Jordan Const v. Fed Nat Mort , 2017 UT 28 ( 2017 )


Menu:
  •                  This opinion is subject to revision before final
    publication in the Pacific Reporter
    
    2017 UT 28
    IN THE
    SUPREME COURT OF THE STATE OF UTAH
    JORDAN CONSTRUCTION, INC.,
    Appellant,
    v.
    FEDERAL NATIONAL MORTGAGE ASSOCIATION,
    Appellee.
    No. 20160474
    Filed May 22, 2017
    On Direct Appeal
    Fourth District, American Fork
    The Honorable Christine S. Johnson
    No. 080104364
    Attorneys:
    Darrel J. Bostwick, Jeffery J. Owens, Salt Lake City, for appellant
    Alexander Dushku, Peter C. Schofield, Justin W. Starr,
    Adam D. Wahlquist, Salt Lake City, for appellees
    CHIEF JUSTICE DURRANT authored the opinion of the Court, in which
    ASSOCIATE CHIEF JUSTICE LEE, JUSTICE DURHAM, JUSTICE HIMONAS, and
    JUSTICE PEARCE joined.
    CHIEF JUSTICE DURRANT, opinion of the Court:
    Introduction
    ¶ 1 This case concerns a general contractor’s attempt to recover
    on a mechanic’s lien. Scott Bell, an employee of Jordan Construction,
    Inc., hired Jordan Construction as the general contractor to build a
    new home on property that he owned (the Property). Several months
    after the start of construction, Mr. Bell secured long-term financing
    and executed a trust deed on the Property. Mr. Bell then failed to pay
    Jordan Construction the full amount due for its work. When the
    home was nearly finished, Jordan Construction discovered that Mr.
    JORDAN CONSTR. v. FNMA
    Opinion of the Court
    Bell had been misusing company funds and terminated him. Mr. Bell
    responded by suing Jordan Construction. Jordan Construction in
    turn recorded a mechanic’s lien and lis pendens on the Property and
    counterclaimed for breach of contract, embezzlement, and
    foreclosure of the mechanic’s lien. Jordan Construction chose not to
    name the holder of the trust deed at that time.
    ¶ 2 While the suit was pending, Jordan Construction discovered
    that some subcontractors had not been paid for their work on the
    Property. Nearly nine months after the completion of construction,
    Jordan Construction filed an amendment to its notice of mechanic’s
    lien to include the additional amounts owed to the subcontractors.
    Jordan Construction then obtained summary judgment on its
    counterclaims against Mr. Bell, applied for a writ of execution, and
    took steps to initiate a sheriff’s sale of the Property.
    ¶ 3 Meanwhile, Mr. Bell had defaulted on his mortgage. The
    trust deed holder conducted a non-judicial foreclosure sale, and
    Federal National Mortgage Association (FNMA)1 purchased the
    trustee’s deed. FNMA then filed a motion asking the district court to
    quash the writ of execution and halt the sheriff’s sale because neither
    it, nor its predecessor in interest, had been named in this action.
    Over Jordan Construction’s objection, the district court quashed the
    writ and halted the sale. Jordan Construction then filed a third-party
    complaint against FNMA, asserting that its mechanic’s lien had
    priority over FNMA’s trustee’s deed.
    ¶ 4 Having been brought in as a party to this action, FNMA
    then prevailed on a series of motions before the district court. Jordan
    Construction asserts on appeal that the district court erred in those
    decisions. First, the district court concluded that FNMA is not bound
    by the judgment rendered against Mr. Bell earlier in the case under
    either the lis pendens or the doctrine of res judicata. Second, the court
    ruled that Jordan Construction’s amended notice of lien—which
    nearly doubled the amount claimed—was untimely. Third, it ruled
    that, under the 2008 Utah Code, Jordan Construction was not
    entitled to recover prejudgment interest on its mechanic’s lien claim.
    In all, FNMA, by obtaining these rulings, whittled down the amount
    that Jordan Construction had sought in its third-party complaint—
    $336,568.66—to $126,956.92, the amount listed on the face of the
    _____________________________________________________________
    1  At some point during the proceedings below, Bank of American
    Fork was substituted for FNMA. We refer to FNMA for convenience,
    as the parties have done in their briefs.
    2
    Cite as: 
    2017 UT 28
    Opinion of the Court
    original lien. FNMA then stipulated to the payment of $126,956.92.
    The district court concluded that FNMA was the successful party
    and awarded it attorney fees under the mechanic’s lien statute, a
    decision which Jordan Construction also challenges on appeal.
    ¶ 5 We affirm the district court’s ruling as to each issue.
    Background
    ¶ 6 This case evolved in two phases. We first discuss the
    procedural facts involved in the first phase, where Jordan
    Construction asserted and prevailed on its counterclaims against Mr.
    Bell. We then discuss the second phase, where FNMA was brought
    into this action as a third-party defendant.
    ¶ 7 In 2006, Jordan Construction was hired by its employee, Mr.
    Bell, to be the general contractor on the construction of his new
    home. Construction on the home began in October 2006. Mr. Bell
    obtained long-term financing on January 31, 2008, executing a trust
    deed that encumbered the Property with the trustee’s right to sell the
    property in case of default.
    ¶ 8 Near the end of construction, in October 2008, Jordan
    Construction discovered that Mr. Bell had been embezzling from the
    company and terminated his employment. The next month, Mr. Bell
    and his brother, Todd Bell, brought suit against Jordan Construction
    alleging, among other things, breach of contract. In December 2008,
    Jordan Construction recorded a Notice of Mechanic’s Lien in the
    amount of $126,956.92 for its work on Mr. Bell’s home.2 It then
    counter-claimed for breach of contract, unjust enrichment,
    promissory estoppel, conversion, and foreclosure of its mechanic’s
    lien, simultaneously recording a lis pendens on the Property. It did
    not, however, name the holder of the trust deed as a party to the
    action.
    ¶ 9 In the months after the suit was filed, Jordan Construction
    continued to investigate Mr. Bell’s activities, discovering that he
    “kept few receipts and records demonstrating how many of the
    subcontractors were paid.” Jordan Construction’s principal, Wesley
    Lewis, had to perform a detailed accounting to determine how much
    Jordan Construction owed to subcontractors for work done on the
    Property, a task that was complicated by Mr. Bell’s failure to keep
    accurate records. This accounting revealed a total of $232,976.81. In
    _____________________________________________________________
    2This notice was amended shortly after it was filed to correct a
    minor procedural error not relevant here.
    3
    JORDAN CONSTR. v. FNMA
    Opinion of the Court
    July 2009, Jordan Construction amended its notice of mechanic’s lien
    to reflect its newly calculated amount.
    ¶ 10 Several months after the amendment, in January 2010,
    Jordan Construction moved for partial summary judgment on all of
    its claims against Mr. Bell. Mr. Bell did not oppose the motion, and
    the court granted it in February 2010. Although Jordan Construction
    had requested summary judgment on the mechanic’s lien claim in its
    motion, the court’s February 2010 order did not mention that claim,
    an oversight the court did not correct until nearly eighteen months
    later.
    ¶ 11 In June 2010, the court entered an order containing its
    findings of fact and conclusions of law regarding Jordan
    Construction’s counterclaims against Mr. Bell, but this order again
    made no mention of the mechanic’s lien claim. Additionally, Jordan
    Construction still had not joined the holder of the trust deed to this
    action. Two months later, Jordan Construction sought permission
    from the district court to file a third-party complaint against the trust
    deed holder, but it did not serve that complaint.
    ¶ 12 Meanwhile, Mr. Bell had defaulted on the promissory note
    that was secured by the trust deed on the Property. FNMA
    purchased the trustee’s deed at a non-judicial foreclosure sale on
    October 1, 2010. Jordan Construction later applied for a writ of
    execution in January 2011. As part of the application for this writ,
    Jordan Construction served on FNMA a “Checklist for Writ of
    Execution for Judgment Debtor and Persons with an Interest in the
    Property,” “Notice of Execution and Exemptions,” and a “Reply and
