9. Thus, “the only relief [the Bank] can rightly seek
    is extra credits . . . . [and t]he proper forum for such a dispute is the district courts.” Gov’t Reply
    10.
    b.      The Plaintiff’s Response.
    The Bank responds that the Final Agreement is an enforceable government contract and
    any claims arising thereunder are within the court’s jurisdiction. Pl. Resp. 4 (citing 28
    U.S.C. § 1491(a)(1)). The Army Corps wanted to protect ecological health and water quality. In
    response, the Bank agreed to “design, construct and maintain [a] wetlands bank” in exchange for
    mitigation credits that could be sold to third parties. Pl. Resp. 4–5. This was an “exchange of
    consideration between parties” memorialized in a “multi-page written agreement.” Pl. Resp. 5.
    The Umbrella Agreement, the Site-Specific Plan, and subsequent amendments reflect
    mutual obligations, rights, and responsibilities evidencing a contract. Pl. Resp. 5. For example,
    Section IX of the Final Agreement states that “[t]he terms and conditions of this Agreement shall
    be binding upon, and inure to the benefit of the parties hereto.” Compl. Ex. B at 13 (Umbrella
    Agreement).     Section IX thereof contains an integration clause, allows only written
    modifications, and restricts third-party claims. Pl. Resp. 5–6 (citing Compl. Ex. B at 14–15
    (Umbrella Agreement)).
    Irrespective of what definition one choses, the Final Agreement includes all elements of a
    contract. Pl. Resp. 6–7 (citing Harbert/Lummus Agrifuels Projects v. United States, 
    142 F.3d 1429
    , 1434 (Fed. Cir. 1998) (holding that an express government contract is evidenced by:
    mutual intent; an exchange of consideration; and lack of ambiguity in offer and acceptance);
    Buchanan v. Doe, 
    246 Va. 67
    , 72 (1993) (defining a contract as an agreement between two or
    6
    more persons that obligates them to do or not do a specific thing)).7 In this case, mutual
    understanding exists, because the Final Agreement sets forth the signatories’ “relative rights and
    duties regarding future performance related to design, construction and maintenance of the
    wetlands bank and the credit compensation to be provided . . . in exchange for such
    performance.” Pl. Resp. 7. And, Section IX(J) of the Final Agreement authorizes the signatories
    “to seek enforcement hereof.” Pl. Resp. 7 (quoting Compl. Ex. B at 15 (Umbrella Agreement)).
    The assertion that the Final Agreement is a “regulatory pronouncement” is not supported
    by the cases cited by the Government. Pl. Resp. 7 (citing Anderson, 
    344 F.3d 1343
    ; D & N
    Bank, 
    331 F.3d 1374
    ). In Anderson, the United States Court of Appeals for the Federal Circuit
    held that the Federal Home Loan Bank Board was not a party to a contract when it issued a
    resolution that approved a bank merger, but instead was a regulator. Pl. Resp. 8–9 (citing
    
