Precision Standard, Inc v. United States ( 2016 )


Menu:
  • In the United States Court of Federal Claims
    No. 11-558C
    (Filed: June 9, 2016)
    **********************************
    PRECISION STANDARD, INC.,
    Contract Disputes Act, 
    41 U.S.C. § 609
    (a) (2012);
    Plaintiff,
    Defense Priorities and
    Allocations Systems;
    v.
    waiver of delivery dates;
    e q u i t abl e adj ust m ent ;
    conditional approval
    THE UNITED STATES,
    Defendant.
    *********************************
    _____________
    OPINION
    _______________
    BRUGGINK, Judge.
    Plaintiff, Precision Standard, Inc. (“PSI”), brings this case pursuant to
    the Contract Disputes Act, 
    41 U.S.C. § 609
    (a) (2012) and the Tucker Act, 
    28 U.S.C. § 1491
    (a) (2012) against the United States seeking equitable adjustment
    and damages arising under various contracts between it and the Defense
    Logistics Agency (“DLA” or “the Agency”), formerly known as the Defense
    Supply Center Richmond (“DSCR”). Pending is defendant’s motion for partial
    summary judgment on Counts 2 through 9 of the complaint.1 The motion is
    fully briefed, and oral argument was held on April 6, 2016. For the reasons
    stated below, we grant in part and deny in part defendant’s motion for
    summary judgment.
    1
    The complaint contains nine counts. Count 1, however, is not included in this
    motion.
    BACKGROUND2
    There are 28 contracts at issue in Counts 2 through 9 of the complaint.
    These contracts, each of which was for a particular aircraft part, were entered
    into between April 2006 and January 2009. The majority of the contracts
    required first article testing to be performed at Warner Robins Air Force Base
    (“Warner Robins”). The remainder required first article testing at Hill Air
    Force Base (“Hill”). They are listed as follows:
    Count              Contract No.         Contract Date    Part
    2                  SPM4A7-07-           March 23, 2007   Upper Thrust
    0105                                  Reverser Fan
    Cowlers
    3                  SP0407-06-M-         April 18, 2006   Structural
    9684                                  Aircraft Panels
    4                  SPM4A7-08-M-         March 31, 2008   Access Covers
    5689
    5                  SP0407-05-C-         March 28, 2005   Trailing Edge
    2028                                  Panels
    6                  SPM4A7-09-D-         July 2009        Bundle Covers
    5547
    7                  SPM4A7-08-D-         July 30, 2008    Coupling
    0316                                  Adapter Sleeves
    8(A)               SPM4A7-07-D-         March 6, 2007    Lower Left
    3180                                  Panel Aircraft
    Assemblies
    8(B)               SPM4A5-08-M-         February 22,     Access Covers
    2072                 2008
    8(C)               SPM4A7-07-M-         April 12, 2007   Fairing
    6269                                  Assemblies
    2
    The facts are drawn from the appendices filed with the parties’ briefing.
    2
    8(D)   SPM4A7-08-C-       June 6, 2008     Aircraft Fairings
    0387
    8(E)   SPM4A7-08-D-       June 23, 2008    Fuselage Fairing
    0274                                Panels
    8(F)   SPM4A7-07-M-       August 6, 2007   Aircraft Fairings
    A678
    8(G)   SPM4A7-07-M-       September 14,    Aileron Trailing
    C357               2007             Edge
    Assemblies
    8(H)   SPM4A7-08-C-       August 16, 2008 Aircraft Access
    0481                               Doors
    9(A)   SPM4A7-08-M-       November 29,     Trailing Edge
    2238               2007             Wing
    Assemblies
    9(B)   SPM4A7-08-M-       January 17,      Insulation
    4809               2008             Panels
    9(C)   SPM4A7-08-M-       February 25,     Lower Bunk
    6942               2008             Panels
    9(D)   SPM4A7-08-M-       March 14, 2008   Aircraft Floor
    7318                                Panels
    9(E)   SPM4A7-08-M-       April 1, 2008    Aircraft Fairings
    8566
    9(F)   SPM4A7-08-M-       May 16, 2008     Wheel Panel
    A725                                Assemblies
    9(G)   SPM4A7-08-M-       May 31, 2008     Aircraft
    A912                                Retainer
    Assemblies
    9(H)   SPM4A7-08-M-       June 10, 2008    Aircraft Floor
    B771                                Panels
    9(I)   SPM4A7-08-M-       July 23, 2008    Aircraft Panel
    D715                                Assembly
    3
    9(J)                SPM4A7-08-M-           August 25, 2008 Helicopter
    F252                                   Access Covers
    9(K)                SPM4A7-09-M-           January 30,       Aircraft Access
    3933                   2009              Doors
    9(L)                SPM4A7-07-M-           October 26,       Cowlings
    0637                   2006
    9(M)                SPM4A7-08-M-           March 5, 2008     Panel
    7193                                     Assemblies
    9(N)                SPM4A7-08-M-           March 21, 2008    Bulkhead Clips
    7646
    The parties set forth arguments which pertain to every contract,
    arguments which pertain to a specific group of contracts, and arguments that
    pertain to individual contracts. Before discussing these arguments, we will
    detail the facts that led to the dispute for each contract individually.
    Count 2
    DLA awarded contract number SPM4A7-07-0105 to PSI on March 23,
    2007. The contract was for 33 upper thrust reverser fan cowling covers for a
    total price of $154, 300. The first article was due for testing 120 days later, on
    July 21, 2007. Defendant claims that the Agency received the first article in
    September 2007. After receiving and testing the first article, DLA rejected it
    on January 11, 2008. In its correspondence with PSI, the Agency stated that the
    first article did not conform to the procurement specifications and pointed out
    nine specific defects. The letter also stated that PSI had the opportunity to
    correct the nonconformance and resubmit two first articles for testing, at a cost
    to PSI of $5,880.20. PSI challenged the rejection on February 14, 2008, and
    requested conditional approval. In its May 7, 2008 response, DLA denied the
    request for conditional approval and informed PSI the first article was not
    manufactured in accordance with the drawings.
