Century Exploration New Orleans, LLC v. United States ( 2013 )


Menu:
  •               In the United States Court of Federal Claims
    No. 11-54 C
    (Filed March 21, 2013)1
    *********************
    CENTURY EXPLORATION             *
    NEW ORLEANS, LLC,               *
    *
    Plaintiff,             *
    *                    Breach of Oil and Gas Lease;
    and                             *                    Risk of Regulatory Change;
    *                    Sovereign Acts Doctrine;
    CHAMPION EXPLORATION, LLC, *                         Outer Continental Shelf Lands Act,
    *                    
    43 U.S.C. §§ 1331-1356
     (2006);
    Third-Party Plaintiff, *                    Motion for Summary Judgment,
    *                    RCFC 56.
    v.                     *
    *
    THE UNITED STATES,              *
    *
    Defendant.             *
    *********************
    Richard K. Leefe, Metairie, LA, for plaintiff Century Exploration New
    Orleans, LLC. Michael R. Gelder and James K. Sticker, III, Metairie, LA, of
    counsel.
    Guy E. Wall, New Orleans, LA, for plaintiff Champion Exploration, LLC.
    Gregg M. Schwind, United States Department of Justice, with whom were
    Stuart F. Delery, Principal Deputy Assistant Attorney General, Jeanne E.
    Davidson, Director, and Steven J. Gillingham, Assistant Director, Washington, DC,
    for defendant.
    1
    / This opinion was issued under seal on March 8, 2013. Pursuant to ¶ 5 of the ordering
    language, the parties were invited to identify any proprietary information contained in the sealed
    opinion and to propose redactions to that opinion. On March 19, 2013, defendant filed a notice
    in which it informed the court that the parties had no proposed redactions to the sealed opinion.
    ______________________________
    OPINION
    ______________________________
    Bush, Judge.
    Now pending before the court are the parties’ cross-motions for partial
    summary judgment, pursuant to Rule 56 of the Rules of the United States Court of
    Federal Claims (RCFC), on plaintiffs’ breach claim (Count I of the complaint).
    The motions have been fully briefed and are now ripe for a decision by the court.
    Because none of the government’s actions in this case breached plaintiffs’ lease,
    the government’s motion for partial summary judgment is granted, and plaintiffs’
    cross-motion for partial summary judgment is denied.
    BACKGROUND2
    I.     Factual Background
    The United States, acting through the Department of the Interior (Interior), is
    the defendant in this case. Interior is charged with managing many of the nation’s
    energy resources, including resources located under the submerged lands of the
    Outer Continental Shelf (OCS)3 in the Gulf of Mexico and in other waters of the
    United States. Interior is responsible for the administration of mineral leases on
    the OCS, as well as the regulation of mineral exploration and production activities
    on the OCS. Plaintiffs Century Exploration New Orleans, LLC (Century) and
    Champion Exploration, LLC (Champion) are the holders of an oil and gas lease for
    a tract of submerged land located on the OCS in the Gulf of Mexico.4
    2
    / The facts recounted here are taken from the parties’ submissions in this case and are
    undisputed unless otherwise noted. The court makes no findings of fact in this opinion.
    3
    / Due to the large number of acronyms and other abbreviations used in this opinion, the
    court has, for the convenience of the reader, provided an appendix defining those terms.
    4
    / Century owns a 90.472222-percent interest in the subject lease, while Champion owns
    the remaining 9.527778-percent interest. Century initially purchased the lease at an auction in
    March 2008, and Champion subsequently acquired a partial interest in the lease from Century.
    continue...
    2
    Following a massive oil spill in 2010, the government adopted a number of
    new requirements for drilling operations on the OCS. In this case, plaintiffs argue
    that those new requirements repudiated and breached their lease and effected a
    taking of their property without the payment of just compensation in violation of
    the Fifth Amendment. Because the court has stayed proceedings on plaintiffs’
    takings claim, this opinion addresses only plaintiffs’ breach of contract claim.
    Accordingly, the court’s recitation of the facts in this case will be limited to those
    most relevant to plaintiffs’ breach claim.
    A.      Legal Framework for Oil and Gas Exploration and Production on
    the Outer Continental Shelf
    Under the Outer Continental Shelf Lands Act of 1953 (OCSLA), 
    43 U.S.C. §§ 1331-1356
     (2006), the United States exercises jurisdiction and control over the
    submerged lands of the OCS.5 The OCS is defined to include all submerged land
    that is beyond the outer limits of state jurisdiction (three nautical miles from shore)
    and within the limits of national jurisdiction (200 nautical miles from shore). See
    
    43 U.S.C. §§ 1301
    , 1331; Amber Res. Co. v. United States, 
    538 F.3d 1358
    , 1362
    (Fed. Cir. 2008) (Amber Resources II).
    In enacting OCSLA, Congress explained that “the [O]uter Continental Shelf
    is a vital national resource reserve held by the Federal Government for the public,
    which should be made available for expeditious and orderly development, subject
    to environmental safeguards, in a manner which is consistent with the maintenance
    of competition and other national needs.” 
    43 U.S.C. § 1332
    (3). In addition,
    OCSLA further provides that “operations in the [O]uter Continental Shelf should
    4
    / ...continue
    In its overview of the facts, the court will generally refer to both plaintiffs collectively, even
    where the described event may have occurred before Champion acquired its interest in the lease.
    5
    / OCSLA extends the legal jurisdiction of the United States to “the subsoil and seabed
    of the [OCS] and to all artificial islands, and all installations and other devices permanently or
    temporarily attached to the seabed, which may be erected thereon for the purpose of exploring
    for, developing, or producing resources therefrom, or any such installation or other device (other
    than a ship or vessel) for the purpose of transporting such resources, to the same extent as if the
    [OCS] were an area of exclusive Federal jurisdiction within a State.” 
    43 U.S.C. § 1333
    (a)(1).
    OCSLA, in other words, applies to drilling rigs, production platforms, pipelines, and other
    structures and facilities, whether permanent or temporary, that are located on the OCS.
    3
    be conducted in a safe manner by well-trained personnel using technology,
    precautions, and techniques sufficient to prevent or minimize the likelihood of
    blowouts, loss of well control, fires, spillages, physical obstruction to other users
    of the waters or subsoil and seabed, or other occurrences which may cause damage
    to the environment or to property, or endanger life or health.” 
    Id.
     § 1332(6).
    Under OCSLA, the Secretary of the Interior (Secretary) is charged with
    issuing and administering leases authorizing private parties to explore the OCS for
    oil and natural gas and, if such exploration is successful, regulating the production
    of oil and natural gas from the leased area. In that regard, OCSLA provides that
    the Secretary
    shall prescribe such rules and regulations as may be
    necessary to carry out such provisions. The Secretary
    may at any time prescribe and amend such rules and
    regulations as he determines to be necessary and proper
    in order to provide for the prevention of waste and
    conservation of the natural resources of the [O]uter
    Continental Shelf, and the protection of correlative rights
    therein, and, notwithstanding any other provisions herein,
    such rules and regulations shall, as of their effective date,
    apply to all operations conducted under a lease issued or
    maintained under the provisions of this subchapter.
    
    43 U.S.C. § 1334
    (a). In accordance with those directives, the Secretary has
    promulgated regulations pursuant to OCSLA. See 30 C.F.R. pt. 250 (2008).6
    During the relevant time period, Interior issued and administered OCS
    leases, and regulated exploration and production activities on the submerged lands
    of the OCS, through the Minerals Management Service (MMS) and its successor
    agency, the Bureau of Ocean Energy Management, Regulation and Enforcement
    (BOEMRE). BOEMRE was subsequently divided into three separate agencies,
    6
    / In this opinion, unless otherwise indicated, the court will generally refer to the version
    of the Code of Federal Regulations (C.F.R.) that was in effect when plaintiffs acquired their
    lease. The relevant provisions of the C.F.R. governing OCS leasing, exploration, and
    development have been relocated from part 250 of title 30 to part 550 of that title.
    4
    each with distinct functions and authorities.7
    The leases issued pursuant to OCSLA “entitle the lessee to explore, develop,
    and produce the oil and gas contained within the lease area, conditioned upon due
    diligence requirements and the approval of the development and production plan
    required by this subchapter.” 
    43 U.S.C. § 1337
    (b)(4). However, “[t]he issuance
    and continuance in effect of any lease, or of any assignment or other transfer of any
    lease, under the provisions of this subchapter shall be conditioned upon
    compliance with regulations issued under this subchapter.” 
    Id.
     § 1334(b).
    OCSLA and its implementing regulations establish a multi-stage process for
    issuing OCS leases and for conducting exploration and production activities under
    those leases. First, the Secretary develops a five-year plan for lease sales based on
    the nation’s energy needs. Second, the leases are awarded to individual bidders
    based on competitive auctions. Third, the lessees conduct exploration activities on
    the leased area to determine whether oil and gas are present. Finally, the lessees
    conduct development and production activities on the site. Each of these distinct
    stages is governed by OCSLA and its implementing regulations. See generally
    Sec’y of Interior v. California, 
    464 U.S. 312
    , 337-40 (1984).
    The leases are awarded to the highest responsible qualified bidder at
    competitive, sealed-bid auctions conducted pursuant to a five-year plan developed
    by the Secretary. See 
    43 U.S.C. §§ 1334
    , 1337, 1344. In developing that plan, the
    Secretary must “select the timing and location of leasing, to the maximum extent
    practical, so as to obtain a proper balance between the potential for environmental
    damage, the potential for the discovery of oil and gas, and the potential for adverse
    impact on the coastal zone.” 
    Id.
     § 1344(a)(3). In addition, the Secretary must
    consider, inter alia, “relevant environmental and predictive information for
    different areas of the [O]uter Continental Shelf” in developing the five-year plan.
    7
    / In May 2010, the Secretary of the Interior announced that MMS would be split into
    three separate agencies: the Bureau of Safety and Environmental Enforcement (BSEE), the
    Bureau of Ocean Energy Management (BOEM), and the Office of Natural Resources Revenue
    (ONRR). Secretarial Order No. 3299 (May 19, 2010). In June 2010, MMS was renamed
    BOEMRE. Secretarial Order No. 3302 (June 18, 2010). The revenue-collection functions of
    BOEMRE were transferred to ONRR in October 2010, and BOEMRE was then divided into two
    new agencies, BSEE and BOEM, in October 2011. See Direct Final Rule, 
    76 Fed. Reg. 64432
    (Oct. 18, 2011).
    5
    
    Id.
     § 1344(a)(2)(H).
    Under OCSLA, a lessee must first submit an exploration plan (EP) to
    Interior for review and approval before conducting any exploration activities under
    its lease, see 
    43 U.S.C. §§ 1340
    (c)(1), 1340(e)(2); 
    30 C.F.R. § 250.201
    , and
    Interior must approve or deny the EP within thirty days of receipt, see 
    43 U.S.C. § 1340
    (c)(1). The lessee must certify that the EP is consistent with the coastal
    management plan of any affected state. 
    Id.
     § 1340(c)(2); 
    30 C.F.R. §§ 250.226
    ,
    250.232, 250.235. Further, the EP must include an Oil Spill Response Plan
    (OSRP) for the proposed drilling facilities, or it must incorporate a previously
    approved regional OSRP. 
    30 C.F.R. § 250.219
    (a). Once an EP is approved by
    Interior, the lessee must conduct all exploration activities on the site in conformity
    with the approved EP. 
    43 U.S.C. § 1340
    (e)(2).
    Following the approval of its EP, an OCS lessee must seek permission to
    conduct exploratory drilling, as described in its approved EP, by filing an
    Application for Permit to Drill (APD). 
    43 U.S.C. § 1340
    (d); 
    30 C.F.R. §§ 250.281
    ,
    250.410. If the application meets each of the requirements of the regulations,
    
    30 C.F.R. §§ 250.411-250.418
    , the lessee can begin exploratory drilling on the site.
    During the development stage, the lessee must submit either a Development and
    Production Plan (DPP) or a Development Operations Coordination Document
    (DOCD), depending upon the location of the lease site, for review and approval by
    Interior.8 
    43 U.S.C. § 1351
    ; 
    30 C.F.R. §§ 250.201
    , 250.241. In addition, the lessee
    must file an APD for any production wells it intends to drill, just as it did for its
    exploratory wells. 
    30 C.F.R. §§ 250.281
    , 250.410.
    OCSLA directs the Secretary to promulgate regulations “for the suspension
    or temporary prohibition of any operation or activity, including production,
    pursuant to any lease or permit.” 
    43 U.S.C. § 1334
    (a)(1). Under OCSLA, the
    Secretary may issue a suspension “at the request of a lessee, in the national interest,
    to facilitate proper development of a lease or to allow for the construction or
    negotiation for use of transportation facilities.” 
    Id.
     § 1334(a)(1)(A). In addition,
    the Secretary may issue a suspension without a request from the lessee “if there is a
    8
    / DOCDs are issued for development of lease sites within the western Gulf of Mexico,
    while DPPs are issued for sites elsewhere. 
    30 C.F.R. § 250.201
    . The review and approval
    process for a DPP is, according to defendant, somewhat more onerous than the process for a
    DOCD. See Def.’s Mot. at 13 n.9.
    6
    threat of serious, irreparable, or immediate harm or damage to life (including fish
    and other aquatic life), to property, to any mineral deposits (in areas leased or not
    leased), or to the marine, coastal, or human environment.” 
    Id.
     § 1334(a)(1)(B).
    In addition to the suspension grounds expressly described in OCSLA, the statute’s
    implementing regulations state that the Secretary may suspend a lease when
    necessary for the installation of safety or environmental protection equipment.
    
    30 C.F.R. § 250.172
    (c). In the absence of negligence or willful misconduct on the
    part of the lessee, the Secretary may extend the duration of a suspended lease for a
    period of time equal to the length of the suspension. 
    43 U.S.C. § 1334
    (a)(1).
    Under the regulations in effect when plaintiffs acquired their lease, MMS
    was authorized to issue Notices to Lessees and Operators (NTLs), which
    “clarify, supplement, or provide more detail about certain requirements.”
    
