Blue Origin Federation, LLC v. United States ( 2021 )


Menu:
  •              In the United States Court of Federal Claims
    No. 21-1695C
    Filed: November 4, 2021
    Reissued: November 18, 2021 *
    FOR PUBLICATION
    BLUE ORIGIN FEDERATION, LLC,
    Plaintiff,
    v.
    UNITED STATES,
    Defendant,
    and
    SPACE EXPLORATION
    TECHNOLOGIES CORP.,
    Defendant–Intervenor.
    Scott E. Pickens, Barnes & Thornburg LLP, Washington, D.C., for the plaintiff, with Scott N.
    Godes and Matthew J. Michaels, of counsel.
    Anthony F. Schiavetti, Commercial Litigation Branch, Civil Division, U.S. Department of
    Justice, Washington, D.C., for the defendant, with Allison M. Genco and Brian M. Stanford,
    Office of the General Counsel, National Aeronautics and Space Administration, of counsel.
    Kara L. Daniels, Arnold & Porter Kaye Scholer LLP, Washington, D.C., for the defendant–
    intervenor, with Mark D. Colley, Nathaniel E. Castellano, Thomas A. Pettit, and Aime JH Joo, of
    counsel.
    MEMORANDUM OPINION
    HERTLING, Judge
    In this post-award bid protest, the plaintiff, Blue Origin Federation, LLC (“Blue Origin”),
    challenges a contract award pursuant to a solicitation under a Broad Agency Announcement
    *Pursuant to
    the protective order in this case, the Court initially filed this opinion under seal
    on November 4, 2021 and directed the parties to propose redactions of confidential or proprietary
    information by November 18, 2021. The parties have jointly submitted to the Court proposed
    redactions. (ECF 76.) The Court adopts those redactions, as reflected in this public version of
    the opinion. Redactions are denoted with three asterisks in square brackets, [***].
    (“BAA”) issued by the National Aeronautics and Space Administration (“NASA”). Under its
    Artemis Program, NASA seeks to develop a Human Landing System (“HLS”) through public –
    private partnerships for the United States to return to the moon. The solicitation at issue was the
    second phase of those efforts. NASA awarded the contract to Space Exploration Technologies
    Corp. (“SpaceX”). The defendants are the United States, acting through NASA, and SpaceX,
    which intervened to defend its contract award.
    In its complaint, Blue Origin alleges that NASA (1) waived material solicitation
    requirements for SpaceX; (2) conducted unequal discussions; (3) failed to amend the solicitation
    when NASA received less funding than anticipated; (4) improperly evaluated offerors’ technical
    ratings; and (5) breached the implied contract of good faith and fair dealing. Blue Origin alleges
    that it would have submitted an alternative proposal if it had known that NASA would waive
    certain requirements of the solicitation. Blue Origin has moved for judgment on the
    administrative record under Rule 52.1 of the Rules of the Court of Federal Claims (“RCFC”).
    The United States has moved to dismiss either under RCFC 12(b)(1) for lack of subject-
    matter jurisdiction or, in the alternative, under RCFC 12(b)(6) f or failure to state a claim upon
    which relief can be granted. The defendant argues that Blue Origin does not have standing to
    bring its challenge because Blue Origin did not have a substantial chance of award, even
    assuming its allegations were true, and Blue Origin’s alternative proposal is speculative.
    Alternatively, the government argues that Blue Origin’s first three claims were waived by failing
    to raise the issues before the close of bidding. SpaceX supports the defendant’s motion to
    dismiss.
    The government and SpaceX have also both cross-moved for judgment on the
    administrative record. They argue that NASA did not waive solicitation requirements, and that
    NASA acted properly within its discretion under the solicitation and procurement law. The
    government and SpaceX argue that, even if the Court finds that NASA acted improperly, Blue
    Origin could not have been prejudiced.
    The Court finds that Blue Origin does not have standing because it did not have a
    substantial chance of award but for the alleged evaluation errors. Its proposal was priced well
    above NASA’s available funding and was itself noncompliant. Blue Origin argues that it would
    have submitted an alternative proposal, but the Court finds its hypothetical proposal to be
    speculative and unsupported by the record. The Court also finds that several of Blue Origin’s
    objections are waived.
    Even if Blue Origin had standing and its objections were not waived, the Court finds that
    it would lose on the merits. Blue Origin has not shown that NASA’s evaluation or its conduct
    during the procurement was arbitrary and capricious or otherwise contrary to law. NASA
    provided a thorough, reasoned evaluation of the proposals, and NASA’s conduct throughout the
    procurement process was not contrary to law.
    Accordingly, the Court grants the government’s motion to dismiss and for judgment on
    the administrative record and SpaceX’s motion for judgment on the administrative record . Blue
    Origin’s motion for judgment on the administrative record is denied.
    2
    I.       BACKGROUND
    The “Moon plan” under NASA’s Artemis Program is “focused on achieving the goal of
    an initial human landing [on the moon] by 2024 with acceptable technical risks, while
    simultaneously working toward sustainable lunar exploration in the mid - to late 2020s.” NASA,
    NASA’s Lunar Exploration Program Overview 9 (Sept. 2020), available at
    https://www.nasa.gov/sites/default/files/atoms/files/artemis_plan-20200921.pdf. To that end,
    NASA began a multi-phase HLS procurement, which started with base-period contracts. The
    plan follows the base period with a follow-on “Option A” solicitation, which is at issue in this
    case. (AR Tab 49 at 62409-10.)
    A.    HLS Base-Period Contract
    For the base-period contracts, NASA solicited proposals for the HLS procurement under
    Appendix H of a BAA titled “Next Space Technologies for Exploration Partnerships-2
    (NextSTEP-2).”1 (AR Tab 28 at 33228; AR Tab 108a-002.) NASA awarded base-period
    contracts to Blue Origin, SpaceX, and Dynetics, Inc. (AR Tab 77 at 63038.)
    During the base period, each contractor was enabled to develop a preliminary design of
    its proposed landing system. (See AR Tab 49 at 62409.) During the base period, NASA
    “dispositioned and approved the final list of standards uniquely applicable to [each] Contractor’s
    adjusted proposal for Option A.” (AR Tab 27 at 24443.) The three base-period contractors were
    each required to “use these standards in preparing [their] Option A proposal[s].” (Id.) NASA’s
    intent was “to transition between the Base period and Option A period without any break in
    contractor performance.” (Id. at 24429.)
    B.    HLS Option A Solicitation
    While the three base-period contractors were performing under their contracts, NASA
    solicited proposals from those contractors for the next phase of the HLS procurement:
    “Option A.” (AR Tab 27.) Only the three awardees of base-period contracts could submit
    proposals under the Option A solicitation.
    The solicitation consisted of the HLS Appendix H Option A solicitation, as amended; the
    NextSTEP-2 BAA; and attachments A through Q to the solicitation. (See id. at 24434-36.) The
    solicitation contemplated the award of a firm fixed-price contract. (Id. at 24432.)
    Federal Acquisition Regulation (“FAR”) 35.016, which governs BAAs, provides that
    1
    “BAAs may be used by agencies to fulfill their requirements for scientific study and
    experimentation directed toward advancing the state-of-the-art or increasing knowledge or
    understanding rather than focusing on a specific system or hardware solution.” FAR 35.016(a).
    3
    1.      Structure
    The HLS Option A solicitation was conducted “as an ‘other competitive procedure’ in
    accordance with FAR 6.102(d)(2) and FAR 35.016 (as deviated).” (Id. at 24473.) A Source
    Evaluation Panel (“SEP”) was responsible for evaluating proposals and presenting the results to
    the Source Selection Authority (“SSA”). (Id. at 24480.) The SEP was comprised of NASA
    subject-matter experts. Three distinct panels were established to review different aspects of the
    proposals: a technical-evaluation panel, price-evaluation panel, and management-evaluation
    panel. After the SEP submitted its evaluations to the SSA, the SSA was “responsible for making
    selections and final contract award decisions based on applying the evaluation, selection, and
    award methodology as described in [the Option A] solicitation.” (Id.)
    The solicitation explained that NASA would “not conduct a comparative analysis and
    trade-off” among proposals. (Id. at 24473.) Instead, the SSA would “consider each proposal on
    its own individual merits, and [would] select for award one or more proposals that individually
    each present value to the Government and that optimize NASA’s ability to meet its objectives as
    set forth in [the Option A] solicitation.” (Id. at 24480.)
    The number of awards NASA would make depended on “funding availability and
    evaluation results.” (Id. at 24481.) Although NASA preferred to award two contracts, “NASA
    reserve[d] the right to change its HLS acquisition strategy at any time.” (Id. at 24429.) The
    solicitation noted that “[f]unds are not currently available for this solicitation, but are expected to
    become available on or before contract award.” (Id. at 24481.) The solicitation expressly noted
    that awards were contingent on those funds becoming available: “The Government’s obligation
    to make awards is contingent upon the availability of appropriated funds from which payments
    can be made and the receipt of proposals that NASA determines are acceptable.” (Id.)
    Consistent with this funding contingency, “NASA reserve[d] the right to select for award
    multiple, one, or none of the proposals received . . . .” (Id.)
    NASA also reserved “the right to conduct post-selection negotiations or discussions if the
    Contracting Officer later determines them to be necessary.” (Id. at 24433.) The solicitation gave
    the SSA the authority to “make initial, non-binding selections of an Offeror or Offerors for the
    purpose of having the Contracting Officer engage in post-selection negotiations with one or more
    Offerors as defined in [the Option A] solicitation.” (Id. at 24480.) The solicitation further
    reserved to NASA “the right to negotiate any aspect of an Offeror’s milestone payment a mounts,
    schedule, and/or acceptance criteria prior to award of Option A.” (Id. at 24467.)
    Under the solicitation, timing is the only difference between post-selection negotiations
    and discussions. “Post-selection negotiations” are defined in the solicitation as “exchanges with
    Offerors who have been selected for potential contract award that result in the Contracting
    Officer inviting the Offeror to revise only those specific portions of its proposal that have been
    identified by the Contracting Officer as open to revision.” (Id. at 24434.) “Discussions” are
    defined as “exchanges with Offerors that occur after receipt of proposals but before selection that
    result in the Contracting Officer inviting the Offeror to revise only those specific portions of its
    proposal that have been identified by the Contracting Officer as open to revision.” (Id.) A
    4
    “‘[p]roposal revision’ is any change made by the Offeror to its proposal that occurs as a result of
    discussion or post-selection negotiations . . . .” (Id.)
    In bold-faced type, the solicitation provided that “[t]he Government may evaluate
    proposals and award contracts without conducting post-selection negotiations or discussions with
    Offerors . . . .” (Id. at 24433 (bold omitted).) As a result, the solicitation directed that “each
    Offeror . . . submit only one proposal which represents its best approach to meeting the
    requirements of the solicitation.” (Id.)
    2.      Evaluation Criteria
    The solicitation designated three evaluation factors: Technical Approach, Total Evaluated
    Price, and Management Approach. (Id. at 24475.) The technical approach was more important
    than the total evaluated price, which was more important than the management approach. (Id.)
    The technical approach and management approach, when combined, were “significantly more
    important” than the total evaluated price. (Id.)
    As further guidance for the technical-approach and management-approach factors, the
    solicitation provided “areas of focus.” (Id.) The areas of focus (each “approximately of equal
    importance within their respective Factor”) were to be “considered in totality to arrive at a single
    adjectival rating for each factor.” (Id.) The adjectival ratings consisted of Outstanding, Very
    Good, Acceptable, Marginal, and Unacceptable. (Id. at 24477.)
    Regarding the technical-approach and management-approach factors, NASA would also
    identify and evaluate specific strengths and weaknesses of each proposal. (Id. at 24476.) For
    these purposes, NASA would “consider how an Offeror’s proposed approach affects risk, such as
    technical risk, risk to meeting the Offeror’s proposed schedule, the need for increased
    Government oversight, or the risk of likelihood of unsuccessful contract performance.” (Id.)
    The solicitation listed five categories of strengths and weaknesses: Significant Strength,
    Strength, Weakness, Significant Weakness, and Deficiency. (Id.) Relevant here, “Weakness”
    was defined as “[a] flaw in the proposal that increases the risk of unsuccessful contract
    performance.” (Id.) “Deficiency” was defined as “[a] material failure of a proposal to meet a
    Government requirement or a combination of significant weaknesses in a proposal that increases
    the risk of unsuccessful contract performance to an unacceptable level.” (Id.)
    The solicitation notified offerors that “proposals evaluated as having one or more
    deficiencies are unawardable,” and that NASA reserved the right to exclude from discussions or
    negotiations the offerors whose proposals were identified as having one or more deficie ncies.
    (Id. at 24480.)
    3.      Statement of Work
    The Statement of Work (“SOW”), Attachment G to the solicitation, described the work to
    be performed under the HLS Option A contract. (AR Tab 27e.) The SOW was common to all
    offerors and described, among other topics, “major milestone reviews for the HLS Program in
    order to be able to assess programmatic and technical progress and performance at key decision
    5
    points in the development and operational lifecycle phases . . . .” (Id. at 32965.) The NASA-led
    critical-milestone reviews included the Flight Readiness Review(s) (“FRR”) and the Design
    Certification Review (“DCR”). (Id. at 32965-66.)
    The FRR is the first critical-milestone review at issue in this case. The FRR has two
    objectives. First, it “examines tests, demonstrations, analyses, and audits that determine the
    system’s readiness for a safe and successful flight or launch and for subsequent flight
    operations.” (Id. at 32972.) Second, it “ensures that all flight and ground hardware, software,
    personnel, and procedures are operationally ready.” (Id.) The FRR Acceptance Criteria include
    certification that “[t]he flight vehicle, launch vehicle, and support spacecraft (such as propellant
    storage, propellant transfer, and/or upper stage vehicles that provide transportation capabilities
    beyond the standard for orbit insertion) are ready for flight.” (Id.) The SOW provided that
    “[t]he FRR should be completed by two (2) weeks before launch of each HLS element.” (Id.)
    The Milestone Acceptance Criteria and Payment Schedule, Attachment O to the solicitation,
    phrased the FRR as a requirement: “An FRR is required prior to each launch of an HLS
    element.” (AR Tab 27k at 33187.)
    The DCR is the second critical-milestone review at issue in this case. This review
    “ensures that the qualification and verifications demonstrate design compliance with the
    functional and performance requirements and human spaceflight certification.” (AR Tab 27e at
    32969.) The SOW provides that the DCR “should be completed at first HLS launch – 9 Months
    (L-9).” (Id.) The Milestone Acceptance Criteria and Payment Schedule clarified that the DCR
    was to be scheduled “9 months before first HLS element launch (L-9 months).” (AR Tab 27k at
    33187 (emphasis added).)
    Both the FRR and the DCR were to be conducted for an “HLS element.” Although the
    SOW did not define “HLS element,” it did define “HLS”:
    HLS: All objects, vehicles, elements, integrated systems, systems,
    subsystems, or components thereof that are designed, developed,
    and utilized by the contractor, its teammates, subcontractors, and
    suppliers in performance of this contract, and which collectively
    comprise the contractor’s Integrated Lander (or elements thereof),
    all Supporting Spacecraft, all launch vehicles necessary for launch
    and delivery of the contractor’s Integrated Lander (or elements
    thereof) and its Supporting Spacecraft, and the contractor’s Active-
    Active docking adapter . . . (if required for performance of the
    contractor’s crewed demonstration mission).
    (AR Tab 27e at 32948 (bold in original).) The parties disagree about how to read this definition
    together with other provisions of the SOW to interpret “HLS element.”
    6
    C.     Source Selection and Award
    1.      Proposals and Evaluations
    Each of the three base-period contractors—Blue Origin, SpaceX, and Dynetics—
    submitted a timely proposal in response to the HLS Option A solicitation. (AR Tab 77 at 63038-
    39.) Blue Origin’s Total Evaluated Price was about $6 billion, and Dynetics’ Total Evaluated
    Price was about $9 billion. (AR Tab 61 at 62856, 62866.) As the SSA noted in her summary of
    the SEP’s evaluation results, “SpaceX’s Total Evaluated Price of $2,941,394,557 was the lowest
    among the offerors by a wide margin.” (AR Tab 77 at 63044.) Although the prices varied, the
    SSA found each price to be fair, reasonable, and balanced. (Id. at 63048, 63054, 63059.)
    Within a few weeks of NASA receiving the Option A proposals, Congress enacted the
    Consolidated Appropriations Act, 2021, which appropriated $850 million for the HLS program
    for fiscal year (“FY”) 2021. Pub. L. 116-260, 
    134 Stat. 1182
     (2020). (See also AR Tab 108b26a
    at 103671-73 (explaining the appropriation and its impact during the selection process).) For
    FY 2021, NASA had sought an appropriation of $3.4 billion for the development of the moon-
    lander systems. Office of Management and Budget, A Budget for America’s Future: Budget of
    the U.S. Government (Fiscal Year 2021) 101 (Feb. 10, 2020). 2 Upon receipt of the FY 2021
    appropriation, the SEP continued its work evaluating the proposals without amending or
    canceling the solicitation. (AR Tab 108b26a at 103671.)
