Ross v. Epic Engineering, PC , 737 Utah Adv. Rep. 38 ( 2013 )


Menu:
  •                      
    2013 UT App 136
    _________________________________________________________
    THE UTAH COURT OF APPEALS
    JASON ROSS,
    Plaintiff and Appellant,
    v.
    EPIC ENGINEERING, PC,
    Defendant and Appellee.
    Opinion
    No. 20110537‐CA
    Filed June 20, 2013
    Eighth District, Duchesne Department
    The Honorable Edwin T. Peterson
    No. 080800020
    Aaron R. Harris and Stephen Quesenberry,
    Attorneys for Appellant
    Brent E. Johnson and Rebecca A. Ryon, Attorneys
    for Appellee
    JUDGE GREGORY K. ORME authored this Opinion, in which
    JUDGES CAROLYN B. MCHUGH and MICHELE M. CHRISTIANSEN
    concurred.
    ORME, Judge:
    ¶1     Jason Ross appeals the district court’s grant of Epic
    Engineering’s motion in limine that excluded the testimony of
    Ross’s expert. Ross also appeals the district court’s subsequent
    grant of Epic’s motion for summary judgment on Ross’s breach of
    contract claim and the resulting dismissal of Ross’s complaint with
    prejudice. We affirm.
    BACKGROUND
    ¶2     In reviewing the district court’s grant of summary judgment,
    we recite the facts in the light most favorable to Ross. See Bowers v.
    Ross v. Epic Engineering, PC
    Call, 
    2011 UT App 143
    , ¶ 2, 
    257 P.3d 433
     (per curiam). Ross retained
    Epic’s services in 2006 for the design of a small commercial
    building to be constructed in Roosevelt, Utah. The contract defined
    the scope of Epic’s work to be “structural engineering and drafting
    of [a] 70ʹ x 100ʹ office and warehouse building” for a fee of $8,250.1
    The plans prepared by Epic included the instruction that “all
    footings shall bear 12ʺ minimum into original undisturbed earth or
    on engineered fill.” Ross hired his brother as the general contractor
    for the building, and Ross’s father assisted in the excavation of the
    site for the building’s foundation.
    ¶3     After the building was constructed, it began to settle as a
    result of unconsolidated fill material underlying the site.
    Approximately ten months after Ross moved into the building, he
    notified Epic that the building was settling and that cracks had
    appeared on the interior and exterior walls. Ross claimed that Epic
    should have prepared a “soils report” as part of its engineering
    plans for the building. Epic denied that the contract required it to
    prepare a soils report and denied that the settling was the result of
    any inadequacies in the structural engineering plans, as the plans
    specifically required that “all footings shall bear 12ʺ minimum into
    original undisturbed earth or on engineered fill.”
    ¶4     Ross filed suit against Epic for breach of contract and
    negligence, arguing that Epic “breached the contract by failing to
    properly engineer the plans.” Early in the litigation, the parties
    agreed to jointly commission a geotechnical investigation to
    determine the cause of the settling. The investigation determined
    that “[n]umerous pieces of asphalt, concrete, and other debris were
    1. Epic later contended that the contract contained a second page
    of terms and conditions, including a limitation of liability and
    standard of care provision that read: “Epic[’s] services shall be
    rendered without any warranty except that Epic will perform in
    accordance with a degree of care and skill generally exercised by
    professionals performing similar work under similar conditions.”
    Ross denied ever receiving page 2 of the contract. For purposes of
    this appeal, we assume Ross is correct on this point.
    20110537‐CA                       2                
    2013 UT App 136
    Ross v. Epic Engineering, PC
    observed in each of the test pits” and that the cause of the settling
    was insufficient compaction. The investigation revealed that “the
    footings for the . . . building were placed on undocumented, loosely
    placed fill material. Moisture later infiltrated the subsurface soils
    next to the structure, causing the fill soil to settle under foundation
    loads.”
