Hayes v. Intermountain Geoenvironmental Servs. Inc. , 446 P.3d 594 ( 2019 )


Menu:
  •                         
    2019 UT App 112
    THE UTAH COURT OF APPEALS
    KIM HAYES AND NANCY HAYES,
    Appellants,
    v.
    INTERMOUNTAIN GEOENVIRONMENTAL SERVICES INC.,
    Appellee.
    Opinion
    No. 20180972-CA
    Filed June 27, 2019
    Second District Court, Farmington Department
    The Honorable Glen R. Dawson
    No. 170700693
    Damian C. Smith, Attorney for Appellants
    Anna Nelson, Attorney for Appellee
    JUDGE RYAN M. HARRIS authored this Opinion, in which
    JUDGES KATE APPLEBY and DIANA HAGEN concurred.
    HARRIS, Judge:
    ¶1      A little more than a year after they built their “dream
    home,” Kim and Nancy Hayes (Plaintiffs) began to notice cracks
    in the house’s foundation and walls, and soon learned that the
    soil beneath the house was unstable. More than a decade earlier,
    Intermountain GeoEnvironmental Services Inc. (IGES) had, at
    the request of a developer (Developer), authored a geotechnical
    report concluding that residential construction could occur on
    the site provided certain precautions were taken. After learning
    that their house was built on unstable soil, Plaintiffs filed suit
    against IGES, asserting various negligence-based tort claims. The
    district court dismissed those claims, concluding that they were
    barred by the economic loss rule. Plaintiffs appeal that decision,
    and we affirm.
    Hayes v. Intermountain GeoEnvironmental Services
    BACKGROUND 1
    ¶2     In 2004, Developer hired IGES to conduct a geotechnical
    investigation and prepare a slope stability report for a
    subdivision it wanted to develop within the city limits of Layton,
    Utah. Layton City required that such a report be generated prior
    to construction of any houses on hillside lots. The lot upon
    which Plaintiffs eventually built their house was within the
    subdivision in question. After its investigation, IGES determined
    that construction could occur within the subdivision, provided
    that certain precautions were taken, ultimately concluding that
    “slope stability is satisfactory and the site is suitable for the
    proposed construction in accordance with the recommendations
    contained in this report.”
    ¶3       Developer sold some of the subdivision lots to a third
    party, who in turn sold one to Plaintiffs. In 2015, Plaintiffs hired
    a general contractor (Contractor) to build a house on the lot, and
    Contractor completed construction that same year. The record
    on appeal contains little information about who designed the
    house and drew the architectural plans that governed
    construction, and does not reveal whether and to what extent
    that designer (in designing the house) or Contractor (in building
    it) relied on IGES’s conclusions. 2
    1. Because this case comes to us on appeal from an order
    granting a motion to dismiss, we recite the facts as alleged in
    Plaintiffs’ complaint, and we assume their truth for the purposes
    of our analysis. See Torgerson v. Talbot, 
    2017 UT App 231
    , ¶ 7, 
    414 P.3d 504
     (“In reviewing a district court’s grant of a motion to
    dismiss for failure to state a claim upon which relief can be
    granted, we accept all facts alleged as true, and indulge all
    reasonable inferences in favor of the non-moving party.”
    (quotation simplified)).
    2. The record contains a copy of the building permit for
    Plaintiffs’ house, and that document lists a firm under the
    (continued…)
    20180972-CA                     2                
    2019 UT App 112
    Hayes v. Intermountain GeoEnvironmental Services
    ¶4      About fourteen months after construction of the house
    was completed, Plaintiffs observed cracks in its foundation
    and walls. Plaintiffs then hired a different engineering firm to
    conduct another geotechnical study of the property. This study
    noted that the house was “experiencing excessive foundation
    settling,” that “some lateral movement of the foundation
    elements has been observed,” and that the movement
    was “believed to be the result of instability in the slope
    immediately below and to the east of the home.” The report
    concluded that “the existing slope at the site fails to meet the
    minimum factors of safety” and, among other measures,
    recommended installing additional support for the foundation of
    the house, which would “likely need to extend at least 65 feet
    below existing foundation elements.” Plaintiffs contacted several
    contractors to ask them to undertake the work, but none was
    willing to do so because of liability concerns. Unable to stabilize
    the structure, Plaintiffs continued to observe widening cracks in
    the foundation and walls of the house, and eventually concluded
    that the house was not safe to live in and was unsalable on the
    real estate market.
