Jacqueline R Sims LLC v. United States ( 2014 )


Menu:
  •        In the United States Court of Federal Claims
    No. 13-174C
    No. 13-196C
    (Filed February 25, 2014)
    ************************************
    *
    JACQUELINE R. SIMS LLC,             *
    *
    Plaintiff,        *
    *
    v.                      *
    *
    THE UNITED STATES,                  *
    *
    Defendant.        *
    *
    *************************************
    OPINION AND ORDER
    Plaintiff Jacqueline R Sims LLC, dba JRS Management (“JRS”), filed the first
    complaint in this case at Civ. No. 13-174 on March 7, 2013. The second complaint was
    filed at Civ. No. 13-196 on March 18, 2013. By Order, these actions were consolidated
    on May 7, 2013. Both of these cases are contract actions.
    On June 25, 2013, JRS filed a motion for leave to amend the pleadings and the
    Court granted the motion. These amended pleadings appear on the docket as attachments
    to the motion at Docket Entry 12.1 After a brief interlude, the parties indicated their
    desire to file dispositive motions. JRS filed two separate summary judgment motions,
    each directed to one of the contracts at issue.2 The Government filed a single motion,
    requesting summary judgment or dismissal, which applies to both actions.
    For the reasons that follow, JRS’s motions are both DENIED and the
    Government’s motion is GRANTED, insofar as it requests summary judgment, and
    DENIED, as moot, with respect to its argument for dismissal.
    1
    The Amended Complaints do not contain any exhibits or other attachments. For this
    reason, any references in this Opinion to attachments to either complaint are directed to
    the attachments to the originally-filed complaints.
    2
    Both motions are filed together as one large document at Docket No. 17. The first,
    entitled “Plaintiff’s Motion for Summary Judgment,” addresses the Ceramics Contract.
    The second, entitled “Memorandum in Support of Plaintiff’s Motion for Summary
    Judgment,” addresses the Parenting Contract.
    1
    I.      Background
    As stated above, this consolidated matter was originally filed as two separate
    cases. The claims are distinct in that they address two different contracts, Contract No.
    DJBP010100000006 (the “Ceramics Contract”) and Control No. DJBP010100000005
    (the “Parenting Contract”) (together, the “Contracts”). The Ceramics Complaint was
    originally filed at Civ. No. 13-174, while the Parenting Complaint was originally filed at
    Civ. No. 13-196. Both contracts were executed by the Bureau of Prisons (“BOP”).
    a. Plaintiff’s Legal Theories
    Both Complaints contain four counts which are substantially similar: (1) that the
    BOP exceeded its authority under FAR Subpart 42.15 by preparing past performance
    evaluations (“PPEs”) for JRS’s performance under the contracts; (2) that the BOP’s
    preparation of the PPEs constitutes a unilateral change of the contract terms in violation
    of 52.212-4(c); (3) that the BOP’s PPEs were arbitrary and capricious because the BOP
    negatively evaluated JRS for its failure to perform under unenforceable contracts; and (4)
    that the BOP breached the implied duty of good faith and fair dealing by producing
    allegedly inaccurate PPEs. The Ceramics Complaint includes one additional count,
    effectively alleging that the BOP affirmatively engaged in bad faith conduct related to the
    evaluation of JRS’s performance under the Ceramics Contract which resulted in JRS
    losing out on a subsequent government contract.
    b. The Ceramics Contract
    The Ceramics Contract was signed on September 24, 2009, with an effective date
    of October 1, 2009. The award was for a single base year plus four option years. The
    value of the Ceramics Contract was an estimated $63,180.
    The Ceramics Contract required JRS to provide an on-site ceramics instructor to
    teach classes to inmates at the Federal Prison Camp, Alderson, West Virginia (“FPC”).
    JRS hired a subcontractor to provide the actual instruction. In practice, the Government
    would provide delivery orders or task orders to JRS requesting services, JRS would
    render service, and then JRS would invoice the Government for payment.
    The Ceramics Contract incorporated FAR 52.216-21, Requirements (Oct 1995)
    Alternate I (Apr 1984). Paragraph c of this provision states that:
    The estimated quantities are not the total requirements of the
    Government activity specified in the Schedule, but are estimates of
    requirements in excess of the quantities that the activity may itself furnish
    within its own capabilities. Except as this contract otherwise provides, the
    Government shall order from the contractor all of that activity’s
    requirements for supplies and services specified in the Schedule that
    exceed the quantities that the activity may itself furnish within its own
    capabilities.
