Cea v. Hoffman ( 2012 )


Menu:
  •                          IN THE UTAH COURT OF APPEALS
    ‐‐‐‐ooOoo‐‐‐‐
    Al Cea and Laura Cea,                       )                  OPINION
    )
    Plaintiffs and Appellants,            )           Case No. 20100728‐CA
    )
    v.                                          )
    )                  FILED
    Roger Hoffman; Modular                      )                (April 5, 2012)
    Manufacturing, LLC; Investors               )
    Collaborative, LLC,                         )              
    2012 UT App 101
    )
    Defendants and Appellees.             )
    ‐‐‐‐‐
    Second District, Ogden Department, 080901240
    The Honorable Ernest W. Jones
    Attorneys:      Alex B. Leeman, Matthew F. McNulty III, and Florence M. Vincent, Salt
    Lake City, for Appellants
    David M. Wahlquist, Christopher S. Hill, and Gregory S. Moesinger,
    Salt Lake City, for Appellees
    ‐‐‐‐‐
    Before Judges McHugh, Voros, and Roth.
    VOROS, Associate Presiding Judge:
    ¶1     Appellants Al and Laura Cea appeal the trial court’s entry of summary judgment
    in favor of Modular Manufacturing, LLC, Investors Collaborative, LLC, and Roger
    Hoffman (collectively Appellees).1 We affirm in part and reverse in part.
    1. Hoffman holds a 90% interest in The Nexus Group, Inc., which holds a 50%
    ownership interest in Investors. Investors is a Utah limited liability company that holds
    a 51% ownership interest in Modular.
    BACKGROUND
    ¶2     This case arises from the Ceas’ unsuccessful attempt to purchase a modular log
    home and have it delivered to their property in California. In June 2006, the Ceas
    entered into a purchase agreement with American TimberCraft, LLC (ATC), a Utah
    limited liability company. Pursuant to that agreement, the Ceas made a down payment
    of $172,116—half the total purchase price—to ATC. ATC incurred financial difficulties
    and never began construction of the home. In November 2006, ATC signed an
    agreement with Modular in which Modular “acquir[ed] from ATC its work in progress
    and pending orders along with all related deposits and down payments,” including the
    Ceas’ $172,116.
    ¶3    Six months later, Modular sent the Ceas a letter (the Modular Letter) explaining
    that ATC had “ceased operations,” “liquidated all company assets,” and was “no longer
    capable of completing or performing on its contract with [the Ceas].” However, the
    Modular Letter added, “all is not lost.” Modular had acquired ATC’s assets and
    proposed two options. The first option was for Modular to complete the Ceas’ log
    home:
    Although Modular did not purchase [ATC] itself[,] as part of
    the asset acquisitions[] Modular agreed to complete all work
    in progress, including orders for which deposits have been
    taken (even if no physical work has commenced). Therefore
    if you had an order with [ATC], Modular has agreed to
    complete the work on your home for the previously agreed
    price, even though it did not acquire your actual contract
    from [ATC]. . . .
    If you decide that you would like to proceed, enter
    into a new contract and have your home completed, there
    are some minor modifications to terms and payment
    schedules. However the specifications for the home itself
    will not change nor will the price.
    The second option was for Modular to refund the Ceas’ deposit:
    At this point in time we (as [Modular]) will be issuing
    new contracts for your home construction (regardless of
    what stage of construction it may be in) in order to complete
    20100728‐CA                                 2
    and give you the assurance of a valid contract for
    performance. In lieu of a new contract we will be willing to
    pay you whatever deposits or payments you made to [ATC]
    for your home should you decide that you would prefer to
    cancel and just walk away.
    The Modular Letter was sent by Modular; it appears that neither Investors nor Hoffman
    signed the letter.
