Summit Multi-Family Housing Corporation v. United States , 2015 U.S. Claims LEXIS 1688 ( 2015 )


Menu:
  •        In the United States Court of Federal Claims
    No. 13-80C
    (Filed: December 17, 2015)
    )      Keywords: Subject Matter
    SUMMIT MULTI-FAMILY                         )      Jurisdiction; RCFC 12(b)(1);
    HOUSING CORPORATION,                        )      Contracts Disputes Act; 41 U.S.C.
    )      § 7102(a)(2); Takings Clause; Bid
    Plaintiff,          )      Protest; Corrective Action
    )
    v.
    )
    THE UNITED STATES,                          )
    )
    Defendant.          )
    )
    Lee P. Reno, Reno and Cavanaugh, PLLC, Washington, DC, with whom was
    Mona M. Lyons, Law Office of Mona Lyons, Washington, DC, for Plaintiff.
    James W. Poirier, Trial Attorney, with whom were Steven J. Gillingham, Assistant
    Director, Robert E. Kirschman, Jr., Director, and Benjamin C. Mizer, Principal
    Deputy Assistant Attorney General, Commercial Litigation Branch, Department of
    Justice, Washington, DC, for Defendant.
    OPINION AND ORDER
    Before the Court in this case are the government’s motion to dismiss for lack of
    subject matter jurisdiction or, in the alternative, for summary judgment, as well as
    Plaintiff’s cross-motion for partial summary judgment. For the reasons set forth below, in
    light of the Federal Circuit’s intervening decision in CMS Contract Mgmt. Servs. v.
    United States, 
    745 F.3d 1379
     (Fed. Cir. 2014), cert. denied, 
    135 S. Ct. 1842
     (2015), the
    Court grants the government’s motion to dismiss Count I (breach of express contract),
    Count II (breach of implied contract), and Count III (breach of implied duty of good faith
    and fair dealing) of Plaintiff’s complaint for lack of subject matter jurisdiction. Further, it
    grants the government’s motion to dismiss Count IV of the complaint, alleging an
    uncompensated taking of property because that claim is not ripe for review. Finally, the
    Court finds that it lacks jurisdiction to consider Count V of Plaintiff’s complaint, which
    Plaintiff has characterized as a bid protest.
    BACKGROUND
    I.     Invitation for Submission of Applications and Award to Plaintiff
    The Plaintiff in this case, Summit Multi-Family Housing Corporation (“SMHC”),
    is an Ohio not-for-profit corporation and a “public housing agency” (“PHA”) within the
    meaning of section 1437a(b)(6) of the United States Housing Act of 1937 (“Housing
    Act”), 
    42 U.S.C. §§ 1437
    –40. 2d Am. Compl. ¶ 3, ECF No. 16. Pursuant to that Act, the
    Secretary of the Department of Housing and Urban Development (“HUD”) is authorized
    to enter into annual contributions contracts (“ACC”) with PHAs. 42 U.S.C. § 1437f(b).
    An ACC, as defined by HUD regulations, is a “contract between HUD and a PHA under
    which HUD agrees to provide funding for a program under the 1937 Act, and the PHA
    agrees to comply with HUD requirements for the program.” 
    24 C.F.R. § 5.403
    . Pursuant
    to an ACC, a PHA may in turn enter into Housing Assistance Payment (“HAP”) contracts
    to make rental subsidy payments to owners of existing dwellings who provide housing to
    eligible low-income tenants. See 42 U.S.C. § 1437f(b)(1).
    On February 5, 2011, HUD issued an Invitation for Submission of Applications
    (“ISA”) “for the purpose of receiving applications from [PHAs] to administer the Project
    Based Section 8 [HAP] Contracts as Performance-Based Contract Administrators
    (PBCA).” 2d Am. Compl. Ex. B at 3. The ISA explained that HUD would “select one
    PBCA for each of the fifty United States, the District of Columbia, the United States
    Virgin Islands, and the Commonwealth of Puerto Rico.” Id. It further provided that “[t]he
    successful applicant for each State . . . will enter into a single Performance-Based Annual
    Contributions Contract . . . with HUD effective October 1, 2011, to administer HAP
    Contracts with owners of Section 8 projects in the State.” Id. Pursuant to the ISA,
    applications were required to include six specific sections: Certifications, Capability
    Statement, Technical Approach, Quality Control Plan, Reasoned Legal Opinion, and
    Disaster Plan. Id. at 10. Failure to comply with the procedures set forth in the ISA, HUD
    warned, “may result in the applicant being disqualified from award consideration.” Id.
    SMHC submitted applications to be the PBCA for New York, New Jersey, and
    Maryland. In three separate letters dated July 1, 2011, HUD notified SMHC that it had
    been “selected by the Department to serve as the new Performance Based Contract
    Administrator (PBCA)” for all three states. 2d Am. Compl. Exs. C–E. The letters stated,
    however, that SMHC’s Disaster Plans were deficient and they directed SMHC to submit
    corrected Disaster Plans by August 31, 2011. Id. In addition, enclosed with the letters
    were lists of the HAP Contracts assigned to the incumbent PBCAs. Id. SMHC was
    instructed to review the lists, determine whether any conflicts of interest existed, and
    submit conflict of interest certifications describing its proposed resolution of any
    conflicts found by July 31, 2011. Id.
    Further, the letters stated that SMHC, as the new PBCA, was required to “be fully
    operational and ready to administer the Annual Contributions Contract[s] (ACC) by
    September 30, 2011.” Id. Specifically, the letters explained, “[b]etween July 1, 2011, and
    September 30, 2011, all of the program and project related files, records, documents, and
    work in progress specified in the Department’s PBCA Transition Guidebook must be
    2
    obtained from the incumbent PBCA.” Id. HUD’s PBCA Transition Guidebook
    “outline[d] a uniform process to transfer responsibilities between Contract Administrators
    (CAs) who administer and oversee certain project-based subsidy contracts, under Section
    8” of the Housing Act. 2d Am. Compl. Ex. G at 4. It set forth specific transition tasks and
    due dates for the completion of those tasks over a ninety-day transition period. See id. at
    5–6. According to SMHC, it commenced performance of those tasks immediately upon
