Carolina Power & Light Co. v. United States , 2014 U.S. Claims LEXIS 320 ( 2014 )


Menu:
  •       In the United States Court of Federal Claims
    No. 11-869C
    (Filed: March 10, 2014)
    ************************************** *
    *
    CAROLINA POWER & LIGHT CO. et al.,     *
    *             Spent Nuclear Fuel Case; Nuclear
    Plaintiffs,        *             Waste Policy Act of 1982;
    *             Recovery of Mitigation Damages
    v.                                    *             for DOE’s Partial Breach of
    *             Contract.
    THE UNITED STATES,                     *
    *
    Defendant.         *
    *
    ************************************** *
    Brad Fagg, with whom were Paul M. Bessette, and David M. Kerr, Morgan Lewis &
    Bockius, LLP, Washington, D.C., for Plaintiffs.
    Christopher J. Carney, with whom were Stuart F. Delery, Assistant Attorney General,
    and Byrant G. Snee, Acting Director, United States Department of Justice, Civil Division,
    Commercial Litigation Branch, Washington, D.C., Jane K. Taylor, Lisa J. Donahue,
    Sonia M. Orfield, and Shari A. Rose, Of Counsel, for Defendant.
    OPINION AND ORDER
    WHEELER, Judge.
    Plaintiffs Carolina Power & Light Company (“CP&L”) and Florida Power
    Corporation (“FPC”) claim damages of $104,991,508 from Defendant caused by the
    failure of the Department of Energy (“DOE”) to collect and dispose of spent nuclear fuel
    beginning January 31, 1998 under the terms of the DOE Standard Contract.
    This is a “Round 2” spent nuclear fuel (“SNF”) damages case. See Indiana
    Michigan Power Co. v. United States, 
    422 F.3d 1369
    , 1378 (Fed. Cir. 2005) (utilities
    required to file successive actions for damages related to DOE’s breach within six years
    of incurring such damages). “Round 1” of this case covered Plaintiffs’ claims for
    damages incurred through December 31, 2005. The Round 1 litigation was resolved by
    this Court in 2008 and upon remand in 2011. Carolina Power & Light Co. v. United
    States, 
    82 Fed. Cl. 23
     (2008); Carolina Power & Light Co. v. United States, 
    98 Fed. Cl. 785
     (2011). This proceeding covers damages sustained from January 1, 2006 through
    December 31, 2010, and covers the same four nuclear power plant sites as Round 1: the
    Harris, Brunswick, Robinson, and Crystal River sites.
    CP&L and FPC are wholly-owned subsidiaries of Progress Energy, Inc., a public
    utility in the southeast United States. Progress Energy, Inc. completed a merger with
    Duke Energy Corporation on July 2, 2012. CP&L is now known as Duke Energy
    Progress, Inc.1 Plaintiffs’ damages consist of costs incurred in mitigation of DOE’s
    partial breach of the Standard Contract. This Court has jurisdiction over Plaintiffs’
    claims pursuant to the Tucker Act, 
    28 U.S.C. § 1491
    (a). See PSEG Nuclear, LLC v.
    United States, 
    465 F.3d 1343
     (Fed. Cir. 2006). Defendant’s liability for partial breach of
    contract has already been established. See Maine Yankee Atomic Power Co. v. United
    States, 
    225 F.3d 1336
    , 1337-40 (Fed. Cir. 2000) (“Maine Yankee”). Thus, the questions
    currently before the Court are limited to the calculation and allocation of damages
    incurred from the DOE’s continuing breach.
    Plaintiffs’ damages claims fall into five broad categories: (1) $66,375,235 to
    complete construction of an Independent Spent Fuel Storage Installation2 at Brunswick;
    (2) $7,760,680 to expand and load spent fuel onto the dry storage facility at Robinson; (3)
    $21,143,250 to design, engineer, and develop a dry storage facility at Crystal River; (4)
    $4,291,417 for the procurement and installation of additional racks in the Harris C spent
    fuel pool; and (5) $5,420,926 to conduct transshipments of spent fuel from the Brunswick
    to Harris plant. However, of this approximately $105 million claim, only $23 million is
    contested by the Government.
    The Court conducted a three-day trial in Washington, D.C. during September 23-
    25, 2013. Plaintiffs called the following witnesses: Allen Brittain, manager of nuclear
    security at Brunswick; Steve Edwards, manager of dry fuel storage at Duke Energy;
    David Guseman, manager of nuclear information technology at Brunswick; Denise
    Hards, business planning manager for customer operations at Progress Energy; and
    Richard Tripp, project manager for the dry storage facility project at Brunswick. Counsel
    for the Defendant called Larry Johnson and Gregory A. Maret as expert witnesses.