    ¶5     Ross and Epic each retained engineers to provide expert
    testimony. Ross retained a geotechnical engineer, while Epic
    secured a structural engineer who is also licensed as a
    general contractor. In his deposition, Ross’s expert explained
    that his company “provide[s] geotechnical consultation for
    new construction of buildings [and] dams. . . . We also provide
    construction materials testing to verify that earthwork and concrete
    construction is conducted in accordance with the plans and
    specifications.” He further explained that geotechnical engineers
    evaluate subsurface soil conditions and the potential impacts of
    new construction, “and from that provide recommendations for
    design of whatever constructive facility we are evaluating.”
    ¶6     Ross’s expert conceded that geotechnical engineers do not
    actually design buildings and that he did not have an opinion on
    the standard of care applicable to Epic.2 Specifically, he stated:
    2. Ross’s expert submitted a proposal to Ross estimating that the
    cost for him to develop an opinion on the standard of care would
    be $5,000. The proposal stated:
    In order to provide our professional opinion on the
    engineer’s standard of care, we recommend that the
    standard of care prevailing at the time in question be
    established through investigation. Investigation
    would include the review of reports, records or
    opinions of other professionals performing the same
    or similar service at the time in question. With this in
    mind, we would propose to visit Roosevelt City and
    Vernal City building departments to review project
    files.
    (continued...)
    20110537‐CA                       3                 
    2013 UT App 136
    Ross v. Epic Engineering, PC
    The standard of care for this project is very important
    to recognize what happened in that locale with the
    local engineers at that time. That is not something
    that we have investigated. Our entire business is
    based on other engineers calling and asking for
    guidance and help in the geotechnical area.
    He also testified that his personal experience with excavation was
    limited to operating a backhoe on two occasions: once to grade a
    road on recreational property that he owns and once to install
    window wells at his home.
    ¶7     Epic’s expert was a structural engineer and licensed general
    contractor with “over 36 years of engineering experience in
    consulting, planning, and designing municipal, commercial and
    residential projects.” In his report, Epic’s expert stated that he was
    retained to provide his professional opinion regarding the standard
    of care expected of structural engineers on projects like the one in
    this case. The expert opined:
    Geotechnical Reports are very expensive and
    typically never ordered for residential or light
    commercial buildings. If the structural engineer is
    familiar with the soils in a particular area it is
    common to use the values listed in the International
    Building Code. Essentially the International Building
    Code has published minimum values that can be
    used for construction in lieu of data obtained from a
    geotechnical report. [Epic’s engineer that prepared
    the plans] testified that he had designed similar
    projects in Roosevelt using the same design
    standards.
    2. (...continued)
    When asked at his deposition, the expert said that he did not
    perform such an investigation because he “never received a notice
    to proceed.”
    20110537‐CA                       4                
    2013 UT App 136
    Ross v. Epic Engineering, PC
    Epic’s expert also concluded that “[t]he existing contours would
    not necessarily indicate the site had been filled” and “[i]f it was
    obvious the existing contours indicated the site had been filled I
    would have expected the City building inspector to alert the
    contractor/owner he needed to provide a soil report required by the
    International Building Code[.]”
    ¶8     At the close of discovery concerning the experts’ opinions,
    Epic moved for summary judgment on both Ross’s negligence
    claim and his contract claim. Epic contended that the negligence
    claim was barred by Utah’s economic loss doctrine and that the
    breach of contract claim failed because Ross had not presented
    expert evidence demonstrating that Epic “failed to properly
    engineer the plans.” Epic asserted that Ross’s engineering expert
    was unqualified to offer an opinion as to the applicable standard of
    care. The court granted Epic’s motion in part, dismissing the
    negligence claim but denying summary judgment on the breach of
    contract claim.
    ¶9      After the matter was set for trial on the contract claim, Epic
    filed a motion in limine, essentially rearguing the points made in
    its earlier motion for summary judgment and seeking to preclude
    Ross’s expert from testifying. As also argued in the earlier motion
    for summary judgment, Epic contended that Ross’s expert, a
    geotechnical engineer, “lacked the relevant knowledge, skill, or
    experience” necessary to testify as to the standard of care expected
    of structural engineers, contractors, or excavators. At the final pre‐
    trial hearing, the district court heard argument on the motion in
    limine. Ross objected because the deadline to respond to the
    motion had not yet passed.3 After argument, the district court
    granted Epic’s motion, stating, “This expert isn’t going to be able
    to testify to the standard of care. I mean it’s very clear that he in his
    3. The district court apparently believed, albeit mistakenly, that
    there was a five‐day deadline for a party to file a response to a
    motion in limine. See Utah R. Civ. P. 7(c)(1) (“Within ten days after
    service of the motion and supporting memorandum, a party
    opposing the motion shall file a memorandum in opposition.”).