    receiving the award letters. 2d Am. Compl. ¶ 55.
    Just as SMHC received an award letter dated July 1, 2011, unsuccessful
    applicants, including the incumbents for New York, New Jersey, and Maryland, received
    letters dated July 1, 2011, notifying them that they had not been selected. 2d Am. Compl.
    Ex. F. These letters offered the unsuccessful PHAs an opportunity for a debriefing
    conference to discuss the weaknesses or deficiencies in their applications. Id. The letters
    to the incumbents stated that they were “required to close-out [their] current [contracts]
    and transfer the program and project files, records, and reports . . . to the [successful]
    PHA during the ninety (90) day period July 1, 2011 to September 30, 2011, as specified
    in the PBCA Transition Guidebook.” Id.
    II.    Bid Protests and HUD’s Corrective Action
    On July 11, 2011, a number of the unsuccessful applicants filed bid protests with
    the Government Accountability Office (“GAO”), contesting the selection of SMHC as
    the PBCA for New York, New Jersey, and Maryland, as well as the selections for forty-
    two other states. See 2d Am. Compl. Exs. I–L. The protestors contended that HUD’s
    evaluation of the applications did not conform with the ISA or procurement law. See
    Def.’s Mot. to Dismiss or, in the Alternative, for Summ. J. (“Def.’s Mot.”) App. at 92–
    111, ECF No. 17; see also CMS Contract Mgmt. Servs. v. United States (CMS I), 
    110 Fed. Cl. 537
    , 548 (2013) (observing that “the protests generally alleged that the PBACCs
    were procurement contracts and not properly awarded in accordance with federal
    procurement law, that out-of-state PHAs were not legally qualified to administer the
    Section 8 program within a given state, and that HUD’s evaluation of the applications
    was flawed”), rev’d sub nom. CMS Contract Mgmt. Servs. v. Massachusetts Hous. Fin.
    Agency, 
    745 F.3d 1379
     (Fed. Cir. 2014), cert. denied, 
    135 S. Ct. 1842
     (2015). SMHC
    claims that it learned of these protests “through informal means” in late July 2011, and it
    intervened in the protests shortly thereafter. Pl.’s Mem. in Opp’n to the Def.’s Mot. to
    Dismiss and in Supp. of Pl.’s Cross-Mot. for Partial Summ. J. (“Pl.’s Mem.”) App. at 13–
    14, ECF No. 21; 2d Am. Compl. ¶ 60.
    Meanwhile, SMHC continued to conduct its transition activities. Pl.’s Mem. App.
    at 13–14. It did so, according to SMHC, based on HUD’s advice. For example, SMHC
    alleges, HUD’s Contract Administrator Oversight Monitor stated during a conference call
    that HUD intended to carry on uninterrupted with the newly awarded PBCA contracts in
    spite of the pending protests. See id. at 14, 1001.
    On July 26, 2011, the president of SMHC sent an email to Deborah Lear, then the
    Director of HUD’s Office of Housing Assistance Contract Administration Oversight,
    “requesting confirmation that [SMHC] should be continuing in accordance with the
    3
    Transition Guide for an October 1 start date” and reminding her that SMHC was
    “expending funds and human resources as [it] move[d] forward.” Def.’s Mot. App. at
    125. In Ms. Lear’s response, dated July 27, 2011, she advised that “[d]ue to the GAO
    protests, we are not in a position to direct any transition activity from incumbents to new
    PBCA[s] for the states under protest.” Id. She also stated that “any decision regarding
    moving forward on any transition activity from [the] incumbent[s] to [SMHC] is a
    business decision left up to your organization.” Id. SMHC contends that it decided to
    move ahead with the transition “to protect its contract interests, and to avoid defaulting
    for failure to meet the Transition Guidebook deadlines.” Pl.’s Mem. at 24.
    On July 21, 2011, HUD moved to dismiss the GAO protests, arguing foremost
    that GAO lacked jurisdiction under the Competition in Contracting Act (“CICA”), 
    31 U.S.C. §§ 3551
    (1), 3552(a), because the ACCs were cooperative agreements, not
    procurement contracts. Pl.’s Mem. App. at 1006. Shortly thereafter, however, HUD
    notified GAO that it was going to withdraw the awards for the contracts that had been
    protested and “evaluate and revise its competitive award process for the selection of
    [PBCAs].” Def.’s Mot. App. at 126.
    HUD notified SMHC and other PHAs of its decision to take corrective action and
    re-compete the contracts in a letter dated August 11, 2011. Pl.’s Mem. App. 1089–90.
    About one month later, HUD sent SMHC another letter, dated September 8, 2011, stating
    that “the Department is rescinding its July 1, 2011, notice of a change of Performance
    Based Contract Administrator (PBCA) in your state.” Id. at 1092.
    According to the Declaration of Janet M. Golrick, who was then the Acting
    Deputy Assistant Secretary for Multifamily Housing Programs within HUD’s Office of
    Housing Division, “HUD’s primary reason for taking corrective action related to a
    contention by the protestors that HUD’s evaluation was flawed because it did not
    specifically inform applicants how HUD would evaluate the proposed fee.” Def.’s Mot.
    App. at 206; see also id. at 207–08. She further asserts that “HUD’s decision to take
    corrective action was solely a result of the allegations raised in the various bid protests
    and reflected a determination by HUD that there were portions of the ISA that needed to
    be improved to ensure the fairness of the competition and to comply with applicable
    law.” Id. at 208.
    III.   Re-Competition, Second Round of Bid Protests, and the Federal Circuit’s
    Decision in CMS Contract Management Services v. United States
    On March 9, 2012, HUD attempted to re-compete the PBACCs in the contested
    states by issuing a Notice of Funding Availability (“NOFA”). Id. at 139. The NOFA
    clarified certain evaluation criteria that had been challenged during the GAO protests.
    See id. at 145. It also explicitly noted for the first time that HUD intended to award
    cooperative agreements, not procurement contracts. Id. Contesting HUD’s
    characterization of the PBACCs as cooperative agreements, seven PHAs subsequently
    filed pre-award bid protests with GAO. See id. at 178–88; Assisted Housing Servs. Corp.,
