UDOT v. Coalt Inc. , 2020 UT 58 ( 2020 )


Menu:
  •                This opinion is subject to revision before final
    publication in the Pacific Reporter
    
    2020 UT 58
    IN THE
    SUPREME COURT OF THE STATE OF UTAH
    UTAH DEPARTMENT OF TRANSPORTATION,
    Petitioner and Cross-Respondent,
    v.
    COALT, INC.,
    Respondent and Cross-Petitioner.
    No. 20161062
    Heard February 12, 2018
    Filed August 17, 2020
    On Certiorari to the Utah Court of Appeals
    Second District, Farmington
    The Honorable John R. Morris
    No. 080700367
    Attorneys:
    Sean D. Reyes, Att’y Gen., Stanford E. Purser, Deputy Solic. Gen.,
    David M. Quealy, William H. Christensen, Asst. Att’y Gens.,
    Salt Lake City, for petitioner and cross-respondent
    Michael R. Carlston, Rodney R. Parker, Salt Lake City,
    for respondent and cross-petitioner
    JUSTICE PETERSEN authored the opinion of the Court in which
    CHIEF JUSTICE DURRANT, ASSOCIATE CHIEF JUSTICE LEE,
    JUSTICE HIMONAS, and JUSTICE PEARCE joined.
    JUSTICE PETERSEN, opinion of the Court:
    INTRODUCTION
    ¶1 The Utah Department of Transportation (UDOT)
    condemned property owned by Coalt, Inc. in connection with the
    Legacy Parkway Project. The Legacy Parkway runs near the
    eastern shore of the Great Salt Lake and its wetlands. Before
    construction could begin, federal law required study of the
    UDOT v. COALT
    Opinion of the Court
    project’s potential environmental impact and approval from
    federal agencies. In 2000, a Final Environmental Impact Statement
    was released. This statement did not rely on the specific property
    at issue in this case (Parcel 84) to mitigate the environmental
    impact of the Parkway. The federal agencies gave the required
    approvals. But the Salt Lake City mayor and numerous public
    interest groups disputed the adequacy of the environmental
    impact statement and argued that UDOT was not doing enough
    to protect the environment.
    ¶2 After years of litigation in federal court, during which the
    project was at a standstill, UDOT entered into a settlement
    agreement with the public interest litigants. As part of the
    settlement, UDOT agreed to a number of new conditions,
    including acquisition of an additional 121 acres of mitigation
    property that would be managed in connection with the Legacy
    Nature Preserve. This property included Parcel 84. Because the
    federal agencies did not require this additional mitigation for their
    approval of the project, the United States Army Corps of
    Engineers (Corps) agreed to allow UDOT to credit the 121 acres
    (including Parcel 84) toward mitigation of future transportation
    projects in the area that required the Corps’ approval.
    ¶3 In light of this background, Coalt argues that UDOT did
    not take Parcel 84 for the Legacy Parkway, but to pay a “ransom”
    demanded by the public interest litigants to settle the federal
    litigation and to mitigate future unspecified transportation
    projects. Based on these assertions, Coalt argues that UDOT does
    not have the authority to condemn its property because these are
    not valid “state transportation purposes”1 or “public use[s]”2 as
    required by state law.
    ¶4 In the alternative, Coalt asserts that if we conclude UDOT
    does have authority to condemn property for these purposes, then
    Coalt’s compensation for the taking should include any increased
    market value caused by Parcel 84’s proximity to the Legacy
    Parkway. The applicable statute states that “any decrease or
    increase of the fair market value of real property prior to the date
    of valuation caused by the public improvement for which such
    1   See UTAH CODE § 72-5-103(1).
    2   See UTAH CONST., art. I, § 22; UTAH CODE § 78B-6-504(1)(d).
    2
    Cite as: 
    2020 UT 58
                             Opinion of the Court
    property is acquired or by the likelihood that the property would
    be acquired for such improvement . . . will be disregarded in
    determining the compensation for the property.” UTAH CODE
    § 57-12-13(3) (1972).3 Coalt argues that “the public improvement
    for which the property was acquired” was not the Legacy
    Parkway but the future unspecified transportation projects
    referenced in the settlement agreement. On this basis, Coalt
    argues that the market value of Parcel 84 should include any
    increase or decrease caused by the property’s proximity to the
    Legacy Parkway.
