Ellis-Hall v. PSC ( 2014 )


Menu:
  •              This opinion is subject to revision before final
    publication in the Pacific Reporter.
    
    2014 UT 52
    IN THE
    SUPREME COURT OF THE STATE OF UTAH
    ———————
    ELLIS-HALL CONSULTANTS, LLC,
    Petitioner,
    v.
    PUBLIC SERVICE COMMISSION OF UTAH; PACIFICORP;
    BLUE MOUNTAIN POWER PARTNERS, LLC; LATIGO WIND PARK, LLC;
    and UTAH CLEAN ENERGY,
    Respondents.
    ———————
    No. 20131146
    Filed November 21, 2014
    ———————
    Original Proceeding in this Court
    ———————
    Attorneys:
    Mary Anne Q. Wood, Stephen Q. Wood, Salt Lake City,
    for petitioner
    Jordan White, R. Jeff Richards, Daniel E. Solander, Gary A. Dodge,
    Phillip J. Russell, Gary G. Sackett, Jessica W. Wilde,
    Stephen K. Christiansen, Salt Lake City, for respondents
    ———————
    JUSTICE LEE authored the opinion of the court, in which
    CHIEF JUSTICE DURRANT, ASSOCIATE CHIEF JUSTICE NEHRING,
    JUSTICE DURHAM, and JUSTICE PARRISH joined.
    ———————
    JUSTICE LEE, opinion of the court:
    ¶1 In 2013, the Utah Public Service Commission approved
    power purchase agreements between PacifiCorp and two small
    power producers, Latigo Wind Park and Blue Mountain Power
    Partners. Under these agreements, PacifiCorp’s Rocky Mountain
    Power division would become obligated to purchase all power
    produced by the producers’ clean energy wind projects in South-
    eastern Utah. This is an appeal by Ellis-Hall Consultants, a com-
    petitor of Latigo and Blue Mountain. Ellis-Hall intervened in the
    PSC proceedings below and sought to challenge the Latigo and
    ELLIS-HALL CONSULTANTS v. PUBLIC SERVICE COMMISSION
    Opinion of the Court
    Blue Mountain agreements. In so doing, Ellis-Hall asserted that
    the PSC had unlawfully excused Latigo and Blue Mountain from
    compliance with the terms of an applicable regulatory tariff, re-
    ferred to as Schedule 38. It also claimed discrimination by Pacifi-
    Corp—in requiring Ellis-Hall to comply with the regulatory re-
    quirements from which Latigo and Blue Mountain had been ex-
    cused. And it asserted that the power purchase agreements were
    too vague to be enforceable, and should be disapproved on that
    basis.
    ¶2 In light of the time-sensitive nature of this matter, we ex-
    pedited this case for briefing and oral argument. And after oral
    argument we issued an order affirming the PSC’s decision, with
    an opinion explaining our analysis to follow. The opinion below
    describes the bases for our decision. We hold that the cited terms
    of Schedule 38 were not contravened by the Latigo and Blue
    Mountain power purchase agreements, and that the “public inter-
    est” inquiry the PSC is charged with does not implicate the dis-
    crimination or vagueness concerns Ellis-Hall identifies.
    I
    ¶3 Ellis-Hall, Blue Mountain, and Latigo are involved in the
    development of wind power generation projects in San Juan
    County. The end goal for each is to sell the power generated by
    those projects (known as qualifying facilities or “QFs”) to Pacifi-
    Corp through its Rocky Mountain Power division—with that
    power then being transmitted along PacifiCorp’s interstate trans-
    mission system via a local interconnection point.
    ¶4 A QF seeking to sell its generated power must enter into
    two distinct contractual arrangements, each subject to PSC ap-
    proval. One is called a large generation interconnection agree-
    ment. This contract governs the QFs’ use of PacifiCorp’s transmis-
    sion system. The other required contract is a power purchase
    agreement with Rocky Mountain Power. This latter agreement,
    governed by Utah Code section 54-12-2 and Rocky Mountain
    Power Electric Service Schedule No. 38, 1 controls Rocky Mountain
    1  Schedule 38 is an element of Tariff No. 49, a regulatory provi-
    sion approved by the Utah Public Service Commission in October
    of 2012 and amended from time to time thereafter.
