H&M Associates, LLC. v. United States ( 2023 )


Menu:
  •              IN THE UNITED STATES COURT OF FEDERAL CLAIMS
    ______________________________________
    )
    H&M ASSOCIATES, LLC,                   )
    )
    Plaintiff,           )   No. 22-110C
    )
    v.                         )   Filed: March 31, 2023
    )
    THE UNITED STATES,                     )
    )
    Defendant.           )
    ______________________________________ )
    OPINION AND ORDER
    Plaintiff H&M Associates, LLC filed this action against the United States alleging that the
    United States Air Force (“USAF”) improperly terminated for default its contract to replace a
    centrifugal Trane chiller at Joint Base San Antonio-Lackland. Before the Court is Defendant’s
    Motion to Dismiss pursuant to Rule 12(b)(1) of the Rules of the United States Court of Federal
    Claims (“RCFC”), for failure to establish subject-matter jurisdiction, and Rule 12(b)(6), for failure
    to state a claim upon which relief may be granted.
    For the reasons discussed below, the Court finds that it lacks subject-matter jurisdiction as
    to any claim premised on a contractual modification or an equitable adjustment (whether raised
    affirmatively or defensively) because no claim was submitted to the contracting officer for final
    decision or certified in accordance with the Contract Disputes Act (“CDA”), 
    41 U.S.C. §§ 7103
    (a)–(b).    However, the challenge to the default termination falls within the Court’s
    jurisdiction, and Plaintiff has at the pleadings stage sufficiently stated a claim upon which relief
    may be granted. Accordingly, Defendant’s Motion to Dismiss is GRANTED in part and
    DENIED in part.
    I. BACKGROUND
    A.     Factual Background 1
    On August 13, 2020, the USAF issued a solicitation to replace a chiller at Joint Base San
    Antonio-Lackland in San Antonio, Texas. Pl.’s Compl. ¶ 7, ECF No. 1. The project was 100%
    set aside for Women Owned Small Businesses. 
    Id. ¶ 8
    . The solicitation required “demolition and
    replacement of the [c]entrifugal chiller, DDC EMCS, pumps, and of limited piping, hangers,
    electrical circuits and components, appurtenances and incidental related work.” 
    Id. ¶ 11
    . The
    solicitation indicated that Defendant would provide the awardee with one set of contract drawings
    and specifications and a virtual site visit. 
    Id.
     ¶¶ 16–17.
    On September 30, 2020, the USAF awarded a fixed price contract to Plaintiff. 
    Id. ¶ 12
    .
    “The contract required Plaintiff to deliver to Defendant all labor, equipment and materials to
    demolish and replace a [c]entrifugal Trane [c]hiller along with various components and
    appurtenances[.]” 
    Id. ¶ 13
    . Additionally, the contract delivery schedule required “delivery of
    design and submittal of long lead items on or before 100 days after receipt of the Notice to
    Proceed” (“NTP”); “the installation of the replacement Trane [c]hiller on or before 120 days after
    receipt of the NTP”; and “completion of all [c]lose out [a]ctivities on or before 30 days after receipt
    of [the] NTP as set forth in FAR [Federal Acquisition Regulation] 52.211-10 ‘Commencement,
    Prosecution, and Completion of Work.’” 
    Id. ¶ 14
    .
    1
    The following background facts are compiled from Plaintiff’s Complaint and
    supplemented in part by materials in the appendix to Defendant’s Motion. See Pl.’s Compl., ECF
    No. 1; App. to Def.’s Mot. to Dismiss Pl.’s Compl., ECF No. 6-1. Each of those materials are
    referenced in or integral to the Complaint, and Plaintiff does not dispute their authenticity.
    Bell/Heery v. United States, 
    106 Fed. Cl. 300
    , 307–08 (2012), aff’d, 
    739 F.3d 1324
     (Fed. Cir. 2014)
    (holding that a court may consider materials specifically referenced in the complaint or integral to
    it without converting a motion to dismiss into a motion for summary judgment).
    2
    On October 7, 2020, Plaintiff, a San-Antonio Trane representative, local installers,
    electricians, and other service providers participated in a site visit. Id. ¶ 19. On October 9, 2020,
    the USAF contracting officer (“CO”), issued a Partial NTP for the design and submittal activities
    and set the 100-calendar-day period of performance as October 13, 2020, to January 20, 2021. Id.
    ¶¶ 9, 21–22, 26.
    Soon thereafter, from October 18 to November 18, 2020, Plaintiff’s owner (and
    representative), Ms. Maumita Mandal, traveled to India because her mother suffered a head injury
    and later passed away. Id. ¶ 24. After Ms. Mandal’s return from India, Plaintiff called the contract
    specialist and the CO several times between November 18 and December 1, 2020, but was unable
    to reach them because their voicemail boxes were full. Id. ¶ 25; ECF No. 6-1 at 4, 42. Between
    December 2, 2020, and January 7, 2021, Plaintiff submitted four requests for information (“RFI”):
    RFI 1 sought information on certain technical requirements and the requested configuration for the
    chiller; RFI 2 asked for make and model numbers for motors that needed replacement; RFI 3
    sought confirmation on licensing; and RFI 4 followed up on questions in RFI 2 that were not
    adequately answered. ECF No. 1 ¶ 31. During the same period, Plaintiff also sent “various emails
    to Defendant asking . . . for responses” to its RFIs. Id. ¶ 32. On December 10, 2020, Plaintiff
    submitted its first set of submittals (“Submittal 0001”) for the chiller and provided the variable
    frequency drive (“VFD”), although Plaintiff had not received a response to RFI 1 yet. Id. ¶ 33.
    On January 8, 2021, Plaintiff emailed the Government with its concerns about the lack of
    responses to its four RFIs. Id. ¶ 34. In particular, the email stated that Plaintiff could not “place a
    purchase order with . . . T[rane] unless the submittals are approved” by the Government. Id. ¶ 35.
    It added that “the Scope of Work [did] not provide any specifications for the chiller equipment to
    know what exactly the [G]overnment wants;” and thus, Plaintiff could not confidently place the
    3
    purchase order. Id. It further advised that the Trane representative, who also was copied on the
    email, had notified Plaintiff that Trane prices would increase the following week; and therefore,
    Plaintiff requested that the approvals for the chiller and VFD as well as responses to the four RFIs
    be expedited. Id. The same day, the Government responded to RFIs 1, 2, and 3; however,
    Plaintiff’s Submittal 0001 was not yet approved. Id. ¶ 36.
    On January 11, 2021, the CO issued a cure notice to Plaintiff. Id. ¶ 37. Plaintiff responded
    via email the same day, providing three dates to discuss the issues and pointing out that many
    emails and calls from Plaintiff to the Government had “never received any responses.” Id. ¶¶ 39–
    40. Plaintiff highlighted that prior emails from Plaintiff to the Government between January 6 and
