Hydraulics International, Inc. v. United States ( 2020 )


Menu:
  •              In the United States Court of Federal Claims
    Nos. 19-105C; 20-598C
    Consolidated
    (Filed: December 15, 2020)
    )
    HYDRAULICS INTERNATIONAL, INC.,                   )     Keywords: Government Contracts;
    )     Jurisdiction; Contracting Officer’s Final
    Plaintiff,                 )     Decision; Technical Data Package.
    )
    v.                                         )
    )
    THE UNITED STATES OF AMERICA,                     )
    )
    Defendant.                 )
    )
    )
    )
    W. Brad English, Maynard Cooper & Gale, P.C., Huntsville, AL, for Plaintiff. Emily J. Chancey,
    Maynard Cooper & Gale, P.C., Huntsville, AL, Of Counsel.
    Igor Helman, Trial Attorney, U.S. Department of Justice, Civil Division, Commercial Litigation
    Branch, Washington, DC, with whom were Patricia M. McCarthy, Assistant Director, Robert E.
    Kirschman, Jr., Director, and Jeffrey Bossert Clark, Acting Assistant Attorney General, for
    Defendant.
    OPINION AND ORDER
    KAPLAN, Judge.
    These consolidated cases are before the Court on the government’s motion to dismiss
    case number 20-598 for lack of jurisdiction. The government argues that the matters raised in the
    complaint were not the subject of a contracting officer’s final decision as required to invoke this
    Court’s jurisdiction under the Contracts Disputes Act, 
    41 U.S.C. §§ 7101
    –7109. For the reasons
    that follow, the government’s motion to dismiss is DENIED.
    BACKGROUND 1
    I.      Case Number 19-105
    On September 19, 2015, the Air Force awarded Hydraulics International, Inc.
    (“Hydraulics”) a contract to engineer, manufacture, and deliver sixty-two MJ-1Es, which are
    electric lift trucks used to load, transport, and unload weapons and similar cargo onto aircraft.
    Compl., Case No. 20-598 (“Compl. 20-598”) ¶¶ 5, 13, ECF No. 1. In February of 2017,
    Hydraulics submitted a Technical Data Package (“TDP”) to the agency and requested payment
    for that package in accordance with CLIN 0005 of the contract, entitled “Product
    Drawings/Models and Associated Lists.” 
    Id. ¶ 14
    ; Compl. 20-598 App. A at 10. 2 The agency
    rejected Hydraulics’ submission on August 2, 2017 because, among other reasons, it did not
    include 3D models of the MJ-1E. Compl. 20-598 ¶¶ 14–15.
    The dispute between Hydraulics and the Air Force regarding the failure to include 3D
    models in the TDP ultimately became the subject of a government claim set forth in a September
    18, 2018 Contracting Officer’s Final Decision. In that decision, the contracting officer (“CO”)
    rejected Hydraulics’ contention that it was not obligated to include 3D models in the TDP.
    Compl. (“Compl. 19-105”) App. A at 7–8, ECF No. 1. The CO further concluded that the agency
    was entitled to withhold $633,000 of the approximately $1.4 million payable to Hydraulics for
    the TDP—the amount an engineering analysis showed it would cost the agency to create the 3D
    models itself. 
    Id.
     at 7–8. Hydraulics appealed the CO’s final decision to this Court on January
    18, 2019. See Compl. 19-105, ECF No. 1.
    II.     Case No. 20-598
    A.      The January 18, 2019 Claim
    On the same day that Hydraulics filed its civil action in case number 19-105 (January 18,
    2019), it submitted certified claims to the CO that ultimately led to the complaint in case number
    20-598. Among these claims, and relevant to the present motion to dismiss, Hydraulics requested
    payment of $784,743.31—the payment remaining under CLIN 0005 after subtracting $633,000,
    the amount the agency withheld because the TDPs did not include 3D models. Compl. 20-598
    App. A at 11–12. 3
    1
    The facts set forth below are based on the allegations in the complaints in case numbers 19-105
    and 20-598, as well as jurisdictional facts drawn from the evidence submitted by the parties.
    Unless otherwise noted, all citations are to the docket for the lead case, number 19-105.
    2
    The complaint in each case incorporates an appendix. The Court will use the pagination in its
    electronic filing system when citing to these appendices.
    3
    In its January 18, 2019 letter, Hydraulics also claimed that the Air Force had breached the
    contract by failing to accept delivery of and make payment for seven MJ-1Es. Compl. 20-598
    App. A at 10. It demanded that the Air Force accept delivery of the trucks and also that it pay
    2
    While its January 18, 2019 claim was pending, Hydraulics offered up two revised TDPs
    for the agency’s consideration, the first of which it submitted on January 24, 2019. Compl.
    20-598 App. A at 22. In the meantime, on March 19, 2019, the CO exercised her statutory
    authority to extend to May 18, 2019 the sixty-day deadline for her final decision on the January
    18 claim. Pl.’s Resp. to Mot. to Dismiss for Lack of Jurisdiction (“Pl.’s Resp.”) App. A at A1,
    ECF No. 23 (CO extension notice for January 18, 2019 certified claim); see also 
    41 U.S.C. § 7103
    (f)(2) (requiring the CO to issue a decision within sixty days of the submission of a certified
    claim over $100,000 or “notify the contractor of the time within which a decision will be
    issued”). Several weeks later, on April 9, 2019, the agency rejected Hydraulics’ first revised TDP
    as incomplete and supplied Hydraulics with a spreadsheet outlining the TDP’s alleged
    deficiencies. Compl. 20-598 App. A at 23.
    On May 15, 2019, Contract Specialist Lisa Samples contacted Hydraulics on the CO’s
    behalf. Pl.’s Resp. App. A at A2. She noted that she understood that Hydraulics intended to
    submit a second revised TDP in the next few days, and asked if Hydraulics would “suspend[] the
    Claim until [Hydraulics] resubmits and the government engineers complete the final review” of
    that second revised TDP. 