    30 C.F.R. § 250.103
    . Further, “NTLs may also outline what [lessees] must
    provide as required information in [their] various submissions to MMS.” 
    Id.
    NTLs are now issued by BOEM. See 
    30 C.F.R. § 550.103
     (2012).
    B.      Plaintiffs’ Oil and Gas Lease for Ewing Bank 920
    In accordance with the Secretary’s lease program for the years 2007-2012,
    the government held an auction in March 2008 (Lease Sale No. 206) for thousands
    of OCS tracts in the Gulf of Mexico. Def.’s Ex. 5.9 Plaintiffs submitted the
    highest bid on a 5760-acre tract known as Block 920, Ewing Bank (EW920).10
    Plaintiffs entered into Lease No. OCS-G 32293 (the lease) on July 8, 2008, and
    that lease became effective on August 1, 2008. Def.’s Ex. 1. The lease has an
    initial term running through July 31, 2016, and for as long thereafter as oil and gas
    are produced from the leased area in paying quantities, or while approved drilling
    or well re-working operations are conducted on the submerged land, or for as long
    as otherwise provided by regulation. 
    Id.
     In order to avoid cancellation of their
    9
    / In this opinion, citations to “Def.’s Ex. __” refer to the specified exhibit in the
    appendix to defendant’s motion for partial summary judgment, as well as the consecutively
    numbered exhibits filed with defendant’s response and its notice of subsequent developments.
    Similarly, citations to “Pls.’ Ex. __” refer to the exhibits in the appendix to plaintiffs’ motion for
    partial summary judgment, as well as the consecutively numbered exhibits to its reply and notice
    of subsequent developments.
    10
    / The bid submitted by plaintiffs was more than five times as high as the only other bid
    submitted for the EW920 lease. See Def.’s Ex. 5 at A138.
    7
    lease, however, plaintiffs were required to commence an exploratory well on the
    site no later than July 31, 2013. See 
    30 C.F.R. § 256.37
    (a)(3).
    Plaintiffs made an initial bonus payment of $23,236,314 to acquire the lease,
    and they have paid the government additional rental payments of $9.50 per acre,
    per lease year – $54,720 per year – since that initial payment. Further, once the
    lease is developed, the government is entitled to a specified percentage of the
    estimated or market value of the oil and gas produced on the leased area as royalty
    payments, subject to a minimum royalty payment of $9.50 per acre, per lease year.
    Def.’s Ex. 1 at A1.
    On December 22, 2008, plaintiffs submitted their EP for the lease to MMS.
    See Def.’s Ex. 2. The EP contemplated the drilling and completion of five
    exploratory wells on the leased area and incorporated by reference a regional
    OSRP approved by MMS in August 2007. See 
    id.
     at A51-A52. In their initial EP,
    plaintiffs certified that they had “the capacity to respond, to the maximum extent
    practicable, to a worst-case discharge, or a substantial threat of such a discharge,
    resulting from the activities proposed in our EP.” 
    Id.
     at A52; see also 
    id.
     at A26
    (“Century . . . has the financial capability to drill a relief well and conduct other
    emergency well control operations.”). Plaintiffs met their bonding requirements
    with an area-wide development bond furnished and maintained in accordance with
    applicable regulations and NTLs then in effect. See Pls.’ Ex. 4 at 13; Def.’s Ex. 2
    at A25. Plaintiffs stated that they anticipated commencing operations under the EP
    as early as March 2009, “[c]ontingent upon receiving regulatory approvals and
    based on equipment and personnel availability,” Def.’s Ex. 3 at A80, and would
    complete those operations by October 13, 2009, Def.’s Ex. 2 at A13.
    In accordance with the Coastal Zone Management Act of 1972 (CZMA),
    
    16 U.S.C. §§ 1451-1464
     (2006), plaintiffs also submitted their proposed EP to the
    State of Louisiana, which approved the EP on January 29, 2009, through the
    Department of Natural Resources, Office of Coastal Restoration and Management.
    See Compl. Ex. C; Def.’s Ex. 2 at A62-A66. MMS subsequently approved the EP
    on February 6, 2009. See Def.’s Ex. 4.
    Plaintiffs performed a reservoir analysis of the leased area, which indicated
    “proved reserves” of approximately 12.7 million barrels of oil equivalent (BOE)
    8
    and “probable reserves” of approximately 2.4 million BOE.11 Those figures were
    later confirmed by an independent analysis. See Compl. ¶ 11; Pls.’ Ex. 3.
    Plaintiffs have not, however, conducted any drilling – exploratory or otherwise –
    on the leased area, nor have any of the site’s prior lessees conducted any drilling
    there. Def.’s Ex. 3 at A84.
    C.      The Deepwater Horizon Disaster and Subsequent Reforms
    On April 20, 2010, an explosion and fire occurred on a semi-submersible
    drilling rig, the Deepwater Horizon, during the temporary abandonment of the
    Macondo exploratory well in the central Gulf of Mexico. The explosion killed
    eleven workers, and the subsequent loss of the vessel two days later, on Earth Day,
    resulted in an oil spill that lasted several months and released 4.9 billion barrels of
    crude oil into the Gulf of Mexico. The blowout preventer (BOP), designed to stop
    the flow of oil in the event of a blowout, failed to do so. The operator of the vessel
    made a number of unsuccessful attempts, using various techniques, to stop the flow
    of crude oil from the well before finally succeeding on July 15, 2010 – eighty-nine
    days after the explosion. The reservoir was permanently sealed in mid-September.
    See Deep Water: The Gulf Oil Disaster and the Future of Offshore Drilling,
    National Commission on the BP Deepwater Horizon Oil Spill and Offshore
    Drilling, at 1-19, 129-70 (January 2011) (National Commission Report).
    In the meantime, more than 45,000 government, industry, and other
    personnel were enlisted in the response effort, along with thousands of government
    and private vessels and aircraft. 
    Id. at 129-70
    . The Deepwater Horizon event was
    deemed to be a “spill of national significance” – the first time in history that term
    had been used. See 
    40 C.F.R. § 300.5
     (2012) (“Spill of national significance
    (SONS) means a spill that due to its severity, size, location, actual or potential
    impact on the public health and welfare or the environment, or the necessary
    response effort, is so complex that it requires extraordinary coordination of federal,
    11
    / The term “proved reserves” essentially refers to the quantity of petroleum that is
    expected to be recovered from the leased area with a reasonable degree of certainty, while
    “probable reserves” refers to the additional quantity of petroleum that is less likely to be
    recovered than proved reserves, but more likely to be recovered than “possible reserves.”
    Compl. ¶ 11 nn.5-6. There should be at least a fifty percent probability that the quantity of
    petroleum actually recovered will equal or exceed the sum of proved reserves and probable
    reserves (also known as “2P”). 
    Id.
     ¶ 11 n.6.
    9
    state, local, and responsible party resources to contain and clean up the
    discharge.”).
    Following the Deepwater Horizon event, in the summer and fall of 2010,
    MMS – and then BOEMRE – imposed a number of substantial new regulations
    and requirements on OCS deepwater drilling operations in the Gulf of Mexico.
    Plaintiffs allege that these new requirements have substantially increased the
    economic costs of their performance under the lease and have therefore repudiated
    and breached that lease.
    1.     The Safety Measures Report
    On April 30, 2010, the President ordered the Secretary to conduct a thorough
    review of the Deepwater Horizon disaster and to submit a report recommending
    new safety and environmental safeguards for deepwater drilling within thirty
    days.12 On May 27, 2010, the Secretary issued a report (the Safety Measures
    Report), which recommended a number of new safety precautions for all deepwater
    drilling operations on the OCS. See Def.’s Ex. 6.
    In the executive summary of the Safety Measures Report, the Secretary
    recommended a six-month moratorium on all OCS deepwater drilling activity
    using a floating rig in the Gulf of Mexico, as well as all permitting for such
    activity, even though there was no specific recommendation for such in the body of
    the report. See 
    id.
     at A210. Following the release of the Safety Measures Report,
    five of the seven experts consulted by Interior during its investigation indicated
    that they had not endorsed the decision to impose a six-month moratorium on
    deepwater operations. The Secretary contacted those individuals, and apologized
    for any misunderstanding or confusion created by the executive summary. See
    Pls.’ Ex. 32 at 2. Interior’s Office of Inspector General later investigated the issue,
    and determined that while the executive summary could have been clearer, that
    lack of clarity did not violate applicable law. See Pls.’ Ex. 36 at 2.
    12
    / The President also established an independent, bipartisan commission to investigate
    the Deepwater Horizon disaster and to make specific recommendations based on that
    investigation. The National Commission on the BP Deepwater Horizon Oil Spill and Offshore
    Drilling issued its report in January 2011.
    10
    2.     The First Moratorium – NTL-04
    On May 28, 2010, the Secretary issued a memorandum to the Director of
    MMS, ordering him to commence a six-month suspension of all pending, current,
    and approved offshore drilling operations on new deepwater wells on the OCS.
    See Def.’s Ex. 7. The memorandum further stated that MMS was not to process
    any APDs for deepwater wells during that six-month period. 
    Id.
     The Secretary
    invoked two regulatory bases for his decision. First, he determined that “at this
    time and under current conditions that offshore drilling of new deepwater wells
    poses an unacceptable risk of serious and irreparable harm to wildlife and the
    marine, coastal, and human environment.” 
    Id.
     (citing 
    30 C.F.R. § 250.172
    (b)).
    Second, the Secretary “determined that the installation of additional safety or
    environmental protection equipment is necessary to prevent injury or loss of life
    and damage to property and the environment.” 
    Id.
     (citing 
    30 C.F.R. § 250.172
    (c)).
    The Secretary explained that his decision was based on Interior’s thirty-day review
    of the Deepwater Horizon disaster, the Safety Measures Report, and the Secretary’s
    “further evaluation of the issue.” 
    Id.
    On May 30, 2010, the Deputy Director of MMS issued Notice to Lessees
    No. 2010-N04 (NTL-04), which provided details on the six-month moratorium on
    deepwater drilling and permitting. Def.’s Ex. 8. The notice explained that MMS
    would not consider applications to drill deepwater wells for a period of six months,
    and further noted that MMS would issue directed suspensions to lessees currently
    conducting such operations.13 NTL-04 referenced the Secretary’s May 28, 2010
    memorandum and the Safety Measures Report as supporting the moratorium.
    See 
    id.
     at A254. The notice stated that the six-month moratorium would not apply
    to intervention or relief wells drilled for emergency purposes. With respect to all
    other active drilling operations, however, the notice provided that affected lessees
    “must proceed at the next safe opportunity to secure the well and take all necessary
    13
    / NTL-04 explained that “[f]or the purposes of this Moratorium NTL, deepwater means
    depths greater than 500 feet.” Def.’s Ex. 8 at A253. Plaintiffs appear to challenge that definition
    of deepwater, arguing that it was inconsistent with an earlier NTL defining that term to include
    only operations in depths greater than 400 meters (1312 feet). See Pls.’ Mot. at 25. However,
    the relevance of that apparent discrepancy is unclear, as plaintiffs’ proposed activities would
    meet either definition of deepwater. See Pls.’ Ex. 4 at 13 (noting that plaintiffs planned to drill
    five exploratory wells in approximately 1500 feet of water); Pls.’ Ex. 8 at 5 (same); Def.’s Ex. 2
    at A14-A18 (same).
    11
    steps to cease operations and temporarily abandon or close the well until [they]
    receive further guidance from the Regional Supervisor for Field Operations.” 
    Id.
     at
    A253.
    On June 22, 2010, a district court in Louisiana issued a preliminary
    injunction enjoining the Secretary’s enforcement of the first moratorium. See
    Hornbeck Offshore Servs., LLC v. Salazar, 
    696 F. Supp. 2d 627
     (E.D. La. 2010).
    The Secretary appealed to the United States Court of Appeals for the Fifth Circuit,
    but that court dismissed the appeal as moot when the Secretary later rescinded the
    first moratorium on July 12, 2010. See Hornbeck Offshore Servs., LLC v. Salazar,
    396 Fed. App’x 147 (5th Cir. 2010).
    3.    New Safety Measures – NTL-05
    On June 8, 2010, MMS issued Notice to Lessees No. 2010-N05 (NTL-05),
    entitled “Increased Safety Measures for Energy Development on the OCS,” which
    imposed new and increased substantive requirements on drilling operations. See
    Def.’s Ex. 11. The new requirements set forth in NTL-05 applied to all OCS
    activity, whether in deepwater or in shallow water. NTL-05 adopted various
    recommendations described in the Safety Measures Report, and which, in the view
    of MMS, warranted immediate implementation. In addition to imposing new
    information and inspection requirements for BOPs, NTL-05 required the chief
    executive officers (CEOs) of affected operators to certify, under threat of criminal
    penalties for false statements, that the operators were in compliance with the
    operating regulations set forth in Part 250 of the Code of Federal Regulations
    (C.F.R.), as well as the operators’ compliance with several other conditions. See
    generally Pls.’ Ex. 4 at 16-18.
    On October 19, 2010, the same district court that enjoined the enforcement
    of the first moratorium set aside NTL-05 because, according to the court, it
    imposed new substantive requirements on drilling operations but was not
    promulgated in accordance with the required process of notice-and-comment
    rulemaking. See Ensco Offshore Co. v. Salazar, No. 10-1941, 
    2010 WL 4116892
    (E.D. La. Oct. 19, 2010).
    4.    New Information Requirements – NTL-06
    On June 18, 2010, MMS issued Notice to Lessees No. 2010-N06 (NTL-06),
    12
    entitled “Information Requirements for Exploration Plans, Development and
    Production Plans, and Development Operations Coordination Documents on the
    OCS,” which rescinded certain limitations set forth in an earlier notice to lessees
    (Notice to Lessees No. 2008-G04) regarding the information that operators were
    required to submit with EPs, DPPs, and DOCDs on blowout and worst-case
    discharge scenarios. See Def.’s Exs. 13-14; Pls.’ Ex. 4 at 18-20. NTL-06 appears
    to be the most significant obstacle to plaintiffs’ performance under the lease, and
    its impacts on plaintiffs will be addressed more fully below.
    5.    The Second Moratorium
    On July 12, 2010, the Secretary issued a memorandum that rescinded the
    first moratorium, but also ordered BOEMRE to issue new suspensions and a freeze
    on permitting based upon a second deepwater moratorium to be in effect through
    November 30, 2010. See Def.’s Ex. 18. In contrast to the May 2010 moratorium,
    which applied to all deepwater drilling activities, the July 2010 moratorium applied
    only to operations using subsea BOPs or surface BOPs on floating facilities.
    Following the permanent closure of the infamous Macondo well in
    September 2010, the Director of BOEMRE issued a memorandum to the Secretary
    recommending that the second moratorium – both the suspensions of drilling
    operations and the prohibition on new permits – be lifted immediately. On October
    12, 2010, the Secretary terminated the second moratorium in a decision
    memorandum, but also ordered the Director of BOEMRE to require the CEO of
    any operator seeking to perform deepwater drilling that would have been subject to
    the now-terminated moratorium to certify that the operator had complied with all
    applicable regulations. See Def.’s Ex. 19 at A404. In addition, the memorandum
    also requires each operator to “demonstrate that it has in place written and
    enforceable commitments, pursuant to applicable regulations, that ensure that
    containment resources are available promptly in the event of a deepwater
    blowout.” 
    Id. 6
    .    The Categorical Exclusions Memorandum
    On August 16, 2010, the Director of BOEMRE directed the agency to stop
    using certain categorical exclusions in performing reviews of drilling operations
    under the National Environmental Policy Act of 1969 (NEPA), 
    42 U.S.C. §§ 4321
    ,
    4331-4335 (2006). Under NEPA, the federal government is required to consider
    13
    the environmental consequences of its actions. In doing so, the agency first
    performs an environmental assessment (EA) to determine whether a proposed
    action will have a significant impact on the environment. If the agency answers
    that question in the negative, it issues a finding of no significant impact (FONSI).
    If the agency determines that its proposed action will have a significant impact on
    the environment, it must prepare a more extensive environmental impact statement
    (EIS). Under regulations promulgated pursuant to NEPA, federal agencies may
    categorically exclude certain types of actions from the requirement to perform an
    EA or an EIS. See 
    40 C.F.R. §§ 1500.4
    (p), 1508.4 (2012). Before the Director’s
    memorandum, EPs were categorically excluded from NEPA review; now, those
    plans had to meet the requirements of NEPA.
    7.    The Drilling Safety Rule
    The Drilling Safety Rule (DSR) codified the new protocols contained in
    NTL-05, as well as a number of new safety requirements recommended in the
    Safety Measures Report. The rule was first published without notice or comment,
    and became effective immediately upon its publication in the Federal Register on
    October 14, 2010. 
    75 Fed. Reg. 63346
     (Oct. 14, 2010); see Def.’s Mot. Exs.
    22-23. The DSR was later published as a final rule, following a comment period,
    on August 22, 2012. 
    77 Fed. Reg. 50856
     (Aug. 22, 2012); see Pls.’ Ex. 33.
    The court need not describe each of the specific provisions of the DSR here; there
    appears to be no dispute that the rule contains new substantive requirements related
    to well bore integrity and well control equipment and procedure, see Pls.’ Ex. 4 at
    26-27, which would impose substantial costs on operators and lessees, see 
    id. 8
    .    The Workplace Safety Rule
    BOEMRE published another regulation, the Workplace Safety Rule (WSR),
    the day after it published the DSR in the Federal Register. 
    75 Fed. Reg. 63610
    (Oct. 15, 2010). The WSR requires each OCS operator to develop and implement
    a Safety and Environmental Management System (SEMS) for its operations.
    Like the DSR, the WSR imposed new substantive requirements on OCS operators;
    unlike the DSR, however, the WSR was not developed or issued in direct response
    to the Deepwater Horizon disaster. Instead, the rule issued on October 15, 2010,
    was the final version of a rule first published in the Federal Register as an
    advanced notice of proposed rulemaking in May 2006, see 
    71 Fed. Reg. 29277
    (May 22, 2006), and then as a notice of proposed rulemaking in June 2009, see
    14
    
