  •          In the United States Court of Federal Claims
    No. 13-365C
    (Filed: July 28, 2014)
    )
    UNITED STATES ENRICHMENT                   )
    CORPORATION,                               )      Motion to Dismiss for Lack of
    )      Subject Matter Jurisdiction;
    Plaintiff,            )      Contract Disputes Act, 41 U.S.C. §
    )      7103; No Standing Claims Arising
    v.                                         )      from Subcontracts
    )
    THE UNITED STATES,                         )
    )
    Defendant.            )
    )
    Thomas A. Lemmer, Denver, CO, for plaintiff.
    James P. Connor, Civil Division, United States Department of Justice, Washington, DC,
    with whom were Stuart F. Delery, Principal Deputy Assistant Attorney General, and Bryant E.
    Snee, Acting Director, for defendant.
    ORDER GRANTING GOVERNMENT’S MOTION TO DISMISS ALL
    SUBCONTRACTOR-RELATED CLAIMS FOR LACK OF JURISDICTION
    FIRESTONE, Judge.
    In this breach of contract case, United States Enrichment Corporation (“plaintiff”
    or “USEC”) alleges that the United States (“the government”) breached numerous
    agreements with plaintiff when the government failed to reimburse certain indirect costs
    that USEC incurred as both a prime contractor and subcontractor while performing work
    at the United States Department of Energy’s (“DOE” or “the agency”) gaseous-diffusion
    plants (“GDPs”) in Portsmouth, Ohio and Paducah, Kentucky. Plaintiff’s claims stem
    from DOE’s purported failure to establish provisional and/or final indirect cost rates in a
    timely manner in connection with those prime and subcontracts, which allegedly resulted
    in USEC being under-compensated throughout performance. USEC claims that DOE’s
    breaches have resulted in damages to USEC totaling $37,970,480 plus interest under the
    Contracts Disputes Act, (“CDA”), 
    41 U.S.C. § 7101
    , et seq., of which $3,823,289 relates
    to damages on USEC’s subcontracts, which are at issue in this opinion.
    The government has moved to dismiss plaintiff’s complaint to the extent that it
    seeks damages related to USEC’s alleged under-reimbursement on contracts between
    plaintiff and other DOE prime contractors. 1 Specifically, the government contends that
    the court lacks jurisdiction to entertain a suit brought directly by USEC in its capacity as
    a subcontractor. For the reasons explained below, the court GRANTS the government’s
    motion.
    I.     BACKGROUND 2
    a. Agreements Between USEC and DOE
    The alleged contract breaches underlying USEC’s complaint arise from several
    agreements between USEC and DOE related to the lease, operation, and maintenance of
    DOE’s GDPs in Portsmouth, Ohio and Paducah, Kentucky. For the purpose of deciding
    1
    The government’s motion originally also sought to dismiss Counts I and III of the complaint,
    which related to USEC’s provisional billing rates for fiscal year (“FY”) 2003 and FY 2004. On
    July 25, 2014, the parties filed a joint status report in which they represented that they had
    reached an agreement to resolve Count I (FY 2003 provisional billing rates), Count III (FY 2004
    provisional billing rates), and Count V (FY 2005 provisional billing rates) without further
    involvement of the court. Accordingly, this opinion is limited to the issue of USEC’s entitlement
    to recover damages related to its subcontracts with other DOE prime contractors.
    2
    The court limits its discussion to those matters necessary to resolve the scope of the
    government’s motion. The facts discussed herein are derived from the complaint together with
    matters incorporated by reference or integral to the claim.
    2
    the government’s motion, these agreements include: (1) a 1993 Memorandum of
    Agreement (“1993 MOA”) providing for services to be exchanged between USEC and
    DOE; 3 (2) a 2003 Agreement for Services (“2003 Services Agreement”), which described
    the process by which USEC and DOE would perform services under the 1993 MOA; (3)
    a 2006 Agreement for Services (“2006 Services Agreement”), which replaced the
    expiring 2003 Services Agreement; (4) a 2006 Memorandum of Agreement (“2006 MOA
    Modification”), which modified the 1993 MOA to account for changes to the underlying
    1993 lease; and (5) direct contracts between DOE and USEC for various services,
    including the “Cold Standby/Cold Shut Down Contract.” These agreements are
    discussed briefly below to provide the necessary context to rule on the government’s
    motion.