    PSI submitted a second first article to Warner Robins for testing in
    September 2008. Contracting Officer (“CO”) Carl Hudson sent PSI a letter on
    April 15, 2009 informing PSI that the second first article failed inspection. The
    letter identified 10 different defects, and offered PSI the option of submitting
    another first article for testing or cancelling the contract. According to the
    4
    letter, the third re-test would cost PSI $6,062.47. In August 2009, DLA
    returned the second first article to PSI. In November 2009, DLA send PSI an
    email requesting that PSI inform the Agency whether it would submit another
    first article and requesting a revised delivery schedule or cancellation request
    by December 3, 2009. PSI did not respond to this email.
    On January 4, 2010, the contracting officer issued a unilateral
    modification P00002 cancelling the contract “at no cost or obligation to either
    party.” Def.’s App. 19A. On April 30, 2010, PSI responded with an inventory
    schedule and advised DLA that it would be submitting is termination
    settlement proposal. 
    Id.
     at 19C. DLA responded on May 4, 2010 with a show
    cause notice, which stated that modification P00002 should not have been
    issued as a unilateral no-cost modification and was therefore rescinded.
    However, the letter informed PSI that it was delinquent on the contract and
    that DLA was considering cancelling for default.
    PSI responded to the show cause notice on May 11, 2010, asserting that
    the Agency illegally imposed a requirement that the parts conform exactly to
    the product-part specifications and arguing that the government had no valid
    basis for a termination for default. It also stated that, on June 1, 2007, PSI had
    written the government asking for assistance and cooperation in checking
    PSI’s drill bit template, but that the government never responded.
    PSI sent a supplemental letter on June 30, 2010, asserting that the part
    it sent as its second first article was actually the same part as the initial first
    article, with the identified defects corrected, yet Warner Robins had found
    completely new defects in the second first article. The letter went on to state
    that the fact that Warner Robins is a manufacturing competitor of PSI created
    a conflict of interest that should disqualify Warner Robins as a first article
    tester.
    On August 17, 2010, the contracting officer issued a termination for
    default for “failure to comply with the essential requirements of the contract.”
    
    Id. at 26
    . Notice of the termination was sent to PSI on September 3, 2010.
    Count 3
    DLA awarded contract number SP0407-06-M-9684 for the manufacture
    of 10 structural aircraft panels to PSI on April 18, 2006. The contract required
    that PSI send its first article to Hill within 90 days (by July 17, 2006). The
    5
    parties disagree about when the first article was shipped to Hill–PSI claims
    May 2008, while the Agency claims June 2008. In any event, it was after the
    90 day period required by the contract.
    On October 7, 2008, Hill reported to the agency that the first article
    failed testing, identifying 9 discrepancies. PSI was informed by letter on
    October 21, 2008. DLA offered PSI the opportunity to resubmit a first article
    and requested that PSI submit a revised delivery schedule by November 4,
    2008. PSI responded, contesting the rejection of the first article, requesting its
    return, and requesting conditional approval. The parties disagree as to whether
    the first article was returned to PSI. The parties executed a bilateral contract
    modification on March 31, 2010, setting the deadline for first article
    resubmission as May 7, 2010.
    As of November 2010, PSI had not delivered a second first article. The
    contracting officer sent PSI a show cause notice requesting a response by
    November 18, 2010. PSI responded, through counsel, on November 26, 2010.
    In the response letter, PSI claimed that the Agency was precluded from
    terminating the contract for default because it had not returned the initial first
    article to PSI and because it never gave PSI a decision on its request for
    conditional approval. PSI indicated to the Agency that it believed DLA used
    the first article but refused to pay for it. PSI also made a claim for equitable
    adjustment for its rejected first article, consisting of $3,000 for the unreturned
    first article, $254.32 for time spend researching and analyzing the show cause
    notice, $806.89 in delay costs, and proposal preparation fees of $800. PSI
    informed DLA that it would work with the Government to establish a new
    discovery schedule after the Government returned the first article and ruled on
    the request for conditional approval.
    In response to PSI’s request for equitable adjustment, DLA issued a
    termination for default on December 6, 2010. DLA stated that it would pay
    $3,000 for the unreturned first article, but it denied the other components of
    PSI’s request for equitable adjustment.
    Count 4
    Contract number SPM4A7-08-M-5689 was awarded to PSI on March
    31, 2008, for the production of 38 access covers for $44,800. It required a first
    article to be delivered at Hill within 180 days (by November 3, 2008). DLA
    inquired about the status of the first article on January 22, 2009. PSI responded
    6
    that the delinquency was due to DX-rated contracts.3 PSI shipped the first
    article in May 2009.
    On November 23, 2009, DLA sent a letter disapproving of the first
    article. Attached to the letter was a list of 14 discrepancies. The letter went on
    to state that a no-cost termination for convenience would be issued and that
    “[n]o further submission is requested or authorized.” Def.’s App. 99. On
    December 2, 2009, DLA sent PSI a proposed bilateral modification to
    terminate the contract at no cost to either party. PSI refused to agree to the
    modification. DLA then informed PSI that the contract would be terminated
    for default.
    PSI responded on November 19, 2010 with a claim for equitable
    adjustment in the amount of $16,144.62. Contracting Officer Sally Gorby sent
    DLA a response letter on December 14, 2010, stating that PSI’s request for
    equitable adjustment was based on the mistaken belief that the contract had
    been terminated for convenience. It further asked PSI to show cause why the
    contract should not be terminated for default. In the alternative, the letter
    offered a no cost termination in lieu of termination for default. PSI responded
    through counsel on December 23, 2010, asserting that the government had
    constructively terminated the contract. PSI therefore purported to convert its
    request for equitable adjustment into a claim for equitable adjustment pursuant
    to the termination clause of the contract. PSI further requested a termination
    for convenience. DLA thereafter issued a termination for default.
    Count 5
    Contract number SP0407-05-C-2028 was awarded on March 28, 2005.
    The first article was due by July 26, 2005. DLA received the first article on
    June 22, 2006. It was rejected on February 27, 2007. PSI subsequently
    submitted a second first article on July 20, 2007, and DLA conditionally
    approved it on December 18, 2007. PSI was notified of the conditional
    approval on January 10, 2008. Thus, pursuant to the contract, the parts were
    3
    Under the Defense Priorities and Allocations Systems (“DPAS”), which is
    used to prioritize performance, defense contracts are identified by rating the
    symbols “DO” and “DX.” Contractors are required to prioritize DX-rated
    orders over DO-rated orders and unrated orders.
    7
    due 293 days later, by October 30, 2008. PSI did not deliver any parts by this
    date.