    ¶5 The court of appeals affirmed the district court’s
    determination that UDOT has the authority to condemn Coalt’s
    land. However, it reversed the district court and held that just
    compensation should include any enhanced value caused by the
    Legacy Parkway. This was primarily due to the court of appeals’
    determination that UDOT had inadequately briefed the valuation
    issue. The court of appeals did not analyze whether the district
    court was correct on the merits.
    ¶6 We agree with the court of appeals that UDOT has
    authority to condemn Parcel 84. So we affirm that part of the court
    of appeals’ decision. And while we also agree that UDOT’s
    briefing on valuation was minimal, the adequacy of UDOT’s
    briefing is not ultimately dispositive. This is because we conclude
    that Coalt has not provided a plausible basis for reversal of the
    3   During the relevant time period, the statute read,
    Before the initiation of negotiations for real
    property, an amount shall be established which is
    reasonably believed to be just compensation
    therefor, and such amount shall be offered for the
    property. In no event shall such amount be less than
    the lowest approved appraisal of the fair market
    value of the property. Any decrease or increase of the
    fair market value of real property prior to the date of
    valuation caused by the public improvement for which
    such property is acquired or by the likelihood that the
    property would be acquired for such improvement, other
    than that due to physical deterioration within the
    reasonable control of the owner, will be disregarded in
    determining the compensation for the property.
    UTAH CODE § 57-12-13(3) (1972) (emphases added)).
    3
    UDOT v. COALT
    Opinion of the Court
    district court’s valuation decision. Accordingly, we reverse this
    portion of the court of appeals’ opinion.
    BACKGROUND
    ¶7 Parcel 84 is an approximately 65-acre piece of
    undeveloped land in Davis County owned by Coalt. It is part of a
    larger 121-acre property that UDOT condemned to mitigate the
    environmental impacts of the Legacy Parkway Project.
    The Legacy Parkway Project and Related Litigation
    ¶8 In the 1990s, the State of Utah determined that traffic
    congestion in southern Davis County had become a problem.
    UDOT began to meet with relevant federal and state agencies,
    political subdivisions, private parties, and members of the public
    to discuss potential solutions. One option included the
    construction of a highway west of Interstate 15. Early in the
    process, UDOT began to acquire property for the future
    construction of the highway and to mitigate its environmental
    impacts.
    ¶9 Before construction could begin, federal law required the
    completion of an environmental impact statement (EIS),4 approval
    4  The National Environmental Policy Act requires federal
    agencies to “include in every recommendation or report on
    proposals for legislation and other major Federal actions
    significantly affecting the quality of the human environment, a
    detailed statement” that includes:
    (i) the environmental impact of the proposed action,
    (ii) any adverse environmental effects which cannot
    be avoided should the proposal be implemented,
    (iii) alternatives to the proposed action, (iv) the
    relationship between local short-term uses of man’s
    environment and the maintenance and enhancement
    of long-term productivity, and (v) any irreversible
    and irretrievable commitments of resources which
    would be involved in the proposed action should it
    be implemented.
    42 U.S.C. § 4332(C). “Copies of such statement and the comments
    and views of the appropriate Federal, State, and local agencies,
    which are authorized to develop and enforce environmental
    (continued . . .)
    4
    Cite as: 
    2020 UT 58
                           Opinion of the Court
    from the Federal Highway Administration (FHWA), and a Clean
    Water Act (CWA) permit from the Corps. A Final Environmental
    Impact Statement was released in June 2000 (2000 EIS). In January
    2001, the Corps approved “the preferred alternative route” for the
    Parkway and granted the necessary CWA permit.
