David Boland, Inc. v. United States ( 2022 )


Menu:
  •                                    No. 22-131C
    (Filed: Monday, October 17, 2022)
    **************************                            28 U.S.C 1491 (2018);
    DAVID BOLAND, INC.,                                   Contract Disputes Act,
    
    41 U.S.C. §§ 7101-09
    ,
    Plaintiff,                      7103 (2018);
    v.                                                    FAR 52.233-3;
    Contracts; motion to
    THE UNITED STATES,                                    dismiss; subject matter
    Defendant.                      jurisdiction; failure to
    state a claim
    **************************
    Denis L. Durkin, Orlando, FL, for plaintiff. Michael S. Vitale and
    Brian V. Johnson, of counsel.
    Jimmy S. McBirney, Trial Attorney, United States Department of
    Justice, Civil Division, Commercial Litigation Branch, Washington, DC,
    with whom were Brian M. Boynton, Principal Deputy Assistant Attorney
    General, Patricia M. McCarthy, Director, and Steven J. Gillingham,
    Assistant Director, for defendant. Brett R. Howard, Deputy District Counsel
    and James M. Inman, Trial Attorney, of counsel.
    OPINION
    BRUGGINK, Judge.
    The United States, through the United States Army Corps of
    Engineers, contracted with plaintiff, David Boland, Inc. (Boland), to
    construct a new building for a “military and training center” in Dublin,
    California. Pending is the government’s motion to dismiss four of the
    complaint’s six counts, either for lack of subject matter jurisdiction or failure
    to state a claim on which relief can be granted. The motion is fully briefed,
    and oral argument was held on October 13, 2022. We grant in part and deny
    in part.
    BACKGROUND 1
    This complaint arises out of a government contractor’s unsuccessful
    requests for equitable adjustments (REA). The government awarded Boland
    with Contract No. W912QR-16-C-0013 (the contract) to construct a new
    building for U.S. Army Reserve personnel on July 6, 2016. The parties
    encountered obstacles, which prompted Boland’s disputed REAs.
    Bid Protest Delay (Counts I and II)
    Shortly after the contract was awarded, an unsuccessful bidder filed a
    protest with the Government Accountability Office (GAO). In compliance
    with regulatory requirements, the government issued a notice to suspend
    performance. 2 Several months later, GAO resolved the protest, and the
    government issued a notice to proceed on November 28, 2016.
    Boland believed that the bid-protest performance delay increased its
    cost of performance. Particularly, Boland claimed that it could not “secure
    certain previously selected subcontractors and suppliers” and “enter[ed] into
    contracts with other companies at increased costs.” Compl. Ex. B. To recover
    for those costs, Boland submitted an uncertified REA (2017 REA) for
    $262,060 on October 25, 2017. 
    Id.
    Not long after, the government informed Boland that its 2017 REA
    needed to “provide actual quotes from [its] subcontractors and suppliers.”
    Mot. to Dismiss App. 1. Boland could not, in its own view however, “isolate
    the additional actual costs incurred” and instead used “published standards”
    to estimate its increased costs. Compl. ¶ 22. Ultimately, Boland never
    provided the government with actual cost data, leaving the issue unresolved. 3
    1
    The background is drawn from the complaint and the attached materials.
    2
    Under FAR 33.104(c)(1), the contracting officer “shall immediately
    suspend performance” when the “agency receives notice of a protest from
    the GAO.”
    3
    After several years, Boland eventually certified its 2017 REA and requested
    a final decision, which the government never issued.
    2
    At an impasse, Boland submitted a second certified REA on
    November 2, 2020 (2020 REA), seeking an additional $329,296 in
    unabsorbed home office overhead incurred during the bid-protest delay.
    Compl. Ex. C. While Boland still “maintain[ed] that there were significant
    increased costs of construction,” it “resolved itself to the fact” that it cannot
    “provide actual cost records.” 
    Id.
