Build, Inc. v. Utah Dep't of Transp. , 428 P.3d 995 ( 2018 )


Menu:
  •                  This opinion is subject to revision before final
    publication in the Pacific Reporter
    
    2018 UT 34
    IN THE
    SUPREME COURT OF THE STATE OF UTAH
    BUILD, INC.,
    Appellant,
    v.
    UTAH DEPARTMENT OF TRANSPORTATION, CLYDE-GENEVA
    CONSTRUCTORS, W.W. CLYDE & CO., and GENEVA ROCK PRODUCTS,
    INC.,
    Appellees.
    No. 20151058
    Filed July 17, 2018
    On Appeal of Interlocutory Order
    Third District, Salt Lake
    The Honorable Ryan M. Harris
    No. 090904101
    Attorneys:
    Michael D. Zimmerman, Troy L. Booher, Beth E. Kennedy,
    Clark B. Fetzer, Salt Lake City, Kim J. Trout, Boise, ID, for appellant
    Stanford P. Fitts, Stephen J. Trayner, S. Spencer Brown, Jessica J.
    Johnston, Salt Lake City, for appellee Utah Department of
    Transportation
    Robert F. Babcock, Brian J. Babcock, Cody W. Wilson, Salt Lake City,
    for appellees Clyde-Geneva Constructors, W.W. Clyde & Co., and
    Geneva Rock Products, Inc.
    ASSOCIATE CHIEF JUSTICE LEE authored the opinion of the Court, in
    which CHIEF JUSTICE DURRANT, JUSTICE HIMONAS, JUSTICE PEARCE, and
    JUSTICE PETERSEN joined.
    ASSOCIATE CHIEF JUSTICE LEE, opinion of the Court:
    ¶1 Build, Inc. was hired by the Utah Department of
    Transportation (UDOT) to work on three different construction
    BUILD v. UDOT
    Opinion of the Court
    projects. Build encountered problems on all three projects, and it
    filed various claims against UDOT and three other contractors on the
    project.1 UDOT moved for summary judgment on two sets of
    claims—claims for breach of contract on the “Arcadia” project and
    claims seeking consequential damages.2 The original judge assigned
    to the case, Judge Kennedy, denied both motions.
    ¶2 After his retirement Judge Kennedy was replaced by Judge
    Harris. Judge Harris ultimately dismissed Build’s claims for breach
    of contract and consequential damages. And Build challenges both
    dismissals on this interlocutory appeal.
    ¶3 Build challenges the dismissal of the Arcadia claim on two
    grounds. It contends (a) that Judge Harris violated a so-called
    coordinate judge rule, which in Build’s view limits the discretion of a
    successor judge to revisit decisions of a predecessor; and (b) that
    Build presented sufficient evidence to defeat UDOT’s motion on its
    merits. Build also challenges the dismissal of its claim for
    consequential damages. It asserts that Judge Harris erred in
    dismissing this claim without full briefing on a motion for summary
    judgment and that he incorrectly concluded that Build lacked proof
    of its consequential damages.
    ¶4 We affirm. Judge Harris had the authority to dismiss both
    claims, and he committed no reversible error by doing so. In so
    holding, we repudiate any language in our precedent that suggests
    that a successor judge on a case is bound by nonfinal decisions and
    rulings made by his predecessor. We clarify that different judges on
    the same case are considered a single judicial officer—and thus that a
    successor judge has the same power to review nonfinal decisions
    that a predecessor would have had.
    I. BACKGROUND
    ¶5 UDOT hired Build to work as a contractor on three different
    construction projects: the Legacy project, the Arcadia project, and the
    I-215 project. Only the facts surrounding the Arcadia project are
    _____________________________________________________________
    1  These parties are Clyde-Geneva Constructors, W.W. Clyde &
    Co., and Geneva Rock Products (collectively “Clyde-Geneva”).
    2 Though we refer throughout to all the appellees collectively as
    “UDOT,” Clyde-Geneva was not a party to the Arcadia project and
    joins the appeal only as to the consequential damages claim.
    2
    Cite as: 
    2018 UT 34
                            Opinion of the Court
    relevant to this appeal, however, so we discuss only that project
    here.
    ¶6 The Arcadia project involved the replacement of a bridge
    and reconstruction of the highway on either side of it. This required
    excavation, and the excavated soil was slated to be disposed as “fill”
    around the boundaries of the project. After excavation began,
    UDOT’s engineer, Rex Harrison, discovered a complication that
    prevented this method of soil disposal. So Build disposed of the soil
    offsite, incurring $389,000 of additional costs.
