Pioneer Reserve, LLC v. United States ( 2014 )


Menu:
  •      In the United States Court of Federal Claims
    No. 14-376C
    (Filed: November 21, 2014)
    **********************
    PIONEER RESERVE, LLC,
    Plaintiff,
    Clean Water Act; mitigation bank;
    v.                                             contract; regulatory function;
    subject matter jurisdiction
    THE UNITED STATES,
    Defendant.
    **********************
    Douglas E. Kahle, Virginia Beach, VA, for plaintiff.
    Sarah M. Valenti, Civil Division, Department of Justice, Washington,
    DC, with whom were Steven J. Gillingham, Assistant Director, Robert E.
    Kirschman, Jr., Director, and Stuart F. Delery, Assistant Attorney General, for
    defendant. Milton W. Boyd, Office of the Chief Counsel, U.S. Army Corps of
    Engineers, Washington, DC, of counsel for defendant.
    _______________
    OPINION
    _______________
    BRUGGINK, Judge.
    Pioneer Reserve, LLC (“Pioneer” or “plaintiff”), presents this court
    with a breach of contract claim. Defendant, the United States Government,
    filed a motion to dismiss plaintiff’s complaint, contending that plaintiff did not
    have a contract with the federal government and that we, therefore, do not
    have subject matter jurisdiction. The matter is fully briefed and we heard oral
    argument on November 6, 2014. For the reasons explained below, we deny
    defendant’s motion.
    BACKGROUND1
    Pioneer Reserve, LLC was formed by the Walther family to manage
    two tracts of valuable land (“the tracts” or “the land”) located in Matanuska-
    Susitna Borough, Alaska that the family acquired in 1998. These tracts of land
    were capable of being developed and therefore had significant value. The
    Walther family also suspected that there would be even greater value in
    preserving the land and selling its status as a preserved natural resource to
    developers who were required to compensate for the impact their
    developments elsewhere would have on other natural resources. The
    framework for this arrangement is set forth in the following statutes and
    regulation.
    I.     The Clean Water Act and Its Implementation Through Regulation
    Congress passed the Clean Water Act to “restore and maintain the
    chemical, physical, and biological integrity of the Nation’s waters.” 33 U.S.C.
    § 1251(a) (2012). The Act accomplishes this restoration by prohibiting the
    discharge of pollutants into bodies of water, 
    id. § 1311(a),
    except by special
    permit issued by the appropriate federal agency. 
    Id. § 1344(a).
    Thus, if a
    developer seeks to dredge or dump fill, i.e., discharge pollutants, into the
    waters, including wetlands,2 of the United States, it must apply for a permit,
    which may or may not be granted after a period for public notice and comment.
    
    Id. After the
    developer applies for the permit, the Department of the Army,
    Corps of Engineers (“Corps”), engages in a public-interest analysis that takes
    into account measures proposed by the developer to mitigate the unavoidable
    1
    The facts are taken from plaintiff’s complaint, and are presumed
    correct for the purposes of defendant’s motion to dismiss, unless challenged.
    Henke v. United States, 
    60 F.3d 795
    , 797 (Fed. Cir. 1995).
    2
    Wetlands are also protected because they “constitute a productive and
    valuable public resource, the unnecessary alteration or destruction of which
    should be discouraged as contrary to the public interest.” 33 C.F.R. §
    320.4(b)(1) (2014).
    2
    impact to the waters or wetlands. 33 C.F.R. § 320.4(r) (2014). The mitigation
    may be accomplished on or off the site intended for development, and the
    Corps may condition the permit upon the implementation of the proposed
    mitigation. 
    Id. § 325.4(a).
    Additionally, the developer is not required to be the
    entity that accomplishes the mitigation. Rather, the regulations contemplate
    an option whereby the developer may secure mitigation “credits” from a third
    party mitigation bank,3 which assumes responsibility for the preservation of a
    piece of land containing natural resources, such as wetlands, in exchange for
    compensation from the developer. See 
    id. § 332.2
    (“The operation and use of
    a mitigation bank are governed by a mitigation banking instrument.”).
    The mitigation banking instrument4 (“instrument”) features prominently
    in the process of proposing, approving, and establishing a mitigation bank.
