The Tolliver Group, Inc. v. United States ( 2022 )


Menu:
  •              In the United States Court of Federal Claims
    No. 17-1763C
    (Filed: August 17, 2022)
    )
    Claim for partial reimbursement of legal
    THE TOLLIVER GROUP, INC.,                   )
    fees in successful defense of qui tam
    )
    suit; FAR Part 31
    Plaintiff,                   )
    )
    v.                                   )
    )
    UNITED STATES,                              )
    )
    Defendant.                   )
    W. Brad English and Emily J. Chancey, Maynard, Cooper & Gale, P.C., Hunstville,
    Alabama, for plaintiff.
    Ashley Akers, Trial Attorney, Commercial Litigation Branch, Civil Division, United
    States Department of Justice, Washington, D.C., for defendant. With her on the briefs were
    Brian Boynton, Principal Deputy Assistant Attorney General, Civil Division, Patricia M.
    McCarthy, Director, and Tara K. Hogan, Assistant Director, Commercial Litigation Branch,
    Civil Division, United States Department of Justice, Washington, D.C.
    OPINION AND ORDER
    LETTOW, Senior Judge.
    Pending before the court are the parties’ renewed cross-motions for summary judgment
    following remand from the United States Court of Appeals for the Federal Circuit. See Tolliver
    Grp., Inc. v. United States, 
    20 F.4th 771
     (Fed. Cir. 2021). The salient question presented is
    whether plaintiff may recover legal fees incurred in defending its contract performance in a qui
    tam suit brought under the False Claims Act. The court concludes (1) that the cost principles and
    procedures in Federal Acquisition Regulation (“FAR”) Subpart 31.2 applied to the contract
    during the period of performance prior to modification and (2) that plaintiff’s request for
    attorneys’ fees satisfies the allowability standards in that subpart. Accordingly, the court
    GRANTS plaintiff’s renewed motion for summary judgment (“Pl.’s Mot.”), ECF No. 75, and
    DENIES the government’s renewed cross-motion for summary judgment (“Def.’s Cross-Mot.”),
    ECF No. 78.
    BACKGROUND 1
    A. Contract Award and Modification
    On August 26, 2011, defendant, the United States Army (“Army” or “government”),
    awarded Task Order 10 under Contract No. W56HZV-09-A-A902 to DRS Technical Services,
    Inc., Joint Stip. ¶ 1, ECF No. 38, which novated to plaintiff, the Tolliver Group, Inc.
    (“Tolliver”), on September 25, 2012, Joint Stip. ¶ 3. The purpose of Task Order 10 was to create
    and deliver technical manuals for the 910 MCV-Mine Clearing System. Joint Stip. ¶ 5. The
    order’s Performance Work Statement required the Army to provide a technical data package to
    Tolliver from the original equipment manufacturer, Joint Stip. ¶¶ 10-12, although Tolliver was
    not required to rely on that information, see United States ex rel. Searle v. DRS Tech. Servs., No.
    1:14-cv-402, 
    2015 WL 6691973
    , at *3 (E.D. Va. Nov. 2, 2015), aff’d, 
    680 Fed. Appx. 163
     (4th
    Cir. 2017). 2
    The Army’s contracting officer representative responsible for Task Order 10 neither
    obtained nor provided the technical data package. Joint Stip. ¶¶ 13-14. The Army directed
    Tolliver to proceed without the technical data package, see App. to Pl.’s Mot. for Summ. J.
    (“Pl.’s App.”) at A1513 (Decl. of Robert Woods ¶ 7 (Sep. 23, 2019)), ECF No. 41-1, which
    plaintiff did, Joint Stip. ¶ 15. Subsequently, Task Order 10 was modified on April 23, 2013, by
    Modification 8, which converted it from a fixed-price, level-of-effort developmental contract to a
    pure firm-fixed-price contract and removed the technical data package requirement from the
    Performance Work Statement. Joint Stip. ¶¶ 4, 17-18.