     Nevertheless, it believed that the
    government owed compensation for unabsorbed overhead. On February 9,
    2021, the government issued a Contracting Officer’s Final Decision (COFD)
    denying Boland’s 2020 REA because it was untimely and failed to meet the
    regulatory requirements to recover unabsorbed overhead. 4
    Power Delay (Counts III and IV)
    Completion of the contract required a power supply to the
    construction site. To supply the necessary power, the government was
    required to contract with Pacific Gas and Electric Company (PG&E).
    Setbacks ensued, and the provision of power was delayed. While the parties
    dispute who was responsible for the power delay, they appear to agree on the
    following facts.
    PG&E needed to inspect the construction site. When PG&E inspected
    the site, it noted several deviations from what the contract required. Boland
    eventually corrected those variances, and the government then signed the
    contract with PG&E. Despite site readiness, installation of the power
    transformer was scheduled to take place in a couple of months. Both parties
    understood that this timeframe would delay the project’s completion, but the
    government claimed that nothing could be done to speed up the process. With
    waiting being the only option, the transformer was installed 8 weeks later.
    To recover for the extended project completion time in 2018, Boland
    submitted a certified REA for $311,411.22 (Power REA), maintaining that
    the power delay “was within the government’s responsibility.” Compl. Ex.
    4
    The contracting officer determined that the 2020 REA was untimely under
    FAR 52.243-4, the FAR provision for “Changes.” While 52.243-4 was
    inapplicable, a timeliness issue did exist. As we later discuss, REAs for bid-
    protest delay must be submitted within 30 days of a notice to proceed under
    FAR 52.233-3.
    3
    G. In its REA, Boland claimed that late power installation delayed the
    project’s completion by 82 days. The government denied the REA and
    instead agreed only to a non-compensable time extension. Unsatisfied with
    the government’s offer, Boland hired an independent consulting firm, AM
    Sist Consulting (AMS). AMS concluded that the government owed Boland
    compensation for 70 additional days. Based on AMS’s report, Boland
    resubmitted its REA in 2020 and requested an adjusted amount of $241,636.
    The contracting officer denied Boland’s adjusted Power REA. In her COFD,
    the contracting officer explained that it was Boland’s protracted site
    preparation that delayed execution of the PG&E power supply contract.
    CIP Wall Repair (Counts V and VI)
    Construction of the building required Boland to install “cast in place”
    (CIP) walls. After Boland installed part of the first wall, it discovered defects
    and promptly notified the government. To assess the situation, Boland hired
    an engineer who evaluated the wall’s defects and concluded that they did not
    “impact the structural adequacy of the wall.” Compl. Ex. J (CIP Wall REA).
    Despite the report, the government feared “increased liability” and issued a
    stop-work order. Compl. ¶ 72. During that time, tests on the wall continued,
    and Boland eventually addressed the faulty installation process successfully
    with a revised concrete mix. See Compl. Ex. J. For the CIP walls already
    installed, Boland compiled a supplementary report to demonstrate the wall’s
    structural integrity and show that it could be adequately repaired. The
    government agreed and lifted the stop-work order.
    The engineering tests increased Boland’s costs. So too, did the stop-
    work order delay. Hoping to recoup its losses, Boland submitted a certified
    REA in 2018, and again in 2019, for $200,967 (CIP Wall REA). Negotiations
    ensued, and a provisional agreement was reached. The agreement fell
    through, however, over allegedly inaccurate scheduling information. In her
    COFD, the contracting officer concluded that Boland was entitled to only
    $18,975—the cost of certain tests which were performed at the government’s
    request and outside of Boland’s contractual obligations.
    Procedural History
    Boland filed its complaint on February 8, 2022. It alleges in Counts I,
    III, and V that it is entitled to equitable adjustments. Each REA-based count
    4
    has a parallel count—Counts II, IV, and VI—which asserts that the
    government breached its implied duty of good faith and fair dealing. The
    United States has moved to dismiss Counts I, II, IV, and VI for lack of subject
    matter jurisdiction or failure to state a claim on which relief can be granted.
    It has not moved to dismiss Counts III and V.
