Utah Dep't of Transp. v. Target Corp. , 414 P.3d 1080 ( 2018 )


Menu:
  •                         
    2018 UT App 24
    THE UTAH COURT OF APPEALS
    UTAH DEPARTMENT OF TRANSPORTATION,
    Appellant,
    v.
    TARGET CORPORATION AND
    WEINGARTEN/MILLER/AMERICAN FORK LLC,
    Appellees.
    Opinion
    No. 20160122-CA
    Filed February 8, 2018
    Fourth District Court, American Fork Department
    The Honorable Thomas Low
    No. 090102037
    Sean D. Reyes, Barbara E. Ochoa, William H.
    Christensen, and Stanford E. Purser, Attorneys for
    Appellant
    Kevin E. Anderson and Jason E. Wilkinson,
    Attorneys for Appellee Target Corporation
    Jeffrey W. Appel, Matthew N. Evans, and Robert P.
    Harrington, Attorneys for Appellee
    Weingarten/Miller/American Fork LLC
    JUDGE RYAN M. HARRIS authored this Opinion, in which JUDGES
    KATE A. TOOMEY and JILL M. POHLMAN concurred.
    HARRIS, Judge:
    ¶1      One extremely small portion of a massive freeway
    interchange was built on land that the Utah Department of
    Transportation (UDOT) took from claimants Target Corporation
    (Target) and Weingarten/Miller/American Fork LLC (Miller)
    (collectively, Claimants). The vast majority of the interchange
    was constructed upon UDOT’s own land or upon land taken
    from others. Claimants complain that the interchange prevents
    UDOT v. Target Corporation
    or impairs motorists from viewing their shopping center, and
    they claim the right to recover severance damages from UDOT
    related to this loss of visibility and related to the loss of a right-
    out exit 1 from the shopping center’s parking lot. The trial court
    allowed that claim to proceed to a jury trial, and a jury awarded
    Claimants more than $2.3 million in severance damages.
    ¶2     UDOT now appeals, and asserts that the trial court erred
    in even allowing Claimants’ suit for severance damages to reach
    the jury. UDOT asserts that Claimants’ evidence was insufficient,
    regarding both causation and damages, to support their claims.
    For the reasons discussed below, we find UDOT’s arguments
    unpersuasive, and therefore affirm.
    BACKGROUND 2
    ¶3    In 2009, UDOT determined that two major highway
    construction projects (the Projects) needed to be built in fast-
    growing Utah County. One project involved widening and
    reconstructing Interstate 15 through essentially the entire length
    of Utah County, from Santaquin to the Salt Lake County line.
    This project, in total, was more than twenty-two miles long. The
    other project involved the construction of a new east-west
    1. A “right-out exit” allows traffic to exit (but not necessarily
    enter) a facility, but only by turning right.
    2. Our recitation of the facts is presented in the light most
    favorable to the jury’s verdict, and comes from the testimony
    and evidence developed at trial. See Smith v. Fairfax Realty, Inc.,
    
    2003 UT 41
    , ¶ 3, 
    82 P.3d 1064
     (on review from the denial of a
    motion for a directed verdict, an appellate court recites facts in
    the light most favorable to the verdict). During the trial, the jury
    heard testimony from several witnesses, including five
    engineers, two expert appraisers, and a representative of Target
    with experience in shopping center development.
    20160122-CA                      2                 
    2018 UT App 24
    UDOT v. Target Corporation
    arterial road from American Fork through Lehi to Saratoga
    Springs. This project, in total, was seven miles long. The two
    Projects intersect at a point in American Fork where Main Street
    crosses I-15. Before the Projects, there was already a freeway
    interchange at the site, allowing motorists to cross I-15 on Main
    Street via an overpass, or get on or off I-15 at that same location.
    The Projects called for the widening of both I-15 and American
    Fork Main Street, and therefore UDOT found it necessary to
    completely rebuild the existing freeway interchange (the
    Interchange).
    ¶4      In order to facilitate construction of the new Interchange
    at that location, UDOT condemned various properties, including
    three relatively small portions 3 of the Alpine Valley Shopping
    Center (the Shopping Center), a mall owned largely by
    Claimants that is located on the northeast corner of the
    Interchange. The Shopping Center is a large retail facility with
    many stores and shops. It has one major “anchor” tenant—
    Target—as well as other smaller retail stores, and includes a
    large outdoor parking lot. Claimants’ witnesses testified at trial
    that the Shopping Center is designed to draw customers from a
    large regional area, and that customers are drawn there due to
    “ease of access and convenience, and knowing how to get there
    by visibility or good signage.” Target owns the land on which its
    store is located, and Miller owns most of the Shopping Center’s
    remaining land. Both Target and Miller share a parking lot, and
    also share a cross-easement across the entirety of the Shopping
    Center. The shared parking lot abuts Main Street, and prior to
    completion of the Projects a driver could easily access
    northbound I-15 by making a right-hand turn out of the south
    side of the parking lot, driving briefly westbound along Main
    3. Two of these three parcels were taken in fee simple, and the
    third was taken in the form of a perpetual slope easement. The
    two parcels taken in fee simple were very small (756 and 928
    square feet, respectively). The slope easement is larger,
    comprising 8,825 square feet.
    20160122-CA                     3                 
    2018 UT App 24
    UDOT v. Target Corporation
    Street, and then merging onto northbound I-15. The original
    northbound I-15 on-ramp was “at grade”—on the same level—
    with Main Street.
