Seneca Sawmill Company v. United States ( 2022 )


Menu:
  •              In the United States Court of Federal Claims
    )
    SENECA SAWMILL COMPANY,                          )
    )
    Plaintiff,                 )
    )            No. 16-1001C
    v.                                        )            (Filed: August 19, 2022)
    )
    THE UNITED STATES OF AMERICA,                    )
    )
    Defendant.                 )
    )
    )
    )
    Michael E. Haglund and Julie E. Weis, Haglund Kelley LLP, Portland, OR, for Plaintiff.
    Daniel B. Volk, Senior Trial Counsel, and Jimmy S. McBirney, Trial Attorney, Commercial
    Litigation Branch, Civil Division, U.S. Department of Justice, Washington, DC, for Defendant,
    with whom were Elizabeth M. Hosford, Assistant Director, Patricia M. McCarthy, Director, and
    Brian M. Boynton, Acting Assistant Attorney General. Benjamin Hartman, Office of the General
    Counsel, U.S. Department of Agriculture, Portland, OR, Of Counsel, for Defendant.
    OPINION AND ORDER
    KAPLAN, Chief Judge.
    This case arises out of a decision by the United States Forest Service (“Forest Service”)
    to partially terminate a timber sale contract it entered with Plaintiff, Seneca Sawmill Company
    (“Seneca”). The termination was effected on the basis of a “supplemental environmental
    assessment” the Forest Service conducted at the direction of the United States District Court for
    the District of Oregon in Cascadia Wildlands v. U.S. Forest Serv., 
    791 F. Supp. 2d 979
     (D. Or.
    2011).
    A contracting officer rejected Seneca’s claim that the Forest Service breached the
    contract when it notified Seneca that it would not be permitted to harvest all of the acreage
    subject to sale under the contract. He concluded that the contract contemplated suspensions and
    partial terminations of timber harvesting based on a variety of causes, including intervening
    litigation. Therefore, he found, Seneca could not recover damages for breach of contract, and
    was limited to the compensation the contract provided. The Chief of the Forest Service
    determined that Seneca was only entitled to recover its out-of-pocket expenses under the contract
    because, he concluded, the partial termination was necessary to comply with a court order as
    provided in the contract.
    After the Court granted in part and denied in part the government’s motion for summary
    judgment, see Seneca Sawmill Co. v. United States (Seneca I), 
    149 Fed. Cl. 83
     (2020), a trial
    was held on Seneca’s breach-of-contract claim in November 2021 in Eugene, Oregon. The
    purpose of the trial was to determine, first, whether the provision of the contract upon which the
    Forest Service relied, concerning terminations to comply with a court order, covered the partial
    termination of the timber sale contract. The Court concludes for the reasons set forth below that
    the Forest Service’s invocation of that provision as grounds for partially terminating the contract
    was improper.
    Notwithstanding that conclusion, the parties stipulated at the pre-trial conference that—
    even if the Forest Service’s reliance on the provision addressing terminations to comply with a
    court order was improper—the agency could have invoked another provision that allows
    termination where continuation of the contract would cause certain environmental injuries or
    other adverse effects. In light of that stipulation, the government can rely on the constructive
    termination doctrine to avoid liability for breach of contract. Therefore, the primary issue before
    the Court, and the focus of most of the testimony at the trial, was what additional compensation,
    if any, would have been due Seneca had the Forest Service proceeded under that alternative
    provision. A subsidiary issue concerns whether Seneca has yet been fully compensated for its
    out-of-pocket expenses.
    The Court has carefully considered the evidence before it and concludes, for the reasons
    set forth herein, that Seneca has failed to show that—using the measure of compensation set
    forth in the contract—it is entitled to additional relief. It has also failed to establish its
    entitlement to additional reimbursement for out-of-pocket expenses. The Court therefore enters
    judgment in favor of the government.
    FINDINGS OF FACT 1
    Seneca Sawmill Company
    Seneca is the largest lumber producer in Oregon, and one of the largest in the United
    States. Trial Tr. (“Tr.”) vol. 1, 33:11–16. It manufactures commodity-type lumber products that
    are used in construction projects, chiefly in single- and multi-family homes. 
    Id.
     13:18–23, 29:5–
    9. Seneca operates three sawmills in Eugene, Oregon, id. 25:24; see also Pl.’s Post-Trial Br.
    (“Pl.’s Br.”) at 3, ECF No. 102, and produces more than five-hundred million board feet of
    lumber per year, Tr. vol. 1, 33:6–10.
    Seneca purchases approximately twenty percent of the timber it processes from the Forest
    Service, the United States Bureau of Land Management, and the Oregon Department of Forestry.
    Id. 40:20–24. The rest of the timber is sourced from its own land, id. 40:7–19, or is purchased on
    the “open market . . . from other private timber landowners,” id. 40:23–25.
    1
    This section sets forth the Court’s principal findings of fact pursuant to Rule 52(a) of the Rules
    of the Court of Federal Claims (“RCFC”). Other findings of fact and rulings on questions of
    mixed fact and law are set out in the Discussion section.
    2
    The majority of the timber that passes through Seneca’s mills—whether harvested from
    its own land or purchased—consists of “second-growth” logs, which are sourced from relatively
    young trees. Id. 25:3–4, 25:12–16, 28:10–19, 32:2–16, 44:19–45:3, 49:2–5, 204:23–205:4; Pl.’s
    Br. at 3–4. Such logs have visible, “coarse” growth rings, “representati[ve] of a second-growth
    log that has grown relatively quickly out in the forest.” Tr. vol. 1, 31:4–8.
    Seneca also occasionally harvests or purchases timber from older, larger trees, which
    supply logs of a “much higher quality than [it] normally see[s] in the [commodity] marketplace.”
    Id. 42:1–8; see also id. 41:21–43:18, 48:9–17, 49:12–18; Pl.’s Br. at 4. These
    “higher-and-better-use” logs are distinguishable by their “fine grain ring count,” Tr. vol. 1, 42:2–
    4, and “clear grain”—that is, by a lack of “knot characteristics” throughout the wood, id. 42:21–
    23.
    Seneca earns a greater profit when it sells high-grade logs to specialty cutting mills than
    it would if it processed the logs into commodity products in its own facilities, because specialty
    mills place a premium on the aesthetic value of older logs with a higher ring count. Id. 41:21–
    43:18 (discussing the “fine grain ring count [of] . . . higher-and-better-use logs” which lack “the
    knot depictions that you would find in the typical commodity products [Seneca] make[s]”); id.
    49:12–18 (Seneca CEO agreeing that, “from a financial standpoint, [it is] important to segregate
    those logs and resell them as opposed to mill them [at Seneca],” and explaining that “[t]he value
    [Seneca] receive[s] by selling them is higher than the value we receive if we were to produce it
    in just the commodity products we make”); see also Pl.’s Br. at 4. 2
    Where the percentage of high-grade logs in a timber sale is relatively small, Seneca
    brings all of the timber harvested to its complex in Eugene, where the high-grade logs are culled
    out for sale to specialty cutting mills. Tr. vol. 1, 48:2–17; see also id. 41:21–43:18, 49:12–18; id.
    92:5–9 (“If a log comes into our yard that has the higher-and-better-use characteristic, it gets set
    aside and sold.”); Pl.’s Br. at 4. If Seneca expects a high yield of “higher-and-better-use” logs, on
    the other hand, it sends the logs directly from the harvest site to a specialty cutting mill. Tr. vol.
    1, 47:6–48:1.
    The Trapper Timber Sale
    The timber sale contract at issue in this case was the product of a forest management
    effort dubbed “the Trapper Project.” Joint Ex. (“JX”) 2 at 8–9, 13. The background of the
    Trapper Project is set forth in detail in the Court’s Opinion and Order of July 2, 2020, granting in
    part and denying in part the government’s motion for summary judgment. See Seneca I, 149 Fed.
    Cl. at 87–94.
    2
    At trial, Seneca’s CEO explained that the decision whether to process timber into commodity
    logs or sell them to a specialty cutting mill depends on “what the market is for special mills at
    that time and what the value of lumber is at that time.” Tr. vol. 1, 92:15–19. Accordingly, he
    explained, part of that determination depends on what price a specialty cutting mill offers to
    Seneca when it advertises logs of a given grade and, often, from a specific stand of timber. Id.
    92:20–93:7, 102:12–16.
    3
    To recapitulate, the Forest Service initiated the Trapper Project in 1998. JX 2 at 15. Its
    goal was to study the effects of forest fires by permitting selective timber harvesting in the
    project area that would replicate the effects of fire on the landscape. See id. at 9, 12; see also JX
    3 at 3.
    Before it conducted the sale at issue in this case, the Forest Service secured a Biological
    Opinion from the United States Fish and Wildlife Service (“FWS”) to determine whether and to
    what extent the Project would impact the northern spotted owl, an endangered species. See JX 2
    at 15, 70, 75, 121–24, 129–34. That Opinion, issued in September 1998, included a finding that
    the Trapper timber sale, among others, was “not likely to jeopardize the continued existence of
    the spotted owl or result in the destruction or adverse modification of spotted owl critical
    habitat.” Id. at 70; see also id. at 134.
    The Forest Service then conducted an environmental assessment (“EA”) of the project
    pursuant to the National Environmental Policy Act of 1969 (“NEPA”), 
    42 U.S.C. §§ 4321
    –70.
    See JX 2 (March 2003 environmental assessment, hereinafter “2003 EA”). In May 2003, it
    issued a Decision Notice and Finding of No Significant Impact (“FONSI”) for the Trapper
    Project. JX 3 (“2003 FONSI”). Relying on the FWS Biological Opinion, the Forest Service
    concluded that the Trapper Project “may affect” but was “not likely to adversely affect” the
    northern spotted owl. Id. at 16.
    In anticipation of the sale, the Forest Service conducted a timber cruise of the Trapper
    area on November 20, 2002. JX 1 (Forest Service Cruise Report). 3 Based on the cruise, the
    Forest Service prepared a prospectus estimating that the sale area would yield a volume of
    12,605 hundred cubic feet (centum cubic feet (“CCF”)) or 8,345 thousand board feet (“MBF”) of
    timber. JX 5 at 2; see also Tr. vol. 1, 118:23–119:3, 236:3–7; Tr. vol. 2, 382:11–13. 4
    The Forest Service conducted an auction in connection with the sale on October
    14, 2003. JX 5 at 1. Seneca bid $117.25 per CCF, JX 8 at 1, and the Forest Service
    awarded it the timber sale contract on October 23, 2003, JX 9; see also JX 10 (Trapper
    Timber Sale Contract No. 000533, hereinafter “Trapper sale contract,” “Trapper sale,” or
    “contract”).
    3
    As Scott Keep, Seneca’s director of wood procurement, explained at trial, a timber “cruise” is a
    survey of a harvest site in which trees are sampled and measured in an effort to assess the
    volume and grade of the harvestable timber. Tr. vol. 1, 80:10–13; see also id. 81:13–15
    (explaining that cruisers “[m]easure every tree in that plot for height, diameter, and then assess
    each log segment [for] grade and potential defect”); id. 153:8–22; Tr. vol. 2, 332:23–333:2
    (explaining that a cruise is “[a] very intense survey of the timber” which is aimed at determining
    volume).
    4
    CCF is the measure of volume the Forest Service employs. See JX 4 at 1. The parties agree that
    0.662 is the proper multiplier to use when converting CCF to express the volume in MBF. See
    Pl.’s Br. at 10–11; Def.’s Post-Trial Resp. Br. at 37 n.15, ECF No. 105; see also JX 96 at 3
    (providing conversion factors for timber sales); JX 4 at 1 (Forest Service appraisal).
    4
    Intervening Litigation and Opposition to the Trapper Project
    The Trapper sale contract designated 149 acres in the Willamette National Forest
    from which Seneca could harvest timber. JX 12 at 3; JX 2 at 22. That timber consisted
    primarily of mature Douglas fir trees that were an average of 140 years old. JX 2 at 46;
    JX 5 at 1.