    ¶4     The Ceas responded with a letter (the First Cea Letter) purporting to accept
    Modular’s proposal to build and deliver the home. However, the Ceas sought to
    change the specifications and place of delivery of the home and sought additional terms
    not offered by Modular, including a new delivery date:
    Please prepare a new contract for us showing the
    $172,116 paid in thr[ough] June 7, 2006. We wish to delete
    the garage. Also, please reflect the 5% of total contract to be
    retained by us and paid upon final setting . . . of log shell.
    [W]e are changing the location of the job, our
    frustration with this project has taken a great toll on us in
    more ways than you can imagine. We . . . will take delivery
    on a new parcel . . . [and] we will obtain all necessary
    permits . . . .
    We hope and expect our new delivery date for this
    shell to be on or before July 31, 2007.
    ¶5     Modular did not respond to the First Cea Letter. One week later, the Ceas sent a
    second letter (the Second Cea Letter) purporting to accept Modular’s proposal to refund
    their deposit:
    Upon further consideration, we respectfully request
    that, in accordance with your December letter, you refund
    the $172,116 we have paid as a deposit on our log home.
    Please send a check at your earliest convenience . . . .
    20100728‐CA                                  3
    This has been a very difficult decision for us, but we
    don’t believe your company can deliver a log home to us in
    any reasonable time frame.
    ¶6     Modular did not respond to the Second Cea Letter, nor did it refund the Ceas’
    deposit. Accordingly, in February 2008, the Ceas sued a number of defendants,
    including Modular, Investors, Hoffman, and ATC. The Ceas alleged (1) breach of
    contract for failure to build and deliver their home or, alternatively, for failing to refund
    the Ceas’ deposit; (2) fraud or intentional misrepresentation; and (3) negligent or
    reckless misrepresentation. These causes of action all arose out of the Modular Letter.2
    ¶7     Appellees successfully moved for summary judgment. The trial court ruled that
    Hoffman “is not personally liable for the actions of Modular” because “Hoffman never
    made any personal representations to the Ceas and that any action by Hoffman was
    limited to his capacity as a representative of [Modular].” It further ruled that Investors
    “is not personally liable for the actions of Modular” because Investors “never made any
    representations to the Ceas, and that any action by Investors was limited to its capacity
    as a representative of Modular.” Finally, the court ruled that Modular and the Ceas
    never formed a binding contract and that Modular made no fraudulent or negligent
    misrepresentations. The Ceas appeal.
    ISSUES AND STANDARDS OF REVIEW
    ¶8     The Ceas assert three principal claims of error. First, they contend that summary
    judgment should not have been granted, because discovery was not complete. Next,
    they contend that a genuine issue of material fact exists as to whether Hoffman is
    personally liable for his role in making distributions from Modular while Modular was
    insolvent. Finally, they contend that a genuine issue of law exists as to whether the
    Ceas and Modular formed a contract.
    ¶9      We review a grant or denial of summary judgment for correctness, affording the
    trial court no discretion, and we view all the facts and reasonable inferences in the light
    most favorable to the nonmoving party. See Orvis v. Johnson, 
    2008 UT 2
    , ¶ 6, 
    177 P.3d 2
    . The Ceas did not allege breach of a third party beneficiary contract, see, e.g., Rio
    Algom Corp. v. Jimco Ltd., 
    618 P.2d 497
    , 506 (Utah 1980), or assignment, see, e.g., Winegar
    v. Froerer Corp., 
    813 P.2d 104
    , 107–08 (Utah 1991).
    20100728‐CA                                   4
    600. Whether a contract exists between parties is ordinarily a question of law, reviewed
    for correctness. See Herm Hughes & Sons, Inc. v. Quintek, 
    834 P.2d 582
    , 583 (Utah Ct.
    App. 1992). However, “‘[a] motion for summary judgment may not be granted if . . .
    there is a factual issue as to what the parties intended.’” West One Trust Co. v. Morrison,
    
    861 P.2d 1058
    , 1062 (Utah Ct. App.1993) (omission in original) (quoting Winegar v.
    Froerer Corp., 
    813 P.2d 104
    , 108 (Utah 1991)).
