Oak Grove Technologies, LLC v. United States ( 2021 )


Menu:
  •               In the United States Court of Federal Claims
    No. 21-775C
    (Filed Under Seal: October 29, 2021)
    (Filed: November 3, 2021)
    )
    OAK GROVE TECHNOLOGIES, LLC, )
    )
    Plaintiff,             )
    )
    v.
    )
    THE UNITED STATES,                   )
    )
    Defendant,             )
    )
    and                                  )
    )
    F3EA, INC.,                          )
    )
    Defendant-
    Intervenor.            )
    )
    )
    OPINION AND ORDER
    SOLOMSON, Judge.
    I.     BACKGROUND
    In the Court’s decision on the merits of this case, the Court expressed the concern
    that the government’s handling of the administrative record (“AR”) “waste[d] judicial
    resources and undermine[d] trust in both the procurement and disputes processes.”
    Oak Grove Techs., LLC v. United States, -- Fed. Cl. --, 
    2021 WL 3627111
    , at *13 (Aug. 2,
    2021). Accordingly, the Court ordered the government “to show cause why Defendant
    should not be sanctioned for wasting the Court’s (and Plaintiff’s) time and resources on
    these administrative record deficiencies.” 
    Id.
     In particular, pursuant to Rule 11 of the
    Rules of the United States Court of Federal Claims (“RCFC”) and this Court’s inherent
    
    On October 29, 2021, the Court filed, under seal, this opinion and order and provided the
    parties the opportunity to propose redactions. On November 3, 2021, the parties filed agreed-
    upon proposed redactions, ECF No. 91, which are incorporated, in full, in this public version of
    this opinion and order.
    1
    authority, this Court “order[ed] the government to show cause why monetary sanctions
    should not be imposed against Defendant for its piecemeal and improper handling of
    the administrative record in this matter.” 
    Id. at *32
    . The Court specifically instructed
    the government to address its omission of two documents from the originally filed
    administrative record: (1) a Defense Contract Management Agency (“DCMA”) report
    regarding Lukos (also referred to in the record as “Offeror H”), AR 4993–5006; and (2)
    what has been referred to as “the [RM] termination letter,” AR 5388–89, which
    documented the Agency’s removal of the first Source Selection Evaluation Board
    (“SSEB”) Chairperson from his role in the procurement at issue.1 Oak Grove, 
    2021 WL 3627111
    , at *32.
    Regarding the RM termination letter, the Court explained at some length why
    that document was significant to the litigation and why it left the Court “with yet
    further, unanswered questions regarding the Agency’s conduct in this procurement and
    the role [RM] played in it,” as well as concerns regarding the nature of the corrective
    action and the “explanation the government previously provided to the Court
    regarding the initial record omissions.” Oak Grove, 
    2021 WL 3627111
    , at *30. The Court
    noted that it “expect[ed] the government to address these concerns in detail.” 
    Id.
    On August 17, 2021, and August 24, 2021, respectively, the government and
    plaintiff, Oak Grove Technologies, LLC (“Oak Grove”), filed responses to the Court’s
    order to show cause. See ECF No. 75 (“Def. Resp.”); ECF No. 76 (“Pl. Resp.”). Despite
    the Court’s having highlighted particular concerns in its merits decision, as noted supra,
    the government did not address them “in detail” or otherwise. Oak Grove, 
    2021 WL 3627111
    , at *30.
    On August 26, 2021, the Court held a status conference to discuss further
    proceedings in this matter. ECF No. 77. Following that status conference, the Court
    ordered the government to file a reply brief for two purposes: (1) to respond to the
    arguments in Oak Grove’s brief; and (2) to explain specific representations the
    government made in its merits briefs regarding the substance of the Agency’s corrective
    action at issue, which the RM termination letter appeared to contradict. ECF No. 78
    (“August 27, 2021 Order”). The government filed its reply brief on September 7, 2021.
    ECF No. 83 (“Def. Reply”).
    On September 14, 2021, the Court held oral argument on the show cause order.
    ECF No. 89 (“Tr.”).
    After considering the parties’ respective positions, the Court concludes that
    RCFC 11 warrants the imposition of sanctions on the government. The Court does not
    1The Court’s published decision redacted the name of that Agency employee, referred to as
    “RM.”
    2
    hold individual government counsel responsible for the fact that several critical
    documents were originally omitted from the administrative record. That does not
    mean, however, that the United States, acting by and through the Department of the
    Army (the “Agency”), can be let off the hook. The facts of this case and its procedural
    history demand some form of accountability for the government’s mishandling of the
    administrative record.
    Given that the predicate for sanctions is detailed at length in the Court’s earlier
    decision, Oak Grove, 
    2021 WL 3627111
    , at *9–*13, *28–*30, the Court repeats itself here
    only to the extent necessary to address the arguments in the briefing on the show cause
    order.
    II.     RCFC 11 GENERAL PRINCIPLES
    The undersigned is hardly the first judge of this Court to consider whether
    sanctions are warranted, pursuant to RCFC 11, for the improper compilation of the
    administrative record. See, e.g., Coastal Env’t Grp., Inc. v. United States, 
    118 Fed. Cl. 15
    , 36
    (2014) (imposing Rule 11 sanctions related to misconduct involving the administrative
    record); Gallup, Inc. v. United States, 
    131 Fed. Cl. 544
    , 547 (2017) (declining to impose
    Rule 11 sanctions where United States Special Operations Command agreed to pay
    plaintiff’s attorney fees and litigation costs, committed to issuing guidance on the
    importance of integrity when preparing the record, and had begun planning training to
    prevent future disclosure problems).2 Federal district courts from coast to coast have
    similarly recognized the possibility of sanctions for administrative record compilation
    failures.3
    The Court begins with the text of RCFC 11, which provides, in part:
    If, after notice and a reasonable opportunity to respond, the
    court determines that RCFC 11(b) has been violated, the court
    may impose an appropriate sanction on any attorney, law
    2In Gallup, the agency committed, specifically, that it would “issue guidance to its contracting
    staff emphasizing the importance of completeness, accuracy, and integrity in preparing records
    and accompanying certifications [and] is in the process of planning a training session . . . that
    will focus on issues of accuracy and ethics in preparing and certifying administrative records.”
    131 Fed. Cl. at 547 (quoting Dkt. No. 28, at 1–2).
    3See, e.g., Nat’l Urb. League v. Ross, 
    2020 WL 5548117
    , at *5 (N.D. Cal. Sept. 15, 2020) (citing cases
    for the proposition that “failure to produce or complete an administrative record can be the
    basis for sanctions”); New York v. Dep’t of Com., 
    461 F. Supp. 3d 80
    , 94 (S.D.N.Y. 2020) (ordering
    government “to reimburse the NGO Plaintiffs for the expenses, including attorney’s fees and
    costs, they reasonably incurred in addressing Defendants’ production failures” with respect to
    an administrative record).
    3
    firm, or party that violated the rule or is responsible for the
    violation.
    RCFC 11(c)(1) (emphasis added). Thus, a party may be sanctioned even if its counsel is
    not.4 RCFC 11(b), in turn, provides (in relevant part):
    By presenting to the court a pleading, written motion, or other
    paper — whether by signing, filing, submitting, or later
    advocating it — an attorney or unrepresented party certifies
    that to the best of the person’s knowledge, information, and
    belief, formed after an inquiry reasonable under the
    circumstances: . . . the factual contentions have evidentiary
    support . . . .
    RCFC 11(b)(3) (emphasis added).
    In this case, the Agency’s contracting officer “certif[ied] that to the best of [his]
    knowledge and belief, and after careful review,” that the filed “documents constitute
    the record of the administrative actions performed in the above-referenced Solicitation
    that is relevant to the issues raised in the plaintiff’s Complaint.” ECF No. 23-1 at 1
    (Certification of Contracting Office Administrative Record). This certification, and the
    filing of the administrative record generally, are subject to RCFC 11. See Antonious v.
    Spalding & Evenflo Cos., Inc., 
    275 F.3d 1066
    , 1074 (Fed. Cir. 2002) (holding that the
    “obligation under Rule 11(b)(3) to conduct a proper prefiling investigation applies not
    only to the complaint but also to ‘other paper[s]’ filed in the case”).5 The government
    nowhere contends otherwise.
    4 “In imposing Rule 11 sanctions, a court may allocate sanctions between an attorney and client
    according to their relative fault.” Judin v. United States, 
    110 F.3d 780
    , 785 (Fed. Cir. 1997). While
    “[a]ttorneys are usually held solely responsible for Rule 11 sanctions when the filing violating
    Rule 11 is unwarranted by existing law, or a good faith argument for extension, modification, or
    reversal of existing law[,] . . . an attorney and client may be held jointly and severally liable for
    filings that are not well grounded in fact.” 
    Id.
     (citing Allen v. Utley, 
    129 F.R.D. 1
    , 9 (D.D.C.
