Hvf West, LLC v. United States ( 2020 )


Menu:
  •            In the United States Court of Federal Claims
    No. 19-1308C
    (Filed Under Seal: April 1, 2020)
    (Reissued for Publication: April 22, 2020) *
    *************************************
    HVF WEST, LLC,                      *
    *
    Plaintiff,              *
    *
    v.                                  *               Postaward Bid Protest; Motion for Stay of
    *               Judgment; RCFC 62(d)
    THE UNITED STATES,                  *
    *
    Defendant,              *
    *
    and                                 *
    *
    LAMB DEPOLLUTION, INC.,             *
    *
    Defendant-Intervenor.   *
    *************************************
    E. Sanderson Hoe, Washington, DC, for plaintiff.
    Steven M. Mager, United States Department of Justice, Washington, DC, for defendant.
    Shar Bahmani, Scottsdale, AZ, for defendant-intervenor.
    OPINION AND ORDER
    SWEENEY, Chief Judge
    Defendant-intervenor Lamb Depollution, Inc. (“Lamb”) moves, pursuant to Rule 62(d) of
    the Rules of the United States Court of Federal Claims (“RCFC”), for a stay of the execution of
    the judgment entered by this court on November 26, 2019, pending its appeal. That judgment
    encompassed an injunction of Lamb’s “continuing performance on the contract awarded to Lamb
    pursuant to the solicitation at issue [in this postaward bid protest],” and also directed that the
    *
    The court issued this Opinion and Order under seal on April 1, 2020, and directed the
    parties to submit proposed redactions. The parties filed a status report on April 21, 2020, in
    which they indicate that no material contained in the court’s decision requires
    redaction.
    government “cancel the contract awarded to Lamb.” J. of Nov. 26, 2019. Plaintiff HVF West,
    LLC (“HVF”) opposes Lamb’s motion. 1
    The court has before it Lamb’s motion, HVF’s response brief, and Lamb’s reply brief.
    As explained below, Lamb has not demonstrated that a stay pending appeal is warranted by the
    circumstances of this litigation. For this reason, Lamb’s motion must be denied.
    I. BACKGROUND
    On February 27, 2019, the Defense Logistics Agency Disposition Services (“DLA”)
    issued solicitation A0007598—an invitation for bids for a contract to purchase and destroy
    United States military property in the Tucson area. 2 In the solicitation, the DLA stated that the
    award would “be based on the highest priced, responsive, responsible bidder, and other factors,
    whose bid is the most advantageous to the [United States] Government.” The DLA further
    explained that the Sales Contracting Officer (“SCO”), when making the award decision, would
    consider various elements, including, as relevant here, a bidder’s (1) financial responsibility and
    (2) its treatment, storage, and disposal facility (“TSDF”) plan.
    After reviewing the bids received in response to the solicitation, the SCO notified Lamb
    that it was the apparent highest bidder. The SCO subsequently issued a Notice of Award to
    Lamb. However, on August 28, 2019, HVF filed its protest in this court alleging various errors
    in the SCO’s evaluation of bids.
    As explained in this court’s opinion denying Lamb’s motion for reconsideration, the
    court sustained HVF’s protest on the grounds that the SCO failed to follow the evaluation
    process with respect to the financial responsibility and the TSDF plan criteria. See Recons. Op.
    2. Regarding financial responsibility, the court held that “[u]nder the solicitation, a bidder was
    required to submit its cost projections to be eligible for an award. Because Lamb did not submit
    its cost projections, the SCO failed to follow the terms of the [s]olicitation.”
    Id. (quoting Op.
    21-
    22). The court also addressed the TSDF plan requirement and noted:
    To receive an award, a bidder needed to submit a TSDF plan detailing, among
    other things, its temporary storage facility meeting the requirements of 40 C.F.R.
    § 761.65, its procedures for dealing with polychlorinated biphenyls, and the EPA
    1
    The government also appealed the judgment but has taken no position on Lamb’s
    request for a stay of the execution of the court’s judgment pending appeal.
    2
    The facts recited here are largely taken from the court’s opinion denying Lamb’s
    motion for reconsideration which issued on January 8, 2020 (“Recons. Op.”). Citations to
    underlying documents on the docket have been omitted here but are found in that prior opinion.
    See Recons. Op.; see also HVF W., LLC v. United States, 
    146 Fed. Cl. 451
    (2020) (“HVF II”).
    Additional background facts are provided in the court’s opinion resolving the parties’ cross-
    motions for judgment on the administrative record which issued on November 22, 2019 (“Op.”).
    See Op.; see also HVF W., LLC v. United States, 
    146 Fed. Cl. 314
    (2019) (“HVF I”), appeals
    docketed, Nos. 2020-1414, 2020-1583 (Fed. Cir. Jan. 30, 2020, Mar. 18, 2020).