    Seneca began building roads and preparing to harvest the timber in 2004. JX 84 at
    2. But before it began logging operations, litigation arose that ultimately resulted in the
    invalidation of both the 1998 FWS Biological Opinion described above and a subsequent
    2005 Opinion. See JX 14 at 1–2, 22–23; JX 33; JX 32; see also Gifford Pinchot Task
    Force v. U.S. Fish and Wildlife Serv., 
    378 F.3d 1059
     (9th Cir. 2004) (invalidating
    September 1998 FWS Biological Opinion); Or. Nat. Res. Council v. Allan, 
    476 F.3d 1031
     (9th Cir. 2007) (holding invalid 2005 FWS Biological Opinion that various timber
    sales (including Trapper) were not likely to jeopardize the continued existence of the
    northern spotted owl or result in the destruction or adverse modification of critical
    habitat).
    As a result of litigation, logging operations were twice suspended between 2004
    and 2010. JX 84 at 11 (noting that operations were suspended due to environmental
    litigation from March 11, 2005, to August 16, 2005, and again from June 28, 2007, to
    September 7, 2007); see also JX 14 at 1–2 (discussing 2005 suspension); JX 16
    (discussing Gifford Pinchot Task Force, 
    378 F.3d 1059
    ); JX 17 (lifting 2005 suspension).
    In addition, environmental groups continued to lobby the Forest Service to cancel the
    sale, arguing the presence of red tree voles (which had not been recorded during the
    original surveys) justified a new environmental analysis. JX 19 at 1 (Letter from Cascadia
    Wildlands); see also JX 28 at 1–3, 5 (Forest Service Memorandum describing litigation
    challenging sale). The Forest Service rejected these requests. JX 18 at 1; see also JX 20 at
    2 (Letter from Forest Service stating that, as of 2007, “no new or additional NEPA
    analysis is being considered”).
    In 2007, as noted, the Ninth Circuit invalidated the 2005 FWS Biological Opinion
    the Forest Service had relied upon to establish its compliance with section 7 of the
    Endangered Species Act in connection with the Trapper sale and other projects. JX 21 at
    9; see also JX 28 at 4 (citing Or. Nat. Res. Council, 
    476 F.3d 1031
    ). At the Forest
    Service’s request, FWS then provided a third Biological Opinion. In the updated Opinion,
    FWS again opined “that the implementation of [the Trapper] project at the anticipated
    levels would not jeopardize the continued existence of the spotted owl, nor would the
    project adversely modify spotted owl critical habitat.” JX 21 at 1 (September 6, 2007
    FWS Biological Opinion).
    In the meantime, opposition to the Trapper Project continued to grow. See, e.g.,
    JX 19 at 1 (Letter from Cascadia Wildlands); JX 28 at 5 (Forest Service memorandum
    describing litigation challenging sale); JX 18 (Forest Service emails describing growing
    opposition to the sale). In May 2010, three scientists who had been involved with the
    Blue River Landscape Strategy submitted comments on the Trapper Project via a letter to
    5
    the Willamette National Forest Supervisor. See JX 27; see also JX 2 at 8–12 (discussing
    Blue River Landscape Strategy in the Willamette National Forest). In it, they argued that,
    given the passage of time, the “value of anticipated lessons from going forward with
    logging of the Trapper Timber Sale is very low relative to what was anticipated when the
    sale and associated monitoring plans were developed in the 1990s.” JX 27 (concluding
    that they “d[id] not oppose efforts to drop the Trapper Timber Sale”).
    A few months later, in July 2010, Seneca informed the Forest Service that it
    intended to begin logging operations the following month. JX 84 at 5. The parties held a
    pre-work meeting on July 26. JX 28 at 1. That meeting prompted the Forest Service to
    review information it had received since 2003 regarding the presence of red tree vole
    nests and spotted owls in the harvest area. See 
    id.
    The review was documented in a July 28, 2010 letter from Forest Wildlife
    Biologist Joe Doerr to Forest Supervisor Meg Mitchell. See JX 28 at 1. Mr. Doerr noted
    that, as mentioned above, red tree vole nests had been reported within the Trapper sale
    area in the years since the preparation of the 2003 EA. Id. at 2. He explained, however,
    that under the standards and guidelines in effect when the 2003 EA was completed, the
    Forest Service had no obligation to conduct additional surveys or take any additional
    action. Id.
    But Mr. Doerr also observed that, on July 27, 2010, an additional pair of northern
    spotted owls had just been found within the Trapper Project area. Id. at 5. He advised that
    the Forest Service “should consider this information and decide whether or not to
    reinitiate consultation [with FWS],” id. at 7, which the Forest Service did that day, JX 30.
    On July 29, 2010, the Forest Service suspended operations on the Trapper sale
    contract pending that consultation to “determine what, if any, additional protective
    measures will be required on the sale.” JX 31 (citing contract provision BT6.25); JX 10 at
    30 (BT6.25 (Protection of Threatened, Endangered, and Sensitive Species) providing
    that, “if new species are listed on the Endangered Species List or the Regional Forester’s
    sensitive . . . species list,” “operations will be suspended at that location until the
    significance or potential significance of the area is determined”).
    On August 30, 2010, FWS issued its fourth Biological Opinion, which was
    entitled “Biological Assessment for Reinitiation of Consultation for the Northern Spotted
    Owl.” JX 34 (August 2010 Biological Opinion). In that Opinion, the FWS stated that “the
    removal of suitable habitat in the Trapper project may affect and is likely to adversely
    affect [the] northern spotted owl pair [previously identified by the Forest Service].” Id. at
    25–26. It concluded, however, that “the proposed action,” i.e., the timber harvest,
    “compl[ies] with the Record of Decision and the Standards and Guidelines of the
    Northwest Forest Plan . . . and the Land and Resource Management Plan of the
    Willamette National Forest.” Id. at 8.
    Thereafter, Forest Wildlife Biologist Joe Doerr conducted a supplemental
    information review. See JX 35 (December 14, 2010 letter from the Willamette National
    6
    Forest Supervisor to the Regional Forester, quoting results of the review). In the review,
    Mr. Doerr referenced a December 10, 2010 FWS Opinion (which does not appear to be in
    the record), and opined that the Opinion did not contain information that “significantly
    change[d] the effects on [the northern spotted owl] from that considered in the original
    2003 Trapper Environmental Assessment, Decision Notice, and Endangered Species Act
    Consultation for the project.” Id. at 1–2. The Forest Supervisor therefore advised the
    Regional Forester that “[b]ecause the project has not changed and the estimated effects to
    owls and red tree voles based on the 2010 analysis are of the same magnitude as
    determined in the original project analysis . . . no additional NEPA analysis is needed for
    the Trapper Timber harvest treatments with respect [to] the effects on wildlife.” Id. at 4.
    The Cascadia Litigation
    A.      The Cascadia Plaintiffs’ Claims
    In the meantime, in October 2010, two environmental advocacy groups brought suit
    against the Forest Service in the United States District Court for the District of Oregon. See
    Cascadia Wildlands, 
    791 F. Supp. 2d 979
    . They sought to enjoin the Trapper sale, contending
    that the Forest Service had failed to comply with NEPA when it authorized the sale in 2003. 
    Id.
    at 984–86; see also Compl. for Decl. and Inj. Relief, ¶¶ 1–4, 45–46, 57, Cascadia Wildlands, 
    791 F. Supp. 2d 979
     (No. 10-6337), ECF No. 1. The Cascadia plaintiffs contended that—before
    going ahead with the sale—the agency had an obligation to conduct a supplemental EA in
    response to the new information concerning the northern spotted owl and the red tree vole nests.
    Id. ¶¶ 4, 55, 57, 60, 62. They also relied upon the Forest Service’s acknowledgement during the
    litigation that the statement in the 2003 EA that the Trapper sale was “not likely to adversely
    affect” the northern spotted owl was wrong. Pls.’ Opening Mem. in Supp. of Mot. for Summ. J.
    at 18–19, Cascadia Wildlands, 
    791 F. Supp. 2d 979
     (No. 10-6337), ECF No. 19.
    B.      The District Court’s Decision
    The district court agreed with the plaintiffs and rejected arguments to the contrary offered
    by the Forest Service (as well as by Seneca as intervenor). See Cascadia Wildlands, 
    791 F. Supp. 2d at 994
    . It found that the “not likely to adversely affect” finding with respect to the spotted owl
    in the 2003 EA, which the government had acknowledged was in error, was “a cornerstone of the
    Trapper Project decision.” 
    Id.
     at 988–90. Therefore, it could not “be disregarded when
    considering whether subsequent information regarding adverse impacts on the species is
    significant or new.” 
    Id. at 988
    . It concluded that the Forest Service’s 2010 recognition of its
    earlier error constituted “new and significant information,” and that its “failure to prepare a
    supplemental EA (or [environmental impact statement]) was an abuse of discretion.” 
    Id. at 991
    .
    The district court further observed that the Trapper Project had been “designed as a
    learning/research project.” 
    Id. at 993
    . Therefore, it held, the 2010 letter from the Blue River
    Landscape Strategy scientists also constituted “new information” that “call[ed] into question the
    learning value of the project” and that “should be evaluated as part of a supplemental EA.” 
    Id.
     at
    991–93.
    7
    C.      The Injunction and Seneca’s Motion for Clarification
    The district court enjoined the Trapper sale on May 24, 2011, “pending the [Forest
    Service]’s preparation of a supplemental EA addressing the new information regarding the
    Northern Spotted owl and learning value of the [Trapper] project and a supplemental Decision
    Notice.” 
    Id. at 994
    . In response, on June 2, 2011, the Forest Service suspended operations on the
    contract pursuant to BT6.02(a)(ii). JX 42. That provision gives the Forest Service the authority to
    suspend or delay operations, in whole or in part, in order “[t]o comply with a court order”
    (among other reasons). JX 10 at 28 (BT6.02 “Interruption or Delay of Operations”).
    On June 20, 2011, representatives from Seneca met with the Willamette National Forest
    Supervisor and contracting officer (“CO”) to discuss the agency’s timeline and required steps for
    preparing the supplemental EA. JX 43. As reflected in an email the Forest Supervisor sent that
    day, Seneca and the Forest Service did not share a common understanding about how the Forest
    Service could comply with the district court’s decision. 
    Id.
     In the Forest Service’s view, it was
    obligated to “updat[e] the surveys [to] meet[] today’s NEPA analysis standards” and “bring the
    EA and corresponding decision up to today’s standards.” 
    Id.
     On the other hand, according to the
    Forest Supervisor, Seneca expected only “a quick fix of the two things the [district court] asked
    [the Forest Service] to correct.” 
    Id.
    On July 19, 2011, Seneca filed a motion for clarification of the district court’s Order.
    Def.-Intervenor’s Mot. for Clarification, Cascadia Wildlands, 
    791 F. Supp. 2d 979
     (No.
    10-6337), ECF No. 43. It asked the district court to “clarify” that its injunction: (1) “does not
    require the Forest Service’s supplemental NEPA analysis to start from scratch on issues either
    not found deficient by the Court or not challenged by plaintiffs”; and (2) “was not intended to
    predetermine the outcome of the supplemental NEPA process by requiring a new decision on all
    issues as if Trapper were a new Project.” Def.-Intervenor’s Mem. in Supp. of Mot. for
    Clarification at 1, Cascadia Wildlands, 
    791 F. Supp. 2d 979
     (No. 10-6337), ECF No. 44.
    Seneca argued that clarification was warranted because “the law recognizes that in some
    situations a decision need not be revisited after NEPA supplementation.” Def.-Intervenor’s Mot.
    for Clarification at 3, Cascadia Wildlands, 
    791 F. Supp. 2d 979
     (No. 10-6337), ECF No. 43.
    Seneca urged the district court to state definitively that the Forest Service would be in
    compliance with its injunction if it issued a supplemental EA that only addressed the new
    information concerning the northern spotted owl and learning value of the Project. See 
    id.
     at 2–4.