    1990)); see also, e.g., Bus. Guides, Inc. v. Chromatic Commc’ns Enters., Inc., 
    498 U.S. 533
    , 550 (1991)
    (“Where a represented party appends its signature to a document that a reasonable inquiry into
    the facts would have revealed to be without merit, we see no reason why a district court should
    be powerless to sanction the party in addition to, or instead of, the attorney.”); Schreiber Foods,
    Inc. v. Beatrice Cheese, Inc., 
    402 F.3d 1198
    , 1205 n.7 (Fed. Cir. 2005) (citing Bus. Guides, Inc., 
    498 U.S. at 550,
     for the proposition that a “party who signs a document in violation of Rule 11 may
    be sanctioned”).
    5The Federal Circuit in Antonious described the standard under Rule 11 of the Federal Rules of
    Civil Procedure, which is identical to RCFC 11. See 
    275 F.3d at 1071
    ; Fed. R. Civ. P. 11.
    4
    In the show cause order, this Court ordered the government to address why
    monetary sanctions should not be imposed pursuant to RCFC 11 and the Court’s
    inherent authority. Oak Grove, 
    2021 WL 3627111
    , at * 32. The government, in its
    response, entirely ignored the directive to address Rule 11 and addressed only the
    Court’s inherent power to impose sanctions — which the government accurately
    describes as “narrowly circumscribed . . . when there [is] no fraud or bad faith.” Def.
    Resp. at 4. The government thus contends that “sanctions are not warranted because
    the issues associated with the AR in this case were not the product of bad faith or
    fraud.” 
    Id. at 5
    . According to the government, “all of the issues associated with the
    [AR] in this case were not due to any intentional omissions by the undersigned
    counsel”6 but instead “were caused by the conception by the supporting contracting
    personnel . . . as to what the full scope of the AR should include for this protest.” Def.
    Resp. at 1. Put yet differently, the government maintains, “the [Agency] believed in
    good faith that it was complete, while simply failing to appreciate the potential
    relevance of the omitted documents to the issues in this protest.” 
    Id. at 3
    .
    The government cannot escape sanctions by ignoring the applicable Rule 11
    standard and pointing only to the heightened standard for imposing sanctions pursuant
    to a court’s inherent powers. The Rule 11 standard for imposing sanctions does not
    require a finding of bad faith and does not excuse a violation based on a showing of
    subjective good faith. See, e.g., Kilopass Tech., Inc. v. Sidense Corp., 
    738 F.3d 1302
    , 1313
    (Fed. Cir. 2013) (explaining that Rule 11 “allows the imposition of punitive sanctions,”
    “does not involve inquiry into a party’s subjective good faith,” and “does not require a
    showing of bad faith”). Instead, “Rule 11 functions to assure that parties assert
    litigation positions that are objectively reasonable at the time of filing.” 
    Id.
     (emphasis
    added). Supreme Court precedent also precludes a “good faith”-type defense to Rule
    11 sanctions. See Chambers v. NASCO, Inc., 
    501 U.S. 32
    , 47 (1991) (“Rule 11 . . . imposes
    an objective standard of reasonable inquiry which does not mandate a finding of bad
    faith.”). This objective standard is “intended to eliminate any ‘empty-head pure-heart’
    justification[s] . . . .” Fed. R. Civ. P. 11 Advisory Committee Notes (1993 Amendment).7
    Applying the correct Rule 11 standard to the facts here, the Court holds that the
    Agency’s “fail[ure] to appreciate the potential relevance of the omitted documents to
    6Again, the Court accepts without hesitation that the government’s counsel of record “was not
    aware of the two documents that are the subject of the show cause order.” Def. Resp. at 3.
    Nevertheless, as discussed infra, that does not excuse the Agency’s failures here.
    7“[W]hat constitutes a reasonable inquiry may depend on such factors as how much time for
    investigation was available to the signer; whether he had to rely on a client for information as to
    the facts underlying the pleading, motion or other paper; whether the pleading, motion or other
    paper was based on a plausible view of the law; or whether he depended on forwarding counsel
    or another member of the bar.” Fed. R. Civ. P. 11 Advisory Committee Notes (1983
    Amendment).
    5
    the issues in this protest” was neither reasonable nor excusable. Def. Resp. at 3.
    Moreover, the Court holds that the failure to include the documents at issue in the
    originally filed administrative record: (1) contributed to substantial delays in the
    resolution of this case; (2) wasted the Court’s time in attempting to engage in fact
    finding on an incomplete record; and (3) had the effect of imposing costs on Oak Grove
    due to, at a minimum, additional briefing, status conferences, and hearings. In short,
    the Agency’s withholding of the documents at issue from the initial filing of the
    administrative record harmed Oak Grove and the judicial process.
    III.   ADMINISTRATIVE RECORD REQUIREMENTS
    Before turning to the specific documents covered by the show cause order (and
    the related issues on which the Court required briefing), the Court writes to amplify its
    previous rejection of the government’s general premise, articulated repeatedly in this
    case — that an agency is entitled to subjectively decide what it believes is relevant to a
    plaintiff’s claims for the purposes of compiling the administrative record. See ECF No.
    47 at 2 (explaining that the government did not include certain documents in the record
    because it considered them not “especially relevant or necessary to the instant protest”
    (emphasis added)); Oak Grove, 
    2021 WL 3627111
    , at *10–*12 (discussing RCFC App. C,
    rejecting the government’s interpretation of it, and holding that “in compiling the
    administrative record, the government does not possess a unilateral veto over
    administrative record documents based on a self-serving conclusion that they are not
    relevant to the procurement decision under review”).
    A. The Administrative Record Must Include Documents Related to the
    Challenged Procurement Decision
    The Court begins with what it believes is common ground: “in a bid protest, the
    administrative record need not consist of every single document related in any way to
    the procurement in question, but may be reasonably limited to materials relevant to the
    specific decisions being challenged.” Tauri Grp., LLC v. United States, 
    99 Fed. Cl. 475
    ,
    481 (2011). That is where the common ground ends, however, as the Court rejects the
    government’s cramped view of the operational meaning of “relevant” in an action
    pursuant to 28 U.S.C. § 1491(b).
    The Court holds that while government agencies need not include in an
    administrative record “every single document related in any way to the procurement”
    at issue, Tauri Grp., 99 Fed. Cl. at 481, agencies must include in the record all documents
    related to their ultimate procurement decision. This standard is not new, and has been
    long articulated in both case law and by government agencies themselves. The U.S.
    Department of Justice, for example, recognizes that “[t]he administrative record is the
    paper trail that documents the agency’s decision-making process and the basis for the
    agency’s decision.” U.S. Dep’t of Justice, Env’t and Nat. Res. Div., Guidance to Federal
    6
    Agencies on Compiling the Administrative Record 1 (Jan. 1999) (providing “guidance to
    agencies in compiling the administrative record of agency decisions other than a formal
    rulemaking or an administrative adjudication”).8
    Accordingly, “[t]he administrative record consists of all documents and materials
    directly or indirectly considered by the agency decision maker in making the challenged
    decision.” Id. at 1–2. A proper administrative record “is not limited to documents
    relevant only to the merits of the agency’s decision” but also “includes documents and
    materials relevant to the process of making the agency’s decision.” Id. at 2 (emphasis
    added). The Justice Department guidance even alludes to the sort of problems the
    Court has been forced to address herein. See id. at 1, 7 (warning that “[i]t is critical for
    the agency to take great care in compiling a complete administrative record” because
    “[i]t is worth the effort and may avoid unnecessary and/or unfortunate litigation issues
    later on” (emphasis added)).
    Critically, the Justice Department advises agencies to include in the record
    “documents and materials” (1) whether they “support or do not support the final
    agency decision,” (2) that either “were before or available to the decision-making office at
    the time the decision was made,” and (3) that “were before the agency at the time of the
    challenged decision, even if they were not specifically considered by the final agency decision-
    maker.” Id. at 2 (emphasis added).9
    Although that Justice Department guidance document is non-binding and “does
    not create any rights,” id. at 7, courts have routinely relied upon it in explaining what
    materials must be included in an administrative record. See, e.g., Sierra Club v. Zinke,
    
    2018 WL 3126401
    , at *3 (N.D. Cal. June 26, 2018) (explaining that “[t]he Department of
    Justice Guidance on compiling administrative records, promulgated in 1999, endorses
    producing materials that [plaintiffs] seek” and noting that “[t]his district has repeatedly
    required deliberative materials (such as internal comments, draft reports, emails, and
    meeting notes) to be added to the administrative record if they were considered in the
    agency’s decision”).10 In that case, the district court dispensed with the government’s
    8See also J. Goldfrank, Guidance to Client Agencies on Compiling the Administrative Record, 48
    U.S. Att’ys’ Bulletin 7 (Feb. 2000),
    https://www.justice.gov/sites/default/files/usao/legacy/2006/06/30/usab4801.pdf.