    B-406738, 
    2012 WL 3341727
     (Comp. Gen. Aug. 15, 2012).
    4
    On August 15, 2012, GAO sustained the protests, concluding that HUD was
    “required to use a procurement instrument that results in a contract to obtain the provision
    of contract administration services by PHAs for the Project-Based Section 8 HAP
    contracts.” Def.’s Mot. App. at 186. It recommended “that HUD cancel the NOFA, and
    solicit the contract administration services . . . through a procurement instrument.” 
    Id.
     On
    December 3, 2012, however, HUD issued a notice indicating that it did not intend to
    follow the GAO’s recommendation. See CMS Contract Mgmt. Servs. v. United States
    (CMS II), 
    745 F.3d 1379
    , 1384 (Fed. Cir. 2014), cert. denied, 
    135 S. Ct. 1842
     (2015).
    The PHAs that had filed protests at GAO then filed pre-award bid protests in the
    Court of Federal Claims, again asserting that the ACCs should be classified as
    procurement contracts and that HUD’s NOFA violated CICA and the Federal Acquisition
    Regulations (“FAR”). CMS I, 110 Fed. Cl. at 541. The Court of Federal Claims granted
    judgment on the administrative record for the government, finding that HUD “properly
    classified [the PBACCs] as cooperative agreements.” Id.
    The PHAs appealed the Court of Federal Claims’ decision and, on March 25,
    2014, the Federal Circuit reversed. CMS II, 745 F.3d at 1386. According to the Federal
    Circuit, the PBACCs constituted procurement contracts and were subject to the statutes
    and regulations applicable thereto. Id. The government petitioned for a writ of certiorari
    from the United States Supreme Court; but on April 20, 2015, the Supreme Court denied
    certiorari, allowing the Federal Circuit’s decision to stand. See 
    135 S. Ct. 1842
     (2015).
    IV.    SMHC’s Action in This Court
    In the meantime, SMHC filed the present complaint in this court on January 30,
    2013, and filed amended complaints on April 22, 2013, and May 13, 2013. ECF Nos. 1,
    13, 16. In its complaints, SMHC claims that it entered into three PBCA contracts with
    HUD on July 1, 2011. 2d Am. Compl. ¶ 54. It further contends that pursuant to those
    contracts, it was required it to undertake certain transition tasks that HUD had identified
    in its Transition Guidebook during the first three months of contract performance. 
    Id.
     It
    claims that it immediately commenced performance under the contracts by beginning to
    perform those tasks. Id. ¶ 55. And finally, it claims that HUD breached the contracts on
    September 8, 2011, when it officially notified SMHC of their rescission. Id. ¶¶ 69–70.
    SMHC’s second amended complaint contains five counts: breach of express
    contract (the three PBCA contracts); breach of implied contract consisting of the same
    terms as the alleged express contracts; breach of implied duty of good faith and fair
    dealing with respect to the three PBCA contracts; uncompensated taking of Plaintiff’s
    property interest in the three PBCA contracts in violation of the Fifth Amendment; and a
    bid protest claim (which was not included in SMHC’s earlier complaints) asserting that
    HUD acted arbitrarily, capriciously, and contrary to law in awarding the PBCA contracts
    to SMHC and then rescinding the contracts on September 8, 2011. Id. ¶¶ 72–100.1
    1
    In Counts I through IV, SMHC seeks $4,938,545.46 in damages—the amount,
    according to SMHC, that it earned in fees under the contracts for the work it performed
    5
    On June 17, 2013, the government filed a motion to dismiss the complaint in its
    entirety for failure to state a claim or, in the alternative, for summary judgment. ECF No.
    17. The government’s primary argument in that motion was that no contract existed
    between HUD and SMHC because the parties never executed a written ACC. Def.’s Mot.
    at 12–16. It further argued that the doctrine of laches barred SMHC’s bid protest claim
    and that, in any event, it was entitled to judgment on the administrative record with
    respect to that claim. Id. at 31–32. SMHC filed a cross-motion for partial summary
    judgment on August 19, 2013. ECF No. 21. The government filed a response and reply
    on November 1, 2013, ECF No. 29; and SMHC filed a reply on December 19, 2013, ECF
    No. 34.
    After the Federal Circuit’s March 25, 2014 decision in CMS II, the government
    filed a notice of supplemental authority in which it contended that—in light of that
    decision—this Court should dismiss Counts I–IV of the complaint for lack of jurisdiction
    pursuant to Rules of the Court of Federal Claims (“RCFC”) 12(b)(1). Def.’s Notice of
    Suppl. Authority at 2–3, ECF No. 35. This Court then stayed the case pending the
    Supreme Court’s disposition of any petition for certiorari filed by the government. Order
    Staying Case, ECF No. 42. As described above, the government filed such a petition,
    which the Supreme Court denied on April 20, 2015. Pursuant to this Court’s Order, the
    parties then filed supplemental briefs addressing the impact of the Federal Circuit’s
    decision in CMS II on this Court’s jurisdiction over SMHC’s complaint. ECF Nos. 50–
    52.
    For the reasons set forth below, the Court concludes that, pursuant to the ruling in
    CMS II, SMHC’s breach of contract claims are subject to the Contract Disputes Act
    (“CDA”), 
    41 U.S.C. § 7102
    (a)(2). It further concludes that SMHC did not submit a valid,
    certified claim to the contracting officer and receive the contracting officer’s final
    decision on that claim, as is required to invoke this Court’s jurisdiction under that Act.
    See M. Maropakis Carpentry, Inc. v. United States, 
    609 F.3d 1323
    , 1329 (Fed. Cir. 2010).
    Therefore, Counts I–III of SMHC’s second amended complaint must be dismissed for
    lack of jurisdiction.
    In addition, the Court finds that because SMHC did not exhaust the required
    administrative procedure for breach of contract, its takings claim is not ripe for review.
    Therefore, Count IV of the complaint must similarly be dismissed.
    prior to HUD’s rescission; or, in the alternative, $2,304,631.02—the amount, according