    ¶5      Plaintiffs then filed their lawsuit, suing IGES, Developer,
    and Contractor. 3 Against IGES, Plaintiffs brought tort claims
    for negligence, negligent misrepresentation, and negligent
    infliction of emotional distress (NIED), as well as a breach of
    contract claim in which Plaintiffs claimed to be third-party
    (…continued)
    heading “Architect or Engineer,” but this is the only mention of
    that firm or its involvement in the project. Plaintiffs did not
    include that firm in their complaint, and do not mention the firm
    in their briefs on appeal.
    3. Plaintiffs sued Developer for negligence and negligent
    misrepresentation. Plaintiffs sued Contractor for breach of the
    implied warranty of habitability. Plaintiffs’ claims against
    Developer and Contractor are not at issue in this appeal.
    20180972-CA                     3               
    2019 UT App 112
    Hayes v. Intermountain GeoEnvironmental Services
    beneficiaries of the 2004 contract between IGES and Developer.
    Plaintiffs sought to recover damages stemming from the damage
    to their house, the diminution in value of their land, and moving
    expenses. IGES moved, pursuant to rule 12(b)(6) of the Utah
    Rules of Civil Procedure, to dismiss all of Plaintiffs’ claims
    against it, arguing that the tort claims were barred under
    both the statutory and common law version of Utah’s economic
    loss rule, and that Plaintiffs were not third-party beneficiaries
    of any contract with IGES. The district court granted IGES’s
    motion, concluding that the economic loss rule applied to bar
    all of Plaintiffs’ tort claims, and that Plaintiffs were not third-
    party beneficiaries of any contract between IGES and
    Developer. 4
    ISSUE AND STANDARD OF REVIEW
    ¶6     Plaintiffs now appeal the district court’s order, arguing
    that the court erred when it applied the economic loss rule to
    4. Because this ruling only disposed of Plaintiffs’ claims against
    IGES, and did not contain any rulings regarding Plaintiffs’
    claims against the other defendants, the ruling did not dispose of
    all matters between all litigants in the action below, and
    therefore was not “a final order or judgment that ends the
    controversy between the litigants.” See Copper Hills Custom
    Homes, LLC v. Countrywide Bank, FSB, 
    2018 UT 56
    , ¶ 10, 
    428 P.3d 1133
     (quotation simplified). Accordingly, the ruling was not
    immediately appealable. See 
    id.
     Plaintiffs attempted to obtain
    certification for appeal pursuant to rule 54(b) of the Utah Rules
    of Civil Procedure, but did so improperly, and on this basis we
    dismissed Plaintiffs’ first appeal on jurisdictional grounds. See
    Hayes v. Intermountain GeoEnvtl. Services, Inc., 
    2018 UT App 223
    ,
    ¶¶ 4–5, 
    437 P.3d 650
    . Thereafter, Plaintiffs dismissed without
    prejudice their claims against the other defendants, thereby
    taking care of the final issues in the case at the district court
    level, and filed a new notice of appeal.
    20180972-CA                     4               
    2019 UT App 112
    Hayes v. Intermountain GeoEnvironmental Services
    dismiss their tort claims. 5 “The decision to grant a motion
    to dismiss presents a question of law that we review for
    correctness.” Davencourt at Pilgrims Landing Homeowners Ass'n v.
    Davencourt at Pilgrims Landing, LC, 
    2009 UT 65
    , ¶ 12, 
    221 P.3d 234
    (quotation simplified). When reviewing such an order, “we
    accept the material allegations in the complaint as true and
    interpret those facts and all reasonable inferences drawn
    therefrom in a light most favorable to the plaintiff as the non-
    moving party.” 