    20110537‐CA                        5                 
    2013 UT App 136
    Ross v. Epic Engineering, PC
    deposition said he wasn’t asked to make that analysis. He would
    be testifying to something that is not relevant to the case[.]” The
    court also concluded that Ross’s expert’s opinion that “a machine
    operator or contractor wouldn’t necessarily be able to determine if
    the soil they were digging into was native or fill” was contrary to
    Utah law. See Smith v. Frandsen, 
    2004 UT 55
    , ¶¶ 18–19, 
    94 P.3d 919
    (explaining that the law deems a contractor to have a high degree
    of specialized knowledge, including “familiar[ity] with conditions
    in the subsurface of the ground”).
    ¶10 The court then, sua sponte, reopened the motion for partial
    summary judgment on the breach of contract claim. The court
    clarified, “The reason the Court did not grant summary judgment
    initially on the first issue was . . . the proffer that the expert[s]
    would disagree on critical issues. They don’t.” The court then
    granted the motion, effectively eliminating all of Ross’s claims, and
    it dismissed Ross’s complaint with prejudice. Ross appeals.
    ISSUES AND STANDARDS OF REVIEW
    ¶11 Ross contends that the district court incorrectly granted
    Epic’s motion in limine, which effectively precluded the
    introduction of his expert’s testimony. “A decision to admit or
    exclude expert testimony is left to the discretion of the trial court,
    and that decision will not be reversed unless it constitutes an abuse
    of discretion.” State v. Holm, 
    2006 UT 31
    , ¶ 89, 
    137 P.3d 726
     (citation
    omitted). “Our review of the district court’s exercise of its
    discretion includes review to ensure that no mistakes of law
    affected a lower court’s use of its discretion.” Eskelson ex rel.
    Eskelson v. Davis Hosp. & Med. Ctr., 
    2010 UT 59
    , ¶ 5, 
    242 P.3d 762
    (citation and internal quotation marks omitted).
    ¶12 Ross also argues that the district court erred when it decided
    Epic’s motion in limine before the expiration of the time allowed
    for him to respond under the Utah Rules of Civil Procedure. “We
    review the interpretation and application of a rule of procedure for
    correctness.” Edwards v. Powder Mountain Water & Sewer, 
    2009 UT App 185
    , ¶ 14, 
    214 P.3d 120
    . However, “‘[i]n order to justify
    20110537‐CA                       6                 
    2013 UT App 136
    Ross v. Epic Engineering, PC
    reversal[,] the appellant must show error that was substantial and
    prejudicial in the sense there is at least a reasonable likelihood that
    in the absence of the error the result would have been different.’”
    Commonwealth Prop. Advocates, LLC v. Mortgage Elec. Registration
    Sys., Inc., 
    2011 UT App 232
    , ¶ 6, 
    263 P.3d 397
     (second alteration in
    original) (quoting Ortega v. Thomas, 
    383 P.2d 406
    , 408 (Utah 1963)).
    See Utah R. Civ. P. 61 (“The court at every stage of the proceeding
    must disregard any error or defect in the proceeding which does
    not affect the substantial rights of the parties.”). Epic does not
    contend that the district court’s interpretation of the applicable rule
    was correct, but it argues that the error was harmless because the
    expert’s qualifications and all other relevant matters had been fully
    briefed during the earlier summary judgment proceedings.
    ¶13 Finally, Ross contends that genuine issues of material fact
    exist, precluding summary judgment as a matter of law. See Utah
    R. Civ. P. 56(c). “An appellate court reviews a trial court’s legal
    conclusions and ultimate grant or denial of summary judgment for
    correctness and views the facts and all reasonable inferences drawn
    therefrom in the light most favorable to the nonmoving party.”