    2
    FAR 52.216-2(c). The Ceramics Contract also incorporated FAR 52.212-4(c), which
    provides that “[c]hanges in the terms and conditions of this contract may be made only by
    written agreement of the parties.”
    The schedule indicated that JRS was required to provide three sessions per week,
    each session lasting three hours. The schedule also reflected that there would be a total
    of 468 one-hour sessions per year. The schedule stated that this plan was “flexible.”
    JRS, by way of its subcontractor, provided services in October and November of
    2009 and January of 2010—i.e., three of the first four months of the initial contract term.
    JRS has been paid in full for all services rendered. JRS did not provide services in
    December of 2009 or for the period from February 1, 2010 to September 30, 2010.
    Despite JRS’s repeated failure to provide services, the Government exercised the first
    option period.
    On September 9, 2010, the BOP generated a past performance evaluation
    (“PPE”), which it submitted to JRS for review and comment. JRS was rated for four
    criteria: quality of service (“unsatisfactory”), timeliness of performance (“poor”),
    business relations (“fair”) and customer satisfaction (“fair”). See Ceramics Compl. at ¶
    36. The PPE referred to JRS’s inability to provide a ceramics instructor during portions
    of the contract period. JRS submitted a response to the PPE on October 29, 2010. The
    substance of the response was that the quality of the services rendered was good, but it
    also explained why the subcontractor did not perform.
    The contracting officer took JRS’s comments into consideration and revised her
    ratings. JRS then evidently requested that the revised evaluation be reviewed by the
    contracting officer’s superior because, on December 16, 2010, FPC’s chief of
    acquisitions issued a memorandum concurring with the contracting officer’s revised
    overall rating of fair. The final evaluation included ratings for JRS’s quality of service,
    timeliness of performance, business relations, and customer satisfaction. The rating for
    quality of service appears to be the only change based on the reevaluation: the final rating
    was changed from “unsatisfactory” to “good.”3 Under the “timelines of performance”
    criteria, for which JRS received a final rating of “poor,” the contracting officer stated:
    A review of the rating period reveals that four task orders were
    issued beginning October 2009 through September 30, 2010; however,
    3
    As stated above, JRS alleges that its original ratings on the four criteria were
    “unsatisfactory,” “poor,” “fair,” and “fair,” respectively. On reevaluation, the latter three
    ratings remain unchanged. However, the quality of service rating was revised to “good,”
    apparently on the basis that the original evaluation considered the entire contract term
    while the revised evaluation only rated JRS for the periods during which service was
    actually rendered. See Ceramics Compl. Ex. E at 2 (“Quality of [S]ervice was not rated
    for the period of time in which service was not rendered. The overall rating for Quality
    of Service, limited to the months service was performed, is revised to Good.”).
    3
    service was not rendered from February 1, 2010 to September 30, 2010.
    JRS initially notified BOP that lack of service was due to personal illness
    of the contract instructor. Although, JRS did inform the BOP of the
    instructor’s illness, such circumstances do not relieve the contractor of
    their obligation to provide service under the terms of the contract.
    Additionally, we note that service was not rendered as of June 2010
    because JRS did not have an employee cleared to enter the institution to
    perform service. Failure to provide service during the last eight months of
    the rating period effectively compromised achievement of the contract
    requirements resulting in a revised rating of Poor for Timeliness of
    Performance for the full rating period.
    Ceramics Compl. Ex. E at 2. JRS’s ratings for business relations and customer
    satisfaction remained “fair,” as in the original evaluation. The memorandum concluded
    with a statement that “[t]hese evaluations may be used to support future award decisions,
    and shall be therefore marked ‘Source Selection Information.’” Id. at 3.
    While all of this was going on, the BOP sent JRS a cure notice on November 12,
    2010. The notice gave JRS 30 days to provide an instructor for the ceramics classes.
    JRS never obtained a replacement instructor. Therefore, on December 27, 2010, the BOP
    terminated JRS for default. The termination was subsequently converted into a
    termination for convenience.
    It is not clear from the record precisely when this occurred, but sometime prior to
    February 28, 2012, JRS submitted a bid to provide radiology technologies services at the
    Federal Correction Institution in Miami, Florida (“FCI Miami”). On February 28, 2012,
    JRS was informed by phone that it had received a negative determination of
    responsibility and that the matter had been referred “to the SBA [Small Business
    Administration] for a COC [Certification of Competency] determination.” Ceramics
    Compl. Ex. F at 1.