    Id.
     (quotation simplified).
    ANALYSIS
    ¶7      As originally articulated, the economic loss rule was
    solely “a judicially created doctrine” marking “the fundamental
    boundary between contract law, which protects expectancy
    interests created through agreement between the parties, and
    tort law, which protects individuals and their property from
    physical harm by imposing a duty of reasonable care.” SME
    Indus., Inc. v. Thompson, Ventulett, Stainback & Assocs., Inc., 
    2001 UT 54
    , ¶ 32, 
    28 P.3d 669
    . In general, “the economic loss rule
    prohibits tort claims for purely economic loss.” Gables at Sterling
    Village Homeowners Ass’n, Inc. v. Castlewood-Sterling Village I, LLC,
    
    2018 UT 04
    , ¶ 47, 
    417 P.3d 95
    .
    ¶8     Although it began as a common-law             creation, the
    economic loss rule now exists in Utah in both        statutory and
    common-law forms. The statutory version of the       economic loss
    rule was enacted in 2008, and applies only to        “action[s] for
    defective design or construction.” See Utah Code     Ann. § 78B-4-
    5. Plaintiffs do not appeal the district court’s dismissal of their
    contract-based claim against IGES, or the district court’s
    subsidiary determination that they were not third-party
    beneficiaries of any contract between IGES and Developer.
    20180972-CA                      5               
    2019 UT App 112
    Hayes v. Intermountain GeoEnvironmental Services
    513(1) (LexisNexis 2018). 6 The common-law version of the
    economic loss rule continues to apply in situations that are
    beyond the scope of the statute. See, e.g., KTM Health Care Inc. v.
    SG Nursing Home, LLC, 
    2018 UT App 152
    , ¶¶ 69–79, 
    436 P.3d 151
    .
    (applying the economic loss rule outside the design or
    construction context). IGES argues that it is protected from
    Plaintiffs’ tort claims under both the statutory and the common-
    law economic loss rule. We agree with IGES that the statutory
    economic loss rule bars Plaintiffs’ tort claims against IGES, and
    therefore we need not consider the applicability of the common-
    law economic loss rule in this case.
    ¶9     Utah’s statutory economic loss rule provides that “an
    action for defective design or construction is limited to breach of
    the contract,” Utah Code Ann. § 78B-4-513(1), and that, in
    general, “an action for defective design or construction may be
    brought only by a person in privity of contract with the original
    contractor, architect, engineer, or the real estate developer,” id.
    § 78B-4-513(4). The statute contains an exception, however, for
    “damage to other property.” Id. § 78B-4-513(2). IGES contends
    that Plaintiffs’ tort claims against it constitute “action[s] for
    defective design or construction,” and are therefore barred by
    the statutory economic loss rule. Plaintiffs resist this
    characterization, and in addition assert that the “other property”
    exception applies in any event. We conclude that Plaintiffs’ tort
    claims constitute actions for defective design and construction,
    as that term is used in the statute, and that the “other property”
    exception does not apply.
    6. While a few cases issued after the passage of Utah Code
    section 78B-4-513 have addressed the economic loss rule in the
    construction context, see, e.g., Reighard v. Yates, 
    2012 UT 45
    , 
    285 P.3d 1168
    ; Davencourt at Pilgrims Landing Homeowners Ass’n v.
    Davencourt at Pilgrims Landing, LC, 
    2009 UT 65
    , 
    221 P.3d 234
    , the
    disputes giving rise to those cases arose before enactment of the
    statute, and therefore the opinions in those cases relied largely
    on the common law and did not directly interpret the statute.
    20180972-CA                     6               
    2019 UT App 112
    Hayes v. Intermountain GeoEnvironmental Services
    A
    ¶10 The first question presented is whether and to what extent
    Plaintiffs’ tort claims constitute “an action for defective design or
    construction” as that term is used in the statutory codification of
    the economic loss rule. See 
    id.