    -2-
    identification number for its facility. Lamb did not submit such a plan. Because
    Lamb failed to submit the materials necessary to receive a contract, the SCO
    failed to follow the terms of the solicitation when he awarded Lamb a contract.
    Id. (quoting Op.
    22). After concluding that the aforementioned errors were prejudicial,
    the court enjoined the DLA
    from continuing performance on the contract awarded to Lamb pursuant to the
    solicitation at issue in this protest, [and] directed the SCO to cancel the contract
    awarded to Lamb, and further direct[ed] the SCO to either (1) select a new
    awardee from among the existing bidders in accordance with the terms of
    solicitation A0007598 or (2) issue a new solicitation.
    Id. at 3
    (quoting Op. 27). In response to the court’s directives, the DLA issued a stop work order
    for performance under Lamb’s contract and issued a bridge contract solicitation, A0008025.
    Both HVF and Lamb submitted bids for the bridge contract, which had not been awarded as of
    the time Lamb’s reply brief was filed.
    Both Lamb and the United States have appealed the court’s rulings in this matter. 
    See supra
    nn.1-2. The court observes that Lamb has not moved swiftly when it has brought its
    objections to the injunction to the court’s attention. HVF I issued under seal on November 22,
    2019, then judgment issued on November 26, 2019, but it was not until December 24, 2019, that
    Lamb filed its motion for reconsideration. HVF II issued under seal on January 8, 2020. Lamb
    did not file its notice of appeal until January 24, 2020, over two weeks later. After an additional
    delay of over one month, Lamb filed its motion for a stay of the execution of the judgment
    pending appeal on February 27, 2020. Lamb’s motion is fully briefed and ripe for decision.
    II. STANDARD OF REVIEW
    “Unless a court issues a stay, a trial court’s judgment . . . normally takes effect despite a
    pending appeal.” Coleman v. Tollefson, 
    135 S. Ct. 1759
    , 1764 (2015). A stay of execution of a
    judgment pending appeal “‘is an intrusion into the ordinary processes of administration and
    judicial review,’ and accordingly ‘is not a matter of right, even if irreparable injury might
    otherwise result to the appellant.’” Nken v. Holder, 
    556 U.S. 418
    , 427 (2009) (quoting Virginian
    R. Co. v. United States, 
    272 U.S. 658
    , 672 (1926); Virginia Petroleum Jobbers Assn. v. FPC, 
    259 F.2d 921
    , 925 (C.A.D.C. 1958) (per curiam)). Therefore, courts should not “reflexively hold[] a
    final order in abeyance pending review.”
    Id. Nevertheless, it
    is well settled that the power to
    stay execution of a judgment pending appeal is “part of [a court’s] traditional equipment for the
    administration of justice.” Scripps-Howard Radio v. FCC, 
    316 U.S. 4
    , 9-10 (1942).
    Pursuant to Rule 8 of the Federal Rules of Appellate Procedure, a motion to stay
    execution of the trial court’s judgment pending appeal ordinarily must be filed in the trial court
    first. See Fed. R. App. P. 8(a)(1)(A); see also Wolfchild v. United States, 
    108 Fed. Cl. 578
    , 583
    (2013) (“Notwithstanding the pendency of an appeal, a motion for stay should first be filed in the
    trial court.”). A stay pending appeal has been described as an extraordinary remedy and is not
    often granted. E.g., Lawson Envtl. Servs., LLC v. United States, 
    128 Fed. Cl. 14
    , 17 (2016);
    -3-
    Turner Constr. Co. v. United States, 
    94 Fed. Cl. 586
    , 589 (2010). If the trial court denies the
    motion, the applicant may seek the same relief in the appellate court. Fed. R. App. P.
    8(a)(2)(A)(2).
    In entertaining a motion under RCFC 62(d), the court considers four factors: (1) whether
    the moving party has made a strong showing that it is likely to succeed on the merits; (2) whether
    the moving party will be irreparably injured absent the requested relief; (3) whether the requested
    relief will substantially injure the other parties interested in the proceeding; and (4) the public
    interest. Hilton v. Braunskill, 
    481 U.S. 770
    , 776 (1987); Standard Havens Prods., Inc. v. Gencor
    Indus., Inc., 
    897 F.2d 511
    , 512 (Fed. Cir. 1990); Alaska Cent. Express, Inc. v. United States, 
    51 Fed. Cl. 227
    , 229 (2001). The court need not assign each factor equal weight. Standard 
    Havens, 897 F.2d at 512
    .
    Consequently, relief is appropriate where the moving party “‘establishes that it has a
    strong likelihood of success on appeal, or where, failing that, it can nonetheless demonstrate a
    substantial case on the merits,’ provided the other factors militate in [its] favor.”