    ANALYSIS
    I. Incomplete Discovery
    ¶10 The Ceas contend that the trial court erred in granting summary judgment
    because, at the time the court heard and ruled on the summary judgment motion,
    discovery was not complete. They note that “this fact was made known to the district
    court in the Ceas’ opposition to the Appellees’ motions for summary judgment as well
    as in oral arguments.”
    ¶11 The Ceas argued below that the existing record demonstrated that Hoffman
    played a substantial role in Modular’s allegedly unlawful distributions. However, they
    also sought to obtain through discovery additional facts to support this allegation.
    Because Modular’s responses to their discovery requests were allegedly deficient, the
    Ceas filed a motion to compel. They filed the motion four months after the close of fact
    discovery under the scheduling order, three months after the Appellees had filed their
    motions for summary judgment, and one month after the Appellees had filed notices to
    submit their summary judgment motions for decision. While the motion to compel was
    pending, the trial court heard and granted the Appellees’ motions for summary
    judgment. The Ceas contend that the court’s ruling was premature because discovery
    was incomplete. “Had Hoffman provided the Ceas with the discovery they requested,
    but which Hoffman failed to provide, such discovery would have supported the Ceas’
    argument,” they contend.
    ¶12 “We generally review a trial court’s discovery rulings for an abuse of discretion,
    but when a trial court does not rule on outstanding discovery motions and thereby fails
    to exercise its discretion, ‘the issue of whether or not it should have [decided the
    outstanding motions] presents a legal question which is subject to de novo review.’”
    Bluemel v. Freestone, 
    2009 UT App 16
    , ¶ 4, 
    202 P.3d 304
     (quoting Energy Mgmt. Servs.,
    LLC v. Shaw, 
    2005 UT App 90
    , ¶ 8, 
    110 P.3d 158
    ). “Generally, summary judgment
    should not be granted if discovery is incomplete since information sought in discovery
    20100728‐CA                                  5
    may create a genuine issue of material fact sufficient to defeat the motion.” 
    Id. ¶ 5
    .
    Here, however, any possible error committed by the trial court was invited by the Ceas.
    ¶13 The invited error doctrine “is crafted to discourage parties from intentionally
    misleading the trial court so as to preserve a hidden ground for reversal on appeal,” as
    well as “to give the trial court the first opportunity to address the claim of error.” State
    v. Geukgeuzian, 
    2004 UT 16
    , ¶ 12, 
    86 P.3d 742
     (internal quotation marks and brackets
    omitted). Under the invited error doctrine, “a party cannot take advantage of an error
    committed at trial when that party led the trial court into committing the error.” 
    Id. ¶ 9
    (internal quotation marks omitted). “Affirmative representations that a party has no
    objection to the proceedings fall within the scope of the invited error doctrine because
    such representations reassure the trial court and encourage it to proceed without
    further consideration of the issues.” State v. Winfield, 
    2006 UT 4
    , ¶ 16, 
    128 P.3d 1171
    .
    ¶14 The Ceas did just that. At the outset of the motion hearing the trial court asked
    Cea’s counsel, “the motion to compel, we don’t need to deal with. Do you agree with
    that, [counsel]?” To which the Ceas’ counsel responded, “Yes. I don’t think the motion
    to submit has been filed.” This affirmative representation by the Ceas’ counsel
    “reassure[d] the trial court and encourage[d] it to proceed without further consideration
    of the issue[].” See Winfield, 
    2006 UT 4
    , ¶ 16. Accordingly, we decline to review this
    claim of error.
    II. Fraud
    A. Hoffman
    ¶15 The Ceas contend that the trial court erred by ruling as a matter of law that
    Hoffman could not be held personally liable for fraud or intentional misrepresentation.