    By email dated November 25, 2008, Milan Reeder, Vice President of
    PSI, advised DLA that PSI would be shipping a minimum of five or more units
    the following week. He also indicated that PSI “ha[d] DX rated contracts
    which took priority.” Def.’s App. 162. A modification was then issued by DLA
    to ship the first five parts by December 5, 2008 and the remaining 50 by the
    end of December in exchange for $350 consideration. PSI objected to this
    modification by letter on December 6, 2008, asserting that delivery of 50
    panels by the end of December was “arbitrary, unrealistic, and nonfeasible.”
    Pl.’s App. 493. The letter also accused DLA of causing delays of
    approximately 17 months, and requested modification to reflect the
    government delays. PSI shipped the first five panels that month, but did not
    submit the remainder.
    On January 22, 2009, DLA sent PSI an email informing it that the
    contract had become delinquent and requesting a status update. DLA again
    contacted PSI on March 23, 2010m offering a no-cost termination for
    convenience. PSI responded, refusing the termination for convenience, stating
    that it had to interrupt production due to DX-rated contracts and that it
    expected to resume production within six weeks. DLA wrote back, stating that
    it would issue a modification changing the delivery date to May 14, 2010. PSI
    responded by email on April 2, 2010, advising that it expected to complete
    delivery of the remaining parts by July 30, 2010.
    DLA sent a show cause notice on November 14, 2010. PSI responded
    by requesting equitable adjustment in the amount of $6,252.64 for the
    government’s delay of its testing decision for both first articles and delay in
    returning the first article to PSI upon PSI’s request.
    On December 2, 2010, DLA issued a contract modification requiring
    the remaining units to be delivered by January 31, 2011. It subsequently denied
    PSI’s request for equitable adjustment on December 8, 2010. PSI responded
    with a letter expressing concern over DLA’s and the contracting officer’s
    course of conduct. It subsequently shipped the remaining parts between
    December 2010 and March 2011.
    8
    Count 6
    DLA awarded contract number SPM4A7-09-D-5547 to PSI in July
    2009 for an indefinite quantity purchase order for bundle covers. On July 24,
    2009, DLA issued Delivery Order 0001 for 24 covers to be delivered by
    November 30, 2009. On October 3, 2009, DLA issued Delivery Order 0002 for
    29 covers for delivery by February 5, 2010. On January 29, 2010, DLA issued
    Delivery Order 0003 for 48 covers to be delivered by June 30, 2010. PSI
    delivered a portion of the covers for Delivery Order 0001 on June 12, 2010,
    and the remainder on July 11, 2010. On July 14, 2010, PSI delivered the covers
    for Delivery Order 0002.
    DLA issued a show cause notice on January 25, 2011, regarding PSI’s
    failure to deliver under Delivery Order 0003. PSI responded that it had never
    received Delivery Order 0003, but that it was prepared to complete all orders
    under the contract, including Delivery Order 0003, within the five year period
    of the contract with the date of Delivery Order 0003 running from the date of
    the letter announcing its existence. On February 10, 2011, the contracting
    officer issued a termination for default as to Delivery Order 0003.
    Count 7
    Count 7 concerns contract number SPM4A7-08-D-0316. This indefinite
    delivery, indefinite quantity contract for coupling adapter sleeves was awarded
    to PSI on July 30, 2008. It provided that delivery of orders was due 111 days
    after receipt of each order. DLA issued the following delivery orders:
    1.     Delivery Order 0001: 111 units due November 18, 2008
    2.     Delivery Order 0002: 74 units due February 22, 2010
    3.     Delivery Order 0003: 81 units due April 27, 2010
    4.     Delivery Order 0004: 80 units due June 28, 2010
    5.     Delivery Order 0005: 79 units due July 28, 2010
    6.     Delivery Order 0006: 283 units due January 5, 2011
    On February 12, 2010, PSI delivered two of the units owed under Delivery
    Order 0002. Between June 2010 and August 2010, it delivered all but 14 of the
    units owed under Delivery Order 0001.
    On November 16, 2010, DLA sent PSI a letter notifying PSI that all of
    the orders except Delivery Order 006 were delinquent and informing PSI that
    9
    it was considering terminating for default. The letter also provided that PSI
    would need to provide monetary consideration before the agency would accept
    any more shipments. It requested a response by November 19, 2010. PSI
    responded, claiming that the agency had overwhelmed it with orders. It also
    stated that it had 97 parts ready to ship but would stop delivery because it
    viewed DLA’s demand for consideration as a stop work order.
    PSI subsequently shipped the 97 parts. It then submitted a claim for
    equitable adjustment on November 26, 2010, demanding $23,012. PSI also
    objected to DLA’s assertion that PSI had repudiated the contract, and
    countered that there was no longer a delivery schedule in place. On December
    8, 2010, DLA sent a letter denying PSI’s request for equitable adjustment. In
    this letter, DLA also stated that it had not waived delivery or the delivery
    schedule and that it expected PSI to deliver Delivery Order 0006 by the
    January 5, 2011 due date. The letter further invited PSI to provide reasonable
    revised delivery dates for Delivery Orders 0003, 0004 and 0005. Otherwise,
    the letter provided, the agency would terminate for default. PSI did not
    respond. The agency thereafter terminated the contract for default on February
    4, 2011.
    Count 8
    Count 8 pertains to eight contracts which are further divided into
    Counts 8(A) through 8(H). The specific facts of each contract are detailed
    below. As of February 22, 2011, PSI had not shipped the required parts for any
    of the eight contracts. DLA therefore wrote PSI offering a no cost, no liability
    termination for all of the contracts and providing that it would terminate them
    for default if PSI did not respond by March 15, 2011. PSI sent a letter to DLA
    on February 28, 2011, challenging the authority of the contracting officer to
    “continually issue demands and threats with arbitrarily and capriciously set
    response-date demands.” Def.’s App. 357.
    PSI responded to DLA’s letter again, through counsel, on April 7, 2011.
    It contended that the government had waived its right to terminate for default,
    and that the only action that DLA could take was to issue formal terminations
    for convenience. The letter also noted that the government had, in the past,
    typically allowed PSI to prioritize its DX-rated contracts over DLA’s DO-rated
    contracts and that the government never set new dates for these contracts
    because it no longer had a need for the products. Thereafter, DLA terminated
    the contracts for default.