    For the reasons explained below, the Court finds that Plaintiffs are entitled to
    recover $103,748,230.14 in mitigation damages through December 31, 2010. The Court
    has disallowed three elements of Plaintiffs’ damages claims. For these items: the
    1
    In this opinion the Court will refer to “Progress Energy” or “Plaintiffs” when describing the entities
    formerly known as Carolina Power & Light Company and Florida Power Corporation.
    2
    An Independent Spent Fuel Storage Installation is a facility designed and constructed for dry storage of
    spent nuclear fuel. The Court will use the term “dry storage facility” when referring to such facilities in
    this opinion.
    -2-
    Brunswick computer system replacement; the Brunswick crane studies; and the Crystal
    River 3 mobile BRE, the Court concludes that Plaintiffs would have incurred these
    expenses for other reasons absent DOE’s partial breach.
    Findings of Fact
    On April 30, 2013, the Court ordered the parties to undergo a comprehensive
    pretrial accounting review process to reach agreement, as much as possible, on the costs
    associated with each of Progress Energy’s mitigation efforts. See Pretrial Order on
    Damages (Dkt. No. 12). With Progress Energy’s cooperation, Defendant reviewed
    invoices, purchase orders and contracts, accounting records and work orders, and other
    electronic data. As a result of this process, the Government does not dispute that
    Progress Energy incurred the costs it claims as damages for the period from January 1,
    2006 through December 31, 2010.
    The pretrial accounting review substantially narrowed the issues before the Court.
    Defendant acknowledges that Plaintiffs are entitled to recover approximately $82 million.
    Defendant’s primary objection to the approximately $23 million in dispute is that these
    costs were not caused by the breach. The following facts are relevant to deciding the
    remaining issues of disagreement.
    A. The Standard Contract for the Disposal of Spent Nuclear Fuel
    On January 7, 1983, Congress passed the Nuclear Waste Policy Act of
    1982 (“NWPA”), Pub. L. 97-425, 
    96 Stat. 2201
    , codified at 
    42 U.S.C. §§ 10101
    -
    10270 (1982).3 In adopting the NWPA, Congress recognized that “radioactive waste
    creates potential risks and requires safe and environmentally acceptable methods of
    disposal,” and that “a national problem has been created by the accumulation of
    [spent nuclear fuel].” 
    42 U.S.C. § 10131
    (a)(1)-(2).
    DOE, acting on behalf of the Government, entered into a “Contract for Disposal of
    Spent Nuclear Fuel and/or High Level Radioactive Waste” (the “Standard Contract”)
    with both CP&L and FPC. (Stip. ¶ 9). The contract CP&L executed covered the SNF
    generated at the Brunswick, Harris, and Robinson plants, and the contract FPC executed
    covered the SNF generated at the Crystal River plant. (Stip. ¶ 10).
    Under the Standard Contract, CP&L and FPC have paid quarterly fees to DOE
    since April 7, 1983, based on electricity production from nuclear fuel in exchange for
    DOE’s obligation to dispose of spent nuclear fuel and high level waste beginning no later
    than January 31, 1998. (Stip. ¶ 13). Through December 31, 2010, Progress Energy paid
    3
    A detailed history of the Nuclear Waste Policy Act of 1982 and the Standard Contract for the disposal
    of spent nuclear fuel can be found in the Court’s previous opinion in the Round 1 litigation. Carolina
    Power, 
    98 Fed. Cl. 785
    .
    -3-
    approximately $820 million in fees for the disposal of spent fuel under the contracts.
    (Stip. ¶ 14). To date, DOE has not provided for the transportation of any SNF or high
    level radioactive waste from Progress Energy’s sites to a DOE facility.
    B. Progress Energy’s Causation Model
    At trial, Plaintiffs illustrated the impact of DOE’s failure to perform by reference
    to PX 335, a summary spreadsheet referred to by the parties and the Court as a causation
    model. The concept of the model is to take real-world factual circumstances of spent fuel
    storage at the subject sites, and to overlay assumptions of required DOE performance.
    (Edwards, Tr. 50-51). From that model, Plaintiffs identified those activities that were
    performed in the real world that would not have been performed if DOE had not
    breached. (Edwards, Tr. 51).
    Plaintiffs based their spent fuel management strategy upon maintenance of full
    core reserve. (Stip ¶ 6). “Full core reserve” refers to the practice of providing enough
    open spaces in the spent fuel pools so that the operator of a nuclear reactor can do a full
    discharge of all of the fuel in the reactor over to the spent fuel pool, if necessary.
    (Edwards, Tr. 73-74). By applying the causation model, Plaintiffs demonstrated that if
    DOE had performed, the number of open spaces in the spent fuel pools would always be
    greater than the full core reserve for each of the units. (Edwards Tr. 82-83). Therefore, if
    DOE had performed, Progress Energy could have maintained full core reserve without
    the need to construct any dry storage facilities. Plaintiffs’ claim covers four nuclear
    power plant sites, but the disputed costs in this case relate only to the mitigation actions
    taken at two Progress Energy sites: Crystal River and Brunswick.
