Rocky Mountain Mobile Medical v. United States ( 2021 )


Menu:
  •      In the United States Court of Federal Claims
    No. 20-1936C
    (Filed: March 18, 2021)
    (Re-Filed: April 6, 2021) 1
    *********************
    ROCKY MOUNTAIN MOBILE MEDICAL,
    Plaintiff,
    v.
    Bid protest; pre-award bid
    THE UNITED STATES,
    protest; FAR 13.106-3(a)
    (2008); exchanges; best value
    Defendant,
    determination.
    and
    MEDEXPRESS AMBULANCE SERVICES, INC.,
    Intervenor.
    **********************
    Shaun C. Kennedy, Denver, CO, for plaintiff, with whom was Thomas
    A. Morales and Hannah E. Armentrout, of counsel.
    Geoffrey M. Long, Trial Attorney, United States Department of
    Justice, Civil Division, with whom were Brian M. Boynton, Acting Assistant
    Attorney General, Robert E. Kirschman, Jr., Director, and Douglas K.
    Mickle, Assistant Director, for defendant. Maj. Laura B. Bauza, United
    States Air Force, of counsel.
    Bradley L. Drell, Alexandria, LA, for intervenor.
    1
    This opinion was originally issued under seal in order to afford the parties
    an opportunity to propose redactions of protected material. The parties filed
    a joint document with proposed redactions on April 1, 2021 (ECF No. 49).
    We thus reissue this opinion with the proposed redactions.
    OPINION
    BRUGGINK, Judge.
    In this post-award bid protest, Rocky Mountain Mobile Medical
    (“RMMM”), alleges that the U.S. Department of the Air Force, U.S. Space
    Force (the “Air Force”) failed to conduct a fair and rational evaluation of
    each offeror’s quotation in accordance with the solicitation and the Federal
    Acquisition Regulation (“FAR”), resulting in a flawed contract award
    decision. Plaintiff filed a motion for judgment on the administrative record
    on January 22, 2021. Plaintiff seeks a permanent injunction preventing the
    agency and intervenor, MedExpress Ambulance Services, Inc.
    (“MedExpress”) from commencing performance on the contract, requiring
    the agency to conduct a reevaluation of quotations in accordance with the
    solicitation, and requiring the agency to create a new award determination.
    The government and intervenor filed their respective responses and the
    government also filed a cross-motion for judgment on the administrative
    record, all of which are fully briefed.
    Oral argument was held on March 12, 2021. Because the agency
    properly documented its decision and its analysis was reasonable, we grant
    defendant’s motion for judgment on the administrative record and deny
    plaintiff’s motion.
    BACKGROUND 2
    On May 8, 2020, the Air Force issued a solicitation seeking quotations
    from contractors to perform ambulance services at two military installations
    in Colorado Springs, Colorado, Peterson Air Force Base (“PAFB”) and
    Schriever Air Force Base (“SAFB”). The contract was for a twelve-month
    base year and four twelve-month option years, including a pre-priced 6-
    month extension of services. The agency set aside the solicitation as “100%
    For Small Business.” Solicitation, AR 43 (ECF No. 34 at 43).
    According to the representations made by the parties during the status
    conference held on December 23, 2020, it is apparent that plaintiff formerly
    served as the incumbent on the SAFB military installation contract.
    Following the agency’s award of this contract to MedExpress and plaintiff’s
    subsequent GAO protest, however, the agency elected to utilize a third-party
    bridge contract to service that base during the pendency of this protest.
    2
    The facts in the background are derived from the administrative record
    (ECF No. 34).
    2
    Additionally, the second location, the PAFB military installation contract, is
    currently being serviced by another contractor.
    The solicitation stated that the agency would select the quote
    providing the best value to the government considering technical capability,
    past performance, and price. The solicitation also allowed the government
    to perform a tradeoff between past performance and price, if it determined
    that to be justifiable and if it would result in providing the best value to the
    government. AR 256.
    The Air Force indicated in the solicitation that this would be “a
    competitive selection conducted in accordance with [FAR] 13.106-2(b)(3).”
    AR 258. There was no indication in the solicitation that FAR Part 15
    procedures would be used. Though not included in the solicitation, the Air
    Force checked boxes in the streamlined acquisition strategy summary
    (“SASS”) indicating that it would use the procedures of FAR Part 13 entitled,
    “Simplified Acquisition Procedures (“SAP”),” but did not check the box that
    would indicate that it was using FAR 15 procedures. AR 458. In the SASS,
    the agency gave its reasoning for selecting FAR 13 procedures and stated
    that because the “acquisition is less than $7M,” it would be able to utilize the
    SAP described in FAR Part 13. AR 458. Although, as plaintiff points out,
    the solicitation notified bidders that “exchanges” might be “conducted with
    one, some, or all offerors,” the term exchanges does not appear in FAR Part
    13, but it does appear in FAR Part 15. AR 258.
    Offerors were required to submit proposals in three separate
    volumes—technical capability, past performance, and price. The evaluation
    was based upon the ratings of these three factors. Technical capability was
    evaluated on a pass/fail basis. It was comprised of two subfactors, staffing
    and response time. To receive a “pass” rating for the technical capability
    factor, both of its subfactors had to receive a “pass” rating. If a proposal
    received a “fail” rating for either subfactor, then the proposal was not
    considered for award. A proposal’s technical capability had to receive a
    “pass” rating to proceed to the past performance and price evaluation. This
    volume was not to exceed six pages double-spaced, excluding a table
    depicting the staffing plan.
    Past performance was assessed on an overall performance confidence
    rating including “substantial confidence,” “satisfactory confidence,” “neutral
    confidence,” “limited confidence,” or “no confidence.” AR 257. The
    solicitation required offerors to submit two recent past performance reference
    citations. For each past performance reference citation, the agency assigned
    recency, relevancy and quality ratings. The solicitation defined recency as
    3
    “work completed or ongoing during the 3 years prior to the solicitation
    issuance of 08 May 2020.” AR 255. After evaluating the recency of a past
    performance, the agency would then assign a “recent” or “not recent” rating.