    In their proposals, Blue Origin and SpaceX took different approaches in design and
    operation of their moon-landing systems. Blue Origin proposed a three-element architecture for
    its Integrated Lander, which consisted of an ascent element, a descent element, and a transfer
    element. (AR Tab 32a at 33339-41.) Blue Origin’s proposal would require three launches. (AR
    Tab 61 at 62852.) SpaceX, in contrast, proposed a single-element Integrated Lander called the
    HLS Starship. (AR Tab 34d.55 at 56274-77.) SpaceX also proposed two types of supporting
    spacecraft: propellant-storage depot and tanker vehicles. (Id. at 56274.) The supporting
    spacecraft launch before the HLS Starship to aggregate and store propellant in low-Earth orbit
    for the HLS Starship to access for the lunar mission. (Id.) SpaceX’s proposal would require 16
    launches. (AR Tab 61 at 62874.)
    The SEP evaluated the proposals and “produced a report for each offeror containing all of
    the SEP’s findings, ratings, and other evaluative content.” (AR Tab 77 at 63039.) As required
    2
    This document is available at https://www.govinfo.gov/content/pkg/BUDGET-2021-
    BUD/pdf/BUDGET-2021-BUD.pdf.
    7
    by the solicitation, the SEP provided adjectival ratings for the technical and management
    evaluation factors:
    Offeror             Technical Rating (Factor 1)          Management Rating (Factor 3)
    Blue Origin           Acceptable                             Very Good
    Dynetics              Marginal                               Very Good
    SpaceX                Acceptable                             Outstanding
    (Id. at 63044.)
    Although the SEP rated SpaceX’s management approach “Outstanding,” the SEP
    assigned SpaceX a weakness for an inconsistency related to milestones within SpaceX’s
    Integrated Master Schedule (“IMS”). (AR Tab 59c at 62812.) SpaceX had proposed a single
    NASA-led FRR for its HLS Starship but no NASA-led FRRs for its supporting spacecraft. (AR
    Tab 34d.33 at 55430.) As a result, of the 16 launches required under SpaceX’s proposal, only
    one would have a NASA-led FRR before launch. The SEP explained that “[w]hile the offeror’s
    proposed milestones, associated acceptance criteria, and IMS are internally consistent, they are
    arguably not consistent with all milestone review requirements as set forth within and
    contemplated by the solicitation’s [SOW] and the solicitation’s Milestone Acceptance Criteria
    and Payment Schedule . . . .” (AR Tab 59c at 62812.)
    The SEP found the relevant terms of the solicitation to be unclear. (Id. at 62813.) Under
    one possible interpretation, “offerors were required to propose an FRR milestone (and associated
    review) to be conducted and achieved for each proposed supporting spacecraft prior to launch
    and flight operations.” (Id.) Under another possible interpretation, “offerors were required to
    propose a single FRR covering the full scope of its demonstration mission prior to the launch of
    any lander element or supporting spacecraft.” (Id.) The SEP found that SpaceX’s “proposed
    FRR milestone is not in accordance with either interpretation.” (Id.) SpaceX “neither proposed
    any FRR events dedicated to one or all of its supporting spacecraft, nor a single FRR to cover the
    full scope of its demonstration mission prior to the launch of its first supporting spacecraft.”
    (Id.) The SEP concluded that “this aspect of [SpaceX’s] proposal increases risk of unsuccessful
    performance and constitutes a weakness.” (Id. at 62814.)
    2.   Post-Selection Negotiation
    According to the contracting officer, after the SEP presented its final evaluation results to
    the SSA, “the SSA noted that it was her opinion that SpaceX’s proposal was both highly rated
    from a non-price perspective, and, in her judgment, provided abundant value at its Total
    Evaluated Price.” (AR Tab 108b26a at 103673.) In a conversation with the SSA about the
    budget, the contracting officer informed the SSA that “NASA’s available funding overall could
    potentially support a contract award to SpaceX . . . , but that NASA was unable to award a
    contract to SpaceX with the specific phasing of milestone payments SpaceX proposed.” (Id.
    (emphasis in original).) NASA’s budget analyst had determined that about $345 million would
    8
    be available for FY 2021 Option A contractor payments. (Id.) SpaceX’s proposed FY 2021
    milestone payments totaled [***], so there was about a [***] shortfall. (Id.) The contracting
    officer thought that the shortfall “was likely not an insurmountable situation given the
    flexibilities that NASA had built into the terms of the Option A solicitation ,” and that “post-
    selection negotiations could be utilized to create a situation in which the Agency would be able
    to afford making a contract award to SpaceX.” (Id.)
    Given the information from the contracting officer, the SSA found that, “at the initial
    prices and milestone payment phasing proposed by each of the Option A offerors, NASA’s
    current fiscal year budget did not support even a single Option A award.” (AR Tab 77 at 63039.)
    As a result, the SSA determined “that NASA should, as a first step, open price negotiations with
    [SpaceX, whose proposal was] both very highly rated from a technical and management
    perspective and that also had, by a wide margin, the lowest initially -proposed price . . . .” (Id.)
    The SSA concluded that “it would be in the Agency’s best interests to make an initial,
    conditional selection of SpaceX to enable the Contracting Officer . . . to engage in post-selection
    price negotiations with this offeror.” (Id.; see also AR Tab 64 (making the initial, non-binding
    selection of SpaceX for award and directing the contracting officer to engage in post-selection
    negotiations).)
    In the contracting officer’s letter to open negotiations, the contracting officer requested
    that SpaceX submit its best final firm-fixed prices for two contract line-item numbers (“CLINs”),
    adjust its payment phasing to accommodate NASA’s FY 2021 funding limitations, and add FRRs
    to its proposal. (AR Tab 63.) The requested additional FRRs included the following:
    (1) A single comprehensive Tanker Starship Supporting Spacecraft
    FRR no later than two weeks prior to the first launch of the Tanker
    Starship Supporting Spacecraft that will address flight readiness for
    the entire Tanker Starship Supporting Spacecraft launch campaign;
    (2) a Depot Starship FRR no later than two weeks prior to the launch
    of the Depot Starship; and (3) within Attachment 12 [Review Plan]
    only, NASA also requests that your firm include potential “delta-
    FRRs” that would be triggered to occur in the event of anomalies,
    mishaps, configuration changes, or other issues directly relevant to
    flight readiness, if and when such issues arise.
    (Id. at 62890 (emphasis in original).)
    In response, SpaceX submitted a revised proposal. (See AR Tab 68 (providing the cover
    letter for SpaceX’s revised proposal and describing the revisions).) SpaceX added the requested
    FRRs for its HLS depot and tanker campaign flights. (Id. at 62903.) SpaceX also adjusted its
    payment milestones so that those that would fall within FY 2021 could be accommodated within
    NASA’s anticipated funding levels, but SpaceX maintained its original pricing regarding the two
    CLINs. (Id. at 62902-03.) SpaceX did not reduce its overall price. (AR Tab 77 at 63039.)
    9
    3.     Award
    After a final review of the offerors’ SEP reports and SpaceX’s revised pricing proposal,
    the SSA selected only SpaceX for award of the Option A contract. (Id. at 63039.) Although the
    SSA reiterated NASA’s preference for making two awards, she noted that the amount of the
    appropriation, when compared to the offerors’ prices, was “incongruent with NASA’s Option A
    acquisition strategy.” (Id. at 63043.) The SSA analyzed each offeror’s proposal and explained
    her selection determination for each. (Id. at 63044-60.)
    After analyzing SpaceX’s proposal, the SSA determined “that SpaceX’s proposal is
    meritorious and advantageous to the Agency, and that it aligns with the objectives as set forth in
    [the Option A] solicitation.” (Id. at 63049.) Regarding SpaceX’s technical approach, the SSA
    found that “the qualitative attributes of SpaceX’s aggregated strengths and its aggregated
    weaknesses are offsetting and that commensurate risk accompanies the meritorious aspects of
    SpaceX’s technical approach.” (Id. at 63048.) Regarding SpaceX’s management approach, the
    SSA “concur[red] with the SEP that SpaceX’s management approach is of exceptional merit and
    fully responsive to the objectives of the solicitation.” (Id. at 63049.) She found “that the
    qualitative attributes of SpaceX’s aggregated strengths, including its rating of High for its Base
    Period Performance, far outweigh the qualitative attributes of its evaluated weaknesses, which
    were relatively minor.” (Id.)
    The SSA “conclude[d] that SpaceX’s acceptable technical approach coupled with its
    outstanding management approach provide abundant value for NASA at its Total Evaluated
    Price.” (Id. at 63049-50.) She also noted that, due to NASA’s post-selection negotiation with
    SpaceX, “the Agency’s budget now permits the award of a contract to SpaceX.” (Id. at 63050.)
    The SSA selected SpaceX’s proposal for an award. (Id.)
    The SSA’s selection determination regarding Blue Origin’s proposal was “based upon the
    results of its evaluation considered in light of the Agency’s currently available and anticipated
    future funding for the HLS program.” (Id. at 63056.) Although the SSA found that “Blue
    Origin’s proposal has merit and is largely in alignment with the technical and management
    objectives set forth in the solicitation,” she did not select Blue Origin for award “because [she
    found] that its proposal does not present sufficient value to the Government when analyzed
    pursuant to the solicitation’s evaluation criteria and methodology.” (Id.)
    The SSA “considered whether it may be in the Government’s best interests to engage in
    price negotiations to seek a lower best and final price from Blue Origin.” (Id.) The SSA
    determined that she could not open price negotiations with Blue Origin in good faith, “given
    NASA’s current and projected HLS budgets.” (Id.) “After accounting for a contract award to
    SpaceX, . . . [the SSA did] not have enough funding available to even attempt to negotiate a price
    from Blue Origin that could potentially enable a contract award.” (Id.) Accordingly, the SSA
    did not select Blue Origin’s proposal for award. (Id.)
    The SSA also did not select Dynetics’ proposal for award. (Id. at 63060.) The details of
    that decision are not relevant to this case.
    10
    D.      GAO Protest
    After receiving notice of NASA’s single award to SpaceX, Blue Origin and Dynetics
    filed protests (later consolidated) with the Government Accountability Office (“GAO”). (AR
    Tab 108b67a at 105016.) As summarized by the GAO, the protests “primarily contend[ed] that
    the agency was required to open discussions, amend, or cancel the Option A BAA when NASA,
    after the receipt of proposals, determined that it had less funding than it needed to support
    multiple awards for the HLS program.” (Id. at 105005.) Blue Origin and Dynetics also argued
    “that NASA unreasonably evaluated proposals.” (Id.) The GAO rejected each of the protestors’
    arguments but one. Blue Origin Fed’n, LLC; Dynetics, Inc.-A Leidos Co., B-419783, B-
    419783.2, B-419783.3, B-419783.4, 2021 CPD ¶ 265 (Comp. Gen. July 30, 2021).
    (AR Tab 108b67a.)
    The protestors argued that SpaceX’s proposal failed to include an FRR for each launch as
    allegedly required by the Option A solicitation. (AR Tab 108b67a at 105074-75.) The SOW
    provided that “[t]he FRR should be completed by two (2) weeks before launch of each HLS
    element.” (AR Tab 27e at 32972 (emphasis added).) The Milestone Acceptance Criteria and
    Payment Schedule provided that “[a]n FRR is required prior to each launch of an HLS element.”
    (AR Tab 27k at 33187 (emphasis added).) The protestors alleged that NASA waived the FRR
    requirement for SpaceX when NASA required SpaceX to include only three FRRs, rather than
    16 FRRs, one for each of its 16 launches. (AR Tab 108b67a at 105075.)
    The GAO agreed with the protestors on this issue. (Id. at 105076.) The GAO interpreted
    “HLS element” to include supporting spacecraft. (Id.) The GAO found that a contrary reading
    would require the GAO “to read ‘supporting spacecraft’ out of the definition of ‘HLS,’ and the
    ‘each’ out of ‘each launch.’” (Id.) Because the solicitation required an FRR for launches of
    supporting spacecraft, the GAO concluded that SpaceX’s three proposed FRRs were insufficient:
    “where the Option A BAA required an FRR before each launch of each HLS element, SpaceX’s
    three proposed FRRs--or one for each type of HLS element--were insufficient when SpaceX’s
    concept of operations will require 16 total launches.” (Id. (emphasis in original).)
    Despite siding with the protestors on the number and timing of FRRs in SpaceX’s
    proposal, the GAO found “no basis on which to sustain the protests because the protestors [had]
    failed to establish any reasonable possibility of resulting competitive prejudice.” (Id. at 105077.)
    The protestors had not alleged “that they otherwise could or would have changed their proposals
    to substantially increase their likelihood of receiving the award had they known of the waiver of
    the FRR requirement.” (Id.) The GAO noted that Blue Origin’s proposed concept of operations
    was “materially different” from SpaceX’s proposed concept of operations. (Id.) Blue Origin,
    therefore, could not “reasonably establish how it could have improved the competitiveness of its
    proposal had it known that the agency would relax the FRR requirement as it did.” (Id.)
    Having found no prejudice to Blue Origin and Dynetics, the GAO denied the protests.
    (AR Tab 108b67a at 105080.)
    11
    E.      Procedural History
    On August 13, 2021, Blue Origin filed its complaint in this court. (ECF 1.) Blue Origin
    asserts five counts, alleging that NASA (1) unlawfully waived material solicitation requirements;
    (2) engaged in improper and unequal discussions; (3) failed to amend its solicitation upon a
    change in requirements; (4) failed to evaluate SpaceX’s proposal in accordance with the
    solicitation; and (5) breached an implied-in-fact contract of good faith and fair dealing. (Id.
    ¶¶ 119-75.)
    Blue Origin seeks declaratory and injunctive relief, requesting that the Court “[d]eclare
    that NASA’s award of the HLS Option A contract to SpaceX is arbitrary, capricious, an abuse of
    discretion, or otherwise not in accordance with law”; “[e]njoin NASA and SpaceX from
    commencing or continuing performance of the HLS Option A contract”; and “[d]irect NASA to
    open discussions with all offerors, allow proposal revisions, re-evaluate revised proposals, and
    make a new selection and award.” (Id. at 58, Prayer for Relief.) Blue Origin also seeks
    attorneys’ fees and costs, its proposal costs, and any other relief that the Court deems just and
    proper. (Id.)
    The parties engaged in preliminary motions practice regarding how much of the
    complaint could be filed in redacted form. The Court heard oral argument on the issue , rendered
    a tentative oral ruling, and directed the parties to continue their negotiations over the redactions.
    The parties largely resolved their disagreements, and, after a ruling on two remaining issues, the
    parties filed public versions of their filings.
    After the government filed the administrative record, which exceeds 135,000 pages, Blue
    Origin moved to complete that record, arguing that documents were missing from it. (ECF 37.)
    After hearing oral argument on the matter, the Court orally denied that motion. (ECF 45.)
    The government has moved to dismiss or, in the alternative, for judgment on the
    administrative record. (ECF 60.) Blue Origin and SpaceX have also moved for judgment on the
    administrative record. (ECF 61 & 62.) The motions have been fully briefed, and the Court heard
    oral argument on October 21, 2021.
    II.    STANDARD OF REVIEW
    A.      Motion to Dismiss
    The government has moved to dismiss both for lack of subject-matter jurisdiction under
    RCFC 12(b)(1) and for failure to state a claim under RCFC 12(b)(6).
    Under RCFC 12(b)(1), the “court must accept as true all undisputed facts asserted in the
    plaintiff’s complaint and draw all reasonable inferences in favor of the plaintiff.” Trusted
    Integration, Inc. v. United States, 
    659 F.3d 1159
    , 1163 (Fed. Cir. 2011). When a plaintiff’s
    jurisdictional facts are challenged, only those factual allegations that the government does not
    controvert are accepted as true. Shoshone Indian Tribe of Wind River Rsrv. v. United States,
    
    672 F.3d 1021
    , 1030 (Fed. Cir. 2012). The court is not “‘restricted to the face of the pleadings’”
    in resolving disputed jurisdictional facts, 
    id.
     (quoting Cedars-Sinai Med. Ctr. v. Watkins, 
    11 F.3d 12
    1573, 1584 (Fed. Cir. 1993), cert. denied, 
    512 U.S. 1235
     (1994)), and may review evidence
    outside the pleadings. 
    Id.
    The plaintiff has the burden of establishing jurisdiction by a preponderance of the
    evidence. Trusted Integration, Inc., 
    659 F.3d at 1163
    . If the court finds that it lacks subject-
    matter jurisdiction over the plaintiff’s claim, RCFC 12(h)(3) requires dismissal of the claim.
    Under RCFC 12(b)(6), dismissal “is appropriate when the facts asserted by the claimant
    do not entitle him to a legal remedy.” Lindsay v. United States, 
    295 F.3d 1252
    , 1257 (Fed. Cir.
    2002). The court must both accept as true a complaint’s well-pleaded factual allegations,
    Ashcroft v. Iqbal, 
    556 U.S. 662
    , 679 (2009), and draw all reasonable inferences in favor of the
    non-moving party. Sommers Oil Co. v. United States, 
    241 F.3d 1375
    , 1378 (Fed. Cir. 2001). To
    avoid dismissal under RCFC 12(b)(6), a complaint must allege facts “plausibly suggesting (not
    merely consistent with)” a showing that the plaintiff is entitled to the relief sought. Bell Atl.