    ¶5     UDOT chose to rebuild the Interchange using an
    innovative “diverging diamond” design, which is “a very
    unique cross-over type interchange” that involves cars
    temporarily driving on the left side of the road. Significantly for
    present purposes, a diverging diamond design requires a lot of
    space, and in this case that design required that the bridge over
    the freeway be built higher than other design options, and also
    required much larger and higher on- and off-ramps. To take one
    specific example, the northbound I-15 on-ramp was raised from
    “at grade” (in the before condition) to a height of some twenty-
    three feet (in the after condition). The new Interchange’s increase
    in height affected Claimants’ property and the surrounding area
    in several ways.
    ¶6     First, the heightened overpass and raised northbound I-15
    on-ramp required UDOT to gradually raise the elevation of Main
    Street as it approached the Interchange. Because Main Street
    itself was being raised, UDOT determined that, “for safety
    reasons,” it could no longer permit right-out access from the
    south end of the Shopping Center onto the now-heightened
    Main Street, although UDOT was able to preserve right-in access
    from westbound Main Street into the parking lot. In connection
    with closing this right-out exit, UDOT took from Claimants one
    small rectangular parcel located on the south side of the shared
    parking lot, along Main Street. UDOT did not build any portion
    of the Interchange on this parcel. Prior to the taking, the right-
    out exit was the most heavily used exit in the parking lot, due to
    its proximity to the northbound I-15 on-ramp. After the taking,
    the closure of the right-out exit required all traffic exiting the
    parking lot to use an intersection located along the east side of
    the Shopping Center, along Kawakami Drive.
    ¶7    Next, to facilitate construction of the heightened
    northbound I-15 on-ramp, UDOT built a retaining wall along the
    20160122-CA                     4                
    2018 UT App 24
    UDOT v. Target Corporation
    northbound on-ramp. In order to support the retaining wall,
    UDOT found it necessary to construct an earthen slope alongside
    the retaining wall. UDOT did not, however, have enough space
    on its own property for the entire dirt support slope, so UDOT
    took a perpetual “slope easement” across a long, narrow parcel
    of Claimants’ land that runs alongside the northbound I-15 on-
    ramp. UDOT then placed a large amount of dirt on the slope
    easement, creating a slope that supported the retaining wall that,
    in turn, supported the raised on-ramp onto northbound I-15.
    While the retaining wall itself is not located on the slope
    easement, the dirt slope supporting the retaining wall is at least
    partially located on the slope easement. 4
    ¶8      At trial, Target’s representative testified that UDOT
    informed him that “it was not feasible to maintain the right-out
    [exit] due to the new construction, the design, specifically, of this
    diverging diamond.” However, no other witness at trial testified
    that the condemnation of Claimants’ specific parcels was
    “essential to the completion of the project as a whole.” See Ivers
    v. Utah Dep’t of Transp., 
    2007 UT 19
    , ¶ 21, 
    154 P.3d 802
    , overruled
    in part on other grounds by Utah Dep’t of Transp. v. Admiral Beverage
    Corp., 
    2011 UT 62
    , 
    275 P.3d 208
     (holding that a claimant is
    4. UDOT correctly points out that Claimants introduced no
    exhibit or testimony demonstrating exactly where the
    boundaries for the slope easement were located, or
    demonstrating exactly how much of the dirt slope ended up
    being located on the slope easement. But it is clear from the trial
    testimony that at least some of the dirt slope supporting the
    northbound I-15 on-ramp is located on the slope easement, and
    therefore is located on property owned by Claimants. In
    addition, during oral argument, UDOT’s counsel acknowledged
    that UDOT placed the dirt slope at least partially on Claimants’
    property. Moreover, one of the jury instructions proposed by
    UDOT and submitted to the jury stated that UDOT acquired the
    slope easement “for the purpose of constructing and maintaining
    slopes on the property as part of the Project[s].”
    20160122-CA                      5                 
    2018 UT App 24
    UDOT v. Target Corporation
    entitled to severance damages related to a view-impairing
    structure “built on property other than that which was
    condemned” only “if the use of the condemned property is
    essential to the completion of the project as a whole”).
    ¶9      Claimants also presented evidence that completion of the
    Interchange affected the visibility—defined as the ability of
    others to view into the property, see 
    id. ¶ 12
    —of the Shopping
    Center. Prior to the Projects, motorists moving in any direction
    on I-15 or Main Street could easily see the Shopping Center as
    they were driving. After the Projects, by contrast, visibility into
    the Shopping Center decreased, chiefly because of the larger and
    taller Interchange. Parts of the Interchange, including the taller
    and wider bridge over the freeway, as well as new or taller
    retaining walls and raised on- and off-ramps, now impair
    motorists’ view of the Shopping Center. Claimants argued that
    they were entitled to be compensated not just for the value of the
    parcels that were taken, but also for “severance damages”
    representing the full loss of the market value of the Shopping
    Center caused by the taking, including diminution in value
    caused by reduced visibility and access.
    ¶10 In support of this contention, Claimants presented
    testimony from an expert appraiser (Appraiser). Appraiser
    valued Claimants’ remaining property twice, once in the
    “before” condition, as though the Interchange had never been
    built, and once in the “after” condition, taking into account any
    effect that the Interchange had on the property’s value.
    Appraiser explained that the difference in these values
    constituted the measure of Claimants’ severance damages.
    Appraiser concluded that Claimants’ remaining property was
    worth approximately 7.5% less in the “after” condition than in
    the “before” condition, and he calculated Claimants’ severance
    damages, based on that conclusion, as more than $2.3 million.