    It also asked the court to confirm that its order did not require the Forest Service to issue a new
    Decision Notice. See id. at 3.
    D.      The District’s Court’s Denial of Seneca’s Motion for Clarification
    The government took no position on Seneca’s motion for clarification. Id. at 2. The
    Cascadia plaintiffs, however, opposed it, see Pls.’ Resp. to Intervenor’s Mot. for Clarification,
    Cascadia Wildlands, 
    791 F. Supp. 2d 979
     (No. 10-6337), ECF No. 47, and, on October 4, 2011,
    the district court largely denied it, see Order, Cascadia Wildlands, 
    791 F. Supp. 2d 979
     (No.
    10-6337), ECF No. 57.
    8
    The district court observed that, given that the Forest Service did not join Seneca’s
    Motion, granting it “would require [the court] to speculate about whether and what aspects of [its
    injunction] may need clarification.” Id. at 2. The district court also expressed reluctance to
    clarify its order as Seneca requested, because such a clarification “might be construed as limiting
    the broad discretion the Forest Service has in determining the scope of a supplemental EA.” Id.
    at 2–3. Though it agreed with Seneca that the injunction “does not predetermine the results of the
    Forest Service’s analysis,” id. at 4, it also observed that leaving the original Decision Notice
    unchanged “d[id] not appear to be a viable option” for the Forest Service, in light of the fact that
    the original Decision Notice and FONSI were based on the erroneous “not likely to adversely
    affect” finding, id. at 3 n.1. Instead, the district court made clear, the Forest Service, “[u]pon
    completion of the supplemented or revised EA,” would be obligated to “prepare a new [FONSI]
    which addresses the effects of the action,” “[r]econsider the original decision,” and “issue a new
    decision notice.” Id. at 3 (quoting Forest Service Handbook 1909.15 (National Environmental
    Policy Act Handbook), Chapter 10 (Environmental Analysis), § 18.4 (Correction,
    Supplementation, or Revision of Environmental Documents and Reconsideration of Decisions to
    Take Action)).
    E.      The Supplemental Environmental Assessment
    On January 5, 2012, Seneca met with representatives from the Forest Service to discuss
    the updated surveys the agency intended to conduct in connection with the supplemental EA. JX
    47 (CO’s meeting notes). At that meeting, the Forest Service advised Seneca that, “due to the
    amount of Red Tree Vole Nests and sensitive mollusks found throughout the sale area,” and, in
    light of the district court’s instruction “to redo the NEPA document and Decision Notice for the
    sale,” the Forest Service anticipated modifications that would reduce the available volume of
    timber for harvesting by approximately two-thirds. Id.
    A year later, on February 11, 2013, the Forest Service issued a notice to the public
    announcing its intent to prepare a revised EA for the Trapper Project. JX 50 at 1. The notice
    explained that, pursuant to the district court’s injunction, the agency planned to prepare a
    “supplemental EA [to] address new information regarding the northern spotted owl [and] address
    the ‘value of learning.’” Id. In addition, the Forest Service stated, it planned to “bring the 2003
    [EA] up to date with current policy and direction.” Id.
    A February 14, 2013 letter to the interdisciplinary team responsible for preparing the
    supplemental EA similarly reflects the Forest Service’s decision to go beyond revisiting the
    impact of the Project on the spotted owl and its learning value. See generally JX 51. McKenzie
    River District Ranger Terry Baker directed that he “expect[ed] the [EA] to meet current NEPA
    requirements, address changed conditions surrounding the Revised Trapper Project (such as the
    Critical Habitat Rule), address instructions from the May 2011 [injunction], and bring the 2003
    [EA] up to date with current policy and direction.” JX 51 at 3; see also id. at 5 (outlining the EA
    revision process, to include: (1) “Analysis to address court order (owl and science)”; and (2)
    “Analysis to meet current NEPA requirements, including changed conditions”); JX 54 at 1 (April
    29, 2013 Trapper Project Interdisciplinary Meeting outlining a “Review of Work that Needs to
    be Done”: (1) “Analysis to address court order (owl and science)”; and (2) “Analysis to meet
    current NEPA requirements, including changed conditions”).
    9
    On April 8, 2013, the Forest Service issued a report entitled “A Supplemental Biological
    Assessment on the Effects of the Trapper Timber Sale of Willamette National Forest on 2012
    Northern Spotted Owl Critical Habitat.” JX 55 (April 2013 Biological Assessment). The April
    2013 Biological Assessment, like the August 2010 Biological Opinion, “determine[ed] that the
    Trapper Timber Sale Project may affect and is likely to adversely affect 2012 spotted owl critical
    habitat.” Id. at 24.
    The Forest Service issued a revised EA in May 2014. JX 59 (“Revised Trapper Project
    Environmental Assessment,” hereinafter “2014 EA” or “revised EA”). It explained that it had
    endeavored “to revise the 2003 environmental analysis and decision for the Trapper Project as
    directed by [the district court’s injunction],” and to “address new information regarding the
    northern spotted owl, address the learning value of the project, and bring the 2003 environmental
    analysis up to date with current policy and direction.” Id. at 7. The agency noted that “[s]pecific
    points of the [injunction]” were addressed, including: “(1) disclosure of new information that
    could influence effects to the northern spotted owl, and (2) the learning value of the project.” Id.
    at 8; see also JX 61 at 1 (stating the same).
    On July 12, 2014, the Forest Service issued a revised Decision Notice and FONSI. JX 61
    (“Decision Notice and Finding of No Significant Impact for the Revised Trapper Project”).
    Based on the information outlined in the revised EA and supporting documents, the Forest
    Service announced, it intended to reduce the size of the Trapper sale down to thirty-three acres.
    Id. at 2. “In addition to meeting [its] contractual obligations” in preparing the supplemental EA
    and issuing the revised Decision Notice, the Forest Service explained, it had conducted the
    “court[-]ordered analysis,” “updat[ed] the EA to meet current standards,” and “addresse[d] the
    original intent of the 2003 Trapper Project purpose and need.” Id. at 13.
    The Forest Service explained that it had removed approximately six acres from the sale to
    protect northern spotted owl habitat. JX 58. It removed an additional eighteen acres to protect the
    Cascade axetail slug, id., which “ha[d] been identified as a new sensitive species since 2003,” JX
    59 at 9. Another eighteen acres were removed because they could not “be justified as benefiting
    from [logging] treatment” or because removal was necessary to protect riparian reserve areas and
    a survey-and-manage fungus. JX 58.
    The Forest Service removed the majority of the harvestable acreage from the Trapper
    sale—nearly eighty acres—to carve out protective buffers for red tree vole nests. Id. Surveys for
    red tree voles conducted in the years since the sale to Seneca had identified twenty-three active
    nests for which buffers were required under the Northwest Forest Plan’s 2001 standards and
    guidelines for survey-and-manage species. JX 59 at 9, 39.
    F.      Dissolution of the District Court Injunction
    On August 12, 2014, the Cascadia plaintiffs and the government jointly filed a stipulated
    motion requesting dissolution of the district court’s May 2011 injunction. See Stip. Mot. to
    Dissolve Inj., Cascadia Wildlands, 
    791 F. Supp. 2d 979
     (No. 10-6337), ECF No. 71.
    10
    The parties represented to the district court that the “Forest Service ha[d] completed a
    revised EA to address [its] injunction, and on July 12, 2014, the agency issued a Decision Notice
    authorizing a revised Trapper project,” which it “plan[ned] to implement . . . in the near future.”
    Id. at 2. The district court granted the motion and dissolved the injunction the following day. See
    Order, Cascadia Wildlands, 
    791 F. Supp. 2d 979
     (No. 10-6337), ECF No. 73.
    Settlement Discussions Regarding Partial Termination
    In the meantime, on July 30, 2014, Contracting Officer Justin Burkey notified Seneca that
    the revised Decision Notice had been issued, and that the Forest Service “ha[d] started the
    required fieldwork to implement . . . the decision.” JX 62. Because the Forest Service anticipated
    “completing the fieldwork by October 2014,” he continued, the agency sought a September
    meeting with Seneca “to review the changes under the Revised Trapper decision” and “discuss
    the modification of the sale and the changed conditions and requirements as it pertains to the
    contract.” 
    Id.
    It is unclear from the record whether a meeting was held with Seneca in September. At
    the end of the month, however, on September 30, 2014, the Regional Forester requested that the
    Chief of the Forest Service exercise his authority to “partially terminate the Trapper timber sale
    pursuant to contract provision CT8.24.” JX 69 at 1. That provision states that the Chief of the
    Forest Service may, “by written notice . . . terminate this contract, in whole or in part,” for any of
    the following reasons:
    (a) To comply with a court order, regardless of whether this timber sale is named
    in such an order, upon determination that the order would be applicable to the
    conditions existing on this timber sale or
    (b) Upon a determination by the Chief that the continuation of all or part of the
    contract would:
    (i) Cause serious environmental degradation or resource damage;
    (ii) Be significantly inconsistent with land management plans adopted or
    revised in accordance with Section 6 of the Forest and Rangeland
    Renewable Resources Planning Act of 1974, as amended;
    (iii) Cause serious damage to cultural resources pursuant to BT6.24;
    (iv) Cause serious damage to cave resources pursuant to BT6.26; or
    (v) Adversely affect species listed as threatened or endangered under the
    Endangered Species Act, 16 USC 1531, et seq., or a sensitive specifies
    identified by the Regional Forester pursuant to BT6.25.
    JX 10 at 108 (hereinafter “provision CT8.24” or “CT8.24”).
    The district court’s injunction, the Regional Forester noted, “required the Forest Service
    to incorporate updated northern spotted owl information and address the ‘learning value’ that
    was part of the rationale for the [Trapper] project.” JX 69 at 2. The culmination of that effort, he
    observed, was the supplemental 2014 EA and revised Decision Notice, the implementation of
    which would result in the removal of acreage “impacted by northern spotted owls (threatened)
    and axtail slugs (sensitive).” Id. at 3. Also to be removed was acreage needed to protect red tree
    11
    vole nests, “riparian areas, and portions that are infeasible to log based on the new unit
    configuration.” Id.
    The Regional Forester proposed that twenty-four acres be deleted from the contract
    pursuant to CT8.24(b)(v), id., i.e., the threatened, endangered, or sensitive species provision, JX
    10 at 108. He also requested that ninety-eight acres be deleted pursuant to CT8.24(b)(i) and (ii),
    JX 69 at 3, i.e., the “environmental degradation or resource damage” provisions, JX 10 at 108.
    On December 17, 2014, the Director of Forest Management, on behalf of the Chief of the
    Forest Service, declined to issue the formal partial termination determination the Regional
    Forester had requested. See JX 73. Instead of unilaterally directing a partial termination, he
    instructed the Regional Forester to try to work out the terms of the partial termination with
    Seneca and memorialize it in a settlement agreement. Id. at 1.
    To those ends, CO Burkey met with Seneca on January 21, 2015. JX 77. He presented a
    “proposed modification package for the Trapper Timber Sale,” and subsequently provided
    “follow up information on the sensitive, threatened and endangered species that have affected the
    sale.” Id. Over the course of the next few months, Seneca and Forest Service officials (including
    the CO) exchanged emails discussing potential recovery under the contractual termination
    provisions. See JXs 75, 76.
    On August 6, 2015, CO Burkey requested that Seneca agree to a schedule that would
    allow the parties to reach an agreement by September 30, 2015. JX 77. He warned that the Forest
    Service would “proceed with a unilateral modification of the Trapper Timber Sale” if it did not
    receive a response from Seneca by that date. Id.
    Seneca’s Certified Claim
    On August 18, 2015, Seneca filed a fourteen-page certified claim addressed to CO
    Burkey, in which it declared that the Forest Service was in material breach of the Trapper
    contract. See JX 78 (certified claim). Seneca characterized the breach as arising out of the
    “permanent refusal” of the Forest Service “to allow Seneca to exercise its contractual right to
    operate and complete the Trapper Timber Sale Contract.” Id. at 6. 5 Seneca argued that the Forest
    Service had violated the implied duty of good faith and fair dealing when it negligently stated in
    the 2003 EA that the sale would likely have no significant impact on the spotted owl. Id. at 8–9.
