Ingham Regional Medical Center v. United States ( 2022 )


Menu:
  •              In the United States Court of Federal Claims
    No. 13-821
    (Filed: 13 December 2022) *
    **************************************
    INGHAM REG. MED. CENTER,             *
    n/k/a MCLAREN GREATER LANSING,       *
    et al.,                              *
    *
    Plaintiffs,        *                        Breach of Contract; Mutual Mistake of Fact;
    *                        Class Certification; Summary Judgment;
    v.                                   *                        TRICARE Reimbursement; Medicare
    *                        Reimbursement; Duty; Breach; Damages;
    THE UNITED STATES,                   *                        Negative Implication Canon; Risk-shifting.
    *
    Defendant.         *
    *
    **************************************
    Alexander J. Pires, Jr., Pires Cooley, of Washington, DC, with whom was Gregory A.
    Brodek, Duane Morris LLP, of Bangor, ME, for plaintiffs.
    A. Bondurant Eley, Senior Trial Counsel, with whom were Steven J. Gillingham,
    Assistant Director, Patricia M. McCarthy, Director, Commercial Litigation Branch, and Brian
    M. Boynton, Principal Deputy Assistant Attorney General, Civil Division, U.S. Department of
    Justice, all of Washington, DC, for defendant.
    OPINION AND ORDER
    HOLTE, Judge.
    Plaintiffs are six hospitals purporting to represent a class of approximately 1,610
    hospitals across the United States in a suit requesting amongst other things the Court interpret
    what the Federal Circuit has deemed an “extremely strange” contract. This contract arose when
    hospitals complained the government underpaid reimbursements for Department of Defense
    Military Health System, TRICARE, outpatient services rendered between 2003 and 2009. After
    running a data analysis, in 2011, the government voluntarily entered a discretionary payment
    process contract with plaintiffs, offering net adjusted payments to reflect the Medicare blended
    rate for outpatient radiology claims. On 9 June 2022, after nine years of litigation and one
    Federal Circuit appeal, this Court heard oral argument regarding the government’s motion for
    summary judgment reviewing three issues: (1) breach of contract; (2) mutual mistake of fact;
    *
    This Opinion was initially filed under seal on 28 November 2022 pursuant to the protective order in this case. The
    Court provided the parties the opportunity to submit proposed redactions on or before 12 December 2022. On 12
    and 13 December 2022, the parties confirmed by email they did not have any proposed redactions. This Opinion is
    now reissued for publication in its original form.
    and (3) class certification. For the reasons detailed in this opinion, the Court: (1) grants in part
    and denies in part the government’s motion for summary judgment as to plaintiffs’ breach of
    contract claim; (2) grants the government’s motion for summary judgment as to plaintiffs’
    mutual mistake of fact claim; and (3) defers ruling on plaintiffs’ motion for class certification.
    As explained infra, the Court holds the government did not have a duty to obtain and
    adjust original native data from plaintiff hospitals, see infra Section IV.A, the government did
    have a duty to correctly adjust data from the government’s TMA database, see infra Section
    IV.B, the government did have a duty to correctly consider zip codes for plaintiff hospital
    locations not provided by the hospitals in their discretionary payment submissions, see infra
    Section IV.C, the government breached its duty to correctly adjust data from TMA’s database,
    see infra Section IV.D, plaintiffs were not obligated to pre-check TMA’s data, see infra Section
    IV.E.1, the government did not prove the discretionary payment agreement shifted the risk of all
    data issues to plaintiff hospitals, see infra Section IV.E.2, and there was no mutual mistake of
    fact, see infra Section V. The Court declines to rule on class certification at this time. See infra
    Section VI. As the only surviving breach of contract claim is the government’s duty to extract,
    analyze, and adjust line items from its database, the parties shall next file a joint status report
    regarding scheduling for updated class certification briefing.
    Finally, as the parties confirmed in the 11 May 2022 pre-oral argument status conference,
    several pending evidentiary motions were not consequential for summary judgment and the
    Court accordingly stays: the government’s motion to exclude inadmissible evidence pursuant to
    Rule 408; plaintiffs’ motion to exclude expert opinions of Jane Jerzak; plaintiffs’ motion to
    exclude expert opinions of Anthony Fay; the government’s motion to strike “Rule 408 Evidence
    Relied on by Plaintiffs in Summary Judgment Briefing”; the government’s motion to strike
    “Paragraphs 3 - 10 of the Dale Thompson Declaration”; the government’s motion to strike
    “Paragraphs 7 and 18 of the Declaration of Sere Allen, and Associated Briefing”; and plaintiffs’
    motion to exclude expert opinions of David Kennell.
    I.        Relevant Background
    A.      Factual History
    TRICARE is a “military health care system” which “provides medical and dental care for
    current and former members of the military and their dependents.” Ingham Reg’l Med. Ctr. v.
    United States, 
    874 F.3d 1341
    , 1342 (Fed. Cir. 2017). TRICARE Management Activity
    (“TMA”), a “field office in the Defense Department [‘DoD’],” managed the TRICARE system. 1
    N. Mich. Hosps., Inc. v. Health Net Fed. Servs., LLC, 344 F. App’x 731, 734 (3d Cir. 2009).
    Hospitals providing TRICARE services are reimbursed according to DoD guidelines. In 2001,
    Congress amended the TRICARE statute to require DoD to follow Medicare rules when
    reimbursing outside healthcare providers. Ingham Reg’l Med. Ctr., 874 F.3d at 1343 (citing 
    32 C.F.R. § 199.14
    ). Due to “the lack of TRICARE cost report data comparable to Medicare’s”
    figures, TMA, however, found it impracticable to immediately adopt Medicare reimbursement
    rules. 
    Id.
     (citation omitted). To facilitate transition to Medicare rules, in 2005, DoD issued a
    Final Rule “which provided a more detailed explanation of the payment rules for hospital-based
    1
    TMA is now known as the Defense Health Agency.
    -2-
    outpatient services.” 
    Id.
     The rule specified “[f]or most outpatient services, hospitals would
    receive payments ‘based on the TRICARE-allowable cost method in effect for professional
    providers or the [Civilian Health and Medical Program of the Uniformed Services]
    (“CHAMPUS”) Maximum Allowable Charge (CMAC).’” 
    Id.
     (citation omitted). The
    TRICARE-allowable cost method “applied until 2009, when TRICARE introduced a new
    payment system for hospital outpatient services that was similar to the Medicare [Outpatient
    Prospective Payment System (‘OPPS’)] rules.” 
    Id.
    On 23 January 2007, two hospitals “filed their first amended complaint in the [United
    States District Court for the District of Delaware] asserting claims for breach of contract implied
    in fact and breach of quasi-contract/unjust enrichment” against TRICARE’s
    intermediary-managed care support contractors (“intermediaries”). N. Mich. Hosps., Inc., 344 F.
    App’x at 735. “The Hospitals alleged [the intermediaries] refused to pay the Hospitals’ facility
    charges for certain outpatient services rendered by the Hospitals to TRICARE beneficiaries,
    despite the fact that the Hospitals submitted claims to [the intermediaries] which included such
    charges.” 
    Id.
     (footnote omitted). The district court dismissed the complaint because the
    hospitals failed to first exhaust their administrative remedies, id. at 739, and the Third Circuit
    affirmed. Id. at 740. The Third Circuit determined, “Without question, the regulations state that
    certain services are reimbursed based on a maximum allowable charge calculation and that
    facility charges, which are not subject to a maximum allowable charge, are paid as billed.” Id. at
    737 (citing 
    32 C.F.R. § 199.14
    (a)(5)(i)–(xi)). The Third Circuit added “the regulations are
    equally clear that the Hospitals are not allowed to simply submit bills for any amount and then
    claim that they are entitled to reimbursement for the full amount charged because any amount
    above the CMAC represents their ‘facilities’ expenses.” 
    Id.
     In dicta, the court stated, “The
    dispute at issue is not a purely legal one, but rather requires factual determinations such as
    whether expenses that qualify as facility charges were incurred, whether such charges were
    properly billed, and how much is owed if they were incurred and properly billed.” N. Mich.
    Hosps., Inc., 344 F. App’x at 737. “Therefore, what is required by the underlying dispute in this
    case is an application of the TRICARE regulations to the Hospitals’ specific claims for
    reimbursement.” 
    Id.
     After the Third Circuit affirmed, “the parties to that suit exchanged email
    communications regarding further steps and potential readjustment with TRICARE.” Op. &
    Order (“14 Jan. 2020 Op. & Order”) at 3 n.2, ECF No. 125.
    In response to hospital complaints, TRICARE hired Kennell and Associates, a consulting
    firm, to “undertake a study [(‘Kennell study’)] of the accuracy of its payments to the hospitals.”
    Ingham Reg’l Med. Ctr., 874 F.3d at 1343–44. The Kennell study “compared CMAC payments
    to the payments that would have been made using Medicare payment principles, and determined
    that DoD ‘(1) underpaid hospitals for outpatient radiology but, (2) correctly paid hospitals for all
    other outpatient services.’” Id. at 1344 (emphasis removed).
    From the Kennell study findings, “DoD created a discretionary payment process
    [(‘DPP’)],” and, on 25 April 2011, DoD notified hospitals by letter of the process for them to
    “request a review of their TRICARE reimbursements (the ‘Letter’).” 2 Id. The DoD also
    2
    The Letter states, in pertinent part:
    -3-
    “published a document titled ‘NOTICE TO HOSPITALS OF POTENTIAL ADJUSTMENT TO
    PAST PAYMENTS FOR OUTPATIENT RADIOLOGY SERVICES’ (the ‘Notice’)” on the
    TRICARE website. Def.’s MSJ App. at A3–A9 [hereinafter DPP Contract Notice], ECF No.
    203-1. 3 Like the Letter, the Notice stated any submission would be treated as “an untimely but
    discretionary appeal under 32 CFR 199.10(a)(5) and (c) provided it is received no later than 23
    June 2011.” Id. at A7. The Notice also indicated: “Based on the request and subject to the
    availability of funds, each hospital will receive adjusted payments in return for acceptance of
    DoD’s offer of additional payment based on criteria established by the agency,” and “payment of
    the discretionary adjustments will also be conditioned on the execution of a release by the
    hospital of any hospital outpatient service claims against the agency, TRICARE beneficiaries
    and the TRICARE [intermediaries].” Id. The Notice described a nine-step methodology by
    which hospitals could “request an analysis of their claims data for possible discretionary
    For purposes of this process, DoD will treat your submission as an untimely but discretionary appeal
    under 32 Code of Federal Regulations 199.10(a)(5) and (c), provided it is received no later than 60
    days from the date of this letter. Based on the request, your hospital may be paid an adjustment,
    subject to the availability of appropriations, in return for your acceptance of DoD’s offer of
    additional payment based on criteria established by the agency. . . . In order to bring closure to any
    concerns regarding payment of hospital outpatient services under the TRICARE regulation prior to
    implementation of OPPS, payment of the discretionary adjustments will also be contingent on the
    execution of a release by the hospital of any hospital outpatient service claims against the agency,
    TRICARE beneficiaries, and TRICARE [intermediaries]. We value your hospital as a partner in
    this effort and remain committed to working with you to complete the analysis of claims data and
    determine if any additional payments may be allowed.
    Def.’s MSJ App. at A1–A2 (DPP Contract Letter), ECF No. 203-1.
    3
    The Notice explained in relevant part:
    The TRICARE regulation provisions on hospital outpatient services, in the absence of adoption of
    the Medicare OPPS methodology, adopted comparable Medicare payments for similar services
    provided in other sites (i.e., physician offices). That is, TRICARE looked to the similarity of
    services being provided, not the site of services, in adopting a reimbursement methodology for
    hospital outpatient services. . . .
    [I]n reviewing payments for hospital services, DoD has determined that, for radiology services . . .
    the technical component of the allowable charge did not approximate the Medicare fair payment for
    such hospital services as well as it could have. That is, looking at the Medicare reimbursement
    methodologies in existence prior to adoption of Medicare OPPS in 2000, . . . some radiology services
    were underpaid in comparison. . . . Thus, although payments to hospitals for radiology services
    were consistent with the duly promulgated regulation, there is a basis for TRICARE to provide an
    opportunity to make some discretionary net payment adjustments to approximate more closely
    Medicare payment methods. . . .
    General TRICARE policy is that payment methodologies follow to the extent practicable Medicare
    payments. Prior to adopting [OPPS], Medicare used a blended rate that factored in a percentage of
    hospital costs and a percentage of the global physician fee schedule to reimburse hospital outpatient
    radiology services. In contrast, TRICARE regulation limited reimbursement to hospitals for
    individual outpatient radiology services to the technical component portion of the [CMAC], which
    was one component of Medicare’s physician fee schedule. Consistent with TRICARE policy under
    statute to pay similar to Medicare, we have determined that discretionary adjusted payments may
    better reflect the Medicare payment amounts for outpatient radiology claims.
    DPP Contract Notice at A5–A7.
    -4-
    adjustment” and to “govern the review of payments for hospital outpatient radiology services and
    payment of any discretionary net adjustments.” Id.
    Step 1 instructed hospitals to “submit[] a request for analysis of their claims data for
    hospital outpatient department radiology charges” for the period before TRICARE OPPS took
    effect. Id. Step 2 in relevant part expounded on submitting claims data, contact information, and
    questions. The second step described the process for determining necessary claims data:
    “[H]ospital[s] submit[] data with [their] name, address, zip code, Tax ID number, TRICARE
    sub ID number, the 6-digit Medicare OSCAR provider number [also known as the provider
    identification number], and [National Provider Identification (‘NPI’) number].” Id. Step 2 also
    directed hospitals to provide contact names and addresses “to be used by TMA for formal
    response to the request.” DPP Contract Notice at A7. Each hospital compiled the required
    information in “[a] separate Excel spreadsheet . . . in the TMA-specified format.” Id. Step 2
    also specified the method to ask TMA questions noting, “Questions of general interest to all
    hospitals will be posted with answers on the TMA website.” DPP Contract Notice at A7; see
    Def.’s MSJ App. at A10–A15 [hereinafter DPP Contract FAQs].
    Steps 3–6 disclose how TMA would extract, exclude, and analyze claims data. DPP
    Contract Notice at A7–A9. Specifically, Step 3 explained “TMA w[ould] extract the claims for
    each hospital for claims for outpatient radiology services during the relevant period.” Id. at A7.
    Step 3 also indicated which of the extracted claims TMA would exclude from consideration,
    such as “if the [Technical Component (‘TC’)] CMAC amount is less than the global CMAC and
    the claim does not have a TC modifier. Id. at A7–A8. Step 4 presented the “‘Medicare’
    method” TMA used to “calculate what would have been paid under the approach that Medicare
    used to pay hospital outpatient radiology claims prior to [Centers for Medicare & Medicaid
    Services (‘CMS’)] implement[ing] . . . the Medicare OPPS in 2000.” Id. at A8. Step 5 detailed
    how TMA “adjust[ed] the ‘Medicare’ amount calculated [through the Medicare Method] in Step
    4 on each claim using the ratio of the actual allowed amount (the amount that a health plan has
    determined to be a fair price for a given medical treatment) on the claim to the TRICARE
    Standard allowed amount (the technical component of the CMAC).” Id. Step 6 explained how
    TMA “then compare[d] the adjusted ‘Medicare’ amount for each claim with the actual allowed
    amounts on that claim” and “calculate[d] the difference between the two amounts.” Id. at A9.
    The difference between the Medicare method calculation and the payment from TMA “w[as]
    used in determining the level of additional payment to the hospital.” DPP Contract Notice at A9.
    If the resulting difference was more or equal to TMA’s payment, “no additional payment shall be
    made.” Id. Step 7 clarified “[i]f the calculations in Step 6 [comparing the actual allowed amount
    and the Medicare method amount] indicate that an additional payment shall be made to the
    hospital, then a hospital-specific offset for cost sharing shall be calculated.” Id.
    Step 8 notified hospitals “[a] written response [at] the hospital’s request w[ould] be sent
    to the individual at the address provided by the hospital [and] provide the calculated
    discretionary adjusted payment and the calculations from which the adjustment was derived.”
    Id. Step 8 added “[w]hile the methodology for calculating the adjustment is not subject to
    questions, any questions regarding the data used in the calculations should be received by TMA
    within 30 days . . . of TMA’s response . . . . Any questions should be accompanied by detailed
    -5-
    explanation of the alleged errors and the proposed corrections with supporting documentation.”
    Id. at A9; see Def.’s MSJ App. at A16 (DPP Contract Sample Response).
    Finally, Step 9 specified TMA’s written response mentioned in Step 8 included “a release
    and agreement to accept the discretionary adjusted payment by the hospital.” DPP Contract
    Notice at A9. Per Step 9, “[t]he signed release and agreement should be returned to TMA within
    30 days of the date of initial response or TMA response to any questions raised in [S]tep 8,
    whichever date is later.” Id. After TMA received “the signed release and agreement, payment
    w[ould] be made to the hospital.” Id.
    Plaintiffs estimate several thousand hospitals submitted requests for discretionary
    payment, including the six named plaintiffs in this case (“plaintiffs”): McLaren Greater Lansing
    (Ingham Regional Medical Center), INTEGRIS Baptist Regional Health Center (Miami),
    INTEGRIS Bass Baptist Health Center, INTEGRIS Grove Hospital, INTEGRIS Baptist Medical
    Center (Integris Baptist), and INTEGRIS Canadian Valley Hospital. See Ingham Reg’l Med.
    Ctr. v United States, 
    126 Fed. Cl. 1
    , 16 (2016), aff’d in part, rev’d in part, 874 F.3d at 1348. The
    Court previously “determined that plaintiffs in this lawsuit have appropriately pled that a
    contract was formed between TMA and plaintiffs through: (1) the April 25, 2011 letter, (2) the
    Notice, (3) the FAQs, (4) the spreadsheets that hospitals submitted to TMA to provide their
    identifying information and indicate their interest in receiving the adjustment, (5) the payment
    adjustment worksheets that TMA provided to hospitals to show the amount of TMA’s proposed
    adjustment, and (6) the release of claims that hospitals executed to receive their adjustment
    payments (‘the Release’).” Def.’s MSJ at 17 (citing Ingham Reg’l Med. Ctr., 126 Fed. Cl. at
    31–32).
    B.      Regulatory Scheme
    The relevant provisions of the regulatory scheme of 
    32 C.F.R. § 199.14
    (a)(5) provide:
    (5) Hospital outpatient services. This paragraph (a)(5) identifies and clarifies
    payment methods for certain outpatient services, including emergency services,
    provided by hospitals . . . .
    (iv) Radiology services. TRICARE payments for hospital outpatient radiology
    services are based on the allowable charge method under paragraph (j)(1) of the
    section. In the case of radiology services for which the CMAC rates are established
    under that paragraph, a payment rate for the technical component of the radiology
    services is provided. Hospital charges for an outpatient radiology service are
    reimbursed using the CMAC technical component rate. . . .
    (xi) Facility charges. TRICARE payments for hospital outpatient facility charges
    that would include the overhead costs of providing the outpatient service would be
    paid as billed. For the definition of facility charge, see § 199.2(b).
    C.      Procedural History
    -6-
    On 21 October 2013, plaintiffs brought this action claiming the government underpaid
    them for certain outpatient medical services they provided between 1 August 2003 and 1 May
    2009. See Ingham Reg’l Med. Ctr., 126 Fed. Cl. at 9. Plaintiffs allege the approximately six
    years of underpayment breached two contracts and violated various statutory and regulatory
    provisions. Id. Plaintiffs seek to represent a class of approximately 1,610 similarly situated
    hospitals. See Pls.’ Mot. to Certify, ECF No. 76.
    On 13 January 2015, the government filed a motion to dismiss plaintiffs’ complaint for
    failure to state a claim pursuant to Rule 12(b)(6) of the Rules of the United States Court of
    Federal Claims (“RCFC”), Def.’s Mot. to Dismiss, ECF No. 41. The government argued
    plaintiffs “fail[ed] to allege facts” sufficient to establish a binding contract with the government
    or that any contract was breached, and absent a valid contract, “there [could] be no mutual
    mistake or breach of the covenant of good faith and fair dealing.” Id. at 1. On 22 March 2016,
    this Court dismissed plaintiffs’ complaint for failure to state a claim. See Ingham Reg’l Med.
    Ctr., 874 F.3d at 1346. Plaintiffs appealed three claims: the “(1) breach of express contract
    between Ingham and DoD based on the [DPP]; (2) revision of Ingham’s contract based on
    mutual mistake, in light of the errors in the calculations of radiology outpatient services and the
    Kennell study; and (3) violations of money-mandating statutes and regulations.” Id. On 3
    November 2017, the Federal Circuit “reverse[d] the dismissal of [plaintiff] Ingham’s breach of
    contract claim, affirm[ed] the dismissal of [plaintiffs’] money-mandating claim, and [did] not
    reach the claim for mutual mistake.” Id. at 1348. Although the Federal Circuit found the
    Release does not bar Ingham from bringing a breach of contract claim, it did not further interpret
    the contract. See id. at 1346. The Federal Circuit remanded the case “for further proceedings on
    the breach of contract claim.” Id. at 1348. On remand, plaintiffs filed an amended complaint,
    the government filed its answer, and the parties engaged in discovery, ECF Nos. 74, 79. This
    case was transferred to the undersigned Judge on 29 July 2019. See Order, ECF No. 114.
    On 14 January 2020, the Court issued an order ruling on five motions regarding the
    government’s effort to “claw back” purportedly privileged documents it inadvertently sent
    plaintiffs. 14 Jan. 2020 Op. & Order. The Court held these communications were not privileged
    by analogizing the DPP to “an insurer’s claim investigation” as “DoD investigated hospitals’
    underpayment claims further before making a payment determination.” Id. at 18. The Court
    stated, “When [one of the allegedly privileged documents] was created, the government’s
    primary focus was the calculation, and recalculation, of TRICARE payments which became the
    government’s business during the [DPP].” Id. at 22. “While there may have been
    communication exchange between the parties regarding ‘settlement’ after the Notice, the
    comments were related to calculation review regarding repayment” and the parties aimed to
    “avoid litigation.” Id. at 19, 21. The Court found “the term ‘settlement’ in this context refers to
    a negotiated business settlement, not the settlement of a legal action, because the government
    sought to correct payment errors and avoid litigation.” Id. at 20. The Court thus held the
    documents in question could not “constitute preparation for litigation,” and the DPP Contract
    was a “negotiated business settlement to agree on a recalculation figure.” Id. at 20, 22.
    On 5 June 2020, plaintiffs filed a renewed motion to certify class and appoint class
    counsel (“Pls.’ Class Cert.”), ECF No. 146. The government filed a response to plaintiffs’
    renewed motion for class certification on 26 August 2021 (“Def.’s Class Cert. Resp.”), ECF No.
    -7-
    207, and on 4 February 2022, plaintiffs filed a reply in support of their renewed motion to certify
    class action and appoint counsel, (“Pls.’ Class Cert. Reply”), ECF No. 226. On 26 August 2021,
    the government filed a motion for summary judgment (“Def.’s MSJ”), ECF No. 203. Plaintiffs
    filed an opposition to government’s motion for summary judgment on 4 February 2022 (“Pls.’
    MSJ Resp.”), ECF No. 225, and on 11 March 2022, the government filed a reply in support of its
    motion for summary judgment (“Def.’s MSJ Reply”), ECF No. 234.
    The parties then filed seven evidentiary motions and one motion for leave to file amended
    briefs. On 26 August 2021, the government filed a motion to exclude inadmissible evidence
    relied upon in plaintiffs’ motion for class certification, ECF No. 204, under Rule 408 of the
    Federal Rules of Evidence (“FRE”). The same day, the government filed a motion to exclude the
    expert opinion of Jane Jerzak, ECF No. 205, and a motion to exclude the expert opinion of
    Anthony Fay, EFC No. 206. On 11 March 2022, the government filed a motion to strike
    inadmissible evidence under FRE 408 relied upon in plaintiffs’ response to the government’s
    motion for summary judgment and plaintiffs’ response to the government’s motion to exclude
    the expert opinion of Jane Jerzak, ECF No. 238. The next day, the government moved to strike
    paragraphs 7 and 18 of the declaration of Sere Allen, ECF No. 239. On 14 March 2022, the
    government moved to strike paragraphs 3 through 10 of Dale Thompson’s declaration, ECF No.
    240. The next day, plaintiffs filed a motion for leave to file amended briefs and appendices, ECF
    No. 242. On 5 April 2022, plaintiffs filed a motion to exclude the expert opinion and continued
    participation of David L. Kennell and Kennell and Associates, ECF No. 251. 4 The Court
    considers plaintiffs’ amended briefs and appendices, ECF No. 242, to the extent they are relevant
    to this Opinion and Order.
    D.       Scope of Questions Presently at Issue
    The Court held a status conference on 11 May 2022 to discuss at length all ten motions
    pending before the Court, ECF No. 241. The Court discussed whether there were material
    disputes of fact to preclude summary judgment and whether the Court should resolve the
    government’s summary judgment motion with plaintiffs’ motion for class certification. 11 May
    2022 Status Conference Tr. (“SC Tr.”) at 6:23–7:2, ECF No. 257. All parties agreed “the
    interpretation of the contract . . . and [the] interpretation of 
    32 C.F.R. § 199.14
     [are] question[s]
    of law,” and decisions in conjunction with class certification would be “a great benefit to clarity
    in the case and a preservation of resources” if adverse to plaintiffs. SC Tr. at 116:12–19. At the
    parties’ request, the Court also considered whether mediation might be appropriate. SC Tr. at
    7:3–4. Plaintiffs preferred mediation, but the government opposed mediation at the time. See
    SC Tr. at 112:17–114:23. The parties discussed their various evidentiary motions and motion for
    leave to file—specifically the materiality of each motion to the government’s motion for
    summary judgment and plaintiffs’ motion for class certification. SC Tr. at 7:5–8.
    During oral argument on 9 June 2022, both parties confirmed there are no disputes of
    material fact on the issues of: (1) TMA’s duties under the contract; and (2) whether there was a
    mutual mistake of fact. 9 June 2022 Oral Argument Tr. (“Tr.”) at 78:11–19, ECF No. 259. The
    parties also agreed their various pending evidentiary motions are not necessary to resolve the two
    4
    The parties also filed response and reply briefs in opposition to these motions and in support of these motions,
    respectively. See ECF Nos. 212, 220, 223, 243, 244, 245, 247, 248, 250, 252, and 253.
    -8-
    summary judgment issues: (1) contract interpretation; and (2) class certification. Tr. at
    78:20–79:4. Thus, the 9 June 2022 oral argument and this opinion and order do not contemplate
    the parties’ evidentiary motions, as the motions to exclude expert opinions, ECF. Nos. 205, 206,
    and 251, and strike certain portions from certain filings, ECF Nos. 238, 239, and 240, are
    contingent upon the Court determining the appropriate interpretation of the DPP Contract. SC
    Tr. at 122:13–16 (THE COURT: “[W]e proceed to summary judgment on the two items
    generally described as . . . CFR 32-199 and the clarification of what’s released as part of the
    DPP, as well as class certification[.]”). In turn, the Court assesses: (1) the extent of TMA’s
    contractual duties under the DPP; and (2) the availability of the defense of mistake regarding 32
    CFR 199.14(a)(5)’s CHAMPUS discount rates. See Tr. 77:6–14 (THE COURT: “Issue 1, if the
    Court finds that the government only had a duty to use the data that it had, that plaintiffs did not
    know about, in order to plug into the DPP, and that they did that, and then on Issue 2, the Court
    finds that there was no mistake with respect to 32 CFR 199.14(a)(5), what issues still remain in
    the case? [PLAINTIFFS]: I don’t think there would be issues remaining[.]”).
    II.    Parties’ Arguments on the Government’s Motion for Summary Judgment
    The government argues plaintiffs’ breach of contract claim fails as a matter of law
    “because the parties’ contract assigned the ultimate responsibility for identifying any errors in
    the adjustment calculation to the plaintiffs, and provided them a hard and fast 30-day deadline for
    doing so.” Def.’s MSJ at 31. For plaintiffs’ mutual mistake of fact claim, the government
    argues “there is no mistake to begin with.” Id. at 32. The government adds “plaintiffs bear the
    risk of the mistakes that they now allege, and . . . the reformation that they seek is legally
    unavailable because TMA specifically explained in the parties’ contract that it was not offering
    any such adjustment.” Id.
    Plaintiffs argue the “Government is liable to Plaintiffs on the following two bases: (1)
    the Government breached the DPP by failing to properly extract and adjust all of Plaintiffs’
    radiology claims[;] and (2) the Parties committed a mutual mistake of fact upon entering the DPP
    by believing that the Government had properly reimbursed Plaintiffs for all categories of
    outpatient services (except for radiology), including by appropriately paying for facility
    charges.” Pls.’ MSJ Resp. at 17. “First, as to the Plaintiffs’ breach of contract claim, the plain
    language of the DPP shows that the Government breached what was a clear contractual duty to
    extract and adjust all of the Plaintiffs’ radiology claims.” Id. at 18. “Second, as to the Plaintiffs’
    claim for mutual mistake, the plain language of § 199.14(a)(5) shows that the Government must
    reimburse hospitals for the overhead costs of providing outpatient services, as billed, including
    for all facility charges.” Id.
    III.   Summary Judgment Standard
    Summary judgment is proper when the evidence fails to reveal a “genuine issue as to any
    material fact and that the moving party is entitled to a judgment as a matter of law.” Anderson v.
    Liberty Lobby, Inc., 
    477 U.S. 242
    , 247 (1986). “Genuine” issues exist if “the evidence is such
    that a reasonable jury could return a verdict for the nonmoving party.” 
    Id. at 248
    . Facts are
    “material” if they “might affect the outcome of the suit” and do not include “irrelevant or
    unnecessary” factual disputes. 
    Id.
     Inferences “must be viewed in the light most favorable” to
    -9-
    the nonmoving party when considering summary judgment. Matsushita Elec. Indus. Co. v.
    Zenith Radio Corp., 
    475 U.S. 574
    , 587 (1986). The moving party “always bears the initial
    responsibility” of presenting evidence which “demonstrate[s] the absence of a genuine issue of
    material fact.” Celotex Corp. v. Catrett, 
    477 U.S. 317
    , 323 (1986). If this burden is met, the
    nonmovant must “set forth specific facts showing that there is a genuine issue for trial.”
    Anderson, 
    477 U.S. at 256
    .
    IV.     Analysis of Plaintiffs’ Breach of Contract Claim
    The government argues: (1) TMA had no contractual duty to extract, analyze, and adjust
    radiology claims data from the hospitals 5 under the contract; and (2) plaintiffs bore the risk of
    any data discrepancy. See generally Def.’s MSJ. The government asserts plaintiffs’ breach of
    contract claim “fails as a matter of law . . . because the parties’ contract assigned the ultimate
    responsibility for identifying any errors in the adjustment calculation to the plaintiffs, and
    provided them a hard and fast 30-day deadline for doing so.” Id. at 31. The government states,
    “[t]he contract provided that TMA would first extract data with certain contractually-specified
    identifiers from its own records, and use the methodology specified in the parties’ contract to
    generate a proposed adjustment amount[.]” Id. (citing DPP Contract Notice at A7–A8). Then,
    “once TMA presented this proposed adjustment amount to the hospitals, the hospitals were
    required to raise ‘any questions regarding the data used in the calculations’ and provide a
    ‘detailed explanation of the alleged errors and the proposed corrections with supporting
    documentation’ within 30 days.” Id. (citing DPP Contract Notice at A8). The government adds
    plaintiffs “received years ago exactly what they bargained for, i.e., a quick payment of a definite
    adjustment amount that they accepted with full knowledge that they had not examined the
    provenance of that number using their own data, and, accordingly, with full acceptance of any
    associated risk.” Id.
    Plaintiffs argue: (1) TMA had a contractual duty to extract, analyze, and adjust plaintiffs’
    radiology claims data under the contract; (2) TMA had a duty to extract line items from its
    database; and (3) TMA bore the risk of any data discrepancy, not plaintiffs. See generally Pls.’
    MSJ Resp. Plaintiffs add “[t]he Government’s attempt to shirk its contractual duty fails as (a)
    the evidence proves that the Government breached the DPP, (b) the Government was responsible
    for ensuring the accuracy of its data, not Plaintiffs, and (c) the Government cannot prove any
    affirmative defense, as is required, to avoid liability.” Id. at 23.
    5
    The Court refers to the data not in TMA’s records as “hospital” data because plaintiffs’ mention of “all of the
    radiology line items,” Pls.’ MSJ Resp. at 27, relates to their argument TMA’s databases were missing certain records
    which the hospitals submitted. See id. at 30 (“The Government does not explain why some of the data did not exist
    in its systems . . . .”); see also Tr. at 101:7–102:3 (“THE COURT: . . . Plaintiffs read [Step 3 as stating] TMA will
    extract the claims for each hospital’s submitted claims for outpatient radiology services? [PLAINTIFFS]: I think
    that’s the only way to fairly interpret that language . . .” (emphasis added)). As a factual matter, the government
    admits records were missing from TMA’s database, but the government contends it was not required under the
    contract to find additional data as a legal matter. Tr. at 13:14–22 (“[THE GOVERNMENT:] . . . [W]e discovered
    that there were 139 line items in the INTEGRIS data set that TMA could not find in its records. So, . . . the
    INTEGRIS data set does contain records that are missing from ours. I don’t think that changes our legal position on
    the motion for summary judgment . . . because . . . there is no contract requirement for us to adjust records that we
    don’t own because the contract’s cast in terms of extraction.”).
    - 10 -
    There are four elements to a breach of contract claim: “(1) a valid contract between the
    parties, (2) an obligation or duty arising out of the contract, (3) a breach of that duty, and (4)
    damages caused by the breach.” San Carlos Irrigation & Drainage Dist. v. United States, 
    877 F.2d 957
    , 959 (Fed. Cir. 1989) (citations omitted). For the first element, the court previously
    found “a valid contract between the parties,” and the parties do not dispute this finding. Ingham
    Reg. Med. Ctr., 126 Fed. Cl. at 22, 31–32 (2016), aff’d in part, rev’d in part on other grounds,
    