    10
    Count 8(A)
    Count 8(A) pertains to contract number SPM4A7-07-D-3180. This
    indefinite delivery, indefinite quantity contract for lower left panel aircraft
    assemblies was awarded to PSI on March 6, 2007. The first article was due at
    Warner Robins 250 days after award on November 5, 2007. On March 20,
    2007, DLA issued Delivery Order 001 for six panels. On March 21, 2007,
    DLA issued Delivery Order 0002 for another six panels. Both orders were
    placed before DLA received the first article for testing.
    On February 5, 2008, in response to a request for clarification, DLA’s
    contract administrator sent an email to PSI, informing it that the first article
    should be shipped against Delivery Order 0001. If approved, the first article
    requirement for Delivery Order 0002 would be deemed satisfied. The email
    also provided that delivery would be due 242 days after first article approval.
    PSI responded, informing DLA that it would have the first article
    complete by March 7, 2008. It followed up via email on March 6, 2008,
    informing PSI that the first article would be ready by March 21, 2008 or
    earlier. On March 14, 2008, DLA issued modifications to Delivery Orders
    0001 and 0002 to revise first article shipment to March 31, 2008. However,
    PSI did not ship the first article by March 31, 2008. DLA inquired into the
    status of the first article on February 26, 2009. PSI did not respond.
    On June 1, 2009, DLA issued Delivery Order 0003 for another six
    panels. It again inquired into the status of the first article on November 30,
    2009. PSI advised the agency that it was planning on submitting its first article
    by December 18, 2009. As of March 29, 2010, PSI still had not delivered the
    first article. In communications with DLA through the Defense Contract
    Management Agency (“DCMA”), PSI indicated that it would ship the first
    article by the middle of April 2010. Nevertheless, the first article was never
    shipped, and on April 27, 2011, DLA terminated the contract for default.
    Count 8(B)
    Contract number SPM4A5-08-M-2072 for 162 aircraft access covers
    was awarded on February 22, 2008. The first article was due at Hill 240 days
    after award. On May 15, 2008, PSI shipped the first article, and on September
    26, 2008, the agency informed PSI that the first article had failed testing. The
    11
    rejection letter invited PSI to submit another first article, submit a rebuttal
    letter, or request cancellation of the contract. The letter requested a response
    within 15 days, and warned that the contracts might be cancelled or terminated
    if PSI did not respond.
    PSI did not respond. On May 4, 2009, DLA again contacted PSI
    requesting a status update within 15 days. DLA contacted PSI again on May
    21, 2009, informing PSI that the contracts might be cancelled if a response was
    not received by May 22, 2009.
    As of February 22, 2011, PSI still had not submitted another first
    article, and DLA issued a show cause notice. The only response was the April
    7, 2011 letter, mentioned above, which expressed discontentment with DLA’s
    course of action regarding the contracts in general but did not provide
    responses as to each specific contract. DLA terminated the contract for default
    on April 29, 2011.
    Count 8(C)
    Contract number SPM4A7-07-M-6269 for 34 fairing assemblies was
    awarded on April 12, 2007. The contract required the first article in 90 days,
    but it also provided that a first article which PSI had previously submitted for
    a contract not at issue in this case would suffice if it was approved. On
    February 14, 2008, and again on October 10, 2009, however, PSI’s first article
    submissions were rejected.
    On March 30, 2010, DLA sent PSI an email offering a no cost
    termination and requesting a response by April 1, 2010. On May 5, 2010, DLA
    sent an email attaching a proposed modification to the contract to terminate it
    at no cost. PSI refused to agree to the no-cost termination.
    As of February 22, 2011, PSI still had not submitted another first
    article, and a show cause notice was issued. PSI responded only via the April
    7, 2011 letter. DLA terminated the contract for default on April 29, 2011.
    Count 8(D)
    Contract number SPM4A7-08-C-0387 for 30 aircraft fairings was
    awarded on June 6, 2008. The first article was due on December 13, 2008. On
    April 21, 2010, a representative of DCMA sent a message to DLA, indicating
    12
    that PSI had made no progress toward the completion of the order. On June 8,
    2010, DLA contacted PSI warning that no progress was being made and
    therefore the contract would be cancelled at no cost to the government.
    PSI responded on June 10, 2010, stating that progress had been made
    and that it did not assent to a termination for convenience. DLA emailed back
    that day, asking “where do we stand on this contract?” Def.’s App. 434. PSI
    did not respond.
    As of February 22, 2011, PSI still had not submitted a first article, and
    DLA issued a show cause notice. PSI only responded via the April 7, 2011
    letter. DLA terminated the contract for default on May 6, 2011.
    Count 8(E)
    On June 23, 2008, DLA awarded PSI contract number SPM4A7-08-D-
    0274, an indefinite delivery, indefinite quantity contract for wing to fuselage
    fairing panels. The first article was due by November 5, 2008. DLA issued the
    following delivery orders: Delivery Order 0001 on September 19, 2008 for 15
    panels, and Delivery Order 0002 on December 5, 2008 for 17 panels.
    On March 13, 2009, PSI told the agency that it had not yet shipped a
    first article or begun production. DLA then issued a modification to Delivery
    Order 0001, adding a requirement of a first article to be delivered by July 6,
    2009. As of February 3, 2010, PSI still had not delivered the first article. DLA
    informed PSI that the item was over-procured and offered a partial
    cancellation, to which PSI agreed. Thus, DLA issued a modification to
    Delivery Order 0002 decreasing it to 6 panels.
    As of February 22, 2011, PSI still had not submitted a first article, and
    DLA issued a show cause notice. PSI responded only via the April 7, 2011
    letter. DLA terminated the contract for default on May 10, 2011.
    Count 8(F)
    DLA awarded contract number SPM4A7-07-M-A678 for 19 aircraft
    fairings to PSI on August 6, 2007. The first article was due February 2, 2008.
    On March 3, 2008, PSI requested a mylar that it needed for the part from DLA.
    It requested the mylar again on June 17, 2009. A 2010 letter from PSI to DLA
    indicated that the mylar was provided to PSI on July 2, 2010.
    13
    On August 8, 2010, DLA issued a modification revising the delivery
    date to January 30, 2011. As of February 22, 2011, PSI still had not submitted
    a first article, and thus a show cause notice was issued. PSI responded only via
    the April 7, 2011 letter. DLA terminated the contract for default on April 29,
    2011.
