Barlow & Haun, Inc. v. United States , 183 Oil & Gas Rep. 487 ( 2014 )


Menu:
  •            In the United States Court of Federal Claims
    No. 08-847L
    (Filed: September 26, 2014)
    ***************************************
    BARLOW & HAUN, INC., a Wyoming        *
    Corporation et al.,                   *                Trial; Suspension of Oil and Gas Leases;
    *                Concurrent Development of Oil and Gas and
    Plaintiffs,       *                Trona; Resource Management Plans; Breach
    *                of Contract; Fifth Amendment Taking;
    v.                                    *                Jurisdiction; Statute of Limitations;
    *                Justiciability; Ripeness; Standing;
    THE UNITED STATES,                    *                Repudiation
    *
    Defendant.        *
    ***************************************
    Drake D. Hill, Casper, WY, for plaintiffs.
    E. Barrett Atwood, United States Department of Justice, San Francisco, CA, for defendant.
    OPINION AND ORDER
    SWEENEY, Judge
    This case concerns twenty-six leases for oil and gas deposits in southwestern Wyoming.
    Defendant, as lessor, has simultaneously acknowledged valid existing rights and indefinitely
    suspended operations and production under the leases. This indefinite suspension, plaintiffs
    contend, excuses their obligation to seek the required permits from defendant to develop the
    leases, and amounts to either a breach of the leases or an uncompensated taking of the lessee’s
    rights under the leases. Defendant counters that the court is precluded from considering
    plaintiffs’ claims on jurisdictional and justiciability grounds, but that even in the absence of such
    bars, plaintiffs cannot prevail on the merits. The court held a trial on all liability and damages
    issues, after which the parties submitted posttrial briefs and presented closing arguments. As set
    forth below, the court concludes that plaintiffs’ takings claim is unripe, that three of the four
    plaintiffs lack standing to assert a claim for breach of contract, and that the remaining plaintiff’s
    breach-of-contract claim fails on its merits.
    -1-
    FACTS
    This section contains the court’s findings of fact as required by Rule 52(a)(1) of the Rules
    of the United States Court of Federal Claims (“RCFC”). 1
    I. Statutory and Regulatory Background
    The leases at issue in this case, which are described in the appendix to this decision, are
    subject to the federal government’s statutory and regulatory authority. Jt. Stip. ¶¶ 24-25. Of
    particular relevance are the statutes and regulations pertaining to the commencement of oil and
    gas operations on land owned by the government, as well as the statutes and regulations related
    to the government’s development and revision of land use plans. 2
    A. Federal Oil and Gas Leasing
    The Mineral Leasing Act, 
    30 U.S.C. §§ 181-287
     (2012), originally enacted in 1920,
    provides the statutory framework for the disposition of mineral deposits, and the lands containing
    such deposits, owned by the United States. 
    Id.
     § 181. Further guidance is contained in the rules
    and regulations that the Secretary of the United States Department of the Interior (“Secretary”) is
    authorized to promulgate to carry out the Act’s provisions. See id. § 189. The Secretary has
    delegated this authority to the Bureau of Land Management (“BLM”). 
    43 C.F.R. § 3160.0-3
    (2013). The Secretary has also authorized the BLM “to issue Onshore Oil and Gas Orders when
    necessary to implement and supplement” the BLM’s regulations; these orders apply to existing
    and future oil and gas leases. 
    Id.
     § 3164.1; see also Onshore Oil and Gas Order Number 1, 
    72 Fed. Reg. 10,308
     (Mar. 7, 2007). The regulations issued by the BLM contain the following
    general requirement:
    The [operator] 3 shall comply with applicable laws and regulations; with the lease
    terms, Onshore Oil and Gas Orders, [and notices to lessees and operators]; and
    1
    The court derives some of these facts from the parties’ Joint Stipulation of Facts (“Jt.
    Stip.”) and pertinent statutes and regulations. The remaining facts are derived from the transcript
    of testimony elicited at trial (“Tr.”) and the exhibits admitted into evidence during trial (“PX,”
    “DX,” or “JX”). Citations to the trial transcript will be to the page number of the transcript and
    the last name of the testifying witness; if more than one witness testified to the same fact, the
    court might only cite to the testimony of one witness. And, where two copies of a single
    document have been admitted into evidence, the court will cite to only one version of the
    document.
    2
    The court cites to the most recent versions of the pertinent statutes and regulations.
    Unless otherwise indicated, the statutory and regulatory provisions cited by the court have
    remained substantively unaltered during the time period covered by this case.
    3
    An operator is “any person or entity including but not limited to the lessee or operating
    rights owner, who has stated in writing to the authorized officer that it is responsible under the
    -2-
    with other orders and instructions of the authorized officer. These include, but are
    not limited to, conducting all operations in a manner . . . which protects other
    natural resources and environmental quality; which protects life and property; and
    which results in maximum ultimate economic recovery of oil and gas with
    minimum waste and with minimum adverse effect on ultimate recovery of other
    mineral resources.
    
    43 C.F.R. § 3162.1
    (a) (footnote added); accord 
    id.
     § 3162.5-2(a); see also id. § 3162.5-1(b)
    (requiring operators to “exercise due care and diligence” to ensure against “undue damage to
    surface or subsurface requirements”); id. § 3162.5-2(d) (requiring operators to “isolate . . . other
    mineral-bearing formations and protect them from contamination”); id. § 3162.5-3 (requiring
    operators to “take all precautions necessary to provide adequate protection for the health and
    safety of life and the protection of property”); 72 Fed. Reg. at 10,335 (requiring operators to
    “minimize adverse effects to surface and subsurface resources” and to “protect the public from
    any hazardous conditions resulting from operations”).
    To commence operations under a lease, an operator must submit an Application for
    Permit to Drill (“APD”). 
    43 C.F.R. § 3162.3-1
    ; 4 72 Fed. Reg. at 10,330. To be considered
    administratively and technically complete, an APD must include a drilling plan, a surface use
    plan of operations, evidence of bond coverage, and “[s]uch other information as may be required
    by applicable orders and notices.” 
    43 C.F.R. § 3162.3-1
    (d); accord 72 Fed. Reg. at 10,330-33.
    The required drilling plan must contain “a description of the drilling program, the surface and
    projected completion zone location, pertinent geological data, expected hazards, and proposed
    mitigation measures to address such hazards,” 
    43 C.F.R. § 3162.3-1
    (e), and “must be in
    sufficient detail to permit a complete appraisal of the technical adequacy of, and environmental
    effects associated with, the proposed project,” 72 Fed. Reg. at 10,331. Indeed, the drilling plan
    must include, among other items:
    a. Names and estimated tops of all geologic groups, formations, members,
    or zones.
    b. Estimated depth and thickness of formations, members, or zones
    potentially containing usable water, oil, gas, or prospectively valuable deposits of
    other minerals that the operator expects to encounter, and the operator’s plans for
    protecting such resources.
    terms and conditions of the lease for the operations conducted on the leased lands or a portion
    thereof.” 
    43 C.F.R. § 3160.0-5
    .
    4
    Section 3162.3-1 did not take its present form until June 1988, 
    53 Fed. Reg. 22,814
    ,
    22,846 (June 17, 1988), after six of the leases at issue were first acquired by one of the plaintiffs,
    see App., infra.
    -3-
    c. The operator’s minimum specifications for blowout prevention
    equipment and diverter systems to be used, including size, pressure rating,
    configuration, and the testing procedure and frequency. . . .
    d. The operator’s proposed casing program, including size, grade, weight,
    type of thread and coupling, the setting depth of each string, and its condition. . . .
    e. The estimated amount and type(s) of cement expected to be used in the
    setting of each casing string. . . .
    ....
    g. The testing, logging, and coring procedures proposed, including drill
    stem testing procedures, equipment, and safety measures.
    h. The expected bottom-hole pressure and any anticipated abnormal
    pressures, temperatures, or potential hazards that the operator expects to
    encounter, such as lost circulation and hydrogen sulfide . . . .
    i. Any other facets of the proposed operation that the operator would like
    the BLM to consider in reviewing the application. Examples include, but are not
    limited to:
    •   For directional wells, proposed directional design, plan view, and vertical
    section in true vertical and measured depths;
    •   Horizontal drilling; and
    •   Coil tubing operations.
    
    Id.
    Upon the receipt of a complete APD, the BLM posts a notice of the APD for a thirty-day
    period of public inspection, 
    id. at 10,333-34
    ; 
    43 C.F.R. § 3162.3-1
    (g), consults with the relevant
    federal surface management agency and other interested parties, 
    43 C.F.R. § 3162.3-1
    (h), and
    conducts an onsite inspection, 72 Fed. Reg. at 10,334. Then, no later than five business days
    after the notice period, the BLM is required to (1) advise the applicant that the APD is approved;
    (2) return the APD with an explanation for why it was not approved; or (3) inform the applicant
    that a final decision will be delayed, explain the reason for the delay, and provide the date that it
    expects to issue a final decision. 
    43 C.F.R. § 3162.3-1
    (h); accord 72 Fed. Reg. at 10,334. Prior
    to approving an APD, the BLM must ensure that certain other statutory and regulatory
    requirements have been met, such as the requirements set forth in the National Environmental
    Policy Act of 1969 and its implementing regulations. 72 Fed. Reg. at 10,334; accord 
    43 C.F.R. § 3162.5-1
    (a). And, the BLM may condition its approval of an APD on the applicant taking
    -4-
    “reasonable mitigation measures to ensure that the proposed operations minimize adverse
    impacts to other resources, uses, and users, consistent with granted lease rights.” 72 Fed. Reg. at
    10,334.
    The Mineral Leasing Act and its implementing regulations also provide for the
    suspension of leases. Under the Act:
    The Secretary of the Interior, for the purpose of encouraging the greatest ultimate
    recovery of . . . oil, gas, . . . [and] sodium, . . . and in the interest of conservation
    of natural resources, is authorized to waive, suspend, or reduce the rental, or
    minimum royalty, . . . whenever in his judgment it is necessary to do so in order
    to promote development, or whenever in his judgment the leases cannot be
    successfully operated under the terms provided therein. . . . In the event the
    Secretary of the Interior, in the interest of conservation, shall direct or shall assent
    to the suspension of operations and production under any lease granted under the
    terms of this chapter, any payment of acreage rental or of minimum royalty
    prescribed by such lease likewise shall be suspended during such period of
    suspension of operations and production; and the term of such lease shall be
    extended by adding any such suspension period thereto.
    