    874 F.3d 1341
     (Fed. Cir. 2017); Def.’s MSJ at 17; Pls.’ MSJ Resp. at 13; see San Carlos
    Irrigation & Drainage Dist., 
    877 F.2d at 959
    ; Def.’s MSJ App. at A1–A2 [hereinafter DPP
    Contract Letter]; DPP Contract Notice at A3–A9; DPP Contract FAQs at A10–A15; Def.’s MSJ
    App. at A17 [hereinafter DPP Contract Release]. The Court accordingly considers: (1) whether
    the contract obligates TMA as plaintiffs allege; (2) if TMA had contractual duties, whether it
    breached those duties; (3) if TMA breached, whether any breach caused plaintiffs’ damage; and
    (4) whether the government proves any viable defenses to plaintiffs’ breach of contract claim.
    See San Carlos Irrigation & Drainage Dist., 
    877 F.2d at 959
    .
    A.       Whether TMA Had a Contractual Duty to Extract, Analyze, and Adjust
    Hospital Radiology Data
    The government concedes the DPP required TMA to fulfill certain contractual
    obligations it owed to plaintiffs. Def.’s MSJ at 34 (noting “TMA’s duties toward the plaintiffs”).
    To determine the extent of the obligations, the Court looks to the DPP’s plain language and gives
    the words their plain and ordinary meaning, unless the language is ambiguous. See United
    Cmtys., LLC v. United States, 
    154 Fed. Cl. 676
    , 681 (2021). The Court first narrows the contract
    provisions to plaintiffs’ radiology data before then determining its ambiguity (or lack thereof)
    and analyzing the plain meaning of the DPP language.
    Missing data is the central problem to the issue of what data the government had a duty to
    correctly adjust. Between hospitals submitting their claims data to intermediaries, intermediaries
    processing the data and submitting it to TMA, and TMA storing the data in its database, some
    claims data was miscategorized or lost. For example, eighty-two line items from
    plaintiff-Ingham were all together missing from TMA’s database. Some of the data loss was due
    to programming errors and records conversion issues with intermediaries between 2003 and 2009
    after original submission, but the extent, timing, and exact causes of the loss are unknown.
    Plaintiffs’ expert report did not opine regarding how much data was missing. 6 The question the
    Court addresses now is whether the government had a duty to find and correct this missing data
    6
    This explanation is based on the parties’ statements at oral argument. See Tr. at 12:7–11 (“[THE
    GOVERNMENT]: . . . Plaintiffs, because of the way they structured their expert report, did not actually address
    that issue specifically, trying to quantify or identify why line items may have been missing or anything to that
    effect.”), 50:12–15 (“THE COURT: . . . [W]hen we were just talking about Ingham as an example, there were 82
    that were missing? [THE GOVERNMENT]: Yes.”), 50:23–51:4 (“[THE GOVERNMENT]: . . . [H]ow this
    particular error manifested itself was the hospital would appropriately code it. It would be a CPT code for an x-ray
    of your arm. It would forward that information to the fiscal intermediary. There’s some crazy data cross-walking
    problem on the part of Healthnet that—a programming error which caused those CPT codes to be rerecorded as
    generic codes.”), 74:9–16 (“[PLAINTIFFS]: . . . [I]t’s not part of our interpretation that there has to be a
    reevaluation of the hospital’s claims, just that the thing that is being extracted is the hospital’s claim and not
    something that the government or its fiscal intermediaries . . . have changed in some way that’s unknown to
    plaintiff[s].”), 257:19–24 (“[THE GOVERNMENT]: . . . [T]he issue is that the fiscal intermediary doesn’t have
    those claims. Right? There was a records conversion issue, and so . . . . I don’t know that we still have them.”).
    - 11 -
    under the DPP, or whether the government could re-calculate the payments under the DPP
    utilizing the data as it existed in 2011 in the government’s possession.
    The government argues, “Plaintiffs fail to cite any provision of their contracts that
    contain” an explicit duty for the government to extract and adjust the hospitals’ radiology data.
    Def.’s MSJ Reply at 6. The government adds, “TMA had no obligation to adjust line items that
    were not in its physical possession.” Tr. at 12:3–5. In response, plaintiffs argue “the plain
    language of the DPP shows that the Government breached what was a clear contractual duty to
    extract and adjust all of the Plaintiffs’ radiology claims.” Pls.’ MSJ Resp. at 18. Plaintiffs assert
    “the Government itself concedes that it did not follow the methodology in the DPP under which
    the Government expressly promised that it would extract and adjust all of the radiology line
    items.” Id. at 27. To support the contention the DPP required TMA “to extract, analyze, and
    adjust all of Plaintiffs’ radiology claims data,” plaintiffs cite several contractual provisions,
    including: the Letter; Step 1; Step 3; Step 4; Step 5; Step 6; Step 7; FAQ 2; and FAQ 14. Id. at
    24–28. Plaintiffs assert “[i]t would be unreasonable to expect a hospital reading the plain
    language of the DPP to infer that only some of the required claims would be included.” Id. at 28.
    The original hospital submissions comprise “all” of plaintiffs’ radiology claims. See Tr. at
    74:9–16 (“[PLAINTIFFS]: . . . [I]t’s not part of our interpretation that there has to be a
    reevaluation of the hospital’s claims, just that the thing that is being extracted is the hospital’s
    claim and not something that the government or its fiscal intermediaries . . . have changed in
    some way that’s unknown to plaintiff[s].”)
    Contract interpretation is a question of law. 7 See Jowett, Inc. v. United States, 
    234 F.3d 1365
    , 1367–68 (Fed. Cir. 2000). The court “must interpret the contract in a manner that gives
    meaning to all of its provisions and makes sense.” 
    Id. at 1368
     (quoting McAbee Constr., Inc. v.
    United States, 
    97 F.3d 1431
    , 1435 (Fed. Cir. 1996)). Beginning with the “plain language,” the
    court must “give the words of the agreement their ordinary meaning unless the parties mutually
    intended and agreed to an alternative meaning.” 
    Id.
     (first quoting McAbee Constr., Inc., 
    97 F.3d at 1435
    , and then quoting Harris v. Dep’t of Veterans Affairs, 
    142 F.3d 1463
    , 1467 (Fed. Cir.
    1998)). The court must also determine “the intent of the parties at the time they contracted, as
    evidenced by the contract itself.” Greco v. Dep’t of the Army, 
    852 F.2d 558
    , 560 (Fed. Cir.
    1988). If multiple interpretations of contract provisions exist, they “should be construed most
    strongly against the drafter.” United States v. Seckinger, 
    397 U.S. 203
    , 210 (1970).
    As a threshold matter, both parties agree the relevant contract language is unambiguous,
    though they disagree as to the interpretation. See Tr. at 72:24–25 (“[PLAINTIFFS]: . . . We
    don’t think there’s an ambiguity.”); 103:13–14 (“[PLAINTIFFS]: . . . I don’t necessarily allege
    that Step 3 is ambiguous.”); Def.’s MSJ Reply at 1 (“In our opening brief, we demonstrated that
    the contracts . . . are simple, straightforward, and fundamentally unambiguous instruments.”).
    As the parties agree the contract is unambiguous, the Court now considers the various terms as
    they relate to TMA’s duties under the contract. First, the Court assesses the role of
    intermediaries who were “made aware of th[e] DoD initiative [to calculate the net adjustments
    7
    As the nonmovant, plaintiffs agree “interpreting [TMA’s] contractual duties is purely an issue of law.” Tr. at
    72:21–23. The Court accordingly need not determine whether the evidence reveals a “genuine issue as to any
    material fact” and must only consider whether the government “is entitled to judgment as a matter of law.”
    Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    , 247 (1986).
    - 12 -
    itself], but [would] not otherwise be involved in the calculation of net adjustments.” DPP
    Contract Letter at A1. The Court then analyzes TMA’s obligations in Step 1 instructing
    hospitals to “submit a request for analysis of their claims data” and in Step 2 directing hospitals
    to enter basic identifying information in a provided Excel spreadsheet as part of the Step-1
    request. DPP Contract Notice at A7. In Step 3, the Court reviews whether “TMA extract[ing]
    the claims for each hospital for claims for outpatient radiology services” provided in the Excel
    spreadsheet requires TMA to consider data not included in the spreadsheet. 
    Id.
     at A7–A8. Next,
    the Court must determine if “each” qualifying “hospital” or “claim” throughout the CHAMPUS
    methodology—as well as FAQ 14, which clarifies the DPP analysis was performed on a service
    line basis—requires TMA to examine all plaintiffs’ radiology data in the aggregate or just
    claims-level data individually. 
    Id.
     at A5–A7; DPP Contract FAQs at A12. If the Court
    determines the DPP Contract obligates TMA to inspect the hospitals’ data as opposed to just
    claims data in TMA’s database, the Court must determine whether TMA had a contractual duty
    to verify its data.
    The government first argues regardless of how the steps are calculated in the
    methodology, the government only has the data previously provided by intermediaries. See
    Def.’s MSJ at 38 (“It was important that individual hospitals provide complete identifying
    information that TMA did not have in order to establish the unique, agreed-upon parameters of
    TMA’s records search for that hospital.”). The Letter provides: “Because this issue affects all
    three TRICARE regions and multiple years of claimed services, DoD has decided to calculate
    the net adjustments itself, rather than through the [intermediaries], which have been made aware
    of this DoD initiative, but will not otherwise be involved in the calculation of net
    adjustments . . . .” DPP Contract Letter at A1. Plaintiffs contend the plain language of the DPP
    explicitly required TMA to extract all the radiology claim data, including data from the hospitals
    not in the database, and to examine its data for errors. Pls.’ MSJ Resp. at 23. To argue the
    government was obligated to analyze the hospitals’ radiology data, plaintiffs emphasize “DoD
    has decided to calculate the net adjustments itself.” Id. at 25 (emphasis removed) (quoting DPP
    Contract Letter at A1). Plaintiffs argue in TMA claiming it would calculate the net adjustments
    itself, “[t]he government impliedly warrant[ed] the accuracy of matters set forth in contract
    documents.” Id. at 23–24 (citing D.F.K. Enters., Inc. v. United States, 
    45 Fed. Cl. 280
    , 285
    (1999)).
    To illustrate the differences in language and meaning between the Letter and plaintiffs’
    interpretation, the Court first reads the Letter through the lens of plaintiffs’ interpretation.
    Plaintiffs’ interpretation of the Letter to input “the hospitals’ data” within the calculations
    essentially requires adding the words “with the hospitals’ data” to read “DoD has decided to
    calculate the net adjustments itself with the hospitals’ data.” See DPP Contract Letter at A1. As
    can be seen from considering the additional limitation, the inclusion of the additional words
    expands the scope of the obligation on the government. The plain meaning of the original
    sentence from the Letter—“DoD has decided to calculate the net adjustments itself, rather than
    through the [intermediaries]”—is TMA would not involve intermediaries in the DPP calculation
    process or use the hospitals’ data from the intermediaries. Id.; see also Tr. at 106:3–11 (“[THE
    GOVERNMENT]: If the [intermediarie]s are not going to be involved with this process, they
    are the repository of the plaintiffs’ submitted hospital data. So . . . we are clearly signaling that
    we are not going back to the clearinghouse, we are not going back to the hospital data. That
    - 13 -
    leaves the only thing to be extracted would be the records in the government’s official record of
    payment in Step 3.”). This original sentence from the Letter does not provide TMA would
    analyze plaintiffs’ data by performing the analysis itself—in fact, the provision lacks any
    mention of data, plaintiffs’ or otherwise. DPP Contract Letter at A1. The Court cannot change
    the plain meaning of the Letter by adding language. See Antonin Scalia & Bryan A. Garner,
    Reading Law: The Interpretation of Legal Texts 174 (2012) (“[I]t is no more the court’s function
    to revise by subtraction than by addition.”). The Court finds plaintiffs’ interpretation
    inapplicable because the interpretation requires the addition of words to support plaintiffs’
    preferred meaning. See 
    id.
    As part of the DPP, DoD further clarified the decision not to use intermediaries in the
    DPP was made for administrative efficiency. See DPP Contract Letter at A1. Intermediaries
    were not involved “[b]ecause this issue affects all three TRICARE regions and multiple years of
    claimed services[.]” 
    Id.
     This explanation further put plaintiffs on notice TMA planned to
    process its data itself to perform the adjustments rather than expending time and resources
    involving numerous outside parties or finding the hospitals’ data to process. The plain meaning
    of the Letter undermines plaintiffs’ argument the government had to analyze the hospitals’ data.
    See Jowett, Inc., 
    234 F.3d at 1368
     (quoting McAbee Constr., Inc., 
    97 F.3d at 1435
    ); DPP
    Contract Letter at A1.
    It is also important to understand the calculation outcome is dependent on which data is
    processed. While the government describes a DPP calculation, plaintiffs confuse the described
    calculation with a calculation outcome which requires utilizing the hospitals’ data. The Letter
    clarifies TMA is only extracting, analyzing, and adjusting the data previously furnished by
    intermediaries—and the Letter clarifies only TMA is doing so. See DPP Contract Letter at A1
    (“DoD has decided to calculate the net adjustments itself, rather than through the
    [intermediaries] . . . .”). Plaintiffs seemingly infer from the government’s responsibility to
    perform calculations a promise the calculations will be perfectly accurate and use the hospitals’
    data to achieve that perfection: “DoD has decided to calculate the net adjustments itself, rather
    than through the [intermediaries],” DPP Contract Letter at A1, according to plaintiffs is
    “unambiguous, and make[s] clear that the duty to extract, analyze, and adjust all of Plaintiffs’
    radiology claims data were [sic] not discretionary tasks, and rested solely with the Government.”
    Pls.’ MSJ Resp. at 26 (emphasis added). The cited sentence of the Letter references who is
    involved in the payment process—DoD, not intermediaries—rather than what is involved in the
    payment process. See DPP Contract Letter at A1. Plaintiffs read in a nonexistent warranty
    regarding the process by asserting the government, as sole arbiter of the calculations, must utilize
    the hospitals’ data. See 
    id.
     The plain language does no more than exclude intermediaries from
    the process. See Jowett, Inc., 
    234 F.3d at 1368
     (quoting McAbee Constr., Inc., 
    97 F.3d at 1435
    );
    DPP Contract Letter at A1.
    In summary, the Court does not read the government’s statement intermediaries would
    not be involved in DPP calculations as making a promise to adjust specific data. The language
    of the Letter refers only to the involvement of intermediaries—or lack thereof—in the DPP
    process and does not imply a guarantee of perfect calculations using the hospitals’ data. The
    plain meaning of the Letter does not bind the government to analyze the hospitals’ data but rather
    - 14 -
    clarifies intermediaries would not be involved for efficiency’s sake. See Jowett, Inc., 
    234 F.3d at 1368
     (quoting McAbee Constr., Inc., 
    97 F.3d at 1435
    ); DPP Contract Letter at A1.
    1.     Whether Step 1 and 2’s Plain Meaning Instructing Hospitals to
    “submit[] a request for analysis of their claims data” Obligates TMA
    to Any Performance
    As part of the DPP, the 2-page Letter made hospitals aware more detailed procedures
    would follow. The Letter stated “[d]etailed instructions will be posted on the [TMA] Web Site”
    and noted these instructions would “explain[] the manner in which a hospital may request th[eir]
    claims data be reviewed for appropriate discretionary adjusted payments.” DPP Contract Letter
    at A1. These instructions were the Notice and “answers to certain Frequently Asked Questions
    (DPP Contract FAQs).” Def.’s MSJ at 11 (citing DPP Contract Notice & FAQs at A3–A15).
    Rather than detailing the methodology or defining the extent of data TMA would use, the Letter
    directs the hospitals to the 7-page Notice and 20-question FAQs. Extrinsic evidence cannot
    change the plain meaning of a writing, but meaning can almost never be plain except in context.
    Restatement (Second) Contracts cmt. b (Am. L. Inst. 1981). Contextualizing the Letter with the
    Notice and FAQs “gives meaning to all . . . provisions and makes sense[,]” allowing the Letter to
    be read as a whole. See Jowett, Inc., 
    234 F.3d at 1368
     (quoting McAbee Constr., Inc., 
    97 F.3d at 1435
    ). The Court accordingly next addresses the Notice and FAQs.
    Steps 1 and 2 of the Notice outlined the process for requesting analysis of claims data:
    Step 1: Hospital submits a request for analysis of their claims data (process defined
    in Step 2) for hospital outpatient department radiology charges during the period
    from August 1, 2003, to April 30, 2009, which is the last day before TRICARE’s
    OPPS became effective on May l, 2009. Small rural hospitals not subject to
    TRICARE’s OPPS until January 1, 2010, shall submit a request for the August 1,
    2003-December 31, 2009 period. Critical Access Hospitals (CAHs) are not subject
    to TRICARE’s OPPS and shall submit a request for the August 1, 2003-November
    30, 2009 period. As of December 1, 2010, CAHs are reimbursed 101 percent of
    reasonable costs. Hospitals not subject to OPPS (such as Cancer and Children’s
    hospitals) shall submit a request for the August 1, 2003-December 31, 2010 period.
    Step 2: As part of the request, hospital submits data with its name, address, zip
    code, Tax ID number, TRICARE sub ID number, the 6-digit Medicare OSCAR
    provider number, and NPI number. If multiple Tax ID or Medicare provider
    numbers were used during this period, hospitals will submit these data. The request
    shall also include the name and address to be used by TMA for formal response to
    the request. A separate Excel spreadsheet must be completed for each hospital in
    the TMA-specified format. An example is posted on the TMA website . . . .
    Hospitals will also submit the name of a contact and a phone number to resolve any
    questions. The request will be submitted to the following address: [omitted]. Any
    questions should be submitted to the following email address: [omitted]. Questions
    of general interest to all hospitals will be posted with answers on the TMA website.
    - 15 -
    DPP Notice at A7. Plaintiffs argue Step 1 of the Notice “provides the hospital submit[] a request
    for analysis of their claims data,” and plaintiffs noted Step 1 “is at the very beginning of the
    hierarchy.” Tr. at 127:16–24. Step 1 required hospitals to submit a request to begin the DPP and
    provided the relevant time period of adjustable claims depending on the type of hospital. The
    plain meaning of Step 1 provided hospitals initiate the “analysis” by “submit[ting] a request”;
    hospitals are the subject of Step 1, and the provision does not obligate TMA to any performance.
    DPP Contract Notice at A7. The FAQs expressly foreclose plaintiffs’ argument TMA should
    have provided its granular data to the hospitals. See DPP Contract FAQs at A11 (“Claims-level
    detail will not be provided due to the number of adjustments over this 7-year period.”). TMA is
    simply the passive recipient of the information per Step 1. FAQ 18 also explained three reasons
    why “the government will not provide individual claims data to each hospital:” (1) providing 10
    million claims of data is impractical; (2) including patient-level data is inadvisable due to privacy
    concerns; and (3) giving hospitals the summary worksheet is sufficient for hospitals to determine
    whether the historical claims counts and amounts are reasonable. DPP Contract FAQs at A14.
    Plaintiffs, therefore, knew before they entered the contract through parallel provisions (Step 1,
    FAQ 11, and FAQ 18) TMA was not providing its claim-level data. DPP Contract Notice at A7;
    DPP Contract FAQs at A11, A14. Although the provision noted, the “hospital submits a request
    for analysis of their claims data[,]” where “their” referred to hospitals, the provision directed
    hospitals to Step 2 for how to “submit[] a request for analysis of their claims data.” DPP
    Contract Notice at A7. As Step 1 directed the parties to Step 2, the Court next considers whether
    the “process defined in Step 2” obligated TMA to extract, analyze, and adjust the hospitals’
    radiology data. See 
    id.
    Plaintiffs state Step 2 “requested Plaintiffs to provide . . . basic [identifying] information
    in an Excel spreadsheet.” Pls.’ MSJ Resp. at 33. Step 2 provided “[a]s part of the [Step 1]
    request, hospital submits data with its name, address, zip code, Tax ID number, TRICARE sub
    ID number, the 6-digit Medicare OSCAR provider number, and NPI number.” DPP Contract
    Notice at A7. Hospitals “shall also include” a contact name and address for correspondence
    related to the Step 9 “formal response.” 
    Id.
     The requested information qualifies as “basic
    [identifying]” data, not claims-level data—billing codes that healthcare entities submit to
    insurance companies—or patient-level data—patients’ personal information, such as medical
    history and demographic characteristics. See 
    id.
     The government argues, “[a]t most, plaintiffs
    seek to infer a promise or warranty that the data that [TMA] was using was perfect from the fact
    that [TMA] did not invite hospitals to submit patient-level data as part of Step 2.” Def.’s MSJ at
    39; see also Tr. at 68:16–21 (“THE COURT: . . . [T]he DPP does not warranty proper data
    going into it and does not warranty that the data going into it, for the purposes of DPP analysis,
    is the same as the data that the hospitals had originally submitted to the intermediary. [THE
    GOVERNMENT]: That’s correct.”). The contextual evidence of Step 1, which only calls
    hospitals to action, renders similar conclusions. Step 2 is an extension of Step 1, as Step 1
    mentioned a “[h]ospital submits a request for analysis of their claims data (process defined in
    Step 2)[.]” DPP Contract Notice at A7. Like Step 1, the plain language of Step 2 only described
    information for plaintiffs—it does not obligate TMA in any way. See 
    id.
     Step 2 also limited the
    information plaintiffs would submit “[a]s part of the request.” 
    Id.
     Notably, under Step 2,
    hospitals were not invited or required to submit claims data—only basic identifying information.
    See 
    id.
     FAQs 1 and 2 from the TMA website together state the limited information needed from
    hospitals more expressly. FAQ 1 clarified hospitals are not required to submit sub-ID numbers.
    - 16 -
    DPP Contract FAQs at A10. FAQ 2 then built on FAQ 1 by answering the question, “Will I
    need to provide further information such as claims-level data or identify the relevant claims or
    patients?” 
    Id.
     TMA answered: “No, you will not. TRICARE will do this. You need to submit
    only the information in the Excel sheet [according to Step 2]. Do not submit patient-level data.”
    
