Ampersand Chowchilla Biomass, LLC v. United States ( 2020 )


Menu:
  •          In the United States Court of Federal Claims
    No. 14-841C
    (Filed Under Seal: October 30, 2020)
    (Reissued: November 9, 2020) 1
    **************************
    *
    AMPERSAND CHOWCHILLA     *                                  American        Recovery       and
    BIOMASS, LLC, and MERCED *                                  Reinvestment Act (“ARRA”); Pub.
    POWER, LLC,              *                                  Law. No. 111-5, Div. B, tit. I, §
    *                                  1603, 123 Stat. 115, 364-66 (2009);
    Plaintiffs,    *                                  Section 1603 Grant; Open-Loop
    *                                  Biomass Facility; Specifically
    v.             *                                  Assigned Function; Oglethorpe
    *                                  Factors; Placed in Service;
    THE UNITED STATES,       *                                  Statutory Interpretation.
    *
    Defendant.     *
    *
    **************************
    Stephen G. Leatham, Heurlin, Potter, Jahn, Leatham, Holtmann & Stoker, P.S., 211 E.
    McLoughlin Blvd., Suite 100, Vancouver, Washington 98663, for Plaintiffs.
    Richard E. Zuckerman, David I. Pincus, G. Robson Stewart, Courtney M. Hutson, Margaret
    E. Sheer, and Katherine R. Powers, U.S. Department of Justice, Tax Division, Court of Federal
    Claims Section, P.O. Box 26, Ben Franklin Station, Washington, D.C. 20044, for Defendant.
    _________________________________________________________
    OPINION AND ORDER
    _________________________________________________________
    WILLIAMS, Senior Judge.
    In this action, Plaintiffs Ampersand Chowchilla Biomass, LLC (“Chowchilla LLC”) and
    Merced Power, LLC (“Merced LLC”) challenge the Government’s denial of grants under Section
    1603 of the American Recovery and Reinvestment Act of 2009 (“ARRA”). This statute, which has
    since expired, provided grants to entities that “place[d] in service specified energy property” in
    2009, 2010, or 2011. Pub. Law. No. 111-5, Div. B, tit. I, § 1603, 123 Stat. 115, 364-66 (2009).
    Each Plaintiff owns an open-loop biomass facility which qualified as a specified energy property
    1
    The Court issued its Opinion under seal to provide the parties an opportunity to submit
    redactions. The parties did not propose any redactions. Accordingly, the Court publishes this
    Opinion.
    under the ARRA (“the Facilities”). Plaintiff Chowchilla LLC sought a grant of $12,282,984, and
    Merced LLC, a grant of $12,299,723. The United States Department of Treasury, which
    administered the Section 1603 program, denied a substantial portion of these grants, finding that
    Plaintiffs’ Facilities had been “placed in service” in 2008—outside the 2009-11 statutory window.
    Under Treasury Regulations, a facility is placed in service when it is “in a condition or state
    of readiness and availability for a specifically assigned function.” Treas. Reg. § 1.46-3(d)(1)(ii).
    Plaintiffs allege the Facilities were placed in service on August 11, 2011, when the Facilities had
    passed all required testing, installed all necessary equipment, were compliant with environmental
    laws, and were selling baseload electricity at amounts required by their Power Purchase Agreements
    (“PPAs”) with Pacific Gas & Electric Company (“PG&E”). Defendant claims that the Facilities
    were placed in service in 2008, when the Facilities’ prior owners substantially completed their
    refurbishment, acquired permits from the San Joaquin Valley Air Pollution Control District, and
    were producing and selling power and generating revenue.
    This Court finds that both Facilities were ready and available to perform their specifically
    assigned function—to produce and sell electricity—in 2008, when the Facilities had synchronized
    to the transmission grid, began selling electricity, operated under their PPAs, and generated
    approximately $2.26 million in revenue. Although the Facilities did not operate at high capacity
    and suffered from emissions violations, these performance problems did not lead to termination of
    their PPAs with PG&E or cessation of the Facilities’ role as a supplier of electricity. In short, the
    Facilities’ specifically assigned function was to produce and sell electricity, and the Facilities were
    ready and available to do so in 2008, precluding their owners from obtaining additional Section
    1603 grants.
    Findings of Fact 2
    The Biomass Facilities
    The Chowchilla Facility (“Chowchilla”) and Merced Facility (“Merced”) are open-loop
    biomass facilities, each with a nameplate capacity of 12.5 megawatts. Jt. Stip. ¶ 10; JX 40 at 1; JX
    32-4. An open-loop biomass facility generates electricity by using various types of organic waste
    as fuel. Tr. 1158-59. Chowchilla and Merced use a mix of agricultural and urban wood waste. Tr.
    1159.
    Producing electricity with biomass is a thornier operation than producing electricity with
    most other fuels. Tr. 1658. Unlike other fuels, a biomass fuel load consists of a hodge-podge of
    organic materials, including orchard prunings, scrap lumber, sawdust, and construction debris. Tr.
    1158-59, 1664; JX 32-4. This variety makes the precise composition of a given fuel load
    unpredictable, making it difficult to maintain consistent operations and to control emissions. Tr.
    934-35, 1579-80, 1664. The Facilities connect to an electric transmission grid overseen by the
    California Independent System Operator (“CAISO”) and operated by PG&E. Tr. 193-94.
    Biomass facilities are equipped with emissions-control technology. Burning of wood waste
    produces pollutants such as nitrous oxide (“NOx”) and, depending on the composition of the waste,
    2
    These findings are derived from the evidentiary record developed during an 11-day trial.
    Grammatical and typographical errors in quotations have not been corrected.
    2
    sulfur oxide (“SO2”). Tr. 1126, 1160. Disposal of wood waste by burning it in a field (an
    “uncontrolled burn”) releases those pollutants unadulterated into the air, contributing to pollution
    problems. Tr. 483, 1160, 1923-24; JX 45-3.
    Biomass facilities produce other pollutants as well, such as PM10 (visible emissions), VOC
    (Volatile Organic Compounds), and NH3 (ammonia), and under state and federal law, must be
    outfitted with technology that reduces emissions. Tr. 594-96, 719-20; PX 45-3. Chowchilla and
    Merced are equipped with technology that measures and controls such emissions including:
    (1) Continuous Emissions Monitoring System (“CEMS”) which records the amount
    of SO2, NOx, CO, and various pollutants that a facility is emitting, and transmits it
    to the District 3
    (2) Continuous Opacity Monitoring System (“COMS”) which records the level of
    opacity of the facility’s emissions and transmits it to the District
    (3) Baghouses or asymmetrical filters which remove particulate matter from flue
    gases and store it in siloes
    (4) Selective non-catalytic reduction (“SNCR”) system which injects anhydrous
    ammonia into the combustor to control NOx emissions
    (5) Limestone injection system which injects limestone into the combustor bed to
    control SO2 emissions, and
    (6) Multiclone and pulse jet baghouse, a second particulate control system that
    removes large portions of particulate matter from the airstream.
    Tr. 149, 152-53, 155, 933, 1125; PX 13; PX 23.
    Ownership of the Facilities
    The Merced facility is the only asset owned by Plaintiff Merced LLC, a California LLC
    formed on May 1, 2001. The Chowchilla facility is the only asset owned by Plaintiff Chowchilla
    LLC, a Massachusetts LLC formed on November 20, 2006. Jt. Stip. ¶¶ 8-10. Plaintiffs Chowchilla
    LLC and Merced LLC are owned by a holding company, Global Ampersand LLC. DX 480. Global
    Ampersand in turn is owned by ACM California LLC, which is owned by Akeida Environmental
    Fund LP (“Akeida Onshore”). 4 Tr. 171-72; DX 480.
    Akeida Onshore is owned by a group of investors in the United States and is managed by
    Akeida Capital Management, LLC (“Akeida Capital”), a fund management entity run by David
    3
    The District refers to the San Joaquin Valley Unified Air Pollution Control District, the local
    authority which enforces California’s implementation plan to achieve federal air quality standards.
    4
    Akeida Environmental Fund LP is known as the “onshore fund.” Tr. 176.
    3
    Kandolha and Harvey Abrahams. Tr. 4, 37-38; DX 480. 5 Akeida Capital manages two other funds:
    Akeida Environmental Master Fund Ltd. (“Akeida Master Fund”) and Akeida Environmental Fund
    Ltd. (“Akeida Environmental Ltd.”), a fund owned by a group of foreign investors. DX 480; Tr.
    174. Akeida Onshore and Akeida Environmental Ltd. collectively own 100 percent of Akeida
    Master Fund. Tr. 171-74; DX 480.
    The Facilities’ History
    The Facilities have had a long and complicated history. Tr. 30. Constructed by California
    Agricultural Power Corporation Energy (“CAPCO Energy”) in the late 1980s, Merced and
    Chowchilla were first operated in October 1988 and February 1990, respectively. Jt. Stip. ¶ 15; DX
    483 at 4. CAPCO Energy sold the Facilities to San Joaquin Valley Energy Partners in 1992, who
    then shut down and “mothballed” them in 1995. Tr. 24; Jt. Stip. ¶ 15. By 2005, the Facilities were
    owned by Global Common, LLC (“Global Common”). JX 19.
    On January 4, 2007, Global Common sold its membership interest in the Plaintiff LLCs to
    Global Ampersand, LLC, a holding company created and owned by a private equity fund,
    Ampersand California Biomass Fund I, LLC (“CalBio”). Tr. 192-93; Jt. Stip. ¶16. CalBio was
    created by employees of London Economics International, LLC (“London Economics”) 6 in the
    spring of 2006, as an investment vehicle for the refurbishment and future operation of the
    Chowchilla and Merced facilities. Tr. 1642, 1650-51; DX 121-15. During CalBio’s ownership,
    the Facilities were run by CalBio’s managing partner and London Economics’ president, A.J.
    Goulding, 7 along with CalBio’s chief operating officer, Eric Shumway. Tr. 1648-49.
    In January 2007, when CalBio acquired the Facilities, they were “inoperable” and had been
    since 1995. Tr. 1653; Jt. Stip. ¶ 15. When power-generating facilities are restarted after an
    extended period of idleness, the owner needs to engage support personnel, “whether it be
    construction or maintenance-type contractors,” to “go through the power plant from end to end,
    break it down into systems, identify[] what needs to be repaired or replaced, put[] together a planned
    approach as well as . . . getting any permitting that is required.” Tr. 347; JX 02 at 3-4. According
    to A.J. Goulding, Chowchilla and Merced faced additional challenges, as the original plans were
    not available, and one facility had been looted for copper causing extensive damage. Tr. 1665.
    After acquiring the Facilities, CalBio set out to secure financing for their refurbishment. Tr.
    1652. On June 29, 2007, Global Ampersand received a $26,500,000 convertible senior secured
    note from D.E. Shaw Synoptic Acquisition VII, LLC (“D.E. Shaw”), an investment vehicle created
    by D.E. Shaw & Co. for the specific purpose of investing in Chowchilla and Merced. Tr. 1191,
    5
    Mr. Kandolha and Mr. Abrahams appeared as corporate representatives of Chowchilla LLC
    and Merced LLC, respectively. Tr. 4. Mr. Kandolha is also a limited partner in Akeida
    Environmental Fund LP. Tr. 203.
    6
    London Economics is an economic and financial consulting firm that specializes in energy
    and infrastructure. Tr. 1638-39.
    7
    Although not admitted as an expert in this case, A.J. Goulding has testified as a regulatory
    economics expert in the electricity and natural gas industries. Tr. 1644-45.
    4
    1655-57; JX 07. 8 The D.E. Shaw note was amended several times, with its principal amount
    increasing to $39,509,999, with accrued interest of $17,968,269 by December 15, 2010. JX 12-2.
    CalBio Enters into Refurbishment and Operations & Maintenance Agreements
    On April 3, 2007, CalBio, through Global Ampersand, engaged Crown Engineering and
    Construction, Inc. (“Crown”), to refurbish the Facilities. DX 258. Crown abandoned the project,
    and Global Ampersand terminated its contract for cause. Tr. 1500, 1649. Mr. Goulding testified
    that Crown’s nonperformance and bankruptcy required the Facilities to find and negotiate with a
    new provider, which had to repeat some of the work, “so the impact was to really delay the schedule
    and increase the cost . . . .” Tr. 1755-56.
    CalBio, through Global Ampersand, subsequently hired NAES Power Contractors, Inc.
    (“NPC”) in December 2007, to complete the refurbishment. Tr. 1649; JX 40-1. In an evaluation
    report dated December 3, 2007, NPC noted that the condition of the Facilities was “generally poor,”
    and identified certain conditions that made refurbishment very challenging, including “the
    condition of some of the plant components, the lack of equipment and material for completion
    (including the absence of comprehensive documentation regarding material/equipment ordered),
    the partially completed nature of some of the work (particularly the electrical work at [Merced]),
    and the budget and time constraints.” JX 02-4.
    The December 19, 2007 construction contract stated that Global Ampersand’s intent was to
    refurbish the Facilities “so as to return their respective 12.5 MW units to full service for the purpose
    of generating electricity for sale.” JX 40-1. The NPC Construction Contract estimated that it would
    cost $2.34 million to complete refurbishment of the Chowchilla facility, and $3.92 million to
    complete refurbishment of the Merced facility. JX 40-1. Under the construction contract, NPC’s
    refurbishment services were divided into “work packages,” for a particular system or subsystem.
    JX 40-1. Once NPC completed a work package, it turned that package over to Global Ampersand
    and project completion would only be declared following final acceptance of these work packages.