    Count 8(G)
    This contract, number SPM4A7-07-M-C357, for 50 aileron trailing
    edge assemblies was awarded to PSI on September 14, 2007. The first article
    was due in 180 days, by March 12, 2008. DLA contacted PSI on June 11,
    2009, to report that the government had a critical need for the parts and to ask
    if the first article had shipped. PSI responded on June 16, 2009, advising that
    the first article was complete and ready for spot welding, and would ship by
    August 19, 2009.
    The first article did not ship by August 19, 2009. On July 12, 2010, PSI
    informed DLA that the reason for the delay was spot welding issues and that
    the first article was expected to ship by July 31, 2010. The first article was not
    shipped by this date. In February 2011, PSI indicated that it would ship the
    first article by the end of March 2011.
    As of February 22, 2011, PSI still had not submitted a first article, and
    a show cause notice was issued. PSI responded only via the April 7, 2011
    letter. DLA terminated the contract for default on April 29, 2011.
    Count 8(H)
    On August 16, 2008, this contract, number SPM4A7-08-C-048, for 38
    aircraft access doors was awarded to PSI. The first article was due by February
    12, 2009. As of July 1, 2009, PSI had not shipped the first article, and DLA
    requested a status update. In response, PSI indicated that it expected to ship
    the first article by September 15, 2009.
    As of June 3, 2010, PSI had still not shipped the part, and DLA
    requested a status update. PSI responded that it intended to ship the part. On
    October 7, 2010, DLA contacted PSI to request a reduction of the quantity by
    four. PSI did not respond, and DLA contacted PSI again on November 8, 2010
    to request a response.
    14
    On December 15, 2010, DLA was notified by DCMA that PSI had not
    yet begun production because it was awaiting approval from DLA on a similar
    part. On January 21, 2011, DLA contacted PSI again asking for the status of
    the part. On January 31, 2011, DLA repeated its request for a status update
    and its request to reduce the total contract amount by four parts. DLA renewed
    this request for the last time on February 7, 2011.
    As of February 22, 2011, PSI still had not submitted a first article, and
    DLA issued a show cause notice. PSI responded via the April 7, 2011 letter.
    DLA terminated the contract for default on May 6, 2011.
    Count 9
    Count 9 pertains to 14 additional contracts, which are divided into
    Count 9(A) through 9(N). Defendant has made a prima facie case that it is
    entitled to summary judgment as to Counts 9(A) through 9(N) because PSI
    either failed to deliver the products or failed to submit second first articles
    after its initial submissions were rejected. As discussed more fully below,
    plaintiff has failed to set forth any meaningful response to defendant’s motion
    as to Counts 9(A) through 9(K). Therefore, for the purpose of brevity, we will
    only provide the facts for Counts 9(L) through 9(M).
    Count 9(L)
    Contract number SPM4A7-07-M-0637 for 12 cowlings was awarded
    on October 25, 2006. The first article was due in 120 days, by February 22,
    2007. On February 9, 2007, PSI submitted a request for copies of three
    drawings that it needed to complete the part. DLA responded, recommending
    that PSI contact Lockheed Martin for the drawings. PSI again requested the
    drawings on April 25, 2007, and they were provided to PSI by DLA on May
    30, 2007.
    On July 26, 2007, the contracting officer issued a modification,
    changing the deadline for first article submission to September 15, 2007. This
    modification also changed the product delivery date to May 13, 2008. On
    October 22, 2007, PSI shipped the first article.
    The first article was rejected on May 20, 2008 because it failed a form,
    fit, and function test and because the spot welds did not conform to the
    drawings. PSI was given the opportunity to submit another first article, with
    15
    PSI to bear the costs. PSI subsequently requested that DLA return the rejected
    first article and asked that DLA send a full copy of the test report. In
    November 2008, PSI submitted five samples to an independent company to
    test the spot welds. The testing company determined that all five samples had
    spot weld failures.
    On January 6, 2009, PSI reported to DLA that it would ship a new first
    article by the end of the month. On January 30, 2009, DLA contacted PSI to
    inform it that the contract was delinquent and demanded monetary
    consideration and an explanation for the delay. PSI responded that the first
    article had not shipped because it was still waiting for the rejected first article
    to be returned.
    On February 11, 2009, PSI received the initial first article back from
    DLA. On March 16, 2009, PSI stated that it would submit a new first article
    by April 15, 2009. As of May 29, 2009, PSI had yet to ship the second first
    article, and DLA contacted PSI to request an updated delivery date.
    On June 10, 2009, PSI shipped the second first article. On December
    17, 2009, PSI was notified that its second first article was rejected, again due
    to spot weld failures and improper fit.
    DLA issued a show cause notice for this contract and two others on July
    8, 2011, offering PSI a no-cost termination or the opportunity to provide
    another first article for testing. PSI responded that the government’s charges
    of delinquency were themselves untimely and argued that there was no
    effective schedule in place.
    DLA terminated the contract for default on September 1, 2011. Four
    months later, PSI submitted a claim for equitable adjustment seeking
    $84,421.55 attributable to government-caused delay. This claim was rejected
    on February 13, 2012.
    Counts 9(M) and 9(N)
    Count 9(M) pertains to contract number SPM4A7-08-M-7193 for 20
    panel assemblies awarded to PSI on March 5, 2008. The first article was due
    by August 22, 2008. PSI submitted a first article, which was rejected by
    Warner Robins on April 30, 2010. The memorandum explaining the rejection
    provided that the panel had the wrong contour and several disbonds were
    16
    found along the edge of the panel. On May 24, 2010, DLA informed PSI of the
    rejection, and invited PSI to submit a new first article. PSI did not respond to
    this letter and did not submit a new first article.
    Count 9(N) pertains to contract number SPM4A7-08-M-7646 for 300
    bulkhead clips which was awarded to PSI on March 21, 2008. The first article
    was due on October 22, 2008. PSI submitted a first article, which was rejected
    by Hill on January 20, 2009 due to dimensional discrepancies and an improper
    bend. On February 4, 2009, DLA informed PSI that it could submit a new first
    article or request a no-cost cancellation. PSI did not respond. DLA contacted
    PSI two more times requesting a response. On April 2, 2010, PSI responded,
    providing that it would submit its first article within 30 days. However, PSI
    never submitted a new first article.
    Both contracts were included in the July 8, 2011 show cause notice
    mentioned above, to which PSI responded by claiming that the government’s
    charges of delinquency were themselves untimely, and that there was no
    effective schedule in place. The contracts were terminated for default on
    September 1, 2011.