    2
    Cite as: 
    2014 UT 52
                           Opinion of the Court
    Power’s obligation to purchase power from the QF, prescribing
    price, quantity, and duration.
    ¶5 In 2012 Latigo and Blue Mountain began negotiating the
    terms of a power purchase agreement with Rocky Mountain Pow-
    er. They also began to pursue interconnection agreements with
    PacifiCorp for use of its local transmission point. Before finalizing
    their interconnection agreements, both Latigo and Blue Mountain
    executed power purchase agreements with Rocky Mountain Pow-
    er and then submitted their agreements to the PSC for approval.
    ¶6 During this same time period, Ellis-Hall was also pursuing
    its own interconnection and power purchase agreements. When
    the Latigo and Blue Mountain power purchase agreements went
    before the PSC, Ellis-Hall had not yet secured a power purchase
    agreement. It was instead involved in negotiations over the terms
    of an interconnection agreement.
    ¶7 Ellis-Hall moved to intervene in the Latigo and Blue Moun-
    tain PSC proceedings. The PSC granted Ellis-Hall’s motions. Ellis-
    Hall then filed formal objections to the approval of the Latigo and
    Blue Mountain power purchase agreements. First, Ellis-Hall
    claimed that PacifiCorp/Rocky Mountain Power had discriminat-
    ed against Ellis-Hall in its pursuit of a power purchase agreement
    in violation of both state and federal law—subjecting Ellis-Hall to
    mandatory compliance with the terms of Schedule 38 but taking a
    more permissive, liberal approach with Latigo and Blue Moun-
    tain. Second, Ellis-Hall asserted that Latigo, Blue Mountain, and
    PacifiCorp had colluded in the negotiation of the power purchase
    agreements in a manner contravening the terms of Schedule 38
    and the public interest element of federal and state law. Third, El-
    lis-Hall challenged the enforceability of the Latigo and Blue
    Mountain power purchase agreements, asserting that they were
    too vague to be enforceable. And finally, Ellis-Hall requested dis-
    covery of material related to its various claims.
    ¶8 During a hearing on these matters, the PSC determined
    that the public interest analysis was limited to whether the rates in
    the power purchase agreements were “just and reasonable.” Ac-
    cordingly, the PSC denied Ellis-Hall’s discovery requests and mo-
    tions to compel, concluding that the discovery went to matters not
    relevant to the public interest inquiry.
    3
    ELLIS-HALL CONSULTANTS v. PUBLIC SERVICE COMMISSION
    Opinion of the Court
    ¶9 After holding the hearing and reviewing the evidence, the
    PSC issued an order approving the Blue Mountain and Latigo
    power purchase agreements. The PSC first rejected Ellis-Hall’s ar-
    gument that the “public interest” standard for approval of power
    purchase agreements goes beyond an inquiry into “just and rea-
    sonable” rates. Thus, because the power purchase agreements
    were consistent with the approved method for calculating the
    rates to be paid to QFs and because they contained terms and
    conditions that adequately protected ratepayers (consumers) from
    risk, the PSC determined that they were in the public interest.
    ¶10 The PSC then rejected both of Ellis-Hall’s contentions re-
    garding Schedule 38—that it mandated the procedures PacifiCorp
    had to follow and that PacifiCorp had discriminated against Ellis-
    Hall by permitting Latigo and Blue Mountain to secure power
    purchase agreements without having first secured interconnection
    agreements. As to the former argument, the PSC held that
    “Schedule 38 does not prescribe the due diligence that PacifiCorp
    must perform but rather acts as a check on the due diligence Pacif-
    iCorp may perform.” And as to the latter, the PSC held that dis-
    crimination claims are “outside the scope of our consideration,”
    and accordingly rejected that argument. Ellis-Hall now seeks re-
    view of the PSC’s order.