    ¶7 Build requested that UDOT compensate it for this additional
    work. UDOT refused. Build then experienced financial problems and
    went out of business. It filed suit against UDOT, asserting that
    UDOT had breached its contract by asking Build to complete work
    that fell outside of the contract and then refusing to compensate
    Build for that work. Build also alleged that UDOT’s failure to
    appropriately compensate Build for this extra work led to lost capital
    and cash flow, lost bonding capacity, and eventually the demise of
    its business. Build sought damages for breach of contract. It also
    requested consequential damages associated with the loss of its
    business.
    ¶8 The agreement between these parties contains two
    provisions dealing with changes to the contract; the viability of
    Build’s claim for breach depends on which of the two applies here.
    One provision, found in Part 1.6, deals with changes that the
    engineer recognizes as falling outside of the contract. It allows
    UDOT to make intentional changes to the project if it does so in
    writing. Build’s breach of contract claim invoked this provision of
    the contract. It asserted that UDOT had recognized that the
    additional soil disposal was outside of the contract’s parameters, and
    claimed that UDOT had breached Part 1.6 by failing to give notice in
    writing and to compensate Build for this change.
    ¶9 UDOT denied that Part 1.6 applied and claimed instead that
    Part 1.5 of the contract controlled. That provision governs if Build
    believes there has been a change in the contract that UDOT does not
    recognize. In that case, Build must give UDOT notice of the “alleged
    change” in writing within five days of the date a change is noted.
    ¶10 The contract also provides that “[f]ailure to provide the
    required notice constitutes a waiver of any and all claims that may
    arise as a result of the alleged breach.” It is undisputed that Build
    failed to provide the notice required by Part 1.5. And UDOT asserted
    that Build had waived its claim to additional compensation by
    3
    BUILD v. UDOT
    Opinion of the Court
    failing to provide this notice. It moved for summary judgment on
    that basis.
    ¶11 UDOT also moved for summary judgment on the
    consequential damages issue. It argued that Build had “failed to
    provide any evidence as to the value of [its] business before and after
    UDOT’s alleged conduct.” UDOT acknowledged that Build had
    designated an expert (Joan Whitacre). But it noted that Ms. Whitacre
    had failed to specify an amount of consequential damages or to
    identify a methodology for calculating such damages.
    ¶12 The summary judgment motion on the breach of contract
    claim was submitted to Judge Kennedy for decision. He denied the
    motion on all counts. In denying the motion Judge Kennedy ruled
    that Build’s claims were “subject to questions of fact, including
    whether UDOT breached its contract with [Build], whether UDOT
    waived the notice provision and whether [Build’s] claims satisfy the
    requirement of the Changed Conditions Clause of the contract
    specifications.”
    ¶13 Judge Kennedy also upheld the viability of Build’s
    consequential damages claim. He concluded that Build had
    “presented evidence—most notably in the form of Joan Whitacre’s
    expert opinion—that supports its consequential damages claim.”
    ¶14 Judge Kennedy retired soon after issuing his decision
    denying UDOT’s motions. He was replaced in this case by Judge
    Harris. By that time the dispositive motion deadline had long since
    passed. Yet UDOT filed two new motions. The first, styled as a
    motion for clarification, related to the Arcadia claim. In that motion,
    UDOT claimed that Judge Kennedy should have applied Meadow
    Valley Contractors, Inc. v. State Department of Transportation—a
    decision addressing contract provisions virtually identical to Parts
    1.5 and 1.6 of the contract between Build and UDOT. 
    2011 UT 35
    , 
    266 P.3d 671
    , abrogated on other grounds by Mounteer Enters., Inc. v.
    Homeowners Ass'n for the Colony at White Pine Canyon, 
    2018 UT 23
    , __
    P.3d __. The Meadow Valley court determined that contractual
    language mirroring Part 1.6 applied only where the engineer
    “knowingly and deliberately” made changes to the contract. 
    Id. ¶ 31.
    And in the absence of a showing of knowledge or deliberate action,
    it held that any alteration to the contract would have to be
    considered an “alleged change”—triggering the language in the
    contract mirroring Part 1.5, with its requirement that the contractor
    provide notice of the alleged change or else forfeit its right to
    compensation. 
    Id. ¶ 33.
    4
    Cite as: 
    2018 UT 34
                            Opinion of the Court
    ¶15 Judge Harris agreed with UDOT that Meadow Valley
    controlled. He held that Build had failed to provide any evidence
    that the change was “knowing and deliberate” on Harrison’s part,
    and that Part 1.5 accordingly applied. And because Build had failed
    to comply with the notification requirements of that Part, Judge
    Harris concluded that Build had waived its claim for additional
    compensation. He accordingly entered summary judgment against
    Build on the Arcadia claim.
    ¶16 UDOT’s second motion was styled as a motion in limine.