     § 78B-4-513(1). Under the statute,
    such actions are “limited to breach of the contract,” and
    therefore cannot be brought in tort. Id. Thus, to the extent
    Plaintiffs’ tort claims constitute an action for defective design or
    construction, those claims are barred.
    ¶11 The question presented is one of statutory interpretation.
    “When interpreting a statute, our objective is to give effect to the
    intent of the legislature in light of the purpose the act was meant
    to achieve.” State v. Hunt, 
    2018 UT App 222
    , ¶ 17, 
    438 P.3d 1
    (quotation simplified). “Because the best evidence of the
    legislature’s intent is the plain language of the statute itself, we
    look first to the plain language of the statute.” GeoMetWatch
    Corp. v. Utah State Univ. Research Found., 
    2018 UT 50
    , ¶ 15, 
    428 P.3d 1064
     (quotation simplified). Sometimes, “the statutory text
    may not be ‘plain’ when read in isolation,” but it “may become
    so in light of its linguistic, structural, and statutory context.”
    Olsen v. Eagle Mountain City, 
    2011 UT 10
    , ¶ 9, 
    248 P.3d 465
    .
    ¶12 As an initial matter, we think it plain that the tort claims
    Plaintiffs filed against IGES constitute “an action.” In this
    context, the word “action” means “[a] civil or criminal judicial
    proceeding.” See Action, Black’s Law Dictionary (10th ed. 2014);
    see also 
    id.
     Action at Law (defining “action at law” as “[a] civil suit
    stating a legal cause of action and seeking only a legal remedy”);
    cf. Utah Code Ann. § 78B-2-101(1) (defining “action” in a statute-
    of-limitations context as including “counterclaims and cross-
    complaints and all other civil actions in which affirmative relief
    is sought”); id. § 78B-6-202(6) (defining “civil action” in an
    alternative-dispute-resolution context as “an action in which a
    party seeks monetary or equitable relief at common law or
    pursuant to statute”). By filing tort claims against IGES,
    Plaintiffs commenced an “action” against it, as that word is used
    in the statute.
    20180972-CA                       7                
    2019 UT App 112
    Hayes v. Intermountain GeoEnvironmental Services
    ¶13 The more interesting part of the inquiry—and the one
    upon which the parties spend their energies—is whether the
    “action” Plaintiffs filed against IGES is one “for defective design
    or construction.” IGES asserts that it is, and points out that the
    gravamen of Plaintiffs’ claim is that their “dream home” was
    built on unstable soil and has been rendered uninhabitable as a
    result of settling and cracking, and that, at root, such claims
    depend on Plaintiffs’ ability to demonstrate that their house was
    poorly designed or constructed. Plaintiffs, by contrast, contend
    that their tort claims against IGES are not for defective design or
    construction, and point out that IGES’s 2004 report was issued
    before any relevant structure—including their house—was
    designed or constructed. Specifically, Plaintiffs assert that IGES’s
    report “was a professional opinion on a state of facts concerning
    a lot later purchased by Plaintiffs,” and argue that “IGES is being
    sued because its opinion about the stability of the slope was
    wrong, not because it improperly designed a structure.”
    ¶14 We find meaningful the statute’s use of the word “for,”
    and see its use as a signal that—in order to determine if an action
    is truly one seeking redress in connection with defective design
    or construction—we should pay close attention to the claimed
    cause of the specific damages sought in the action. The statute
    asks us to consider what the “action” is being brought “for.”
    That is, the legal label placed on each cause of action is less
    important, in this context, than the underlying factual scenario
    giving rise to the general grievance being lodged. Thus, to
    answer the question presented, we must examine the relief
    sought by Plaintiffs against IGES, as well as Plaintiffs’ basic
    underlying theory of causation.