    Id. at 513
    (quoting 
    Hilton, 481 U.S. at 778
    ). When the equitable factors weigh decidedly in the moving
    party’s favor, “it will ordinarily be enough that the [moving party] has raised questions going to
    the merits so serious, substantial, difficult and doubtful, as to make them a fair ground for
    litigation.”
    Id. (quoting Hamilton
    Watch Co. v. Benrus Watch Co., 
    206 F.2d 738
    , 740 (2d Cir.
    1953)); accord Alaska 
    Cent., 51 Fed. Cl. at 230
    (“[I]f the equities weigh heavily in favor of
    maintaining the status quo, this court may grant an injunction under RCFC 62([d]) where the
    question raised is novel or close, especially when the case will be returned to the trial court
    should the movant succeed.”).
    III. ANALYSIS
    A. Likelihood of Success on the Merits
    The court first considers whether Lamb is likely to succeed on the merits of its appeal or
    has, at least, a substantial case on the merits. Regarding its appeal, Lamb argues that it need only
    prevail on one of its three arguments contesting this court’s resolution of HVF’s protest, which
    are as follows: (1) the DLA’s contract award to Lamb did not fall within this court’s bid protest
    jurisdiction; (2) HVF lacked standing to bring this protest; and (3) the SCO’s evaluation of
    Lamb’s bid was rational. Generally, Lamb contends that it has made a strong showing of likely
    success on appeal or, at least, a substantial case on the merits.
    While the court would agree that any one of Lamb’s principal arguments, if successful,
    would be sufficient to invalidate the court’s reasons for entering the injunction in favor of HVF
    in November 2019, the court cannot agree that Lamb has made a strong showing of likelihood of
    success, or even a substantial case on the merits, for its appeal to the United States Court of
    Appeals for the Federal Circuit (“Federal Circuit”). Thus, as explained below, the first factor to
    be weighed regarding the issuance of a stay pending appeal in this matter weighs against Lamb.
    The court addresses each of Lamb’s arguments against the court’s injunction of performance
    under Lamb’s contract in turn.
    -4-
    1. Jurisdiction
    HVF’s protest of the DLA’s contract award to Lamb was within this court’s jurisdiction
    “because the resulting contract from the [A0007598] solicitation at issue was for a mixed
    transaction—the awardee would be buying property from the government while also providing a
    non-de minimis [removal and destruction of military equipment] service to the government.”
    Op. 12. Lamb raises three principal arguments which, in its view, invalidate the jurisdictional
    ruling of this court. 3
    First, Lamb argues that a close reading of the solicitation shows that Lamb’s contract
    primarily involved the sale to Lamb of scrap military equipment, with only a de minimis service
    of demilitarization and/or mutilation. This court analyzed the A0007598 solicitation, however,
    and applied the mixed transaction test described in NASA-Reconsideration, B-408823.2, 2014
    CPD ¶ 147 (Comp. Gen. May 8, 2014). The court remains convinced that the mixed transaction
    test is valid and that under this test, the DLA contract with Lamb was a mixed transaction that
    brings HVF’s protest within this court’s jurisdiction over protests of procurement contracts.
    Indeed, nothing in Lamb’s motion or its reply brief presents a more persuasive analysis of the
    nature of the A0007598 solicitation. 4
    Second, Lamb argues that this court’s application of the mixed transaction test in NASA-
    Reconsideration presents a matter of first impression that warrants a stay pending appeal so that
    the Federal Circuit can resolve Lamb’s “substantial case on the merits.” Mot. 8. But as Lamb
    notes, the mixed transaction test is buttressed by Government Accountability Office (“GAO”)
    decisions dating from 1987 through 2014, which hardly makes the instant case a matter of first
    impression. Nothing in Lamb’s motion or reply brief justifies the rejection of the GAO’s mixed
    transaction test or a stay founded on Lamb’s arguments against this court’s jurisdictional
    holding. 5
    Third, Lamb cites a variety of decisions by the GAO and this court in an attempt to
    3
    The court has considered all of Lamb’s arguments. To the extent that a cursory
    argument is not addressed in this opinion it was deemed to be unpersuasive.
    4
    Lamb’s reliance on language in the A0008025 solicitation, which was created by DLA
    as a replacement contracting vehicle once the court enjoined Lamb’s performance under the
    A0007598 solicitation, is unhelpful. As Lamb points out in its reply brief, contract requirements
    that were the focus of the court’s rejection of the award of the contract to Lamb were modified or
    eliminated in the bridge contract solicitation. See Reply 15 n.10.
    5
    Lamb’s reliance on PDS Consultants, Inc. v. United States, 
    133 Fed. Cl. 810
    (2017)
    (“PDS II”), is misplaced. The underlying bid protest opinion in that matter, PDS Consultants,
    Inc. v. United States, 
    132 Fed. Cl. 117
    (2017), aff’d, 
    907 F.3d 1345
    (Fed. Cir. 2018), resolved a
    conflict between different statutory preference schemes applicable in government contracting.