    January 8 raised concerns “that responses to RFIs and submittals [were] not being provided from
    the [G]overnment, and that as a result[,] timely delivery of this project will be difficult.” Id. ¶ 39.
    Plaintiff also complained that the contract did not offer product specifications for heavy ticket
    items and that it was too risky for Plaintiff “to proceed with a half a million dollar purchase from
    T[rane] for just one item – the [c]hiller” without first receiving approvals or responses to the RFIs.
    Id. ¶ 41. That day and the following day, when Plaintiff reached out to local installers about the
    project, they were already aware of the January 11, 2021, cure notice. Id. ¶ 42.
    On January 13, 2021, a cure meeting was held. Id. ¶ 44. The next day, the Government
    responded to RFI 4 and approved Submittal 0001. Id. ¶¶ 31, 51. On January 19, 2021, Plaintiff
    requested an updated submittal list via email, noting that she was uncertain what submittals would
    be needed other than the chiller and VFD. Id. ¶ 47; see ECF No. 6-1 at 51. “The CO referred Ms.
    Mandal to Attachment 2 of the contract, a draft Material Submittal, and told her to ask for
    recommendations from her subcontractors and suppliers,” as it was up to the contractor to
    determine what was needed to fulfill the contract. ECF No. 1 ¶ 47; see ECF No. 6-1 at 50. The
    4
    CO also stated he was open to a follow up call “to answer any other questions” and “provide as
    much direction and guidance” as possible, noting that the Government was relying on Plaintiff’s
    expertise and knowledge to execute the work. ECF No. 6-1 at 50. Ms. Mandal responded, stating
    she understood and would “pass the message to [her] installers and the manufacturer.” Id. Plaintiff
    alleges, however, that “the CO refused to provide the list she requested.” ECF No. 1 ¶ 47.
    On January 22, 2021, the CO issued a letter of concern, “alleging that Plaintiff had delayed
    the contract and could be assessed liquidated damages.” Id. ¶ 48. The CO also warned that if
    Plaintiff did not take corrective action to cure its performance the Government would be forced
    “to exercise its rights under FAR clause 52.249-10 ‘Default (Fixed Price Construction).’” Id. The
    January 22 letter further indicated that Plaintiff was delinquent with various submittals that should
    have been completed within the 100 days allocated in the NTP, including for “chiller pumps,
    motors, piping materials, valves and flanges, [and] backflow devi[c]es which are indispensable
    and may be long lead items.” ECF No. 6-1 at 53; see ECF No. 1 ¶ 50. In the same letter, the
    Government admitted partial responsibility for not providing timely responses to the submittals
    and RFIs, caveating, however, that “some of the information requested by [Plaintiff] should . . .
    [have been] obtained as part of [the] field investigation as well as determinations made by [its]
    team/subcontractors.” ECF No. 1 ¶ 52; see id. ¶¶ 51, 54. The CO thus extended the period of
    performance by 37 days to account for the Government’s delay but informed Plaintiff that it “is
    expected to accelerate performance to mitigate unsatisfactory progress.” Id. ¶ 55; see id. ¶ 56.
    On January 28, 2021, Plaintiff responded to the CO, requesting an “Equity Adjustment”
    because the Government delayed in responding to Plaintiff’s RFIs and approving its submittals,
    during which time “all mechanical compan[ies], parts [sic] and fabricators . . . raised their prices,
    and [refused] . . . to honor their previously quoted prices.” Id. ¶ 58. Specifically, Plaintiff advised
    5
    that the revised cost for a Trane chiller was now $1,010,000 (compared to the fixed award price of
    $725,691.41 for the full contract) while a York chiller with identical chiller specifications to that
    of Trane would cost $810,000. Id. ¶ 59; see ECF No. 6-1 at 67, 69. Alternatively, Plaintiff
    requested a termination for convenience. ECF No. 1 ¶ 60. The CO responded to Plaintiff the same
    day, requesting documentation to substantiate the equity adjustment, noting the request for a
    termination for convenience was not justified at that time, and referring Plaintiff to its SBA
    representative to advise on the ramifications of a default termination. Id. ¶¶ 60–61; see ECF No.
    6-1 at 58.
    On February 8, 2021, the CO issued a show cause notice, explaining that since Plaintiff
    had failed to cure the conditions endangering performance under the contract, the Government was
    considering terminating the contract under the provisions for default. ECF No. 1 ¶ 63. The notice
    advised that Plaintiff should present “in writing . . . any facts bearing on the question . . . within
    10 days after receipt of this notice.” ECF No. 6-1 at 63. Over two months later, on April 21, 2021,
    Plaintiff emailed stating that it “intended to, and still continued to comply with the terms and
    conditions of the contract,” and reiterated that much of the information it needed from USAF to
    effect performance was not available in a timely fashion and caused a steep price increase. ECF
    No. 1 ¶¶ 64–66. It proposed the installation of a York chiller instead. Id. ¶ 67. The email also
    stated that under its York proposal, Plaintiff could complete “the job without the CO issuing
    additional money, which would be in the interest of the Government[,] and that once the
    Government agrees, [Plaintiff] could move quickly to place orders and get the full work completed
    in 22-24 weeks’ time frame.” Id. ¶ 69. The Government did not respond to the April 2021 email,
    and on July 20, 2021, the CO terminated the contract for default. 2 Id. ¶ 72.
    2
    The Government claims that it does not have a record of receiving the April 21, 2021,
    6
    B.     Procedural History
    On February 3, 2022, Plaintiff filed its Complaint against the United States in this Court,
    challenging the USAF’s termination for default and asserting five causes of action: (1) the
    Government’s actions and failure to respond to Plaintiff’s requests for critical information
    contributed to delays and ultimately default; (2) the CO abused his discretion and failed to
    reasonably follow FAR requirements when terminating for default; (3) the Government breached
    its duty of good faith and fair dealing by not providing critical information to Plaintiff in a timely
    manner as well as by allegedly leaking information disrupting Plaintiff’s ability to acquire a local
    installer; (4) Plaintiff’s default was excused because of defective specifications, excusable delays,
    and commercial impracticability or impossibility; and (5) the Government breached its duty to
    cooperate with Plaintiff and not hinder performance by not clarifying specifications and by not
    providing sufficient information. ECF No. 1 ¶¶ 73–149.
    On May 4, 2022, Defendant moved to dismiss the Complaint pursuant to RCFC 12(b)(1)