    Corp. v. Twombly, 
    550 U.S. 544
    , 557 (2007). “The plausibility standard is not akin to a
    ‘probability requirement,’ but it asks for more than a sheer possibility that a defendant has acted
    unlawfully.” Iqbal, 
    556 U.S. at 678
     (quoting Twombly, 
    550 U.S. at 556
    ).
    B.      Motion for Judgment on the Administrative Record
    On a motion for judgment on the administrative record pursuant to RCFC 52.1, the
    court’s review is limited to the administrative record, and the court makes findings of fact as if it
    were conducting a trial on a paper record. See Bannum, Inc. v. United States, 
    404 F.3d 1346
    ,
    1354 (Fed. Cir. 2005). The court must determine whether a party has met its burden of proof
    based on the evidence contained within the administrative record. 
    Id. at 1355
    . Unlike motions
    for summary judgment, genuine issues of material fact will not foreclose judgment on the
    administrative record. 
    Id. at 1356
    .
    III.   JURISDICTION
    The Tucker Act, 
    28 U.S.C. § 1491
    (b)(1), establishes the jurisdiction of the Court of
    Federal Claims over bid protests:
    [T]he Unite[d] States Court of Federal Claims . . . shall have
    jurisdiction to render judgment on an action by an interested party
    objecting to a solicitation by a Federal agency for bids or proposals
    for a proposed contract or to a proposed award or the award of a
    contract or any alleged violation of statute or regulation in
    connection with a procurement or a proposed procurement.
    
    28 U.S.C. § 1491
    (b)(1). This provision “expressly waives sovereign immunity for claims against
    the United States in bid protests,” covering “a broad range of potential disputes arising during the
    course of the procurement process.” Sys. Application & Techs., Inc. v. United States, 
    691 F.3d 1374
    , 1380 (Fed. Cir. 2012).
    To establish standing under this court’s bid-protest jurisdiction, a protestor must be an
    “interested party.” 
    28 U.S.C. § 1491
    (b)(1). The Federal Circuit has interpreted this term to
    13
    require a protestor to have alleged facts, which if true, “establish that it (1) is an actual or
    prospective bidder, and (2) possesses the requisite direct economic interest.” Rex Serv. Corp. v.
    United States, 
    448 F.3d 1305
    , 1307 (Fed. Cir. 2006). Here, the first prong is not at issue because
    Blue Origin is an actual bidder.
    The second prong, in contrast, is at issue. In determining whether a protestor has alleged
    facts demonstrating the “requisite direct economic interest,” the court must decide whether those
    alleged facts show the protestor was prejudiced by the alleged errors. Statistica, Inc. v.
    Christopher, 
    102 F.3d 1577
    , 1581 (Fed. Cir. 1996). To establish prejudice for standing purposes
    in a post-award bid protest, the protestor’s complaint must “show that there was a ‘substantial
    chance’ it would have received the contract award but for the alleged error in the procurement
    process.” Info. Tech. & Applications Corp. v. United States, 
    316 F.3d 1312
    , 1319 (Fed. Cir.
    2003) (quoting Alfa Laval Separation, Inc. v. United States, 
    175 F.3d 1365
    , 1367 (Fed. Cir.
    1999) (citation omitted)). The government and SpaceX argue that Blue Origin’s allegations do
    not establish, as a matter of law, that it was prejudiced by the alleged errors.
    For the limited purpose of determining whether it has standing, a protestor’s allegations
    are assumed to be true. Am. Relocation Connections, L.L.C. v. United States, 789 F. App’x 221
    (Fed. Cir. 2019) (“For standing, we presume the party bringing a bid protest will succeed on the
    merits of its claim and ask whether it has alleged an injury (or prejudice) caused by the procuring
    agency’s actions.”); L-3 Commc’ns Corp. v. United States, 
    99 Fed. Cl. 283
     (2011) (“[T]he
    prejudice determination for purposes of standing assumes all non-frivolous allegations to be true,
    whereas the post-merits prejudice determination is based only on those allegations which have
    been proven true.”). “Prejudice is a question of fact . . . .” Am. Relocation Connections, 789 F.
    App’x at 225 (citing Bannum, 
    404 F.3d at 1353-54
    ).
    The Court first considers whether Blue Origin has standing based on the proposal it
    submitted to NASA and then considers whether it has standing based on an alternative proposal,
    which Blue Origin now alleges it would have submitted if it had known that NASA would waive
    certain solicitation requirements.
    A.      Submitted Proposal
    In response to NASA’s HLS Option A solicitation, Blue Origin proposed a three-element
    architecture for its Integrated Lander. (AR Tab 32a at 33339-41.) This proposed architecture
    would require three launches and no support spacecraft. (AR Tab 61 at 62852.) Blue Origin’s
    Total Evaluated Price totaled just under $6 billion; Blue Origin sought about [***] during
    FY 2021. (AR Tab 61 at 62856; see also AR Tab 108b67a at 105010 (calculating price for
    FY 2021) (citing AR Tab 32d.87).)
    The HLS procurement was conducted “as an ‘other competitive procedure’ in accordance
    with FAR 6.102(d)(2) and FAR 35.016 (as deviated).” (AR Tab 27 at 24473.) The governing
    BAA regulation, FAR 35.016, provides that “[w]ritten evaluation reports on individual proposals
    will be necessary but proposals need not be evaluated against each other since they are not
    submitted in accordance with a common work statement.” FAR 35.016(d). The solicitation
    explained that NASA would “not conduct a comparative analysis and trade-off” among
    14
    proposals; instead, “each proposal [would] be evaluated on its own individual merits.” (AR
    Tab 27 at 24473.)
    “In light of this structure,” the government argues, “Blue Origin lacks standing to
    challenge NASA’s evaluation of SpaceX’s proposal at all, because Blue Origin was not
    competing against SpaceX, but hoping to convince NASA that its proposal merited the
    investment of available NASA research and development funding.” (ECF 60 at 39-40.) During
    oral argument, the government expanded on its position to argue that an unsuccessful bidder
    under a BAA could challenge an agency’s failure to award it a contract but could not challenge
    or seek to enjoin an agency’s award to another, successful bidder.
    That general argument must fail in the face of the facts underlying NASA’s solicitation;
    the government’s argument elevates form over substance. The Option A solicitation noted that
    this procurement deviated from the typical BAA procedures. (AR Tab 27 at 24473.) Although
    “proposals need not be evaluated against each other since they are not submitted in accordance
    with a common work statement,” FAR 35.016(d), for this procurement there was in fact a
    common work statement, the SOW. (See AR Tab 27e.)
    Not only was there a common work statement, but NASA did in fact compare the
    proposals to each other during parts of the evaluation. NASA’s comparison among proposals is
    evidenced by the SSA’s Source Selection Statement. The SSA acknowledged the competitive
    nature of the acquisition by explaining that “NASA’s HLS acquisition strategy has been to
    maintain a competitive environment through the initial crewed lunar demonstrations and beyond,
    thereby creating performance and pricing incentives for contractors at all stages of the HLS
    Program.” (AR Tab 77 at 63043.) Moreover, her summary of evaluation results placed the
    technical and management adjectival ratings for all offerors in a common chart and then
    explicitly compared proposal prices. (Id. at 63044.)
    Because NASA compared and competed against each other the three proposals for award,
    the government’s argument that Blue Origin lacks standing based only on the fact that NASA
    used a BAA as its method of procurement is not congruent with the facts of the award at issue.
    The government’s argument that Blue Origin is unable to show prejudice on this basis alone is
    insufficient to defeat Blue Origin’s standing. Other facts in this case, however, do prevent Blue
    Origin from establishing prejudice to support its standing.
    1.     Proposed Price Greatly Exceeded Available Funding
    Blue Origin’s milestone payments for FY 2021 were more than triple NASA’s FY 2021
    budget for the Option A contract. Upon receiving its FY 2021 appropriation from Congress,
    NASA determined that about $345 million would be available for FY 2021 Option A contractor
    payments. (AR Tab 108b26a at 103673.) Blue Origin’s proposal had sought about [***] during
    FY 2021. (AR Tab 108b67a at 105010 (citing AR Tab 32d.87).)
    Considering the funding shortfall, even if the Court found that either NASA’s evaluation
    of SpaceX was improper or SpaceX’s proposal was unawardable, Blue Origin cannot show that
    it would be in a position for award. NASA had anticipated when it issued the solicitation that it
    15
    may have limited funding and expressly “reserve[d] the right to select for award multiple, one, or
    none of the proposals received . . . .” (AR Tab 27 at 24481 (emphasis added).) Once Congress
    made its funding decision, NASA could not have awarded Blue Origin the contract at its
    proposed price or anything close to it.
    SpaceX’s proposed FY 2021 milestone payments, totaling [***], were also above
    NASA’s funding limit. (AR Tab 108b26a at 103673.) The contracting officer concluded that
    the shortfall of approximately [***] between the funds available to NASA and SpaceX’s
    proposal was not insurmountable. (Id.) Indeed, SpaceX did adjust its payment schedule to meet
    NASA’s available budget during post-selection negotiations. (AR Tab 68 at 62902-03.)
    Blue Origin alleges that it also would have adjusted its payment schedule to meet
    NASA’s budget. Robert Smith, Blue Origin’s final approval authority for its strategy and offer
    to NASA, averred that he “can state definitively that Blue Origin would have fit its proposal
    within the Agency’s estimated budget for an HLS Option A contract.” (ECF 61-1, Pl.’s Ex. 1,
    Decl. of Robert H. Smith, ¶ 26.) During Blue Origin’s GAO protest, Jeff Bezos, Blue Origin’s
    founder, published an open letter to NASA Administrator Nelson, offering to waive “‘all
    payments in the current and next two government fiscal years up to $2B to get the program back
    on track right now.’” (ECF 1, ¶ 111 (quoting Letter from Jeff Bezos to Administrator Nelson).)
    In the protest before the Court, Mr. Smith raised the figure to “over $3 billion as a Blue Origin
    private contribution to add valuable competition and assist in addressing NASA’s HLS Option A
    budget and funding shortfall . . . .” (ECF 61-1, Pl.’s Ex. 1, Decl. of Robert H. Smith, ¶ 24.)
    These post-award offers to contribute funds were not before NASA at the time it made its
    award, and NASA had no obligation to ask Blue Origin to improve its proposal by absorbing
    costs or lowering the price. The solicitation warned offerors “that the Government may evaluate
    proposals and award contracts without conducting discussions or post-selection negotiations,”
    and, “[t]herefore, each Offeror shall submit only one proposal which represents its best approach
    to meeting the requirements of the solicitation.” (AR Tab 27 at 24473 (emphasis added).)
    Faced with this explicit direction, Blue Origin chose to submit a proposal that did not
    include a $2 or $3 billion corporate contribution. Blue Origin’s effort to conduct public-relations
    negotiations after the award in the context of its bid protest is insufficient to support a finding of
    prejudice when its proposed FY 2021 milestone payments were priced at more than [***] times
    NASA’s budget for the Option A contract. When considered with other factors discussed below,
    the Court finds that this funding shortfall was too substantial for Blue Origin to establish that it
    would have had a substantial chance of award but for the alleged evaluation errors. See Alfa
    Laval Separation, Inc., 
    175 F.3d at 1368
     (“[W]hile price differential may be taken into account,
    it is not solely dispositive; we must consider all the surrounding circumstances in determining
    16
    whether there was a substantial chance that a protestor would have received an award but for a
    significant error in the procurement process.”). 3
    2.      No Supporting Spacecraft
    Blue Origin’s lead claim alleges that NASA waived certain solicitation requirements for
    SpaceX’s proposal. (ECF 1, ¶¶ 119-37.) Specifically, Blue Origin alleges that NASA waived
    required reviews for SpaceX’s supporting spacecraft. (Id.) As the GAO found with respect to
    the FRRs, however, Blue Origin could not have benefited from a similar waiver because Blue
    Origin had not proposed any supporting spacecraft. (See AR Tab 108b67a at 105077-78.) As
    the Federal Circuit has held, “[w]ithout a showing of harm specific to the asserted error, there is
    no injury to redress, and no standing to sue.” Labatt Food Serv., Inc. v. United States, 
    577 F.3d 1375
    , 1381 (Fed. Cir. 2009) (finding that there was no connection between the government’s
    error and the protestor’s failure to secure the contract).
    SpaceX’s approach differed from Blue Origin’s approach. SpaceX proposed two types of
    supporting spacecraft along with a single-element Integrated Lander. (AR Tab 34d.55 at 56274-
    77.) Blue Origin did not propose any supporting spacecraft; instead, it proposed a three-element
    architecture for its Integrated Lander. (AR Tab 32a at 33339-41.) As a result of this difference
    in approach, SpaceX’s proposal would require 16 launches (of which 15 would be for supporting
    spacecraft) (AR Tab 61 at 62874), while Blue Origin’s proposal would require three launches,
    one for each element of its Integrated Lander (AR Tab 61 at 62852).
    Setting aside its hypothetical alternative proposal discussed below, Blue Origin cannot
    demonstrate that it could have benefited from a similar waiver for supporting spacecraft—Blue
    Origin proposed no supporting spacecraft. (See AR Tab 32a at 33339-41.) Even if NASA erred
    in not requiring reviews for the supporting spacecraft proposed by SpaceX, Blue Origin cannot
    meet its burden to show that it was competitively injured by such a waiver.
    3.      Noncompliance
    In order to overcome the lack of direct competitive injury attributable to the differences
    between SpaceX’s proposal and its own, Blue Origin alleges that SpaceX’s proposal was not
    compliant with the terms of the solicitation and unawardable. In contrast, Blue Origin alleges
    that its own proposal was next in line for award because it was compliant and awardable.
    According to Blue Origin, NASA should not have chosen SpaceX for the post-selection
    negotiation but instead should have fallen back on Blue Origin’s proposal, because it had
    submitted a compliant, awardable proposal and was next in line. This argument is fatally flawed
    3 Although Alfa Laval held at the merits stage that a price differential alone is not dispositive,
    the price differential in that case resulted from differences between offers. See Alfa Laval
    Separation, Inc., 
    175 F.3d at 1368
    . The support for finding no prejudice in this case is stronger
    because the price disparity exists between NASA’s available funding and Blue Origin’s proposal
    price. The difference between Blue Origin’s proposal price and SpaceX’s proposal price —
    though also disparate—does not factor into the Court’s analysis here.
    17
    because NASA determined that Blue Origin’s submitted proposal also was not in compliance
    with the solicitation.
    The solicitation provided that “[t]he Government will not make advance payments;
    proposals containing an advance payment are ineligible for contract award.” (AR Tab 27 at
    24479.) As the SSA noted, the SEP identified “two instances of proposed advance payments
    within Blue Origin’s proposal. . . . Specifically, Blue Origin proposed milestones at the outset of
    its Option A performance that the SEP determined were not commensurate with performance.”
    (AR Tab 77 at 63054.)
    The SSA “concur[red] with the SEP’s assessment that [Blue Origin’s] kickoff meeting-
    related payments are counter to the solicitation’s instructions and render Blue Origin’s proposal
    ineligible for award without the Government engaging in discussions or negotiations with Blue
    Origin, either of which would provide an opportunity for it to submit a compliant revised
    proposal.” (Id.) The SSA found that Blue Origin’s proposal was “not awardable.” (Id. at 63056
    n.1.)
    Blue Origin, in a declaration of its Senior Vice President of Advanced Development
    Programs, alleges that it could have explained the purported advance payment issue if NASA
    had opened negotiations with Blue Origin. (ECF 61-1, Pl.’s Ex. 2, Decl. of Brent Sherwood,
    ¶ 14.) Blue Origin allegedly “would have made clear in its proposal that the purported advance
    payment issue discussed in Blue Origin’s SEP report were [sic] not advance payments but rather
    were long-lead item procurement payments.” (Id.)
    NASA, however, was under no obligation to negotiate with Blue Origin. The solicitation
    had provided that “[t]he Government may evaluate proposals and award contracts without
    conducting post-selection negotiations or discussions with Offerors . . . .” (AR Tab 27 at 24433
    (bold omitted).) The SSA explained that she would have allowed Blue Origin to correct the
    advance-payment issue through negotiations or discussions, but she did not conclude that Blue
    Origin’s proposal “present[ed] a good value to the Government” sufficient to warrant either
    discussions or negotiations. (AR Tab 77 at 63056-57 n.1.)
    Accordingly, even assuming its allegations to be true, Blue Origin cannot establish that it
    would have had a substantial chance of award but for NASA’s alleged errors. Blue Origin’s
    submitted proposal was priced at more than three times NASA’s FY 2021 budget for the Option
    A contract, would not have benefited from waived reviews for supporting spacecraft, and was
    unawardable without discretionary negotiations. Considering these factors together, Blue
    Origin’s allegations cannot establish prejudice for purposes of standing.