    If a past performance reference received a “not recent” rating, then it would
    not be evaluated for relevancy or quality, and the reference would not receive
    an overall performance confidence rating.
    The solicitation defined relevancy “as a present or past performance
    effort involving similar scope, magnitude, and complexity of effort as this
    solicitation.” AR 256. If a past performance reference received a “not
    relevant” rating, then the evaluation process was to end at that point, and the
    reference would not be evaluated for quality or given an overall performance
    confidence rating.
    The quality assessment was based upon past performance reference
    citations, the quality assessment definitions listed in table one of the
    solicitation, and information independently obtained by the Contracting
    Officer (“CO”). The agency then assigned an overall performance
    confidence rating based upon the definitions listed on Table two of the
    solicitation. AR 257.
    Price was evaluated in accordance with FAR 13.106-3(a) (2008), after
    the technical and past performance evaluations, to determine if the proposed
    price was reasonable and balanced. The solicitation required offerors to
    submit a firm-fixed price quote and detailed pricing data specifying the unit
    price and the extended amount for each contract line item number.
    A. Evaluation
    On July 7, 2020, the submission deadline, the agency received six
    proposals from six different offerors: Contractor A, RMMM, MedExpress,
    Contractor D, Contractor E, and Contractor F.
    The agency completed a preliminary review of all six offers for
    compliance with the solicitation instructions and initially found that three of
    the six were “non-compliant,” including Contractor D, Contractor F, and
    Contractor A. 3 AR 491. “Exchange notices” were sent to these three
    3
    Contractor D had pricing inconsistencies (essentially rounding errors) that
    were resolved. Contractor F did not submit any past performance references
    and stated they did not have DoD experience, but submitted two (2) non-
    DoD references as a result of the exchanges. Contractor A had rounding
    issues with pricing and technical volume was more than six (6), which
    4
    offerors, however, and all six offers were considered compliant after the
    issues were resolved. RMMM argues that these exchanges were an
    indication that the agency elected to use elements of FAR Part 15.
    MedExpress also included a three-page introduction letter along with
    its technical submission. Because the package collectively exceeded the six
    page limit, the Contracting Officer, Ms. Sheri L. Burks (“ CO”) removed the
    introductory material before forwarding the technical capability volume for
    evaluation. RMMM contends that MedExpress’s inclusion of the three-page
    introductory letter rendered its submission non-compliant and that its
    submission should have been excluded; that it was error for the CO to simply
    remove the introductory letter.
    The agency convened a Technical Evaluation Team (“TET”) to
    evaluate the technical capability of each quotation on a “pass/fail” basis.
    With the exception of Contractor A, all the offerors received an overall rating
    for both subfactors of “pass.” Contractor A received a “fail” rating for not
    meeting the response time requirements, making it ineligible for award.
    The CO then evaluated the remaining five quotes for past performance
    and price. Both Contractor D and MedExpress received an overall
    “substantial confidence” rating. RMMM received an overall “satisfactory
    confidence” rating. Contractor E received an overall “neutral confidence”
    rating, and Contractor F was not rated because the references it provided
    were not deemed relevant in accordance with the solicitation’s definition for
    relevancy. The CO’s evaluation of each offeror’s past performance is
    depicted in table one below:
    Table 1: Past Performance Evaluation
    Offeror       Recency Per     Relevancy Per   Quality Rating    Overall
    Citation          Citation      Per Citation    Confidence
    Rating
    Ref 1    Yes     Ref 1    Yes        Marginal       Satisfactory
    RMMM
    Ref 2    Yes     Ref 2    Yes       Satisfactory    Confidence
    CPAR     Yes     CPAR     Yes       Satisfactory
    S                S
    CPAR     Yes     CPAR     Yes       Satisfactory
    S                S
    Ref 1    Yes     Ref 1    Yes       Exceptional     Substantial
    Contractor D                                                        Confidence
    Ref 2    Yes     Ref 2    No         Not Rated
    exceeded the page limit per the instructions in 52.212-1 but corrected the
    pricing and technical volume to six (6) pages after exchanges.” AR 491.
    5
    Ref 1    Yes     Ref 1    Yes     Exceptional
    MedExpress     Ref 2    Yes     Ref 2    Yes     Satisfactory   Substantial
    Confidence
    CPAR     Yes     CPAR     Yes     Exceptional
    S                S
    Ref 1    Yes     Ref 1    Yes     Satisfactory    Neutral
    Contractor E    Ref 2    Non-    Ref 2    Non-    Non-Rated      Confidence
    Respon           Respon      (Non-
    sive             sive    Responsive
    )
    Ref 1    Yes     Ref 1    No       Not Rated     Not Rated
    Contractor
    Ref 2    Yes     Ref 2    No       Not Rated
    F
    AR 498.
    MedExpress received an overall “substantial confidence” rating based
    on information provided by the references and/or information available in
    the Contractor Performance Assessment Reporting System (“CPARS”)
    reports or the Past Performance Information Retrieval System (“PPIRS”)
    reports as part of an independent Government assessment. The CO found
    that MedExpress had “exceptional” and “satisfactory” quality ratings,
    allowing the government to have confidence in the contractor’s ability to
    successfully perform the contract. MedExpress submitted two references,
    both of which the CO determined were “recent” and “relevant” reference
    citations. Both references stated that MedExpress was an excellent partner
    and that they would award another contract to MedExpress. Additionally,
    the CO found that the contractor never provided services using expired
    vehicle permits, nor experienced staffing issues or delays. The CO also
    found that all of MedExpress’s quality ratings were “satisfactory” or
    “exceptional,” resulting in an overall “substantial confidence” rating.