    Id.
     Hydraulics responded the same day that it would agree to “suspend”
    the deadline for the agency’s final decision for an additional two weeks, until Friday May 31,
    2019. 
    Id.
     It made clear, however, that it was “NOT withdrawing [its] claim.” 
    Id.
    Hydraulics then submitted a second revised TDP on May 17, 2019. Compl. 20-598 App.
    A at 23. On May 29, 2019, the agency rejected the second revised TDP as incomplete. 
    Id.
    The next day, May 30, 2019, Hydraulics and the agency met to discuss and clarify the
    agency’s concerns about the second revised TDP. 
    Id. at 24
    . During the meeting, Hydraulics
    stated that it would submit a third revised TDP by June 20, 2019, and that the third revised TDP
    would contain the corrections the agency had requested and/or that Hydraulics would identify
    and justify any failure to make those corrections. 
    Id.
    B.      The CO’s May 31, 2019 Disposition of the January 18, 2019 Claim
    Although it offered to submit a third revised TDP, Hydraulics did not agree to the
    continued suspension of its claim. Therefore, on May 31, 2019, the deadline for the CO’s
    decision on that claim, she issued a memorandum addressed to Hydraulics whose subject line
    read as follows: “Contracting Officer Final Decision—Certified Claim dated 18 January 2019
    under [the Hydraulics contract].” Compl. 20-598 App. A at 21. In the memorandum, the CO
    rejected Hydraulics’ claim that further payment was due because—even leaving aside the issue
    of Hydraulics’ failure to provide 3D models—the Air Force had not received and approved any
    of the TDPs Hydraulics had submitted. 
    Id. at 24
    .
    The CO then recounted why the agency had rejected the TDPs that Hydraulics had
    submitted before it filed its January 18, 2019 claim, as well as its bases for finding incomplete
    the two revised TDPs Hydraulics submitted while the claim was pending. She also noted that at
    Hydraulics for the service and storage of those units. 
    Id. at 11
    . The parties ultimately settled this
    aspect of Hydraulics’ claim. Compl. 20-598 ¶ 20.
    3
    the meeting between the agency and Hydraulics the day before, Hydraulics had offered to submit
    a third revised TDP on June 20, 2019. 
    Id.
    The CO then opined that “[Hydraulics] is still performing within the terms of the contract
    and payment by the Government for this delivery is pending an acceptable submittal.” 
    Id.
    “[W]ith [Hydraulics] working to resubmit the TDP,” according to the CO, “there is not currently
    a material dispute or issue in controversy.” 
    Id.
     “After re-submittal and the engineering review is
    complete and the TDP is found to meet the criteria established by Air Force for approval,” she
    stated, “payment pursuant to the contract shall be considered.” 
    Id.
     But “[u]ntil that time,” the CO
    concluded, “payment will not be considered” and Hydraulics’ claim would be “denied in full as
    there is no issue in controversy or material dispute.” 
    Id.
    C.      Agency Rejection of Subsequently Submitted TDPs
    On June 20, 2019, Hydraulics submitted its third revised TDP, Pl.’s Resp. App. A at A5,
    which the agency rejected on August 2, 2019, 
    id.
     at A8. The agency found the TDP incomplete
    because, among other reasons, Hydraulics had not included several drawings which it alleged
    were proprietary in nature and therefore not subject to inclusion in the TDP. 
    Id.
    Hydraulics submitted a fourth revised TDP on September 16, 2019. 
    Id.
     at A62–63. The
    agency also found that submission incomplete. Thus, on November 20, 2019, the agency sent
    Hydraulics a “100% TDP submittal final rejection letter,” prepared by an Air Force engineering
    data analyst. 
    Id.
     at A65, A69–70. The letter stated that Hydraulics’ failure to supply the missing,
    allegedly proprietary drawings rendered its submissions fatally deficient. 
    Id.
    D.      Hydraulics’ Appeal to the Court
    On May 13, 2020, Hydraulics filed case number 20-598, which challenges the Air
    Force’s refusal to pay Hydraulics the $784,743.31 it alleges that it is due under CLIN 0005 for
    the TDPs it has submitted (leaving aside the issues concerning the 3D models). See Compl.
    20-598. On May 28, 2020 the Court consolidated case number 20-598 with case number 19-105.
    Order, ECF No. 16.
    The government filed the present motion to dismiss for lack of jurisdiction on September
    28, 2020. Def.’s Mot. to Dismiss (“Def.’s Mot.”), Case No. 20-598, ECF No. 11. Hydraulics has
    filed its response and oral argument was held on the motion on December 3, 2020. ECF Nos. 23,
    26.
    DISCUSSION
    Pursuant to the Tucker Act, the United States Court of Federal Claims may “render
    judgment upon any claim against the United States founded either upon the Constitution, or any
    Act of Congress or any regulation of an executive department, or upon any express or implied
    contract with the United States, or for liquidated or unliquidated damages in cases not sounding
    in tort.” 
    28 U.S.C. § 1491
    (a) (2012). Subsection (a)(2) of section 1491 further grants the Court of
    Federal Claims “jurisdiction to render judgment upon any claim by or against, or dispute with, a
    contractor arising under section 7104(b)(1) of title 41”—that is, the Contract Disputes Act
    4
    (“CDA”), 
    41 U.S.C. §§ 7101
    –7109. The CDA states that a contractor may bring an action de
    novo in federal court “within 12 months from the date of receipt of a contracting officer’s
    decision.” 
    41 U.S.C. § 7104
    (b)(3). Therefore, a party seeking to invoke this court’s jurisdiction
    under the CDA must have first submitted a valid claim to the contracting officer and received the
    contracting officer’s final decision on that claim. M. Maropakis Carpentry, Inc. v. United States,
    