    All parties in that case agreed that a stay pending appeal was warranted to ensure that the Federal
    Circuit could provide guidance on a matter of first impression. PDS 
    II, 133 Fed. Cl. at 817
    . PDS
    II addressed a rare circumstance that bears no resemblance to the request for a stay currently
    before the court.
    -5-
    undermine the court’s reliance on and application of the mixed transaction test described in
    NASA-Reconsideration. The court disagrees with Lamb’s conclusion that the cited decisions are
    more persuasive in this matter than NASA-Reconsideration. The court agrees, instead, with
    HVF’s contention that some of this precedent was considered, and rightly rejected, in HVF I, and
    that most of the new decisions cited by Lamb are inapposite. The court will briefly address two
    decisions upon which Lamb places the most emphasis.
    Lamb attempts to show, by citing various excerpts of Resource Recovery International
    Group, Inc., B-265880, 95-2 CPD ¶ 277 (Comp. Gen. Dec. 19, 1995) (“RRIG”), that the GAO
    has already decided that contracts such as Lamb’s contract with the DLA have only a de minimis
    demilitarization component and thus are not mixed transactions. But as this court previously
    noted, the mixed transaction test is not mentioned in RRIG, and the fundamental jurisdictional
    question in this bid protest was not an issue in RRIG. Op. 12 & n.10. The court observes that
    the GAO explicitly noted in RRIG that its review of DLA sales contracts was established not by
    any jurisdictional test but by consent provided by DLA in a letter dated January 13, 1987. RRIG,
    95-2 CPD ¶ 277 n.1. RRIG does not contradict or undermine the jurisdictional analysis
    conducted by this court in HVF I.
    Lamb also relies on a GAO decision regarding a protest brought by a disappointed bidder
    for a scrap metal sales contract with the United States Department of the Army, Army Materiel
    Command, Santa Rita, LLC, B-411467.2, 2015 CPD ¶ 222 (July 20, 2015). Santa Rita does not
    help Lamb. First, in Santa Rita the GAO employed the mixed transaction test, which is further
    authority for the use of the test in this bid protest. Second, as HVF points out, the scrap metal
    sales contract in Santa Rita was very different in character, and much less demanding as to the
    awardee’s responsibilities, than was the case in Lamb’s contract with the DLA. These
    differences distinguish Santa Rita, where the GAO declined jurisdiction over the protest because
    the scrap sales contract in that competition was not a mixed transaction. Having considered
    RRIG and Santa Rita, and the other authorities relied upon by Lamb, the court is not persuaded
    that Lamb has a substantial case on appeal to argue that this court lacked jurisdiction over HVF’s
    bid protest.
    2. HVF’s Standing
    Lamb’s second challenge relates to HVF’s standing to protest. In the context of a
    postaward bid protest, the plaintiff must establish that there was a substantial chance it would
    have received the contract but for the procuring agency’s errors. Info. Tech. & Applications
    Corp. v. United States, 
    316 F.3d 1312
    , 1319 (Fed. Cir. 2003) (“ITAC”) (citing Alfa Laval
    Separation, Inc. v. United States, 
    175 F.3d 1365
    , 1367 (Fed. Cir. 1999)). In other words, a
    protestor has standing if, but for the agency’s errors, it could compete for the award. Impresa
    Construzioni Geom. Domenico Garufi v. United States, 
    238 F.3d 1324
    , 1334 (Fed. Cir. 2001)
    (citing Alfa 
    Laval, 175 F.3d at 1367
    ). Here, the court found that HVF had standing because it
    was a strong competitor for award of the contract with the DLA if the award to Lamb was set
    aside. Op. 14.
    Lamb raises two arguments challenging the court’s holding on standing. First, Lamb
    argues that the only appropriate test for standing in the circumstances of this contract award is
    -6-
    the test used in United States v. International Business Machines Corp., 
    892 F.2d 1006
    (Fed. Cir.
    1989) (“IBM”), and that under the IBM test, HVF did not possess standing to bring its bid
    protest. Second, Lamb argues that even if IBM does not provide the appropriate test for
    standing, HVF’s fourth-place ranking on price shows that HVF did not possess standing to bring
    its suit. The court addresses each argument in turn.
    In its opinion resolving the parties’ cross-motions for judgment on the administrative
    record, the court thoroughly considered IBM and concluded that the standing test therein (for
    sealed bid competitions where bids differ only as to price) was not applicable in this mixed
    transaction sales contract competition because nonprice factors would be evaluated by the DLA
    along with price when making an award under the A0007598 solicitation. Op. 13-14. In the
    background section of the opinion, the court examined the instructions to bidders in the
    solicitation, which was not a model of clarity, and noted several instances where nonprice factors
    would be considered by the DLA.