    Anderson, 344 F.3d at 1357
    ). In this case, the Final Agreement does not only approve of a
    wetlands bank, but sets forth “a mutual and detailed agreement” and “evidences the [Army]
    Corps’ agreement to award specific credits for specific types of wetlands restoration within the
    bank.” Pl. Resp. 9. Because “the analysis in D & N Bank is essentially the same [as in
    Anderson] and Anderson relies on D & N Bank,” that case is similarly inapposite to “the facts
    and agreement in the case at bar.” Pl. Resp. 9.
    In addition, as the Government concedes, contracts “generally are presumed to create a
    substantive right to damages as a remedy.” Pl. Resp. 10 (quoting Gov’t Mot. 9). Therefore,
    according to the United States Court of Appeals for the Federal Circuit in Holmes v. United
    States, 
    657 F.3d 1303
    (2011), “when a breach of contract claim is brought in the [United States]
    Court of Federal Claims under the Tucker Act, the plaintiff comes armed with the presumption
    that money damages are available, so that normally no further inquiry is required.” Pl. Resp. 12
    (quoting 
    Holmes, 657 F.3d at 1314
    ). In fact, a government contract expressly must disavow
    money damages to avoid this presumption. Pl. Resp. 12 (citing 
    Holmes, 657 F.3d at 1314
    ).
    Here, the Final Agreement contemplates money damages, because the Army Corps was well
    aware that the Bank sold the credits to third parties, and thus any breach “would inherently affect
    the monetary compensation [the Bank] could derive from . . . the wetlands bank.” Pl. Resp. 13.
    c.             The Court’s Resolution.
    Common law governs the contractual relationship between a private party and the United
    States. See United States v. Winstar Corp., 
    518 U.S. 839
    , 871 (1996) (explaining that “ordinary
    principles of contract construction and breach . . . [that apply] to any contract action between
    private parties” govern a contract with the Government); Perry v. United States, 
    294 U.S. 330
    ,
    352 (1935) (“When the United States, with constitutional authority, makes contracts, it has rights
    and incurs responsibilities similar to those of individuals who are parties to such instruments.”).
    Accordingly, the United States Court of Appeals for the Federal Circuit has held that
    “jurisdiction under the Tucker Act requires the litigant to identify a substantive right for money
    7
    The Final Agreement specifies that it is governed by and is to be construed in
    accordance with United States and Virginia law. Pl. Resp. 6 (citing Compl. Ex. B at 14
    (Umbrella Agreement, Section IX(G))).
    7
    damages against the United States separate from the Tucker Act itself.” See 
    Todd, 386 F.3d at 1094
    . An express contract with the Government entails the following elements:
    (1) mutuality of intent to contract;
    (2) lack of ambiguity in offer and acceptance;
    (3) consideration; and
    (4) a government representative having actual authority to bind United States in
    contract.8
    