    to SMHC, it incurred in costs and expenses, plus its lost profits. 2d Am. Compl. ¶¶ 78,
    81, 89, 93. In Count V, SMHC seeks $690,106.26—the amount it expended in preparing
    its bid. Id. ¶ 100.
    6
    Finally, the Court concludes that SMHC lacks standing to assert the claims set
    forth in Count V of its amended complaint, which it characterizes as a “bid protest.”
    Accordingly, Count V is dismissed for lack of jurisdiction.
    DISCUSSION
    I.     Motion to Dismiss Under RCFC 12(b)(1)
    Whether this Court has jurisdiction to decide a case is a threshold matter, and, if
    no jurisdiction exists, the Court must order dismissal without proceeding further. See
    PODS, Inc. v. Porta Stor, Inc., 
    484 F.3d 1359
    , 1365 (Fed. Cir. 2007) (citing Steel Co. v.
    Citizens for a Better Env’t, 
    523 U.S. 83
    , 94–95 (1998)). In deciding a motion to dismiss
    for lack of subject matter jurisdiction, the court accepts as true all undisputed facts in the
    plaintiff’s complaint and draws all reasonable inferences in favor of the plaintiff. Trusted
    Integration, Inc. v. United States, 
    659 F.3d 1159
    , 1163 (Fed. Cir. 2011). If subject matter
    jurisdiction is challenged, however, the plaintiff cannot rely merely on allegations in the
    complaint, but must instead bring forth relevant, competent proof to establish jurisdiction.
    Reynolds v. Army & Air Force Exch. Serv., 
    846 F.2d 746
    , 748 (Fed. Cir. 1988). The
    party invoking a court’s jurisdiction bears the burden of establishing it, and must
    ultimately do so by a preponderance of the evidence. Id.; Rocovich v. United States, 
    933 F.2d 991
    , 993 (Fed. Cir. 1991).
    II.    Jurisdiction Over Counts I–III—Contract Claims
    A.      Tucker Act
    Pursuant to the Tucker Act, the United States Court of Federal Claims may
    “render judgment upon any claim against the United States founded either upon the
    Constitution, or any Act of Congress or any regulation of an executive department, or
    upon any express or implied contract with the United States, or for liquidated or
    unliquidated damages in cases not sounding in tort.” 
    28 U.S.C. § 1491
    (a) (2012).
    Subsection (a)(2) of the section 1491 further grants the Court of Federal Claims
    “jurisdiction to render judgment upon any claim by or against, or dispute with, a
    contractor arising under section 7104(b)(1) of title 41”—that is, the CDA—“including a
    dispute concerning termination of a contract, rights in tangible or intangible property,
    compliance with cost accounting standards, and other nonmonetary disputes on which a
    decision of the contracting officer has been issued under section 6 of that Act.”
    B.      The Contract Disputes Act
    The CDA covers any claims based upon “any express or implied contract . . .
    made by an executive agency for—(1) the procurement of property, other than real
    property in being; (2) the procurement of services; (3) the procurement of construction,
    alteration, repair, or maintenance of real property; or (4) the disposal of personal
    property.” 
    41 U.S.C. § 7102
    (a). Under the CDA, “procurement” means “the acquisition
    by purchase, lease or barter, of property or services for the direct benefit or use of the
    Federal Government.” New Era Constr. v. United States, 
    890 F.2d 1152
    , 1157 (Fed. Cir.
    1989) (quotation and emphasis omitted).
    7
    The CDA sets forth its own jurisdictional requirements. See M. Maropakis
    Carpentry, 
    609 F.3d at
    1327–28. In particular, it states that a contractor may only bring
    an action de novo in federal court “within 12 months from the date of receipt of a
    contracting officer’s decision.” 
    41 U.S.C. § 7104
    (b)(3). Thus, the Federal Circuit has held
    that for the Court of Federal Claims to possess jurisdiction, the contractor must have first
    submitted a valid claim to its contracting officer and received the contracting officer’s
    final decision on that claim. M. Maropakis Carpentry, 
    609 F.3d at
    1327–28. Further,
    “[w]hen the Contract Disputes Act applies, it provides the exclusive mechanism for
    dispute resolution; the Contract Disputes Act was not designed to serve as an alternative
    administrative remedy, available at the contractor’s option.” Dalton v. Sherwood Van
    Lines, Inc., 
    50 F.3d 1014
    , 1017 (Fed. Cir. 1995).
    The definition of “claim” for purposes of the CDA derives from the FAR, which
    implements the CDA. See M. Maropakis Carpentry, 
    609 F.3d at
    1327–28. FAR 2.101
    provides, in pertinent part that “claim” means “a written demand or written assertion by
    one of the contracting parties seeking, as a matter of right, the payment of money in a
    sum certain, the adjustment or interpretation of contract terms, or other relief arising
    under or relating to the contract.” Id.; see also FAR 52.233-1 (setting forth, in a standard
    contract clause, the same definition of “claim” as in FAR 2.101). The Federal Circuit,
    interpreting this provision, has held that a valid CDA claim consists of three components:
    “(1) a written demand, (2) seeking, as a matter of right, (3) the payment of money in a
    sum certain.” Northrop Grumman Computing Sys., Inc. v. United States, 
    709 F.3d 1107
    ,
    1112 (Fed. Cir. 2013) (citing Reflectone, Inc. v. Dalton, 
    60 F.3d 1572
    , 1575–76 (Fed.
    Cir. 1995)). The Federal Circuit has further explained that “[w]hile a valid claim under
    the CDA must contain ‘a clear and unequivocal statement that gives the contracting
    officer adequate notice of the basis and amount of the claim,’ the claim need not take any
    particular form or use any particular wording.” 
    Id.
     (quoting Contract Cleaning Maint.,
    Inc. v. United States, 
    811 F.2d 586
    , 592 (Fed. Cir. 1987)). “All that is required,” the
    Federal Circuit has observed, “is that the contractor submit in writing to the contracting
    officer a clear and unequivocal statement that gives the contracting officer adequate
    notice of the basis and amount of the claim.” 
    Id.
     (quoting Contract Cleaning Maint., Inc.,
    