    B.      Alternative Proposal
    As noted, the GAO found that Blue Origin could not establish prejudice for its submitted
    proposal. Blue Origin pivots and now alleges before the Court that it would have submitted an
    alternative proposal if it had known that NASA would waive solicitation requirements. Blue
    Origin alleges that the alternative proposal it would have submitted would have both received
    18
    higher ratings than SpaceX’s proposal and been within NASA’s budget. (ECF 1, ¶ 26; see also
    ECF 69 at 46-49.)
    Blue Origin alleges that it “would have proposed a fundamentally different technical
    approach.” (ECF 1, ¶ 26; see also ECF 61-1, Pl.’s Ex. 1, Decl. of Robert H. Smith, ¶¶ 12-14
    (explaining Blue Origin’s alternative approach), Pl.’s Ex. 2, Decl. of Brent Sherwood, ¶ 14
    (same).) Blue Origin asserts that it too would have proposed a single-element Integrated Lander,
    [***]. (ECF 1, ¶ 26.) This alternative design would “take full advantage of Blue Origin’s
    [***].” (Id. ¶ 13.) As did SpaceX’s proposal, to support its own single-element Integrated
    Lander, “Blue Origin would have proposed a large number of launches and Low Earth Orbit
    rendezvous events, allowing for the incorporation of elements such as a propellant depot in Low
    Earth Orbit to be refueled by multiple launches.” (Id.)
    The details of Blue Origin’s alternative approach are unclear, as is the precise nature of
    what Blue Origin would have proposed; Blue Origin has not submitted any contemporaneous
    documentary evidence to support its allegations of its alternative architecture. Mr. Smith avers
    that “Blue Origin originally proposed to use the [***] in its Base Period proposal but changed
    this approach” because of the Option A requirements. (ECF 61-1, Pl.’s Ex. 1, Decl. of Robert H.
    Smith, ¶ 13.) Blue Origin, however, had proposed the same three-element lander for its proposal
    during the base-period contract (AR Tab 9 at 266), and the [***] is already an element of the
    proposal Blue Origin submitted for Option A (AR Tab 32a at 33385). Blue Origin has not
    explained how to reconcile the record with its proposed approach.
    The three base-period contractors were required to use the standards developed during the
    base period in preparing their Option A proposals. (AR Tab 27 at 24443.) NASA intended “to
    transition between the Base period and Option A period without any break in contractor
    performance.” (Id. at 24429.) Although NASA intended to continue performance into the
    Option A contract, the government admits that the Option A solicitation “did not expressly
    prohibit an offeror from proposing an approach entirely different from the one it had spent 12
    months developing during its base period performance.” (ECF 68 at 13.)
    Despite Blue Origin’s allegation that it had been [***], it would have had to start from
    scratch with NASA. Blue Origin’s alternative proposal is purely speculative, including
    hypothetical pricing and hypothetical technical ratings.
    A protestor need not show that it would have won the contract but for the alleged errors,
    but conjecture is not enough. Bannum, 
    404 F.3d at 1358
    ; accord HVF W., LLC v. United States,
    846 F. App’x 896, 898 (Fed. Cir. 2021) (holding that a protestor’s allegations based on
    conjecture “are insufficient to show [the protestor] had a substantial chance of winning the
    award”).
    Blue Origin alleges that its price would have been lower and speculates that its technical
    ratings would have been higher. (ECF 1, ¶ 26.) The Court has no way to perform a hypothetical
    evaluation to determine whether Blue Origin’s alternative proposal would even be awardable
    much less have a substantial chance of award. Blue Origin is in the position of every
    disappointed bidder: Oh. That’s what the agency wanted and liked best? If we had known, we
    19
    would have instead submitted a proposal that resembled the successful offer, but we could have
    offered a better price and snazzier features and options. Blue Origin cannot use its speculative
    alternative proposal to establish that it would have had a substantial chance of award but for
    NASA’s alleged evaluation errors. Such an approach runs directly counter to the judicial role in
    Administrative Procedure Act (“APA”) review, as applied in resolving bid protests.
    In cases in which an agency would be required to reopen the bidding process, the Federal
    Circuit has held that “all a protestor must establish to demonstrate prejudice is that . . . it is a
    qualified bidder and could compete for the contract.” Tinton Falls Lodging Realty, LLC v.
    United States, 
    800 F.3d 1353
    , 1360 (Fed. Cir. 2015). In Tinton Falls, only small-business
    concerns were eligible to compete for the solicitation. Id. at 1359. If the protestor’s bid protest
    succeeded, then the agency would have been required to reopen the bidding process because no
    eligible bidders would be remaining. Id. The protestor itself admitted that it was not a small-
    business concern for purposes of the original solicitation but argued that it could compete if the
    bidding process was reopened on an unrestricted basis. Id. On these facts, the Federal Circuit
    upheld on clear-error review a determination by this court that the protestor had demonstrated
    prejudice. Id. at 1360.
    Blue Origin alleges that its alternative proposal is evidence that it was prejudiced , but
    Blue Origin does not base its standing argument on Tinton Falls, so the parties did not brief
    applicability of that case to the facts and circumstances of the procurement at issue. Because
    Blue Origin has not raised the argument, it is waived. Nevertheless, for the sake of
    completeness, the Court considers whether an argument premised on Tinton Falls would have
    led to a different conclusion on standing. It would not have.
    The allegations in Tinton Falls were different from Blue Origin’s. In Tinton Falls, the
    plaintiff’s protest, if successful, would have meant that there were no eligible awardees, thus
    requiring the government to go back to square one. In contrast, in this case, Blue Origin’s
    allegations, even if true, would not require the government to go back and recompete the
    requirements at issue. Rather, under the express terms of the solicitation, NASA would have
    been permitted to select SpaceX as the presumptive awardee and to engage in post-selection
    negotiations with SpaceX—to the exclusion of all other offerors—and thus cure any deficiency,
    if there were any. (AR Tab 27 at 24480.) Because NASA did exactly what the solicitation
    permitted, Blue Origin cannot demonstrate a “substantial chance” of award, even assuming all its
    factual allegations (as opposed to legal conclusions) were true. Put differently, even if Blue
    Origin’s allegations are assumed to be true, the result of accepting them would mean that NASA
    would only have to go back to engage in further negotiations with SpaceX; it would not require a
    complete redo of the entire evaluation and selection process. Cf. Bluewater Mgmt. Grp., LLC v.
    United States, 
    150 Fed. Cl. 588
    , 611 (2020) (finding that “nothing in the solicitation prohibited
    20
    the [agency] from concluding that a not-fully-compliant proposal could be made compliant and,
    therefore, eligible for award, after discussions”).4
    In sum, Blue Origin cannot establish prejudice on review of its submitted proposal or its
    hypothetical alternative proposal. Even assuming Blue Origin’s allegations of errors to be true,
    Blue Origin cannot establish that it was prejudiced by those errors, especially when taking into
    account the broad discretion afforded NASA under FAR part 35. Accordingly, the Court lacks
    standing over each of Blue Origin’s five claims, all of which are based on this court’s 
    28 U.S.C. § 1491
    (b)(1) jurisdiction.
    IV.       WAIVER
    Relying on the waiver rule established in Blue & Gold Fleet, L.P. v. United States,
    
    492 F.3d 1308
     (Fed. Cir. 2007), the government and SpaceX also argue that many of Blue
    Origin’s objections are waived.
    Under Blue & Gold Fleet, “a party who has the opportunity to object to the terms of a
    government solicitation containing a patent error and fails to do so prior to the close of the
    bidding process waives its ability to raise the same objection subsequently in a bid protest action
    in the Court of Federal Claims.” 
    Id. at 1313
    . This waiver rule furthers the statutory mandate in
    
    28 U.S.C. § 1491
    (b)(3), which provides that “‘the courts shall give due regard to the interests of
    national defense and national security and the need for expeditious resolution of the action.’” 
    Id.
    (quoting 
    28 U.S.C. § 1491
    (b)(3)) (emphasis in original).
    The Federal Circuit reasoned that the rationale underlying its doctrine applicable to
    challenges of solicitations with patent ambiguities applies when a party recognizes a patent error
    in a solicitation but does not object until after the close of the bidding process. 
    Id. at 1314
    . The
    “waiver rule . . . prevents contractors from taking advantage of the government and other
    bidders, and avoids costly after-the-fact litigation.” 
    Id.
     Without a waiver rule, a contractor could
    discover a defect in a solicitation, remain silent, and submit its first proposal. 
    Id.
     If the first
    proposal is not selected for award, “the contractor could then come forward with the defect to
    restart the bidding process, perhaps with increased knowledge of its competitors.” 
    Id.
    Expanding its application of Blue & Gold Fleet’s waiver rule, the Federal Circuit has
    held that “the reasoning of Blue & Gold applies to all situations in which the protesting party had
    4
    Bluewater Management involved a procurement governed by FAR part 15, which permits
    discussions to be held with offerors who submitted deficient proposals. 150 Fed. Cl. at 611. The
    basis for finding that NASA could engage in further negotiations with SpaceX is even stronger in
    this case because the solicitation was conducted as an “other competitive procedure” under
    FAR 6.102(d)(2) and FAR 35.016 (as deviated). These regulations do not impose requirements
    on agencies regarding exchanges with offerors and, thus, leave the agency with discretion within
    the bounds of fairness. The solicitation here expressly reserved to NASA “the right to negotiate
    any aspect of an Offeror’s milestone payment amounts, schedule, and/or acceptance criteria prior
    to award of Option A.” (AR Tab 27 at 24467.)
    21
    the opportunity to challenge a solicitation before the award and failed to do so.” COMINT Sys.
    Corp. v. United States, 
    700 F.3d 1377
    , 1382 (Fed. Cir. 2012). “[A]ssuming that there is adequate
    time in which to do so, a disappointed bidder must bring a challenge to a solicitation containing a
    patent error or ambiguity prior to the award of the contract.” 
    Id.
    Courts have held that when Blue & Gold Fleet’s waiver rule applies, a court must dismiss
    the action; it has no discretion to allow the plaintiff to maintain the action. See, e.g., SEKRI, Inc.
    v. United States, 
    152 Fed. Cl. 742
    , 752 (2021), appeal filed, No. 21-1936 (Fed. Cir. 2021);
    Contract Servs., Inc. v. United States, 
    104 Fed. Cl. 261
    , 273 (2012); Unisys Corp. v. United
    States, 
    89 Fed. Cl. 126
    , 139 (2009); see also Per Aarsleff A/S v. United States, 
    829 F.3d 1303
    ,
    1317 (Fed. Cir. 2016) (Reyna, J., concurring) (“Dismissal is mandatory, not discretionary.”).
    The Court considers the issue of waiver under the RCFC 12(b)(6) standard. SEKRI, Inc.,
    152 Fed. Cl. at 752-54; accord 10 Tanker Air Carrier, LLC v. United States, No. 21-1084, 
    2021 WL 3828652
    , at *13 n.5 (Fed. Cl. Aug. 27, 2021); WaveLink, Inc. v. United States, 
    154 Fed. Cl. 245
    , 266 n.15 (2021). But see M.R. Pittman Grp., LLC v. United States, 
    154 Fed. Cl. 241
    , 245
    (2021) (dismissing claim under Blue & Gold Fleet for lack of subject-matter jurisdiction under
    RCFC 12(h)(3)), appeal filed, No. 21-2325 (Fed. Cir. 2021).
    The government and SpaceX argue that many of Blue Origin’s objections in Counts 1
    through 3 of its complaint are waived pursuant to Blue & Gold Fleet. These counts allege that
    NASA (1) unlawfully waived material solicitation requirements; (2) engaged in improper and
    unequal discussions; and (3) failed to amend its solicitation upon a change in requirements.
    A.      Count 1: Waiver of Solicitation Requirements
    Blue Origin alleges that NASA waived for SpaceX two types of critical milestone
    reviews—the FRRs and the DCR—and several other technical and readiness reviews. (ECF 1,
    ¶¶ 119-37.) In outlining the requirements for the conduct of the FRR and the DCR, the relevant
    provisions of the solicitation refer to milestone reviews required for an “HLS element.” Blue
    Origin argues the reference to “HLS element” in the solicitation includes all spacecraft required
    by the proposal, including supporting spacecraft.
    The solicitation’s Milestone Acceptance Criteria and Payment Schedule provided that
    “[a]n FRR is required prior to each launch of an HLS element.” (AR Tab 27k at 33187
    (emphasis added).) The SOW added that “[t]he FRR should be completed by two (2) weeks
    before launch of each HLS element.” (AR Tab 27e at 32972 (emphasis added).) Although the
    SOW provided that the DCR “should be completed at first HLS launch – 9 Months (L-9)” (Id. at
    32969 (emphasis added)), the Milestone Acceptance Criteria and Payment Schedule clarified that
    the DCR was to be scheduled “9 months before first HLS element launch (L-9 months)” (AR
    Tab 27k at 33187 (emphasis added)).
    The government and SpaceX argue that the term “HLS element” refers to only the
    Integrated Lander, not supporting spacecraft. (ECF 60 at 54-58; ECF 62 at 39-46.) They argue
    that the requirements for an FRR and a DCR preceding the launch of an HLS element are
    appropriate only for crewed vehicles and not uncrewed supporting spacecraft. Although all
    22
    parties argue that “HLS element” is unambiguous, the government and SpaceX argue that, if the
    term is ambiguous, it is patently ambiguous, and Blue Origin’s challenge is waived.
    1.     Ambiguity
    To interpret a solicitation, courts employ the same principles that govern the
    interpretation of contracts. Safeguard Base Operations, LLC v. United States, 
    989 F.3d 1326
    ,
    1344 (Fed. Cir. 2021). Thus, courts “begin with the plain language of the document.” Banknote
    Corp. of Am. v. United States, 
    365 F.3d 1345
    , 1353 (Fed. Cir. 2004). A court “must consider the
    solicitation as a whole, interpreting it in a manner that harmonizes and gives reasonable meaning
    to all of its provisions.” 
    Id.
     The terms of the solicitation are “ambiguous only if [the] language
    is susceptible to more than one reasonable interpretation.” 
    Id.
    Although the SOW did not define “HLS element,” it did define “HLS”:
    HLS: All objects, vehicles, elements, integrated systems, systems,
    subsystems, or components thereof that are designed, developed,
    and utilized by the contractor, its teammates, subcontractors, and
    suppliers in performance of this contract, and which collectively
    comprise the contractor’s Integrated Lander (or elements thereof),
    all Supporting Spacecraft, all launch vehicles necessary for launch
    and delivery of the contractor’s Integrated Lander (or elements
    thereof) and its Supporting Spacecraft, and the contractor’s Active-
    Active docking adapter . . . (if required for performance of the
    contractor’s crewed demonstration mission).
    (AR Tab 27e at 32948 (bold in original) (emphasis in italics added).)
    Blue Origin interprets “HLS element” to include supporting spacecraft, arguing that
    “HLS element” means “element of an HLS.” (ECF 69 at 4.) The SOW’s definition of “HLS”
    includes “all Supporting Spacecraft.” (AR Tab 27e at 32948.) Moreover, Blue Origin points out
    that the term “element” is used in contexts that require it to be interpreted as applying to
    something other than the Integrated Landers. (ECF 69 at 5-6.) See e.g., AR Tab 27e at 32989
    (“The [Assembly, Integration and Test] Plan(s) shall include the following elements . . . .”
    (emphasis added)); id. at 32986 (“The contractor shall perform Mission and Fault Management
    . . . Design, Analysis, and Test to integrate and assess design information, interface s,
    requirements, and compatibility as an element of the integrated mission design.” (emphasis
    added)).
    Blue Origin adds that “Integrated Lander” is also a defined term in the SOW, so if NASA
    had intended “HLS element” to mean “Integrated Lander element,” it would have used the
    defined term. (ECF 69 at 5; see also AR Tab 27e at 32948 (defining “Integrated Lander”).)
    Blue Origin also points out that the SOW includes launch vehicles and supporting spacecraft in
    the scope of the FRRs. (ECF 61-1 at 14-15.) Expounding on this latter point, Blue Origin refers
    to the first FRR Acceptance Criterion, which provided the following: “The flight vehicle, launch
    vehicle, and support spacecraft (such as propellant storage, propellant transfer, and/or upper
    23
    stage vehicles that provide transportation capabilities beyond the standard for orbit insertion)
    are ready for flight.” (AR Tab 27e at 32972 (emphasis added).)
    The GAO agreed with Blue Origin’s interpretation of “HLS element.” The GAO found
    “that the Option A BAA required a FRR to be completed prior to each launch of an HLS
    element, which definition includes supporting spacecraft. (AR Tab 108b67a at 105076
    (emphasis in original).) The GAO found that a contrary reading would require the GAO “to read
    ‘supporting spacecraft’ out of the definition of ‘HLS,’ and the ‘each’ out of ‘each launch.’” (Id.)
    The GAO also found that it would have to read in “each type” to accept the position ultimately
    taken by NASA during negotiations requiring SpaceX to add two FRRs, one before its Tanker
    Starship and one before its Depot Starship. (Id.)
    Blue Origin’s interpretation of “HLS element,” adopted by the GAO, is reasonable.