    DISCUSSION
    I. Subject Matter Jurisdiction
    Like all federal courts, the Court of Federal Claims is one of “limited
    jurisdiction” that is “defined . . . by federal statute.” Badgerow v. Walters,
    
    142 S. Ct. 1310
    , 1315 (2022). The relevant jurisdictional statute here is the
    Tucker Act, 
    28 U.S.C. § 1491
     (2018), which “confers jurisdiction upon the
    Court of Federal Claims over the specified categories of actions brought
    against the United States,” Fisher v. United States, 
    402 F.3d 1167
    , 1172 (Fed.
    Cir. 2005) (en banc). It includes actions against the United States founded on
    “any express or implied contract with the United States.” § 1491(a)(1).
    The Contract Disputes Act (CDA) “grants the court jurisdiction over
    actions brought on claims within twelve months of a contracting officer’s
    final decision.” James M. Ellet Const. Co. v. United States, 
    93 F.3d 1537
    ,
    1541 (Fed. Cir. 1996); 
    41 U.S.C. § 7104
    (b)(3). For jurisdictional purposes,
    then, there must be “both a valid claim and a contracting officer’s final
    decision on that claim.” M. Maropakis Carpentry, Inc. v. United States, 
    609 F.3d 1323
    , 1327 (Fed. Cir. 2010). The CDA does not define a “claim,”
    though, so we must “look to the definition of ‘claim’ in the FAR.” Creative
    Mgmt. Servs. v. United States, 
    989 F.3d 955
     (Fed. Cir. 2021). Section 2.101
    provides that a “[c]laim means a written demand or written assertion by one
    of the contracting parties seeking, as a matter of right, the payment of money
    in a sum certain, the adjustment or interpretation of contract terms, or other
    relief arising under or relating to the contract.” 
    48 CFR § 2.101
     (2021).
    The plaintiff “bears the burden of establishing subject matter
    jurisdiction by a preponderance of the evidence.” Reynolds v. Army & Air
    Force Exch. Serv., 
    846 F.2d 746
    , 748 (Fed. Cir. 1988). When a defendant
    moves to dismiss for lack of subject matter jurisdiction, the court assumes
    that the undisputed facts in the complaint are true and draws reasonable
    inferences in the plaintiff’s favor. Acevedo v. United States, 
    824 F.3d 1365
    ,
    1368 (Fed. Cir. 2016).
    5
    In its motion to dismiss, the government argues that Count I (based
    on the REAs for bid-protest delay) was improperly submitted to the
    contracting officer because Boland did not present its REAs for increased
    supplier costs and unabsorbed overhead at the same time. In Counts II, IV,
    and VI (the claims for bad faith), however, the government argues that
    Boland never submitted those claims to the contracting officer at all. The
    issue, then, is whether Boland submitted valid claims to the contracting
    officer.
    A. Count I—Boland’s REAs for Bid-Protest Delay
    In Count I—based on Boland’s 2017 REA for increased costs and its
    2020 REA for unabsorbed overhead—Boland alleges that the government’s
    “unilateral directive to suspend performance on the contract delayed the
    project’s completion, increased Boland’s cost of construction, and
    constituted a direct change to the Contract,” entitling it to an equitable
    adjustment. Compl. ¶ 93.
    The government moves to dismiss Count I for lack of subject matter
    jurisdiction because Boland’s complaint seeks to impermissibly combine two
    REAs into one. While Boland submitted two separate REAs to the
    contracting officer (the 2017 and 2020 REAs), it now combines those two
    REAs into one count. 5 The government argues this is impermissible because
    the two claims were separately presented to the contracting officer, and this
    court can only have jurisdiction if Boland presents those REAs as separate
    counts. It also argues that this court cannot have jurisdiction over the 2017
    REA because it was a “facially invalid claim” that failed to provide actual
    cost data.
    For jurisdictional purposes, all that the CDA requires is a “valid claim
    and a contracting officer’s final decision on that claim.” Maropakis, 
    609 F.3d at 1327
    . In this case, Boland satisfied those two jurisdictional requirements.