    ¶15 Our examination of Plaintiffs’ complaint reveals that they
    are seeking only monetary relief from IGES, and that the
    damages they seek fall into four categories. First, Plaintiffs
    identify a category of damages “measured by actual physical
    damage—and eventual total destruction—of” their house.
    Second, Plaintiffs identify a category of damages related to
    having to move out of the damaged house, including “costs
    involved in finding replacement housing [and] storage
    20180972-CA                     8                
    2019 UT App 112
    Hayes v. Intermountain GeoEnvironmental Services
    expenses.” Third, as part of their NIED claim, Plaintiffs seek
    damages for emotional distress associated with the “actual
    physical peril” of being in the “zone of danger” created by
    occupying a house they deem unsafe. Finally, Plaintiffs seek
    damages related to harm to their lot, pointing out that the land
    itself “is undergoing continuing sliding and destruction such
    that it is totally unsuitable for residential construction.”
    ¶16 The first three of Plaintiffs’ four categories of claimed
    damages clearly are aimed at seeking redress “for defective
    design or construction.” Under Plaintiffs’ own version of events,
    IGES’s allegedly faulty slope stability recommendations led to
    Plaintiffs purchasing the lot, then constructing a house upon it,
    then to the house settling and cracking, and then to emotional
    distress and moving expenses. Indeed, the entire point of
    commissioning a geotechnical report in this case was to
    determine whether houses could safely be built in the proposed
    subdivision and, if so, what sort of foundation and support those
    houses would need. Even Plaintiffs’ chosen geotechnical
    engineer, whose report is attached to their complaint,
    acknowledges that houses can be safely constructed on the
    property, as long as their foundations are bolstered by supports
    extending at least sixty-five feet below the surface. Buildings
    must be designed and constructed to fit the land upon which
    they are built, and when a house is built to specifications that are
    inappropriate for the site, that is ultimately a design and
    construction issue. A common-sense understanding of Plaintiffs’
    action is that they claim to have suffered damages arising from
    something that went wrong—a defect—in the design and
    construction of their house. Even if the architect or the builder
    did not cause this defect, it is nonetheless a defect in the design
    and construction of the house, and the action is one “for
    defective design or construction.”
    ¶17 A closer look at the language and context of the statutory
    economic loss rule reinforces this common-sense approach.
    Plaintiffs resist the application of the statute to their case by
    arguing that IGES “did not act as a ‘design professional’ in this
    case” and that the report was not “design work,” but rather, was
    20180972-CA                     9                
    2019 UT App 112
    Hayes v. Intermountain GeoEnvironmental Services
    “a professional opinion about an existing state or condition.” But
    Plaintiffs’ argument does not match the statute’s language or
    context.
    ¶18 Geotechnical engineering recommendations are an
    important first step in the design and construction process. See,
    e.g., American Bar Ass’n, The Construction Project § 2.III.D
    Geotechnical Engineer (Marilyn Klinger & Marianne Susong
    eds., 2006) (“A geotechnical engineer is often an essential
    participant on the design team. . . . [T]he geotechnical engineer
    . . . provides recommendations for the design of the proposed
    structure’s foundation and structural system. This information
    . . . is typically one of the starting points for the structural
    engineer.”); Shannon J. Briglia & Michael C. Loulakis,
    Geotechnical Risk Allocation on Design-Build Construction Projects, J.
    Am. C. Constr. Law., at 4, Sept. 2017 (“[G]eotechnical engineers
    are retained by or on behalf of the owner to ascertain site
    conditions, which information the design team uses to develop
    its plans and specifications.”); see also Terracon Consultants W. Inc.