    This motion asked the court to exclude the testimony of Joan
    Whitacre and Build’s president Freddie Stromness on the amount of
    Build’s consequential damages. In so moving UDOT pointed out that
    Build had never provided a calculation of its consequential damages.
    And it asserted that Whitacre and Stromness should be prohibited
    from testifying as to that amount on that basis.
    ¶17 At the hearing on the motion Judge Harris noted that a
    decision granting UDOT’s motion in limine would “fatally wound”
    the business devastation basis of the consequential damages claim.
    And he ultimately granted the motion. In so doing he also entered an
    order dismissing the consequential damages claim outright,
    concluding that the claim “fails for lack of proof” because Whitacre
    and Stromness were barred from testifying on the issue.
    ¶18 Build petitioned for leave to file this interlocutory appeal.
    We granted the petition, and review the dismissal of Build’s claims
    de novo, affording no deference to the district court’s analysis. We do
    so because the district court’s decision amounted to a summary
    dismissal of Build’s claims,3 and summary judgment is subject to de
    novo review. See Dillon v. S. Mgmt. Corp. Ret. Tr., 
    2014 UT 14
    , ¶ 21,
    
    326 P.3d 656
    .
    ¶19 We consider Build’s challenges to the dismissal of the
    Arcadia claim first, in Part II below. Then we address Build’s
    _____________________________________________________________
    3  UDOT’s motion for clarification on the Arcadia claim was
    effectively a motion to reconsider summary judgment. Infra ¶ 20 n.4.
    And that makes Judge Harris’s dismissal of the breach of contract
    claim in substance a grant of UDOT’s original summary judgment
    motion. The procedural basis for Judge Harris’s dismissal of the
    consequential damages claim is less clear. Infra ¶ 43. That said,
    because it has the effect of a grant of summary judgment, we treat it
    that way for the purposes of our standard of review.
    5
    BUILD v. UDOT
    Opinion of the Court
    arguments regarding the consequential damages claim, in Part III.
    We affirm on all counts, and in so doing reinforce the authority of a
    successor judge (here, Judge Harris) to make any decisions that
    could be made by a predecessor (Judge Kennedy).
    II. DISMISSAL OF THE ARCADIA CLAIM
    ¶20 Build challenges the dismissal of the Arcadia claim on two
    grounds. First it says that Judge Harris lacked the authority to
    reconsider a motion previously denied by Judge Kennedy, citing a
    so-called coordinate judge rule in our cases. And second, even
    assuming that Judge Harris had the authority to decide the issue,
    Build claims that he erred in granting summary judgment.4 We
    disagree on both counts and affirm.
    A. The “Coordinate Judge Rule”
    ¶21 A line of our cases refers to a set of limits on the authority of
    a successor judge to reconsider decisions of a predecessor. The first
    of these cases is Richardson v. Grand Central Corp., 
    572 P.2d 395
    (Utah
    1977). In Richardson we stated that “ordinarily one judge of the same
    court cannot properly overrule the decision of another judge of that
    court.” 
    Id. at 397.
    We connected this principle to the doctrine of the
    “law of the case.”5 
    Id. And we
    made reference to an exception to this
    _____________________________________________________________
    4 Build also makes a third argument. It says that UDOT’s motion
    for clarification may properly be viewed as a new motion for
    summary judgment. And it asserts that Judge Harris erred in
    granting the motion because the dispositive motion deadline had
    passed. We reject this argument, however, because we disagree with
    its premise. The motion, in substance, was not a new motion but a
    motion to reconsider. And although Judge Harris was not required
    to rule on such a motion, he had the discretion to do so. A.S. v. R.S.,
    
    2017 UT 77
    , ¶ 28, 
    416 P.3d 465
    (“[T]rial courts are under no
    obligation to consider motions for reconsideration and any decision
    to address or not to address the merits of such a motion is highly
    discretionary.” (citation omitted) (internal quotation marks
    omitted)). His decision on such a motion, moreover, obviates the
    need for us to decide whether it would be error for a court to rule on
    a new motion after the dispositive motion deadline has passed
    without an extension of the deadline.
    5 “Under the law of the case doctrine, a court [may] decline to
    revisit issues within the same case once the court has ruled on
    6
    Cite as: 
    2018 UT 34
                             Opinion of the Court
    general rule—to the notion that “the ruling of one judge as to the
    sufficiency or effect of pleadings, does not prevent another division
    of the court from considering the same question of law if it is
    properly involved on a subsequent motion which presents the case
    in a different light.” 
    Id. ¶22 We
    reinforced the premises of the Richardson case in our
    subsequent decision in Sittner v. Big Horn Tar Sands & Oil, Inc., 
    692 P.2d 735
    (Utah 1984). Sittner makes express reference to a set of rules
    governing a “coordinate judge.” 