    By email dated March 6, 2012, JRS informed FCI Miami that it had contracted
    with a subcontractor to provide the requested services. JRS requested that the FCI
    reverse its determination of nonresponsibility, withdraw the COC referral, and award JRS
    the contract. JRS’s March 6, 2012 email did not refer to the Ceramics Contract at all.
    On March 27, 2012, JRS submitted a “Contracts Disputes Act Claim” regarding
    the December 16, 2010 PPE. JRS requested equitable adjustment for an alleged
    unilateral change in the Ceramics Contract’s terms based on the Government’s generation
    of the PPE without JRS’s express consent. JRS also argued, for the first time, that the
    contract was unenforceable as an indefinite delivery/requirements contract (for reasons
    which will be discussed below). JRS argued that the unenforceability of the contract
    rendered the BOP’s evaluation of JRS’s performance erroneous because the evaluation
    relied upon JRS’s failure to perform when it was not legally obligated to perform at all.
    4
    On May 24, 2012, JRS’s claim was denied in its entirety. The contracting
    officer’s decision explained that, while FAR 42.1502(b) described instances when a
    contracting officer must produce a PPE, it did not prohibit contracting officers from
    producing them in situations not covered by the regulation. With respect to JRS’s
    unenforceability argument, the contracting officer observed that JRS had failed to raise
    the issue more than a year before when it first had an opportunity to challenge the PPE
    ratings and therefore summarily rejected this argument.
    On August 15, 2012, JRS submitted a revised claim which presented additional
    information and documentation but which was otherwise similar to its previous claim.
    This claim expanded the scope of JRS’s legal arguments from the two grounds expressed
    in the original claim (unilateral change in the contract’s terms and unenforceability) to
    the additional legal theories which form the basis of the instant litigation: violation of
    FAR 42.1502, unilateral modification of the contract, breach of the covenant of good
    faith and fair dealing, unenforceability and bad faith.
    On October 12, 2012, the contracting officer summarily rejected JRS’s revised
    claim, finding that “the allegations made stem from the same set of operative facts as, and
    are substantially the same as, the original claim [JRS] filed on March 27, 2012.”
    Ceramics Compl. Ex. J. The contracting officer also concluded that JRS’s claims
    pertaining to the FCI Miami contract were not related to the Ceramics Contract and
    therefore rejected JRS’s arguments relating to the FCI Miami contract. This litigation
    followed.
    c. The Parenting Contract
    On August 20, 2009, the parties entered into the Parenting Contract. The
    substantive provisions of the Parenting Contract largely mirror those in the Ceramics
    contract. The similarities between the two contracts include the inclusion of FAR
    52.216-21, Requirements (Oct 1995) Alternate I (Apr 1984) and FAR 52.212-4(c).
    The Parenting Contract established an effective date of October 1, 2009, and
    awarded a base year plus four one year option periods. The value of the contract was
    estimated at $81,432. The general structure of this arrangement mirrors the structure of
    the Ceramics Contract, save that the classroom subject matter was parenting skills rather
    than ceramics. Thus, JRS hired subcontractors to provide the actual instruction, JRS
    would receive notice of services to be furnished via delivery or task orders, and JRS
    would invoice the Government after services had been rendered.
    JRS, through its subcontractors, provided services for the first year of the contract
    and the first four months of the first option period. JRS has been paid in full for all
    services rendered. No services were rendered during the last eight months of the first
    option period, and the Government opted not to exercise the second option period.
    The BOP generated PPEs for the base year and the first option period. Both
    evaluations were submitted to JRS for review. JRS submitted a rebuttal, wherein it
    5
    countered specific ratings from the evaluation. On February 24, 2011, JRS was informed
    that the base year PPE had been reevaluated; JRS received an overall rating of “good” for
    the base year evaluation.
    On March 27, 2012, JRS submitted a “Contracts Disputes Act Claim” regarding
    the base year and option year PPEs on the Parenting Contract. Once again, JRS argued
    that the generation of PPEs amounted to a unilateral change in the terms of the contract
    and for the first time, argued that the Parenting Contract was legally unenforceable for
    the same reasons expressed in the Ceramics Contract claim.
    From this point, the Parenting Contract and the Ceramics Contract claims
    followed virtually identical paths. On the same date as the contracting officer denied
    JRS’s Ceramics Contract claim, May 24, 2012, the contracting officer also denied the
    Parenting Contract claim. The contracting officer’s reasoning mirrored the reasoning in
    the Ceramics Contract claim, to include the observation that JRS never raised the issue of
    enforceability when it first had an opportunity to comment on its ratings.