    and 12(b)(6). See generally Def’s Mot. to Dismiss, ECF No. 6. The Government argues that the
    Court lacks jurisdiction over any of Plaintiff’s claims that seek a contractual modification or
    equitable adjustment and lacks jurisdiction to grant the broad declaratory relief Plaintiff seeks. Id.
    at 8–9, 26, 32. The Government concedes that the Court has jurisdiction over a prior material
    breach defense to the termination for default but alleges that Plaintiff has failed to state a plausible
    claim for which relief may be granted. Id. at 33. The motion is now fully briefed and ripe for
    decision. See Pl.’s Opp’n, ECF No. 7; Def.’s Reply, ECF No. 9. On December 16, 2022, the
    Court held oral argument.
    email; however, for the purposes of the motion to dismiss, it accepts Plaintiff’s allegation as true.
    Def.’s Mot. to Dismiss at 33, ECF No. 6; Oral Arg. Tr. at 21:25–22:18, ECF No. 13.
    7
    II. DISCUSSION
    A.     Jurisdiction of the Court of Federal Claims
    The Tucker Act provides that “[t]he Court of Federal Claims shall have jurisdiction to
    render judgment upon any claim by or against, or dispute with, a contractor arising under [the
    CDA] including a dispute concerning termination of a contract, rights in tangible or intangible
    property, compliance with cost accounting standards, and other nonmonetary disputes on which a
    decision of the contracting officer has been issued under section 6 of that Act.” 
    28 U.S.C. § 1491
    (a)(2); 
    41 U.S.C. §§ 7101
    –09. Pursuant to the CDA, “contractors are required first to pursue
    claims with the contracting officer, the official charged with administering that particular
    government contract on behalf of the agency.” M. Maropakis Carpentry, Inc. v. United States, 
    84 Fed. Cl. 182
    , 195–96 (2008) (citing 
    41 U.S.C. §§ 605
    (a), 609(a)), aff’d, 
    609 F.3d 1323
     (Fed. Cir.
    2010). This requirement, along with other procedural claim requirements, are “‘jurisdictional
    prerequisites’ to filing an action in the Court of Federal Claims.” 
    Id.
     (citations omitted).
    B.     Standard of Review
    1.      RCFC 12(b)(1)
    Before reaching the merits of a plaintiff’s action, the Court must as a threshold matter
    assure itself that subject-matter jurisdiction exists. See RCFC 12(b)(1), (h)(3); Steel Co. v. Citizens
    for a Better Env’t, 
    523 U.S. 83
    , 94–95 (1998) (affirming that subject-matter jurisdiction “‘spring[s]
    from the nature and limits of the judicial power of the United States’ and is ‘inflexible and without
    exception’” (quoting Mansfield v. Swan, 
    111 U.S. 379
    , 382 (1884))). The plaintiff bears the burden
    of establishing by the preponderance of evidence the Court’s jurisdiction over its claim. See Estes
    Express Lines v. United States, 
    739 F.3d 689
    , 692 (Fed. Cir. 2014).
    When deciding whether to dismiss a complaint pursuant to RCFC 12(b)(1) for lack of
    subject-matter jurisdiction, the Court must accept all factual allegations as true and draw all
    8
    reasonable inferences in the claimant’s favor. See Henke v. United States, 
    60 F.3d 795
    , 797 (Fed.
    Cir. 1995). However, if a complaint contains challenged factual allegations, for purposes of ruling
    on a motion to dismiss, the court may inquire into facts necessary to support jurisdiction and may
    resolve disputed facts. See Al Johnson Constr. Co. v. United States, 
    19 Cl. Ct. 732
    , 733 (1990);
    see also Indium Corp. of Am. v. Semi-Alloys, Inc., 
    781 F.2d 879
    , 884 (Fed. Cir. 1985) (affirming
    that a court may consider “evidentiary matters outside the pleadings” when assessing a Rule
    12(b)(1) dismissal).
    2.      RCFC 12(b)(6)
    The Court must also dismiss an action if it fails to state a claim for which relief may be
    granted. RCFC 12(b)(6). To avoid dismissal under RCFC 12(b)(6), “a complaint must contain
    sufficient factual matter, accepted as true, to ‘state a claim to relief that is plausible on its face.’”
    Ashcroft v. Iqbal, 
    556 U.S. 662
    , 678 (2009) (quoting Bell Atl. Corp. v. Twombly, 
    550 U.S. 544
    ,
    570 (2007)). Although a complaint need not contain detailed factual allegations to raise a plausible
    claim, a plaintiff must provide “more than labels and conclusions, and a formulaic recitation of the
    elements of a cause of action will not do.” Twombly, 
    550 U.S. at 555
    ; see Papasan v. Allain, 
    478 U.S. 265
    , 286 (1986) (holding that courts “are not bound to accept as true a legal conclusion
    couched as a factual allegation”). In deciding a motion under RCFC 12(b)(6), the Court may
    consider the complaint itself, “the written instruments attached to it as exhibits, ‘documents
    incorporated into the complaint by reference, and matters of which a court may take judicial
    notice.’” Todd Constr., L.P. v. United States, 
    94 Fed. Cl. 100
    , 114 (2010) (quoting Tellabs, Inc.
    v. Makor Issues & Rts. Ltd., 
    551 U.S. 308
    , 322 (2007)), aff’d, 
    656 F.3d 1306
     (Fed. Cir. 2011).
    9
    C.     The Court Lacks Jurisdiction Over Claims and Defenses Not Submitted to the CO
    for a Final Decision.
    The Government argues that the Court does not possess jurisdiction to award monetary
    relief or to consider allegations that effectively seek a contractual modification or equitable
    adjustment since no claim was properly certified and submitted to the CO for a final decision. ECF
    No. 6 at 26–29; see ECF No. 9 at 10–12. The Court agrees. Plaintiff has not met its jurisdictional
    burden regarding any claim for monetary relief and any contractual modification, equitable
    adjustment, or defense that effectively requests a change in the contract because the Complaint
    does not allege (and Plaintiff concedes) no claim was submitted to the CO pursuant to the CDA’s
    presentment requirements.
    Establishing this Court’s jurisdiction under the CDA requires both a valid claim and a CO’s
    final decision on that claim. M. Maropakis Carpentry, 
    609 F.3d at 1327
    . Other than providing
    that the contractor’s claim must be in writing and submitted to the contracting officer for a final
    decision, the CDA does not define the term “claim.” 
    41 U.S.C. §§ 7103
    (a)(1)–(2). The FAR,
    however, does. It defines a claim as a “written demand or written assertion by one of the
    contracting parties seeking, as a matter of right, the payment of money in a sum certain, the
    adjustment or interpretation of contract terms, or other relief arising from or relating to th[e]
    contract.” 
    48 C.F.R. § 2.101
    ; see 
    id.
     § 52.233-1(c). “While a CDA claim need not be submitted
    in any particular form or use any particular wording, it must contain ‘a clear and unequivocal
    statement that gives the contracting officer adequate notice of the basis and amount of the claim.’”
    M. Maropakis Carpentry, 
    609 F.3d at 1327
     (quoting Cont. Cleaning Maint., Inc. v. United States,
    