    DISCUSSION
    The government argues that it is entitled to summary judgment with
    respect to Counts 6, 7, 8(A), 8(C) through 8(H), and 9(A) through 9(K)
    because PSI failed to deliver the required products. Each of the 19 contracts
    associated with Counts 8 and 9 incorporates either FAR 52.209-3(d) or FAR
    52.209-4(d), which both state that if “the Contractor fails to deliver any first
    article on time, or the Contracting Officer disapproves of any first article, the
    Contractor shall be deemed to have failed to make delivery within the meaning
    of the Default clause of this contract.” 
    48 C.F.R. §§ 52.209-3
    (d), 52.209-4(d)
    (2015). Although the contracts underlying Counts 6 and 7 did not have first
    article requirements, PSI failed to deliver all of the parts ordered. The default
    clause in these contracts states that the government may terminate a contract
    for default “if the Contractor fails to - (i) Deliver the supplies or to perform the
    services within the time specified in this contract or any extension.” 
    Id.
     §
    52.249-8(a)(1). Defendant therefore argues that the agency was entitled to
    terminate these contracts for default pursuant to their respective default
    clauses.
    17
    For Counts 2-4, 8(B), and 9(L) through 9(N), the government contends
    that it is entitled to summary judgment because PSI’s first articles failed
    inspection and PSI never submitted second first articles. Defendant claims that,
    because successful first article submissions were required under these
    contracts, DLA was entitled to terminate for default upon PSI’s failure to
    submit acceptable first articles. In response to PSI’s allegation that Warner
    Robins improperly rejected PSI’s first articles in order to purchase the same
    parts from its own internal manufacturing facility, defendant points out that
    this argument fails because the first articles for Counts 3, 4, 8(B) and 9(N)
    were submitted to Hill, not Warner Robins, and PSI has offered no evidence
    that Warner Robins even manufactured the same parts required by the
    contracts in Counts 2, 9(L), and 9(M). Rather, defendant argues, PSI is
    engaging in mere speculation.
    For Count 5, PSI’s appeal of the denial of its request for equitable
    adjustment, defendant argues that it is entitled to summary judgment because
    PSI did not make a timely request for equitable adjustment. Rather, it raised
    the issue nearly four years after receiving notice that its first article was
    rejected and nearly three years after receiving notice that its second first article
    was conditionally approved. In addition, PSI was provided additional time
    within which to deliver the remaining parts, but PSI failed to meet those
    deadlines and therefore is entitled to no more from the government.
    In response, plaintiff argues that, for all of the contracts, DLA waived
    delivery dates through its course of dealing with PSI over the years. According
    to plaintiff, PSI and DLA had an informal working relationship whereby
    delivery schedules were not strictly enforced and DLA regularly allowed
    deadlines to pass. Plaintiff contends that it relied on this waiver by accepting
    contracts based on the understanding that DLA would continue to be flexible
    with delivery schedules.
    Plaintiff also argues that for all of the contracts at issue in this motion,
    DLA abused its discretion by failing to consider the impact of DX-rated orders
    when terminating PSI’s contracts for default. Plaintiff contends that under the
    Defense Priorities and Allocations Systems (“DPAS”), which is used to
    prioritize the performance of defense contracts, contractors are required to
    prioritize DX-rated orders over DO-rated orders and unrated orders. All of the
    contracts listed in the complaint were DO-rated or unrated. However, during
    the relevant time period, PSI had a number of DX-rated orders with Sikorsky
    Aircraft Corporation. Plaintiff argues that the law required it to reschedule and
    18
    delay its lower-rated orders with DLA in order to accomodate the DX-rated
    orders. Further, plaintiff contends that the government was aware of PSI’s DX-
    rated contracts and therefore should have considered them when determining
    whether to terminate for default.
    Regarding Counts 2, 3, 4, 8(B), 9(L), 9(M), and 9(M), the contracts for
    which PSI’s initial first article was rejected and it did not submit second first
    articles, PSI argues that DLA abused its discretion because it failed to grant
    conditional approval for first articles with easily correctable defects. Plaintiff
    provides the affidavit of Jeremy Wilczewski, the Chief Operating Officer of
    PSI, explaining how PSI could have easily corrected the defects that DLA
    identified in its first article rejections.
    PSI concludes by arguing that DLA was obligated by law to equitably
    adjust the contract associated with Count 5. PSI contends that FAR 52.209-4(f)
    requires the government to pay the contractor for delays in first article
    approval if timely written request is made and that, here, a timely request was
    made–four days after the agency issued a modification extending the delivery
    date.
    Defendant replies that, having met its burden of establishing that PSI
    did not meet the performance deadlines, the burden shifts to PSI to excuse the
    failure to deliver. Defendant claims that plaintiff’s argument that the
    government waived delivery deadlines is without support because it fails to
    establish the elements necessary to prove a waiver: (1) failure to terminate
    within a reasonable time after default under circumstances indicating
    forbearance and (2) reliance by the contractor on the failure to terminate.
    DeVito v. United States, 
    413 F.2d 1147
    , 1154 (Ct. Cl. 1969). According to
    defendant, PSI offers no evidence that it performed on the contracts, or that it
    continued to perform after the expiration of the delivery dates. Defendant also
    contends that plaintiff has failed to sufficiently explain why its obligations to
    complete DX-rated contracts precluded it from fulfilling its obligations under
    the contracts with DLA and argues that plaintiff’s conditional approval
    argument is unsupported by the evidence.
    We begin by addressing plaintiff’s general arguments that DLA waived
    the delivery deadlines through its course of dealing and that DLA abused its
    discretion in failing to consider the impact of PSI’s DX-rated contracts when
    it terminated several of the contracts for default. As we discuss in detail below,
    we agree with defendant. Plaintiff has failed to establish waiver as to any of
    19
    the contracts or that DLA was required to consider PSI’s DX-rated contracts
    when terminating for default.4
    Plaintiff argues that, for all of the contracts at issue and for past
    contracts, DLA routinely allowed delivery dates to pass and generally made it
    clear to PSI that time was not of the essence. Thus, according to plaintiff, it
    accepted the contracts with the expectation that DLA would continue not to
    strictly enforce delivery dates. Plaintiff points out that, in 2009, DLA went
    through a reorganization that involved a restructuring of its post-award branch.