    Id. at 736.
    It also reiterates the
    notion that a successor judge may overrule a previous judge’s
    decision where the issues are presented in a “different light”—a
    matter that Sittner refers to as one of “several exceptions” to the
    general rule. 
    Id. ¶23 The
    Sittner framework has been invoked in several of our
    subsequent cases.6 More recently, in Red Flame, Inc. v. Martinez, we
    recognized a new exception to the Sittner rule—an exception
    upholding a successor judge’s authority to revisit a previous judge’s
    decision where “it appears to the second judge that the first ruling
    was clearly erroneous and will infect the subsequent proceedings
    with error.” 
    2000 UT 22
    , ¶ 5, 
    996 P.2d 540
    (citation omitted).
    ¶24 Build challenges Judge Harris’s decision under this line of
    cases. Build says that Judge Kennedy’s decision denying UDOT’s
    motion for summary judgment motion was not “clearly erroneous”
    and insists that the matter was not presented to Judge Harris in a
    “different light.” And for these reasons Build claims that Judge
    Harris was foreclosed from revisiting Judge Kennedy’s earlier
    summary judgment decision—notwithstanding his determination
    that the Arcadia claim was destined for failure at trial.
    them.” McLaughlin v. Schenk, 
    2013 UT 20
    , ¶ 22, 
    299 P.3d 1139
    (alteration in original) (citation omitted) (internal quotation marks
    omitted).
    6  See, e.g., Mascaro v. Davis, 
    741 P.2d 938
    , 946–47 (Utah 1987)
    (reversing decision by successor judge reconsidering the decision of
    a predecessor); State v. Lamper, 
    779 P.2d 1125
    , 1129 (Utah 1989)
    (finding that a successor judge erred in not revisiting a ruling after a
    change in the law); AMS Salt Indus., Inc. v. Magnesium Corp. of Am.,
    
    942 P.2d 315
    , 319 (Utah 1997) (affirming a successor judge’s reversal
    of a prior judge because of the “additional evidence . . . adduced”
    (omission in original) (citations omitted)).
    7
    BUILD v. UDOT
    Opinion of the Court
    ¶25 We concede that the above cases yield a plausible basis for
    Build’s position. The cited cases admittedly can be read to establish a
    limitation on the authority of a successor judge to revisit decisions of
    a predecessor. But that view of these cases is at odds with a different
    line of authority in our law—a set of rules and cases that establishes
    that “any order or other decision, however designated, that
    adjudicates fewer than all the claims or the rights and liabilities of
    fewer than all the parties . . . may be changed at any time before the
    entry of judgment adjudicating all the claims and the rights and
    liabilities of all the parties.” UTAH R. CIV. P. 54(b); see also Macris v.
    Sculptured Software, Inc., 
    2001 UT 43
    , ¶¶ 29–30, 
    24 P.3d 984
    (holding
    that “the law of the case doctrine does not prevent a judge from
    reconsidering his or her previous nonfinal orders” and extending
    this principle to a successor judge, who is not treated as a different
    judge, “but rather as the same judicial officer reconsidering a prior
    ruling” (citations omitted)); Mid-Am. Pipeline Co. v. Four-Four, Inc.,
    
    2009 UT 43
    , ¶¶ 11, 14, 
    216 P.3d 352
    (explaining that the law of the
    case doctrine preserves a judge’s discretion to revisit a prior ruling
    and holding that this rule applies “regardless of whether the judge
    has changed or remained the same throughout the proceedings”);
    McLaughlin v. Schenk, 
    2013 UT 20
    , ¶¶ 22–24, 
    299 P.3d 1139
    (same).
    ¶26 Our “law of the case” precedent is thus in a state of internal
    conflict. On one hand we have purported to limit the authority of a
    successor judge to revisit the decisions of a predecessor. But on the
    other we have recognized the broad discretion of any judge (even a
    successor) to revisit prior rulings. These two lines of authority stand
    in inevitable conflict with each other. And the time has accordingly
    come for us to reconcile them.
    ¶27 We do so by adopting a limiting construction of the Sittner
    line of cases. On reflection, we view the principles stated in those
    cases as hortatory—expressing best-practice considerations for
    successor judges, and not limitations to be enforced by a reviewing
    court on appeal. Thus, we reinforce the broad discretion of any judge
    (whether initially assigned to the case or stepping in as a successor to
    another) to revisit any nonfinal decision entered previously. And we
    frame the considerations set forth in the Sittner line of cases as mere
    8
    Cite as: 
    2018 UT 34
                            Opinion of the Court
    factors that successor judges may wish to take into account in
    exercising their broad discretion in this area.7
    ¶28 We cannot take the Sittner line of cases at face value. To do
    so would introduce an operational inefficiency into our system.8 If a
    successor judge is convinced that a predecessor made an error in
    entering a nonfinal order, it makes no sense to require the successor
    judge to reinforce that order at all costs. The successor judge should
    retain the discretion to overturn the prior decision—whether or not it
    is presented in a “different light,” and whether or not it is “clearly
    erroneous.” At least sometimes it will make sense for the successor
    judge to step in and correct what he perceives as an error in an
    earlier order even when the case is presented in the same light, and
    even when the error is less than clear.