    C. Crystal River 3 Nuclear Power Plant
    The Crystal River 3 Nuclear Power Plant is a single unit pressurized water reactor
    (“PWR”) site located near Crystal River, Florida. (Stip. ¶ 15). As a result of DOE’s
    breach, dry storage of spent fuel was required at Crystal River. Progress Energy
    commenced development of a dry storage facility at Crystal River, and undertook certain
    activities in support of that effort during the claim period.
    At trial, Plaintiffs demonstrated that Progress Energy would not have built a dry
    storage facility if DOE had performed because of the difficulties of building dry storage
    at Crystal River. (Edwards, Tr. 104). The difficulties include the fact that Crystal River
    is a small, compact nuclear site, surrounded by four fossil units on all sides. (Edwards,
    Tr. 96-97). Furthermore, a significant amount of state environmental permitting is
    required to build a dry storage facility and the project requires soil remediation. In sum,
    in a world of legally-required DOE performance, the management of Progress Energy
    would not approve of the construction of a dry storage facility at the Crystal River site. If
    -4-
    DOE had performed, Progress Energy could have maintained full core reserve without
    the expenses and construction challenges associated with building a dry storage facility.
    On February 13, 2013, Plaintiffs announced that the Crystal River unit would be
    permanently retired. (Stip. ¶ 17). Even considering the early retirement of the site in
    2013, Progress Energy would not have constructed a dry storage facility at Crystal River
    if DOE had been performing. As Plaintiffs testified, DOE has taken the position that
    under the Standard Contract, DOE will only accept fuel out of the spent fuel pools.
    (Edwards, Tr. 104). If DOE would not accept fuel in canisters in the non-breach world, it
    would make no sense for Progress Energy to construct a dry storage facility in the non-
    breach world. Moreover, if the plant was going to be retired, the dry storage facility and
    the canisters would need to be decommissioned in only a few years. (Edwards, Tr. 105).
    For these reasons, building a dry storage facility in the non-breach world would involve
    significant risk and expense with little value in return.
    To study and design the Crystal River dry storage facility, Progress Energy had to
    take several actions for which it now seeks mitigation damages. First, prior to moving
    the 110-ton dry-storage casks from the reactor building to the dry storage site, Progress
    Energy had to evaluate the path the casks would take, in order to make sure that the
    weight could be accommodated. Second, the Crystal River dry storage facility project
    necessitated the relocation of the eastern perimeter of the site. To support security during
    this process, Progress Energy acquired a mobile bullet-resistant enclosure (“BRE”) in
    which a security officer sits to monitor a portion of a nuclear facility. (Tripp, Tr. 282).
    Third, in connection with the anticipated loading of the fuel into the Crystal River dry
    storage facility, Progress Energy had to collect data about the core components of the fuel
    being stored. This information was required to ensure that Progress Energy used the
    proper canister and spacers.
    D. Brunswick Nuclear Plant
    The Brunswick Nuclear Plant is a two unit boiling water reactor (“BWR”) site
    located near Southport, North Carolina. (Stip. ¶ 46). In or about 2003, Progress Energy
    determined that it would require additional spent fuel storage capacity at Brunswick by
    2010. (Stip. ¶ 54). To accommodate its SNF storage needs at Brunswick, Progress
    Energy elected to construct a dry storage facility. From January 1, 2006 through
    December 31, 2010, Progress Energy incurred costs to construct the Brunswick dry
    storage facility and conduct the initial loading campaign. (Stip. ¶ 58). The following
    costs are contested by the Government.
    First, Progress Energy claims it is entitled to damages for costs to accommodate
    larger storage casks. After the breach, Progress Energy switched from rail 75-ton casks
    to larger 110-ton dry-storage casks in order to store the spent fuel on location. At trial,
    Plaintiffs demonstrated a proven track record of an ability to handle 75-ton casks at the
    -5-
    Brunswick site. Indeed, from January 1, 2006 through December 31, 2010, Progress
    Energy made sixteen transshipments of spent fuel assemblies from Brunswick to Harris
    using 75-ton casks. The switch to the heavier casks necessitated several modifications to
    the site and reactor buildings at Brunswick. These mitigation damages include the
    following challenged costs: (1) removing a beam from the spent fuel cask preparation
    area, (Tripp Tr. 294-95); (2) installing a cask loading platform, (Tripp, Tr. 273); (3)
    conducting heat load analyses (Tripp, Tr. 295); and (4) installing helium/drying racks.
    (Tripp, Tr. 295-96).