    Id.
     The instructions of Step 2 limited who could submit data and further limited submitted data
    to a hospital’s “name, address, zip code, Tax ID number, TRICARE sub ID number, the 6-digit
    Medicare OSCAR provider number, and NPI number.” DPP Contract Notice at A7. Step 2 does
    not obligate TMA to any action—let alone to analyze data not submitted. Step 1, Step 2, FAQ 1,
    and FAQ 2 accordingly specify what the hospitals needed to submit with a request and what they
    did not, but the plain meaning of these provisions does not bind the government to analyze the
    hospitals’ radiology data. See Jowett, Inc., 
    234 F.3d at 1368
     (quoting McAbee Constr., Inc., 
    97 F.3d at 1435
    ); DPP Contract Notice at A7; DPP Contract FAQs at A10.
    2.     Whether Step 3 Requires TMA to Reference External Data Sources
    Step 3 of the Notice included the first mention of an action by TMA:
    Step 3: TMA will extract the claims for each hospital for claims for outpatient
    radiology services during the relevant period (either the August 2003-April 2009,
    August 2003-December 2009, or August 2003-November 2010 period). All
    hospital outpatient department claims for radiology paid as billed, with OHI, or
    with a professional modifier (-26) will be excluded. Radiology claims will include
    codes within the CPT range of 70000-79999 and which were codes with a non-zero
    rate in the Technical Component (TC) field of the CMAC rate file. Within this
    group of claims, if the TC CMAC amount is less than the global CMAC and the
    claim does not have a TC modifier, it will be excluded.
    DP Contract Notice at A7–A8 (emphasis added). As to Step 3, the government argues “plaintiffs
    posit that essentially any difference between TMA’s data and the hospital’s data constitutes a
    contract breach. However, this proposition cannot be derived from Step 3, and is not in the
    parties’ contract at all.” Def.’s MSJ at 42. The government asserts the following actions did not
    violate its obligations under Step 3 because “[t]he issue was not with the extraction itself, but
    with the contents of the underlying records, whose examination and correction was in no way
    required by the contract”: excluding (1) “some miscoded line items”; (2) “dump coded records”;
    and (3) “line items without TC modifiers.” 
    Id.
     at 42–43 (citing DPP Contract Notice A7–A8).
    Plaintiffs respond TMA’s extraction of data “from its own records . . . does not explain
    why some of the data did not exist in [TMA’s] systems or how this somehow justifies failing to
    perform its contractual obligations.” Pls.’ MSJ Resp. at 30. Plaintiffs also contend “[t]he
    Government cannot reasonably argue that it was not required to conduct due diligence on its own
    data, while at the same time refusing Plaintiffs access to the data.” 
    Id.
     Plaintiffs argue TMA
    should have corrected errors with the data “(e.g., the records conversion issue for 2003-2004 in
    the South regarding to which the Government stipulated, and a fiscal intermediary advising of
    erratic TC modifier practices in May 2011).” 
    Id.
     at 30–31 (citing Def.’s MSJ at 43–44).
    Plaintiffs add “if you look at Step 3, the government’s basic obligation was to extract the claims
    - 17 -
    from each hospital for claims for outpatient radiology services during the relevant period.
    Claims from each hospital has to mean the claims that the hospital submitted.” Tr. at 70:8–14.
    Building on the information hospitals supplied in Step 2, Step 3 provided “TMA will
    extract the claims for each hospital for claims for outpatient radiology services during the
    relevant period.” DPP Contract Notice at A7. From Merriam-Webster Dictionary’s definition of
    “extract,” only two definitions are relevant: (1) “to draw forth (as by research)” e.g., “extract
    data”; and (2) “to select (excerpts) and copy out or cite.” Extract, Merriam Webster Dictionary,
    (11th ed. 2022); see Af–Cap, Inc. v. Chevron Overseas (Congo) Ltd., 
    475 F.3d 1080
    , 1088 (9th
    Cir. 2007) (“When determining the plain meaning of language, we may consult dictionary
    definitions.”). Using either definition, the word “extract” contemplates removing or copying
    something from somewhere. Although plaintiffs argued under Step 3, “somewhere” must “mean
    the claims that the hospital submitted,” Tr. at 70:13–14, plaintiffs admitted TMA extracted line
    items from TMA’s own database as a practical matter. Tr. at 111:23–112:4 (“[COURT]: . . . .
    [Step 3] begins, ‘TMA will extract the claims.’ Where is TMA to extract the claims from?
    [PLAINTIFFS]: Well, from the database that the government maintains. . . . [COURT]: From
    TMA’s database? [PLAINTIFFS]: Yeah, from TMA’s database”), 113:23–24
    (“[PLAINTIFFS]: . . . . [A]s a practical matter, TMA was looking to its database.”). Further, in
    arguing FAQ 4 does not support the government’s position, plaintiffs admitted TMA was “just
    going to look at the records that are in the database and use those as a basis for the adjustment.”
    Tr. at 20:11–13. Plaintiffs were aware at numerous stages of the process—from extracting line
    items, Tr. at 111:23–112:4, to determining adjustment bases, Tr. 113:23–24—TMA was utilizing
    its database. “The process of interpretation . . . turns in good part on what the court regards as
    normal habits in the use of language, habits that would be expected of reasonable persons in the
    circumstances of the parties.” E. Allan Farnsworth, Contracts 456 (4th ed. 2004). The parties
    were aware TMA extracted line items from TMA’s own database, contextualizing the
    interpretation of from where “TMA will extract the claims for each hospital.” DPP Contract
    Notice at A7; see, e.g., George Backer Mgt. Corp. v. Acme Quilting Co., 
    385 N.E.2d 1062
    , 1065
    (N.Y. 1978) (If particularized meaning is intended, “surely no problem of draftsmanship would
    have stood in the way of its being spelled out.”).
    TMA extracted data from its database, so at oral argument the Court questioned “where
    also in Step 3 then is TMA obligated to collect data from outside its database to make it match
    something that the hospitals had submitted to the intermediaries?” to which plaintiffs responded,
    “I think that’s built into what we believe is the only reasonable interpretation of what it means to
    extract claims for each hospital.” Tr. at 113:8–15. The notion TMA’s duties are assumed,
    however, only points back to the Court’s interpretation of “extract.” When the Court asked
    whether Step 3 obligated TMA to seek data outside its database, plaintiffs initially said, “No,”
    but plaintiffs later said, “‘[Y]es,’ . . . because Step 3 obligate[d] the government to adjust the
    claims that the hospitals submitted.” Tr. at 112:11–19. Plaintiffs admitted for TMA to collect
    data it lacked, TMA would “have [had] to go to the fiscal intermediaries[,]” Tr. at 177:15–16;
    however, the contract expressly stated TMA would not go to the intermediaries. See DPP
    Contract Letter at A1 (“DoD has decided to calculate the net adjustments itself, rather than
    through the [intermediaries].”); supra Section IV.A. Further, FAQ 2 clarified hospitals did not
    need to provide claims-level data, rather “TRICARE will do this.” DPP Contract FAQs at A10
    (answering “[y]ou need to submit only the information in the Excel sheet” to the question “Will I
    - 18 -
    need to provide further information?”). Plaintiffs attempted to contextualize the notion TMA
    would adjust the claims with an action TMA explicitly rejected: using intermediaries. See DPP
    Contract Letter at A1; supra Section IV.A. Plaintiffs’ arguments Step 3 obligated TMA to
    extract the hospitals’ radiology data accordingly impermissibly reach beyond the plain meaning
    of the text. See Jowett, Inc., 
    234 F.3d at 1368
     (quoting McAbee Constr., Inc., 
    97 F.3d at 1435
    );
    DPP Contract Notice at A7; DPP Contract FAQs at A10.
    After TMA “extract[ed] the claims for each hospital” meeting certain criteria, Step 3
    further provided certain claims “will be excluded” from what “TMA will extract.” DPP Contract
    Notice at A7–A8. For example:
    All hospital outpatient department claims for radiology paid as billed, with [other
    hospital insurance (‘OHI’)], or with a professional modifier (-26) [the professional
    component used when a physician interprets but does not perform the test] will be
    excluded. . . . Within this group of [radiology] claims, if the Technical Component
    (TC) CMAC amount is less than the global CMAC and the claim does not have a
    TC modifier, it will be excluded.
    