    They contend that, notwithstanding curtailed discovery, record evidence creates a
    genuine issue of material fact as to whether Hoffman made distributions in violation of
    the Utah Revised Limited Liability Company Act, see Utah Code Ann. § 48‐2c‐602
    (2010),3 and “whether Hoffman was a mere agent of Modular or whether Hoffman had
    a more substantial relationship with Modular that would impose personal liability upon
    him for his actions.” In support of these claims, the Ceas’ brief relies principally on two
    portions of the record.
    3. We cite to the current version of the code as a convenience to the reader because the
    relevant provisions have not been substantively amended since the events relevant to
    this appeal occurred.
    20100728‐CA                                  6
    ¶16 First, the Ceas allege that “Modular did in fact make distributions, that such
    distributions were made while Modular was insolvent, and that Hoffman played a
    substantial role in Modular’s decision to make those insolvent distributions.” We have
    reviewed the pages of the record cited in support of this statement and do not agree that
    they support the propositions for which the Ceas cite them.
    ¶17 In particular, we do not agree that in his deposition Hoffman testified—or that it
    may reasonably be inferred from his testimony—that he “played a substantial role in
    Modular’s decision to make those insolvent distributions.” In fact, when asked about
    what happened to computers, software, and other equipment owned by Modular,
    Hoffman did not testify from personal experience, but stated, “I know the process.”
    The process he described was that someone else “decided that he would take some
    FranklinSquires staff, or whatever, and they would physically go up and get all of the
    tools, equipment, and that included the computers and all that. They put them in their
    office facility, which had a large warehouse attached.”4 This deposition testimony does
    not support a reasonable inference that Hoffman authorized Modular to make
    distributions or that any such distributions were unlawful.
    ¶18 Second, the Ceas allege that “Hoffman testified that he authorized distributions
    by Modular when Modular was a ‘financial train wreck.’” We have reviewed the pages
    of the record cited in support of this statement and, again, we conclude that they do not
    support the proposition for which the Ceas cite them.
    ¶19 The portions of Hoffman’s depositions relied on do not describe Hoffman’s
    authorizing distributions by Modular when Modular was “a financial train wreck,” but
    describe Investors’ forming Modular for the purpose of acquiring “certain assets from
    ATC” at a time when ATC was “a financial train wreck.” Investors sought to “acquire
    only certain assets” of ATC because ATC had developed “an incredible product, but the
    company itself was a financial disaster.” Accordingly, Investors “determined that no,
    we don’t want to buy the company. They had a closet full of financial skeletons that we
    did not want to go into.” This testimony does support a reasonable inference that ATC
    was insolvent, but not that Modular was insolvent, as the Ceas allege.
    4. FranklinSquires Investments, LLC holds a 50% ownership interest in Investors.
    20100728‐CA                                 7
    ¶20 In sum, the Ceas have not demonstrated a genuine issue of material fact with
    respect to this claim. We therefore affirm the trial court’s ruling on this point.5
    B. Modular
    ¶21 The Ceas also contend that they detrimentally relied on Modular’s and Investors’
    representations “by not seeking recovery of the money paid towards the construction of
    their modular home by pursuing claims against Modular and other defendants in the
    underlying case until after Modular had already ceased operations and Modular’s
    assets were already looted by Investors.” This argument is unsupported by any
    citations to the record. It is thus inadequately briefed. See Utah R. App. P. 24(a)(9)
    (“The argument shall contain . . . the contentions and reasons of the appellant with
    respect to the issues presented . . . with citations to the . . . parts of the record relied
    on.”). Moreover, the premise of the argument—that Modular was a “financial train
    wreck”—is not supported by the portions of the record the Ceas cite elsewhere in their
    brief.
    ¶22 In sum, the Ceas’ assertion that a genuine issue of material fact exists as to
    whether Hoffman or Modular committed fraud against the Ceas is not supported by
    citations to the record on appeal. We thus affirm the trial court on this issue.
