Park Properties Associates, L.P. v. United States ( 2014 )


Menu:
  •       In The United States Court of Federal Claims
    No. 04-1757C
    This Opinion and Order Will Not Be Published in the U.S. Court of Federal Claims
    Reporter Because It Does Not Add Significantly to the Body of Law.
    (Filed: September 19, 2014)
    _________
    PARK PROPERTIES ASSOCIATES,
    L.P., et al.,                                   *
    *
    Plaintiffs,               *
    *
    v.                                       *
    *
    THE UNITED STATES,                              *
    *
    Defendant.                *
    *
    _________
    OPINION and ORDER
    __________
    ALLEGRA, Judge:
    This contract case is pending before the court on the parties’ cross-motions for partial
    summary judgment on damages. Plaintiffs entered into rent subsidy agreements with the United
    States Department of Housing and Urban Development (HUD), known as “Housing Assistance
    Payment” (HAP) contracts. This court previously determined that defendant repudiated those
    contracts in 1994, when Congress amended the controlling statute to alter the way in which rent
    increases were to be determined. Park Props. Assocs., L.P. v. United States, 
    74 Fed. Cl. 264
    ,
    265-66 (2006) (Park Properties I). Later, the court held that a limitation found in the HAP
    contracts could not be applied to limit the damages owed by defendant. Park Props. Assocs.,
    L.P. v. United States, 
    82 Fed. Cl. 162
    , 176 (2008) (Park Properties II).
    The court stayed resolution of the pending cross-motions until the Federal Circuit decided
    Haddon Housing Associates Ltd. Partnership v. United States, 
    711 F.3d 1330
     (Fed. Cir. 2013).
    Following the issuance of that opinion, the parties have agreed that: (i) Departments of Veterans
    Affairs and Housing and Urban Development, and Independent Agencies Appropriation Act of
    1995, Pub. L. No. 103-327, 
    108 Stat. 2298
    , 2315 (1994) (the 1994 Act), as implemented by
    HUD, breached provisions in plaintiffs’ HAP contracts; (ii) the Overall Limitation provision
    found in plaintiffs’ HAP contracts cannot be applied to reduce plaintiffs’ rent adjustments for
    purposes of calculating damages herein; and (iii) the provision of the 1994 Act that required a
    deduction in adjustments for units that did not turnover cannot be applied to reduce plaintiffs’
    rent adjustments for purposes of calculating their damages. As will be discussed below, three
    issues remain in dispute.
    A detailed recitation of the background facts in this case may be found in this court’s
    prior opinions. See Park Properties II, 82 Fed. Cl. at 164-67; Park Properties I, 74 Fed. Cl. at
    266-70. The court will not restate these facts, but instead hereby incorporates, by reference,
    these prior recitations.
    The first issue presented by the parties’ pending motions regards the applicability of the
    six-year statute of limitations found in 
    28 U.S.C. § 2501
     to plaintiffs’ claims. The question is
    whether plaintiffs are entitled to recover damages for the so-called “stub period,” that is, the
    period between December 10, 1998 (the date that is six years prior to the date they filed this
    suit), and the immediately succeeding anniversary dates in the relevant HAP contracts.
    Defendant argues that these damages should be barred because they relate back to an anniversary
    date that falls outside the statute of limitations. Plaintiffs, however, rely on Pennsauken Senior
    Towers Urban Renewal Associates, LLC v. United States, 
    83 Fed. Cl. 623
    , 629 (2008), in which
    Judge Lettow concluded that such “stub period” damages were recoverable. Finding
    Pennsauken (and its progeny) persuasive, the court hereby adopts the analysis therein and rules
    in favor of plaintiffs on this issue. See Ocean View Towers Assocs., Ltd. P’ship, 
    88 Fed. Cl. 169
    ,
    175-78 (2009); Cathedral Square Partners Ltd. P’ship v. S.D. Hous. Dev. Auth., 
    2011 WL 43019
    , at *13 (D.S.D. Jan. 5, 2011); see also Haddon Hous. Assocs., 711 F.3d at 1340-41
    (indicating that Pennsauken “provided a succinct analysis of [this] jurisdictional issue,” but
    declining to reach the merits); cf. One & Ken Valley Hous. Grp. v. Main St. Hous. Auth., 
    2012 WL 1458202
    , at *25 (D. Me. Apr. 17, 2012), aff’d, 
    716 F.3d 218
     (1st Cir. 2013), cert. denied,
    