    The process begins when the entity seeking to establish a mitigation bank,
    which is referred to as the “sponsor,” submits a proposal to the Corps. This
    proposal must contain the following: a draft mitigation plan describing “the
    ecological characteristics of the proposed compensatory mitigation project
    site;” a work-plan for restoring, enhancing, or preserving the resources
    described; “the number of credits to be provided, including a brief explanation
    of the rationale for this determination;” and the method of achieving
    preservation, including any legal arrangements or instruments necessary to
    ensure the long-term protection of the site. 
    Id. § 332.8(c)(1)(iii).
    The district
    engineer, on behalf of the Corps, then assembles an Interagency Review Team
    (“IRT”) to review the documents submitted by the sponsor. 
    Id. § 332.8(b)(1).
    “[R]epresentatives from the U.S. Environmental Protection Agency, U.S. Fish
    3
    A mitigation bank is defined as “a site or suite of sites, where
    resources (e.g., wetlands, streams, riparian areas) are restored, established,
    enhanced, and/or preserved for the purpose of providing compensatory
    mitigation for impacts authorized by” a permit issued by the Army Corps of
    Engineers. 33 C.F.R. § 332.2. “In general, a mitigation bank sells
    compensatory mitigation credits to permittees whose obligation to provide
    compensatory mitigation is then transferred to the mitigation bank sponsor.”
    
    Id. 4 “Mitigation
    bank instrument means the legal document for the
    establishment, operation, and use of a mitigation bank.” 33 C.F.R. § 332.2.
    “The instrument provides the authorization for the mitigation bank . . . to
    provide credits to be used as compensatory mitigation for [Department of the
    Army] permits.” 
    Id. § 332.8(d)(1).
    3
    and Wildlife Service, NOAA Fisheries, the National Resource Conservation
    Service, and other federal agencies, as appropriate, may participate in the
    IRT.” 
    Id. § 332.8(b)(2).
    The IRT will review the proposal, instrument, “and other appropriate
    documentation and provide comments to the district engineer” in order “to
    facilitate the establishment of mitigation banks.” 
    Id. § 332.8(b)(3).
    During the
    IRT review period, the public is also given a 30-day period to comment on the
    sponsor’s proposal. 
    Id. § 332.8(d)(5).
    If the district engineer determines that
    the proposal has potential, he or she will provide the sponsor with the district
    engineer’s initial evaluation letter along with comments from the public and
    the IRT. 
    Id. § 332.8(d).
    “After considering comments from the district
    engineer, the IRT, and the public, if the sponsor chooses to proceed with
    establishment of the mitigation bank . . . he must prepare a draft instrument
    and submit it to the district engineer.” 
    Id. § 332.8(d)(6)(i).
    The draft
    instrument must contain the mitigation plan and a credit release schedule. 
    Id. § 332.8(d)(6).
    When the sponsor submits the draft instrument, it triggers one
    more round of review and comments by the district engineer and the IRT. 
    Id. § 332.8(d)(7).
    The sponsor has the ability to alter the draft instrument to
    respond to comments. If the feedback during this round of review indicates
    that the draft instrument is generally acceptable, then the sponsor may submit
    a final instrument. 
    Id. Submission of
    the final instrument results in a final round of review by
    the district engineer and the IRT. 
    Id. § 332.8(d)(8).
    Although the district
    engineer “retains final authority for approval of the instrument,” he or she
    “will give full consideration to any timely comments and advice of the IRT.”
    
    Id. § 332.8(b)(4).
    Once the final instrument is approved, the district engineer
    arranges for the instrument to be signed by the parties. 
    Id. § 332.8(d)(8);
    33
    C.F.R. § 332.8(a)(1) (“All mitigation banks . . . must have an approved
    instrument signed by the sponsor and the district engineer prior to being used
    to provide compensatory mitigation” credits.). Members of the IRT also have
    the option of signing the instrument to “indicate their agreement with the terms
    of the instrument” or to “submit a letter expressing concurrence with the
    instrument.” 33 C.F.R. § 332.8(b)(3). Once the mitigation banking instrument
    is signed, the mitigation bank may begin to sell credits according to the agreed-
    upon credit release schedule.
    4
    II.    The Process of Establishing the Pioneer Reserve Mitigation Bank
    When plaintiff first began contemplating the option of using its land to
    establish a mitigation bank, it operated under the belief that the Alaska
    Railroad Corporation was planning to construct an extension of the railroad
    that would impact wetlands and other water resources. The future railroad
    extension would be located within the same watershed, or “land area that
    drains to a common waterway,” 
    id. § 332.2
    , as the tracts of land owned by the
    Walther family. The fact that the proposed railroad extension and the tracts
    were located within the same watershed was important to plaintiff’s calculus
    regarding future use because the applicable regulations require, as a general
    proposition, that compensatory mitigation “be located within the same
    watershed as the impact site, and should be located where it is most likely to
    successfully replace lost functions and services.” 