    ¶10 Within weeks, a number of public interest groups sued in
    federal district court to vacate the permit. The federal district
    court ruled in UDOT’s favor, prompting the public interest
    groups to seek an injunction from the Tenth Circuit. The Tenth
    Circuit granted the injunction, which halted the project during the
    pendency of the appeal.
    ¶11 On appeal, the public interest litigants urged the Tenth
    Circuit to order the agencies to prepare a new or supplemental
    EIS and process a new CWA permit application that adequately
    addressed: “(1) mass transit alternatives, (2) alternative land use
    scenarios, (3) land use and growth impacts, (4) impacts on Salt
    Lake City, (5) wetlands and wildlife impacts, and (6) air quality
    impacts.” Utahns for Better Transp. v. U.S. Dep’t of Transp., 
    305 F.3d 1152
    , 1162 (10th Cir. 2002), as modified on reh’g, 
    319 F.3d 1207
    (10th
    Cir. 2003).
    ¶12 Ultimately, the Tenth Circuit concluded that the 2000 EIS
    was “inadequate” in a number of ways and that the Corps’ grant
    of the CWA permit was “arbitrary and capricious.”
    Id. at 1192.
    The Tenth Circuit determined that in approving the project, the
    federal agencies had failed to adequately consider the impact of
    the Parkway on wildlife and whether less damaging alternatives
    were practicable.
    Id. ¶13 So UDOT
    and the FHWA returned to the drawing board.
    For two years they worked to complete new environmental
    studies. In December 2004, they released a draft of a new EIS for
    public comment (2004 Draft EIS). The 2004 Draft EIS did not
    include Parcel 84 as part of the mitigation for the project. After
    reviewing the 2004 Draft EIS, the public interest litigants were
    unsatisfied.
    ¶14 At this point, the project had been stalled for almost four
    years. In September 2005, UDOT entered into settlement
    negotiations with the litigants. The parties eventually reached a
    standards, shall be made available . . . to the public as provided by
    section 552 of Title 5 . . . .”
    Id. 5
                              UDOT v. COALT
    Opinion of the Court
    settlement agreement that called for additional measures to
    protect the wetlands and its wildlife inhabitants from the effects
    of the Parkway, including a speed limit of fifty-five miles per
    hour, the prohibition of trucks, a ban on billboards, and noise-
    reducing pavement. The agreement also required additional land
    for environmental mitigation that would be managed in
    connection with the Legacy Nature Preserve. Parcel 84 was part of
    this additional mitigation.
    The Corps’ Approval of Property for Future Mitigation Credit
    ¶15 While the additional mitigation property was necessary
    to end the litigation that had halted construction, it was not a
    prerequisite to federal approval of the project. The settlement
    agreement stated that the Corps “has provided a letter advising
    that it will allow credits from this Mitigation Property to be used
    as mitigation for transportation projects.” The agreement did not
    limit the mitigation credits to any specific project.
    ¶16 The Utah Legislature approved UDOT’s execution of the
    settlement agreement by resolution in November 2005, “to resolve
    all pending litigation and potential future claims . . . and allow for
    the construction of the Legacy Parkway.” In January 2006, both
    the FHWA and the Corps approved the Final Supplemental EIS.
    Condemnation of Parcel 84 and Ensuing Litigation
    ¶17 UDOT subsequently began eminent domain proceedings
    to acquire Parcel 84. UDOT identified the Legacy Parkway as the
    project for which it was acquiring the property in its complaint
    and the attached Condemnation Resolution. Coalt fought the
    condemnation, arguing that UDOT did not have the authority to
    condemn Parcel 84 because it was not doing so for a
    transportation purpose or a public use, but to settle third-party
    litigation and mitigate a future unspecified transportation project.
    ¶18 After a bench trial, the district court rejected Coalt’s
    argument and found in favor of UDOT. It ruled that UDOT had
    authority to take Parcel 84, concluding that it “was necessary to
    effect a lifting of the stay on construction of the Legacy Parkway
    imposed by the Tenth Circuit Court of Appeals,” and that it was
    for a “public state transportation purpose.”