    JX 40-5. NPC agreed that Chowchilla would be ready for commissioning on March 4, 2008, and
    ready for commercial operation on April 14, 2008, while Merced would be ready for commissioning
    on April 14, 2008, and commercial operation on May 9, 2008. JX 40-1; JX 02-4.
    When it contracted with NPC to refurbish the Facilities, Global Ampersand had already
    engaged North American Energy Services Company (“NAES”) to take over maintenance and
    operation of the Facilities, once refurbishment was complete. Tr. 25. That arrangement is
    memorialized in an Operations & Maintenance Agreement (“O&M Agreement”) dated March 27,
    2007. JX 01. NAES provided operation and maintenance services to Merced and Chowchilla from
    2007 through 2014. JX 01.
    8
    Jeffrey Hoover, a vice president and executive director of D.E. Shaw & Co., L.P., from 2005
    through June 2012, testified that his primary function at D.E. Shaw was to identify power generation
    facilities with power purchase agreements that D.E. Shaw could acquire and stabilize with cash
    infusions. Tr. 1484-86. D.E. Shaw reviewed the Facilities’ PPAs when conducting due diligence
    before investing in the Facilities. Tr. 1497.
    5
    Interconnection Agreement with PG&E: Facilities Cleared to Sell Electricity
    The Facilities’ owners have sold the electricity produced at Chowchilla and Merced to
    PG&E and CAISO. Tr. 220-21. PG&E required any facility intending to sell electricity via its
    transmission grid to enter into an interconnection agreement. DX 227-6; DX 228-6; Tr. 856. On
    March 24, 2008, CalBio entered into interconnection agreements with PG&E with respect to the
    Facilities. DX 227-36; DX 228-36. Under these agreements, the Facilities were required to pass
    “pre-parallel testing,” to ensure that they could operate at the same frequency and in the same phase
    as the transmission grid so that the Facilities would not damage the grid and could operate safely.
    Tr. 869-70.
    PG&E completed its pre-parallel testing and cleared Chowchilla to generate and sell
    electricity at its full rated output on June 17, 2008, and Merced, on August 24, 2008. DX 153-2;
    DX 151-1. The Facilities’ passage of pre-parallel testing and subsequent interconnection with the
    grid was a “milestone achieved” and indicative of completing “the requirements of PG&E.” Tr.
    1658-59; DX 153-2.
    Power Purchase Agreements
    On September 14, 2005, Global Common—the Facilities’ then owner—entered into a
    Master Power Purchase and Sale Agreement with PG&E under which PG&E agreed to purchase
    electricity produced by the Facilities. JX 19; JX 20; JX 21. By the time CalBio acquired the
    Facilities in January 2007, there were two sets of minor amendments to the PPAs, 9 and on March
    30, 2007, CalBio and PG&E agreed to a third set of amendments. DX 80-2; DX 87-3.
    Under the 2005 PPAs between CalBio’s predecessor, Global Common, and PG&E, and all
    amended versions, the Facilities were to provide PG&E with baseload electricity. JX 20-1; JX 21-
    1. The Master Power Purchase Agreement defines baseload as “a Product for which Delivery levels
    are uniform for all Delivery Periods.” Tr. 399; JX 19-37. Facility-specific PPA Confirmation
    Agreements provided that “‘baseload’ means unit-contingent firm energy delivered with the
    applicable Capacity Factors provided herein.” Tr. 400; JX 20-2; JX 21-2.
    The PPAs provided that the “Contract Capacity” for each facility was “at any time . . . the
    lower of 9.0 MW or the Net Rated Output Capacity” of each Facility, which was approximately
    10.5 MW. Tr. 401; JX 20 at 2, 8; JX 21 at 2, 8. The PPAs established performance penalties that
    CalBio would incur if the Facilities did not produce at the following capacity factors, depending on
    the time of year and time of day:
    9
    Global Common and PG&E amended Chowchilla’s and Merced’s PPAs, in July and
    November 2006, to increase the contract price, extend the Guaranteed Commercial Operation Date,
    and add terms relating to the California Renewables Portfolio Standard, a California state program
    requiring certain electricity-generating entities to procure a specified amount of renewable energy
    resources. DX 78-1, 5; DX 79-1, 7; DX 85-1, 5; DX 86-1, 7.
    6
    TOD [“Time of Delivery”] PERIOD
    Period                             1. Super-Peak           2. Shoulder          3. Night
    [weekdays,           [weekdays,     [11 pm-7 am]
    1 pm-8 pm]            7 am-1 pm,
    8 pm-10 pm;
    weekends,
    7 am-10 pm]
    A. June – September                             95%                90%               80%
    B. December & January                           90%                90%               80%
    C. Feb. – May, Oct. & Nov.                      80%                80%               60%
    ***
    For each TOD Period, if the applicable Capacity Factor is less than the applicable
    Performance Requirement, then the Performance Penalty for such TOD Period
    shall be calculated as follows:
    Performance Penalty =           (Performance Requirement – Payment
    Capacity Factor) x Performance Penalty
    Factor x Maximum Monthly TOD
    Payment.
    . . . For the purposes of illustration, the Performance Requirement in Period A2 is
    90 percent Capacity Factor and the Performance Penalty Factor for Period A2 is
    2.0. If the actual Capacity Factor in Period A2 were 88.5 percent, then Seller would
    pay Buyer the following Performance Penalty = (90% - 88.5%) x 2.0 = 1.5% x 2.00
    = 3.00 percent of the Maximum Monthly TOD Payment for TOD Period A2.
    JX 20 at 6-7; JX 21 at 6-7; Tr. 1170-71.
    Eric Bomgardner, NAES’ plant manager for the Facilities from June 2009 until 2014,
    understood that CalBio intended Chowchilla and Merced to be baseload-producing facilities, which
    he defined as “continuous operating facilit[ies] subject to intermittent demands of increase, decrease
    or don’t produce at all . . . [at] levels . . . identified further [in] the PPA.” Tr. 399-400. 10 Chad
    Curran, PG&E’s energy contract manager, oversaw the PPAs and described each Facility as “a
    baseload facility [that] would operate more or less continually . . . [m]ost hours of the day, often at
    10
    Mr. Bomgardner has worked in the power generation industry for approximately 33 years.
    As the plant manager from 2009 to 2014, Mr. Bomgardner was responsible for day-to-day
    operations of Chowchilla and Merced. Tr. 335-39.
    7
    near—at or near the full capability of the facility.” Tr. 845, 862. 11 David Kandolha testified that
    as baseload facilities, Chowchilla and Merced were “designed to . . . operate at or near capacity at
    all times.” Tr. 105. CalBio’s managing partner, A.J. Goulding, understood the Facilities to be
    “baseload continuous production plants” and that the target production “would have been expressed
    in the [PPAs].” Tr. 1620, 1703.
    Producing baseload electricity is to be distinguished from producing “peaking” and
    “dispatchable” electricity. Tr. 2122-23; JX 20-1; JX 21-1. A peaking facility would operate only
    during peak hours and would only require a capacity factor of two to eight percent. A dispatchable
    facility would operate at PG&E’s request. Tr. 862; JX 19 at 37. Unlike a baseload facility, peaking
    and dispatchable facilities must be able to ramp operations up and down quickly and do not need
    to be able to produce electricity on a continual basis. Tr. 2122.
    Activation of the PPAs
    Under the PPAs, PG&E’s obligation to purchase electricity from the Facilities for a 15-year
    period was to begin on the “Initial Delivery Date.” JX 20-1; JX 21-1. Establishment of the Initial
    Delivery Date depended upon the parties declaring that the Facilities met three conditions: (1)
    achievement of the “commercial operation date;” (2) PG&E’s receipt of a “Performance
    Assurance” payment of $2,281,000 from Global Ampersand; and (3) approval of the PPAs by the
    California Public Utilities Commission (“CPUC”). JX 20 at 1-2; JX 21 at 1-2; DX 78-3; DX 85-2.
    Obtaining approval of the PPAs from CPUC meant issuance of a final, nonappealable order
    approving the PPAs and a finding by the Commission that the procurement was “from an eligible
    renewable energy resource for purposes of determining Buyer’s compliance with any obligation it
    may have to procure eligible renewable energy resources pursuant to the California Renewables
    Portfolio Standard.” Tr. 867; JX 19 at 10, 34.
    Meeting the commercial operation date had two requirements. First, CalBio needed to
    declare “commercial operations,” which the PPA defined as operating and being able “to produce
    and deliver energy to Buyer pursuant to the terms of this Agreement.” Tr. 854; JX 19-9. PG&E’s
    contract manager explained that “the purpose of the commercial operation date is for both of the
    parties to agree and for PG&E to accept that the facility is prepared to begin the delivery term.” Tr.
    857-58. Second, PG&E needed to accept the results of the facility’s Initial Capacity Demonstration
    Test. JX 19 at 9, 40. PG&E’s Initial and Annual Capacity Test principles, attached to the PPAs,
    required that the Facilities demonstrate that they could meet the “performance requirements
    specified in [the PPA] . . . for a duration of 336 consecutive hours,” i.e., 14 days. Tr. 868; JX 19-
    40.
    Mr. Curran testified that compliance with local permitting was “not something that PG&E
    considered in accepting the Commercial Operation Date.” Tr. 902. Nor did PG&E consider
    11
    Chad Remley Curran was PG&E’s Rule 30(b)(6) representative. Tr. 847. As a PG&E
    contract manager from 2008 through 2016, Mr. Curran managed “PG&E’s contracts to purchase
    energy from third parties,” ensuring that “both parties adhere to the terms and conditions of the
    contract, resolving disagreements, verifying completion of milestones under power purchase
    agreements, interpreting contract language.” Tr. 844-46. Mr. Curran has a joint MBA from
    Berkeley and Columbia. Tr. 847.
    8
    whether the Facilities had installed and were operating with all of the equipment required under
    their permits.
    Id. Chowchilla’s Fourth Amended
    PPA
    On December 8, 2008, CalBio and PG&E agreed to a Fourth Amendment to Chowchilla’s
    PPA: (1) extending the Guaranteed Commercial Operation Date from December 31, 2007, to
    December 12, 2008, and waiving the “Daily Delay Damages” for failure to achieve Commercial
    Operation by the 2007 deadline; (2) allowing Chowchilla to announce the Initial Energy Delivery
    Date on December 12, 2008, without upfront payment of the $2,281,000 Performance Assurance
    and providing a less rigorous alternative to the Initial Capacity Test requirements; and (3) waiving
    all performance penalties for three months following the December 12, 2008 Commercial
    Operation Date. DX 81 at 2, 5, 7, 8, 9.
    PG&E’s energy contract manager, Mr. Curran, testified that PG&E frequently extended
    contract deadlines for the procurement of renewable energy around the time of CalBio’s 2008-09
    contract negotiations because PG&E, as an investor-owned utility, had to purchase a certain
    percentage of electricity from renewable resources or be subject to fines by the State of California.
    Tr. 865-66. 12 Procuring electricity from renewable resources proved difficult for PG&E in 2008
    and 2009 because, as Mr. Curran described, the facilities using renewable resources were “newer”
    and the industries supporting them were “nascent.” Tr. 866. As a result, PG&E “often found that
    [renewable-energy] facilities were unable to meet the deadlines to deliver energy to [PG&E] by the
    date . . . agreed to in the power purchase agreements” and “amended contracts to either reduce
    performance requirements or allow extensions of the dates by which the facilities needed to begin
    delivering the energy.” Tr. 866-67.
    CalBio’s predecessor, Global Common, had negotiated a Guaranteed Commercial
    Operation Date of December 31, 2007 for Chowchilla in the First Amendment to the PPA, executed
    on July 27, 2006. DX 78-2. Although Section 3.8(d) of the Master PPA authorized PG&E to assess
    “Daily Delay Damages” and retain monies from the security deposit as liquidated damages for each
    day that the Commercial Operation Date was delayed, PG&E did not impose Daily Delay Damages
    and instead worked with CalBio to set a new Guaranteed Commercial Date. DX 81-8. By the time
    that CalBio negotiated this Fourth Amendment to the PPA, Chowchilla had not met its Guaranteed
    Commercial Date for over a year.
    In addition, PG&E agreed to amend the original Initial Capacity Test which required
    Chowchilla to demonstrate that it met the PPA’s performance requirements for a duration of 336
    consecutive hours, or 14 days. JX 19-40. Under the Fourth Amendment, PG&E opted to review
    Chowchilla’s meter data instead of requiring a two-week performance test “[i]n order to start
    12
    California established the Renewable Portfolio Standard (“RPS”) Program in 2002. Cal.
    Pub. Util. Code § 399.11 (2003). Under the RPS Program, electricity-generating corporations had
    to increase their purchase of eligible renewable energy resources to an amount that equaled 20
    percent of their total retail sales or be forced to procure additional renewable resources in
    subsequent years to compensate for the shortfall.
    Id. The state-mandated 20
    percent target for
    purchase of renewable energy by electricity-generating corporations, originally intended to take
    effect in 2017, was accelerated to 2010 by the state legislature in a 2006 amendment. Cal Pub. Util.
    Code § 399.11 (2006); see S.B. 1078, 2001-2002 Sess. (Cal. 2002).
    9
    deliveries as soon as possible.” Tr. 873-74; JX 18; DX 81-7. Ultimately, PG&E determined that
    Chowchilla passed the Initial Capacity Test, finding that Chowchilla “would have met the test
    requirements during several periods of time during August and September 2008.” JX 18; Tr. 875.