    ¶29 This case is a good example. The successor judge in this case
    became convinced that his predecessor had erred in denying
    UDOT’s motion for summary judgment. And if he was right in that
    assessment (a question we turn to below), it would make no sense to
    require him to let the case go to trial. Such a requirement—under a
    strict reading of the Sittner line of cases—would direct the successor
    judge to subject the parties to a trial that the judge knows to be
    pointless (because it would inevitably result in the entry of judgment
    as a matter of law9). That makes no sense as a practical matter. And
    _____________________________________________________________
    7 This formulation is consistent with a premise of our opinion in
    Red Flame, Inc. v. Martinez—that “[i]t is not that the second judge
    lacks power to revisit an earlier judge’s rulings,” but rather that
    “there are circumstances where that power should not be exercised.”
    
    2000 UT 22
    , ¶ 4, 
    996 P.2d 540
    (citation omitted).
    8 See Richardson v. Grand Cent. Corp., 
    572 P.2d 395
    , 397 (Utah 1977)
    (recognizing that the law of the case doctrine promotes judicial
    economy because it aids in “avoid[ing] the delays and the difficulties
    involved in repetitious contentions and rulings upon the same
    proposition in the same case”).
    9  See Salo v. Tyler, 
    2018 UT 7
    , ¶ 31, 
    417 P.3d 581
    (“The summary
    judgment standard anticipates—and mirrors—the directed verdict
    inquiry. If a defendant can show that the plaintiff has no legally
    sufficient evidentiary basis for its claims at trial, the defendant may
    establish the lack of a genuine issue of material fact and an
    entitlement to judgment as a matter of law.”).
    9
    BUILD v. UDOT
    Opinion of the Court
    presumably that is why our more recent cases yield to all judges the
    authority to revisit prior nonfinal decisions.
    ¶30 This is not to say that the decision to revisit a prior order
    should be made willy-nilly. We still see wisdom in the cautionary
    standards set forth in the Sittner line of cases. A successor judge
    should tread lightly before jumping to the conclusion that his
    perspective on the case is superior. He should measure twice before
    cutting down the decision of a predecessor. That is how we take the
    standards set forth in our Sittner cases. They articulate principles that
    the careful successor judge would be wise to account for. Before
    overruling a predecessor the successor judge should ask whether his
    perspective of the case is different from—or better than—that of the
    judge whose decision he is about to strike down. And he should
    pause before concluding that the prior judge’s ruling (and not his
    own) is clearly in error.10
    ¶31 That decision, however, is for the successor judge, not for a
    reviewing court on appeal. The successor judge, after all, is the court
    whose decision is being reviewed on appeal. He is the “same judicial
    officer” as the judge whose decision he overturned. Macris, 
    2001 UT 43
    , ¶ 30. The fiction on appeal, in other words, is that there is no such
    thing as a predecessor or successor—just the district court.
    ¶32 We reject Build’s threshold argument on this basis. We
    conclude that Judge Harris had the authority to overturn the
    decision of Judge Kennedy denying UDOT’s motion for summary
    judgment. And we reframe our case law in this field to clarify that
    the limitations on successor judges are hortatory considerations for
    trial judges, not enforceable standards to be applied on appeal.
    _____________________________________________________________
    10  Not every prior decision, moreover, is worth a probing second
    look. Some nonfinal decisions represent the exercise of classic
    judicial discretion. Others will have little effect on further
    proceedings in the case. Those sorts of decisions probably should be
    left alone, as any attempt to revisit them seems likely to introduce
    unnecessary delay and inefficiency in the disposition of the case. But
    the decision at issue here is different. It involved the denial of a
    dispositive motion for summary judgment. And the perception of
    error on that kind of decision could predictably cut the other way on
    delay and inefficiency, as noted above. See supra ¶¶ 28–29.
    10
    Cite as: 
    2018 UT 34
                             Opinion of the Court
    B. Merits of the Summary Dismissal of the Arcadia Claim
    ¶33 That leads us to the merits of Judge Harris’s decision on
    summary judgment. Build asserts that there was a dispute of
    material fact as to whether Build had waived its claim to
    compensation for its extra work under the terms of the parties’
    contract. And it asks us to reverse on that basis.