    Id.
     at A7. In addition to defining “extract” as “to select (excerpts) and copy out or cite,”
    Merriam Webster Dictionary also defines “exclude” as “to expel . . . especially from a place or
    position previously occupied.” See Extract, Exclude, Merriam Webster Dictionary. Reading the
    definitions together, TMA must extract data before it can then exclude portions of its extractions
    because TMA must “select” excerpts of data from hospitals request before it is able to “expel”
    certain data points. As the ordinary meaning of the Step 3 exclusions merely narrow the
    universe of considered data from what “TMA will extract,” the claims data “TMA will extract”
    is the largest universe of data TMA was obligated to consider. Excluding existing database data
    is the plain meaning of excluding data TMA extracts in Step 3. See Jowett, Inc., 
    234 F.3d at 1368
     (quoting McAbee Constr., Inc., 
    97 F.3d at 1435
    ); DPP Contract Notice at A7–A8.
    One of the excluded claims relates to “dump codes.” The government explained a dump
    code is a non-CMAC-associated generic code from a fiscal intermediary resulting from the
    inability of the coder to input the proper CPT code. See Tr. at 46:16–21. 8 Regarding “dump
    codes,” Step 3 provided “[r]adiology claims will include codes within the CPT range of
    70000-79999 and which were codes with a non-zero rate in the TC field of the CMAC rate file.”
    DPP Contract Notice at A7 (emphasis added). Dump codes have a zero rate in the TC field, so
    dump codes were not included in the data TMA extracted according to Step 3. 
    Id.
     Plaintiffs
    argue TMA erred by excluding dump codes. See Pls.’ MSJ Resp. at 21. TMA’s obligations
    stem from the contract, and the contract expressly provided TMA would exclude dump codes.
    See DPP Contract Notice at A7. Plaintiffs admitted under Step 3 “the DPP provided that claims
    with certain CPT codes would be adjusted” and “[a] dump code falls outside that.” Tr. at 63:6–9.
    Therefore, TMA did not err in excluding dump codes per Step 3. Under a plain meaning rule,
    there is a two-stage process. In the first stage, the court makes a preliminary determination of
    whether the language in dispute lacks the required degree of clarity before going on to the second
    8
    The government noted during oral argument, “there were 82 line items [out of 4,006 total] for Ingham that were
    not adjusted because of the dump code issue.” Tr. at 46:9–11; see Tr. at 44:18–19 (“[THE GOVERNMENT:] . . .
    [W]e adjusted 4,006 line items for Ingham.”).
    - 19 -
    stage, that of interpretation. E. Allan Farnsworth, Contracts 464 (4th ed. 2004) (quoting Arthur
    L. Corbin, The Parol Evidence Rule, 53 YALE L.J. 603, 622 (1944)). The direction of Step 3 that
    dump codes fall outside of TMA’s adjustment purview does not “lack the required degree of
    clarity,” so the Court does not need to proceed with interpretation. See 
    id.
    i.       Whether the Word “Each” Qualifies “Claim” and “Hospital”
    in Steps 1 through 6 Individually or Collectively
    Plaintiffs contend the government was obligated to analyze the hospitals’ radiology data.
    Pls.’ MSJ Resp. at 27. Plaintiffs emphasize the word “each” in Steps 3 through 6 supports their
    hospital-data interpretation. 9 
    Id.
     After admitting at oral argument TMA extracted claims from
    9
    The Notice provides in full Steps 3–6:
    Step 3: TMA will extract the claims for each hospital for claims for outpatient radiology services
    during the relevant period (either the August 2003-April 2009, August 2003-December 2009, or
    August 2003-November 2010 period). All hospital outpatient department claims for radiology paid
    as billed, with OHI, or with a professional modifier (-26) will be excluded. Radiology claims will
    include codes within the CPT range of 70000-79999 and which were codes with a non-zero rate in
    the Technical Component (TC) field of the CMAC rate file. Within this group of claims, if the TC
    CMAC amount is less than the global CMAC and the claim does not have a TC modifier, it will be
    excluded.
    Step 4: TMA will calculate what would have been paid under the approach that Medicare used to
    pay hospital outpatient radiology claims prior to CMS’s implementation of the Medicare OPPS in
    2000. Medicare used a weighted blending of two factors with 42 percent for the first factor and 58
    percent for the second factor. We refer to this as the “Medicare” method. Specifically, TMA would
    use the following formula to calculate the “Medicare” allowed amount for each hospital radiology
    claim:
    .42 (BC*CCR) + .58 (.62 global CMAC)
    where: BC = billed charge for that line item
    CCR= the hospital-specific outpatient cost-to-charge ratio
    Global CMAC = the global CMAC for that CPT code (line item)
    TMA will perform separate calculations of the “Medicare” amount for the following periods. Each
    period corresponds to a change in the TRICARE CMAC amounts:
    August 11, 2003-February 29, 2004
    March 1, 2004-March 31, 2005
    April 1, 2005-February 28, 2006
    March 1, 2006-January 31, 2007
    February 1, 2007-February 29, 2008
    March 1, 2008-February 28, 2009
    March 1, 2009-March 31, 2010
    April 1, 2010-June 30, 2010
    July 1, 2010-July 31, 2010
    August 1, 2010-December 31, 2010
    The outpatient cost-to-charge ratio (CCR) used for each period shall be the hospital-specific
    outpatient CCR in effect on the first day of each period as provided on the Outpatient Provider
    Specific File (OPSF) available from CMS’s OPPS Pricer file.
    Step 5: To reflect the value of discounts at network hospitals, TMA will adjust the “Medicare”
    amount calculated in Step 4 on each claim using the ratio of the actual allowed amount on the claim
    to the TRICARE Standard allowed amount (the technical component of the CMAC). For example,
    if the TRICARE Standard technical portion of the CMAC for a radiology claim was equal to $100
    - 20 -
    its database, plaintiffs agreed the phrase “each hospital” in Step 3 is the same as “each hospital”
    in Step 2:
    A separate Excel spreadsheet must be completed for each hospital in the
    TMA-specified format.
    DPP Contract Notice at A7 (emphasis added); Tr. at 112:5–7. The word “each” immediately
    precedes—and modifies—the word “hospital,” so the plain meaning of the word “each”
    instructed TMA to extract data based on the individual hospitals that submitted their identifying
    information per Steps 1 and 2. See DPP Contract Notice at A7 (“TMA will extract the claims for
    each hospital . . . .”). The plain meaning of “each hospital” accordingly does not change the
    scope of TMA’s duty to “extract [from its database] the claims for each hospital” which
    submitted identifying information according to Step 2. 
    Id.
    Regarding Steps 4 through 6, the word “each” modifies “hospital radiology claim” in
    Step 4, and “claim” in Steps 5 and 6. 
    Id.
     at A8–A9. As Steps 4, 5, and 6 sequentially follow
    Steps 1, 2, and 3, the “each hospital radiology claim” and “each claim” language in Steps 4, 5,
    and 6 referred only to each individual claim extracted and not excluded under Step 3. Steps 4
    through 6 described the calculations TMA was to perform, so the word “each” in this context
    denoted TMA was to analyze claims on an individual basis as opposed to collectively. The DPP
    specifically included “each” as the modifier as opposed to an indefinite article like “a.” “Each”
    is a word of limitation as opposed to the generalizing force of “a.” See Am. Bus Ass’n v. Slater,
    
    231 F.3d 1
    , 4–5 (D.C. Cir. 2000). The only interpretation that “makes sense,” therefore, is if the
    plain meaning of the word “each” does not broaden TMA’s duty to extract data from its database
    and then use this data for TMA’s analysis of individual claims for each hospital. Put differently,
    TMA is only responsible for analyzing the data of each claim of each hospital. See Jowett, Inc.,
    
