Willis v. DeWitt , 786 Utah Adv. Rep. 28 ( 2015 )


Menu:
  •                      
    2015 UT App 123
    _________________________________________________________
    THE UTAH COURT OF APPEALS
    WILLIAM D. WILLIS AND PAULA A. WILLIS,
    Plaintiffs and Appellants,
    v.
    RAYMOND C. DEWITT AND RC DEWITT CONSTRUCTION, INC.,
    Defendants and Appellees.
    Opinion
    No. 20130867-CA
    Filed May 14, 2015
    Fifth District Court, St. George Department
    The Honorable James L. Shumate
    No. 120500368
    Darwin C. Fisher, Attorney for Appellants
    Peter H. Barlow, Sadé A. Turner, Heinz J. Mahler,
    and Andrew R. Hale, Attorneys for Appellees
    JUDGE MICHELE M. CHRISTIANSEN authored this Opinion, in
    which JUDGES J. FREDERIC VOROS JR. and STEPHEN L. ROTH
    concurred.
    CHRISTIANSEN, Judge:
    ¶1     William D. and Paula A. Willis appeal from the district
    court’s grant of summary judgment in favor of Raymond C. DeWitt
    and RC DeWitt Construction, Inc. (collectively, DeWitt). We affirm.
    BACKGROUND
    ¶2    In 2005, the Willises contracted with DeWitt for the
    construction of a new house in a residential development. Before
    constructing any houses in the development, DeWitt discovered
    Willis v. DeWitt
    that expansive soil was present in multiple lots in the
    development.1 As a result, DeWitt had the top sixteen feet of soil
    removed from the affected areas and replaced with compacted fill.
    DeWitt was aware that the fill mixture included some amount of
    expansive soil but believed that the fill would not be expansive and
    that the fill provided “a very safe condition to build upon.”
    ¶3     DeWitt commenced construction on the Willises’ house, and
    the Willises took possession of the completed home on December
    27, 2005. Within a few months, the Willises began to notice defects
    in the home that appeared to be related to earth movement or
    settlement, such as cracking of their driveway, garage ceiling, and
    exterior walls. In 2008, the Willises received a letter from a
    neighbor claiming that damage to neighborhood homes was caused
    by expansive soil.
    ¶4      The Willises filed suit against DeWitt in June 2012, asserting
    claims of fraudulent misrepresentation, fraudulent nondisclosure,
    negligent misrepresentation, breach of contract, breach of the
    covenant of good faith and fair dealing, and breach of implied
    warranty for DeWitt’s failure to disclose the presence of expansive
    soil in the development. DeWitt moved for summary judgment,
    arguing that the Willises’ claims were time-barred by the relevant
    statutes of limitations. The district court granted summary
    judgment in favor of DeWitt on the Willises’ fraud and breach-of-
    implied-warranty claims. The district court initially denied
    DeWitt’s motion for summary judgment on the Willises’ claims for
    breach of contract and breach of the covenant of good faith and fair
    dealing. The court explained that “there is a question of fact as to
    whether or not any ‘fraudulent concealment’ took place,” which
    the court believed could allow the Willises to “invoke the discovery
    rule and thereby toll the statute of limitations” with respect to
    those claims.
    1. Expansive soil can damage building foundations by swelling as
    it absorbs water and contracting as it dries.
    20130867-CA                       2                
    2015 UT App 123
    Willis v. DeWitt
    ¶5     DeWitt filed a new motion for summary judgment
    addressing the fraudulent-concealment issue, and the district court
    concluded that the undisputed evidence showed that the Willises
    had knowledge of their claims on February 28, 2006. The district
    court therefore concluded that the Willises’ contract-based claims
    brought on June 15, 2012, were time-barred under the six-year
    limitations period for contract actions against a builder. The
    Willises appeal.
    ISSUE AND STANDARD OF REVIEW
    ¶6      The Willises challenge the district court’s grant of summary
    judgment dismissing their claims for breach of contract and breach
    of the covenant of good faith and fair dealing.2 “[W]e review a
    district court’s grant of summary judgment for correctness,
    considering only whether the trial court correctly applied the law
    and correctly concluded that no disputed issues of material fact
    existed.” Francis v. State, 
    2013 UT 65
    , ¶ 19, 
    321 P.3d 1089
     (citation
    and internal quotation marks omitted).
    ANALYSIS
    ¶7     The Willises argue that the district court erred both in
    concluding that there was no genuine dispute as to when the
    Willises had knowledge of their claims and in concluding that “the
    discovery rule does not apply to toll the statute of limitations.” We
    do not directly reach the issues raised by the Willises, because we