    Request for Hearing form.” FNMA did not file a reply or request a
    hearing.
    ¶ 13 Jordan Construction did not immediately act on the writ,
    but instead moved in June 2011 to amend the court’s order granting
    partial summary judgment against Mr. Bell to include the mechanic’s
    lien foreclosure claim. The court, recognizing that its original order
    should have included the mechanic’s lien claim, granted the motion
    in July 2011 and modified its findings of fact and conclusions of law
    in August 2011 to include that claim. Jordan Construction then
    requested that the Utah County Sheriff notice a proposed foreclosure
    sale of the Property, which was set for September 14, 2011.
    ¶ 14 FNMA then took its first action in this proceeding—it filed a
    motion to quash the writ and halt the sale. The court granted this
    request, and Jordan Construction then sought and was granted
    permission to file a third-party complaint against FNMA. This
    complaint against FNMA, the beginning of the second phase of this
    4
    Cite as: 
    2017 UT 28
    Opinion of the Court
    case, contained only a single claim for declaratory relief. That claim
    sought a declaration that FNMA was bound by the findings of fact
    and conclusions of law entered against Mr. Bell earlier in the case.
    The district court granted FNMA’s motion to dismiss the complaint
    because it concluded FNMA was not bound by its earlier ruling.
    Jordan Construction then amended its complaint, this time asserting
    the same declaratory relief claim and a mechanic’s lien claim against
    FNMA. The district court again dismissed the declaratory relief
    claim, but it allowed the mechanic’s lien claim to go forward.
    ¶ 15 After fact discovery, FNMA filed a number of motions for
    partial summary judgment. We discuss these motions, and the
    district court’s rulings on them, in some detail because Jordan
    Construction challenges the district court’s resolution of these
    motions on this appeal, and also because they are relevant for
    determining which party was “successful” in this action for attorney
    fee purposes.
    ¶ 16 FNMA first sought a ruling that it was not liable for attorney
    fees incurred in connection with the judgment rendered against Mr.
    Bell. Second, it argued that it was not bound by the judgment
    rendered against Mr. Bell earlier in the action. Third, it contended
    that Jordan Construction’s second amended notice of lien, filed in
    July 2009 to add the amounts it paid to subcontractors, was untimely
    because it was filed more than 180 days after the certificate of
    occupancy was issued in October 2008. Finally, it sought a ruling
    that Jordan Construction was not entitled to prejudgment interest on
    its mechanic’s lien claim brought under the 2008 Utah Code. Jordan
    Construction filed its own motion for summary judgment, arguing
    that FNMA was bound by the rulings entered against Mr. Bell and
    that its lien had priority over FNMA’s interest.
    ¶ 17 The district court denied Jordan Construction’s motion
    seeking a declaration that FNMA was bound by rulings entered
    against Mr. Bell, and it granted all of FNMA’s motions except the
    one regarding the timeliness of the lien amendment. The court
    denied summary judgment on the timeliness of the lien because
    Jordan Construction had raised a new argument at oral argument—
    that a newly discovered certificate of occupancy was issued in June
    2011. This newly discovered certificate contradicted an admission
    that Jordan Construction had made earlier in the litigation, which
    stated
    Request No. 2: Admit that Scott Bell began occupying
    the Property in October 2007.
    5
    JORDAN CONSTR. v. FNMA
    Opinion of the Court
    Response: Admit that Scott Bell occupied the property
    pursuant to a temporary occupancy permit beginning
    in October 2007. However, construction on his home
    was not yet finished, no final inspection had been
    completed and no permanent occupancy permit had
    been issued until October 2008.
    ¶ 18 Based on this newly discovered certificate, Jordan
    Construction brought a motion for partial summary judgment
    arguing that the timeliness of the lien should be decided based on
    the certificate issued in 2011. FNMA filed its own motion arguing
    that summary judgment should be granted on the basis of Jordan
    Construction’s admission that a certificate of occupancy was issued
    in October 2008. Jordan Construction then moved to withdraw the
    admission. The court denied Jordan Construction’s motions to
    withdraw the admission and for summary judgment, and granted
    FNMA’s motion, ruling that the second amendment to the lien was
    untimely.
    ¶ 19 The court also denied Jordan Construction’s motion for
    summary judgment regarding the validity and priority of the
    original lien, because it found that there were genuine issues of
    material fact as to whether Jordan Construction materially
    abandoned construction for a time, which would sever the relation
    back of its lien. Rather than go through the expense of a trial on the
    priority issue, FNMA stipulated to the entry of judgment in the
    amount of the original mechanic’s lien, $126,956.92.
    ¶ 20 FNMA then sought its attorney fees as the “successful”
    party in an action to enforce a mechanic’s lien.3 Jordan Construction
    also argued that it was the “successful” party and requested its
    attorney fees. The district court concluded that FNMA was the
    successful party because it prevailed on virtually every disputed
    issue and successfully reduced Jordan Construction’s recovery to
    approximately 38% of the amount it originally sought in the third-
    party complaint.
    ¶ 21 Jordan Construction now appeals. It asserts that the district
    court erred in 1) quashing the writ of execution and halting the
    sheriff’s sale; 2) concluding that FNMA is not bound by the partial
    _____________________________________________________________
    3   Under Utah Code section 38-1-18(1) (2008), the “successful
    party” in an action to enforce a mechanic’s lien “shall be entitled to
    recover a reasonable attorneys’ fee, to be fixed by the court, which
    shall be taxed as costs in the action.”
    6
    Cite as: 
    2017 UT 28
    Opinion of the Court
    summary judgment rendered against Mr. Bell in the first phase of
    this case; 3) concluding that Jordan Construction’s second amended
    notice of lien was untimely; 4) concluding that prejudgment interest
    is not available on a mechanic’s lien claim under the 2008 Utah Code;
    and 5) concluding that FNMA was the “successful” party below. We
    have jurisdiction under Utah Code section 78A-3-102(3)(j).
    Issues and Standards of Review
    ¶ 22 This case presents five issues for our review. The first issue
    is whether the district court erred in quashing the writ of execution
    and halting the sheriff’s sale. We review a district court’s decision to
    reconsider an earlier decision for an abuse of discretion.4
    ¶ 23 The second issue is whether the district court erred in
    concluding that neither the lis pendens nor the doctrine of res judicata
    require that FNMA be bound by the partial summary judgment
    entered against Mr. Bell. This issue presents a question of law, which
    we review for correctness.5
    ¶ 24 The third issue is whether the district court erred in
    concluding that Jordan Construction’s second amended notice of
    mechanic’s lien was untimely. “An appellate court reviews a trial
    court’s ‘legal conclusions and ultimate grant or denial of summary
    judgment’ for correctness, and views ‘the facts and all reasonable
    inferences drawn therefrom in the light most favorable to the
    nonmoving party.’”6
    ¶ 25 One component of the third issue is whether the district
    court erred in refusing to permit Jordan Construction to withdraw its
    admission that a certificate of occupancy was issued for the Property
    in October 2008. The standard of review for amendment or
    withdrawal of admissions is a two-step, “‘conditional’ discretionary
    standard.”7 Rule 36(c) of the Utah Rules of Civil Procedure provides
    that a district court “may permit withdrawal or amendment” if two
    requirements are met: 1) “presentation of the merits of the action will
    _____________________________________________________________
    4 IHC Health Servs., Inc. v. D & K Mgmt., Inc., 
    2008 UT 73
    , ¶ 27, 
    196 P.3d 588
    .
    5 Press Publ’g, Ltd. v. Matol Botanical Int’l, Ltd., 
    2001 UT 106
    , ¶ 19,
    