    The Amendment described CalBio’s financial issues as the impetus for PG&E’s waiver of
    the requirement that CalBio pay the $2,281,000 Performance Assurance upfront. The Fourth
    Amended PPA stated in the “Whereas” clause that CalBio could not post the Performance
    Assurance “due to liquidity challenges.” DX 81-1. PG&E extended this payment deadline from
    December 12, 2008 to July 31, 2009, and authorized a payment plan. DX 81 at 5-6. Under the
    payment plan, PG&E retained 10 percent of the balance it owed on Global Ampersand’s invoices
    from the first four months of performance and 25 percent for the next four months.
    Id. at 5.
            Finally, the Fourth Amended PPA provided Chowchilla a three-month grace period from
    performance penalties following the Initial Delivery Date because the Facilities were having
    difficulty meeting the performance requirements under the PPA, and PG&E needed renewable
    energy sources to meet its renewable energy goals. Tr. 865; DX 81-8.
    Merced’s Fourth Amended PPA
    On February 18, 2009, CalBio and PG&E agreed to a Fourth Amendment to Merced’s PPA,
    incorporating most of the modifications in Chowchilla’s Fourth Amended PPA but granting an
    extended, four-year reduction in performance penalties. DX 88. PG&E agreed to: extend the
    Guaranteed Commercial Operation Date from September 30, 2007 to March 1, 2009, waive the
    “Daily Delay Damages” that would accrue if Merced failed to achieve Commercial Operation by
    the 2007 deadline, allow Merced to announce the Initial Energy Delivery Date without upfront
    payment of the Performance Assurance, relax the Initial Capacity Test requirements, and waive
    performance penalties following the March 1, 2009 Commercial Operation Date. DX 88 at 2, 5, 7,
    8, 9. For the Initial Capacity Test, PG&E opted to look at Merced’s meter data from the third and
    fourth quarters of 2008, instead of requiring Merced to undergo a two-week test. Tr. 872-73.
    In Merced’s Fourth Amended PPA, PG&E granted a more generous multi-year, tiered
    exemption from performance penalties. For the first contract year, PG&E eliminated performance
    penalties entirely and reduced them for the next three years:
    Contract Year               Performance Penalty Reduction
    1                                100%
    2                                 75%
    3                                 50%
    4                                 25%
    5 onwards                              0%
    DX 88-8.
    Chowchilla’s Fifth Amended PPA
    On September 23, 2009, CalBio and PG&E agreed to a Fifth Amendment to Chowchilla’s
    PPA, incorporating the four-year performance penalty reduction in Merced’s Fourth Amended PPA
    and granting another extension for payment of the $2,281,000 Performance Assurance from July
    10
    21, 2009, to June 30, 2011. DX 82. This Amendment, like the Fourth Amendments to the PPAs,
    acknowledged that CalBio could not post the Performance Assurance “due to liquidity challenges”
    and gave the Facilities some relief from the performance requirements. Tr. 865; DX 82-1.
    Defendant’s expert, Todd Filsinger, testified that the performance penalty modifications
    reflected the parties’ understanding that “regular operation” for the Facilities did not mean the kind
    of consistent operation that could be achieved, for example, by a nuclear power plant. Tr. 2014.
    “[PG&E was] giving the plant . . . a break . . . in understanding what it takes to get . . . power into
    the grid for this type of facility.”
    Id. 2007-2008:
    Initial Refurbishment Activity and Production
    Refurbishment of Chowchilla and Merced began shortly after CalBio purchased the
    Facilities on January 4, 2007. Tr. 192-93; Jt. Stip. ¶ 16.
    Permits Required for Refurbishing the Facilities
    Chowchilla and Merced are located in the San Joaquin Valley, which the United States
    Environmental Protection Agency (“EPA”) has designated as a “nonattainment area”—an area that
    exceeds emissions standards mandated by the Clean Air Act. Tr. 371, 377, 591-92; JX 13-1. Under
    the Clean Air Act, states which have nonattainment areas must establish a “state implementation
    plan” to achieve federal air quality standards. Tr. 1900-01; JX 13-3. The San Joaquin Valley Air
    Pollution Control District enforces California’s implementation plan through its local rules and
    permit process. Tr. 24, 586; JX 48 at 18-19.
    The District requires one such permit, an Authority to Construct (“ATC”), for facilities that
    will have “equipment that may emit air pollution” or equipment used for controlling air pollution.
    Tr. 485-86. The ATC is an “initial permit” that grants an owner permission to construct a facility
    in accordance with applicable conditions that enable it to meet the District’s and EPA’s emissions
    standards. Tr. 436-37, 486, 1902. The District may issue a facility-wide ATC comprised of
    individual ATCs governing different components of the facility. Tr. 1940-41. The ATCs are not
    Permits to Operate (“PTO”), but, as happened here, facilities may generate and sell electricity under
    an ATC. PX 13.
    After a facility has complied with all ATC conditions, the facility may apply to have its
    ATC converted into a PTO. Tr. 1905. The PTO encompasses a set of permits containing the
    conditions set forth in the ATCs and any modifications. Tr. 435-36. It is possible that a facility
    could receive a PTO for one component, such as the boiler, but not others that remain noncompliant
    with ATC conditions. Tr. 1940-41.
    A District inspector confirms that a facility is complying with its ATC by performing
    various tests, including a source test, a Relative Accuracy Test Audit (“RATA”), and a seven-day
    drift test. Tr. 146-47. In a source test, an independent testing company measures emissions to
    determine compliance with standards for emissions of NOx, SO2, CO, and PM10. Tr. 147. In a
    RATA test, a facility’s Continuous Emissions Monitoring Systems levels are compared to readings
    from independent testing equipment to ensure the CEMS is producing reliable emissions-
    measurement data.
    Id. A seven-day drift
    test determines whether the CEMS can stay calibrated by
    running for a set period of time and assessing how far the system “drifts” between calibrations. Tr.
    148.
    11
    Biomass facilities, such as Chowchilla and Merced, have more difficulty passing these tests
    than a typical electricity-producing facility. The Facilities’ former compliance and operations
    manager testified:
    It’s more difficult for a biomass plant to pass a RATA test or a source test compared
    to a gas-fired power plant. . . . Natural gas . . . [is] consistent in quality, it doesn’t
    vary much, whereas biomass material fuel that is being [used] as fuel comes from
    different sources. So its quality varies very, very widely. And with that quality of
    fuel going into the combustor, it makes it very difficult to have consistent operations.
    It swings up and down. And so frequent adjustment has to be made to be able to
    maintain operations in compliance with all the permits.
    Tr. 925, 935.
    If the facility successfully passes these tests and proves compliance with the remaining ATC
    conditions, the District converts the facility-wide ATC into a facility-wide PTO. Tr. 719, 1905;
    DX 201-2. After the District has granted a facility-wide PTO, facilities such as Chowchilla and
    Merced must apply for a Title V permit, required under the federal Clean Air Act, for “major
    sources of air pollution.” Tr. 428-29, 1906-07; see 42 U.S.C. §§ 7661a, 7661(2), 7412(a)(1).
    When a facility is operating outside of its permit conditions or District rules, the District has
    disciplinary options: (1) issuance of a Notice of Violation (“NOV”) which carries monetary
    penalties and typically additional oversight or testing; (2) for a willful violation, an abatement
    order—a rare occurrence; and (3) rescission or revocation of the ATC or PTO, which is also rare.
    Tr. 487-88, 481-82, 1942.
    In the event a facility is violating, or expects to violate, the conditions of its ATC or PTO,
    the owner can apply for a variance, which permits it to lawfully operate outside of those conditions
    for up to a year from issuance. Tr. 487, 494. The District prefers to work with biomass facilities
    through the NOV process to bring them back into compliance, rather than shut them down and
    cause more agricultural waste to be burned in open fields. Tr. 483-84, 487. Failure to comply can
    also subject the operator to enforcement action from the EPA. 42 U.S.C. § 7413(a)(1); 40 C.F.R.
    § 52.23.
    The Facilities’ ATCs
    The District granted ATCs for Chowchilla on April 19, 2007, while Merced, which had
    been granted ATCs in October 2005, was issued revised ATCs on February 5, 2007. PX 13-1; PX
    23-1.
    2008 Operations: Passage of Pre-Parallel Testing, Turnover of Facilities from Construction
    Contractor to Owner, Commencement of Commercial Operations, and Sale of Electricity to
    CAISO and PG&E
    Refurbishment progressed to the point where Plaintiffs “restarted” the Chowchilla plant on
    April 24, 2008, and the Merced plant, on July 5, 2008. Tr. 1864 (stating that these dates marked
    when the Facilities had their “initial fire”); JX 137 at 2. As of June 17, 2008, Chowchilla had
    “completed the requirements of PG&E” after passing its pre-parallel inspection, operating at 12.5
    MW, and first selling at that capacity on the grid. DX 178; DX 180-2. The Facilities were still
    12
    experiencing emissions problems, and Chowchilla failed a RATA test in August 2008, and a source
    test in September 2008. PX 108; PX 109; PX 142-20. Mr. Goulding understood Chowchilla to be
    commercially operational as of August 2008, because the Facility had “completed the testing,” was
    under the PPA, and was “released to generate at full capacity.” Tr. 1514-15.
    In September 2008, NPC advised PG&E that it had completed all work packages for
    Chowchilla and Merced and that the plants were ready to begin their capacity performance tests.
    DX 35; DX 174. Defendant’s expert, Todd Filsinger, testified that these September 2008 dates
    were important dates for Section 1603 purposes, because they signaled when NPC finished its work
    and were a good estimate of “when [NPC] felt it was there.” Tr. 1965.
    The Facilities experienced outages in 2008, including one at Chowchilla that lasted six
    weeks in October 2008, due to an overheated transformer. Tr. 2067; PX 103-6.
    2008 Emissions Problems, NOVs and Variances
    Soon after Chowchilla and Merced restarted in April and July 2008, the San Joaquin Valley
    Unified Air Pollution Control District and the United States Environmental Protection Agency
    began issuing Notices of Violation to the Facilities. See e.g., DX 197. Chowchilla failed an
    inspection on June 3, 2008, and received six NOVs in August 2008, for failing to install a truck
    tipper (part of the fuel handling system), various vent filters, an NH3 flow rate indicator, and a fly
    ash silo filter as well as for exceeding emissions limits. Tr. 372-74, 151-52; JX 05-5; DX 197-1.
    It then received another NOV in November 2008, for operating without a certifiable CEMS. Tr.
    414. On October 20, 2008, the District issued Merced three NOVs—for operating without a truck
    tipper, and an ammonia injection system, and for operating a diesel fire pump driver without a
    Permit to Operate. Tr. 600-04; JX 03-3; JX 04-1. For the entirety of its 2008 operations,
    Chowchilla continued to operate without the truck tipper, the vent filter, as well as with exceedances
    for NOx, SOx, CO, and PM10. Tr. 411-12; JX 48.
    Faced with emissions exceedances, CalBio in late 2008, submitted an application to the
    District seeking a variance for each Facility. Specifically, CalBio sought permission to operate
    Chowchilla from December 17, 2008, to April 30, 2009, with excess NOx, SOx, CO, ammonia slip,
    and visible emissions “until the ammonia injection system [could] be managed properly to bring
    the plant into compliance.” Tr. 498-99; JX 45 at 2-4. The District granted this request and found
    that closing Chowchilla “would be without a corresponding benefit in reducing air contaminants,
    because the closing of this facility would cause more farmers to burn their agricultural wastes in
    the open, uncontrolled.’” Tr. 513; JX 45 at 3-4. Under the December 17, 2008 variance,
    Chowchilla was required to operate at a reduced capacity to maintain emissions below the permitted
    limits, except when testing. Tr. 502; JX 45-3.
    On December 2, 2008, CalBio sought a variance to operate Merced from December 2, 2008,
    through March 15, 2009, with excess NOx emissions and without conducting tests by dates required
    by its ATC. PX 24 at 1-2, 10. The District denied CalBio’s request for a variance for Merced,
    finding that Plaintiff Merced LLC “demonstrated an unwillingness to comply with District Rules
    and permit conditions by failing to contact the District for a start up inspection prior to operation,”
    “commencing operation without an ammonia injection system,” and “operating without a certified
    or properly working CEMS.” PX 25 at 3; see Tr. 511-12, 732. Despite their lack of compliance
    with emissions requirements in 2008, the Facilities continued to operate and sell electricity.
    13
    The Facilities Generate Approximately $2.26 Million in Revenue in 2008
    In 2008, Chowchilla generated 20,553 Megawatt Hours (“MWh”) of energy, resulting in
    revenue of $1,408,941, and Merced generated 14,306 MWh in 2008, resulting in revenue of
    $851,152. PX 103-7. A.J. Goulding testified that this revenue was a “big deal” because CalBio
    had finally reached the point where it “[got] paid after a long process.” Tr. 1659. Because the
    Facilities “provided power to the system” and “got paid” in 2008, Mr. Goulding deemed the
    Facilities commercially operational. Tr. 1754.
    While the Facilities had the option in 2008 to sell electricity to PG&E at a reduced or test
    price under their PPAs, CalBio decided to sell to third parties on the CAISO spot market at higher
    prices. Tr. 1552-53, 1576. When Chowchilla achieved its Initial Energy Delivery Date under its
    PPA on December 12, 2008, all of its sales then went to PG&E, accounting for $170,659 in revenue.
    PX 103-7. During this time, the Facilities were also selling Renewable Energy Credits (“RECs”).
    Tr. 1996; see Tr. 866-67, 1613.