    RMMM takes issue with the overall confidence rating assigned to
    MedExpress, contending that it should have been no higher than “neutral.”
    MedExpress’s first reference was for an ambulance services contract
    at Creech Air Force Base in Nevada. The reference for this contract was [
    ], the CO for the contract at Creech Air Force Base, who gave the following
    response to the question, “Has there ever been a time when the contractor did
    not have current employee certifications or vehicle permits?”: “No; there has
    not been anytime that contractor did not have current employee certifications
    or vehicle permits.” AR 495. She also gave the following response to the
    question, “Would you award another contract to this contractor? Why/why
    not?”: “Yes; Definitely would award another contract to this contractor.
    Their support to Creech EMS has been an outstanding partner.” AR 495.
    6
    MedExpress’s second reference was for its contract for ambulance
    services with the Louisiana Rural Ambulance Alliance, Inc. (“LRAA”), in
    which it provided “emergency medical response in the form of ambulance
    and/or personnel in times of disaster and in cooperation with Federal, State,
    and Local Governments.” AR 489. MedExpress further explained that it had
    performed “[m]ost recently to respond to the COVID pandemic in the New
    Orleans, Louisiana area.” AR 489. The contract type was indicated as firm-
    fixed-price at [   ] per day, and the contract was awarded competitively in
    2017 with performance ongoing. AR 489. MedExpress also submitted
    information that the LRAA contract’s annual dollar amount was “[to be
    determined], 2020 [year to date]: [    ].” AR 831.
    The Air Force solicited further information about the LRAA contract
    from [        ], the CEO of LRAA. [           ] gave the following response
    to the question, “Did the contractor exhibit/experience staffing issues or
    delays during performance?”: “Med Express has never experienced staffing
    issues or delays during performance. Med Express has consistently
    performed above expectations and provided leadership for not only Med
    Express crews but for other services responding.” AR 495.
    [          ] also gave the following response for MedExpress to the
    question, “Has there ever been a time when the contractor did not have
    current employee certifications or vehicle permits?”: “We have activated our
    contract with Med Express over seven times in the last 3 years; for every
    response/event MedExpress has always had current employee certifications
    and vehicle permits.” AR 495. Additionally, the CPARS report for
    MedExpress from September 2018 to September 2019 reflected
    “exceptional” ratings in quality, schedule, and management.
    Contractor D received an overall “substantial confidence” rating
    based on information provided by the references and/or information available
    in CPARS/PPIRS reports as part of an independent Government assessment.
    Similar to the past performance citations that MedExpress received,
    Contractor D also received high praise in responses from its three references.
    Although only one of the references cited was considered “relevant,” overall
    the quality rating provided for the recent and relevant reference citation was
    exceptional, leading to a “substantial confidence” rating overall. RMMM
    argues that this was error; that Contractor D should have been excluded
    because only one of its references was found to be relevant.
    RMMM received an overall “satisfactory confidence” rating based
    upon information provided by the references and information available in
    CPARS/PPIRS reports as part of an independent Government assessment.
    7
    RMMM received a “marginal” quality rating for its services at SAFB
    because the contractor provided these services using ambulance vehicles
    with expired permits and unpermitted vehicles. Additionally, after an
    inspection that occurred in May 2020, the government found that RMMM
    used “expired supplies, medications, and missing equipment vital to
    emergency services.” AR 499. Although these deficiencies were corrected
    in about three weeks during RMMM’s contract with SAFB, these issues
    lowered the government’s confidence that RMMM could successfully
    perform medical services according to solicitation requirements. RMMM
    argues that it should have been afforded the opportunity through “exchanges”
    to provide ameliorating information and that not receiving that opportunity
    was prejudicial error.
    RMMM offered two reference citations, the first reference was from
    its contract at the SAFB, and was submitted by [          ], a CO at this Air
    Force Base. He gave the following response to the question, “Would you
    award another contract to this contractor? Why/why not?”:
    No, after an anonymous tip from a former employee a thorough
    inspection was conducted for the contract. That inspection
    showed that the contractor had been using expired medical
    equipment to perform services on Schriever AFB. Attached is
    a copy of the cure notice that was provided to the contractor.
    Due to the contractor’s previous discrepancies, Schriever AFB
    has been conducting more thorough and frequent inspections
    to ensure the contractor is continuing to perform contractually.
    The contractor did cure their deficiencies, but the confidence
    that we had in their ability to protect Schriever was greatly
    diminished.
    AR 496. A response by the same reference to the question, “Has there
    ever been a time when the contractor did not have current employee
    certifications or vehicle permits?” was as follows: “Yes; there was an
    ambulance that expired April 2019, Feb 2019, and an ambulance that was
    never permitted.” AR 496. Although RMMM had been given the
    opportunity to address the negative past performance references and cured
    the discrepancies noted while completing its contract at SAFB, the Air
    Force’s confidence in the contractor’s ability to successfully perform was
    impacted according to the reference citation. The quality rating assigned for
    that reference citation was “marginal.”
    The second reference was from its contract at the United States Air
    Force Academy (“USAFA”) in Colorado Springs, CO, and was submitted by
    8
    [              ], a contracting specialist at this location. [   ] gave the
    following response to the question, “Would you award another contract to
    this contractor? Why/why not?”: “Yes, they have proven to perform in an
    environment that is not without risk and demands customer satisfaction.
    While I would always encourage competition to check the market conditions,
    they have in previous acquisitions for USAFA presented economical and
    satisfactory performance over time.” AR 496. A response by the same
    reference to the question, “Did the contractor exhibit/experience staffing
    issues or delays during performance?” was as follows: “Never to the point of
    jeopardizing the mission, had few to no corrective action reports over
    previous and current contract which were immediately addressed. Appears
    to be normal management/staff turnover and associated learning curve that
    comes with this turnover.” AR 496. The quality rating assigned for that
    reference citation was “satisfactory.”