    ¶19 With respect to determining just compensation for the
    taking, Coalt argued that UDOT took Parcel 84 for future
    transportation projects, not the Legacy Parkway, and that
    therefore the market value of Parcel 84 should include any
    6
    Cite as: 
    2020 UT 58
                           Opinion of the Court
    increase caused by the Legacy Parkway. The district court rejected
    this argument and excluded from the market value of Parcel 84
    any appreciation caused by its proximity to the Legacy Parkway.
    ¶20 Coalt appealed. The court of appeals affirmed the district
    court on the issue of UDOT’s authority. Utah Dep’t of Transp. v.
    Coalt Inc., 
    2016 UT App 169
    , ¶ 20, 
    382 P.3d 602
    . However, it
    reversed the district court’s conclusion that Coalt was not entitled
    to compensation for the increased value of the property resulting
    from the influence of the Parkway.
    Id. ¶ 29.
    This holding was due
    in large part to the court’s finding that UDOT had not adequately
    briefed the valuation issue.
    Id. ¶ 24.
    The court of appeals
    remanded for a redetermination of the property’s fair market
    value, including the influence of the Parkway.
    Id. ¶¶ 29–30.
       ¶21 UDOT petitioned for certiorari review of the court of
    appeals’ reversal of the district court’s valuation decision and its
    determination that UDOT had inadequately briefed the issue.
    Coalt cross-petitioned for review of the court of appeals’ decision
    that UDOT was authorized to condemn Parcel 84.
    ¶22 We granted certiorari on all issues. We exercise
    jurisdiction under Utah Code section 78A-3-102(3)(a).
    STANDARD OF REVIEW
    ¶23 “On certiorari, we review the court of appeals’ decision
    for correctness.” PC Riverview, LLC v. Xiao-Yan Cao, 
    2017 UT 52
    ,
    ¶ 20, 
    424 P.3d 162
    .
    ANALYSIS
    ¶24 We are presented with three issues. First, we must decide
    whether UDOT has authority to condemn Parcel 84. If we
    conclude it does, we must then decide whether just compensation
    for the taking should include any increase in the value of Parcel 84
    caused by the development of the Parkway itself. However,
    before we reach the merits of that question, we must address the
    adequacy of UDOT’s briefing before the court of appeals. We
    address the scope of UDOT’s authority first.
    I. UDOT’S AUTHORITY TO CONDEMN PARCEL 84
    ¶25 Coalt argues that UDOT’s taking of Parcel 84 exceeds its
    statutory and constitutional condemnation authority. Coalt’s
    argument relies upon two related premises. Coalt asserts that
    UDOT took Parcel 84 not to mitigate the environmental impact of
    the Legacy Parkway, but as a “ransom” paid to private litigants so
    they would drop the federal litigation. Additionally, because the
    7
    UDOT v. COALT
    Opinion of the Court
    federal agencies did not require the additional mitigation to
    approve the project and the Corps therefore agreed to let UDOT
    use it in obtaining Corps approval of future transportation
    projects, Coalt asserts that the mitigation included in the
    settlement agreement is not actually for the Legacy Parkway but
    for “unspecified future projects.”
    ¶26 Based upon these antecedent presumptions, Coalt first
    argues that UDOT lacks statutory authority to take Parcel 84.
    Utah’s general eminent domain statute permits condemnation
    only when necessary for a public use. See UTAH CODE § 78B-6-501.
    The eminent domain statute identifies many public uses, among
    which are “roads, byroads, streets, and alleys for public vehicular
    use,”
    id. § 78B-6-501(2)(c)(v), and
    “all other public uses authorized
    by the Legislature,”
    id. § 78B-6-501(2)(b). The
    public uses
    enumerated in this statute are the “starting point.” Utah Dep’t of
    Transp. v. Carlson, 
    2014 UT 24
    , ¶ 20, 
    332 P.3d 900
    . The legislature
    has enacted a range of other statutes authorizing public uses
    beyond those listed here. See
    id. ¶ 21
    n.2 & n.3.