    According to plaintiff, the agency thereafter abruptly changed its course of
    dealing, resulting in DLA suddenly demanding performance for all contracts
    at once. This argument, however, does not explain why DLA’s decision to
    terminate any specific contract was unreasonable. What we would need from
    plaintiff to accept its waiver argument are contract-specific facts showing
    “failure to terminate within a reasonable time after default under circumstances
    indicating forbearance.” DeVito, 
    413 F.2d at 1154
    . The broad approach which
    plaintiff takes in arguing waiver by DLA is not sufficient. Only the
    circumstances surrounding each individual contract determine whether the
    agency was within its rights in terminating that contract for default.
    Counts 2, 3, and 4 all had first article submissions which were rejected.
    In Count 2, a second first article was submitted and also rejected. The agency
    therefore informed PSI that it could either submit another first article or cancel
    the contract. PSI, however, failed to inform the agency whether it would
    submit a new first article or agree to a cancellation. As to Count 3, after the
    first article was rejected, the parties bilaterally set a new date for first article
    resubmission. However, that date passed without PSI submitting a new first
    article. In Count 4, after the first article was rejected, the agency sent a
    proposed bilateral termination for convenience. PSI refused to sign it, but did
    not indicate that it planned to submit another first article. The agency
    ultimately issued show cause notices for each of these contracts. These facts
    cannot be construed as showing waiver by DLA. PSI was given the option to
    either resubmit a first article or cancel the contract–neither option is indicative
    of forebearance by DLA.
    4
    Plaintiff makes these arguments as to all of the contracts, but Counts 7, 8(A),
    8(C) through 8(H), and 9(A) through 9(K) rest entirely on these arguments.
    20
    Count 7 pertains to an indefinite delivery, indefinite quantity contract
    consisting of six separate orders. The first five had delivery dates spanning
    from November 2008 through July 2010. Nevertheless, as of November 2010,
    PSI had only shipped a portion of the first two orders. DLA thus notified PSI
    that the contract was delinquent and that consideration was required before it
    would accept any more shipments. PSI, however, did not take any steps
    towards providing consideration and establishing new delivery dates. Instead,
    it submitted a claim for equitable adjustment, which DLA subsequently denied.
    In its denial letter, DLA reiterated that it expected delivery for the final order
    and that if PSI did not provide revised delivery dates for the earlier orders,
    DLA would terminate for default. These facts do not indicate forbearance by
    DLA. Moreover, PSI has not shown “reliance by the contractor on the failure
    to terminate and continued performance by him under the contract, with the
    Government’s knowledge and implied or express consent.” DeVito, 188 Ct. Cl.
    at 1154. While PSI shipped some parts after it was notified of its
    delinquencies, this was not done with the government’s consent, as DLA had
    informed PSI that it would require consideration before accepting late
    shipments. Def.’s App. 248-49. Thereafter, PSI never informed the agency
    whether it was working on the remaining parts. Nor did it ship them.
    The contracts in Counts 8(A), 8(C) through 8(H), and 9(A) through
    9(K) had first article requirements, but PSI failed to provide a first article.
    Count 8(C)’s first article requirement was tied to another contract. If the other
    first article was accepted, PSI would receive a first article waiver for this
    contract. However, the first article submission for the other contract was
    rejected twice, and PSI did not indicate whether it would submit another first
    article. DLA therefore offered PSI a no-cost termination, which PSI refused
    to sign. PSI did not, however, indicate that it would submit another first article
    and never delivered one. This course of conduct again fails to show reliance
    by PSI on the failure to terminate or continued performance under the contract
    and thus fails to meet the requirements for waiver.
    Counts 8(D), 8(F), and 9(A) through 9(K) transpired similarly–PSI
    failed to deliver the first article on time and, for several of the counts, declined
    to agree to the government’s proposed no-cost cancellation. However, PSI
    never indicated to DLA that it was working on a first article and planned to
    21
    complete performance.5 Thus, DLA terminated the contracts for default. As
    stated above, this course of conduct does not establish reliance by PSI on the
    failure to terminate or continued performance under the contract, and therefore
    it fails to meet the requirements for waiver.
    For Counts 8(A), 8(E), 8(G), and 8(H), the agency requested several
    status updates after the first article deadlines passed. Each time, PSI advised
    that it was working on the first article or otherwise gave a new shipment date.
    However, PSI never delivered the first articles and therefore DLA issued show
    cause notices. These contracts can be differentiated from those discussed
    above, however, because there is evidence that PSI told the agency that it was
    working on the first articles and would ship them soon, which is indicative of
    reliance. DLA’s failure to terminate when PSI indicated that it would ship the
    first article late therefore could be construed as a waiver of the delivery date.
    Thus, we are unable to grant summary judgment as to these contracts.
    Next, we find no abuse of discretion in DLA’s failure to consider the
    impact of PSI’s DX-rated contracts when it terminated several of PSI’s
    contracts for default. Plaintiff is correct that it was required to give DX-rated
    orders preference over DO-rated and unrated orders. 
    15 C.F.R. § 700.14
    (b)
    (2015). However, PSI has not alleged that it was forced into accepting DO-
    rated and unrated orders from DLA. In fact, the regulations provide that a
    contractor shall not accept a rated order for delivery if it cannot fill the order
    by the required date, or if it will interfere with previously accepted DO or DX-
    rated orders. 
    Id.
     § 700.13(b). PSI, however, never declined any contracts
    because of performance issues stemming from other rated contracts. See Def.’s
    App. 1065 (deposition of Jeremy Wilczewski). Thus, PSI was not acting under
    duress and the blame cannot be shifted to the agency for failing to consider
    5
    For Counts 8(D) and 9(K), PSI was asked where it stood on the contract but
    did not respond. Plaintiff contends that it was customary for PSI to
    communicate with DLA through DCMA and thus DLA was given status
    updates through DCMA, but does not provide any evidence that PSI gave DLA
    specific updates as to the progress of these contracts. For Count 9(A), the
    government warned PSI that, if it did not propose a new delivery date, the
    contract would be terminated for default. PSI responded, but did not propose
    a new delivery date. For Counts 9(D), 9(G), and 9(J), PSI provided a new ship
    date but did not ship by this date and did not otherwise indicate that it was
    working on the first article.
    22
    PSI’s higher-rated orders. PSI simply should not have accepted orders which
    it was unable to fill or which interfered with earlier higher-rated orders.