    Additionally, the CPARS assessed for contract FA700014C0009 for
    the period Oct 2018-Mar 2019 reflected a “satisfactory” in quality, a
    “marginal” in schedule, and a “satisfactory” in management for a satisfactory
    quality rating for that citation. The CPARS assessed for contract
    FA255016C0001 for the period Oct 2018-Sept 2019 reflected a
    “satisfactory” in quality, a “satisfactory” in schedule, and a “satisfactory” in
    management, with an overall “satisfactory” quality rating for that citation.
    Finally, the CO evaluated price in accordance with FAR 13.106-3(a)
    to determine if the offeror’s quoted price was reasonable and balanced.
    Because the solicitation states that price will only be assessed on quotes that
    received a “pass” rating for both technical subfactors, only the five quotes
    which received a “pass” in technical capability were evaluated for price:
    Table 2: Price Evaluation
    Offeror   Technical Quality           Overall        Total Price     Difference in
    Capabilit Rating Per       Confidence                     Price compared
    y      Citation        Assessment                       to the IGE
    Rating
    [   ]   [   ]        [   ]            [ ]                [   ]       [       ]
    RMMM      PASS     Marginal, Sat,    Satisfactory   $4,677,600.00      [               ]
    Sat, & Sat       Confidence
    PASS     Exceptional &      Substantial          [   ]           [       ]
    Contractor            Not Rated        Confidence
    D
    MedExpre PASS        Exceptional,      Substantial   $5,282,100.00          [       ]
    ss                Sat, &           Confidence
    Exceptional
    9
    Contractor PASS      Sat & Non-      Neutral           [   ]            [   ]
    E               Rated (Non-     Confidence
    Responsive)
    PASS   Not Rated &     Not Rated          [   ]            [   ]
    Contractor
    Not Rated
    F
    AR 500.
    The CO conducted a price analysis comparing MedExpress’s quoted
    priced to the Independent Government Estimate (“IGE”) for the base period
    and all option years, which also included the pre-priced 6-month extension.
    She found that MedExpress’s prices for the base period was [       ] than the
    IGE of [           ] and [     ] for the option years. In conclusion, the CO
    determined that MedExpress’s evaluated price of $5,282,100.00 was fair and
    reasonable in accordance with FAR 13.103-3(a)(1).
    The CO stated that the solicitation allows the government to select an
    offer providing the best value considering all three factors. In her best value
    analysis, the CO stated that although the technical and past performance
    factors, when combined, are approximately equal to price, the solicitation
    allows the government to perform a tradeoff between past performance and
    price, if it determines that it is justifiable and will result in the best value for
    the government. Here, the CO found that although MedExpress’s price was
    higher than RMMM’s total price, MedExpress provided a higher overall
    performance confidence rating warranting a tradeoff with RMMM, which
    provided a lower overall performance confidence rating.
    The CO determined that significant value for the agency in terms of
    quality, schedule, and management exists between the past performance
    “satisfactory” and “substantial confidence” ratings, and thus, she found that
    paying slightly more for higher past performance ratings constituted the best
    value for the government. 4 The CO concluded that paying an additional
    4
    The CO explained that a contractor receiving a “substantial confidence”
    rating, with documented excellent past performance, gives the government
    confidence that “there is little to low risk in operations, compliance, legal,
    quality, and unsuccessful performance of these vital, life-saving, mission
    essential, emergency services.” AR 499. She also stated that a “satisfactory
    confidence” rating gives the government “a reasonable expectation that [the
    contractor] can perform these critical lifesaving services, however,” because
    issues exist with the contract, the government has questions regarding
    whether the contractor would be successful in executing the contract. AR
    499.
    10
    $604,500.00 over the course of five years of performance on the contract (the
    difference between $4,677,600.00 and $5,282,100.00), an additional
    $120,900 per year, was justifiable in view of the appreciable difference in
    past performance ratings. This represented less than a 13% difference over
    the contract’s lifetime. The CO found, however, that performing a similar
    tradeoff between RMMM and Contractor D was not necessary. Contractor
    D’s quoted price was $1,404,312.00 more than RMMM’s, while both
    Contractor D and MedExpress received the same “substantial confidence”
    rating.
    MedExpress’s past performance evaluation showed that it filled all
    required positions on time with the “necessary education, experience and all
    required certifications/licensing in accordance with the contract requirement
    and specifications 97% of the time during performance.” AR 498.
    MedExpress was evaluated as “very responsive when it comes to responding
    to any issues or concerns 95% of the time as well as very professional and
    adheres to what is required to provide continued mission support.” AR 498.
    The CO noted that the contractor was reported as actively responding to
    concerns with personnel to prevent any service issues within its control 98%
    of the time, and that MedExpress complied with regulations and proactively
    communicated regarding questions and concerns during performance.
    Because MedExpress’s past performance was exceptional, she concluded
    that the government could be confident that it would meet and exceed the
    contract requirements concerning quality, schedule, and management.
    B. Exchanges Prior to Award
    The solicitation stated that the agency was not required to conduct
    exchanges with all offerors, but that exchanges might be conducted with
    “one, some, or all offerors.” AR 258. The Air Force did in fact conduct what
    it characterized as exchanges prior to award, but only with Contractor F and
    Contractor A, regarding discrepancies with their respective quotes. The Air
    Force advised Contractor F that its quote failed to comply with the
    solicitation in that it did not submit past performance references as required
    by solicitation Addendum 52.212-1, section 1.4. AR 526. Although
    Contractor F submitted a past performance narrative, it failed to include the
    required references. Contractor F responded to the exchange notice that
    same day and provided the two past performance references. On July 16,
    2020, the agency sent Contractor F a second exchange notice asking it to
    address the technical acceptability requirement by providing a single-page
    explanation of how it would ensure employee compliance with certifications
    and licenses during contract performance. Contractor F furnished a single-
    page response.