    ¶27 With regard to public highways in particular, the
    Rights-of-Way Act empowers UDOT to “acquire any real
    property . . . necessary for temporary, present, or reasonable
    future state transportation purposes by . . . condemnation.” UTAH
    CODE § 72-5-103(1). Section 102 lists a number of “state
    transportation purposes” including “the mitigation of impacts
    from public transportation projects.”
    Id. § 72-5-102(12). ¶28
    Coalt asserts that because settling litigation is not one of
    the state transportation purposes enumerated in the Rights-of-
    Way Act, UDOT has exceeded its statutory authority. But the fact
    that UDOT agreed to take the additional mitigation property as
    part of a settlement is not legally relevant in and of itself. What
    matters is the purpose of the taking. Coalt asks us to ignore the
    facts of the case before us, as demonstrated by a hypothetical
    Coalt advances in which it compares the scenario here with one in
    which a private citizen harasses UDOT with litigation to induce a
    settlement that would increase his personal residential property
    value. As the court of appeals noted,
    This is not a circumstance where, in order to settle a
    lawsuit over a public project, a state agency
    condemns a parcel of land physically and
    functionally unrelated to the project itself in order to
    satisfy a litigant’s private interests, also unrelated to
    8
    Cite as: 
    2020 UT 58
                            Opinion of the Court
    the project. We have no occasion to consider the
    quite dissimilar issues those circumstances might
    raise.
    Utah Dep’t of Transp. v. Coalt Inc., 
    2016 UT App 169
    , ¶ 18 n.6, 
    382 P.3d 602
    .
    ¶29 The very focus of the federal litigation was the question
    of what steps were necessary to minimize the environmental
    impact of running the Legacy Parkway along the wetlands of the
    Great Salt Lake. UDOT believed the 2000 EIS provided sufficient
    environmental protection. But the public interest litigants
    disagreed. The litigants did not advance a private, personal
    agenda. Rather their arguments centered on the sufficiency of the
    environmental impact statement.
    ¶30 The Tenth Circuit concluded that the litigants had
    identified legitimate problems with the 2000 EIS and the CWA
    permit. The Tenth Circuit concluded that in granting the CWA
    permit, the Corps had acted arbitrarily and capriciously because it
    had not adequately studied the impact of the highway on wildlife.
    The Tenth Circuit observed,
    The Great Salt Lake (“GSL”) and the wetlands
    surrounding its shoreline serve as an important
    habitat for a variety of birds, reptiles, amphibians,
    and mammals, some of which are endangered. The
    wetlands of the GSL account for 75 percent of all
    wetlands in the State of Utah, whose total land area
    consists of only 1.5 percent wetlands. The shores of
    the GSL are internationally important because they
    are a link of the Pacific Flyway for migratory
    waterfowl and a link of the Western Hemisphere
    Shorebird Reserve Network (“WHSRN”). Some two
    to five million birds use the GSL yearly and 90
    percent of that use is concentrated in the eastern
    shore.
    Utahns for Better Transp. v. U.S. Dep’t of Transp., 
    305 F.3d 1152
    , 1161
    (10th Cir. 2002), as modified on reh’g, 
    319 F.3d 1207
    (10th Cir. 2003).
    ¶31 The Tenth Circuit rejected the 2000 EIS and the CWA
    permit. UDOT spent two more years studying how much
    mitigation was necessary for the project to go forward. UDOT
    thought the solution was contained in the 2004 Draft EIS. But
    again, the public interest litigants disagreed. And as is always the
    case with litigation, UDOT had no guarantee that it would
    9
    UDOT v. COALT
    Opinion of the Court
    prevail. So it resolved the dispute as to how much mitigation was
    necessary through compromise.