    USEC and DOE entered into the GDP Lease, effective July 1, 1993, for uranium
    enrichment facilities at the Portsmouth and Paducah GDPs. Compl. ¶ 13. Although the
    attached 1993 MOA contemplated that USEC and DOE would provide services to each
    other in connection with the lease, the 1993 MOA did not establish the details for how
    those services would be provided. See Compl. ¶¶ 14-15. Those details were fleshed out
    in the 2003 and 2006 Service Agreements entered into between USEC and DOE.
    The 2003 and 2006 Services Agreements set forth the process by which USEC
    would perform services for DOE. Specifically, the agreements stated that USEC’s work
    at the Portsmouth and Paducah plants would be performed pursuant to written “Work
    3
    The 1993 MOA, which has not been provided to the court, was attached to the Lease
    Agreement between DOE and USEC for the GDPs at issue in this case.
    3
    Authorizations” issued by DOE, which would be payable within a set period of time after
    invoicing. Compl. ¶¶ 23-25; Def.’s Mot. Dismiss App. at A3.
    In late 2006, USEC and DOE modified the 1993 MOA to account for a change to
    the 1993 lease. 4 The 2006 MOA Modification described certain “Captive” services that
    USEC and DOE would provide at the Portsmouth and Paducah plants, and also indicated
    that USEC could provide related Captive services to other DOE prime contractors.
    Article II of the 2006 MOA Modification provided:
    1. The general purposes of this Services Agreement Modification No. 1 are
    to enable DOE to provide to USEC certain services at the GDPs and to
    enable USEC to provide to DOE certain services at the GDPs. Nothing in
    this Services Agreement Modification No. 1 shall be interpreted to require
    either DOE or USEC . . . to furnish any service or services to the other
    Party in the event service(s) of that type is not necessary for a Party’s own
    programmatic needs or to require either Party to purchase any service(s),
    captive or otherwise, from the other Party.
    2. For the purposes of obtaining Captive Services as designated on
    Appendix B of this Services Agreement Modification No. 1, the definition
    of the Parties shall include any prime contractor or subcontractor
    performing work on behalf of either DOE or USEC. An agreement for
    Captive Services approved in advance by the DOE Lease Administrator
    between a DOE prime contractor or subcontractor and USEC for work
    approved after execution of this Services Agreement Modification No. 1
    shall be treated as an agreement under the provisions of this Services
    Agreement Modification No. 1, including, but not limited to, the provisions
    related to ARTICLE IV A.1, and shall be on a cost reimbursable basis.
    Def.’s Mot. Dismiss App. at A19. The 2006 MOA Modification also stated that,
    4
    The 2006 MOA Modification left in place the 2006 Services Agreement. See Def.’s Mot.
    Dismiss App. at A19 (“Work Authorizations or other implementing agreements previously
    issued pursuant to the Services Agreement, dated as of July 1, 1993, shall continue to be in effect
    under the terms of each respective Work Authorization or other implementing agreement, unless
    and until superseded by a subsequent agreement, contract, or Work Authorization.”).
    4
    consistent with Article II, USEC would perform for DOE (or its contractors or
    subcontractors) on a cost-reimbursement basis, without fees or profit. 
    Id.
     at A20, A24-
    25.
    Between 2005 and 2011, USEC and DOE allegedly entered into more than thirty
    cost-reimbursement Work Authorizations for USEC’s work at the Portsmouth and
    Paducah plants under the 2003 and 2006 Services Agreements. Plaintiff also alleges that
    throughout the relevant period, USEC provided services to DOE through sixteen
    subcontracts with other DOE prime contractors using USEC’s DOE-approved rates.
    Because these rates were lower than USEC’s anticipated final rates, USEC claims that it
    was under-reimbursed in connection with these subcontracts in the amount of $3,823,289.