    Second, Progress Energy seeks to recover costs for the crane studies it conducted
    at Brunswick. Prior to DOE’s partial breach, Progress Energy used two 125-ton
    Brunswick cranes to load 75-ton casks for shipment to the Harris site. As part of the
    Brunswick dry storage project, Progress Energy concluded that it would be prudent to
    determine if its existing cranes were qualified to lift the heavier 110-ton dry-storage
    casks. The crane review revealed problems with the structural design of the Units 1 and
    2 cranes—conditions that existed since the plant began operations. As a result of the
    Brunswick crane studies, Progress Energy temporarily downgraded the cranes to 40 tons
    and made modifications addressing newly discovered issues, such as seismic and wind
    loads, to restore the cranes to their original capacity. Based on the studies, Progress
    Energy also found it necessary to replace the wire ropes to prepare for lifting the 110-ton
    dry-storage casks. (Tripp, Tr. 287).
    Third, Progress Energy had to expand, by some 177,000 square feet, the security
    protected area around the plant to include the dry storage facility. (Tripp, Tr. 278). The
    existing protected area had 33 zones, and an additional 14 zones were needed to
    accommodate the dry storage facility. (Tripp, Tr. 278). This expansion created
    additional alarm points, but Progress Energy’s security alarm processing computer server
    at the time did not have the capacity for these additional inputs. (Tripp, Tr. 279).
    Progress Energy upgraded the security computer system at Brunswick to accommodate
    the expanded protected area. Prior to initiation of the Brunswick dry storage project, the
    security system computer, server, and workstations at the plant were part of a system
    which had been installed during the 1990s. (Guseman, Tr. 346). The system was still
    operational, but it had been in a limited support mode for a number of years. (Brittain,
    Tr. 433).
    Building the dry storage facility required the use of materials classified as
    “safeguards” information, which must be maintained and used strictly in accordance with
    Nuclear Regulatory Commission (“NRC”) regulations for the control and protection of
    such information. Since the dry storage site at Brunswick was outside of the protected
    area at the time of construction, a safeguards information area was constructed outside of
    the protected area for the purpose of housing dry storage materials. (Tripp, Tr. 281).
    -6-
    Discussion
    A. Standard of Review
    In awarding damages for a partial breach of contract, the Court must endeavor to
    place the injured party in as good of a position as it would have been if the breaching
    party had performed. Sys. Fuels, Inc. v. United States, 
    666 F.3d 1306
    , 1314 (Fed. Cir.
    2012). In SNF cases, the plaintiff is entitled to recover its reasonable costs incurred in its
    efforts to mitigate damages. Plaintiffs must show that: (1) the damages were reasonably
    foreseeable by the breaching party at the time of contracting; (2) the breach was a
    substantial causal factor in the incurrence of damages; and (3) the damages are
    established with reasonable certainty. Indiana Michigan, 
    422 F.3d at
    1373 (citing Energy
    Capital Corp. v. United States, 
    302 F.3d 1314
    , 1320 (Fed. Cir. 2002)).
    1. Foreseeability
    A plaintiff may only recover for mitigation costs that were reasonably foreseeable
    by the breaching party at the time of contracting. Yankee Atomic Elec. Co. v. United
    States, 
    536 F.3d 1268
    , 1273 (Fed. Cir. 2008). Here, DOE was aware that if it failed to
    pick up Plaintiffs’ spent fuel, Plaintiffs would have to incur substantial costs storing the
    spent fuel on their own. See Indiana Michigan, 
    422 F.3d at 1375
     (“Having been placed
    in a position where they are required to find alternate storage for SNF, the utilities must
    de facto accept responsibility to guard against the environmental impact of improperly-
    disposed and maintained SNF, a situation which the NWPA was enacted to avoid.”). The
    Court finds that, at the time of contracting, DOE could have reasonably foreseen
    Plaintiffs’ efforts to store spent fuel after Plaintiffs became aware that DOE did not
    intend to perform.
    2. Causation
    A plaintiff bears the burden of proving that DOE’s partial breach was a substantial
    causal factor of each claimed mitigation cost. See Indiana Michigan, 
    422 F.3d at 1373
    .
    Although Indiana Michigan stated that the utilities must satisfy the substantial causal
    factor test, previous decisions of this Court have applied the more difficult “but-for”
    causation test. See, e.g., Northern States Power Co. v. United States, 
    78 Fed. Cl. 449
    ,
    462 (2007) (holding that utility presented sufficient evidence showing that it would have
    pursued cheaper interim storage options in the but-for world). Ultimately, the selection
    of a causation standard is at the trial court’s discretion and depends upon the facts of the
    case. Citizens Fed. Bank v. United States, 
    474 F.3d 1314
    , 1318 (Fed. Cir. 2007). For
    each of the disputed damages items here, the Court will apply the but-for test or the
    substantial causal factor test as appropriate.
    -7-
    To prove causation, a plaintiff must present evidence about its condition, assuming
    full Government performance, to allow the Court to compare the breach and non-breach
    worlds. Yankee Atomic, 
    536 F.3d at 1273
    . A non-breaching party should not be placed
    in a “better position” through an award of damages than if there had been no breach—if a
    cost “would have been incurred even in the non-breach world, it is not recoverable.”