    As with the Ceramics Contract, JRS submitted a second, more detailed claim on
    August 15, 2012. Just as the revised Ceramics Contract claim anticipated the legal claims
    filed in Civ. No. 13-174, the revised Parenting Contract claim anticipates the legal claims
    filed in Civ. No. 13-196. The Parenting Complaint mirrors the Ceramics Complaint save
    that it does not include the affirmative bad faith claim raised with respect to the Ceramics
    Complaint.
    Finally, as with the Ceramics Contract claim, the revised Parenting Contract claim
    was denied on October 12, 2012. The contracting officer again found that the arguments
    raised in the revised claim were substantially the same as those raised in the original
    Parenting Contract claim. This litigation followed.
    II.     Standard of Review
    Under Rule 56 of the Rules of the Court of Federal Claims, summary judgment is
    appropriate when there is no genuine issue as to any material fact and the moving party is
    entitled to judgment as a matter of law. See RCFC 56(c); see also Celotex Corp. v.
    United States, 
    477 U.S. 317
    , 322 (1986); Anderson v. Liberty Lobby, Inc., 
    477 U.S. 242
    ,
    247-48 (1986). A dispute is “genuine” only if the evidence is such that a reasonable jury
    could return a verdict for the non-moving party. Anderson, 
    477 U.S. at 248
    . A fact is
    only material if it might “affect the outcome of the suit under the governing law.” 
    Id.
    III.    Discussion
    The Court is faced with opposing motions and the legal standard described above
    applies equally to all of the pending motions. However, because the material facts are
    not in dispute, the Court will address both parties’ opposing arguments simultaneously.
    6
    In presenting their arguments, the parties have combined a few of the Counts in
    JRS’s complaints into one argument. To reiterate, both complaints state four counts: (1)
    that the BOP exceeded its authority to prepare performance evaluations as delineated in
    FAR Subpart 42.15; (2) that the BOP’s preparation of the PPEs amounts to a unilateral
    change in the terms of the contracts, in violation of the Contracts’ express incorporation
    of FAR 52.212-4(c); (3) that the BOP’s evaluations were arbitrary and capricious because
    JRS received negative evaluations for failing to perform under contracts which were
    unenforceable; and (4) that the BOP, by preparing the PPEs as if JRS was obligated to
    perform when JRS claims it was not, breached the implied duty of good faith and fair
    dealing. The Ceramics Complaint states a fifth count alleging affirmative bad faith on
    the BOP’s part when the BOP delivered the Ceramics PPE directly to FCI Miami.
    The key issue in this case is the enforceability of the contracts. Unless the
    contracts are enforceable to some degree, JRS’s arguments concerning violation of the
    FAR in preparing performance evaluations, unilateral change in the contracts, wrongful
    negative evaluations under the contracts, and the effect of the negative evaluations lack a
    legal basis.
    a. The Enforceability of the Contracts
    The parties agree that the contracts are both unenforceable as written. Where the
    parties differ is their view of the degree to which these initially-unenforceable contracts
    became enforceable due to their conduct. On the one hand, JRS argues that the contracts
    are enforceable only to the extent that JRS performed. The Government, on the other
    hand, argues that JRS waived its opportunity to raise this argument or, alternatively, that
    there was an implied-in-fact contract (actually, two contracts) between the parties. As the
    Court understands the Government’s position, both arguments result in a contract
    identical in scope to the original.
    The flaw that both parties agree renders the contracts unenforceable as written is
    that although the contracts purport to be requirements/indefinite quantity contracts, the
    contracts cannot be requirements contracts because they failed to make JRS the exclusive
    provider of services, see Horn v. United States, 
    98 Fed. Cl. 500
    , 504-505 (2011) (Smith,
    J.) (finding that FAR 52.216-21 (Oct. 1995) Alternate I (Apr. 1984) negates the
    exclusivity element necessary for a requirements contract), and they cannot be indefinite
    quantities contracts because they did not specify a guaranteed minimum number of
    services to be provided. See 
    id. at 505
     (an indefinite quantities contract requires an
    expressly-stated minimum quantity to be enforceable).
    JRS’s argument for limited enforceability relies on Willard, Sutherland & Co. v.