    That error, Seneca argued, along with the supposed “willful misconduct” of the Forest Service
    scientists who publicly criticized the continuation of the project, each played a part in the district
    court’s decision to issue the injunction in Cascadia. Id. According to Seneca, the Forest Service
    could be held liable for breach of contract “if its own unreasonable or wrongful actions caused
    5
    In the claim letter, Seneca stated that the breach “occurred at a date between November 2013
    and March 17, 2014 that is currently unknown to Seneca and appears at this time to be
    November 4, 2013.” JX 78 at 1. Elsewhere in its claim letter, Seneca states that on that date
    (November 4, 2013) the parties held a meeting on the revised EA and that a Forest Service
    representative told Seneca that the revised Trapper Project would be reduced to thirty-six acres.
    Id. at 5.
    12
    the court order [suspending a timber sale] to be imposed in the first place.” Id. at 8 (quoting H.N.
    Wood Prods. v. United States, 
    59 Fed. Cl. 479
    , 487 (2003)).
    Seneca also sought to neutralize the impact of the contract’s partial termination
    provisions on its breach-of-contract claims. It asserted that—because it had already declared that
    the Forest Service was in material breach—it was too late for the Forest Service to invoke those
    provisions. 
    Id.
     at 7–8. Seneca advised the CO that it was discontinuing its performance on the
    contract but that it would be willing to perform under the revised Trapper Project to mitigate its
    losses. Id. at 1. It appended to its claim a worksheet setting forth its calculation of its damages
    for breach of contract, including lost profits and out-of-pocket expenses, id. at 12–13, which it
    estimated to be $4,440,369, id. at 18.
    The May 9, 2016 Contracting Officer’s Final Decision and Partial Termination of
    the Contract
    On April 8, 2016, some seven to eight months after Seneca filed its certified claim, the
    Regional Forester again requested that the Chief of the Forest Service “partially terminate the
    Trapper timber sale pursuant to contract provision CT8.24.” JX 81 at 1. This time, however, he
    proposed that the termination be effected under paragraph (a), id. at 2, which states in pertinent
    part that the Chief of the Forest Service, “by written notice, may terminate this contract, in whole
    or in part,” “[t]o comply with a court order, regardless of whether this timber sale is named in
    such an order, upon determination that the order would be applicable to the conditions existing
    on this timber sale,” JX 10 at 108 (CT8.24(a)).
    On May 9, 2016, the Acting Director of Forest Management approved the request for
    partial termination on behalf of the Chief of the Forest Service. JX 83 at 2. He stated that—
    effective that day—the Forest Service was cancelling Seneca’s right to harvest all but
    twenty-seven acres available under the original Trapper sale pursuant to provision CT8.24(a). Id.
    Accordingly, he observed, Seneca would receive compensation calculated under CT9.53. Id. at 1.
    On that same day, CO Burkey issued a final decision denying in substantial part Seneca’s
    certified claim. JX 84 (Contracting Officer’s Notice of Final Decision (“COFD”)). He rejected
    Seneca’s argument that the Forest Service had breached the contract by preventing it from
    harvesting the acreage included in the contract. Id. at 15. He found that the terms of the contract
    authorized the Forest Service to impose each of the suspensions of performance about which
    Seneca complained in its claim letter. Id. at 10–11, 13. He also noted that the result of the EA the
    district court had ordered was a reduction in the acreage in the Trapper sale and that, since the
    injunction had been dissolved, the Forest Service had attempted to reach an agreement to modify
    the contract under CT8.24. Id. at 12–13. Therefore, he stated, while Seneca could not harvest the
    total estimated volume of the sale that was originally awarded, the Forest Service’s actions were
    consistent with the contract. Id. at 15.
    On May 12, 2016, the Forest Service unilaterally modified the contract to reflect the
    changes required under the COFD and the decision of the Acting Director of Forest
    Management. JX 85. In addition, and consistent with the COFD, see JX 84 at 15, the CO advised
    Seneca that it was entitled to recover its out-of-pocket expenses in the amount of $141,327.98,
    13
    plus $5,578.20 in interest, JX 85; see also JX 86 at 1 (CO’s May 12, 2016 letter stating that
    “execution of the required modification has occurred and that operations on the Trapper Timber
    Sale can resume”).
    Performance of the Modified Contract
    On March 10, 2017, Seneca emailed CO Marc Dasher, posing questions about the revised
    contract. JX 87. He explained that, in the Forest Service’s view, “the contract remains in effect”
    and had not been breached, and that therefore “Seneca remains obligated to complete it.” JX 88
    at 1.
    Seneca harvested timber from seven of the twenty-seven-acre revised sale in 2017,
    exclusively via helicopter logging. Tr. vol. 1, 61:12–22, 62:20–23. It harvested the remaining
    twenty acres in 2018, employing cable logging and ground-based logging methods. Id. 62:24–
    63:4. The contract was closed on March 23, 2020. JX 100.
    The Present Case
    A.      Complaints and Dispositive Motions
    In the meantime, on August 12, 2016, several months after the CO rejected its claim and
    the Forest Service partially terminated the contract, Seneca filed the present action. See Compl.,
    ECF No. 1. In its complaint, it alleged breach of contract and requested an award of damages
    totaling $4,440,369. Id. ¶ 23.
    On October 14, 2016, the government filed a motion to dismiss Seneca’s complaint under
    RCFC 12(b)(6), Def.’s Mot. to Dismiss, ECF No. 6, which the Court denied on March 29, 2017,
    Op. and Order at 6, ECF No. 15. Seneca filed a motion to amend its complaint, Pl.’s Mot. to File
    First Am. Compl., ECF No. 33, which the Court granted on November 2, 2018, Order, ECF No.
    36.
    Seneca filed its amended complaint on November 2, 2018. See First Am. Compl., ECF
    No. 37. In it, Seneca alleged that the Forest Service breached the Trapper contract by electing to
    “prepar[e] an entirely new environmental assessment” in response to the district court’s
    injunction, rather than “the supplemental environmental assessment called for in the [district]
    Court’s Order.” Id. ¶ 12. In addition, Seneca challenged the Forest Service’s decision to
    terminate the contract under CT8.24(a), alleging that “the Forest Service breached its contractual
    obligation set out in contract provisions CT8.24 and CT9.53 not to modify or terminate a timber
    sale contract to comply with a court order unless the contracting officer made a determination
    that the modification or termination was ‘necessary for correction of the deficiencies raised by
    the appeal or lawsuit.’” Id. ¶ 13.
    A period of discovery followed, after which the government filed a motion for summary
    judgment on July 25, 2019. Def.’s Mot. for Summ. J., ECF No. 47. The Court granted the motion
    in part on July 2, 2020. Seneca I, 
    149 Fed. Cl. 83
    . It agreed that the government was entitled to
    summary judgment as to Seneca’s claim based on the duty of good faith and fair dealing, 
    id.
     at
    14
    101–03, but rejected the balance of the government’s arguments as to Seneca’s
    breach-of-contract claims, 
    id.
     at 95–101.
    The Court explained that the Forest Service may have erred when it invoked CT8.24(a) to
    partially terminate the Trapper contract because the district court’s order did not require
    cancellation of the contract; it merely directed the Forest Service to conduct a supplemental EA
    and then decide for itself what action to take. 
    Id.
     at 99–100. It observed, however, “that even if
    Seneca ultimately demonstrates that CT8.24(a) did not justify the partial termination of the
    contract, the government may be able to rely upon the doctrine of constructive termination by
    establishing that it could have invoked any of the grounds for termination set forth in
    CT8.24(b).” 
    Id. at 96
    .
    B.      The Trial
    The Court held a two-day trial on Seneca’s breach-of-contract claim on November 1 and
    2, 2021. At trial, Seneca alleged that it is entitled to an additional $66,208.16 in uncompensated
    out-of-pocket costs (pursuant to contract provisions CT9.51, CT9.52(b), or CT9.53). Pl.’s Br. at
    22. It also alleged that the Forest Service breached the Trapper contract by invoking CT8.24(a)
    instead of CT8.24(b) and argued that it is entitled to relief for the value of the deleted timber in
    the amount of either $1,775,243 or $2,757,706. 
    Id.
     at 23–25.
    In support of its claims, Seneca presented the testimony of Todd Payne, its President and
    CEO; Carl Harrison, its logging manager; Scott Keep, its director of wood procurement; Brian
    Carlin, its Senior Vice President and Chief Financial Officer; William Roach, a consulting
    forester; and Paul Beck, who, at the time of trial, was the Chief Executive Officer of the
    Mountain Western Log Scaling and Grading Bureau.
    Two witnesses testified for the government: Thomas Rudisill, the Forest Service’s timber
    program manager and silviculturist for the Willamette National Forest; and David Bishop, the
    Forest Service’s pre-sale forester for the McKenzie River Ranger District within the Willamette
    National Forest.
    The parties filed post-trial briefs in the case on December 20, 2021, see 
    id.,
     February 2,
    2022, see Def.’s Post-Trial Resp. Br. (“Def.’s Resp.”), ECF No. 105, and March 4, 2022, see
    Pl.’s Post-Trial Reply Br. (“Pl.’s Reply”), ECF No. 108. The Court heard closing arguments on
    June 23, 2022.
    DISCUSSION
    Jurisdiction
    The first issue before the Court is whether it has jurisdiction over Seneca’s claims under
    the Contract Disputes Act (“CDA”). See 
    28 U.S.C. § 1491
    (a)(2) (granting the Court of Federal
    Claims “jurisdiction to render judgment upon any claim by or against, or dispute with, a
    contractor arising under section 7104(b)(1) of title 41, including a dispute concerning
    termination of a contract . . . and other nonmonetary disputes on which a decision of the
    15
    contracting officer has been issued”). “The CDA mandates that ‘[e]ach claim by a contractor
    against the Federal Government relating to a contract shall be submitted to the contracting officer
    for a decision.’” Tolliver Grp., Inc. v. United States, 
    20 F.4th 771
    , 775 (Fed. Cir. 2021) (quoting
    
    41 U.S.C. § 7103
    (a)(1)). Therefore, “obtaining a final decision on a claim is a jurisdictional
    prerequisite to adjudication of that claim in” this court. 
    Id.
     at 775–76 (citing 
    41 U.S.C. §§ 7104
    (b)(1), 7103(g); Raytheon Co. v. United States, 
    747 F.3d 1341
    , 1354 (Fed. Cir. 2014));
    see also M. Maropakis Carpentry, Inc. v. United States, 
    609 F.3d 1323
    , 1328 (Fed. Cir. 2010)
    (“[F]or the Court of Federal Claims to have jurisdiction under the CDA, the contractor must
    submit a proper claim—a written demand that includes (1) adequate notice of the basis and
    amount of a claim and (2) a request for a final decision.” (citing Ellett Constr. Co. v. United
    States, 
    93 F.3d 1537
    , 1541–42 (Fed. Cir. 1996))). “The purpose of the requirement is ‘to create
    opportunities for informal dispute resolution at the contracting officer level and to provide
    . . . clear notice as to the’ content of ‘contract claims.’” Tolliver Grp., Inc., 20 F.4th at 776
    (quoting Raytheon, 747 F.3d at 1354).
    The government contends that the Court lacks jurisdiction to determine whether Seneca is
    due any relief under the contract’s termination provisions because, in its August 2015 request for
    a contracting officer’s final decision, Seneca pressed only a breach-of-contract claim and sought
    damages based solely on that claim. See Def.’s Resp. at 15–19. Therefore, according to the
    government, the Court lacks jurisdiction to consider the questions before it now: whether the
    Forest Service properly invoked CT8.24(a) when it partially terminated the Trapper sale and, if
    not, whether it could have instead invoked CT8.24(b). Id.