    Orvis v. Johnson, 
    2008 UT 2
    , ¶ 6, 
    177 P.3d 600
     (citations and internal
    quotation marks omitted). A defendant, as the party moving for
    summary judgment on an issue on which the plaintiff will have the
    burden of proof at trial,
    may satisfy its burden on summary judgment by
    showing, by reference to “the pleadings, depositions,
    answers to interrogatories, and admissions on file,
    together with the affidavits, if any,” that there is no
    genuine issue of material fact. Upon such a showing,
    . . . the burden then shifts to the nonmoving party,
    who “may not rest upon the mere allegations or
    denials of the pleadings,” but “must set forth specific
    facts showing that there is a genuine issue for trial.”
    
    Id. ¶ 18
     (emphasis in original) (quoting Utah R. Civ. P. 56(c)).
    20110537‐CA                       7                 
    2013 UT App 136
    Ross v. Epic Engineering, PC
    ANALYSIS
    I. The District Court Did Not Abuse Its Discretion When It
    Excluded the Testimony of Ross’s Expert.
    ¶14 In his complaint, Ross alleged that Epic “breached the
    contract by failing to properly engineer the plans.” Because the
    contract was silent on the parties’ relevant expectations and
    obligations, both Ross and Epic retained expert witnesses to
    provide insight on the appropriate standard of care for a structural
    engineer.4
    Where the average person has little understanding of
    the duties owed by particular trades or professions,
    expert testimony must ordinarily be presented to
    establish the standard of care. For instance, expert
    testimony has been required to establish the standard
    of care for medical doctors, architects, engineers,
    insurance brokers, and professional estate executors.
    4. As a point of clarification, while the term “standard of care” is
    usually employed in a tort setting, the parties and the district court
    used it in this contract dispute in reference to the possibility that
    Epic had an implied obligation to have a soils report prepared as
    part of its contractual duties in preparing building plans. While we
    employ the terminology used in the arguments and analysis as
    posed by the parties and the district court, we would be remiss if
    we did not point out that this is really more a matter of whether
    there was an implied contractual term rather than of establishing
    a “standard of care” as the term is typically used.
    A term is implied‐in‐law where the contract is silent.
    An implied‐in‐law term will be imposed even though
    the parties may not have intended it and binds the
    parties to a legally enforceable duty. However, the
    court can only supply reasonable terms to
    supplement a contract which is silent.
    Allstate Enters., Inc. v. Heriford, 
    772 P.2d 466
    , 468 (Utah Ct. App.
    1989) (citations omitted).
    20110537‐CA                       8                
    2013 UT App 136
    Ross v. Epic Engineering, PC
    Wycalis v. Guardian Title, 
    780 P.2d 821
    , 826 n.8 (Utah Ct. App. 1989)
    (emphasis added) (citations omitted).
    ¶15 Ross argues that the district court abused its discretion in
    excluding the testimony of his expert witness. Rule 702 of the Utah
    Rules of Evidence specifies that
    a witness who is qualified as an expert by
    knowledge, skill, experience, training, or education
    may testify in the form of an opinion or otherwise if
    the expert’s scientific, technical, or other specialized
    knowledge will help the trier of fact to understand
    the evidence or to determine a fact in issue.
    Utah R. Evid. 702(a). “The trial court is given discretion under Rule
    702 of the Utah Rules of Evidence to determine the admissibility of
    expert testimony, and to determine if the expert witness is qualified
    to give an opinion on a particular matter.” Dikeou v. Osborn, 
    881 P.2d 943
    , 947 (Utah Ct. App. 1994) (brackets, citation, and internal
    quotation marks omitted).
    ¶16 Ross argued that his expert was qualified to provide
    testimony about the standard practices of structural engineers
    because the expert was a licensed engineer. Utah law requires that
    “the standard of care in a trade or profession generally must be
    determined by testimony of witnesses in the same trade or
    profession.” Ortiz v. Geneva Rock Prods., Inc., 
    939 P.2d 1213
    , 1217 n.2
    (Utah Ct. App. 1997) (brackets, citation, and internal quotation
    marks omitted). But not every engineer is qualified to opine about
    the standard of care or the standard practices applicable to all other
    engineers.