    9See also U.S. Army Judge Advocate General’s Legal Center & School, Dep’t of the Army,
    Federal Litigation Deskbook 2016 G-39 (instructing that “[t]he agency should include all
    materials that might have influenced its decision, not just the documents upon which it relied”
    and that “[a]n agency may not exclude from the administrative record documents that reflect
    pertinent but unfavorable information” (citing cases)).
    10See also United Farm Workers v. Adm’r, U.S. EPA, 
    2008 WL 3929140
    , at *2 (N.D. Cal. Aug. 26,
    2008) (citing U.S. Dep’t of Justice, Env’t and Nat. Res. Div., Guidance to Federal Agencies on
    Compiling the Administrative Record (Jan. 1999) and ultimately holding that “the ‘whole
    7
    argument that so-called agency “deliberative documents” do not belong in the record.
    See Sierra Club, 
    2018 WL 3126401
    , at *3 (describing the government claim that “agency
    deliberative documents are not properly considered part of the administrative record
    and therefore generally should not be produced as part of a record filed with the court,
    nor listed in a privilege log” (emphasis in original)). The district court concluded that,
    with respect to such deliberative documents, “[t]he current Department of Justice
    position is contrary to the law in this Circuit.” 
    2018 WL 3126401
    , at *3.
    This Court need not address the deliberative documents question in this case
    because the government has never asserted that the Agency relied upon such an
    exception to withhold the documents at issue. That said, the Court concurs with the
    United States District Court for the Southern District of Florida’s view of relevancy, as
    applied to deliberative documents or any others:
    It is difficult to reconcile the notion that deliberative
    documents are irrelevant to judicial review []with the APA’s
    command that review is to be based on the “whole record.”
    The definition of “whole record” — material that was directly
    or indirectly considered by agency decisionmakers — should
    be the agency’s north star. Either a document was considered
    or it was not; there is no obvious place for “relevance” under that
    standard.
    Ctr. for Biological Diversity v. U.S. Fish & Wildlife Serv., 
    2020 WL 2732340
    , at *5 (S.D. Fla.
    May 26, 2020) (emphasis added). The district court elaborated further on the issue of
    “relevance”:
    [A]gency action is indeed judged based on the agency’s stated
    rationale. . . . [But that] does not mean that courts have no role
    in ensuring at the outset that they have been presented with
    the whole record. . . . [I]t is also true that deliberative
    documents are prone to reveal the mental processes of
    decisionmakers — in fact, that is a requirement to claim the
    record’ subject to review under the [Administrative Procedure Act (“APA”)] is not merely the
    record designated and submitted by the agency” (quoting Portland Audubon Soc. v. Endangered
    Species Comm., 
    984 F.2d 1534
    , 1548 (9th Cir. 1989))); see also In re United States, 
    875 F.3d. 1200
    ,
    1208 (9th Cir. 2017) (relying upon the Justice Department guidance document), vacated on other
    grounds by In re United States, -- U.S. --, 
    138 S. Ct. 443
    , 445 (2017). In In re United States, the
    Supreme Court remanded the case, requiring the lower courts to resolve “threshold arguments”
    before addressing the administrative record; it left to the district court the discretion to compel
    document disclosures after giving the government an opportunity to argue the issue. 
    138 S. Ct. at 445
    .
    8
    privilege, and such privileged documents should be excluded
    from the record. . . . But that’s not a matter of relevance; to the
    extent a deliberative document discloses the factors that were
    or were not considered by the agency, it may “go to the heart”
    of whether a decision was arbitrary and capricious.
    
    Id.
     (internal citations omitted) (emphasis in original); see also 
    id. at *8
     (holding “that
    deliberative documents may be withheld from the record only upon invocation of the
    deliberative process privilege, as documented in a privilege log”). By way of analogy,
    in the discovery context, “[i]t is not for a party to determine, by a unilateral review of
    documentation, whether information is relevant to the case.” Sanchez v. U.S. Airways,
    Inc., 
    202 F.R.D. 131
    , 135 (E.D. Pa. 2001).11
    In sum, the government’s view of relevancy in this case would undermine the
    requirement that the Court consider the “whole record.” 5 U.S.C. § 706; see also L. Beck,
    Agency Practices and Judicial Review of Administrative Records in Informal Rulemaking,
    Report for the Admin. Conf. of the U.S., at 31 (May 14, 2013) (“ACUS Report”)
    (explaining that “using a ‘relevancy’ standard . . . raises the question of whether
    application of such an intervening test would narrow the administrative record beyond
    the ‘whole record’ required for judicial review” and advising that “[a]gency guidance
    should avoid introducing subjective judgments regarding whether materials have been
    ‘relied’ upon or are ‘relevant’”).12
    B. Federal Circuit Precedent Does Not Preclude Discovery Regarding
    How an Agency Compiled, or What It Omitted from, the
    Administrative Record
    In Axiom Resource Management, the Federal Circuit cautioned against
    “adding . . . documents to the record without evaluating whether the record before the
    agency was sufficient to permit meaningful judicial review.” 
    564 F.3d 1374
    , 1380 (Fed.
    Cir. 2009). That decision, however, provides no guidance on when documents that
    11Seealso Christine Asia Co., Ltd. v. Alibaba Grp. Holding Ltd., 
    327 F.R.D. 52
    , 54 (S.D.N.Y. 2018)
    (“The weight of authority in this Circuit goes against allowing a party to redact information
    from admittedly responsive and relevant documents ‘based on that party's unilateral
    determinations of relevancy.’” (quoting Cyris Jewels v. Casner, 
    2016 WL 2962203
    , at *4 (E.D.N.Y.
    May 20, 2016))); Polk v. Swift, -- F.R.D. --, 
    2021 WL 2941994
    , at *2 (D. Wyo. Jan. 22, 2021) (noting
    that even “[a]fter the 2015 amendments to Rule 26, . . . “[r]elevance is to be ‘construed broadly
    to encompass any matter that bears on, or that reasonably could lead to the other matter that
    could bear on any party's claim or defense.’” (quoting State Farm Mut. Auto. Ins. Co. v. Fayda,
    
    2015 WL 7871037
     at *2 (S.D.N.Y. Dec. 3, 2015), aff'd, 
    2016 WL 4530890
     (S.D.N.Y. Mar. 24, 2016))).
    12Available at https://www.acus.gov/publication/agency-practices-and-judicial-review-
    administrative-records-informal-rulemaking-report.
    9
    indisputably were before an agency properly may be excluded from the compiled
    administrative record. In that regard, while the government, in the undersigned’s
    experience, typically (and correctly) has resisted the characterization of the
    administrative record as a “fiction,” see Naval Systems, Inc. v. United States, 
    153 Fed. Cl. 166
    , 177–78 (2021) (discussing the compilation and contents of the administrative
    record), that is because that label suggests that the record is a fluid concept without
    boundaries; if the record is a mere “fiction,” the record may include whatever the
    parties want this Court to consider. Neither the government nor this Court has any
    interest in returning to such a pre-Axiom world — and that would be improper post-
    Axiom, in any event. But the “necessary corollary” of the administrative record not
    being some fiction to which the parties may add whatever they please is that neither
    this Court nor plaintiffs should “have to police the government’s filing as if routine
    discovery rules apply.” Oak Grove, 
    2021 WL 3627111
    , at *12 (noting that “to a great
    extent, a plaintiff in a § 1491(b) action is at the mercy of the government to file a
    complete, certified record”).
    Moreover, if the government is going to err on the side of excluding material
    from an agency record based on its own sub-silentio relevancy determinations, not only
    does that likely violate this Court’s rules,13 but also such a strategy will invite discovery
    battles surrounding the compilation of the administrative record that neither the
    government nor this Court wish to encourage.
    Parties — and particularly the government — should keep in mind that Axiom
    was concerned with this Court’s not crossing the line from a proper APA review of
    agency action into de novo review by testing an agency’s decision against evidence that
    was not before the agency. Axiom, 
    564 F.3d at 1380
    –82. Nothing in Axiom, however,
    would preclude this Court from following the guidance in Cubic Applications, Inc. v.
    United States, 
    37 Fed. Cl. 345
     (1997), that “[i]n order to preserve a meaningful judicial
    review, the parties must be able to suggest the need for . . . possibly limited discovery,
    aimed at determining, for example, whether other materials were considered . . . .” 37 Fed.
    Cl. at 350 (emphasis added); see also Naval Systems, 153 Fed. Cl. at 182 (describing a
    “type of circumstance[] in which extra-record evidence should be considered” as
    including a protest arising “from the very omission of evidence upon which the Agency
    relie[d]”). To be clear, the Court is not talking about discovery to add materials to the
    record; that is something that Axiom generally precludes. But Axiom does not preclude
    discovery regarding how an agency compiled the administrative record or what was
    omitted from it. Naval Systems, 153 Fed. Cl. at 179 (“Nor has our Court clearly defined
    13See Oak Grove, 
    2021 WL 3627111
     at *12 n.13 (explaining that “there is a distinction between the
    GAO’s record production requirements and the Court’s Rules governing the filing of the
    administrative record”).