    Appraiser testified that there were two main factors that
    contributed to the property’s diminution in value: loss of
    visibility, largely because of the presence of the larger and taller
    Interchange, and loss of the right-out exit onto Main Street.
    20160122-CA                     6                 
    2018 UT App 24
    UDOT v. Target Corporation
    However, Appraiser did not attempt to provide any specific
    values for these individual components of loss—that is,
    Appraiser did not provide the jury with any specific amounts for
    damages related to loss of the right-out exit alone, or for
    damages related to loss of visibility alone, or for damages related
    to loss of visibility related to any specific component of the
    Interchange. At the close of Claimants’ case, UDOT moved for a
    partial directed verdict on the issue of severance damages,
    arguing that Claimants should not be allowed to recover
    severance damages at all. Specifically, UDOT argued that
    Claimants failed to “elicit[] any testimony from any witness that
    this property was essential to the project as a whole,” and
    therefore their claim for severance damages was infirm under
    the rubric set forth in Ivers, 
    2007 UT 19
    , ¶ 21. The trial court
    denied UDOT’s motion, reasoning that although no witness
    explicitly testified that UDOT’s takings were “essential to the
    project as a whole,” the evidence was nonetheless sufficient to
    potentially support a finding that the takings were “essential.”
    ¶11 After deliberation, the jury awarded Claimants a total of
    $87,910 for the value of the property interests that UDOT
    actually took (the two small parcels taken in fee simple plus the
    perpetual slope easement). In addition, the jury awarded
    Claimants a combined $2,381,294 in severance damages. UDOT
    takes issue with the severance damages portion of the jury’s
    verdict, and first expressed its displeasure with this award by
    asking the trial court to enter a judgment notwithstanding the
    verdict, again asserting that Claimants “failed to establish
    through testimony of any fact or expert witness that the property
    taken by [UDOT] was ‘essential to the completion of the project
    as a whole.’” The trial court denied that motion.
    ISSUES AND STANDARD OF REVIEW
    ¶12 UDOT now appeals the award of severance damages to
    Claimants, and asserts that the trial court should have granted
    its motions for partial directed verdict and/or for judgment
    20160122-CA                     7                
    2018 UT App 24
    UDOT v. Target Corporation
    notwithstanding the verdict on that issue. We review a trial
    court’s denial of a motion for directed verdict for correctness.
    Proctor v. Costco Wholesale Corp., 
    2013 UT App 226
    , ¶ 6, 
    311 P.3d 564
    . Likewise, we review for correctness a trial court’s denial of a
    motion for judgment notwithstanding the verdict. Neff v. Neff,
    
    2011 UT 6
    , ¶ 49, 
    247 P.3d 380
    . On either a motion for directed
    verdict or a motion for judgment notwithstanding the verdict,
    we will reverse the trial court’s ruling “only if, viewing the
    evidence in the light most favorable to the prevailing party, we
    conclude that the evidence is insufficient to support the verdict.”
    Lawrence v. MountainStar Healthcare, 
    2014 UT App 40
    , ¶ 18, 
    320 P.3d 1037
     (citation and internal quotation marks omitted).
    ANALYSIS
    ¶13 It is a bedrock principle of both the federal and state
    constitutions that the government cannot take a citizen’s
    property for public use without paying that citizen “just
    compensation” for the value of the property taken. See U.S.
    Const. amend. V; see also Utah Const. art. I, § 22. “The policy
    behind Utah’s constitutional provision is to ensure that the
    burden for damage done to private property is ‘distributed
    among all the taxpayers’ rather than ‘upon those only who
    sustained the injury.’” See Utah Dep’t of Transp. v. Admiral
    Beverage Corp., 
    2011 UT 62
    , ¶ 21, 
    275 P.3d 208
     (quoting Kimball v.
    Salt Lake City, 
    90 P. 395
    , 397 (Utah 1907)). The constitutional
    guarantee of “just compensation” “is triggered when there is any
    substantial interference with private property which destroys or
    materially lessens its value, or by which the owner’s right to its
    use and enjoyment is in any substantial degree abridged or
    destroyed.” 
    Id. ¶ 22
     (citation and internal quotation marks
    omitted). There exist “two broad categories of takings”: physical
    takings and regulatory takings. Alpine Homes, Inc. v. City of West
    Jordan, 
    2017 UT 45
    , ¶ 18. This case involves a physical taking.
    ¶14 A physical taking is the most obvious kind of taking, and
    occurs when the government physically appropriates a citizen’s
    20160122-CA                     8                 
    2018 UT App 24
    UDOT v. Target Corporation
    property. See View Condo. Owners Ass’n v. MSICO, LLC, 
    2005 UT 91
    , ¶ 31, 
    127 P.3d 697
    . Certainly, a landowner is entitled to
    compensation when the government undertakes a “physical
    invasion or permanent occupation of his or her property.”
    America West Bank Members, LC v. State, 
    2014 UT 49
    , ¶ 32, 
    342 P.3d 224
     (citation and internal quotation marks omitted). There
    are several different types of physical takings, including, for
    instance, an outright fee-simple taking as well as the taking of a
    more limited property interest such as an easement. See Utah
    Code Ann. § 78B-6-502 (LexisNexis 2012) (providing that “fee
    simple” ownership and “easement[s]” are both “rights in lands
    [that] are subject to being taken for public use”). In this case, the
    jury determined that Claimants were entitled to $87,910 as “just
    compensation” for UDOT’s three physical takings. No party has
    appealed that portion of the jury’s decision.