    Energy Northwest v. United States, 
    641 F.3d 1300
    , 1307 (Fed. Cir. 2011). The burden
    on a plaintiff is one of “persuasion.” Southern Nuclear Operating Company v. United
    States, 
    637 F.3d 1297
    , 1304 (Fed. Cir. 2011). In this case, Plaintiffs and Defendant have
    agreed on the vast majority of costs. The remaining disputed costs are challenged on
    grounds that Plaintiffs have failed to prove causation.
    3. Reasonable Certainty
    A plaintiff may only recover those damages that can be shown with reasonable
    certainty. Vermont Yankee Nuclear Power Corp. v. Entergy Nuclear Vermont Yankee,
    LLC, 
    683 F.3d 1330
    , 1349 (Fed. Cir. 2012). With these principles in mind, the Court
    ordered the parties to undergo a comprehensive pretrial accounting review process to
    reach agreement as much as possible on the costs associated with each of Progress
    Energy’s mitigation efforts. As a result of this process, the Government does not contest
    the accuracy of the dollar amounts, and does not dispute that the expenditures were
    reasonable at the time the sums were expended by Plaintiffs.
    B. Disputed Costs
    The parties agree that Plaintiffs are entitled to recover $81,950,260 in mitigation
    damages. The remaining $23,041,248 of Plaintiffs’ claim consists of six categories that
    the Government asserts are not recoverable: (1) damages related to the construction of a
    dry storage facility at Crystal River; (2) costs to accommodate larger casks; (3) the
    Brunswick crane studies; (4) the Brunswick computer system replacement; (5) the
    Crystal River Assembly data; and (6) the Crystal River mobile BRE. The Government
    argues that for these challenged items Plaintiffs failed to carry the burden to show that
    those same costs would not have been incurred if DOE had performed. The Court
    addresses each of the disputed items below.
    C. Deduction of Indirect Costs
    In SNF cases, the proper calculation of damages considers both direct and indirect
    costs. Energy Northwest, 
    641 F.3d at 1306
    . Progress Energy has asserted damages
    related to certain types of costs that cannot be directly identified with specific sub-
    projects. These costs include internal labor, indirect overhead, and staff augmentation
    support. If Progress Energy is entitled to include allocations of indirect costs in its
    damages claim, then the disallowance of particular direct costs also necessitates the
    disallowance of the indirect costs associated with that direct cost. Here, the
    Government’s cost-accounting expert, Larry Johnson, has devised a formula to capture
    -8-
    the estimated indirect costs associated with each direct claim. (DX 451 at 13-14). Using
    this formula, the Court has deducted the associated indirect costs of the disallowed claims
    from Progress Energy’s overall claim.
    Additionally, $162,927 of the allocated costs identified by the Government’s
    expert are attributable to direct costs that have been removed from the claim by Progress
    Energy but for which Progress Energy failed to remove the associated indirect overhead
    costs. (DDX 2 at 29). Therefore, the Court has reduced Progress Energy’s claim further
    by $162,927 to account for the indirect overhead associated with the direct costs that
    Progress itself has removed from the claim.
    1. Crystal River 3 Causation
    Progress Energy seeks to recover $21,143,438 in damages related to the
    construction of a dry storage facility at Crystal River. Plaintiffs illustrated the impact of
    DOE’s failure to perform by reference to summary spreadsheet PX 335. In Round 1 of
    the litigation, the Court found that this model created a plausible non-breach world on
    which to base its damages. Carolina Power, 98 Fed. Cl. at 795. Here, in the Round 2
    litigation, the Government disputes that Progress Energy has proven entitlement to the
    costs associated with constructing dry storage at Crystal River. The underlying model
    was the same as the one used in Round 1 of the litigation, but the causation model for
    Crystal River needed to be updated to reflect the fact that Progress Energy decided to
    permanently close the Crystal River plant in February 2013. (Edwards, Tr. 185-86).
    Furthermore, the Government argues that some spent fuel might have been on the Crystal
    River site long enough in a world of DOE performance that the presence of that fuel
    might have persuaded Plaintiffs to construct dry storage anyway.
    a. The Revised Model
    At the time the original causation model was created for these proceedings the
    model went forward to the end of Crystal River’s expected operation in 2036. (Edwards,
    Tr. 94). On February 13, 2013, Plaintiffs announced that the Crystal River unit would be
    permanently retired. (Stip. ¶ 17). Therefore, at the time of trial, Plaintiffs decided to
    amend the causation model. Plaintiffs knew that it was no longer accurate to show
    discharges every two years going forward to 2036, and so Progress Energy changed the
    model so that it stopped in 2013.
    The Government disputes causation for all Crystal River costs, and argues that
    Progress Energy failed to present a complete causation model establishing what its costs
    would have been in the absence of the breach. This argument elevates form over
    substance. At trial, a plaintiff bears the burden of establishing that the alleged mitigation
    costs were caused by the breach. Energy Northwest, 
    641 F.3d at 1307
    . A plaintiff can
    prove the amount of costs by whatever means available, so long as “the cumulative result
    -9-
    is a reasonable certainty that the awarded costs were actually caused by the breach.” 