    10
    supplementation as the addition of evidence that the agency considered but omitted
    from the record.”).14
    Accordingly, and even considering the presumptions of good faith and
    regularity (as applied to the compilation of the administrative record), if the record was
    limited to only what the agency designated, “[e]ven material that was heavily
    considered by decision-makers would amount to ‘extra-record’ evidence if the agency
    failed to designate it.” Ctr. for Biological Diversity, 
    2020 WL 2732340
    , at *3; see also 
    id. at *6
     (holding that “even accounting for the presumption of regularity,” permitting too
    “large [of a] measure of discretion in determining the content of the administrative
    record . . . risks frustrating effective judicial review”). The government should think
    hard about whether relying upon such circular logic and dubious relevancy
    determinations will benefit it in the long run.
    In any event, as discussed below, the Court holds that the Agency’s failure to
    include the documents at issue in the initially filed administrative record was improper
    under not only the above-discussed Justice Department guidance — which, although
    non-binding, the Court views as accurately describing an agency’s duty — but also
    under any definition of relevance.
    IV.     THE AGENCY UNREASONABLY OMITTED THE DOCUMENTS AT
    ISSUE FROM THE INITIAL ADMINISTRATIVE RECORD FILING
    The Court notes, once again, that the factual findings surrounding the various
    debacles with the administrative record are detailed in the Court’s merits decision. Oak
    Grove, 
    2021 WL 3627111
    , at *9–*13, *28–*30. Accordingly, the Court endeavors to repeat
    facts, whether substantive or procedural, only to the extent necessary for context and
    clarity.
    A. The DCMA Report
    The government contends that “the omission of the DCMA pre-award report did
    not come to our attention until oral argument in this case.” Def. Resp. at 6 (emphasis
    added). The government does not make clear what it intends by the plural possessive
    14Axiom does not conflict with this Court’s earlier observation that an agency’s compilation of
    the administrative record is subject to the Court’s review: “Effective judicial review of an
    agency’s exercise of discretion is irreconcilably at odds with the notion that the reviewing
    court’s inquiry must be confined to an administrative record that is likewise the product of the
    agency’s sole discretion.” Pikes Peak Fam. Hous., LLC v. United States, 
    40 Fed. Cl. 673
    , 676–77
    (1998); see also ACUS Report at 66, 69 (noting that “the agency does not unilaterally determine
    what constitutes the administrative record” and warning that “the risk of incompleteness may
    rise with delayed compilation of an administrative record”).
    11
    “our” but to the extent it is meant to refer to the Department of Justice, the Court fully
    credits the assertion. 
    Id. at 3
     (representing that “the undersigned counsel was not aware
    of the two documents that are the subject of the show cause order” at the time the
    administrative record was filed). On the other hand, to the extent that the government
    asserts that Agency personnel, including the contracting officer, were not aware of the
    DCMA report, the Court rejects that contention. As the government itself noted, the
    Agency included the DCMA report at issue in the administrative record of a related
    GAO protest. Def. Reply at 8–9 n.5. The Agency’s personnel clearly were aware of the
    DCMA report.
    Thus, the only question the Court need decide is whether the contracting officer,
    acting on behalf of the Agency, reasonably concluded that the DCMA report was not
    properly part of the administrative record in this case. On that precise question, the
    government offered little to no explanation in its initial response to the Court’s show
    cause order. Def. Resp. at 6–7. Indeed, the government forthrightly expressed its
    “regret that we (along with the Court and the parties) were not made aware of this
    document” — presumably by the Agency — “until late in the proceedings.” 
    Id. at 7
    .
    The Court appreciates the government’s candor and remorse, but that apology hardly
    excuses the fact that the Agency failed to include the DCMA report in the record until
    after both the completion of the merits briefing and oral argument.
    The government in its reply brief asserts that “under the totality of these
    circumstances, with zero evidence of fraud or bad faith, penalizing the Government
    with sanction[s] amounts to a zero tolerance standard that is wholly inappropriate[.]”
    Def. Reply at 10 (emphasis in original). As the Court made clear, supra, however, Rule
    11 does not require that this Court make a finding of fraud or bad faith to impose
    sanctions. To be clear, the Court does not suggest that mere accident or oversight are
    proper predicates for sanctions. Accordingly, the Court is not a proponent of, nor is the
    Court applying, a “zero tolerance standard.” Rather, in this case, the government
    concedes that the Agency made a deliberate decision not to include the documents at
    issue, Tr. 13:3–22, and did not consult Justice Department counsel about that decision,
    Tr. at 11:12–15. The Court concludes that, in light of the facts and issues at the heart of
    this case, the Agency acted in an objectively unreasonable manner that is consistent
    with, at a minimum, an attempt to shape the record in its favor.
    The government troublingly proffers almost no explanation for why the Agency
    affirmatively declined to include the DCMA report in the initial AR in this case. The
    government asserts that both documents at issue “were not originally in the AR because
    they were not considered relevant to the instant protest as they pertained to the ‘first’
    evaluation of proposals (before the GAO protest and corrective action), not the second
    evaluation currently being challenged.” Def. Resp. at 3 (citing ECF No. 47). According
    to the government, the Agency “simply fail[ed] to appreciate the potential relevance of
    the omitted documents to the issues in this protest.” Id. The Court rejects that
    12
    explanation as objectively unreasonable. This rejection is not simply the Court’s
    Monday-morning quarterbacking.
    As explained in the Court’s merits decision, a central issue in this case was
    whether Oak Grove even had standing to pursue its protest as an “interested party”
    pursuant to 28 U.S.C. § 1491(b). Oak Grove, 
    2021 WL 3627111
    , at *7–8; Plaintiff’s Motion
    for Judgment on the Administrative Record, ECF No. 27, at 14–18. In a nutshell, the
    government’s consistent position — throughout the prior GAO litigation and before this
    Court — has been that Oak Grove lacked standing due to the existence of a so-called
    intervening offeror. Pl. Resp. at 6 (quoting the GAO record). The government’s
    argument was that Oak Grove lacked standing because even if it could demonstrate
    that the Agency’s contract award to Defendant-Intervenor was erroneous, Oak Grove
    still would not have had a substantial chance of receiving the contract award, as Offeror
    H was determined to be eligible for award, while Oak Grove was not. Thus, for Oak
    Grove to have standing, and to succeed on the merits, Oak Grove had to allege and then
    prove that both Defendant-Intervenor and Offeror H were ineligible for award. Pl.
    Resp. at 6.
    Accordingly, the DCMA report was objectively and clearly material to the
    government’s standing argument. As the Court previously explained, the DCMA
    report reflects a recommendation of “No Award” for Offeror H. Oak Grove, 
    2021 WL 3627111
    , at *18 (citing AR 4994). The RFP required the Agency, at a minimum, to
    consider that recommendation, if not follow it, but “[n]owhere does the record
    demonstrate that the Agency even considered this DCMA finding (assuming for the
    sake of argument that the contracting officer were permitted to depart from it).” Oak
    Grove, 
    2021 WL 3627111
    , at *18 (citing AR 1714 (RFP § M.4.3.7) and explaining that
    “[t]his document clearly demonstrates that [Offeror H] was found to be not financial[ly]
    capable and thus was not awardable consistent with the RFP’s requirements”). Because
    the RFP required that the “Prime offeror must be deemed financially responsible by the
    Contracting Officer based on the Financial Capability Risk Assessment[,]” the notion that
    the DCMA report was immaterial to the government’s standing argument is facially
    inconsistent not only with the findings in the document itself but also the obvious
    purpose for which the DCMA prepared it. AR 1714 (§ M.4.3.7) (emphasis added).
    During oral argument on the show cause order, the government argued that the
    DCMA report was not relevant to the dispute because “the audit report is not a ground
    for finding [Offeror H] ineligible.” Tr. 16:21–22. But that is nothing more than an
    argument on the merits, supporting the government’s position on the standing
    question. The government cannot be permitted to make a self-serving merits
    determination to avoid producing certain (damaging) documents as part of the
    administrative record in the first place.