    Anderson, 344 F.3d at 1352
    ; see also Massie v. United States, 
    166 F.3d 1184
    , 1188 (Fed. Cir.
    1999) (“[A]ny agreement can be a contract within the meaning of the Tucker Act, provided that
    it meets the requirements for a contract with the Government.”).
    First, contract formation requires “an objective manifestation of voluntary, mutual
    assent.” 
    Anderson, 344 F.3d at 1353
    (citing RESTATEMENT (SECOND) OF CONTRACTS § 18
    (1981)). In other words, there must be a “clear indication of intent to contract and the other
    requirements for concluding that a contract was formed.” D & N 
    Bank, 331 F.3d at 1378
    .
    A good example is found in D & N Bank, where a Bank Board Resolution was deemed
    not to be a product of negotiation between the two parties, but only a memorialization of the
    Board’s approval of a merger between D & N Bank and another thrift bank. 
    See 331 F.3d at 1379
    ; see also 
    Anderson, 344 F.3d at 1357
    (same). In this case, unlike D & N Bank, the Final
    Agreement indicates a clear intent by the Army Corps to contract, and imposes mutual
    obligations on both parties. Compl. Ex. B at 11 (Umbrella Agreement) (“Bank Sponsor shall be
    responsible for maintaining the Bank in perpetuity[.]”); Compl. Ex. B at 13 (Umbrella
    Agreement) (“The terms and conditions of this Agreement shall be binding upon, and inure to
    the benefit of the parties hereto[.]”); Compl. Ex. B at 13 (Umbrella Agreement) (“[T]he Corps
    Permit Officer will specify any contemplated multiplier [for assigning credit liabilities to
    projects] and a rationale for its application.”).
    The inquiry into whether there is a mutual intent to contract overlaps, in part, with the
    requirement that there be a lack of ambiguity in offer and acceptance, since a plaintiff must offer
    objective evidence of “the existence of an offer and a reciprocal acceptance . . . [t]o satisfy its
    burden to prove . . . mutuality of intent.” 
    Anderson, 344 F.3d at 1353
    ; see also RESTATEMENT
    (SECOND) OF CONTRACTS § 22(1) (“The manifestation of mutual assent to an exchange ordinarily
    takes the form of an offer or proposal by one party followed by an acceptance by the other party
    or parties.”). In this case, the Final Agreement contains definite terms and recites the obligations
    contained and acceptance manifested by the signatures from a Bank representative, a District
    Engineer for the Army Corps, and a representative from USFWS. The documents and exhibits
    that together comprise the Final Agreement were reviewed and signed by the parties over the
    course of several years, suggesting a negotiated arms-length process. This ongoing process,
    8
    The Government has not argued that the Army Corps did not have authority to bind the
    United States in contract.
    8
    culminating in the parties signing three separate agreements, represents “the manifestation of
    willingness to enter into a bargain, so made as to justify another person in understanding that his
    assent to that bargain is invited and will conclude it.” 
    Anderson, 344 F.3d at 1353
    (quoting
    RESTATEMENT (SECOND) OF CONTRACTS § 24).
    As consideration for the Bank’s promise to restore wetlands subject to the Final
    Agreement, the Army Corps promised to issue the Bank credits, each now allegedly valued at
    $10,000 (Compl. ¶ 51).9 See, e.g., Smith v. Mountjoy, 
    280 Va. 46
    , 53, 
    694 S.E.2d 598
    , 602
    (2010) (“Consideration is, in effect, the price bargained for and paid for a promise. It may be in
    the form of a benefit to the party promising or a detriment to the party to whom the promise is
    made.” (quoting Brewer v. First Nat’l Bank of Danville, 
    202 Va. 807
    , 815 (1961)). In addition,
    under Virginia law, the Bank’s substantial remediation efforts investments are sufficient
    consideration for the Army Corps’ promise to award marketable credits. 
    Id. Therefore, the
    Government is mistaken in minimizing the substantial investment that the Bank has undertaken
    (Gov’t Reply 5–7), including the set-aside of a large number of acres of land, restoration of the
    land, and promises of long-term maintenance of that land. See, e.g., Compl. Ex. B at 11 (Long-
    Term Maintenance); Compl. Ex. C (Site-Specific Plan); see also Son 
    Broadcasting, 52 Fed. Cl. at 824
    (treating a permit and site plan to build a transmission tower as a contract, because of the
    plaintiff’s “substantial” investment in site development).
    Therefore, under the Final Agreement, the Army Corps agreed to enter into a contract
    with private parties to accomplish wetland restoration in exchange for issuing credits that could
    be sold “to third parties as compensation mitigation for unavoidable impacts to wetlands that
    were permitted pursuant to Section 404 [33 U.S.C. § 1344] of the [Clean Water Act].” Compl. ¶
    25; see also Compl. Ex. B at 1 (“The purpose of this Agreement is to establish the general
    provisions for . . . a compensatory wetland bank . . . . to compensate for unavoidable impacts to
    wetlands in advance of development actions[.]”); 60 FED. REG. at 58,608 (“The overall goal of a
    mitigation bank is to provide economically efficient and flexible mitigation opportunities[.]”).
    Contrary to the Government’s assertion, the Final Agreement is not a “regulatory
    instrument.” Gov’t Mot. 7. To distinguish a regulatory proclamation from a contract, the court
    may examine “resolutions, forbearance letters, assistance agreements, and supervisory action
    agreements to see if they consist of only regulatory proclamations, or if they include additional
    language, which clearly manifests the government’s intention to contract.” First Fed. Lincoln