    37 P.3d 1121
    .
    6   Orvis v. Johnson, 
    2008 UT 2
    , ¶ 6, 
    177 P.3d 600
     (citations omitted).
    7 Langeland v. Monarch Motors, Inc., 
    952 P.2d 1058
    , 1060 (Utah
    1998).
    7
    JORDAN CONSTR. v. FNMA
    Opinion of the Court
    be promoted,” and 2) “withdrawal or amendment will not
    prejudice” the party who requested the admission. We review the
    question of whether these two threshold requirements have been
    satisfied under “a somewhat more exacting standard of review” than
    simple abuse of discretion.8 If the threshold requirements are met,
    we then review the court’s decision to grant the motion to withdraw
    or amend and will “reverse[] only upon a finding of abuse of
    discretion, i.e., if there is no reasonable basis for the decision.”9
    ¶ 26 The fourth issue is whether the district court erred in
    concluding that prejudgment interest is unavailable under the 2008
    version of the mechanic’s lien statute. “A trial court’s decision to
    grant or deny prejudgment interest presents a question of law which
    we review for correctness.”10
    ¶ 27 The fifth issue is whether the district court erred in
    concluding that FNMA was the “successful” party in this action for
    attorney fee purposes. We review the district court’s determination
    of who is successful in these circumstances for an abuse of
    discretion.11
    Analysis
    ¶ 28 The first question we must address is whether the district
    court erred in quashing the writ of execution and halting the sheriff’s
    sale. Jordan Construction argues that FNMA waived its right to
    challenge the writ of execution by failing to file a request for hearing
    as provided in Utah Rule of Civil Procedure 64E. We reject this
    argument because the district court had discretion, under Utah Rule
    of Civil Procedure 54(b) and the law of the case doctrine, to revisit its
    earlier decision to issue the writ of execution. FNMA’s decision not
    to file a request for hearing on the issuance of the writ did not
    deprive the district court of that discretion. The district court
    therefore did not abuse its discretion in quashing the writ and
    halting the sale.
    ¶ 29 We next explain that FNMA is not bound by the order
    entered against Mr. Bell under either the doctrine of res judicata or
    _____________________________________________________________
    8   Id. at 1061.
    9   Id.
    10   Smith v. Fairfax Realty, Inc., 
    2003 UT 41
    , ¶ 16, 
    82 P.3d 1064
    (citation omitted).
    11   R.T. Nielson Co. v. Cook, 
    2002 UT 11
    , ¶ 25, 
    40 P.3d 1119
    .
    8
    Cite as: 
    2017 UT 28
    Opinion of the Court
    the lis pendens. Jordan Construction argues that FNMA, which had
    notice of—but chose not to intervene in—the litigation against Mr.
    Bell, is bound by the interlocutory order granting partial summary
    judgment entered against him. This argument is based on Jordan
    Construction’s assertion that FNMA is Mr. Bell’s successor-in-
    interest to the Property because FNMA purchased the Property that
    Mr. Bell previously owned. In Jordan Construction’s view, FNMA
    and Mr. Bell are in privity, and, as a result, FNMA took the property
    subject to the existing judgment that had been entered against Mr.
    Bell. But even assuming that FNMA was Mr. Bell’s successor, which
    FNMA disputes, neither res judicata nor the recording of the lis
    pendens requires that FNMA be bound by the ruling entered against
    Mr. Bell, because that order was interlocutory. Under our precedent
    regarding the “law of the case” doctrine, a district court has broad
    discretion to revisit earlier rulings before a case has proceeded to a
    final judgment. The district court thus properly concluded that
    FNMA is not bound by the order granting partial summary
    judgment against Mr. Bell.
    ¶ 30 We then turn to Jordan Construction’s second amended
    notice of lien, and we affirm the district court’s judgment that the
    notice was untimely. In reaching this conclusion, we reject Jordan
    Construction’s three arguments on this point. First, Jordan
    Construction argues that the district court erred in denying its
    request to withdraw its admission that a certificate of occupancy was
    issued in October 2008. We conclude that the district court had
    discretion to deny this request because FNMA would have been
    prejudiced by the long delay between the admission and the request
    to withdraw. Second, Jordan Construction argues that the doctrine of
    equitable tolling should be applied to toll the time for filing an
    amended notice of lien. We reject this argument as unpreserved.
    Finally, Jordan Construction argues that the relation back doctrine
    should apply to its second amended notice of lien, such that the
    amended notice should be treated as though filed on the date of its
    original notice of lien. We reject this argument because the
    legislature, through the mechanic’s lien statute, has crafted a careful
    scheme that balances multiple interests, and for us to apply the
    relation back doctrine where the legislature has not provided for it
    would frustrate that scheme.
    ¶ 31 We then turn to the question of whether prejudgment
    interest is available on a mechanic’s lien claim under the 2008
    version of the Utah Code, which did not specifically provide for
    prejudgment interest. We affirm the district court’s conclusion that
    prejudgment interest is unavailable. Because mechanic’s liens are
    9
    JORDAN CONSTR. v. FNMA
    Opinion of the Court
    creatures of statute, we have held that the value of items the
    legislature did not provide in those statutes cannot be claimed on the
    face of a mechanic’s lien. As a logical extension of that conclusion,
    the overall recovery available in a mechanic’s lien action, like the
    amount claimable in a notice of lien, is limited to the items expressly
    provided by the statute. We thus presume the legislature’s omission
    of prejudgment interest was intentional and conclude that it is not
    available in a mechanic’s lien action under the 2008 Utah Code.
    ¶ 32 Finally, we assess whether the district court abused its
    discretion in concluding that FNMA was the successful party for
    attorney fee purposes. We find no abuse of discretion because Jordan
    Construction sought an amount almost three times greater than what
    it ultimately recovered, and FNMA prevailed on virtually every
    motion throughout this litigation. We agree with the district court
    that it would be contrary to common sense to conclude that Jordan
    Construction was “successful” given these circumstances. The
    district court thus did not abuse its discretion. We address each issue
    in turn.
    I. The District Court Did Not Err in Quashing the Writ of Execution
    and Halting the Sheriff’s Sale
    ¶ 33 Jordan Construction argues that the district court erred in
    quashing the writ of execution. The Utah Rules of Civil Procedure
    provide the process for obtaining and challenging writs. Under rule
    64(e)(1), “[a]ny person claiming an interest in the property [that is
    the subject of a writ] has the same rights and obligations as the
    [party against whom judgment has been entered] with respect to the
    writ.” If a person claiming an interest in the property is “named by
    the plaintiff and served with the writ and accompanying papers,”
    then that person “shall exercise those rights and obligations within
    the same time allowed” the party against whom judgment has been
    entered.12 For writs of execution, one such right is the right to “reply
    to [a] writ and request a hearing,” which “shall be filed and served
    within 14 days after service of the writ and accompanying papers.”13
    Reading these two rules together, a person claiming an interest in
    property that is the subject of a writ of execution who wishes to
    exercise the right to reply and request a hearing on the writ must file
    and serve such a reply and request for hearing “within 14 days after”
    being served with “the writ and accompanying papers.”
    _____________________________________________________________
    12   UTAH R. CIV. P. 64(e)(1).
    13   UTAH R. CIV. P. 64E(d)(1).
    10
    Cite as: 
    2017 UT 28
    Opinion of the Court
    ¶ 34 Jordan Construction argues that FNMA, as a “person
    claiming an interest” in the Property, had an obligation to “exercise
    [its] rights . . . within the same time allowed” Mr. Bell, the party
    against whom judgment had been entered in the first phase of this
    case. Jordan Construction asserts that, under these procedural rules,
    FNMA had only 14 days from the date it was served with the writ
    during which it could object to the writ. The parties do not dispute
    that FNMA did not file or serve a reply or request for hearing within
    that time. Jordan Construction argues that this “fail[ure] to follow
    procedural rules” deprived the district court of “discretion” to revisit
    its earlier decision to issue the writ.
    ¶ 35 We disagree. As an initial matter, Jordan Construction has
    cited no authority that a district court lacks discretion to quash a writ
    of execution where an interested person challenges that writ more
    than 14 days after receiving it. To the contrary, the general rule is
    that a district court has discretion to revisit any prior decision in a
    case before the entry of a final judgment.14 But in any event, we need
    not decide the waiver question here because we conclude the district
    court in this case had discretion to revisit this writ because it was
    procedurally deficient. Rule 64E(a) provides that “[a] writ of
    execution is available to seize property in the possession or under