    See Pl.’s Opp’n 10.
    USEC and DOE also entered into several direct contracts, the largest of which
    was the Cold Standby/Cold Shutdown Contract, which was definitized in 2003. The
    Cold Standby/Cold Shutdown Contract involved the operation, maintenance, and support
    of the Portsmouth gaseous-diffusion plant in a “cold standby” status, and included
    provisions to address billing of indirect costs prior to the establishment of final indirect
    cost rates. Def.’s Mot. Dismiss App. at A39-40, A45.
    b. Regulatory Background Concerning Billing and Payment Under the DOE-
    USEC Agreements
    Plaintiff alleges that most of its agreements with DOE incorporated FAR 52.216–7
    or similar language, which governed how USEC would be reimbursed by DOE. Compl.
    ¶¶ 52-54. In general, DOE was to provide interim reimbursements to USEC for indirect
    5
    costs, payable within 30 days of USEC’s submission of an invoice. 
    Id. ¶ 55
    . These
    reimbursements were to be based upon billing rates approved by DOE or, in some
    instances, DOE’s auditors. 
    Id.
    Under FAR 52.216–7, DOE was required to make interim payments to USEC as
    work progressed for those costs that the Contracting Officer deemed allowable under the
    FAR and terms of the contract. FAR 52.216–7(a)(1). Until DOE and USEC established
    final annual indirect cost rates for a given period, however, reimbursement was to be
    made “at billing rates established by the Contracting Officer or by an authorized
    representative . . . subject to adjustment when the final rates are established.” FAR
    52.216–7(e). These billing rates were to be the “anticipated final rates,” and could be
    “prospectively or retroactively revised by mutual agreement, at either party’s request, to
    prevent substantial overpayment or underpayment.” FAR 52.216–7(e)(1)-(2).
    FAR 52.216–7(d) establishes a procedure for determining final indirect cost rates.
    Within six months of the expiration of a given fiscal year, USEC was required to submit
    its proposed final indirect rates to the Contracting Officer and the government’s audit
    agency, the Defense Contract Audit Agency (“DCAA”). 5 FAR 52.216–7(d)(2)(i);
    Compl. ¶ 106. Any extension of this six-month period was required to be in writing and
    was only to be granted in “exceptional circumstances.” FAR 52.216–7(d)(2)(i). USEC
    and the government were required to “establish the final indirect cost rates as promptly as
    practical after receipt of [USEC’s] proposal.” FAR 52.216–7(d)(2)(ii).
    5
    USEC has termed its cost rate proposal submissions “incurred cost submissions” (“ICS”).
    6
    Within sixty days after settlement of final indirect cost rates, USEC was required
    to “update its billings on all contracts to reflect the final settled rates and update the
    schedule of cumulative direct and indirect costs claimed and billed . . . .” FAR 52.216–
    7(d)(2)(v). This was to be followed by a written settlement between USEC and DOE that
    set forth:
    (i) the agreed-upon final annual indirect cost rates, (ii) the bases to which
    the rates apply, (iii) the periods for which the rates apply, (iv) any specific
    indirect cost items treated as direct costs in the settlement, and (v) the
    affected contract and/or subcontract, identifying any with advance
    agreements or special terms and the applicable rates.
    FAR 52.216–7(d)(3). One hundred and twenty days after settlement, USEC was required
    to submit a completion invoice (or voucher) that reflected the settled amounts and rates,
    including settled subcontract amounts and rates. 6 FAR 52.216–7(d)(5). At any time or
    times before final payment, however, DOE had the right to audit USEC’s invoices or
    vouchers and statements of cost. FAR 52.216–7(g).
    c. USEC’s Provisional Billing Rates for Fiscal Year 2003
    Throughout FY 2003, USEC billed—and DOE reimbursed—USEC’s indirect
    costs based upon the indirect cost billing rates that DOE had most recently approved. For
    USEC work performed at the GDPs in FY 2003, USEC initially billed DOE based on its
    FY 2002 approved billing rates, which the DCAA had approved on December 28, 2001.