    The government and SpaceX, however, demonstrate how other provisions of the
    solicitation cut against Blue Origin’s interpretation. (ECF 60 at 54-58; ECF 62 at 39-46.) They
    interpret “HLS element” to refer to only the Integrated Lander. The government notes that the
    “HLS” definition includes the word “element” and uses that word to refer to parts of the
    Integrated Lander. (ECF 60 at 54.) The government argues that the word “element” thus
    facially refers to parts of the Integrated Lander.
    The terms “Integrated Lander” and “Supporting Spacecraft” are also defined terms in the
    SOW:
    Integrated Lander: Any and all combinations of contractor
    elements (e.g. Ascent Element), including potentially a single
    element, which is integrated at any time crew are onboard.
    Supporting Spacecraft: Any contractor spacecraft that is not
    otherwise the Contractor’s HLS Integrated Lander, Launch
    Vehicle, or [Active-Active docking adapter], but that is otherwise
    required for the Contractor to execute its demonstration mission or
    any portion thereof in performance of this contract, including, but
    not limited to, rendezvous, proximity operations, docking and
    undocking . . . , propellant transfer, and orbital maneuvering and
    transfer.
    (AR Tab 27e at 32948 (bold in original) (emphasis in italics added); see also AR Tab 27 at
    24430 (providing similar definitions in the main body of the Option A solicitation).) The
    definition of “Integrated Lander” refers to its “contractor elements,” but the definition of
    “Supporting Spacecraft” is defined in opposition to the Integrated Lander and does not use the
    word “element.”
    24
    The government and SpaceX collect other provisions of the SOW and the main
    solicitation document that use the word “element” referring only to the Integrated Lander:
    •   The SOW defines “HLS Flight Operations” as “the period of performance that begins
    with the first Earth launch of any element of the HLS Integrated Lander, includes the
    entirety of the HLS Mission, and concludes with the subsequent transition of the
    uncrewed HLS out of the [Crewed Staging Vehicle] approach ellipsoid.” (AR Tab 27e at
    32999 (emphasis added).)
    •   “NASA will not take ownership of the Integrated Lander, any individual elements
    thereof, or Supporting Spacecraft.” (AR Tab 27 at 24443 (emphasis added).)
    •   “The Offeror is required to propose how it will launch and deliver its Integrated Lander
    (and all elements thereof) to the Moon using commercial launch vehicle(s), including all
    phases of launch vehicle flight and, if applicable, any Supporting Spacecraft. It is
    permissible for individual components of the Offeror’s HLS Integrated Lander to be
    launched as separate elements on multiple commercial launch vehicles, depending on the
    Offeror’s architecture.” (Id. at 24453 (emphasis added).)
    The government also argues that Blue Origin “ignores the word ‘element’ and seeks to
    make ‘HLS element’ coextensive with ‘HLS.’” (ECF 68 at 24.) To read “HLS element” to be
    any constituent part of the HLS would not make any sense, the government argues, because it
    would lead to “unworkable over-breadth”—even “an element would be an HLS element, which
    is tautological but meaningless.” (Id. at 24-25.)
    Further, the government argues that its interpretation is consistent with the SOW’s stated
    purpose of the milestone reviews. (Id. at 25-26.) The Integrated Lander is the only part of the
    HLS that carries humans onboard. The SOW provides that “[t]he HLS Program Office has
    defined major milestone reviews for the HLS Program in order to be able to assess programmatic
    and technical progress and performance at key decision points in the development and
    operational lifecycle phases, with the ultimate goal of certifying the lander for crewed operations
    to and from the lunar surface and assessing the likelihood of mission success.” (AR Tab 27e at
    32964 (emphasis added).) SpaceX adds that the first FRR Acceptance Criterion, on which Blue
    Origin also relies, makes “clear that the status of support spacecraft is something for NASA to
    consider during the FRR of something else—i.e., the launch of each HLS Lander element.”
    (ECF 62 at 44.)
    Ultimately, the government and SpaceX have provided enough context from the
    solicitation to support their interpretation of “HLS element,” even though it appears to conflict
    with the SOW’s own (seemingly unworkable) definition of “HLS.”
    The interpretation of the term “HLS element” proposed by the government and SpaceX is
    also reasonable.
    Each side’s interpretation of the solicitation term “HLS element” is internally consistent
    and reasonable. Each side’s interpretation of the term is also flawed and inconsistent with other
    25
    terms of the solicitation. The only conclusion to be drawn is that the term “HLS element” is
    ambiguous.
    2.     Patency
    For the waiver rule to apply, the ambiguity must be patent. A patent error is “‘an obvious
    omission, inconsistency or discrepancy of significance’” that “could have been ‘discovered by
    reasonable and customary care.’” Per Aarsleff A/S, 829 F.3d at 1312-13 (quoting E.L. Hamm &
    Assocs., Inc. v. England, 
    379 F.3d 1334
    , 1339 (Fed. Cir. 2004) and Analytical & Rsch. Tech.,
    Inc. v. United States, 
    39 Fed. Cl. 34
    , 46 (1997)). A document is patently ambiguous when the
    document “contains facially inconsistent provisions that would place a reasonable contractor on
    notice and prompt the contractor to rectify the inconsistency by inquiring of the appropriate
    parties.” Stratos Mobile Networks USA, LLC v. United States, 
    213 F.3d 1375
    , 1381 (Fed. Cir.
    2000).
    The term “HLS element” in the solicitation is patently ambiguous, as has been recognized
    at every stage of this procurement.
    During Q&A, one anonymized offeror requested clarification from NASA due to the
    potential ambiguity in one of the solicitation’s documents that included relevant definitions,
    including the definition of “HLS”:
    Given the ubiquitous use of the term “HLS” in applicable and
    reference documents, the current definition creates a number of
    logical inconsistencies and interpretation issues. For example, all
    [Interface Control Documents (“ICDs”)] use the phrase “HLS
    shall…,” often when seemingly intending “HLS Integrated Lander
    shall…” This creates ambiguity in terms of which vehicles (e.g.,
    launch vehicles or support vehicles) must contain which interfaces.
    (AR Tab 20 at 448 (bold omitted).)
    In response, NASA did not clarify how to read “HLS” or “HLS element” in the SOW,
    specifically. Instead, NASA merely clarified its intent not to disturb the meaning of “HLS” in
    the solicitation documents:
    Note the caveat in section 1.3.2 [of the solicitation], “When used
    within this document, the following definitions apply.” The intent
    is not to disturb the relative ubiquitous use of “HLS” in other
    solicitation and contract documents. Unless otherwise specified, the
    scope of ICDs remains the “HLS Integrated Lander” (as that term is
    defined in the main body of the solicitation). Similarly for the [Data
    Procurement Document], the revised definitions are not intended to
    change the scope of deliverables (i.e., [Data Requirements
    Descriptions] are generally applicable to the Integrated Lander
    unless “Supporting Spacecraft” or “Launch Vehicle” are explicitly
    26
    identified). Similarly for the Design and Construction standards,
    unless otherwise noted, scope is applicable to the HLS Integrated
    Lander.
    (Id.) Although NASA provided this clarification, it did not clarify or take any other action to
    remove the ambiguity surrounding the meaning of the term “HLS element” from the SOW.
    The Q&A log was provided to all offerors as part of Amendment 1 to the Option A
    solicitation. (AR Tab 26 at 24420.)
    Given the exchange during Q&A to which it had access, Blue Origin could and should
    have discovered the ambiguity in the meaning of the term “HLS element” “‘by reasonable and
    customary care.’” Per Aarsleff A/S, 829 F.3d at 1313 (quoting Analytical & Rsch. Tech., 39 Fed.
    Cl. at 46); see also Inserso Corp. v. United States, 
    961 F.3d 1343
    , 1349 (Fed. Cir. 2020); M.R.
    Pittman Grp., LLC, 154 Fed. Cl. at 244; Quanterion Sols., Inc. v. United States, 
    152 Fed. Cl. 434
    , 445 (2021) (“An ambiguity in an [Request for Proposals (“RFP”)] is generally patent if
    offerors seek clarification of the ambiguous provision prior to submitting their proposals. ”). In
    Per Aarsleff A/S, the Federal Circuit held that “the ambiguity in the solicitation was patent, as
    reflected in the questions received by the Air Force and the [solicitation’s] two plausible
    interpretations . . . .” 829 F.3d at 1312. Unlike NASA in this case, the Air Force in Per Aarsleff
    A/S removed the ambiguity through clarification. See id. at 1312-13. The ambiguity in this case
    remained between the SOW’s definitions and requirements, even after clarification. See Aero
    Spray, Inc. v. United States, No. 21-1079C, 
    2021 WL 5023371
    , at *24-25 (Fed. Cl. Oct. 21,
    2021) (finding an ambiguity to be patent in a situation in which an ambiguity was identified
    during Q&A but not clarified and finding a challenge in that case to be waived).
    NASA itself noticed the inconsistency in the SOW’s requirements caused by the
    ambiguous definition of “HLS element” during its evaluation of the proposals. The SEP
    recognized that the relevant terms concerning the FRRs were unclear and offered two possible
    interpretations. (AR Tab 59c at 62813.) Under the first possible interpretation, “offerors were
    required to propose an FRR milestone (and associated review) to be conducted and achieved for
    each proposed supporting spacecraft prior to launch and flight operations.” (Id.) Under the other
    possible interpretation, “offerors were required to propose a single FRR covering the full scope
    of its demonstration mission prior to the launch of any lander element or supporting spacecraft.”
    (Id.) Thereafter, in his letter to SpaceX initiating negotiations, the contracting officer also
    acknowledged the “arguably ambiguous nature of this topic.” (AR Tab 63 at 62890.)
    Blue Origin knew or should have known that the SOW’s term “HLS element” had more
    than one reasonable meaning and had a duty to raise the issue earlier. It did not do so. “HLS
    element” is patently ambiguous, and Blue Origin’s challenge is waived.
    Blue Origin’s challenge regarding the FRRs is waived for an additional reason. The
    solicitation reserved to NASA “the right to negotiate any aspect of an Offeror’s milestone
    payment amounts, schedule, and/or acceptance criteria prior to award of Option A.” (AR Tab 27
    at 24467.) NASA entered negotiations with SpaceX. As noted, NASA recognized the ambiguity
    in the solicitation over the FRR requirement and the meaning of “HLS element.” (AR Tab 63.)
    27
    NASA requested that SpaceX agree to additional FRRs “to meet NASA’s intent of its FRR
    requirement for supporting spacecraft.” (Id. at 62890.) If that negotiation is improper, then the
    terms of the solicitation giving NASA the authority to negotiate acceptance criteria must also be
    improper. Any defect in the solicitation’s provision reserving for NASA this authority to
    negotiate certain changes would be patent because that reservation is contained in clear and
    unambiguous language in the solicitation. Blue Origin did not object to this provision before the
    close of the bidding process, and, accordingly, its objection now is waived.
    Blue Origin’s allegations regarding the FRRs and the DCR in Count 1 are waived.
    B.      Count 2: Unequal Discussions
    Blue Origin alleges that NASA violated procurement laws and regulations by holding
    improper and unequal discussions because NASA “held discussions with only SpaceX and
    permitted SpaceX to revise its unawardable and noncompliant proposal.” (ECF 1, ¶ 144.)
    In the solicitation, NASA reserved “the right to conduct post-selection negotiations or
    discussions if the Contracting Officer later determines them to be necessary.” (AR Tab 27 at
    24433.) The SSA had the authority to “make initial, non-binding selections of an Offeror or
    Offerors for the purpose of having the Contracting Officer engage in post-selection negotiations
    with one or more Offerors as defined in [the Option A] solicitation.” (Id. at 24480.) As noted
    above, the solicitation further reserved to NASA “the right to negotiate any aspect of an
    Offeror’s milestone payment amounts, schedule, and/or acceptance criteria prior to award of
    Option A.” (Id. at 24467.)
    The solicitation defines “post-selection negotiations” and “discussions.” “Post-selection
    negotiations” are defined in the solicitation as “exchanges with Offerors who have been selected
    for potential contract award that result in the Contracting Officer inviting th e Offeror to revise
    only those specific portions of its proposal that have been identified by the Contracting Officer
    as open to revision.” (Id. at 24434.) “Discussions” are defined as “exchanges with Offerors that
    occur after receipt of proposals but before selection that result in the Contracting Officer inviting
    the Offeror to revise only those specific portions of its proposal that have been identified by the
    Contracting Officer as open to revision.” (Id.) A “‘[p]roposal revision’ is any change made by
    the Offeror to its proposal that occurs as a result of discussion or post-selection
    negotiations . . . .” (Id.)
    NASA followed the terms of the solicitation when it conducted post-selection
    negotiations with only SpaceX and allowed SpaceX to revise its proposal. The SSA made an
    initial, non-binding selection of SpaceX for award, as was expressly permitted under the
    solicitation. (AR Tab 64.) The contracting officer then negotiated with SpaceX regarding the
    prices of CLINs, the payment phasing, and the FRR requirement. (AR Tab 63.)
    If NASA’s post-selection negotiation with SpaceX was contrary to law, then the terms of
    the solicitation authorizing NASA’s conduct must also be contrary to law. If those terms
    constitute a defect in the solicitation, that defect would be patent because the clear and
    unambiguous terms of the solicitation authorize the precise actions that NASA undertook. Blue
    28
    Origin did not object to those terms before the close of the bidding process. Accordingly, Blue
    Origin’s challenge under Count 2 of its complaint, to the extent that the claim can be considered
    a challenge to the solicitation’s terms, is waived.
    C.      Count 3: Failure to Amend the Solicitation
    Blue Origin also argues that NASA unlawfully refused to amend its solicitation to give
    all offerors the opportunity to revise their proposals once Congress set the funding limits for the
    HLS program. (ECF 1, ¶¶ 152-62.) Blue Origin points to the difference between NASA’s
    funding request of $3.4 billion FY 2021 for the HLS program and the appropriation of $850
    million. Blue Origin alleges that this difference “create[d] a material departure from the
    assumptions set forth in the solicitation.” (Id. ¶ 154.) Because NASA’s funding allocation
    “directly correlate[d] to the size and scope of its Solicitation,” Blue Origin argues that NASA
    “was required to either notify all offerors of the change in circumstance or to amend the
    Solicitation, once it became aware of the changed circumstances.” (Id. ¶ 155.)
    Blue Origin maintains that both NASA’s decision not to notify all offerors of its changed
    circumstances related to the available funding and NASA’s decision not to amend the solicitation
    to account for the new level of funding were “arbitrary and violated Federal procurement
    regulations.” (Id. ¶ 156.) Blue Origin alleges that, if it had known of NASA’s funding
    limitations, it would have reduced its proposed price and revised its technical and management
    proposal. (Id. ¶¶ 157, 161.) Blue Origin contends that these changed circumstances led NASA
    to change (1) its stated intention to award two HLS Option A contracts and (2) its requirements
    for FRRs and other mandatory reviews. (Id. ¶¶ 155-60, see also ECF 61-1 at 60-64.)
    1.      Change in Intended Number of Awards
    a.     Defect
    The HLS Option A solicitation did not specify the amount NASA anticipated being
    available to fund Option A awards. Instead, the solicitation expressly provided that “[f]unds are
    not currently available for this solicitation, but are expected to become available on or before
    contract award.” (AR Tab 27 at 24481.) The solicitation informed all offerors that NASA’s
    ability to make awards was “contingent upon the availability of appropriated funds from which
    payments can be made and the receipt of proposals that NASA determines are acceptable.” (Id.)
    Although NASA preferred to award two contracts, “NASA reserve[d] the right to select for
    award multiple, one, or none of the proposals received . . . .” (Id.)
    If, as Blue Origin argues, NASA violated federal procurement regulations when it made a
    single award based on its available funding without amending the solicitation, then the
    solicitation’s terms providing NASA the flexibility to do so must also have been improper
    because NASA did precisely what it told offerors it might do.
    b.     Patency
    The solicitation’s terms were explicit in reserving NASA’s right to make a single award
    or even no award. (Id.) If these terms are illegal, the defect would be patent because the terms
    29
    are clear and unambiguous. Moreover, Blue Origin knew or should have known that NASA’s
    available FY 2021 funding would not support an award to Blue Origin.
    Congress passed the Consolidated Appropriations Act for Fiscal Year 2021 on December
    21, 2020, several weeks after Blue Origin submitted its final Option A proposal to NASA, but
    months before NASA announced the award of the Option A contract on April 16, 2021. Pub. L.
    116-260, 
    134 Stat. 1182
     (2020). (See also AR Tab 77 (dating Source Selection Statement April
    16, 2021).) The President signed the bill into law on December 27, 2020. (See AR Tab 108b26a
    at 103671.) The Consolidated Appropriations Act appropriated $850 million in FY 2021 funding
    for the entire HLS program, which includes the Option A contract, money committed for
    FY 2021 to base-period milestone payments, HLS programmatic operations budget, and other
    related activities. (Id. at 103672-73.)