    30 U.S.C. § 209
    . Leases cannot expire while in suspension. 
    Id.
     § 226(i). The relevant
    regulations mirror these provisions. See 
    43 C.F.R. § 3103.4-4
    (a) (“A suspension of all
    operations and production may be directed or consented to by the authorized officer only in the
    interest of conservation of natural resources.”); 
    id.
     § 3103.4-4(b) (“The term of any lease shall be
    extended by adding thereto the period of the suspension, and no lease shall be deemed to expire
    during any suspension.”); id. § 3103.4-4(d) (“Rental and minimum royalty payments shall be
    suspended during any period of suspension of all operations and production directed or assented
    to by the authorized officer . . . .”). 5
    B. Federal Land Policy
    The other statute relevant in this case is the Federal Land Policy and Management Act of
    1976, 
    43 U.S.C. §§ 1701-1787
     (2012), which provides the framework for the federal
    government’s land use planning and management. Under this Act, the Secretary is authorized to
    “develop, maintain, and, when appropriate, revise land use plans which provide by tracts or areas
    for the use of the public lands.” 
    Id.
     § 1712(a). The Secretary may delegate these responsibilities
    to the BLM, id. § 1731, and promulgate rules and regulations to implement the statutory
    requirements, id. § 1740.
    As set forth in the Act’s implementing regulations, “[r]esource management plans are
    designed to guide and control future management actions and the development of subsequent,
    5
    Section 3103.4-4 was published in May 1988, 
    53 Fed. Reg. 17,340
    , 17,354 (May 16,
    1988), after six of the leases at issue were first acquired by one of the plaintiffs, see App., infra.
    -5-
    more detailed and limited scope plans for resources and uses.” 6 
    43 C.F.R. § 1601.0-2
     (2012).
    However, a resource management plan “is not a final implementation decision on actions which
    require further specific plans, process steps, or decisions under specific provisions of law and
    regulations.” 
    Id.
     § 1601.0-5(n).
    The development or revision of a resource management plan is a lengthy, multistep
    process. See generally id. §§ 1610.4-.5. Broadly summarized, the relevant BLM field office
    must (1) gather and analyze a wide spectrum of information and data from a variety of sources,
    id. §§ 1610.4-1 to -4; (2) prepare a draft resource management plan and draft environmental
    impact statement in which it describes and analyzes resource management alternatives and
    identifies a preferred alternative, id. §§ 1610.4-5 to -7; (3) review any comments on its draft
    plan, id. § 1610.4-8; and (4) submit a recommended proposed resource management plan and
    final environmental impact statement to the appropriate BLM state office, id. §§ 1610.4-8,
    1610.5-1. Then, the BLM state office (1) publishes the proposed resource management plan and
    final environmental impact statement, id.; (2) resolves any protests of the proposed plan, id.
    §§ 1610.5-1 to -2; and (3) approves the proposed plan in a “concise public record of the
    decision,” id. § 1610.5-1. “All future resource management authorizations and actions” are
    required to “conform to the approved plan.” Id. § 1610.5-4. However, in appropriate
    circumstances, a resource management plan may be amended to permit a previously prohibited
    resource use. Id. § 1610.5-5. The amendment process requires, among other things, the
    preparation of an environmental assessment or an environmental impact statement. Id.
    II. The Pre-August 1991 Landscape and Plaintiffs’ Acquisition of Leases
    Plaintiff Barlow & Haun, Inc. (“Barlow & Haun”) is a Wyoming corporation that, among
    other things, identifies oil and gas prospects and then markets those prospects to the oil and gas
    industry for further development. Tr. 72, 1286-87 (Doelger). More particularly, Barlow &
    Haun’s business model involves developing sufficient geologic support to justify exploration and
    drilling on its leases, and then marketing its findings to the oil and gas industry via
    prospectuses. 7 Id. at 1286, 1289 (Doelger). Barlow & Haun generally does not act as an
    operator; rather, its goal is to partner with oil and gas producers to develop the leases. 8 Id. at
    1286-87, 1289 (Doelger). In furtherance of its efforts, Barlow & Haun and another plaintiff,
    TriContinental Resources (“TriContinental”), a Wyoming partnership, began to acquire oil and
    gas leases in the Green River Basin in southwestern Wyoming, in what has been designated as
    the Known Sodium Leasing Area (“KSLA”). Jt. Stip. ¶¶ 11, 22. The KSLA derives its name
    from the presence of trona deposits; trona is the hard component of sodium, Tr. 950 (Murphy),
    6
    A “resource management plan” is another name for the land use plan described in the
    Federal Land Policy and Management Act of 1976. See 
    43 C.F.R. § 1601.0-5
    (n).
    7
    Prospectuses are also known as “blue books.” Tr. 1298-98 (Doelger).
    8
    However, Barlow & Haun was the operator of a dry hole well at Cedar Mountain. Tr.
    1287 (Doelger). As the operator, it “permitted the well, . . . bonded the well, . . . contracted for
    the rig, [and] managed the operations.” 
    Id.
    -6-
    and sodium is a leasable mineral under the Mineral Leasing Act, 
    30 U.S.C. § 181
    . By 1992, the
    KSLA encompassed approximately 694,000 acres of land, with approximately 400,000 acres
    owned by the federal government and the remaining acreage owned by the state of Wyoming and
    Anadarko Petroleum Company (“Anadarko”). Tr. 951-52 (Murphy).
    Two BLM field offices are responsible for overseeing activities within the KSLA: the
    western portion of the KSLA is administered by the Kemmerer field office and the eastern
    portion is administered by the Rock Springs field office. 
    Id. at 3468
     (Madrid); DX 102A. In
    June 1986, the BLM issued a record of decision approving and adopting a resource management
    plan covering the land within the Kemmerer field office’s area of administration (the “Kemmerer
    Resource Management Plan”). Jt. Stip. ¶ 16; JX 25. The record of decision allowed for oil and
    gas drilling and production, subject to the BLM’s regulatory authority. Jt. Stip. ¶¶ 17-18. It did
    not mention any potential conflict with the underground mining of trona. 
    Id. ¶ 17
    . The record of
    decision remained in effect until 2010. 
    Id. ¶¶ 19, 57
    .
    The twenty-six leases at issue in this case, which are situated in the KSLA and cover just
    over 26,000 acres of land, were acquired while the 1986 record of decision was in place, 
    id. ¶¶ 60-81
    . Barlow & Haun and TriContinental originally acquired record title interest in sixteen
    of the leases before August 1991, when the conflict between trona and oil and gas, described
    below, became evident. 
    Id. ¶¶ 61, 63-68, 70-77, 80
    . They subsequently assigned their interests
    in all sixteen of these leases to other entities, before Barlow & Haun reacquired record title
    interest in them in the 2000s. 
    Id.
     Notably, TriContinental has not possessed record title interest
    in any of the leases at issue since June 1, 2000. See 
    id. ¶ 61
     (noting that TriContinental
    relinquished its interest in one lease effective June 1, 2000); 
    id. ¶¶ 63-66, 68, 71-74, 76, 80
    (noting that TriContinental relinquished its interest in eleven leases effective August 1, 1990).
    With respect to the remaining ten leases at issue, Barlow & Haun initially acquired one
    lease in 1999, four more leases in 2001, and the five remaining leases in 2008. 
    Id. ¶¶ 60, 62, 69, 78-79, 81
    . Barlow & Haun has continuously maintained a 100% record title interest in the leases
    it acquired in 1999 and 2008, 
    id. ¶¶ 60, 81
    , but not in the leases it acquired in 2001. 
    Id. ¶¶ 62, 69, 78-79
    . In the appendix, the court identifies each lease, the first date that the lease was
    acquired by one of the plaintiffs, and the date that Barlow & Haun most recently acquired an
    interest in the lease.
    The relevant provisions of all twenty-six leases are very nearly identical. For example,
    all but one of the leases contains the following granting clause:
    [T]his lease is issued granting the exclusive right to drill for, mine, extract,
    remove and dispose of all the oil and gas . . . in the lands described [herein] . . . .
    Rights granted are subject to applicable laws, the terms, conditions, and attached
    stipulations of this lease, the Secretary of the Interior’s regulations and formal
    orders in effect as of lease issuance, and to regulations and formal orders hereafter
    promulgated when not inconsistent with lease rights granted or specific provisions
    of this lease.
    -7-
    
    Id. ¶ 24
    . The remaining lease (WYW84463) similarly provides:
    This oil and gas lease is issued for a period of ten (10) years to the above-
    named lessee pursuant and subject to the provisions of the Mineral Leasing Act
    and subject to all rules and regulations of the Secretary of the Interior now or
    hereafter in force, when not inconsistent with any express and specific provisions
    herein, which are made a part hereof.
    ....
    The lessee is granted the exclusive right and privilege to drill for, mine,
    extract, remove, and dispose of all the oil and gas . . . in the lands leased . . . .
    JX 26 at BH005120-21. Other similarities include provisions requiring the lessee to pay the
    United States rentals and royalties, see JX 26, and the lack of any stipulations on oil and gas
    production related to trona, Jt. Stip. ¶ 26.
    Furthermore, all of the leases contain provisions describing the parties’ responsibilities
    regarding operations. In particular, each lease reserves to the United States the right to control
    the rates of development and production for the public interest. See JX 26; see also 
    id.
     at
    BH005121 (containing, in lease WYW84463, a more detailed provision indicating that the
    Secretary, in carrying out the public interest, could “take into consideration, among other things,
    Federal laws, State laws, and regulations issued thereunder, or lawful agreements among
    operators regulating either drilling or production, or both”). In addition, each lease requires the
    lessee to conduct operations in the least intrusive manner possible. See, e.g., 
    id.
     at BH003155
    (containing provisions, found in twenty-five of the leases, that require the lessee to (1) “conduct
    operations in a manner that minimizes adverse impacts to the land, air, and water, to cultural,
    biological, visual, and other resources, and to other land uses or users” and to “take reasonable
    measures deemed necessary by [the United States] to accomplish” this requirement, and (2)
    “maintain a safe work environment in accordance with standard industry practices . . . and take
    measures necessary to protect the health and safety of the public”), BH005121 (providing, in
    lease WYW84463, that the lessee agrees “to carry on all operations in accordance with approved
    methods and practice as provided in the Oil and Gas Operating Regulations, having due regard
    for the prevention of waste of oil or gas or damage to deposits or formations containing oil, gas,
    or water or to coal measures or other mineral deposits, for conservation of gas energy, for the
    preservation and conservation of the property for future productive operations, and for the health
    and safety of workmen and employees”).
    III. The Trona Conflict
    In August 1991, Atlantic Richfield Company (“ARCO”) submitted an application to the
    BLM for an oil and gas unit designation for the proposed development of the Overland Trail
    Unit, a portion of which was located in the KSLA. Jt. Stip. ¶ 27. A trona mining company,
    FMC Wyoming Corporation, received notice of ARCO’s application and, concerned with the
    possibility of concurrent development of oil and gas and trona, lodged a formal protest with the
    -8-
    BLM. 
    Id. ¶ 28
    ; Tr. 874 (Murphy). The BLM began to investigate the issue of concurrent
    development and prepare a regulatory response. Jt. Stip. ¶ 29.
    Because an agreement with the trona mining companies for concurrent development had
    not been reached and a regulatory response from the BLM was not immediately forthcoming,
    ARCO requested, in June 1992, that the BLM issue an indefinite suspension of all of its leases
    located in the KSLA to protect ARCO’s investment in the area. 
    Id. ¶¶ 30-31
    . The leases
    identified by ARCO included seventeen of the twenty-six leases at issue in this case. 
    Id. ¶ 31
    .
    The BLM granted ARCO’s request in part, suspending operations on ARCO’s leases from
    September 1992 through January 1993. 
    Id. ¶ 32
    . Because the situation remained unchanged in
    January 1993, ARCO requested another indefinite suspension of its leases. 
    Id. ¶ 33
    . The BLM
    suspended the leases through December 1993. 
    Id. ¶ 34
    .
    While the negotiations between the oil and gas and trona industries concerning
    concurrent development continued, the BLM developed its policy response: the Wyoming
    Trona/Oil and Gas Conflict Policy (“Conflict Policy”). 
    Id. ¶ 35
    . The Conflict Policy was based
    on the principle of “first in time, first in right.” 
    Id. ¶ 36
    . The BLM had developed the Conflict
    Policy after reviewing input from the oil and gas and trona industries, and securing the approval
    of all three mineral owners in the KSLA (the BLM, the state of Wyoming, and Anadarko’s
    predecessor, Union Pacific Resources Group, Inc. (“Union Pacific”) 9). 
    Id.
     The BLM
    disseminated the Conflict Policy to leaseholders in the KSLA and other interested parties in
    April 1993 for review and comment. 
    Id.
    In August 1993, while the BLM was still soliciting comments, the Petroleum Association
    of Wyoming, the Trona Section of the Wyoming Mining Association, and Union Pacific formed
    the Joint Industry Committee (“JIC”) to develop an alternative to the Conflict Policy. 10 
    Id. ¶ 37
    .
    In response, the BLM decided to table its formal adoption of the Conflict Policy. 
    Id. ¶ 38
    . The
    JIC, using outside contractors, began to study the issue of concurrent development in an attempt
    9
    The relationship between Anadarko and Union Pacific is not accurately stated in the
    trial record. See Tr. 952 (Murphy) (describing Anadarko as a subsidiary of Union Pacific). The
    court takes judicial notice, pursuant to Rule 201(b)(2) of the Federal Rules of Evidence, that
    Anadarko acquired Union Pacific in 2000, and that Union Pacific is a subsidiary of Anadarko.
    See Press Release, Anadarko Petroleum Corporation, Anadarko and Union Pacific Resources
    Close Merger (July 14, 2000), http://www.anadarko.com/Investor/Pages/NewsReleases/News
    Releases.aspx?release-id=104508.
    10
    Subsequently, in April 1995, the JIC formalized its membership and organization in a
    Participant Agreement. DX 113. The signatories to the agreement were Rock Springs Royalty
    Company; Union Pacific; FMC Corporation; Tg Soda Ash, Inc.; Rhone Poulenc of Wyoming,
    L.P.; General Chemical (Soda Ash) Partners and Solvay Soda Ash Joint Venture; the Petroleum
    Association of Wyoming; and the Wyoming Mining Association Trona Subcommittee. 
    Id.
     The
    agreement also reflected that the BLM and the state of Wyoming intended to participate in the
    JIC’s activities. 
    Id.
    -9-
    to find a technical solution. 
    Id. ¶ 39
    ; JX 7. ARCO once again requested that the BLM
    indefinitely suspend its leases in the KSLA, and the BLM suspended the leases through January
    1995. Jt. Stip. ¶ 40.
    By 1995, the BLM realized that the JIC’s development of an alternative to the Conflict
    Policy would take years to accomplish due to the complex technical investigation required. 
    Id. ¶ 41
    . Thus, in April 1995, it established the Mechanically Mineable Trona Area (“MMTA”), an
    area encompassing the northeastern portion of the KSLA, within which oil and gas operations
    and production were suspended for a three-year period–from May 1995 to May 1998. Id.; JX 7.
    The BLM extended the suspension for another year in 1998. Jt. Stip. ¶ 42. Finally, on April 29,
    1999, the JIC Policy Committee submitted its findings to the JIC and the BLM. 
    Id. ¶ 43
    . To
    allow more time for it to consider the findings, the BLM suspended the leases in the MMTA for
    another year, through May 1, 2000. 
    Id. ¶ 44
    . Ultimately, the BLM decided to postpone the
    issuance of a policy regarding concurrent development to permit the peer review of the JIC’s
    findings by Yates Petroleum Corporation (“Yates”). 
    Id. ¶¶ 45-46
    . Thus, on April 19, 2000, the
    BLM suspended all oil and gas leases in the MMTA “indefinitely” pursuant to 
    30 U.S.C. § 209
    ,
    