    the control of the defendant following entry of a final judgment or order
    requiring the delivery of property or the payment of money.”15 The
    writ in this case was issued in January 2011, before final judgment
    had been entered. At that point in the litigation, as Jordan
    Construction concedes, Mr. Bell’s claims, as well as his brother’s
    claims, against Jordan Construction remained pending, and none of
    _____________________________________________________________
    14 UTAH R. CIV. P. 54(b) (“[A]ny order or other decision, however
    designated, that adjudicates fewer than all the claims or the rights
    and liabilities of fewer than all the parties does not end the action as
    to any of the claims or parties, and may be changed at any time
    before the entry of judgment adjudicating all the claims and the
    rights and liabilities of all the parties.” (emphasis added)); IHC
    Health Servs., Inc. v. D & K Mgmt., Inc., 
    2008 UT 73
    , ¶ 27, 
    196 P.3d 588
    (“While a case remains pending before the district court prior to any
    appeal, the parties are bound by the court’s prior decision, but the
    court remains free to reconsider that decision.”).
    15   UTAH R. CIV. P. 64E(a) (emphasis added).
    11
    JORDAN CONSTR. v. FNMA
    Opinion of the Court
    Jordan Construction’s counterclaims had been certified as final
    under Utah Rule of Civil Procedure 54(b).16
    ¶ 36 So even in the absence of FNMA’s request, the district court
    would have been within its discretion to quash the writ because the
    writ never should have been issued. Because there had not been a
    “final judgment,” a writ of execution was not available under these
    circumstances, and the district court could have revisited its decision
    to grant the writ for that reason alone.17 The fact that FNMA called
    the court’s attention to other reasons for quashing the writ does not
    deprive the district court of authority to revisit a decision that it
    would otherwise have discretion to reconsider. We therefore reject
    Jordan Construction’s argument and hold that the district court did
    not abuse its discretion in quashing the writ and halting the sheriff’s
    sale.
    II. The District Court Correctly Concluded that FNMA Is Not
    Bound by the Interlocutory Order Entered Against Mr. Bell by
    Either the Recording of the Lis Pendens or the Doctrine of Res Judicata
    ¶ 37 Jordan Construction argues that because FNMA purchased
    the Property that Mr. Bell previously owned, FNMA is Mr. Bell’s
    successor-in-interest, and FNMA should therefore be bound by the
    judgment entered against Mr. Bell in the early stages of this case. It
    makes two arguments in support of this claim. First, it argues that
    the lis pendens recorded at the outset of this suit put FNMA on notice
    that it was buying the Property subject to the outcome of the
    litigation, and second, that the doctrine of res judicata prevents
    FNMA from re-litigating the order entered against Mr. Bell. We
    reject both arguments because the case had not proceeded to a final
    _____________________________________________________________
    16  See UTAH R. CIV. P. 54(b) (“When an action presents more than
    one claim for relief—whether as a claim, counterclaim, cross claim,
    or third party claim—and/or when multiple parties are involved,
    the court may enter judgment as to one or more but fewer than all of
    the claims or parties only if the court expressly determines that there
    is no just reason for delay.”).
    17  FNMA also argues that it had no obligation to file a request for
    hearing because, at the time of the application for writ of execution,
    the underlying order that supported the application for writ did not
    mention the mechanic’s lien claim. We do not reach this question
    because we conclude the district court had the discretion to revisit its
    earlier ruling based on the procedural deficiency of the writ.
    12
    Cite as: 
    2017 UT 28
    Opinion of the Court
    judgment when FNMA requested the district court to revisit its
    earlier rulings.18
    A. The Recording of the Lis Pendens Does Not Require that FNMA Be
    Bound by the Interlocutory Order Entered Against Mr. Bell
    ¶ 38 The parties agree on the general legal effect that follows the
    recording of a lis pendens. “The recording of a lis pendens provides
    constructive notice to all persons that the rights and interests in the
    property at issue are controverted. One who purchases property
    subject to a lis pendens acquires only the grantor’s interest therein,
    as determined by the outcome of the litigation.”19 But the parties
    here dispute what the “outcome of the litigation” means. In FNMA’s
    view, it means a final judgment on the merits.20 In Jordan
    Construction’s view, it means “the judgment against [Mr.] Bell
    insofar as it applies to the property in question.” Jordan
    Construction’s argument is that FNMA was required to intervene in
    the litigation before the district court entered its order against Mr.
    Bell, and because it did not, it is bound by that “outcome.” We agree
    with FNMA.
    ¶ 39 Jordan Construction provides no explanation for why the
    “outcome of the litigation” should include an interlocutory order.
    That is, it provides no reasoning for why FNMA was required to
    intervene in the litigation before the judgment against Mr. Bell was
    _____________________________________________________________
    18  As noted below, FNMA disputes the notion that it is Mr. Bell’s
    successor-in-interest. See infra ¶ 38 n.20, ¶ 42 n.24. We do not address
    these alternative arguments because, even assuming FNMA is Mr.
    Bell’s successor-in-interest, the district court did not err in
    concluding that FNMA was not bound by the earlier order entered
    against Mr. Bell.
    19   Timm v. Dewsnup, 
    921 P.2d 1381
    , 1392 (Utah 1996).
    20  FNMA also makes a second argument: that a lis pendens affects
    only a property interest that is “the subject of pending litigation,”
    and that only Mr. Bell’s interest—and not the trust deed holder’s
    interest—was the “subject of the litigation” because Jordan
    Construction did not name the trust deed holder in its mechanic’s
    lien foreclosure action. See Bagnall v. Suburbia Land Co., 
    579 P.2d 914
    ,
    916 (Utah 1978). We do not reach this question, because we conclude
    that, in any event, FNMA is bound only by the outcome of the
    litigation.
    13
    JORDAN CONSTR. v. FNMA
    Opinion of the Court
    entered. We conclude that one who purchases property subject to a
    lis pendens is bound only by a final judgment rendered against the
    seller, but if the purchaser acquires the property while the litigation
    remains pending, we see no reason why that purchaser should not
    be entitled to ask the court to revisit its earlier interlocutory rulings
    against its predecessor in interest.
    ¶ 40 Having decided that a lis pendens binds purchasers only to a
    final judgment, and not to interlocutory rulings, the question then is
    whether the judgment rendered against Mr. Bell was final. As noted
    above, it was not. Mr. Bell’s and his brother’s claims against Jordan
    Construction had not yet been resolved. And there was no 54(b)
    certification of Jordan Construction’s counterclaims against Mr.
    Bell.21 In the absence of a final judgment, the district court did not
    abuse its discretion in granting FNMA’s request that it revisit its
    earlier interlocutory rulings.
    ¶ 41 In sum, FNMA is bound only by the outcome of the
    litigation, and the litigation here had not progressed to an outcome
    at the time FNMA asked the district court to revisit its order.
    Therefore, the lis pendens does not bind FNMA to the interlocutory
    order entered against Mr. Bell in the first phase of this case. We next
    discuss why, for a similar reason, res judicata does not bind FNMA.
    B. The Doctrine of Res Judicata Does Not Require that FNMA Be Bound
    by the Interlocutory Order Entered Against Mr. Bell
    ¶ 42 Jordan Construction argues that the district court erred in
    concluding that FNMA is not bound under the doctrine of res
    judicata by the judgment rendered against Mr. Bell.22 This doctrine
    promotes judicial efficiency and consistency by preventing re-
    litigation of issues and claims already resolved in a final judgment
    on the merits between the same parties or their privies.23 Jordan
    _____________________________________________________________
    21   See supra ¶ 35.
    22   The doctrine of res judicata includes two species: issue
    preclusion and claim preclusion. Oman v. Davis Sch. Distr., 
    2008 UT 70
    , ¶ 28, 
    194 P.3d 956
    . Jordan Construction does not specify which it
    is claiming applies here. Ultimately, the distinction does not matter
    for this case, because both types require a final judgment in an
    earlier proceeding.
    23   See 
    id.
     (noting that the doctrine’s purposes “include
    ‘(1) preserving the integrity of the judicial system by preventing
    inconsistent judicial outcomes; (2) promoting judicial economy by
    preventing previously litigated issues from being relitigated; and
    (Continued)
    14
    Cite as: 
    2017 UT 28
    Opinion of the Court
    Construction’s argument fails because this doctrine does not apply
    given that there had not yet been a final judgment at the time that
    FNMA entered this case.24
    ¶ 43 Jordan Construction concedes that both claim and issue
    preclusion require a “final judgment on the merits in [a] previous
    action.”25 It argues, however, that what is a “final judgment” for res
    judicata purposes is different than what is a “final judgment” in other