    74 Fed. Reg. 28639
     (June 17, 2009). In other words, the rulemaking process that
    culminated in the WSR was initiated long before plaintiffs acquired their lease.
    9.     CEO Compliance Statement and Enhanced Scrutiny of
    Containment Resources – NTL-10
    On November 8, 2010, BOEMRE issued Notice to Lessees No. 2010-N10
    (NTL-10), which requires the CEO statement discussed in the October 12, 2010
    memorandum. See Def.’s Ex. 26. NTL-10 also informed lessees that they must
    submit information with their OSRPs regarding their access to and deployment of
    containment resources, and that such information would be subject to additional
    scrutiny by BOEMRE. NTL-10 was later replaced by rules published in the
    Federal Register following the process of notice-and-comment rulemaking. See
    Pls.’ Ex. 4 at 29.
    10.    The December 2010 Clarification Document
    On December 13, 2010, BOEMRE released a guidance document to clarify
    the meaning of many of its actions, such as NTL-06, the new Drilling Safety Rule,
    the required NEPA assessments, and the NTL-10 compliance statement. See
    Def.’s Exs. 27-28. Plaintiffs do not contend that this document imposed any new
    requirements that were not already included in earlier NTLs or regulations.
    D.     Subsequent Action on Plaintiffs’ Lease
    On June 16, 2011, the Secretary sent a memorandum to BOEMRE, in which
    he ordered the agency to establish an expedited process for OCS lessees to request
    and obtain one-year suspensions and extensions of their leases. See Def.’s Ex. 29.
    On June 29, 2011, BOEMRE issued NTL No. 2011-N05, which implemented the
    Secretary’s orders. See Def.’s Ex. 30. In order to obtain a suspension and
    extension under that notice, an OCS lessee was required to certify that: (1) no oil
    or gas had been produced from the leased area as of May 15, 2011; (2) the leased
    area is under at least 500 feet of water (i.e., in deepwater); and (3) the lease is set to
    expire on or before December 31, 2015. 
    Id.
     at A529. Plaintiffs requested a
    suspension of their lease on July 5, 2011, see Def.’s Ex. 31, and BOEMRE
    approved plaintiffs’ request on August 11, 2011, see Def.’s Ex. 32.
    Under applicable regulations, OCS lessees are required to submit a revised
    15
    OSRP for approval every two years. See 
    30 C.F.R. § 254.30
    (a). Plaintiffs’ EP was
    based on a regional OSRP submitted in May 2007 and approved in August of that
    year. See Def.’s Ex. 2 at A51; Pls.’ Ex. 1 at 9.14 Plaintiffs continued to revise their
    regional OSRP in accordance with the regulations, even after the occurrence of the
    governmental actions challenged in this case, and BSEE approved the most recent
    revision to plaintiffs’ OSRP on November 8, 2012. See Def.’s Exs. 16-17, 40.
    Plaintiffs have continued to make the required rental payments under their lease,
    even after the events that plaintiffs view as a repudiation and total breach of the
    lease. Plaintiffs have not, however, ever filed an APD to conduct any exploratory
    drilling on the leased area.
    II.    Procedural History
    On January 25, 2011, Century filed its three-count complaint in this matter.15
    In its complaint, Century asserts that the government breached its lease agreement
    with plaintiffs (Count I); that it effected an uncompensated taking of its private
    property in violation of the Fifth Amendment (Count II); and that the government’s
    activities may have given rise to other, unspecified causes of action (Count III).
    Century asserts that the government’s actions in this case violated various sections
    of the Administrative Procedure Act (APA), 
    5 U.S.C. §§ 553
    , 706 (2006), and
    applicable regulations. Century requests a money judgment for its expectation
    damages under the lease or lost profits, whichever is greater. In the alternative,
    Century seeks as just compensation the fair market value of its interest in the lease.
    In the pre-suit notice sent to the government, Century asserted that its lost profits
    are equal to approximately $650 million. Def.’s Ex. 37 at A555.
    On April 5, 2011, defendant filed a motion to order the joinder of Champion
    14
    / Plaintiffs’ regional OSRP was first approved as early as 2004, see Pls.’ Ex. 1 at 3, and
    was revised a number of times before the August 2007 approval, see 
    id. at 4-9
    . The most recent
    revision of the OSRP uses EW920 as the basis for the worst-case discharge scenario, while the
    earlier versions of the plan used a different lease tract known as Ship Shoal 153.
    15
    / On November 23, 2010, Century sent to the President, the Secretary of the Interior,
    the Director of BOEMRE, local BOEMRE officials, and the Governor of Louisiana a letter that
    provided notice of Century’s claims and requested a decision on those claims within sixty days
    as required under OCSLA, 
    43 U.S.C. § 1349
    (a)(2)(A). The letter and supporting documents
    were delivered to the United States on November 24, 2010. Century received no response from
    the government within the sixty-day time period. See Def.’s Ex. 37.
    16
    pursuant RCFC 19(a). In the alternative, defendant asserted that the instant suit
    must be dismissed in its entirety pursuant to RCFC 12(b)(7) and RCFC 19(b)
    should joinder of Champion prove to be infeasible. In the same motion, defendant
    argued that the takings claim raised in Count II of the complaint must be dismissed
    under RCFC 12(b)(6) for failure to state a claim upon which relief can be granted.
    Because the property rights at issue in plaintiffs’ takings claim were created by the
    lease that plaintiffs allege has been breached, defendant argued that plaintiffs must
    seek relief under a breach of contract theory, not under a takings theory.
    On June 21, 2011, the court issued an order directing the Clerk’s Office to
    notify Champion of the pendency of this action as a potentially interested party
    pursuant to RCFC 14(b). That notice was duly issued by the Clerk’s Office on
    July 19, 2011, and Champion subsequently filed a complaint against defendant, in
    accordance with RCFC 14(c), on September 12, 2011. In its complaint, Champion
    adopted the allegations set forth in the initial complaint filed by Century, but also
    reserved its right to make an election of remedies at a later date. Following
    briefing and oral argument on defendant’s motion to dismiss under RCFC 12(b)(6),
    the court denied that motion on January 24, 2012, and stayed further proceedings
    on plaintiffs’ takings claim pending the resolution of their breach of contract claim.
    Defendant filed separate answers to plaintiffs’ complaints on March 9, 2012.
    On July 13, 2012, defendant filed a motion for partial summary judgment on
    plaintiffs’ breach of contract claim.16 In that motion, the government argues that it
    did not breach any express term of plaintiffs’ lease, nor did it breach the implied
    duty of good faith and fair dealing. In the alternative, defendant argues that even if
    there had been a breach in this case, the government is still shielded from liability
    under the sovereign acts doctrine. Finally, the government asserts that, should the
    court conclude that there was a breach in this case, and that the government is not
    protected from liability by the sovereign acts doctrine, plaintiffs are precluded from
    seeking damages for a total breach under the election of remedies doctrine.
    16
    / The parties filed a Joint Preliminary Status Report (JPSR) on April 27, 2012. In the
    JPSR, the government proposed a schedule for the filing and briefing of dispositive motions by
    the parties. Plaintiffs, in contrast, argued that the parties should be afforded an opportunity to
    conduct discovery before any further motions practice. The court established a briefing schedule
    for dispositive motions from the parties, but informed plaintiffs that the court would consider a
    motion under RCFC 56(d) at the appropriate time. See Scheduling Order of May 4, 2012.
    17
    On September 10, 2012, plaintiffs responded to the government’s motion
    and filed their own cross-motion for partial summary judgment. In their motion,
    plaintiffs argue that the government’s actions following the Deepwater Horizon
    disaster breached the express terms of their lease, as well as the implied duty of
    good faith and fair dealing. Plaintiffs further assert that defendant cannot invoke
    the sovereign acts doctrine in this case because the government’s actions were not
    public and general, but were instead targeted at its obligations under OCS leases.
    Finally, plaintiffs argue that the election of remedies doctrine does not preclude
    their action for total breach because plaintiffs’ post-breach actions were for the sole
    purpose of mitigating their damages.
    Defendant filed its response and reply on October 30, 2012, and plaintiffs
    filed their reply on November 13, 2012. In addition, defendant filed a notice of
    subsequent developments in the case on December 11, 2012, and plaintiffs filed a
    similar notice on February 5, 2013. The court heard oral argument on the parties’
    cross-motions for partial summary judgment on February 12, 2013.
    DISCUSSION
    I.    Standard of Review
    “[S]ummary judgment is a salutary method of disposition designed to secure
    the just, speedy and inexpensive determination of every action.” Sweats Fashions,
    Inc. v. Pannill Knitting Co., 
    833 F.2d 1560
    , 1562 (Fed. Cir. 1987) (internal
    quotations and citations omitted). The moving party is entitled to summary
    judgment “if the movant shows that there is no genuine issue as to any material
    fact and the movant is entitled to judgment as a matter of law.” RCFC 56(a).
    A genuine issue of material fact is one that could change the outcome of the
    litigation. Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    , 247-48 (1986).
    A summary judgment “motion may, and should, be granted so long as whatever is
    before the . . . court demonstrates that the standard for the entry of summary
    judgment, as set forth in Rule 56[], is satisfied.” Celotex Corp. v. Catrett, 
    477 U.S. 317
    , 323 (1986).
    “[A] party seeking summary judgment always bears the initial responsibility
    of informing the . . . court of the basis for its motion, and identifying those portions
    of ‘the pleadings, depositions, answers to interrogatories, and admissions on file,
    together with the affidavits, if any,’ which it believes demonstrate the absence of a
    18
    genuine issue of material fact.” 
    Id.
     (quoting former version of Fed. R. Civ. P.
    56(c)). However, the non-moving party has the burden of producing sufficient
    evidence that there is a genuine issue of material fact in dispute which would allow
    a reasonable finder of fact to rule in its favor. Anderson, 
    477 U.S. at 256
    . Such
    evidence need not be admissible at trial; nevertheless, mere denials, conclusory
    statements or evidence that is merely colorable or not significantly probative is not
    sufficient to preclude summary judgment. Celotex, 
    477 U.S. at 324
    ; Anderson, 
    477 U.S. at 249-50
    ; Barmag Barmer Maschinenfabrik AG v. Murata Mach., Ltd., 
    731 F.2d 831
    , 835-36 (Fed. Cir. 1984). “The party opposing the motion must point to
    an evidentiary conflict created on the record at least by a counter statement of a
    fact or facts set forth in detail in an affidavit by a knowledgeable affiant.” Barmag,
    