    ¶11 We have jurisdiction under Utah Code section 78A-3-
    102(3)(e)(i), and review the PSC’s decision under the terms of the
    Utah Administrative Procedures Act, UTAH CODE sections 63G-4-
    101 to -601. Our review of the PSC’s factual determinations is def-
    erential; we may reverse the agency’s findings only if they are ar-
    bitrary, capricious, or “beyond the tolerable limits of reason.”
    Utah Chapter of the Sierra Club v. Utah Air Quality Bd., 
    2006 UT 74
    ,
    ¶ 9, 
    148 P.3d 960
    (internal quotation marks omitted). As to thresh-
    old legal questions, however, our review is nondeferential—de
    novo. See Manzanares v. Byington (In re Baby B), 
    2012 UT 35
    , ¶ 41,
    
    308 P.3d 382
    .
    II
    ¶12 Ellis-Hall challenges the PSC’s approval of the Latigo and
    Blue Mountain power purchase agreements on three grounds:
    (a) the PSC failed to require strict compliance with the terms of
    Schedule 38, which Ellis-Hall views as nondiscretionary; (b) Pacif-
    iCorp engaged in discrimination in its application of the terms of
    4
    Cite as: 
    2014 UT 52
                           Opinion of the Court
    Schedule 38—applying them leniently to Latigo and Blue Moun-
    tain but strictly to Ellis-Hall—in a manner inconsistent with the
    “public interest”; and (c) the terms of the Latigo and Blue Moun-
    tain power purchase agreements were too vague to be enforcea-
    ble. We reject all three arguments and accordingly affirm.
    A. Schedule 38
    ¶13 Ellis-Hall first claims error in the PSC’s failure to insist on
    strict compliance with the terms of Schedule 38. This claim rests
    specifically on the Schedule 38 provision regarding interconnec-
    tion agreements. Ellis-Hall reads this provision to require an in-
    terconnection agreement as a prerequisite to the approval of a
    power purchase agreement, and charges the PSC with reversible
    error for not holding Latigo and Blue Mountain to strict compli-
    ance with this provision.
    ¶14 We view Schedule 38’s terms differently. Granted, this
    document contemplates that owners of QFs above a certain capac-
    ity “will be required to enter into written power purchase and in-
    terconnection agreements” with PacifiCorp/Rocky Mountain
    Power, under the terms and conditions of the Schedule. Rocky
    Mountain Power Elec. Serv. Schedule No. 38, at 38.1 (Sept. 1,
    2014), available at https://www.rockymountainpower.net/about/
    rar/uri.html. And, as Ellis-Hall indicates, the PSC has sometimes
    referred to the terms of Schedule 38 as “the steps required to ob-
    tain” a viable power purchase agreement. But that does not trans-
    form every term and condition of Schedule 38 into a hard-and-fast
    prerequisite. Instead, the nature and extent of the requirements of
    Schedule 38 are dictated by its terms. And the document speaks
    directly and unambiguously to Ellis-Hall’s argument: It “reserves
    the right to condition execution of the power purchase agreement
    upon simultaneous execution of an interconnection agreement be-
    tween the owner and the Company’s power delivery function.” 
    Id. at 38.5.
      ¶15 That proviso is incompatible with Ellis-Hall’s position. Far
    from requiring an interconnection agreement as a prerequisite to a
    purchase agreement, Schedule 38 deems this a discretionary mat-
    ter. This is confirmed by the surrounding terms of the document,
    which simply state that “in addition to negotiating a power pur-
    chase agreement,” QFs “are also required to enter into an inter-
    connection agreement,” and that “[i]t is recommended that [the QF]
    5
    ELLIS-HALL CONSULTANTS v. PUBLIC SERVICE COMMISSION
    Opinion of the Court
    initiate its request for interconnection as early in the planning
    process as possible” to ensure that the interconnection agreement
    and purchase agreement negotiations proceed “in a timely man-
    ner on a parallel track.” 