    13
    Moreover, Oak Grove persuasively argues that the Agency went to some length
    to conceal what the administrative record revealed about Offeror H. For example, in
    the record submitted to the GAO, the Agency extensively redacted documents related
    to criticisms of Offeror H, including a notable redaction obscuring that it was “found
    [by DCMA] to be NOT financially capable of performing the contract.” Pl. Resp. at 7
    (depicting redacted evaluation document); id. at 8 (noting that Oak Grove “objected to
    these redactions” at the GAO). The Court agrees with Oak Grove that “[t]he Agency’s
    arguments ignore that the Agency reviewed the DCMA report, believed it important
    enough to document in its [Prenegotiation Objective Memorandum / Price Negotiation
    Memorandum], but then chose to redact that information at GAO and to withhold the
    DCMA report from both GAO and this Court.” Pl. Resp. at 8. While the Court cannot
    police the Agency’s past conduct regarding the record before the GAO, there is no
    reason the Court cannot consider such conduct in determining whether the Agency had
    a reasonable basis to keep the DCMA report from Oak Grove and the Court in this
    proceeding.15
    Finally, the government argues that its AR production was extensive, but that
    fact supports, rather than undermines, Oak Grove’s position. For example, the
    government observes that “[t]he AR that we filed in this case . . . included the full
    record of the GAO proceedings pertaining to Oak Grove as well as additional documents
    that were not included in the GAO record pertaining to Offeror H.” Def. Resp. at 2 (emphasis
    added). That assertion merely begs the question why, then, did the Agency deliberately
    omit the DCMA report, which also pertained to Offeror H? The government never
    suggested that the Agency’s omission was simply inadvertent. And again, the Court
    cannot conclude that the Agency had a reasonable basis to omit the DCMA report from
    the record, particularly given the government’s admission that the Agency included
    documents related to Offeror H in the initial administrative record filing with the Court.
    While the government now avers that it included such documents “because Oak Grove
    specifically challenged [Offeror H’s] cost proposal . . . [s]o documents were introduced
    with respect to that,” Tr. 21:8–14, the problem is that RFP § M.4.3.7 (AR 1714) is located
    within the RFP’s evaluation factors covering the “Cost/Price Evaluation” (§ M.4.3). AR
    1713.16 And § M.4.3.7 specifically required the consideration of the Financial Capability
    15Redactions here would have been entirely inappropriate; a fortiori, withholding entire
    documents is no better. See Doe v. Trump, 
    329 F.R.D. 262
    , 276 (W.D. Wash. 2018) (“[T]he court
    concludes that ‘the better . . . approach is to not provide litigants with the carte blanche right to
    willy-nilly redact information from otherwise responsive documents in the absence of privilege,
    merely because the producing party concludes on its own that some words, phrases, or
    paragraphs are somehow not relevant.’” (quoting Bonnell v. Carnival Corp., 
    2014 WL 10979823
    , at
    *4 (S.D. Fla., Jan. 31, 2014))).
    16A solicitation’s evaluation factors are generally contained within an RFP’s Section M. See AR
    1709 (RFP § M.4 (“Factors”), RFP § M.4.1 (“Factor 1 – Capability Evaluation Approach”)); AR
    14
    Risk Assessment DCMA prepared. The Agency cannot explain why that report is any
    less relevant to the § M.4.3 evaluation than all of the other cost proposal materials the
    Agency did include in its initial record filing. The most reasonable explanation, if not
    the only reasonable explanation, is that the Agency selectively omitted a document that
    was harmful to its position.
    In sum, as Oak Grove argues, the Agency’s failure to include the DCMA report
    “forced extensive added effort by this Court and the parties.” Pl. Resp. at 10.
    B. The RM Termination Letter
    On June 1, 2021, the government included the RM termination letter as part of a
    corrected AR filing, see ECF No. 55, made pursuant to the following court order:
    [C]ounsel of record for the government shall consult with the
    cognizant contracting officer to determine whether any other
    documents relating to the agency’s decision-making at issue (e.g.,
    the contract awardee’s proposal, Offeror H’s proposal,
    and/or [RM’s] role in the procurement at any stage) were
    omitted from the administrative record. Counsel of record
    shall complete the administrative record and certify
    compliance with this order in a status report, on or before
    Friday, June 4, 2021, at 12:00 p.m.
    ECF No. 53 (May 28, 2021, Order) (emphasis added). Thereafter, the government
    certified as follows:
    Pursuant to the Court’s order of May 28, 2021, defendant, the
    United States, respectfully submits the following status
    report. This is to certify that, we have consulted with agency
    contracting officer in obtaining documents that were omitted
    from the administrative record, we have complied with the
    Court’s order in correcting and completing the administrative
    record.
    ECF No. 60 (June 4, 2021, Status Report) (emphasis added). To be clear, then, the Court
    did not order the government to produce the termination letter specifically. Rather, the
    government apparently determined, when ordered to do so, that the document was
    necessary to complete the administrative record because it related “to the agency’s
    decision-making at issue.” In including the RM termination letter, the government thus
    1712 (RFP § M.4.2 (“Factor 2: Past Performance Evaluation Approach”)); AR 1713 (RFP § M.4.3
    (“Factor 3 – Cost/Price Evaluation Approach”)).
    15
    implicitly agreed that the letter was necessary to complete and correct the
    administrative record.17
    Equally important is what the government did not do. The government did not
    seek, for example, in camera review of the RM termination letter to establish that it was
    irrelevant either “to the agency’s decision-making at issue” or otherwise to this case,
    generally.18 Indeed, even now, the government does not assert that the Agency made
    the correct call with respect to the RM termination letter, but rather admits that had the
    government’s counsel of record “been aware of the April 30, 2020 termination letter,
    [he] would have included it in the AR.” Def. Resp. at 5. In other words, with respect to
    the RM termination letter (as with the DCMA report), the only question for the Court is
    whether the government’s proffered excuse for the Agency — that it “simply fail[ed] to
    appreciate the potential relevance of the omitted document[] to the issues in this
    protest,” Def. Resp. at 3 — is objectively reasonable. Based on the foregoing analysis
    alone, the Court answers that question in the negative. Nevertheless, the Court will
    address the government’s additional arguments.
    Notwithstanding that the Agency produced the RM termination letter without
    being specifically ordered to do so, the government asserts, post hoc, that the document
    was irrelevant to this case based on a version of a harmless error argument. According
    to the government, the Agency “unintentionally and inadvertently omitted a document
    that is helpful to the Government in countering the protestor’s allegation that [RM]” — the
    initial SSEB Chairperson — “may have improperly steered award to F3EA.” Def. Resp.
    at 5–6 (emphasis added). That is true, the government posits, because “[a]lthough the
    termination letter is critical of [RM] in his role as SSEB chair . . . the letter also
    demonstrates that [RM] had no role in the second source evaluation determination at
    issue in this protest.” Id. at 5. The assertion that the RM termination letter “is helpful to
    17As the Court previously noted, the RM termination was added to the AR “without any
    explanation for its original omission . . . .” Oak Grove, 
    2021 WL 3627111
    , at *10.
    18Cf. MVS USA, Inc. v. United States, 
    111 Fed. Cl. 639
    , 643 n.4 (2013) (noting that the
    “government provided the MOA after completion of briefing, ostensibly to address questions
    that had arisen in the briefing on the dispositive motions,” but overruling “the government's
    objections to its inclusion” in the administrative record); Inst. for Fisheries Res. v. Burwell, 
    2017 WL 89003
    , at *1 (N.D. Cal. Jan. 10, 2017) (“It is obvious that in many cases internal comments,
    draft reports, inter– or intra-agency emails, revisions, memoranda, or meeting notes will inform
    an agency’s final decision. Therefore, the government is wrong to assert that these types of
    materials, as a categorical matter, should be excluded from the universe of materials ‘directly or
    indirectly considered by agency decision-makers.’ Of course, these types of materials could be
    protected from disclosure by the deliberative process privilege. But the scope of the privilege
    doesn’t define the scope of the material directly or indirectly considered. If a privilege applies,
    the proper strategy isn’t pretending the protected material wasn’t considered, but withholding
    or redacting the protected material and then logging the privilege.” (citations omitted)).
    16
    the government” is “the kind of argument that only a lawyer could love,” Est. of Rao v.
    United States, 
    987 F. Supp. 249
    , 253 (S.D.N.Y. 1997), and is demonstrably wrong.
    First, before the government proffered this explanation, the Court already had
    found that “[t]he Agency issued this [termination] letter . . . during corrective action,
    before the Agency’s second award decision.” Oak Grove, 
    2021 WL 3627111
    , at *11 n.10
    (citing AR 5388) (emphasis added). The government makes no attempt to address that
    factual finding with any specificity. Moreover, during the hearing on the show cause
    order, the government agreed with the Court’s understanding of the RM termination
    letter:
    The Court: You can tell me that this is not accurate, but a
    sane, rational[-]person[’s] reading [of] this is that there was
    corrective action, the corrective action was to review and
    amend the [proposal evaluation report (“PER”)], there were
    multiple versions of that PER that were produced, there were
    still problems between the subsequent versions of the PER
    having disagreements between the documented findings and
    the requirements, and then, since those persisted, [RM] was
    replaced.
    Am I not reading that right?
    [Government]: No, that’s what it says.
    Tr. 30:1–11 (emphasis added). When the Court pressed the government regarding
    precisely when the Agency removed RM as SSEB Chairperson during the corrective
    action process, the government repeatedly admitted that it did not know. 
    Id. at 30:15
    –
    20; 31:1–2 (“I don’t know those details.”). The Court remains uncertain how, in light of
    that exchange, the government could make the assertion that the RM termination
    somehow definitively “demonstrates that [RM] had no role in the second source
    evaluation determination.” Def. Resp. at 5.