    9
    As 
    discussed supra
    , the Bank committed to restore agricultural and forested areas to
    wetlands and preserve existing wetlands, as well as provide financial assurance for the Bank’s
    performance under the Final Agreement. Compl. ¶ 23 & Ex. B at 5. In exchange, the Army
    Corps would issue the Bank one wetland credit per 1.00 acre of restored cropland, 0.50 acres of
    restored previously-drained forest; or 7.5 acres of existing wetlands. Compl. Ex D.
    Ironically, the Final Agreement requires more from the Bank than of the Army Corps, but
    once consideration is established, however, courts do not weigh the adequacy of that
    consideration. See WILLISTON ON CONTRACTS § 7.21 (Adequacy of consideration) (“[S]o long
    as the requirement of a bargained-for benefit or detriment is satisfied, the fact that the relative
    value or worth of the exchange is unequal is irrelevant[.]”)
    9
    Bank v. United States, 
    60 Fed. Cl. 501
    , 503–04 (2004); cf. 
    Anderson, 344 F.3d at 1358
    (citing
    First Commerce Corp. v. United States, 
    335 F.3d 1373
    , 1378 (Fed. Cir. 2003). The fact that “no
    landowner can develop a mitigation bank absent [Army] Corps approval,” does not preclude the
    Army Corps from contracting with a private party.10 Hearts Bluff Game 
    Ranch, 669 F.3d at 1331
    .
    Nor is the Government correct that the absence of words such as “money” or “damage”
    preclude the remedy of money damages. “[I]n a contract case, the money-mandating
    requirement for Tucker Act jurisdiction normally is satisfied by the presumption that money
    damages are available for breach of contract, with no further inquiry being necessary.” 
    Holmes, 657 F.3d at 1314
    . The Government has cited no explicit language in the Final Agreement that
    overcomes the presumption of money damages, because none exists. To the contrary, explicit
    language in the Final Agreement and in communications between the parties manifests the Army
    Corps’ intention to enter into a contractual relationship with the Bank.
    For these reasons, the court has determined that it has jurisdiction to adjudicate the
    alleged breach of contract claims in the April 15, 2013 Complaint.
    2.             Whether The April 15, 2013 Complaint Pled A Breach Of Contract
    Claim.
    a.             The Government’s Argument.
    The Government also argues that the Bank did not sufficiently plead a breach of contract
    claim, requiring the court to dismiss the April 15, 2013 Complaint, pursuant RCFC 12(b)(6).
    Gov’t Mot. 10–11. First, the Bank did not allege a contractual duty by the Army Corps to adjust
    credit composition. Gov’t Mot. 11. The relevant provision of the Final Agreement states: “the
    credit composition . . . may be adjusted to reflect the maturation of the restored or created
    wetlands.” Gov’t Mot. 12 (quoting Compl. Ex. B at 11 (Umbrella Agreement); see also Gov’t
    Mot. 12 (citing Nat’l By-Prods., Inc. v. United States, 
    405 F.2d 1256
    , 1264 (Ct. Cl. 1969) (“[F]or
    a government representation . . . to be binding as a contractual obligation, it must have been in
    the form of an undertaking rather than a mere prediction or statement of opinion or intention.”)).
    Second, the Government’s “continued willingness to discuss an adjustment of the credit
    composition” cannot be construed as a breach of duty. Gov’t Mot. 14 (citing Compl. Ex. F).
    Third, the Bank has claimed speculative damages based on a “fair market value” of
    $10,000 per credit. Gov’t Mot. 15 (citing Wells Fargo Bank, N.A. v. United States, 
    88 F.3d 1012
    , 1023 (Fed. Cir. 1996) (declining to award speculative damages). The Bank’s valuation,
    10
    In Hearts Bluff Game Ranch, the United States Court of Appeals for the Federal Circuit
    held that the Army Corps’ refusal to allow the plaintiff to operate a mitigation bank was not a
    taking because the Army Corps’ “discretionary denial of access into the Corps program cannot
    be a cognizable property 
    interest.” 669 F.3d at 1331
    . Therefore, the Government’s assertion that
    Hearts Bluff Game Ranch prohibits the Army Corps from contracting with private parties to
    operate a mitigation bank is without merit. Gov’t Resp. 7.
    10
    however, “makes the implausible assumption that [the Bank] could have sold those credits on top
    of the cache of credits it hasn’t sold.” Gov’t Mot. 15 (citing Compl. ¶ 51).
    b.      The Plaintiff’s Response.
    The Bank responds that, because the Army Corps breached its contractual duty to adjust
    credit composition, the suggestion that “negotiations” are ongoing is not accurate, and the
    damages claimed are the foreseeable loss of profits. Pl. Resp. 20, 22. The only reasonable
    interpretation of the Final Agreement at issue, i.e., “the credit composition will be reevaluated
    and may be adjusted to reflect maturation” (Comp. Ex. B at 11), is that “the provision obligates
    the [Army] Corps to adjust the credit composition, if the required reevaluation reflects a different
    outcome than the breakdown contemplated by the parties prior to construction of the wetlands
    bank.” Pl. Resp. 17 (emphasis in original). To interpret that text of the Final Agreement as an
    option within the discretion of the Army Corps “flies in the face of the entire purpose of the
    agreement and . . . renders the phrase meaningless surplusage.” Pl. Resp. 17; see also 
    id. at 16
    (citing Nat’l By-Prods., 
    405 F.2d 1256
    (requiring that the text of a contract be construed in
    context); United Int’l Investigative Servs. v. United States, 
    109 F.3d 734
    , 737 (Fed. Cir. 1997)
    (holding that a contract must be interpreted, “as a whole and in a manner which gives reasonable