    Id. (emphasis added).
    Under the section
    prescribing the procedures for finalizing a power purchase
    agreement, moreover, Schedule 38 merely requires a QF to pro-
    vide a written statement of the “status of interconnection ar-
    rangements.” 
    Id. at 38.2
    (emphasis added); see also 
    id. at 38.3–38.4
    (noting that if a QF wishes for Rocky Mountain Power to draft a
    proposed power purchase agreement, the QF “may” be required
    to provide “evidence that any necessary interconnection studies
    have been completed and assurance that the necessary intercon-
    nection arrangements are being made in accordance with Part II”
    (emphasis added)).
    ¶16 Nowhere does Schedule 38 make an interconnection
    agreement a prerequisite to a power purchase agreement. It in-
    stead treats this as a matter of discretion. And in any event the
    document nowhere prescribes any timing requirement. Again it
    treats this as discretionary—recommending interconnection re-
    quests “as early in the planning process as possible,” but nowhere
    dictating that the matter be finalized before the purchase agree-
    ment is entered into.
    ¶17 We affirm the Public Service Commission on this basis. We
    agree with the PSC that as to interconnection agreements,
    “Schedule 38 does not prescribe the due diligence that PacifiCorp
    must perform but rather acts as a check on the due diligence Pacif-
    iCorp may perform.”
    B. The “Public Interest” and Alleged Discrimination
    ¶18 Ellis-Hall’s next claim of error implicates its allegation of
    discrimination in the application of the terms of Schedule 38. Here
    the argument is one of differential treatment—that Latigo and
    Blue Mountain were given wide latitude as to the timing of an in-
    terconnection agreement, but Ellis-Hall has not been afforded
    such leniency. And Ellis-Hall asserts that this alleged discrimina-
    tion calls into question the key determination for the PSC—
    whether the Latigo and Blue Mountain power purchase agree-
    ments were in the “public interest.”
    ¶19 This argument implicates a threshold legal question—of
    the meaning of “public interest” in the terms of the governing
    6
    Cite as: 
    2014 UT 52
                            Opinion of the Court
    federal and state laws to be applied by the PSC. To sustain its
    challenge to the PSC’s approval of the Latigo and Blue Mountain
    power purchase agreements, Ellis-Hall would first have to estab-
    lish that its concerns regarding discrimination are implicated by
    the “public interest” standard that the PSC is charged with apply-
    ing. We affirm on the ground that Ellis-Hall has failed to carry
    that burden.
    ¶20 Ellis-Hall cites generally to provisions of state and federal
    law that protect power producers from discriminatory business
    practices. 2 But none of these provisions are properly implicated in
    this proceeding. In considering the parties’ power purchase
    agreements for approval, the PSC is tasked with a narrow, specific
    inquiry—to approve the agreed-upon power purchase rates as
    consistent with the “public interest.” That inquiry does not impli-
    cate the broader discrimination concerns identified by Ellis-Hall,
    and we affirm on that basis, as explained below.
    ¶21 The PSC administers state and federal laws requiring Pacif-
    iCorp to purchase wholesale power from QFs. Its jurisdiction over
    QF rates and the public interest originate in federal law. Under
    the Public Utility Regulatory Policies Act of 1978 (PURPA), Pub.
    L. No. 95-617, 92 Stat. 3117, the Federal Energy Regulatory Com-
    mission (FERC) is required to set rates for purchases from QFs
    that are “just and reasonable to the electric consumers of the elec-
    tric utility and [are] in the public interest.” 16 U.S.C. § 824a-
    3(b)(1). And PURPA also “requires each state regulatory authori-
    2  See 18 C.F.R. § 292.304(a)(1)(ii) (2014) (prohibiting discrimina-
    tion “against qualifying cogeneration and small power production
    facilities”); 
    id. § 358.4(a)–(c)
    (requiring “strict” enforcement of “all
    tariff provisions relating to the sale or purchase of open access
    transmission service, if the tariff provisions do not permit the use
    of discretion”); UTAH CODE § 54-3-7 (prohibiting public utilities
    from “extend[ing] to any person any form of contract or agree-
    ment, or any rule or regulation, or any facility or privilege except
    such as are regularly and uniformly extended to all corporations
    and persons”); 
    id. § 54-3-8(1)(a)
    (prohibiting public utilities from
    “mak[ing] or grant[ing] any preference or advantage to any per-
    son” with regard to any “rates, charges, service, facilities or in any
    other respect”).