    ¶17 We recognize that “[a]n expert witness belonging to one
    school may testify against a member of another school once the
    expert provides sufficient foundation to show that the method of
    treatment at issue is common to both schools or that the expert is
    knowledgeable about the standard of care of the other school.”
    Boice v. Marble, 
    1999 UT 71
    , ¶ 14, 
    982 P.2d 565
    . See also Arnold v.
    20110537‐CA                       9                 
    2013 UT App 136
    Ross v. Epic Engineering, PC
    Curtis, 
    846 P.2d 1307
    , 1310 (Utah 1993) (stating that a witness is
    allowed to testify “when a witness is knowledgeable about the
    standard of care of another specialty or when the standards of
    different specialties on the issue in a particular case are the same”).
    On the other hand, an expert may be excluded if unable to establish
    a common standard of care. See, e.g., Burton v. Youngblood, 
    711 P.2d 245
    , 248 (Utah 1985) (“The trial court did not hold that a member
    of one school cannot testify against a member of another school as
    a matter of law. It only held that under the facts of this case, the
    foundation necessary to allow a member of one medical specialty
    to testify about the standard of care applicable to a member of
    another medical specialty had not been established.”).
    ¶18 We disagree with Ross’s contention that his expert “opined
    about a standard of care that applies to all engineers, regardless of
    their specialty.” On the contrary, Ross’s expert admitted that he
    was not asked to and did not prepare an opinion as to the standard
    of care applicable to Epic. The expert acknowledged that
    geotechnical engineers—of which he is one—do not design
    buildings and that he would need to conduct an investigation
    involving the “review of reports, records or opinions of other
    professionals performing the same or similar service at the time in
    question” in order to develop an opinion on the standard of
    care applicable here. An opinion developed through such an
    undertaking would not be the result of his “knowledge, skill,
    experience, training, or education,” as required by the Utah Rules
    of Evidence. See Utah R. Evid. 702(a). See also Dikeou, 
    881 P.2d at 947
     (“By definition, an expert [in the context of a medical
    malpractice claim] is one who possesses a significant depth and
    breadth of knowledge on a given subject. To allow a doctor in one
    specialty, retained as an expert witness, to become an ‘expert’ on
    the standard of care in a different medical specialty by merely
    reading and studying the documents in a given case invites
    confusion, error, and a trial fraught with unreliable testimony.”).
    Therefore, we agree that Ross’s expert was not qualified to opine
    on the standard of care expected of Epic.
    20110537‐CA                       10                
    2013 UT App 136
    Ross v. Epic Engineering, PC
    ¶19 The remainder of Ross’s expert’s contentions related either
    to evidence not in dispute or to matters in which he lacked relevant
    experience or knowledge. For example, Ross’s expert stated in his
    report that an engineer looking at the lot where the building was
    to be constructed should have been immediately concerned with
    the obvious fill and the slope on the lot.5 However, the expert could
    not testify whether such an observation would then entail a related
    obligation for Epic under the contract. The expert opined “that a
    machine operator or contractor wouldn’t necessarily be able to
    determine if the soil they were digging into was native or fill based
    on personal experience in determining if a soil mass is fill or
    naturally deposited.” But, he was not qualified to offer this opinion
    because his personal experience in excavation was limited to two
    small personal projects. His opinion is also contradictory to our
    Supreme Court’s decision in Smith v. Frandsen, 
    2004 UT 55
    , 
    94 P.3d 919
    , which states that “builder‐contractors are expected to be
    familiar with conditions in the subsurface of the ground.” 
    Id. ¶ 19
    .
    See 
    id. ¶ 20
     (“The facts indicate that [the employee of the general
    contractor] supervising the excavation and placement of the . . .
    foundation had ‘no prior construction experience.’ Nevertheless,
    [the employee] is deemed to possess the knowledge of a reasonably
    prudent builder‐contractor under similar circumstances, and, as a
    matter of law, a builder of ordinary prudence would have
    discovered the insufficient compaction on [the] lot[.]”).