    Second, during the show cause hearing, the Court asked the same question to a
    government witness, Mr. [DW], who replaced RM as SSEB Chairperson. See Tr. 31:19–
    21; AR 5390. Mr. [DW] responded that his involvement with the procurement began in
    February 2020 when “corrective actions were ongoing” and he was asked to
    “review . . . the actions . . . taken so far and provide . . . an assessment” to his
    supervisor. Tr. 31:24–32:6 (emphasis added). As a result of Mr. [DW]’s analysis, “the
    recommendation to [the CO] was that [RM] be removed” and, thus, Mr. [DW] “was
    17
    inserted into the source selection as the source selection chair.”19 Tr. 32:11–14. Thus,
    there is no doubt that RM played a role in the corrective action from the conclusion of
    the GAO protest in January 2020, through at least part of the corrective action period,
    until his removal as SSEB Chairperson at the end of April 2020. Mr. [DW] informed the
    Court that RM only “made some initial drafts” that Mr. [DW] reviewed and that “never
    went forward” to be “acted on,” see Tr. 32:19–25, but that is a far cry from definitively
    substantiating that RM — or, more critically, his work — played no role in the ultimate
    source selection decision at issue in this case.
    Mr. [DW]’s representations to the Court provide, if anything, good reason for
    Oak Grove (and the Court) to have concerns about how RM’s prior work may have
    impacted the second source selection at issue here:
    THE COURT: Let me understand what you did not do. You
    did not take the initial evaluations, put them to the side,
    throw them in the trash can, and start the evaluation over
    from scratch of the proposals.
    MR. [DW]: We did not take all of them and set them aside
    and start again because, as I said, I could not do anything
    with[out] the two subject matter experts whose input was
    actually very critical in understanding the merits of the
    exercises that were part of Sections L and M.
    Tr. 34:4–13. (Those subject matter experts who performed the initial proposal
    evaluations apparently were unavailable during corrective action.)
    The Court remains perplexed by the government’s unequivocal assertion that
    “[RM] played no role in the second evaluation . . . .” Def. Reply at 7. While he may
    have played no role in the final “August 2020 . . . award” decision or the final decision
    document itself, 
    id.,
     that plainly does not mean that he had no influence on the work
    product Mr. [DW] and other Agency personnel considered or relied upon. In any case,
    Oak Grove was entitled to develop arguments on those subjects, but was deprived of
    the opportunity to do so.
    Accordingly, the Court rejects the government’s assertion that because “[RM]
    played no role in the second evaluation, the termination letter was not germane to the
    evaluation decision.” Def. Reply at 7. RM’s role and influence in this procurement was
    a central factual issue in Oak Grove’s claims. The government’s attempt to minimize
    his role in the procurement and the corrective action — based on the very termination
    19 Mr. [DW] likely misspoke as the record indicates he was appointed SSEB Chairperson on May
    4, 2020 (“source selection chair” is not referenced). AR 5390.
    18
    letter which lends support to Oak Grove’s central thesis — is rejected (and, in any event,
    is a post hoc rationale for why it was excluded from the record). In sum, the Court
    agrees with Oak Grove that “[c]ontrary to the [termination] Memorandum, the Agency
    sought to present a picture of objective, impartial involvement by [RM]” and that the
    termination letter “contradicts” — or, at the very least, arguably undermines — “the
    Agency’s position” throughout this litigation. Pl. Resp. at 9 (noting that the AR did not
    otherwise “reveal[] internal concerns about [RM’s] actions”).20
    ****
    All of this discussion leads the Court to address yet two additional arguments
    the government makes: (1) that “neither the [Agency] nor the Department of Justice
    concealed the fact of the prior role of [RM] as SSEB chair in the Raptor IV procurement”
    (see Def. Resp. at 5); and (2) that the government did not mischaracterize the Agency’s
    corrective action (see Def. Reply at 2–7). The Court addresses each issue, in turn, below.
    V.      THE ADMINISTRATIVE RECORD, AS INITIALLY FILED,
    OBSCURED RM’S ROLE IN THE PROCUREMENT
    With regard to RM’s role in the procurement, the government notes that “[t]wo
    documents originally included in the GAO record, and included in the original AR that
    we filed in this Court on February 10, 2021, identified [RM] as the SSEB chair.” Def.
    Resp. at 5 (citing AR 1582, 1631). The first reference is to a signature block on the
    second page of the Source Selection Plan (AR 1582); the second is to an organization
    chart depicting the “Source Selection Team Structure” (AR 1631). While the
    government argues that Oak Grove, therefore, was on notice of RM’s true role and
    presumably could have sought additional documents earlier in the case, neither Oak
    Grove nor the Court can be expected to have located those two needles in a “4,862
    page[]” haystack. Def. Resp. at 2.21
    To be clear, the Court reaches no conclusion on the substance of RM’s conduct. Again, the
    20
    Court’s point is simply that APA review requires the agency to file “the whole record” and that
    Oak Grove was deprived of the opportunity to make arguments based upon the missing
    document. 5 U.S.C. § 706 (“the court shall review the whole record”).
    21The Court does not hold that a plaintiff-protester is never responsible for finding such needles
    in a voluminous administrative record. Nor does the Court attempt here to define in all
    circumstances when a plaintiff has sufficient notice of the existence (or likely existence) of
    documents such that the plaintiff must raise the issue in a timely manner with the government
    or the Court. Instead, as explained in this section of this order, the Court finds only that under
    the facts of this case — including, but not limited to, the virtually camouflaged location of the
    information at issue — neither the Court nor Oak Grove were on notice of RM’s true role in the
    procurement at issue.
    19
    The existence of those documents does not demonstrate the government’s good
    faith — even if good faith were the relevant standard for Rule 11 — particularly because
    the government, throughout its merits briefing, repeatedly and exclusively referred to
    RM as the contracting officer’s representative or “COR.” See, e.g., ECF No. 30 at 59
    (“COR [RM] allegedly discussed efforts to steer the procurement towards the awardee,
    F3EA”), 61 (arguing that “as a Government official, [RM], the COR, is presumed to act
    lawfully”), 64–65 (quoting statement of “COR [RM]”), 70 (referring to “a COR, such as
    [RM]”). In one such reference, the government responds to an Oak Grove argument,
    noting as follows:
    Oak Grove cites to that portion of the OCI investigation report
    where the contracting officer summarized the statement of
    COR [RM], where [RM] stated, in effect, that, in creating the
    RAPTOR IV sample STOs, the [Agency] made significant
    changes to the RAPTOR III performance work statements “to
    mitigate the incumbent advantage.”
    ECF No. 30 at 69 (quoting AR 2044).
    To the extent the government was discussing RM’s role on the predecessor
    contract, it understandably refers to RM as the “COR.” On the other hand, the above
    quote describes RM’s knowledge of RAPTOR IV — the procurement at issue — in
    which he served as the SSEB Chairperson, not the COR. Similarly, in arguing that
    “[t]he contracting officer, in his discretion, unequivocally determined that [an] OCI did
    not exist in the RAPTOR IV procurement,” the government asserted that such
    discretion “does not rest with a COR, such as [RM].” Id. at 70. This statement is
    misleading on its face (even if unintentionally so) because RM was not the COR, but
    rather the SSEB Chairperson, on RAPTOR IV.
    The government’s response brief (on the merits) repeats the same pattern and
    suffers from the same problem; it never once identifies RM as the SSEB Chairperson.
    For example, there is this statement:
    [T]he contracting officer did investigate the allegations by
    interviewing the contracting officer’s representative (COR)
    [RM] and at least six other Government and contractor
    witnesses and reviewed written statements and documents:
    [RM] and the other witnesses flatly denied the allegations of
    wrongdoing lodged against COR [RM] by Oak Grove.
    ECF No. 38 at 30 (emphasis in original). Of course, at that point, RM was the SSEB
    Chairperson on RAPTOR IV, and not just the COR on the predecessor contract.
    20
    More significantly still — as highlighted in the Court’s merits decision — as late
    as oral argument on the merits, neither the Justice Department nor Agency counsel
    themselves knew what role RM had played in the procurement at issue. Oak Grove,
    
    2021 WL 3627111
    , at *28 (citing ECF No. 45 (“May 24, 2021 Tr.”) at 122:15–22). To make
    matters worse, “[t]he government emphasized — erroneously, as it turns out — that
    regardless of whatever role [RM] may have played in the evaluations, ‘there was a
    separate source selection evaluation board.’” 
    2021 WL 3627111
    , at *28 (quoting May 24,
    2021 Tr. at 122:25 – 123:1). That statement was flat wrong given that RM managed the
    SSEB. And, even once RM had been replaced, there was no “separate” SSEB; the first
    SSEB’s work was not redone (a difficulty the Court addresses below).