    234 F.3d at 1368
     (quoting McAbee Constr., Inc., 
    97 F.3d at
    1435 and giving “the words of the
    agreement their ordinary meaning unless the parties mutually intended and agreed to an
    alternative meaning”); DPP Contract Notice at A7–A9.
    and the actual allowed amount on the claim was equal to $95, the ratio is 0.95. This difference could
    occur because of a hospital discount. In this example, the adjusted “Medicare” amount would be
    equal to 0.95 multiplied by the “Medicare” amount prior to adjustment. If both the actual and the
    TRICARE Standard amounts were equal (for example, because there were no discounts), the ratio
    would be equal to 1.0 (the ratio could not exceed a value of 1.0). For purposes of this discretionary
    adjustment, this process will level discounts over the period even if the hospital may not have had a
    network agreement in effect at the time of any individual service claim.
    Step 6: TMA will then compare the adjusted “Medicare” amount for each claim with the actual
    allowed amounts on that claim. TMA will calculate the difference between the two amounts. The
    positive and negative differences will be summed over the entire 2003-2009 period (or the
    2003-2010 period for hospitals not subject to OPPS). If the sum of the differences is positive
    (because the adjusted “Medicare” allowed amounts exceed the actual allowed amounts) then this
    information will be used in determining the level of the additional payment to the hospital. If the
    actual allowed amounts are equal to or exceed the “adjusted Medicare” amounts, then no additional
    payment shall be made.
    DPP Contract Notice at A7–A9 (emphasis added).
    - 21 -
    3.     Whether FAQ 14’s Clarification of “The Notice to Hospitals of
    Potential Adjustment to Past Payment for Outpatient Radiology
    Services” Applies to the Kennell Study or the DPP Calculations
    The government argues FAQ 14, which clarifies the DPP “analysis was performed on a
    service line basis, rather than on a hospital specific basis,” does not impose a duty on TMA to
    extract and analyze the hospitals’ radiology data. Def.’s MSJ Reply at 14–15 (quoting FAQ 14).
    The government asserts FAQ 14 is irrelevant to TMA’s duty as “it is describing the methodology
    that was used in the Kennell studies that were conducted prior to the [DPP] to determine whether
    TRICARE’s payment methodology was comparable to Medicare’s across different types of
    outpatient services generally.” Id. at 14. Plaintiffs argue FAQ 14 does require the government
    to extract all hospital radiology claims, emphasizing “[t]he [data] analysis was performed on a
    service line basis.” Id.
    The FAQ, published in 2013, mentions the data analysis of hospital outpatient services
    generally, not just radiology claims, so the FAQ—by its plain meaning—refers to the Kennell
    study. See DPP Contract FAQs at A12. The 2013 FAQ also refers to the data analysis in past
    tense which further signals it refers to the Kennell study, which accounted for 2003–2009 data:
    FAQ 14 specifies “[t]he analysis was performed on a service line basis, rather than on a hospital
    specific basis,” confirming the provision must refer to the Kennell study and not the
    yet-to-be-performed DPP calculations according to the contract. See id. (emphasis added). The
    Kennell study does not apply to individual hospital claims, and the DPP obligated TMA to
    perform—but not to the extent of extracting and analyzing radiology data not in the database.
    FAQ 14’s clarification of “The Notice to Hospitals of Potential Adjustment to Past Payment for
    Outpatient Radiology Services” applies to the Kennell study, which occurred before the
    publication of the Notice and thus does not provide context to TMA’s contractual duty regarding
    plaintiffs’ data. See J & B Steel Contractors, Inc. v. C. Iber & Sons, Inc., 
    642 N.E.2d 1215
    , 1218
    (Ill. 1994) (interpreting existence of ambiguity by looking solely at what appears within the
    written contract itself).
    4.     Whether Spearin Applies
    Citing D.F.K. Enterprises, Inc., a 1999 Court of Federal Claims case in which a contractor
    sued alleging the Army Corps of Engineers breached a contract to paint a water storage tank by
    misrepresenting the amount of adverse weather experienced at the site, plaintiffs argue TMA
    “had a contractual duty to verify its data because it implicitly warranted that its representations
    about the data were accurate.” Pls.’ MSJ Resp. at 26 (citing D.F.K. Enters., Inc., 
    45 Fed. Cl. at 285
    ); see infra Section IV.B (holding TMA’s data and its performance according to the DPP
    methodology were both within TMA’s control). In a related 1918 case, the Supreme Court
    considered a government contract to construct a dry dock at the Brooklyn Navy Yard. United
    States v. Spearin, 
    248 U.S. 132
    , 133 (1918). The Court found “the insertion of the articles
    prescribing the character, dimensions and location of the sewer imported a warranty that if the
    specifications were complied with, the sewer would be adequate. This implied warranty is not
    overcome by the general clauses requiring the contractor to examine the site . . . .” 
    Id. at 137
    .
    Further, in Spearin, the government specified steps for the contractor to follow, which implied
    these steps would lead to a certain result. 
    Id. at 133
    ; see also Lakeshore Eng’g Servs., Inc. v.
    - 22 -
    United States, 
    748 F.3d 1341
    , 1349 (Fed. Cir. 2014) (“[T]he Supreme Court in Spearin
    recognized that an implied warranty arises in a particular circumstance: when a contractual
    requirement binds the builder to follow design specifications stated in the contract.”). The basis
    for the “Spearin Doctrine” is when contractors are bound to build according to the plans and
    specifications provided by the owner, the contractor should not be responsible for damages that,
    through no fault of his own, occur when the plans and specifications are defective. In response
    to plaintiffs’ citation of D.F.K. Enterprises, Inc., the government characterizes D.F.K.
    Enterprises, Inc. as “a Spearin warranty case” and clarifies “Spearin does not apply in a ‘case
    [that] does not involve a design specification that bound [the contractor] but turned out to
    produce a defective or unsafe construction.’” Def.’s MSJ Reply at 13 (first citing D.F.K. Enters.,
    Inc., 
    45 Fed. Cl. at 285
    , and then citing Lakeshore, 748 F.3d at 1349). The Court agrees Spearin
    implied warranties apply in design specification cases, and plaintiffs fail to cite any non-design
    specification cases for their argument. In this case, moreover, the contract specified how TMA
    should perform under the DPP Contract, not how the contractor—plaintiffs in this case—should
    perform. For example, Step 3 of the contract states, “TMA will extract the claims for each
    hospital for claims for outpatient radiology services during the relevant period.” See Def.’s MSJ
    Reply at 10–11 (citing DPP Contract Notice at A7–A8). TMA created a duty for itself, if
    anything, not an implied warranty.
    The government argues further on the issue of implied warranties, “if the government was
    promising to do something as elaborate as going and checking records . . . there would be an
    explicit express obligation in the contract to do that.” Tr. at 125:6–9. The government explained
    “that would be a very complicated prospect and it’s in no way contemplated in the language of
    this instrument.” Tr. at 125:9–11. Plaintiffs responded “[i]f the government was going to do
    anything less than its promise, which was to extract all the hospitals’ claims, it should have
    provided a disclaimer of that fact and it didn’t.” Tr. at 125:21–24. Plaintiffs’ argument on this
    point requires the Court first accept their argument TMA had an express obligation to analyze
    the hospitals’ data, which the Court rejects. See infra Section IV.A.5. Further, the Court agrees
    with the government if TMA had promised to analyze the hospitals’ data, which would have
    required requesting data from intermediaries or plaintiffs themselves and would have been a
    complicated process, the DPP Contract would have provided so expressly. See DPP Contract
    Notice at A7 (requesting “claims” data—not “all” or “new” data). TMA thus lacked a
    contractual duty to extract, analyze, and adjust the hospitals’ radiology data. See Moore v.
    Shawmut Woodworking & Supply, Inc., 
    788 F.Supp.2d 821
    , 825, 829 (S.D. Ind. 2011) (finding a
    breach of contract can be predicated upon a contractual duty only when the contract affirmatively
    evinces an intent to charge one party with a duty).
    5.     Conclusion
    The Court finds TMA did not have a contractual duty to “locate, identify, and adjust each
    and every line item for radiology ever paid,” or put another way, “the Parties’ contracts
    contained no requirement that the Government extract and adjust all of Plaintiffs’ radiology
    data.” Def.’s MSJ at 34; Def.’s MSJ Reply at 6 (cleaned up); see Jowett, Inc., 
    234 F.3d at 1368
    (quoting McAbee Constr., Inc., 
    97 F.3d at 1435
    ); Trauma Serv. Grp. v. United States, 
    104 F.3d 1321
    , 1325 (Fed. Cir. 1997); San Carlos Irrigation & Drainage Dist., 
    877 F.2d at 959
    ; DPP
    Contract Letter at A1–A2; DPP Contract Notice at A3–A9; DPP Contract FAQs at A10–A15;
    - 23 -
    DPP Contract Release at A17. As the government has shown TMA lacked this specific
    contractual duty, the government has proven it is “entitled to a judgment as a matter of law”; the
    Court accordingly grants the government’s motion for summary judgment as to plaintiffs’ breach
    of contract claim regarding TMA’s lack of contractual duty to extract, analyze, and adjust the
    hospitals’ radiology data. Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    , 247 (1986).
    B.       Whether TMA Had a Contractual Duty to Extract, Analyze, and Adjust
    Radiology Data from its Database
    Regarding TMA’s duty to extract, analyze, and adjust radiology data, plaintiffs argue
    even if the Court found TMA was not obligated “to extract and analyze all of plaintiffs’
    radiology data,” “there would still be a breach.” Tr. at 131:8–16. Plaintiffs note “[t]he
    government has . . . stipulated to the fact that there were line items in their database that met the
    criteria for extraction that were not adjusted. That’s still a breach.” Tr. at 131:18–21; see also
    Tr. at 85:4–7 (“[PLAINTIFFS:] . . . [T]he government has stipulated that there are certain claims
    that did meet the criteria for extraction that were not adjusted, even though they were in their
    database.”).
    As discussed supra Section IV.A.2, Step 3 provided “TMA will extract the claims” and
    then exclude certain claims using specified criteria. See DPP Contract Notice at A7. The
    government admits “[t]he contract provided that TMA first would extract data with certain
    contractually-specified identifiers from its own records, and use the methodology specified in the
    parties’ contract to generate a proposed adjustment amount.” Def.’s MSJ at 31 (citing DPP
    Contract Notice at A7–A8). The government also concedes it “failed to include [several] line
    items . . . that met the criteria for extraction set forth in Step 3.” Def.’s MSJ Reply at 5 (citing
    DPP Contract Notice at A9; DPP Contract FAQs at A15). The government also conceded at oral
    argument TMA’s exclusion of several line items “although they met the criteria for extraction”
    “would not be compliant with Step 3.” See Tr. at 80:1–9. The government then stated: “[D]id
    our algorithm fail in some way on Step 3 for these 13 line items? Sure.” Tr. at 81:19–21. The
    government finally said “[it] agreed to extract the records in our possession.” Tr. at 97:20–21.
    The government admitting it had a duty according to Step 3 is consistent with the contract
    language; to assert otherwise would lead to the absurd result where TMA could have performed
    calculations based on plainly incorrect data that did not match the data in TMA’s system. At oral
    argument, the government admitted if TMA provided bogus data, it technically would have
    breached the contract. Tr. at 97:3–10 (“THE COURT: But if [TMA] provided bogus data, that
    wouldn’t be following the process as detailed in the DPP, that would be a breach. [THE
    GOVERNMENT]: . . . yes.”); see also Tr. at 224:2–7 (“[PLAINTIFFS:] . . . [I]f the government
    were not obligated to use accurate data in doing its adjustments, on some level it would be an
    illusory promise, right, because the government could use whatever data and come up with
    whatever result and it wouldn’t be a breach.”). 10 The Court accordingly finds TMA did have a
    10
    The algorithm’s failure does not amount to an illusory promise, a promise that is unenforceable due to
    indefiniteness or lack of mutuality. 1 Corbin on Contracts § 1.17 (2022). A promise conditioned upon an event
    within the promisor’s control is not illusory if the promisor also “impliedly promises to make reasonable effort to
    bring the event about or to use good faith and honest judgment in determining whether or not it has in fact
    occurred.” Id. In this case, TMA had a duty to extract data in its records, but the failure to utilize “perfect data” is
    not illusory.
    - 24 -
    duty under the plain language of Step 3 to extract, analyze, and adjust radiology data from its
    database. See Jowett, Inc., 
    234 F.3d at 1368
     (quoting McAbee Constr., Inc., 
    97 F.3d at 1435
    );
    Trauma Serv. Grp., 
    104 F.3d at 1325
    ; San Carlos Irrigation & Drainage Dist., 
    877 F.2d at 959
    ;
    DPP Contract Letter at A1–A2; DPP Contract Notice at A3–A9; DPP Contract FAQs at
    A10–A15; DPP Contract Release at A17.
    C.      Whether TMA Had a Contractual Duty to Consider Zip Codes Not Provided
    by Hospitals
    Regarding plaintiff Integris Baptist, who the government stipulates had five unadjusted
    line items during the DPP because of an alternate zip code, the government states “there is no
    dispute that Integris Baptist did not advise TMA that it provided radiology services in zip code
    73116” under Step 2. Def.’s MSJ Reply at 4 (citing DPP Contract Notice at A7). Step 2
    provided “[a]s part of the request, hospital submits data with its . . . zip code[.]” DPP Contract
    Notice at A7. FAQ 8 answered “[p]lease provide the address and zip code of the physical
    location of the hospital” to the question “[s]hould I provide the address of the physical location
    of the hospital or a billing address?” DPP Contract FAQs at A11.
    The government argues “it does not appear that plaintiffs could meet their burden of
    proving [TMA’s failure to adjust five line items associated with an alternative zip code for
    Integris Baptist Medical Center] constituted an error of extraction. Step 2 of the Notice required
    hospitals to provide zip code information to TMA to facilitate the extraction process.” Def.’s
    MSJ at 43 n.9 (citations omitted). Plaintiffs, however, contend “the DPP doesn’t make any
    provision that if a hospital has multiple locations, that all of the zip codes must be separately
    identified in the DPP.” Tr. at 9:18–20.
    Plaintiffs admit there is no “evidence that [Integris Baptist] did” provide TMA with its
    73116 zip code so this issue is not factually disputed. Tr. at 8:14–21. Plaintiffs, however, argue
    Integris Baptist was not obligated to do so because the contract only provided hospitals must
    submit their “zip code” not “zip codes.” Tr. at 8:19–9:2. The government counters it is “a
    reasonable reading of the provision to assume that if a hospital has more than one physical
    location, it’s going to advise the government to that effect.” Tr. at 10:6–9. The government
    argues “under FAQ 8, the physical location zip code had to be provided and [Integris Baptist]
    didn’t.” Tr. at 10:17–18.
    Interpreting the zip code requirement of Step 2 requires examining its context. Step 2
    provides: “As part of the request, hospital submits data with its name, address, zip code, Tax ID
    number, TRICARE sub ID number, the 6-digit Medicare OSCAR provider number, and NPI
    number. [(“Sentence 1”).] If multiple Tax ID or Medicare provider numbers were used during
    this period, hospitals will submit these data. [(“Sentence 2”).]” DPP Contract Notice at A7
    (emphasis added). The plain meaning of Sentence 1 in context requires submission of only one
    zip code. Reading the two sentences together raises the negative implication canon, a tool of
    contract interpretation this court has employed many times. See, e.g., United Pac. Ins. v. United
    States, 
    497 F.2d 1402
    , 1405 (Ct. Cl. 1974) (applying the rule of expressio unius est exclusio
    alterius to find when language specifically provided where flashings were to be installed, there
    was manifested an intention the flashings are not required to be installed elsewhere); Pub. Util.
    - 25 -
    Dist. No. 1 v. United States, 
    20 Cl. Ct. 696
    , 700 (1990) (interpreting a contract using the doctrine
    of expressio unius est exclusion alterius); Nicholson v. United States, 
    29 Fed. Cl. 180
    , 196
    (1993) (explaining where particular things are specified in a contract, others of the same general
    character are impliedly excluded); Sam Rayburn Mun. Power Agency v. United States, No.
    20-1535, 
    2021 WL 4888872
    , at *12 (Fed. Cl. Oct. 19, 2021) (Holte, J.) (finding damages were
    generally available under a contract, as an issue of subject matter jurisdiction, when the contract
    enumerated three exceptions to damages); see also Scalia & Garner, supra, at 107–11
    (describing the negative implication canon as “[t]he expression of one thing implies the
    exclusion of others”). By listing two specific identifying criteria from Sentence 1 for which
    hospitals should submit multiple values, “Tax ID” and “Medicare provider numbers[,]” DPP
    Contract Notice at A7, Sentence 2 of the Notice implied hospitals did not have to submit
    multiple values for the non-listed identifying criteria, including zip codes. See, e.g., United
    States v. Giordano, 
    416 U.S. 505
    , 514 (1974) (finding an individual government employee was
    not authorized to perform an action under a statute authorizing only two types of officials). The
    plain meaning of Step 2 did not, therefore, require hospitals to submit multiple zip codes, and the
    Court thus finds TMA did have a duty to consider zip codes for hospital locations not provided
    by the hospitals. 11 See Jowett, Inc., 
    234 F.3d at 1368
     (quoting McAbee Constr., Inc., 
    97 F.3d at 1435
    ); Pub. Util. Dist. No. 1, 
    20 Cl. Ct. at 700
    ; United Pac. Ins. v., 
    497 F.2d at 1405
    ; DPP
    Contract Notice at A7.
    D.       Whether TMA Breached its Contractual Duty to Extract, Analyze, and
    Adjust Radiology Data from its Database and Damages
    Regarding TMA’s breach, plaintiffs argue, “the Government itself concedes that it did
    not follow the methodology in the DPP[.]” Pls.’ MSJ Resp. at 27. Plaintiffs also argue the errors
    with the data were not trivial, “[r]ather, the Excluded Hospitals Memo and the Settlement
    Agreement prove that the Government failed to follow the DPP methodology on a substantially
    large scale, rather than just in a few insignificant instances.” Id. at 29. Plaintiffs further argue
    the government’s failure to extract line items “for unknown reasons” supports plaintiffs’
    argument “the Government does not understand its own data and failed to satisfy its contractual
    obligations.” Id. at 29–30.
    To prove breach of contract, plaintiffs must show the government “fail[ed] to perform a
    contractual duty when it [was] due.” Trauma Serv. Grp., 
    104 F.3d at 1325
    . The Court finds
    supra Section IV.B the DPP Contract obligated TMA to extract, analyze, and adjust plaintiffs’
    radiology data TMA had in its system, and this is the duty plaintiffs allege TMA failed to
    perform. See Pls.’ MSJ Resp. at 27. “The Government stipulates that there are nine line items
    for Integris Baptist Medical Center, and four line items for Integris Bass Baptist Medical Center
    that were not extracted from TMA’s databases in 2011, although they met the criteria for
    extraction.” Def.’s MSJ at 30 (emphasis added) (citations omitted). The government concedes
    11
    The Court holds under the plain meaning of Step 2 of the Notice but notes the parties did not discuss the language
    of Sentence 2, “multiple Tax ID or Medicare provider numbers[,]” or the negative implication canon at oral
    argument or in their briefing. See generally Tr.; Def.’s MSJ; Pls.’ MSJ Resp.; Def.’s MSJ Reply. Additionally, the
    record does not reflect whether the multiple zip codes of Integris Baptist also had multiple associated Tax ID or
    Medicare provider numbers or, if so, whether Integris Baptist submitted those numbers as required by Step 2. The
    Court denies the government’s motion for summary judgment as to the line items covered by the alternative zip
    code, see infra Section IV.F, but notes additional discovery may be required to determine liability.
    - 26 -
    its “algorithm fail[ed] in some way on Step 3 for these 13 line items[.]” Tr. at 81:19–21. The
    government also states, “We believe that the contract express provisions provided what would
    and would not be included in the adjustment set.” Tr. at 48:18–20. The government accordingly
    admits TMA failed to follow the extraction criteria, at least in part.
    Although the government admits it technically breached the DPP Contract regarding
    extraction, it argues “where government records are in the tens of millions, I think it would be
    unreasonable to expect perfection . . . on something of this scale.” Tr. at 59:6–10. As support,
    the government cites to FAQ 18 which contextualizes Step 8, directing questions about the
    content—not the calculation—of claims data to TMA within thirty days of request response
    receipt. Tr. at 82:13–18 (“[THE GOVERNMENT]: . . . [T]he purpose of the claims counts, it’s
    from FAQ 18 and I think that the final sentence of that FAQ . . . the intention is that hospitals can
    review these amounts to determine whether the historical claims counts and amounts are
    reasonable.”). FAQ 18 stated, “Hospitals can review [the summary worksheet] amounts to
    determine whether the historical claims counts and amounts are reasonable.” DPP Contract
    FAQs at A14. The government emphasizes the language “are reasonable” to argue the
    government did not “promis[e] exactitude.” Tr. at 82:18–21. The government adds FAQ 18
    “doesn’t say exact; it says reasonable.” Tr. at 82:18. Plaintiffs respond, “[j]ust because Question
    18 says ‘reasonable’ . . . the very best hospitals could do is some sort of reasonableness check.”
    Tr. at 86: 8–11. Plaintiffs also argue “the hospitals [did not] ha[ve a] way of easily figuring this
    out or doing some calculation as part of the DPP.” Tr. at 62:1–5.
    The government argues “historical claims counts and allowed amounts would be used to
    assess reasonableness, not exactitude[,]” and thus, “even though it’s not, strictly speaking, a
    complete compliance with Step 3, given the contract obligations as a whole, we don’t believe
    that would be a breach either, particularly given Step 8.” Tr. at 80:13–19. The government also
    argues infinitesimal variance is not “within the contemplation of the contract” under Southwest
    Welding. Tr. at 83:23–25. In Southwest Welding, a contractor could not recover extra
    compensation for additional work entitled by a 0.16 percent deviation from a base number of 90
    degrees because it was within the variation contemplated by use of the figure “90 degrees plus or
    minus.” Sw. Welding & Mfg. Co. v. United States, 
    373 F.2d 982
    , 985 (Ct. Cl. 1967). The
    government asserts it did not “know that the technical noncompliance . . . with respect to this
    negligible number of line items . . . is as grievous as it would appear on the face.” Tr. at
    84:9–17. Plaintiffs note in the Southwest Welding case, “there were plus and minus symbols”
    following the parameter at issue indicating there was an acceptable margin of error. Tr. at
    85:17–20. Plaintiffs argue unlike Southwest Welding, “[t]here weren’t any plus or minus
    symbols in the DPP or anything like plus or minus symbols[.]” Tr. at 85:21–22.
    “When performance of a duty under a contract is due any non-performance is a breach.”
    Restatement (Second) of Contracts § 235(2) (Am. L. Inst. 1981). The Restatement further
    explains: “[A] duty is discharged when it is fully performed. Nothing less than full
    performance, however, has this effect and any defect in performance, even an insubstantial one,
    prevents discharge on this ground.” § 235, cmt. a. “[A] ‘reasonable’ breach of contract is
    nonetheless a breach.” Stockton E. Water Dist. v. United States, 
    583 F.3d 1344
    , 1365 (Fed. Cir.
    2009). The government admits its “performance of a duty under [the DPP] contract”—extracting
    plaintiffs’ radiology data which was in TMA’s database—was due. See § 235(2). Contrary to
    - 27 -
    the Restatement, the government argues something less than full performance discharged its
    obligation under the DPP. See § 235, cmt. A; Tr. at 80:13–19. In unambiguous terms, however,
    the DPP Contract provided TMA’s duty was to “extract the claims for each hospital” and then
    exclude certain claims. DPP Contract Notice at A7–A8. The government admitted it failed to do
    just that. See e.g., Tr. at 81:19–21. Following the Restatement’s guidance, the Court finds
    “[n]othing less than full performance” can satisfy TMA’s obligation to perform under the DPP
    Contract, and “a ‘reasonable’ breach of contract is nonetheless a breach.” § 235, cmt. a; Stockton
    E. Water Dist., 
    583 F.3d at 1365
    . As a matter of law regarding contract interpretation and the
    government’s admission, the government’s failure to extract all thirteen line items for Integris
    Baptist and Integris Bass Baptist constitutes a breach of TMA’s duty according to Step 3. See
    Stockton E. Water Dist., 
    583 F.3d at 1365
    ; DPP Contract Notice at A7; supra Section IV.B.
    1.      Damages
    To prevail on their breach of contract claim, plaintiffs must also prove damages. See San
    Carlos Irrigation & Drainage Dist., 
    877 F.2d at
    960 (citing Com. Int’l Co. v. United States, 
    338 F.2d 81
    , 86 (1964)). “Damages for a breach of contract are recoverable where: (1) the damages
    were reasonably foreseeable by the breaching party at the time of contracting; (2) the breach is a
    substantial causal factor in the damages; and (3) the damages are shown with reasonable
    certainty.” Indiana Michigan Power Co. v. United States, 
    422 F.3d 1369
    , 1373 (Fed. Cir. 2005)
    (citation omitted). The government admitted if the Court finds TMA was obligated to extract
    and analyze plaintiffs’ radiology data from its system, and if the Court finds the government
    failed to sufficiently prove a defense, the Court “would find that [the government] owed one
    [named plaintiff] hospital $486”—plaintiffs would be entitled to some damages. Tr. at 133:7–15.
    The parties, however, did not agree to any specific amount of damages, and plaintiffs argued
    damages would be calculated after class certification. See Tr. at 134:2–7 (“a class would be
    certified . . . and determining which hospitals were entitled to damages would be something that
    would be resolved at that stage.”). The Court accordingly finds the government did not carry its
    burden as the moving party of establishing plaintiffs cannot prove damages, and thus the
    government did not show it is “entitled to a judgment as a matter of law” in this respect.
    Anderson, 477 U.S. at 247; see Tr. at 133:7–15.
    E.      The Government’s Defenses to Breach of Contract
    In a breach of contract case, “[o]nce the facts of breach are established, the defendant has
    the burden of pleading and proving any affirmative defense that legally excuses performance.”
    Shell Oil Co. v. United States, 
    751 F.3d 1282
    , 1297 (Fed. Cir. 2014) (quoting Stockton E. Water
    Dist., 
    583 F.3d at 1360
    ). The defendant also has the burden of proving any risk-shifting defense
    against a breach of contract claim by a preponderance of the evidence. See Cardiosom, L.L.C. v.
    United States, 
    117 Fed. Cl. 526
    , 532 (2014) (denying the government’s motion for summary
    judgment in a breach of contract case, in part, because the contract did not shift the relevant risk
    to plaintiff). The Court accordingly considers first whether plaintiffs were obligated to check the
    data under the DPP and second whether the DPP shifted the risk of any data errors to plaintiffs.
    1.      Whether Plaintiffs Had a Contractual Obligation to Check
    Discretionary Adjusted Payment Data
    - 28 -
    In relevant part, Step 8 regarding written requests to TMA provided:
    While the methodology for calculating the adjustment is not subject to questions,
    any questions regarding the data used in the calculations should be received by
    TMA within 30 days of the date of TMA’s response as specified in the response.
    Any questions should be accompanied by detailed explanation of the alleged errors
    and the proposed corrections with supporting documentation.
    DPP Contract Notice at A9. The government contends Step 8 “unequivocally placed the
    ultimate responsibility for identifying any errors in the adjustment calculation squarely on the
    plaintiffs, and not the Government.” Def.’s MSJ at 34. The government elaborates “the
    hospitals shouldered the obligation under the contract to raise ‘any questions regarding the data
    used in the calculations’ and provide a ‘detailed explanation of the alleged errors and the
    proposed corrections with supporting documentation’ within 30 days.” 
    Id.
     at 35–36. Step 8
    “created a process by which the hospitals could challenge any perceived mistakes in the
    calculations received, putting the onus on the hospitals to do so.” Id. at 43.
    Plaintiffs respond by noting the government’s “deliberate choice to use permissive
    language in Step 8,” notably “should,” shows “Step 8 in no way required Plaintiffs to confirm
    that the Government’s data was accurate.” Pls.’ MSJ Resp. at 34–35 (citing DPP Contract
    Notice at A9). Plaintiffs further argue “[t]he Government could have similarly stated in Step 8
    that ‘the hospitals are required to verify the Government’s calculations’ or that ‘the hospitals
    must verify the Government’s data. However, the Government chose not to incorporate such
    language.” Id. at 34. Plaintiffs argued Step 8 “is not what the Government asserts it is. It was
    not ever intended to place an obligation on hospitals to undertake some elaborate investigation
    and identify all possible errors. It was intended to set a time frame when they could ask
    questions.” Tr. at 243:19–25.
    While the government at times argued at oral argument Step 8 obligated the hospitals to
    verify the data TMA presented, Tr. at 93:11–12 (“[THE GOVERNMENT:] . . . it is a contract
    obligation to bring any questions within a 30-day window”), the government admitted plaintiffs
    were not obligated under the contract to check data, rather the contract merely permits plaintiffs
    to verify. 12 See Tr. at 229:11–17 (“I agree that . . . Step 8 doesn’t say must—the language is not
    as strong [as Lakeshore], but it’s still structurally putting the contractor on notice.”), 57:15–18
    (government counsel characterizing Step 8 as plaintiffs’ “opportunity” to check radiology data),
    93:8–11 (“[THE GOVERNMENT:] . . . the language in Step 8 is precatory only insofar as the
    choice to undertake . . . a challenge rests with the Plaintiff”); see also Tr. at 91:21–24
    (“[PLAINTIFFS:] . . . there’s nothing in the language of Step 8 that imposes an obligation on
    12
    As relevant to the Court’s finding of no mutual mistake of fact infra Section V, the government admitted at oral
    argument Step 8 only applies to radiology data questions. See Tr. at 229:24–230:4 (“THE COURT: . . . [Y]ou
    argue that Step 8 applies to radiology claims. Are you also arguing that Step 8 applies to non-radiology claims?
    [THE GOVERNMENT]: No. THE COURT: Not at all? [THE GOVERNMENT]: No.”). The government
    argued non-radiology risk shifting only occurs by operation of law, citing ConocoPhillips v. United States, 
    501 F.3d 1374
     (Fed. Cir. 2007), because plaintiffs chose to enter a business settlement expressly limited to radiology claims,
    necessarily foreclosing adjustment for non-radiology claims. Tr. at 230:4–6 (“[THE GOVERNMENT]: . . . [T]he
    risk shifting that occurs with respect to the non-radiology claims is by operation of law, not by contract
    [pro]vision.”).
    - 29 -
    the hospitals to [investigate data]”). Plaintiffs therefore could verify the data but did not have to.
    See e.g., Telzrow v. United States, 
    127 Fed. Cl. 115
    , 123–24 (2016) (holding the contract allowed
    but did not require the government to collaborate with landowners on restoration project).
    Further, Step 8 provided “any questions regarding the data used in the calculations should
    be received by TMA within 30 days of the date of TMA’s response as specified in the response.”
    DPP Contract Notice at A9 (emphasis added). The Step 8 language is permissive, allowing
    plaintiffs to submit questions if they so choose. See id.; Tr. at 91:24–92:1 (“[PLAINTIFFS]: . . .
    I mean, really what [Step 8] does is put a time limit on how long [hospitals] are allowed to ask
    questions if they so choose.”). If plaintiffs did not challenge TMA’s data under Step 8, plaintiffs
    signed the Release, and TMA then paid the hospitals. See DPP Contract Notice at A9. The
    government did not claim plaintiffs breached the DPP Contract by not checking the data, as the
    government might claim if plaintiffs were obligated to verify the data. As TMA was required to
    perform according to the DPP Contract even if plaintiffs failed to question the radiology data,
    and as the government does not now claim plaintiffs breached the contract by failing to question
    the data, the Court finds the plain meaning of Step 8 provided plaintiffs the option to challenge
    TMA’s data—but not the obligation. 13 Jowett, Inc., 
    234 F.3d at 1368
     (quoting McAbee Constr.,
    Inc., 
    97 F.3d at 1435
    ) (holding courts “must interpret the contract in a manner that gives meaning
    to all of its provisions and makes sense.”); DPP Contract Notice at A9.
    2.       Whether Plaintiffs Bore the Risk of Any Data Issues
    The government argued even if Step 8 is only optional and does not obligate plaintiffs to
    check TMA’s data, it structurally places risk on plaintiffs, making them “the insurers of this
    calculation.” Tr. at 212:11–13. As the Court finds TMA did not have a duty to analyze the
    hospitals’ radiology data, the Court need not analyze whether plaintiffs bore the risk of this
    alleged breach of contract. See supra Section IV.A. By contrast, as the Court finds TMA did
    have a duty to extract, analyze, and adjust radiology data from TMA’s database, the Court must
    consider whether plaintiffs bore the risk of this alleged breach of contract. See supra Section
    IV.B.
    The government argues TMA was not required to disclaim data accuracy because “[t]he
    entire contract structure provided plaintiffs with more than adequate notice that they, not the
    Government, were to be the ultimate insurers of the proposed adjustment calculations, and that
    they should act accordingly.” Def.’s MSJ Reply at 8. Considering Step 8 and FAQ 18, the
    government argues this case is like Lakeshore wherein the Federal Circuit recognized a
    contract’s structure may “‘reinforce[] the allocation of risk by affirmatively pointing [a] potential
    contractor to the mechanism it should use . . . to account for potential . . . error[,]’ and put that
    potential contractor on notice to protect its interests.” Id. at 9–10 (quoting Lakeshore, 748 F.3d
    at 1347). The government also distinguishes Metcalf Construction Co., 742 F.3d at 995–96, by
    13
    Plaintiffs argue even if the Court finds the DPP Contract did require hospitals submit questions per Step 8, “the
    Government made it impossible for Plaintiffs to do so within thirty days.” Pls.’ MSJ Resp. at 35. As the
    government notes, impracticability is “‘intended for use as a defense to a breach-of-contract claim for
    nonperformance, not as a theory to be used in pursuit of an affirmative remedy[.]’” Def.’s MSJ at 44 n.10 (quoting
    CanPro Invs., Ltd. v. United States, 
    130 Fed. Cl. 320
    , 345 (2017))). Additionally, some hospitals submitted
    questions within the thirty-day period. Id.; Tr. at 247:14–249:3. The Court finds supra plaintiffs were not obligated
    to verify TMA’s data, so the Court need not consider plaintiffs’ impracticability argument.
    - 30 -
    arguing “here, (1) there were no affirmative representations, and (2) consistent with Lakeshore,
    the contract implicitly warned plaintiffs . . . were to take into account a risk or [sic] error.” Def.’s
    MSJ Reply at 10. The government adds “[t]here would be no need for Step 8 . . . if TMA was
    guaranteeing that the data that it extracted from its own databases, or the extraction process
    itself, would be perfect.” Def.’s MSJ at 41. The government contends “hospitals were free to
    check against their own records for the same services[.]” Def.’s MSJ Reply at 5 (citing DPP
    Contract Notice at A9; DPP Contract FAQs at A15).
    Plaintiffs respond “the DPP . . . did not allocate the risk to Plaintiffs.” Pls.’ MSJ Resp. at
    37 (citing Metcalf Constr. Co., 742 F.3d at 996). Plaintiffs also note “[i]f the Federal Circuit
    considered Step 8 to be a basis upon which to defeat Plaintiffs’ claim, the Federal Circuit would
    have presumably done so, rather than remanding the claim.” Id. at 38–39 (citing Glaxo Grp. Ltd.
    v. TorPharm, Inc., 
    153 F.3d 1366
    , 1371 (Fed. Cir. 1998) (“[A]n appellate court may affirm a
    judgment of a district court on any ground the law and the record will support . . . .”)).
    Regarding its argument the contract expressly shifted the risk of data errors to plaintiffs,
    the government argued “although . . . Lakeshore is maybe 75 percent on all fours, it’s the closest
    case.” Tr. at 227:17–19. In Lakeshore, the Federal Circuit affirmed the Court of Federal
    Claims’ grant of summary judgment in favor of the government. 748 F.3d at 1343. To solicit
    “bids for a contract for [future, indefinite] repair, maintenance, and construction services at Fort
    Rucker, Alabama[,]” the United States Army Contracting Agency instructed prospective
    contractors to submit bids using prices found in the Universal Unit Price Book (“UUPB”) and
    then multiply these costs by coefficients to account for costs not considered in the UUPB. Id.
    The Federal Circuit noted “[a] fundamental aspect of contracts for future performance is how
    they allocate risks related to the performance.” Id. at 1350. The Federal Circuit concluded that
    “the language of the contract does not promise that the prices [provided] in the UUPB were
    accurate or place on the government the risk that they will turn out to be inaccurate” and instead
    “the only reasonable conclusion on the evidence here is that any risk that the prices in the UUPB
    were inaccurate at the time of contracting was borne by [the plaintiff].” Id. at 1347. The Federal
    Circuit supported its conclusion with three reasons: (1) the contract lacked a promise the prices
    would be accurate, and the firm fixed-price nature of the agreement in dispute shifted the risk to
    the contractor; (2) the contract “affirmatively point[ed] the potential contractor to the mechanism
    it should use in its bid to account for potential error in the 2006 UUPB prices”; and (3) the
    plaintiff’s “own actions ma[d]e clear that it understood that it was responsible for checking the
    2006 UUPB unit prices and setting its coefficients accordingly.” Id. The essence of the Federal
    Circuit’s conclusion was rooted in its finding the plaintiff could not “rewrite the clauses to
    provide it protections the government did not agree to.” Id. at 1348 (citing ConocoPhillips v.
    United States, 
    501 F.3d 1374
    , 1379 (Fed. Cir. 2007)).
    First, unlike Lakeshore, the contract in this case did not involve future government
    procurement but rather the calculation of discretionary adjustment payments for past services
    performed by plaintiffs. The DPP Contract involved an adjustment paid shortly after the contract
    was executed, unlike Lakeshore involving payment for services “indefinite as to delivery and
    quantity” rendered at some undetermined future date with potential interim market fluctuations
    in material or labor prices. The risk borne by the contractor in Lakeshore was risk of future
    market price fluctuations, outside the government’s control, whereas in this case the government
    - 31 -
    asks the Court to find plaintiffs bore the risk of the government’s failure to perform according to
    the contract. See DPP Contract Notice at A7–A9.
    Second, the government admits Step 8 “is not as strong” as the risk-shifting language in
    Lakeshore. Tr. at 229:1–13. In Lakeshore, the Federal Circuit noted the procurement contract
    stated the plaintiff must use a coefficient to “take into account ‘all costs other than the prepriced
    unit prices,’ and it provide[d] a nonexclusive list of the factors that the coefficient must include,
    one of which [wa]s ‘[o]ther risks of doing business.’” 748 F.3d at 1347. The Lakeshore
    solicitation also provided “the coefficients must ‘contain all costs other than the prepriced unit
    prices, as no allowance [would] be made after award.’” Id. at 1343. In this case, however, the
    DPP Contract obligated the government to “extract the claims[,]” “calculate what would have
    been paid under the [Medicare method,]” and send a written response to hospitals detailing “the
    calculated discretionary adjusted payment and the calculations from which the adjustment was
    derived.” DPP Contract Notice at A7–A9. The contract then provided plaintiffs the opportunity
    to check the data and calculations according to Step 8. Step 8 noted “any questions regarding the
    data used in the calculations should be received by TMA within 30 days of the date of TMA’s
    response[.]” Id. at A9. Given the contract obligated TMA to “extract” radiology line items from
    its database, the plain meaning and purpose of Step 8 was to give hospitals a chance to
    cross-reference their data with a summary of TMA’s extracted data. See Tr. at 212:16–24
    (“[PLAINTIFFS:] . . . [T]he purpose of Step 8 is to limit the amount of time in which the
    government will entertain questions from the plaintiffs. It says if you have any questions about
    the calculations . . . you have to get those to us within 30 days, otherwise we’re not going to
    listen to them.”). Though the government argues TMA “made no statements or promises that its
    own work is accurate[,]” Tr. at 229:20–21, TMA did expressly promise it would extract from its
    database and include or exclude radiology line items according to specific criteria. See DPP
    Contract Notice at A7; Tr. at 239:11–15 (“[PLAINTIFFS:] . . . [T]he government promised that
    it would extract the hospitals’ claims. The government has to perform that promise even if it
    turns out that it’s difficult for the government to do so.”).
    Not only is Step 8 weaker than the contractual language the Federal Circuit held shifted
    risk to the contractor in Lakeshore, but also the DPP Contract did affirmatively obligate TMA to
    perform in a particular manner which it admits it failed to do—e.g., “TMA will extract the
    claims for each hospital for claims for outpatient radiology services during the relevant period[.]”
    DPP Contract Notice at A7. In Lakeshore, the Federal Circuit held the plaintiff “has advanced
    no evidence that could support a finding that the government represented that the UUPB prices
    were accurate and could be relied on by [the plaintiff], with the government assuming the risk of
    error in those prices.” 748 F.3d at 1348. A key distinction between this case and Lakeshore is
    the government here did not do what the contract specified it must. 14 By asking the Court to
    enforce the contract according to TMA’s express obligations to consider its own data, plaintiffs
    14
    Though the government’s argument using Lakeshore is distinguishable when it comes to plaintiffs’ TMA-data
    duty claim—alleging the government had a duty to adjust line items in its database—the government’s argument
    using Lakeshore is more closely analogous against plaintiffs’ “hospital-data duty” claim—alleging the government
    had a duty to adjust all hospital data, including data from intermediaries or plaintiffs not in TMA’s database. Like
    the contract in Lakeshore, the DPP Contract does not expressly provide for this hospital-data obligation. The Court
    finds the government prevails as a matter of law on plaintiffs’ hospital-data duty claim because the government was
    not obligated to analyze all hospital’s radiology data, supra Section IV.A. There is therefore no reason to analyze
    further whether plaintiffs bore the risk of their hospital-data duty claim.
    - 32 -
    in this case are accordingly not seeking to “rewrite the clauses to provide it protections the
    government did not agree to[,]” but rather plaintiffs request TMA perform as it was contractually
    obligated. Lakeshore, 748 F.3d at 1348 (citing ConocoPhillips, 
    501 F.3d at 1379
    ). Further,
    TMA’s data and its performance according to the DPP methodology were both within TMA’s
    control, unlike the materials and labor pricing in Lakeshore.
    Plaintiffs add, unlike Lakeshore, “there’s nothing in Step 8 that says you have to do this,
    otherwise the government is off the hook and they don’t have to perform their obligations under
    the agreement.” Tr. at 216:23–25. Although the government states it does not argue the Release
    applies, Step 8 aside, the government’s argument would require the Court to enforce the Release
    against plaintiffs’ remaining breach of contract claim. The government also mentioned the
    Release as barring plaintiffs’ claim at oral argument. See Tr. at 227:2–3 (“[THE
    GOVERNMENT:] . . . They know that the deadline cannot be extended. That’s in the FAQs.
    They execute[d] a release.”). This argument, however, improperly contradicts the Federal
    Circuit’s guidance: the Release cannot bar a suit for breach of the underlying contract. See
    Ingham Reg’l Med. Ctr. v. United States, 
    874 F.3d 1341
    , 1347 (Fed. Cir. 2017) (“[T]he Release
    cannot be enforced against a claim for breach of the underlying contract.”). In short, the
    government cannot argue the Step 8 option allows TMA to avoid performing a proper
    calculation.
    In addition to express risk allocation, the government argues the DPP Contract
    structurally or impliedly allocated risk of radiology data discrepancies to plaintiffs. See Def.’s
    MSJ at 37. Even if risk is not expressly allocated to one party, risk may still be attributed to a
    party for “conscious ignorance” when “he was not only so aware that his knowledge was limited
    but undertook to perform in the face of that awareness[.]” Restatement (Second) of Contracts,
    § 154 cmt. c (Am. L. Inst. 1981). In Metcalf Construction Co., the Federal Circuit ruled a
    contractor failed to establish liability in its suit alleging the Navy breached its duty of good faith
    and fair dealing under a contract to design and build military housing. 742 F.3d at 997. The
    contractor did not “bear the risk of significant errors in the pre-contract assertions by the
    government about the subsurface site conditions” even when the contract required the contractor
    to conduct an independent investigation upon award. Id. at 995–96. Conversely, to the extent
    plaintiffs rely on assumptions when contracting with the government, it is “incumbent upon the
    plaintiffs to investigate those issues before entering into the contract.” ConocoPhillips, 
    501 F.3d at 1380
    . In ConocoPhillips, the plaintiffs entered multiple contracts “contain[ing] an economic
    price adjustment clause that caused the contract price to be adjusted each month based on a
    publication known as the Petroleum Marketing Monthly (‘PMM’).” 
    Id. at 1376
    . The plaintiffs
    argued reformation of the contracts was necessary because “they did not appreciate the way in
    which the price changes reported by the PMM could differ from price changes reported by other
    sources of market information.” 
    Id.
     at 1379–80. The Federal Circuit held “[t]o the extent the
    plaintiffs thought that the PMM tracked other market publications more closely than it did,” they
    should have gathered more information before entering the contracts. 
    Id. at 1380
    .
    ConocoPhillips is distinguishable from this case as plaintiffs are not asserting they relied on their
    own assumptions but rather plaintiffs relied on TMA’s express contractual duty to extract,
    analyze, and adjust TMA’s data according to the DPP Contract. See ConocoPhillips, 
    501 F.3d at 1380
    ; supra Section IV.B. The government also admits the Federal Circuit in ConocoPhillips
    did not discuss risk-shifting in the breach of contract analysis section. Tr. at 87:7–9 (“THE
    - 33 -
    COURT: . . . [D]oes Conoco discuss risk in the breach of contract section? [THE
    GOVERNMENT]: No[.]”). In this case, as TMA expressly promised to use its data for the
    adjustments, plaintiffs cannot impliedly bear the risk of the government’s “pre-contract
    assertions” even though Step 8 gives plaintiffs a thirty-day option window to question the
    government’s written response, akin to offering a contractor an opportunity to perform a site
    visit. See Metcalf Constr. Co., 742 F.3d at 995–96.
    As TMA had an express duty it admittedly failed to perform, this case is distinguishable
    from Lakeshore regarding express allocation of risk and from Conoco regarding implied
    allocation of risk. The Court accordingly finds the government has not met its burden of
    showing it is “entitled to judgment as a matter of law” for whether plaintiffs bore the risk as to
    the government’s breach of its contractual duty to extract, analyze, and adjust radiology data
    from TMA’s database. Anderson, 
    477 U.S. at 247
    ; see Lakeshore, 748 F.3d at 1348; Metcalf
    Constr. Co., 742 F.3d at 990–91; ConocoPhillips, 
    501 F.3d at 1380
    .
    F.       Conclusion
    As the Court finds TMA was not obligated to perform what plaintiffs argue was TMA’s
    contractual duty to extract and adjust the hospitals’ data, the Court accordingly grants in part the
    government’s motion for summary judgment as to plaintiffs’ breach of contract claim regarding
    TMA’s contractual duty to extract and adjust the hospitals’ data. See supra Section IV.A. As
    the government, however, admits TMA failed to meet what plaintiffs assert was TMA’s
    contractual duty to extract, analyze, and adjust radiology claims data from TMA’s database, and
    as the government has not met its burden of proving any breach of contract defenses, the Court
    accordingly denies in part the government’s motion for summary judgment as to plaintiffs’
    breach of contract claim regarding TMA’s contractual duty to extract, analyze, and adjust
    radiology claims data from TMA’s database. See supra Sections IV.B, D. As the government
    admits TMA failed to meet what plaintiffs assert was TMA’s contractual duty to extract, analyze,
    and adjust radiology claims data for an alternative zip code for plaintiff Integris Baptist, the
    Court accordingly denies in part the government’s motion for summary judgment as to plaintiffs’
    breach of contract claim regarding TMA’s contractual duty to extract, analyze, and adjust
    radiology claims data for the five line items under Integris Baptist’s alternative zip code. 15 See
    supra Section IV.C.
    V.      Analysis of Plaintiffs’ Mutual Mistake of Fact Claim
    The Restatement (Second) of Contracts Section 152, titled “When Mistake of Both
    Parties Makes a Contract Voidable” (the “mutual mistake” doctrine), provides:
    (1) Where a mistake of both parties at the time a contract was made as to a basic
    assumption on which the contract was made has a material effect on the agreed
    exchange of performances, the contract is voidable by the adversely affected
    party unless he bears the risk of the mistake under the rule stated in § 154.
    15
    Plaintiffs did not cross-move for summary judgment, so the Court only decides the government’s motion for
    summary judgment.
    - 34 -
    (2) In determining whether the mistake has a material effect on the agreed
    exchange of performances, account is taken of any relief by way of
    reformation, restitution, or otherwise.
    (Am. L. Inst. 1981). The classic illustration of a mutual mistake is: “A contracts to sell and B to
    buy a tract of land, the value of which has depended mainly on the timber on it. Both A and B
    believe that the timber is still there, but in fact it has been destroyed by fire. The contract is
    voidable by B.” § 152, illus. 1. The Federal Circuit in Atlas Corp. v. United States provided the
    standard for a mutual mistake of fact claim:
    A party seeking to state a claim for reformation of a contract under the doctrine of
    mutual mistake must allege four elements:
    (1) the parties to the contract were mistaken in their belief regarding a fact;
    (2) that mistaken belief constituted a basic assumption underlying the contract;
    (3) the mistake had a material effect on the bargain; and
    (4) the contract did not put the risk of the mistake on the party seeking reformation.
    