    811 F.2d 586
    , 592 (Fed. Cir. 1997)). A claim also must “indicate to the contracting officer that
    the contractor is requesting a final decision.” 
    Id.
    10
    With respect to claims that seek the payment of money, the claim must “demand a ‘sum
    certain.’” Creative Mgmt. Servs., LLC v. United States, 
    989 F.3d 955
    , 962 (Fed. Cir. 2021). “[T]he
    absence of a sum certain is ‘fatal to jurisdiction under the CDA.’” Securiforce Int’l Am., LLC v.
    United States, 
    879 F.3d 1354
    , 1359–60 (Fed. Cir. 2018) (quoting Northrop Grumman Computing
    Sys., Inc. v. United States, 
    709 F.3d 1107
    , 1112 (Fed. Cir. 2013)). Moreover, if the claim demands
    more than $100,000, it must be certified, as required by 
    41 U.S.C. § 7103
    (b)(1). Although a
    “defective certification” does not deprive the Court of jurisdiction, a failure to certify does. 
    Id.
     §
    7103(b)(3); 
    48 C.F.R. § 33.201
     (“Failure to certify shall not be deemed to be a defective
    certification.”). The same jurisdictional presentment requirements apply to claims “seeking an
    adjustment of contract terms [or an equitable adjustment] . . . whether [a contractor is] asserting
    the claim against the government as an affirmative claim or as a defense.” Securiforce Int’l Am.,
    