    30 U.S.C. § 226
    (i), and 43 C.F.R. ¶ 3103.4-4. 11 
    Id. ¶ 46
    ; JX 11. All of the leases at issue in this
    case were included in the suspension. Compare JX 11 (listing the affected leases), with App.
    (listing the leases at issue in this case).
    The BLM received the Yates report in August 2002. Jt. Stip. ¶ 48. Keeping the
    indefinite suspension in place, the BLM began to evaluate the report, the JIC’s
    recommendations, and input from the various stakeholders. 
    Id. ¶ 49
    . On April 15, 2004, the
    BLM held a public meeting to present its proposed solution to the oil and gas and trona conflict.
    
    Id. ¶ 50
    ; PX 292A. Specifically, the BLM proposed (1) establishing an Oil-Gas-Trona
    Management Area (“OGTMA”), an area roughly equivalent to the MMTA; (2) prioritizing
    conventional trona mining over oil and gas leasing and development within the OGTMA; (3)
    continuing the indefinite suspension of existing oil and gas leases within the OGTMA; and (4)
    analyzing, during the Kemmerer Resource Management Plan revision process, a moratorium of
    further oil and gas leasing within the OGTMA as part of the preferred alternative. PX 292A.
    Plaintiffs did not attend the meeting due to a lack of sufficient advance notice, but they did
    subsequently receive the BLM’s presentation materials. Jt. Stip. ¶ 50. Not long after the
    meeting, the BLM opted not to use the OGTMA label, deciding instead to revert to calling the
    affected area the MMTA. See Public Comment Notice, 
    69 Fed. Reg. 42,204
     (July 14, 2004); see
    also PX 109 (noting, in a January 2005 newsletter, that the BLM had changed the name of the
    area from the OGTMA to the MMTA).
    IV. Shallow Gas Drilling in the MMTA
    While the oil and gas leases in the MMTA remained suspended, an oil and gas operator,
    Saurus Resources, Inc. (“Saurus”), decided to pursue shallow gas development in the KSLA.
    11
    The BLM’s suspension letter erroneously refers to 43 C.F.R. ¶ 3103.4-4 as “43 C.F.R.
    ¶ 3104.4-4.” See 43 C.F.R. pt. 3100 (1999).
    -10-
    DX 22; DX 221; Tr. 159, 1335, 1352 (Doelger). Saurus entered into an agreement to pursue this
    development with Barlow & Haun and TriContinental on October 1, 1998. DX 22; Tr. 1352
    (Doelger). The project included, among other prospects, four suspended leases in the MMTA
    near a trona mine. DX 22; DX 23. Saurus met with the BLM in October 1998 to discuss its
    shallow gas drilling proposal. DX 101 at ¶¶ 29-30. Saurus subsequently submitted ten APDs to
    the BLM related to suspended leases in the MMTA, proposing to drill to shallow depths above
    an active trona mine. 
    Id. ¶¶ 31, 35
    . On October 29, 1998, Saurus and Barlow & Haun presented
    their proposal to the JIC. 
    Id. ¶¶ 32-34
    ; DX 27. The BLM then processed Saurus’s APDs,
    eventually rejecting them on November 17, 1998, due to the ongoing work of the JIC. DX 101
    at ¶ 35. However, Saurus continued to negotiate with the trona mining company, and the two
    eventually reached an agreement on a drilling plan. 
    Id. ¶ 39
    . The JIC evaluated and approved
    the agreement as an experimental model. DX 36.
    Having obtained approval of its proposed drilling plan, Saurus submitted five new APDs
    to the BLM in January 2000. DX 101 at ¶ 40. Saurus again indicated its intent to drill to
    shallow depths above an active trona mine, but proposed the use of new drilling practices. 
    Id. ¶¶ 39-40
    . The BLM approved the APDs in May 2000, at the same time terminating the
    suspensions of the relevant leases. 
    Id. ¶ 45
    .
    Once the BLM had approved its APDs and lifted the suspensions, Saurus began its
    shallow gas drilling. 
    Id.
     It drilled three wells above the trona mine, but because it encountered
    noncommercial amounts of gas, it abandoned those wells. 
    Id. ¶ 46
    ; JX 27 at BLMRS02-001985.
    Saurus allowed these leases to expire pursuant to their terms. DX 101 at ¶ 46. Saurus also
    drilled four other wells on leases within the MMTA, but none of those wells was proven to be
    economic. JX 27 at BLMRS02-001985; Tr. 1354 (Doelger). Ultimately, pursuant to the terms
    of a January 2003 settlement agreement, Saurus assigned its interest in these leases to its
    investors. DX 64; Tr. 1355 (Doelger). The investors formed two limited liability companies to
    serve as holding companies for the leases–plaintiffs NOWIO-S, LLC (“NOWIO-S”) and
    NOWIO-V, LLC (“NOWIO-V”). 12 DX 64; Tr. 1294 (Doelger), 2011 (Webb). NOWIO-S and
    12
    In their amended complaint, plaintiffs allege that NOWIO-S and NOWIO-V are
    “owners” of the oil and gas lease rights at issue in this case. See Am. Compl. ¶¶ 2-3, 5-8.
    However, in its amended answer, defendant denies that NOWIO-S and NOWIO-V “currently”
    own such oil and gas lease rights. See Am. Answer ¶¶ 2, 7-8. There was no evidence presented
    at trial regarding what, if any, record title interest NOWIO-S or NOWIO-V may have held in the
    leases at issue. Rather, plaintiff’s title expert, Ruth Reile, testified that (1) for lease
    WYW149082, “NOWIO owns 100%” of the operating rights interest “from the surface to the
    base of the Green River formation”; (2) for lease WYW103501, “plaintiff entities” own 50% of
    the operating rights interest “from the surface to the base of the Green River . . . formation” and
    100% of the operating rights interest “below the base of the Green River formation”; and (3) for
    the remaining leases, “plaintiff entities” own 100% of the operating rights interest. Tr. 1770-72
    (Reile). She further testified that the “plaintiff entities” obtained their operating rights interests
    on the same dates that Barlow & Haun last acquired record title interest in the leases. 
    Id. at 1773-74
     (Reile). Ms. Reile defined “plaintiff entities” as the plaintiffs named in the complaint,
    -11-
    NOWIO-V attempted, with the assistance of Barlow & Haun, to find an operator to replace
    Saurus, but were unsuccessful. Tr. 2028, 2034-35, 2038 (Webb). Barlow & Haun eventually
    ceased its efforts to locate a new operator, likely between October 2006 and June 2007. See 
    id. at 2038-40
     (Webb); DX 82.
    V. The Kemmerer Resource Management Plan Revision Process
    A. The July 2007 Draft Resource Management Plan and Environmental Impact Statement
    The BLM formally initiated the process to revise the Kemmerer Resource Management
    Plan in June 2003.13 JX 21 at 1-13. 14 In July 2007, the BLM issued its Draft Resource
    Management Plan and Environmental Impact Statement for the Kemmerer Field Office Planning
    Area. Jt. Stip. ¶ 53. The document contained several statements pertinent to the issues in this
    case. In the first chapter, which addressed the purpose of and need for a revised resource
    management plan, the BLM indicated that the revised plan would “recognize valid existing
    rights.” JX 21 at 1-11. The BLM described the proposed resource management alternatives in
    the second chapter of the document, explaining that the alternative designated as the “preferred
    alternative” was its “preliminary preference,” did not “represent a final BLM decision,” and
    could change between the draft and final environmental impact statements “based on comments
    received on the Draft EIS, new information, or changes in BLM policies or priorities.” 
    Id. at 2-2
    .
    The BLM’s preferred alternative provided, with respect to the conflict between oil and gas and
    trona:
    
    id. at 1785
     (Reile), but did not explain whether all, or just a subset, of the plaintiffs owned
    operating rights for each lease.
    Ms. Reile’s trial testimony is insufficient to establish the interests held by NOWIO-S and
    NOWIO-V. Plaintiffs should have entered into a stipulation with defendant regarding their
    ownership interests prior to trial, or, at trial, presented explicit testimony or documentation
    demonstrating the precise interests possessed by each entity. They failed to follow any of these
    avenues. No other witness testified regarding the interests held by NOWIO-S and NOWIO-V,
    and Ms. Reile’s expert report, which presumably would have contained this information, is not
    part of the record. Thus, all that can be concluded from the evidence presented at trial is that
    either NOWIO-S or NOWIO-V owns an operating rights interest in lease WYW149082, and that
    NOWIO-S and NOWIO-V may own operating rights interests in the remaining leases.
    13
    As noted above, the KSLA existed within the boundaries of two BLM field offices–the
    Kemmerer field office and the Rock Springs field office. Activities within the Rocks Springs
    field office’s boundary were governed by the Green River Resource Management Plan. See JX
    18. If necessary, the BLM would amend the Green River Resource Management Plan to
    conform to the new Kemmerer Resource Management Plan. Id.; Tr. 424 (Davis).
    14
    JX 21 is the Draft Resource Management Plan and Environmental Impact Statement
    for the Kemmerer Field Office Planning Area. All page citations for JX 21 are to the page
    numbers used in the document.
    -12-
    Existing oil and gas leases are suspended in the MMTA; new oil and gas leases
    are not being issued in the MMTA. . . . [T]he MMTA is administratively
    unavailable for new fluid mineral leasing until the oil and gas resource can be
    recovered without compromising the safety of underground miners.
    
    Id. at 2-45
    . In addition, the BLM indicated that it had considered an alternative that would have
    cancelled all existing oil and gas leases, but rejected that alternative without detailed analysis
    based on the following rationale: “The BLM must, by law, recognize all valid existing rights.”
    
    Id. at 2-5
    . In the third chapter of the document, which pertained to the environment affected by
    the draft plan, the BLM explained the procedure for pursuing oil and gas development:
    After acquiring an oil and gas lease, and prior to development, an
    application for permit to drill (APD) must be filed with . . . the BLM Kemmerer
    Field Office if the well is located on a federal oil and gas lease in the planning
    area. . . . Once the permit is approved, the company may proceed with drilling
    according to the applicable oil and gas lease stipulations and any site-specific
    conditions of approval that are applied to the permit at the time of approval.
    