    ¶34 The issue on summary judgment is whether the UDOT
    engineer (Harrison) understood that he was ordering extra work. His
    understanding and intention control whether Part 1.5 or Part 1.6
    applies, which is the dispositive question in this case. If Harrison
    believed that he was ordering work that was outside the scope of the
    contract, then Part 1.6 of the contract applies. That provision requires
    UDOT to make the changes in writing. Because UDOT did not fulfill
    this requirement under Part 1.6, it would be liable if this provision
    applied. But if Harrison did not believe he was ordering extra work,
    Part 1.5 applies. That provision gives Build five days to give written
    notice of the “alleged change” to UDOT, or else it “waives[s] . . . any
    and all claims that may arise as a result of the alleged change.” Build
    did not give the required notice of the “alleged change” to UDOT
    within five days. So Build is left without recourse if Part 1.5 controls.
    ¶35 To escape Part 1.5, Build must show that Harrison
    “knowingly and deliberately” made changes to the contract or
    “believed” that the change “altered the contract.” Meadow Valley
    Contractors, Inc. v. State Dep’t of Transp., 
    2011 UT 35
    , ¶ 32, 
    266 P.3d 671
    , abrogated on other grounds by Mounteer Enters., Inc. v. Homeowners
    Ass'n for the Colony at White Pine Canyon, 
    2018 UT 23
    , __ P.3d __. This
    standard requires proof that Harrison subjectively believed that he
    was seeking a change that altered the contract. Yet Harrison testified
    to the contrary. He stated in a declaration submitted in response to
    Build’s motion for summary judgment that he “did not consider
    Build’s hauling of the extra material from the project site to the
    County dump to constitute change involving extra work as there
    was no change of contract plans or specification by actions they were
    undertaking.”
    ¶36 This statement, if unrebutted, is enough to sustain UDOT’s
    motion for summary judgment. Build seeks to overcome it by
    pointing to material in the record that in its view establishes a
    genuine issue of material fact about Harrison’s belief. But none of
    Build’s points is persuasive.
    ¶37 Build first cites to language in the contract—to a provision
    stating that “fill slopes may be flattened as shown on plans in order
    11
    BUILD v. UDOT
    Opinion of the Court
    to waste excess material,” and to another clause indicating how
    much excavated material would be disposed of at various locations
    within the project site. But these provisions don’t rebut Harrison’s
    testimony of his subjective belief. At most they go to the question
    whether Harrison’s belief was based on a reasonable interpretation
    of the contract. But again the question is not whether his belief was
    reasonable; just whether he in fact held that belief. And these pieces
    of evidence accordingly give no traction to Build’s case.
    ¶38 Build next points to testimony from Harrison. It notes that
    Harrison stated that “the contractor was allowed to dispose of
    excavated material in waste areas” within the project site. In Build’s
    view this means that Harrison understood offsite areas to be excluded
    by the contract. But we do not read this permissive statement as
    exclusive. And we reiterate, as with the contract provisions, that
    Build’s evidence does not contradict Harrison’s stated belief that no
    extra-contractual work was required.
    ¶39 Build also cites to Harrison’s statement that he instructed
    Build to haul the excess clay offsite based on an exercise of his
    “personal engineering judgment.” Here the implication is that
    Harrison’s “personal engineering judgment” stands in contrast to the
    contractual arrangement. We are not sure that that follows. But even
    if we accepted Build’s chain of inferences, we would revert back to
    the point that this evidence again does not contradict Harrison’s
    stated subjective belief.
    ¶40 The next arrow in Build’s quiver is a letter from Harrison to
    Build stating that a “changed condition is acknowledged as the basis
    of [Build’s] claim, in that . . . [excavated material] could no longer be
    effectively disposed of within the contract limits.” But there are two
    problems with this letter. First is the fact that this statement seems to
    be nothing more than an acknowledgment and restatement of
    Build’s position. Second, even if this were a concession, it would
    reflect UDOT’s and Harrison’s belief in 2008 when the letter was
    written. Again this does not contradict Harrison’s statement about
    his belief at the time these events occurred in 2006.
    ¶41 Build’s final move is to cite a change order from UDOT
    indicating that part of the project “is constructed on an unstable
    historic land slide” and detailing the “corrective action” taken to
    “improve      its   stability   per      Geotechnical     Engineers[’]
    recommendations.” Like the letter from Harrison, however, this
    change order came long after the fact, in 2007. Even if we read this as
    a flat concession by UDOT—which we do not—it doesn’t directly
    12
    Cite as: 
    2018 UT 34
                             Opinion of the Court
    contradict Harrison’s direct evidence of his subjective belief at the
    time the events occurred. Again, this evidence might be probative as
    to the reasonability of Harrison’s belief at the time. But that question
    is irrelevant. The issue is whether Harrison “knowingly and
    deliberately” made changes to the contract. And the change order
    does not go to that issue.