    B. The Qui Tam Litigation and Resulting Claim to the Contracting Officer
    “On April 15, 2014, Robert Searle filed a qui tam suit against Tolliver under the False
    Claims Act in the United States District Court for the Eastern District of Virginia.” Joint Stip.
    ¶ 19. Mr. Searle’s qui tam action claimed that Tolliver violated the False Claims Act by
    performing without the technical data package and by deviating from certain military standards
    and Army regulations in the final version of the technical manuals that it created. See Searle,
    
    2015 WL 6691973
    , at *1. The District Court entered summary judgment in Tolliver’s favor on
    November 2, 2015, Joint Stip. ¶ 20, which Mr. Searle appealed to the United States Court of
    Appeals for the Fourth Circuit, Joint Stip. ¶ 21. The Court of Appeals affirmed the District
    1
    The recitations that follow do not constitute findings of fact but rather are recitals
    attendant to the pending motion and reflect matters drawn from the complaint, the parties’ briefs,
    and documents appended to the complaint and briefs.
    2
    Because qui tam relators prosecute not only their own case but also represent the United
    States, they bind the United States to any judgment they obtain, and therefore a district court’s
    findings of fact in a qui tam action are res judicata against the government. See Stauffer v.
    Brooks Bros., Inc., 
    619 F.3d 1321
    , 1329 (Fed. Cir. 2010). Consequently, this court must treat as
    established and undisputed any fact found by the Eastern District of Virginia in the qui tam
    litigation underpinning this action.
    2
    Court’s decision on February 23, 2017. Joint Stip. ¶ 22; see also Searle, 680 Fed. Appx. at 168.
    The United States declined to intervene or move to dismiss the qui tam suit at trial or on appeal,
    Joint Stip. ¶¶ 23-24, although it appears to have “recogniz[ed] from the outset that the qui tam
    action lacked merit,” Tolliver Grp., Inc. v. United States, 
    146 Fed. Cl. 475
    , 480 (2020) (citing
    Hr’g Tr. 29:22 to 31:2 (Nov. 15, 2019), ECF No. 48), vacated and remanded, 
    20 F.4th 771
    .
    On June 15, 2017, Tolliver submitted a certified claim to the Army contracting officer
    seeking $195,899.[78], Joint Stip. ¶ 25, which it represented was 80% of the attorneys’ fees that
    it incurred in defending itself in the qui tam action, Joint Stip. ¶ 26.3 “In its claim, Tolliver
    expressly cited [48 C.F.R. (“FAR”)] § 31.205-47, which sets forth cost principles for allowability
    of legal costs in commercial contracts.” Tolliver Grp., 146 Fed. Cl. at 481 (internal citations
    omitted). On September 8, 2017, the contracting officer denied Tolliver’s claim in full. Joint
    Stip. ¶ 27. The contracting officer determined that Tolliver’s litigation costs were not allocable
    to Task Order 10 “because they were not incurred specifically for the contract and did not
    provide the government with a benefit,” and “the fixed-price nature of the contract” proscribed
    such reimbursement “in the absence of a contract clause providing otherwise.” Tolliver Grp.,
    146 Fed. Cl. at 481 (citing Pl.’s App. at A1433-35).
    C. Claims Court Litigation and Appeal Regarding Tolliver’s Claim
    Tolliver brought suit in this court under 
    41 U.S.C. § 7104
    (b)(1) on November 9, 2017,
    alleging that the government had made a constructive change to Task Order 10 by requiring
    Tolliver to proceed without the technical data package and that it was entitled to recover 80% of
    its legal fees related to the qui tam action under FAR § 31.205-47. See generally Compl., ECF
    No. 1. The court issued two opinions relevant to the parties’ present motions.
    First, on October 26, 2018, the court denied the government’s motion to dismiss
    Tolliver’s complaint for failure to state a claim. See Tolliver Grp., Inc. v. United States, 
    140 Fed. Cl. 520
     (2018). The court held that FAR § 31.205-47 applied to Task Order 10 before
    Modification 8 because (1) FAR Part 31 applies to a fixed-price contract when cost analysis is
    performed, which was required under Task Order 10 before Modification 8, (2) Modification 8
    used forward-looking language and lacked retroactive effect over the pre-modification period of
    contract performance, and (3) under the Christian doctrine, 4 FAR § 31.205-47 was incorporated
    into Task Order 10. Id. at 526-29.