    affirm the district court’s grant of summary judgment on the
    alternative ground that Utah Code section 78B-2-225(3)(a) is a
    statute of repose not subject to equitable tolling and there are no
    2. The Willises do not appeal the district court’s grant of summary
    judgment on their fraud or breach-of-warranty claims.
    20130867-CA                      3                
    2015 UT App 123
    Willis v. DeWitt
    disputed facts regarding when that statute began to run or when
    it expired.
    I. Utah Code Section 78B-2-225(3)(a) Is a Statute of Repose.
    ¶8      “A statute of limitations requires a lawsuit to be filed within
    a specified period of time after a legal right has been violated or the
    remedy for the wrong committed is deemed waived.” Berry ex rel.
    Berry v. Beech Aircraft Corp., 
    717 P.2d 670
    , 672 (Utah 1985). “A
    statute of repose bars all actions after a specified period of time has
    run from the occurrence of some event other than the occurrence
    of an injury that gives rise to a cause of action.” 
    Id.
     Once the
    statutory period set by a statute of repose expires, “any cause of
    action is barred regardless of usual reasons for tolling the statute.”
    Perry v. Pioneer Wholesale Supply Co., 
    681 P.2d 214
    , 219 (Utah 1984)
    (internal quotation marks omitted). Thus, a party’s ignorance of the
    injury, which is generally a ground for equitable tolling of a statute
    of limitations, does not toll a statute of repose. See 
    id. ¶9
         Utah Code section 78B-2-225 governs actions against
    providers of construction services for work done on a building site.
    Utah Code Ann. § 78B-2-225(1)(f), (3)(a) (LexisNexis 2008).3 A
    homebuilder such as DeWitt is a provider as defined by the statute,
    see id. § 78B-2-225(1)(f), and section 78B-2-225(3)(a) therefore
    governs the Willises’ claims here. That subsection states, “An action
    by or against a provider based in contract or warranty shall be
    commenced within six years of the date of completion of the
    improvement or abandonment of construction.” Id. § 78B-2-
    225(3)(a). By its plain language, this statute “bars all actions after a
    specified period of time has run from the occurrence of some event
    3. Although the Willises’ house was completed in December 2005,
    we cite the 2008 codification of the statute at Utah Code section
    78B-2-225 because our legislature has directed that section 78B-2-
    225 “applies to all causes of action that accrue after May 3, 2003.”
    Utah Code Ann. § 78B-2-225(11) (LexisNexis 2008).
    20130867-CA                        4                
    2015 UT App 123
    Willis v. DeWitt
    other than the occurrence of an injury.” See Berry, 717 P.2d at 672.
    Utah Code section 78B-2-225(3)(a) is therefore a statute of repose.4
    ¶10 This conclusion is bolstered by our supreme court’s
    interpretation of Utah Code section 78-12-25.5 in Craftsman Builder’s
    Supply, Inc. v. Butler Manufacturing Co., 
    1999 UT 18
    , 
    974 P.2d 1194
    .
    There, the court concluded that section 78-12-25.5, a predecessor to
    section 78B-2-225, was a statute of repose. 
    Id.
     In Craftsman, the
    statute at issue stated that “no action for breach of contract or
    warranty may be commenced against a provider more than six
    years after completion of the improvement or abandonment of
    construction” and established a twelve-year limitations period for
    all other actions. 
    Id. ¶ 24
     (quoting Utah Code Ann. § 78-12-25.5(4)
    (Michie 1996)); see also Utah Code Ann. § 78-12-25.5(5). The
    supreme court held that “[b]ecause these periods start to run on the
    date of completion or abandonment of the improvement without
    regard to the ‘occurrence of an injury that gives rise to a cause of
    action,’ they are statutes of repose.” Craftsman, 
    1999 UT 18
    , ¶ 26
    (quoting Berry, 717 P.2d at 672). The court then concluded that “the
    statute of repose provisions are not subject to a discovery rule” and
    barred the plaintiff’s claims. Id. ¶ 27. Given that the language of
    section 78B-2-225(3)(a) is functionally identical to the language
    4. The Willises assert that “[t]he issue of whether Utah Code Ann.
    § 78B-2-225(3)(a) is a statute of repose or a statute of limitations was
    never presented to the court or decided by the trial court, and is
    raised by [DeWitt] for the first time on [the] Willises’ appeal.” The
    Willises therefore argue that we should “refuse to consider” this
    issue. However, even if we were to conclude that DeWitt failed to
    raise this issue in the district court, that conclusion would not bar
    our consideration of the issue, because “[w]e may affirm a
    judgment on an unpreserved alternate ground where the alternate
    ground is apparent on the record.” Angel Investors, LLC v. Garrity,
    