    In sum, the assertion that the Court or Oak Grove should have discovered RM’s
    true role in the RAPTOR IV procurement — based on just two bare references in the
    administrative record — when neither the Justice Department nor Agency counsel
    could tell the Court what role RM played in the procurement rings particularly hollow,
    as does the government’s assertion that RM’s role was “never raised.” Tr. at 77:21–22.
    The government cannot claim ignorance of something so central to the case while
    simultaneously asserting that the plaintiff should have known it; to permit such a claim
    would be to allow the government to use the proverbial needle in a haystack as both a
    sword and shield.
    The fact is that RM’s role in this procurement was at the center of Oak Grove’s
    case. Accordingly, the Court wholeheartedly agrees with Oak Grove’s argument:
    Rather than saying, you know what, we had relevant
    documents that were missed, we failed to produce them,
    we’re sorry, we’ve now been through multiple rounds of [the
    government] trying to justify something that is clearly
    indefensible. . . .
    [T]he fact that [RM] had something to do with this
    procurement has been a centerpiece of our protest from the
    get-go. We’ve been saying since the get-go that there’s an
    impropriety here with him. . . .
    And what [the government] did . . . whether . . . his role [is
    reflected] in some signature block . . . [or] some [reference]
    buried somewhere [—] [the government] withheld a
    document by which they removed him as the SSEB chair from
    this procurement, and that removal is not reflected[.] [I]t’s not
    reflected in their source selection decision document; it’s not
    reflected in their Source Selection Advisory Committee
    memorandum; it’s not reflected anywhere. And it wasn’t
    21
    produced to the Court until — this Court, because of its
    diligence, discovered that.
    And to put that on anybody but the party who’s responsible
    for certifying this record is really blaming others for not
    finding needles in haystacks to question whether or not the
    United States properly put its record together. The United
    States’ obligation is to put the record together.
    Tr. at 81:16 – 82:17; see Oak Grove, 
    2021 WL 3627111
    , at *12 (holding that “plaintiffs must
    be entitled to rely upon the government’s certification that the filed administrative
    record is complete” and that “[p]laintiffs should not have to police the government’s
    filing as if routine discovery rules apply[,]” and noting that “to a great extent, a plaintiff
    in a § 1491(b) action is at the mercy of the government to file a complete, certified
    record”).
    The bottom line in the Court’s view is that there are all sorts of arguments Oak
    Grove may have raised (or questions the Court may have asked) had the record timely
    contained the RM termination memorandum. The Court will not rehash its merits
    decision here; suffice it to say, the Court rejects the government’s assertion of harmless
    error or any similar argument.22
    VI.     THE AGENCY’S CORRECTIVE ACTION
    The final issue from the show cause order briefing relates to how the government
    described the Agency’s corrective action. This issue is important because the Court
    (and apparently Oak Grove) did not understand the nature of the corrective action — if
    it is even fair to describe it as such — until the RM termination letter was added to the
    administrative record. To explain the troubling nature of this issue, the Court
    compares: (1) the government’s representations to GAO about the promised corrective
    action; with (2) the administrative record’s description of the nature of the corrective
    action the Agency implemented; and with (3) the description of the corrective action in
    the RM termination memorandum.
    22See Oak Grove, 
    2021 WL 3627111
    , at *29 (noting that the “[termination] document – produced
    way too late in the day for this litigation – certainly casts a long shadow over [RM’s] conduct in
    his role as SSEB Chair during this procurement, lends more than a modicum of support to the
    allegations of [misconduct by] F3EA’s former employees, and was not addressed by either the
    PCO’s investigation memoranda or counsel of record in this case”).
    22
    As part of the show cause briefing schedule, the Court explained and ordered as
    follows:
    [T]he government in its motion for judgment on the
    administrative record (“MJAR”) represented to the Court that
    following the initial GAO protest, “the SSEB convened to
    evaluate proposals a second time” and that “[t]he [Agency]
    received and evaluated ten proposals[.]” ECF No. 30 at 8
    (emphasis added); see 
    id.
     (“Of the ten proposals
    reevaluated . . . .” (emphasis added)). The Court had expected
    the parties to address this issue in the further briefing the
    Court had ordered, but the Court recognizes that it should
    have made this expectation explicit — and does so now.
    Accordingly, the government shall address, in its reply brief,
    whether in the originally filed administrative record (i.e., in
    the absence of the RM termination letter) there is evidence
    that the Agency’s corrective action only consisted of
    “review[ing] and amend[ing] the PER” and not reevaluating
    the proposals, as the Agency had represented at GAO. The
    government shall also address the above-quoted
    representations contained in its MJAR.
    August 27, 2021 Order at 1–2.
    The Agency “represented to GAO that, as part of corrective action, ‘[t]he
    [Agency] will reevaluate proposals consistent with the solicitation, determine the impact
    of the reevaluations on the source selection decision, and document its reevaluation[.]’”
    Oak Grove, 
    2021 WL 3627111
    , at *30 (quoting AR 348 (emphasis added)). Consistent
    with that representation, the government asserted that “the SSEB convened to evaluate
    proposals a second time.” ECF No. 30 at 8. The initial administrative record is
    considerably vaguer about precisely what the putative “corrective action” consisted of,
    but there is nothing in the record clearly inconsistent with what the Agency committed
    to the GAO or the government’s subsequent description to the Court — at least, there
    was not, until the RM termination letter was added to the record.
    The RM termination letter described the corrective action as rather minimal. In
    particular, the RM termination letter reveals that “‘[t]he corrective action was to add the
    omitted information into the PER, review the findings for compliance and determine if
    the ratings assessed were still relevant considering the additional information.’” 
    Id. at *29
     (quoting AR 5388). That description gave the Court considerable pause and left the
    Court with the distinct impression — late in these proceedings — that the Agency did
    not reconvene the SSEB “to evaluate proposals a second time” and thus did not perform
    a “reevaluation” as it represented.
    23
    The government responds that: (1) “the [Agency], did, in fact, ‘evaluate
    proposals a second time’”; and (2) the administrative record already disclosed the true
    nature of the correction action, and thus the RM termination letter did not reveal
    anything new to the parties or the Court. Def. Reply at 2, 4. The Court rejects both
    arguments.
    The government’s support for its first contention is that “evaluators changed
    many of the substantive ratings and evaluative results . . . .” Def. Reply at 2. While the
    government repeatedly focuses on what “[t]he [Agency] changed” — and argues that
    those changes “led us to reasonably conclude that the [Agency] evaluated proposals a
    ‘second time’” — that assertion does not help it. Def. Reply at 3–4 (emphasis added).
    As an initial matter, the word “us” strikes the Court as strange. Even if “us” is intended
    to refer to the Justice Department, surely the Agency itself knows whether proposals
    were evaluated a second time. Does the Justice Department mean to say that it was
    misled by the Agency?
    The Court does not dwell on that semantic issue because, in any event, the
    Court’s concern is not assuaged by the mere fact that there was a second award decision
    supported by a second evaluation document with different ratings than the first.
    Rather, the Court’s concern is that the government represented that “the SSEB convened
    to evaluate proposals a second time” — the implication of “a second time” being from
    scratch.23 In reality, however, the Agency simply assigned someone new to fix the
    award documentation, and only part of it, at that. See, e.g., Tr. 33:11–19 (“Mr. [DW]: Cost
    price and past performance were not really picked up and readdressed. . . . Technical
    was where the biggest issues were and where I focused my attention. I was not able to
    bring all the players back together. There were two special operations representatives.
    We were unable to bring them back to reevaluate.” (emphasis added)); Tr. 34:8–13 (“Mr.
    [DW]: We did not take all of [the initial evaluations] and set them aside and start again
    because, as I said, I could not do anything with[out] the two subject matter experts
    whose input was actually very critical in understanding the merits of the exercises that
    were part of Section L and M.”).
    In sum, what Mr. [DW] did as RM’s replacement as SSEB Chairperson was
    “reassess[] whether or not the original findings were accurate.” Tr. 34:20–21; see also Tr.
    36:15–20 (“We reviewed all of the original findings. . . . [I]n the case of me being new, I
    added in what I had observed that was relevant to Factors L and M.”). The fact that Mr.
    23See, e.g., Orbis Sibro, Inc., B-418165.7, 
    2021 WL 1750369
    , at *3–4 (Comp. Gen. Apr. 12, 2021)
    (noting agency’s explanation “that, in order to ensure a proper and thorough evaluation, the
    reevaluation did not rely on the previous evaluation but was performed anew” to include not
    only “a complete reevaluation of all proposals,” but also “a new tradeoff analysis, and a new
    selection decision by a new source selection team” (emphasis added)).
    24
    [DW] performed some sort of “reconciliation,” and “came up with a consensus” used to
    revise the PER, Tr. 36:19–20, is plainly not the same as reconvening the SSEB to evaluate
    proposals a second time. The Court here in no way criticizes Mr. [DW]’s work, nor
    does the Court hold that agencies lack discretion to propose corrective action, including
    the scope of a proposed reevaluation. Rather, the Court is merely contrasting the
    Agency’s representation of the planned corrective action to GAO with the Agency’s
    actual corrective action — including as it was represented in the government’s briefs —
    to underscore the potential significance of the RM termination letter. Oak Grove should
    have had the opportunity to make arguments about the possible implications of that
    document.