    879 F.3d at 1362
     (quoting M. Maropakis Carpentry, 
    609 F.3d at 1331
    ).
    At the outset, the Court notes that it is difficult to glean from the Complaint itself precisely
    what claims and defenses Plaintiff raises given both the organization of the five causes of action
    in the Complaint, as well as the repeated or substantially similar allegations in each. Nevertheless,
    consistent with Plaintiff’s representations at oral argument, the Court will construe the Complaint
    as alleging two standalone causes of action—the breach of the duty of good faith and fair dealing
    not to interfere (Cause III) and a challenge to the default termination (Cause II), with the remaining
    three causes of action representing additional defenses to the default termination. See Oral Arg.
    Tr. at 34:13–34:22, ECF No. 13. With that framework in mind, the Court addresses Defendant’s
    jurisdictional arguments in turn.
    1.      Breach of the Duty of Good Faith and Fair Dealing
    The Court does not have jurisdiction over Cause III because Plaintiff has not shown that
    such claim, or indeed any claim for monetary relief, was presented to the CO for a final decision.
    11
    As relevant here, the Complaint alleges that the Government breached its implied duty of good
    faith and fair dealing because it interfered with Plaintiff’s performance of the contract by not
    providing in a timely manner critical information requested by Plaintiff. ECF No. 1 ¶¶ 97–99,
    105, 109. The claim then asserts that the Government’s delay was “the proximate reason why
    [Plaintiff] could not place orders on [the] high-priced items” (i.e., the Trane chiller), id. ¶ 100; that
    the delays were not cured by the “self-serving decision to only award [Plaintiff] thirty-seven days
    . . . to finish performance,” id. ¶ 101; and that “[t]he Government’s admitted delays in responding
    to [Plaintiff’s RFIs] were not excusable,” id. ¶ 103.           Plaintiff alleges this breach of the
    Government’s duty “directly affected Plaintiff’s ability to perform under the contract,” causing a
    direct domino effect leading to Plaintiff’s alleged default. Id. ¶ 116; see id. ¶¶ 105–06; see also
    ECF No. 13 at 36:1–14; 44:1–8. As a remedy for the alleged breach, Plaintiff seeks lost profits,
    breach damages, fees, and costs. ECF No. 1 ¶¶ 156–57.
    The Complaint, however, does not allege that Plaintiff submitted a written claim to the CO
    asserting that it was entitled to such monetary relief on the basis of the Government’s alleged
    breach of good faith and fair dealing.            At most, the Complaint references Plaintiff’s
    communications to the Government requesting information necessary to place orders and the CO’s
    responses. See, e.g., id. ¶¶ 31–32, 34–36, 39–40, 64–71. According to these allegations, Plaintiff
    expressed concerns to the CO about a lack of information, the Government’s delay in responding
    to requests for information, and the effect of these circumstances on Plaintiff’s ability to perform.
    But Plaintiff neither alleges, nor do the actual communications show, that Plaintiff sought, “as a
    matter of right, the payment of money in a sum certain” as a result of the alleged breach or that
    Plaintiff requested the CO to make a final decision on that claim. M. Maropakis Carpentry, 
    609 F.3d at 1327
    . The absence of such facts, which are a prerequisite to bringing a CDA claim even
    12
    in cases asserting a breach of the implied duty of good faith and fair dealing, is fatal. See, e.g.,
    Bowman Constr. Co. v. United States, 
    154 Fed. Cl. 127
    , 139 (2021) (holding that lack of sum
    certain demand was fatal to claim alleging breach of the duty of good faith and fair dealing);
    Mansoor Int’l Dev. Servs., Inc. v. United States, 
    121 Fed. Cl. 1
    , 2, 6 (2015) (holding there was
    subject-matter jurisdiction over a breach of good faith and fair dealing claim because the
    jurisdictional requirements were satisfied, i.e., a claim was submitted to the CO); Sarro & Assocs.,
    Inc. v. United States, 
    152 Fed. Cl. 44
    , 53 (2021) (same). Accordingly, the Court concludes that it
    does not have jurisdiction over Plaintiff’s claim for breach of the duty of good faith and fair
    dealing.
    2.      Challenge to the Termination For Default
    The Court likewise lacks jurisdiction as to any part of Plaintiff’s defenses to the default
    termination that effectively request a change in the contract—whether that be an extension of time,
    a contractual modification, or an equitable adjustment—since such claims also must be presented
    to the CO for a final decision first. See Securiforce Int’l Am., 
    879 F.3d at 1363
    . In challenging
    the default termination, the Court understands the assertions in the Complaint to raise the following
    affirmative defenses to Plaintiff’s default: (1) prior material breach; (2) the CO’s abuse of
    discretion; and (3) commercial impossibility/impracticability. ECF No. 1 ¶¶ 73–95, 119–49. Of
    these, the commercial impossibility/impracticability defense solely involves an alleged
    constructive change to the contract requiring a CO’s final decision.
    As an initial matter, the Court notes that the Complaint states a commercial
    impracticability—not impossibility—defense because “‘impossibility’ of performance [only]
    exists ‘when it is objectively determined that no contractor could perform the work.’” TPL, Inc.
    v. United States, 
    118 Fed. Cl. 434
    , 442 (2014) (quoting Conner Bros. Constr. Co., Inc. v. United
    States, 
    65 Fed. Cl. 657
    , 686 (2005)). That is not the case here. As the Complaint’s allegations
    13
    make clear, the ultimate barrier to performance was the prohibitive costs of the Trane chiller that,
    according to Plaintiff, was a result of the Government’s actions leading to its default. These
    allegations, thus, amount to a claim of commercial impracticability. 
    Id.
    Regardless, the Court lacks jurisdiction to entertain Plaintiff’s impracticability defense.
    “Impracticability is ‘treated as a type of constructive change to the contract; because a
    commercially impracticable contract imposes substantial unforeseen costs on the contractor, the
    contractor is entitled to an equitable adjustment.’” 
    Id.
     (quoting Raytheon Co. v. White, 
    305 F.3d 1354
    , 1367 (Fed. Cir. 2002)). As discussed above, the Court does not have jurisdiction under the
    CDA over a claim seeking a change to the contract that was not first presented to the CO for final
    decision, even when, as here, it is raised as a defense.
    In this case, the Complaint does not allege that Plaintiff submitted a request for an equitable
    adjustment to the CO. It contends only that Plaintiff responded to the CO’s January 11 cure notice
    by requesting an “Equity Adjustment,” to which the CO responded by directing Plaintiff to submit
    a request for equitable adjustment with supporting documentation. ECF No. 1 ¶¶ 58, 61; see ECF
    No. 6-1 at 57. Plaintiff does not allege that it complied with that instruction or otherwise pursued
    presentment of a claim for increased costs. Indeed, Plaintiff conceded that no request for an
    equitable adjustment was ever properly submitted. See ECF No. 13 at 47:16–22. Even if
    Plaintiff’s response to the January 11 cure notice could be considered as such a request, it was not
    certified and thus fails on that independent ground. 3 Therefore, the impracticability defense cannot
    proceed.
    3
    Certification was necessary because any claim seeking the difference between the fixed
    award price ($725,691.41) and the increased cost of the Trane chiller ($1,010,000) would have
    exceeded $100,000. ECF No. 1 ¶ 59; see 
    48 C.F.R. § 252.243-7002
    ; 
    41 U.S.C. § 7103
    (b)(1).
    14
    D.     The Court Lacks Jurisdiction Over Declaratory Relief Plaintiff Seeks.
    The Court also lacks jurisdiction to grant the broad declaratory relief Plaintiff seeks in its
    prayer for relief. Specifically, Plaintiff asks the Court to declare that (1) “the Government’s delays
    were not excusable and directly caused [Plaintiff]’s delays,” ECF No. 1 ¶ 153; (2) “the
    Government’s extension for 37 days was self-serving since the Government’s own actions were
    not excusable and [Plaintiff] deserved a more reasonable time to perform,” 
    id. ¶ 154
    ; 4 and (3) “the
    Government is not entitled to reprocurement costs or liquidated damages,” 
    id. ¶ 155
    . Under the
    Tucker Act, the declaratory relief enumerated above is unavailable.
    “[T]he Court may award equitable or other nonmonetary relief in Tucker Act cases in only
    three statutorily defined circumstances: (1) in bid protest actions brought pursuant to 
    28 U.S.C. § 1491
    (b); (2) as ‘incident of and collateral to’ a monetary judgment, as set out in the first two
    sentences of 
    28 U.S.C. § 1491
    (a)(2); and (3) for certain types of nonmonetary CDA claims, as
    described in the last sentence of § 1491(a)(2).” Sergent’s Mech. Sys., Inc. v. United States, 
    157 Fed. Cl. 41
    , 47 (2021); see Alvarado Hosp., LLC v. Price, 
    868 F.3d 983
    , 999 (Fed. Cir. 2017)
    (“The Tucker Act does not generally confer jurisdiction for actions seeking declaratory or
    4
    Although Plaintiff alleges the 37-day extension was self-serving and unreasonable, ECF
    No. 1 ¶¶ 76, 101, it does not allege that it timely appealed the CO’s final decision granting the
    extension, as required by the FAR. 
    48 C.F.R. § 52.249
    –10(b)(2) (providing that extensions for
    excusable delay are final decisions subject to appeal in accordance with the Disputes clause). Since
    that extension was granted on January 22, 2021, the period to appeal expired one year later on
    January 22, 2022—approximately two weeks before Plaintiff filed the instant complaint. See
    Textron Aviation Def. LLC v. United States, 
    161 Fed. Cl. 256
    , 264 (2022) (citing 
    42 U.S.C. §§ 7104
     (a), (b)(3)). Relief addressing the 37-day extension is therefore beyond the Court’s
    jurisdiction or, in the alternative, fails to state a claim. See Inter-Coastal Xpress, Inc. v. United
    States, 
    296 F.3d 1357
    , 1365 (Fed. Cir. 2002) (holding that the CDA’s statute of limitations is
    jurisdictional and operate as limit on the Tucker Act’s waiver of sovereign immunity); but see
    Creative Mgmt. Servs., LLC v. United States, 
    989 F.3d 955
    , 961–62 (Fed. Cir. 2021) (questioning
    whether the CDA’s twelve-month filing period is a jurisdictional requirement).
    15
    injunctive relief.”). Because this is not a bid protest action, only§ 1491(a)(2) applies. That section
    states:
    [t]o provide an entire remedy and to complete the relief afforded by the judgment,
    the court may, as an incident of and collateral to any such judgment, issue orders
    directing restoration to office or position, placement in appropriate duty or
    retirement status, and correction of applicable records, and such orders may be
    issued to any appropriate official of the United States. In any case within its
    jurisdiction, the court shall have the power to remand appropriate matters to any
    administrative or executive body or official with such direction as it may deem
    proper and just. The Court of Federal Claims shall have jurisdiction to render
    judgment upon any claim by or against, or dispute with, a contractor arising under
    section 7104(b)(1) of title 41, including . . . other nonmonetary disputes on which
    a decision of the contracting officer has been issued under section 6 of that Act.
    