    Second, on January 22, 2020, the court denied the government’s motion for summary
    judgment, while granting in part and denying in part Tolliver’s summary judgment motion. See
    Tolliver Grp., 146 Fed. Cl. at 479. The court held, relying on United States v. Spearin, 
    248 U.S. 132
     (1918), that “the contract could not be performed as specified in the original Performance
    3
    A nine-cent discrepancy appears between the amount set out in the parties’ joint
    stipulation, Joint Stip. ¶ 25 ($195,899.87), and the amount of Tolliver’s claim, Pl.’s App. at
    A1242 ($195,899.78). The court applies the amount stated in the claim.
    4
    See G. L. Christian & Assocs. v. United States, 
    160 Ct. Cl. 1
    , 15-16 (1963).
    3
    Work Statement . . . , engendering changed conditions of performance” that “directly constituted
    the basis of the qui tam suit” and entitled Tolliver to recover part of its attorneys’ fees. 
    Id.
     In
    doing so, the court declined to address Tolliver’s allowability claim under FAR Subpart 31.2 and
    instead held that the Army had breached the implied warranty of performance. Id. at 483-84.
    After subsequent opinions denying the government’s motion for reconsideration and
    ruling that Tolliver’s attorneys’ fees were reasonable, the government appealed the court’s
    decisions. See Tolliver Grp., 
    20 F.4th 771
    . Because Tolliver had not explicitly raised the
    implied warranty of performance and the Spearin doctrine in its claim to the Army contracting
    officer, the Court of Appeals held that this court lacked jurisdiction to decide a claim on those
    grounds. 
    Id. at 776-77
    . This court’s decision was vacated on that jurisdictional ground and
    remanded “for such further proceedings as may be appropriate.” 
    Id. at 778
    . This court ordered
    renewed briefing to clarify which issues the parties wished to pursue. See Order of May 6, 2022,
    ECF No. 74. The parties again cross-moved for summary judgment, and the matter is fully
    briefed. See Pl.’s Mot.; Def.’s Cross-Mot.; Pl.’s Reply and Resp., ECF No. 81; Def.’s Reply,
    ECF No. 82.
    STANDARDS FOR DECISION
    Summary judgment shall be granted “if the movant shows that there is no genuine dispute
    as to any material fact and the movant is entitled to judgment as a matter of law.” Rule 56(a) of
    Rules of the Court of Federal Claims (“RCFC”). A material fact is one that “might affect the
    outcome of the suit.” Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    , 248 (1986) (interpreting
    Fed. R. Civ. P. 56). 5 A genuine dispute exists when the finder of fact may reasonably resolve the
    dispute “in favor of either party.” 
    Id. at 250
    .
    The movant bears the burden of demonstrating the absence of any genuine disputes of
    material fact, see Celotex Corp. v. Catrett, 
    477 U.S. 317
    , 323 (1986), and must “cit[e] to
    particular parts of materials in the record, including depositions, documents, electronically stored
    information, affidavits or declarations, stipulations[,] . . . admissions, interrogatory answers, or
    other materials,” RCFC 56(c)(1)(A). The court “may consider other materials in the record”
    even if not cited by the parties. See RCFC 56(c)(3). “[T]he inferences to be drawn . . . must be
    viewed in the light most favorable to the party opposing the motion.” Matsushita Elec. Indus.
    Co. v. Zenith Radio Corp., 
    475 U.S. 574
    , 587-88 (1986) (quoting United States v. Diebold, Inc.,
    
    369 U.S. 654
    , 655 (1962)). If the record taken as a whole “could not lead a rational trier of fact
    to find for the non-moving party, there is no ‘genuine issue for trial,’” and summary judgment is
    appropriate. 
    Id.
     (quoting First Nat’l Bank of Ariz. v. Cities Serv. Co., 
    391 U.S. 253
    , 289 (1968)).