    7
    ELLIS-HALL CONSULTANTS v. PUBLIC SERVICE COMMISSION
    Opinion of the Court
    ty . . . to implement FERC’s rules.” FERC v. Mississippi, 
    456 U.S. 742
    , 751 (1982) (citing 16 U.S.C. § 824a-3(f)). Thus, PURPA gives
    FERC, and by extension the PSC, “a statutory mandate to set a
    rate that is in the public interest.” Am. Paper Inst., Inc. v. Am. Elec.
    Power Serv. Corp., 
    461 U.S. 402
    , 417 (1983) (internal quotation
    marks omitted).
    ¶22 The “public interest,” in this legal context, does not encom-
    pass any and all considerations of interest to the public—such as
    the nondiscrimination principles cited by Ellis-Hall. Instead “the
    words ‘public interest’ in a regulatory statute . . . take meaning
    from the purposes of the regulatory legislation” in question.
    NAACP v. Fed. Power Comm’n, 
    425 U.S. 662
    , 669 (1976). And here
    those purposes are limited—focusing on the setting of “reasonable
    prices,” 
    id. at 670,
    and on establishing incentives for the increased
    production of QF facilities “to reduce reliance on fossil fuels.” Am.
    Paper 
    Inst., 461 U.S. at 417
    ; see also UTAH CODE § 54-12-1(2) (“[T]he
    policy of this state [is] to . . . promote a diverse array of economi-
    cal and permanently sustainable energy resources in an environ-
    mentally acceptable manner”); 
    id. § 54-12-2(2)
    (“The commission
    shall establish reasonable rates, terms, and conditions for the pur-
    chase or sale of electricity. . . .”).
    ¶23 Both federal and state law balance these objectives by re-
    quiring public utilities to purchase power from QFs at, or in some
    cases below, a utility’s “full avoided cost.” 18 C.F.R.
    § 292.304(a)(2), (b)(2)–(3) (2014); UTAH CODE § 54-12-2(2). 3 Avoided
    cost is “the incremental cost[] to an electric utility of electric ener-
    gy or capacity or both which, but for the purchase from the quali-
    fying facility or qualifying facilities, such utility would generate
    itself or purchase from another source.” 18 C.F.R. § 292.101(b)(6).
    In plain English, this means that public utilities purchase QF
    3  See also Steven R. Miles, Note, Full-Avoided Cost Pricing Under
    the Public Utility Regulatory Policies Act: “Just and Reasonable” to
    Electric Consumers?, 69 CORNELL L. REV. 1267, 1277 n.66 (1984)
    (discussing the public interest requirement and the purposes of
    PURPA and explaining that “[b]y establishing the price for pur-
    chases from qualifying facilities at the statutory ceiling, the full-
    avoided cost rule fulfills [the] purpose [of PURPA] to the maxi-
    mum extent permissible”).
    8
    Cite as: 
    2014 UT 52
                             Opinion of the Court
    power at the same rate the utility would have paid in acquiring or
    producing the same power through other means.
    ¶24 This concept of avoided cost is incorporated in the Latigo
    and Blue Mountain power purchase agreements. These contracts
    prescribe PacifiCorp’s avoided cost as the rate to be paid for QF
    power produced by Latigo and Blue Mountain. And the decision
    before us in this case is the PSC’s approval of that rate as con-
    sistent with the public interest.