    The government’s position lacks merit. The standard requiring that an action before this
    court be based on the “same claim” as the one presented to the contracting officer “does not
    require ridged adherence to the exact language or structure of the original administrative CDA
    claim.” Scott Timber Co. v. United States, 
    333 F.3d 1358
    , 1365 (Fed. Cir. 2003). The Court may
    exercise its jurisdiction where the claims “arise from the same operative facts, claim essentially
    the same relief, and merely assert differing legal theories for that recovery.” 
    Id.
    As described above, in its certified claim, Seneca alleged that—when the Forest Service
    decided to partially cancel the Trapper sale as a result of the findings in its supplemental EA—
    the agency breached its obligations under the timber sale contract; in particular, its implied duty
    of good faith and fair dealing. See JX 78 at 6–11 (certified claim). Seneca also challenged the
    Forest Service’s right to invoke the contract’s partial termination provisions, arguing that, in
    light of the alleged material breach, it was too late to do so. 
    Id.
     at 7–8.
    The CO, who had for months been involved in efforts to settle the dispute with Seneca,
    rejected both claims. See JX 84 (COFD). He denied the breach-of-contract claim on the grounds
    that reduction in the acreage covered by the sale was governed by the partial termination
    provisions. 
    Id.
     at 10–13. Therefore, he found, Seneca could not recover damages on the basis of
    breach of contract. 
    Id.
     Instead, the agency partially terminated the contract under CT8.24(a), and
    the CO determined that Seneca was due only the compensation awardable under the contract
    itself, which was $141,327.98 in out-of-pocket expenses. 
    Id.
     at 14–15.
    16
    When the case came to this Court, Seneca similarly pressed a breach-of-contract claim,
    again including a claim that the Forest Service breached its implied obligation of good faith and
    fair dealing. First Am. Compl. ¶ 11; id. ¶ 13 (asserting that “the Forest Service breached its
    implied duty to cooperate and not to hinder performance of plaintiff’s timber sale contract”). It
    also argued, as it had before the CO, that the Forest Service could not invoke CT8.24(a) to avoid
    liability for damages based on breach of contract. Id. ¶ 13.
    To be sure, in challenging before this Court the CO’s authority to invoke the partial
    termination provision, Seneca relied upon a different legal theory than the one it articulated in its
    certified claim. 6 Nonetheless, the claims before the CO were based on essentially the same
    operative facts, namely, the Forest Service’s decisions: (1) to expand the supplemental EA to
    cover matters allegedly not required by the district court’s decision, JX 78 at 4–5, 12; First Am.
    Compl. ¶¶ 13, 18; and (2) not to allow Seneca to harvest timber on all the acreage covered by the
    contract but to instead partially terminate the contract under CT8.24, JX 78 at 7–8; First Am.
    Compl. ¶¶ 17, 19.
    There is similarly no merit to the government’s argument that the Court lacks jurisdiction
    to award relief on the basis of the remedial provisions available under CT8.24(b). Def.’s Resp. at
    18–19. The Court agrees that this question was not presented to or considered by the CO. But the
    argument that CT8.24(b) applies is part of the government’s defense against Seneca’s
    breach-of-contract claims. See Rsrv. Ranch v. United States, 
    39 Fed. Cl. 696
    , 719 (1997), aff’d,
    
    217 F.3d 850
     (Fed. Cir. 1999) (“It is settled law that where the government has canceled a
    contract based upon erroneous grounds, the cancellation may be sustained if there existed an
    adequate ground for cancellation at the time of cancellation, even if the ground was not then
    known.”) (collecting cases). Given the Court’s determination (explained below) that CT8.24(a)
    was not properly invoked, the Court would have to find the government in breach of contract if it
    were not able to consider whether the Forest Service could have instead relied on CT8.24(b).
    In short, the government’s jurisdictional arguments lack merit. The Court turns, therefore,
    to the question of whether the agency properly invoked CT8.24(a) as the basis for partial
    termination of the contract.
    The Invocation of CT8.24(a) to Terminate the Trapper Contract
    The Forest Service relied upon CT8.24(a) as the basis for its partial termination of the
    Trapper contract. JX 83 at 1. As noted above, that provision states, in pertinent part, that the
    6
    Specifically, Seneca alleged in its complaint that, under CT9.53, the CO was required to
    independently determine what changes in the contract were required to correct the deficiencies
    that the district court identified in Cascadia Wildlands. First Am. Compl. ¶ 13. Because he had
    not done so, Seneca contended, the Forest Service could not invoke CT8.24(a). 
    Id.
     This Court
    rejected that argument in ruling on the motion for summary judgment, holding that, under
    CT8.24, it was the job of the Chief of the Forest Service to determine the scope of the actions
    needed to comply with the Court order or with NEPA. Seneca I, 149 Fed. Cl. at 99 (observing
    that “CT8.24(a) states in pertinent part that the Chief of the Forest Service may terminate the
    contract in whole or in part ‘[t]o comply with a court order’”).
    17
    Chief of the Forest Service may terminate the contract in whole or in part “[t]o comply with a
    court order.” JX 10 at 108.
    CT8.24(a) does not apply to the partial termination of the Trapper sale because the
    district court did not direct that the contract be terminated in whole or in part. More to the point,
    the district court did not require the Forest Service to remove acreage from the sale, nor did it
    determine how much and which acreage to remove. It was the Forest Service that made those
    decisions, after it prepared a supplemental EA as the district court had ordered. The Forest
    Service achieved compliance with the district court’s order when it considered new information
    regarding the northern spotted owl and the learning value of the Trapper Project and prepared a
    supplemental EA and new Decision Notice based on its review of that information.
    Further, the district court explicitly recognized the possibility that “the Forest Service,
    after preparing a supplemental EA, [might] make[] the Decision to go forward with Trapper.”
    Cascadia Wildlands, 
    791 F. Supp. 2d at 994
    . And, in denying Seneca’s motion for clarification,
    the district court reiterated that its injunction “d[id] not predetermine the results of the Forest
    Service’s analysis.” Order at 4, Cascadia Wildlands, 
    791 F. Supp. 2d 979
     (No. 10-6337), ECF
    No. 57.
    Moreover, it was the Forest Service that decided to expand the scope of the supplemental
    EA beyond the particular areas of concern the district court identified. The Forest Service
    publicly stated that the purposes of its revised environmental assessment were “to disclose
    effects of harvesting timber already sold under contract, and to respond to analysis deficiencies
    identified by the [injunction].” JX 50 at 2 (emphasis added); see also JX 51 at 3 (explaining that
    the revised EA would “address instructions from the May 2011 [injunction], and bring the 2003
    environmental analysis up to date with current policy and direction”) (emphasis added); JX 51 at
    5 (outlining the EA revision process, which included: (1) “Analysis to address court order (owl
    and science)”; and (2) “Analysis to meet current NEPA requirements, including changed
    conditions”); JX 54 at 1 (April 29, 2013 Trapper Project Interdisciplinary Meeting outlining
    “Work that Needs to be Done”: (1) “Analysis to address court order (owl and science)”; and (2)
    “Analysis to meet current NEPA requirements, including changed conditions”); JX 59 at 7, JX
    61 at 1 (all stating that the Forest Service aimed to revise its 2003 EA by bringing the
    environmental analysis up to date with current policy).
    In its Post-Trial Response Brief, the government argues that “even if the acreage
    reductions at issue here were not required in response to the district court’s 2011 injunction
    order, they were certainly required in response to that court’s 2014 minute order dissolving the
    injunction.” Def.’s Resp. at 27. It so contends because the decision to dissolve the injunction
    “was based on the representation that the Forest Service planned to implement the revised
    environmental assessment and decision notice.” 
    Id.
     This argument is likewise unpersuasive.
    The district court did not say why it was dissolving the injunction. Presumably, it lifted
    the injunction because the parties requested that it do so in the wake of the Forest Service’s
    completion of “a revised EA to address [the] Court’s injunction” and its issuance of a
    Supplemental Decision Notice. Stip. Mot. to Dissolve Inj. at 2, Cascadia Wildlands, 
    791 F. Supp. 2d 979
     (No. 10-6337), ECF No. 71. The government’s argument that—by lifting its injunction
    18
    against performance on the contract—the district court somehow also compelled the partial
    termination the Forest Service implemented is illogical.
    For these reasons, this case is not at all like Scott Timber Co. v. United States, as the
    government argues. Def.’s Resp. at 26 (citing 
    692 F.3d 1365
    , 1373–74 (Fed. Cir. 2012)). In that
    case, after a district court issued a preliminary injunction suspending certain timber sales in the
    context of environmental litigation, the Forest Service entered a settlement agreement with the
    plaintiffs. Scott Timber, 692 F.3d at 1369–70. In the settlement, the Forest Service agreed to
    continue the suspension of operations until it completed certain wildlife surveys. Id. at 1370. The
    district court entered the agreement as a formal order in the case, and dismissed the complaint,
    subject to reinstatement in the event of a material breach of the settlement. Id.
    The plaintiff in Scott Timber contended that the suspension was undertaken to comply
    with the settlement agreement and was not necessary “to comply with a court order.” Id. at 1373.
    The Federal Circuit rejected this argument. Id. It noted that the district court had specifically
    ordered the parties to comply with the settlement agreement (which included the suspension of
    the sale). Id. at 1374. In addition, the district court’s order contemplated that if the Forest Service
    did not perform the surveys required by the settlement, it would enter an order enforcing the
    agreement. Id. “In this light,” the court of appeals observed, “it is clear that the agreement was
    the equivalent of a ‘court order’ within the suspension clause of the contracts.” Id.
    By contrast, in Cascadia Wildlands, the district court entered a judgment on the docket
    that vacated its order suspending the timber sale. See Docket, Cascadia Wildlands, 
    791 F. Supp. 2d 979
     (No. 10-6337), ECF No. 73. It did not order cancellation of the contract by, for example,
    mandating compliance with the Decision Notice. The Court concludes, therefore, that the partial
    termination was not necessary “to comply with a court order,” and that CT8.24(a) did not
    provide the Forest Service with the authority to impose such a termination.
    Damages Under CT8.24(b)
    For the reasons set forth above, the Court has concluded that CT8.24(a) did not authorize
    the Forest Service’s partial termination of the Trapper timber sale. The parties have stipulated,
    however, that if the Court were to find that the Forest Service could not rely on CT8.24(a), it
    could have proceeded under CT8.24(b)(i), (b)(ii), and/or (b)(v). Therefore, the government is
    entitled to rely upon the doctrine of constructive termination to limit Seneca’s relief to that which
    the contract provides for terminations under those provisions.
    The dispute before the Court concerns what that relief would be. Provision CT9.52
    applies to terminations under CT8.24(b)(i) and (b)(ii). JX 10 at 108 (explaining that
    “compensation for termination under paragraphs (b)(i) through (b)(iv) shall be calculated
    pursuant to CT9.52”). That provision states that the contractor’s compensation will consist of
    “[t]he difference between Current Contract Rates for the remaining uncut volume and the rates
    paid for comparable timber on the same National Forest during the preceding 6-month period
    multiplied by the remaining uncut volume.” 
    Id.
     at 111 Terminations under CT8.24(b)(v),
    however, are subject to CT9.51, 
    id. at 108
     (explaining that “compensation for termination under
    19
    paragraph (b)(v) shall be calculated pursuant to CT9.51”), which limits relief to out-of-pocket
    expenses, 
    id. at 111
     (CT9.51).