    United States, 
    262 U.S. 489
     (1923) and the Horn case just mentioned. In both cases, the
    contract at issue was similar to those now before the Court and, in both cases, the contract
    was found to be unenforceable as written, but enforceable to the extent to which it was
    actually performed. See Willard, 
    262 U.S. at 494
     (“While the contract at its inception
    was not enforceable, it became valid and binding to the extent that it was performed.”);
    Horn, 98 Fed. Cl. at 506 (finding that, even though the contract was unenforceable at its
    7
    inception, the plaintiff was “nonetheless entitled to payment for services actually ordered
    by, and performed for, the BOP.”) (citing Willard, 
    262 U.S. at
    494
    The Government’s first argument is that JRS cannot even make an argument for
    limited enforceability, because JRS waived its chance to do so. But all of the cases cited
    by the Government for this proposition involved a knowing waiver of rights under the
    contract. See Ling-Temco-Vought, Inc. v. United States, 
    201 Ct. Cl. 135
    , 
    475 F.2d 630
    ,
    637 (1973) (“wherever a contract not already fully performed is continued in spite of a
    known breach, the wronged party cannot avail himself of that excuse); see also Aleutian
    Constructors v. United States, 
    24 Cl. Ct. 372
    , 384 (1991) (the Government knew of a
    breach and did not request remedy). Here, there is no evidence that JRS knew of the
    unenforceability. It could not therefore waive its right to raise this argument.
    The Government’s alternate argument that the contracts are implied-in-fact
    contracts is based on Howell v. United States, 
    51 Fed. Cl. 516
     (2002). In Howell, the
    court addressed a set of indefinite quantity contracts which failed to expressly state a
    guaranteed minimum. Facially, then, the Howell contracts resembled the contracts in
    Willard and Horn, the cases cited by JRS. Unlike Willard and Horn, however, the
    Howell contracts were found enforceable. In short, the court’s decision was based upon
    the inclusion of FAR 52.216-22,4 which necessarily obligated the Government “to order
    some minimum quantity of plaintiff’s services.” Howell, 51 Fed. Cl. at 523 (emphasis in
    original). The Court merely supplied the specific minimum in contracts which already
    contained an implicit minimum. See id. at 523-24.
    The problem with this argument is that the relevant FAR provision for the
    contracts at issue is FAR 52.216-21, not FAR 52.216-22, as in the Howell case. In the
    Court’s view, FAR 52.216-21 does not carry the same implicit minimum as FAR 52.216-
    22. Instead, FAR 52.216-21 leaves open the possibility that the Government will
    purchase nothing at all. See FAR 52.216-21, Requirements (Oct 1995) Alternate I (Apr
    1984) (“Except as this contract otherwise provides, the Government shall order from the
    Contractor all of that activity’s requirements for supplies and services in the Schedule
    that exceed the quantities that the activity may furnish within its own capabilities.”)
    (emphasis added).
    Willard and Horn, on the other hand, are directly applicable: they held that
    contracts unenforceable at their inception for the same reason as the contracts now before
    the Court become enforceable to the extent that they are actually performed by the
    parties. Accordingly, the Court concludes that the contracts were both enforceable to the
    extent that they were actually performed. Nevertheless, the Court’s determination that
    the contracts are enforceable to some degree does not necessarily lead to JRS’s other
    conclusions.
    4
    Note that this provision is not the same as the provision now before the Court: the
    contracts-in-suit contain FAR 52.216-21, not 52.216-22.
    8
    b. The Government Did Not Exceed Its Authority Under FAR
    Subpart 42.15 or Unilaterally Change the Terms of the Contracts
    Based on the limited enforceability of the contracts, JRS argues that the BOP’s
    preparation of the PPEs went beyond its authority either under the FAR or the contract
    itself. In effect, these arguments boil down to two points: (1) the BOP violated FAR
    Subpart 42.15 by preparing performance evaluations which are not mandated by that
    FAR provision, and (2) the Government breached the terms of the contract by making a
    unilateral change.
    JRS focuses on FAR 42.1502 (included under FAR Subpart 42.15) in particular.
    According to JRS, FAR 42.1502 describes the only situations in which a government
    agency can prepare PPEs (presumably absent contractual authority to do so). The
    Government argues to the contrary, arguing that FAR 42.1502 only applies to situations
    in which the government must or must not prepare PPEs. In all other instances, the
    Government argues, the preparation of PPEs is left to the discretion of the contracting
    officer.