    contexts, for example for appeal purposes. In its view, “[t]he two
    concepts are not necessarily tied together.” It argues that because the
    district court decided “all issues relating to the property” between
    Jordan Construction and Mr. Bell, this constitutes a “final judgment
    on the merits” for res judicata purposes.
    ¶ 44 There is simply no support for the premise that “final
    judgment” means something different for res judicata purposes than
    its well-established meaning for purposes of an appeal. To the
    contrary, Jordan Construction’s interpretation of “final judgment”
    would likely sow confusion and is inconsistent with our procedural
    rules and other areas of our caselaw. First, rule 54(b) of the Utah
    Rules of Civil Procedure provides that “any order or other decision,
    however designated . . . may be changed at any time before the entry
    of judgment adjudicating all the claims and the rights and liabilities
    of all the parties.”26 Second, we have a specific doctrine that deals
    with a district court’s discretion to revisit interlocutory rulings
    before the entry of final judgment: the “law of the case” doctrine. We
    have said that “[w]hile a case remains pending before the district
    court prior to any appeal, the parties are bound by the court’s prior
    (3) protecting litigants from harassment by vexatious litigation.’”
    (citation omitted)).
    24 FNMA also argues that res judicata is inapplicable because
    FNMA was not in privity with Mr. Bell. We do not reach this issue
    because our conclusion that there had been no final judgment is
    dispositive.
    25 Jones, Waldo, Holbrook & McDonough v. Dawson, 
    923 P.2d 1366
    ,
    1370 (Utah 1996) (issue preclusion); Mack v. Utah State Dep’t of
    Commerce, Div. of Sec., 
    2009 UT 47
    , ¶ 29, 
    221 P.3d 194
     (claim
    preclusion).
    26   UTAH R. CIV. P. 54(b) (emphasis added).
    15
    JORDAN CONSTR. v. FNMA
    Opinion of the Court
    decision, but the court remains free to reconsider that decision.”27 It
    would thus be inconsistent with our law of the case doctrine to hold
    that a district court is barred, under res judicata principles, from
    revisiting issues it has decided earlier in the same case before
    entering a final judgment.
    ¶ 45 We conclude that the res judicata doctrine’s requirement of a
    “final judgment” does not include an interlocutory ruling within the
    course of a single proceeding. Rather, “final judgment” has the same
    meaning as that term does for purposes of appeal. As discussed
    above, the district court’s order granting partial summary judgment
    against Mr. Bell was not final because other claims remained
    pending in the case, and no rule 54(b) certification had been issued.28
    The district court thus correctly concluded that the doctrine of res
    judicata does not bind FNMA under these circumstances.
    III. The District Court Did Not Err in Concluding that
    Jordan Construction’s Second Amended Notice of
    Mechanic’s Lien Was Untimely
    ¶ 46 The parties agree that the timeliness of the second amended
    notice of mechanic’s lien turns on the date a certificate of occupancy
    was issued for the Property. Under the statute, a party has 180 days
    from that date to file its notice of lien.29 It is undisputed that Jordan
    Construction filed its second amended notice of lien in July 2009,
    more than 180 days after October 2008. Jordan Construction makes
    three arguments in support of its claim that its second amended
    notice was nevertheless timely. First, it argues that the district court
    abused its discretion in refusing to permit Jordan Construction to
    withdraw its admission that a certificate of occupancy was issued in
    October 2008. Second, it argues that equitable tolling principles
    apply to toll the time for amending its notice of mechanic’s lien.
    Finally, it argues that the relation back doctrine should apply, such
    that the second amended notice of mechanic’s lien should be treated
    _____________________________________________________________
    27 IHC Health Servs., Inc. v. D & K Mgmt., Inc., 
    2008 UT 73
    , ¶ 27, 
    196 P.3d 588
    .
    28   See supra ¶ 35.
    29  The statute requires that a notice of lien be filed within 180 days
    of “final completion of the original contract,” which the parties agree
    in this case means “the date of issuance of a permanent certificate of
    occupancy by the local government entity having jurisdiction over
    the construction project.” UTAH CODE § 38-1-7(1) (2008).
    16
    Cite as: 
    2017 UT 28
    Opinion of the Court
    as though filed on the date the notice of lien was originally filed.
    None of these arguments has merit.
    A. The District Court Did Not Abuse Its Discretion in Refusing to Permit
    Jordan Construction to Withdraw Its Admission that a Certificate of
    Occupancy Was Issued in October 2008
    ¶ 47 Jordan Construction admitted in response to a discovery
    request that the issuance of a certificate of occupancy—the key date
    for the timeliness of the notice of lien—occurred in October 2008. The
    admission stated:
    Request No. 2: Admit that Scott Bell began occupying
    the Property in October 2007.
    Response: Admit that Scott Bell occupied the property
    pursuant to a temporary occupancy permit beginning
    in October 2007. However, construction on his home
    was not yet finished, no final inspection had been
    completed and no permanent occupancy permit had
    been issued until October 2008.
    ¶ 48 After discovering a certificate of occupancy issued by Provo
    City in June 2011, Jordan Construction sought to withdraw its
    admission. The district court denied its request. Rule 36(c) of the
    Utah Rules of Civil Procedure provides the framework for requests
    to withdraw an admission: A district court “may permit withdrawal
    or amendment” if two requirements are met: 1) “presentation of the
    merits of the action will be promoted,” and 2) “withdrawal or
    amendment will not prejudice” the party who requested the
    admission. Because the presence of those threshold requirements is a
    prerequisite for a court to allow withdrawal or amendment, their
    presence or absence is subject to “a somewhat more exacting
    standard of review” than simple abuse of discretion.30 After
    considering the threshold requirements, this court then reviews the
    district court’s decision to grant or deny the motion to withdraw or
    amend, and will “reverse[] only upon a finding of abuse of
    discretion, i.e., if there is no reasonable basis for the decision.”31
    ¶ 49 First, the district court concluded that allowing withdrawal
    would not promote presentation of the merits of the action. We need
    _____________________________________________________________
    30 Langeland v. Monarch Motors, Inc., 
    952 P.2d 1058
    , 1061 (Utah
    1998).
    31   
    Id.
    17
    JORDAN CONSTR. v. FNMA
    Opinion of the Court
    not reach this issue because we conclude that the district court’s
    prejudice determination was correct, and therefore it had discretion
    to deny Jordan Construction’s request to withdraw.32
    ¶ 50 Second, to determine whether “a party will be prejudiced by
    the withdrawal of an admission,” we ask “whether the party is now
    any less able to obtain the evidence required to prove the matter
    which was admitted than he would have been at the time the
    admission was made.”33 There are a number of grounds to support
    the conclusion that FNMA would now have greater difficulty
    obtaining evidence to prove that the issuance of a certificate of
    occupancy occurred in October 2008. Jordan Construction’s
    admission was filed February 1, 2013. It did not seek to withdraw its
    admission until April 6, 2015. As FNMA points out, this date was
    “26 months after making the admission, more than a year after fact
    discovery closed, and six-and-a-half years after the case was
    originally filed.” Perhaps most problematic is that Jordan
    Construction was provided a copy of the 2011 certificate of
    occupancy in July 2013, and yet still did not seek to withdraw its
    admission until nearly two years later, long after the close of fact
    discovery.
    ¶ 51 Because Jordan Construction had admitted that a certificate
    of occupancy was issued in October 2008, FNMA took no steps in
    discovery to ascertain the date the certificate of occupancy was
    issued. We agree with the district court that, if withdrawal were
    permitted at this late stage, “FNMA would be left attempting to
    depose witnesses in order to confirm” that a certificate had been
    issued many years earlier, a fact that “it seems unlikely that any
    witness would be equipped” to address. The district court properly
    _____________________________________________________________
    32  Jordan Construction also argues that it should have been
    allowed to withdraw its admission because the facts it admitted
    were not necessary to answer the request for admission, and, in its
    view, rule 36 does not allow for “additional explanation or qualified
    admissions.” But the rule is phrased broadly, in that it provides that
    “[a]ny matter admitted under this rule is conclusively established
    unless the court on motion permits withdrawal or amendment of the
    admission.” UTAH R. CIV. P. 36(c) (emphasis added). There is nothing
    in the rule that prohibits a party from making a broader admission
    than is technically called for by the request for admission. We
    conclude that parties offer overly broad admissions at their peril.
    33   Langeland, 952 P.2d at 1063 (citation omitted).
    18
    Cite as: 
    2017 UT 28