    731 F.2d at 836
    . Any evidence presented by the non-movant is to be believed and
    all justifiable inferences are to be drawn in its favor. Anderson, 
    477 U.S. at
    255
    (citing Adickes v. S.H. Kress & Co., 
    398 U.S. 144
    , 158-59 (1970)).
    Issues of contract interpretation are amenable to summary judgment. See
    San Carlos Irrigation & Drainage Dist. v. United States, 
    877 F.2d 957
    , 959
    (Fed. Cir. 1989) (“Whether a contract creates a duty is a legal question of contract
    interpretation.”); see also Varilease Tech. Grp. v. United States, 
    289 F.3d 795
    , 798
    (Fed. Cir. 2002) (“Contract interpretation is a question of law generally amenable
    to summary judgment.”); Gov’t Sys. Advisors, Inc. v. United States, 
    847 F.2d 811
    ,
    812 n.1 (Fed. Cir. 1988) (“Contract interpretation is a matter of law and thus is
    amenable to decision on summary judgment.”).
    II.   Analysis of the Cross-Motions for Partial Summary Judgment
    The parties have filed cross-motions for partial summary judgment.
    Defendant argues that there are no genuine issues of material fact in this case, and
    that it is entitled to judgment as a matter of law with respect to whether plaintiffs’
    lease has been breached and whether the government would be shielded from such
    a breach under the sovereign acts doctrine. Plaintiffs, in contrast, argue that there
    are no disputed issues of material fact with respect to their own motion, but
    contend that there are such disputes with respect to the government’s motion.
    Plaintiffs assert that they are entitled to judgment as a matter of law on the issue of
    liability.
    19
    A.     Applicable Law
    Plaintiffs seek damages for the government’s alleged breach of contract,
    which requires plaintiffs to demonstrate: (1) a valid contract between the parties;
    (2) an obligation or duty arising from that contract; (3) a breach of that duty; and
    (4) damages caused by the breach. San Carlos, 
    877 F.2d at 959
    . Defendant does
    not dispute that the lease in this case is a contract; rather, the dispute between the
    parties is whether the government has breached any of its duties under the lease.
    See Mobil Oil Exploration & Producing S.E., Inc. v. United States, 
    530 U.S. 604
    (2000) (holding that offshore leases issued pursuant to OCSLA are contracts);
    Amber Res. Co. v. United States, 
    68 Fed. Cl. 535
     (2005) (Amber Resources I)
    (same), aff’d, 
    538 F.3d 1358
     (Fed. Cir. 2008).
    Plaintiffs argue that the government’s conduct with respect to OCS leases
    following the Deepwater Horizon disaster was a repudiation of those leases,
    resulting in a total breach. “When the United States enters into contract relations,
    its rights and duties therein are governed generally by the law applicable to
    contracts between private individuals.” Lynch v. United States, 
    292 U.S. 571
    , 579
    (1934). In applying private contract law to OCS leases, the court may look to the
    Restatement of Contracts for guidance. See Mobil Oil, 
    530 U.S. at 608
    .
    When the performance of a duty under a contract is due, nonperformance of
    that duty is a breach of the contract. Restatement (Second) of Contracts § 235
    (1981). Nonperformance of a duty will be considered a total breach when “it so
    substantially impairs the value of the contract to the injured party at the time of the
    breach that it is just in the circumstances to allow him to recover damages based on
    all his remaining rights to performance.” Id. § 243. In addition, an obligor may
    commit a breach through repudiation, which is defined as “a voluntary affirmative
    act which renders the obligor unable or apparently unable to perform without such
    a breach.” Id. § 250.
    B.     The Government Did Not Repudiate or Otherwise Breach
    Plaintiffs’ Lease
    For the reasons discussed below, the court concludes that the government’s
    actions in this case did not breach any of the express terms of plaintiffs’ lease.
    Plaintiffs cannot, moreover, challenge the substantive validity of the government’s
    actions in this court on the asserted basis that section 1 of the lease incorporated
    20
    the judicial review provisions of the APA as an express term of the lease. Finally,
    the court holds that the government did not breach its implied duty of good faith
    and fair dealing in enacting the comprehensive reform measures challenged by
    plaintiffs in this case.
    1.    None of the Challenged Governmental Actions Breached
    Any Express Term of Plaintiffs’ Lease
    It is difficult to discern which specific terms of the lease, according to
    plaintiffs, have been breached by the government in this case. Plaintiffs argue that
    the government has changed the rules governing offshore exploration and
    production in unexpected ways, and that those changes have rendered plaintiffs’
    performance under the lease commercially impracticable. In plaintiffs’ view, those
    actions have breached both section 1 and section 2 of their lease. Plaintiffs further
    argue that NTL-06 has breached section 8 of their lease. For the reasons discussed
    below, the court concludes that none of those actions breached any express term of
    plaintiffs’ lease.
    a.     The New Regulations Did Not Breach the Lease
    Under section 2 of the lease, the government “grant[ed] and lease[d] to the
    Lessee the exclusive right and privilege to drill for, develop, and produce oil and
    gas resources, except helium gas, in the submerged lands of the [leased area].”
    Def.’s Ex. 1 at A1. Plaintiffs argue that the new regulations have breached the
    terms of the lease by destroying the fruits of its bargain with the government.
    Plaintiffs assert that performance under the lease has been rendered commercially
    impracticable due to the new requirements imposed by the DSR and the WSR.
    Section 2 of the lease does not, however, grant plaintiffs an absolute right to
    conduct exploration or production activities on the leased area. Rather, because
    those rights are qualified by the need to obtain various approvals, “the contract, in
    practice, amount[s] primarily to an opportunity to try to obtain exploration and
    development rights in accordance with the procedures and under the standards
    specified in the cross-referenced statutes and regulations.” Mobil Oil, 
    530 U.S. at 620
    ; see also Sec’y of Interior v. California, 
    464 U.S. 312
    , 317 (1984) (“A lessee
    does not . . . acquire an immediate or absolute right to explore for, develop, or
    produce oil or gas on the OCS; those activities require separate, subsequent federal
    authorizations.”); Amber Resources II, 
    538 F.3d at 1371
     (noting that OCS leases do
    21
    not “give the lessees any ultimate rights to develop the leases or produce oil and
    gas, and that granting permission for ongoing exploration and development was
    clearly a matter subject to the discretion of the Department of the Interior”).
    When they executed their lease, the parties shared a mutual understanding
    that the law governing exploration and development under the lease might change
    in the future, and the terms of the lease expressly provided for such change in
    section 1:
    This lease is issued pursuant to the Outer Continental
    Shelf Lands Act of August 7, 1953, 
    67 Stat. 462
    ;
    
    43 U.S.C. § 1331
     et seq., as amended (
    92 Stat. 629
    ),
    (hereinafter called the “Act”). The lease is issued subject
    to the Act; all regulations issued pursuant to the Act and
    in existence upon the Effective Date of this lease; all
    regulations issued pursuant to the statute in the future
    which provide for the prevention of waste and
    conservation of the natural resources of the Outer
    Continental Shelf and the protection of correlative rights
    therein; and all other applicable statutes and regulations.
    Def.’s Ex. 1 at A1.
    Under section 1, the lease is subject to the terms of OCSLA and any other
    “applicable statutes” that were in effect when the lease was executed. In addition,
    the lease is subject to any “applicable regulations” that were in effect at the time of
    lease execution. Finally, the lease is subject to future regulations, as long as they
    are issued pursuant to OCSLA and “provide for the prevention of waste and
    conservation of the natural resources of the Outer Continental Shelf and the
    protection of correlative rights therein.” 
    Id.
    On the other hand, section 1 makes it equally clear that the lease is not
    subject to existing statutes or regulations that are not “applicable.” Further, the
    lease is not subject to subsequently enacted statutes or to later amendments to
    existing statutes. Thus, section 1 allocates the risk of certain legal changes – future
    regulations issued pursuant to OCSLA – to plaintiffs, and it allocates the risk of
    other legal changes – future statutes, amendments of existing statutes, and future
    regulations issued pursuant to statutes other than OCSLA – to the government.
    22
    This reading is consistent with the Supreme Court’s decision in Mobil Oil
    and with the Federal Circuit’s decision in Amber Resources II. In Mobil Oil, the
    Supreme Court addressed whether the enactment of the Outer Banks Protection Act
    (OBPA), Pub. L. No. 101-380, § 6003, 
    104 Stat. 484
    , 555 (1990), breached several
    OCS leases. OBPA prevented MMS from approving any plan or permit for
    drilling operations off the North Carolina coast before the Secretary received
    recommendations from a newly created environmental review panel and made a
    report to Congress based upon those recommendations. OBPA further provided
    that no such approvals were to occur, in any event, for a period of at least thirteen
    months. The plaintiffs in that case asserted that the new statute breached their OCS
    leases because those leases incorporated the terms of OCSLA, which required that
    EPs be approved within thirty days. The Supreme Court agreed, explaining that
    “under the contracts, the incorporated procedures and standards amounted to a
    gateway to the companies’ enjoyment of all other rights.” Mobil Oil, 
    530 U.S. at 620
    . In the Court’s view, OBPA significantly narrowed that gateway and therefore
    materially breached the plaintiffs’ leases.
    The Federal Circuit followed the same approach in Amber Resources II.
    There, an amendment to the CZMA created a new role for coastal states in MMS’s
    review of lessee-requested suspensions. The court first noted that section 1 of the
    OCS leases in that case – which was largely identical to section 1 of the lease in
    this case – did not incorporate future statutes. For that reason, the court concluded
    that the amendment to the CZMA was not incorporated into the plaintiffs’ leases.
    Amber Resources II, 
    538 F.3d at 1371-72
    . The court further held that the CZMA
    amendment effected a substantial change in the governing procedures for granting
    lessee-requested suspensions and therefore breached the plaintiffs’ leases.
    In both cases, the ultimate result was based on a preliminary determination
    that the leases at issue did not incorporate future statutory changes. Those cases
    did not hold, however, that the government assumes the risk of future regulations,
    at least not those issued under OCSLA. See 
    id. at 1368
     (“[W]e treat the lease
    agreements as incorporating by reference any statutes or regulations that were in
    effect at the time of the leases’ execution and any regulations promulgated
    pursuant to those statutes.”), 1371 (noting that the lessees in Mobil Oil “bargained
    for a right to explore for and extract oil and gas from the leases, subject to a
    particular statutory regime”) (emphasis added).
    Plaintiffs argue that section 1 cannot be interpreted to subject their lease to
    23
    every future regulation issued pursuant to OCSLA because such an interpretation
    would render their contract illusory. The court agrees that a contract subject to the
    unbounded discretion of the government would be illusory and thus unenforceable.
    See Torncello v. United States, 
    681 F.2d 756
    , 760 (Ct. Cl. 1982) (explaining that a
    contracting party “may not reserve to itself a method of unlimited exculpation
    without rendering its promises illusory and the contract void”); see also
    Stockton E. Water Dist. v. United States, 
    583 F.3d 1344
    , 1357 (Fed. Cir. 2009)
    (“[T]here is the obvious question of whether making the contracts subject to
    whatever future federal law or policy may hold would make the contracts
    illusory.”). In this case, however, section 1 does not grant the government
    unfettered authority to change the rules during the game; instead, its discretion is
    cabined by an important limiting principle.
    Section 1 of the lease creates a substantial degree of certainty for lessees by
    allocating to the government the risk of future statutory changes, while allocating
    to the lessee the risk of future regulations issued pursuant to a single statute, to
    which the lease is expressly subject. As this court explained in Amber Resources I,
    68 Fed. Cl. at 547, “[a] regulation’s scope and effect . . . are subject to the enabling
    statute.” For that reason, “subjecting a lease to any future regulation issued
    pursuant to the OCSLA limits the lease’s modification to the contours of that act.”
    Id. The lease is subject only to future regulations issued pursuant to OCSLA,
    which constrains the scope and content of those regulations. In short, plaintiffs are
    entitled to a stable statutory regime under section 1 of the lease, but they assumed
    the risk of future regulatory changes within the context of that statutory regime.
    In addition to section 1, a number of other sections in the lease describe
    plaintiffs’ obligation to conduct their activities in accordance with controlling
    regulations. The lease provides in section 9, for example, that all operations on the
    leased area must be conducted “in accordance with approved exploration plans and
    approved development and production plans as are required by regulations.”
    Def.’s Ex. 1 at A2. Section 10 of the lease states that “[t]he Lessee shall comply
    with all regulations and Orders.” Id. Further, section 12 of the lease provides that
    the lessee must “maintain all operations within the leased area in compliance with
    regulations or orders intended to protect persons, property, and the environment on
    the [OCS].” Id. at A6.
    There is no dispute that plaintiffs’ lease is subject to the terms of OCSLA,
    which is expressly incorporated into their lease by reference. The statute provides
    24
    in part that “[t]he Secretary may at any time prescribe and amend such rules and
    regulations as he determines to be necessary and proper in order to provide for the
    prevention of waste and conservation of the natural resources of the [OCS].”
    
    43 U.S.C. § 1334
    (a). Importantly, OCSLA provides that any regulations issued
    under the statute apply to both new and existing leases as of their effective date.
    See 
    id.
     (“[N]otwithstanding any other provisions herein, such rules and regulations
    shall, as of their effective date, apply to all operations conducted under a lease
    issued or maintained under the provisions of this subchapter.”) (emphasis added).
    The Secretary’s ability to regulate offshore operations pursuant to OCSLA
    does not provide the government with a “route of complete escape” from its duties
    under its contract with plaintiffs. See Torncello, 681 F.2d at 769 (“It is hornbook
    law . . . that a route of complete escape vitiates any other consideration furnished
    and is incompatible with the existence of a contract.”). Indeed, the ability to
    regulate is essential to the discharge of the Secretary’s statutory duty to prevent
    waste and conserve the natural resources of the OCS. See 
    43 U.S.C. § 1334
    (a).
    Here, the regulations challenged by plaintiffs – the DSR and the WSR – are
    amendments to the regulations that implement OCSLA, and were themselves
    promulgated pursuant to OCSLA. See Def.’s Exs. 22, 24; 
    30 C.F.R. § 250.101
    .
    For that reason, plaintiffs’ lease is subject to those regulations under section 1.
    Plaintiffs argue that the regulations nonetheless breached the lease because they
    were not issued for the purpose of preventing waste and conserving the resources
    of the OCS. See Pls.’ Reply at 17. Plaintiffs’ assertions in that regard are both
    unsubstantiated and irrelevant in the context of an action for breach of contract.
    Plaintiffs may challenge the substantive validity of the regulations in district court,
    but they may not do so here. See Murphy v. United States, 
    993 F.2d 871
    , 874
    (Fed. Cir. 1993).17 In sum, neither the DSR nor the WSR breached any term of
    plaintiffs’ lease.
    b.      Neither of the Moratoria Breached the Lease
    Plaintiffs assert that the moratoria that were in effect from May 2010 until
    October 2010 breached their lease. The moratoria, according to plaintiffs, harmed
    17
    / Plaintiffs argue that the judicial review provisions of the APA are incorporated into
    the lease by reference (in section 1) and thus allow plaintiffs to sue for damages in this court
    based on alleged violations of the APA. The court addresses that argument more fully infra.
    25
    them in two ways. First, plaintiffs assert that the first moratorium diminished the
    availability of drilling rigs and personnel in the Gulf of Mexico. Compl. ¶¶ 17-18.
    Further, plaintiffs assert that the second moratorium, in combination with other
    regulatory measures, increased plaintiffs’ borrowing costs by preventing drilling
    on the leased area. Pls.’ Mot. at 52-53; Pls.’ Ex. 12 ¶¶ 3-4. The court concludes
    that the moratoria did not breach any term of plaintiffs’ lease.
    The first moratorium was implemented through NTL-04 on May 30, 2010.
    See Def.’s Ex. 8. NTL-04 informed lessees that MMS would not consider any
    applications to conduct deepwater drilling operations for a period of six months,
    i.e., until November 30, 2010, and also instructed lessees to terminate any such
    operations at the next safe opportunity. The first moratorium was in effect for
    approximately four weeks before it was preliminarily enjoined by a district court
    on June 22, 2010. See Hornbeck, 
    696 F. Supp. 2d at 639
    . On July 12, 2010, the
    Secretary issued a decision memorandum, which rescinded the first moratorium
    and imposed a new moratorium, to remain in effect until November 30, 2010.18
    See Def.’s Ex. 18. Based on a recommendation from the BOEMRE Director, the
    Secretary lifted the second moratorium on October 12, 2010. See Def.’s Ex. 19.
    Both moratoria did two things: first, they suspended drilling operations in
    deepwater, and, second, they temporarily ceased permitting for such activities.
    There is no dispute that plaintiffs were not affected by the suspensions because
    plaintiffs were not conducting any drilling operations on the site, nor had they
    submitted an application to do so. MMS issued letters to the lessees who were
    actually conducting such operations pursuant to their leases; plaintiffs were not
    among them. See Def.’s Ex. 8 at A253 (“Under 30 CFR 250.172, the Regional
    Supervisor for Production and Development will issue Suspensions of Operations
    (SOO) to all OCS Lessees and Operators currently drilling or proposing to drill
    new deepwater wells consistent with this Moratorium NTL.”); Def.’s Ex. 18 at
    A395 (“I direct you to withdraw the suspension letters issued under [NTL-04], and
    I direct you to issue new suspensions . . . . To provide certainty to affected
    18
    / The first moratorium applied to activities in more than 500 feet of water, while the
    second moratorium applied to operations using a subsea BOP or a surface BOP on a floating
    facility, without regard to water depth. As explained in the Secretary’s memorandum, however,
    both moratoria generally applied to the same facilities because “as a practical matter, 500 feet of
    depth is the typical trigger for needing to use floating drilling facilities.” Def.’s Ex. 18 at A382.
    26
    operators, please issue the suspension orders promptly.”).19
    Plaintiffs never submitted an APD that might have been considered and
    approved by MMS in the absence of the moratoria, but they argue that doing so
    would have been futile. Plaintiffs state that they intended to conduct operations
    under their lease in 2010, and that the moratoria prevented them from doing so.
    It is far from clear, however, that the moratoria had any real effect on plaintiffs’
    ability to move forward with their plans. Plaintiffs submitted their EP to conduct
    operations under the lease on December 22, 2008, see Def.’s Ex. 2, and MMS
    approved that EP on February 6, 2009, see Def.’s Ex. 4. In their EP, plaintiffs
    stated that they planned to commence operations under their lease by March 2009.
    Def.’s Ex. 2 at A13; see also Def.’s Ex. 3 at A80. But plaintiffs had not filed an
    application to pursue those operations by the time of the explosion on the
    Deepwater Horizon more than a year later, on April 20, 2010, nor have they made
    any attempt to file an application since that time. Further, the second moratorium
    was terminated more than two years ago, and plaintiffs have not yet filed an
    application for a drilling permit. Plaintiffs’ assertion that a total breach of their
    lease resulted from an inability to secure a drilling permit during the four months
    the moratoria were in effect is untenable. The court further notes that plaintiffs
    requested, and were granted, a one-year extension of their lease. See Def.’s Exs.
    31-32.
    Even if plaintiffs had submitted an application during the moratoria, and
    MMS had refused to consider that application while the two moratoria were in
    effect, it is far from clear that the resulting delay would have breached their lease.
    In Sun Oil Co. v. United States, 
    572 F.2d 786
     (Ct. Cl. 1978), the Court of Claims
    concluded that the government’s delay in approving the plaintiffs’ application to
    install a production platform on one of the two oil fields covered by their lease
    19
    / Even if plaintiffs had been operating under their lease and had received a suspension
    pursuant to either of the moratoria, the suspension would not have breached plaintiffs’ lease.
    Section 13 of the lease states that “[t]he Lessor may suspend or cancel this lease pursuant to
    section 5 of the Act,” Def.’s Ex. 1 at A6, and the referenced section of OCSLA, as well as its
    implementing regulations, authorize suspensions of the type at issue in this case, see 
    43 U.S.C. § 1334
    (a)(1)(B); 
    30 C.F.R. § 250.172
    . Plaintiffs’ argument that the suspensions were infirm
    because they were issued as part of a blanket moratorium, rather than as individual suspensions,
    is without merit because BOEMRE issued a suspension letter to each affected lessee or operator.
    27
    following a blowout at another nearby well did not breach the plaintiffs’ lease.20
    The plaintiffs in that case argued that the government had delayed the approval of
    their application for more than six months. The court, however, first explained that
    “[t]he blow out was a devastating event and required careful, prudent and cautious
    actions by Interior to control the oil spill first, and, second, to assure that such a
    blow out did not occur again.” 
    Id. at 804
    . The court noted that under OCSLA,
    “the Secretary was responsible for the administration of [OCS] leases and was
    under a duty to protect the environment against waste and to conserve natural
    resources.” 
    Id.
     For that reason, according to the court, “it was not only reasonable,
    but also the legal obligation of the Secretary to employ procedures different from
    those followed prior to the blow out to assure that such disasters would not occur.”
    