    PSI attempts to argue that the burden to rearrange the delivery schedule
    can be shifted to the agency because it was on notice of PSI’s DX-rated
    contracts. There is no merit to this argument, however, because the agency was
    not given proper notice. The regulation dealing with the notice requirement
    provides that
    [i]f a person has accepted a rated order and subsequently finds
    that shipment or performance will be delayed, the person must
    notify the customer immediately, give the reasons for the delay,
    and advise of a new shipment or performance date. If
    notification is given verbally, written (hard copy) or electronic
    confirmation must be provided within one working day of the
    verbal notice.
    Id. § 700.13(d)(3). There is no indication in the record that PSI provided notice
    to the agency. As to all of the contracts pertaining to Count 8, PSI first
    mentioned its DX-rated contracts in its response to DLA’s show cause notice,
    well after it had failed to meet delivery deadlines. This reference by PSI to its
    DX-rated contracts simply refers to an “understanding” that PSI would
    prioritize DX-rated contracts. Def.’s App. 297, 316. This is unspecific and
    does not suffice to provide the notice required by the regulations. In fact, the
    only contracts for which PSI explicitly informed the agency that delivery
    would be delayed due to DX-rated contracts were those underlying Counts 4
    and 5. However, rather than notifying the agency immediately and providing
    reasons for the delay, as required by the regulations, PSI waited until the
    agency inquired about the late shipment before it mentioned that it had
    interrupted production due to DX-rated contracts. See Pl.’s App. 398; Def.’s
    App 162-64. DLA therefore had no obligation to allow PSI to extend delivery
    dates due to conflicts with higher-rated contracts. Accordingly, we reject the
    argument, as to all contracts, that DLA abused its discretion in failing to
    consider the impact of PSI’s DX-rated contracts when it terminated several of
    PSI’s contracts for default.
    Thus, we are left with plaintiff’s remaining arguments as to Counts 2,
    3, 4, 5, 6, 8(B), 9(L), 9(N), and 9(M). Regarding Count 5, plaintiff’s remaining
    argument is that it was entitled to equitable adjustment because the
    government delayed first article approval. We reject this argument because the
    23
    government did equitably adjust the contract. The relevant FAR provision
    provides that if the government delays completion of first article disapproval
    or conditional approval, it “shall, upon timely written request from the
    Contractor, equitably adjust under the Changes clause of this contract the
    delivery or performance dates and/or the contract price, and any other
    contractual term affected by the delay.” 
    48 C.F.R. § 52.209
    –4(f) (2015). The
    parts were originally due in October 2008. DLA issued several modifications
    extending the due date, which ultimately resulted in a January 2011 due date.
    Thus, if DLA delayed performance, it remedied its delay by equitably
    adjusting the performance dates of the contract. We therefore grant summary
    judgment as to Count 5.
    As to Count 6, plaintiff argues that DLA’s decision to terminate the
    contract for default based on PSI’s failure to deliver Delivery Order 0003 was
    arbitrary and capricious because PSI never received the third order. Defendant
    contends that the order was sent to the email address provided by PSI. Plaintiff
    responds that DLA has not verified whether the order actually went through.
    The contracting officer stated in her deposition that Delivery Order 0003 was
    sent by the same means as Delivery Orders 0001 and 0002, and that it was
    posted to DLA’s computerized ordering system. However, she could not recall
    if she checked her electronic contract file to see if the notice had actually been
    sent to PSI. We find that this information presents fact issues which we cannot
    resolve on summary judgment, and therefore deny summary judgment as to
    Count 6.
    The remaining issue is whether the first articles for the contracts
    associated with Counts 2, 3, 4, 8(B), 9(L), 9(N), and 9(M) should have been
    granted conditional approval because their defects were easily correctable.
    Plaintiff points to a number of Armed Services Board of Contract Appeals
    (“ASBCA”) decisions in which termination for default of a contract which
    provides for conditional approval was reversed where the first article with
    easily correctable defects was rejected. See, e.g., Marvin Engineering
    Company, Inc., 
    ASBCA No. 27016
    , 
    84-2 BCA ¶ 17,401
    ; Harco Manufacturing
    Company, 
    ASBCA No. 27567
    , 85-1 DCA ¶ 17,926. Forfeiture is inappropriate
    where the only basis for rejection of the first article is defects that could be
    easily corrected during production.
    To support its argument that the defects were easily correctable,
    plaintiff provides the affidavit of its Chief Operating Officer. In this affidavit,
    Mr. Wilczewski notes the discrepancies identified in the notices of first article
    24
    rejections as to the relevant contracts and explains how each defect could have
    been corrected during production. The contract underlying Count 3, for
    example, was rejected due to dimensional discrepancies, because a strap was
    off-center, because the part was the wrong shade of gray, and because two
    certifications were missing. Wilczewski explains in his affidavit that the
    dimensional variations could have been easily corrected by adjusting the trim
    fixture, and the strap could have been easily corrected by adjusting its location.
    Wilczewski Affidavit ¶ 39. Moreover, he states that the color could have been
    easily changed, and the missing certifications could have been easily remedied
    by giving the government the correct paperwork. 
    Id.
    We find that the Wilczewski affidavit is sufficient to defeat the
    government’s motion for summary judgment as to these counts. See
    TechSearch, LLC v. Intel Corp., 
    286 F.3d 1360
    , 1372 (Fed. Cir. 2002) (“[T]the
    party opposing the motion for summary judgment . . . must point to an
    evidentiary conflict created on the record, at least by a counter-statement of a
    fact set forth in detail in an affidavit by a knowledgeable affiant.”). The
    affidavit has set forth facts which create a genuine issue as to whether these
    defects were easily correctable and thus whether PSI was entitled to
    conditional approval of its initial first articles. Therefore, we deny summary
    judgment as to Counts 2, 3, 4, 8(B), 9(L), 9(N), and 9(M).6
    CONCLUSION
    For the reasons stated herein, we grant in part and deny in part
    defendant’s motion for summary judgment. The clerk is directed to enter
    judgment for defendant as to Counts 5, 7, 8(C), 8(D), 8(F), and 9(A) through
    9(K). The parties are directed to consult and jointly propose a trial schedule by
    June 30, 2016.
    s/ Eric G. Bruggink
    ERIC G. BRUGGINK
    Senior Judge
    6
    Plaintiff also makes additional count-specific arguments as to Count 2, 3, 4, and
    9(L). However, because plaintiff has already defeated summary judgment as to
    these counts with its conditional approval argument, there is no need to address
    these arguments.