    Id.
     at 3-22 to -23. Finally, in the fourth chapter of the document, which concerned the
    environmental consequences of the proposed alternatives, the BLM stated:
    In portions of the planning area, conflicts have occurred under all alternatives
    between oil and gas and trona, and may occur in the future between oil and gas
    and coal. Since 2004, the BLM has been working with industries, regulatory
    agencies, and other land owners to study and resolve technical and safety issues
    regarding recovery of overlapping oil and gas and trona resources. The
    conclusion from the deliberations is that oil and gas development and trona
    mining are basically incompatible because of the exposure of the underground
    trona workforce to risks associated with nearby high-pressure gas wells. The
    preferred course of action is to administer the area exclusively for trona extraction
    until conventional trona mining is complete. Therefore, an area has been
    designated, the MMTA, in which oil and gas leasing and development are
    currently prohibited. No formal decision has yet been made on the management
    of the oil and gas and trona resources within the MMTA boundary. This decision
    will be a part of the revision of the Kemmerer RMP.
    
    Id. at 4-29
    .
    -13-
    B. The August 2008 Proposed Resource Management Plan and Final Environmental
    Impact Statement
    After receiving input on its draft document, JX 22 at ES-6, 15 the BLM, in August 2008,
    issued its Proposed Resource Management Plan and Final Environmental Impact Statement for
    the Kemmerer Field Office Planning Area, Jt. Stip. ¶ 56. Portions of this document remained
    unchanged from the draft document, including the statements that all valid existing rights would
    be recognized, JX 22 at 1-13, 2-5, the passage addressing the status of oil and gas leases in the
    MMTA, 
    id. at 2-46
    , and most of the description of the conflict between oil and gas and trona, 
    id. at 4-31
    . However, there were some differences. First, the BLM’s preferred alternative was no
    longer characterized as its “preliminary preference” that could be changed; all language relating
    to the preliminary nature of the preferred alternative was removed. Second, the BLM amended
    its rationale for rejecting the alternative that would have resulted in the cancellation of all oil and
    gas leases to provide: “The BLM must, by law, recognize all valid existing rights. However, the
    BLM can impose reasonable limits on the manner and pace of development.” 
    Id. at 2-5
    . Third,
    the BLM amended its discussion of the procedure for pursuing oil and gas development to
    provide:
    Prior to drilling on a federal lease within the planning area, an application
    for permit to drill (APD) must be filed with . . . the BLM Kemmerer Field Office.
    . . . Once the permit is approved, the company proceeds with drilling according to
    the applicable oil and gas lease stipulations and any site-specific conditions of
    approval (COAs) that are applied to the permit at the time of approval.
    When an oil and gas lease is issued, it constitutes a valid existing right;
    BLM cannot unilaterally change the terms and conditions of the lease. Existing
    leases would not be affected by decisions resulting from this RMP that designate
    areas administratively unavailable for oil and gas leasing. New restrictions such
    as controlled surface use or timing restrictions in the form of stipulations could
    not be added to an existing lease. Existing leases would not be terminated until
    the lease expires. However, based on site or project-specific environmental
    analysis, COAs could be applied at the APD and Sundry Notice stage, and at
    subsequent development stages, to mitigate potential impacts from oil and gas
    operations within existing lease areas, providing the leaseholder’s right to develop
    the lease remains intact.
    
    Id. at 3-25
    . Finally, the BLM deleted the last two sentences of its description of the ongoing
    conflict between oil and gas and trona, which had indicated that the BLM had not made a
    “formal decision” concerning the management of the resources within the MMTA. Compare 
    id. at 4-31
    , with JX 21 at 4-29.
    15
    JX 22 is the Proposed Resource Management Plan and Final Environmental Impact
    Statement for the Kemmerer Field Office Planning Area. All page citations for JX 22 are to the
    page numbers used in the document.
    -14-
    C. The May 2010 Record of Decision and Approved Kemmerer Resource Management
    Plan
    In May 2010, after the conclusion of the protest period, JX 23 at 1-1, 16 the BLM issued
    its Record of Decision and Approved Kemmerer Resource Management Plan, Jt. Stip. ¶ 57.
    With this document, the BLM approved (with some changes, clarifications, and corrections not
    pertinent to this case) the resource management plan that it proposed in August 2008, JX 23 at 1-
    1 to 1-3, and replaced the plan that it had issued in 1986, 
    id. at 1-4
    ; Jt. Stip. ¶ 57. The BLM
    reiterated in this document that “valid existing rights” would be recognized. JX 23 at 2-15. The
    BLM also described the existing state of affairs in the MMTA, noting: “Existing oil and gas
    leases are suspended in the MMTA. The MMTA is administratively unavailable for new fluid
    mineral leasing until the oil and gas resource can be recovered without compromising the safety
    of underground miners.” 
    Id. at 2-26
    .
    Although Barlow & Haun frequently called the BLM to ascertain when the record of
    decision would be issued, plaintiffs never participated in the revision process. Tr. 1656-57,
    1688-89 (Easley), 3627 (Madrid). Moreover, since the BLM issued its record of decision in May
    2010, Barlow & Haun has not contacted the BLM to ascertain the effect that the new resource
    management plan would have on its leases in the MMTA. 
    Id. at 1688
     (Easley).
    VI. The Current Status of the Leases
    The twenty-six leases at issue in this case remained suspended throughout the Kemmerer
    Resource Management Plan revision process. See generally App. (listing the leases at issue in
    this case); JX 11 (listing the leases in the MMTA that were suspended); JX 21 at 2-45 (noting, in
    the July 2007 planning document, that existing oil and gas leases in the MMTA were
    suspended); JX 23 at 2-26 (indicating, in the May 2010 record of decision, that oil and gas leases
    in the MMTA remained suspended). Although the BLM suspended these leases “indefinitely,”
    JX 11, the suspension was not irreversible. Indeed, both the BLM and plaintiffs could have
    taken steps to trigger the lifting of the suspension.
    The BLM, pursuant to its regulatory authority, was responsible for monitoring lease
    suspensions to determine whether they should continue or be terminated. PX 19 at .31C3; Tr.
    3640, 3702 (Madrid). If the BLM determined that the conditions supporting a lease suspension
    no longer existed, then it was authorized to terminate the suspension. PX 19 at .31C3. The BLM
    made such a determination in May 2012, when, on its own initiative, it terminated the suspension
    of two leases at issue in this case that were located outside of the MMTA (leases WYW122215
    and WYW122863). Jt. Stip. ¶ 59; Tr. 3641-42 (Madrid), 3440 (Weaver).
    16
    JX 23 is the Record of Decision and Approved Kemmerer Resource Management
    Plan. All page citations for JX 23 are to the page numbers used in the document.
    -15-
    For their part, plaintiffs could have sought the termination of the suspension of the leases
    at issue by submitting an APD. See PX 19 at .31C2; Tr. 3643, 3702 (Madrid). If plaintiffs had
    submitted an APD, and that APD was approved by the BLM, then the BLM would have lifted
    the suspension of the pertinent lease. See PX 19 at .31C2c; Tr. 3643, 3702 (Madrid). Of course,
    it may have been difficult for plaintiffs to obtain the BLM’s blanket approval of an APD in the
    MMTA. Susan Davis, who worked for a trona mining company for eleven years and then as a
    petroleum engineer for the BLM in the Green River Management Area for seven years, Tr. 415-
    18 (Davis), testified that BLM personnel, upon receiving the APD, would have immediately
    advised the trona mining companies of the application, 
    id. at 425-26
     (Davis). Those companies,
    in turn, would have stated their objections to the APD and, in the words of Ms. Davis, “made the
    [applicant’s] life so miserable it would have been a good recommendation to have [the applicant]
    pull [its] APD.” Id.; accord 
    id. at 432
     (Davis); see also 
    id. at 3945
     (Lewis) (remarking that the
    BLM would not approve oil and gas development where active trona mining was occurring).
    Importantly, however, Ms. Davis’s testimony does not reflect the BLM’s official policy for
    processing APDs; as set forth above, upon receipt of an APD, the BLM must post a notice of the
    APD for a thirty-day period of public inspection, consult with the relevant federal surface
    management agency and other interested parties (such as the trona mining companies that would
    be affected by the oil and gas drilling described in the APD), conduct an onsite inspection, and
    then, no later than five business days after the notice period, advise the applicant regarding the
    status of the APD. 
    43 C.F.R. § 3162.3-1
    (g)-(h); 72 Fed. Reg. at 10,334. Moreover, the obstacles
    described by Ms. Davis could have been surmounted in appropriate circumstances. Indeed, the
    BLM approved five APDs submitted by Saurus for suspended leases in the MMTA, thereby
    terminating the suspensions. DX 101 at ¶¶ 40, 45. Despite the possibility of success, there is no
    evidence that plaintiffs submitted an APD for any of the leases at issue. See also Tr. 1690
    (Easley) (indicating that there were no requests to lift suspensions in the MMTA after May
    2010); id. at 3626 (Madrid) (indicating that there were no requests to lift suspensions in the
    MMTA after 2004); cf. Tr. 518-19 (Doelger) (asserting that Barlow & Haun, despite its
    partnership with Saurus in a project where Saurus submitted APDs for leases in the MMTA that
    were approved by the BLM, had no knowledge prior to this litigation that the BLM would
    consider an APD in the MMTA).
    PROCEDURAL HISTORY
    Barlow & Haun, TriContinental, and NOWIO-S filed a complaint in this court on
    November 11, 2008, alleging that the BLM, by permanently suspending all oil and gas
    operations in the MMTA, had (1) taken their interests in a number of oil and gas leases for public
    use without just compensation in violation of the Fifth Amendment to the United States
    Constitution and (2) breached both the express provisions of the leases and the implied covenant
    of good faith and fair dealing. The case was assigned to the Honorable George W. Miller, Jr.
    Defendant moved to dismiss the complaint as barred by the applicable statute of limitations
    pursuant to RCFC 12(b)(1), or, in the alternative, to dismiss the takings claim as precluded by
    the existence of contracts between the parties pursuant to RCFC 12(b)(6). Judge Miller denied
    defendant’s motions. Barlow & Haun, TriContinental, and NOWIO-S amended their complaint
    on September 30, 2010, to add a fourth plaintiff, NOWIO-V, and to remove references to six
    expired leases.
    -16-
    After the close of discovery, the parties cross-moved for summary judgment. Judge
    Miller denied the parties’ motions in an unreported August 22, 2012 order, and the case was set
    for trial. The case was subsequently reassigned to the undersigned, who held trial in Cheyenne,
    Wyoming from April 15-30 and September 16-17, 2013. During trial, the court heard testimony
    and received other evidence related to both liability and damages. The parties submitted posttrial
    briefs, and the court heard closing arguments on March 7, 2014.
    THRESHOLD ISSUES
    Before reaching the merits of plaintiffs’ claims, the court must address two threshold
    issues raised by defendant. First, defendant contends that the court lacks jurisdiction over
    plaintiffs’ amended complaint because plaintiffs’ claims accrued beyond the applicable
    limitations period. Second, defendant contends that the court cannot entertain plaintiffs’
    amended complaint because none of plaintiffs’ claims has ripened. As explained in more detail
    below, the court concludes that plaintiffs have satisfied the statute of limitations, but that the
    only ripe claim presented by plaintiffs is their claim for breach of contract. This latter
    conclusion requires the court to address a third threshold issue: whether TriContinental,
    NOWIO-S, and NOWIO-V have standing to assert the surviving breach-of-contract claim. The
    court concludes that they do not.
    I. Jurisdiction–Statute of Limitations
    Defendant’s first contention concerns the statute of limitations. To fall within the court’s
    jurisdiction, claims against the United States must be “filed within six years after such claim first
    accrues.” 
    28 U.S.C. § 2501
     (2012); see also John R. Sand & Gravel Co. v. United States, 
    552 U.S. 130
    , 133-35 (2008) (providing that the limitations period set forth in 
    28 U.S.C. § 2501
     is an
    “absolute” limit on the ability of the United States Court of Federal Claims to reach the merits of
    a claim). “A claim first accrues within the meaning of the statute of limitations when all the
    events have occurred which fix the liability of the Government and entitle the claimant to
    institute an action.” Brown Park Estates-Fairfield Dev. Co. v. United States, 
    127 F.3d 1449
    ,
    1455 (Fed. Cir. 1997) (internal quotation marks omitted).
    Defendant argues that all of plaintiffs’ claims accrued no later than May 1, 2000, the
    effective date of the indefinite suspension of the leases at issue; therefore, plaintiffs’ complaint,
    filed more than eight years later, is time barred. Notably, defendant unsuccessfully advanced
    this identical argument before Judge Miller in its motion to dismiss. See generally Barlow &
    Haun, Inc. v. United States, 
    87 Fed. Cl. 428
    , 434-38 (2009). The court generally will not reopen
    issues that have been previously decided in the same case. Messinger v. Anderson, 
    225 U.S. 436
    , 444 (1912). However, it has the power to do so in “extraordinary circumstances” when, for
    example, the prior decision is “‘clearly erroneous and would work a manifest injustice.’”
    Christianson v. Colt Indus. Operating Corp., 
    486 U.S. 800
    , 817 (1988) (quoting Arizona v.
    California, 
    460 U.S. 605
    , 618 n.8 (1983)); see also Jamesbury Corp. v. Litton Indus. Prods., Inc.,
    