    609 F.3d 1323
    , 1327–28 (Fed. Cir. 2010).
    The government does not deny that Hydraulics filed a valid certified claim on January 18,
    2019 asserting its entitlement to payment of $784,743.31 under CLIN 0005, contending such
    payment was due given the TDPs it had already submitted for the agency’s approval. Nor does it
    deny that while that claim was pending Hydraulics submitted two revised TDPs that the Air
    Force found incomplete and therefore insufficient to trigger the agency’s payment obligation.
    Nonetheless, according to the government, this Court lacks jurisdiction over Hydraulics’
    complaint in case number 20-598 because that claim was allegedly not the subject of a final
    decision by the CO.
    The government’s argument lacks merit for several reasons. For one thing, it is
    inconsistent with the express text of what the government euphemistically calls the “May 2019
    Letter.” See, e.g., Def.’s Mot. at 6. The subject line of the CO’s memorandum of May 31, 2019
    states that it represents the “Contracting Officer Final Decision” on Hydraulics’ January 18, 2019
    claim. Compl. 20-598 App. A at 21. In the body of the memorandum the CO similarly states that
    it is “the final decision of the Contracting Officer.” Id. at 25. In addition, in the memorandum,
    the CO purports to deny Hydraulics’ claims for payment “in full,” including the claim for
    $784,743.31 that is before the Court in case number 20-598. Id. The CO concludes her
    memorandum with standard language advising Hydraulics of its right to appeal her final decision
    to this court or to the agency board of contract appeals. Id.
    The government argues nonetheless that the “May 2019 Letter” was not a final decision
    because in it the CO “expressly discusse[d] additional submissions by [Hydraulics] that the Air
    Force was expecting, which [the agency] would then review to determine if they complied with
    the contract requirements.” Def.’s Mot. at 6–7. In fact, the government notes, the CO stated that
    in light of these planned future submissions, “there is not currently a material dispute or issue in
    controversy.” Id. at 7 (quoting 2019 Contracting Officer Final Decision, Compl. 20-598 App. A
    at 24).
    Of course, the fact that Hydraulics intended to submit yet another revised TDP in an
    effort to satisfy the agency does not bear on whether the CO’s decision finally disposed of its
    claimed entitlement to payment based on the TDPs it had already submitted. Indeed, the
    government acknowledged as much at the oral argument on its motion to dismiss. Oral Arg. at
    5:21–6:02 (stating in response to a question from the Court that it would be “fair to read [the
    CO’s] letter” to have rejected as “inadequate” the TDPs submitted prior to the May 31, 2019
    decision letter). And even had the CO attempted to reserve judgment on Hydraulics’ entitlement
    to payment, that would not be a barrier to this Court’s exercise of jurisdiction; the claim would
    be “deemed” denied in any event because her deadline for deciding the January 18, 2019 claim
    expired as of May 31. Rudolph & Sletten, Inc. v. United States, 
    120 Fed. Cl. 137
    , 143–44
    (2015); see also 
    41 U.S.C. § 7103
    (f)(2). Therefore, the Court has jurisdiction over Hydraulics’
    5
    claim that it is entitled to a payment of $784,743.31 under CLIN 0005, and the government’s
    motion must be denied.
    Finally, the Court notes that (as described above) Hydraulics submitted two further
    revised TDPs after the CO issued her final decision—one on June 20, 2019 and another on
    September 16, 2019. Pl.’s Resp. App. A at A5, A62–63. The Air Force’s engineering analysts
    rejected those packages as incomplete on August 2, 2019 and November 20, 2019 respectively.
    