    895 F.2d 745
    , 750 (Fed. Cir. 1990).
    Plaintiffs aver the mutual mistake issue is whether specific categories, including facility
    charges, were correctly paid before the DPP. See Tr. at 166:4–8. To frame the mutual mistake
    issue, the Court notes plaintiffs clarified at oral argument their only allegation of mutual mistake
    is whether 
    32 C.F.R. § 199.14
    (a)(5)(xi) requires TMA to reimburse plaintiffs for outpatient
    service “facility charges.” Tr. at 137:3–7 (“THE COURT: . . . [T]he parties’ disagreement is
    whether the agency’s mandate was to provide facility charges over the 199.14 enumerated
    outpatient services, correct? [PLAINTIFFS]: Correct.”), 147:18–24 (“[PLAINTIFFS]: . . .
    [T]he DPP represents that prior payments had been made in accordance with Medicare
    principles. . . . The mistake was that the hospitals believed that proper facility charge payments
    had already been made.”). Plaintiffs further clarified regarding radiology data and calculations
    per the DPP Contract—plaintiffs’ breach of contract claim—they “do not allege (and do not need
    to allege) ‘mistakes’ in the calculations, and do not seek reformation of the DPP on that basis.”
    Pls. MSJ Resp. at 38. Plaintiffs do not allege a mutual mistake of fact regarding dump codes,
    either. See Tr. at 63:14–20 (“[PLAINTIFFS]: Well, I think that the government was aware the
    dump codes were a problem. I think the government had knowledge of that and failed to
    disclose that knowledge as part of the DPP. THE COURT: So there was no mistake of fact; the
    government knew about it? [PLAINTIFFS]: Correct[.]”). Notably, other than facility charges
    under § 199.14(a)(5)(xi), plaintiffs do not claim a mutual mistake of fact regarding general
    underpayment in relation to Medicare principles. Tr. at 138:6–9 (“THE COURT: . . . [O]ther
    than the 199.14 payment of facilities charges . . . is there any other mutual mistake of fact?
    [PLAINTIFFS]: No[.]”), 207:9–16 (“THE COURT: If zero dollars are due under (xi), is there
    still underpayment? [PLAINTIFFS]: “I don’t believe that there would be underpayment, at least
    in the way we formulated our claims for those other categories of outpatient services.”). The
    Court accordingly need only analyze whether the parties were mutually mistaken as to the
    interpretation of § 199.14(a)(5)(xi).
    - 35 -
    A.      Whether the Parties Were Mistaken in Their Belief Regarding a Fact
    The first element of the mutual mistake standard requires “the parties to the contract [to
    be] mistaken in their belief regarding a fact[.]” Atlas Corp., 895 F.2d at 750. “An erroneous
    mutual belief about the contents of a written agreement is sufficient to constitute a ‘mistake’ for
    this purpose: reformation is available when the parties, having reached an agreement and having
    attempted to reduce it to writing, fail to express it correctly in the writing.” Nat’l Australia Bank
    v. United States, 
    452 F.3d 1321
    , 1329 (Fed. Cir. 2006) (cleaned up). “Reformation is not a
    proper remedy for the enforcement of terms to which the defendant never assented; it is a remedy
    the purpose of which is to make a mistaken writing conform to antecedent expressions on which
    the parties agreed.” Atlas Corp., 895 F.2d at 750 (quoting 3 Corbin on Contracts § 614 at 723
    (1960)).
    The government contends reformation of a contract based on mutual mistake is
    “extraordinary relief” which “is not legally available under the circumstances of this case,
    because TMA considered, and disclaimed at the time of contract formation, any intention to
    provide hospitals with a markup for hospital overhead through the [DPP] in the first place.”
    Def.’s MSJ at 45–46. The government argues the DPP Contract “stat[ed] unequivocally that
    ‘[a]ny interpretation [of] the regulation provision that facility charges were to be paid on all
    hospital outpatient services in addition to the allowable charge authorized for specified
    outpatient services is unsupportable.’” Id. at 53 (quoting DPP Contract Notice at A5). In other
    words, the government argues the contract “cannot now be ‘reformed’ to create a contract
    obligation that DoD explicitly refused to offer.” Id. The government concludes “[t]here is no
    aspect of plaintiffs’ ‘mutual mistake’ that is legally viable, and, as such, the Government is
    entitled to summary judgment in its favor.” Id. at 71.
    Plaintiffs argue courts “frequently use the power of a court of equity to reform contracts
    so that they conform to the intention of the parties.” Pls.’ MSJ Resp. at 45 (quoting Nippon
    Hodo Co. v. United States, 
    160 F. Supp. 501
    , 502 (Ct. Cl. 1958)) (cleaned up). Plaintiffs assert
    “the Parties made a mutual mistake by believing that the Government had reimbursed Plaintiffs
    for facility charges for all categories of outpatient reimbursement services.” 
    Id.
     Plaintiffs argue
    “[t]he Government offered to pay hospitals the amounts it owed them, but only for outpatient
    radiology services, and only as quantified by the Kennell Study.” 
    Id.
     at 46 (citing DPP Contract
    Letter at A1–A2; DPP Contract Notice at A3–A9). TMA, plaintiffs argue, “affirmatively and
    unambiguously represented in the DPP that radiology was the only underpaid outpatient
    service.” 
    Id.
     (citing DPP Contract Notice at A6; DPP Contract FAQs at A12–A13). Further,
    plaintiffs claim “the DPP failed to reflect anywhere that facility charges were not factored into
    payments,” and “[t]hus, radiology was not the only underpaid outpatient service[.]” 
    Id.
    The 1990 Federal Circuit case Atlas Corp. concerned contracts with the government to
    produce uranium and offers an analytical framework for determining proper reformation of a
    contract. 895 F.2d at 750. Although the Federal Circuit found no mutual mistake in Atlas Corp.,
    the court recognized reformation would be appropriate where “the parties recognize the existence
    of a fact about which they could negotiate” and “they mutually form a belief concerning that
    fact, but their belief is erroneous.” Id. (finding no mutual mistake and so no contract reformation
    because “[t]he parties could not have formed a mutually mistaken belief concerning a fact whose
    - 36 -
    existence they could not recognize”). In Atlas Corp., the Federal Circuit listed several cases
    where courts did permit reformation of contracts. See id. at 751 (citing Sw. Welding & Mfg. Co.
    v. United States, 
    373 F.2d 982
    , 990 (Ct. Cl. 1967) (the parties mistakenly believed the price of
    steel was lower than it actually was); Walsh v. United States, 
    102 F. Supp. 589
     (Ct. Cl. 1952)
    (the parties erroneously believed the minimum wage rate was a certain amount, even though it
    had increased earlier); Aluminum Co. of Am. v. Essex Grp., Inc., 
    499 F. Supp. 53
     (W.D. Pa.
    1980) (the parties erroneously believed the Wholesale Price Index would accurately represent
    nonlabor production costs for the purpose of a contractual escalation clause)); see also
    Bowen–McLaughlin–York Co. v. United States, 
    813 F.2d 1221
     (Fed. Cir. 1987) (reformation
    permitted where the parties erroneously omitted certain price items which existed and could have
    been included in the contract). The Court of Claims also reformed a contract in National Presto
    Industries, Inc. v. United States where plaintiff contractor entered a contract with the
    government, but neither party knew at the time of negotiations the step they had cut to save costs
    would end up being necessary. 
    338 F.2d 99
     (Ct. Cl. 1964). The Federal Circuit in Atlas Corp.
    discussed National Presto Industries, stating, “Although the parties did not know of the need for
    the additional equipment, they clearly recognized that the equipment might be needed. . . .
    Therefore, there was a mutual mistake[.]” Atlas Corp., 895 F.2d at 751 (citation omitted) (citing
    Nat’l Presto Indus., 
    338 F.2d at 107
    ).
    At oral argument, the parties admitted they are unsure whether the Atlas Corp.
    mutual-mistake-of-fact standard requires the parties share the same mistaken belief, although the
    government added it has not “seen a case where the actual mistaken belief was not the same.”
    Tr. at 135:23–136:21. The government stated, “[A]t a minimum, the parties have to share the
    same intention.” Tr. at 136:7–8. Indeed, the first element of a mutual mistake claim requires
    “the parties recognize the existence of a fact about which they could negotiate,” and “they
    mutually form a belief concerning that fact, but their belief is erroneous.” Atlas Corp., 895 F.2d
    at 750. The exemplary mutual mistake cases cited by the Federal Circuit in Atlas Corp. involved
    parties sharing the same belief. See e.g., Sw. Welding & Mfg. Co., 
    373 F.2d at 991
    ; Walsh, 
    102 F. Supp. at 591
    ; Aluminum Co. of Am., 
    499 F. Supp. at
    69–70. The parties further would have
    assented to the deal had they been aware of the truth regarding the fact, and thus, reformation
    was a viable option. See Atlas Corp., 895 F.2d at 751 (“Other cases in which courts have
    permitted reformation of contracts similarly show that the parties held an erroneous belief
    concerning a fact whose existence the parties recognized and about which they could reach
    agreement.”).
    The Court accordingly must determine whether the parties shared a mistaken belief.
    Plaintiffs argue the regulation mandates TMA reimburse facility charges under 
    32 C.F.R. § 199
    (a)(5)(xi) for all outpatient services, whereas TMA expressly stated in the DPP Contract
    “[a]ny interpretation [of] the regulation provision that facility charges were to be paid on all
    hospital outpatient services in addition to the allowable charge authorized for specific outpatient
    services is unsupportable.” DPP Contract Notice at A5. As the parties’ beliefs on the
    interpretation of the regulation are diametrically opposed, the Court does not find the parties
    “mutually form[ed] a belief concerning [a] fact[.]” Atlas Corp., 895 F.2d at 750–51; see Nat’l
    Australia Bank, 
    452 F.3d at 1329
    . Further, as the parties entirely disagreed on the interpretation
    of the regulation when they entered the DPP Contract, plaintiffs in this case cannot contend the
    parties “reached an agreement[,] . . . attempted to reduce it to writing, [and] fail[ed] to express it
    - 37 -
    correctly in the writing.” Nat’l Australia Bank, 
    452 F.3d at 1329
     (internal quotations omitted);
    see also Am. President Lines, Ltd. v. United States, 
    821 F.2d 1571
    , 1582 (Fed. Cir. 1987) (“The
    purpose and function of the reformation of a contract is to make it reflect the true agreement of
    the parties on which there was a meeting of the minds.”).
    “Reformation is not a proper remedy for the enforcement of terms to which the defendant
    never assented; it is a remedy the purpose of which is to make a mistaken writing conform to
    antecedent expressions on which the parties agreed.” Atlas Corp., 895 F.2d at 750. The
    government, however, never assented to making facility charge payments atop other payments
    for outpatient services; the government in fact argues the opposite. Tr. at 143:21–23 (“[THE
    GOVERNMENT]: . . . [Plaintiffs] contend, and we disagree, . . . there’s a facility charge
    payment due on top of the CMAC.”). The government states, “TMA expressly rejected the
    option of offering hospitals an overhead markup on top of the reimbursement amounts[.]” Def.’s
    MSJ Reply at 43 (citing DPP Contract Notice at A5). This express rejection in the DPP states,
    “[A]ll categories of hospital outpatient services paid in accordance with the specific terms of
    199.14(a)(5)(i) through (x) received the correct payment under the TRICARE regulation and are
    not entitled to an additional ‘facility charge’ under paragraph (xi).” DPP Contract Notice at A5.
    This DPP language expresses TMA’s intention of not paying additional facility charges atop
    payments for various outpatient services. Id. Further, when asked at oral argument how the DPP
    Contract dealt with facility charges, plaintiffs responded, “[F]acility charge payments were not
    offered as part of the DPP.” Tr. at 147:8–11, 147:20–22 (“[PLAINTIFFS]: . . . [T]he DPP
    represents that no additional facility charge payment is necessary.”). The government added
    “[t]here [are] no documents or government witness testimony to suggest that the government was
    mistaken factually about the way that these matters are reimbursed.” Tr. at 165:16–19.
    The parties disagree on the interpretation of the statute relative to facility charges such
    that the Court cannot hold they had a meeting of the minds on this issue. Compare Pls.’ MSJ
    Resp. at 41 (“Section 199.14(a)(5) provides that the Government must reimburse Plaintiffs for
    twelve categories of outpatient hospital services, including facility charges.”), with Def.’s MSJ
    Reply at 51 (quoting Pls.’ MSJ Resp. at 5, 54–55) (the government rejects plaintiffs’ claim
    “TMA admitted . . . the ‘facility charge’ provision of 
    32 C.F.R. § 199.14
    (a)(5) was intended to
    provide for a markup for hospital overhead on top of reimbursements otherwise paid as described
    in the regulation, and is now taking a supposedly contrary ‘convenient litigating position[.]’”).
    Without a meeting of the minds, the parties cannot have mutually come to a mistaken belief.
    Against the government’s argument TMA “considered and disclaimed . . . any intention
    to provide hospitals with a markup for hospital overhead[,]” plaintiffs argue, “the DPP’s central
    purpose was to reimburse hospitals for any outpatient category where the hospitals were paid less
    than they should have been paid when applying Medicare fair payment principles.” Pls.’ MSJ
    Resp. at 49. Plaintiffs emphasize “the Notice states that all categories of hospital outpatient
    services paid pursuant to 1991.4(a)(5)(i) [sic] through (x) ‘are not entitled to an additional
    “facility charge” under paragraph (xi).’” 
    Id.
     (quoting DPP Contract Notice at A5). Plaintiffs
    argue this “explanation thus suggests that [the government incorrectly believed] facility charges
    were already appropriately included in the payments pursuant to the regulation.” 
    Id.
    - 38 -
    At oral argument, the government stated the general purpose of the contract was to “bring
    closure to any concerns regarding payment of hospital outpatient services under the TRICARE
    regulation, prior to the implementation of OPPS.” Tr. at 145:10–14 (quoting DPP Contract
    Letter at A1–A2). Plaintiffs contended “the purpose of the DPP was to provide payment to the
    hospitals that was consistent with . . . the requirements of the regulation and the statute.” Tr. at
    234:10–12. In response to plaintiffs’ appeal to “equity” and the “spirit and purpose” of the DPP
    as grounds for reformation, the government argues “plaintiffs misapprehend the spirit and central
    purpose of the [DPP,]” which “was to settle definitively outstanding disputes between the parties
    that had arisen in connection with the interpretation of 
    32 C.F.R. § 199.14
    (a)(5) and a supposed
    difference between levels of reimbursement for outpatient services between Medicare and
    TRICARE.” Def.’s MSJ Reply at 43. To determine the parties’ intent, the Court looks to the
    plain language of “the contract itself.” Greco v. Dep’t of the Army, 
    852 F.2d 558
    , 560 (Fed. Cir.
    1988); see CITGO Asphalt Refin. Co. v. Frescati Shipping Co., 
    140 S. Ct. 1081
    , 1088 (2020)
    (“[T]he parties’ intent ‘can be determined from the face of the agreement’ and ‘the language that
    they used to memorialize [that] agreement.’”). Plaintiffs’ characterization of the general purpose
    of the DPP Contract to argue TMA would have consented to paying facility charges conflicts
    with the plain terms of the DPP Contract: “The intent and effect of the regulation provision for
    reimbursement of facility charges was to pay all other hospital outpatient services not
    specifically listed in the regulation provision with a stated allowable charge methodology based
    on billed charges.” DPP Contract Notice at A5. The government was not mistaken in the DPP
    regarding whether facility charges needed adjustment because they expressly excluded facility
    charges from the scope of consideration. See 
    id.
    The remedy for mutual mistake of fact is to reform the contract—in this case, the DPP
    Contract. The Court is, however, unable to reform the DPP Contract in a way which does not
    “reflect the true agreement of the parties on which there was a meeting of the minds.” Am.
    President Lines, Ltd., 
    821 F.2d at 1582
    . As the parties did not “mutually form a belief
    concerning [a] fact,” and as TMA did not assent to reimbursing plaintiffs’ facility charges as
    plaintiffs request, the Court finds plaintiffs’ claim fails the first element of a mutual mistake of
    fact claim. 16 Atlas Corp., 895 F.2d at 750; see Nat’l Australia Bank, 
    452 F.3d at 1329
    ; Am.
    President Lines, Ltd., 
    821 F.2d at 1582
    . 17 As plaintiffs failed to satisfy the first element of a
    mutual mistake claim, the Court accordingly grants the government’s motion for summary
    judgment as to plaintiffs’ mutual mistake of fact claim. See Atlas Corp., 895 F.2d at 750 (“A
    party seeking to state a claim for reformation of a contract under the doctrine of mutual mistake
    must allege four elements[.]”). Although the Court finds plaintiffs failed to satisfy a necessary
    16
    In dicta in Northern Michigan Hospitals, Inc. v. Health Net Federal Services, LLC, a related case preceding the
    present action discussed supra Section I.A, the Third Circuit provided if “the dispute at issue is not a purely legal
    one, but rather requires factual determinations[,]” such as applying the TRICARE regulations to the Hospitals’
    specific claims for reimbursement, “what is required by the underlying dispute . . . is an application of the
    TRICARE regulations to the Hospitals’ specific claims for reimbursement.” 344 F. App’x 731, 737 (3d Cir. 2009).
    After the Third Circuit affirmed the dismissal of Northern Michigan Hospitals’ claim, the parties in this case entered
    the DPP Contracts instead of pursuing their “implied in fact and breach of quasi-contract/unjust enrichment” claims
    in the Third Circuit case. Id. at 735. Further, during oral argument on 9 June 2022, both parties confirmed there are
    no disputes of material fact on the issues of TMA’s duties under the contract and whether there was a mutual
    mistake of fact. Tr. at 78:11–19.
    17
    As the Court finds plaintiffs’ claim fails the first element of a mutual mistake of fact claim, the Court need not
    consider the parties’ arguments regarding whether TMA’s interpretation of 
    32 C.F.R. § 199.14
    (a)(5)(xi) was correct,
    including evaluation of the Kisor deference factors.
    - 39 -
    element of their mutual mistake of fact claim, the Court nonetheless analyzes the other three
    elements in the alternative.
    B.      Whether the Mistaken Belief Constituted a Basic Assumption Underlying the
    Contract
    For a mutual mistake of fact claim to succeed, the mistaken belief must have “constituted
    a basic assumption underlying the contract[.]” 
    Id.
     This element presupposes proving a mistake
    under element one of the Atlas Corp. analysis. Because the Court finds there was no mistake, no
    mistake could have constituted a basic assumption underlying the contract. Plaintiffs’ claim
    accordingly fails element two of the Atlas Corp. analysis. Id.; see supra Section V.A.
    C.      Whether the Mistake had a Material Effect on the Bargain
    A party asserting a mutual mistake of fact must show the mistaken belief “had a material
    effect on the bargain[.]” Atlas Corp., 895 F.2d at 750. This element is contingent on finding a
    mistaken fact per element one of the Atlas Corp. analysis. Because the Court finds there was no
    mistake, no mistake could have had a material effect on the bargain. Plaintiffs’ claim
    accordingly fails element three of the Atlas Corp. analysis. Id.; see supra Section V.A.
    D.      Whether Plaintiffs Bore the Risk of Mistake
    Element four of the Atlas Corp. analysis requires plaintiffs show “the contract did not put
    the risk of the mistake on [them].” Atlas Corp., 895 F.2d at 750. The Court finds there was no
    mistake sufficient to satisfy element one of the Atlas Corp. analysis, and thus the Court need not
    address Atlas Corp. element four. See id. Assuming in the alternative plaintiffs’ claim “DoD
    and Class Members had been parties to a mutual mistake because, contrary to DoD’s
    representations in the contract documents, radiology was not the only outpatient service that
    TRICARE underpaid” was true, and there was a mutual mistake of fact as to the underpayment
    of non-radiology outpatient services, the Court analyzes whether plaintiffs bore the risk of the
    mistake. Pls.’ Class Cert. at 15; see Atlas Corp., 895 F.2d at 750.
    Restatement (Second) of Contracts Section 154 provides:
    A party bears the risk of a mistake when
    (a) the risk is allocated to him by agreement of the parties, or
    (b) he is aware, at the time the contract is made, that he has only limited
    knowledge with respect to the facts to which the mistake relates but treats
    his limited knowledge as sufficient, or
    (c) the risk is allocated to him by the court on the ground that it is reasonable
    in the circumstances to do so.
    In Harbor Insurance Co. v. Stokes, the DC Circuit stated “[i]n the comments to § 154(b), the
    Restatement reformulates treating ‘limited knowledge as sufficient’ as ‘conscious ignorance[.]’”
    - 40 -
    