    ¶15 When the land that is condemned constitutes only a
    portion of a larger parcel, a landowner may be entitled to more
    than merely the market value of the portion of the land that is
    actually taken. Specifically, the landowner may be entitled to
    “severance damages” for any diminution in the value of the
    remaining portion of the landowner’s property, as long as the
    landowner can demonstrate that the diminution in value was
    caused by the taking. See id. § 78B-6-511(2) (LexisNexis 2012)
    (stating that, “if the property sought to be condemned
    constitutes only a part of a larger parcel,” a landowner may
    recover “the damage[] which will accrue to the portion not
    sought to be condemned by reason of its severance from the
    portion sought to be condemned”); see also Severance Damages,
    Black’s Law Dictionary (10th ed. 2014) (defining “severance
    damages” as “compensation awarded to a landowner for the loss
    in value of the tract that remains after a partial taking of the
    land”).
    ¶16 The “cardinal and well-recognized rule” regarding the
    measure of severance damages is that a landowner is entitled to
    recover “the difference in market value of the property before
    and after the taking.” See Admiral Beverage, 
    2011 UT 62
    , ¶ 30
    20160122-CA                      9                 
    2018 UT App 24
    UDOT v. Target Corporation
    (citation and internal quotation marks omitted); see also 
    id. ¶ 31
    (stating that a court, “in order to correctly evaluate . . . severance
    damages,” must view those damages “in the composite as it will
    be after the taking and after the improvement has been
    constructed”). After a four-year detour to the contrary, our
    supreme court has now determined that severance damages may
    include damages resulting from the property’s reduced visibility.
    See 
    id. ¶¶ 15
    –19 (overruling Ivers, 
    2007 UT 19
    , ¶¶ 11–15, and
    stating that “when a landowner suffers the physical taking of a
    portion of his land, he is entitled to severance damages
    amounting to the full loss of market value in his remaining
    property caused by the taking,” including damages for loss of
    visibility). A landowner bears the burden of proving an
    entitlement to a specific amount of severance damages. State ex
    rel. Road Comm’n v. Williams, 
    452 P.2d 548
    , 549–50 (Utah 1969).
    ¶17 An entitlement to severance damages exists, however,
    only if landowners can show a causal link between the taking of
    a portion of their land and the diminution in the value of the
    remainder. See Ivers, 
    2007 UT 19
    , ¶ 18 (stating that “[w]hether
    severance damages are awardable hinges on whether the
    severance of the condemned property, and the use of that
    property, caused damage to the remaining property”); see also
    Utah Dep’t of Transp. v. D’Ambrosio, 
    743 P.2d 1220
    , 1222 (Utah
    1987) (stating that a landowner is entitled to recover severance
    damages “caused by the taking of a portion of the parcel of
    property where the taking or the construction of the
    improvement on that part causes injury to that portion of the
    parcel not taken”); Utah Code Ann. § 78B-6-511(2) (providing
    that recoverable severance damages consist of those damages
    incurred “by reason of [the remaining parcel’s] severance from
    the portion sought to be condemned”).
    ¶18 In this case, Claimants assert entitlement to two types of
    severance damages. First, Claimants maintain that their
    remaining property has diminished in value due to loss of
    visibility that they claim has resulted from the construction of
    the new Interchange. Second, Claimants assert that their
    20160122-CA                      10                
    2018 UT App 24
    UDOT v. Target Corporation
    remaining property has diminished in value because of the loss
    of the right-out exit onto American Fork Main Street. For its part,
    UDOT asserts that Claimants have not presented sufficient
    evidence to support their claim to either type of severance
    damages, but for different reasons.
    A.     Severance Damages for Loss of Visibility
    ¶19 With regard to Claimants’ assertion that they are entitled
    to severance damages for loss of visibility, UDOT maintains that
    Claimants have not presented sufficient evidence of the
    necessary causal link between the taking of their property and
    their claimed severance damages.
    ¶20 There are two methods by which a landowner can
    demonstrate the requisite causal link. First, if the visibility issues
    stem from a “structure” that is built upon the part of the
    property that was taken, causation is presumed. See Ivers, 
    2007 UT 19
    , ¶ 20 (stating that “when the state condemns a portion of
    land and builds a view-impairing structure directly on that land,
    the damage to the remaining property is recoverable . . . because
    when the condemned land is used for the construction of the
    view-impairing structure, the damage to the remaining property
    is clearly caused by the severance”). Second, if the visibility
    issues stem from a “structure” that was not built on the part of
    the property that was taken, causation is not presumed, and the
    property owner is entitled to severance damages only if it can
    demonstrate that “the use of the condemned property is
    essential to the completion of the project as a whole.” 
    Id. ¶ 21
    .
    ¶21 The main thrust of UDOT’s arguments, both before the
    trial court and on appeal, is that Claimants have not established,
    through competent evidence, that their parcels were “essential”
    to the Projects as a whole, and therefore cannot avail themselves
    of the second method of proving severance damages. As noted
    above, none of Claimants’ witnesses directly testified that the
    taken parcels were “essential” to the Projects as a whole.
    20160122-CA                      11                
    2018 UT App 24
    UDOT v. Target Corporation
    ¶22 Claimants, however, maintain that they can demonstrate
    causation through the first method, and that they therefore need
    not prove that the taken parcels were “essential to the Projects as
    a whole.” Specifically, Claimants assert that the view-impairing
    structure is the entire Interchange, and they argue from that
    premise that, because part of the Interchange (the dirt slope
    supporting the retaining wall on the northbound I-15 on-ramp)
    was built on their property, causation for severance damages
    should be presumed. UDOT disagrees, and posits that the view-
    impairing “structure” is not the entire Interchange but, instead,
    the specific component parts of the Interchange (such as the
    raised freeway overpass, or new retaining walls on the southern
    end of the Interchange), only one of which (the northbound I-15
    on-ramp) was even partially built on Claimants’ taken property.