    Id. at 1309
    . Here, the Court finds that Progress Energy has met this burden. All dry storage
    facility-related spent fuel storage activities during the claim period were undertaken
    because the company expected that the unit would soon run out of space and lose full
    core reserve in its pools. (Edwards, Tr. 93). Plaintiffs showed at trial that in a world of
    legally-required DOE performance, no dry storage would be required to maintain full
    core reserve at Crystal River. Furthermore, Plaintiffs showed that the management of
    Progress Energy would never approve of the construction of a dry storage facility, if
    DOE had been performing, because of the associated risks and costs. The Court finds
    that Progress Energy has met its burden of showing that it would not have incurred these
    costs in the absence of the breach.
    b. The Effect of the Crystal River Retirement
    The Government also argues that the retirement of the Crystal River unit in 2013
    makes certain costs incurred during the claim period unrecoverable because Plaintiffs
    have failed to meet their burden of showing that dry storage would not have been pursued
    at Crystal River in light of that subsequent retirement. (Tr. 32, Statement of Counsel). In
    its pretrial brief, the Government pointed out that in the non-breach world, if DOE were
    performing and the Crystal River plant was shut down, Progress Energy would have
    made an assessment about how long it would need to keep its spent fuel pool operating
    before all the SNF would be gone.
    The Government’s position is an argument for the next round of this litigation not
    for the claims currently before the Court. The announcement of Crystal River’s closure
    came two years after the claims period ended. The relevant time for assessing the
    recoverability of costs for mitigation activities is at the time those mitigation steps are
    taken. At trial, Progress Energy explained that at all times during the claims period,
    Plaintiffs believed Crystal River to be an operating plant, with an operating license that
    would be extended through 2036. (Edwards, Tr. 93). At issue here is causation for
    mitigation damages incurred during this claims period, and the retirement of Crystal
    River in 2013 cannot have caused Progress Energy to incur costs prior to 2010. Put
    another way, recoverable costs cannot be rendered unrecoverable by future events outside
    of the claim period.
    c. Effect on Future Proceedings
    At trial, Progress Energy showed that by using just Crystal River’s own
    allocations to remove SNF, Crystal River could have all its SNF removed by 2025.
    (Edwards, Tr. 113-15). This evidence supports Progress Energy’s contention that it
    would have made no business sense to construct dry storage at Crystal River that would
    - 10 -
    only be used for nine years. Indeed, the 2025 fuel “out date”4 was the worst case
    scenario that Plaintiffs arrived at by making conservative assumptions about pick-up rate
    allotments. (Edwards, Tr. 133). Plaintiffs further explained that this worst case
    assumption would not reflect DOE performance because Duke Energy operates as a
    single fleet and would have utilized inter-utility exchanges to remove the SNF on an
    expedited basis.
    The Government argues that if Progress Energy is awarded the costs for dry
    storage at Crystal River based upon the testimony it adduced regarding a 2025 final SNF
    removal date, the company should be held to this date in future proceedings. Such a
    finding would likely be at odds with the evidence introduced at trial and with common
    sense assumptions about how DOE would respond to a plant’s closing. 5 However, the
    Court will refrain from ruling on the merits of the Government’s argument. A ruling on
    this issue would have no effect on damages in this proceeding. Rather, the Government
    seeks a finding from the Court that would have a preclusive effect in future proceedings.
    This would constitute an advisory opinion, and the Court is prohibited from issuing
    advisory opinions. Fina Oil and Chemical Company v. United States, 
    123 F.3d 1466
    ,
    1470 (Fed. Cir.1997). Accordingly, the Court rejects the Government’s request to hold
    Progress Energy to this date in future proceedings.
    2. Costs to Accommodate Larger Casks
    Plaintiffs seek $828,129 in damages to cover the costs associated with the
    modifications and activities necessary to support the larger and heavier dry storage
    canisters necessitated by DOE’s breach. Specifically, the costs include: (1) $517,603 for
    4
    The “out date” is the date by which the last fuel assembly would be removed by the plant. See, e.g.,
    Portland Gen. Elec. Co. v. United States, 
    107 Fed. Cl. 633
    , 644 (2012). The date is used to determine
    whether a utility would choose to leave its fuel in wet storage and incur ongoing costs for operating a
    spent fuel pool or close the wet pool or move the SNF in to dry storage.