    “Offerors in a government solicitation are ‘charged with knowledge of law and fact
    appropriate to the subject matter.’” Inserso Corp., 961 F.3d at 1350 (quoting Per Aarsleff A/S,
    829 F.3d at 1314). In Inserso, the Federal Circuit held that a protestor had waived its right to
    object to an unequal disclosure regarding prices. Id. The case involved two competitions, and
    “the express terms of the solicitation contemplated overlap of bidders in the two competitions.”
    Id. The protestor, “if it had taken reasonable care,” would have known that unequal disclosure
    was likely to occur. Id.
    Here, if Blue Origin had taken “reasonable care,” it would have known that based on the
    level of funding appropriated to the entire HLS program, NASA could not support a single award
    to Blue Origin at the price it proposed, let alone multiple awards to Blue Origin and one of its
    competitors. Appropriation laws are matters of public record and are accessible on Congress’s
    website, congress.gov. See, e.g., Consolidated Appropriations Act of 2021, H.R.133, 116th
    Cong. (2020), https://www.congress.gov/bill/116th-congress/house-bill/133/text/enr. Blue
    Origin’s proposed FY 2021 milestone payments of about [***] exceeded the FY 2021 funding
    appropriated for the entire HLS program. (See AR Tab 108b67a at 105010 (citing AR
    Tab 32d.87).)
    Blue Origin argues that NASA “itself decided to divert HLS funds from the Option A”
    effort after receipt of proposals, and that no offeror can be expected to keep apprised of how
    agencies decide to allocate their appropriations. (ECF 69 at 30.) This argument is sensible in
    routine procurements but ignores the realities of the procurement at issue.
    First, the diversion of funds Blue Origin identifies in its response encompassed the entire
    first decade of the HLS program. (Id. at 31 (quoting AR Tab 55 at 6206 (“This goal effectively
    forces ~$4B of milestone payments for ‘services’ into the HLS budget out to 2030 . . . [W]ithout
    the introduced ‘services’ line, the identified budget available for milestone payments between
    FY21-FY30 is ~$8.7B – which is over ~$1.5B more than the combined ~$7.1B of the notional”
    Contractor B and Contractor C proposals.)).) This argument glosses over the fact that Blue
    Origin’s proposal was unworkable in the first year of the HLS Option A program, FY 2021,
    because it proposed 2021 milestone payments that exceeded the entire HLS program’s FY 2021
    funding.
    30
    Second, Blue Origin’s argument discounts the high profile of the HLS program and Blue
    Origin’s own role in advocating for its funding. Blue Origin was one of only three offerors in
    line for award of a multi-billion-dollar contract to land humans on the lunar surface. According
    to lobbying disclosure reports, of which the Court takes judicial notice, during the period
    Congress was debating the appropriations bill that funded the HLS program, the fourth quarter of
    2020 (“Q4 2020”), Blue Origin spent close to a million dollars ($895,000) lobbying both houses
    of Congress. Most of these funds ($800,000) were spent on lobbying contacts that included
    efforts to influence the outcome of the appropriations bill. Blue Origin itself lobbied Congress
    specifically on “issues related to space transportation” in the Consolidated Appropriations Act of
    2021. See Blue Origin, LLC, Lobbying Report Q4 2020. Blue Origin also hired several
    lobbying firms to advocate on its behalf with respect to NASA’s appropriations. See Maynard,
    Cooper & Gale, P.C., Lobbying Report Q4 2020; K&L Gates LLP, Lobbying Report Q4 2020;
    Barnes & Thornburg, LLP, Lobbying Report Q4 2020; Clark Hill, PLC, Lobbying Report Q4
    2020; ATS Communications, Inc., Lobbying Report Q4 2020; Red Maple Consulting, LLC,
    Lobbying Report Q4 2020.5 Although the administrative record is silent on the question, it is
    inconceivable that Blue Origin would lobby Congress itself and pay others to lobby on its behalf
    and not be kept informed of the outcome of these efforts. Even though it may not generally be
    appropriate to impute knowledge of a procuring agency’s funding levels to offerors, in this case
    Blue Origin must have had knowledge of the amount Congress ultimately appropria ted to NASA
    for the HLS program.
    Beyond Blue Origin’s own lobbying activities, the enactment of the Consolidated
    Appropriations Act itself was newsworthy, and articles in the relevant trade-industry media
    covered the level of appropriations for the HLS program. See, e.g., Marcia Smith, Final FY2021
    NASA Funding Provides Only 25 Percent of HLS Request, SpacePolicyOnline.com (Dec. 21,
    2020, 3:24 PM), https://spacepolicyonline.com/news/final-fy2021-nasa-funding-provides-only-
    25-percent-of-hls-request/; Chelsea Gohd, NASA Hits Pause on its Artemis Moon Lander
    5  The lobbying reports are available publicly online:
    https://lda.senate.gov/filings/public/filing/d7d64b10-efcc-457b-a2e8-8d0fc4ca177a/print/ (Blue
    Origin); https://lda.senate.gov/filings/public/filing/7f51324b-8b82-4322-b21f-
    dcd66d262694/print/ (Maynard, Cooper & Gale, P.C.);
    https://lda.senate.gov/filings/public/filing/86997916-1fac-41f6-8c03-3fdf625bc8f4/print/ (K&L
    Gates LLP); https://lda.senate.gov/filings/public/filing/0995184f-2e15-430a-99d5-
    85c235c834a1/print/ (Barnes & Thornburg, LLP);
    https://lda.senate.gov/filings/public/filing/e292f8c6-2037-4ac7-a962-ccbbb1ea2e3b/print/ (Clark
    Hill, PLC); https://lda.senate.gov/filings/public/filing/24adb113-7938-40a1-9434-
    85ba3385e6c6/print/ (ATS Communications, Inc.);
    https://lda.senate.gov/filings/public/filing/ab54faf9-bc78-4070-9f19-9501e9544631/print/ (Red
    Maple Consulting, LLC).
    31
    Competition, Space.com (Feb. 3, 2021), https://www.space.com/nasa-artemis-moon-lander-
    competition-delay.
    In this context, Blue Origin’s argument that it should not be subject to a duty to have
    been aware of the amount appropriated for the HLS program or to have made contemporaneous
    inquiries of NASA on the impact of the funding level rings hollow. Appropriations acts are
    laws; the appropriations act providing funding for the HLS program was directly relev ant to the
    subject matter of the procurement. Under Federal Circuit precedent, Blue Origin was “‘charged
    with knowledge’” of this appropriations law. Inserso Corp., 961 F.3d at 1350 (quoting Per
    Aarsleff A/S, 829 F.3d at 1314). Whatever merit Blue Origin’s argument would have in the run-
    of-the-mill procurement, it is insufficient in this procurement.
    Under these circumstances, Blue Origin had the opportunity to raise any concerns about
    the impact of the appropriation figure for the HLS program on the proposal-selection process in
    the more-than-four months NASA spent evaluating the proposals and deliberating the award of
    the Option A contract after the enactment of the Consolidated Appropriations Act for FY 2021.
    If Blue Origin believed the HLS funding itself to be an agency requirement that changed after the
    receipt of proposals, Blue Origin had the opportunity to protest when it became clear that NASA
    did not intend to make an amendment of a patent, unambiguous solicitation term. Blue Origin
    failed to lodge such a protest.
    By failing to object to NASA’s election not to amend the Option A solicitation to reflect
    funding constraints, Blue Origin has waived its right to make that argument now. See Blue &
    Gold Fleet, 
    492 F.3d at 1313
    ; VS2, LLC v. United States, No. 21-1028C, 
    2021 WL 4167380
    , at
    *10 (Fed. Cl. Sept. 1, 2021) (discussing subsequent cases applying Blue & Gold Fleet that
    “shift[ed], until the contract award date, the cut-off for a challenge to a solicitation that would
    not have been possible prior to the proposal due date”).
    2.      Change in Review Requirements
    Blue Origin also argues that NASA was required to amend its solicitation to reflect a
    reduction in its need for FRRs and other critical milestone reviews. This relaxation in
    requirements, Blue Origin contends, resulted in “less costly performance by SpaceX relating to
    the FRRs, saving SpaceX (and NASA) hundreds of millions of dollars.” (ECF 61 -1 at 63.) Had
    NASA “properly revised” its solicitation to reflect this allegedly relaxed review requirement,
    Blue Origin asserts that it “would have proposed a fundamentally different technical approach”
    at a significantly lower price. (Id. at 68-69.)
    As previously noted, NASA had reserved “the right to negotiate any aspect of an
    Offeror’s milestone payment amounts, schedule, and/or acceptance criteria prior to award of
    Option A.” (AR Tab 27 at 24467.) Accordingly, Blue Origin’s argument that NASA was
    required to amend its solicitation to update the number of required FRRs and other reviews is
    untimely for the same reasons its objections related to NASA’s funding requirements are
    untimely under Blue & Gold Fleet. If negotiating reviews is improper, then the terms of the
    solicitation allowing such negotiations must also be improper. That defect would be patent
    because the solicitation expressly reserved to NASA the right to negotiate FRRs and other
    32
    critical reviews to achieve the best value for the government. Blue Origin had notice that the
    specific timing and acceptance criteria were subject to NASA’s discretion and further
    negotiation.
    Blue Origin argues that the solicitation’s “unambiguous and specific timing required for
    the critical milestone requirements” forced Blue Origin to change its proposed HLS architecture.
    (ECF 61-1 at 69.) The terms of the solicitation, however, establish that NASA had discretion to
    “negotiate any aspect” of an offeror’s acceptance criteria. (AR Tab 27 at 24467 (emphasis
    added).) If, as Blue Origin contends, the timing of these critical milestone reviews was holding
    Blue Origin back from proposing a different, better architecture (ECF 61-1 at 68-69), it was
    incumbent upon Blue Origin to raise its concern over the express, unambiguous terms of the
    solicitation with NASA prior to submitting its proposal. Blue Origin did not do so.
    In Count 3, Blue Origin challenges NASA’s decision not to amend its solicitation, which
    already anticipated the need for flexibility. Consideration of both the allegedly changed
    requirements—the intended number of awards and the critical milestone review requirements—
    was left to NASA’s discretion by the solicitation’s express terms. Being authorized by those
    terms, that discretion cannot now be challenged as improper. Blue Origin’s challenge under
    Count 3 of its complaint, to the extent that the claim can be considered a challenge to the
    solicitation’s terms, is waived.
    In sum, Blue Origin’s objections regarding the FRRs and the DCR in Count 1 are waived;
    Counts 2 and 3 are waived in their entirety.
    V.     MERITS
    Even if it had standing and portions of its complaint were not waived, Blue Origin could
    not succeed on the merits.
    Bid protests are evaluated under the APA’s standard of review. See 
    28 U.S.C. § 1491
    (b)(4) (adopting the standard of 
    5 U.S.C. § 706
    ). Under that standard, an agency’s
    procurement action may only be set aside if it is “arbitrary, capricious, an abuse of discretion, or
    otherwise not in accordance with the law.” 
    5 U.S.C. § 706
    (2)(A). A court may grant relief only
    upon the finding that either “the procurement official’s decision lacked a rational basis” or “the
    procurement procedure involved a violation of regulation or procedure.” Impresa Construzioni
    Geom. Domenico Garufi v. United States, 
    238 F.3d 1324
    , 1338 (Fed. Cir. 2001).
    On the merits, Blue Origin alleges that NASA (1) unlawfully waived material solicitation
    requirements for SpaceX; (2) engaged in improper and unequal discussions; (3) failed to amend
    its solicitation upon receiving its appropriation; (4) failed to evaluate SpaceX’s proposal in
    accordance with the solicitation; and (5) breached an implied-in-fact contract of good faith and
    fair dealing. The government and SpaceX argue that NASA acted properly.
    33
    A.      Counts 1 and 4: Waiver of Solicitation Requirements and Improper
    Evaluation
    The Court’s review of a procuring agency’s decision is “highly deferential.” Advanced
    Data Concepts v. United States, 
    216 F.3d 1054
    , 1058 (Fed. Cir. 2000). Under the APA’s
    rational basis test, a court determines “whether the contracting agency provided a coherent and
    reasonable explanation of its exercise of discretion, and the disappointed bidder bears a ‘heavy
    burden’ of showing that the award decision had no rational basis.” Banknote Corp. of Am., 
    365 F.3d at 1351
     (quoting Domenico Garufi, 
    238 F.3d at 1332-33
    ) (internal quotation marks
    omitted). The court does not second-guess “discretionary determinations of procurement
    officials” involved in challenges that “deal with the minutiae of the procurement process in such
    matters as technical ratings.” E.W. Bliss Co. v. United States, 
    77 F.3d 445
    , 449 (Fed. Cir. 1996).
    The FAR provision governing BAAs provides that “[p]roposals received as a result of the
    BAA shall be evaluated in accordance with evaluation criteria specified therein through a peer or
    scientific review process.” FAR 35.016. As explained in the background section above, NASA
    conducted a multi-layered evaluation. The SEP was responsible for evaluating proposals and
    presenting the results to the SSA, who was “responsible for making selections and final contract
    award decisions based on applying the evaluation, selection, and award methodology as
    described in [the Option A] solicitation.” (AR Tab 27 at 24480.) The SSA would “consider
    each proposal on its own individual merits, and [would] select for award one or more proposals
    that individually each present value to the Government and that optimize NASA’s ability to meet
    its objectives as set forth in [the Option A] solicitation.” (Id.)
    In evaluating the technical and management approaches of the proposals, NASA would
    “consider how an Offeror’s proposed approach affects risk, such as technical risk, risk to meeting
    the Offeror’s proposed schedule, the need for increased Government oversight, or the risk o f
    likelihood of unsuccessful contract performance.” (Id. at 24476.) NASA then would rate
    features of each proposal using five categories of strengths and weaknesses: Significant Strength,
    Strength, Weakness, Significant Weakness, and Deficiency. (Id.)
    In addition to the traditional discretion that courts give to agencies, the BAA in this case
    reserved certain rights to NASA, providing NASA flexibility in the highly technical field of
    rocket science. The solicitation reserved to NASA “the right to negotiate any aspect of an
    Offeror’s milestone payment amounts, schedule, and/or acceptance criteria prior to award of
    Option A.” (Id. at 24467.)
    Blue Origin argues that NASA’s evaluation was “arbitrary, capricious, and
    unlawful . . . .” (ECF 1, ¶ 121 (Count 1) (citing 
    5 U.S.C. § 706
    (2)(A), ¶ 164 (Count 4)
    (providing same basis for challenge).) In Counts 1 and 4, Blue Origin raises three objections to
    NASA’s evaluation, arguing that NASA (1) either waived material review requirements or failed
    to rate the proposals appropriately on their proposed review requirements; (2) disparately and
    unequally evaluated SpaceX’s and Blue Origin’s communications link non-closures; and
    (3) improperly double-counted certain positive attributes of SpaceX’s proposal.
    34
    1.      Review Requirements
    Blue Origin alleges that NASA unlawfully waived for only SpaceX several required
    reviews, including FRRs, the DCR, and several other technical and readiness reviews. (Id.
    ¶¶ 119-37.) Blue Origin further alleges that NASA failed to evaluate properly the risk related to
    SpaceX’s approach to these reviews. (Id. ¶¶ 166-67.)
    a.      FRR Requirements
    As the Court found above, the term “HLS element” in the FRR and DCR requirements is
    patently ambiguous, and, therefore, Blue Origin cannot now challenge NASA’s interpretation.
    See NVY Technologies, Inc. v. United States, 
    370 F.3d 1153
    , 1162 (Fed. Cir. 2004) (“If an
    ambiguity is obvious and a bidder fails to inquire with regard to the provision, his interpretation
    will fail.”); Grumman Data Sys. Corp. v. Dalton, 
    88 F.3d 990
    , 998 (Fed. Cir. 1996) (“If a
    solicitation contains contract language that is patently ambiguous, a protestor cannot argue . . .
    that its interpretation is proper unless the protestor sought clarification of the language from the
    agency before the end of the procurement process.”).
    Blue Origin argues that SpaceX’s failure to include additional FRRs should have
    rendered SpaceX’s proposal unawardable as a Deficiency, rather than as a Weakness, the rating
    the SEP assigned to this aspect of SpaceX’s proposal. (ECF 61-1 at 55-56; see also AR Tab 59c
    at 62812-14.) The solicitation defined “Weakness” as “[a] flaw in the proposal that increases the
    risk of unsuccessful contract performance.” (AR Tab 27 at 24476.) “Deficiency” was defined as
    “[a] material failure of a proposal to meet a Government requirement or a combination of
    significant weaknesses in a proposal that increases the risk of unsuccessful contract performance
    to an unacceptable level.” (Id.)
    The SEP did not find SpaceX’s approach to be a material failure to meet a requirement,
    but the SEP did explain that SpaceX’s approach increased the risk of unsuccessful contract
    performance. (See AR Tab 59c at 62812-14.) The SEP explained that SpaceX “did not propose
    any . . . FRR milestone review events prior to the launch of their supporting spacecraft (namely,
    their depot and tanker Starships) which commence their demonstration mission.” (Id. at 62813.)
    Put another way, SpaceX “neither proposed any FRR events dedicated to one or all of its
    supporting spacecraft, nor a single FRR to cover the full scope of its demonstration mission prior
    to the launch of its first supporting spacecraft.” (Id.) The SEP found that, “in either case,
    [SpaceX’s] proposal is inconsistent with this required milestone (or milestones) as set forth in the
    solicitation.” (Id.)