    When both parties have moved for summary judgment, “the court must evaluate each
    party’s motion on its own merits, taking care in each instance to draw all reasonable inferences
    against the party whose motion is under consideration.” Mingus Constructors, Inc. v. United
    States, 
    812 F.2d 1387
    , 1391 (Fed. Cir. 1987). “The fact that both parties have moved for
    5
    Because RCFC 56 mirrors Fed. R. Civ. P. 56, the rules should be interpreted in pari
    materia.
    4
    summary judgment does not mean that the court must grant judgment as a matter of law for one
    side or the other.” 
    Id.
     “To the extent there is a genuine issue of material fact, both motions must
    be denied.” Marriott Int’l Resorts, L.P. v. United States, 
    586 F.3d 962
    , 969 (Fed. Cir. 2009).
    ANALYSIS
    “An action brought before the Court of Federal Claims under the Contract Disputes Act
    must be based on the same claim previously presented to and denied by the contracting officer.”
    Raytheon Co. v. United States, 
    747 F.3d 1341
    , 1354 (Fed. Cir. 2014) (brackets omitted) (quoting
    Scott Timber Co. v. United States, 
    333 F.3d 1358
    , 1365 (Fed. Cir. 2003)). Here, Tolliver’s claim
    to the contracting officer sought “$195,889.78 for allowable legal fees associated with defending
    itself” in the qui tam litigation based on grounds of equitable adjustment and the cost principles
    and procedures in FAR Part 31, specifically FAR § 31.205-47, “Costs related to legal and other
    proceedings.” Pl.’s App. at A1242. On remand, Tolliver confines its argument to FAR Part 31;
    thus, the court will focus on the allowability analysis presented in FAR § 31.201-2,
    “Determining allowability.”
    The parties’ cross-motions for summary judgment raise multiple seemingly threshold
    issues to resolve before addressing allowability, viz., whether a firm-fixed-price, level-of-effort
    developmental contract supports cost principles and procedures and whether the Christian
    doctrine incorporates FAR Subpart 31.2. Compare Pl.’s Mot. at 11-16, with Def.’s Cross-Mot. at
    11-19. While the answers to such questions could prove dispositive, these contentions are
    actually part of the allowability analysis. FAR § 31.201-2(a) indicates that “[a] cost is allowable
    only when” it is (1) reasonable, (2) allocable to the contract, (3) compliant with pertinent
    accounting standards, (4) compliant with the terms of the contract, and (5) compliant with
    limitations found in FAR Subpart 31.2. The court will therefore address the parties’ contentions
    concerning applicability of cost principles within the context of its allowability analysis. It will,
    however, first address the terms of the contract.
    A. Contract Terms
    Tolliver asserts that reimbursement of its legal fees under FAR § 31.205-47 is consistent
    with the terms of Task Order 10 because (1) the risk of incomplete performance was allocated to
    the government pre-modification, rendering pre-modification Task Order 10 a cost-type contract,
    Pl.’s Mot. at 12-14, (2) the prospective language of Modification 8 limited its scope to post-
    modification contract performance, id. at 11-12, and (3) the Christian doctrine incorporated FAR
    Part 31 cost principles into Task Order 10 (i.e., the contract implicated FAR Subpart 31.2,
    contracts with commercial organizations, the government was required to perform cost analysis,
    and Task Order 10 was a developmental contract), id. at 14-16.
    The government contends that cost principles and procedures are inconsistent with the
    terms of Task Order 10 because (1) Task Order 10 was a firm-fixed-price contract before and
    after Modification 8, Def.’s Cross-Mot. at 6-8, 11-14; Def.’s Reply at 2, 6 (2) there is no
    6
    Regardless of this contention, the government appears to concede that Modification 8
    lacked retroactive effect to cover the pre-modification period of performance and instead only
    5
    provision in Task Order 10 to permit a price adjustment for contractor costs incurred beyond the
    contract price, Def.’s Cross-Mot. at 8-9, (3) the required cost analysis under Task Order 10
    served to assess the reasonableness of the contract price, not to assess the allowability of incurred
    costs, id. at 8 n.5, 9-11, (4) there is no foundation for incorporating FAR Part 31 cost principles
    and procedures into Task Order 10 using the Christian doctrine, id. at 17-19, and (5) permitting
    cost principles and procedures under Task Order 10 would negate the policy purposes of
    allocating risk to the contractor in firm-fixed-price contracts, id. at 14-17.