    Beginning with USEC’s invoice for March 2003, USEC began using revised billing rates
    6
    The Allowable Cost and Payment Clause specifies that “[t]he prime contractor is responsible
    for settling subcontractor amounts and rates included in the completion invoice or voucher and
    providing status of subcontractor audits to the contracting officer upon request.” FAR 52.216–
    7(d)(5).
    7
    approved by DCAA on March 21, 2003. On August 27, 2003, USEC notified DOE that
    its approved revised billing rates were too low and had resulted in significant unbilled
    costs for work performed in FY 2003. Compl. ¶ 108. On January 19, 2004, USEC
    proposed second revised billing rates for FY 2003. Compl. ¶ 109. On May 25, 2004,
    DCAA approved the second revised billing rates for FY 2003 based on USEC’s January
    19, 2004 request. Compl. ¶ 110. In June 2004, USEC determined that these approved
    revised rates were still too low and requested third revised billing rates on June 10, 2004.
    Comp. ¶ 111; Pl.’s Opp’n 6. Plaintiff alleges that DOE did not respond to this request
    until August 25, 2011, when DOE rejected USEC’s invoice. See Pl.’s Opp’n 6, 12.
    d. USEC’s Provisional Billing Rates for Fiscal Year 2004
    For USEC work at the GDPs in FY 2004, USEC initially billed DOE based on its
    FY 2003 billing rates approved by DCAA on March 21, 2003. USEC subsequently
    submitted proposed revised billing rates on January 19, 2004, February 18, 2004, and
    March 26, 2004, none of which received DOE approval. On April 30, 2004, USEC
    submitted another revised request for FY 2004 billing rates, making several formatting
    changes to facilitate a DOE audit and correcting minor mistakes in the March 26, 2004
    proposed rates letter. On June 1, 2004, DOE approved USEC’s April 30, 2004 FY 2004
    billing rates. USEC applied these FY 2004 billing rates beginning on May 1, 2004. By
    letter dated March 24, 2005, USEC notified DOE that its April 30, 2004 approved billing
    rates for FY 2004 were significantly lower than USEC’s actual incurred costs in FY 2004
    and requested that DOE approve revised billing rates so that USEC could prepare
    adjustment invoices to recover the unbilled costs. Compl. ¶¶ 145-46. Plaintiff alleges
    8
    that DOE did not respond to this request. See Compl. ¶ 147; Pl.’s Opp’n 12 (claiming
    that prior to August 25, 2011, DOE never expressly rejected USEC’s requests for revised
    billing rates).
    e. USEC’s Certified Claims and DOE’s Denial of those Claims
    On December 2, 2011, USEC submitted its first certified claim to DOE’s
    Contracting Officer for allegedly unreimbursed indirect costs for the years 2003 through
    2009 in the amount of $11,217,504. Compl. ¶¶ 84-85. On June 1, 2012, DOE’s
    Contracting Officer issued her final decision and denied USEC’s claim in its entirety.
    Compl. ¶ 89; Def.’s Mot. Dismiss App. at A256-75. 7 USEC submitted a second claim on
    February 16, 2012, demanding payment for breach of contract damages equaling
    $8,992,660, plus interest, in unreimbursed indirect costs allocable to eleven DOE
    contracts, plus damages caused under its subcontract agreements during FY 2010. Def.’s
    Mot. Dismiss App. at A278. While the second claim was still pending, plaintiff
    submitted a third claim, on May 8, 2012, demanding payment for breach of contract
    equal to $17,760,316 plus interest in unreimbursed indirect costs allocable to a total of
    7
    The Contracting Officer’s decision provided, inter alia:
    USEC was late submitting documents, sporadically submitted revisions,
    frequently revised submissions, and didn’t fulfill its responsibility by responding
    to DOE’s questions regarding these submissions in a timely manner. Further,
    despite the complexity of USEC’s cost accounting practices, the changing indirect
    rate models, the number and volume of documents submitted, and the numerous
    retroactive accounting practice changes proposed by USEC, the DOE has met its
    obligations under the various contract agreements with USEC.