    meaning to all its parts” (internal quotations omitted)). Moreover, applicable federal regulations
    require that the wetland mitigation banks’ credits reflect actual site conditions. Pl. Resp. 18
    (citing 33 C.F.R. § 332.8(o)(3) (“The number of [wetland mitigation bank] credits must reflect
    the difference between pre- and post-compensatory mitigation project site conditions.”); 60 FED.
    REG. at 58,612 (“The number of available credits in a mitigation bank may need to be adjusted to
    reflect actual conditions.”). In addition, as a matter of law, Virginia courts have construed
    “may” as a mandatory term. Pl. Resp. 18–20 (citing Martin v. Howard, 
    273 Va. 722
    , 727 (2007)
    (construing “may” as mandatory in a statute allowing for exhumation of a body for genetic
    testing)).
    Second, the August 24, 2012 email does not evidence ongoing negotiations, but instead
    the Army Corps’ attempt to impose additional requirements on the Bank not included in the
    Final Agreement. Pl. Resp. 20–21.
    Third, the amount of damages incurred by the Bank has been addressed in Neely v.
    United States, 
    285 F.2d 438
    , 443 (Ct. Cl. 1961), wherein the United States Court of Claims held
    that lost profits were compensable damages. See 
    Neely, 285 F.2d at 443
    (explaining that, in
    certain circumstances, “loss of [sic] anticipated profits . . . . is a recognized measure of
    damages”). In addition, Wells Fargo Bank, cited by the Government, supports the Banks’
    position that the loss of profits tied to the loss of credits “were foreseeable at the time the parties
    entered into the Agreement.” Pl. Resp. 21–22 (citing Wells Fargo 
    Bank, 88 F.3d at 1023
    ).
    c.      The Court’s Resolution.
    For a claim to survive a motion to dismiss under RCFC 12(b)(6), it must be supported by
    more than merely speculative factual allegations, but the court also must make all reasonable
    inferences in favor of the plaintiff. See 
    Twombly, 550 U.S. at 555
    . Interpretation of a contract
    starts with the plain language, interpreted in light of the context, and giving “reasonable meaning
    11
    to all its parts.” United Int’l Investigative 
    Servs., 109 F.3d at 737
    (quoting Granite Constr. Co. v.
    United States, 
    962 F.2d 998
    , 1003 (Fed. Cir. 1992)).
    In this case, the plain language of the Final Agreement supports the Bank’s allegation
    (Compl. ¶ 50) that the Army Corps had a duty to fairly consider adjustments to the credit
    compensation. Compl. Ex. B at 11 (Umbrella Agreement) (“[A]t the end of the 5-year
    monitoring period . . . , the credit composition will be reevaluated and may be adjusted to reflect
    maturation of the restored or created wetlands.”). The April 15, 2013 Complaint also alleges that
    the Army Corps acknowledged that the forested wetlands at issue matured. Compl. ¶¶ 45–46.
    Therefore, it is reasonable to infer that the Army Corps breached the Final Agreement by not
    fairly and reasonably considering an adjustment to the credits at that time. Of course, the
    underlying factual issue of whether the Army Corp acted reasonably cannot be decided on a
    motion to dismiss. See, e.g., TrinCo Inv. Co v. United States, 
    722 F.3d 1375
    , 1380 (Fed. Cir.
    2013) (“To avoid dismissal under [RCFC] 12(b)(6), a party need only plead . . . with facts
    sufficient to nudge ‘claims across the line from conceivable to plausible.’” (quoting 
    Twombly, 550 U.S. at 570
    )). Although the word “may” appears to give the Army Corps’ discretion in
    adjusting the credit composition, that does not relieve the Army Corps from its obligation to
    issue credits, and the text of the Final Agreement does not state an “opinion or intention.” Cf.
    Nat’l 
    By-Prods., 405 F.2d at 1264
    (“[F]or a government representation . . . to be binding as a
    contractual obligation, it must have been in the form of an undertaking rather than a mere
    prediction or statement of opinion or intention.”).
    Therefore, whether the Army Corps denied the Bank’s request for a credit adjustment is a
    factual inquiry that cannot be decided on a motion to dismiss. See Bradley v. Chiron Corp., 
    136 F.3d 1317
    , 1321 (Fed. Cir. 1998) (When ruling on a motion to dismiss under Rule 12(b)(6),
    “factual statements in the complaint are accepted as true . . . . [and dismissal] is proper only
    when, on the complainant’s version of the facts, the premises of a cognizable claim have not
    been stated.”). The Complaint alleges that the August 24, 2012 email contains that denial.
    Compl. ¶ 49. The August 24, 2012 email states that the Army Corps does not support “issuing
    additional credit to the bank merely because the project . . . is an ecological success.” Compl.
    Ex. E at 1. To the extent that the Army Corps suggested other ways in which the Bank could
    generate additional credits, that is beside the point. Compl. Ex. E at 1 (“Additional
    compensatory mitigation credits could be generated from this site through additional real estate
    protection.”). The August 24, 2012 email evidences that the Army Corps denied the Bank’s
    request to issue credits, and, therefore, is sufficient to overcome the Government’s Motion To
    Dismiss.
    Finally, although the Government argues that $10,000 per credit of damages (Compl. ¶
    51) is speculative, this is not grounds for dismissal.
    12
    IV.    CONCLUSION.
    For these reasons, the Government’s July 24, 2013 Motion To Dismiss is denied. The
    court will contact the parties to convene a status conference to discuss discovery and a trial date.
    IT IS SO ORDERED.
    s/ Susan G. Braden
    SUSAN G. BRADEN
    Judge
    13
    