    v. Mandalay Resort Group, 
    206 P.3d 81
    , 89 (Nev. 2009) (en banc)
    (considering geotechnical engineers to be design professionals
    for the purposes of the economic loss rule). Given these realities,
    geotechnical engineers are considered “design professionals” as
    that term is defined in another analogous section of the Utah
    Code. See Utah Code Ann. § 13-8-2(1)(c) (LexisNexis 2013)
    (defining “design professional” as “an architect, engineer, or land
    surveyor,” including “any other person who, for a fee or other
    compensation, performs services similar to the services of an
    architect, engineer, or land surveyor in connection with the
    development of land” (emphasis added)). Although the
    statutory economic loss rule does not use the term “design
    professional,” it certainly uses the word “design,” see Utah Code
    Ann. § 78B-4-513(1) (2018), and in determining what the
    legislature meant through its use of that term, it is helpful to
    examine how it has defined similar terms in analogous contexts,
    see, e.g., Wasatch Crest Ins. Co. v. LWP Claims Adm’rs Corp., 
    2007 UT 32
    , ¶¶ 13–14, 
    158 P.3d 548
     (looking to other sections of
    the Utah Code for guidance in defining the relevant term where
    20180972-CA                      10               
    2019 UT App 112
    Hayes v. Intermountain GeoEnvironmental Services
    the term was not defined in the statute at issue); Territorial Sav.
    & Loan Ass’n v. Baird, 
    781 P.2d 452
    , 461 (Utah 1989) (same).
    By including engineers within the definition of “design
    professional” elsewhere in the Utah Code, the legislature
    appears to have recognized the reality that engineers are often
    integral members of a building’s design team. 7
    ¶19 Accordingly, the bulk of Plaintiffs’ lawsuit against IGES
    can comfortably be categorized as “an action for defective design
    or construction.” A lawsuit that seeks recovery from a design
    professional—including a geotechnical engineer—for the
    diminution in value of (or costs to repair) a structure that has
    settled or sustained damage as a result of subsidence will nearly
    always be properly categorized as a lawsuit seeking recovery for
    defective design or construction. 8 Therefore, to the extent
    7. As discussed at oral argument, the architect hired to design a
    building sometimes subcontracts with a geotechnical engineer
    for the express purpose of obtaining advice for the design of the
    building’s foundation. In such scenarios, the geotechnical
    engineer may work closely with the architect and may well be
    directly involved in the actual design of the building. But—
    assuming the architect actually relies upon the geotechnical
    engineer’s recommendations—we see no principled reason to
    treat a geotechnical engineer who completed his or her work
    months before the building was designed any differently than an
    engineer who works closely with the architect on a specific set of
    plans and specifications. In each situation, the engineer’s
    recommendations are an important part of the building’s design,
    and any action against the engineer for damage to the building
    alleged to be caused by the engineer’s faulty recommendations
    would constitute an action for defective design or construction.
    8. We do not mean to suggest that every case involving building
    subsidence is automatically “an action for defective design or
    construction.” For example, if the building is settling because the
    adjoining landowner dug a tunnel under it, and the plaintiff is
    (continued…)
    20180972-CA                    11               
    2019 UT App 112
    Hayes v. Intermountain GeoEnvironmental Services
    Plaintiffs seek damages related to the structure itself—including
    claims for diminution in its value, repair costs, moving expenses
    incurred for having to leave the structure, or emotional distress
    related to living in it—their claims constitute actions for
    defective design or construction, and are covered by Utah Code
    section 78B-4-513(1).
    ¶20 Plaintiffs’ fourth category of damages—a claim for
    damage to the lot—presents a closer question. With regard to
    this category of damages, Plaintiffs’ claims do not directly
    implicate any actual structure; instead, Plaintiffs seek recovery of
    damages to the land itself. Although it is not entirely clear, at
    this stage of the proceedings, what this claim is designed to
    encompass—after all, IGES did not create whatever slope
    stability issues might inhere in Plaintiffs’ lot—Plaintiffs appear
    to be asserting that the value of their lot has diminished now
    that it is known that construction on the property will be
    problematic. Though Plaintiffs do not phrase it in exactly this
    way, they appear to be claiming that, when they purchased their
    lot, they did so in reliance on IGES’s recommendations, and paid
    a price for the lot commensurate with it being readily buildable,
    and that the lot is no longer worth what they paid for it because
    of the slope stability issues that have since come to light.