    FAR 42.1502 states:
    (a) General. Past performance evaluations shall be prepared at
    least annually and at the time the work under a contract or order is
    completed. Past performance evaluations are required for contracts and
    orders for supplies, services, research and development, and contingency
    operations, including contracts and orders performed inside and outside
    the United States, with the exception of architect-engineer and
    construction contracts or orders, which will still be reported into the
    Architect-Engineer Contract Administration Support System (ACASS)
    and Construction Contractor Appraisal Support System (CCASS)
    databases of CPARS. These evaluations are generally for the entity,
    division, or unit that performed the contract or order. Past performance
    information shall be entered into CPARS, the Governmentwide evaluation
    reporting tool for all past performance reports on contracts and orders.
    Instructions for submitting evaluations into CPARS are available at
    http://www.cpars.gov/.
    (b) Contracts. Except as provided in paragraphs (e), (f), and (h) of
    this section, agencies shall prepare evaluations of contractor performance
    for each contract (as defined in FAR part 2) that exceeds the simplified
    acquisition threshold and for each order that exceeds the simplified
    acquisition threshold. Agencies are required to prepare an evaluation if a
    modification to the contract causes the dollar amount to exceed the
    simplified acquisition threshold.
    (c) Orders under multiple-agency contracts. Agencies shall
    prepare an evaluation of contractor performance for each order that
    exceeds the simplified acquisition threshold that is placed under a Federal
    Supply Schedule contract or placed under a task-order contract or a
    9
    delivery-order contract awarded by another agency (i.e., Government wide
    acquisition contract or multi-agency contract). Agencies placing orders
    under their own multiple-agency contract shall also prepare evaluations
    for their own orders. This evaluation shall not consider the requirements
    under paragraph (g) of this section. Agencies are required to prepare an
    evaluation if a modification to the order causes the dollar amount to
    exceed the simplified acquisition threshold.
    (d) Orders under single-agency contracts. For single-agency task-
    order and delivery-order contracts, the contracting officer may require
    performance evaluations for each order in excess of the simplified
    acquisition threshold when such evaluations would produce more useful
    past performance information for source selection officials than that
    contained in the overall contract evaluation (e.g., when the scope of the
    basic contract is very broad and the nature of individual orders could be
    significantly different). This evaluation need not consider the requirements
    under paragraph (g) of this section unless the contracting officer deems it
    appropriate.
    (e) Past performance evaluations shall be prepared for each
    construction contract of $650,000 or more, and for each construction
    contract terminated for default regardless of contract value. Past
    performance evaluations may also be prepared for construction contracts
    below $650,000.
    (f) Past performance evaluations shall be prepared for each
    architect-engineer services contract of $30,000 or more, and for each
    architect-engineer services contract that is terminated for default
    regardless of contract value. Past performance evaluations may also be
    prepared for architect-engineer services contracts below $30,000.
    (g) Past performance evaluations shall include an assessment of
    contractor performance against, and efforts to achieve, the goals identified
    in the small business subcontracting plan when the contract includes the
    clause at 52.219-9, Small Business Subcontracting Plan.
    (h) Agencies shall not evaluate performance for contracts awarded
    under Subpart 8.7.
    (i) Agencies shall promptly report other contractor information in
    accordance with 42.1503(h).
    Several parts of this FAR provision inform the Court’s conclusion that a
    contracting officer is given discretion to prepare performance evaluations in those
    circumstances not expressly described in the FAR. First, paragraph (a) generally
    provides that PPEs should be produced annually. This language is very broad. Second,
    Paragraphs (b) through (d) require preparation of PPEs when a contract exceeds a
    simplified acquisition threshold. They do not forbid PPEs; they only state requirements
    for when an evaluation must be prepared. Third, Paragraph (h) expressly states that
    agencies “shall not” evaluation performance in limited circumstances not relevant here.
    This tells the Court that the drafters of the FAR knew how to withhold authority when
    10
    they wished to do so. Finally, Paragraphs (e) and (f) simply require evaluations when
    construction or architect-engineer services contracts exceed a specified value.
    JRS argues that the second sentence in both Paragraphs (e) and (f) somehow
    indicates the intent to limit the discretion of contracting officers. Both paragraphs
    include a statement that “[p]ast performance evaluations may also be prepared for
    [construction or architect-engineer services] contracts below” the specified value. To the
    contrary, the Court reads these two statements as simply affirming the general authority
    of contracting officers to prepare PPEs on a discretionary basis. The provisions stand
    only for the proposition that a contracting officer must prepare evaluations when
    expressly required, but that he otherwise has the discretionary authority to prepare PPEs
    when not expressly required. They stand for nothing more. Thus, by this Court’s reading
    of the FAR, contracting officers have broad discretion in producing evaluations, except in
    the limited circumstances discussed in FAR 42.1502.