    Consistent with a Weakness rating, the SEP concluded that SpaceX’s approach to
    milestone review events increased risk:
    This inconsistency between [SpaceX’s] proposal and the milestone
    review events contemplated by the solicitation has the effect of
    lessening NASA’s involvement and participation in assessing flight
    readiness for [SpaceX’s] supporting spacecraft prior to launch of
    such spacecraft. Therefore, this aspect of [SpaceX’s] proposal
    35
    increases risk of unsuccessful performance and constitutes a
    weakness.
    (Id. at 62814.)
    The SEP’s conclusion is reasonable, and the Court will not second-guess the SEP’s
    expertise to assess this risk, which depends on technical judgment.6 See E.W. Bliss Co., 
    77 F.3d at 449
    . The distinction between a Deficiency and a Weakness lies in how serious a risk a defect
    presents. For a defect to rise to the level of a Deficiency, it must “increase[ ] the risk of
    unsuccessful contract performance to an unacceptable level.” (AR Tab 27 at 24476.)
    Distinguishing a Deficiency from a Weakness entails the exercise of judgment in a highly
    technical area. The Court is in no position to assess the risk in SpaceX’s proposal and may not
    use deferential APA review to disregard the judgment of the SEP and the SSA to substitute its
    own judgment on such a highly technical and nuanced question.
    If failing to meet a solicitation requirement required a Deficiency rating, then Blue
    Origin’s own proposal would have several Deficiency ratings. Although the SEP found that
    Blue Origin failed to meet several requirements, the SEP never assigned to Blue Origin a
    Deficiency. For example, the SEP found that Blue Origin’s proposal failed “to meet an
    important mission-related requirement” because its manual control system “is not compliant with
    HLS-R-0004, which requires that the offeror’s approach to manual control must have single fault
    tolerance.” (AR Tab 59a at 62647.) The SEP also found that Blue Origin’s communications
    links “fall short of NASA’s requirements includ[ing] critical ones as [***].” (Id. at 62654.)
    Neither SpaceX nor Blue Origin received any Deficiency rating. (See generally AR Tab 59c;
    AR Tab 59a.) Blue Origin itself, therefore, benefited from the NASA’s discretion to determine
    which requirements were a “material failure,” as required by the definition of “Deficiency.” (See
    AR Tab 27 at 24476.) See also IAP World Servs., Inc. v. United States, 
    152 Fed. Cl. 384
    , 401
    (2021) (“[I]f correcting the error would decrease [the protestor’s] chance of award, it cannot
    establish prejudice.”).
    b.     DCR and Other Reviews
    Aside from the FRR requirements, Blue Origin argues that SpaceX did not meet the
    schedule requirements for the DCR, the Mission Specific Preliminary Design Review, the
    Mission Specific Critical Design Review, and the System Acceptance Review. (ECF 1, ¶¶ 130-
    31.) Blue Origin alleges that “NASA did not assign any weaknesses for SpaceX’s failure to
    meet these requirements,” so NASA “essentially waived” them. (Id.) In its motion for judgment
    on the administrative record, Blue Origin adds to the list of allegedly waived reviews the Launch
    6  Even if Blue Origin’s claim were not waived regarding FRRs and even if the term “HLS
    element” included supporting spacecraft, NASA had the discretion to negotiate the acceptance
    criteria. (See AR Tab 27 at 24467.) NASA did negotiate the FRR requirement with SpaceX, and
    SpaceX agreed to perform additional NASA-led FRRs. (AR Tab 63.)
    36
    Vehicle Systems Readiness Review, Pre-Mate Readiness Review, and the Launch Readiness
    Review. (ECF 61-1 at 44.)
    The HLS Option A procurement is highly technical and contains a voluminous record.
    The Court’s review considers “whether the contracting agency provided a coherent a nd
    reasonable explanation of its exercise of discretion . . . .” Banknote Corp. of Am., 
    365 F.3d at 1351
     (quoting Domenico Garufi, 
    238 F.3d at 1332-33
    ) (internal quotation marks omitted). Blue
    Origin cannot undercut NASA’s thorough analysis by grasping for anything NASA specifically
    did not reference from its 60-page solicitation with its 78-page SOW. (AR Tab 27; AR
    Tab 27e.) The SEP wrote a 59-page report for SpaceX and a 75-page report for Blue Origin.
    (AR Tab 59c; AR Tab 59a.) The SSA wrote another 24 pages to explain her source selection.
    (AR Tab 77.) The Court finds NASA’s explanation to be well-documented, detailed, and
    thorough.
    In such matters as technical evaluations, courts defer to an agency’s expertise because the
    agency is better situated to make those determinations. Kinemetrics, Inc. v. United States, No.
    21-1626, 
    2021 WL 4237169
    , at *7 (Fed. Cl. Sept. 10, 2021); see also E.W. Bliss Co., 
    77 F.3d at 449
    ; Squire Sols., Inc. v. United States, No. 21-1494C, 
    2021 WL 4805540
    , at *14-16 (Fed. Cl.
    Sept. 30, 2021) (declining to second-guess an agency’s technical evaluation involving
    discretionary determinations in a technical BAA). The record does not indicate that NASA
    ignored the review requirements; as the analysis below makes clear, the SSA acknowledged
    SpaceX’s schedule risk but found that other attributes reduced that risk. (See AR Tab 77 at
    63049.) The Court is not competent to determine whether SpaceX’s approach increased any risk
    and, if so, to substitute its judgment for that of NASA in evaluating whether such risk increased
    the potential for unsuccessful performance to an unacceptable level. Although NASA did not
    specifically address by name each of the reviews that Blue Origin has put at issue, the absence of
    references to the other reviews is an indication that NASA was not concerned with the risks
    presented by those reviews. This conclusion is the logical inference to draw from the fact that
    the SEP did discuss concerns regarding the FRR requirement at length. (See AR Tab 59c at
    62812-14.)
    On the record before the Court and reasonable inferences therefrom, Blue Origin has not
    met its burden to show that NASA’s award decision was arbitrary and capricious. The Court
    finds NASA’s explanation to be “a coherent and reasonable explanation” of its award decision.
    See Banknote Corp. of Am., 
    365 F.3d at 1351
    .
    Blue Origin further argues that it was irrational for NASA to rate SpaceX’s management
    approach Outstanding, given “SpaceX’s blatant failure to meet numerous milestone review and
    mission specific launch vehicle review requirements as mandated by the Solicitation.” (ECF 61-
    1 at 52.) The solicitation defined “Outstanding” as “[a] thorough and compelling proposal of
    exceptional merit that fully responds to the objectives of the BAA,” and the “[p]roposal contains
    strengths that far outweigh any weaknesses.” (AR Tab 27 at 24477.) The rating does not require
    perfection; the rating, instead, requires a weighing of strengths and weaknesses.
    The SSA provided four paragraphs to support SpaceX’s Outstanding rating for its
    management approach. (AR Tab 77 at 63048-49.) Her first paragraph highlights the attributes
    37
    of SpaceX’s management approach that she found most compelling, and she notes that these
    attributes will help reduce SpaceX’s schedule risk:
    The positive attribute of SpaceX’s management proposal that I
    found to be the most compelling is its exceedingly thorough and
    thoughtful management approach and organizational structure
    within Area of Focus 1, Organization and Management. I concur
    with the SEP that this represents a significant strength in SpaceX’s
    management approach. In particular, I acknowledge SpaceX’s
    approach to leveraging its deep bench of personnel and expertise, its
    prior program management experience, and lessons learned from
    those experiences that SpaceX will bring to bear in its management
    of the HLS effort. Similarly, I find attractive SpaceX’s proposal to
    replicate and utilize management processes, toolsets, and software
    that have been effectively employed on other, similar programs and
    will ensure effective traceability and tracking of progress on the
    HLS contract. I concur with the SEP that together, these attributes
    will help reduce SpaceX’s schedule risk and allow for more effective
    management of its contractual progress.
    (Id. (emphasis added).) The SSA continues in this thorough manner for another three
    paragraphs, concluding that, “[l]ike the SEP, I find that the qualitative attributes of SpaceX’s
    aggregated strengths, including its rating of High for its Base Period Performance, far outweigh
    the qualitative attributes of its evaluated weaknesses, which were relatively minor.” (Id. at
    63049.)
    The SSA’s weighing of strengths and weaknesses is consistent with an Outstanding
    rating, and such determinations are left to the considered and reasoned judgment of the agency,
    not the Court.
    2.     Disparate Treatment
    An agency acts in an arbitrary and capricious manner when it treats like cases
    dissimilarly. See Mission1st Grp., Inc. v. United States, 
    144 Fed. Cl. 200
    , 215 (2019) (“It is well
    established that treating like cases in an unequal fashion is a hallmark of arbitrary decision-
    making.”). The Federal Circuit has established two standards for finding disparate treatment.
    Off. Design Grp. v. United States, 
    951 F.3d 1366
    , 1372-73 (Fed. Cir. 2020). Under the first
    standard, “a protestor must show that the agency unreasonably downgraded its proposal for
    deficiencies that were ‘substantively indistinguishable’ or nearly identical from those contained
    in other proposals.” Id. at 1372. Under the second standard, “[a] protestor may also prevail by
    showing that the agency inconsistently applied objective solicitation requirements between it and
    the other offerors, such as proposal page limits, formatting requirements, or submission
    deadlines.” Id.
    In this case, Blue Origin is challenging disparate technical ratings, so the first standard
    applies. Blue Origin argues that “NASA disparately and unequally analyzed SpaceX’s and Blue
    38
    Origin’s communication link non-closures.” (ECF 61-1 at 58.) Blue Origin was assigned a
    Significant Weakness for this issue, and SpaceX received a Weakness. (AR Tab 59a at 62654;
    AR Tab 59c at 62793.) The SEP explained that “[d]uring all portions of the mission, HLS is
    required to be able to communicate concurrently with Mission Systems, Suits, and the Lunar
    orbiting crew occupying Orion.” (AR Tab 59c at 62793.) For Blue Origin to prevail on its
    disparate-treatment claim, its proposal must have been “‘substantively indistinguishable’ or
    nearly identical” to SpaceX’s proposal. Off. Design Grp., 951 F.3d at 1372.
    The record indicates that Blue Origin’s proposal was substantively distinguishable from
    SpaceX’s proposal. The proposals were quantitatively different. In its evaluation of Blue
    Origin’s proposal, the SEP found that “[f]our of the six communications links proposed by the
    offeror will not close as currently designed, and for a fifth link, it may potentially close, but with
    very low positive margin.” (AR Tab 59a at 62654.) In contrast, the SEP found for SpaceX that
    two of the communications links may not close. (AR Tab 59c at 62793.) In addition to the
    quantitative difference, the SEP provided on this communications topic a multiple-paragraph
    analysis of each proposal, evaluating each proposal’s unique risks to the mission. (AR Tab 59c
    at 62793; AR Tab 59c at 62654-55.)
    Because the proposals are substantively distinguishable, NASA was entitled to treat each
    one distinctively on its own strengths and weaknesses, as it in fact did. Blue Origin’s disparate-
    treatment claim fails.
    3.      Double-Counted Attribute
    Blue Origin also argues that “NASA improperly awarded SpaceX multiple credits for the
    same positive attributes of its proposal.” (ECF 61-1 at 59.) Specifically, Blue Origin alleges that
    NASA repeatedly credited SpaceX’s increased ability to deliver and return an increased science
    payload, improperly citing this attribute of SpaceX’s proposal as a Significant Strength under
    one factor and as a Strength under a second factor. (Id. at 59-60 (citing AR Tab 59c at 62779-
    81.)
    NASA’s evaluation did not improperly double-count the attribute Blue Origin cites.
    NASA documented the distinct and separate benefits of the attribute in SpaceX’s proposal. The
    SEP rated SpaceX’s proposal a Significant Strength for its proposed capability. (AR Tab 59c at
    62779.) The SEP based its rating on the combination of 12 features, not just the cargo capacity
    of SpaceX’s proposed vehicle. (Id. at 62780-81.) The SEP found that SpaceX’s “proposal
    verifiably exceeds the thresholds and/or meets the goals for twelve of NASA’s functional
    performance requirements for its initial demonstration mission,” noting that “[t]ogether,
    [SpaceX’s] proposed capabilities appreciably exceed stated requirements in a manner that will be
    advantageous to NASA . . . .” (Id.)
    The SSA agreed with the SEP’s rating of a Significant Strength for SpaceX’s proposed
    capability, noting “the SEP’s independent analysis and verification of these attributes, which
    lends credence to the feasibility of SpaceX’s approach to meeting NASA’s performance
    requirements.” (AR Tab 77 at 63044.) The SSA found “this suite of augmented capabilities and
    SpaceX’s approach to achieving them in a manner that will not comprise its ability to meet
    39
    NASA’s other requirements to be a particularly noteworthy attribute of SpaceX’s design with
    abundant potential benefit for NASA.” (Id. at 63044-45.)
    The SSA also provided support for the separate Strength SpaceX’s proposal received
    from the SEP for its cargo allocation:
    I note that the SEP also assigned SpaceX an additional, separate
    strength within Technical Area of Focus 1 specifically concerning
    its science payload delivery and return allocations. It is my
    assessment that SpaceX received some credit for these augmented
    capabilities and the flexibilities they create for NASA in the above-
    discussed significant strength. However, this separate strength
    focused on SpaceX’s unique design attributes that enable the
    creative use of available space, including its combination of
    unpressurized and pressurized cargo areas and its stowage plan,
    which will make efficient use of available space for science payloads
    and streamline their deployment and sample returns. Thus, I find
    this specific strength to be noteworthy of its own accord, and I agree
    with the SEP that the assignment of this standalone strength was
    appropriate.
    (Id. at 63045 (emphasis added).) The SSA adequately explained that the so-called double-
    counted positive attribute offered NASA distinct benefits in separate technical areas.
    NASA “provided a coherent and reasonable explanation of its exercise of discretion” on
    this issue. See Banknote Corp. of Am., 
    365 F.3d at 1351
    . The SSA directly addressed the issue
    Blue Origin raises, and she offered a reasonable basis supported by the record for her
    conclusions. NASA’s evaluation of SpaceX’s cargo capacity was not irrational.
    In sum, Blue Origin has failed to demonstrate that NASA’s evaluation of SpaceX’s
    proposal was arbitrary, capricious, or otherwise contrary to law.
    B.      Count 2: Unequal Discussions
    Blue Origin alleges that NASA “violated procurement laws and regulations by engaging
    in improper and unequal discussions where it held discussions with only SpaceX and permitted
    SpaceX to revise its unawardable and noncompliant proposal.” (ECF 1, ¶ 144.) Specifically,
    Blue Origin argues that NASA violated 
    10 U.S.C. § 2305
    (b)(4)(A) and several FAR provisions
    requiring agencies to act fairly and impartially. Even if this claim were not waived, Blue Origin
    cannot succeed on the merits.
    Section 2305(b)(4)(A) provides that “[t]he head of an agency . . . may award a contract
    . . . after discussions with the offerors, provided that written or oral discussions have been
    conducted with all responsible offerors who submit proposals within the competitive range.”
    
    10 U.S.C. § 2305
    (b)(4)(A). The FAR directs contracting officers to “[e]nsure that contractors
    receive impartial, fair, and equitable treatment,” FAR 1.602-2(b), and provides that “[a]ll
    40
    contractors and prospective contractors shall be treated fairly and impartially but need not be
    treated the same,” FAR 1.102-2(c)(3). See also FAR 1.102 (“The Federal Acquisition System
    will . . . [c]onduct business with integrity, fairness, and openness.”). “[T]he basic rule of fair
    treatment of all offerors, FAR 1.102-2(c) applies [to BAAs] even though it is not mentioned in
    FAR 35.016.” Ralph Nash & John Cibinic, 19 Nash & Cibinic Rep. ¶ 24 (2005) (“Nash &
    Cibinic”).
    To determine whether an agency acted improperly under a BAA, the analysis must begin
    with the terms of the solicitation. BAAs are governed by FAR 35.016, which provides that
    “[p]roposals received as a result of the BAA shall be evaluated in accordance with evaluation
    criteria specified therein . . . .” FAR 35.016; see also AshBritt, Inc. v. United States, 
    87 Fed. Cl. 344
    , 374 (2009) (“It is a fundamental tenet of procurement law that proposals must be evaluated
    in accordance with the terms of the solicitation.”); WaveLink, Inc., 154 Fed. Cl. at 271 (citing
    AshBritt, 87 Fed. Cl. at 374).
    Under the express terms of the solicitation, NASA reserved “the right to conduct post-
    selection negotiations or discussions if the Contracting Officer later determines them to be
    necessary.” (AR Tab 27 at 24433.) The solicitation further provided the SSA with the authority
    to “make initial, non-binding selections of an Offeror or Offerors for the purpose of having the
    Contracting Officer engage in post-selection negotiations with one or more Offerors as defined
    in [the Option A] solicitation.” (Id. at 24480 (emphasis added).) NASA also reserved “the right
    to negotiate any aspect of an Offeror’s milestone payment amounts, schedule, and/or acceptance
    criteria prior to award of Option A.” (Id. at 24467.)