    In order to address these arguments, we must confront three
    questions.
    1.
    ¶23 First, we must determine whether, as a legal matter, a
    view-impairing structure that is only partially constructed upon
    the taken parcel is presumed to have caused severance damages
    to the remaining parcel or, instead, whether the view-impairing
    structure must be constructed entirely upon the taken parcel to
    qualify for a presumption of causation. We conclude that, in
    order to be presumed to have caused severance damages to the
    remaining parcel, a view-impairing structure need not be
    entirely constructed within the taken parcel.
    ¶24 We draw support for this conclusion from Utah State Road
    Commission v. Miya, 
    526 P.2d 926
     (Utah 1974). In that case, the
    state condemned, for a road construction project, one small part
    (comprising less than one acre) of a forty-four-acre parcel owned
    by the claimant. 
    Id. at 927
    . As part of that project, the state then
    constructed a “viaduct” over some adjacent railroad tracks. 
    Id. at 928
    . While it is not entirely clear from the opinion, it appears that
    20160122-CA                        12              
    2018 UT App 24
    UDOT v. Target Corporation
    the viaduct was at least partially constructed upon the land
    taken from the claimant. 5 
    Id.
     The claimant asserted a right to
    recover severance damages related to the loss of view on its
    remaining acreage caused by the construction of the viaduct. 
    Id. at 929
    . The trial court awarded claimant $8,000 in severance
    damages, and our supreme court affirmed, holding that “the loss
    of view occasioned by a proposed public structure to be erected,
    in part at least upon a parcel of property taken by condemnation
    from a unit of property” could be compensated with an award of
    severance damages. 
    Id.
     (emphasis added) (citations omitted).
    ¶25 Indeed, we cited this portion of Miya when we considered
    the Ivers case. See Utah Dep’t of Transp. v. Ivers, 
    2005 UT App 519
    ,
    ¶ 23 & n.6, 
    128 P.3d 74
    , rev’d in part on other grounds, 
    2007 UT 19
    ,
    
    154 P.3d 802
    . In so doing, we noted that the rule set forth in
    Miya—“requiring the view-obstructing improvement to be
    constructed, at least partially, upon the land severed from the
    condemnee”—is in keeping “with the principles recognized in
    both earlier and later Utah cases.” 
    Id.
     (emphasis added). While
    our supreme court has not directly addressed this issue since
    Miya, that court’s opinions in Ivers and Admiral Beverage contain
    language indicating continued support of the rule set forth in
    Miya. See Admiral Beverage, 
    2011 UT 62
    , ¶ 2 (noting that “[n]o part
    of the I-15 freeway itself is located on or touches Admiral’s
    5. This court has read Miya in this manner once before. In this
    court’s decision in Utah Department of Transportation v. Ivers, 
    2005 UT App 519
    , 
    128 P.3d 74
    , rev’d in part on other grounds, 
    2007 UT 19
    , 
    154 P.3d 802
    , we noted some uncertainty about whether the
    viaduct in the Miya case was partially constructed on the taken
    property, but concluded that Miya could not plausibly be read
    any other way. 
    Id. ¶ 23 & n.6
     (stating that, “[i]n Miya, the viaduct
    was constructed, in part, on the land taken from the
    landowners,” and noting in a footnote that the court’s “reliance
    on” a particular quotation “indicates that the viaduct was built,
    at least in part, upon a parcel of property taken from the
    landowners”).
    20160122-CA                     13                
    2018 UT App 24
    UDOT v. Target Corporation
    property” (emphasis added)); Ivers, 
    2007 UT 19
    , ¶ 3 (noting in
    support of its rejection of claimant’s severance damages claim
    that “[n]o portion of the raised highway, its footings, or its
    foundation was constructed on the condemned land” (emphasis
    added)).
    ¶26 Further support for our conclusion can be found in case
    law from other jurisdictions that, like ours, allow recovery of
    severance damages for loss of visibility. 6 At least some of those
    courts have held that such damages are recoverable even where
    the view-impairing structure is built only partially on the taken
    property. See, e.g., State v. Strom, 
    493 N.W.2d 554
    , 561 (Minn.
    1992) (holding that where “property taken by the state from the
    abutting owner was used” to build a view-obstructing structure,
    the landowner may recover severance damages for loss of
    visibility); 
    id. at 564
     (Simonett, J., concurring) (noting specifically
    that “the embankment [that obstructs visibility] is partially on
    land taken” from the landowner (emphasis added)).
    ¶27 We also note that UDOT appeared to concede this point at
    oral argument. In response to questioning from the court, UDOT
    conceded that Claimants would, at least theoretically, be entitled
    to severance damages for loss of visibility caused solely by the
    northbound I-15 on-ramp, because UDOT conceded that the on-
    ramp (although not necessarily the Interchange) was at least
    partially constructed on property taken from Claimants. 7 As
    6. Some jurisdictions (including our own from 2007 to 2011, see
    Ivers, 
    2007 UT 19
    , ¶¶ 11–15) do not allow any recovery of
    severance damages for loss of visibility. See, e.g., Department of
    Transp. v. Marilyn Hickey Ministries, 
    159 P.3d 111
    , 116 (Colo.