    A threshold dispute concerns what volume of the timber which was terminated could
    have been cancelled under CT8.24(b)(i) or (ii) (i.e., to avoid environmental degradation or
    because the harvest would be inconsistent with forest plans), and how much could have been
    terminated under CT8.24(b)(v) (i.e., to protect threatened and endangered species). 7 Another
    dispute concerns how “uncut volume” should be determined for purposes of calculating
    compensation under CT9.52. 8 The parties also take conflicting positions regarding the “current
    contract rate” to use for relief under CT9.52, with Seneca arguing that the appropriate rate is
    $112.01 per MBF, Pl.’s Br. at 10–11; Pl.’s Reply at 9, and the government contending that it
    should be $225.32 per MBF, Def.’s Resp. at 37. 9
    While these disagreements were the focus of much of the testimony and evidence
    adduced at trial, the Court finds it unnecessary to resolve them. Seneca is not entitled to further
    recovery under CT9.52 because it has not persuaded the Court that “the rates paid for
    comparable timber on the same national forest” during the six-month period that preceded the
    partial termination were higher than the then-current contract rates. This is so even if, as Seneca
    contends, current contract rates were $112.01 per MBF.
    A.      Seneca’s Burden
    The parties agree, and the Court finds, that there was no comparable timber purchased on
    the Willamette National Forest during the six-month period preceding the partial termination of
    7
    The government argues that 48 of the 122 cancelled acres could have been terminated under
    CT8.24(b)(v) (to protect the northern spotted owl and the Cascade axetail slug), with the
    remaining 74 acres cancelled under either (b)(i) or (b)(ii). See Def.’s Resp. at 42. Seneca, on the
    other hand, argues that only 24 acres could have been removed under CT8.24(b)(v) with the
    remaining 98 acres removed under either (b)(i) or (b)(ii). See Pl.’s Br. at 12–13; Pl.’s Reply at 6.
    8
    The government contends that “uncut volume” is measured by the volume identified in the
    contract. Tr. vol. 1, 156:5–23 (arguing that “the contract number is what controls” (citing JX 12
    at 3)); Def.’s Resp. at 42–43. Seneca contends that “uncut volume” means the actual volume of
    timber on the deleted acres, Pl.’s Br. at 15, and argues that the Court should approve the
    calculation of the uncut volume set forth in a timber cruise performed in 2014 by Jackson and
    Prochnau at Seneca’s request, 
    id.
     at 15–19; Pl.’s Reply at 8.
    9
    The difference is based on whether or not the contract rate should incorporate the Emergency
    Rate Reduction the government agreed to provide purchasers in July 2009 in the wake of the
    so-called “great recession.” See JX 98 (contract rates); JX 23 (Seneca’s June 4, 2009 request for
    an Emergency Rate Reduction). The government argues that Seneca cannot rely on the reduced
    rate because in the contract modification that established the reduced rates Seneca agreed “to
    release the United States (acting by and through the U.S. Forest Service) from all liability,
    including further consideration or compensation, resulting from this modification.” Def.’s Resp.
    at 41 (quoting JX 25 at 2 (July 29, 2009 agreement to modify Trapper contract)).
    20
    the Trapper contract on May 9, 2016. See Pl.’s Br. at 12–13; Def.’s Resp. at 39; see also Tr. vol.
    1, 240:24–241:6, 265:5–12 (testimony of Seneca witness Paul Beck); Tr. vol. 2, 372:24–373:13
    (testimony of government expert witness David Bishop). Therefore, the parties agree, a
    reasonable method for computing the compensation due to Seneca would be to determine the
    difference between the then-current contract rates during that period and the rate a reasonable
    purchaser would have been willing to pay for comparable timber had such timber been put on
    sale. But the parties differ sharply as to the latter. Seneca argues that the rate for comparable
    timber in the six months preceding the partial termination would have been $584.22 per MBF,
    Pl.’s Br. at 21, 24, while the government argues that the rate would have been much lower, at
    $73.21 per MBF, Def.’s Resp. at 38–40.
    As plaintiff, it is Seneca’s burden to establish its entitlement to damages. Northrop
    Grumman Computing Sys., Inc. v. United States, 
    823 F.3d 1364
    , 1368 (Fed. Cir. 2016) (“It is
    fundamental in contract law that in order to recover on a breach of contract claim, a plaintiff
    must prove damages—that it has been harmed.” (citing Restatement (Second) of Contracts § 346
    (Am. L. Inst. 1981))). It is also “incumbent upon [the plaintiff] to establish a reasonable method
    for computing the requested compensation.” Daly Const., Inc. v. Garrett, 
    5 F.3d 520
    , 522 (Fed.
    Cir. 2019); see also Sonoma Apartment Assocs. v. United States, 
    939 F.3d 1293
    , 1299 (Fed. Cir.
    2019) (“Plaintiffs must provide some measure of substantiation to show the reasonableness of
    their calculations.”). And the evidence a plaintiff submits must support the calculation of those
    damages to a “reasonable certainty.” Indiana Michigan Power Co. v. United States, 
    422 F.3d 1369
    , 1373 (Fed. Cir. 2005) (citing Energy Capital Corp. v. United States, 
    302 F.3d 1314
    , 1320
    (Fed. Cir. 2002)); see also Restatement (Second) of Contracts § 352 (Am. L. Inst. 1981)
    (“Damages are not recoverable for loss beyond an amount that the evidence permits to be
    established with reasonable certainty.”).
    For the reasons set forth below, Seneca has not shown that the rate that it would have had
    to pay for comparable timber in 2016 was greater than the then-current contract rate for the
    Trapper logs, and if so, by how much. It has therefore failed to establish its entitlement to
    additional damages under CT9.52.
    B.      The Opinion of Paul Beck
    Seneca relied largely on the testimony of Paul Beck to support its argument that a
    reasonable purchaser would have paid $584.22 per MBF for comparable timber in the six months
    before the partial termination of the contract. Mr. Beck is the outgoing CEO of the Mountain
    Western Log Scaling and Grading Bureau, Tr. vol. 1, 188:14–17, and has decades of experience
    as a log scaler and buyer, id. 188:20–190:4. He has substantial experience bidding on Forest
    Service and other public timber sales, including those that contain high-grade logs like those
    available under the Trapper sale. Id. 189:18–24, 201:12–18, 203:17–24, 204:16–23, 215:17–
    19. 10
    10
    Although Seneca has characterized Mr. Beck as an expert in timber appraisal, Pl.’s Br. at 5,
    15, 19–21, and Mr. Beck prepared several “expert” reports in connection with this case to which
    he referred during his testimony, Tr. vol. 1, 212:9–17, 259:23–24; see also id. 5:10–13, Seneca
    did not ask the Court to qualify Mr. Beck as such at trial.
    21
    Seneca tasked Mr. Beck with performing an appraisal of the 98 acres of timber that it
    contends the Forest Service could have removed from the Trapper sale pursuant to CT8.24(b)(i)
    and/or (b)(ii). Id. 212:18–22; see also id. 232:18–233:4, 249:19–250:5. The first step of such an
    appraisal, he explained, is to perform a timber cruise to determine the volume of the uncut timber
    and, “more importantly,” its quality, so that he could value the timber on a per thousand board
    feet basis. Id. 214:8–13. Based on the timber cruise Jackson and Prochnau performed at Seneca’s
    request in 2014, id. 218:20–25, he opined that 6.11 million board feet of timber could have been
    harvested on the deleted 98 acres, id. 218:8–12, 235:4–18, 263:11–17. Mr. Beck next estimated
    the “pond value” of the timber based on its volume and quality. Id. 214:13–18. The “pond
    value,” Mr. Beck explained, is the amount that the timber is worth after it is harvested and
    delivered to the mill. Id. 214:15–18; see also id. 216:14–17 (testifying that the pond value is “the
    value of [a] log delivered to its final destination, the mill”). Mr. Beck chose to appraise the
    timber to the highest market. Id. 229:13–14. He assumed, therefore, that the winning bidder for a
    sale which took place in the six months before May 2016 would have expected to sell all of the
    Douglas fir harvested from the deleted acres to specialty cutting mills willing to pay a premium
    on high-grade logs for their aesthetic value. Id. 229:23–25 (testifying that Seneca would not have
    processed a single log in its own facilities); see also Pl.’s Br. at 20 (“As Mr. Beck explained at
    trial, had the 98 acres removed from the Trapper timber sale been rebid in the first quarter of
    2016 as a stand-alone timber sale, virtually all of the Douglas fir volume would have been
    delivered to area cutting mills.”).
    Mr. Beck valued the Douglas fir on the basis of the prices contained in a July 1, 2018 log
    purchase agreement between Seneca and Herbert Lumber, an old-growth mill to which Seneca
    frequently sold high-grade logs it opted not to process in its own facilities. Tr. vol. 1, 211:20–
    212:8 (citing JX 92 (2018 Herbert Lumber log purchase agreement)); Pl.’s Br. at 20. He valued
    the remaining timber, consisting of Cedar and Hemlock, on the basis of the Log Lines index. See
    Pl.’s Br. at 20, 24; see also JX 101 (Log Lines 2003–2018 report for Region 3). 11 His analysis
    yielded an estimated pond value of $5.83 million for all of the remaining uncut timber. Tr. vol. 1,
    263:21–25.
    Next, Mr. Beck estimated the cost of harvesting and delivering the timber, which he
    calculated at just over $2 million, or $289.15 per MBF. Id. 216:18–217:8; see also id. 249:14–15
    (referencing JX 105 at 12); id. 258:19–259:3 (referencing JX 105 at 8). This total included
    logging costs, id. 214:19–215:10, 216:18–20, the cost of constructing roads, id. 214:23–25,
    217:6–7, the cost to deliver logs via truck to the appropriate mill, id. 214:25–215:5, 216:24–
    215:1, and the cost of disposing of “the nonmerchantable material, limbs, [and] chunks that [are]
    burnt at the end of the timber sale,” id. 217:3–5.
    11
    Mr. Beck did not use the Log Lines index for the Douglas fir because, he explained, Log Lines
    blends the prices of high-grade logs with those of commodity logs (which are 95% of the total
    market). Tr. vol. 1, 206:12–18, 206:23–207:1. He opined that Log Lines shows the trend in
    commodity logs and, he said, “those coarse grain logs” have “absolutely no relevance to the
    high-quality cutting mill-type logs.” Id. 206:17–20.
    22
    Using these figures, Mr. Beck determined that the residual value of the uncut volume of
    timber (i.e., pond value minus costs) was $3,785,085. Id. 249:2 (referencing JX 105 at 5); see
    also Def.’s Resp. at 32 (referencing JX 105 at 5). According to Mr. Beck, this figure represented
    “the value of [the] trees on . . . the stump,” or, in other words, what the “stand of [deleted] timber
    was worth.” Tr. vol. 1, 217:10–13; id. 250:15–16 (“It would have sold for $3.7 million.”); id.
    274:21–24 (“[W]ould you have been prepared to bid the $3.7 million in residual value that your
    appraisal shows for that 98-acre timber sale? A. At least.”).
    In its Post-Trial Brief, Seneca acknowledges that Mr. Beck made several errors when he
    calculated the residual value of the uncut volume of timber during the six-month period before
    May 9, 2016. See Pl.’s Br. at 18–21, 24. First, Seneca observes, he miscalculated the uncut
    volume that remained after the partial termination because he failed to account for the timber that
    was removed under CT8.24(b)(v) rather than (b)(i) or (b)(ii). Id. at 18–19. With this error
    corrected, Seneca asserts, the remaining uncut volume was 5,840 MBF (rather than 6,110 MBF).
    Id.
    Second, Mr. Beck’s error regarding the remaining uncut volume also caused him to
    overstate the pond value of the deleted timber. Id. at 20. As corrected, Seneca asserts, the “pond
    value” for the remaining uncut volume of 5,840 MBF is $5,464,511 (rather than $5.83 million).
    Id.
    Finally, Seneca observes that two components of Mr. Beck’s cost of performance
    calculation must be adjusted. Id. at 21. First, when the uncut volume is corrected and multiplied
    by Mr. Beck’s logging cost figure of $289.15 per MBF, the logging costs are reduced from
    $1,769,869 to $1,691,673. Id. Second, Seneca acknowledges, Mr. Beck overstated the road
    construction costs. Id. Those costs should have been $183,229, or 64.75% of $278,676, id.