    The SSA made an initial, non-binding selection of one offeror, SpaceX, for award. (AR
    Tab 64.) The contracting officer then negotiated with SpaceX regarding the prices of CLINs, the
    payment phasing, and the FRR requirement. (AR Tab 63.) In short, NASA followed the
    procedure for post-selection negotiations explicitly set out in the solicitation when it conducted
    post-selection negotiations with only SpaceX and allowed SpaceX to revise its proposal.
    This court recently addressed a similar dispute in which a protestor challenged an
    agency’s characterization of certain exchanges the agency had with other offerors. WaveLink,
    Inc., 154 Fed. Cl. at 269-72. Although the protestor argued that the exchanges were discussions,
    Judge Solomson held that “an express provision in the RFP controls and permitted the Agency’s
    approach . . . .” Id. at 271. In language that was “clear and unambiguous,” the RFP defined the
    exchanges at issue as clarifications, not discussions.7 Id. Because “the Agency followed the
    RFP’s terms regarding the characterization of the communication, [the exchange] was not a
    discussion.” Id.
    The solicitation in this case, like the RFP in WaveLink, differentiated forms of exchanges
    between the agency and offerors—the difference is timing. “Post-selection negotiations” are
    7 Judge Solomson also held in WaveLink that, if the protestor would have challenged the
    RFP’s provision, such a challenge would be untimely, and Blue & Gold Fleet would require
    dismissal under RCFC 12(b)(6). WaveLink, Inc., 154 Fed. Cl. at 271 n.21.
    41
    defined in the solicitation as “exchanges with Offerors who have been selected for potential
    contract award that result in the Contracting Officer inviting the Offeror to revise only those
    specific portions of its proposal that have been identified by the Contracting Officer as open to
    revision.” (AR Tab 27 at 24434 (emphasis added).) “Discussions” are defined as “exchanges
    with Offerors that occur after receipt of proposals but before selection that result in the
    Contracting Officer inviting the Offeror to revise only those specific portions of its proposal that
    have been identified by the Contracting Officer as open to revision.” (Id. (emphasis added).)
    The solicitation’s definitions of “post-selection negotiations” and “discussions” are clear
    and unambiguous. NASA followed the solicitation’s terms regarding the characterization of the
    exchange as a post-selection negotiation with SpaceX. Accordingly, NASA did not conduct
    discussions, and 
    10 U.S.C. § 2305
    (b)(4)(A)’s provision governing discussions does not apply.
    The SSA’s initial selection decision was not arbitrary and capricious; she explained her
    rationale for her selection of SpaceX. (AR Tab 62.) After reviewing SpaceX’s SEP report and
    receiving the SEP’s briefings regarding its evaluation results for SpaceX’s proposal, the SSA
    determined “that it is in the Agency’s best interests to conditionally select SpaceX’s proposal for
    the purposes of engaging in limited, post-selection price negotiations with this offeror.” (Id. at
    62883.) As a basis for that decision, she described the features of SpaceX’s proposal significant
    to her reasoning: “In particular, I concur with the SEP’s conclusions that SpaceX offered a
    uniquely meritorious proposal with notable qualitative attributes, both in terms of its technical
    approach and its management approach. Furthermore, SpaceX’s proposal provides abundant
    value to NASA at the price it proposed.” (Id.) She also noted that her selection was non-final.
    (Id.)
    The SSA’s explanation provides the key to the fairness question. The FAR provides that
    “[a]ll contractors and prospective contractors shall be treated fairly and impartially but need not
    be treated the same.” FAR 1.102-2(c)(3) (emphasis added). SpaceX was the highest-rated and
    lowest-priced offeror. As the SSA noted in her Source Selection Statement, she did not conclude
    that Blue Origin’s proposal “present[ed] a good value to the Government.” (AR Tab 77 at
    63056-57 n.1.) In other words, Blue Origin and SpaceX were not similarly situated. See A-T
    Sols., Inc. v. United States, 
    122 Fed. Cl. 170
    , 183 (2015) (“[O]fferors who are not similarly
    situated may be treated differently.”); Lockheed Martin Corp. v. United States, 
    124 Fed. Cl. 709
    ,
    722 (2016) (“To the extent proposals differ, the government may rationally take different action
    regarding different proposals.”). The Court finds that the SSA’s initial selection of only SpaceX
    to enter negotiations was rational based on the differences between proposals.
    In sum, NASA followed the terms of the solicitation, explained its reasoning for selecting
    SpaceX for negotiations, and treated offerors fairly. Blue Origin has not shown that NASA acted
    improperly by holding post-selection negotiations with only SpaceX and by allowing SpaceX to
    revise its proposal during negotiations.
    C.      Count 3: Failure to Amend the Solicitation
    In its third claim, Blue Origin alleges that NASA failed to amend the Option A
    solicitation upon a change in requirements, i.e., a change in the intended number of awards and a
    42
    change in review requirements. (ECF 1, ¶¶ 152-62.) Even assuming this claim were not waived,
    Blue Origin cannot succeed on the merits.
    In its complaint, Blue Origin cites FAR 15.206(a) as establishing the “axiomatic and . . .
    fundamental procurement principle” that, when the government’s requirements change, agencies
    must amend their solicitations and allow offerors to update their proposals. (Id. ¶ 153.)
    FAR 15.206(a) provides that “[w]hen, either before or after receipt of proposals, the Government
    changes its requirements or terms and conditions, the contracting officer shall amend the
    solicitation.” FAR 15.206(a).
    As the government and SpaceX point out, however, NASA solicited HLS Option A
    proposals not as competitive proposals subject to FAR part 15, but “as an ‘other competitive
    procedure’ in accordance with FAR 6.102(d)(2) and FAR 35.016 (as deviated).” (See AR
    Tab 27 at 24473.) Neither provision of the FAR on which the solicitation is based incorporates
    FAR part 15. See FAR 6.102(d)(2); FAR 35.016. Accordingly, there is no requirement in the
    FAR or the solicitation that NASA’s conduct here must adhere to FAR 15.206(a), and Blue
    Origin has pointed to no other source of law that imposes the mandates of FAR part 15 on
    NASA’s consideration of the offers to this solicitation.8 Nonetheless, as Professors Nash and
    Cibinic have noted, “the basic source selection rules when BAAs are used are similar to those for
    competitive negotiations in FAR Part 15.” Nash & Cibinic. Here, NASA’s solicitation
    anticipated a funding limitation and provided discretion to negotiate acceptance criteria. NASA
    complied with the terms of the solicitation and, thus, had no legal obligation to amend its
    proposal under FAR 15.206(a). See Ocean Ships, Inc. v. United States, 
    115 Fed. Cl. 577
    , 590-91
    (2014) (finding that FAR 15.206(a) was not triggered by agreements to raise wages because the
    RFP expressly identified the potential for a wage increase).
    In Blue Origin’s response, perhaps recognizing that FAR 15.206(a) does not support its
    claim, Blue Origin expands the grounds of its failure-to-amend argument. (ECF 69 at 30.) In
    addition to asserting NASA was required to amend its Option A solicitation pursuant to
    FAR 15.206(a), Blue Origin contends that the principles of fairness and impartiality established
    by the FAR require NASA to amend its solicitation to reflect changed requirements. (Id.) See
    FAR 1.102-2(c)(3) (“[a]ll contractors and prospective contractors shall be treated fairly and
    impartially but need not be treated the same”); FAR 1.602-2(b) (“Contracting Officers shall . . .
    [e]nsure that contractors receive impartial, fair, and equitable treatment.”).
    8 The GAO has explained that, “[l]ike Subpart 36.6 and Subpart 8.4 procurements, FAR
    §6.102(d) carves out BAA procurements from those conducted using ‘competitive proposals’
    and defines them as ‘other competitive procedures.’ . . . BAA procurements are not conducted
    under FAR Part 15; rather, they are conducted using procedures established by FAR §35.016.”
    Millennium Space Sys., Inc., B-406771, 2012 CPD ¶ 237, 
    2012 WL 3610072
    , at *5 (Comp. Gen.
    Aug. 17, 2012).
    43
    Neither the FAR’s fairness provisions nor FAR 15.206, if fully applicable, support Blue
    Origin’s claim because Blue Origin has failed to demonstrate that NASA’s requirements for the
    HLS Option A solicitation changed during the procurement process.
    Blue Origin asserts that NASA acted improperly when it did not notify all offerors of its
    “change in requirements” based on the allocated HLS program funds. (ECF 61-1 at 61-62.) To
    support its argument that agencies are obligated “to advise offerors of . . . changed conditions
    due to unavailability of funds,” Blue Origin relies heavily on the GAO’s decision in Joint Action
    in Community Service, Inc. (Id. at 62 (underline omitted).) In Joint Action, the GAO found that
    the government had acted improperly when it reopened negotiations with only one offeror “and
    negotiated [a] necessary price reduction to meet available funding limits.” Joint Action in
    Community Service, Inc., B-214564, 1984 CPD ¶ 228 (Comp. Gen. Aug. 27, 1984), aff’d but
    relief modified, B-214564.2, 1985 CPD ¶ 13 (Comp. Gen. Jan. 3, 1985). The GAO found that, if
    the protestor in Joint Action had been given the same “opportunity to negotiate a price
    reduction,” the protestor “could have substantially reduced the difference between the two
    offers” and stood a substantial chance of award. 
    Id.
    Blue Origin argues that NASA’s “action here . . . mirrors that in Joint Action” because
    “the substantial change in requirements was the level of available funding and the restructuring
    of the awardee’s proposal to come within the level of available funding.” (ECF 61-1 at 63
    (underline omitted).) In making this comparison, however, Blue Origin ignores a crucial
    distinction; the GAO found that the government had enabled the awardee’s proposal to fall
    within the amount of available funding by “alter[ing] the RFP requirements by substituting
    [Government Furnished Property] for what was previously contractor-furnished property.” B-
    214564, 1984 CPD ¶ 228. It was this alteration that constituted improper government action. 
    Id.
    The change in requirements in Joint Action was not the level of available funding, as
    Blue Origin argues; rather, the government’s stated requirements for furnished property changed
    to accommodate the funding allocated. 
    Id.
     Here, NASA’s FY 2021 funding allocation for the
    HLS program caused no comparable change to the BAA requirements. 9
    The FY 2021 funding itself does not constitute a change to NASA requirements. As the
    Court previously noted, the HLS Option A solicitation did not state the amount of funding
    9  The GAO’s holding in Joint Action is also inapplicable to the present case because in Joint
    Action the proposals of both the protestor and the awardee were “substantially equal on technical
    merit,” and the awardee’s evaluated cost was only 17 percent lower than the protestor’s
    evaluated cost. B-214564, 1984 CPD ¶ 228. Based on the substantial technical balance between
    the proposals and the fact that the protestor was within the competitive range, the GAO found
    that the protestor was prejudiced when the agency improperly negotiated a price reduction only
    with the awardee. 
    Id.
     Here, Blue Origin’s proposal was rated lower than SpaceX’s on
    management quality and was more than twice the price of SpaceX’s proposal. Accordingly,
    these additional factors that guided the GAO to find in the protestor’s favor in Joint Action are
    absent here.
    44
    NASA anticipated or considered necessary to fund Option A contract awards. (See AR Tab 27 at
    24481.) The difference between the amount Congress appropriated to the HLS program and the
    amount requested by NASA does not imply a change in NASA’s HLS requirements. In fact,
    NASA explicitly provided for this type of funding situation by conditioning award of any HLS
    contracts “upon the availability of appropriated funds from which payments can be made and the
    receipt of proposals that NASA determines are acceptable.” (Id.) Accordingly, Blue Origin’s
    argument that this difference in funding constituted a change in requirements fails in the face of
    the express language of the solicitation.
    NASA also did not change its review requirements. The solicitation reserved to NASA
    “the right to negotiate any aspect of an Offeror’s milestone payment amounts, schedule, and/or
    acceptance criteria prior to award of Option A.” (AR Tab 27 at 24467.) NASA negotiated its
    FRR requirement with SpaceX (AR Tab 63), and, as the Court found above, NASA acted within
    its discretion regarding the other reviews.
    The requirements simply did not change, so NASA did not need to amend the
    solicitation. NASA anticipated that the HLS Option A contracts would be subject to funding
    limitations based on the amount appropriated to the HLS program. NASA thus structured its
    solicitation to make all awards contingent on funding and, in this highly technical context,
    reserved for itself the discretion to negotiate features of offerors’ proposals. Blue Origin has
    failed to demonstrate that NASA acted improperly by not amending its solicitation.
    D.      Count 5: Breach of Implied-in-Fact Contract
    Blue Origin’s final claim alleges that NASA “breached the implied contract to consider
    all bids fairly and honestly by conducting the procurement in an arbitrary, capricious, and
    irrational manner.” (ECF 1, ¶ 171.) Blue Origin reasserts its allegations from its other claims
    and adds an allegation that NASA improperly favored SpaceX’s proposal. (Id. ¶¶ 172-74.)
    The Federal Circuit in Safeguard Base Operations recently held that a claim by a
    protestor for a breach of implied-in-fact contract in the procurement context falls within the bid-
    protest jurisdiction of this court under 
    28 U.S.C. § 1491
    (b)(1). 989 F.3d at 1342-43. Courts
    review these breach-of-contract claims under the APA’s standard, as courts do for any other
    § 1491(b)(1) claim. See id. at 1332, 1342. Safeguard Base Operations did not address, however,
    how these claims differ from other procurement-related claims that a protestor may allege in a
    bid protest.
    In this case, the Court need not conduct a separate analysis. At oral argument, Blue
    Origin argued that, even if the Court rejected all its other claims, pieces of each claim in
    combination could support its breach-of-contract claim. A case like the one Blue Origin
    attempts to present might exist, but it is not this one. Here the Court has found no portion of
    NASA’s evaluation to have been arbitrary and capricious; the sum of Blue Origin’s claims does
    not yield more than the sum of its parts.
    Although Blue Origin has not alleged bad faith, its claim of favoritism implies bad faith
    through innuendo. Blue Origin has not supported such a claim, has presented no facts in the
    45
    record to sustain the claim, and has not come close to meeting the heightened burden of proof
    that the claim requires. See Am-Pro Protective Agency, Inc. v. United States, 
    281 F.3d 1234
    ,
    1239-40 (Fed. Cir. 2002) (adopting the “clear and convincing” burden of proof to overcome the
    presumption of the government’s good faith).
    Blue Origin has not established that NASA breached its implied-in-fact contract of good
    faith and fair dealing.
    E.      Failure to Demonstrate Prejudice
    Even if the Court had found on the merits that NASA had erred, Blue Origin could not
    demonstrate prejudice on the merits. As in the standing stage of analysis, “[t]o establish
    prejudicial error, a protestor must show that but for that error, the protestor had a substantial
    chance of receiving a contract award.” Off. Design Grp., 951 F.3d at 1373-74. The Federal
    Circuit has held that “[d]e minimis errors in the procurement process do not justify relief.” Id. at
    1374.
    Blue Origin cannot show prejudice for the same reasons elaborated in the standing
    analysis. Blue Origin’s proposal was priced at more than [***] times NASA’s FY 2021 budget
    for the Option A contract, Blue Origin could not have benefited from waived reviews for
    supporting spacecraft because it did not propose any, and its proposal was unawardable without
    discretionary negotiations. As discussed above, the SSA reasonably exercised her discretion not
    to engage in those negotiations.
    VI.    CONCLUSION
    In summary, the Court has found that Blue Origin does not have standing, several of its
    objections are waived, and, in the alternative, it loses on the merits. First, Blue Origin does not
    have standing because it was not prejudiced by the alleged errors. In other words, Blue Origin
    did not have a substantial chance of award but for the alleged evaluation errors. Second, by not
    objecting earlier, Blue Origin has waived the objections regarding FRRs and the DCR in Count 1
    and its objections in Counts 2 and 3 in their entirety. Finally, Blue Origin has not established
    that NASA’s evaluation of SpaceX’s proposal or its conduct during the procurement was
    arbitrary, capricious, or otherwise contrary to law.
    46
    Because Blue Origin has not succeeded on the merits, it has failed to satisfy the standards
    for receiving injunctive relief. See PGBA, LLC v. United States, 
    389 F.3d 1219
    , 1229 (Fed. Cir.
    2004) (requiring success on the merits as the first consideration in deciding whether to issue a
    permanent injunction).
    For the above-stated reasons, Blue Origin’s complaint is dismissed, and the Court rules
    on the parties’ motions as follows:
    •   The government’s motion to dismiss (ECF 60) under RCFC 12(b)(1) is granted.
    •   The government’s motion for judgment on the administrative record (ECF 60) is
    granted.
    •   SpaceX’s motion for judgment on the administrative record (ECF 62) is granted.
    •   Blue Origin’s motion for judgment on the administrative record (ECF 61) is
    denied.
    The Court will issue an order in accordance with this memorandum opinion.
    s/ Richard A. Hertling
    Richard A. Hertling
    Judge
    47