    Boland’s 2017 and 2020 REAs (which together make up Count I) were
    5
    Within the same argument, the government asserts that Boland withdrew
    its 2017 REA for increased subcontractor and supplier costs when it later
    submitted its 2020 REA for only unabsorbed overhead. We find no merit in
    this argument. In its 2020 REA, Boland stated that it still “maintain[ed] that
    it was entitled to” recover increased costs of construction. Compl. Ex. C.
    6
    certified claims submitted to the contracting officer, and Boland filed its
    complaint within 12 months of the contracting officer’s final decision or lack
    thereof. These undisputed facts are all that are necessary to establish
    jurisdiction over Count I.
    About the government’s suggestion that Boland needed to submit one
    combined claim to the contracting officer, we know of no such requirement.
    Not only does the government’s position lack support in the CDA—which
    does not speak to how counts must be structured—but it also subverts the
    CDA’s purpose. Requiring Boland to resubmit two previously denied
    certified claims as one would be “inimical to two goals of the CDA:
    providing for the efficient and fair resolution of contract claims.” Reflectone,
    60 F.3d at 1580; cf. Ellett, 
    93 F.3d at 1545
     (stating that it would be a “futile
    act” for a contractor to formally submit a claim to the contracting officer after
    the contracting officer has already made a final determination). All that the
    CDA requires is that a contracting officer have the first opportunity to review
    a contractor’s claim. Scott Timber Co. v. United States, 
    333 F.3d 1358
    , 1366
    (Fed. Cir. 2003). The contracting officer had that opportunity here, so
    Boland’s resubmission of one combined REA would serve no purpose.
    Finally, there is no merit to the government’s argument that Boland’s
    2017 REA was a “facially invalid claim” because it failed to include actual
    cost data. “[N]either the CDA nor its implementing regulations . . . requires
    submission of a detailed cost breakdown or other specific cost-related
    documentation with the claim.” H.L. Smith, Inc. v. Dalton, 
    49 F.3d 1563
    ,
    1564 (Fed. Cir. 1995). An REA satisfies the definition of a claim, Reflectone,
    Inc. v. Dalton, 
    60 F.3d 1572
    , 1577 (Fed. Cir. 1995), and nothing more is
    required, Maropakis, 
    609 F.3d at 1327
    . Thus, this court has jurisdiction over
    Count I, and we deny the government’s motion to dismiss it.
    B. Counts II, IV, and VI—Boland’s Claims for Breach of Implied Duties
    Boland asserts in these three counts that the government breached its
    implied duty of good faith and fair dealing. The government counters that
    Boland never presented these claims for breach to the contracting officer. We
    must decide, then, whether Boland’s implied duty claims are “based on [a]
    claim previously presented to and denied by the contracting officer.” Scott
    Timber, 
    333 F.3d at 1365
    .
    “[T]wo claims may be considered the same for CDA jurisdictional
    purposes if they arise from the same operative facts, claim essentially the
    7
    same relief, and merely assert differing legal theories for that recovery.”
    Kiewit Infrastructure W. Co. v. United States, 
    972 F.3d 1322
    , 1328 (Fed. Cir.
    2020) (internal quotations omitted). In Reliance Insurance Company v.
    United States, the Federal Circuit explained that a request for equitable
    adjustment is not a “clear and unequivocal claim” for a violation of the “duty
    of good faith.” 
    931 F.2d 863
    , 866 (Fed. Cir. 1991). On that basis, the court
    determined that it had no jurisdiction to consider any separate claims based
    on breach of contract for good faith and fair dealing. 
    Id.
     We do not read
    Reliance to mean that an REA can never be a clear and unequivocal claim
    for breach of contract. Cf. Crown Coat Front Co. v. United States, 
    386 U.S. 503
    , 511 (1967) (“[T]he contractor has agreed in effect to convert what
    otherwise might be claims for breach of contract into claims for equitable
    adjustment.”). Rather, Reliance simply rejects the position that an REA is by
    itself also a claim for breach of contract. We therefore must engage in a fact-
    based inquiry to determine whether Boland’s claims for breach of contract
    are the same as its requests for equitable adjustments. We address each claim
    in turn.