    Def.’s Mot. Dismiss App. at A273.
    9
    eleven DOE contracts, plus damages caused under subcontract agreements during FY
    2011. DOE denied both claims on August 15, 2012. 8 Compl. ¶¶ 94, 99.
    USEC filed its fourteen-count complaint on May 30, 2013. Briefing was complete
    on December 4, 2014, and oral argument on the government’s partial motion to dismiss
    for lack of jurisdiction was held on April 27, 2014. 9 Following oral argument, the court
    stayed consideration of the case to allow the parties to discuss settlement.
    On July 25, 2014, the parties filed a joint status report in which they indicated that
    USEC had agreed to dismiss Counts I, III, and V with prejudice. See Joint Status Report,
    ECF No. 36. The parties indicated that they were unable, however, to reach a resolution
    concerning the government’s requested dismissal of plaintiff’s claims relating to costs
    incurred under USEC’s contracts with other DOE contractors. The court now turns to
    those claims.
    8
    The Contracting Officer’s decision provided, inter alia:
    USEC has claimed numerous costs associated with its subcontracts with various
    other entities, some of which were DOE prime contractors . . . . With limited
    exceptions, the CDA does not afford subcontractors the ability to pursue a claim
    directly against the Government arising out of subcontracts. Those exceptions are
    not applicable here. Further, DOE is not a party to those subcontracts or
    otherwise in privity with USEC regarding those agreements. Each of the
    subcontracts likely contains mechanisms for handling disputes, all of which may
    be pursued between USEC and the prime contractors with which USEC has an
    agreement. Consequently, all costs attributable to issues arising under the
    subcontracts are denied.
    Def.’s Mot. Dismiss App. at A284.
    9
    As noted, the government’s motion originally sought to dismiss USEC’s claims related to
    provisional billing rates in 2003 and 2004, as well as all subcontractor-related claims. See note
    1.
    10
    II.    DISCUSSION
    a. Standard of Review
    The Tucker Act vests this court with jurisdiction over “any claim against the
    United States founded either upon the Constitution, or any Act of Congress or any
    regulation of an executive department, or upon any express or implied contract with the
    United States, or for liquidated or unliquidated damages in cases not sounding in tort.”
    
    28 U.S.C. § 1491
    (a)(1). When proceeding against the government for breach of contract,
    a plaintiff is generally obligated to demonstrate the existence of a direct contract between
    the government and the plaintiff. This well-established rule exists because “the
    government consents to be sued only by those with whom it has privity of contract.”
    Erickson Air Crane Co. of Wash. v. United States, 
    731 F.2d 810
    , 813 (Fed. Cir. 1984).
    Subcontractors and other third parties are generally not permitted to raise claims directly
    against the government, and instead “have the option of enforcing their subcontract rights
    against the prime contractor in appropriate proceedings, or of prosecuting a claim against
    the government through and in right of the prime contractor’s contract, and with the
    prime contractor’s consent and cooperation.” Id.; see also E.R. Mitchell Constr. Co. v.
    Danzig, 
    175 F.3d 1369
    , 1370 (Fed. Cir. 1999) (discussing pass-through suits).
    The burden of establishing jurisdiction falls on the plaintiff. Banks v. United
    States, 
    741 F.3d 1268
    , 1277 (Fed. Cir. 2014); Estate of Hage v. United States, 
    687 F.3d 1281
    , 1290-91 (Fed. Cir. 2012). Where, as here, the government has moved to dismiss
    certain claims on jurisdictional grounds, “the factual allegations in the complaint are not
    controlling and only uncontroverted factual allegations are accepted as true.” Shoshone
    11
    Indian Tribe of Wind River Reservation v. United States, 
    672 F.3d 1021
    , 1030 (Fed. Cir.