    Id.
    The temporary pause in deepwater permitting in this case was well within
    the government’s authority under both the terms of the lease and applicable law.
    Furthermore, plaintiffs’ operations under the lease were never suspended because
    there were no active operations to suspend. Plaintiffs never attempted to secure a
    drilling permit. Even if plaintiffs had filed an application for a drilling permit, and
    the approval of that permit had been delayed due to the moratorium, such a short
    delay would not have effected a total breach of the lease, particularly in light of the
    absence of any express deadlines for the review and approval of APDs in the lease,
    under the statute, or under the regulations. Finally, the circumstances that resulted
    in the implementation of the moratorium, described in exhaustive detail in the
    Secretary’s memorandum, see Def.’s Ex. 18, demonstrate that any hypothetical
    delay would have been entirely reasonable, see Sun Oil, 572 F.2d at 804. Neither
    of the moratoria breached plaintiffs’ lease.21
    20
    / The blowout in that case occurred off the coast of Santa Barbara, California, and, until
    the Deepwater Horizon disaster in 2010, had been the largest oil spill in U.S. history. See
    National Commission Report at 28-29.
    21
    / Plaintiffs also assert that there was a sustained downturn in the rate of permit issuance
    – the cleverly named “permitorium” – following the termination of the second moratorium. See
    Pls.’ Mot. at 58-59; Pls.’ Ex. 7. Plaintiffs do not explain how an apparent slowdown in the
    issuance of permits to other lessees could somehow breach their own lease, aside from noting
    their claimed inability to obtain a permit under the modified regulatory regime.
    28
    c.      The Notices to Lessees Did Not Breach the Lease
    Plaintiffs further contend that notices issued to lessees by MMS and
    BOEMRE – NTL-05, NTL-06, and NTL-10 – breached the terms of their lease.22
    Plaintiffs argue that none of the notices could have been reasonably foreseen by the
    parties at the time of contracting, and that each of the notices has dramatically
    increased their costs of performance under the lease. For the reasons discussed
    below, the court concludes that none of those notices breached any express term of
    plaintiffs’ lease.
    Section 10 of plaintiffs’ lease states that “[t]he Lessee shall comply with all
    regulations and Orders.” Def.’s Ex. 1 at A2 (emphasis added). In addition, the
    lease is further modified by Stipulation No. 8, which states that “[t]he lessee and its
    operators, personnel, and subcontractors are responsible for carrying out the
    specific [environmental] mitigation measures outlined in the most current MMS
    Notices to Lessees, which interpret requirements in the above-mentioned
    implementing regulations,” which the stipulation defines as 30 C.F.R. Part 250.23
    Def.’s Ex. 1 at A5. Accordingly, there is no question that the lease contemplated
    the government’s issuance of NTLs, and requires plaintiffs, as well as their
    operators, employees, and subcontractors, to meet the requirements of the “most
    current” NTLs issued under OCSLA’s implementing regulations.
    Plaintiffs do not dispute that their lease incorporated the regulations in effect
    when the lease was executed. Those regulations provide that “MMS may issue
    Notices to Lessees and Operators (NTLs) that clarify, supplement, or provide more
    detail about certain requirements.” 
    30 C.F.R. § 250.103
    . Further, “NTLs may also
    outline what [lessees and operators] must provide as required information in [their]
    22
    / Plaintiffs argue that NTL-04 breached their lease as well, but the court has already
    addressed that notice supra. In addition, it appears – although it is not clear – that plaintiffs also
    assert that NTL No. 2012-N06 breached their lease. See Pls.’ Mot. at 12.
    23
    / While the primary focus of Stipulation No. 8 is the protection of marine mammals and
    other threatened and endangered species, see Def.’s Ex. 1 at A5, that provision also notes that the
    general purpose of OCSLA is to promote the expeditious and orderly development of the OCS
    subject to environmental safeguards, and then references the implementing regulations for
    OCSLA contained in Part 250 of the Code of Federal Regulations. Further, the requirement that
    lessees and their operators, employees, and subcontractors comply with the most current NTLs is
    not expressly limited to the protection of marine mammals or other species.
    29
    various submissions to MMS.” Id. Defendant notes that the government has
    issued NTLs for those purposes since 1992. See Def.’s Mot. at 32 n.11.
    i.     NTL-05 Did Not Breach the Lease
    NTL-05 was issued by MMS on June 8, 2010, see Def.’s Ex. 11, and it was
    set aside by the district court on October 19, 2010, Ensco, 
    2010 WL 4116892
    . In
    setting aside the notice, the district court held that NTL-05 was a substantive rule
    that should have been issued under the formal process of notice-and-comment
    rulemaking. Here, plaintiffs assert that the notice dramatically increased their costs
    of performance, see Pls.’ Mot. at 55, and also breached the lease by “denying
    Century its statutory right to participate in the notice and comment procedure,”
    Compl. ¶ 21. Plaintiffs’ arguments in this regard are without merit.
    NTL-05 imposed a number of information, certification, and inspection
    requirements that had been recommended for immediate implementation in the
    Safety Measures Report. Compare Def.’s Ex. 6 at A18-A28 with Def.’s Ex. 11.
    Plaintiffs were never ordered to meet those requirements, because they apply only
    to drilling operations, and plaintiffs have never conducted any drilling operations
    under their lease, nor have they submitted an application to do so. NTL-05,
    moreover, was in effect for only four months, and, with the exception of one week
    in late-October 2010, would not have affected active operations under any lease
    during that time due to the moratoria. Plaintiffs do not dispute the short duration
    of NTL-05, nor do they respond to the argument that plaintiffs could not have been
    affected by its requirements. Instead, plaintiffs point out that the requirements
    contained in NTL-05 were later incorporated, along with new requirements, into
    the DSR and thus remain in effect to this day. Because the court has already held
    that the DSR did not breach plaintiffs’ lease, there is no basis for concluding that
    the less onerous requirements of NTL-05 breached the lease, particularly when
    those requirements were never applied to plaintiffs.
    ii.    NTL-06 Did Not Breach the Lease
    NTL-06 requires plaintiffs to adopt new assumptions in their calculation of
    the worst-case discharge scenario required under the regulations. Plaintiffs argue
    that, due to those new assumptions, NTL-06 has breached their lease in two ways.
    First, plaintiffs contend that they are now required to demonstrate the financial
    capability to respond to a much higher worst-case discharge volume than before,
    30
    and that they are unable to do so.24 That change, according to plaintiffs, breaches
    sections 1 and 2 of their lease. Second, plaintiffs argue that the higher worst-case
    discharge volume has increased their bonding requirement in violation of section 8
    of their lease.25 The court concludes that NTL-06 does not breach any term of the
    lease.
    Under the regulations in effect when plaintiffs executed their lease, lessees
    were required to include a blowout scenario with their EP. 
    30 C.F.R. § 250.213
    (g).
    In addition, lessees were required to include an OSRP with their EP, or they could
    refer to a previously approved regional OSRP. 
    Id.
     § 250.219. The OSRP, in turn,
    was required to include the lessee’s calculation for worst-case discharge volume.
    Id. §§ 250.219(a)(2)(iv), 254.26(a). The lessees were instructed to “provide any
    assumptions made and the supporting calculations used to determine this volume,”
    id. § 254.26(a); additionally, the regulations set forth a number of assumptions that
    had to be made in calculating the worst-case discharge volume, id. § 254.47.
    Under the regulations in effect for EPs, plaintiffs were required to attest that they
    “have or will have the financial capability to drill a relief well and conduct other
    emergency well control operations” and they were also required to demonstrate
    sufficient Oil Spill Financial Responsibility (OSFR), which is often satisfied with a
    bond. See id. § 250.213(e).
    In essence, plaintiffs argue that the regulations set forth a limited number of
    assumptions that had to be made when calculating the worst-case discharge
    24
    / Plaintiffs argue that, before NTL-06, they were required to certify that they had the
    financial capability to respond to a worst-case discharge volume of 1500 barrels for 30 days;
    following NTL-06, however, plaintiffs state that they must now certify that they have the
    financial capability to respond to a worst-case discharge volume of 142,977 barrels for 120 days.
    Plaintiffs assert that the change in worst-case discharge volume and response time has increased
    their required financial certification amount from only $4.3 million to more than $1.8 billion.
    Pls.’ Mot. at 33-34. Those precise dollar figures, however, are based on a ten-day response with
    a daily volume of 1500 barrels and a 120-day response with a daily volume of 50,000 barrels.
    See Pls.’ Ex. 8 at 2.
    25
    / Plaintiffs also argue that NTL-06 is a substantive regulation that should have been
    issued in accordance with the requirements of notice-and-comment rulemaking. Pls.’ Mot. at 54.
    That argument is not properly before this court. If plaintiffs believe that NTL-06 did not meet
    the procedural requirements of the APA, they are entitled to file a petition for review in district
    court. See 
    5 U.S.C. §§ 702
    , 706(2)(D); Ensco, 
    2010 WL 4116892
    .
    31
    volume, and that NTL-06 added a number of new substantive requirements not
    contained in the regulations. That argument, however, mischaracterizes both the
    nature of the regulations and the effect of the notice. The OSRP regulations do set
    forth a number of assumptions and factors to be considered in calculating the
    worst-case discharge volume, see 
    id.
     § 254.47, and those assumptions are
    incorporated into the regulations that govern EPs, see id. § 250.219, as well as the
    regulations that govern OSFR, see id. § 253.14.
    With respect to the information required for an EP, however, the regulations
    provide that “[o]n a case-by-case basis, the Regional Supervisor may require you
    to submit additional information if the Regional Supervisor determines that it is
    necessary to evaluate your proposed plan or document.” Id. § 250.201(b).
    Similarly, the regulations provide that “[t]he Regional Supervisor may limit the
    amount of information or analysis that you otherwise must provide in your
    proposed plan or document under this subpart” when certain requirements are met.
    Id. § 250.201(c). In other words, the information required for EPs, including the
    required blowout scenario, is not a fixed or stagnant set of requirements, as
    plaintiffs suggest.
    In NTL No. 2008-G04, MMS modified the regulatory requirements by
    reducing the amount of information that operators were required to provide for
    their EPs and DOCDs. See Def.’s Ex. 15. Therefore, plaintiffs in this case
    prepared their EP based not on what the regulations required on their face, but on
    the more limited information required under NTL No. 2008-G04. NTL-06, in turn,
    rescinded NTL No. 2008-G04, and thus required plaintiffs to again provide the
    information originally mandated under the regulations – regulations that were in
    effect when the lease was executed and to which the lease has continually,
    therefore, been subject. Stipulation No. 8 of the lease also requires plaintiffs to
    meet the mitigation measures “outlined in the most current MMS Notices to
    Lessees” issued pursuant to the OCSLA regulations. See Def.’s Ex. 1 at A5.
    Plaintiffs acknowledge in their complaint that the effect of NTL-06 was to
    “rescind[] certain limitations previously put into place by NTL No. 2008-G04.”
    Compl. ¶ 23.
    To the extent that the government requested additional information from
    plaintiffs via electronic mail or other means, see Pls.’ Exs. 21, 25-26, such requests
    were authorized by the regulations in effect when the lease was executed, see 
    30 C.F.R. § 250.201
    (b), and plaintiffs were required to comply with those requests,
    32
    see 
    id.
     § 250.186(a) (“You must submit information and reports as MMS
    requires.”). In sum, the requirements imposed by both NTL-06 and the e-mail
    correspondence from the agency were well within the government’s authority
    under the lease; the regulations in effect when the lease was executed; and the lease
    requirements that subjected operators to the most current NTLs issued pursuant to
    the implementing regulations. The calculations currently required for a worst-case
    discharge scenario are fully consistent with both the lease terms and regulations in
    effect when the lease was executed. Thus, where the referenced calculations have
    now resulted in plaintiffs’ inability to demonstrate their financial capability, that
    inability does not reflect a breach of section 1 or section 2 of plaintiffs’ lease.
    Likewise, the court holds that NTL-06 did not breach section 8 of the lease,
    which provides that “[t]he Lessee shall maintain at all times the bond(s) required
    by regulation prior to the issuance of the lease and shall furnish such additional
    security as may be required by the Lessor if, after operations have begun, the
    Lessor deems such additional security to be necessary.” Def.’s Ex. 1 at A2.
    Plaintiffs argue that the new assumptions and calculations required by NTL-06
    increased their required bond from $35 million to $150 million.
    The court first notes that section 8 of the lease does not impose a duty on the
    government; rather, it imposes a duty on the lessees to secure and maintain a bond
    in the amount required by the regulations in effect on the date of lease execution.
    Section 8 further provides that the government may require the lessees to furnish
    “additional security” if it is deemed to be necessary after the commencement of
    operations on the site. In order to demonstrate a breach of section 8 of the lease,
    plaintiffs must establish that they are now required to furnish a bond that exceeds
    the bond required under the regulations in effect when the lease was executed.
    They have failed to do so.
    Before NTL-06 was issued, plaintiffs were required to maintain their bond in
    accordance with the regulations that were in effect when their lease was executed;
    after the issuance of NTL-06, plaintiffs have remained under an obligation to
    maintain their bond in accordance with the regulations in effect when their lease
    was executed. Contrary to plaintiffs’ assertions, there has been no change in the
    bonding requirements set forth in the regulations; those requirements, from the
    outset, have been based on specified worst-case discharge volumes as follows:
    33
    Worst-Case Discharge Volume                 Applicable Amount of OSFR
    More than 1000 barrels but not more than                  $35,000,000
    35,000 barrels
    More than 35,000 barrels but not more than                $70,000,000
    70,000 barrels
    More than 70,000 barrels but not more than               $105,000,000
    105,000 barrels
    More than 105,000 barrels                                $150,000,000
    