    Id. § 332.8(b)(1).
    Believing that the Alaska Railroad Corporation’s extension project
    would generate demand for compensatory mitigation credits, plaintiff
    considered whether it would be beneficial to become the supplier. To that end,
    it engaged an environmental consulting firm, Restoration and Science
    Engineering (“RSE”), to assess the potential use of the land as a mitigation
    bank. During this assessment period, the Walther family and RSE sought the
    Corps’ opinion about the possible use of the land as a mitigation bank.
    “Members of the Walther family and RSE met with Corps’ representatives, on
    numerous occasions, including site visits that made detailed findings about the
    habitats, characteristics, and ecological functions performed by the [l]and.”
    Compl. ¶ 24. After that evaluation, RSE concluded that the land was suitable
    for preservation and use as mitigation bank because of the land’s ecological
    functions. The Corps similarly determined “that the proposed preservation
    was appropriate and practicable.” Compl. ¶ 25. Having gained the sense that
    preservation of the tracts would “generate significant wetland mitigation
    credits, suitable for use in a wetland mitigation bank,” the Walther family
    proceeded to draft a mitigation banking instrument. Compl. ¶ 26.
    Part of the draft instrument was the mitigation plan and map of the two
    tracts of land: the Edgerton Bank Parcel, which is comprised of 165.80 acres,
    and the Seldon Bank Parcel, which measures 105 acres. RSE mapped each
    parcel, indicating the different habitats and the corresponding capacity for
    certain ecological functions. This map was used to determine the proposed
    number of credits. The Corps indicated its agreement with the proposed
    figures for each parcel: 151.81 wetland mitigation credits for the Edgerton
    5
    Bank Parcel and 83.73 wetland mitigation credits for the Seldon Bank Parcel.
    “In reliance on the Corps’ determination that the Pioneer Reserve Bank would
    be authorized to sell 151.81 wetland mitigation credits by virtue of inclusion
    of the Edgerton Bank Parcel, the Walther family conveyed the [l]and to
    Pioneer.” Compl. ¶ 31.
    Representatives of the Corps and Pioneer signed the mitigation banking
    instrument. The document provides that it “is an agreement made and entered
    into by Pioneer Reserve, LLC (Sponsor) and the U.S. Army Corps of
    Engineers, Alaska District (Corps),” that becomes “effective upon the latter
    date of signature by the Sponsor and the Corps.” Compl. Ex. B, at 1-2.
    Specifically, the instrument characterizes itself as “[t]he legally binding and
    enforceable agreement between the District Engineer of the Corps, and a
    mitigation Bank Sponsor that formally establishes the mitigation Bank and
    stipulates the terms and conditions of its construction, operation, use and long-
    term management.” 
    Id. at 12.
    In addition, the instrument states that
    “[c]ertification of 83.73 credits in the Seldon Bank Parcel and 151.81 credits
    in the Edgerton Bank Parcel is established by the execution of this instrument.”
    
    Id. at 10.
    The instrument also includes Pioneer’s obligations for proper
    physical, legal, and financial maintenance of the wetland bank into the future.
    Attached to and included by reference in the instrument are the mitigation
    plan, ecological reports, and the maps used to determine the number of credits.
    See 
    id. at 21,
    57, 63.
    Once the mitigation banking instrument was signed, Pioneer
    encumbered both parcels of land with a perpetual conservation and
    preservation easement as required in the agreement. Thereafter, Pioneer was
    able to sell some its Edgerton Bank Parcel credits to the Alaska Department
    of Transportation for $79,000 per credit. No further sales took place, however,
    because, although the Alaska Railroad Corporation was seeking credits to
    compensate for the unavoidable impacts caused by its railroad extension, the
    Corps unilaterally reduced the number of wetland mitigation credits available
    from the Edgerton Bank Parcel from 151.81 to 16.92. The Alaska Railroad
    Corporation purchased the remaining 16.92 credits attributable to the Edgerton
    Bank Parcel and then had to secure the remaining credits from another bank
    located in a different service area. According to plaintiff, its inability to sell
    the full complement of credits cost resulted in a loss of $12 million.