    ¶42 UDOT has proffered direct evidence of Harrison’s subjective
    belief at the time of the “alleged change,” including by Harrison’s
    own testimony. Nothing Build provides directly contradicts this
    evidence. Much of Build’s evidence goes to the reasonableness of
    Harrison’s belief; some of it at best reflects Harrison’s understanding
    long after the fact. It would not be reasonable for a jury to infer from
    this evidence that Harrison believed he was changing the contract.
    We affirm Judge Harris’s dismissal of the breach of contract claim on
    this basis.
    III. DISMISSAL OF THE CONSEQUENTIAL DAMAGES CLAIM
    ¶43 Build also appeals the district court’s decision to dismiss its
    claim for consequential damages. The court dismissed these claims
    as a natural result of its decision granting UDOT’s motion in limine.
    The decision on the motion in limine excluded Build’s two witnesses
    on consequential damages, Stromness and Whitacre. Without those
    witnesses, the district court determined that Build’s consequential
    damages claim was baseless. And it dismissed the claim on that
    basis.
    ¶44 Build challenges this decision on two fronts. It first says that
    the court erred in dismissing the consequential damages claim
    without the benefit of full briefing on a motion for summary
    judgment on the matter. Alternatively, Build challenges the district
    court’s decision on its merits—asserting that it presented sufficient
    evidence in support of its claim beyond the excluded testimony of
    Stromness and Whitacre.
    ¶45 Build’s first point may have merit. It may have been
    preferable for the district court to order briefing on the question
    whether the decision granting the motion in limine should lead to the
    summary dismissal of the consequential damages claim. No
    summary judgment motion was pending, after all. And a summary
    dismissal of a claim is a more substantial step than a mere decision
    to exclude testimony or evidence.
    ¶46 We need not reach the question whether this amounted to
    reversible error, however. The district court retained the discretion to
    extend the dispositive motion deadline and to order the parties to
    13
    BUILD v. UDOT
    Opinion of the Court
    brief a new motion for summary judgment on the consequential
    damages claim.11 And we conclude that any alleged error in the
    failure to do so was harmless.
    ¶47 The record shows quite clearly that Build could not have
    proven its consequential damages claim without the testimony of
    Stromness and Whitacre. Because Build never disclosed a calculation
    method or the amount of consequential damages it was claiming,
    moreover, any additional evidence it might have proffered likely
    could have been properly excluded under civil rule 26(d)(4). UTAH R.
    CIV. P. 26(d)(4) (“If a party fails to disclose or to supplement timely a
    disclosure or response to discovery, that party may not use the
    undisclosed witness, document or material at any hearing or trial
    unless the failure is harmless or the party shows good cause for the
    failure.”)); 
    id. 26(a)(1)(C) (“[A]
    party shall, without waiting for a
    discovery request, serve on the other parties . . . a computation of
    any damages claimed . . . .”). That renders any arguable error in the
    failure to order briefing on a motion for summary judgment
    harmless, as such a motion would surely have been granted on this
    record.
    ¶48 Build had a series of opportunities to present evidence in
    support of its consequential damages claim. It repeatedly failed to do
    so. This series of failures culminated in the decision granting the
    motion in limine. And that decision would inevitably have led to the
    dismissal of the consequential damages claim even if the propriety of
    such dismissal had been fully briefed on a motion for summary
    judgment.
    ¶49 Build’s first chance to proffer evidence to prove its amount
    of consequential damages came at the earlier summary judgment
    phase. At that stage the record is clear that Build identified only
    Whitacre’s and Stromness’s testimony in support of this claim. In
    UDOT’s original motion for summary judgment on the
    consequential damages claim, UDOT asserted that “Build ha[d]
    failed to provide any evidence as to the value of [its] business before
    and after UDOT’s alleged conduct.” It also alleged that “Build’s
    consequential damage/business devastation claim is based upon the
    opinions of Build’s expert, Joan Whitacre.” When so challenged,
    _____________________________________________________________
    11  See UTAH R. CIV. P. 56(b) (noting that a party may file
    a motion for summary judgment at any time no later than 28 days
    after the close of all discovery “[u]nless the court orders otherwise”).
    14
    Cite as: 
    2018 UT 34
                             Opinion of the Court
    Build did not directly contradict UDOT’s characterization. Instead,
    Build referred again to Whitacre’s testimony and adverted vaguely
    to generic evidence in the record—such as evidence of “25 years [of]
    Build’s financial records.” It thus asserted that it had “placed into the
    record . . . relevant admissible information from which the jury may
    determine fair market value before and after UDOT’s wrongful
    conduct.” Yet Build’s only apparent witness on the matter was
    Stromness, and Stromness was excluded by the decision granting the
    motion in limine.