    839 F.2d 1544
    , 1551 (Fed. Cir. 1988) (agreeing that a trial judge considering a motion for
    summary judgment is not bound by the summary judgment ruling of the trial judge previously
    -17-
    assigned to the case), overruled on other grounds by A.C. Aukerman Co. v. R.L. Chaides Constr.
    Co., 
    960 F.2d 1020
     (Fed. Cir. 1992) (en banc). Moreover, because the statute of limitations is a
    jurisdictional limitation, it may be raised as an issue at any time. Arbaugh v. Y & H Corp., 
    546 U.S. 500
    , 506 (2006). As explained below, there is no legal basis to modify Judge Miller’s prior
    ruling on the statute of limitations.
    A. Plaintiffs’ Claim for Breach of Contract
    The court first addresses plaintiffs’ breach-of-contract claim. Normally, in an action for
    breach of contract, a claim accrues when the breach occurs. Holmes v. United States, 
    657 F.3d 1303
    , 1317 (Fed. Cir. 2011). Judge Miller addressed the accrual date of plaintiffs’ claim for
    breach of contract in his ruling on defendant’s motion to dismiss:
    The mere announcement that the Government does not intend to perform its
    contractual obligation is a repudiation, not a breach, and that repudiation does not
    commence the running of the statute of limitations. Such a repudiation ripens into
    a breach either when the Government actually fails to honor its obligations or
    when the promisee brings suit. . . . Because the time for the Government’s
    performance and a refusal to perform (i.e., a refusal of a specific request by
    plaintiffs to mine), do[] not appear to have yet taken place, for the limited
    purposes of this motion and for the reasons stated below, the Court construes the
    indefinite suspensions of the leases as a repudiation of the plaintiff[s’] contract
    rights that did not accrue as a breach of contract until the plaintiffs chose to treat
    them as a breach by filing suit. Thus, the breach of contract claim is timely filed.
    Barlow & Haun, Inc., 87 Fed. Cl. at 436 (citations and internal quotation marks omitted); see
    also id. at 437 (“[F]or the purpose[] of considering a motion to dismiss on statute of limitations
    grounds, the Court cannot conclude that the resolution of the future state of the oil and gas leases
    came to rest on May 1, 2000, since it appears to have been in play at least through 2004.”).
    Posttrial, plaintiffs allege that the BLM breached the leases at issue by eliminating their
    right under the leases to explore for and produce oil and gas, and by imposing new conditions on
    the leases–accommodating the concerns of the trona industry and ensuring the safety of
    underground trona miners–that were not contemplated at the time that the leases were executed.
    Plaintiffs further contend that these breaches resulted from the BLM’s indefinite suspension of
    the leases–a suspension that was finalized with the issuance of the August 2008 planning
    document–and the BLM’s approval of a new resource management plan with the May 2010
    record of decision. 17 Both the indefinite suspension and the approval of a new resource
    17
    See, e.g., Pls.’ Posttrial Mem. 33 (contending that the August 2008 planning document
    prohibited oil and gas development), 35 (contending that the August 2008 planning document
    prohibited oil and gas development and that the May 2010 record of decision did not alter this
    prohibition), 41-42 (asserting that the Kemmerer Resource Management Plan approved in 1986,
    which contained no restrictions on oil and gas production, was replaced in May 2010 by a
    -18-
    management plan, plaintiffs argue, constituted repudiations of leases, which they opted to treat as
    breaches by filing suit. Defendant completely disregards plaintiffs’–and Judge Miller’s–
    treatment of the BLM’s actions as repudiations. 18 Instead, it remains steadfast in its contention
    that plaintiffs’ breach-of-contract claim is premised on the BLM’s May 1, 2000 indefinite
    suspension of the leases, and is therefore barred by the statute of limitations. Because Judge
    Miller has already rejected a May 1, 2000 accrual date, and because defendant has not pointed to
    any evidence or raised any legal argument demonstrating that Judge Miller was incorrect in
    concluding that plaintiffs’ claim for breach of contract accrued when they filed suit in 2008, the
    court will not disturb Judge Miller’s holding that plaintiffs’ breach-of-contract claim was timely
    filed.
    B. Plaintiffs’ Takings Claim
    Defendant also contends that plaintiffs’ Fifth Amendment takings claim is untimely.
    Because “[a] claimant under the Fifth Amendment must show that the United States, by some
    specific action, took a private property interest for a public use without just compensation,” a
    Fifth Amendment takings claim “accrues when that taking action occurs.” Alliance of
    Descendants of Tex. Land Grants v. United States, 
    37 F.3d 1478
    , 1481 (Fed. Cir. 1994) (citation
    omitted); accord Ingrum v. United States, 
    560 F.3d 1311
    , 1314 (Fed. Cir. 2009) (“[A] claim
    alleging a Fifth Amendment taking accrues when the act that constitutes the taking occurs.”).
    In its motion to dismiss, defendant argued that plaintiffs’ takings claim accrued no later
    than May 1, 2000, the effective date of the BLM’s indefinite suspension of the leases at issue,
    because no government action affecting plaintiffs’ rights under the leases occurred after that
    date. Plaintiffs responded by arguing that their takings claim could not have accrued before 2007
    because up until that time, the BLM continued to represent that no final decision had been made
    regarding the oil and gas and trona conflict. In his ruling, Judge Miller noted that he was unable
    to “conclude that the resolution of the future state of the oil and gas leases came to rest on May
    1, 2000, since it appears to have been in play at least through 2004.” Barlow & Haun, Inc., 87
    Fed. Cl. at 437. In other words, there had been no final decision from the BLM regarding
    plaintiffs’ ability to pursue oil and gas development under the leases. Id. at 436-37. As a result,
    Judge Miller explained, he was unable to conclude that the facts presented demonstrated that the
    resource management plan that prohibited oil and gas production until all trona mining was
    complete), 67 (characterizing the August 2008 planning document as a repudiation).
    18
    Indeed, these actions must be characterized as repudiations rather than as breaches by
    nonperformance. Compare Restatement (Second) of Contracts § 235(2) (1981) (indicating that
    nonperformance of a contractual duty when due constitutes a breach of contract), with id.
    § 250(a) (defining repudiation as a statement indicating that a party will commit a breach). The
    BLM’s suspension of the leases and subsequent adoption of a new resource management plan
    were not failures to perform obligations that had become due under the leases. Rather, these
    actions pertained to the BLM’s future performance under the leases.
    -19-
    dismissal of plaintiffs’ takings claim on statute of limitations grounds was warranted as a matter
    of law. Id. at 437.
    Posttrial, plaintiffs contend that the BLM effected a taking of the leases at issue by
    placing on them the burden of protecting the trona industry and the underground trona miners,
    thereby effectively prohibiting the oil and gas development allowed under the leases. They
    further assert that the taking occurred either in August 2008–the date they allege that the BLM’s
    indefinite suspension of the leases became a final decision–or in May 2010–the date that the
    BLM approved a new resource management plan. To avoid addressing plaintiffs’ two alternative
    accrual dates head-on, defendant mischaracterizes the accrual date alleged by plaintiffs, 19 and
    makes no attempt to explain why Judge Miller’s decision was factually or legally improper.
    Accordingly, the court will not disturb Judge Miller’s holding that plaintiffs’ takings claim was
    timely filed.
    II. Justiciability
    Even if the court possesses jurisdiction to entertain a claim, “the existence of jurisdiction
    does not confirm the court’s ability to supply relief.” Murphy v. United States, 
    993 F.2d 871
    ,
    872 (Fed. Cir. 1993). Plaintiffs must also establish that their claims are justiciable. Id.; see also
    Fisher v. United States, 
    402 F.3d 1167
    , 1176 (Fed. Cir. 2005) (panel portion) (noting that
    justiciability “encompasses a number of doctrines under which courts will decline to hear and
    decide a cause,” including the “doctrines of standing, mootness, ripeness, and political
    question”). The court’s inquiry into the justiciability of a case is distinct from its inquiry into
    whether it has jurisdiction over the case’s subject matter. See Powell v. McCormack, 
    395 U.S. 486
    , 512 (1969) (“[T]here is a significant difference between determining whether a federal court
    has ‘jurisdiction of the subject matter’ and determining whether a cause over which a court has
    subject matter jurisdiction is ‘justiciable.’” (citing Baker v. Carr, 
    369 U.S. 186
    , 198 (1962)));
    Murphy, 
    993 F.2d at 872
     (“Justiciability is distinct from jurisdiction[.]”). In other words, the
    court may find that it possesses jurisdiction over the subject matter of a claim but that the dispute
    is nevertheless nonjusticiable. 20
    19
    “Plaintiffs plainly assert that the May 2000 indefinite suspension constituted a taking.”
    Def.’s Br. 71.
    20
    In such cases, the claim should be dismissed as nonjusticiable and not for lack of
    subject matter jurisdiction. See, e.g., Baker, 
    369 U.S. at 196
     (holding that a case that is
    “unsuited to judicial inquiry or adjustment” should be dismissed for “a failure to state a
    justiciable cause of action” and not for “a lack of jurisdiction of the subject matter” (internal
    quotation marks omitted)); Oryszak v. Sullivan, 
    576 F.3d 522
    , 526-27 (D.C. Cir. 2009)
    (Ginsburg, J., concurring) (noting that when “a plaintiff makes a claim that is not justiciable . . . a
    court should dismiss the case for failure to state a claim” and that “it is important to distinguish
    among failure to state a claim, a claim that is not justiciable, and a claim over which the court
    lacks subject matter jurisdiction”); F. Alderete Gen. Contractors, Inc. v. United States, 
    715 F.2d 1476
    , 1480 (Fed. Cir. 1983) (reciting “the long-standing rule in the Federal courts that
    jurisdiction is determined at the time the suit is filed and, after vesting, cannot be ousted by
    -20-
    A. Ripeness
    A claim is not ripe for judicial review when it is contingent upon future events that may
    or may not occur. Thomas v. Union Carbide Agric. Prods. Co., 
    473 U.S. 568
    , 580-81 (1985).
    The ripeness doctrine “prevent[s] the courts, through avoidance of premature adjudication, from
    entangling themselves in abstract disagreements over administrative policies, and also to protect
    the agencies from judicial interference until an administrative decision has been formalized and
    its effects felt in a concrete way by the challenging parties.” Abbott Labs. v. Gardner, 
    387 U.S. 136
    , 148-49 (1967), overruled on other grounds by Califano v. Sanders, 
    430 U.S. 99
     (1977). The
    doctrine generally derives “from Article III limitations on judicial power and from prudential
    reasons for refusing to exercise jurisdiction.” Reno v. Catholic Soc. Servs., Inc., 
    509 U.S. 43
    , 57
    n.18 (1993). However, when “[t]he ripeness inquiry concerns whether [a plaintiff] ripened his
    regulatory takings claim by exhausting his administrative remedies,” the inquiry is prudential in
    nature. McGuire v. United States, 
    707 F.3d 1351
    , 1358-59 (Fed. Cir. 2013) (citing Suitum v.
    Tahoe Reg’l Planning Agency, 
    520 U.S. 725
    , 734 (1997); Zipes v. Trans World Airlines, Inc.,
    