    Pioneer filed its complaint here on May 5, 2014. It asserts that the
    Corps materially breached the contract when it unilaterally and without cause
    6
    drastically reduced the number of credits available for sale from the Edgerton
    Bank Parcel. Defendant has moved to dismiss on the ground that plaintiff’s
    complaint does not allege a cause of action within this court’s jurisdiction
    because the mitigation banking instrument is not a contract. We conclude, for
    the reasons explained below, that the complaint alleges sufficient facts to
    support its assertion that the mitigation banking instrument was, in fact, a
    contract. We thus deny the motion.
    DISCUSSION
    The Court of Federal Claims possesses only that jurisdiction authorized
    by statute. Kokkonen v. Guardian Life Ins. Co. of Am., 
    511 U.S. 375
    , 373
    (1994). The relevant provision here is the Tucker Act, which grants us
    jurisdiction to adjudicate “any claim against the United States founded either
    upon the Constitution, or any Act of Congress or any regulation of an
    executive department, or upon any express or implied contract with the United
    States, or for liquidated or unliquidated damages in cases not sounding in tort.”
    28 U.S.C. § 1491(a)(1) (2012). Plaintiff must establish by a preponderance of
    the evidence that its claim falls within the subject matter jurisdiction of this
    court before we may consider the merits of the claim. M. Maropakis
    Carpentry, Inc. v. United States, 
    609 F.3d 1323
    , 1327 (Fed. Cir. 2010).
    Pioneer asserts that we have jurisdiction pursuant to the Tucker Act
    because there is an express contract between plaintiff and the United States
    government. To prove the existence of a contract, “[o]ne must show (1)
    mutuality of intent to contract; (2) consideration; and (3) lack of ambiguity in
    offer and acceptance.” D & N Bank v. United States, 
    331 F.3d 1374
    , 1378
    (Fed. Cir. 2003) (citing Lewis v. United States, 
    70 F.3d 597
    , 600 (Fed. Cir.
    1995)). Additionally, when the federal government is party to the contract,
    “the government representative whose conduct is relied upon must have actual
    authority to bind the government in contract.” 
    Id. While defendant
    does not
    dispute that plaintiff dealt with a government agent that had authority to enter
    into a binding agreement, it does contest the existence of the other elements of
    a contract. Specifically, defendant alleges that Pioneer cannot establish the
    requisite intent to contract because the agency gave its approval to the
    instrument as an exercise of its regulatory function rather than in its role as a
    party exchanging a promise. Defendant points to the regulations set forth at
    33 C.F.R. Part 332, and argues the following:
    7
    [T]he regulations specifically frame the mitigation bank
    instrument as “provid[ing] the authorization for the mitigation
    bank . . . to provide credits to be used as compensatory
    mitigation for [Corps] permits.” 33 C.F.R. § 332.8(a)(1). The
    regulations also state that “[a]ll mitigation banks must have an
    approved instrument signed by the sponsor and the district
    engineer prior to being used to provide compensatory mitigation
    for DA permits.” 33 C.F.R. § 332.8(a)(1). Such approval is a
    regulatory function, and not a contractual relationship.
    Def.’s Mot. to Dismiss 10.5 According to defendant, “the Corps does not
    execute mitigation bank instruments to accomplish wetlands restoration, but
    rather to document that the Corps has evaluated and approved the mitigation
    banker’s plan.” 
    Id. at 11
    (quotations omitted). Thus, defendant argues that the
    Corps has nothing to exchange in consideration for its approval of the
    mitigation banking instrument. According to defendant, the absence of
    consideration and mutual intent to contract show that plaintiff did not have a
    contract with the government6 and, therefore, plaintiff’s complaint should be
    dismissed for lack of subject matter jurisdiction.
    To support its argument, defendant points to D & N Bank v. United
    States, 
    331 F.3d 1374
    (Fed. Cir. 2003). In that case, D & N Bank (“D & N”)
    sought to recover damages for breach of contract which occurred when,
    because of new federal legislation, D & N was not able to use the goodwill
    value of the thrift that it recently acquired with the approval of the Federal
    Home Loan Bank Board. 
    Id. at 1376-77.