    III. Contract Claims
    ¶23 The Ceas contend that the trial court erred by ruling as a matter of law that the
    Modular Letter was not an offer, that neither the First nor Second Cea Letter was an
    acceptance, and that no consideration existed for a contract. As we understand their
    argument, the Ceas maintain that the Modular Letter contained two alternative offers:
    (1) an offer to complete ATC’s agreed performance, and (2) an offer to refund the Ceas’
    deposit. The Ceas argue that the First Cea Letter constituted a valid acceptance of the
    offer to complete performance. Alternatively, the Ceas argue that the Second Cea Letter
    constituted a valid acceptance of the offer to refund their deposit.
    5. The Ceas also claim that Hoffman “personally authorized” the Modular Letter and
    therefore is contractually liable to them. As this claim appears to rest on the same
    factual theory we determine is unsupported by the record, it also fails.
    20100728‐CA                                  8
    ¶24 Generally, formation of a contract requires an offer, an acceptance, and
    consideration. See Golden Key Realty, Inc. v. Mantas, 
    699 P.2d 730
    , 732 (Utah 1985). An
    offer is a “‘manifestation of willingness to enter into a bargain, so made as to justify
    another person in understanding that his assent to the bargain is invited and will
    conclude it.’” Engineering Assocs. v. Irving Place Assocs., 
    622 P.2d 784
    , 787 (Utah 1980)
    (quoting Restatement (Second) of Contracts § 24) (1981). “For an offer to be one that
    would create a valid and binding contract, its terms must be definite and
    unambiguous.” DCM Inv. Corp. v. Pinecrest Inv. Co., 
    2001 UT 91
    , ¶ 12, 
    34 P.3d 785
    . The
    obligations of the parties must be “set forth with sufficient definiteness that [the
    contract] can be performed.” Ferris v. Jennings, 
    595 P.2d 857
    , 859 (Utah 1979); see 1
    Williston on Contracts § 4.21, at 644 (4th ed.) (discussing the definiteness of offers and
    noting that “[a] lack of definiteness in an agreement may concern the time of
    performance, the price to be paid, work to be done, property to be transferred, or
    miscellaneous stipulations to the agreement”). “The terms of a contract are reasonably
    certain if they provide a basis for determining the existence of a breach and for giving
    an appropriate remedy.” Restatement (Second) of Contracts § 33(2). An offer (other
    than an option contract) may be withdrawn at any time before acceptance. See J.R. Stone
    Co. v. Keate, 
    576 P.2d 1285
    , 1288 (Utah 1978).
    ¶25 “An acceptance is a manifestation of assent to an offer, such that an objective,
    reasonable person is justified in understanding that a fully enforceable contract has
    been made.” Cal Wadsworth Constr. Co. v. City of St. George, 
    898 P.2d 1372
    , 1376 (Utah
    1995). It “must unconditionally assent to all material terms presented in the offer,
    including price and method of performance, or it is a rejection of the offer.” 
    Id.
     “An
    offeree’s proposal of different terms from those of the offer constitutes a counteroffer,
    and no contract arises unless the original offeror accepts it unconditionally.” 
    Id. at 1377
    ;
    1 Corbin on Contracts § 3.27 (1993) (“Any expression of assent that changes the terms of
    the offer in any material respect may be operative as a counter‐offer.”). Generally, a
    counteroffer “operates as a rejection of the original offer.” 1 Williston on Contracts § 5.3,
    at 908 (4th ed.); Burton v. Coombs, 
    557 P.2d 148
    , 149 (Utah 1976) (noting that a
    counteroffer rejects the offer). The offeree’s power to accept the original offer is thereby
    terminated. See Burton, 557 P.2d at 149. However, “[i]f the original offeror accepts the
    counteroffer before it is withdrawn, a binding contract is created.” Cal Wadsworth
    Constr. Co., 898 P.2d at 1378 (citing R.J. Daum Constr. Co., 
    247 P.2d 817
    , 819 (Utah 1952)).