    2007); see also 7A Nichols on Eminent Domain, § G9A.04[4][c][iii]
    (Matthew Bender, 3rd ed.).
    7. UDOT’s concession here was limited because, as discussed
    below, UDOT points out that Claimants presented to the jury
    only a total composite figure comprising all of its claimed
    (continued…)
    20160122-CA                      14                 
    2018 UT App 24
    UDOT v. Target Corporation
    noted elsewhere herein, the only part of the northbound on-
    ramp (for that matter, the only part of the entire Interchange)
    that was constructed on Claimants’ property is part of the slope
    supporting the on-ramp’s retaining wall. By conceding a
    theoretical entitlement to severance damages for loss of visibility
    caused by the northbound on-ramp, UDOT was necessarily
    conceding the point that a structure, in order to be considered to
    have presumptively caused severance damages, does not have to
    be entirely constructed on land taken from the claimant.
    2.
    ¶28 Second, we must determine what the “structure” is for
    purposes of the causation analysis. There are three possibilities.
    First, “structure” could be defined extremely broadly, to mean
    the entirety of the freeway Projects in question. Neither party
    advocates for this position, and we conclude that this position is
    foreclosed by applicable case law. Second, the “structure” in
    question could be the Interchange, in its entirety. Claimants
    advocate for this position. Third, the “structure” in question
    could be the individual component parts of the Interchange that
    are alleged to have affected Claimants’ visibility. UDOT
    advocates for this position. We find Claimants’ position most
    persuasive.
    ¶29 The “structure” in question cannot be the entirety of the
    Projects. This possibility has already been rejected by our
    (…continued)
    severance damages, and did not endeavor to itemize or
    individually value each part of their claimed severance damages
    (such as, for instance, loss of visibility solely due to the presence
    of the northbound on-ramp). UDOT therefore takes the position
    that, even though Claimants would be theoretically entitled to
    recover severance damages for loss of visibility caused by the
    northbound I-15 on-ramp, Claimants’ specific evidence for this
    item of severance damages was insufficient.
    20160122-CA                        15              
    2018 UT App 24
    UDOT v. Target Corporation
    supreme court. In State v. Harvey Real Estate, 
    2002 UT 107
    , 
    57 P.3d 1088
    , the court stated that severance damages were available for
    “damages caused by the construction of the improvement made
    on the severed property,” and emphasized that severance
    damages cannot include “damages caused by other facets of the
    construction project.” 
    Id. ¶ 10
    ; see also 
    id.
     (noting that the court
    would not allow a landowner to “present evidence of all
    damages conceivably stemming from” a “multi-mile-length road
    construction project,” and certainly not “those damages
    attributable to construction occurring miles away”). Likewise, in
    Ivers, the court refused to allow an award of severance damages
    caused by the loss of view resulting from the construction of a
    raised highway, when the land taken from the claimant was
    used only for construction of a small portion of a frontage road
    that, while inarguably part of the same overall construction
    project, was itself separate from the raised highway. See Ivers,
    
    2007 UT 19
    , ¶¶ 1, 17 (stating that the claimant’s land “was
    condemned as part of a single project to build a structure that
    would impair the view from the remaining property, but in
    which that structure was not built on the severed land”). Thus,
    the “structure” in question must be defined more narrowly than
    by reference to the entire multi-mile Projects constructed here.
    ¶30 While reference to the entirety of the two multi-mile
    Projects is far too broad, we perceive UDOT’s position as too
    narrow. UDOT asserts that the “structure” in question is not the
    Interchange in its entirety but, rather, its specific individual
    components—for instance, the raised overpass, the raised
    northbound on-ramp, new retaining walls and sound walls—
    that Claimants assert impair the Shopping Center’s visibility.
    UDOT concedes that at least a portion of the northbound on-
    ramp was built on Claimants’ property, and therefore makes at
    least a theoretical concession that Claimants would be entitled to
    severance damages resulting from loss of visibility caused
    directly by the presence of the new northbound on-ramp. But
    UDOT maintains that it should not have to pay severance
    damages for loss of visibility caused by any other component
    20160122-CA                     16                
    2018 UT App 24
    UDOT v. Target Corporation
    part of the Interchange, because none of the other parts of the
    Interchange were even partially constructed on Claimants’ land.
    ¶31 We disagree, because we view the Interchange as one
    interconnected structure. Each part of the Interchange has some
    effect on the others, all stemming from UDOT’s choice of a
    “diverging diamond” design. That design choice required a
    raised and widened freeway overpass, as well as raised on- and
    off-ramps. The raised on- and off-ramps, in turn, required new
    and higher retaining walls and slope supports. It seems to us
    unduly artificial to require a condemnation claimant to break a
    freeway interchange into component parts for the purpose of
    proving a claim to severance damages. 8 We also wonder
    whether we could, on any principled basis, halt the sub-dividing
    process once it begins. 9
    8. If the structure in question were a building instead of a
    freeway interchange, the analysis would be clearer. It would
    make little sense to say that a claimant could recover severance
    damages for loss of visibility occasioned by a single part or
    feature of a building (say, a wing of the building, or an awning,
    column, or steeple) but could not recover severance damages for
    loss of visibility occasioned by other parts of that same building.
    While we concede that a building is perhaps more clearly one
    contiguous “thing” than a freeway interchange is, we cannot
    conceive of any principled basis upon which to distinguish the
    two scenarios.