    D & N argued that its ability to use
    5
    The regulation quoted by defendant provides, in full, that “All
    mitigation banks and in-lieu fee programs must have an approved instrument
    signed by the sponsor and the district engineer prior to being used to provide
    compensatory mitigation for DA permits.” 33 C.F.R. § 332.8(a)(1) (General
    Considerations). In another section, the regulation defines mitigation banking
    instrument as “the legal document for the establishment, operation, and use of
    a mitigation bank.” 
    Id. § 332.2
    (Definitions).
    6
    We note that the government’s position in this case should be
    contrasted with its stance in United States v. Hawkins, No. 3:05CV-12-H
    (W.D. Ky. March 31, 2006), where the government sought to enforce the terms
    of a mitigation banking instrument by arguing that the instrument was a
    contract.
    8
    the goodwill value gained in the merger was a term of the contract it had with
    the Federal Home Loan Bank Board regarding the acquisition. 
    Id. The problem
    in that case, however, was that D & N did not provide sufficient
    evidence that a contract existed between it and the Federal Home Loan Bank
    Board. The Court of Appeals for the Federal Circuit described the evidence
    as follows:
    [N]one of these documents purports to be a contract between D
    & N and the government or indicates that it binds parties on
    either side of the transaction. . . . [T]he only piece of paper that
    can be viewed as indicating a promise by someone with any
    authority is the Bank Board Resolution. This document,
    however, only shows the [Federal Home Loan] Bank Board’s
    approval of the merger. Mere approval of the merger does not
    amount to intent to contract. The Bank Board, in its regulatory
    capacity, must approve all mergers.
    
    Id. at 1378.
    The Court of Appeals went on to note that there was no evidence
    of negotiation, no evidence of mutual intent to contract, especially in the
    absence of a written agreement purporting to set forth the agreement of the
    parties, and no discussion of goodwill, let alone D & N’s right to use the value
    of goodwill, in the documents presented to the court by D & N. 
    Id. at 1378-79.
    In the absence of the aforementioned, the Federal Circuit concluded that the
    Federal Home Loan Bank Board’s approval of the merger was a function of
    its regulatory or sovereign duty rather than evidence of its intent to contract
    with D & N. 
    Id. at 1380,
    1382; see also Anderson v. United States, 
    344 F.3d 1343
    , 1355-57 (Fed. Cir. 2003) (holding that the agency had not expressed the
    requisite intent to be bound and instead imposed a regulatory condition when
    it included in the resolution a provision requesting the bank to submit and
    justify the value of the goodwill and the proposed amortization schedule at a
    later date).
    We find defendant’s reliance on D & N to be misplaced. Unlike the
    situation in D & N, there is a document in this case which provides that it is
    “[t]he legally binding and enforceable agreement between the District
    Engineer of the Corps, and a mitigation Bank Sponsor that formally establishes
    the mitigation Bank and stipulates the terms and conditions of its construction,
    operation, use and long-term management.” Compl. Ex. B, at 12. The
    agreement states that “[c]ertification of 83.73 credits in the Seldon Bank Parcel
    and 151.81 credits in the Edgerton Bank Parcel is established by the execution
    9
    of this instrument.” Compl. Ex. B, at 10. Furthermore, the agreement records
    a promise “whereby Pioneer agrees to acquire and preserve 235.54 acres of
    threatened resources which benefits the Corps in its efforts to maintain the
    ecological health of the region and to carry out its duties to protect the quality
    of the area’s waters under the Clean Water Act.” Pl.’s Resp. 3-4 (citations
    omitted). In exchange for plaintiff’s promise “to preserve the [l]and, the Corps
    agreed to award Pioneer ‘Bank credits’ which it can sell to third parties.” 
    Id. Additionally, plaintiff
    alleges and defendant does not dispute that these terms
    were agreed to after a series of meetings, site visits, and the production of
    ecological reports. The complaint thus alleges negotiation, mutual intent to
    contract, bargained for exchange of consideration, and a memorialized final
    instrument setting forth the terms of the bargain.
    Plaintiff argues that this case is analogous to Davis Wetlands Bank, LLC
    v. United States, which was recently decided by this court, and which also
    involved environmental mitigation banking. 
    114 Fed. Cl. 113
    (2013). In
    Davis Wetlands Bank, the court was presented with defendant’s theory that
    Davis’ signed final mitigation banking instrument was merely a regulatory
    action, not a contract. The court examined the instrument and supporting
    documents “‘to see if they consist of only regulatory proclamations, or if they
    include additional language, which clearly manifests the government’s intent
    to contract.’” 