    5
    After closing arguments, both parties submitted supplemental briefing on the issue of whether any case
    law has addressed DOE’s potential departure from previously announced pick-up rate allotments to deal
    with the circumstances of a nuclear plant shutdown. This issue will not be ripe until the next round of
    litigation. However, the case law supports Plaintiffs’ argument that it would not be appropriate for the
    Court to make a preclusive finding about a fuel “out date.” The case law suggests that in a reasonable
    non-breach world, DOE might depart from previously announced rates and remove the spent fuel in an
    expedited manner. See Yankee Atomic Elec. Co. v. United States, 
    679 F.3d 1354
    , 1360 (Fed. Cir. 2012)
    (affirming trial court’s finding that DOE would not have adopted an oldest fuel first procedure in the non-
    breach world); Portland Gen. Elec., 107 Fed. Cl. at 645 (finding that parties would depart from previously
    announced pick-up allotments by exchanging allocations to maximize savings and efficiency).
    - 11 -
    the Brunswick plant modifications; (2) $90,600 for the Brunswick wire rope; and (3)
    $280,946 for the Crystal River haul path evaluation.
    The Standard Contract requires DOE to provide casks for transportation that are
    suitable for use at the sites and that meet regulatory requirements. There are essentially
    three major categories of casks: heavy rail, light rail, and truck. DOE has not indicated
    what sort of cask it would have used had it performed as required. (Edwards, Tr. 141).
    Plaintiffs take the position that, if DOE had performed, DOE would have supplied a 75-
    ton light rail cask at Brunswick. (Edwards, Tr. 139).
    According to Plaintiffs, there was a proven track record at the Brunswick site of an
    ability to handle 75-ton casks. In support of their claims, Plaintiffs point to the real world
    use of 75-ton casks to ship spent nuclear fuel from the Brunswick plant. These
    transshipments were made for years prior to DOE’s partial breach without the need for
    the dry storage facility-related modifications. After the breach, Progress Energy was
    forced to switch to larger 110-ton dry-storage casks. The Government contends that
    Plaintiffs would have chosen to switch to large rail casks at the Brunswick and Crystal
    River plants regardless of the breach. According to the Government, Plaintiffs have
    failed to prove that Progress Energy would have foregone spending the modest sums
    necessary to undertake the conversion to large rail casks, which could have saved
    potentially tens of millions of dollars in loading costs.
    The Court finds that if DOE had not partially breached the Standard Contract,
    there would have been no need to switch from 75-ton casks to the larger 110-ton casks.
    At trial, Progress Energy found support for this argument from none other than the
    Government’s expert witness, Mr. Maret. In Round 1 of this litigation, when calculating
    the loading cost deduction, Mr. Maret assumed that Progress Energy would be using 75-
    ton casks when transferring spent fuel to Yucca Mountain. (PX 245 at 14). Mr. Maret
    made this assumption because the comparatively small cask would have maximized the
    “loading cost” damage reduction in that case. Yet, in Round 2 of this litigation, Mr.
    Maret argued that in a non-breach world, Plaintiffs would have made the modifications to
    handle 110-ton casks.
    The Court finds no valid justification for this reversal of position. The
    Government explains that the management of Progress Energy would likely consider the
    tradeoffs between making the modifications and the potential risk of not doing so. For
    example, Mr. Maret explained that larger casks might reduce the risks of radiation
    exposure. However, such considerations would have been just as true in Round 1 when
    the same expert took the opposite position and declared that the use of 75-ton casks was
    reasonable. The Court finds that the claimed costs are recoverable.
    - 12 -
    3. Brunswick Crane Studies
    Progress Energy seeks $429,330 in costs for the crane studies it conducted at
    Brunswick along with $43,582.86 in indirect costs.6 Prior to DOE’s partial breach,
    Progress Energy used two 125-ton Brunswick cranes to load 75-ton casks for shipment to
    the Harris site. The switch to heavier 110-ton dry-storage casks prompted Progress
    Energy to conduct a review of its cranes. Problems with the structural design were
    discovered, and Plaintiffs made modifications to the cranes. Plaintiffs have voluntarily
    removed the costs for these modifications from Progress Energy’s current claim.
    However, Plaintiffs argue that the crane studies themselves would not have been
    necessary if the Government had not breached the contract.
    Here, Plaintiffs have not met their burden of persuasion.            The needed
    modifications that Progress Energy made after the study suggest that the study had value
    beyond the need for dry storage at Brunswick, and would have been performed
    independent of the breach. At the very least, the Court finds that the benefit Progress
    Energy received should reduce Plaintiffs’ damages. Kansas Gas & Electric Co. v. United
    States, 
    685 F.3d 1361
    , 1367 (Fed. Cir. 2012) (reducing plaintiff’s damages to account for
    efficiency benefits from a re-rack project). As a result, the Court finds that the
    $472,913.86 for the crane study is unrecoverable.
    4. Brunswick Computer System Replacement and BNP Safeguards Area
    Progress Energy seeks $437,837 in direct costs and $107,452 in indirect costs to
    recover the expenses associated with the replacement of the security computer system at
    Brunswick. According to Progress Energy, it had to upgrade the security computer
    system at Brunswick to accommodate the expanded protected area around the Brunswick
    plant to include the dry storage facility. The expanded protected area created additional
    alarm points, but Progress Energy’s security alarm processing computer at the time did
    not have the capacity for these additional inputs. Accordingly, Plaintiffs argue that
    DOE’s breach was a substantial causal factor of the cost incurred to upgrade the
    computer system.