    1. Count II—Bid-Protest Delay
    Three things must be true for two claims to be considered the same:
    (1) the claims are based on the same operative facts; (2) the claims seek
    essentially the same relief; and (3) the claims assert the same or similar legal
    theory for relief. See Kiewit, 972 F.3d at 1328. First, the 2017 REA, which
    sought to recover only for increased subcontractor and supplier costs. The
    government denied Boland’s 2017 REA for failure to provide actual cost
    data. Boland argues in this court that the government breached its duty of
    good faith and fair dealing because its denial was “pretextual” since the
    government knew that providing actual cost data was not possible. Compl. ¶
    21.
    “Operative facts are the essential facts that give rise to a cause of
    action.” Renda Marine, Inc. v. United States, 
    71 Fed. Cl. 378
    , 389 (2006).
    The operative facts necessary to establish a claim that the government has
    breached its implied duties include whether the government “destroy[ed] the
    reasonable expectations of the other party,” or “interfere[d] with or fail[ed]
    to cooperate in the other party’s performance.” Centex Corp. v. United States,
    
    395 F.3d 1283
    , 1304 (citing Restatement (Second) of Contracts, § 205
    (1981)). By contrast, a claim to recover increased costs incurred from bid-
    protest delay need only show a causal relationship between the “stop-work
    8
    order” and an “increase” in “the Contractor’s cost[s].” FAR 52.233-3.
    As Boland appeared to concede at oral argument, its 2017 REA “did
    not include the operative facts underlying a breach of the duty of good faith
    and fair dealing.” Walsh Constr. Co. v. United States, 
    132 Fed. Cl. 282
    , 291
    (2017). Instead, Boland merely informed the government of “price increases”
    and requested an equitable adjustment. Compl. Ex. E. Nothing in Boland’s
    2017 REA suggests that the government acted in bad faith or “pretextual[ly].
    Compl. ¶ 21. At best, Boland’s request for a final decision simply
    acknowledged that the government demanded actual cost data. But that
    acknowledgment, by itself, is not a “clear and unequivocal statement that
    gives the contracting officer adequate notice of the basis . . . of the claim.”
    Scott Timber, 
    333 F.3d at 1365
    .
    Next, the 2020 REA. Boland’s 2020 REA requested reimbursement
    for its unabsorbed overhead during the bid protest. Compl. Ex. C. Boland
    argues now that the government breached its duty of good faith and fair
    dealing by erroneously denying the 2020 REA.
    We can readily reject this argument. To establish jurisdiction,
    Boland’s claim to the contracting officer must allege bad faith (or at least the
    same operative facts). Maropakis, 
    609 F.3d at 1327
    . Yet Boland does not
    point to its claim. It curiously points instead to the contracting officer’s final
    decision, arguing that the contracting officer’s misapplication of the law was
    in bad faith. But an erroneous decision—even the most egregious—could not
    itself be part of the original claim submitted to the contracting officer. More
    to the point, this court “does not review the CO’s decision; it conducts de
    novo review of the claims that were put before the CO.” Accord HCIC
    Enterprises, LLC v. United States, 
    149 Fed. Cl. 297
    , 301 (2020) (emphasis
    added); Bell/Heery v. United States, 
    106 Fed. Cl. 300
    , 308 (2012) (“This
    court hears suits directly on the claim, not appeals of contracting officers’
    decisions.” (internal quotations omitted)). We have jurisdiction to review
    only Boland’s claim to the contracting officer, and that claim did not include
    a breach of the implied duty of good faith. Thus, we dismiss Count II for lack
    of subject matter jurisdiction.
    2. Count IV—Permanent Power Delay
    The impediments to securing power for the construction site delayed
    the project’s completion. Boland’s Power REA claimed that it “was within
    the government’s responsibility” to reach an agreement with PG&E to
    9
    maintain schedule. Compl. Ex. G. Similarly, in Count IV of Boland’s
    complaint, it argues that the government’s “inability to timely enter into an
    agreement with PG&E . . . constitute[d] a breach of the duty of good faith
    and fair dealing.” Compl. ¶ 105.