    Id. at 3
    -6. Based on these elements of the solicitation, and its
    consideration of IBM and other relevant precedent, the court determined that this competition
    was not governed by the standing test in IBM. Nothing in Lamb’s motion or reply brief
    convinces the court that the solicitation, which governed the mixed transaction competition in
    this protest, should be read to establish a competition that falls within the IBM line of precedent. 6
    Lamb also contends that HVF fails the test for standing provided by precedent binding on
    this court, even if IBM is determined not to be applicable. According to Lamb, HVF’s ranking
    on price was too far below that of Lamb. Lamb concludes that HVF did not have a direct
    economic interest in the competition, i.e., did not have a substantial chance of receiving the
    contract award, and thus lacked standing to bring its bid protest.
    The court disagrees. HVF met the appropriate test for standing because it was in a
    position to compete for the award if the award to Lamb was found to be erroneous. A protestor
    need not be next in line for award if the allegations in the complaint point to a substantial chance
    that the awardee and other competitors were incorrectly ranked as superior to the protestor. E.g.,
    Raymond Express Int’l, LLC v. United States, 
    124 Fed. Cl. 79
    , 87 (2015) (citing 
    ITAC, 316 F.3d at 1319
    ). The court concludes that Lamb does not have a substantial case on appeal supporting
    its position that HVF lacked standing to bring its bid protest.
    3. Evaluation of Lamb’s Proposal
    Lamb’s third challenge relates to the merits of HVF’s protest. When the court reached
    the merits of HVF’s protest, it found two aspects of the evaluation of Lamb’s bid, regarding
    Lamb’s financial responsibility and its TSDF plan, to be inconsistent with the solicitation and
    irrational. Op. 21-23. These findings of irrationality are now contested by Lamb. Further,
    Lamb argues that these protest grounds were waived by HVF because they were not raised in
    HVF’s earlier protests before the agency and the GAO. The court will address the waiver issue
    6
    The court held, in addition, that even if the IBM test for standing were applied to
    HVF’s protest, the test was satisfied because in its complaint HVF adequately challenged all of
    the bidders with a higher bid price. Op. 14 n.11 (citing 
    IBM, 892 F.2d at 1010-11
    ).
    -7-
    before turning to the specific topics of Lamb’s financial responsibility and its TSDF plan. First,
    however, the court considers whether Lamb is correct when its asserts that it had no obligation to
    submit required information in writing in support of its showing of financial responsibility and
    an adequate TSDF plan.
    Both the financial responsibility and TSDF plan criteria are found in the “Criteria used
    for Award” section of the solicitation. Administrative R. (“AR”) 188-89. There is no indication
    in the solicitation that these criteria could be satisfied by informal, undocumented telephone
    conversations or the assumptions of the SCO based on a bidder’s track record with the agency.
    Instead, this section of the solicitation is replete with references to information that would be
    provided by the bidder in written form.
    The following excerpts are typical of this solicitation section, and show that written
    documentation was the norm for satisfying these evaluation criteria: (1) “Identification and
    description of at least one temporary storage facility . . . .”; (2) “The procedures for
    identification, removal, treatment and temporary storage of regulated [polychlorinated biphenyl]
    items.”; (3) “The Environmental Protection Agency (EPA) identification number of the facility
    where demilitarization, mutilation and remediation is to be accomplished.”; (4) “Evidence of an
    established working relationship with the transporters and disposal facilities identified. If an
    existing relationship does not exist, the bidder should provide written evidence of the
    transporters or disposal facility willingness to provide subcontracting services under this
    Auction.”; (5) “Provide evidence of availability of [processing] facilities for the duration of the
    period of performance, either by ownership and existing lease or by letter from the facility
    owners . . . .”; (6) “Provide a cost projection with regard to each contract operation, i.e.,
    transporting, storage, [Demilitarization/]Mutilation, sales, and hazardous material and waste
    disposal. The cost projections must be itemized.”; (7) “[P]rovide evidence that the capital is
    available to cover projected costs. This may be in the form of a letter of intent from a financial
    institution or an itemized certified financial statement.”; and (8) “Documentation on the bidder’s
    training program sufficient to demonstrate compliance with [various laws and regulatory
    requirements].”
    Id. at 188.
    A successful bidder, in view of these directives in the solicitation,
    was required to provide, in writing, documents that would satisfy the financial responsibility and
    TSDF plan evaluation criteria.
    Lamb argues, nonetheless, that nothing in the solicitation required it to respond to the
    financial responsibility and TSDF plan evaluation criteria in writing. That reading is not a
    logical interpretation of the solicitation sections that address a bidder’s financial responsibility
    and TSDF plan, which are discussed in more detail below. Nor does Lamb’s proposition
    comport with the solicitation, when that document is considered as a whole, because the types of
    information to be submitted to and considered by the DLA were, almost exclusively, written
    materials. See, e.g., Magnus Pac. Corp. v. United States, 
    133 Fed. Cl. 640
    , 681 (2017) (“It is a
    well-established principle of government contract law that solicitation terms must be considered
    as a whole to discern their meaning.” (citing Merando, Inc. v. United States, 
    475 F.2d 603
    , 605
    (Ct. Cl. 1973))). The court concludes that Lamb was not excused from providing to the DLA, in
    writing, materials substantiating its financial responsibility and its TSDF plan.