    The Government argues that the security system would have been upgraded
    regardless of DOE’s breach. The Government finds strong support in a document
    produced by Progress Energy, an engineering change package (EC), which suggests that
    standardization across the sites was the primary reason for the computer replacement.
    The EC reads:
    6
    Progress Energy’s original claim was for $564,104. However, there were two line-item charges, for
    $90,600 and $44,165, which were not crane study costs and were removed from this particular claim.
    - 13 -
    This SCS [security computer system] replacement will standardize the
    [Brunswick] SCS to the Progress Energy fleet SCS software solution. The
    other three nuclear sites in the Progress Energy Nuclear Plant Fleet use the
    same SCS the GSE Access Alarm Reporting Detection System (GAARDS).
    The software code for this SCS is owned by Progress Energy. This fleet
    standard SCS will be installed at [Brunswick] to replace the current
    [Brunswick] SCS. This fleet approach to the SCS installations will allow
    for greater system support and lower costs for maintaining the security
    computer systems.
    (PX398 at CP_FP00360371).
    This document shows the standardization benefits provided by the replacement,
    and suggests that this cost would have been incurred even in the non-breach world.
    These upgrades might not have occurred at the exact same time in the non-breach world
    as they did in the actual world, but they would have occurred at a reasonably similar time
    given the age of the equipment. Accordingly, Plaintiffs’ $545,289 claim for the computer
    system replacement is denied.
    Plaintiffs also seek to recover $13,932 for the costs associated with constructing
    the safeguards information area. The Court has already found that DOE’s partial breach
    caused Progress Energy to construct the dry storage facility at Brunswick, and the building
    of this facility necessitated the construction of the safeguards information area. Thus, the
    Court finds that Plaintiffs would not have constructed the safeguards information area if
    DOE had performed under the Standard Contract. For this reason, Plaintiffs can recover
    $13,932.
    5. Crystal River 3 Assembly Data
    Progress Energy seeks $66,321 to recover the cost of obtaining discharged fuel
    dimensional data regarding SNF stored at Crystal River. The Government’s expert, Mr.
    Maret, suggested that this same sort of data would be required if DOE had performed and
    was required to load a DOE-supplied cask. (Maret, Tr. 486, 524). However, the
    information Plaintiffs had to acquire is not the kind of information that would necessarily
    be needed to load the fuel into any cask. Rather, the spent fuel data that Plaintiffs had to
    acquire was far more detailed and was dictated by the unique technical specifications of
    the particular Transnuclear cask that was selected for the dry storage caused by DOE’s
    breach. (Edwards, Tr. 144-47). The data that had to be acquired was even more detailed
    than the generic spent fuel assembly information called out in the DOE Standard
    Contract. Accordingly, the Court finds that these costs would not have been incurred in
    the non-breach world and are therefore recoverable.
    - 14 -
    6. Crystal River 3 Mobile BRE
    Plaintiffs seek to recover $60,150 of direct costs and $1,999 of allocated indirect
    costs to cover the cost of a mobile BRE. According to Progress Energy, the mobile BRE
    was acquired to support security during the perimeter relocation that was part of the
    Crystal River dry storage project. The Government contends that the BRE was used for
    reasons unrelated to dry storage.
    At trial, Mr. Tripp, a project manager at the Brunswick plant, testified that the
    mobile BRE was shipped from Crystal River to Brunswick when it was needed to
    complete a chiller project that he managed. This project had no relation to spent fuel.
    (Tripp, Tr. 282, 333). Upon completion of that project, the mobile BRE was returned to
    Crystal River. However, Plaintiffs did not offer any evidence showing what the BRE is
    being used for now that it is back at Crystal River. The Court can only assume that it is
    not being used to support the dry storage of spent nuclear fuel since that project has been
    suspended.
    A plaintiff must prove the extent to which its incurred costs differ from the costs it
    would have incurred in the non-breach world. Energy Northwest, 
    641 F.3d at 1306
    .
    Here, the Court finds that Plaintiffs have failed to prove that the cost of the BRE is
    different from the cost it would have incurred in the non-breach world. The fact that the
    BRE was needed at Brunswick suggests that Progress Energy would have had to
    purchase a BRE anyway. The $62,149 claim for the mobile BRE is not recoverable.
    Conclusion
    Based upon the foregoing, the Court awards damages to Plaintiffs of
    $103,748,230.14. The Court directs the Clerk to enter judgment in favor of Plaintiffs in
    that amount. Pursuant to Rule 54(d) of the Court, reasonable costs are awarded to
    Plaintiffs.
    IT IS SO ORDERED.
    s/ Thomas C. Wheeler
    THOMAS C. WHEELER
    Judge
    - 15 -