    9. As noted, UDOT conceded that Claimants have at least a
    theoretical entitlement to severance damages caused by loss of
    visibility related to the northbound on-ramp. But absent that
    concession, UDOT could potentially have argued that only the
    dirt slope support was actually constructed on Claimants’
    property, while the actual retaining wall and the rest of the on-
    ramp were not. If we permit UDOT to subdivide the Interchange
    down into its component parts (e.g., bridges and on-ramps), we
    (continued…)
    20160122-CA                    17                
    2018 UT App 24
    UDOT v. Target Corporation
    ¶32 We are also guided by our supreme court’s language in
    Ivers and Admiral Beverage. In those cases, it appears that the
    court thought of the “structure” in broader terms than UDOT
    now advocates. For instance, in Ivers and Admiral Beverage, the
    court referred to the structure in question as simply “the raised
    highway” or “the I-15 freeway,” rather than to individual on-
    ramps or retaining walls. See Ivers, 
    2007 UT 19
    , ¶¶ 1, 3; Admiral
    Beverage, 
    2011 UT 62
    , ¶ 2.
    ¶33 Moreover, in Admiral Beverage, the supreme court
    overruled its own previous holding, outlined in Ivers, that loss of
    visibility damages were not recoverable as part of severance
    damages. See Admiral Beverage, 
    2011 UT 62
    , ¶¶ 17–19. The court
    did so, in part, because it deemed the Ivers rule “unworkable in
    practice” because of the difficulty encountered by appraisers
    who were asked, under the Ivers rule, to “assign specific values”
    to loss of visibility damages as part of an overall severance
    damages analysis. 
    Id. ¶ 39
    ; see also 
    id. ¶ 41
     (noting that the Ivers
    rule required appraisers to “resort to rank speculation when
    attempting to exclude the loss of visibility from fair market
    value”). The court applied a holistic approach to severance
    damages, determining that such damages are computed by
    simply “comparing the market value of the portion of property
    not taken with its market value before the taking.” 
    Id. ¶ 30
    ; see
    also City of Hildale v. Cooke, 
    2001 UT 56
    , ¶ 20, 
    28 P.3d 697
     (noting
    the “cardinal and well-recognized rule” that severance damages
    consist of “the difference in market value of the property before
    and after the taking” (citation and internal quotation marks
    omitted)). It would be inconsistent with this overall approach to
    require Claimants’ appraisers to engage in a similarly
    speculative effort to isolate the severance damages caused by
    (…continued)
    are aware of no principle that would prevent condemnors from
    subdividing each component part into its own respective sub-
    parts (e.g., retaining walls, slope supports).
    20160122-CA                     18                
    2018 UT App 24
    UDOT v. Target Corporation
    one component part of a freeway interchange separate from
    those severance damages caused by another.
    ¶34 Accordingly, we view the “structure” in question as the
    Interchange, rather than as the Projects or as the Interchange’s
    individual component parts.
    3.
    ¶35 Finally, after answering the first two questions, we must
    determine whether, as a factual matter, the structure (as we have
    defined it) was at least partially constructed upon the taken
    parcel. It should be evident by now that it was.
    ¶36 As described above, one extremely small part (the slope
    supporting a retaining wall that is part of the northbound I-15
    on-ramp) of the Interchange was built on land taken from
    Claimants. Under these circumstances, Claimants are entitled to
    recover severance damages caused by loss of visibility resulting
    from construction of the entire Interchange. 10 The structure in
    10. We are aware that, in some cases, it may be difficult to
    determine where an “interchange” begins and ends. In this case,
    however, as far as we are aware, all of the items that were
    described as part of the cause of Claimants’ severance damages
    for loss of visibility (e.g., the raised freeway overpass, the
    northbound I-15 on-ramp, the new retaining walls) are
    unquestionably part of the Interchange. However, we note that,
    at oral argument and at one point in its reply brief, UDOT made
    some mention of “sound walls” that it claimed were quite a
    distance away from the Shopping Center. This argument was not
    well-developed in UDOT’s briefing, and as a result we are not
    certain exactly which “sound walls” UDOT is referring to or
    where they are located, or whether UDOT is even attempting to
    argue that the sound walls in question are not part of the
    Interchange. We note simply that we consider any such claim on
    UDOT’s part—that some of the items included as causes of
    (continued…)
    20160122-CA                       19            
    2018 UT App 24
    UDOT v. Target Corporation
    question—the Interchange—was at least partially built on land
    taken from Claimants, and these facts entitle Claimants to take
    advantage of the presumption that the severance damages they
    suffered as a result of the construction of the Interchange were
    incurred “by reason of the severance.” See Utah Code Ann.
    § 78B-6-511(2) (providing that recoverable severance damages
    consist of those damages incurred “by reason of [the remaining
    parcel’s] severance from the portion sought to be condemned”);
    see also Ivers, 
    2007 UT 19
    , ¶ 20 (stating that “when the
    condemned land is used for the construction of the view-
    impairing structure, the damage to the remaining property is
    clearly caused by the severance”).
    ¶37 Thus, with regard to their claims for severance damages
    for loss of visibility, Claimants are able to demonstrate the
    requisite causal link through the first method—by showing that
    the view-impairing structure (the Interchange) was at least
    partially constructed on their former land. With regard to those
    damages claims, it is not necessary for Claimants to prove that
    the taken parcels were “essential” to the Projects as a whole. The
    trial court therefore did not err by allowing Claimants’ suit for
    severance damages for loss of visibility to proceed to a jury trial.