    ¶32 Coalt essentially asks us to conclude that unless UDOT
    deemed Parcel 84 to be necessary mitigation for the Parkway on
    its own, independent of any third-party influence, then UDOT did
    not really take the property for the project. Rather it took the
    property to appease the third party, thus addressing a private
    rather than a public purpose.
    ¶33 This is similar to the argument we rejected in another
    case related to mitigation of the Legacy Parkway, Utah Department
    of Transportation v. G. Kay, Inc., 
    2003 UT 40
    , 
    78 P.3d 612
    . That case
    involved an earlier taking of land by UDOT for the Legacy Nature
    Preserve. See
    id. ¶¶ 2–3.
    We noted that “[b]ecause construction of
    the highway would necessitate filling wetlands subject to federal
    regulation,” UDOT had to obtain the CWA permit discussed
    above.
    Id. ¶ 2.
    Before providing the permit, the Corps required the
    taking that was the subject of that case to offset the environmental
    effects of the Parkway.
    Id. Like Coalt argues
    here, the defendant in
    that case complained that “the condemnation statute does not
    authorize UDOT to acquire land for the purpose of satisfying an
    agreement with federal agencies.”
    Id. ¶ 10.
    We disagreed:
    Federal influence in UDOT’s decision-making
    process would call UDOT’s action into question only
    if it showed that UDOT was attempting to do
    something other than mitigate impacts of a state
    transportation project when it brought the action to
    condemn G. Kay’s property for the preserve. Here,
    however, UDOT’s interaction with the [Corps]
    actually demonstrates that the proposed preserve
    was motivated by UDOT’s desire to obtain the
    permit required to proceed with the project. It
    therefore supports, rather than undermines, the
    conclusion that creation of the preserve was
    motivated by a “transportation purpose.”
    Any role played by federal agencies in selecting the
    particular land to be taken is likewise irrelevant. We
    do not review the internal processes of, or external
    influences on, UDOT in arriving at its decision to
    condemn particular properties for transportation
    purposes, except for indications of bad faith.
    Id. ¶¶ 10–11. 10
                            Cite as: 
    2020 UT 58
                           Opinion of the Court
    ¶34 Similarly, the fact that the public interest litigants
    influenced the final amount of mitigation that UDOT condemned
    for the Parkway is not necessarily material. Indeed, UDOT sought
    input from interested constituencies from the outset of the
    planning process. This would be relevant only if the facts showed
    that UDOT actually took Parcel 84 to do something other than
    mitigate the effects of the Parkway, or that UDOT acted in bad
    faith. Neither is the case here. After years of delay and having its
    first EIS and CWA permit thrown out by the Tenth Circuit, UDOT
    determined that the settlement agreement was necessary to end
    the dispute over environmental mitigation and lift the federal
    injunction that had halted the project. As in G. Kay, this
    demonstrates that UDOT’s taking of Parcel 84 was motivated by
    its desire to proceed with the project. This supports rather than
    undermines the conclusion that the taking and associated
    mitigation was for the Parkway. The legislature and the governor
    agreed that the settlement was necessary to proceed with the
    project. We will not second-guess that determination absent an
    indication of bad faith.
    ¶35 Next, Coalt argues that because the settlement agreement
    stated that the Corps would consider the additional land as
    mitigation for other “transportation projects” without reference to
    a specific project, the taking cannot be “necessary” to a state
    transportation purpose or public use as required by state law, see
    UTAH CODE §§ 72-5-103(1), 78B-6-504(1)(b), because the nature of
    the future project and its timeframe are unknown. If that were
    actually what happened, Coalt would have a point. It is correct
    that the language of the settlement agreement states that the
    Corps would consider the additional mitigation toward other
    “transportation projects.” But UDOT did not unnecessarily file a
    complaint to take Parcel 84 on the off-chance that it might be
    necessary to mitigate a future, unknown project. It made a
    beneficial agreement with the Corps, because the Corps did not
    require the additional mitigation for the CWA permit. The record
    facts clearly show that UDOT agreed to take Parcel 84 as
    mitigation for the Parkway.