    Boland’s Power REA does not rest on the same operative facts as a
    breach of implied duties claim nor was the latter claim expressly presented
    to the contracting officer. To recover for performance delay, a contractor
    must “establish the extent of the delay, the contractor’s harm resulting from
    the delay, and the causal link between the government’s wrongful acts and
    the delay.” Essex Electro Engineers, Inc. v. Danzig, 
    224 F.3d 1283
    , 1295
    (Fed. Cir. 2000). On the other hand, a breach of implied duties claim looks
    to whether the government destroyed the reasonable expectations of the other
    party or interfered with or failed to cooperate in the other party’s
    performance. While these may sound similar, a breach of the implied duty of
    good faith requires something more. Courts “presum[e] that government
    officials act in good faith.” Am-Pro Protective Agency, Inc. v. United States,
    
    281 F.3d 1234
    , 1239 (Fed. Cir. 2002). To prevail, a contractor must show
    “that the government had a specific intent to injure it.” Caldwell & Santmyer,
    Inc. v. Glickman, 
    55 F.3d 1578
    , 1581 (Fed. Cir. 1995).
    Here, Boland asserts facts that, if proven, would entitle it to recover
    for performance delay. Even so, Boland’s Power REA contains nothing to
    suggest that “the government had a specific intent to injure it.” 
    Id.
     A charge
    that the government did not satisfy its contractual obligations, without more,
    is not “specific enough to give the officer notice of [a claim of failure to act
    in good faith] and allow him to make an informed judgment.” Monterey
    Consultants, Inc. v. United States, 
    159 Fed. Cl. 641
    , 651 (2022). For that
    same reason, Boland also could not have expressly presented the claim, as it
    would have required Boland to allege a specific intent to injure. As a result,
    Boland’s Power REA is not the same as a claim for breach of implied duties
    nor was it expressly presented to the contracting officer. We therefore
    dismiss Count IV for lack of subject matter jurisdiction.
    3. Count VI—CIP Wall Delay
    Finally, in Boland’s CIP Wall REA, Boland alleged that the
    government’s suspension of work was unwarranted and unreasonable.
    Compl. Ex. J. In Count VI, however, Boland claims that the government’s
    “inability to engage [with Boland] in a timely manner,” “its unjustified and
    10
    unsupported stop work order,” “its denial of Boland’s REA,” and “its
    repudiation of [the provisional] agreement” all violated the government’s
    duty of good faith and fair dealing. Compl. ¶ 112.
    Once again, Boland’s breach of good faith claim does not rest on the
    same operative facts as the CIP Wall REA. While Boland’s CIP Wall REA
    may have asserted the operative facts for a performance-delay claim, it did
    not include an assertion that “the government had a specific intent to injure
    it.” Caldwell & Santmyer, 
    55 F.3d at 1581
    . For that reason, its CIP Wall REA
    and its implied duty claim are not the same. Thus, we dismiss Count VI for
    lack of subject matter jurisdiction.
    II. Failure to State a Claim 6
    The government moves to dismiss Count I for failure to state a claim.
    Count I involves Boland’s 2017 and 2020 REAs for increased subcontractor
    and supplier costs and unabsorbed overhead incurred during the bid-protest
    delay.
    On a Rule 12(b)(6) motion to dismiss, the court will “consider the
    complaint in its entirety, as well as other sources courts ordinarily examine
    when ruling on Rule 12(b)(6) motions to dismiss, in particular, documents
    incorporated into the complaint by reference, and matters of which a court
    may take judicial notice.” Tellabs, Inc. v. Makor Issues & Rights, Ltd., 
    551 U.S. 308
    , 322 (2007). The court accepts as true the “well-pleaded factual
    allegations” in the complaint and determines whether those allegations
    “plausibly give rise to an entitlement to relief.” Ashcroft v. Iqbal, 
    556 U.S. 662
    , 679 (2009). If the well-pleaded facts asserted by the plaintiff do not
    “entitle him to a remedy” under the law, the claim should be dismissed. Perez
    v. United States, 
    156 F.3d 1366
    , 1370 (Fed. Cir. 1998).