    455 U.S. 385
    , 393 (1982)).
    1. Plaintiffs’ Claim for Breach of Contract
    Defendant first contends that plaintiffs’ breach-of-contract claim is not ripe for
    adjudication. However, as noted by plaintiffs, all of the case law cited by defendant in support of
    its contention relates to when a takings claim ripens. The standard is different for breach-of-
    contract claims, which ripen when the breach occurs because that is the time when the
    nonbreaching party is entitled to bring suit. See Nager Elec. Co. v. United States, 
    368 F.2d 847
    ,
    851-52 (Ct. Cl. 1966) (“For contract cases, . . . normally the cause of action first accrues, and the
    statute begins to run, when the work is completed or the items delivered (and accepted), or the
    services rendered, or (if the contract was never completed) when the breach became total. That
    was considered to be the time when the contractor could ordinarily demand his money and bring
    his suit if payment was not made.”). Moreover, where a party has repudiated a contract, a claim
    for breach of contract ripens when performance becomes due or when the other party to the
    contract opts to treat the repudiation as a present total breach. See 
    id.
     (indicating that where “the
    contract was never completed,” a party could sue for breach of contract “when the breach
    became total”); Franconia Assocs. v. United States, 
    536 U.S. 129
    , 143 (2002) (noting that “a
    repudiation ripens into a breach” at the time performance is due or when the nonrepudiating
    party chooses to treat the repudiation as a breach); Plaintiffs in Winstar-Related Cases v. United
    States, 
    37 Fed. Cl. 174
     (1997) (holding that certain plaintiffs’ contract claims did not ripen at the
    time that the relevant statute was enacted because the statutory enactment constituted an
    subsequent events, including action by the parties” (emphasis added)); see also Kontrick v. Ryan,
    
    540 U.S. 443
    , 455 (2004) (“Clarity would be facilitated if courts and litigants used the label
    ‘jurisdictional’ . . . only for prescriptions delineating the classes of cases (subject-matter
    jurisdiction) and the persons (personal jurisdiction) falling within a court’s adjudicatory
    authority.”).
    -21-
    anticipatory breach), aff’d, Ariadne Fin. Servs. Pty. Ltd. v. United States, 
    133 F.3d 874
     (Fed. Cir.
    1998).
    As noted above, plaintiffs allege that the BLM repudiated the leases at issue by
    suspending the leases indefinitely and by issuing a new resource management plan, but that those
    repudiations did not constitute breaches until they chose to treat them as present breaches when
    they filed suit. Under the applicable case law, plaintiffs’ claim for breach of contract was ripe as
    of the date they filed suit.
    2. Plaintiffs’ Takings Claim
    The ripeness analysis for plaintiffs’ takings claim is not as straightforward. Defendant
    argues that plaintiffs’ takings claim is not ripe for adjudication because plaintiffs have not
    availed themselves of the BLM’s regulatory process for obtaining permission to pursue oil and
    gas development under the leases at issue. “[A] claim that the application of government
    regulations effects a taking of a property interest is not ripe until the government entity charged
    with implementing the regulations has reached a final decision regarding the application of the
    regulations to the property at issue.” Williamson Cnty. Reg’l Planning Comm’n v. Hamilton
    Bank of Johnson City, 
    473 U.S. 172
    , 186 (1985); accord Palazzolo v. Rhode Island, 
    533 U.S. 606
    , 620-21 (2001) (“[A] landowner may not establish a taking before a land-use authority has
    the opportunity, using its own reasonable procedures, to decide and explain the reach of a
    challenged regulation. Under our ripeness rules a takings claim based on a law or regulation
    which is alleged to go too far in burdening property depends upon the landowner’s first having
    followed reasonable and necessary steps to allow regulatory agencies to exercise their full
    discretion in considering development plans for the property, including the opportunity to grant
    any variances or waivers allowed by law.”); MacDonald, Sommer & Frates v. Yolo Cnty., 
    477 U.S. 340
    , 348 (1986) (“It follows from the nature of a regulatory takings claim that an essential
    prerequisite to its assertion is a final and authoritative determination of the type and intensity of
    development legally permitted on the subject property.”); Boise Cascade Corp. v. United States,
    
    296 F.3d 1339
    , 1351 (Fed. Cir. 2002) (explaining that “[t]he rule that a taking does not ripen
    unless a permit is applied for and denied” has been “consistently followed”). For an agency
    action to be final, two conditions must be met: “First, the action must mark the ‘consummation’
    of the agency’s decisionmaking process–it must not be of a merely tentative or interlocutory
    nature. And second, the action must be one by which ‘rights or obligations have been
    determined,’ or from which ‘legal consequences will flow.’” Bennett v. Spear, 
    520 U.S. 154
    ,
    177-78 (1997), quoted in NSK Ltd. v. United States, 
    510 F.3d 1375
    , 1385 (Fed. Cir. 2007); see
    also Cooley v. United States, 
    324 F.3d 1297
    , 1302 (Fed. Cir. 2003) (“A permit denial is final
    when the applicant has no appeal mechanism available and the denial is based on an unchanging
    fact.”); 
    id. at 1303
     (noting that the finality of a permit denial was not altered by the government’s
    “courteous, but ineffectual invitation” to the plaintiff “to submit more information if it wished to
    continue to pursue a permit”). However, an agency’s “purposeful bureaucratic delay and
    obfuscation” in the permitting process will not prevent a court from finding the existence of a
    final decision. Bayou des Familles Dev. Corp. v. United States, 
    130 F.3d 1034
    , 1038 (Fed. Cir.
    1997); accord Palazzolo, 
    533 U.S. at 621
     (“Government authorities . . . may not burden property
    by imposition of repetitive or unfair land-use procedures in order to avoid a final decision.”).
    -22-
    In the regulatory takings context, a final decision is necessary because it establishes, with
    sufficient certainty, what limitations, if any, the agency will place on the property. Morris v.
    United States, 
    392 F.3d 1372
    , 1376 (Fed. Cir. 2004); accord Palazzolo, 
    533 U.S. at 621
     (“As a
    general rule, until the[] ordinary [administrative] processes have been followed the extent of the
    restriction on property is not known and a regulatory taking has not yet been established.”);
    MacDonald, 
    477 U.S. at 348
     (“A court cannot determine whether a regulation has gone ‘too far’
    unless it knows how far the regulation goes.”); Williamson, 
    473 U.S. at 191
     (remarking that “the
    factors of particular significance” in the regulatory takings inquiry “cannot be evaluated until the
    administrative agency has arrived at a final, definitive position regarding how it will apply the
    regulations at issue to the particular land in question”). Thus, “when an agency provides
    procedures for obtaining a final decision, a takings claim is unlikely to be ripe until the property
    owner complies with those procedures.” Morris, 
    392 F.3d at 1376
    ; see also United States v.
    Riverside Bayview Homes, Inc., 
    474 U.S. 121
    , 127 (1985) (“A requirement that a person obtain
    a permit before engaging in a certain use of his or her property does not itself ‘take’ the property
    in any sense: after all, the very existence of a permit system implies that permission may be
    granted, leaving the landowner free to use the property as desired.”).
    There is no dispute in this case that a permitting process exists and that under the leases
    at issue, plaintiffs cannot pursue oil and gas development without first obtaining a permit.
    Indeed, the permitting process–which entails the filing, and the BLM’s approval, of an APD
    prior to exploration and development–is longstanding and well known by the oil and gas
    industry. It is also undisputed that plaintiffs, who were keenly aware of the permitting process,
    never took the first step to obtain approval–the submission of an APD to the BLM–to develop
    any of the leases. Because plaintiffs never sought the required permit, the BLM has not had the
    opportunity to review a complete APD, post the APD for the thirty-day period of public
    inspection, and then render a final decision demonstrating how it would apply its land use
    regulations–i.e., the relevant resource management plan–to the leases. In the absence of such a
    final decision, plaintiffs’ takings claim is unripe.
    Plaintiffs seek to avoid this result by arguing that their takings claim is ripe because they
    have established the futility of submitting an APD. The futility of complying with applicable
    administrative procedures has been recognized as an exception to the ripeness doctrine in takings
    cases. See, e.g., Palazzolo, 
    533 U.S. at 622
     (stating that the “[r]ipeness doctrine does not require
    a landowner to submit applications for their own sake” and explaining that applications are
    required only when “there is uncertainty as to the land’s permitted use”); The Stearns Co. v.
    United States, 
    396 F.3d 1354
    , 1358 (Fed. Cir. 2005) (holding that where there are two
    mechanisms by which a property owner may obtain a permit to conduct surface mining and the
    property owner only avails itself of one of those mechanisms, the property owner’s “decision to
    avoid the remaining administrative procedures can[not] be excused as futile”); Cooley, 
    324 F.3d at 1302
     (“[A] claimant can show its claim was ripe with sufficient evidence of the futility of
    further pursuit of a permit through the administrative process.”); Benchmark Res. Corp. v.
    United States, 
    74 Fed. Cl. 458
    , 469 (2006) (“[P]laintiffs have not provided evidence sufficient to
    demonstrate futility of application to the [Office of Surface Mining Reclamation and
    Enforcement] regarding coal mining operations over the whole Property.”). In this case,
    -23-
    plaintiffs argue that in the August 2008 planning document, as approved in the May 2010 record
    of decision, the BLM made it clear that there would be no oil and gas development in the
    MMTA until all trona mining had been completed. However, as explained below, plaintiffs’
    interpretation of the two documents is too narrow. As a result, the futility exception to the
    ripeness requirement does not provide them with relief.
    According to precedent binding on this court, a plaintiff cannot invoke the futility
    exception to the ripeness requirement unless it has already availed itself of the relevant agency’s
    regulatory process. In Palazzolo, the United States Supreme Court held that when an “agency
    charged with enforcing a challenged land-use regulation entertains an application from an owner
    and its denial of the application makes clear the extent of development permitted,” and when the
    owner has otherwise complied with the pertinent regulations, “federal ripeness rules do not
    require the submission of further and futile applications with other agencies.” 
    533 U.S. at
    625-
    26. Similarly, the United States Court of Appeals for the Federal Circuit (“Federal Circuit”) has
    held that “the futility exception simply serves ‘to protect property owners from being required to
    submit multiple applications when the manner in which the first application was rejected makes
    it clear that no project will be approved.’” Howard W. Heck, & Assocs., Inc. v. United States,
    