    ¶36 We conclude that UDOT ultimately condemned the
    additional mitigation property, which includes Parcel 84, to
    mitigate the environmental impacts of the Parkway and to allow it
    to proceed with construction of the Parkway. These are
    unquestionably state transportation purposes under the
    Rights-of-Way Act.
    Id. § 72-5-102. 11
                              UDOT v. COALT
    Opinion of the Court
    ¶37 UDOT contends that it also had statutory authority to
    condemn Parcel 84 under the catch-all provision of the eminent
    domain statute because the legislature authorized the
    condemnation when it approved the settlement agreement. See
    id. § 78B-6-501(2)(b) (providing
    that eminent domain may be
    exercised for “all other public uses authorized by the
    Legislature”). Coalt disagrees that the resolution specifically
    authorized the taking. We need not resolve this issue as we have
    concluded that UDOT had ample statutory authority under the
    Rights-of-Way Act.
    ¶38 Finally, Coalt asserts that UDOT lacked constitutional
    authority to condemn Parcel 84 under the Takings Clause of the
    Utah Constitution, which permits property to be taken only for a
    public use.5 Coalt argues that settling litigation is not a “public
    use.” For the reasons articulated above, we reject Coalt’s
    characterization of UDOT’s purpose for condemning Parcel 84.
    The taking was to mitigate the impact of the Parkway and to lift
    the stay on construction. Coalt’s constitutional argument is
    without merit.
    ¶39 Because we conclude that UDOT does have authority to
    take Coalt’s property, we now analyze how Parcel 84 should be
    valued for purposes of just compensation.
    II. THE VALUATION OF PARCEL 84
    ¶40 UDOT challenges the court of appeals’ decision that
    Coalt’s compensation should include any increase in the value of
    its land caused by its proximity to the Legacy Parkway. As noted
    above, the district court found in favor of UDOT on this issue. But
    the court of appeals reversed the district court because it
    determined UDOT’s briefing was inadequate on this point.
    ¶41 Accordingly, we must first address the adequacy of
    UDOT’s briefing before the court of appeals on the issue of Parcel
    84’s valuation. While we agree that UDOT’s briefing was minimal,
    we ultimately do not decide whether UDOT’s briefing was
    adequate because it is not determinative. Regardless of the
    adequacy of UDOT’s briefing, we cannot rule in Coalt’s favor
    5  Article I, section 22 of the Utah Constitution states, “Private
    property shall not be taken or damaged for public use without
    just compensation.”
    12
    Cite as: 
    2020 UT 58
                            Opinion of the Court
    because it has not provided a plausible basis for reversal of the
    district court. This is because Coalt’s valuation arguments rely on
    the antecedent presumptions we rejected above.
    ¶42 The court of appeals concluded that UDOT’s briefing on
    valuation was inadequate, finding that it had “made no effort to
    defend the district court’s decision” and “failed to include any
    response to Coalt’s arguments . . . or any reference to the issue at
    all.” Utah Dep’t of Transp. v. Coalt Inc., 
    2016 UT App 169
    , ¶ 22, 
    382 P.3d 602
    . Relying on Broderick v. Apartment Management
    Consultants, L.L.C., 
    2012 UT 17
    , 
    279 P.3d 391
    , the court of appeals
    reversed the district court and ruled in Coalt’s favor after
    concluding that Coalt had advanced a plausible argument and
    “competently called into question” the district court’s reasoning.
    Coalt, 
    2016 UT App 169
    , ¶ 25. The court of appeals did not analyze
    whether the district court’s decision was “ultimately right or
    wrong.”
    Id. ¶43 Rule 24(a)–(b)
    of the Utah Rules of Appellate Procedure
    requires, among other things, that both appellant and appellee
    briefs contain “reasoned analysis supported by citations to legal
    authority and the record.” And an appellee brief must respond in
    substance to the issues presented in the appellant’s brief. Brown v.
    Glover, 
    2000 UT 89
    , ¶ 22, 
    16 P.3d 540
    .