    The parties’ arguments focus on two questions: whether the cost principles and
    procedures of FAR Part 31 would have applied to Task Order 10 pre-modification and whether
    FAR § 31.205-47 would be incorporated into Task Order 10 in the absence of an express
    contract provision.
    1. Applicability of Cost Principles and Procedures to Pre-modification Task Order 10
    The parties’ disagreement about whether pre-modification Task Order 10 was a cost-type
    contract or a pure firm-fixed-price contract overlooks that FAR Part 31 cost principles and
    procedures would apply in either scenario. If Task Order 10 operated as a cost-type contract pre-
    modification, then cost principles and procedures would apply as a matter of regulation. As a
    firm-fixed-price, level-of-effort contract, “[t]he product of the contract” was “the results
    achieved through application of the required level of effort,” and “payment [was] based on the
    effort expended rather than on the results achieved.” FAR § 16.207-2; see also McDonnell
    Douglas Corp. v. United States, 
    37 Fed. Cl. 295
    , 299 n.5 (1997) (“[F]ixed-price level of effort
    contracts . . . operate more like cost-reimbursement contracts with limitation of costs clauses.
    The [g]overnment sets contract prices based on labor hours and when that price is reached, the
    contractor is relieved of any further liability.”). If Tolliver was reimbursed for effort expended
    as contrasted to results achieved, then pre-modification Task Order 10 did indeed operate as a
    cost-type contract with the government reimbursing Tolliver’s labor and other related costs. See
    Pl.’s App. at A2 (outlining price ceiling under Task Order 10 to reimburse labor and travel).
    Alternatively, if Task Order 10 was always a pure firm-fixed-price contract, the FAR
    would still dictate application of cost principles and procedures. “Fixed-price contracts are not
    categorically immune from applicability of cost principles.” Tolliver Grp., 140 Fed. Cl. at 526.
    The FAR indicates when a fixed-price contract is subject to cost principles. First, FAR Part 31
    “shall be used in the pricing of fixed-price contracts, subcontracts, and modifications to contracts
    and subcontracts whenever (a) cost analysis is performed, or (b) a fixed-price contract clause
    requires the determination or negotiation of costs.” FAR § 31.102 (emphasis added).
    prospectively changed Task Order 10 from a firm-fixed-price, level-of-effort developmental
    contract to a pure firm-fixed-price contract. See Def.’s Cross-Mot. at 2-3, 12-13 (“Task Order 10
    unambiguously states that (prior to Modification 08) it is a ‘firm-fixed-price level of effort’
    contract.”); see also Tolliver Grp., 140 Fed. Cl. at 527-28 (“By its express terms, Modification 8
    sets out no indication that it was to have retroactive effect, but rather uses forward-looking
    language, which generally implies that a modification lacks retroactive effect.”).
    6
    Second, “[a] firm-fixed-price, level-of-effort term contract is suitable for investigation or
    study in a specific research and development area.” FAR § 16.207-2 (emphasis added). FAR
    Subpart 31.2 cost principles “shall be used in pricing . . . developmental . . . contracts . . . with
    commercial organizations whenever cost analysis is performed as required by 15.404-1(c).”
    FAR § 31.103(a) (emphasis added). As incorporated into Task Order 10, Pl.’s App. at A234,
    FAR § 15.404-1(c) explains that “[t]he [g]overnment may use various cost analysis techniques
    and procedures to ensure a fair and reasonable price, given the circumstances of the acquisition.
    Such techniques and procedures include,” inter alia, “[v]erification that the offeror’s cost
    submissions are in accordance with the contract cost principles and procedures in [FAR P]art
    31.” FAR § 15.404-1(c)(2)(i), (iv) (emphasis added).