    ¶50 Build had another chance to alert the court to additional
    evidence in response to UDOT’s motion in limine. Here UDOT
    argued that Build’s consequential damages claim was based on
    Whitacre’s testimony. Build responded that UDOT’s characterization
    was “incomplete” because its claim was also “based on the facts
    considered by Ms. Whitacre[,] . . . evidence of Build’s financial
    condition provided in this case[,] . . . and the opinions of Fred
    Stromness.” Again, Build did not point to any witnesses outside of
    those that the court excluded.
    ¶51 Build’s last chance to proffer additional evidence was at the
    hearing on the motion in limine. There, the following exchange took
    place:
    The Court: [I]t seems to me you have [not given a basis for the
    computation], by preventing Mr. Stromness, who will be your
    witness on this; right? You don’t have another.
    Mr. Fetzer [counsel for Build]: We have Ms. Whitacre on the
    causation and the—the fact and causation of the damages, we
    have—
    The Court: Okay. And they’re not challenging that, they’re not
    challenging Ms. Whitacre being able to get put on the stand
    and testify as to causation about business devastation. Who’s
    your guy?
    Mr. Fetzer: Mr. Stromness.
    The Court: For the number. Okay.
    Mr. Fetzer: Mr. Stromness.
    Here again Build failed to identify a witness outside of Stromness or
    Whitacre. Later at that hearing, Judge Harris suggested that he was
    considering the option of “kick[ing Build’s] whole claim for a failure
    to disclose.” He added, “if you think I’m seeing that inappropriately
    or incorrectly, I’d like to hear from you and like to know what else
    you think I can do about it.” But Build doubled down on Stromness
    15
    BUILD v. UDOT
    Opinion of the Court
    as its witness. If Build had another witness to rely on for this claim, it
    did not give so much as a hint to that effect on the record.
    ¶52 With the above in mind, we find no reversible error in the
    district court’s decision to dismiss the consequential damages claim.
    Full briefing on the question may have been a best practice. But we
    find any arguable error in the decision not to order such briefing to
    be harmless. The record clearly shows that Build relied only on
    Stromness and Whitacre to support its consequential damages claim
    at every step of the litigation. And for that reason we think it
    inevitable that the district court would have dismissed the claim
    even if it had ordered full briefing on a motion for summary
    judgment.
    ¶53 Build suggests that it conceivably could have identified
    alternative theories of consequential damages. It alludes to the
    notion of attorney fees as consequential damages in its brief. And it
    referred to other possible theories at oral argument—including the
    notion that the district court’s failure to order briefing somehow
    prevented it from developing a record of the basis for its
    consequential damages claim in the district court. But these
    arguments likewise fail. The record developed above shows that
    Build had ample opportunity to present another theory of
    consequential damages. And in any event it seems clear that any
    new theory would have been excluded as not having been
    previously disclosed under Utah Rule of Civil Procedure 26.
    ¶54 At the hearing on the motion in limine the district court had
    the opportunity to allow Build to supplement its disclosures, re-open
    discovery, and push the trial back to allow Build to introduce new
    evidence or theories in support of its claim for consequential
    damages. But the court declined to do so. In UDOT’s words (at the
    hearing), the court “disallow[ed] them from going back to start
    over,” forcing them to “live with what they’ve got and have given us
    so far.” That decision was understandable—certainly within the
    court’s ample discretion. And it led to the inevitable decision to
    dismiss the consequential damages claim for lack of supporting
    evidence in the record.
    ¶55 We affirm on this basis. We find no reversible error in the
    dismissal of the consequential damages claim because Build never
    disclosed an amount of consequential damages or a basis for
    calculating it. When the only two witnesses who might have testified
    to any such amount were excluded, the claim was left without a leg
    to stand on. And no alternative theory could have rescued that claim
    16
    Cite as: 
    2018 UT 34
                            Opinion of the Court
    because any such theory also would have been infected by Build’s
    failure to disclose.
    IV. CONCLUSION
    ¶56 We affirm the dismissal of Build’s Arcadia claim despite the
    limitations stated in our Sittner line of cases. We reframe those
    limitations as hortatory factors for successor judges to consider. And
    we reinforce the discretion of a successor or coordinate judge to
    reconsider a predecessor judge’s nonfinal rulings. We also affirm the
    dismissal of both the Arcadia claim and the consequential damages
    claim on their merits, deeming any arguable error in the dismissal of
    the latter claim harmless.
    17