Document Info

Docket Number: 13-268C

Citation Numbers: 114 Fed. Cl. 113, 78 ERC (BNA) 1266, 2013 U.S. Claims LEXIS 1936, 2013 WL 6653684

Judges: Braden

Filed Date: 12/16/2013

Precedential Status: Precedential

Modified Date: 11/7/2024

Authorities (22)

donald-k-anderson-angel-cortina-jr-and-patricia-b-wallace-and-david , 344 F.3d 1343 ( 2003 )

United States v. Winstar Corp. , 116 S. Ct. 2432 ( 1996 )

Jill K. Massie, as Mother and Next Friend of Autumn Massie ... , 166 F.3d 1184 ( 1999 )

Colonel David W. Palmer, II v. United States , 168 F.3d 1310 ( 1999 )

Holmes v. United States , 657 F.3d 1303 ( 2011 )

F. S. Neely v. United States , 285 F.2d 438 ( 1961 )

United States v. Smith , 39 F.2d 851 ( 1930 )

United International Investigative Services v. The United ... , 109 F.3d 734 ( 1997 )

Smith v. Mountjoy , 280 Va. 46 ( 2010 )

Harbert/lummus Agrifuels Projects, Harbert International, ... , 142 F.3d 1429 ( 1998 )

Meadow Green-Wildcat Corporation, D/B/A Wildcat Mountain ... , 936 F.2d 601 ( 1991 )

National By-Products, Inc. v. The United States , 405 F.2d 1256 ( 1969 )

d-n-bank-a-federal-savings-bank-in-its-own-right-and-as-successor-to , 331 F.3d 1374 ( 2003 )

Bell Atlantic Corp. v. Twombly , 127 S. Ct. 1955 ( 2007 )

Donald A. Henke v. United States , 60 F.3d 795 ( 1995 )

Karen S. Reynolds v. Army and Air Force Exchange Service , 846 F.2d 746 ( 1988 )

daniel-w-bradley-v-chiron-corporation-william-j-rutter-edward-e , 136 F.3d 1317 ( 1998 )

Granite Construction Company v. The United States , 962 F.2d 998 ( 1992 )

jerry-todd-benjamin-e-abeyta-christopher-blas-abeyta-richard-acker , 386 F.3d 1091 ( 2004 )

United States v. Testan , 96 S. Ct. 948 ( 1976 )

View All Authorities »