    811 F.2d at 592
    ).
    For claims seeking more than $100,000, FAR 2.101 additionally incorporates
    within the definition of “claim” the CDA’s certification requirement. 
    41 U.S.C. § 7103
    (b)(1). That requirement provides as follows:
    For claims of more than $100,000 made by a contractor, the contractor shall
    certify that--
    (A)     the claim is made in good faith;
    (B)     the supporting data are accurate and complete to the best of the
    contractor’s knowledge and belief;
    (C)     the amount requested accurately reflects the contract adjustment
    for which the contractor believes the Federal Government is
    liable; and
    (D)     the certifier is authorized to certify the claim on behalf of the
    contractor.
    8
    Id.; see also FAR 33.207(c) (providing specific certification language, which includes the
    language of § 7103(b)(1) nearly verbatim).
    C.      The Court Lacks Jurisdiction Over Plaintiff’s Contract Claims
    In CMS II, the government argued that HUD’s PBACCs are cooperative
    agreements and not procurement contracts and that their principal purpose was to
    distribute grant funds. 745 F.3d at 1385–86. The Federal Circuit, however, rejected that
    argument, concluding that “the primary purpose of the PBACCs is to procure the services
    of the PBCAs to support HUD’s staff and provide assistance to HUD with the oversight
    and monitoring of Section 8 housing assistance.” Id. at 1385. As both SMHC and the
    government agree, the necessary conclusion to be drawn from the Federal Circuit’s
    decision is that PBACCs are procurement contracts subject to the CDA. See Def.’s Resp.
    to Order at 3, ECF No. 50; Pl.’s Resp. to Order at 2, ECF No. 51.
    SMHC argues nonetheless that its breach of contract claims are not subject to the
    CDA’s exhaustion requirement, contending that the July 1, 2011 contracts it entered with
    HUD were not themselves PBACCs. See Pl.’s Resp. to Order at 2. “At most,” SMHC
    contends, they were “agreements to later enter into what should have been procurement
    contracts but were not regarded as such by either party at the time.” Id.
    This contention is unavailing for several reasons. First, the contention is
    inconsistent with the allegations in SMHC’s complaints. As described above, SMHC’s
    complaints clearly characterize the breach claims as involving violations of the PBACCs
    themselves, and not violations of some other preliminary agreement to enter PBACCs.
    Moreover, and in any event, SMHC acknowledges that “[t]he July 1, 2011
    contracts obligated SMHC to be ‘fully operational and ready to administer the [PBACCs]
    by September 30, 2011’ and to obtain ‘all of the program and project related files,
    records, documents, and work in progress specified in the Department’s PBCA Transition
    Guidebook’ from the incumbent Contract Administrator between July 1, 2011 and
    September 30, 2011.” Id. (quoting HUD’s selection letters). Thus, even if the alleged
    breaches were of an agreement to subsequently enter procurement contracts, that
    agreement in and of itself allegedly obligated SMHC to provide transitional services to
    HUD and would therefore be considered a procurement contract in its own right.
    SMHC’s argument that—assuming that the CDA applies—it complied with that
    Act’s administrative exhaustion requirement is similarly unpersuasive. It observes that
    “[o]n December 9, 2011, only a few months after HUD rescinded the July 1, 2011
    contracts, SMHC submitted a letter (the written claim) to then-HUD Secretary Shaun
    Donovan (the contracting officer) requesting reimbursement ‘for all expenses incurred’
    pursuant to the July 1, 2011 contracts and ‘payment of the Administrative Fees to which
    [SMHC] would have been entitled . . . had HUD not unilaterally repudiated and breached
    its contract[s] with SMHC.’” Id. at 5–6 (quoting Pl.’s Resp. to Order Ex. 1 at 1). SMHC
    notes that “HUD did not respond to the December 9, 2011 letter within the 60 days
    mandated by the CDA” or to a subsequent demand letter sent by its counsel to then-
    Secretary Donovan on October 12, 2012. Id. at 6.
    9
    Assuming (without deciding) that then-Secretary Donovan could be considered a
    contracting officer for purposes of the CDA, the two letters nonetheless do not meet the
    CDA’s exhaustion requirements. As explained above, a valid CDA claim consists of
    three components: “(1) a written demand, (2) seeking, as a matter of right, (3) the
    payment of money in a sum certain.” Northrop Grumman Computing, 709 F.3d at 1112
    (citing Reflectone, Inc., 
    60 F.3d at
    1575–76). In this case, neither letter constitutes a
    claim because neither identifies a “sum certain” that SMHC was seeking as a matter of
    right.
    Further, neither letter satisfies the certification requirement for claims exceeding
    $100,000 set forth in section 7103(b) of the CDA and incorporated into FAR 2.101. As
    described above, a certification must affirmatively state that the claim is made in good
    faith; that the supporting data are accurate and complete to the best of the contractor’s
    knowledge and belief; that the amount requested accurately reflects the contract
    adjustment for which the contractor believes the federal government is liable; and that the
    certifier is authorized to certify the claim on behalf of the contractor. 
    41 U.S.C. § 7103
    (b)(1). None of these requirements are met in the two letters SMHC sent to then-
    Secretary Donovan.2
    In short, this Court lacks jurisdiction over SMHC’s contract claims (contained in
    Counts I–III of its complaint) because SMHC failed to exhaust its administrative
    remedies under the CDA by failing to file a valid, certified claim with HUD.
    Accordingly, Counts I through III of the complaint must be dismissed.
    III.   Count IV—Takings
    In Count IV of its complaint, SMHC alleges that the PBACC contracts it entered
    with HUD created property interests protected by the Fifth Amendment’s Takings
    Clause. 2d Am. Compl. ¶ 91. Therefore, SMHC claims, when HUD unilaterally
    rescinded the contracts, it was required to compensate SMHC for its “costs, expenses,
    earned Administrative Fees, and/or earned profits” lost as a result of the government’s
    taking of its contract property. Id. ¶ 92.
    It is well established that claims for damages under the Takings Clause of the
    Fifth Amendment are within this Court’s Tucker Act jurisdiction. E.g., Jan’s Helicopter
    Serv., Inc. v. Fed. Aviation Admin., 
    525 F.3d 1299
    , 1309 (Fed. Cir. 2008). The
    government argues, however, that because SMHC failed to exhaust the administrative
    procedure prescribed by the CDA for pursuing its breach of contract claims, its takings
    claim is not ripe and should be dismissed on that basis.
    2
    These requirements are more than just a formality. Indeed, the Federal Circuit has held
    that “the statutory mandate that all claims over [a specified amount] must be certified is
    one of the most significant provisions of the CDA.” Fidelity Const. Co. v. United States,
    