    ¶21 Ultimately, however, we view this portion of the claim as
    one for defective design or construction also. As noted, IGES was
    originally hired to provide recommendations regarding what
    kind of structures could be built on the property. That is, its
    recommendations were to be used principally as guidance for
    (…continued)
    pointing the finger at the neighbor rather than at an architect,
    contractor, or geotechnical engineer, the case would arguably
    not be so categorized. But we are hard-pressed to imagine a
    building-subsidence case in which the plaintiff is pointing the
    finger at a contractor or design professional that would not be
    “an action for defective design or construction.”
    20180972-CA                     12               
    2019 UT App 112
    Hayes v. Intermountain GeoEnvironmental Services
    designers and builders of structures. This is not a case in which
    IGES’s recommendations were to be used for, say, determining
    whether mining or grazing operations could usefully be
    conducted on the property. IGES’s recommendations were
    always about buildability, which is ultimately a design and
    construction issue. Indeed, if we are construing Plaintiffs’ claim
    correctly, the purported diminution in value of Plaintiffs’ lot has
    to do with whether, and to what extent, the lot is buildable—that
    is, whether a prospective purchaser will be able to build a house
    on that lot and, if so, what kind of additional foundation
    requirements must be included in the structure’s design in order
    to make construction feasible.
    ¶22 In the end, we conclude that each category of damages
    Plaintiffs seek from IGES is related to allegations of defective
    design or construction. Accordingly, Plaintiffs’ tort claims
    constitute an “action for defective design or construction,” and
    are therefore within the purview of Utah Code section 78B-4-
    513(1), which—subject to two exceptions, see Utah Code Ann.
    § 78B-4-513(2), one of which is discussed below—requires such
    claims to be brought, if at all, as contract claims.
    B
    ¶23 The statutory economic loss rule provides an exception
    for claims seeking redress for “damage to other property,” even
    if that damage is caused by “defective design or construction.”
    See id. § 78B-4-513(2). Plaintiffs assert that this exception applies
    here, at least to their claims for damage to the house (as opposed
    to damage to the lot), which they attempt to characterize as
    “other property.” We disagree.
    ¶24 Although the statutory codification of the economic loss
    rule does not provide a complete definition of the phrase “other
    property,” it does provide helpful guidance as to the term’s
    reach, specifying that the “other property” exception set forth in
    subsection (2) of the statute cannot apply to “the failure of
    construction to function as designed,” or to the “diminution of
    20180972-CA                     13               
    2019 UT App 112
    Hayes v. Intermountain GeoEnvironmental Services
    the value of the constructed property because of the defective
    design or construction.” 
    Id.
     § 78B-4-513(3). This language directly
    forecloses Plaintiffs’ argument that the house constitutes “other
    property” not subject to the economic loss rule.
    ¶25 Moreover, the “other property” exception is also part of
    the common-law economic loss rule, and was incorporated
    into the codification of the statutory economic loss rule. See, e.g.,
    Davencourt at Pilgrims Landing Homeowners Ass’n v. Davencourt at
    Pilgrims Landing, LC, 
    2009 UT 65
    , ¶ 25, 
    221 P.3d 234
     (discussing
    the “other property” exception in the context of the common-
    law economic loss rule). Because the legislature, in codifying
    the economic loss rule, drew the term from the common law,
    we find it helpful to examine how courts employ that term
    in common law cases. In Davencourt, our supreme court held
    that individual components of the product bargained for
    cannot constitute “other property.” 
    Id.
     (holding that the
    condominiums at issue were purchased as a “finished product,”
    and therefore the “individual components”—including the roof,
    the foundation, and the siding—were not “other property”); see
    also American Towers Owners Ass’n v. CCI Mech., Inc., 
    930 P.2d 1182
    , 1191 (Utah 1996) (holding that “walls, wall coverings,
    carpeting, wall hangings, curtains, and other furnishings”
    were not “other property” because “the ‘property’ was the
    entire complex itself that was constructed as an integrated
    unit under one general contract”), abrogated on other grounds by
    Davencourt at Pilgrims Landing Homeowners Ass'n, 
    2009 UT 65
    .