    ¶26 “Consideration is present when there is an act or promise given in exchange for
    the other party’s promise.” Healthcare Servs. Group Inc. v. Utah Dep’t of Health, 
    2002 UT 5
    , ¶ 17, 
    40 P.3d 591
     (citing Aquagen Int’l, Inc. v. Calrae Trust, 
    972 P.2d 411
    , 413 (Utah
    20100728‐CA                                   9
    1998)). “Thus, ‘there is consideration whenever a promisor receives a benefit or where
    [a] promisee suffers a detriment, however slight.’” 
    Id.
     (quoting Gasser v. Horne, 
    557 P.2d 154
    , 155 (Utah 1976) (alteration in original)).
    ¶27 The proponent of the contract “has the burden of showing that an offer and
    acceptance were more probable than not.” Sackler v. Savin, 
    897 P.2d 1217
    , 1222 (Utah
    1995). Whether a contract exists between parties is ordinarily a question of law,
    reviewed for correctness. See Herm Hughes & Sons, Inc. v. Quintek, 
    834 P.2d 582
    , 583
    (Utah Ct. App. 1992). Here, Appellees contend that the essential facts are undisputed.
    Although the Ceas frame the issue as one of fact—and disputed fact at that—they also
    argue that, given the existing factual picture, “a binding contractual relationship exists
    between these parties.” We thus consider the question before us to be whether the
    undisputed facts show that the parties formed a contract under the foregoing principles
    of contract formation.
    ¶28 We first consider whether the parties formed a contract for the completion of
    construction. The Ceas challenge the trial court’s ruling that the Modular Letter did not
    operate as an offer to complete construction due to the indefinite and uncertain nature
    of the contractual terms. However, we agree with Modular that, even if the Modular
    Letter operated as an offer, the First Cea Letter constituted a counteroffer and thus a
    rejection. As Modular notes, the First Cea letter sought to change material terms,
    including the specifications of the home, the location of delivery, and the time for
    completion of performance. The First Cea Letter was, therefore, a counteroffer that
    Modular did not accept. Accordingly, we affirm the trial court’s ruling that the Ceas
    and Modular did not enter into a contract for Modular to complete construction and
    delivery of the home.
    ¶29 We next consider whether the parties formed a contract for the return of the
    Ceas’ $172,116 deposit. Again, the trial court ruled that the Modular Letter was too
    indefinite and uncertain in its terms to operate as an offer. Modular likewise asserts
    that the Modular Letter was too indefinite to constitute a valid offer to refund the Ceas’
    deposit, because it was made in the context of a letter that had alternatives and options,
    indicating that the parties had not determined a course and were merely negotiating.
    We disagree.
    ¶30 The Modular Letter states that the Ceas may receive their deposit back instead of
    continuing with the construction and delivery of their home: “In lieu of a new contract
    20100728‐CA                                 10
    we will be willing to pay you whatever deposits or payments you have made to ATC
    for your home should you decide that you would prefer to cancel and just walk away.”
    It therefore expresses assent on behalf of Modular to refund the Ceas’ deposit and it
    empowers the Ceas to accept that refund, end its relationship with Modular, “and walk
    away.” Further, both parties were aware of the precise amount the Ceas had deposited,
    $172,116. The Modular Letter was therefore an effective offer to refund the deposit.
    ¶31 As noted above, the First Cea Letter included a counteroffer to Modular’s
    proposal to complete construction. However, by not accepting that counteroffer,
    Modular left the Ceas free to withdraw it, which they effectively did in the Second Cea
    Letter. The Second Cea Letter also operated as an acceptance of Modular’s offer to
    refund the deposit. That letter clearly states, “Upon further consideration, we
    respectfully request that, in accordance with your December letter, you refund the
    $172,116 we have paid as a deposit on our log home.” Nothing suggests that “the
    parties had not come to an agreement on the essential terms of the contract.” See Sackler
    v. Savin, 
    897 P.2d 1217
    , 1221 (Utah 1995).