    Opinion of the Court
    concluded that FNMA would be prejudiced by Jordan
    Construction’s long delay in seeking withdrawal of its admission,
    and therefore properly rejected Jordan Construction’s request to
    withdraw the admission.
    B. Jordan Construction Did Not Preserve the Issue of Whether Principles of
    Equitable Tolling Apply to Its Amended Notice of Mechanic’s Lien
    ¶ 52 Jordan Construction next argues that principles of equitable
    tolling should be applied to toll the statutory deadline for filing a
    notice of mechanic’s lien. We decline to address this argument
    because it was not raised before the district court.
    ¶ 53 “As a general rule, we ‘will not consider an issue unless it
    has been preserved in the court below.’”34 Jordan Construction
    makes no response to FNMA’s assertion that this issue was
    unpreserved. In the proceedings below, Jordan Construction’s
    memorandum in opposition to FNMA’s motion on the timeliness of
    the second amended lien contains arguments regarding only
    substantial compliance, res judicata, and relation back. We are unable
    to find the equitable tolling issue preserved in the record, and we
    therefore decline to address this argument.
    C. The Relation Back Doctrine Does Not Apply to Amendments to
    Notices of Mechanic’s Liens
    ¶ 54 Jordan Construction finally argues that its notice of
    mechanic’s lien was timely under the doctrine of “relation back.” To
    support this argument, Jordan Construction invokes Utah Rule of
    Civil Procedure 15(c), which permits subsequent pleadings to relate
    back to the date of the initial pleading in certain circumstances.35
    Jordan Construction argues that the “rationale” of this rule should be
    applied to statutory deadlines for filing mechanic’s lien notices. In its
    view, because the rules of civil procedure allow for amended
    pleadings to relate back to the date of filing the initial pleading in
    certain circumstances, amendments to mechanic’s lien notices should
    _____________________________________________________________
    34 VCS, Inc. v. Countrywide Home Loans, Inc., 
    2015 UT 46
    , ¶ 33, 
    349 P.3d 704
     (citation omitted).
    35 See UTAH R. CIV. P. 15(c) (2016) (“Whenever the claim or defense
    asserted in the amended pleading arose out of the conduct,
    transaction, or occurrence set forth or attempted to be set forth in the
    original pleading, the amendment relates back to the date of the
    original pleading.”).
    19
    JORDAN CONSTR. v. FNMA
    Opinion of the Court
    similarly relate back to the date of original filing whenever those
    circumstances are met.
    ¶ 55 We reject this argument. Jordan Construction provides no
    authority supporting the proposition that the rationale underlying
    rule 15(c) can be applied to mechanic’s lien notices. Unlike rule 15(c),
    the mechanic’s lien statute is silent regarding relation back of
    amendments. It provides that “a person claiming benefits under this
    chapter shall file . . . a written notice to hold and claim a lien within”
    the statutory timeline.36 “[O]ur general rule is that we will ‘give
    effect to omissions in statutory language’ by presuming them to be
    purposeful.”37 Because mechanic’s liens are peculiarly creatures of
    statute, they are particularly unsuited for uncodified exceptions to
    statutory deadlines.38 To hold that amendments made after the
    statutory deadline relate back to the date of initial filing would be to
    infer a substantive term not provided by the legislature, which
    would frustrate the carefully balanced scheme it chose to implement.
    Instead, to gain the benefits of the statute, a party must comply with
    its terms.39 We thus hold that, in the absence of a statutory term so
    providing, the relation back doctrine has no application to
    mechanic’s lien notice deadlines.
    ¶ 56 In sum, the district court did not err in concluding that the
    second amended notice of lien was untimely. We next turn to the
    issue of prejudgment interest.
    IV. The District Court Did Not Err in Concluding that Prejudgment
    Interest Is Unavailable Under the 2008 Version of the
    Mechanic’s Lien Statute
    ¶ 57 Jordan Construction argues that the district court erred in
    concluding that it was not entitled to prejudgment interest on its
    _____________________________________________________________
    36   UTAH CODE § 38-1-7(1)(a)(i) (2008).
    372 Ton Plumbing, L.L.C. v. Thorgaard, 
    2015 UT 29
    , ¶ 47, 
    345 P.3d 675
     (citation omitted).
    38 See id. ¶ 32 (“[W]e presume ‘that the expression of one [term]
    should be interpreted as the exclusion of another,’ and will not ‘infer
    substantive terms into the text that are not already there.’” (second
    alteration in original) (citations omitted)).
    39See AAA Fencing Co. v. Raintree Dev. & Energy Co., 
    714 P.2d 289
    ,
    291 (Utah 1986) (per curiam) (“[C]ompliance with the statute is
    required before a party is entitled to the benefits created by the
    statute.”).
    20
    Cite as: 
    2017 UT 28
    Opinion of the Court
    mechanic’s lien claim arising under the 2008 Utah Code. We affirm
    the district court and hold that prejudgment interest is not available
    on mechanic’s lien claims brought under this version of the statute.40
    ¶ 58 Jordan Construction argues that a mechanic’s lien action fits
    within our caselaw describing when prejudgment interest is
    available. “[W]e have stated that prejudgment interest may be
    proper when ‘the loss ha[s] been fixed as of a definite time and the
    amount of the loss can be calculated with mathematical accuracy in
    accordance with well-established rules of damages.’”41 Jordan
    Construction relies on this statement of our common law rule for the
    availability of prejudgment interest to argue that prejudgment
    interest is available on mechanic’s lien claims, despite statutory
    silence on the issue. But this argument overlooks the unique nature
    of mechanic’s liens and our precedent describing them as being
    creatures of statute.
    ¶ 59 First, the only prejudgment interest cases cited by Jordan
    Construction are also breach of contract cases that do not address a
    mechanic’s lien claim untethered to a breach of contract.42 Because
    the contractual claims at issue in these cases entitled the prevailing
    party to prejudgment interest, these cases did not make a distinction
    between the availability of prejudgment interest based on a breach of
    _____________________________________________________________
    40 We note that the mechanic’s lien statute was amended in 2012
    to expressly provide for prejudgment interest. UTAH CODE § 38-1a-
    309 (2012). The parties dispute the relevance of this amendment to
    the availability of prejudgment interest. As is typical in cases
    involving subsequent legislative amendment, one party contends the
    amendment clarified the law, and the other contends that it changed
    the law. We need not delve into this question here because we
    consider other sources of authority sufficient to determine that
    prejudgment interest was unavailable under the 2008 Utah Code.
    41 Iron Head Constr., Inc. v. Gurney, 
    2009 UT 25
    , ¶ 11, 
    207 P.3d 1231
    (second alteration in original) (citation omitted).
    42 E.g., id. ¶ 3 (“Iron Head filed both a mechanic’s lien against the
    Gurneys’ home and a suit alleging breach of contract, unjust
    enrichment, and quantum meruit, and requesting foreclosure of the
    mechanic’s lien.”); Lignell v. Berg, 
    593 P.2d 800
    , 809 (Utah 1979) (“In
    contract cases, certainly, interest on amounts found to be due in
    judicial proceedings is recovery to which the creditor is entitled as a
    matter of law.”).
    21
    JORDAN CONSTR. v. FNMA
    Opinion of the Court
    contract claim and based on a mechanic’s lien claim. These cases are
    thus unhelpful to the ultimate resolution of the issue before us.
    Moreover, Jordan Construction has not cited any cases outside of
    this jurisdiction where prejudgment interest was awarded on a
    mechanic’s lien claim even though the applicable statute—like
    Utah’s—is silent on prejudgment interest.
    ¶ 60 Second, we are dealing with mechanic’s liens, which we
    have said are “statutory creatures unknown to the common law.” 43
    Given that these statutes create rights unknown to the common law,
    the scope of the rights created are coextensive with what is provided
    for by statute. In 2 Ton Plumbing, L.L.C. v. Thorgaard, we recognized
    this principle in holding that a lien claimant’s notice of lien was
    invalid where it included items not specifically recognized by statute
    as being the subject of a mechanic’s lien.44 There we said that
    “[w]hen interpreting statutory text, we presume ‘that the expression
    of one [term] should be interpreted as the exclusion of another,’” and
    we “will not ‘infer substantive terms into the text that are not already
    there.’ ‘[W]e assume, absent a contrary indication, that the
    legislature used each term advisedly . . . [and] seek to give effect to
    omissions in statutory language by presuming all omissions to be
    purposeful.’”45
    ¶ 61 Jordan Construction argues that 2 Ton’s holding spoke only
    to what amounts a party may validly list on the face of its lien and
    that we did not address what is ultimately recoverable in an action
    to enforce the lien. While that may be true, the principle underlying
    our decision in that case compels its extension to the present case.
    The extent of overall recovery available on a mechanic’s lien claim,
    just like the amount that can be validly listed on the lien itself, can be