    ¶25 We affirm that decision. Ellis-Hall has nowhere contested
    the PSC’s conclusion that an avoided cost rate is in the public in-
    terest. Nor could it. As the above-cited standards indicate, avoid-
    ed cost rates are a safe-harbor of reasonableness in advancing the
    public’s interest in protecting ratepayers.
    ¶26 We likewise reject Ellis-Hall’s attempt to inject broader
    nondiscrimination principles into the PSC’s approval of the QF
    rates agreed to in the Latigo and Blue Mountain power purchase
    agreements. 4 Those principles were not the domain of the PSC in
    this proceeding. Its role was simply to approve the agreed-upon
    rates as consistent with the statutory and regulatory concept of
    the public interest. And because that concept is limited to the rea-
    4   It is worth mentioning that some of the federal anti-
    discrimination provisions Ellis-Hall cites cut decidedly against the
    substance of its discrimination argument. For instance, the Code
    of Federal Regulations requires “strict[]” enforcement of “all tariff
    provisions relating to the sale or purchase of open access trans-
    mission service, if the tariff provisions do not permit the use of discre-
    tion.” 18 C.F.R. § 358.4(a) (emphasis added). In other words, the
    federal anti-discrimination regulations clearly contemplate some
    discretion and leniency in the process. See also 
    id. § 358.4(b)–(c)
    (prohibiting the application of tariff provisions in any “unduly
    discriminatory manner, if the tariff provisions permit the use of discre-
    tion” and prohibiting the giving of any “undue preference . . . relat-
    ing to the sale or purchase of transmission service” (emphasis
    added)).
    9
    ELLIS-HALL CONSULTANTS v. PUBLIC SERVICE COMMISSION
    Opinion of the Court
    sonableness of the rates in question, Ellis-Hall’s argument fails as
    a matter of law. 5
    ¶27 Ellis-Hall’s challenge to the denial of its discovery requests
    fails on the same ground. Ellis-Hall sought discovery on the na-
    ture and extent of any differential treatment by PacifiCorp/Rocky
    Mountain Power. Because those issues were irrelevant to the
    PSC’s assessment of the power rates set forth in the Latigo and
    Blue Mountain agreements, the PSC was right to deny Ellis-Hall’s
    requests for discovery. We therefore also affirm the PSC’s denial
    of Ellis-Hall’s requests for discovery.
    C. Enforceability of Power Purchase Agreements
    ¶28 Ellis-Hall’s final claim touches on the enforceability of the
    Latigo and Blue Mountain power purchase agreements. The ar-
    gument here is that certain terms of these agreements—such as
    the type of turbine to be utilized by these QFs—are too vague to
    be enforceable.
    ¶29 This claim falters on grounds set forth above. Again, the
    PSC’s role in approving a QF power purchase agreement is to
    confirm that the rates agreed to are in the “public interest.” See su-
    pra ¶¶ 20–26. And that question is resolved conclusively—and in
    favor of affirmance—by the avoided-cost terms of the Latigo and
    Blue Mountain power purchase agreements.
    5  Ultimately, Ellis-Hall’s assertion of discrimination turns on the
    concern that the terms of Schedule 38 have been applied leniently
    to Latigo and Blue Mountain. Even if that concern were properly
    presented, it would not sustain a finding of discrimination
    “against qualifying cogeneration and small power production fa-
    cilities,” 18 C.F.R. § 292.304(a)(1)(ii)—much less a remedy of more
    restrictive treatment of Latigo and Blue Mountain. An alternative
    remedy would be to confer similar leniency on Ellis-Hall. And un-
    less and until such treatment is withheld (in Ellis-Hall’s pursuit of
    its own power purchase agreement), any claim of discrimination
    is unripe.
    10
    Cite as: 
    2014 UT 52
                          Opinion of the Court
    ¶30 Once that determination was (properly) made, there was
    no work left for the PSC to do. Thus, the PSC was not thereafter
    tasked to assess the vagueness or enforceability of the Latigo or
    Blue Mountain agreements. This final claim of error accordingly
    fails regardless of whether the terms of the contract are too vague
    to be enforceable.
    ——————
    11