    Id.
     at A8, A65. At the oral argument on the government’s motion to dismiss, both parties agreed
    that—to avoid future disputes over the scope of the claim before this Court in case number
    20-598—the CO should be given the opportunity to review whether these subsequently
    submitted TDPs trigger the agency’s obligation to make payment to Hydraulics. Oral Arg. at
    17:20–17:44. Therefore, the Court will remand case number 20-598 to the CO for sixty days, for
    the purpose of permitting her to issue a new final decision addressing the impact of the
    subsequently submitted TDPs.
    CONCLUSION
    The government’s motion to dismiss is DENIED. Case No. 20-598, ECF No. 11.
    Additionally, the Court directs the Clerk to terminate the gavel pending next to Plaintiff’s
    response to the government’s motion. Case No. 19-105, ECF No. 23. Consistent with the Court’s
    opinion, the Court shall retain jurisdiction over case number 20-598. The matter of whether any
    of the TDPs submitted since May 31, 2019 trigger the agency’s obligation to pay Hydraulics
    under CLIN 0005 is REMANDED back to the contracting officer for a final decision within
    sixty days of the date of this decision, in accordance with Rule 52.2 of the Rules of the Court of
    Federal Claims. Both cases are STAYED pending that final decision.
    IT IS SO ORDERED.
    s/ Elaine D. Kaplan
    ELAINE D. KAPLAN
    Judge
    6
    

Document Info

Docket Number: 19-105

Judges: Elaine D. Kaplan

Filed Date: 12/15/2020

Precedential Status: Precedential

Modified Date: 12/15/2020