    11
    On July 17, 2020, the Air Force sent a third exchange notice to
    Contractor F, concerning the technical acceptability of Contractor F’s quote.
    The agency notified Contractor F that its quote was deficient because it
    “restate[d] the requirement(s), [and] mention[ed] training, but [did] not
    include a clear approach for meeting the 8-minute response time.” AR 539.
    Contractor F was permitted to submit a single-page response to correct this
    discrepancy, which it did on July 20, 2020.
    On July 7, 2020, the agency notified Contractor A that its technical
    capability volume exceeded the six-page limit and that its prices were not
    rounded to the nearest dollar. Contractor A submitted a revised technical
    capability volume and corrected its pricing. The agency sent a second
    exchange notice to Contractor A on July 16, 2020, stating that its quote was
    deficient because it failed to provide a plan to meet the eight-minute response
    time requirement. Contractor A responded the next day. Contractor A’s
    revised approach still did not meet the response time requirements and it later
    withdrew from the competition.
    RMMM contends that, like Contractor F and Contractor A, it should
    have been notified of the agency’s concerns about its own past performance
    references. If it had been, it argues, RMMM could have explained or
    corrected the problems.
    C. RMMM’s Protest at GAO
    On September 17, 2020, the Air Force notified RMMM that its quote
    was not selected for award. RMMM filed a protest with the Government
    Accountability Office (“GAO”) on September 24, 2020. The basis for its
    challenge was that the agency allowed MedExpress’s technical volume to
    exceed the page limit and because its evaluation of past performance was
    unreasonable. RMMM argued that the agency should have ignored
    everything after the first six pages of the technical proposal, including the
    three-page introduction letter, effectively proposing that half the technical
    proposal be ignored. GAO dismissed the protest on December 16, 2020,
    concluding that the agency could and did sever MedExpress’s introductory
    letter from the technical capability volume; it was not necessary to consider
    only the three-page letter of introduction and the first three pages of the
    awardee’s technical quotation. Rocky Mountain Mobile Med., B-418788.2,
    
    2020 WL 7698817
     (Comp. Gen. Dec. 23, 2020). The GAO also found that
    the Air Force was reasonable in its evaluation of RMMM’s past performance
    references. 
    Id.
    12
    On September 17, 2020, the Air Force notified MedExpress that it
    would be the awardee. Rocky Mountain filed its bid protest here on
    December 21, 2020. Award has not yet occurred, pending resolution of this
    protest.
    DISCUSSION
    Our review is deferential in accordance with the standard set forth in
    the Administrative Procedures Act, 
    5 U.S.C. § 706
    , which is to say that we
    review agency action in a procurement for illegality and a lack of rationality.
    Impressa Construzioni Geom. Domenico Garufi v. United States, 
    238 F.3d 1324
    , 1332-33 (Fed. Cir. 2001). So long as the agency’s decision was not
    irrational or otherwise illegal, we will leave it undisturbed.
    RMMM brings four challenges: (1) the agency was required to, but
    did not, conduct discussions with RMMM to address adverse past
    performance information; (2) MedExpress’s technical capability volume
    should have been excluded as noncompliant; (3) the agency’s overall
    performance confidence rating was irrational because it incorrectly
    concluded that MedExpress’s LRAA past performance reference was
    “relevant”; (4) the agency treated RMMM unequally by relaxing its past
    performance evaluation of Contractor D and assigning it an overall past
    performance assessment of “substantial confidence,” rather than “neutral
    confidence,” despite the fact that Contractor D only had one relevant past
    performance reference. Plaintiff seeks permanent injunctive relief to enjoin
    the Air Force from continuing its award to MedExpress.
    When considering whether to grant a permanent injunction, the court
    must consider whether “(1) the plaintiff has succeeded on the merits, (2) the
    plaintiff will suffer irreparable harm if the court withholds injunctive relief,
    (3) the balance of hardships to the respective parties favors the grant of
    injunctive relief, and (4) the public interest is served by a grant of injunctive
    relief.” Centech Grp., Inc. v. United States, 
    554 F.3d 1029
    , 1037 (Fed. Cir.
    2009). Although an award of injunctive relief is based on consideration of
    this four-factor test, failure to achieve success on the merits is dispositive.
    See Career Training Concepts, Inc. v. United States, 
    83 Fed. Cl. 215
    , 219
    (2008) (“[A] permanent injunction requires actual success on the merits.”).
    For the reasons below, we find that all four of plaintiff’s challenges lack merit
    and it is therefore unnecessary to consider the last three factors. We consider
    each of plaintiff’s arguments in turn.
    A. The Air Force Reasonably Conducted Exchanges with Offerors by
    Following the Simplified Acquisition Procedures of FAR Part 13
    13
    RMMM argues that the Air Force failed to conduct discussions in
    accordance with FAR 15.306 and FAR 15.307, and thus, the agency’s
    evaluation was arbitrary and capricious. Although plaintiff acknowledges
    that the solicitation was issued under FAR Part 13 procedures, and that these
    procedures provided the agency more flexibility than FAR Part 15, it argues
    that by conducting exchanges with some offerors, the agency signaled its
    intent to incorporate elements of FAR Part 15 generally. Thus, once the
    agency elected to exercise its right to conduct discussions under the SAP of
    FAR Part 13, the agency was obligated to comply with both the procedural
    requirements of FAR 15.306 and FAR 15.307.
    There is no question that the agency engaged in what it termed
    exchanges with two of the offerors, and that such exchanges are more
    typically associated with FAR Part 15 procedures. Indeed, there is no
    reference to them in FAR Part 13. As plaintiff points out, FAR Part 13 gives
    the contracting officer broad discretion in fashioning suitable evaluation
    procedures, including the possibility of incorporating procedures prescribed
    in Parts 14 and 15. FAR 13.106-2(b)(1). RMMM’s argument is that, having
    chosen, in effect to exercise this option, the agency did not go far enough and
    failed to apply the exchange process to plaintiff.