    -8-
    a. Waiver
    Turning now to the waiver issue, Lamb argues, as it has before, that HVF waived all
    protest grounds that were not raised in earlier protests. Lamb cites no statutory or regulatory
    authority for its waiver argument. Further, only one of the decisions cited by Lamb is from a bid
    protest, and that case involved not an agency-level protest or a GAO protest, but a proceeding
    before the Office of Hearing and Appeals (“OHA”) of the Small Business Administration
    (“SBA”). In that quite different set of circumstances, this court found waiver based on both the
    “unique expertise of the SBA” and Federal Circuit precedent that requires protestors to first
    exhaust certain administrative remedies at the OHA before seeking relief in this court. See Team
    Waste Gulf Coast, LLC v. United States, 
    135 Fed. Cl. 683
    , 688-89 (2018) (citing Palladian
    Partners, Inc. v. United States, 
    783 F.3d 1243
    , 1257-61 (Fed. Cir. 2015)).
    The court finds that Lamb’s waiver argument is entirely unsupported by relevant
    authority. For the reasons stated in this court’s prior ruling, the fact that HVF did not pursue the
    same arguments in earlier protests before the agency and the GAO as it does here does not
    constitute waiver of those protest grounds. See Op. 22 (citing Sotera Defense Solutions, Inc. v.
    United States, 
    118 Fed. Cl. 237
    , 255 n.8 (2014), for the rule that new protest grounds may be
    raised in this court after an unsuccessful GAO protest); HVF Resp. 8 n.5 (citing additional
    authority for this rule). Lamb has not presented a substantial case in support of its waiver
    argument.
    b. Financial Responsibility
    With respect to Lamb’s contentions regarding the financial responsibility criteria, the
    court begins its discussion with a review of the evolution of Lamb’s arguments on this topic
    during this protest. In its motion for judgment on the administrative record filed on October 16,
    2019, Lamb relied solely on the administrative record to contend that the written documents it
    submitted to the DLA were sufficient to show financial responsibility pursuant to the evaluation
    criteria stated in the solicitation, and that the DLA’s relaxation of the requirement for the
    submission of cost projections was, at most, a de minimis procurement error unworthy of judicial
    relief. Over two months later, in its motion for reconsideration filed on December 24, 2019, it
    went beyond the administrative record and attached a declaration from Greg S. Lamb, president
    and owner of the company. In his declaration, Mr. Lamb stated that “it would have taken Lamb
    approximately 2-3 hours to draft and finalize a cost projection summarizing anticipated
    operations in connection with the Tucson [DLA contract].” Lamb Dec. 23, 2019 Decl. ¶ 20. Mr.
    Lamb also stated that Lamb had significant experience on another DLA contract in Texarkana,
    and that Lamb had communicated to the SCO its intention to perform the Tucson DLA contract
    in the same manner as the Texarkana DLA contract.
    Id. ¶¶ 5,
    7-11. Largely based on Mr.
    Lamb’s declaration, Lamb argued that the SCO reasonably concluded that Lamb was financially
    responsible.
    The court concluded that reconsideration was not warranted on the basis of evidence that
    Lamb could have provided earlier, but did not. Recons. Op. 4. The court also held that nothing
    in this new evidence showed that the SCO’s evaluation and award conformed to solicitation
    requirements, which explicitly required cost projections from the successful bidder.
    Id. Thus, -9-
    the court affirmed its holding that Lamb had not met the financial responsibility requirements
    and that the award of the contract to Lamb was irrational.
    Since December 24, 2019, Lamb’s arguments regarding financial responsibility have
    remained the same, with Lamb relying on an updated version of Mr. Lamb’s declaration. See
    Lamb Feb. 21, 2020 Decl. ¶¶ 5, 7-11, 20. In its motion for a stay pending appeal filed on
    February 27, 2020, which might be described as Lamb’s third bite at the apple on the issue of
    financial responsibility, Lamb reasserts its argument that the SCO reasonably concluded that
    Lamb was financially responsible. The court observes, however, that notwithstanding the
    evidence presented by Lamb more than four months after Lamb’s motion for judgment on the
    administrative record was due, “the SCO could only award a contract to a bidder who submitted
    cost projections, which Lamb did not do.” Recons. Op. 4. The award of the contract to Lamb
    was contrary to the solicitation and irrational, and was properly enjoined by this court. Lamb has
    not made a substantial case on the financial responsibility issue currently on appeal to the
    Federal Circuit.