    Under FAR 52.233-3, a contractor is entitled to an equitable
    adjustment for bid-protest delay if two things are true: (1) the “stop-work
    order” increased the contractor’s cost of performance; and (2) the contractor
    “asserts its right to an adjustment within 30 days” of the notice to proceed,
    or the contracting officer “act[s] upon” an untimely proposal. FAR 52.233-
    6
    Because we conclude that we have no jurisdiction over Counts II, IV, and
    VI, we do not decide whether they state a claim. We review only Count I—
    the only remaining count subject to the motion to dismiss.
    11
    3(b). This seemingly straightforward provision is at the center of the current
    controversy.
    The parties do not dispute that Boland’s bid-protest REAs were
    untimely. They disagree, however, over whether Boland’s failure to comply
    with the deadline bars the claim. In the government’s view, the claims were
    late, and the contracting officer did not “act upon” either proposal. On the
    other hand, Boland argues that its untimeliness is not dispositive—not
    because the contracting officer acted on the proposal, but because the
    regulation “does not speak to what happens if a claim is not made within 30
    days.” Pl.’s Resp. 29.
    We are unpersuaded by Boland’s strained reading of FAR 52.233-3.
    Despite Boland’s suggestion to the contrary—for which it cites no supporting
    authority—the regulation does speak to untimely claims. The regulation
    explains that a contractor is entitled to an equitable adjustment only “if” the
    request is brought within 30 days after work resumes or the contracting
    officer acts upon the untimely claim. FAR 52.233-3(b)(2). And when
    interpreting a statute, “we look first to the word’s ordinary meaning.”
    Mohamad v. Palestinian Auth., 
    566 U.S. 449
    , 454 (2012) (using dictionaries
    to determine ordinary meaning). With that in view, the word “if”
    “introduc[es] a clause of condition,” If, Oxford Dictionary, (2d online ed.
    1989), which is “[s]omething demanded or required as a prerequisite to the
    granting or performance of something else,” Condition, Oxford Dictionary
    (2d online ed. 1989). Simply put, the regulation means what it says: if the
    contractor does not submit the REA within 30 days, the government may
    adjust the contract, but it is not required to. Compliance with the provision is
    therefore a precondition to bringing a claim.
    Finally, to bypass FAR 52.233-3 altogether, Boland appears to take
    the CDA where no contractor has taken it before. The CDA in effect
    preempts FAR 52.233-3 because the CDA allows a contractor to “bring an
    action directly on the claim in the United States Court of Federal Claims,
    notwithstanding any contract provision, regulation, or rule of law to the
    contrary.” § 7104(b) (emphasis added). Yet there is no case where Section
    7104(b) acted as an “ace in the hole” with the power to trump seemingly
    nettlesome FAR provisions. Instead, this court has consistently interpreted
    Section 7104(b) to be only jurisdictional and presupposes a valid claim
    exists. See, e.g., Westdale N.W. Ctr. v. United States, 
    154 Fed. Cl. 557
    , 576
    (2021). Boland has no underlying claim, and Section 7104(b) cannot provide
    12
    it with one.
    It is undisputed that Boland failed to present either bid-protest REA
    to the contracting officer within 30 days of the notice to proceed. As a result,
    Count I fails to state a claim, and it must be dismissed.
    CONCLUSION
    For the reasons stated above, the government’s motion to dismiss is
    granted in part and denied in part. Counts II, IV, and VI are dismissed for
    lack of subject matter jurisdiction. Count I is dismissed for failure to state a
    claim. The parties are directed to file a joint status report regarding further
    proceedings on or before November 15, 2022.
    s/Eric G. Bruggink
    ERIC G. BRUGGINK
    Senior Judge