    Id. at 122
    (quoting First Fed. Lincoln Bank v. United States, 
    60 Fed. Cl. 501
    , 504 (2004)). After reviewing the relevant documents, the court
    held the following:
    [T]he Final Agreement contains definite terms and recites the
    obligations contained and acceptance manifested by the
    signatures from a Bank representative, a District Engineer for
    the Army Corps, and a representative from [the United States
    Fish and Wildlife Service]. The documents and exhibits that
    together comprise the Final Agreement were reviewed and
    signed by the parties over the course of several years, suggesting
    a negotiated arms-length process. This ongoing process . . .
    represents the manifestation of willingness to enter into a
    bargain, so made as to justify another person in understanding
    that his assent to that bargain is invited and will conclude it.
    As consideration for the Bank’s promise to restore
    wetlands subject to the Final Agreement, the Army Corps
    promised to issue the bank credits . . . .
    10
    Therefore, under the Final Agreement, the Army Corps
    agreed to enter into a contract with private parties to accomplish
    wetland restoration in exchange for issuing credits that could be
    sold to third parties . . . .
    
    Id. at 121-22
    (quotations and citations omitted). The court concluded that
    “[t]he fact that ‘no landowner can develop a mitigation bank absent [Army]
    Corps approval,’ does not preclude the Army Corps from contracting with a
    private party.” 
    Id. at 122
    (quoting Hearts Bluff Game Ranch v. United States,
    
    669 F.3d 1326
    , 1331 (Fed. Cir. 2012)).
    We agree with the analysis in Davis Wetlands Bank. The instrument
    presented by Pioneer purports to be the a legally binding agreement between
    plaintiff and the Army Corps, which lays out the obligations that each party
    assumes by entering into the agreement. Pioneer agreed to preserve in
    perpetuity two parcels of valuable land in exchange for the ability to sell
    “credits” to third parties who have “debits” owing to development projects that
    unavoidably impact waterways. The Corps, by agreeing to this arrangement,
    carries out a purpose of the agency, which is to restore and preserve the United
    States waterways pursuant to the Clean Waters Act. While this arrangement
    is made against a regulatory background, that background is not incompatible
    with the development of a binding agreement. The regulations merely describe
    the ground rules pursuant to which the Corps may accept, reject, or respond to
    an offer. In turn, if a counter-offer is made, the sponsor is not obligated to
    accept it, but may respond with acceptance, a rejection, or another counter-
    offer. In this case, the process ended in the memorialization of a mitigation
    banking instrument that establishes the parties’ respective roles, benefits, and
    obligations concerning the mitigation bank. In the absence of any factual
    challenge to the elements of the contract asserted by Pioneer, we hold that the
    complaint alleges sufficient facts to establish the existence of a contract.
    Defendant makes a second challenge to our jurisdiction, namely that
    plaintiff has not identified a right to recover money damages. A money-
    mandating source is necessary because “jurisdiction under the Tucker Act
    requires the litigant to identify a substantive right for money damages against
    the United States separate from the Tucker Act.” Todd v. United States, 
    386 F.3d 1091
    , 1094 (Fed. Cir. 2004). Defendant contends that “[n]ot even a
    liberal reading” of the instrument “creates any inference that the Government
    obligated public money to this instrument.” Def.’s Mot. to Dismiss 13.
    Plaintiff responds that the standard is whether there is a fair inference that the
    11
    contract is “reasonably amenable to the reading that it mandates a right of
    recovery in damages.” Holmes v. United States, 
    657 F.3d 1303
    , 1309 (Fed.
    Cir. 2011). Additionally, plaintiff cites Holmes, for the proposition that “when
    a breach of contract claim is brought in the Court of Federal Claims under the
    Tucker Act, the plaintiff comes armed with the presumption that money
    damages are available, so that normally no further inquiry is required.” 
    Id. at 1314.
    Defendant has offered us no plausible reading of the agreement under
    which the parties disavow the possibility of money damages if plaintiff
    prevails on the merits. Plaintiff has presented a contract that can be fairly
    interpreted as mandating money damages as a remedy and thus brings a claim
    for breach within our jurisdiction.
    CONCLUSION
    We deny the motion to dismiss. Defendant is directed to answer the
    complaint on or before December 19, 2014.
    s/ Eric G. Bruggink
    ERIC G. BRUGGINK
    Judge
    12