    c. TSDF Plan
    The evolution of Lamb’s arguments regarding the sufficiency of its TSDF plan
    submissions to the DLA bear many similarities to Lamb’s evolving position on the issue of
    financial responsibility. In its motion for judgment on the administrative record filed on October
    16, 2019, Lamb relied on four pages of the administrative record, AR 70, 148, 188, 253, to
    contend that the written documents it submitted were sufficient to satisfy the TSDF plan
    requirement. In Lamb’s motion for reconsideration filed on December 24, 2019, Lamb went
    beyond the administrative record and attached three declarations—from the president, vice
    president and general manager of the company. These declarations, and the narrative in Lamb’s
    motion for reconsideration, attempt to show that through email messages, telephone
    conversations, and site visits, the DLA obtained sufficient information to satisfy Lamb’s TSDF
    plan requirement.
    The court concluded that reconsideration was not warranted on the basis of evidence that
    Lamb could have provided earlier, but did not. Recons. Op. 4. The court also held that nothing
    in this new evidence showed that the SCO’s evaluation and award conformed to solicitation
    requirements “because, pursuant to the terms of the solicitation, a bidder could only be an
    awardee if it identified a [TSDF] meeting the requirements set forth in” 40 C.F.R. § 761.65.
    Id. Thus, the
    court affirmed its holding that Lamb had not met the TSDF plan requirement and that
    the award of the contract to Lamb was irrational.
    Since December 24, 2019, Lamb’s arguments regarding the TSDF plan have remained
    the same, with Lamb relying on an updated version of Mr. Lamb’s declaration, as well as the
    same December 2019 declarations proffered from the vice president and general manager of
    Lamb. In its motion for a stay pending appeal filed on February 27, 2020, Lamb reasserts its
    argument that the SCO reasonably concluded that Lamb satisfied the TSDF plan requirement.
    The court observes, however, that notwithstanding the evidence presented by Lamb at this late
    date, Lamb’s submission of information regarding its TSDF plan fell short of the solicitation’s
    requirements. The award of the contract to Lamb was contrary to the solicitation and irrational,
    -10-
    and was properly enjoined by this court. Lamb has not made a substantial case regarding the
    sufficiency of its TSDF plan submission for its appeal to the Federal Circuit.
    B. Irreparable Harm
    Having found that Lamb is not likely to succeed in its appeal, and that Lamb does not
    have a substantial case for its appeal, the court now considers whether Lamb will suffer
    irreparable harm absent a stay of the execution of the court’s judgment. Irreparable harm is only
    present if the stay applicant “will be denied any meaningful relief if its motion is denied and it
    should ultimately prevail.” Minor Metals, Inc. v. United States, 
    38 Fed. Cl. 379
    , 381 (1997).
    This court has stated that “[o]nly economic loss that threatens the survival of a movant’s
    business constitutes irreparable harm.” Sierra Military Health Servs., Inc. v. United States, 
    58 Fed. Cl. 573
    , 582 (2003) (quoting Found. Health Fed. Servs. v. United States, No. 93-1717, 
    1993 WL 738426
    , at *3 (D.D.C. Sept. 23, 1993)). In a patent infringement case, the Federal Circuit in
    Standard Havens equated “employee layoffs, immediate insolvency, and, possibly, extinction”
    with irreparable 
    harm. 897 F.2d at 515
    . In its motion, Lamb describes the financial impacts of
    the court’s November 2019 injunction on its business in exactly these terms.
    It is important to note, however, that Lamb is responsible, in part, for the imposition of
    the injunction. None of the financial distress faced by Lamb, were the court to rule in favor of
    HVF’s request for an injunction, was discussed by Lamb in its motion for judgment on the
    administrative record. Recons. Op. 4 & n.2. The court weighed the factors for granting
    injunctive relief in the absence of input from Lamb on this topic. Lamb’s irreparable injury, as
    alleged, is partly of its own making.
    The court notes, too, that Lamb states in its reply brief that it is actively being considered
    for the award of the bridge contract; indeed, Lamb indicates that it is now the putative awardee
    pending verification of its responsibility. Although Lamb suggests that its bridge contract bid
    price is far less advantageous to Lamb, and that there is uncertainty as to whether Lamb will
    actually receive the award, the prospects of receipt of the financial benefits of the bridge contract
    mitigate the impact of the court’s injunction on Lamb’s financial health and survival as a
    business entity. 7 The court concludes, nonetheless, that Lamb has identified at least some
    irreparable financial injury that weighs in favor of its request for a stay of judgment pending
    appeal.
    C. Substantial Injury to Other Parties
    The third factor that the court must consider in determining whether to stay the execution
    of its judgment pending appeal is whether such a stay would substantially injure the other parties.