    On that note, the government also contends, that “the [RM] termination letter did
    not present any new facts regarding the scope of corrective action performed than that
    contained in the original AR.” (Def. Reply at 4). In support, the government relies on
    the following statement within the August 21, 2020, Memorandum for the Record from
    the “Source Selection Advisory Counsel Chairperson” (or “SSAC”):
    As a result of the corrective action, the PER was updated to
    reflect an accurate representation of the evaluation of the
    Offerors[’] proposals inserting additional findings and
    ensuring that the findings were consistent with the evaluation
    criteria outlined in the solicitation.
    AR 3343 (emphasis added), quoted in Def. Reply at 4.24
    With the benefit of hindsight, and the RM termination letter now in hand, the
    Court understands how to properly read that summary. But, standing alone, that
    statement is ambiguous insofar as it suggests that updates to the PER were made “[a]s a
    result of the corrective action” — implying the updates followed a reevaluation. AR
    3343 (emphasis added). In light of the Agency’s commitment to GAO that the Agency
    would complete a reevaluation, and given the government’s assertion in its brief that
    the Agency reconvened the SSEB, the Court reasonably (but obviously incorrectly) read
    the SSAC’s memorandum as asserting that the PER was updated only after a complete
    reevaluation process. Again, whether deliberately or not, the Court was misled by the
    omission of the RM termination letter. The nature of the actual corrective action only
    became clear once the Court heard Mr. [DW]’s explanation at the show cause hearing.
    The other document in the administrative record upon which the government
    relies — the August 28, 2020, Source Selection Decision Document (“SSDD”) — suffers
    from a similar ambiguity. The SSDD notes that “the PCO initiated corrective actions
    24The government (see Def. Reply at 4) mistakenly cites AR 3349–50, which is the Source
    Selection Decision Document, not the referenced SSAC Chairperson’s Memorandum.
    25
    and arranged for an independent review of the evaluation.” AR 3350 (emphasis added)
    (quoted in Def. Reply at 4).25 If anything, this makes it appear as if the Agency
    conducted a new, second evaluation — consistent with the corrective action promised
    to the GAO — and then, only after that reevaluation, arranged for an independent
    review of that second evaluation. Indeed, the SSDD indicates that a new contract award
    decision was made only “[a]fter a full review of the evaluation results from the SEEB
    members and my independent review of the evaluation documentation[,]” further
    suggesting that there was a full reevaluation and an independent review by the SSDD’s
    author. AR 3350 (emphasis added). In other words, the phrase “my independent
    review” refers to one the Source Selection Authority conducted, leading readers away
    from understanding that the first referenced “independent review” was itself the
    corrective action conducted by the new SSEB Chairperson, Mr. [DW]. Moreover, the
    SSDD indicates that the new, final award decision is “[b]ased on the findings presented
    to the SSAC and Final SSEB PER,” and that “the SSAC independently reviewed and
    compared the results of the SSEB evaluation and determined it was conducted in
    accordance with the factors set forth and the evaluation criteria in the solicitation . . . .”
    AR 3371 (emphasis added). Of course, not until the hearing on the show cause order
    did the Court learn that the SSEB was not reconvened or otherwise reconstituted — as
    noted, supra, several of the original evaluators were unavailable and were not
    reengaged.
    More significantly, as counsel for Oak Grove argued, the limited corrective action
    implemented was entirely inappropriate where, as here, the SSEB Chairperson was
    removed “mid-corrective action” for “competency issues” and then, rather than “dump
    the PER” or “convene new people to conduct a new evaluation,” the Agency continued
    “writing on [RM’s] slate.” Tr. 68:17 – 69:4. The Court agrees with Oak Grove:
    At the end of the day, . . . [t]hey’re working off [RM’s]
    memo. They’re working off his sheet. They’re adjusting
    here; they’re adjusting there. [But,] [t]his is not a new
    evaluation.
    Tr. 69:4–9. Accordingly, the Court rejects the government’s assertion that “[RM] played
    no role in the second evaluation”; indeed, the only way this assertion is possibly true is
    25Similarly, the Court notes that in the Agency’s GAO brief in the protest proceedings following
    the putative corrective action, the Agency represented that it “re-evaluated proposals as part of
    the corrective action consistent with the evaluation criteria set forth in the Solicitation and
    arranged for an independent review of the evaluation.” AR 975 (emphasis added). The
    Agency’s representation to the GAO concerning the nature of the corrective action would lead
    an uninformed reader to believe that there were two steps to the corrective action: (1) a
    reevaluation of proposals; and (2) an independent review of that evaluation. In fact, however, it
    turns out that the “independent review” was the reevaluation.
    26
    if the phrase “second evaluation” is read exceedingly narrowly to mean just the sign-off
    on the final revised SSEB recommendation.26 Def. Reply at 7. But even if that were a
    reasonable way to characterize what happened, it would not excuse the Agency’s
    failure to include the RM termination letter in the administrative record.
    In sum, the Court concludes that the RM termination letter “was a relevant
    document to the matter” and that both Oak Grove and the Court were harmed by the
    Agency’s failure to include it in the initial record. Tr. 49:5–8 (“But at the end of the day,
    [RM] was removed. Everybody in this process knew it and they kept it from [plaintiff’s
    counsel], they kept it from GAO, they kept it from this Court.”). At a minimum, the
    Agency’s failure to include the RM termination letter in the administrative record —
    when combined with various assertions in the briefs and other documents in the record
    — had the effect of concealing RM’s true role in the procurement and the precise nature
    of the corrective action. Cf. Antonious v. Spalding & Evenflo Cos., Inc., 
    275 F.3d 1066
    , 1075
    (Fed. Cir. 2002) (“Advancing even a single invalid theory forces the defendant to
    respond and to do work it should not have been required to do.”). There is no question
    that, without the RM termination letter, the Court would not have the clear picture it
    now has regarding the true nature of the corrective action.
    26The government points to AR 3530 for the proposition that the “existing AR plainly showed”
    that “[RM] had no involvement in the August 2020 re-evaluation and award.” Def. Reply at 7
    (citing AR 3530, AR 3885–86). But AR 3530 is a declaration (made under penalty of perjury)
    from RM’s second-line supervisor, submitted to the GAO, representing that she “saw no
    indications that [RM] acted improperly during the source selection process” but that “for un-
    related reasons, [she] had another Government employee conduct an independent evaluation of
    the proposals for [the procurement] which resulted in the updated Proposal Evaluation
    Report.” AR 3530. The supervisor’s declaration omits that RM was removed from his position
    as SSEB Chairperson, omits that he played a role in the corrective action process (whatever that
    entailed), and certainly would lead a reader to believe that there was an entirely new
    “evaluation of the proposals” — something that did not happen. As Mr. [DW] made clear, his
    “independent” review did not consist of a wholesale reevaluation, but rather was focused on
    the quality of the PER to ensure it aligned with the extant evaluations performed by evaluators
    — former SSEB members — that were not reconvened because they were no longer available.
    The other cited document is the second award notification letter to Oak Grove, see AR 3884–
    3886. It, too, does not disclose anything about the mechanics of the supposed reevaluation or
    RM’s involvement in the putative corrective action. With the benefit of the RM termination
    letter, we now know that when the government told Oak Grove that “the Government
    conducted an independent review of the individual evaluations to ensure that all of the
    evaluations and findings were assessed in accordance with the solicitation procedures,” that did
    not mean the Agency had performed a reevaluation. AR 3885.
    27
    VII.   CONCLUSION
    For all the above reasons, and pursuant to RCFC 11, the Court concludes that the
    United States must pay the legal costs and expenses Oak Grove incurred in dealing with
    the administrative record issues that were the subject of the Court’s show cause order.
    The Agency’s failure to include the omitted documents was neither reasonable nor
    excusable — it was, rather, an improper compilation, submission, and certification of
    the administrative record. The omissions delayed resolving this case, wasted the
    Court’s judicial resources by forcing the Court to engage in fact finding on an
    incomplete record, and imposed substantial costs on Oak Grove.
    Counsel for Oak Grove and the government are directed to meet-and-confer in
    good faith regarding those costs and submit a joint status report on or before
    November 19, 2021, indicating whether they have reached an agreement on a fair and
    reasonable sum, or detailing their respective positions if the parties are unable to reach
    an agreement. A fair and reasonable sum will include costs incurred in reviewing,
    responding to, preparing for, or participating in (as applicable): (1) the supplemental
    administrative record filings (made after the merits briefing and following oral
    argument); (2) related orders of this Court; (3) related supplemental briefs; and
    (4) related status conferences and the show cause hearing.
    IT IS SO ORDERED.
    s/Matthew H. Solomson
    Matthew H. Solomson
    Judge
    28