    28 U.S.C. § 1491
    (a)(2) (emphasis added). A review of the plain language of § 1491(a)(2)
    demonstrates that the Court lacks broad jurisdiction to issue equitable relief in general and
    specifically to grant the three requests for declaratory relief Plaintiff seeks here.
    The relief sought by Plaintiff cannot be “incident to or collateral to” a money judgment
    because Plaintiff has not stated a claim for money that is within the Court’s CDA jurisdiction, as
    explained above. Id. As well, the specific relief sought—declaring that the Government’s delays
    were inexcusable, the 37-day extension was self-serving, or that the Government is not entitled to
    reprocurement costs or liquidated damages—does not fit in the narrow categories of equitable
    relief outlined in the first two sentences of § 1491(a)(2). See id. Although the final sentence of §
    1491(a)(2) permits the Court to hear nonmonetary CDA claims, relief is plainly unavailable unless
    the dispute has been presented to and a final decision has been issued by the contracting officer as
    provided for by the CDA. Id.; see Alliant Techsystems, Inc. v. United States, 
    178 F.3d 1260
    , 1267
    (Fed. Cir. 1999). As the Court already held, the Complaint does not allege that any claim was
    submitted to the CO pursuant to the CDA. See supra § II.C. Nor can Plaintiff circumvent the
    16
    limitations on the Court’s jurisdiction by merely “reframing monetary claims as nonmonetary.”
    Securiforce Int’l Am., 
    879 F.3d at 1360
    .
    Accordingly, the Court lacks jurisdiction to provide the broader declaratory relief sought
    by Plaintiff.
    E.      The Complaint Sufficiently Alleges a Claim for Relief.
    The Court does have jurisdiction over the remainder of Plaintiff’s claim challenging the
    termination for default under the contract as written. See Securiforce Int’l Am., 
    879 F.3d at
    1362–
    63 (holding that an affirmative defense to a default termination, such as fraud or prior material
    breach, “need not first be presented to the CO for a final decision, since a defense is not a claim
    for money, and the CO has no necessary role in assessing the defense”). Accordingly, it may
    entertain Plaintiff’s first two defenses—prior material breach and abuse of discretion—at least to
    the extent they do not effectively seek a contractual modification or equitable adjustment. The
    Government concedes as much but argues that Plaintiff has failed to state a claim for relief on
    those grounds. ECF No. 6 at 2, 33; ECF No. 9 at 8. Taking as true the allegations in the Complaint,
    the Court finds that Plaintiff has stated a plausible challenge to the default termination that is at
    this early stage sufficient to survive a motion to dismiss.
    Principally, unlike other causes of action, in a default termination challenge the
    Government (not the plaintiff) “bears the burden of proof on the issue of default by the contractor”
    and, specifically, “the correctness of its actions in terminating a contractor for default.” Lisbon
    Contractors, Inc. v. United States, 
    828 F.2d 759
    , 763 (Fed. Cir. 1987) (emphasis omitted). This is
    so, in part, because a termination for default is “a drastic sanction which should be imposed (or
    sustained) only for good grounds and on solid evidence.” Keeter Trading Co. v. United States, 
    79 Fed. Cl. 243
    , 252 (2007) (quoting Lisbon Contractors, 
    828 F.2d at 765
    ). Although a contracting
    officer has the discretion to terminate a contract, “the exercise of that discretion must be fair and
    17
    reasonable, not arbitrary or capricious.” Darwin Constr. Co. v. United States, 
    811 F.2d 593
    , 597
    (Fed. Cir. 1987) (quoting Udis v. United States, 
    7 Cl. Ct. 379
    , 387 (1985)). Accordingly, in a case
    where a contractor has failed to make sufficient progress, a decision to terminate for default may
    be upheld only when the contracting officer had a reasonable belief that “there was no reasonable
    likelihood the contractor would perform within the time remaining.” Securiforce Int’l Am., 
    879 F.3d at 1364
    ; see Lisbon Contractors, 
    828 F.2d at 765
    .
    The Government has not cited any cases that have decided the question of the propriety of
    a default termination on a motion to dismiss.        See ECF No. 13 at 17:24–18:17, 19:5–7
    (acknowledging the unusual nature of its dismissal request).        The Government argues that
    dismissal at the pleadings stage is nonetheless proper because the allegations in the Complaint
    confirm that (1) Plaintiff failed to reassure the Government it would complete the contract because
    it conditioned performance on a modification of the contract price or brand requirement, and (2)
    Plaintiff was not close to completing the contract within the requisite period of performance. See
    ECF No. 9 at 12–13. While these facts may ultimately support a finding that the termination for
    default was justified, the Government has not shown that they are dispositive of the issue as a
    matter of law, especially when Plaintiff has alleged a prior material breach defense. Keeter
    Trading, 
    79 Fed. Cl. at 253
     (“[A] contractor’s refusal to perform in the presence of a material
    breach of contract by the government does not constitute a repudiation.”); see Danzig v. AEC
    Corp., 
    224 F.3d 1333
    , 1337 (Fed. Cir. 2000). Rather, the Federal Circuit has described the
    evaluation of a default termination decision as a fact-intensive inquiry, which would typically not
    be well suited for resolution on a motion to dismiss. See McDonnell Douglas Corp. v. United
    States, 
    323 F.3d 1006
    , 1013, 1016–17 (Fed. Cir. 2003) (explaining the comprehensive factual and
    evidentiary issues that a court must consider when reviewing the circumstances leading up to a
    18
    default termination, such as a contractor’s performance history, issues with subcontractors and
    suppliers, and financial situation). Here, the facts and circumstances surrounding the parties’
    communications, Plaintiff’s performance, the alleged anticipatory repudiation, and other context
    leading to the default decision have yet to be developed.
    So too are Plaintiff’s allegations that the CO abused his discretion. The Government
    reduces those allegations to a complaint that the CO did not make an explicit determination about
    each factor set forth in FAR 49.402-3 (Procedure for Default) when issuing the termination. ECF
    No. 6 at 45–46; ECF No. 9 at 22–23. As it correctly points out, “‘failure to consider one or more
    of the [FAR] factors should not invalidate a termination for default where the totality of the
    circumstances demonstrates a reasonable exercise of discretion.’” Morganti Nat’l, Inc. v. United
    States, 
    49 Fed. Cl. 110
    , 132 (2001) (alterations in original omitted) (emphasis added) (quoting
    Lafayette Coal Co., 
    ASBCA No. 32174
    , 89–
    3 BCA ¶ 21,963
    , 
    1989 WL 74885
     (1989), aff’d, 
    36 F. App’x 452
     (Fed. Cir. 2002)); see DCX, Inc. v. Perry, 
    79 F.3d 132
    , 135 (Fed. Cir. 1996). But Cause
    II cannot fairly be read so narrowly; and in any event, an assessment of the totality of the
    circumstances surrounding the termination is nonetheless necessary. Moreover, other contentions
    asserted in Plaintiff’s abuse of discretion count require further factual review. See ECF No. 1 ¶¶
    80–95 (alleging, among other things, that the CO’s decision was based on his subjective opinion
    and subject to outside influence). Thus, a determination at the motion to dismiss stage is not
    appropriate.
    Moreover, even if the Government adequately proves default, the plaintiff may
    demonstrate that the default was excusable under the contract, e.g., by showing that improper
    government actions were the cause of the default, rendering the plaintiff unable to perform. Keeter
    Trading, 
    79 Fed. Cl. at 252
    . “[W]hen determining whether a party caused a material breach, the
    19
    court must consider the nature and effect of the violation, viewed in context”—again requiring an
    inquiry into the facts and circumstances surrounding the alleged material breach. See 
    id. at 253
    .
    Here, the Complaint contains various factual allegations asserting that the Government’s conduct
    contributed to Plaintiff’s deficient performance, including that the Government failed to promptly
    provide information necessary to prepare submittals and place orders, leaked information that
    complicated Plaintiff’s ability to hire an installer, and provided limited and illegible specifications.
    See, e.g., ECF No. 1 ¶¶ 49, 53, 56, 71, 141–42.
    The Government argues that Plaintiff’s excuses are not valid. See ECF No. 6 at 37. On a
    Rule 12(b)(6) motion, however, the question is not whether Plaintiff “will ultimately prevail, but
    whether [its] complaint [is] sufficient to cross the federal court’s threshold.” Skinner v. Switzer,
    