    ¶26 Plaintiffs argue that, because they purchased the land and
    contracted for the building of the house in two separate
    transactions, the house constitutes “a separate property,” distinct
    from the land, and should fall under the “other property”
    exception. Plaintiffs assert that IGES’s recommendations applied
    “only to a plot of land,” and reason that their house was a
    “separate improvement, apart from the land, that was separately
    bargained for and purchased.” (Quotation simplified.) Plaintiffs
    compare their situation to one “where a defectively designed
    building collapses and destroys a building built on adjacent
    property.”
    20180972-CA                     14               
    2019 UT App 112
    Hayes v. Intermountain GeoEnvironmental Services
    ¶27 But IGES’s recommendations did not apply only to a
    plot of land, as Plaintiffs contend. The report was obtained by
    a developer to assess the suitability of that land for construction
    of houses. As discussed above, the entire point of the report
    was to provide input regarding the type of support
    any structures built on that land would need. Contrary to
    Plaintiffs’ assertions, the condition of the land is inextricably
    bound to the construction of the house. For instance, Plaintiffs’
    house presumably could have been built—exactly as it was—
    and placed on a more stable piece of land without incident;
    likewise, even according to Plaintiffs’ expert, the land could have
    supported a house built with a different foundation. The alleged
    defect in this case lies at the intersection of the house and the
    land; neither is defective without the other. Even though
    Plaintiffs purchased the lot before they contracted for the
    construction of the house, the house and the land upon which it
    is built constitute an inseparable “integrated unit” for all intents
    and purposes.
    ¶28 Accordingly, we conclude that the “other property”
    exception built into the statutory economic loss rule is
    inapplicable here.
    CONCLUSION
    ¶29 By filing tort claims against IGES for faulty soils
    recommendations, Plaintiffs are attempting to blame IGES
    for damage to their house, moving expenses, and emotional
    distress, as well as diminution in value of their land. Given their
    nature, these are actions “for defective design or construction,”
    as that term is used in the statutory version of the economic loss
    rule. Utah Code Ann. § 78B-4-513. Moreover, these are not
    claims for damage to “other property.” As a result, Plaintiffs’
    tort claims against IGES are barred by the statutory economic
    loss rule.
    ¶30 Even though Plaintiffs may not bring tort claims against
    IGES, parties in Plaintiffs’ shoes typically are not without a
    20180972-CA                     15               
    2019 UT App 112
    Hayes v. Intermountain GeoEnvironmental Services
    remedy. The economic loss rule, as applied in the construction
    context, envisions a chain of contractual relationships, and
    generally requires that parties in such situations bring claims
    against the entities with whom they are in privity of contract. In
    Plaintiffs’ case, that could have been the contractor who built
    their house, or the architect who designed it, or any other person
    or entity with whom they have a direct contractual relationship.
    There are also limited opportunities to bring other claims in
    these situations, including claims for breach of the warranty of
    habitability. See Davencourt at Pilgrims Landing Owners Ass’n v.
    Davencourt at Pilgrims Landing, LC, 
    2009 UT 65
    , ¶¶ 49–63, 
    221 P.3d 234
    . Indeed, Plaintiffs brought some such claims in this case
    against Contractor and Developer. In this case, Plaintiffs are
    disappointed that Contractor apparently does not possess valid
    insurance coverage, a circumstance that is extremely unfortunate
    for Plaintiffs but—even if true—is not grounds for us to ignore
    the strictures of the economic loss rule, which bars the claims at
    issue in this appeal. See Wasatch County v. Tax Comm’n, 
    2009 UT App 221
    , ¶ 5 n.3, 
    217 P.3d 270
     (“It is not within our province to
    read something into the statute not found there, nor to carve out
    exceptions to meet hard cases.” (quotation simplified)).
    ¶31   Affirmed.
    20180972-CA                    16              
    2019 UT App 112