    ¶32 However, Modular contends that the First Cea Letter, by countering and thus
    rejecting the offer to build and deliver the home, also effectively rejected the offer to
    refund the Ceas’ $172,116 deposit. In more general terms, Modular argues that where
    an offeree receives two mutually exclusive offers, a counteroffer to the first offer rejects
    not only the first offer, but the second as well.
    ¶33 Even if this position were true as a general matter—a question on which we
    express no opinion—it is not true here. A counteroffer operates as a rejection of an offer
    because “it is interpreted as being, in effect, a statement by the offeree not only that he
    will enter into the transaction on the terms stated in his counteroffer, but also by
    implication that he will not assent to the terms of the original offer.” 1 Williston on
    Contracts § 5.3, at 911 (4th ed.). Here, the Ceas’ sequential responses to Modular’s
    alternative offers must be viewed in light of the elephant in the room: Modular was
    holding the Ceas’ $172,116 deposit. The counteroffer in the First Cea Letter may be
    interpreted as a statement by the Ceas, by implication, that they rejected Modular’s
    proposal to complete construction. But it may not reasonably be interpreted as a
    statement by the Ceas, by implication, that they also rejected Modular’s offer to refund
    their $172,116 deposit.
    20100728‐CA                                  11
    ¶34 In simple terms, Modular said, “We have your $172,116. Do you want us to
    return the money or finish the job?” By counteroffering—and then withdrawing their
    counteroffer before Modular accepted it—the Ceas replied, in effect, “We don’t want
    you to finish the job.” The unstated implication of this reply was not “so just go ahead
    and keep our money”; it was, if anything, “so just go ahead and refund our money.”
    Accordingly, the First Cea Letter did not reject Modular’s refund offer, and the Second
    Cea Letter accepted it.
    ¶35 Finally, the Ceas contend that the trial court erred in ruling as a matter of law
    that the agreement was not supported by consideration. Modular conceded at oral
    argument that, assuming the Modular Letter operated as an offer to refund the Ceas’
    deposit and the Second Cea Letter operated as an acceptance of that offer, the resulting
    agreement was supported by adequate consideration.6
    ¶36 Consequently, we hold that the trial court erred in ruling as a matter of law that
    no contract was formed between Modular and the Ceas with respect to the return of the
    Ceas’ $172,116 deposit. We conclude that the undisputed record facts, together with
    Modular’s concession on appeal, demonstrate that a contract was formed between the
    Ceas and Modular for the return of the Ceas’ $172,116 deposit.7
    IV. Remaining Issues
    ¶37 In addition to the foregoing issues, the Ceas raise a number of challenges to the
    form of the trial court’s rulings. These challenges either lack merit or are rendered moot
    by our decision. Accordingly, we do not address them further. Nor do we address the
    Ceas’ claim based on the Uniform Commercial Code, as it was raised for the first time in
    their reply brief. See Allen v. Friel, 
    2008 UT 56
    , ¶ 8, 
    194 P.3d 903
     (“It is well settled that
    issues raised by an appellant in the reply brief that were not presented in the opening
    brief are considered waived and will not be considered by the appellate court.”
    (internal quotation marks omitted).
    6. This concession finds support in the record.
    7. The Ceas also contend that the record facts demonstrate the existence of a genuine
    issue of material fact as to whether Investors or Hoffman or both share Modular’s
    contractual liability. For reasons explained above, we reject this contention.
    20100728‐CA                                  12
    CONCLUSION
    ¶38 We conclude as a matter of law that Modular and the Ceas formed a contract for
    the return of the Ceas’ $172,116 deposit, and we thus reverse the ruling of the trial court
    on this point. In all other respects, we affirm the ruling of the trial court. The case is
    remanded for further proceedings consistent with this opinion. No costs or fees are
    awarded.
    ____________________________________
    J. Frederic Voros Jr.,
    Associate Presiding Judge
    ‐‐‐‐‐
    ¶39    WE CONCUR:
    ____________________________________
    Carolyn B. McHugh,
    Presiding Judge
    ____________________________________
    Stephen L. Roth, Judge
    20100728‐CA                                 13