    CalBio’s Inability to Monetize PTCs Via a Tax Equity Transaction
    CalBio and D.E. Shaw had originally planned to create additional revenue by monetizing
    production tax credits generated by the Facilities through a tax-equity transaction. Tr. 1687. As
    CalBio expected the Facilities’ Production Tax Credits to exceed CalBio’s tax liability in 2008,
    CalBio and D.E. Shaw worked together to secure a tax-equity transaction before 2009. Tr. 1555-
    56. CalBio fielded tax-equity offers from State Street Bank and G.E. Energy Financial Services,
    Inc. (General Electric). Tr. 1614, 1724-25. Negotiations with General Electric progressed to the
    point that CalBio and D.E. Shaw thought a deal was possible, but on July 10, 2008, General Electric
    pulled out of the project. Tr. 1725-26; PX 90. According to CalBio, General Electric’s unexpected
    pullout caused “liquidity challenges, which among other things, ma[de] it impossible for [CalBio]
    to fund the Delivery Term Security [the Performance Assurance] required under the existing PPA.”
    JX 23.
    CalBio Takes PTCs and Recognizes Depreciation in 2008
    CalBio did not find a tax equity investor in 2008, and, after consulting with its accountants,
    took $347,855 in PTCs for the energy produced by both Facilities. Tr. 793, 1673, 1691-92; DX
    160 at 1, 27. Mr. Goulding testified, “[i]n 2008, we provided power to the system and we got paid.
    From a tax perspective, we believe that that was sufficient to qualify for the production tax credits
    . . . .” Tr. 1754. In addition to claiming PTCs, CalBio recognized depreciation of assets for both
    Facilities on its financial statements and tax returns in 2008. Tr. 1603; DX 59; see also DX 115-
    13; DX 122-9; DX 160-1, 9; DX 168-4; DX 186-1. In its May 25, 2010 financial statements
    submitted to Akeida and D.E. Shaw, CalBio stated, “Ultimately, the continuation of the company
    is dependent upon its ability to negotiate new PPAs and achieve a level of operation sufficient to
    meet cash flow requirements.” DX 122-7.
    At the time CalBio took these PTCs on its 2008 tax return, it was the parent of Plaintiffs
    here—the LLCs that owned the Chowchilla and Merced facilities then and now. As Plaintiffs were
    disregarded entities in 2008, CalBio reported the PTCs on its tax return Form 1065 on a
    consolidated basis without segregating out or separately identifying Plaintiffs, and reflected the
    PTCs in Form 8835 (Renewable Electricity Production Credit). JX 39-15.
    14
    By late 2008, the Facilities were suffering from serious cash flow problems. In its December
    2008 report, NAES noted continued issues with “start-up, testing and troubleshooting for all
    systems,” and stated that cash flow issues would impact operations more severely as vendors
    declined to provide materials and services to the plants. PX 84-3. The Facilities also experienced
    increased operating costs because the price of biomass rose. DX 121 at 12-13.
    2009: More Milestones, Operational Problems, and NOVs
    CalBio and the Plaintiff LLCs entered 2009 with the Facilities producing electricity, albeit
    without properly-functioning emissions-control equipment and in excess of emission limits
    imposed by their ATCs, District rules, and federal law. Operating in this manner led to NOVs from
    the District for each Facility. JX 45-2; PX 24; PX 17. Chowchilla received relief via a variance
    giving it until April 29, 2009 to reach compliance. JX 45. Merced was denied a variance, and
    therefore faced monetary penalties. Tr. 13; PX 25.
    Despite these continuing compliance problems, the Facilities moved forward with respect
    to milestones in their O&M Agreement and their PPAs. CalBio declared that the “takeover date”
    under the O&M agreement occurred on January 1, 2009. Tr. 410-11; JX 06-1. Global Ampersand
    and PG&E had declared Chowchilla’s PPA Initial Delivery Date to be December 12, 2008,
    signaling that the plant had begun “commercial operations,” which meant it was able to deliver
    baseload power in accordance with the PPA. PG&E and Global Ampersand declared Merced’s
    Initial Delivery Date to be February 21, 2009. Tr. 259; DX 241.
    The Facilities Enter the Operational Phase Under the O&M Agreement in January 2009
    According to the January 2009 report Global Ampersand sent to D.E. Shaw, if it were not
    for fuel shortages, the Facilities’ boilers would have been running 96 percent of the time that month.
    Tr. 1533; PX 104-17. Additionally, capital shortages resulted in temporary employees at the
    Facilities no longer working during the early months of 2009 because they were not being paid. Tr.
    1533-34; PX 104-29. In January 2009, neither Facility had resolved its emissions issues and, even
    if fuel had been available, were prohibited from producing at a 96 percent capacity factor until those
    issues were resolved.
    In January 2009, Chowchilla’s capacity factor was 63.7 percent and Merced’s capacity
    factor was 37.9 percent. Tr. 418-19. Although the Facilities should have been producing in the 80
    to 90 percent range for baseload as of January 2009, penalties were waived for Chowchilla for
    another month. See DX 81-8. Merced did not begin to deliver power to PG&E under its PPA until
    March 1, 2009, with penalties reduced for four years. See DX 88-8. Instead, Merced was
    generating electricity for sale to CAISO and third parties until that time.
    The District Converts Chowchilla’s ATC to a PTO in April 2009
    On April 21, 2009, the District converted Chowchilla’s facility-wide ATC into a facility-
    wide Permit to Operate, indicating that Chowchilla was compliant with its ATC conditions. Tr.
    1939, 1979; DX 437. Around that time, the EPA also deemed Chowchilla’s Title V permit
    application administratively complete. PX 105. Chowchilla was granted a Title V permit in August
    2009. Tr. 1908. Merced did not complete its Title V application until August 2010, and received
    its Title V permit in 2011. Tr. 1907-08; PX 125.
    15
    On April 15, 2009, CalBio filed a second variance application for Chowchilla for the period
    from April 30, 2009, to December 16, 2009, as Chowchilla was still experiencing problems with
    the ammonia injection system and with continued exceedances of emission limits on NOx, PM10,
    and ammonia. PX 17 at 3, 10; Tr. 503-05.
    Continuing Environmental Problems in 2009
    On March 25, 2009, the EPA, pursuant to the Clean Air Act, submitted an information
    request to Plaintiff, identifying emissions exceedances and asking about the Facilities’ testing and
    results. Tr. 597-98; PX 101. CalBio responded to the EPA’s request on May 7, 2009, stating that
    “emission testing has been and continues to be an ongoing process.” Tr. 425; PX 101 at 8-9. CalBio
    stated that although emissions exceedances were substantial, the emissions were offset by CalBio’s
    procurement of Emission Reduction Credits (“ERCs”) through a California state program and the
    Facilities’ disposal of agricultural wood waste that otherwise would have been burned in open
    fields. PX 101 at 2. CalBio also reported that the project continued to face severe financial
    hardship, which caused operating performance to suffer and “limited [CalBio’s] ability to
    proactively address several mechanical issues.”
    Id. at 2, 6.
            On July 23, 2009, the EPA issued Chowchilla and Merced their first federal NOVs
    identifying eight violations of District rules that had been occurring since startup. JX 13 at 8-9; see
    Tr. 586. Similar to the findings made by the District in issuing its NOVs in 2008, the EPA found
    that Chowchilla and Merced had violated federal emissions limits and failed to install required
    equipment such as a CEMS. Tr. 149-50.
    Regarding testing, the Facilities struggled for most of 2009. Still operating with a
    malfunctioning and uncertified CEMS and DAHS, 13 Chowchilla passed a source test on May 14,
    2009. Tr. 394, 728. Chowchilla completed its initial certification for its CEMS on August 28,
    2009, but then failed source tests in September and October 2009. PX 144-15. Chowchilla
    successfully completed the seven-day drift test in approximately September or October 2009. Tr.
    393. Merced failed source tests on March 17 and 18 and June 26, 2009, and failed a RATA test on
    June 29, 2009. PX 123. Merced’s Continuous Opacity Monitoring System was not tested and
    certified until September 14, 2009, and issues with Merced’s CEMS were not resolved until 2011.
    Tr. 342, 409-10, 729-30.
    The Facilities’ Production and Revenue in 2009
    In 2009, Chowchilla generated 50,905 MWh of electricity, resulting in revenue of
    $4,624,942, and Merced generated 48,591 MWh, resulting in revenue of $4,223,825. DX 214-9.
    In 2009, Chowchilla had an average capacity factor of 53.9 percent, with a monthly high of 77.1
    percent (April), and Merced had an average capacity factor of 51.2 percent, with a monthly high of
    64.2 percent (December). DX 214-3
    13
    The DAHS is a computer system that helps generate environmental compliance reports. Tr.
    394.
    16
    CalBio’s Continuing Financial Problems in 2009 and the May 25, 2009 Loan from ACM 4
    Secured by the Facilities
    On February 17, 2009, Congress passed the American Recovery and Reinvestment Act of
    2009 (“ARRA”), to address the financial crisis that had come to the fore the previous year.
    Recognizing that many entities had severely diminished cash flows as a result of the crisis that made
    tax credits of dubious value, Congress established a mechanism for entities to receive Section 1603
    grants in lieu of tax credits when investing in certain renewable energy facilities. See Alta Wind I
    Owner Lessor C v. United States, 
    897 F.3d 1365
    , 1368 (Fed. Cir. 2018).
    Having failed to monetize the PTCs in 2008, CalBio and D.E. Shaw were still looking for
    capital and struggling with cash flow problems. CalBio and D.E. Shaw did not believe the Facilities
    qualified for a Section 1603 grant. D.E. Shaw’s Kyle Bethancourt and Justin Chan determined that
    it would be “an uphill battle” for Chowchilla and Merced to secure grants because the Facilities
    were regularly selling power, even on the spot market, and had been connected to the grid in 2008.
    Tr. 1552-54; DX 182-3; see also Tr. 1560-66; DX 166. D.E. Shaw did not obtain a formal
    determination from counsel as to the Facilities’ eligibility for Section 1603 grants because it did not
    believe it likely the Facilities would receive awards due to “placed-in-service issues.” Tr. 1624-26.
    Mr. Goulding agreed that the Facilities were not eligible for a Section 1603 grant. Tr. 1683. Mr.
    Goulding testified that CalBio “believed it would have been to [CalBio’s] benefit to be able to attain
    the cash grant and explored it, you know, as much as we could and felt that it was not—not
    possible.” Tr. 1684; see DX 166-1; Tr. 1544.
    CalBio’s search for funding eventually led it to Akeida Capital Management, and
    discussions between CalBio and Akeida Capital began in February 2009. 14 Tr. 1668-69; DX 111.
    On March 12, 2009, Global Ampersand and Akeida Master Fund signed a draft term sheet. Tr.
    208; DX 112-9. On March 17, 2009, as part of Akeida’s due diligence, Akeida requested and
    received Global Ampersand’s audited financial statements, which showed that CalBio recognized
    depreciation on Chowchilla in May 2008, and on Merced in September 2008. Tr. 1968; DX 115-
    13; DX 122-9.
    On May 25, 2009, ACM Corp. 4, LLC (“ACM 4”), a Cayman Islands entity wholly owned
    by Akeida Master Fund and represented by Mr. Kandolha, provided a $9,000,000 secured term loan
    to Global Ampersand backed by the Facilities. Tr. 45-46, 164, 177-78. The loan was signed by
    Mr. Kandolha as lender. Tr. 235.
    Section 5.20(b) of the Loan Agreement, “Incentives and Tax Credits,” expressly stated that
    “[t]he Borrower and/or the Facilities [was] eligible to receive, and/or participate in . . . the Incentives
    and Tax Credits listed on Schedule 5.20,” and the only tax credits listed on Schedule 5.20 were
    Production Tax Credits. JX 30 at 57-58, 122. Mr. Kandolha testified that it was important to ACM
    4 that the Facilities qualified for Production Tax Credits at that time because CalBio intended to
    monetize the PTCs in exchange for an equity investment that would allow it to service its loans.
    Tr. 76. According to Mr. Kandolha, taking PTCs was a condition of ACM 4’s loan because “[t]he
    14
    Akeida Capital Management had three funds. Mr. Kandolha ran the Akeida Environmental
    Fund LP and Akeida Environmental Master Fund Ltd. Tr. 41. Akeida Environmental Fund LP
    owned 100 percent of the membership interest in ACM California LLC, which in turn owned 100
    percent of the membership interest in Global Ampersand.
    Id. 17
    understanding under the loan [was] that [CalBio] would get a tax equity investor to take those PTCs
    and pay them so that they could pay us back.” Id.; see also Tr. 256; Def.’s Cross-Mot. for Summ.
    J., Ex. 5 at 16.
    The Loan Agreement between ACM 4 and Global Ampersand provided:
    No Borrower shall, until satisfaction in full of the Obligations and termination of the
    Commitments:
    ***
    7.18: Incentives and Tax Credits
    (a) Take any action (or fail to take any action) or permit any event or circumstance
    to occur (excluding events or circumstances beyond its control after the exercise of
    reasonable diligence) which would result in any of the Facilities ceasing to qualify
    as an open-loop biomass facility as defined in Code Section 45(d)(3).
    (b) Take any action (or fail to take any action) or permit any event or circumstance
    to occur (excluding events or circumstances beyond its control after the exercise of
    reasonable diligence) which would result [in] any Borrower and/or Facility
    becoming ineligible to receive and/or participate in any Incentive or Tax Credit or
    Incentive or Tax Credit Program listed in Schedule 5.20 . . . .