    B.     Severance Damages for Loss of the Right-Out Exit
    ¶38 This does not end our analysis, however, because there is
    another component of severance damages to which Claimants
    assert entitlement: severance damages associated with loss of the
    right-out exit onto Main Street. At oral argument, UDOT
    conceded that Claimants were theoretically entitled to recovery
    of this component of severance damages, but maintained that
    Claimants had not presented sufficient evidence of damages
    with regard to that claim. We find UDOT’s arguments
    (…continued)
    Claimants’ loss of visibility damages may not be part of the
    Interchange—to be inadequately briefed and developed.
    20160122-CA                     20                
    2018 UT App 24
    UDOT v. Target Corporation
    unpersuasive, and agree with Claimants that they presented
    sufficient evidence of their claimed severance damages.
    ¶39 “[T]he proper measurement of severance damages is
    determined by comparing the market value of the portion of
    property not taken with its market value before the taking.” See
    Admiral Beverage, 
    2011 UT 62
    , ¶ 30. Prior to Admiral Beverage,
    under the rule set out in Ivers under which claimants could
    recover for loss of view but not for loss of visibility, see Ivers,
    
    2007 UT 19
    , ¶¶ 11–15, appraisers could not simply state their
    conclusions in such straightforward before-and-after terms.
    Instead, they had to attempt to “assign specific values to [some]
    of the numerous factors affecting market value, including any
    decrease in value due to loss of visibility.” See Admiral Beverage,
    
    2011 UT 62
    , ¶ 39. Our supreme court noted that this task was
    “extreme[ly] difficult[], if not impossibl[e],” for appraisers to
    accomplish without resorting to “rank speculation.” 
    Id. ¶ 41
    .
    Partially for this reason, our supreme court overruled its holding
    in Ivers that condemnation claimants could not recover
    severance damages for loss of visibility. Ever since Admiral
    Beverage, condemnation claimants have been able to assert claims
    to a full complement of severance damages, measured using a
    simple before-and-after metric, and limited only by general
    notions of causation and evidentiary proof.
    ¶40 Thus, there is no requirement, in Admiral Beverage or in
    any other case of which we are aware, that Claimants must
    present their severance damages on a line-item basis, including a
    discrete value for, specifically, damages suffered by virtue of the
    loss of the right-out exit. 11 Claimants are free to present their
    11. There is a statutory mandate that, in condemnation cases, “as
    far as practicable compensation shall be assessed for each source
    of damages separately.” See Utah Code Ann. § 78B-6-511
    (LexisNexis 2012). UDOT makes passing mention of this statute
    in its brief, but makes no argument that this statute should be
    (continued…)
    20160122-CA                    21                
    2018 UT App 24
    UDOT v. Target Corporation
    severance damages evidence in a more general way, by
    presenting to the factfinder evidence of what the property was
    worth prior to the taking, and what it is worth after the taking. 12
    ¶41 In this case, Claimants did just that, and we find no legal
    infirmity in their efforts. Appraiser concluded that Claimants’
    remaining property was worth approximately $2.3 million less
    after the Interchange was built than it was before construction
    began. Appraiser testified that there were two main factors that
    contributed to the property’s diminution in value—loss of
    (…continued)
    read in a manner that would put it at odds with our supreme
    court’s analysis in Admiral Beverage.
    12. Despite the difficulty of the endeavor, as described in Admiral
    Beverage, 
    2011 UT 62
    , ¶¶ 38–39, it may be true that, in some cases
    and under some factual circumstances, appraisers would be able
    to itemize and individually value the various factors that
    comprise the total diminution in value. Where this is possible,
    and where appraisers are comfortable making the attempt,
    claimants may wish to consider presenting such evidence, since
    stating diminution in value only in general terms carries some
    risk. For instance, if we had reached the opposite result in this
    case with regard to Claimants’ entitlement to severance damages
    for loss of visibility for the entire Interchange, and concluded
    instead that Claimants were entitled to severance damages only
    for those two items conceded by UDOT (namely, (a) loss of the
    right-out exit and (b) loss of visibility related to the northbound
    I-15 on-ramp), we would have had to confront the question of
    whether to dismiss those claims for lack of proof, since no
    witness at trial offered any actual damages figure for the jury to
    consider on either of these two specific items, or whether to
    remand the case for a new trial on damages. Claimants dodged
    that bullet here, however, due to our conclusion that Claimants
    are entitled to recovery of all of the categories of severance
    damages for which they sought compensation at trial.
    20160122-CA                     22                
    2018 UT App 24
    UDOT v. Target Corporation
    visibility and loss of the right-out exit. Appraiser’s failure to
    provide specific values for these individual components of loss,
    in particular for loss in value caused by the loss of the right-out
    exit alone, does not render his testimony infirm or inadmissible,
    at least not in this case.
    CONCLUSION
    ¶42 Even though only a small portion of the enormous
    Interchange was actually built on the land UDOT took from
    Claimants, that small portion enables Claimants to take
    advantage of a much easier pathway to prove a causal link
    between the taking and their claimed damages. Because the
    Interchange was at least partially built on the taken property, a
    causal link between the taking and Claimants’ severance
    damages for loss of visibility is presumed. Claimants do not
    need to prove that the taking of their parcels was “essential” to
    the Projects as a whole.
    ¶43 Claimants are likewise entitled to recover severance
    damages for loss of the right-out exit onto Main Street. UDOT
    concedes that Claimants are theoretically entitled to these
    damages. Because we conclude that Claimants are entitled to
    recover each of the categories of severance damages at issue in
    this appeal, it necessarily follows that their damages evidence,
    presented merely in a before-and-after manner, was sufficient on
    the facts of this case.
    ¶44   Affirmed.
    20160122-CA                    23                
    2018 UT App 24