    (citing JX 80 (List of Changes for Contract Modification) and referencing JX 105 at 12), rather
    than the $238,257.85 to which Mr. Beck testified at trial, Tr. vol. 1, 135:9–12. With those
    adjustments, Seneca argues, the total cost of performing the timber harvest of the remaining
    uncut volume would be $2,052,686. Pl.’s Br. at 21.
    Adopting these adjusted figures, Seneca argues in its Post-Trial Brief that the residual
    value of the uncut timber was $3,411,825, id., rather than $3,785,085, as Mr. Beck had testified,
    Tr. vol. 1, 249:2; Def.’s Resp. at 32. Seneca also used the adjusted figures to calculate the dollar
    rate that would have been paid for comparable timber, see Pl.’s Br. at 21 (citing Pl.’s Br. Ex. A,
    at 1, ECF No. 102-1), a task Mr. Beck did not perform, Tr. vol. 1, 241:2–23. Seneca explains that
    it divided the revised residual value ($3,411,825) by the volume of deleted timber (5,840 MBF),
    yielding a 2016 bid rate of $584.22 per MBF. Pl.’s Br. at 21 (citing Pl.’s Br. Ex. A, at 1). The
    difference between that rate and what Seneca argues was the then-current contract rate ($112 per
    MBF) is $472.21 per MBF. Id. And when that difference is multiplied by the remaining uncut
    volume, Seneca argues, it is due $2,757,706 in compensation under CT 9.52. Id. at 23–24 (citing
    Pl.’s Br. Ex. A at 1).
    23
    C.      Flaws in Mr. Beck’s Methodology
    1.      Appraising to the Highest Market
    While Seneca has corrected the errors described above in its Post-Trial Brief, Mr. Beck’s
    testimony was flawed in a number of other more significant respects. Perhaps most egregiously,
    he indulged an assumption about the value of the timber to be sold in the hypothetical sale that
    contradicts both Seneca’s practice in determining its bid and even his own. Specifically, he
    assumed that a purchaser for a hypothetical sale in 2016 would have calculated the amount it
    would bid with the expectation that the entirety of Douglas fir logs harvested from the deleted
    acres—more than 90% of the total timber volume in the sale—would be sold to specialty cutting
    mills. See Pl.’s Br. at 20; Tr. vol. 1, 229:12–25.
    Seneca’s CEO testified, however, that, in 2003, Seneca expected between 25% and 35%
    of the Trapper logs would be sold to specialty cutting mills. Tr. vol. 1, 94:18–24. The rest, he
    said, would be processed in Seneca’s own facilities. Id. 52:2–10 (testifying that, had Seneca
    harvested the entire Trapper sale in 2003, it would have processed the majority of the timber in
    its own mills to make commodity products). Similarly, in its 2015 claim letter, Seneca stated that
    it “expected to process [6,614 MBF]” of the 8,724 MBF timber in the sale (i.e., approximately
    75%) “in its own processing facilities.” JX 78 at 12. And when Seneca harvested 1,857 MBF in
    the modified Trapper sale in 2017, JX 94 at 1, it sold only 392 MBF—barely 20%—to specialty
    cutting mills, Tr. vol. 1, 117:4–13.
    Moreover, Mr. Beck testified that it was his practice to bid on similar sales with the
    expectation that approximately 25% of the harvest would yield high-grade logs. Id. 203:21–24.
    And in an earlier report he drafted to support Seneca’s original claim for compensatory damages,
    including lost profits, he acknowledged that 75% of the Trapper sale “would have been
    processed by Seneca’s mills . . . based on what they said they were going to do . . . on this
    particular case.” Id. 261:3–9.
    The Court recognizes Mr. Beck’s years of experience performing timber appraisals and
    does not doubt his good faith. But it is not clear to the Court that Mr. Beck understood his task to
    be projecting what a reasonable bidder would have paid at a sale of comparable timber by the
    Forest Service. His methodology of appraising to the highest market significantly inflated the
    value of the uncut timber and does not capture the real-world practices that contractors follow
    when determining their bids. For these reasons alone, Mr. Beck’s opinion regarding the rate that
    would have been paid for comparable timber, during a hypothetical sale conducted in the six
    months before May 9, 2016, lacks credibility.
    2.      Reliance on 2018 Purchase Order with Herbert Lumber
    The Court also found unpersuasive Mr. Beck’s testimony regarding the price Seneca
    might expect specialty cutting mills to pay for comparable timber in the period between
    December 2015 and May 2016. As noted above, he based his opinion on a July 2018 purchase
    24
    order with Herbert Lumber. Mr. Beck testified that it was reasonable to use that purchase order
    because the market for higher-and-better-use logs is “pretty stable.” Tr. vol. 1, 223:1–3; see also
    id. 222:15–25 (explaining that this purchase order “was specific to Trapper”); id. 223:3–5 (“I
    have literally written purchase orders that were in place for five years.”). But Mr. Beck’s
    testimony on this point is not supported by objective evidence. In fact, based on the Log Lines
    index the parties put into evidence, it appears that prices for Douglas fir spiked between 2016
    and 2018. See JX 101 at 1. 12
    In addition, the Court found Mr. Beck’s testimony about the trajectory of the specialty
    log market during this period unpersuasive. Mr. Beck testified that prices in the specialty log
    market between 2003 and 2016, while on an upward trajectory, Tr. vol. 1, 205:23–24, 252:1–12,
    252:20, were nonetheless “fairly flat,” see, e.g., id. 252:4, 252:12–16, 254:10–13. At the same
    time, he also testified that the pond value of the ninety-eight deleted acres “increase[d] in value
    significantly between 2003 and 2016,” because of shortages in the supply of high-grade logs. Id.
    272:18–273:1.
    These two statements seem to contradict each other, and Mr. Beck’s demeanor during his
    testimony appeared to reflect that he was tentative and unsure about the market’s trajectory. 13
    Further, in 2003, Seneca estimated the pond value for the entirety of the Trapper sale
    timber (shown as “total realization,” “total value,” and “gross value” in Seneca’s bid calculation
    sheet), to be approximately $3.5 million. JX 7 at 1–2. If Mr. Beck is to be believed, then by 2016
    the price for just one-third of that timber was some two-thirds higher (or $5.8 million). Similarly,
    12
    In its Post-Trial Brief, Seneca suggests that as an alternative to the Herbert Lumber purchase
    order, the Court might instead rely on a 2016 “catch-all” purchase order from another milling
    operation. Pl.’s Br. at 24–25 (citing JX 82 (2016 Oregon Overseas Timber purchase order)). It
    argues that using the prices contained in that purchase order would result in a reduced residual
    value of $2,429,398 and a bid rate of $415.99 per MBF (as compared to the rate of $584/22 per
    MBF derived from the Herbert Lumber order). Id. At trial, the Court sustained the government’s
    objection to the consideration of this argument because it was not made a part of Mr. Beck’s
    report and because counsel for the government did not become aware of it until the Friday before
    trial. See Tr. vol. 1, 224:8–17. The Court therefore will not consider the Oregon Overseas
    purchase order in calculating damages.
    13
    Other witnesses also offered conflicting testimony about the nature of the specialty log market.
    Seneca CEO Todd Payne, for example, testified that “the market for appearance grade specialty
    products that cutting mills are looking to source” is “much more stable” than that of the
    commodity logs processed by his own company. Tr. vol. 1, 45:21–46:4. In nearly the same
    sentence, however, Mr. Payne testified that the market for higher-and-better-use timber has been
    rising in the past two decades, owing to increased environmental protections and evolving forest
    management efforts in the Pacific Northwest. Id. 45:20–46:4, 49:19–50:17 (explaining that “the
    type of wood that [the specialty mills are] able to manufacture from is much less today than it
    was, say, [twenty] years ago”). In fact, he testified, in light of the price increase in the twenty
    years since it bid on the original Trapper sale, Seneca would not have been willing to bid on the
    sale at all had it occurred in 2016 rather than in 2003. Id. 49:19–50:8, 51:7–17.
    25
    Mr. Beck ultimately calculated a “residual value”—revenue from the sale less costs to harvest
    it—of nearly $3.8 million for the six-month period before May 2016. Tr. vol. 1, 249:2. That
    resulted in a margin that is nearly 10 times the roughly $390,000 margin Seneca projected for the
    entire sale in its bid calculations in 2003. JX 7 at 1. These results seem highly improbable and
    provide another reason why the Court cannot credit Mr. Beck’s analysis.
    3.      Mr. Beck’s Difficulty Answering Questions
    Based on both his demeanor and the substance of his testimony, the Court’s impression
    was that Mr. Beck did not have a good handle on, among other things, the components of the
    formula for determining compensation under CT9.52. For example, at trial, government counsel
    asked Mr. Beck what figure he used as the current contract rate in his analysis. Tr. vol. 1,
    233:18–19, 233:23–24. Mr. Beck was unable to give a clear answer. See, e.g., id. 234:22–235:3
    (“Q. Well, if I said to you, are you able to tell me, you know, just based on looking at your
    report, what current contract rate you used for your analysis, would you be able to get to that rate
    just by looking at your report? A. I wouldn’t. The – the rate – the advertised rate only matters
    now. Never mind.”).
    Further, Mr. Beck initially testified that his determination of residual value included a
    deduction for the stumpage payments that a hypothetical purchaser would make to the Forest
    Service. Id. 248:19–23. When pressed, however, he conceded that his cost estimate did not
    include those payments. Id. 249:19–23.
    Finally, Mr. Beck testified that average logging costs during the relevant time period
    would have been $289.15 per MBF. Id. 258:16–21. Yet in his initial report, which was prepared
    to support a claim for breach-of-contract damages, he had estimated costs of $514.86 per MBF in
    the last six months of 2013. Id. 260:1–14. He was unable to explain this substantial disparity. See
    id. 260:4–9, 260:12–14 (stating of his own expert report, “I’m not familiar with this—this
    document”); id. 261:9–20 (“I think that $514 reflects the fact there was a heck of lot more
    helicopter logging to begin with. I’m not sure. I’d have to spend more time studying it.”). Given
    that increased logging costs would affect the rate a purchaser would be willing to pay for timber,
    this disparity is a critical one. Mr. Beck’s inability to answer questions and seeming lack of
    preparation at trial further undermines the Court’s confidence in his analysis.
    D.      Testimony of David Bishop
    At trial, the government presented the testimony of David Bishop, the pre-sale forester
    for the McKenzie River Ranger District. Tr. vol. 2, 328:25–329:1. Mr. Bishop has been
    employed by the Forest Service since 1975, id. 329:8–9, 329:15–20, and has been stationed at
    the Willamette National Forest (after previously being stationed there from 1979 to 1986) since
    1990, id. 330:7–13. Over the last thirty-plus years, Mr. Bishop has conducted numerous
    appraisals in connection with timber sales within the Willamette National Forest, id. 330:16–25;
    see also id. 344:7–14 (testifying that he performs five or six appraisals per year on timber in the
    Willamette National Forest), including an appraisal of the original Trapper timber sale in 2003,
    id. 333:3–334:3, 334:8–9, 336:9–11, 344:6–17; see also JX 4 (Forest Service Appraisal of
    original Trapper sale dated August 24, 2003). At the government’s request, and without
    26
    objection by Seneca, the Court qualified Mr. Bishop as an expert in Forest Service timber
    appraisal. Tr. vol. 2, 346:21–347:4.
    Mr. Bishop explained that the purpose of the appraisals he performs is to set an
    “advertised rate” (minimum bid) for timber sales. Id. 333:10–12, 334:15–23, 335:6–8. Pursuant
    to Forest Service policy, his objective is to set the advertised rate at a level that is between 70%
    and 85% of the winning bid. Id. 335:12–19.
    Mr. Bishop begins his work by attending and supervising a pre-sale timber cruise. Id.
    332:10–22, 333:5–9, 351:6–13. The sole purpose of a Forest Service cruise is to determine the
    volume of the timber, id. 332:23–333:2; the cruise is not intended to determine its grade or
    quality, id. 351:14–352:2; see also id. 353:24–354:14. The cruise volume is used to appraise the
    value of the timber. Id. 333:5–12.