    30 C.F.R. § 253.13
    (b)(1). Under these regulations, moreover, the government may
    require an operator to furnish a bond that exceeds what is set forth in the table
    presented above, based on environmental and other concerns, with an upper limit
    of $150 million. See 
    id.
     § 253.13(b)(3). Neither the table, nor the government’s
    ability to deviate from that table, has changed since plaintiffs executed their lease.
    Compare 
    30 C.F.R. § 253.13
    (b)(1), (b)(3) with 
    30 C.F.R. § 553.13
    (b)(1), (b)(3)
    (2012).
    NTL-06 does not require plaintiffs to furnish a bond that exceeds what was
    required under the regulations in effect when they signed their lease; instead, what
    has changed are the underlying factors that determine which category the required
    bond amount falls under – specifically, plaintiffs’ worst-case discharge volume.
    Because that volume was only 1500 barrels before NTL-06 became effective,
    plaintiffs fell within the category requiring only a $35 million bond under the
    regulations. NTL-06 changed the calculation of worst-case discharge volume, and
    had the effect of increasing that volume to 142,977 barrels for plaintiffs’ proposed
    operations under their lease. Under the regulations in effect when plaintiffs signed
    their lease – and under the regulations in effect today – a worst-case discharge
    volume of that magnitude places plaintiffs in the highest category and requires
    them to furnish a bond in the amount of $150 million. The court has already held
    that the changes in the calculation of worst-case discharge volume effected through
    NTL-06 did not breach plaintiffs’ lease. Similarly, the fact that the new
    calculations raised plaintiffs’ discharge volumes and consequently elevated
    plaintiffs’ bond requirement to a higher category does not reflect a breach of
    section 8 of the lease by defendant.
    Plaintiffs are correct that the government may not, consistent with section 8,
    34
    require them to furnish a bond that exceeds what the regulations required when the
    lease was signed until after operations have commenced. In this case, however, the
    government has never required plaintiffs to furnish a bond that exceeds what the
    regulations have always required. In any event, even if the court has misread the
    language of section 8, and NTL-06 has in fact breached section 8 of the lease, the
    government is nonetheless protected from liability for such a breach under the
    sovereign acts doctrine, as discussed more fully infra.
    iii.   NTL-10 Did Not Breach the Lease
    Plaintiffs argue that NTL-10 breached their lease by imposing substantial
    new costs on their performance. NTL-10 does set forth two new requirements,
    but neither of them breaches plaintiffs’ lease. First, the notice requires operators
    to certify, through an “authorized company official,” that its activities will comply
    with applicable regulations, including the new regulations that were issued in 2010.
    Def.’s Ex. 26 at A501-A502. The court has already held that those regulations did
    not breach plaintiffs’ lease, so plaintiffs fail to establish why requiring an operator
    to certify its compliance with them, and with other pre-existing regulations, would
    do so.
    NTL-10 also informs operators that “BOEMRE will evaluate whether each
    operator has submitted adequate information demonstrating that it has access to
    and can deploy surface and subsea containment resources that would be adequate
    to promptly respond to a blowout or other loss of well control.” Def.’s Ex. 26 at
    A502. The regulations that were in effect when plaintiffs signed their lease, and
    that remain in effect today, require plaintiffs to demonstrate that they have both the
    financial capability to respond to a worst-case discharge scenario and access to the
    equipment needed to do so. See 
    30 C.F.R. §§ 250.213
    (e), 254.23-254.26; see also
    
    30 C.F.R. §§ 550.213
    (e) (2012). The regulations also provide that “[i]n addition to
    the requirements listed in this part, [operators] must provide any other information
    the Regional Supervisor requires for compliance with appropriate laws and
    regulations.” 
    30 C.F.R. § 254.5
    (d). NTL-10 does not breach plaintiffs’ lease.
    d.    The Categorical Exclusions Memorandum Did Not
    Breach the Lease
    Plaintiffs assert that the memorandum issued by the Director of BOEMRE
    on August 16, 2010 breached their lease. That memorandum stated that the agency
    35
    would review its use of categorical exclusions for certain plans and documents, and
    that those plans and documents would not be categorically excluded from NEPA
    during the pendency of the agency’s review. See Def.’s Ex. 21. Plaintiffs assert
    that this change has increased the costs of their performance under the lease, see
    Pls.’ Mot. at 56, and has therefore breached the lease. Plaintiffs are incorrect.
    Plaintiffs’ lease is subject to NEPA and its implementing regulations, at least
    those regulations that were in effect when the lease was executed. Under NEPA,
    agencies may exempt certain categories of activities from environmental review
    when they “do not individually or cumulatively have a significant effect on the
    human environment and have been found to have no such effect in procedures
    adopted by a Federal agency.” 
    40 C.F.R. § 1508.4
    . The categorical exclusion of
    activities from environmental review was and is within the discretion of individual
    agencies; nothing in plaintiffs’ lease can be read to provide static treatment for
    their activities in perpetuity. In fact, the regulations then in effect expressly state
    that the government would perform the environmental reviews and documentation
    required by NEPA in reviewing EPs. See 
    30 C.F.R. § 250.232
    (c). The categorical
    exclusions memorandum did not breach any term of plaintiffs’ lease.
    2.     This Court May Not Hear Plaintiffs’ Challenges to the
    Substantive Validity of the Government’s Actions
    In their motion, plaintiffs argue that this court is empowered to review the
    government’s actions in this case under the standard of judicial review set forth in
    section 706 of the APA. By its own terms, the lease is subject to statutes that were
    in existence on the effective date of the lease. Plaintiffs therefore argue that the
    substantive standard of review described in the APA is, in effect, a term of the
    lease, which was breached when the government imposed requirements on lessees
    that were, according to plaintiffs, arbitrary and capricious. As discussed above,
    section 1 of plaintiffs’ lease states that
    [t]his lease is issued pursuant to the Outer Continental
    Shelf Lands Act of August 7, 1953, 
    67 Stat. 462
    ;
    
    43 U.S.C. § 1331
     et seq., as amended (
    92 Stat. 629
    ),
    (hereinafter called the “Act”). The lease is issued subject
    to the Act; all regulations issued pursuant to the Act and
    in existence upon the Effective Date of this lease; all
    regulations issued pursuant to the statute in the future
    36
    which provide for the prevention of waste and
    conservation of the natural resources of the Outer
    Continental Shelf and the protection of correlative rights
    therein; and all other applicable statutes and regulations.
    Def.’s Ex. 1 at A1. Plaintiffs argue that the term “other applicable statutes,” as
    used in section 1, must be interpreted to include the APA. The court disagrees
    because that term of the lease applies only to “applicable statutes,” and the court
    concludes that the APA is not applicable.
    There is no question that this court is without subject matter jurisdiction over
    claims under the APA. See Lion Raisins, Inc. v. United States, 
    416 F.3d 1356
    ,
    1370 n.11 (Fed. Cir. 2005) (“Of course, no APA review is available in the Court of
    Federal Claims.”); Crocker v. United States, 
    125 F.3d 1475
    , 1476 (Fed. Cir. 1997)
    (affirming that this court “lacks the general federal question jurisdiction of the
    district courts, which would allow it to review the agency’s actions and to grant
    relief pursuant to the Administrative Procedure Act”); Murphy, 
    993 F.2d at 874
    (Fed. Cir. 1993) (“[T]he Claims Court has no authority to invoke the APA.”).
    Interior cannot, through its standard lease forms, somehow endow this court
    with jurisdiction over claims challenging government action under the APA;
    Congress has vested subject matter jurisdiction over such claims in other fora. Cf.
    Belk v. United States, 
    858 F.2d 706
    , 711 (Fed. Cir. 1988) (Bennett, J. concurring)
    (“Further, the parties cannot by their consent confer jurisdiction on a court.”).
    To the extent that plaintiffs seek to challenge the reasonableness or substantive
    validity of the government’s actions, they have an available remedy in the district
    courts. See Bowen v. Massachusetts, 
    487 U.S. 879
    , 891 n.16 (1988) (noting that
    federal district courts may review agency action under the APA pursuant to their
    federal question jurisdiction); Russell v. United States, 
    78 Fed. Cl. 281
    , 288 (2007)
    (noting that “the APA confers jurisdiction for judicial review of final agency
    decisions on the United States district court and not the Court of Federal Claims”);
    McNabb v. United States, 
    54 Fed. Cl. 759
    , 767 (2002) (holding that “APA reviews
    are conducted in federal district court rather than the Court of Federal Claims”).
    Because this court has no jurisdiction to hear plaintiffs’ claims challenging the
    substantive validity or reasonableness of the government’s actions, the APA cannot
    37
    be construed as an “applicable statute” under section 1 of the lease.26
    3.      The Government Did Not Breach Its Implied Duty of
    Good Faith and Fair Dealing
    Plaintiffs further argue that the government has breached the implied duty of
    good faith and fair dealing by dramatically increasing their costs of performance
    under the lease. In plaintiffs’ view, even if the APA is not incorporated as an
    express term of the lease under section 1, an implied duty imposes the exact same
    standard of conduct on the government. In other words, when the government acts
    in a manner that is arbitrary or capricious, it necessarily breaches the implied duty
    of good faith and fair dealing, according to plaintiffs, even if such conduct does not
    breach any express term of the lease. Defendant, in contrast, argues that the duty
    must be tethered to an express term of the lease and cannot create new obligations
    that do not appear on the face of the lease. On that point, defendant is correct.
    The covenant of good faith and fair dealing is implied in every contract and
    imposes certain obligations on the contracting parties, including a duty not to
    “interfere with the other party’s performance and not to act so as to destroy the
    reasonable expectations of the other party regarding the fruits of the contract.”
    Centex Corp. v. United States, 
    395 F.3d 1283
    , 1304 (Fed. Cir. 2005); see also
    Restatement (Second) of Contracts § 205 (“Every contract imposes upon each
    party a duty of good faith and fair dealing in its performance and its
    enforcement.”).
    In Precision Pine & Timber, Inc. v. United States, 
    596 F.3d 817
     (Fed. Cir.
    26
    / The court notes that certain statutes are clearly “applicable” in that they are part of the
    comprehensive scheme that governs offshore exploration and development, and many of those
    statutes are in fact expressly referenced in the lease, in the statute, or in the regulations. See,
    e.g., Def.’s Ex. 1 at A5 (the Endangered Species Act and the Marine Mammal Protection Act);
    
    43 U.S.C. § 1351
    (d) (CZMA); 
    id.
     § 1351(e) (NEPA). In contrast, the Federal Circuit has refused
    to read general contract terms as incorporating specific rights under the APA and other statutes.
    See, e.g., Nat’l Leased Hous. Ass’n v. United States, 
    105 F.3d 1423
    , 1431-33 (Fed. Cir. 1997)
    (rejecting the plaintiffs’ argument that a provision in a housing assistance payment contract,
    which made the parties subject to “all applicable regulations,” incorporated the rulemaking
    procedures of the APA, 
    5 U.S.C. §§ 551
    , 553 (2006), or the disclosure requirements of the
    Freedom of Information Act, 
    5 U.S.C. § 552
     (2006)). Plaintiffs’ expansive reading of section 1
    would incorporate the entire United States Code as a term of the lease.
    38
    2010), the plaintiff in that case argued that the government breached the implied
    duty of good faith and fair dealing when it suspended timber harvesting activities
    under a number of contracts. The court first explained that the government
    breaches the implied duty “when the subsequent government action is specifically
    designed to re-appropriate the benefits the other party expected to obtain from the
    transaction, thereby abrogating the government’s obligations under the contract.”
    