    JX 30 at 65, 70.
    The Loan Agreement also expressly stated that “production tax credits [were] currently
    being distributed to [Global Ampersand] and its shareholders.” Tr. 234; JX 30-122. Mr. Goulding
    explained that this was an “acknowledgment that production tax credits [were] being earned” and
    “[were] sitting on the tax returns of the individual investors.” Tr. 1687; see Tr. 1587.
    Simultaneously with ACM 4’s loan to Global Ampersand, on May 25, 2009, D.E. Shaw
    agreed to subordinate its loan to ACM 4’s loan. Tr. 1200-02, 1217; JX 09. CalBio, through Global
    Ampersand, used the funds to refurbish the Facilities. Tr. 1722. Despite the cash injection from
    the ACM 4 loan, as of September 2009, Global Ampersand had still not paid PG&E the $2,281,000
    Performance Assurance.
    On October 27, 2009, Global Ampersand was in default on the ACM 4 loan, and the default
    had not been cured by December 15, 2009. Tr. 83; DX 245.
    2010: Environmental Violations Continue, the Facilities Cease Operations Due to Financial
    Issues, and Akeida Onshore Purchases the Facilities
    The joint monthly operations report for the month ending June 30, 2010, showed that
    Chowchilla had an average capacity factor of 35.8 percent for the first six months of 2010 and that
    Merced had an average capacity factor of 15.7 percent, for this timeframe. DX 222-4.
    In May 2010, the United States Department of Justice (“DOJ”), at the request of the EPA
    and the District, sent a letter to Global Ampersand raising several issues with emissions controls,
    stating that the Facilities “exceeded permitted [emissions] levels several fold, and in some instances
    18
    greater than ten-fold,” and that both lacked an operational Selective Non-Catalytic Reduction
    (“SNCR”) system. Tr. 615-16; PX 97-2; PX 94-2. DOJ stated that the Facilities’ failure to install
    these systems alone would support penalties of $32,500 per day and proposed $1.6 million in
    penalties to settle the Facilities’ alleged violations of the Clean Air Act. Tr. 614; PX 94-2. DOJ
    and Akeida, CalBio’s successor, ultimately settled for $835,000 in penalties. JX 41 at 6-7; JX 42
    at 6-7.
    Due to funding issues, Merced ceased operations temporarily in April 2010, and Chowchilla
    temporarily in May 2010, both at Global Ampersand’s direction. DX 218-6; DX 220-5. In June
    2010, CalBio made the decision to suspend operations completely, also due to funding issues. Tr.
    277; DX 222 at 5-6.
    2010: Continuing Financial Problems
    CalBio’s financial struggles with the Facilities continued in 2010. In May 2010, Akeida
    Master Fund, through ACM 4, accelerated the due date of its May 25, 2009 loan to Global
    Ampersand, because no payments were being made. Tr. 85-87; JX 31 at 2. By July 2010, CalBio,
    lacking funds for refurbishment, was exploring options to sell the Facilities while attempting to
    negotiate another amended PPA with PG&E, to no avail. Tr. 99-100; 567-68.
    In 2010, CalBio was still looking to sell or recapitalize the Facilities with the assistance of
    its creditors, D.E. Shaw, and Akeida Master Fund. As part of those efforts, CalBio retained Shaw
    Consultants International, an independent engineering firm, to write a technical evaluation study
    that presented a fulsome picture of the state of the Facilities. Tr. 99, 2005-06; JX 32-33. After
    assessing the Facilities, Shaw Consultants International issued its report on December 1, 2010,
    finding that the Facilities had experienced poor operational performance since 2008, directly
    resulting from the lack of funding for maintenance and CAPEX projects. DX 249-11; Tr. 2005.
    The report identified deficiencies affecting production and emissions compliance, and detailed a
    lengthy list of projects that would enable the Facilities to “significantly improve both plant capacity
    factor and fuel heat rates in addition to allowing plant personnel to stay ahead of the curve in terms
    of maintenance.” DX 284 at 24-30; Tr. 443-44.
    After accelerating Global Ampersand’s loan, Akeida Capital, which managed Akeida
    Master Fund, considered a few options—finding a buyer for the Facilities, foreclosing on the
    Facilities, or buying the Facilities itself. In a September 2010 memorandum, Akeida Capital’s
    Travis Windholz positively assessed the viability of purchasing the Facilities, stating the Facilities
    had the permits needed for ongoing operations, that construction had been substantially completed
    in 2008, and that the expenditures needed to reach “optimal levels” of performance were “limited.”
    JX 31 at 5-6 (estimating about $3 million in capital expenditures and deferred maintenance). Mr.
    Windholz expected Akeida Capital would pay no more than $2 million to acquire Global
    Ampersand: $500,000 in cash and $1.5 million in contingent payments. JX 31-4. The memo also
    reflected that, as a part of its plan to acquire the Facilities, Akeida intended to purchase D.E. Shaw’s
    debt. JX 31-3; Tr. 1358.
    On December 15, 2010, ACM Corp. 6, LLC (“ACM 6”), a special purpose LLC wholly
    owned by Akeida Master Fund, paid $350,000 to D.E. Shaw for the outstanding debt related to D.E.
    Shaw’s construction loan. Tr. 29; JX 11-2; JX 12. At the time, the loan had a principal amount of
    $39,509,999, plus accrued interest of $17,968,269. JX 12-2; see Tr. 1207-09, 1221.
    19
    Akeida’s Acquisition of CalBio
    On December 28, 2010, twelve days after the LLC owned by Akeida Master Fund purchased
    the D.E. Shaw debt, a different Akeida Capital managed fund, Akeida Onshore, through a wholly
    owned special purpose LLC, ACM California LLC, acquired 100 percent of CalBio’s membership
    interest in Global Ampersand, pursuant to a Membership Interest Purchase Agreement (“MIPA”).
    Tr. 95, 190, 532; JX 33. The following diagram represents the ownership structure of the Akeida
    entities at the time of Akeida Onshore’s purchase of the Facilities on December 28, 2010:
    DX 480 (“El Nido Biomass” refers to the Merced facility). CalBio recognized a sales price of $74.4
    million on its 2010 tax return along with a taxable gain of $26 million. JX 39-12; Tr. 1432. Akeida
    Onshore treated the acquisition as an asset acquisition for tax purposes because “both CalBio and
    ACM California are pass-through entities” and disregarded for tax purposes. Tr. 532.
    According to the MIPA, which was signed by Akeida Capital’s principal, David Kandolha,
    ACM California paid $100,000 up front and agreed to $1.3 million in additional payments. JX 33-
    19; see Tr. 535. The MIPA expressly stated that PTCs were “currently being distributed to
    Ampersand California Biomass Fund I, LLC [i.e., CalBio] and its members” as of December 28,
    2010. JX 33-90; see also Tr. 539, 1700. As part of the December 28, 2010 transaction, ACM
    California LLC assumed Global Ampersand’s liabilities. Tr. 95; see JX 33.
    Akeida Onshore did not take depreciation or PTCs in 2010. Tr. 96.
    2011: The Facilities Enter A Consent Decree with EPA and District
    On February 14, 2011, due to the Facilities’ history of NOVs and failed emissions-related
    tests, the United States Department of Justice and the District jointly filed an 18-count Complaint
    against Plaintiff Merced LLC and a 20-count Complaint against Plaintiff Chowchilla LLC, seeking
    20
    injunctive relief to stop operations at both Facilities, though Global Ampersand had already ceased
    operations in June 2010. JX 47, JX 48. The United States and the District alleged that the Facilities
    failed to install necessary equipment such as a certified CEMS, SNCR system, failed to utilize other
    required equipment (such as a bin bent filter and truck tipper), and exceeded emissions limits. Tr.
    1912-13; JX 48; JX 47 at ¶¶ 88, 164, 174, 181.
    On the same date that suit was filed, Chowchilla LLC and Merced LLC entered consent
    decrees with the EPA and the District. Tr. 157; JX 41-34; JX 42-34. The consent decrees required
    the Facilities to install, test, and certify certain equipment, notify the EPA and the District of any
    potential violations, and pay stipulated penalties of $835,000 for violations. Tr. 157-58. Akeida
    Onshore was ultimately responsible for those penalties. Tr. 158-59.
    Prior to the acquisition closing on December 28, 2010, David Kandolha had received the
    December 1, 2010 technical evaluation report issued by Shaw Consultants International, and
    Akeida Onshore hired Shaw Consultants International to oversee the implementation of the report’s
    recommendations. Tr. 99. Improvements made by Akeida Onshore cost $7.56 million for
    Chowchilla and $7.39 million for Merced. PX 87-4; PX 88-4. Akeida Onshore replaced a variety
    of equipment: automated ammonia injection systems were installed and certified in June 2011, and
    the CEMS and flow monitor were certified on August 11, 2011, along with the CEMS quality
    assurance and control program. DX 272; DX 273; DX 299; DX 300; DX 354. With new emissions
    equipment, Chowchilla and Merced were able to pass the source test, RATA test, and seven-day
    drift test on August 2 and 5, 2011, respectively. Tr. 668-70, 1152-53; PX 155-6.
    2011: Global Ampersand Obtains Amendments to the PPAs and Applies for State and
    Federal Grants
    On February 3, 2011, Global Ampersand entered into another set of PPA amendments with
    PG&E, the sixth for Chowchilla and the fifth for Merced. Tr. 864; DX 83; DX 89. In these PPA
    Amendments, the parties expressly recognized two circumstances: (1) that both the Chowchilla and
    Merced Facilities would be “unable to continue to operate” without additional revenue from the
    PPAs and (2) that PG&E and Global Ampersand desired “to amend the PPA[s] to enable Global to
    continue to operate . . . producing RPS-eligible energy, and contributing to [PG&E’s] achievement
    of its RPS compliance requirements.” DX 83-1; DX 89-1. These Amendments increased the
    contract price and the Performance Assurance, created a new formula to calculate performance
    penalties, waived all performance penalties previously incurred, and waived all performance
    penalties for the rest of the year. Tr. 864-65, 904; DX 83 at 2,5,6,14; DX 89 at 2, 5, 6, 14.
    On January 26, 2011, Global Ampersand submitted an application to the California Energy
    Commission seeking funding under the Commission’s Existing Renewable Facilities Program
    (“ERFP”) and anticipated receiving $2.3 million in incentive payments per Facility, by December
    31, 2011. Tr. 813-14; JX 51-3; DX 29-3. However, as Mr. Kandolha testified, “the [ERFP]
    program was discontinued in 2011. So there again I think we got a few hundred thousand from this
    program.” Tr. 814.
    The Section 1603 Grant Applications
    In early 2011, Akeida Capital decided to apply for Section 1603 grants and retained
    Novogradac & Company LLP, a public accounting firm, to act as independent auditor and certify
    21
    Global Ampersand’s Section 1603 applications. Tr. 127; PX 87; PX 88. Nathaniel Eng, a
    California-licensed CPA and the Novogradac manager responsible for the Facilities’ audits agreed
    that the sales price listed by CalBio in its 2010 tax return of $74.5 million was the correct acquisition
    price. Tr. 688-90.
    Novogradac determined that Chowchilla had an eligible cost basis of $40,943,280, which
    would yield a 30 percent Section 1603 grant of $12,282,984. Tr. 687; PX 87-4. Novogradac
    concluded that Merced had an eligible cost basis of $40,999,077, yielding a Section 1603 grant of
    $12,299,723. Tr. 687; PX 88-4. In October 2011, Plaintiffs applied for grants in these amounts
    and indicated on their applications that their properties were placed in service on August 11, 2011.
    Tr. 116-17; see Tr. 1428-32; PX 87; PX 88.
    2012-2015 Operations
    After August 2011, the Facilities still had some operational issues. According to their
    submissions to the EPA and the District, the Facilities exceeded emission limits in some respects
    for limited periods in 2012. Tr. 642; see DX 303 at 39. The Facilities continued to receive NOVs,
    but most were for “procedural violations,” i.e., for “submitting incorrect information in certain
    reports.” Tr. 738-39. Ryan Hayashi, the District’s Director for Compliance, testified that at this
    time the Facilities were no more on his “radar” than other facilities under his jurisdiction. Tr. 739;
    see also Tr. 446-47.
    In the 2012 report covering August 2011 through August 2012 regarding Chowchilla, Mr.
    Kandolha represented that the Facility produced approximately 52.7 million KWh, although he had
    estimated in his Section 1603 application that annual production would be 93 million KWh. Tr.
    780; DX 28; DX 142-3. In its 2013 report covering August 2012 through August 2013 regarding
    Chowchilla, Mr. Kandhola represented that the Facility produced approximately 64.6 million KWh.
    Tr. 405; DX 143. In subsequent reports, Chowchilla stated that annual production for the Facility
    was approximately 82.6 million KWh in 2014, approximately 68.7 million KWh in 2015, and
    approximately 78.7 million KWh in 2016. Tr. 787; DX 144-3; DX 145-3; DX 435. In all these
    reports, Chowchilla stated that there were no “interruptions in production during the year, other
    than routine maintenance[.]” DX 142-3; DX 143-3; DX 144-3; DX 145-3; DX 435. Merced
    similarly represented from 2012 through 2016 that it did not experience “any interruptions in
    production” during these years, other than routine maintenance. DX 138-3; DX 139-3; DX 140-3;
    DX 141-3; see also Tr. 787. 15
    The only penalty assessed against the Facilities from 2011 to 2014 was associated with a
    failed 2013 source test for visible emissions that was imposed by the District. Tr. 561; DX 303-39.