    562 U.S. 521
    , 529–30 (2011) (internal citations omitted); see Nalco Co. v. Chem-Mod, LLC, 
    883 F.3d 1337
    , 1350 (Fed. Cir. 2018) (“The ‘purpose of a motion to dismiss is to test the sufficiency of
    the complaint, not to decide the merits.’” (quoting Gibson v. City of Chi., 
    910 F.2d 1510
    , 1520
    (7th Cir. 1990)) (emphasis in original)). As the Federal Circuit has explained, Twombly’s
    “‘plausibility standard is not akin to a probability requirement.’ Rather, Plaintiffs need only
    ‘nudge their claims across the line from conceivable to plausible.’” CODA Dev. S.R.O. v.
    Goodyear Tire & Rubber Co., 
    916 F.3d 1350
    , 1360 (Fed. Cir. 2019) (internal citations omitted).
    Accepting Plaintiff’s allegations as true, the Complaint pleads “enough facts to state a
    claim to relief that is plausible on its face.” Twombly, 
    550 U.S. at 570
    . The Court acknowledges
    that other allegations in the Complaint may call into question the bases of Plaintiff’s defenses,
    including, for example, Plaintiff’s representation in the April 21 email to the CO that it could
    quickly continue performing if the Government approved the installation of a York chiller. See
    ECF No. 1 ¶¶ 66–69. Whether Plaintiff’s defenses are ultimately meritorious is a question for
    20
    another day. Considering the allegations as a whole, Plaintiff is entitled to try to establish in further
    proceedings that the sequence of events amounted to a prior material breach and excusable delay.
    Cf. E&I Glob. Energy Servs., Inc. v. United States, No. 2022-1472, 
    2022 WL 17998224
    , at *5
    (Fed. Cir. Dec. 30, 2022) (reversing Rule 12(c) dismissal of default termination challenge).
    In sum, accepting the allegations in the Complaint as true—i.e., that the CO abused his
    discretion in reaching the default decision, that the Government’s delay, failure to provide missing
    information, leak of information, and incomplete or illegible specifications rendered Plaintiff
    unable to perform—Plaintiff has sufficiently stated a plausible claim for relief at this early stage
    of the proceedings. And given the initial burden upon the Government to prove the correctness of
    its actions and the drastic nature of a default termination, the Court finds that dismissal of the
    default termination challenge in its entirety under RCFC 12(b)(6) is not justified.
    III. CONCLUSION
    For these reasons, the Government’s Motion to Dismiss Plaintiff’s Complaint pursuant to
    RCFC 12(b)(1) and 12(b)(6) (ECF No. 6) is GRANTED in part and DENIED in part.
    SO ORDERED.
    Dated: March 31, 2023                                   /s/ Kathryn C. Davis
    KATHRYN C. DAVIS
    Judge
    21
    