    RMMM argues that what the agency did was conduct discussions
    under FAR 15.306(d)(3) which requires the CO to “indicate to, or discuss
    with, each offeror still being considered for award, deficiencies, significant
    weaknesses, and adverse past performance information to which the offeror
    has not yet had an opportunity to respond.” FAR 15.306(d)(3). Having done
    so, it argues that the agency’s communications were unequal because the
    agency did not disclose adverse past performance deficiencies to RMMM
    and did not permit it to explain the deficiencies. 5 RMMM also argues that
    the discussions violated FAR 15.307(b) which requires that each contractor
    5
    RMMM claims that, contrary to [        ] response, it maintained the Colorado
    Department of Revenue Emergency Vehicle Equipment Authorization and
    El Paso County Board of County Commissioners Ambulance Service
    License without lapse. RMMM states that it would have “further explained
    that the local El Paso County permit referenced by [              ] did not even
    apply to Rocky Mountain’s performance of the SAFB contract.” Pl’s Mem.
    at 34. Plaintiff adds that it would have also explained mitigating information,
    that the expired medical supplies referred to in [       ] response are included
    on the U.S. Federal Drug Administration’s Drug Shortage List because of a
    supply chain shortage caused by the COVID pandemic.
    14
    “be given an opportunity to submit a final proposal revision” at the
    conclusion of discussions. FAR 15.307(b).
    The most basic difficulty with plaintiff’s argument is that the agency
    did precisely what it advertised it would do: have exchanges with some but
    not all bidders. There is a clear warning in the solicitation that the agency
    reserved the right to conduct “exchanges” with some, all, or none of the
    bidders. RMMM thus got precisely what it gambled on. 6 If, as plaintiff
    argues, the possibility of exchanges would seem to be a reference to FAR
    Part 15, the agency simultaneously disavowed such an intent by stating that
    such communications could be with a limited number of bidders, which, as
    plaintiff currently argues, was something the agency did not have the option
    of doing. Plaintiff contends that the exchanges actually held were conducted
    pursuant to 15.306(d), which specifically requires access by all bidders to the
    exchange process.
    In addition, if RMMM thought that the agency’s description of
    potential exchanges was inconsistent with FAR Part 15, the time to complain
    of that was prior to bidding. 7 While it argues that it was fooled into thinking
    that perhaps the agency had in mind the more selective, benign
    communications offered by 15.306(a) or (b), the solicitation is not so limited.
    The potential for mischief should have been apparent. In any event, the
    solicitation did not contemplate use of a competitive range, which is
    presumed under section 15.306(b) and (d), another dissonance which
    RMMM should have picked up on.
    Plaintiff responds that Dubinsky v. United States, 
    43 Fed. Cl. 243
    (1999), stands for the proposition that a solicitation conducted pursuant to
    FAR Part 13, must also comply with the procedural requirements of FAR
    15.306 and FAR 15.307, as “it is not ‘appropriate’ for an agency to cherry-
    pick which FAR Part 15 procedures to apply.” Pl. Mem. at 22-23 (citing
    Dubinsky, 43 Fed. Cl. at 264). The facts of Dubinsky are distinguishable,
    however. The agency in that case did not inform offerors that the agency
    was using SAP under FAR Part 13, nor did the solicitation specifically warn
    bidders of the possibility of exchanges with some bidders. As a result, the
    6
    The GAO has found that it was “not legally objectionable” for a CO to
    follow a provision of a solicitation that reserved the right to conduct
    discussions with any or all offerors, even where that solicitation was issued
    pursuant to FAR 13. Oregon Innovative Products, B- 231767, 
    1988 WL 227585
     (Comp. Gen. Aug. 2, 1988). We agree.
    7
    Blue & Gold Fleet, L.P. v. United States, 
    492 F.3d 1308
    , 1313 (Fed. Cir.
    2007).
    15
    Dubinsky court was “obligated to analyze the agency’s conduct under the
    rubric of Part 15.” 
    Id.
     The court noted that “[i]f simplified procedures under
    Part 13 had been utilized, then many of plaintiff’s concerns about the conduct
    of discussions in this procurement would be irrelevant,” because “[t]he
    simplified acquisition procedures in Part 13 allow contracting officers
    considerable flexibility in the contract award process.” Id. at 254. 8 Of course
    such simplified procedures were called out in this procurement.
    In short, the agency may have announced the creation of a platypus of
    a procurement, drawing bits and pieces from various practices, but RMMM
    cannot legitimately complain that it had reason to be surprised at what
    actually happened. Alternatively, RMMM was on notice that the agency had
    created what it argues now is a potentially illegal syncretism of processes.
    B. The Agency Rationally           Evaluated    MedExpress’s      Technical
    Capability Volume
    RMMM argues that because the solicitation limited the technical
    volume to six pages and warned that quotes not meeting the solicitation
    requirements “may be considered non-compliant,” the agency should have
    considered MedExpress’s proposal as non-compliant for exceeding the page
    limit. AR 245. While the CO removed MedExpress’s introductory letter
    before referring the technical proposal to the TET, RMMM argues that the
    proper response should have been to disqualify the entire proposal or
    evaluate only the first six pages of the total submission. Pl’s Mem. at 39
    (citing Board of Regents of Nev. Sys. of Higher Educ. on Behalf of Desert
    Res. Inst. v. United States, 
    132 Fed. Cl. 435
    , 452 (2017)). RMMM asserts
    that it was prejudiced because MedExpress’s introduction letter provided a
    description of MedExpress’s experience with similar projects, its technical
    capabilities, and approaches to ambulance service performance.
    The government responds that the agency enforced the page
    requirement for the technical capability volume because the CO submitted
    8
    In its reply, plaintiff argues that the court’s alternative holding in Dubinsky
    supports its argument that the Air Force was required to follow FAR Part 15.