    The consent decrees were terminated in 2015. Tr. 159.
    The Denial of the Section 1603 Grant and Continuing Financial Problems
    On September 10, 2012, Treasury issued Merced LLC, a Section 1603 grant of $1,136,519,
    and on January 10, 2013, Chowchilla LLC, a grant of $1,136,207. DX 467; DX 468. In the award
    letters, Treasury stated:
    15
    The Government vigorously disputes that there were no interruptions in production at these
    times with respect to both Chowchilla and Merced. Def.’s Am. Post-Trial Br. 55.
    22
    We have determined that most of the property which is the subject of the application
    was placed in service in 2008 and is ineligible for payment. Of the remaining costs
    indicated as eligible in the cost certification, we adjusted the construction loan
    interest expense to more closely reflect the interest incurred on the portion of the
    eligible cost between December 28, 2010 and August 11, 2011.
    Tr. 1789; DX 467; see also DX 468. 16
    Ms. Ellen Neubauer, Treasury’s Section 1603 Program Director, explained that Treasury
    denied the remaining grant amounts because “the prior owners of the project company treated the
    project, for federal tax purposes, as having been placed in service in 2008” and “[t]he Section 1603
    program is not in a position to revisit that treatment.” Tr. 1776; PX 160-1. In Treasury’s view, if
    a facility had received PTCs, it was ineligible to receive a grant, regardless of whether the prior
    award of PTCs was appropriate. Tr. 1778. Treasury did not evaluate whether the prior owner’s
    determination was correct because “the Section 1603 program doesn’t make tax determinations” or
    amend an erroneous return. Tr. 1776-77.
    On December 28, 2012, after Treasury denied Merced the bulk of the grant, ACM 6 and
    Global Ampersand agreed to write down the ACM 6 loan by $25,820,044. DX 02-2. On December
    30, 2013, Akeida Master Fund wrote down the D.E. Shaw loan by an additional $16,500,000 and
    reduced the interest rate on the note to 0.1 percent on any remaining debt. Tr. 546, 758; DX 02-2.
    On March 26, 2014, Mr. Kandolha contacted Congressman Jim Costa of California’s 16th
    Congressional District in an effort to understand why Treasury denied the grants. Tr. 144. On June
    5, 2014, Representative Costa wrote a letter to urge Treasury to “reevaluate its decision.” PX 45;
    Tr. 144, 1108.
    After Mr. Kandolha’s efforts failed, Akeida Master Fund agreed to write down the D.E.
    Shaw loan by an additional $8,000,000 on December 30, 2014. DX 02-2; Tr. 757-58. Then on
    December 30, 2015, Global Ampersand and Akeida Master Fund agreed to write down the ACM 6
    loan by an additional $5,000,000. DX 02-2. Akeida Master Fund recognized the forgiven debt as
    income on its tax returns in all relevant years. DX 02-2; DX 06-8; DX 07-2; DX 08 at 10, 28; Tr.
    545, 1442.
    In December 2013, Global Ampersand entered negotiations with LightBeam Electric
    Company (“LightBeam”) to sell the Facilities as part of LightBeam’s potential initial public
    offering (“IPO”). Tr. 540, 975; see Tr. 963, 966, 971-72. LightBeam submitted its Form S-1
    Registration Statement to the Security and Exchange Commission (“SEC”) on January 13, 2015.
    16
    The Treasury Department’s Office of Housing and Energy oversees the Section 1603
    program. Tr. 1762. Grants may be given for both refurbished facilities and new facilities, although
    more grants were provided for the latter. Tr. 1786. As part of its administration of the Section
    1603 program, Treasury had an interagency agreement with the Department of Energy (“DOE”),
    and a DOE subdivision, National Renewable Energy Laboratory (“NREL”) reviewed Section 1603
    grant applications to determine eligibility, including an analysis of the placed-in-service date. Tr.
    1763. NREL would then make a recommendation to Treasury, which would decide whether the
    application should be granted. Tr. 1772, 1788. Treasury and NREL primarily focused on electricity
    production and testing relating to electricity, with a lesser focus on emissions testing. Tr. 1764-65.
    23
    Tr. 965, 968-69. In conjunction with the potential IPO, Deloitte & Touche LLP (“Deloitte”)
    rendered an audit opinion regarding Global Ampersand and its subsidiaries for the years ended
    December 31, 2014 and 2013, and concluded that there was substantial doubt as to the company’s
    ability to continue as a going concern, due in large part by the company’s inability to pay its debts,
    most of which were “related party debt that was forgiven.” Tr. 1005, 1014; DX 147 at 288, 294.
    Deloitte determined that both ACM 6 and ACM 4 were related parties to Global Ampersand for
    audit purposes. Tr. 1016-17; DX 147 at 300-01. The audit report stated that no principal payments
    had ever been made on the ACM 4 note as of that time, April 2015, and that the note had originally
    matured on May 25, 2011. DX 147 at 301.
    The S-1 listed total losses of $7,724,000 derived from the audited financial statements. Tr.
    981; DX 147-93. Lightbeam’s James Lavelle explained: “As we understood, [Global Ampersand]
    had had some operating difficulties in advance of our becoming involved with them; that they had
    retained an operations and maintenance engineering firm that was providing them with advice and
    management activities to upgrade the operating condition and performance of both projects.” Tr.
    981-82. The S-1 further indicated that Global Ampersand incurred losses of $9,635,000 in 2013.
    DX 147-28. According to the S-1, the plants required an extensive ramp up and testing period
    extending into 2013, and maintenance and repair costs were high. Tr. 998; DX 147-133.
    LightBeam never purchased Chowchilla and Merced, and the IPO was withdrawn in December
    2015. Tr. 995-96.
    Expert Testimony
    Plaintiffs called Mr. Anthony Foster, a professional engineer who has worked in the biomass
    power industry for the past 30 years, to render an expert opinion regarding the Facilities’ placed-
    in-service dates. Tr. 1051-52, 1057-58. 17 The Court accepted Mr. Foster as an expert in
    engineering, plant operations, and testing with respect to biomass burning, electricity-generating
    facilities. Tr. 1096.
    Defendant orally moved to exclude Mr. Foster’s expert report, PX 185. Tr. 1109-10.
    Defendant contended that significant passages of the expert report precisely mirrored the language
    in a letter sent by Mr. Kandolha to Congressman Costa on March 26, 2014. Tr. 1100-09. This
    language in Mr. Kandolha’s letter and Mr. Foster’s expert report states:
    Mr. Kandolha’s Letter                           Mr. Foster’s Expert Report
    Under the District rules, the date that the Under the District Rules, the date that the
    facilities first complied with their ATCs and facilities first complied with their ATCs and
    were lawfully able to operate under the were lawfully able to operate under the
    17
    Mr. Foster received an undergraduate degree in aeronautical engineering from California
    Polytechnic State University in 1969 and attended graduate courses at Carnegie Mellon University,
    New York University, and the University of Pittsburgh. Tr. 1051, 1068. In the 1970s, Mr. Foster
    designed a system to incinerate wood waste while correcting air emission issues. Tr. 1052. From
    approximately 1975 to 1985, Mr. Foster worked for Koppers Company as the assistant manager of
    engineering for the forest products division, where he developed designs for, and oversaw the
    conversion of approximately 20 power facilities. Tr. 1052-53, 1074-75.
    24
    California Health and Safety Code was August       California Health and Safety Code was August
    11, 2011 when the District accepted the results    11, 2011 when the District accepted the results
    of the plants’ successful testing and all          of the plants’ successful testing and all
    required pollution control and plant control       required pollution control and plant control
    equipment had been installed.                      equipment had been installed.
    In order for a power plant to be placed in         In order for a power plant to be placed-in-
    service, it must pass all of its critical          service, it must pass all of its critical
    preoperational testing. Merely synchronizing       preoperational testing. Merely synchronizing
    to the grid and producing electric is not          to the grid and producing electricity is not
    enough. It is also not enough to test some of      enough. It is also not enough to test some of
    the components. The entire, integrated unit        the components. The entire, integrated unit
    must be tested.                                    must be tested.
    DX 484; PX 185 at 10-11; see also PX 185 at 12.
    Mr. Foster testified that while he had received language to consider for his report from
    Plaintiffs’ counsel, he independently considered whether that language was appropriate to include
    in his report and stood by it as accurate, and “wrote every word” in his report. Tr. 1114-15, 1118.
    The Court denied Defendant’s motion to exclude Mr. Foster’s report, and noted that the
    issues Defendant raised affected the weight of Mr. Foster’s testimony—not its admissibility. Tr.
    1118-19.
    Mr. Foster opined that the Facilities were placed in service on August 11, 2011, and no
    earlier. Tr. 1158; see also PX 185 at 13. Mr. Foster testified that he arrived at his opinion by
    applying the IRS definition of “placed in service” as “delineated by five factors,” to the facts in the
    case. Tr. 1083, 1085. He reviewed a significant number of the NOVs the Facilities had received
    between 2008 and 2010, as well as the PPAs, but he did not review a comprehensive record of
    power generation at the Facilities between 2008 and 2010. Tr. 1097-98.
    Defendant called Todd Filsinger, a licensed mechanical engineer and a senior accredited
    appraiser with the American Society of Appraisers, who has been qualified as an expert
    approximately 10 or 20 times before, and has previously served as the Government’s expert on
    issues relating to Section 1603. Tr. 1814-15; DX 22 at 136. 18 The Court admitted Mr. Filsinger as
    18
    Mr. Filsinger received a bachelor’s degree in mechanical engineering from Colorado State
    University in 1985, and a master’s degree in business administration from the University of
    Colorado, with an emphasis on finance and management in 1990. Tr. 1795-96. Mr. Filsinger
    worked for R.W. Beck, an engineering consultancy, for approximately 13 years, and for PHB
    Hagler Bailly, where he worked with numerous utilities and power companies, analyzing assets,
    revenue requirements for acquisitions, and refurbishment costs. Tr. 1798-1801, 1805. Mr. Filsinger
    served as COO for Calpine Energy. Tr. 1806-09. Mr. Filsinger started Filsinger Energy Partners
    (“FEP”) in 2010, where he and his 25 employees provide consulting services, including valuations
    of power stations and equipment in the energy sector. Tr. 1809-10.
    25
    an expert in plant management, management and financing of energy companies and facilities,
    energy company and asset restructuring, and valuation of energy companies and assets. Tr. 1833-
    34. 19 Mr. Filsinger opined that Chowchilla and Merced were placed in service in May and August
    2008, respectively and testified on the valuation of the Facilities. Tr. 1876.
    Discussion
    Jurisdiction and Legal Standards
    The Court has jurisdiction over this action pursuant to the Tucker Act, 28 U.S.C. § 1491
    (2012). The Tucker Act provides this Court with jurisdiction over specific categories of claims
    against the United States, including those claims “founded either upon the Constitution, or any Act
    of Congress or any regulation of an executive department . . . in cases not sounding in tort.”
    § 1491(a)(1). A plaintiff who brings suit under the Tucker Act must “demonstrate that the source
    of substantive law he relies upon ‘can fairly be interpreted as mandating compensation by the
    Federal Government for the damages sustained.’” United States v. Mitchell, 
    463 U.S. 206
    , 216-17
    (1983) (quoting United States v. Testan, 
    424 U.S. 392
    , 400 (1976)).
    Because Section 1603 of the American Recovery and Reinvestment Tax Act of 2009
    (“ARRA”) requires the Secretary of the Treasury to provide a grant, upon application, to individuals
    who “place[d] in service specified energy property” between January 1, 2009 and December 31,
    2011, for a portion of the expense of such property, it is a money-mandating statute. Pub. L. No.
    111-5, Div. B, tit. I, § 1603, 123 Stat. 115, 364-66 (2009);
    id. § 407(d)(3); W.E.
    Partners II, LLC
    v. United States, 
    119 Fed. Cl. 684
    , 690 (2015); LCM Energy Sols. v. United States, 
    107 Fed. Cl. 770
    , 772 (2012); ARRA Energy Co. I v. United States, 
    97 Fed. Cl. 12
    , 21-22 (2011).
    The Court reviews claims for tax refunds and claims predicated on Section 1603 on a de
    novo basis. W.E. Partners 
    II, 119 Fed. Cl. at 690
    . Plaintiffs have the burden of proving entitlement
    to additional Section 1603 payments and the quantum of any such payments. WestRock Va. Corp.
    v. United States, 
    941 F.3d 1315
    , 1318 (Fed. Cir. 2019); WMI Holdings Corp. v. United States, 
    891 F.3d 1016
    , 1021 (Fed. Cir. 2018).
    Plaintiffs Have Not Demonstrated Entitlement to Additional Section 1603 Grants
    In this action, Plaintiffs challenge Treasury’s denial of over $22,000,000 in grants—the bulk
    of the Section 1603 grants they sought.
    At the outset, the Court addresses Defendant’s legal argument that the Internal Revenue
    Code bars Plaintiffs outright from receiving Section 1603 grants because the prior taxpayer, CalBio,
    claimed depreciation and PTCs in 2008, which were “allowable” as a matter of law because the
    IRS did not challenge CalBio’s depreciation deductions and PTCs. In so arguing, Defendant quotes
    dicta from Virginian Hotel Corp. of Lynchburg v. Helvering, 
    319 U.S. 523
    , 527-28 (1943), stating:
    19
    Plaintiffs opposed Mr. Filsinger’s admission as an expert on two grounds. First, Plaintiffs
    argued that Mr. Filsinger’s application of his industry experience to determine the placed-in-service
    date was irrelevant to the tax law analysis under Section 1603. Tr. 1828. Second, Plaintiffs argued
    that Mr. Filsinger’s testimony regarding fair market value of the Facilities as of January 1, 2011,
    was irrelevant to the calculation of basis for a grant under Section 1603. Tr. 1829-1832. The Court
    overruled both objections. Tr. 1833.