Document Info

Docket Number: 22-110

Judges: Kathryn C. Davis

Filed Date: 3/31/2023

Precedential Status: Precedential

Modified Date: 3/31/2023

Authorities (34)

Coda Dev. S.R.O. v. Goodyear Tire & Rubber Co. , 916 F.3d 1350 ( 2019 )

Papasan v. Allain , 106 S. Ct. 2932 ( 1986 )

Estes Express Lines v. United States , 739 F.3d 689 ( 2014 )

McDonnell Douglas Corporation, and General Dynamics ... , 323 F.3d 1006 ( 2003 )

Mansfield, Coldwater & Lake Michigan Railway Co. v. Swan , 4 S. Ct. 510 ( 1884 )

Nalco Company v. Chem-Mod, LLC , 883 F.3d 1337 ( 2018 )

Dcx, Inc. v. William J. Perry, Secretary of Defense , 79 F.3d 132 ( 1996 )

Morganti National, Inc. v. United States , 2001 U.S. Claims LEXIS 57 ( 2001 )

Alliant Techsystems, Inc., Global Environmental Solutions ... , 178 F.3d 1260 ( 1999 )

Lisbon Contractors, Inc. v. The United States , 828 F.2d 759 ( 1987 )

Indium Corporation of America v. Semi-Alloys, Inc. , 781 F.2d 879 ( 1985 )

bell/heery v. United States , 739 F.3d 1324 ( 2014 )

Steel Co. v. Citizens for a Better Environment , 118 S. Ct. 1003 ( 1998 )

Tellabs, Inc. v. Makor Issues & Rights, Ltd. , 127 S. Ct. 2499 ( 2007 )

Bell/Heery v. United States , 2012 U.S. Claims LEXIS 929 ( 2012 )

Darwin Construction Co., Inc. v. United States , 811 F.2d 593 ( 1987 )

Mansoor International Development Services, Inc. v. United ... , 2015 U.S. Claims LEXIS 556 ( 2015 )

Securiforce International America, LLC v. United States , 879 F.3d 1354 ( 2018 )

Bell Atlantic Corp. v. Twombly , 127 S. Ct. 1955 ( 2007 )

Ashcroft v. Iqbal , 129 S. Ct. 1937 ( 2009 )

View All Authorities »