    ¶20 While Frandsen involved tort claims, see 
    id. ¶ 1,
     the
    underlying logic is equally applicable here. Like Frandsen, this case
    involves the determination of where liability should fall when no
    contractual provision specifies which party has the duty to assess
    whether a building site can support the planned structure. See 
    id. ¶ 27
     (“As a policy matter, we believe that our holding will
    5. Epic’s limited contractual responsibility was to prepare building
    plans. The contract terms do not include a requirement that Epic
    inspect the building site. Ross’s expert did not testify—and was not
    qualified to testify—about whether an agreement to prepare such
    plans necessarily implied an obligation to walk the ground where
    the building would be constructed.
    20110537‐CA                      11                
    2013 UT App 136
    Ross v. Epic Engineering, PC
    encourage builders and contractors to exercise that level of care
    consistent with the expertise legally imputed to them. In addition,
    our decision preserves the contractual expectations of developers
    and builder‐contractors.”). Likewise, we reject Ross’s argument
    that the case “certainly does not stand for the proposition that
    [Epic] was absolved of a contractual duty based upon a contractor’s
    presence on the property” because Ross failed to provide any
    admissible evidence or testimony indicating that such a duty was
    imputed to Epic.6
    ¶21 The remainder of the expert testimony offered by Ross
    related to undisputed matters concerning the cause of the
    building’s settling, the extent of the settling, and the measures that
    would be required to stabilize the building. The court was within
    its discretion to conclude that the expert did not qualify under rule
    702 to offer his opinions either because he was unqualified to so
    opine or because the issue was not in dispute. Accordingly, the
    district court properly granted Epic’s motion in limine that
    excluded Ross’s expert’s testimony.
    II. The District Court’s Error in Prematurely Ruling on Epic’s
    Motion in Limine Does Not Warrant Reversal.
    ¶22 It is undisputed that the district court ruled on Epic’s motion
    in limine prior to the deadline provided by rule 7(c) of the Utah
    Rules of Civil Procedure. See Utah R. Civ. P. 7(c) (“Within ten days
    6. In essence, Ross claims that Epic, as the structural engineer in
    this case, was required to have a soils report prepared even though
    structural engineers are unable to perform such analyses
    themselves. Ross’s expert testified that performing a geotechnical
    study of the site prior to construction would have cost between
    $4,000 and $5,000, while Epic’s fees under the contract were $8,250.
    If fully half (or more) of Epic’s fee were allocable to outsourcing a
    soils study, surely the contract would have referred to this
    important aspect of the contracted‐for work and would not have
    described the scope of work as being limited to the preparation of
    plans.
    20110537‐CA                      12                
    2013 UT App 136
    Ross v. Epic Engineering, PC
    after service of the motion and supporting memorandum, a party
    opposing the motion shall file a memorandum in opposition.”).
    Such an error does not warrant reversal, however, if it is
    “sufficiently inconsequential so no reasonable likelihood exists that
    the error affected the outcome of the proceedings.” Jones v. Cyprus
    Plateau Mining Corp., 
    944 P.2d 357
    , 360 (Utah 1997). Ross argues
    that we are in no position to decide “whether or not [his expert]
    was qualified to testify, because [Ross] had no chance even to
    create a record of [the expert’s] specific qualifications.” We
    disagree. In fact, it was the expert’s own testimony that provided
    the district court with the foundation for its ruling. The expert
    stated that he did not have an opinion on the relevant standard of
    care and that he would need to perform an investigation to form
    such an opinion.
    ¶23 Likewise, Ross was not prejudiced by the premature ruling
    because the district court’s consideration of the motion in limine
    involved essentially the same evidence submitted with the earlier
    summary judgment motion. Ross seemed to acknowledge this fact
    in arguing against the motion in limine, telling the court, “They
    made the same argument in their summary judgment motion. The
    exact same argument was there.” While additional time may have
    allowed Ross to refine his arguments somewhat, he points to
    nothing new that he would have added had he been permitted the
    opportunity to submit a memorandum in opposition to the motion.
    And from all that appears, the pivotal analysis by the district court
    would have remained the same. See Utah R. Civ. P. 61 (stating that
    an error is harmless and does not warrant disruption of a ruling or
    order if it “does not affect the substantial rights of the parties”).
    Therefore, Ross was not prejudiced by the district court’s error, and
    we decline to overturn its ruling.