    26
    “Under our federal tax system there is no machinery for formal allowances of deductions from gross
    income. Deductions stand if the Commissioner takes no steps to challenge them.” Def.’s Am. Post-
    Tr. Br. 77 n.31. In Virginian Hotel, the Supreme Court recognized, however, that the precept of a
    deduction being “allowed” when unchallenged by the IRS does not universally apply.
    Id. at 526.
    The Court in Virginian Hotel continued: “Income tax returns entail numerous deductions. If the
    deductions are not challenged, they are certainly ‘allowed’ since tax liability is determined on the
    basis of the returns. Apart from contested cases, that is indeed the only way in which deductions
    are ‘allowed.’”
    Id. at 527
    (emphasis added). Here, where Plaintiffs are challenging these
    deductions and claiming the PTCs their predecessor, CalBio, took in 2008 were wrong, Defendant’s
    broad and unusual construction of allowability has no place. The fact that CalBio’s tax position
    was unaudited does not establish the allowability of the depreciation and PTCs vel non or prevent
    this Court from reviewing de novo whether these tax positions were proper.
    At issue in this action is whether the Facilities were “placed in service” within the 2009 to
    2011 statutory window authorized for Section 1603 grants. Plaintiffs claim the Facilities were
    placed in service in 2011, and that they are entitled to the full amount of grants. Defendant contends
    that Treasury correctly concluded that the Facilities were placed in service in 2008.
    When Were the Facilities Placed In Service?
    The Fifth Circuit has instructed that the “appropriate method for determining the year that
    an electric generating facility is placed in service is to analyze a taxpayer’s fact situation, using a
    common sense approach in the context of the policy behind the investment tax credit, the Treasury
    Regulations determining ‘placed in service,’ and the Revenue Ruling factors.” Sealy Power Ltd. v.
    Comm’r, 
    46 F.3d 382
    , 393 (5th Cir. 1995). The parties agree that the Facilities are open-loop
    biomass facilities that would qualify for the Section 1603 program if they were placed in service
    between 2009 and 2011. Under Treasury Regulation 1.46-3(d)(1)(ii), facilities are “placed in
    service” in the year when they are “placed in a condition or state of readiness and availability for
    [their] specifically assigned function.” See also JX 45 at 5. It is a question of fact whether the
    Facilities “were ready and available for specifically assigned functions” within the timeframe
    permitted by Section 1603. Armstrong World Indus., Inc. v. Comm’r, 
    974 F.2d 422
    , 429-30 (3d
    Cir. 1992). 20
    The Court must first determine what the Facilities’ “specifically assigned function” was, in
    order to decide when the Facilities were “in a condition or state of readiness and availability” to
    perform that function.
    The Facilities’ Specifically Assigned Function
    Plaintiffs contend that under both CalBio’s ownership from June 29, 2007 until December
    28, 2010, and under Akeida Onshore’s ownership (and Akeida Capital’s management) 21 from
    20
    In Sealy, the Fifth Circuit disagreed with the Tax Court’s legal standard for defining when
    an asset is placed in service, and therefore characterized the issue as a question of 
    law. 46 F.3d at 393
    .
    21
    Plaintiffs Ampersand Chowchilla Biomass, LLC and Merced Power, LLC are wholly owned
    subsidiaries of Global Ampersand, LLC, an entity wholly owned by ACM California, LLC, which in
    27
    December 28, 2010 until the present, these electricity-producing biomass Facilities had a multi-
    faceted function that would require certain outputs, type of sales, contractual performance, and
    standards of environmental compliance. In Plaintiffs’ view, the Facilities’ specifically assigned
    function was “to produce electricity on a baseload basis for sale to PG&E at the quantities required
    under the [Power Purchase Agreements], reliably, and in compliance with applicable law.” Pls.’
    Post-Tr. Br. 3. In contrast, the Government argues that the Facilities’ specifically assigned function
    was simply “to produce and sell electricity.” Def.’s Am. Post-Tr. Br. 82.
    The Court finds that the Facilities’ specifically assigned function was to produce and sell
    electricity. The record here, viewed against the requirements of the Treasury Regulations and the
    Revenue Ruling factors, does not support a finding that the Facilities’ function was to generate
    electricity at the capacity levels stated in their PPAs for sale to a single buyer, PG&E, meeting
    manifold environmental compliance requirements.
    To be sure, the PPAs were the cornerstone of the Facilities’ functioning as ongoing
    businesses concerns, as these agreements guaranteed an income stream and contemplated their
    long-term supply of electricity to PG&E. 22 But the PPAs were not as rigid and inflexible as
    Plaintiffs portray them to be. They did not, as Plaintiffs argue, require continuous operation at
    specified capacity levels as a condition of performance, and the parties negotiated amendments to
    these PPAs to permit the Facilities to operate at lower levels.
    Indeed, Plaintiffs’ detailed articulation of the Facilities’ function is very close to the
    characterization of an electricity-generating facility’s specifically assigned function the Sealy Court
    rejected as being unduly restrictive, i.e., “consistently sustaining generation levels near its rated
    
    capacity.” 46 F.3d at 392
    . In Sealy, the Fifth Circuit found that achieving ideal or near ideal
    production levels was not required for a facility to achieve its specifically assigned 
    function. 46 F.3d at 393
    . To the contrary, the Sealy Court found that the legislative history of the investment
    tax credit—which applies the same definition of “placed in service” as Section 1603—indicates
    that “Congress did not intend to impose the stringent requirement of regular achievement of
    anticipated production levels when it created the credit.”
    Id. The Sealy Court
    reasoned:
    In defining ‘placed in service,’ Treasury Regulation § 1.46-3(d)(1)(ii) neither states
    nor implies that the property must produce an anticipated or projected amount before
    it may be considered ready and available for a specifically assigned function.
    Neither do the examples in Treasury Regulation § 1.46-3(d)(2)(ii) and (iii)—
    turn is wholly owned by Akeida Environmental Fund LP (“Akeida Onshore”). DX 480. Akeida Capital
    Management (“Akeida”) controls Akeida Onshore.
    22
    The PPAs were also important to investors. A June 15, 2007 due diligence report by
    BayernLB—an early candidate for a tax equity investment—stated that Global Ampersand “has
    entered into a 15-year [PPA] to sell all electricity produced by the plants to Pacific Gas and Electric
    Company.” DX 248-1. A September 2008 Confidential Memo created “for the solicitation of tax
    equity investors to monetize the section 45 production tax credits . . .” states the same intention to
    sell electricity under the PPAs in the “investment considerations” section of the memo. DX 254 at
    2, 6. A February 2011 memo singles out the Facilities’ PPAs as the reason for “strong project cash
    flows.” DX 127-2. D.E. Shaw reviewed the Facilities’ PPAs when conducting due diligence before
    investing in the Facilities. Tr. 1497.
    28
    illustrating when property acquired for use in a trade or business or for the
    production of income is placed in service—support the . . . unduly strict construction
    of the statute.
    Id. at 394.
             As the Sealy Court recognized, Treasury Regulation § 1.46(d)(2)(iii) provides an example
    illustrating “placed-in-service” equipment that is operational but still undergoing testing to
    eliminate defects.
    Id. The Sealy Court
    explained: “This example acknowledges that defective
    performance—presumably performance below that which was anticipated or projected—does not
    bar an asset’s ‘placed in service’ designation.”
    Id. For the purpose
    of the “placed in service” test,
    it is sufficient that the “property be ready and available to play its role in an operating facility,
    regardless of the level of production attained.”
    Id. at 397.
             While purchasing the Facilities’ electricity under these PPAs, PG&E accepted performance
    at less than the capacity factors stated on the face of these agreements. Both at the time ACM 6, a
    special entity owned by Akeida Environmental Master Fund Ltd., made a loan to CalBio in May
    2009, and at the time Akeida Onshore purchased the Plaintiff LLCs in December 2010, Akeida was
    aware that the PPAs had been amended and that PG&E was not demanding performance at the
    stated capacity levels and was willing to waive or reduce performance penalties. In February and
    September 2009, for example, PG&E and CalBio entered into amendments incorporating a four-
    year penalty reduction in the event of the Facilities’ failure to meet capacity requirements—
    eliminating penalties entirely for 2009 to 2010 and waiving penalties if the Facilities performed at
    25 percent, 50 percent, and 75 percent of their target capacity factors in 2010-11, 2011-12, and
    2012-13, respectively. DX 88; DX 82.
    Permitting the Facilities to generate electricity at these lower capacity factors was not all
    bad for PG&E as it enabled these biomass Facilities to continue their contractual performance and
    entitled PG&E to Renewable Energy Credits under California law for procuring electricity from a
    renewable energy source, which was hard to come by at those times. The California state
    Renewables Portfolio Standard program established targets for investor-owned utilities like PG&E
    to procure a certain percentage of their energy from “renewable” sources including biomass, and if
    PG&E did not meet its RPS, it was subject to fines. At the time, there was not a large supply of
    renewable energy for PG&E to buy. So PG&E and CalBio (and later, Plaintiffs’ parent) mutually
    agreed to amend the PPAs to waive performance penalties for failure to achieve baseload capacity,
    increase revenue to the Facilities, and contribute to PG&E’s achievement of its RPS requirements.
    From a contractual perspective, it was in PG&E’s interest to maintain the viability of the Facilities
    so PG&E could acquire Renewable Energy Credits. From an environmental perspective, it was
    better to have biomass processed in a facility rather than being burned in open fields which yielded
    higher levels of toxic emissions. Thus, the parties’ course of dealing under the PPAs evinces a
    flexible contractual relationship permitting less than consistent baseload production.
    Akeida’s David Kandolha described the Facilities’ specifically assigned function in terms
    of their PPAs, stating, “[each Facility’s] financial purpose [was] to sell power to PG&E under its
    PPA.” Tr. 194. Further, Mr. Kandolha believed the Facilities were “supposed to produce at a
    steady, consistent rate, which is close to their capacity—rated capacity of these facilities is 10.6
    megawatts. And with a baseload facility, your objective is to produce as close to that base load
    amount as you can.” Tr. 103. But this taxpayer’s desire to produce as close to baseload as possible
    29
    did not mean, as Plaintiffs argue, that if the Facilities fell below this capacity, they could not be
    deemed to have been ready and available to perform their function. As the parties’ course of dealing
    under the PPAs indicated, compliance with the capacity factors stated in the PPAs was not
    “required” in order for the Facilities to be “in a condition or state of readiness and availability to
    perform” under their contracts. The history of the PPA amendments, PG&E’s willingness to accept
    less than baseload and waive penalties, indicate that the Facilities would do their best to achieve
    baseload production, but that baseload production was a target, not a mandatory minimum
    performance requirement. See Tr. 1657-58.
    Finally, the Court does not add the heightened requirement Plaintiffs suggest to the
    Facilities’ specifically assigned function—that they had to be operating in accordance with
    environmental laws and regulations—and that their failure to do so—receiving NOVs and fines—
    was equivalent to operating “illegally,” preventing them from meeting their specifically assigned
    function.
    The PPAs unsurprisingly required compliance with law and regulation. But Plaintiffs’
    contention that CalBio’s receipt of NOVs, emissions violations, and its successor’s entry of consent
    decrees in civil lawsuits in December 2010 and April 2011, meant that the Facilities were operating
    “illegally” such that they were not performing their specifically assigned function, goes too far.
    Achieving compliance with environmental law was not part and parcel of the Facilities’ function to
    produce electricity using biomass. Rather, producing electricity using biomass even with emissions
    violations avoided burning waste in open fields—a circumstance local environmental authorities
    viewed as more problematic than operating with emissions violations. According to the testimony,
    emissions issues were common for biomass plants at that point in time, and it was preferable from
    an environmental standpoint to keep these plants going and avoid wood and agricultural waste being
    burned in open fields.
    The PPAs do not support Plaintiffs’ contention that environmental considerations were
    paramount with respect to, or even integral to, the Facilities’ function. In the context of
    administering the PPAs, PG&E’s energy contract management team would not typically require
    information regarding a plant’s pollution control equipment capabilities and status. Tr. 913.
    Generally, PG&E would not review tests required by the San Joaquin Valley Unified Air Pollution
    Control District as part of determining whether a facility had commenced commercial operations.
    Tr. 897. While it is true that these biomass plants had hefty emissions violations and were under
    scrutiny by the federal and local environmental compliance agencies, they paid for the exceedances
    and continued operating at reduced levels to reduce emissions. See Tr. 1749-51.
    In sum, the Facilities’ specifically assigned function while operated under both CalBio and
    Akeida Onshore was to produce and sell electricity.
    Placed-in-Service Date
    To determine when Chowchilla and Merced were “in a condition or state of readiness and
    availability to” produce and sell electricity, the Court applies the five-factor test set forth in
    Oglethorpe Power Corp., et al. v. Commissioner and IRS Revenue Rulings. See Oglethorpe Power
    Corp., et al. v. Comm’r, 
    60 T.C.M. 850
    (1990); Rev. Rul. 84-85, 1984-1 C.B. 10; Rev. Rul.
    79-98, 1979-1 C.B. 103; Rev. Rul. 76-256, 1976-2 C.B. 46; Rev. Rul. 76-428, 1976-2 C.B. 47.