    45 F.3d 499
    , 502 (D.C. Cir. 1995) (citing Restatement (Second) of Contracts § 154 cmt. c. (Am.
    L. Inst. 1981)). The Restatement reads:
    c. Conscious ignorance. Even though the mistaken party did not agree to bear the
    risk, he may have been aware when he made the contract that his knowledge with
    respect to the facts to which the mistake relates was limited. If he was not only so
    aware that his knowledge was limited but undertook to perform in the face of that
    awareness, he bears the risk of the mistake. It is sometimes said in such a situation
    that, in a sense, there was not mistake but “conscious ignorance.”
    § 154 cmt. c. Commenting on the scope of “conscious ignorance,” the court stated, “The
    Restatement has quite logically set ‘conscious ignorance’ in a section explicitly addressing risk
    allocation.” Harbor Ins. Co., 45 F.3d at 502.
    The government argues “a party bears the risk of a mistake when [it] is aware, at the time
    the contract is made, that it has only limited knowledge with respect to the facts which the
    mistake relates but treats that limited knowledge as sufficient.” Def.’s MSJ at 47 (citing
    ConocoPhillips v. United States, 
    501 F.3d 1374
    , 1380 (Fed. Cir. 2007)). 18 The government
    argues “‘[e]very time parties enter into a contract, they act with incomplete information[,]’” and
    “[t]herefore, ‘[w]here [the parties] have been explicitly concerned about an issue, but decide to
    press forward without further inquiry or explicit provision, it is reasonable to suppose that they
    intend the contract to dispose of the risk in question, i.e., to bar any reopening at the behest of the
    party who, it turns out, would have done better without the contract.” Id. at 48 (quoting Harbor
    Ins. Co., 45 F.3d at 502). As an initial matter for the government’s risk-bearing argument, the
    government admits Step 8 of the DPP, which in pertinent part reads, “[t]he response will provide
    the calculated discretionary adjusted payment and the calculations from which the adjustment
    was derived[,]” applies to “radiology only[,]” so the government argues its “position is that the
    imposition of the risk of mistake occurs . . . by operation of law, as a result of [plaintiffs’]
    conscious choice to proceed and go forward on the basis of limited knowledge.” DPP Contract
    Notice at A9; Tr. at 211:4–23. The government argues because the contract was “consciously
    considered,” the resulting contractual relationship is not a mistake, but rather “awareness
    of . . . uncertainty[.]” Def.’s MSJ at 48 (quoting Loral Corp. v. United States, 
    434 F.2d 1328
    ,
    1331 (Ct. Cl. 1970)).
    To support their contention that they did not bear the risk of errors, plaintiffs cite Metcalf
    Construction Co., stating: “In Metcalf Construction Co., the Government made representations
    to the plaintiff in its pre-contract requests and questions-and-answers, and the plaintiff later sued
    the Government for breach of contract.” Pls.’ MSJ Resp. at 37 (quoting Metcalf Constr. Co. v.
    United States, 
    742 F.3d 984
    , 996 (Fed. Cir. 2014)).
    18
    The plaintiffs in ConocoPhillips, discussed supra Section IV.E.2, argued their contracts should be reformed based
    on mutual mistake because “when they entered into the contracts they believed that the [Petroleum Marketing
    Monthly (‘PMM’)] accurately reflected market prices, and they did not appreciate the way in which the price
    changes reported by the PMM could differ from price changes reported by other sources of market information.”
    
    501 F.3d at
    1379–80. The contracts were, however “very clear about the price that [would] be paid to the contractor
    and how that price [would] be adjusted.” 
    Id. at 1380
    . The Federal Circuit held “[t]o the extent the plaintiffs thought
    that the PMM tracked other market publications more closely than it did . . . it was incumbent upon the plaintiffs to
    investigate those issues before entering into the contract.” 
    Id.
     (citing Restatement (Second) of Contracts § 154(b)).
    - 41 -
    The court held that nothing in the contract “expressly or implicitly warned Metcalf
    that it could not rely on, and that instead it bore the risk of error in, the government’s
    affirmative representations . . . . The natural meaning of the representations was
    that, while Metcalf would investigate conditions once the work began, it did not
    bear the risk of significant errors in the pre-contract assertions by the
    government[.]”
    Id. (quoting Metcalf Constr. Co., 742 F.3d at 995–96).
    The government asserts plaintiffs incorrectly view “the fact that TMA provided them
    with limited information, particularly as to the [Kennell] studies, during the settlement process,
    [as] effectively mak[ing] TMA their insurer[.]” Def.’s MSJ at 50. Plaintiffs had other options,
    according to the government, but chose to proceed with “conscious ignorance” instead. Id. at
    50–51. For example, the government contends plaintiffs could have “avail[ed] themselves of the
    FAQ process to obtain additional information[,]” “attempt[ed] to negotiate contract terms that
    were more protective of their interests in light of the limited information TMA had provided[,]”
    “walk[ed] away from the proposed arrangement entirely,” or resolved to litigate. Id. at 51
    (emphasis removed). Instead, the government emphasizes, “in the face of their limited
    knowledge, [plaintiffs] made the conscious choice to press forward with the deal without
    alteration, and they chose to compromise their unadjudicated legal claims, electing the certainty
    of settlement over the uncertainty of litigation.” Id.
    The government further notes a “party who has made inquiries that have gone
    unanswered fails to exercise due diligence and assumes the risk of mistake if it executes a
    contract notwithstanding its lack of knowledge.” Id. at 51–52 (citing CanPro Invs. Ltd. v. United
    States, 
    130 Fed. Cl. 320
    , 342 (2017) (finding “[plaintiff]’s execution of the lease in light of its
    admitted lack of knowledge concerning what it deems a ‘basic assumption’ regarding the lease
    constitutes a failure to exercise due diligence and thus places the risk of a mistake resulting from
    such lack of knowledge squarely on [plaintiff].” (citation omitted))). Plaintiffs “did not even
    make inquiries before executing the contract[,]” according to the government. Id. at 52. The
    government summarizes: “The fact that plaintiffs were contacted years later by a law firm, and
    now regret the decision that they made on limited knowledge in 2011 to accept the terms of
    TMA’s settlement offer, is not a circumstance that now enables them to reform their contract.”
    Id. (footnote omitted). In response to plaintiffs’ contention there was no express allocation of
    risk to plaintiffs, the government argues “the risk of mistake may shift in ways other than
    through express contract provisions.” Def.’s MSJ Reply at 39.
    Plaintiffs assert “[t]o allocate the risk of a mutual mistake to a particular party, there must
    be ‘an agreement explicitly reached or implied from customary practice, as to who should bear
    the risk of mistake.’” Pls.’ MSJ Resp. at 50 (quoting Burnside-Ott Aviation Training Ctr., Inc. v.
    United States, 
    985 F.2d 1574
    , 1582 (Fed. Cir. 1993)). Plaintiffs state: “In Burnside-Ott Aviation
    Training Ctr., Inc., for example, the court denied the Government summary judgment’s [sic]
    motion against the Plaintiffs’ mutual mistake claim[,]” determining because “the contract does
    not say ‘anything about which party to a government contract bears the risk of misclassification
    of service employees . . .further [sic] examination is needed to determine whether the parties had
    - 42 -
    an agreement, explicitly reached or implied from customary practice, as to who should bear the
    risk of mistake.’” 
    Id.
     (quoting Burnside-Ott Aviation Training Ctr., Inc., 
    985 F.2d at 1582
    ).
    Similarly, plaintiffs cite S.A. Healy Co. v. United States, noting in that case “the Government
    argued that the following contract provision allocated the risk of insufficient appropriations (the
    relevant risk in this case) to the plaintiff: ‘The contractor is also cautioned that the prosecution
    of the work at a rate that will exhaust the funds reserved before the end of the fiscal year will be
    at his own risk.’” 
    Id.
     at 50–51 (quoting 
    576 F.2d 299
    , 304–05 (Ct. Cl. 1978)). In S.A. Healy
    Co., plaintiffs argue, “[t]he court determined that the ‘clause as a whole is not sufficient to shift
    this burden to the contractor when the administrative agency is at least partly to blame for the
    funds shortage.’” Id. at 51 (quoting 
    576 F.2d at
    304–05). Plaintiffs contrast S.A. Healy Co. with
    this case, asserting “the Parties did not enter into any agreement regarding who would bear the
    risks of the mistake[,]” and the government’s arguments fail because “there was not a single
    provision or disclaimer in the DPP that expressly or implicitly warned Plaintiffs that [they] could
    not rely on [the] Government’s affirmative representations, and that Plaintiffs bore the risk of
    error.” 
    Id.
     Plaintiffs also cite National Presto Industries as instructive. Id. at 52. In National
    Presto Industries, Inc. v. United States, the plaintiff entered a contract containing “no disclaimers
    of Government liability or warranties by the plaintiff” with the Ordnance Department of the
    Army “for the commercial production of 105-millimeter artillery shells.” 
    338 F.2d 99
    , 101, 109
    (Ct. Cl. 1964). The 1964 Court of Claims found although the plaintiff was an “active partner” in
    the process, “this was not a performance contract; plaintiff was not an expert, promising to
    perform and taking the whole risk and anxiety of the project off the Government’s shoulders.”
    