    no broader than what is provided for by statute. In 2 Ton, we stated
    that “where the statute fails, courts cannot create rights” and “[a]
    lien created solely by statute depends on the terms of the statute.”46
    ¶ 62 This conclusion is supported by the fact that the legislature
    has elsewhere delineated what is ultimately recoverable in a
    _____________________________________________________________
    AAA Fencing Co. v. Raintree Dev. & Energy Co., 
    714 P.2d 289
    , 291
    43
    (Utah 1986) (per curiam).
    44   
    2015 UT 29
    , ¶ 43, 
    345 P.3d 675
    .
    45 Id. ¶ 32 (second, third, fourth, and fifth alterations in original)
    (citations omitted).
    46   Id. ¶ 21 (citations omitted).
    22
    Cite as: 
    2017 UT 28
    Opinion of the Court
    mechanic’s lien claim beyond the amount listed on the face of the
    lien. For example, the legislature specifically provided that attorney
    fees are recoverable in an action to recover on the lien.47 While it
    specifically provided for attorney fees, it did not provide that
    prejudgment interest is recoverable in the action. The principle that
    underlies our 2 Ton decision is that what is left unsaid in the
    mechanic’s lien statute is not available for recovery in a mechanic’s
    lien action.
    ¶ 63 Finally, other jurisdictions, which we cited with approval in
    2 Ton, have also reached the conclusion that where prejudgment
    interest is not specifically enumerated as recoverable in a mechanic’s
    lien claim, it is unrecoverable.48
    ¶ 64 We therefore affirm the district court and conclude that
    prejudgment interest is unavailable on a mechanic’s lien claim under
    the 2008 Utah Code.
    V. The District Court Did Not Abuse Its Discretion in Concluding
    that FNMA Was the Successful Party in this Action for
    Attorney Fee Purposes
    ¶ 65 Jordan Construction argues that it was an abuse of
    discretion for the district court to conclude that FNMA was the
    “successful”49 party in the proceedings below. Utah Code section 38-
    1-18(1) (2008) provides that the “successful party” in an action to
    enforce a mechanic’s lien “shall be entitled to recover a reasonable
    _____________________________________________________________
    47   UTAH CODE § 38-1-18(1) (2008).
    48 See Nat’l Lumber Co. v. United Cas. & Sur. Ins. Co., 
    802 N.E.2d 82
    ,
    88 (Mass. 2004) (statutory interest not available on mechanic’s lien
    claim because “the nature of the [] action is in rem, to enforce a lien”
    and therefore does not involve “contractual obligations”); Artsmith
    Dev. Grp., Inc. v. Updegraff, 
    868 A.2d 495
    , 497 (Pa. Super. Ct. 2005)
    (holding that trial court properly denied claim for interest “because
    the mechanics’ lien statute . . . does not authorize a lien for these
    amounts” and noting that “[i]tems other than labor and materials are
    more properly sought in an action for breach of the construction
    contract, if that contract authorizes recovery of interest”).
    49  We have treated the inquiry of who is a “successful party”
    under this statute as synonymous with the issue of who is a
    “prevailing party” in other contexts, A.K. & R. Whipple Plumbing &
    Heating v. Guy, 
    2004 UT 47
    , ¶ 19, 
    94 P.3d 270
    , and we continue to
    treat the terms synonymously here.
    23
    JORDAN CONSTR. v. FNMA
    Opinion of the Court
    attorneys’ fee, to be fixed by the court, which shall be taxed as costs
    in the action.” We have directed lower courts to “use their common
    sense in deciding whether a party was ‘successful’ in bringing or
    defending against a mechanic’s lien enforcement action.”50 We
    specifically cautioned against considering only “the net judgment in
    the case” and stressed the importance of “’looking at the amounts
    actually sought and then balancing them proportionally with what
    was recovered.’”51 The district court followed this instruction
    precisely in concluding that FNMA was the successful party. We
    therefore find no abuse of discretion.52
    ¶ 66 Jordan Construction makes only one argument: in its view,
    it was “successful” because it recovered the amount on the face of its
    original lien, $126,956.92. The premise of this argument is that
    because FNMA stipulated to the payment of some amount toward a
    mechanic’s lien claim, Jordan Construction was “successful” on that
    claim. But this argument is inconsistent with our precedent. As this
    case shows, a party can ultimately recover some amount on a
    mechanic’s lien claim, but still not be “successful” in the action.
    ¶ 67 For example, a similar argument was made in A.K. & R.
    Whipple Plumbing and Heating v. Guy.53 There, we declined to adopt
    “a rigid rule that would deprive trial courts of their power to apply
    their discretion and common sense to this issue, and would require a
    trial court to award fees to whichever party emerged with a net
    judgment, no matter how insignificant.”54 We concluded that “[s]uch
    a result is not required by the statute.”55 But that’s essentially what
    Jordan Construction asks for here: a rigid application of a rule that
    would mean, because Jordan Construction obtained some amount of
    recovery on its mechanic’s lien claim, it therefore was “successful”
    on that claim. We reject this approach.
    ¶ 68 Consistent with our precedent, the district court issued a
    detailed analysis of the “common sense” approach it applied in
    determining FNMA to be the successful party. The court conceded
    _____________________________________________________________
    50   Id. ¶ 26.
    51   Id. (citation omitted).
    52   See R.T. Nielson Co. v. Cook, 
    2002 UT 11
    , ¶ 25, 
    40 P.3d 1119
    .
    53   
    2004 UT 47
    , 
    94 P.3d 270
    .
    54   Id. ¶ 25.
    55   Id.
    24
    Cite as: 
    2017 UT 28
    Opinion of the Court
    that if Jordan Construction had, from the outset, sought to enforce
    only its original lien and recovered the amount that it did here, it
    would undoubtedly have been the successful party. But that is not
    what happened. Here, Jordan Construction’s third-party complaint
    against FNMA alleged that it was entitled to recover $336,568.66 at
    the sheriff’s sale of the Property. In the end, it recovered just over
    one-third of that amount. Thus, between a total victory for Jordan
    Construction and a total victory for FNMA, the amount recovered
    was closer to a total victory for FNMA.
    ¶ 69 Moreover, the court noted that Jordan Construction lost on
    almost all of the disputed issues that were resolved on motion before
    the court. FNMA successfully 1) quashed the writ of execution, 2)
    moved to dismiss the first third-party complaint, 3) moved to
    dismiss one of the two claims in the amended third-party complaint,
    and 4) whittled down the amount on the mechanic’s lien claim to
    $126,956.92 through a number of motions for partial summary
    judgment. Jordan Construction lost motion after motion, and in the
    end it achieved what the district court called a “pyrrhic” victory. The
    district court was correct that it would “strain[] logic” to conclude
    that Jordan Construction should recover its fees here; instead, FNMA
    was the “comparative victor.”
    ¶ 70 We agree with the district court’s analysis. A district court
    has discretion to view the entire course of proceedings and assess
    whether a party who achieved some amount of recovery on a
    mechanic’s lien claim was “successful” on that claim or not. We
    accordingly affirm on this issue.
    VI. FNMA Is Entitled to Reasonable Attorney Fees
    Incurred on Appeal
    ¶ 71 FNMA requests its attorney fees for this appeal. “[W]hen a
    party is entitled to attorney fees below and prevails on appeal, that
    party is ‘also entitled to fees reasonably incurred on appeal.’”56 As
    discussed above, the district court awarded attorney fees to FNMA
    for being the “successful” party in the action to foreclose on the
    mechanic’s lien. Because we affirm the district court, we conclude
    that FNMA is entitled to attorney fees for this appeal. We remand
    this case to the district court for an award of attorney fees reasonably
    incurred on this appeal.
    _____________________________________________________________
    56  Dillon v. S. Mgmt. Corp. Ret. Trust, 
    2014 UT 14
    , ¶ 61, 
    326 P.3d 656
    (citation omitted).
    25
    JORDAN CONSTR. v. FNMA
    Opinion of the Court
    Conclusion
    ¶ 72 We affirm the district court on all grounds. The district court
    had discretion to quash the writ of execution and halt the sheriff’s
    sale because it was merely reconsidering a prior ruling, which is well
    within a district court’s discretion. The district court correctly
    concluded that FNMA is not bound by the interlocutory order
    entered against Mr. Bell. Jordan Construction has failed to show that
    the district court erred in concluding its second amended notice of
    mechanic’s lien was untimely. The district court had discretion to
    deny Jordan Construction’s request to withdraw its admission; the
    doctrine of relation back does not apply to mechanic’s lien statutory
    deadlines; and the issue of equitable tolling was not preserved. The
    district court also correctly concluded that prejudgment interest is
    not available on mechanic’s lien claims under the 2008 version of the
    statute, because that statute does not specifically provide for such
    interest. And finally, we find no abuse of discretion in the district
    court’s conclusion that FNMA was the successful party for attorney
    fee purposes. We accordingly affirm and remand for the district
    court to determine the appropriate fee award.
    26
    