    700 F.2d 1379
    , 1384 (Fed. Cir. 1983).
    10
    The Court agrees with the government. The purpose of the ripeness doctrine is to
    prevent the courts, “through avoidance of premature adjudication, from entangling
    themselves in abstract disagreements over administrative policies, and also to protect the
    agencies from judicial interference until an administrative decision has been formalized
    and its effects felt in a concrete way by the challenging parties.” Abbott Labs. v. Gardner,
    
    387 U.S. 136
    , 148–49 (1967), overruled on other grounds by Califano v. Sanders, 
    430 U.S. 99
     (1977). “In assessing ripeness, there are two basic factors: ‘(1) the fitness of the
    issues for judicial decision[;] and (2) the hardship to the parties of withholding court
    consideration.’” Sys. Application & Techs., Inc. v. United States, 
    691 F.3d 1374
    , 1383–
    84 (Fed. Cir. 2012) (alteration in original) (quoting Abbott Labs., 
    387 U.S. at 149
    ).
    “When a party challenges government action, the first factor becomes a question of
    whether the challenged conduct constitutes a final agency action.” Id. at 1384.
    In this case, the takings claim is not fit for review because it is inextricably
    intertwined with SMHC’s contract claims. There has been no final agency decision with
    respect to the action that SMHC challenges as a taking—the rescission of its alleged
    contracts with HUD—because the claims have not been presented to the contracting
    officer as the CDA requires.
    In short, permitting SMHC to bring the takings claim to Court without first filing
    a contract claim with the contracting officer would allow it to circumvent the
    administrative process that Congress established for the resolution of federal procurement
    contract disputes. For that reason, the Court concludes that the takings claim should be
    dismissed as unripe. See McGuire v. United States, 
    707 F.3d 1351
    , 1359–60 (Fed. Cir.
    2013) (“There is no dispute that ‘when an agency provides procedures for obtaining a
    final decision, a takings claim is unlikely to be ripe until the property owner complies
    with those procedures.’” (quoting Morris v. United States, 
    392 F.3d 1372
    , 1376 (Fed. Cir.
    2004))); Medina Const., Ltd. v. United States, 
    43 Fed. Cl. 537
    , 560 (1999) (takings claim
    involving rights under contract not ripe for review where plaintiff failed to present claims
    to contracting officer as required by the CDA). Accordingly, the Court lacks jurisdiction
    over the claims asserted in Count IV of SMHC’s complaint.
    IV.    Count V—Bid Protest
    The Court of Federal Claims’ bid protest jurisdiction is defined by 
    28 U.S.C. § 1491
    (b)(1). That provision grants the Court jurisdiction to “render judgment on an
    action by an interested party objecting to . . . a proposed award or the award of a contract
    or any alleged violation of statute or regulation in connection with a procurement or a
    proposed procurement.” As specified, only an “interested party” has standing to invoke
    the Court’s bid protest jurisdiction under 
    28 U.S.C. § 1491
    (b)(1). CGI Fed. Inc. v. United
    States, 
    779 F.3d 1346
    , 1348 (Fed. Cir. 2015); Myers Investigative and Sec. Servs., Inc. v.
    United States, 
    275 F.3d 1366
    , 1369 (Fed. Cir. 2002) (“[S]tanding is a threshold
    jurisdictional issue.”). An “interested party” is “an actual or prospective bidder or offeror
    whose direct economic interest would be affected by the award of the contract.” CGI
    Fed., 779 F.3d at 1348 (quoting Am. Fed’n of Gov’t Emps., AFL-CIO v. United States,
    