    Id. at 829
    . In that case, however, the court concluded that the government had not
    breached the implied duty because there was no evidence that the challenged
    suspensions “were undertaken for the purpose of delaying or hampering [the]
    contracts.” 
    Id. at 830
    .
    The court in Precision Pine explained that “[t]he implied duty of good faith
    and fair dealing cannot expand a party’s contractual duties beyond those in the
    express contract or create duties inconsistent with the contract’s provisions.” 
    Id. at 831
    . In that case, the court noted that the plaintiff had acquired the right to harvest
    timber, but also explained that the right was expressly qualified by a contract
    clause under which the plaintiff agreed to interrupt or delay activities under the
    contract in order to prevent environmental degradation or to comply with a court
    order. Because the challenged suspension was expressly contemplated under the
    terms of the contract, the court held that it did not result in a breach of the implied
    duty of good faith and fair dealing.
    In Scott Timber Co. v. United States, 
    692 F.3d 1365
     (Fed. Cir. 2012), the
    Federal Circuit applied the same legal standard in similar factual circumstances.
    Following its earlier decision in Precision Pine, the court held that there was no
    breach of the implied duty of good faith and fair dealing when the government
    suspended timber harvesting contracts for what the plaintiff asserted was an
    unreasonable period of time. The court held that there was no evidence that the
    government had targeted the suspended contracts for the purpose of preventing
    performance by the plaintiff or to re-appropriate any benefit under the contract.27
    
    Id. at 1374-75
    .
    Here, likewise, there is no evidence that the government’s actions targeted
    plaintiffs’ lease for the purpose of re-appropriating any of plaintiffs’ benefits under
    27
    / There is substantial overlap between the Federal Circuit’s approach to the implied
    duty of good faith and fair dealing, and the “public and general” inquiry required under the
    sovereign acts doctrine, discussed infra.
    39
    the lease. Plaintiffs argue that their claim is tethered to section 2 of the lease,
    which grants them the “exclusive right and privilege to drill for, develop, and
    produce the oil and gas resources” on the leased area. Pls.’ Mot. at 73-74. Much
    like the contract rights at issue in Precision Pine, however, plaintiffs’ rights under
    their lease are limited by its express terms, as well as the statutory and regulatory
    requirements incorporated by reference. Because the government’s actions were
    authorized under the lease and applicable law, they cannot breach the implied duty
    of good faith and fair dealing. See Precision Pine, 
    596 F.3d at 830
    ; see also 13
    Richard A. Lord, Williston on Contracts § 63:22 (2000) (“As a general principle,
    there can be no breach of the implied promise or covenant of good faith and fair
    dealing where the contract expressly permits the actions being challenged, and the
    defendant acts in accordance with the express terms of the contract.”).
    Plaintiffs assert that the implied duty has been breached because the actions
    taken by the government have dramatically increased plaintiffs’ costs. However,
    there is no express term in the lease that immunizes them from future increases in
    their costs of performance. See Bradley v. Chiron Corp., 
    136 F.3d 1317
    , 1326
    (Fed. Cir. 1998) (noting that “implied covenants of good faith and fair dealing are
    limited to assuring compliance with the express terms of the contract and cannot be
    extended to create obligations not contemplated in the contract”).
    Finally, the record indicates that the government has acted in good faith,
    granting plaintiffs an extension of their lease to afford them additional time to
    comply with the new regulatory requirements and to account for any time lost due
    to the moratoria on permitting and other activities. The lease extension further
    undermines plaintiffs’ assertion that the government targeted their contracts for the
    purpose of preventing performance or to re-appropriate a benefit for itself.28 Cf.
    Conner Bros. Constr. Co. v. United States, 
    550 F.3d 1368
    , 1378 (Fed. Cir. 2008)
    28
    / Plaintiffs argue that the extension granted to them is not evidence of the government’s
    good faith because such an extension was required under OCSLA. See, e.g., Pls.’ Mot. at 66.
    However, the section of OCSLA referenced by plaintiffs does not require the Secretary to grant
    extensions to any particular lessee; rather, it simply requires the Secretary to promulgate
    regulations providing for such extensions. See 
    43 U.S.C. § 1334
    (a)(1) (stating that the
    “regulations prescribed by the Secretary under this subsection shall include, but not be limited
    to, provisions . . . for the extension of any such permit or lease affected by suspension . . . by a
    period equivalent to the period of such suspension . . ., except that no permit or lease shall be so
    extended when such suspension . . . is the result of gross negligence or willful violation of such
    lease or permit, or of regulations issued with respect to such lease or permit”).
    40
    (“The Corps of Engineers did not seek to shift its costs to [the plaintiff], and it
    granted [the plaintiff] contract extensions to compensate for the period in which
    [the plaintiff] was shut down.”).
    C.     Even if the Court Were to Hold that the Government Breached
    Plaintiffs’ Lease, It Would Be Shielded from Liability under the
    Sovereign Acts Doctrine
    The government argues that even if its actions breached the lease, it is still
    immune from liability under the sovereign acts doctrine. In that regard, defendant
    contends that the reforms adopted in the wake of the Deepwater Horizon disaster
    were public and general in nature, and that those sovereign actions rendered its
    contractual performance under the original lease impossible. Plaintiffs, in contrast,
    argue that the doctrine does not apply in this case because the government’s
    actions were not public and general, but were instead nothing more than an effort
    to escape its contractual obligations. The court agrees with defendant.
    1.     Applicable Law
    The sovereign acts doctrine is a variation of the common law doctrine of
    impossibility, adapted for the unique circumstances faced by the government as a
    contractor. Under the impossibility doctrine, also known as the impracticability
    doctrine,
    [w]here, after a contract is made, a party’s performance is
    made impracticable without his fault by the occurrence of
    an event the non-occurrence of which was a basic
    assumption upon which the contract was made, his duty
    to render that performance is discharged, unless the
    language or the circumstances indicate the contrary.
    Restatement (Second) of Contracts § 261. The impossibility doctrine applies to,
    inter alia, statutory, regulatory, or other legal changes that render performance by
    one of the contracting parties impracticable:
    If the performance of a duty is made impracticable by
    having to comply with a domestic or foreign
    governmental regulation or order, that regulation or order
    41
    is an event the non-occurrence of which was a basic
    assumption on which the contract was made.
    Id. § 264; see Hicks v. United States, 
    89 Fed. Cl. 243
    , 258 (2009) (noting that the
    the doctrine may be applied when performance by one of the parties is rendered
    impracticable because of an intervening government order).
    In general, the impossibility defense is not available when the barrier to
    performance was created by the party seeking to invoke the defense. See
    Restatement (Second) of Contracts § 261 (limiting a contractor’s use of the defense
    to impracticability caused by the occurrence of an event “without his fault”); id.
    § 261, comment d (“If the event is due to the fault of the obligor himself, this
    Section does not apply.”). The sovereign acts doctrine was established in the early
    years of the Court of Claims, see Wilson v. United States, 
    11 Ct. Cl. 513
     (1875);
    Jones v. United States, 
    1 Ct. Cl. 383
     (1865); Deming v. United States, 
    1 Ct. Cl. 190
    (1865), and addresses situations in which the government’s acts as a sovereign
    render the performance of its duties as a contractor impracticable. In such cases,
    “[t]he two characters which the government possesses as a contractor and as a
    sovereign cannot be thus fused; nor can the United States while sued in the one
    character be made liable in damages for their acts done in the other.” Jones, 1 Ct.
    Cl. at 384.
    In those early cases, the court emphasized that the sovereign acts doctrine
    did not afford any special treatment for the government. Rather, its purpose was to
    ensure that the government as contractor was treated the same as any private
    contractor whose performance was rendered impracticable by an intervening act of
    the government. See id. (“In this court the United States appear simply as
    contractors; and they are to be held liable only within the same limits that any other
    defendant would be in any other court.”); Deming, 1 Ct. Cl. at 191 (“In this court
    the United States can be held to no greater liability than other contractors in other
    courts.”).
    In order to ensure that the government was afforded the same treatment as a
    private contractor, the court held that it was necessary to draw a sharp distinction
    between the government-as-sovereign and the government-as-contractor, and that
    the distinction between the two would be maintained as long as the sovereign acts
    that rendered performance impracticable were “public and general.” See Jones,
    1 Ct. Cl. at 384 (“Whatever acts the government may do, be they legislative or
    42
    executive, so long as they be public and general, cannot be deemed specially to
    alter, modify, obstruct or violate the particular contracts into which it enters with
    private persons.”); see also Wilson, 11 Ct. Cl. at 521 (“This double character of the
    Government cannot be lost sight of in any of its transactions.”); Deming, 1 Ct. Cl.
    at 191 (“The United States as a contractor are not responsible for the United States
    as a lawgiver.”).
    The doctrine was later adopted by the Supreme Court of the United States,
    see Horowitz v. United States, 
    267 U.S. 458
    , 461 (1925) (“It has long been held by
    the Court of Claims that the United States when sued as a contractor cannot be held
    liable for an obstruction to the performance of the particular contract resulting from
    its public and general acts as a sovereign.”), and it has been applied in a number of
    cases by this court and the Federal Circuit. In the leading case on the doctrine, the
    Supreme Court explained that
    [t]he sovereign acts doctrine thus balances the
    Government’s need for freedom to legislate with its
    obligation to honor its contracts by asking whether the
    sovereign act is properly attributable to the Government
    as contractor. If the answer is no, the Government’s
    defense to liability depends on the answer to the further
    question, whether that act would otherwise release the
    Government from liability under ordinary principles of
    contract law.
    United States v. Winstar Corp., 
    518 U.S. 839
    , 896 (1996).
    In subsequent years, the Federal Circuit has followed the general approach
    set forth by the Court of Claims in its earliest cases on the sovereign acts doctrine.
    First, that court has explained that the government-as-sovereign must be separated
    from the government-as-contractor, and that the latter must be treated in the same
    manner as any private contractor:
    The basic notion of the sovereign acts doctrine is that the
    United States as a contracting party acts in a different
    capacity from its role as a sovereign. As a contractor, it
    stands in the same shoes as any private party would in
    dealing with another private party; as a sovereign, it
    43
    stands apart. The acts of one are not to be ‘fused’ with
    the other – if an act of the Government as sovereign
    would justify non-performance by any other defendant
    being sued for contract breach, then the Government as
    contractor is equally free from liability for non-
    performance.
    Stockton East, 
    583 F.3d at 1366
    .
    Further, when the government’s actions render performance impracticable,
    those actions will be viewed as sovereign acts only if they are public and general,
    while any interference with the government’s contracts must be only incidental.
    See Klamath Irrigation Dist. v. United States, 
    635 F.3d 505
    , 520 (Fed. Cir. 2011)
    (“The government is not liable for breach of contract whenever it takes any
    generally applicable action in its sovereign capacity that incidentally frustrates
    performance of a contract to which it is a party.”); see also Winstar, 
    518 U.S. at 896
     (noting that “governmental action will not be held against the Government for
    purposes of the impossibility defense so long as the action’s impact upon public
    contracts is, as in Horowitz, merely incidental to the accomplishment of a broader
    governmental objective”).
    In contrast, the sovereign acts defense never applies when the government’s
    actions were designed to target its contractual obligations or when those actions
    have the substantial effect of releasing it from its obligations. See Winstar, 
    518 U.S. at 899
     (explaining that a government action is not public and general when
    “it has the substantial effect of releasing the Government from its contractual
    obligations”); Stockton East, 
    583 F.3d at 1366
     (noting that the relevant question is
    whether the “act [is] simply one designed to relieve the Government of its contract
    duties, or is it a genuinely public and general act that only incidentally falls upon
    the contract?”); Conner Bros., 550 F.3d at 1374 (“[T]he sovereign acts defense is
    unavailable where the governmental action is specifically directed at nullifying
    contract rights.”); Yankee Atomic Elec. Co. v. United States, 
    112 F.3d 1569
    , 1575
    (Fed. Cir. 1997) (“The Government-as-contractor cannot exercise the power of its
    twin, the Government-as-sovereign, for the purpose of altering, modifying,
    obstructing or violating the particular contracts into which it had entered with
    private parties.”).
    Finally, even if the government demonstrates that its actions were sovereign
    44
    in nature, it must still prove that those actions rendered its performance impossible.
    Casitas Mun. Water Dist. v. United States, 
    543 F.3d 1276
    , 1287 (Fed. Cir. 2008)
    (“[P]erformance by the government is excused under the sovereign acts defense
    only when the sovereign act renders the government’s performance impossible.”).
    However, the Federal Circuit “and its predecessor have long recognized that the
    doctrine of impossibility does not require a showing of actual or literal
    impossibility of performance but only a showing of commercial impracticability.”
    Seaboard Lumber Co. v. United States, 
    308 F.3d 1283
    , 1294 (Fed. Cir. 2002).
    For the reasons noted below, the court concludes that the actions challenged here
    were sovereign in nature – i.e., they were public and general – and rendered the
    government’s performance under the lease not only impracticable, but legally
    impossible.
    2.    The Government’s Response to the Deepwater Horizon
    Disaster Was a Sovereign Act
    The government asserts that the actions challenged by plaintiffs in this case
    were designed to achieve important public purposes, such as drilling safety and
    environmental protection, and were not an attempt to relieve the government of its
    contractual obligations. Plaintiffs disagree, arguing that the government’s actions
    fail to meet the first prong of the sovereign acts defense for two different reasons.
    First, plaintiffs argue that the government has not established that its response to
    the Deepwater Horizon disaster was truly motivated by its ostensible objectives.
    Rather, according to plaintiffs, it is possible that the government may have used the
    disaster as a mere pretext for escaping its duties under the lease. Second, plaintiffs
    argue that the government’s actions were not public and general because they did
    not directly affect anyone other than OCS lessees.
    The Supreme Court and the Federal Circuit have identified a number of
    questions that are relevant to a court’s determination of whether a sovereign act is
    public and general in nature. First, was the government action designed for the
    specific purpose of abrogating its contractual obligations? This inquiry focuses on
    the government’s intent. Second, was the primary consequence of the government
    action to release the government from its contracts or otherwise confer some
    material benefit on the government as a contractor? This inquiry focuses on the
    effects of the government’s action. Finally, was the government action targeted
    solely at its contracting partners or did it have a broader impact? This inquiry
    focuses on the distribution or scope of the government’s action. For the reasons
    45
    discussed below, the court holds that each of these factors leads to the conclusion
    that the government was acting in its sovereign capacity when it adopted the
    regulatory reforms now challenged by plaintiffs.
    a.     The Government Did Not Engage in the Challenged
    Actions for the Purpose of Escaping Its Obligations
    Plaintiffs assert that the moratoria, the new regulations, and the guidance
    issued through NTLs were not really intended to ensure human safety, protect the
    environment, or conserve the natural resources of the OCS. Instead, according to
    plaintiffs, the disaster merely provided a convenient excuse for the government to
    disregard its obligations under the lease. See Pls.’ Mot. at 2 (asserting that there
    “are disputed issues of material fact regarding the promulgation and scope of the
    rules and regulations and the Government’s bad faith and unfair dealing”); 63
    (asserting that “the precise purpose of the reform efforts” was to release the
    government from its contractual obligations); Pls.’ Reply at 17 (“Plaintiffs dispute
    the Government’s unsubstantiated conclusions that its actions and inactions
    following Deepwater Horizon were ‘for the prevention of waste and conservation
    of the natural resources of the Outer Continental Shelf and the protection of
    correlative rights therein’ within the contemplation of Section 1 of the Lease, or
    were ‘public and general’ for purposes of the sovereign acts and unmistakability
    doctrines.”).
    The Federal Circuit has held that actions carried out with the purpose of
    relieving the government-as-contractor of its duties are not sovereign in nature.
    See Conner Bros., 550 F.3d at 1374 (“[W]hen considering whether the alleged
    sovereign act is exclusively directed to aborting performance of government
    contracts, courts addressing the sovereign acts doctrine have looked to the extent to
    which the governmental action was directed to relieving the government of its
    contractual obligations.”). Plaintiffs argue, in effect, that the government’s actions
    in this case were designed with the purpose of escaping its contractual obligations.
    In Yankee Atomic, 
    112 F.3d at 1569
    , the government entered into contracts
    with a number of nuclear utilities, under which it agreed to provide uranium
    enrichment services to those utilities at fixed prices. Many years later, the
    government discovered that decontaminating and decommissioning the facilities
    used to enrich uranium under its earlier contracts might exceed $20 billion over
    forty years. In order to cover those unexpected costs, Congress imposed a special
    46
    assessment on all domestic utilities that had purchased uranium enrichment
    services in the past, whether those services were purchased directly from the
    government or from another party on the secondary market. The plaintiff in that
    case argued that the special assessments breached its earlier contract with the
    government for uranium enrichment services by retroactively increasing the price
    of those services.
    The Federal Circuit rejected that argument and held that the government was
    protected from liability under the sovereign acts doctrine. The court focused on the
    purpose of the governmental action – i.e., on whether the legislation imposing the
    special assessment was enacted for the benefit of the government-as-contractor or
    for the benefit of the public. The court concluded that “Congress’s main purpose
    was to spread the costs of a problem that it realized only after the contracts had
    been performed.” 
    Id. at 1575-76
    . In addition, the Federal Circuit distinguished the
    Supreme Court’s earlier decisions in Lynch v. United States, 
    292 U.S. 571
     (1934),
    and Perry v. United States, 
    294 U.S. 330
     (1935), explaining that those cases
    “involved situations where the congressional act made clear that its purpose was, at
    least in part, to abrogate past public contracts.” Yankee Atomic, 
    112 F.3d at 1577
    .
    In short, what the Federal Circuit found most important was whether the action
    asserted by the government to be a sovereign act was designed to benefit the
    government-as-contractor or the public. See 
    id. at 1575
     (“Thus, it is not a hard and
    fast rule, but rather a case-specific inquiry that focuses on the scope of the
    legislation in an effort to determine whether, on balance, that legislation was
    designed to target prior governmental actions.”).
    Similarly, in Conner Bros., 550 F.3d at 1368, the Federal Circuit held that
    the government’s actions were not motivated by an intent to benefit the
    government as a contractor, but were instead based on important and unrelated
    national security concerns. There, the plaintiff was constructing a headquarters
    facility for the Army Rangers at Fort Benning, Georgia, but was temporarily
    denied access to the construction site following the events of September 11, 2001.
    The Federal Circuit denied the contractor’s claim for delay damages and held that
    the government was protected from liability under the sovereign acts doctrine. In
    reaching that decision, the court emphasized that the purpose of the exclusion order
    was to maintain security, not to relieve the government of its contractual
    obligations:
    The Army did not exclude [the contractor] from the
    47
    worksite because it was unhappy with [its] performance,
    or because it was unhappy with the contract price, or
    because it decided that it no longer wanted a new Ranger
    headquarter facility. Rather, [the commander] made a
    determination that excluding [the contractor] directly
    served the government’s broader objective of restricting
    access to the compound in order to minimize potential
    threats to operational security and to facilitate
    deployment.
    550 F.3d at 1377.
    Here, plaintiffs’ argument simply strains credulity. The record compiled by
    the parties in this case is replete with contemporaneous documents discussing the
    impacts of the Deepwater Horizon disaster, and explaining how the augmented
    regulatory regime would reduce the risk of such a catastrophic event in the future.
    The court concludes that there is no genuine issue of material fact as to whether the
    purposes of the government’s reform efforts were to ensure human safety, protect
    the environment, and conserve the natural resources of the OCS.29
    b.      The Government Gained No Material Benefit by
    Virtue of the Challenged Actions
    In addition to examining the purpose of the government’s actions, courts
    have reviewed whether those actions would inure to the benefit of the government
    in its role as a contractor. See Conner Bros., 550 F.3d at 1378 (finding it relevant
    that the “government gained no economic advantage” in exercising its sovereign
    powers); see also Winstar, 
    518 U.S. at 896
     (noting that the sovereign acts doctrine
    is inapplicable to governmental actions tainted by an object of “self-interest” or
    “self-relief”). Here, there is no evidence that the government will derive any
    economic or other material benefit by virtue of its actions in the wake of the
    Deepwater Horizon disaster. Rather, it appears that those actions might actually
    impose significant economic costs and administrative burdens on the government.
    29
    / In contrast, there is a genuine dispute between the parties with respect to whether the
    government’s specific responses to the disaster were reasonable, but, for the reasons discussed
    above, that issue is not properly before the court in this case.
    48
    First, the government states that the administrative burden of implementing
    its new regulatory requirements will be substantially greater than the burden of
    administering leases under the earlier regulatory regime. Plaintiffs do not dispute
    that assertion. Given the amount of new information required from operators,
    which plaintiffs argue will impose a nearly insurmountable burden upon them,
    the government’s predictions of increased burdens of its own appear to be well-
    founded.
    Further, to the extent that the new regulatory requirements delay or foreclose
    exploration and production activities under existing leases, as plaintiffs predict
    they will, the government stands to incur substantial economic losses due to
    unrealized royalties. In this case, neither the purpose nor the consequence of the
    government’s actions is to release the government from its contractual obligations
    or to confer an economic or other material benefit upon the government. Thus, the
    substantial effect of the regulatory reforms challenged by plaintiffs supports the
    government’s assertion of the sovereign acts doctrine.
    Plaintiffs fare no better in their contention that this is a “change of heart”
    case, asserting that “in response to Deepwater Horizon, the Government lowered
    its acceptable level of risk and imposed new conditions on its obligations to allow
    drilling – mandatory conditions commensurate with its new, lower tolerance for
    risk.” Pls.’ Mot. at 66. Plaintiffs’ argument is based on the faulty assumption that
    it was the government, rather than plaintiffs, who agreed to bear the costs of
    responding to a catastrophic blowout or other similar event under the lease.
    Section 14 of the lease states that “[t]he Lessee shall indemnify the Lessor for, and
    hold it harmless from, any claim, including claims for loss or damage to property
    or injury to persons resulting from any operation on the leased area conducted by
    or on behalf of the Lessee.” Def.’s Ex. 1 at A6. In addition, the regulations in
    effect when the lease was executed state that the lessee or operator “must
    immediately control, remove, or otherwise correct any hazardous oil and gas
    accumulation or other health, safety, or fire hazard.” 
    30 C.F.R. § 250.107
    (b); see
    generally 
    id.
     pt. 253 (requiring lessees to demonstrate sufficient OSFR); 
    id.
     pt. 254
    (requiring lessees to submit an OSRP). The challenged reforms do not protect the
    government from exposure to risks it assumed under the lease. Rather, they ensure
    that the parties contractually responsible for responding to blowouts and spills –
    lessees and operators – are actually able to meet their responsibilities.
    49
    c.     The Impact of the Government’s Actions Are Broad
    and Are Not Limited to the OCS Lessees
    In plaintiffs’ view, the government’s actions in this case are not protected by
    the sovereign acts doctrine, regardless of whether they serve an important public
    purpose, because they are targeted exclusively at OCS lessees. The Federal Circuit
    has explained that “[a]nother factor relevant to the ‘public and general’ inquiry is
    whether the governmental action applies exclusively to the contractor or more
    broadly to include other parties not in a contractual relationship with the
    government.” Conner Bros., 550 F.3d at 1375. In this case, it is clear that the
    government’s actions will have impacts on parties other than the OCS lessees.
    Further, those actions are clearly designed to prevent another catastrophic oil spill
    – an event that, like the Deepwater Horizon disaster, would have immeasurable
    impacts on parties other than the lessees.
    Plaintiffs assert that the environmental and safety risks the new regulations
    and requirements are designed to address were created by contract and exist only
    because the government has decided to allow exploration and production on the
    OCS pursuant to those contracts. Further, plaintiffs note that many of the new
    requirements were issued as NTLs, which by definition apply only to OCS lessees.
    The fact that subcontractors and service providers may be impacted by the
    regulations is irrelevant, plaintiffs argue, because the only parties directly affected
    by the new requirements are lessees.
    First, as defendant notes, the Federal Circuit has applied the sovereign acts
    doctrine to government actions that directly affected only its contracting partners
    and addressed risks that were created by the existence of the affected contracts.
    In Klamath, 
    635 F.3d at 505
    , and Casitas, 
    543 F.3d at 1276
    , for example, the
    Federal Circuit held that the government’s actions in those cases were sovereign,
    even though the water reductions affected only the plaintiff water districts and
    addressed environmental risks that were created by the reclamation projects.
    The government argues that a sovereign act is public and general when it
    impacts parties that are not in contractual privity with the government. Plaintiffs,
    in contrast, argue that such an act is public and general only when it affects parties
    that have absolutely no connection to the contracts. The government’s position is
    consistent with case law from this court and the Federal Circuit. In Yankee Atomic,
    