    Third, “[c]ost analysis shall be used to evaluate the reasonableness of individual cost
    elements when certified cost or pricing data are required.” FAR § 15.404-1(a)(3). “The
    contracting officer shall obtain certified cost or pricing data” when “none of the exceptions in
    15.403-1(b) applies.” FAR § 15.403-4(a)(1). Task Order 10 pre-modification was a firm-fixed-
    price, level-of-effort, developmental contract. See FAR § 16.207-2; see also Tolliver Grp., 140
    Fed. Cl. at 526. Task Order 10 required cost analysis because none of the exceptions in FAR
    § 15.403-1(b) applied to the developmental nature of the technical manuals in the contract.
    Because cost analysis was required, the cost principles and procedures of FAR Part 31,
    specifically FAR Subpart 31.2, were applicable to the pre-modification contract. See FAR
    § 31.102. The government contends that such a holding would “upend the nature of the firm-
    fixed-price contract” and “undermine the intent of the parties in contracting, the nature of the
    contract type, and the purpose for which firm-fixed-price contracts are utilized in government
    contracting.” Def.’s Cross-Mot. at 16. This is incorrect. The FAR itself mandates the court’s
    holding, which is a reading of the FAR applied to Task Order 10—nothing more.
    2. Incorporation of FAR § 31.205-47 to Task Order 10
    The parties acknowledge directly or indirectly, as the court previously observed, that
    “neither an express nor implied term allowing cost reimbursement appears in the contract.”
    Tolliver Grp., 140 Fed. Cl. at 529. “For a court to incorporate a clause into a contract under the
    Christian doctrine, it generally must find (1) that the clause is mandatory; and (2) that it
    expresses a significant or deeply ingrained strand of public procurement policy.” K-Con, Inc. v.
    Sec’y of Army, 
    908 F.3d 719
    , 724 (Fed. Cir. 2018) (discussing Christian, 160 Ct. Cl. at 11-17).
    “In this case, cost principles apply by operation of law if the contract required a cost analysis
    [and] if reimbursement of legal fees claimed by Tolliver represents a significant or deeply
    ingrained aspect of a fixed-price, level-of-effort development contract.” Tolliver Grp., 140 Fed.
    Cl. at 529. As demonstrated supra, cost principles and procedures, specifically FAR § 31.205-
    47, were mandatory to pre-modification Task Order 10 because the government was required to
    conduct cost analysis as part of Tolliver’s level-of-effort contract. The question then is whether
    cost principles and procedures, specifically FAR § 31.205-47, are significant or deeply ingrained
    in public procurement policy. The court responds in the affirmative.
    Since its inception in 1983, the FAR has included, in one form or another, cost principles
    and procedures related to False Claims Act proceedings. See Establishing the Federal
    7
    Acquisition Regulation, 
    48 Fed. Reg. 42,102
    , 42,327 (Sep. 19, 1983) (to be codified at 
    48 C.F.R. § 31.205-47
    ); see also Brownlee v. Dyncorp., 
    349 F.3d 1343
    , 1349-51 (Fed. Cir. 2003)
    (discussing the regulatory history of FAR § 31.205-47 generally and its application to criminal
    convictions of fraud specifically). Decades of practice demonstrate the deeply ingrained nature
    of this regulation. See, e.g., S.J. Amoroso Const. Co., Inc. v. United States, 
    12 F.3d 1072
    , 1076
    (Fed. Cir. 1993) (observing that regulations implementing policies of the Buy American Act
    before and after the enactment of the FAR in 1983 had “reflected this significant, statutory policy
    for over 25 years”). Furthermore, FAR § 31.205-47 and its general coverage of False Claims
    Act costs have survived decades of legislation, persuasive evidence that “Congress . . . ha[s]
    approved the existing regulatory approach.” Brownlee, 
    349 F.3d at
    1354 (citing Young v. Cmty.