    2012). As a result, the court will look beyond the pleadings, if necessary, to inquire into
    whether jurisdiction exists. See Banks, 741 F.3d at 1277. Indeed, where the court’s
    jurisdiction is challenged on the grounds that plaintiff lacked contractual privity with the
    government, the court will closely read any contractual documentation to determine
    whether it possesses authority to proceed. See N. Hartland, L.L.C. v. United States, 
    78 Fed. Cl. 172
    , 179-81 (2007), aff’d, 309 F. App’x 389 (Fed. Cir. 2009).
    b. The Court Lacks Jurisdiction to Consider Plaintiff’s Claims Stemming
    from its Contracts with Other DOE Prime Contractors
    The government argues that the court lacks jurisdiction to hear claims related to
    USEC’s contracts with other DOE prime contractors on the ground that, as a
    subcontractor, USEC is not in privity with the government and thus lacks standing to sue
    the government directly under the Tucker Act or CDA. The government also contends
    that USEC might not have needed to show privity if it had shown that DOE’s prime
    contractors were merely purchasing agents for DOE, but that USEC elected not to make a
    claim based on agency. 10
    Plaintiff attempts to avoid dismissal by arguing that its claims stem from its direct
    contracts with the government. Specifically, plaintiff contends that (1) USEC and DOE
    entered into direct agreements with each other that “required” USEC to provide services
    to DOE through other prime contractors, which would be reimbursed at the same rate that
    10
    Plaintiff neither alleges facts consistent with an agency theory nor responds to the
    government’s arguments in its briefs.
    12
    USEC billed DOE directly; or, in the alternative, that (2) USEC is entitled to recover
    subcontract-related losses as “consequential damages” flowing from plaintiff’s direct
    contracts with DOE, because such damages were the foreseeable consequence of the
    government’s failure to timely approve USEC’s billing rates. 11 The court rejects both
    arguments for the reasons that follow, and concludes that plaintiff has failed to meet its
    burden of adequately alleging subject matter jurisdiction as to its subcontractor-related
    claims.
    To begin, plaintiff’s assertion that the agreements between the government and
    USEC “required” USEC to contract with other DOE prime contractors is not supported. 12
    The 2006 MOA Modification states:
    Nothing in this Services Agreement Modification No. 1 shall be interpreted
    to require either DOE or USEC . . . to furnish any service or services to the
    other Party in the event service(s) of that type is not necessary for a Party’s
    own programmatic needs or to require either Party to purchase any
    11
    In a footnote, plaintiff also suggests that the court should relax the privity requirement because
    of DOE’s role in negotiating the terms of USEC’s agreements with other DOE prime contractors.
    See Pl.’s Opp’n 24 n.7 (“DOE should not be permitted to dictate contractual terms of the DOE
    Subcontract Agreements while at the same time disclaiming any responsibility for abiding by its
    obligation to ensure proper payment is made under the DOE Subcontract Agreements.”).
    Plaintiff’s argument is unavailing. This court has repeatedly held that the government’s close
    contractual oversight, including drafting the language used in agreements between a prime
    government contractor and its subcontractors, is insufficient to establish privity between the
    government and a subcontractor. See G4S Tech. LLC v. United States, 
    114 Fed. Cl. 662
    , 670-73
    (2014); O. Ahlborg & Sons, Inc. v. United States, 
    74 Fed. Cl. 178
    , 190 (2006).
    12
    Plaintiff’s complaint alleges numerous legal conclusions concerning the effect of various
    provisions of these agreements. See, e.g. Compl. ¶ 22 (“The 2006 [MOA Modification] requires
    that USEC perform certain services for DOE for other DOE contractors at the GDPs under DOE
    Subcontract Agreements.”) (emphasis added). The court is not obligated to accept legal
    conclusions as true for the purpose of deciding the government’s motion to dismiss for lack of
    subject matter jurisdiction. See Kam-Almaz v. United States, 
    682 F.3d 1364
    , 1368 (Fed. Cir.
    2012).
    13
    service(s), captive or otherwise, from the other Party.
    Def.’s Mot. Dismiss App. at A19. Given this language disclaiming any requirement to
    perform services, the court rejects plaintiff’s assertion that the 2006 MOA Modification
    created a link between DOE and USEC that required USEC “to enter into . . . subcontract
    agreements and DOE [to] approv[e] USEC’s provisional billing rates that DOE had to
    use to recover its costs under these subcontract agreements.” Oral Argument Hr’g Tr. 29
    17-24, 3:00 P.M., April 24, 2014.