    As Mr. Bishop described in detail at trial, see id. 336:8–344:5, with the timber volume in
    hand (and through the appraisal process), id. 334:20–23, he uses Forest Service software to
    determine the appropriate advertised rate, id. 341:19–22. The data inputs used to appraise timber
    are updated on a monthly basis. Id. 344:3–5, 365:1–366:24.
    Mr. Bishop used the Forest Service software to appraise the original Trapper sale in 2003.
    Id. 334:10–13, 334:25–335:3, 336:8–11. That appraisal resulted in an advertised rate of $83.52
    per CCF. Id. 337:1–9; JX 4 at 1 (Mr. Bishop’s 2003 appraisal of the original Trapper sale).
    Seneca’s winning bid was $117.25 per CCF. JX 8. The advertised rate ($83.52 per CCF) was
    71.2% of this winning bid, thus meeting the Forest Service’s target. See Tr. vol. 2, 362:3–6.
    Mr. Bishop used the same methodology to conduct “a hypothetical appraisal of the
    Trapper Timber Sale as if the original 149-acre sale had been sold on May 9, 2016, rather than
    [in] 2003.” Id. 347:13–16, 347:22–348:1. That effort yielded a hypothetical advertised rate of
    $52.15 per CCF, id. 350:2–5, which is substantially below the 2003 advertised rate of $83.52 per
    CCF, id. 350:7–10. Mr. Bishop attributed the difference to significant increases in logging costs
    from 2003 to 2016. See id. 379:14–25.
    Mr. Bishop used the hypothetical advertised rate of $52.15 per CCF to project the
    winning bid in the hypothetical sale. Id. 348:2–9. He adjusted that advertised rate by the
    percentage by which the bid premium in Seneca’s 2003 Trapper bid exceeded the 2003
    advertised rate (i.e., 40.39%). 14 The result—$73.21 per CCF—is what the Forest Service
    software calculates a hypothetical purchaser would have paid had the Trapper sale been held in
    2016. See Def.’s Resp. at 39–40.
    Mr. Bishop testified that, since 1990, he has performed four or five timber appraisals per
    year (and assisted in one or two others annually) in the Willamette National Forest, employing
    the Forest Service software he described. See Tr. vol. 2, 344:6–17. Mr. Bishop also explained
    that he typically attends the auctions for sales he has appraised to assess the accuracy of his
    14
    The “bid premium” is the difference between the advertised rate and the rate at which the
    timber ultimately is sold. Tr. vol. 2, 335:20–23.
    27
    appraisals. Id. 344:18–345:1. He then takes into account the information he has learned in
    performing future appraisals. Id. 345:2–4. In addition, the Forest Service conducts reviews and
    issues reports addressing how well each district performs in accomplishing its target of setting
    minimum bids in timber sales at 70–85% of the winning bid. Id. 345:5–11.
    Mr. Bishop was a credible witness and, given his many years of experience conducting
    Forest Service appraisals, his opinions are entitled to significant weight. In addition, the
    methodology that he employed—which utilized the software that the Forest Service routinely
    uses to determine the minimum bid price—was sound. Further, Mr. Bishop’s opinion, unlike Mr.
    Beck’s, directly addresses the requirement in CT9.52 that contract rates be compared with “the
    rates paid for comparable timber on the same National Forest.” JX 10 at 111. Mr. Bishop did not
    attempt to determine the value of the Trapper timber on the open market. See Tr. vol. 2, 355:4–8.
    His analysis was designed to determine the price at which the timber would have sold had the
    Forest Service held a sale in the six months before May 9, 2016, the date of the partial
    termination. See id. 355:6–11, 348:5–9; see also Def.’s Br. at 38–40.
    To be sure, the Forest Service’s appraisal system is not invariably accurate. But Mr.
    Beck’s statement—that the agency’s appraisals “never seem to be right . . . especially in a sale
    like Trapper”—is not supported by the record. See Tr. vol. 1, 233:25–244:1; see also id. 244:4–
    15 (“How can you appraise a sale if you’re not . . . looking at the quality of the log? . . . how can
    you make a determination of what the value is? And that’s what an appraisal is. It’s valuation.”).
    Mr. Beck admitted that he had never studied how frequently the Forest Service’s appraisals met
    their target. Id. 243:19–22. And the fact is that Mr. Bishop used the same methodology for the
    appraisal of the hypothetical 2016 sale as he did for the original Trapper sale in 2003, which, as
    described above, met the Forest Service’s target. Tr. vol. 2, 334:10–13.
    Seneca also references five timber sales of “significant volume” on which it bid in 2016
    and in which its “bid was a minimum of 1.75 to nearly seven times the advertised bid value.”
    Pl.’s Br. at 25 (citing JX 96). The document in which these sales are reflected was prepared by
    the government to illustrate, among other things, that the value Mr. Beck ascribed to the Trapper
    timber was far higher than any of Seneca’s bids for timber sales in the Willamette National
    Forest between 2002 and 2019. See Tr. vol. 2, 363:3–6. It includes a list of more than a hundred
    sales on which Seneca bid over the course of seventeen years. See JX 96. In many instances, it
    reflects that the Forest Service met the 70–85% target; in others it did not. Mr. Bishop
    acknowledged that it was not uncommon for the total bid to dramatically exceed the appraised
    value. See Tr. vol. 2, 364:4–7. But it is impossible to determine from the document why the
    Forest Service did not meet its target in particular cases, including for the five sales Seneca has
    cherry-picked out of the list. And because the Forest Service did in fact meet its target for the
    original Trapper timber sale in 2003, it seems more likely than not that the appraisal conducted
    for a hypothetical Trapper timber sale held in 2016 was also accurate.
    In short, the Court assigns greater weight to Mr. Bishop’s opinion than it does to Mr.
    Beck’s. It concludes that Seneca has failed to show that a reasonable purchaser would have paid
    a rate for the timber sold in the hypothetical 2016 sale that was higher than the applicable
    contract rate. Nor did Seneca demonstrate with reasonable certainty how much higher those rates
    28
    would have been. Therefore, the Court concludes that Seneca is not entitled to an award of
    damages under CT9.52.
    Out-of-Pocket Expenses
    Under either CT9.51, CT9.52, or CT9.53, Seneca was entitled to secure reimbursement
    for its out-of-pocket expenses as defined in BT6.02, see JX 10 at 111–12 (CT9.51, CT9.52, and
    CT9.53), i.e., its “unrecovered costs arising directly from performing the contract as a result of
    an interruption of operations and occurring prior to contract termination,” JX 12 at 30 (BT6.02).
    In accordance with the COFD concerning Seneca’s breach-of-contract claim, see JX 84 at 15, the
    Forest Service reimbursed Seneca for out-of-pocket expenses in the amount of $141,327.98, Pl.’s
    Br. at 22. That amount was based on the difference between the original road reconstruction
    package for the Trapper sale and the modified sale that the Forest Service developed for
    purposes of attempting to settle Seneca’s claim. See JX 80 at 2 (noting the “costs of specified
    road reconstruction package no longer used”); see also Tr. vol. 1, 146:19–147:4 (discussing JX
    80).
    At trial, Brian Carlin, Seneca’s Senior Vice President and Chief Financial Officer,
    acknowledged that he “ha[d] no idea” whether or not the $141,327.98 that the Forest Service
    paid Seneca accurately reflects the expenses Seneca incurred for roads that ultimately were not
    needed for the modified sale. See Tr. vol. 1, 147:5–8. He acknowledged that Seneca did not
    conduct an analysis that would have allowed it to make a similar determination. Id. 146:11–18.
    Nonetheless, Seneca contends that it is still owed additional reimbursement for road costs
    (as well as the expenses of engineering services and bond premiums it paid). See Pl.’s Br. at 22;
    Pl.’s Reply at 4–5. Relying upon entries in Seneca’s general ledger, Mr. Carlin testified that
    Seneca spent a total of $238,257.85 on roads, Tr. vol. 1, 135:8–12, $21,004 for engineering
    expenses, id. 136:20–25, and $4,397 for bond premiums, id. 137:8–13 (referencing
    demonstrative exhibit). The total expenses, according to Mr. Carlin, were $263,658.85. Id.
    138:17–139:2.
    Seneca urges the Court to accept this figure based on Mr. Carlin’s testimony and to use a
    pro rata approach to determine what portion of the total represents unrecovered costs, i.e.,
    expenses incurred which would not have been incurred in harvesting the trees under the modified
    sale. See Pl.’s Br. at 22. That approach, Seneca argues, results in a determination that Seneca’s
    out-of-pocket expenses total $207,536.14, which leaves a balance owing it of $66,208.16. Id.;
    see also Tr. vol. 1, 139:7–8. 15
    The Court agrees with the government that Seneca has not established its entitlement to
    the additional reimbursement it seeks. Provisions CT9.51, CT9.52, and CT9.53 state not only
    that upon a partial termination the purchaser is entitled to reimbursement for out-of-pocket
    15
    Seneca reasons that, as a result of the partial termination, it could harvest only 21.28% of the
    alleged 8,724 MBF of timber available in the original Trapper timber sale (as determined by the
    Jackson and Prochnau cruise). See Pl.’s Br. at 22. It therefore contends that it is entitled to
    reimbursement for 78.72% of its total costs ($238,257.85), or $207,536.14.
    29
    expenses, but also that the “Purchaser agrees to provide receipts or other documentation to [the]
    Contracting Officer that clearly identify and verify actual expenditures.” JX 10 at 111–12
    (stating the same at CT9.51, CT9.52, and CT9.53).
    There is nothing in the record demonstrating (and Seneca does not appear to argue) that it
    provided the CO with receipts or documentation that clearly identified and verified its actual
    expenditures for any of these items. Further, Seneca has not provided such receipts or
    documentation to the Court. Instead, it relies entirely upon Mr. Carlin’s testimony, which he
    based on data from Seneca’s general ledger. Tr. vol. 1, 139:17–19; see also id. 139:20–140:4
    (observing that “the various expenditures . . . associated with the [original] Trapper” sale “go[]
    back a long way,” and so he was “relying on [Seneca’s] general ledger system to a great degree,”
    but that he “believe[d]” his summary was “a proper reflection of expenses incurred”). But even
    then, Seneca did not seek to introduce the ledgers themselves into evidence. 16
    On cross-examination, Mr. Carlin was asked whether any of the expenses Seneca now
    claims could be verified “by looking at receipts, contracts, purchase orders, canceled checks, [or]
    documents of that nature.” Id. 143:5–9. Mr. Carlin responded that Seneca did have
    documentation for the road expenditures “in a file . . . at the office” that he had secured from the
    accounting department and which he had looked at the preceding Friday. Id. 143:10–23. Mr.
    Carlin did not know whether this documentation was provided to the government. Id. 143:24–
    144:7. He acknowledged that neither he nor anyone he could name at Seneca had done so. Id.
    144:12–145:7; see also id. 147:12–23 (agreeing that he “ha[d] not” provided receipts or other
    documentation, and that he was “not aware of anyone specifically at Seneca who has”).
    In any case, if there is supporting documentation for the road expenditures in a file, it was
    also never introduced into evidence. The Court concludes, therefore, that Seneca has failed to
    provide adequate substantiation for its claim that it is entitled to additional reimbursement for
    out-of-pocket expenses.
    CONCLUSION
    On the basis of the foregoing, the government is entitled to judgment on Seneca’s
    breach-of-contract claim. Each party shall bear its own costs. The Clerk is directed to enter
    judgment accordingly.
    IT IS SO ORDERED.
    s/ Elaine D. Kaplan
    ELAINE D. KAPLAN
    Chief Judge
    16
    Mr. Carlin testified by reference to a demonstrative exhibit, Pl.’s Ex. 212, which the Court
    permitted him to use over the government’s objection, see Tr. vol. 1, 141:4–17.
    30