    Nutrition Inst., 
    476 U.S. 974
    , 983 (1986) (“[A] ‘congressional failure to revise or repeal the
    agency’s interpretation is persuasive evidence that the interpretation is the one intended by
    Congress.’” (quoting NLRB v. Bell Aerospace Co., 
    416 U.S. 267
    , 275 (1974))) and San Huan
    New Materials High Tech, Inc. v. Int’l Trade Comm’n, 
    161 F.3d 1347
    , 1355 (Fed. Cir. 1998)).
    In short, the court reads FAR § 31.205-47 into pre-modification Task Order 10 as a
    mandatory element—FAR Part 31’s cost principles and procedures are mandated by regulation
    because the Army was required to conduct cost analysis on Tolliver’s level-of-effort,
    developmental contract—and such principles are deeply ingrained in procurement policy as
    indicated by decades of their implementation in the regulatory framework of federal
    procurement.
    B. Reasonableness, Allocability, Accounting Standards, and Limitations in FAR Subpart 31.2
    Having ascertained that FAR Part 31’s cost principles and procedures apply to pre-
    modification Task Order 10 and that FAR § 31.205-47 should be read into the contract under the
    Christian doctrine, the court proceeds to the remaining allowability analysis factors outlined in
    FAR § 31.201-2(a).
    “A cost is reasonable if, in its nature and amount, it does not exceed that which would be
    incurred by a prudent person in the conduct of competitive business.” FAR § 31.201-3(a).
    Relying on Tolliver Group, Inc. v. United States, 
    149 Fed. Cl. 304
    , 305 (2020), Tolliver argues
    that its request for $195,889.78—representing 80% of its attorneys’ fees incurred in defending
    itself in the qui tam action—is “eminently reasonable” because its fees were well documented, in
    line with prevailing rates for the D.C. metro area, and supported by declarations by two
    knowledgeable, outside attorneys. See Pl.’s Mot. at 8-10. The government’s response is silent
    on the reasonableness of attorneys’ fees. In relevant part, the court has already ruled once in this
    case that Tolliver’s requested fees are reasonable for the reasons cited in Tolliver’s motion. See
    Tolliver Grp., 149 Fed. Cl. at 307-08 (citing Rumsey v. Dep’t of Justice, 
    866 F.3d 1375
    , 1379
    (Fed. Cir. 2017) (explaining that movant’s burden is “routinely satisf[ied]” by the “[s]ubmission
    of invoices and billing records”); Morris v. Sec’y of Dep’t of Health and Human Servs., 
    20 Cl. Ct. 14
    , 29 (1990) (explaining that the court may look to declarations made by other attorneys
    about the reasonableness of fees in a geographic area); and Lost Tree Village Corp. v. United
    States, 
    135 Fed. Cl. 92
    , 96 (2017) (“Fees incurred and paid by a client at an agreed rate are
    presumptively reasonable because in reaching agreement, lawyer and client have already
    considered and weighed all the relevant factors.”) (brackets and quotation marks omitted)). The
    8
    court incorporates its prior decision here and concludes that Tolliver’s requested fees are indeed
    reasonable.
    “A cost is allocable if it is assignable or chargeable to one or more cost objectives on the
    basis of relative benefits received or other equitable relationship.” FAR § 31.201-4; see also
    Boeing N. Am., Inc. v. Roche, 
    298 F.3d 1274
    , 1281 (Fed. Cir. 2002) (“[T]he concept of
    allocability is addressed to the question whether a sufficient ‘nexus’ exists between the cost and
    a government contract.” (citing Lockheed Aircraft Corp. v. United States, 
    179 Ct. Cl. 545
    , 558-
    60 (1967))). In particular,
    [a] cost is allocable to a [g]overnment contract if it (a) [i]s incurred specifically
    for the contract; (b) [b]enefits both the contract and other work, and can be
    distributed to them in reasonable proportion to the benefits received; or (c) [i]s
    necessary to the overall operation of the business, although a direct relationship to
    any particular cost objective cannot be shown.