    258 F.3d 1294
    , 1299 (Fed. Cir. 2001)); see also Info. Tech. & Applications Corp. v.
    United States, 
    316 F.3d 1312
    , 1319 (Fed. Cir. 2003). In a post-award bid protest, a
    11
    disappointed bidder may establish its “direct economic interest” by showing that it had a
    “substantial chance” of winning the award “but for the alleged error in the procurement
    process.” Tinton Falls Lodging Realty, LLC v. United States, 
    800 F.3d 1353
    , 1358 (Fed.
    Cir. 2015); see also Bannum, Inc. v. United States, 
    404 F.3d 1346
    , 1358 (Fed. Cir. 2005).
    In this case, at least up until oral argument was held, the government did not
    challenge SMHC’s standing to pursue its bid protest. See Def.’s Resp. to Order at 2
    (“We do not challenge the jurisdiction of the Court to consider Summit’s claim for bid
    preparation costs.”). Despite this concession, of course, the Court has an independent
    duty to “satisfy itself . . . of its own jurisdiction.” Textile Prod’s, Inc. v. Mead Corp., 
    134 F.3d 1481
    , 1485–86 (Fed. Cir. 1998) (quoting Bender v. Williamsport Area Sch. Dist.,
    
    475 U.S. 534
    , 541 (1986)); see also Special Devices, Inc. v. OEA, Inc., 
    269 F.3d 1340
    ,
    1342–43 (Fed. Cir. 2001).
    Notwithstanding the government’s prior concession, the Court concludes that it
    lacks jurisdiction over the bid protest claim because SMHC lacks standing to pursue it.
    To be sure, SMHC would have standing to challenge the corrective action that HUD
    took, which resulted in the withdrawal of the contract award, the subsequent issuance of
    the NOFA, and a re-competition. See, e.g., Sys. Application & Techs., Inc., 691 F.3d at
    1382–83 (awardee has standing to challenge corrective action that results in rescission of
    its award and re-competition of contract). But SMHC does not claim that HUD’s decision
    to take corrective action was arbitrary, capricious, or contrary to law. In fact, SMHC’s
    allegations suggest precisely the opposite conclusion.
    Thus, SMHC’s complaint cites Ms. Golrick’s statements that the process HUD
    used during the initial procurement “needed to be improved to ensure the fairness of the
    competition and to comply with applicable law” and that HUD had failed to specifically
    disclose “how HUD would evaluate the proposed fee [under the ISA]”). 2d Am. Compl.
    ¶ 96 (alteration in original). It also cites and quotes statements made by the government
    in its pleadings before the trial court in CMS I to the effect that HUD used ambiguous
    evaluation criteria and that its ISA and selection process created confusion and was
    inconsistent with HUD standards. Id. Each of these explanations, SMHC alleges, was “an
    admission by [HUD] that it failed to comply with the statutes, regulations, and other
    HUD standards that govern HUD in administering ‘procurements’ for the award of
    PBCA contracts.” Id.; see also Pl.’s Mem. at 58–59.
    Further, at oral argument on the cross motions, which was held on December 9,
    2015, counsel for SMHC confirmed that it was not alleging that HUD acted unlawfully or
    unreasonably when it decided to take corrective action. Rather, counsel contended that
    the gravamen of Count V of the complaint was that the initial competition was marked by
    violations of law and/or arbitrary action and that SMHC suffered injury as a result of
    these alleged violations because they resulted in the cancellation of its contract. Oral Arg.
    at 20:30–21:53.
    Of course, the mere fact that HUD decided to take corrective action is not
    sufficient to show that its initial award to SMHC was arbitrary, capricious, or contrary to
    law. ManTech Telecomms. & Info. Sys. Corp. v. United States, 
    49 Fed. Cl. 57
    , 72 & n.24
    12
    (2001) (observing that “the government is not obliged to admit an error as a precondition
    to proposing corrective action,” nor is it “necessary for an agency to conclude that the
    protest is certain to be sustained before it may take corrective action; where the agency
    has reasonable concern that there were errors in the procurement, even if the protest
    could be denied” (quotation omitted)), aff’d, 30 F. App’x 995 (Fed. Cir. 2002); accord
    Data Monitor Sys., Inc. v. United States, 
    74 Fed. Cl. 66
    , 74 (2006). But more to the point,
    to the extent that the initial procurement was marred by arbitrary, capricious, or illegal
    decision-making by HUD, SMHC lacks standing to challenge such decision-making
    because SMHC was not injured by those alleged improprieties. See Info. Tech., 
    316 F.3d at 1319
     (observing that “the question of prejudice goes directly to the question of
    standing” and that “prejudice (or injury) is a necessary element of standing” (quotation
    and citations omitted)). To the contrary, at the end of the allegedly flawed process,
    SMHC was the awardee. In fact, SMHC originally intervened on the side of HUD to
    defend the original award when it was challenged before the GAO.
    It was not the award, but rather it was the corrective action (whose lawfulness and
    reasonableness SMHC does not challenge) that resulted in injury to SMHC. And while
    there are many cases in which a successful offeror challenges the reasonableness of an
    agency’s corrective action, SMHC has not identified a single case in which a successful
    offeror whose award was rescinded as a result of voluntary corrective action mounted a
    bid protest that instead challenged the very process that had resulted in its contract
    award.3
    In short, SMHC lacks standing to mount the claim it articulates in Count V of its
    complaint. Accordingly, that Count must be dismissed.4
    CONCLUSION
    On the basis of the foregoing, the government’s motion to dismiss the complaint
    is GRANTED and Plaintiff’s complaint is DISMISSED without prejudice. The parties’
    3
    It also bears noting that even if SMHC somehow had standing to challenge the process
    that resulted in its contract award, any challenge to that process would in any event be
    moot. See Coastal Envtl. Grp., Inc. v. United States, 
    114 Fed. Cl. 124
    , 131 (2013) (“[T]he
    Court of Federal Claims has consistently found that the cancellation of a procurement
    renders a protest of that procurement moot.”); CCL Serv. Corp. v. United States, 
    43 Fed. Cl. 680
    , 689–90 (1999) (concluding that the court could not award bid preparation costs
    where protestor did not challenge corrective action which resulted in cancelation of the
    solicitation and decision to re-solicit the procurement, because the corrective action
    rendered moot the unsuccessful offeror’s challenge to the original evaluation and award).
    4
    In light of its conclusion that it lacks jurisdiction over Count V of the complaint, the
    Court does not address the government’s argument that the doctrine of laches bars
    SMHC’s pursuit of its bid protest claim.
    13
    cross-motions for summary judgment are therefore DENIED as moot. Each side shall
    bear its own costs.
    The Clerk is directed to enter judgment accordingly.
    IT IS SO ORDERED.
    /s/ Elaine D. Kaplan
    ELAINE D. KAPLAN
    Judge
    14
    