    134 F.3d 1468
    , 1472 (Fed. Cir. 1998) (quoting S. Pac. Transp. Co. v. City of L.A., 
    922 F.2d 498
    ,
    504 (9th Cir. 1990) (emphasis added)); accord McGuire, 707 F.3d at 1361-62; Estate of Hage v.
    United States, 
    687 F.3d 1281
    , 1287-88 (Fed. Cir. 2012) (rejecting the plaintiff’s contention that
    applying for a special use permit to maintain its irrigation ditches would be futile because,
    among other reasons, the plaintiff’s only permit-related disputes with the Forest Service
    concerned its grazing permits, not its special use permits); Morris, 
    392 F.3d at 1376
     (quoting
    Heck, and explaining that if “further administrative process could reasonably result in a more
    definitive statement of the impact of the regulation, the property owner is generally required to
    pursue that avenue of relief before bringing a takings claim,” but “where the agency’s decision
    makes clear that pursuing remaining administrative remedies will not result in a differing
    outcome, the remaining remedies are futile and the impact of the regulation on the use of the
    property is reasonably certain”); George E. Warren Corp. v. United States, 
    341 F.3d 1348
    , 1351
    (Fed. Cir. 2003) (“Futility occurs where the filing party already knows that the agency would
    deny its claim because the agency has already done so.”); Cooley, 
    324 F.3d at 1302-03
     (“After a
    final decision, an applicant need not submit further applications. . . . Submitting a new
    application is futile when unchanging facts and applicable law preclude a permit.”). The only
    exception to the requirement that an application be submitted prior to asserting futility in a
    judicial proceeding, the Federal Circuit has explained, is when “the administrative entity has no
    discretion regarding the regulation’s applicability and its only option is enforcement” because “in
    such circumstances, no uncertainty remains regarding the impact of the regulation, certainty
    being the basis for the ripeness requirement.” Greenbrier v. United States, 
    193 F.3d 1348
    , 1359
    (Fed. Cir. 1999) (citation omitted); accord Palazzolo, 
    533 U.S. at 620
     (“While a landowner must
    give a land-use authority an opportunity to exercise its discretion, once it becomes clear that the
    agency lacks the discretion to permit any development, or the permissible uses of the property
    are known to a reasonable degree of certainty, a takings claim is likely to have ripened.”);
    Anaheim Gardens v. United States, 
    444 F.3d 1309
    , 1316 (Fed. Cir. 2006) (“[A] claimant need
    not obtain a final decision if the agency lacks any discretion to avoid the allegedly offending
    regulatory action, or if the record shows, with a reasonable degree of certainty, the remaining
    -24-
    permissible uses of the property after the regulatory action because there can be no variance from
    the facial requirements of the applicable regulation.”).
    Here, the BLM retained the discretion to allow oil and gas development in appropriate
    circumstances. In its August 2008 planning document, the BLM noted that an APD must be
    submitted to pursue oil and gas development under a federal lease. It further explained that it
    would recognize all valid existing rights, that existing leases would not be affected by the new
    resource management plan, and that it would use site-specific conditions of approval to mitigate
    the adverse effects of oil and gas development. The BLM did note that all existing oil and gas
    leases in the MMTA were suspended and that its preferred course of action was to administer the
    KSLA exclusively for trona mining. However, the suspensions benefitted leaseholders by
    prolonging the life of the leases and excusing their payment obligations. And, the BLM’s
    preferred alternative reflected its recognition that existing leases could not be unilaterally altered
    by a new resource management plan–the BLM stated that it would not issue new leases until the
    safety of underground trona miners could be ensured, but did not affirmatively or impliedly state
    that it would deny APDs for existing leases.
    The BLM’s May 2010 record of decision was more succinct. In that document, the BLM
    formally adopted its preferred alternative, which provided that existing oil and gas leases in the
    MMTA were currently suspended, and that new leasing would not be permitted until it was
    certain that the safety of underground miners would not be compromised. 21 It also reiterated that
    it would recognize valid existing rights.
    Taken together, the August 2008 and May 2010 planning documents reflect the BLM’s
    intent to honor the rights of existing leaseholders to develop their leases, and that the BLM’s
    approval of an APD, or any conditions that the BLM appended to a drilling permit, would be
    based on a site-specific analysis. Of course, merely because the BLM has the discretion to
    approve oil and gas development in the MMTA under the new resource management plan does
    not mean that it will ultimately choose to exercise that discretion by approving an APD. But, so
    long as the BLM retained the discretion to approve an APD, plaintiffs were required to submit
    one. 22 See Palazzolo, 
    533 U.S. at 620
    ; Anaheim Gardens, 444 F.3d at 1316; Greenbrier, 193
    21
    Plaintiffs do not and cannot argue that any of the leases at issue constitute “new”
    leases.
    22
    It bears noting that the evidence in the record reflects that the BLM actually approved
    APDs in the MMTA during the period in which all oil and gas leases were suspended. As
    described above, in May 2000, the BLM approved APDs, and lifted the suspensions of the
    pertinent leases, to allow Saurus to pursue shallow gas development in the MMTA. Given that
    the status quo has not changed since May 2000 (existing oil and gas leases in the MMTA remain
    suspended), the fact that the BLM was willing to entertain and approve APDs in the MMTA
    supports the contention that the BLM has the discretion to allow oil and gas development in the
    MMTA. See also Heck, 
    134 F.3d at 1468
     (noting that a futility argument can be rejected when
    there is evidence that an agency has previously granted permits).
    -25-
    F.3d at 1359. Because plaintiffs have not submitted an APD, they cannot invoke the futility
    exception to the ripeness requirement.
    In sum, plaintiffs’ failure to submit an APD is fatal to both their ripeness argument in
    general, and their attempt to invoke the futility exception to the ripeness requirement more
    specifically. Accordingly, plaintiffs’ takings claim is not ripe and must be dismissed.
    B. Standing
    As a result of the court’s conclusion that the only claim ripe for adjudication is plaintiffs’
    claim for breach of contract, the court must address whether all four plaintiffs have standing to
    assert such a claim. The Tucker Act explicitly recognizes that an express or implied contract
    with the United States can provide the basis for jurisdiction in this court. 
    28 U.S.C. § 1491
    (a)(1).
    However, for a plaintiff to maintain a claim for breach of contract under the Tucker Act, “there
    must be privity of contract between the plaintiff and the United States.” 23 Cienega Gardens v.
    United States, 
    194 F.3d 1231
    , 1239 (Fed. Cir. 1998); accord First Annapolis Bancorp, Inc. v.
    United States, 
    644 F.3d 1367
    , 1373 (Fed. Cir. 2011) (“A plaintiff must be in privity with the
    United States to have standing to sue the sovereign on a contract claim.”).
    The evidence presented at trial reflects that Barlow & Haun, the current record title
    holder of the leases at issue, was the only plaintiff in privity with the United States when the
    breach-of-contract claim accrued in 2008. The last date that TriContinental possessed record
    title interest in any of the leases at issue was June 1, 2000, well outside of the six-year limitations
    period. And, there is no evidence that NOWIO-S and NOWIO-V have, or ever had, a
    contractual relationship with the United States with respect to any of the leases at issue.
    Accordingly, TriContinental, NOWIO-S, and NOWIO-V lack standing to sue for breach of
    contract and must be dismissed from this action.
    BREACH OF CONTRACT
    Having disposed of the threshold issues, the court turns to the merits of Barlow & Haun’s
    sole surviving claim–its claim for breach of contract. As noted above, Barlow & Haun alleges
    that the BLM breached the leases at issue by eliminating its right under the leases to explore for
    and produce oil and gas, and by imposing new conditions on the leases–accommodating the
    concerns of the trona industry and ensuring the safety of underground trona miners–that were not
    23
    There are several exceptions to this general rule. See First Hartford Corp. Pension
    Plan & Trust v. United States, 
    194 F.3d 1279
    , 1289 (Fed. Cir. 1999). These exceptions include
    suits by intended third-party beneficiaries, suits by subcontractors “by means of a pass-through
    suit when the prime contractor is liable to the subcontractor for the subcontractor’s damages,”
    and suits by government contract sureties “for funds improperly disbursed to a prime contractor.”
    
    Id.
     “[T]he common thread that unites these exceptions is that the party standing outside of
    privity by contractual obligation stands in the shoes of a party within privity.” 
    Id.
     None of these
    exceptions is applicable in this case.
    -26-
    contemplated at the time that the leases were executed. 24 These allegations are premised on the
    BLM’s indefinite suspension of the leases, which, according to Barlow & Haun, was finalized
    with the issuance of the August 2008 planning document, and the BLM’s approval of a new
    resource management plan in May 2010. Each of the BLM’s actions, Barlow & Haun contends,
    constituted a repudiation of the leases.
    “To recover for breach of contract, a party must allege and establish: (1) a valid contract
    between the parties, (2) an obligation or duty arising out of the contract, (3) a breach of that duty,
    and (4) damages caused by the breach.” San Carlos Irrigation & Drainage Dist. v. United States,
    