    Because the United States has not filed a brief responding to Lamb’s motion, there is no
    identified injury to the DLA should a stay issue, although both Lamb and HVF speculate as to
    the advantages and disadvantages that a stay might provide the government. As for HVF, its
    7
    The third exhibit attached to Lamb’s reply brief states that it is Lamb Fuels, Inc., not
    Lamb Depollution, Inc., that has bid on the bridge contract. In its brief, Lamb treats these
    entities as the same business concern.
    -11-
    prospects for award of the bridge contract appear slim, if Lamb’s reply brief presents an accurate
    picture of the status of that competition. Given the nature of the information currently before the
    court, no substantial injury to the other parties has been identified in the event that the court
    should stay its judgment pending appeal. This factor, too, weighs in favor of Lamb’s request.
    D. Public Interest
    The fourth and final factor concerns the public interest. Here, HVF has the stronger
    argument. The court issued the injunction because the DLA did not follow the terms of the
    solicitation in its award to Lamb. The injunction in this case thus serves to preserve the fairness
    of competition for government contracts. This is not of minor import; indeed, this is the function
    of the court’s bid protest jurisdiction. See, e.g., Red River Holdings, LLC v. United States, 
    91 Fed. Cl. 621
    , 628 (2010) (stating that “the public interest is best served when procurement errors
    are rectified and the award is made to the correct contractor in accord with the contract
    solicitations and the award criteria”). The fourth factor weighs against the issuance of a stay of
    the execution of this court’s judgment pending appeal.
    E. Weighing of the Factors
    Having considered each of the factors applicable to a stay of the execution of its
    judgment pending appeal, the court must weigh the factors against one another. Standard
    
    Havens, 897 F.2d at 513
    . The court must “weigh[] the equities as they affect the parties and the
    public.” E.I. DuPont de Nemours & Co. v. Phillips Petroleum Co., 
    835 F.2d 277
    , 278 (Fed. Cir.
    1987). When the movant fails to demonstrate a strong likelihood of success on appeal, a stay
    pending appeal is appropriate when the applicant presents a substantial case and the balance of
    hardships tips in its favor. Standard 
    Havens, 897 F.2d at 512
    -13; Alaska 
    Cent., 51 Fed. Cl. at 230
    . Here, however, Lamb does not present even a substantial case on the merits, nor do the
    other factors, when considered together, tip the balance in Lamb’s favor.
    The court notes, for example, that the degree of irreparable monetary injury to Lamb is
    somewhat uncertain, given Lamb’s status as putative awardee of the bridge contract. The court
    notes, too, that Lamb’s own actions have contributed to both the imposition of the injunction, 
    see supra
    Section III.B, and to the urgency of its request for a stay pending appeal, because Lamb
    repeatedly delayed the filing of its motions to obtain relief from the injunction. By Lamb’s own
    count, it waited seven weeks to seek a stay pending appeal. These actions, along with the public
    interest factor, tip the balance of the equities against Lamb. See Lawson 
    Envtl., 128 Fed. Cl. at 19
    (discounting an assertion of irreparable harm where the movant delayed the filing of its
    motion seeking a stay pending appeal).
    Even if the court were to conclude that the irreparable injury to Lamb tips the balance of
    the second, third, and fourth factors in Lamb’s favor, a conclusion not endorsed by the court
    here, there would not be sufficient justification for a stay pending appeal. Finding that the
    balance of harms weighs in the applicant’s favor, standing alone, is insufficient to support a stay
    pending appeal. When, for the purpose of its analysis, a court finds that the balance of harms is
    favorable to a stay applicant, the movant’s substantial case on the merits may permit the court to
    enter a stay. Standard 
    Havens, 897 F.2d at 512
    -13. In other words, the first factor—likelihood
    -12-
    of success or, at a minimum, substantial case—is essential.
    Id. Unfortunately for
    Lamb, it has
    not demonstrated even a substantial case on the merits. Since more than a possibility of relief on
    appeal is required, 
    Nken, 556 U.S. at 434
    , the first factor, alone, prevents Lamb from obtaining a
    stay pending appeal in this matter.
    IV. CONCLUSION
    For the reasons discussed above, the court DENIES Lamb’s motion for a stay of the
    execution of the court’s judgment pending appeal.
    The court has filed this ruling under seal. The parties shall confer to determine proposed
    redactions to which all the parties agree. Then, by no later than Friday, April 17, 2020, the
    parties shall file a joint status report indicating their agreement with the proposed redactions,
    attaching a copy of those pages of the court’s ruling containing proposed redactions, with
    all proposed redactions clearly indicated. The parties also shall, by the same date, file any
    redacted versions of documents they filed under seal in this case to the extent such redacted
    versions have not already been filed.
    IT IS SO ORDERED.
    s/ Margaret M. Sweeney
    MARGARET M. SWEENEY
    Chief Judge
    -13-