    112 F.3d at 1575-76
    , for example, the Federal Circuit explained that the special
    50
    assessments in that case were imposed not only on the government’s contracting
    partners, but also on nuclear utilities that purchased uranium enrichment services
    on the secondary market. While those utilities were not parties to the contracts,
    they were certainly connected to them because they purchased enrichment services
    from parties who had purchased those services directly from the government.
    Plaintiffs are incorrect in their assertion that NTLs are addressed to lessees
    alone. While those documents are referred to as “NTLs,” each NTL clearly states
    that it is a “Notice to Lessees and Operators.” See, e.g., Def.’s Ex. 8 at A253.
    Further, not all OCS lessees are operators, nor are all operators OCS lessees. See
    
    30 C.F.R. § 250.150
     (defining an operator as the party the lessees have designated
    as having control over the leased area, and noting that “[a]n operator may be a
    lessee, the MMS-approved designated agent of the lessee(s), or the holder of
    operating rights under an MMS-approved operating rights assignment”). Many of
    the requirements set forth in the NTLs challenged by plaintiffs are directed at
    operators rather than lessees. See, e.g., Def.’s Ex. 26 (stating that BOEMRE will
    evaluate whether operators have adequately demonstrated their access to sufficient
    containment resources in their OSRP) (emphasis added).
    In addition, while the NTLs are sent to OCS lessees and operators, those
    notices and the regulations challenged by plaintiffs have impacts on parties other
    than lessees and operators, and the new requirements they contain are designed to
    reduce the risk of blowouts and other events that could threaten the entire Gulf
    region. It is instructive to note that the plaintiffs in Hornbeck and Ensco, two cases
    upon which plaintiffs rely heavily in this case, were not OCS lessees; they were
    service providers involved in the offshore industry in the Gulf of Mexico.
    3.    The Government’s Sovereign Acts Rendered Performance
    by the Government Impossible
    In addition to proving that its actions were public and general in nature, the
    government must also prove that those actions rendered its performance under the
    lease impracticable. In this case, the impracticability of the performance is plain:
    the government cannot allow plaintiffs to proceed under the old regulatory regime
    without violating the law. Plaintiffs do not contend that the government may allow
    them to explore and develop the leased area in accordance with the requirements
    that were in effect when the lease was originally executed. Instead, plaintiffs argue
    that the government has failed to demonstrate impracticability in this case because
    51
    the lease allocates the risk of unforeseeable regulatory changes to the government.
    In short, plaintiffs assert that the government cannot demonstrate impracticability
    because it breached the lease. Plaintiffs’ argument fails for two reasons.
    First, the sovereign acts doctrine is an affirmative defense, and it applies
    only when there has been a breach of contract. See Conner Bros., 550 F.3d at 1371
    (“The doctrine is an affirmative defense that is an inherent part of every
    government contract.”); see also Stockton East, 
    583 F.3d at 1360
     (“Once the
    Government’s breach of contract has been established, the Government is liable for
    the breach and ensuing damages, unless it can prove an affirmative defense of
    some kind that absolves it from that liability.”). For that reason, the existence of a
    breach does not preclude the applicability of the sovereign acts doctrine; indeed,
    the existence of a breach is a prerequisite to its applicability.30
    Further, plaintiffs’ argument is in direct conflict with the central holding in
    this case: that plaintiffs assumed the risk of future regulations under the lease.
    Because the court has already held that the lease allocates the risk of such changes
    to plaintiffs, it cannot accept a contrary argument that the lease allocates the risk of
    those changes to the government for purposes of the sovereign acts doctrine. The
    government has demonstrated that if the sovereign acts doctrine applies here, the
    reform efforts implemented in the summer and fall of 2010 have rendered its
    performance under the earlier regulatory regime – i.e., by allowing plaintiffs to
    perform under the old rules – legally impossible. See Restatement (Second) of
    Contracts § 264, comment a (“The fact that it is still possible for a party to perform
    if he is willing to break the law and risk the consequences does not bar him from
    claiming discharge.”).
    CONCLUSION
    The court concludes that the actions undertaken by defendant in the wake of
    the Deepwater Horizon disaster did not breach any term of plaintiffs’ lease. In the
    30
    / The court has already held that none of the government’s actions in this case breached
    plaintiffs’ lease, and the court’s discussion of the sovereign acts doctrine necessarily assumes –
    in contrast to the court’s holding on the issue of breach – that the government had breached the
    lease. The court’s two holdings in this case – i.e., that the government did not breach the lease,
    and that the government is protected from liability under the sovereign acts doctrine – are thus
    alternative, rather than complementary.
    52
    alternative, even if the court were to hold that the government breached plaintiffs’
    lease, defendant would be shielded from liability under the sovereign acts doctrine.
    For these reasons, defendant’s motion for partial summary judgment on plaintiffs’
    breach claim is granted, and plaintiffs’ cross-motion for partial summary judgment
    on the same breach claim is denied. The court thus directs the parties to confer for
    the purpose of proposing the most appropriate means for expeditiously resolving
    plaintiffs’ remaining claims.31
    Accordingly, it is hereby ORDERED that
    (1)     Defendant’s Motion for Partial Summary Judgment, filed
    July 13, 2012, is GRANTED;
    (2)     Plaintiffs’ Cross Motion for Partial Summary Judgment, filed
    September 10, 2012, is DENIED;
    (3)     Pursuant to RCFC 54(b), insofar as there is no just reason for delay,32
    the Clerk’s Office is directed to ENTER judgment for defendant as to
    Count I of the complaints of both Century and Champion, and to
    DISMISS that count, with prejudice;
    (4)     The parties are directed to CONFER to determine how they wish to
    proceed with respect to the remaining claims (Count II and Count III);
    31
    / The court notes that Century’s complaint set forth three counts: the breach claim
    (Count I), the takings claim (Count II), and an unspecified claim (Count III), which purports to
    include “any and all other causes of action that the actions and inactions of the United States
    give rise to, including those as described in this Complaint.” Compl. ¶ 63. In the two years
    since Century filed its complaint in this court, plaintiffs have made no attempt to further develop
    or explain the content or jurisdictional basis of the third count of that complaint.
    32
    / In Count II of their complaints, plaintiffs argue that the government has effected an
    uncompensated taking of their contract rights. Because this court’s disposition of Count I of the
    complaint will be critically important to its consideration of Count II, the court believes that a
    final resolution of plaintiffs’ breach claim will promote judicial economy and conserve the
    parties’ resources. For that reason, the court has ordered the entry of judgment on Count I
    pursuant to RCFC 54(b) to afford plaintiffs the opportunity to seek immediate review of this
    court’s decision in the Federal Circuit in the event they determine an appeal is warranted.
    53
    (5)   On or before March 19, 2013, the parties shall CONFER and FILE
    with the Clerk’s Office a redacted copy of this opinion, with any
    material deemed proprietary blacked out and enclosed in brackets, so
    that a copy of the opinion can then be prepared and made available in
    the public record of this matter; and
    (6)   The parties shall FILE a Joint Status Report by March 29, 2013,
    proposing the next steps in this litigation.
    /s/Lynn J. Bush
    LYNN J. BUSH
    Judge
    54