Document Info

Docket Number: Case No. 20160474

Citation Numbers: 2017 UT 28

Filed Date: 5/22/2017

Precedential Status: Precedential

Modified Date: 5/22/2018

Authorities (12)

Smith v. Fairfax Realty, Inc. , 483 Utah Adv. Rep. 15 ( 2003 )

IHC Health Services, Inc. v. D & K MANAGEMENT, INC. , 615 Utah Adv. Rep. 32 ( 2008 )

MacK v. Utah State Department of Commerce , 635 Utah Adv. Rep. 79 ( 2009 )

Oman v. Davis School District , 614 Utah Adv. Rep. 16 ( 2008 )

Iron Head Construction, Inc. v. Gurney , 628 Utah Adv. Rep. 20 ( 2009 )

Press Pub., Ltd. v. MATOL BOTANICAL INTERNATIONAL , 37 P.3d 1121 ( 2001 )

Artsmith Development Group, Inc. v. Updegraff , 2005 Pa. Super. 11 ( 2005 )

Dillon v. Southern Management Corp. Retirement Trust , 2014 Utah LEXIS 54 ( 2014 )

A.K. & R. Whipple Plumbing & Heating v. Guy , 501 Utah Adv. Rep. 12 ( 2004 )

Orvis v. Johnson , 595 Utah Adv. Rep. 22 ( 2008 )

2 Ton Plumbing, L.L.C. v. Thorgaard , 779 Utah Adv. Rep. 6 ( 2015 )

VCS, Inc. v. Countrywide Home Loans, Inc. , 2015 Utah LEXIS 144 ( 2015 )

View All Authorities »