    III. The District Court Correctly Granted Epic’s Motion for
    Summary Judgment on the Breach of Contract Claim.
    ¶24 While the district court initially denied Epic’s motion for
    summary judgment on Ross’s contract claim, a trial court has the
    authority to revisit any prior ruling so long as a final judgment has
    20110537‐CA                      13                
    2013 UT App 136
    Ross v. Epic Engineering, PC
    not been entered in the case. IHC Health Servs., Inc. v. D&K Mgmt.,
    Inc., 
    2008 UT 73
    , ¶ 27, 
    196 P.3d 588
    . Summary judgment is proper
    whenever there is no genuine issue of material fact and the moving
    party is entitled to judgment as a matter of law. See Utah R. Civ. P.
    56(c). When the district court revisited its ruling on the motion for
    summary judgment on the breach of contract claim, it explained
    that “[t]he reason the Court did not grant summary judgment
    initially on the first issue was . . . the proffer that the expert[s]
    would disagree on critical issues. They don’t.” Ross, however,
    alleges that a standard of care analysis is not essential to his breach
    of contract claim and granting summary judgment on that basis
    was inappropriate. Ross seemingly claims that the jury must first
    determine whether there was a page 2 to the contract, which the
    parties dispute, and that only then does the standard of care
    analysis become potentially relevant. In so arguing, Ross overlooks
    that we must review the facts in a light most favorable to him,
    including that there was no page 2.
    ¶25 Without the second page, which Epic claimed defined and
    limited its liability under the contract, Ross is better positioned to
    argue that Epic was expected, as an inherent requirement of
    building plan preparation, to undertake a soil study of the property
    and assess whether the soils on the building site complied with the
    standard—“original undisturbed earth or . . . engineered
    fill”—called for in the plans Epic prepared. But it would still be
    necessary to determine whether investigation of the soil on the
    building site was an implied term of the structural engineering
    contract.7
    ¶26 The crux of the dispute, then, is whether it is generally
    understood that a structural engineer owes a duty to determine the
    7. Ross’s brother, who served as general contractor on the project
    and who presumably was not named as a defendant by reason of
    the family connection, admitted that he was not aware whether a
    soils analysis had been performed by Epic, which we assume
    means he never asked to see such a report and that he would not
    necessarily be able to recognize non‐native soil.
    20110537‐CA                       14                
    2013 UT App 136
    Ross v. Epic Engineering, PC
    type of soil on a building site, such that in a case where the contract
    is silent on the issue and calls only for the preparation of plans, it
    is nonetheless reasonable to assume the parties intended to impose
    such a requirement. Because we have determined that the district
    court correctly excluded the testimony of Ross’s expert witness, the
    only admissible testimony bearing on the question was that of
    Epic’s expert witness. Epic’s expert testified that soil reports are not
    typically ordered for projects of this size and that it is proper for
    the engineer preparing the plans to simply incorporate the values
    listed in the International Building Code, as was done here.8 Epic’s
    expert’s opinion dovetails with the decision in Smith v. Frandsen,
    
    2004 UT 55
    , 
    94 P.3d 919
    , which held that “builder‐contractors are
    expected to be familiar with conditions in the subsurface of the
    ground.” 
    Id. ¶ 19
    . Because Ross was unable to “set forth specific
    facts showing that there is a genuine issue for trial” concerning this
    issue, see Utah R. Civ. P. 56(e), the district court correctly granted
    summary judgment to Epic.
    CONCLUSION
    ¶27 We conclude that the district court did not abuse its
    discretion under rule 702 of the Utah Rules of Evidence when it
    granted Epic’s motion in limine excluding the testimony of Ross’s
    expert witness. The district court’s procedural error in ruling on the
    motion before allowing Ross the requisite time to reply under the
    Utah Rules of Civil Procedure had no impact on the outcome and
    therefore does not warrant reversal. Because there is no genuine
    issue of material fact bearing on the pivotal contract issue, the
    district court correctly granted summary judgment to Epic on the
    breach of contract claim.
    ¶28    Affirmed.
    8. Indeed, Epic’s expert testified that he had previously designed
    similar projects in Roosevelt using exactly the same design
    standards.
    20110537‐CA                       15                
    2013 UT App 136