    JRS’s breach argument is less clear than its FAR argument, but seems to boil
    down to the argument that the preparation of the PPEs was a unilateral change to the
    contracts. This argument is based on two points: (1) the Contracts did not expressly
    provide for the preparation of evaluations, and (2) the Contracts expressly incorporated
    FAR 52.212-4, which includes a requirement that any modification to the scope of the
    contract “may be made only by written agreement of the parties.” FAR 52.212-4(c). JRS
    argues that the Government unilaterally modified the Contracts and did not do so in
    writing, which act constitutes a breach.
    As to whether the contract expressly provides for the preparation of evaluations,
    both contracts state that “[t]he [contracting officer] is responsible, as applicable, for: …
    evaluating performance.” See Ceramics Compl. Ex. A at 9; Parenting Compl. Ex. A at
    10. This is the only language in either contract that refers to performance evaluation, and
    it certainly does not place a duty upon the BOP not to prepare the evaluations. Indeed, it
    does seem to be a provision that expressly provides for preparation of evaluations.
    The statement quoted above also disposes of JRS’s argument based on the written
    modification agreement requirement of the FAR. Once again, the Contracts both
    provided that the contracting officer could evaluate performance “as applicable.” The
    Court’s discussion of FAR 42.1502 demonstrates that an evaluation in this particular
    instance is left to the discretion of the contracting officer. It would then follow that a
    contracting officer’s exercise of that discretion falls within the purview of the Contracts’
    “as applicable” language. No modification was necessary for the BOP to evaluation
    JRS’s performance.
    c. The Government Did Not Breach Any Implied Covenant of Good
    Faith And Fair Dealing
    JRS next argues, with respect to both contracts, that the Government breached an
    implied covenant of good faith and fair dealing. For example, JRS claims that the
    11
    Government’s ratings were decreased based on JRS’s failure to perform work which it
    was under no obligation to perform. The Government, of course, argues to the contrary.
    The implied duty of good faith and fair dealing “is an implied duty that each party
    to a contract owes to its contracting partner.” Centex Corp. v. United States, 
    395 F.3d 1283
    , 1304 (Fed. Cir. 2005). This duty imposes obligations on both parties, including
    “the duty not to interfere with the other party’s performance and not to act so as to
    destroy the reasonable expectations of the other party regarding the fruits of the contract.”
    
    Id.
     This implied duty extends to the Government. 
    Id.
    As the Government observes here, JRS must clear a significant evidentiary hurdle
    in order to meet its burden. This hurdle comes in the form of the presumption that
    government officials act in good faith. See Kalvar Corporation, Inc. v. United States,
    
    211 Ct. Cl. 192
    , 
    543 F.2d 1298
    , 1301-1302 (1976); see also Road and Highway Builders,
    LLC v. United States, 
    702 F.3d 1365
    , 1368 (Fed. Cir. 2012) (“We and our predecessor
    court, the Court of Claims, have long upheld the principle that government officials are
    presumed to discharge their duties in good faith.”). This presumption may only be
    overcome by the presentation of clear and convincing evidence that the official did not
    discharge his or her duty in good faith. See Am-Pro Protective Agency, Inc. v. United
    States, 
    281 F.3d 1234
    , 1239-40 (Fed. Cir. 2002).
    Here, the only evidence before the Court shows that the parties entered into a pair
    of contracts that, while unenforceable, were not treated as such. JRS argues that the
    Government’s performance evaluations were inaccurate because JRS was not obligated to
    perform. While it certainly was not obligated to perform under an unenforceable
    contract, the evidence shows that despite the flaws in the written language of the
    contracts, the parties intended to be bound. For a period of time, JRS performed exactly
    as called for in the contracts. See Ceramics Compl. at ¶ 25 (JRS performed during
    October and November of 2009, the first two months of the contract); Parenting Compl.
    at ¶ 26 (JRS performed for the entire first year of the contract, as well as the first four
    months of the option year one). The Government paid for all services rendered. After an
    initial period of performance, JRS suddenly ceased providing services on both contracts.
    Even though the contracts were unenforceable as written, this evidence does not
    demonstrate any bad faith on the Government’s part. The parties performed as if their
    conduct was governed by an enforceable contract: JRS performed and the Government
    paid. Indeed, after the Government prepared the performance evaluations for both
    contracts, JRS had the opportunity to comment on the evaluations. JRS did not raise
    even the specter of unenforceability. From the Court’s view, both parties acted as if they
    were bound by a contract which required that JRS perform certain services whenever the
    Government requested them.