    134 S. Ct. 986
     (2014); Greenleaf Ltd. P’ship v. Ill. Hous. Dev. Auth., 
    2010 WL 3894126
    , at *8
    (N.D. Ill. Sept. 30, 2010).
    The second issue focuses on whether plaintiffs can recover for payments due from HUD
    on vacant units. While both parties agreed that HUD did not pay any of the eighty percent owed
    on the vacant units, defendant argues that plaintiffs are not entitled to receive any damages for
    vacant units because they failed to file monthly claims for contract rent subsidies for those units,
    as required by HUD. Plaintiffs did not address this issue in their briefs. But, this was
    understandable as defendant did not address this issue until the supplemental briefing in the
    Haddon case – and then proceeded without any supporting affidavits. 1 In the court’s view,
    defendant’s delay in pressing this argument waived this issue, leading to the conclusion that
    1
    In its supplemental brief, defendant stated: “[D]uring our discussions with plaintiffs,
    we learned, for the first time, that plaintiffs have not received subsidy payments for vacant units
    in the real world because plaintiffs have not filed monthly claims for contract rent subsidies for
    their vacant units. In light of this fact, we question whether plaintiffs are entitled to receive any
    damages for the days during which their units were vacant.” (Emphasis in original).
    -2-
    plaintiffs are entitled to the payments in question. See Enzo Biochem, Inc. v. Gen-Probe, Inc.,
    
    424 F.3d 1276
    , 1284 (Fed. Cir. 2005) (“Attorney argument is no substitute for evidence.”);
    Johnston v. IVAC Corp., 
    885 F.2d 1574
    , 1581 (Fed. Cir. 1989) (“Attorneys’ argument is no
    substitute for evidence.”); In re Budge Mfg. Co., 
    857 F.2d 773
    , 776 (Fed. Cir. 1988) (statements
    of attorney are “no evidence”); Mel Williamson, Inc. v. United States, 
    229 Ct. Cl. 846
    , 848
    (1982) (“Argument is not fact.”).
    The final issue focuses on whether plaintiffs are entitled to lost profit damages associated
    with the reduced rents in their renewal HAP contracts. However, a careful review of the
    complaint and the other filings in this case reveals that plaintiffs did not raise this claim in their
    complaint. As this claim was not properly raised, in the court’s view, this issue has been waived.
    See Casa de Cambio Comdiv S.A., de C.V. v. United States, 
    291 F.3d 1356
    , 1366 (Fed. Cir.
    2002), cert. denied, 
    538 U.S. 921
     (2003) (rejecting claim that “was not properly raised” as “[n]o
    mention of this theory appears in [the] complaint”); McVey Co. v. United States, 
    111 Fed. Cl. 387
    , 399 n.10 (2013); Englewood Terrace Ltd. P’ship v. United States, 
    86 Fed. Cl. 720
    , 728
    (2009); see also Becton Dickinson & Co. v. C.R. Bard, Inc., 
    922 F.2d 792
    , 800 (Fed. Cir. 1990).
    (As the old adage goes, “what is sauce for the goose is sauce for the gander.”)
    Even if this claim were properly pled, there is a fundamental problem with plaintiffs’
    claim in terms of foreseeability and, in particular, the notion that it was foreseeable that the
    parties would renew their contracts based upon the rents under the original contract and the
    extensions thereof. To recover lost profits, plaintiffs must show that the profits were reasonably
    foreseeable or actually foreseen by the breaching party at the time of the contracting. See
    Anchor Sav. Bank, FSB v. United States, 
    597 F.3d 1356
    , 1361 (Fed. Cir. 2010); Energy Capital
    Corp. v. United States, 
    302 F.3d 1314
    , 1324-25 (Fed. Cir. 2002); see also Restatement (Second)
    of Contracts § 351 (1981); Franconia Assocs. v. United States, 61 Fed Cl. 718, 746 (2004).
    Plaintiffs cannot hope to make this showing primarily because the damages they seek relate not
    to the original contract, but to subsequent renewal contracts – contracts that neither party
    envisioned when the original contracts were signed, that no party was forced to sign and that
    plaintiffs could have rejected. These renewal contracts, indeed, arose under a statutory regime
    that was not adopted by Congress until 1997. See Multifamily Assisted Housing Reform and
    Affordability Act of 1997 (MAHRA), Pub. L. No. 105-65, 
    111 Stat. 1344
     (1997); 42 U.S.C. §
    1437f note. 2 That plaintiffs chose to proceed on terms that they now view as unfavorable
    provides no legal basis upon which they may predicate their request for lost profits. In other
    words, the lost profits in question were not reasonably foreseeable and no recovery on this claim
    is allowed.
    2
    In its supplemental brief, plaintiffs asserted that Congress’ adoption of MAHRA
    effectively made the renewal of the contracts mandatory. They asserted that various criteria
    (e.g., the availability of adequate and affordable housing) required this result. Plaintiffs,
    however, did not provide any real details as to how the detailed provisions of MAHRA required
    this result. See MAHRA, § 515. A review of the statute suggests that property owners, like
    plaintiffs, had a choice – they could renew their contracts or provide tenants with notices of their
    intent not to renew. MAHRA, §§ 514(d), 515(c); see also 
    24 C.F.R. § 402.8
    . That plaintiffs
    eventually chose to renew their contracts does not alter this fact.
    -3-
    Based on the foregoing, the court GRANTS, in part, and DENIES, in part, plaintiffs’
    motion for summary judgment and GRANTS, in part, and DENIES, in part, defendant’s motion
    for summary judgment. On or before October 15, 2014, the parties shall file a joint status report
    indicating how this case should proceed.
    IT IS SO ORDERED.
    s/Francis M. Allegra
    Francis M. Allegra
    Judge
    -4-