    2009 UT 40
    , ¶ 38, 
    216 P.3d 944
     (citation and internal quotation
    marks omitted). Because the record is adequate for us to affirm on
    this alternative ground, we exercise our discretion to do so here.
    20130867-CA                        5                
    2015 UT App 123
    Willis v. DeWitt
    considered in Craftsman, we conclude that section 78B-2-225(3)(a)
    is likewise a statute of repose.
    ¶11 The Willises argue that section 78B-2-225(3)(a) is not a
    statute of repose because this court, in Moore v. Smith, 
    2007 UT App 101
    , 
    158 P.3d 562
    , affirmed a district court’s equitable tolling of the
    limitations period set forth in Utah Code section 78-12-21.5(3)(a).
    Section 78-12-21.5 was recodified in 2008 as section 78B-2-225, and
    the relevant provision of section 78B-2-225 is identical to the
    provision analyzed in Moore. Compare Utah Code Ann. § 78-12-
    21.5(3)(a) (Lexis Supp. 1999), with Utah Code Ann. § 78B-2-225(3)(a)
    (LexisNexis 2008). However, the issue before this court in Moore
    was whether a trial court may apply an equitable discovery rule to
    a statutory limitations period that does not include an “internal,”
    or statutory, discovery rule. 
    2007 UT App 101
    , ¶¶ 26–29. The
    question of whether section 78-12-21.5(3)(a) was a statute of
    repose—and thus whether the trial court erred in tolling the
    limitations period on that basis—was never addressed in Moore and
    does not appear to have been raised by the appellant as a ground
    for reversal.5 
    Id.
     Moore therefore did not decide whether section
    78-12-21.5(3)(a) was a statute of repose, and its holding is not
    inconsistent with our conclusion that section 78B-2-225(3)(a) is a
    statute of repose.
    II. The Willises’ Contract-Based Claims Are Barred by Utah Code
    Section 78B-2-225(3)(a).
    ¶12 Having concluded that Utah Code section 78B-2-225(3)(a) is
    a statute of repose, we next consider whether the Willises’ contract
    5. The appellants in Moore v. Smith did argue that “the legislature
    intended to hold contract claims related to property improvements
    outside of the application of any discovery rule.” 
    2007 UT App 101
    ,
    ¶ 28, 
    158 P.3d 562
    . However, this court held that the appellants
    “provide[d] no authority for this legislative intent argument,” and
    we rejected the argument without addressing its merits. 
    Id. 20130867
    -CA                       6                 
    2015 UT App 123
    Willis v. DeWitt
    claims are time-barred under that statute. “An action by or against
    a provider based in contract or warranty shall be commenced
    within six years of the date of completion of the improvement or
    abandonment of construction.” Utah Code Ann. § 78B-2-225(3)(a)
    (LexisNexis 2008). It is undisputed that DeWitt completed
    construction and the Willises took possession of the house on
    December 27, 2005. The Willises therefore needed to commence any
    contract or warranty action against DeWitt within six years of that
    date. The Willises did not file suit until June 15, 2012. As a result,
    their contract claims are time-barred under the statute.6 We
    therefore affirm the district court’s summary judgment dismissing
    the Willises’ claims.
    CONCLUSION
    ¶13 Utah Code section 78B-2-225(3)(a) is a statute of repose and
    therefore may not be tolled by application of a discovery rule. The
    Willises’ contract claims were not brought within six years of the
    completion of construction as required by statute, and are thus
    time-barred. We affirm the district court’s summary judgment.
    6. The Willises’ fraudulent-concealment argument is premised on
    a variation of the discovery rule that is applicable in cases
    involving statutes of limitations. See Berenda v. Langford, 
    914 P.2d 45
    , 51–52 (Utah 1996). Because Utah Code section 78B-2-225(3)(a)
    is a statute of repose, “the discovery rule cannot operate to toll” the
    six-year limit. See Kunz v. Kunz (In re Marriage of Kunz), 
    2006 UT App 151
    , ¶ 21, 
    136 P.3d 1278
    . The Willises have raised no argument
    that the circumstances of this case justify an exception to this rule.
    20130867-CA                       7                 
    2015 UT App 123
                                

Document Info

Docket Number: 20130867-CA

Citation Numbers: 2015 UT App 123, 350 P.3d 250, 786 Utah Adv. Rep. 28, 2015 Utah App. LEXIS 125, 2015 WL 2242547

Judges: Christiansen, Voros, Roth

Filed Date: 5/14/2015

Precedential Status: Precedential

Modified Date: 10/19/2024