    For these reasons, the Court finds that JRS has failed to demonstrate anything in
    the Government’s actions that breach the implied duty of good faith and fair dealing or
    otherwise demonstrate that the BOP’s evaluations were arbitrary or capricious.
    12
    Therefore, the Government is entitled to summary judgment with respect to JRS’s
    implied duty claims.
    d. The Government Did Not Affirmatively Act in Bad Faith
    This particular argument applies only to the Ceramics Contract. Relying on
    Levering & Garrigues Co. v. United States, 
    71 Ct.Cl. 739
    , 757 (1931), JRS argues not
    that the BOP failed to act in good faith, but that its conduct was so arbitrary and grossly
    erroneous that it constitutes bad faith. The Government argues that the contracting
    officer’s actions were in accord with the relevant regulations.
    This argument revolves largely around JRS’s proposal relating to the FCI Miami
    solicitation. Specifically, JRS notes that even though the contracting officer marked the
    Ceramics PPE as “source selection information,” the PPE was never submitted to the Past
    Performance Information Retrieval System (“PPIRS”). Because the PPE was never
    submitted to PPIRS, JRS argues that the FCI Miami contracting officer “did not obtain
    the evaluation by accessing the PPIRS database of her own volition.” Ceramics Mot. at
    18. It appears, based on the pleadings, that the FCI Miami contracting officer received
    the PPE directly from the FPC officers in West Virginia. JRS claims that its bid on the
    FCI Miami solicitation was rejected because of the Ceramics PPE.
    The Court returns once again to the presumption of good faith on the part of
    government officials. See Road and Highway Builders, 702 F.3d at 1368. The only
    evidence that JRS has provided in support of this argument is that the FPC contracting
    officer provided the Ceramics evaluation to the FCI Miami staff. Thus, JRS has offered
    no evidence that the contracting officer was acting in bad faith by providing the PPE to
    FCI Miami. To the contrary, as the Government argues, the contracting officer’s
    disclosure of the Ceramics evaluation was proper under the FAR. See FAR 9.105-1(d)
    (“Contracting officers and cognizant contract administration offices that become aware of
    circumstances casting doubt on a contractor’s ability to perform contracts successfully
    shall promptly exchange relevant information.”) (emphasis added); see also FAR 9.105-
    1(a) (“Before making a determination of responsibility, the contracting officer shall
    possess or obtain information sufficient to be satisfied that a prospective contractor
    currently meets the applicable standards in 9.104.”).
    In addition, the Government briefly touches on a point that this Court finds
    particularly relevant here. The Government observes that JRS should have filed a bid
    protest on the FCI Miami solicitation if it wished to protest the finding of non-
    responsibility. The Court agrees on this point, as it appears that the alleged injury which
    resulted from the alleged bad faith is JRS’s failure to receive the FCI Miami award; the
    alleged actions did not interfere with the performance of the Ceramics Contract in any
    way.
    Again, the record is devoid of any evidence that supports JRS’s legal theory.
    JRS’s failure to meet its evidentiary burden once again leads the Court to conclude that
    the Government is entitled to summary judgment with respect to JRS’s bad faith claim.
    13
    IV.     Conclusion
    In sum, the Court finds that the undisputed facts entitle the Government to
    summary judgment on all counts of both complaints. Regarding Count I, the
    Government did not exceed its authority under FAR Subpart 42.15 when it prepared the
    performance evaluations at issue. As to Count II, the Government did not unilaterally
    change the terms of either contract when it prepared the evaluations. Even though the
    contracts were unenforceable, the Court does not believe that the evaluations were
    arbitrary or capricious, as alleged in Count III, because both parties acted for substantial
    periods of time as if they both intended to be bound by the contracts. Even when given
    the opportunity to raise this issue when it was provided with the draft evaluations, JRS
    failed to do so. JRS failed to present any evidence that the Government breached the
    implied duty of good faith and fair dealing, as alleged in Count IV. Likewise, JRS has
    failed to present any evidence of bad faith as alleged in Count V of the Ceramics
    Complaint.
    Because the Court has determined that the Government is entitled to summary
    judgment as to all counts in JRS’s two complaints, it does not reach the Government’s
    arguments for dismissal pursuant to RCFC 12(b)(6).
    For these reasons, JRS’s motions for summary judgment are DENIED and the
    Government’s motion for summary judgment is GRANTED. The Clerk is directed to
    enter judgment accordingly.
    s/ Edward J. Damich
    EDWARD J. DAMICH
    Judge
    14