    We disagree. In Dubinsky, the court alternatively found that even if that
    procurement was conducted under FAR Part 13, FAR 15.307(b) would apply
    because “defendant conceded that FAR 15.306 applied.” Dubinsky, 43 Fed.
    Cl. at 263. The court held that, having conceded that FAR 15.306 applied to
    that procurement, the agency could not sever the applicability of FAR
    15.307(b). Here there was no such concession.
    16
    the copy of MedExpress’s technical capability volume, but not the
    introductory letter. Indeed, plaintiff concedes that there is no indication in
    the record that the agency ever reviewed the introduction letter. Pl’s Mem.
    at 38. The government also argues that there is no authority limiting the Air
    Force to either rejecting the proposal or lopping the last three pages off.
    We agree with the government. The CO was reasonable in enforcing
    the page-limit requirement by discarding MedExpress’s introductory letter
    prior to sending the balance to the evaluators. 9 In the absence of any
    evidence that the introductory letter impacted the evaluation, the letter of
    introduction did not give MedExpress any advantage over the others. 10
    C. The Air Force Rationally Found MedExpress’s Past Performance
    Relevant
    RMMM asserts that the Air Force irrationally found that the past
    performance reference for MedExpress’s LRAA contract was relevant,
    resulting in an irrational overall performance confidence assessment rating
    for MedExpress. RMMM argues that the agency failed to show adequate
    justification for its decision that MedExpress’s LRAA past performance
    reference satisfied the relevancy requirement. RMMM also asserts that the
    agency relied on MedExpress’s description of its work performed under the
    LRAA contract, without conducting its own investigation to verify its
    relevancy.
    RMMM contends that MedExpress’s LRAA contract was not relevant
    under the solicitation’s definition, which defined relevancy as “a past or
    present past performance effort involving similar scope, magnitude, and
    complexity of effort as this solicitation.” AR 256. RMMM argues that there
    are several issues with MedExpress’s LRAA contract, causing the past
    9
    Plaintiff’s argues in its reply that the Air Force’s “acceptance of
    MedExpress’s noncompliant proposal,” constituted an inconsistent
    application of the solicitation requirements because the Air Force required
    Contractor A to revise its noncompliant proposal. Pl’s Reply at 18. (ECF
    No. 40 at 18). By disregarding the introductory letter, however, the Air Force
    enforced the page-limit requirement.
    10
    In Board of Regents, the CO’s decision to include the preliminary materials
    in the page limit rather than excluding them, was in accordance with the
    solicitation and the decision thus does not represent a controlling rule of
    procurement law. Board of Regents, 132 Fed. Cl. at 452.
    17
    performance to fall short of the solicitation’s definition requirement that the
    contract be similar in magnitude and complexity.
    First, RMMM argues that although MedExpress’s past performance
    volume indicated that the price of the LRAA contract was “[         ] per day,”
    the volume lacked detail on the number of days included in the contract
    performance. AR 489. It points out that the LRAA contract reference, [
    ], stated that the LRAA “activated [its] contract with Med Express over seven
    times in the last 3 years,” without, however, providing any further
    information on the total number of days of contract performance. AR 320.
    Plaintiff argues that the agency did not explain how it came to the conclusion
    that the contract’s total dollar value was over [           ]. Thus, RMMM
    contends that there was no basis to conclude that the LRAA contract was
    similar in magnitude to the solicitation.
    RMMM also argues that MedExpress’s LRAA contract lacks the
    same “complexity of effort” required by the solicitation’s relevancy
    definition. RMMM states that the only similarity between the two contracts
    is that they are both for ambulance services. RMMM argues that the LRAA
    contract and the current solicitation are dissimilar, as the LRAA was for as
    services as needed and was an augmentation to the services of other entities,
    whereas the present solicitation requires the contractor to be the sole provider
    of services 24 hour per day services, every day of the year. Additionally, the
    LRAA contract was not providing services at a federal facility, while this
    solicitation requires services to be provided at a military installation. Thus,
    plaintiff argues that the agency’s relevancy assessment of the LRAA contract
    was arbitrary and capricious.
    RMMM thus concludes that MedExpress’s past performance volume
    only provided one relevant reference, disqualifying it from receiving a
    “substantial confidence” rating. Instead, because MedExpress’s LRAA past
    performance reference was not relevant to the solicitation, it should have
    been assessed a “neutral confidence” rating.
    We disagree. The agency’s evaluation of MedExpress’s past
    performance LRAA contract reference was rational. First, the solicitation
    points out that “The past performance assessment [is] subjective.” AR 255.
    While the determination is subject to a review for reasonableness, the Federal
    Circuit has held that an agency’s “determination of relevance is owed
    deference as it is among ‘the minutiae of the procurement process,’” which
    this court “‘will not second guess.’” Glenn Def. Marine (ASIA), PTE Ltd. v.
    United States, 
    720 F.3d 901
    , 911 (Fed. Cir. 2013) (quoting E.W. Bliss Co. v.
    United States, 
    77 F.3d 445
    , 449 (Fed. Cir. 1996)).
    18
    RMMM’s claim that the agency’s determination of the LRAA
    contract’s total dollar value was not supported by the record is refuted, as it
    conceded during oral argument, by the amended record which includes
    MedExpress’s statement that the LRAA contract’s total dollar value was [
    ] as of August 27, 2020. AR 831. As to RMMM’s assertion that the LRAA
    effort is not similar in complexity to this solicitation, this solicitation does
    not define complexity, and the agency’s relevancy assessment was within its
    discretion and not unreasonable. In the CO’s view, MedExpress’s LRAA
    contract was relevant because the LRAA’s description of work and dollar
    value matched the solicitation’s requirements of complexity of effort,
    magnitude, and scope:
    [T]he primary services of both efforts is the provision of
    medical transportation and support services. It is apparent that
    [MedExpress’s] reference involves the very type of medical
    services contemplated by the [solicitation]. Additionally, both
    efforts require the awardee to provide qualified personnel and
    to comply with applicable professional standards and license
    requirements.