Document Info

Docket Number: 13-80C

Citation Numbers: 124 Fed. Cl. 562, 2015 U.S. Claims LEXIS 1688, 2015 WL 9252556

Judges: Elaine D. Kaplan

Filed Date: 12/17/2015

Precedential Status: Precedential

Modified Date: 10/19/2024

Authorities (18)

Califano v. Sanders , 97 S. Ct. 980 ( 1977 )

Special Devices, Inc. v. Oea, Inc. , 269 F.3d 1340 ( 2001 )

Reflectone, Inc. v. John H. Dalton, Secretary of the Navy , 60 F.3d 1572 ( 1995 )

Fidelity Construction Company v. The United States , 700 F.2d 1379 ( 1983 )

Steel Co. v. Citizens for a Better Environment , 118 S. Ct. 1003 ( 1998 )

Contract Cleaning Maintenance, Inc. v. The United States , 811 F.2d 586 ( 1987 )

Textile Productions, Inc. v. Mead Corporation and Fiber ... , 134 F.3d 1481 ( 1998 )

Pods v. Porta Stor , 484 F.3d 1359 ( 2007 )

Robert E. Morris and Carol L. Morris v. United States , 392 F.3d 1372 ( 2004 )

John G. Rocovich, Jr. v. The United States , 933 F.2d 991 ( 1991 )

Trusted Integration, Inc. v. United States , 659 F.3d 1159 ( 2011 )

american-federation-of-government-employees-afl-cio-american-federation , 258 F.3d 1294 ( 2001 )

Jan's Helicopter Service, Inc. v. Federal Aviation ... , 525 F.3d 1299 ( 2008 )

Abbott Laboratories v. Gardner , 87 S. Ct. 1507 ( 1967 )

John H. Dalton, Secretary of the Navy v. Sherwood Van Lines,... , 50 F.3d 1014 ( 1995 )

Karen S. Reynolds v. Army and Air Force Exchange Service , 846 F.2d 746 ( 1988 )

Myers Investigative and Security Services, Inc. v. United ... , 275 F.3d 1366 ( 2002 )

Bannum, Inc. v. United States , 404 F.3d 1346 ( 2005 )

View All Authorities »