    FAR § 31.201-4 (emphasis added). Tolliver asserts that its attorneys’ fees are allocable to Task
    Order 10 because, but for the government’s direction to proceed without the government
    furnished information required under the Performance Work Statement, there would have been
    no qui tam suit against which to defend itself. Pl.’s Mot. at 6, 16-17. Moreover, plaintiff argues
    that it was essential to the continued operation of its business to avoid incurring a claimed multi-
    million-dollar judgment in the qui tam action. See Pl.’s Reply and Resp. at 4. The government
    argues that Tolliver fails to demonstrate how it satisfies any of the requirements of FAR §
    31.201-4, but it erroneously presents those requirements in the conjunctive instead of the
    disjunctive. See Def.’s Cross-Mot. at 20-21. Instead, Tolliver need only satisfy one of those
    criteria to prove allocability. Here, there is no genuine dispute that it incurred its legal fees
    “specifically for the contract” and to preserve “the overall operation of [its] business.” But for
    the Army’s direction to proceed without the technical data package, Tolliver would not have
    been open to the qui tam suit that risked a large monetary judgment. The fees are therefore
    allocable to Task Order 10. See Lockheed, 179 Ct. Cl. at 558 (“[I]t is fair to allocate to
    government contracts the costs of services which . . . are essential to the existence and
    continuance of the business entity.”).
    “The Cost Accounting Standards [(“CAS”)] . . . are designed to achieve ‘uniformity and
    consistency’ in allocating costs to government contracts.” Boeing, 
    298 F.3d at 1283
     (quoting
    Rice v. Martin Marietta Corp., 
    13 F.3d 1563
    , 1565 (Fed. Cir. 1993)). Tolliver cites to CAS
    § 9904.406-50 and § 9905.506-60(b) to argue that its attorneys’ fees may properly be allocated
    to the period they benefit—the pre-modification period of performance—instead of the period in
    which they were incurred—the post-modification period of performance. Pl.’s Mot. at 6-7. The
    government’s response is silent on the question of accounting standards. The court has not
    identified any accounting principles or standards relevant to Task Order 10 that would prohibit
    reimbursement of attorneys’ fees incurred in the qui tam litigation over Tolliver’s pre-
    modification performance.
    FAR § 31.205-47 limits the allowability of legal costs. See Tolliver Grp., 140 Fed. Cl. at
    529. “Costs incurred in connection with any proceeding brought by . . . a third party in the name
    9
    of the United States under the False Claims Act” in which the contractor successfully defends
    itself, FAR § 31.205-47(b), “may be allowable to the extent that” the costs are reasonable, are
    not otherwise recovered from the government or a third party, are appropriate, and do not exceed
    80% of the fees incurred, FAR § 31.205-47(e). As discussed immediately above, Tolliver’s fees
    of $195,889.78 represent 80% of its total litigation costs and were “eminently reasonable.”
    Tolliver Grp., 149 Fed. Cl. at 305. Because Tolliver incurred these fees in a qui tam suit that
    resulted from the government’s direction to proceed under Task Order 10 without the requisite
    technical data package, it is appropriate for the government to reimburse them. Neither party has
    argued or produced any evidence that Tolliver has recovered these fees from another source.
    The court therefore concludes that they are consistent with the relevant limitations on
    allowability in FAR Subpart 31.2.
    CONCLUSION
    The court holds that, as a matter of law, Tolliver is entitled to recover 80% of its
    attorneys’ fees incurred in defending itself in the qui tam suit under the terms of pre-modification
    Task Order 10. There is no genuine dispute that Task Order 10 issued as a firm-fixed-price,
    level-of-effort development contract that, per the FAR, required the government to conduct cost
    analysis and therefore incorporated the mandatory and deeply ingrained cost principles and
    procedures in FAR Part 31. Based on these determinations, the court GRANTS Tolliver’s
    motion for summary judgment and DENIES the government’s cross-motion for summary
    judgment. The court awards Tolliver $195,899.78 in attorneys’ fees related to the qui tam suit.
    The clerk is directed to enter judgment in accord with this disposition.
    It is so ORDERED.
    s/ Charles F. Lettow
    Charles F. Lettow
    Senior Judge
    10