    The court also rejects plaintiff’s contention that USEC’s subcontracts with other
    DOE prime contractors were incorporated into USEC’s direct contract(s) with the
    government. Plaintiff relies on a section of the 2006 MOA Modification for this
    assertion, which states that
    An agreement for Captive Services approved in advance by the DOE Lease
    Administrator between a DOE prime contractor or subcontractor and USEC
    for work approved after execution of [this agreement] shall be treated as an
    agreement under the provisions of [this agreement,] including, but not
    limited to, the provisions related to ARTICLE IV A.1, and shall be on a
    cost reimbursable basis.
    Def.’s Mot. Dismiss App. at A19 (emphasis added). The court concludes that this
    language, alone, is insufficient to demonstrate privity between the government and USEC
    as to USEC’s subcontracts. At best, this language might support a finding of jurisdiction
    based on a theory of agency, but plaintiff has failed to make such an allegation, and the
    court will not interpret USEC’s argument to encompass such a theory. 13 Rather, because
    13
    In order to support a direct claim against the government as a subcontractor based on an
    agency theory, the subcontractor must demonstrate that “[t]he prime contractor was (1) acting as
    a purchasing agent for the government; (2) the agency relationship between the government and
    14
    USEC entered into separate agreements with prime contractors to provide Captive work,
    those agreements are controlling. To recover additional indirect costs, USEC must
    comply with the mechanisms set forth in those agreements and applicable regulations.
    See 
    48 C.F.R. § 52.216
    –7(d)(5) (“The completion invoice or voucher shall include settled
    subcontract amounts and rates. The prime contractor is responsible for settling
    subcontractor amounts and rates included in the completion invoice or voucher and
    providing status of subcontractor audits to the [C]ontracting [O]fficer upon request.”). 14
    The court also rejects plaintiff’s alternative argument that USEC can recover
    “consequential damages” under its direct contracts with DOE that relate to USEC’s
    subcontracts. The 2003 and 2006 Service Agreements expressly addressed the
    availability of such damages:
    Each Party’s liability to the other Party, to parties related to the other Party,
    and to third persons arising out of or in connection with this Agreement,
    shall be governed by the provisions of the Lease Agreement and applicable
    law.
    ....
    Neither Party shall be liable to the other Party for consequential, indirect or
    special damages, including loss of profit, fee, compensation of any kind or
    losses, costs or damages due to business interruption, arising out of the
    activities contemplated by this Agreement.
    the prime contractor was established by clear contractual consent; and (3) the contract stated that
    the government would be directly liable to the vendors for the purchase price.” Nat’l Leased
    Hous. Ass’n v. United States, 
    105 F.3d 1423
    , 1436 (Fed. Cir. 1997) (quoting United States v.
    Johnson Controls, Inc. v. United States, 
    713 F.2d 1541
    , 1551 (Fed. Cir. 1993)).
    14
    At oral argument, plaintiff was unable to explain why this procedure would not provide it with
    the relief it seeks with regard to its subcontract-related claims.
    15
    Def.’s Mot. Dismiss App. at A6 (emphasis added). Plaintiff has not provided any
    evidence or argument that would alter the court’s conclusion that this language
    unambiguously disclaims the right of either USEC or the government to recover
    consequential damages stemming from agreements associated with work at the GDPs.
    III.   CONCLUSION
    For the foregoing reasons, the court finds that it lacks jurisdiction to hear
    plaintiff’s request for relief stemming from its subcontract agreements with other DOE
    prime contractors. Therefore, the government’s Partial Motion to Dismiss is
    GRANTED. The parties shall file a status report no later than August 7, 2014, to
    propose a discovery and briefing schedule to address the remaining claims.
    IT IS SO ORDERED.
    s/Nancy B. Firestone
    NANCY B. FIRESTONE
    Judge
    16
    