    AR 448. We have no basis for overturning this assessment.
    While RMMM argues that the record “contains no explanation,
    contemporaneous or otherwise” of the agency’s decision for evaluating
    MedExpress’s past performance for relevancy, the record documents the
    pertinent facts leading to the agency’s decision. Pl.’s Mem. at 34. The
    agency developed a chart to evaluate the recency of each offeror’s past
    performance. The chart had two columns detailing factors that the agency
    used to determine whether each past performance reference was relevant, the
    citation’s description of work and total dollar value. For the description of
    work column, the agency noted that the LRAA contract required MedExpress
    to provide emergency medical services “in the form of Ambulance Services
    and personnel in the time of a disaster and in corporation with Federal, State,
    and Local Government,” and the most recent emergency was a “response to
    COVID pandemic in New Orleans.” AR 503. For the total dollar value
    column, the agency noted that the LRAA contract’s value was “[                    ]
    YTD 2020/ [          ] per unit, per day, as required for disaster relief efforts.”
    AR 503. After reviewing all of the pertinent information provided by
    MedExpress including the responses from the LRAA reference, [                    ],
    the agency determined that the LRAA contract was relevant because the
    LRAA’s description of work and total dollar value matched the solicitation’s
    requirements of complexity of effort, magnitude, and scope.
    19
    There is no legal support for RMMM’s argument that the agency
    should have conducted an independent verification of the LRAA contract for
    relevancy, rather than relying solely on MedExpress’s past performance
    volume and [            ] responses. Even if the solicitation did require an
    independent investigation, which it does not, RMMM fails to acknowledge
    that the agency did conduct independent research; the past performance
    evaluation was based on the responses of the past performance reference
    citations that each offeror submitted, and any other information that the
    government obtained independently, including the government’s
    CPARS/PPIRS reports. In fact, MedExpress’s “substantial confidence” past
    performance rating was “based on information assessed as provided by the
    references and/or information available in CPARS/PPIRS reports as part of
    an independent Government assessment.” AR 495.
    Plaintiff concedes that the government correctly recognized that the
    solicitation did not only define “relevant,” but also provided a definition for
    “not relevant.” The solicitation defined “not relevant” as a “present or past
    performance effort involving little or none of the scope and magnitude of
    effort as this solicitation.” AR 256. The binary nature of the relevance
    determination means that only those past performance efforts involving
    “little or none” of the scope and magnitude of effort of the solicitation are
    not relevant. Thus, the agency’s relevancy assessment was rational, as the
    agency could not conclude that the LRAA reference involved “little or none
    of the scope and magnitude of effort” as compared to the solicitation, such
    that the effort was “not relevant.” AR 256.
    D. The Agency’s Evaluation of Contractor D’s Past Performance
    Assessment did not Prejudice RMMM
    We will assume for argument’s sake that the agency’s past
    performance evaluation of Contractor D was contrary to the solicitation,
    which required each contractor to submit two references, and that both
    references had to be “recent” and “relevant.” AR 249. Contractor D
    remained in the competition despite the agency’s rejection of one of its past
    performance references as, among other things, irrelevant. RMMM states
    that if RMMM knew that the agency would deviate from the evaluation
    criteria, RMMM would have prepared its past performance volume
    differently by omitting the reference for the SAFB contract which resulted in
    an adverse rating and argues that it would have received a higher overall
    performance confidence rating if the agency only evaluated its USAFA
    contract past performance reference.
    20
    Plaintiff’s argument would have more traction if Contractor D had
    been selected for award. But it was not. At the end of the day, plaintiff was
    not competing against Contractor D, it was competing against MedExpress,
    which did submit two relevant past performance references. For a protestor
    to prevail in a bid protest, it must show that, absent the alleged error, there
    would be a reasonable likelihood of the protestor receiving the contract. Linc
    Gov’t Servs., LLC v. United States, 
    96 Fed. Cl. 672
    , 695 (2010). Even if
    Contractor D received a “neutral confidence” rating, it would not affect the
    agency’s decision that MedExpress’s proposal presented a better value to the
    government than RMMM’s proposal. We therefore fail to see the prejudice
    to plaintiff nor any basis for taking the award away from intervenor.
    Trying to reconstruct the procurement in light of the agency’s
    apparently erroneous treatment of Contractor D would be highly unfair to
    MedExpress and would necessarily involve accepting a contrived and highly
    speculative scenario. It involves an assumption that, if RMMM had known
    that it could get by with one reference, it would have deleted the problematic
    one, and that the agency would treat that one reference as so superior that,
    like Contractor D, it would vault RMMM’s assessment to “outstanding.”
    Presumably others would have had the same opportunity, however, further
    muddying a conclusion that the result would have been different. It is much
    simpler to deal with the undisputed facts: MedExpress and RMMM were the
    two finalists; both were given the opportunity and obligation to furnish two
    past performance references; the agency was impressed with intervenor’s
    prior performances and justifiably concerned about plaintiff’s. Even
    assuming a foul up with respect to Contractor D, that fact was an irrelevant
    sideshow.
    CONCLUSION
    Plaintiff asserts that the agency erred in several ways, and that
    collectively, these mistakes warrant the court’s intervention on a theory that
    the whole (a general verdict of unfairness) is greater than the sum of its parts.
    We are not permitted to take a gestalt approach to bid protests, however. To
    overturn an agency action, we must find a discrete, prejudicial error. This
    may not have been a textbook procurement, but none of the alleged errors
    individually or collectively permit the court to reverse. Therefore, no relief
    is warranted, and we deny plaintiff’s motion for judgment on the
    administrative record and grant defendant’s cross-motion. The Clerk of
    Court is directed to enter judgment for defendant. No costs.
    21
    s/Eric G. Bruggink
    ERIC G. BRUGGINK
    Senior Judge
    22