    Id. at 109
    . Plaintiffs contend even if they were “active partners” in the DPP, the government was
    the reason for plaintiffs’ limited knowledge, so the risk remains with the government. Pls.’ MSJ
    Resp. at 52–53. Plaintiffs note like the National Presto Industries contract, the DPP Contract
    “did not contain any disclaimers of Government liability or any warranties by the Plaintiffs.” Id.
    at 53.
    The government notes “in the Burnside-Ott case cited by the plaintiffs, the Federal
    Circuit reversed a grant of summary judgment because . . . ‘further examination is needed to
    determine whether the parties had an agreement, explicitly reached or implied from customary
    practice, as to who should bear the risk of mistake.’” Def.’s MSJ Reply at 39–40 (quoting
    Burnside-Ott Aviation Training Ctr., Inc., 
    985 F.2d at 1582
    ). In response to plaintiffs’ use of
    S.A. Healy Co., the government argues “[t]he court in that case had no occasion to consider
    whether, and under what conditions, risk shifting occurs by operation of law outside of
    circumstances where there is an express contract provision, because the only task before the
    court was to interpret the provision in question.” 
    Id.
     at 40 (citing S.A. Healy Co., 
    576 F.2d at
    304–05). The government also distinguishes National Presto Industries, stating it “does not
    stand for the proposition that the risk of mistake cannot shift in the absence of an express
    contract provision.” 
    Id.
     Although the court acknowledged the absence of disclaimers and
    warranties in the particular contract at issue as part of its analysis, the government asserts “the
    Claims Court’s determination that the risk of mistake did not shift to the contractor was based
    upon the fact that the overall dealings between the parties—not just the contract
    provisions—established that the contractual relationship at issue was that of a ‘joint enterprise’
    pioneering a new technology.” 
    Id.
     at 40–41 (citing Nat’l Presto Indus., Inc., 338 F.2d at 109).
    - 43 -
    This court has found “a party ‘cannot rely upon a mutual mistake of fact to avoid
    enforcement of a contract where . . . the “mistake” is a result of that party’s failure to exercise
    due diligence.’” CanPro Invs. Ltd., 130 Fed. Cl. at 342 (quoting Griffin & Griffin Expl., LLC v.
    United States, 
    116 Fed. Cl. 163
    , 175 (2014)). In CanPro, the plaintiff alleged it reasonably
    relied on the government to provide all material information relating to the lease, and it “never
    received the information it requested and that it knew was needed to develop an informed belief
    concerning the [issue], but that it nonetheless executed the lease.” 
    Id.
     This court found
    “[plaintiff]’s execution of the lease in light of its admitted lack of knowledge . . . constitutes a
    failure to exercise due diligence and thus places the risk of a mistake resulting from such lack of
    knowledge squarely on [plaintiff].” 
    Id.
     This court held “‘[i]gnorance is never sufficient to
    constitute a ground of relief if it appears that the requisite knowledge might have been obtained
    by reasonable diligence.’” 
    Id.
     (quoting Griffin & Griffin Expl., LLC, 116 Fed. Cl. at 175).
    In this case, plaintiffs signed the DPP knowing “facility charge payments were not
    offered as part of the DPP.” Tr. at 147:8–11, 147:20–22 (“[PLAINTIFFS:] . . . [T]he DPP
    represents that no additional facility charge payment is necessary.”). Plaintiffs asserted at oral
    argument “they were reasonably . . . relying upon what the DPP said.” Tr. at 178:6–7. When the
    Court asked, “Did the plaintiffs inquire as to the government’s stating that it [did] correctly
    reimburse for non-radiology claims?” plaintiffs responded, “I’m not sure whether
    any . . . potential plaintiffs did. I’m not aware of the named plaintiffs having done that. No.”
    Tr. at 178:4–13. Although plaintiffs admit they did not exercise due diligence to determine
    whether they were correctly reimbursed for non-radiology outpatient services, plaintiffs
    nonetheless signed the DPP. See Def.’s MSJ App. at A19 (Ingham Regional Medical Center),
    A21 (Integris Baptist Regional), A23 (Integris Bass Baptist), A25 (Integris Grove Hospital), A27
    (Integris Baptist Medical), A29 (Integris Canadian Valley). Plaintiffs also admit when they
    signed the DPP they had not seen the Kennell Study underlying TMA’s analysis of outpatient
    service reimbursements. Pls.’ MSJ Resp. at 52 (“[T]he Government refused to provide Plaintiffs
    with a copy of the Kennell Study until years later, in 2013, after Plaintiffs had made multiple
    attempts and FOIA requests to obtain it.”). Plaintiffs accordingly concede they signed the DPP
    Contract despite their “limited knowledge.” Id.; see ConocoPhillips, 
    501 F.3d at 1380
    (determining “it cannot be said that either party could have been mistaken” as to the calculation
    method imagined by the contract). By agreeing to the DPP’s terms despite admitting they “ha[d]
    only limited knowledge with respect to the facts to which the mistake relates[,]” plaintiffs
    “b[ore] the risk of [the] mistake” they now allege. Restatement (Second) of Contracts § 154(b);
    see ConocoPhillips, 
    501 F.3d at 1380
     (holding contractors bore risk of investigating the
    calculation method before entering contract).
    Plaintiffs signed the DPP knowing they had limited knowledge regarding the facts
    underlying the alleged mistake, thus plaintiffs failed to “exercise due diligence[,]” and so the risk
    of any mistake “resulting from such lack of knowledge [is placed] squarely on” plaintiffs.
    CanPro Invs. Ltd., 130 Fed. Cl. at 342. As the DPP Contract expressly disclaims paying
    plaintiffs for the mistake they now allege, “it was incumbent upon the plaintiffs to investigate
    those issues before entering into the contract.” ConocoPhillips, 
    501 F.3d at 1380
    . By acting on
    limited knowledge with “conscious ignorance” and agreeing to the DPP without investigation,
    plaintiffs bore the risk of mistake. Even if, counterfactually, their claim satisfied elements one,
    two, and three of the Atlas Corp. analysis, plaintiffs’ mutual mistake of fact claim would fail
    - 44 -
    element four. As stated supra Section V.A, the government has shown plaintiffs failed to prove
    all four elements of their mutual mistake of fact claim, and the alternative analysis does not
    change the Court’s finding the government has shown it is “entitled to judgment as a matter of
    law” regarding plaintiffs’ mutual mistake of fact claim. 19 See Anderson v. Liberty Lobby, Inc.,
    
    477 U.S. 242
    , 250 (1986); Atlas Corp., 895 F.2d at 750; ConocoPhillips, 
    501 F.3d at 1380
    .
    VI.      Class Certification
    Plaintiffs seek class certification arguing “[t]he Class Members are hospitals that
    provided outpatient healthcare services to current and former military members and their families
    covered under the U.S. Government’s TRICARE program.” Pls.’ Class Cert. at 1. Plaintiffs
    assert “approximately 1,600 similarly situated hospitals across the United States . . . , entered
    into the exact same reimbursement contract with the U.S. Government, which contract was the
    subject of the exact same mutual mistake, and were as a result all systematically underpaid by
    the U.S. Government in the same way under that common contract.” 
    Id.
     According to plaintiffs,
    19
    In the alternative, the government asserts “the parties’ contracts are settlement agreements” which “definitively
    settled the question of whether TRICARE underpaid hospitals relative to the Medicare rates . . . , as well as ‘any and
    all claims . . . arising out of or resulting from or in in anyway relating to payments . . . or any other means of
    compensation’ . . . prior to the institution of the TRICARE [OPPS].” Def.’s MSJ Reply at 32–33. “These
    features[,]” the government argues, “foreclose the applicability of the mutual mistake doctrine in this case as a
    matter of law.” Id. at 33. According to the government, plaintiffs’ allegation about “erroneous factual assumptions”
    is not relevant because “[a] settlement agreement that resolves known factually disputed issues in the face of
    uncertainty is equally immune from reformation on the grounds of mutual mistake.” Id. (citing Tarrant v. Monson,
    
    96 Nev. 844
    , 845–46 (1980)). The government notes “[a]t the time of contracting, the parties were aware . . . there
    was an unresolved dispute between TMA and hospitals over the proper interpretation of 
    32 C.F.R. § 199.14
    (a)(5).”
    
    Id.
     at 36–37 (citing DPP Contract Notice at A5).
    Though the Court previously found “the [L]etter and Notice initiating the [DPP] were sent to expressly avoid
    litigation” and so “cannot constitute preparation for litigation[,]” the Court found the DPP Contract was a
    “negotiated business settlement” resolving payment discrepancy issues by “recalculating TRICARE payments,
    which became the government’s business during the [DPP].” 14 Jan. 2020 Op. & Order at 20, 25. While the DPP
    Contract was not prepared in anticipation of litigation, the parties used “the term ‘settlement’ as a negotiated
    business settlement to bring finality to payment adjustments.” Id. at 20. A Nevada Supreme Court case cited by the
    government, Tarrant v. Monson, involved an agreement between a jeweler and customer after the jeweler misplaced
    the customer’s ring and offered instead a replacement ring before later finding the original ring. 96 Nev. at 845; see
    Def.’s MSJ Reply at 33. In Tarrant, the Nevada Supreme Court held: “One who acts, knowing that he does not
    know certain matters of fact, makes no mistake as to those matters. If a person is in fact aware of certain
    uncertainties a mistake does not exist at all.” Id. Further, “[o]ne who is uncertain assumes the risk that the facts will
    turn out unfavorably to his interests.” Id. “Since [the jeweler] at time of agreement knew that the ring might later
    be found, [the jeweler] bargained with conscious uncertainty and not under a mistaken belief. [The jeweler]
    assumed the risk that the facts would turn out unfavorably to his interests.” Id. at 846. Although the roles of the
    parties in this case are reversed compared to Tarrant, with plaintiffs seeking contract reformation and the
    government defending, the government argues in this case, like Tarrant, “[t]he parties d[id] know what they d[id]n’t
    know.” Tr. at 148:14–15. Plaintiffs entered the DPP Contract knowing they did not know whether they were
    correctly paid facility charges, even with the express provision providing for the opposite of their current mutual
    mistake argument—“[hospitals] are not entitled to an additional ‘facility charge’ under paragraph (xi).” DPP
    Contract Notice at A5; see Def.’s MSJ App. at A19 (Ingham Regional Medical Center), A21 (Integris Baptist
    Regional), A23 (Integris Bass Baptist), A25 (Integris Grove Hospital), A27 (Integris Baptist Medical), A29 (Integris
    Canadian Valley). To the extent the contract qualified as a settlement agreement, the Court would alternatively find
    plaintiffs bore the risk under the DPP negotiated business settlement. See Tarrant, 
    96 Nev. 844
    ; 14 Jan. 2020 Op. &
    Order at 22.
    - 45 -
    “[c]ommon issues thus predominate” as “the financial injury suffered by each of the Class
    Members is easily ascertained through a uniform damages methodology” and “[t]he only
    difference among Class Members is the amount of damages.” 
    Id.
     The parties briefed their
    argument for class certification pertaining to the potential class of approximately 1,600 hospitals.
    See Def.’s Class Cert. Resp.; Pls.’ Class Cert. Reply.
    Plaintiffs argue at least two facts are common to all Class members: (1) “the
    Government failed to calculate properly payments owed to Class Members for outpatient
    radiology services in accordance with the contract because it omitted hospital claims data, which
    are the specific line item requests for reimbursement submitted by hospitals to TRICARE”; and
    (2) “the Government’s representation in the contract that categories of outpatient services other
    than radiology services were not underpaid was incorrect” because it “improperly failed to
    account for facility charges when it made representations in the [DPP] that all other outpatient
    services had been paid at amounts equal to or more than that which would have been paid under
    Medicare principles.” Pls.’ Class Cert. at 2–3. Plaintiffs “seek certification pursuant to RCFC
    23 of the following Class: [a]ll hospitals in the United States that participated in the [DPP]
    described in the . . . [L]etter . . . , and the Notice . . . referred to therein, and that signed a release
    and received a payment through the [DPP].” Id. at 4.
    Plaintiffs argue their breach of contract claim raises at least two common issues of law
    and fact: (1) “[w]hether, in calculating the amounts owed to Class Members, the Government
    captured and used all of the claims data that it was required to use under the terms of the
    contract;” and (2) “[w]hether the Government paid each Class Member the amount it was
    entitled to under the [DPP].” Id. at 24. Plaintiffs argue the breach of contract claim affects all
    class members. Id. The relevant potential class, however, is only the class of plaintiffs affected
    by the government’s breach of contract for failure to follow the DPP in limited circumstances
    because the Court finds the DPP Contract only obligated TMA to use its data, not the hospitals’
    data. See supra Sections IV.A, B, D; Tr. at 132:4–13.
    Plaintiffs argue the proposed class of approximately 1,600 hospitals satisfies RCFC class
    certification requirements, which have been “‘succinctly described as comprising inquiry into the
    elements of numerosity, commonality, typicality, adequacy, and superiority.’” Pls.’ Class Cert.
    at 19 (quoting Singleton v. United States, 
    92 Fed. Cl. 78
    , 82 (2010)). Plaintiffs’ class
    certification briefing does not address the “numerosity, commonality, typicality, adequacy, and
    superiority” of the narrow class of plaintiffs affected by the government’s breach of contract for
    failure to follow the DPP in limited circumstances. See supra Section IV.F. In oral argument on
    9 June 2022 on the government’s motion for summary judgment, plaintiffs admitted if the Court
    finds the DPP Contract only obligated TMA to use its data, the class would be “smaller than the
    whole class” argued in briefing. Tr. at 132:4–13. Plaintiffs focused their briefing on arguing
    commonality under the breach of contract claim for the large class of approximately 1,600
    hospitals and did not address the commonality of what plaintiffs admit is a smaller class. See
    Pls.’ Class Cert. at 22–25.
    Based on the summary judgment holding in this order, the Court therefore needs further
    information regarding how plaintiffs in this post-summary judgment smaller class would meet
    the requirements for class certification. See Tr. at 260:21–261:9 (“THE COURT: Is that not a
    - 46 -
    fair, clear, ascertainable grouping of hospitals that is smaller than the full class alleged by
    plaintiffs now, but a class capable of being defined and a class that would have each individual
    hospital making its own individual calculation of damages? [THE GOVERNMENT]: . . . [T]o
    make a prima facie case, even on those points, you’re still left with the problem of taking their
    data and doing a comparison to the government’s data.”). The Court accordingly declines to rule
    on plaintiffs’ class certification motion at this time. As the only surviving claims are breach of
    contract for failure to follow the DPP in a few limited circumstances, the parties did not
    adequately brief the narrower proposed class of plaintiffs arising under the remaining claims.
    The parties shall file a joint status report providing the parties’ views on class certification for the
    smaller class of plaintiffs affected by the government’s breach of contract for failure to follow
    the DPP in limited circumstances and on whether further briefing is necessary.
    VII.    Conclusion
    For the foregoing reasons, the Court GRANTS plaintiffs’ motion for leave to file
    amended briefs and appendices to the extent considered in this Opinion and Order, ECF No. 242,
    and GRANTS IN PART and DENIES IN PART the government’s motion for summary
    judgment, ECF No. 203. The Court GRANTS the government’s motion for summary judgment
    as to plaintiffs’ hospital-data duty and mutual mistake of fact claims but DENIES the
    government’s motion as to plaintiffs’ TMA-data duty and alternate zip code claims. The Court
    STAYS the evidentiary motions as the Court established in the status conference held on 11 May
    2022 20 plaintiffs’ motions to exclude expert opinions—ECF Nos. 205, 206—and the continued
    participation of Kennell, ECF No. 251, are not consequential for the government’s summary
    judgment motion. For the same reason, the Court STAYS the government’s motions to strike
    “Paragraphs 3 - 10 of the Dale Thompson Declaration,” ECF No. 239, and “Paragraphs 7 and 18
    of the Declaration of Sere Allen, and Associated Briefing,” ECF No. 240. The Court STAYS the
    government’s motion to exclude inadmissible evidence pursuant to Rule 408, ECF No. 204, and,
    thus, the Court STAYS the government’s motion to strike “Rule 408 Evidence Relied on by
    Plaintiffs in Summary Judgment Briefing,” ECF No. 238. On or before 28 December 2022, the
    parties SHALL FILE a joint status report updating the Court on plaintiffs’ motion for leave to
    file amended briefs and appendices and providing their views on further briefing related to
    plaintiffs’ motion to certify class.
    IT IS SO ORDERED.
    s/ Ryan T. Holte
    RYAN T. HOLTE
    Judge
    20
    See supra Section I.D (noting government’s motions to exclude expert opinions of Jane Jerzack, ECF No. 205,
    Anthony Fay, ECF No. 206, and David Kennell, ECF No. 251; motions to strike “Rule 408 Evidence Relied on by
    Plaintiffs in Summary Judgment Briefing,” ECF No. 238, “Paragraphs 7 and 18 of the Declaration of Sere Allen,
    and Associated Briefing,” ECF No. 239, and “Paragraphs 3 - 10 of the Dale Thompson Declaration,” ECF No. 240;
    and motion to exclude inadmissible evidence pursuant to Rule 408, ECF No. 204, are not consequential for
    summary judgment).
    - 47 -
    

Document Info

Docket Number: 13-821

Judges: Ryan T. Holte

Filed Date: 12/13/2022

Precedential Status: Precedential

Modified Date: 12/13/2022

Authorities (31)

Moore v. SHAWMUT WOODWORKING & SUPPLY, INC. , 788 F. Supp. 2d 821 ( 2011 )

United States v. Giordano , 94 S. Ct. 1820 ( 1974 )

S. A. Healy Co. v. United States , 576 F.2d 299 ( 1978 )

ConocoPhillips, Conoco, Inc. v. United States , 501 F.3d 1374 ( 2007 )

Stockton East Water District v. United States , 583 F.3d 1344 ( 2009 )

Amer Bus Assn v. Slater, Rodney E. , 231 F.3d 1 ( 2000 )

United States v. Spearin , 39 S. Ct. 59 ( 1918 )

Jowett, Incorporated v. United States , 234 F.3d 1365 ( 2000 )

McAbee Construction, Inc. v. United States , 97 F.3d 1431 ( 1996 )

Celotex Corp. v. Catrett, Administratrix of the Estate of ... , 106 S. Ct. 2548 ( 1986 )

Anderson v. Liberty Lobby, Inc. , 106 S. Ct. 2505 ( 1986 )

Commerce International Company, Inc. v. The United States , 338 F.2d 81 ( 1964 )

United States v. Seckinger , 90 S. Ct. 880 ( 1970 )

San Carlos Irrigation and Drainage District v. The United ... , 877 F.2d 957 ( 1989 )

United Pacific Insurance v. United States , 497 F.2d 1402 ( 1974 )

NIPPON HODO COMPANY v. United States , 160 F. Supp. 501 ( 1958 )

Trauma Service Group v. United States , 104 F.3d 1321 ( 1997 )

Singleton v. United States , 2010 U.S. Claims LEXIS 68 ( 2010 )

Indiana Michigan Power Company v. United States , 422 F.3d 1369 ( 2005 )

Nicholson v. United States , 1993 U.S. Claims LEXIS 141 ( 1993 )

View All Authorities »