    ¶44 There is no “bright-line rule determining when a brief is
    inadequate.” Bank of Am. v. Adamson, 
    2017 UT 2
    , ¶ 12, 
    391 P.3d 196
    . And the “ultimate question” is not “whether there is a
    technical deficiency in [briefing] meriting a default.”
    Id. (alteration in original)
    (quoting State v. Nielsen, 
    2014 UT 10
    , ¶ 41, 
    326 P.3d 645
    ). “While this court will not lightly toss aside partially briefed
    but still discernable arguments, we are limited by the practical
    considerations that an unbriefed argument presents.” Heslop v.
    Bear River Mut. Ins. Co., 
    2017 UT 5
    , ¶ 50, 
    390 P.3d 314
    .
    ¶45 An appellant bears the burden of persuasion on appeal.
    Broderick, 
    2012 UT 17
    , ¶ 19. But a court may rule in favor of an
    appellant for purposes of that case if the appellee inadequately
    briefs an argument and the appellant provides a plausible basis
    for reversal. See
    id. ¶46 UDOT contests
    the court of appeals’ characterization of
    its briefing as inadequate. UDOT points out that Coalt relies on
    the same premises for both its authority and valuation arguments,
    13
    UDOT v. COALT
    Opinion of the Court
    and it asserts that it directly attacked those premises throughout
    its briefing in the court of appeals. We agree.6 However, we note
    that UDOT refuted Coalt’s assertions primarily in the authority
    context and devoted only one paragraph to valuation.
    ¶47 UDOT identifies this one paragraph as the point at which
    it addressed valuation before the court of appeals. While the
    paragraph does not use the word “valuation,” we agree that it
    does cite the district court’s findings and conclusions involving
    the issue. And UDOT does defend the district court’s ruling in its
    favor, however briefly. But UDOT should have more explicitly
    addressed valuation, where Coalt raised it as a stand-alone claim.
    ¶48 Overall, we agree with the court of appeals that UDOT’s
    briefing of the valuation issue was scant. But while this is a close
    call, we ultimately conclude that the adequacy of UDOT’s briefing
    is not dispositive. Because Coalt’s authority and valuation
    arguments rest on the same assertions, which UDOT has
    addressed, this is not a situation in which we have insufficient
    information to make a ruling. Nor must we bear the parties’
    burden of research.
    ¶49 Ultimately, we conclude that Coalt has not presented a
    plausible basis for reversal. Coalt’s valuation argument relies on
    the same foundational presumptions that we rejected in the
    authority context. See supra ¶¶ 25–39. We cannot reject these
    assertions on one hand but find them plausible on the other.
    6   Coalt’s brief states,
    The thrust of Coalt’s valuation argument [in the
    court of appeals] was that its property was not part
    of the Legacy project. Coalt relied upon its arguments
    concerning UDOT’s statutory and constitutional
    authority, as well as UDOT’s statements in the
    settlement documents, to demonstrate that the trial
    court’s decision that Coalt’s land was “within the
    scope of the Legacy Parkway Project” was
    erroneous. . . . Instead, it condemned the property to
    settle litigation and for mitigation of unspecified future
    projects unrelated to Legacy Parkway.
    (Emphases added.) This foundation underlies both Coalt’s
    authority and valuation arguments.
    14
    Cite as: 
    2020 UT 58
                          Opinion of the Court
    Accordingly, we conclude that Coalt has not provided a plausible
    basis for reversal and reverse the court of appeals on this issue.
    CONCLUSION
    ¶50 UDOT condemned Parcel 84 as mitigation for the Legacy
    Parkway Project, which is a public state transportation purpose. It
    had authority to do so under the Rights-of-Way Act and the Utah
    Constitution. Accordingly, we affirm the court of appeals with
    regard to UDOT’s condemnation authority.
    ¶51 With regard to the valuation of Parcel 84, we conclude
    that Coalt has not provided a plausible basis for reversal of the
    district court. Accordingly, we reverse the court of appeals and
    reinstate the judgment of the district court.
    15