    While the Federal Circuit has not directly addressed this issue, the appellate courts that have
    30
    addressed a property’s placed-in-service date for tax purposes have applied these factors. 
    Sealy, 46 F.3d at 394-95
    ; 
    Armstrong, 974 F.2d at 434-35
    .
    The Oglethorpe factors for determining when property is placed in service are:
    1. The necessary permits and licenses for operating have been obtained.
    2. All critical tests necessary for proper operation have been performed.
    3. The unit has been placed in the control of the taxpayer by the construction
    contractor.
    4. The unit has been synchronized with the transmission grid.
    5. Daily operation of the unit has begun.
    Oglethorpe, 
    60 T.C.M. 850
    (1990).
    No single factor is dispositive, and the weight given to a specific factor depends on the facts
    of the case. Oglethorpe, 
    60 T.C.M. 850
    (1990) (requiring a “consideration and balancing
    of all the factors”); Green Gas Del. Statutory Tr. v. Comm’r, 
    147 T.C. 1
    , 51 (2016) (“Application
    of this multifactor test requires balancing the factors as applied to the specific facts of a case.”); see
    
    Sealy, 46 F.3d at 395
    (stating that the Oglethorpe factors “are only indicative of ‘placed in service’
    or ‘operational’ status” and all need not be met to find that a facility had been placed in service).
    The IRS has cautioned that these factors are only “guideposts” and that determining when property
    was placed in service requires examining the totality of the circumstances. I.R.S. Tech. Adv. Mem.
    201113025 (Apr. 1, 2011). Moreover, as recognized by the IRS in Technical Advice Memoranda,
    “one cannot simply take a ‘snapshot’ at a moment in time, as events before and after the key date
    must be considered to determine [when] the facilities . . . were placed in service . . . .” Id.; I.R.S.
    Tech. Adv. Mem. 200537034 (Sept. 16, 2005).
    Plaintiffs argue that both Chowchilla and Merced were placed in service on August 11,
    2011, when the Facilities produced baseload electricity at capacity factors required by their Power
    Purchase Agreements and in compliance with applicable law and the terms of their ATCs.
    Plaintiffs acknowledge that Oglethorpe factors three and four do not support their proposed
    August 11, 2011 placed-in-service date, as it is undisputed that Chowchilla and Merced were in
    CalBio’s control by 2009, at the latest, and that both Facilities were synchronized to the
    transmission grid in 2008—Chowchilla in May 2008 and Merced in September 2008. Tr. 48-49;
    see also Tr. 1087-88. Plaintiffs instead rely on Oglethorpe factors one, two, and five, arguing these
    factors support a placed-in-service date of August 11, 2011 for both Facilities. The Court addresses
    these three factors in turn.
    Necessary Permits and Licenses
    With respect to the first factor, Plaintiffs argue that the necessary permits and licenses for
    operating the Facilities were not obtained by 2008. PX 13; PX 23. Plaintiffs argue that the ATCs
    that the Facilities obtained in 2007, only gave them permission to operate conditionally and
    therefore do not indicate a readiness and availability to produce baseload electricity. Moreover,
    Plaintiffs contend that even though the Facilities had ATCs in 2008, and Chowchilla received its
    31
    facility-wide PTO in April 2009, the Facilities never complied with the terms of those ATCs and
    did not obtain Title V permits until 2011.
    Defendant contends that the only permit necessary to begin generating power was an ATC
    from the District, which Chowchilla received on April 19, 2007, and Merced received on February
    3, 2007. Tr. 1881; Def.’s Am. Post-Tr. Br. 87; PX 13 at 2; PX 23 at 2.
    The record supports Defendant’s position. It is undisputed that the Facilities received ATCs
    in 2007. The ATCs were the only permits necessary for the Facilities to begin producing electricity
    under the PPAs, and they began producing electricity under those permits in 2008. The Facilities
    notified the EPA in 2008 that they had begun initial operations. DX 34; DX 200. PG&E’s energy
    contract manager testified that compliance with local permitting was not something that PG&E
    considered in accepting the Commercial Operation Date, nor did PG&E consider whether the
    Facilities had installed and/or were operating with all of the equipment required under their permits.
    Tr. 902; see also JX 19-12. Defendant is correct that the ATCs and interconnectedness with the
    grid sufficed to render the Facilities “in a condition of readiness and availability” to produce and
    sell electricity.
    While Plaintiffs contend that the Facilities were not in compliance with conditions in their
    ATCs and local and federal environmental requirements, this did not mean that they were not
    “placed in service.” The ATCs were never revoked, and the receipt of NOVs did not nullify the
    ATCs. Rather, such violations were a fact of life for biomass plants at that time and the District
    permitting them to operate in the face of these NOVs was environmentally preferable to shutting
    down the Facilities and having agricultural and wood waste burned in open fields. Tr. 483.
    Plaintiffs’ suggestion that the Facilities cannot be deemed to have obtained the requisite
    permits because they failed to meet all of the ATCs’ conditions does violence to the legal regime
    in place: the District’s oversight of the Facilities via the ATCs, NOVs, and variance process, and
    its assent to the Facilities’ continued operations under their ATCs. Plaintiffs’ position ignores the
    reality that the permits remained in place, allowed operations, and were eventually converted into
    PTOs. Once the Facilities received and implemented their ATCs, they were ready and available to
    generate electricity and revenue. This occurred in 2008.
    Critical Tests Necessary for Proper Operations
    With respect to factor two, the parties differ as to what constitute “critical tests.” Plaintiffs
    contend that environmental tests required by the ATCs were critical. Defendant argues that the
    critical tests necessary for the Facilities to produce and sell electricity were “pre-parallel testing,
    which ensures that the Facility operates at the same frequency and phase as the electrical grid,” as
    well as testing under the O&M agreement, and testing under the PPAs. Successful pre-parallel
    testing allowed the Facilities to synchronize to the grid and begin selling electricity, which occurred
    on June 17, 2008, for Chowchilla and on August 24, 2008, for Merced. Tr. 1883-85, 1989-90; DX
    178, DX 151. The PPA testing regime required the Facilities to pass Initial Capacity Demonstration
    Tests by demonstrating that they could meet the PPA performance requirements for a duration of
    336 consecutive hours. JX 19-40. In 2008, PG&E accepted meter data demonstrating the Facilities’
    ability to meet the PPAs’ performance requirements for specific months in lieu of successful
    capacity test results. JX 17; JX 18. The Court finds that the critical tests necessary for proper
    32
    operation were pre-parallel testing and those specified in the PPAs, and that the Facilities passed
    these tests by 2008.
    Plaintiffs overstate the role that environmental compliance and testing have in the placed-
    in-service analysis, arguing that all critical tests necessary for proper operation included “operating
    legally and not emitting excessive amounts of pollution.” Pls.’ Post-Tr. Br. 6. Plaintiffs contend
    that tests that were critical for operation included those required by California law and by their
    ATCs: a source test, RATA test, and seven-day drift test. Chowchilla did not pass a source test
    until August 28, 2009, and continued to exceed the ATC’s maximum emissions for certain
    chemicals until 2011.
    Id. Chowchilla had not
    conducted a RATA test as of February 2011.
    Id. Merced was unable
    to pass a source test until October 20, 2009, and unable to pass a RATA test
    until September 25, 2009, and like Chowchilla, continued to exceed its emission limits in 2009 and
    2010.
    Id. Additionally, Plaintiffs argue
    that in 2008, neither Facility had critical systems that would
    have permitted environmental testing (including a CEMS system and an SNCR system).
    Id. at 20.
    While the Facilities clearly had environmental compliance issues, the record demonstrates that, in
    California, a biomass facility’s noncompliance with emissions requirements did not prevent that
    facility from being ready and available to perform its specifically assigned function of generating
    and selling electricity.
    Mr. Filsinger, Defendant’s expert in engineering, plant operations and testing for biomass
    facilities, persuasively opined that the environmental tests required by the ATCs were not critical,
    given that environmental compliance for a biomass facility was always “difficult” because of the
    significant variance in the makeup of the fuel used—biomass which was a “very inconsistent
    product,” as it “varie[d] hour by hour, day by day, week by week, month by month.” Tr. 1889,
    1987, 1999-2001; see also DX 197 at 29, DX 483 at 22. Mr. Filsinger testified that if the fuel was
    inconsistent, the fuel may be “wetter” and “more difficult to burn,” which would, for example,
    affect the Facilities’ “NOX profile.” Tr. 1986.
    Because the Facilities’ specifically assigned function did not include compliance with
    environmental law, the environmental testing requirements Plaintiffs emphasize were not “critical
    tests necessary for proper operation.” Passage of these tests was not necessary for the Facilities to
    generate and sell electricity. Indeed, under IRS regulations, examples of when a property “shall be
    considered in a condition or state of readiness and availability for a specifically assigned
    function[,]” include instances where “[e]quipment is acquired for a specifically assigned function
    and is operational but is undergoing testing to eliminate any defects.” Treas. Reg. § 1.46-
    3(d)(2)(iii).
    Daily or Normal Operations
    With respect to the fifth factor indicating that a Facility has been placed in service, that daily
    or normal operations had begun, Plaintiffs argue that neither Facility began daily operations until
    August 2011, as the Facilities suffered from repeated shutdowns and environmental compliance
    issues before that time. Tr. 2299-300. However, it is uncontroverted that the Facilities were
    generating and selling electricity in 2008, and that they generated revenue of $2,260,093 that year,
    and $8,866,767 in 2009. PX 103-7; DX 214-9. On its tax returns filed on June 1, 2009, CalBio
    designated Chowchilla’s placed-in-service date as May 15, 2008, and Merced’s, as July 1, 2008.
    Tr. 1539; DX 59. According to D.E. Shaw’s Mr. Hoover, these dates represented “[t]he first
    instance that the projects came online.” Tr. 1539. Here, as in Sealy, CalBio’s activities operating
    33
    these electricity-generating Facilities and performing under their long-term agreements with PG&E
    constituted the operation of a business even though they experienced some operational and financial
    problems. 
    See 43 F.3d at 397
    .
    In arguing that the Facilities were not conducting daily operations in 2008, Plaintiffs point
    to various pieces of emissions equipment that were either missing or ineffective—the Continuous
    Emissions Monitoring System, Continuous Opacity Monitoring System, and DAHS—and the fact
    that the Facilities were not producing electricity at the capacity factors required by the PPAs.
    Because emissions compliance was not integral to the Facilities’ function, those emissions
    compliance issues did not prevent the Facilities from operating. Although the capacity factors that
    Chowchilla and Merced achieved in 2008-10 were below the range stated to be required in the
    PPAs, PG&E accepted this level of performance, amended the PPAs to waive or reduce
    performance penalties, and continued to work with CalBio to keep the Facilities operational. The
    Court finds that daily operations began at both Facilities in 2008, when they first produced and sold
    electricity.
    Passage of Control and Synchronization to the Grid
    As Plaintiffs recognize, Oglethorpe factors three and four do not support a placed-in-service
    date of 2011. Rather, the evidence is clear that control passed to the Facilities’ owners in 2008, and
    it is uncontroverted that the Facilities were synchronized to the grid in 2008, had passed pre-parallel
    testing, and were released under their Interconnection Agreements with PG&E to sell electricity in
    the summer of 2008. The construction contractor, NPC, left the Facilities in September 2008, work
    packages were turned over to the owner that year, and the owner declared commercial operations
    that year and was receiving revenue that year—all indicia that control of the Facilities had passed
    to the owner. Tr. 1964-65; DX 168, DX 174.
    Conclusion
    In this Court’s view, all five Oglethorpe factors indicate that the Facilities were placed in
    service in 2008, while CalBio owned them. While some evidence suggests that Merced was not
    placed in service until early 2009, this does not help Plaintiffs. In an alternative argument, Plaintiffs
    attempt to have Akeida reap Section 1603 benefits for a time frame when Akeida had nothing to do
    with the Facilities and CalBio owned the Plaintiff LLCs that in turn owned the Facilities. Plaintiffs
    argue that even if this Court were to find that the Facilities were placed in service on or after January
    1, 2009, before Akeida acquired the property in December 2010, Plaintiffs, as subsidiaries of
    Akeida at the time the grant applications were filed in 2011, would be entitled to the Section 1603
    grants even though the Facilities had been placed in service by an unrelated entity, CalBio. Pls.’
    Post-Tr. Rebuttal at 9-10. The Section 1603 Program was intended to encourage construction of
    alternative energy facilities and investment in renewable energy sources and provided grants to
    entities that placed such renewable energy facilities in service. Back in 2009, Akeida had no role
    whatsoever with respect to the Facilities—it did not refurbish or place the Facilities in service at
    that time—CalBio did. In any event, the weight of the evidence indicates that both Facilities were
    placed in service in 2008.
    Plaintiffs’ position that the Facilities should not be deemed to have been placed in service
    until August 2011—when they operated at or close to capacity and passed their environmental
    testing, is dependent upon their characterization of the Facilities’ specifically assigned function as
    34
    operating at the capacity factors stated in the PPAs and in compliance with environmental law. But
    neither operating at these production levels nor achieving compliance with environmental laws was
    necessary for these Facilities to meet their specifically assigned functions of generating electricity
    and revenue.
    As Plaintiffs have failed to demonstrate entitlement to additional Section 1603 grants, the
    Clerk of the Court is directed to enter judgment for Defendant.
    s/Mary Ellen Coster Williams
    MARY ELLEN COSTER WILLIAMS
    Senior Judge
    35