    877 F.2d 957
    , 959 (Fed. Cir. 1989); see also Trauma Serv. Grp. v. United States, 
    104 F.3d 1321
    ,
    1325 (Fed. Cir. 1997) (“To prevail, [plaintiff] must allege facts showing both the formation of an
    express contract and its breach.”). The parties agree that the leases at issue constitute valid
    contracts between Barlow & Haun and the United States. However, they have not reached a
    similar consensus regarding the remaining elements of Barlow & Haun’s breach claim.
    I. The BLM’s Contractual Duties
    Implicit in Barlow & Haun’s claim for breach of contract is the assumption that the BLM
    possessed duties under the leases at issue that it repudiated. Although Barlow & Haun has the
    burden to demonstrate all elements of its claim, San Carlos Irrigation & Drainage Dist., 
    877 F.2d at 959
    , it does not identify the precise duties that the BLM repudiated. Nevertheless, based on its
    allegations that the BLM both extinguished, and imposed new conditions on, its right to explore
    24
    In their amended complaint, plaintiffs allege that the BLM breached the leases at
    issue by violating the implied covenant of good faith. Am. Compl. ¶ 28. However, the only
    evidence regarding good faith elicited by plaintiffs at trial concerned whether the BLM acted in
    good faith by issuing the leases in the first place–an issue of contract formation, not contract
    performance. See Tr. 430-35 (Davis), cited in Pl.’s Posttrial Mem. 43. Moreover, in their
    pretrial and posttrial memoranda, plaintiffs fail to discuss, much less cite, the three recent,
    significant decisions from the Federal Circuit addressing the implied duty of good faith and fair
    dealing: Precision Pine & Timber, Inc. v. United States, 
    596 F.3d 817
     (Fed. Cir. 2010); Scott
    Timber Co. v. United States, 
    692 F.3d 1365
     (Fed. Cir. 2012); and Metcalf Construction Co. v.
    United States, 
    742 F.3d 984
     (Fed. Cir. 2014). Thus, the court concludes that plaintiffs
    abandoned their allegation that the BLM breached the covenant of good faith. See RCFC App.
    A ¶ 14(a)(2) (requiring a plaintiff’s pretrial memorandum to include “a statement of the issues of
    fact and law to be resolved by the court,” and providing that “[t]he issues should be set forth in
    sufficient detail to enable the court to resolve the case in its entirety by addressing each of the
    issues listed”); Palumbo v. United States, 
    113 F. Supp. 450
    , 453 (Ct. Cl. 1953) (explaining that
    the court would only address “claims upon which evidence was introduced” at trial); Thermalon
    Indus., Ltd. v. United States, 
    51 Fed. Cl. 464
    , 470 n.3 (2002) (“Plaintiff has abandoned its claim
    for consequential damages, presenting no evidence at trial as to these damages and making no
    mention of them in its post-trial brief.”); see also Rosco, Inc. v. Mirror Lite Co., 
    304 F.3d 1373
    ,
    1382 (Fed. Cir. 2002) (agreeing that a claim that was addressed in a posttrial brief had not been
    abandoned).
    -27-
    for and produce oil and gas, it is apparent that there are two main contractual duties implicated in
    its claim: (1) the BLM’s obligation to provide Barlow & Haun with the exclusive right to
    explore for and develop oil and gas on the lands described in the leases and (2) the BLM’s
    obligation to consider Barlow & Haun’s APDs pursuant to the pertinent statutes and regulations.
    The court therefore turns to Barlow & Haun’s contention that the BLM breached the leases by
    repudiating these obligations.
    II. The BLM Did Not Repudiate Its Contractual Obligations
    As noted above, Barlow & Haun contends that the BLM anticipatorily repudiated the
    leases at issue by finalizing the indefinite suspension of the leases in its August 2008 planning
    document and by approving a new resource management plan in May 2010. An anticipatory
    repudiation occurs when a party renounces a contractual duty before performance is due.
    Franconia Assocs., 
    536 U.S. at 143
    . The renunciation often takes the form of a statement by a
    contracting party indicating that it will commit a breach that would give the other contracting
    party a claim for damages for total breach. See 
    id.
     (citing Restatement (Second) of Contracts
    § 250); Mobil Oil Exploration & Producing Se., Inc. v. United States, 
    530 U.S. 604
    , 608 (2000).
    “A mere assertion that the party will be unable, or will refuse to perform his contract is not
    sufficient; it must be a distinct and unequivocal absolute refusal to perform the promise . . . .”
    Smoot’s Case, 
    82 U.S. 36
    , 48 (1872) (internal quotation marks omitted); accord Dow Chem. Co.
    v. United States, 
    226 F.3d 1334
    , 1344 (Fed. Cir. 2000) (holding that the repudiating party’s
    refusal to perform its duties under the contract must “communicate that refusal distinctly and
    unqualifiedly to the other party”). And, the breach must be total, i.e., one “that ‘so substantially
    impairs the value of the contract to the injured party at the time of the breach that it is just in the
    circumstances to allow him to recover damages based on all his remaining rights to
    performance.’” Mobil Oil, 
    530 U.S. at 608
     (quoting Restatement (Second) of Contracts § 243).
    As Barlow & Haun notes, the August 2008 planning document, which contained the
    proposed resource management plan and the final environmental impact statement, indicated that
    the BLM’s “preferred course of action [was] to administer the [planning] area exclusively for
    trona extraction until conventional trona mining [was] complete.” JX 22 at 4-31. This
    statement, Barlow & Haun contends, constitutes the BLM’s definitive refusal to honor the
    twenty-six leases at issue. There are two problems with Barlow & Haun’s contention. First, the
    quoted statement reflects the BLM’s “preferred,” not its chosen, course of action. It therefore
    could not constitute an unequivocal refusal to perform.
    Second, and more importantly, the August 2008 planning document contains multiple
    statements reflecting the BLM’s intent to honor existing oil and gas leases. For example, the
    BLM represented that under the proposed resource management plan, it would “recognize valid
    existing rights.” Id. at 1-13; accord id. at 2-5. And, the BLM indicated that lessees could pursue
    the development of oil and gas on their leaseholds by submitting an APD, further explaining:
    When an oil and gas lease is issued, it constitutes a valid existing right;
    BLM cannot unilaterally change the terms and conditions of the lease. Existing
    leases would not be affected by decisions resulting from this RMP that designate
    -28-
    areas administratively unavailable for oil and gas leasing. New restrictions such
    as controlled surface use or timing restrictions in the form of stipulations could
    not be added to an existing lease. Existing leases would not be terminated until
    the lease expires. However, based on site or project-specific environmental
    analysis, [conditions of approval] could be applied at the APD and Sundry Notice
    stage, and at subsequent development stages, to mitigate potential impacts from
    oil and gas operations within existing lease areas, providing the leaseholder’s
    right to develop the lease remains intact.
    Id. at 3-25. These statements certainly cannot be characterized as an absolute refusal to perform
    contractual duties. Rather, they support the BLM’s position that it would perform its obligations
    under existing leases by reviewing APDs submitted by its lessees. Therefore, the August 2008
    planning document cannot constitute a repudiation of Barlow & Haun’s leases.
    In the May 2010 record of decision, the BLM approved the resource management plan
    that it proposed in the August 2008 planning document. Although it noted that “[e]xisting oil
    and gas leases are suspended in the MMTA” and that it would not issue new leases “until the oil
    and gas resource can be recovered without compromising the safety of underground miners,” JX
    23 at 2-26, the BLM made it clear that it would recognize “valid existing rights,” id. at 2-15.
    The May 2010 record of decision does not contain any statement that could be characterized as
    BLM refusing to perform its obligations under existing oil and gas leases. Rather, the document
    reflects the exact opposite. Therefore, it cannot constitute a repudiation of Barlow & Haun’s
    leases.
    Barlow & Haun’s contention that the BLM repudiated the leases at issue is based solely
    on the statements made by the BLM in the August 2008 and May 2010 planning documents.
    Barlow & Haun neither alleges, nor elicited any evidence at trial, that the BLM otherwise
    advised it, either through direct communications or by adopting new regulations, that it would
    not perform its contractual obligations. Indeed, the trial record reflects that Barlow & Haun
    remained entitled to pursue oil and gas development under its leases by submitting an APD, and
    that the BLM remained committed to reviewing APDs pursuant to the process set forth in its
    regulations. Moreover, those regulations, which were incorporated into all of the leases at issue,
    allow the BLM to condition its approval of an APD on the applicant taking measures to
    minimize adverse impacts on other resources, uses, and users. Thus, any representation by the
    BLM that it would consider the impact that oil and gas drilling at a particular site would have on
    trona mining and miners could not constitute a repudiation of the leases. More than that is
    needed.
    III. Absent a Repudiation, There Is No Valid Claim for Breach of Contract
    As noted above, Barlow & Haun does not allege that the BLM failed to perform under
    the leases at issue. Rather, Barlow & Haun’s claim for breach of contract is premised on the
    BLM’s purported repudiation of the leases, which it chose to treat as a breach by filing suit.
    Barlow & Haun’s approach was born of necessity. The BLM had not actually failed to perform a
    presently due contractual obligation prior to plaintiffs filing suit. Further, a claim that the
    -29-
    indefinite suspension of the leases themselves constituted a failure to perform (rather than a
    repudiation) would likely run afoul of the statute of limitations because the suspension
    commenced more than six years before plaintiffs filed suit. And, a claim that the imposition of
    new conditions on the leases constituted a failure to perform (rather than a repudiation) is
    problematic because the BLM possesses the authority to impose conditions on development.
    Lacking a valid claim for breach of contract by nonperformance, Barlow & Haun was left
    with its allegations that the BLM breached the leases by repudiating them. However, Barlow &
    Haun has not established that the BLM repudiated the leases. It therefore cannot prevail on its
    breach-of-contract claim. Consequently, there is no need for the court to consider the evidence
    adduced at trial regarding damages.
    CONCLUSION
    Barlow & Haun undoubtedly faces an uphill battle in developing the leases at issue in this
    case. The BLM has clearly decided to prioritize the recovery of trona over the recovery of oil
    and gas in the MMTA. However, the law is clear that the submission of an APD is a necessary
    prerequisite to a successful takings claim and that an unequivocal refusal to review an APD–
    whether before or after its submission–is a necessary prerequisite to a claim for breach of
    contract by repudiation. Barlow & Haun has failed to make the required showings, compelling
    the court to find in defendant’s favor.
    For the reasons stated, the court DISMISSES plaintiffs’ takings claim as unripe. In
    addition, the court DISMISSES the breach-of-contract claim asserted by TriContinental,
    NOWIO-S, and NOWIO-V for lack of standing. And, the court DISMISSES Barlow & Haun’s
    claim for breach of contract WITH PREJUDICE. No costs. The clerk is directed to enter
    judgment accordingly.
    IT IS SO ORDERED.
    s/ Margaret M. Sweeney
    MARGARET M. SWEENEY
    Judge
    -30-
    APPENDIX
    Interest First Acquired                    Interest Last Acquired
    % of
    Record       Date                                              Date
    Title      Interest                                         Interest
    Interest     First                    % of Record Title        Last
    Lease No.       Owner*     Owned      Acquired ** Owner*          Interest Owned        Acquired
    B&H        75%                     8/1/2003
    WYW84463          B&H       75%         4/1/2001
    B&H        100%                    9/1/2008
    WYW101764         TriCon    100%        3/1/1988       B&H        100%                    7/1/2003
    WYW101979         TriCon    100%        3/1/1988       B&H        100%                    7/1/2003
    B&H        50%                     6/1/2000
    WYW103501         TriCon    100%        5/1/1988
    B&H        100%                    8/1/2003
    WYW104183         B&H       100%        6/1/1987       B&H        100%                    7/1/2003
    WYW104210         TriCon    100%        5/1/1988       B&H        100%                    7/1/2003
    WYW105017         TriCon    100%        8/1/1988       B&H        100%                    7/1/2003
    WYW105484         B&H       100%        9/1/1987       B&H        100%                    7/1/2003
    WYW108093         B&H       100%        4/1/2001       B&H        100%                    7/1/2003
    WYW108098         B&H       100%        8/1/1988       B&H        100%                    7/1/2003
    WYW108889         TriCon    100%        8/1/1988       B&H        100%                    7/1/2003
    WYW108891         TriCon    100%        9/1/1988       B&H        100%                    7/1/2003
    B&H        100% of sections 4,     7/1/2003
    WYW113112         TriCon    100%        10/1/1990
    8, & 10
    *
    “B&H” is Barlow & Haun and “TriCon” is TriContinental.
    **
    “The Date Interest First Acquired” is the date that one of the plaintiffs first obtained an
    interest in the specified lease. See Jt. Stip. ¶¶ 60-81. Ownership of most of these leases
    subsequently changed hands on one or more occasions before Barlow & Haun reacquired them
    on the date set forth in the final column. Id.
    -31-
    B&H      50% of section 34    7/1/2003
    B&H      100% of section 34   9/1/2008
    WYW113412      TriCon    100%      10/1/1988     B&H      100%                 7/1/2003
    WYW114025      TriCon    100%      11/1/1988     B&H      100%                 7/1/2003
    WYW114036      TriCon    100%      11/1/1988     B&H      100%                 7/1/2003
    WYW114891      TriCon    100%      6/1/1989      B&H      100%                 7/1/2003
    WYW117039      TriCon    100%      3/1/1990      B&H      100%                 7/1/2003
    WYW121393      B&H       100%      9/1/2008      B&H      100%                 9/1/2008
    WYW121394      B&H       100%      9/1/2008      B&H      100%                 9/1/2008
    WYW121395      B&H       100%      9/1/2008      B&H      100%                 9/1/2008
    WYW121402      B&H       100%      9/1/2008      B&H      100%                 9/1/2008
    WYW122215      B&H       100%      4/1/2001      B&H      100%                 7/1/2003 †
    WYW122863      B&H       100%      9/1/2008      B&H      100%                 9/1/2008
    WYW123810      B&H       100%      4/1/2001      B&H      100%                 7/1/2003
    WYW149082      B&H       100%      2/1/1999      B&H      100%                 2/1/1999
    †
    Lease 122215 expired under its own terms on November 30, 2012. Tr. 3442 (Weaver).
    -32-
    

Document Info

Docket Number: 1:08-cv-00847

Citation Numbers: 118 Fed. Cl. 597, 183 Oil & Gas Rep. 487, 2014 U.S. Claims LEXIS 1028, 2014 WL 4802941

Judges: Margaret M. Sweeney

Filed Date: 9/26/2014

Precedential Status: Precedential

Modified Date: 10/19/2024

Authorities (42)

Califano v. Sanders , 97 S. Ct. 980 ( 1977 )

Baker v. Carr , 82 S. Ct. 691 ( 1962 )

Reno v. Catholic Social Services, Inc. , 113 S. Ct. 2485 ( 1993 )

Franconia Associates v. United States , 122 S. Ct. 1993 ( 2002 )

The Stearns Company, Ltd. v. United States , 396 F.3d 1354 ( 2005 )

Ingrum v. United States , 560 F.3d 1311 ( 2009 )

Palumbo v. United States , 113 F. Supp. 450 ( 1953 )

cienega-gardens-claremont-village-commons-covina-west-apartments-del-amo , 194 F.3d 1231 ( 1998 )

Nager Electric Company, Inc. And Keystone Engineering ... , 368 F.2d 847 ( 1966 )

Thomas v. Union Carbide Agricultural Products Co. , 105 S. Ct. 3325 ( 1985 )

Dow Chemical Company, Plaintiff/cross-Appellant v. United ... , 226 F.3d 1334 ( 2000 )

F. Alderete General Contractors, Inc. v. United States , 715 F.2d 1476 ( 1983 )

Ariadne Financial Services Pty. Ltd. And Memvale Pty. Ltd. ... , 133 F.3d 874 ( 1998 )

Holmes v. United States , 657 F.3d 1303 ( 2011 )

bayou-des-familles-development-corporation-coast-quality-construction , 130 F.3d 1034 ( 1997 )

First Annapolis Bancorp, Inc. v. United States , 644 F.3d 1367 ( 2011 )

Bennett v. Spear , 117 S. Ct. 1154 ( 1997 )

Nsk Ltd. v. United States , 510 F.3d 1375 ( 2007 )

San Carlos Irrigation and Drainage District v. The United ... , 877 F.2d 957 ( 1989 )

Boise Cascade Corporation v. United States , 296 F.3d 1339 ( 2002 )

View All Authorities »