Utah State Eng'r v. Johnson (In Re Utah Lake & Jordan River) , 427 P.3d 558 ( 2018 )


Menu:
  •                       
    2018 UT App 109
    THE UTAH COURT OF APPEALS
    IN THE MATTER OF THE GENERAL DETERMINATION OF THE RIGHTS TO
    THE USE OF ALL THE WATER, BOTH SURFACE AND UNDERGROUND,
    WITHIN THE DRAINAGE AREA OF UTAH LAKE AND JORDAN RIVER IN
    UTAH, SALT LAKE, DAVIS, SUMMIT, WASATCH, SANPETE AND JUAB
    COUNTIES, IN UTAH.
    UTAH STATE ENGINEER, PROVO RIVER WATER USERS ASSOCIATION,
    METROPOLITAN WATER DISTRICT OF SALT LAKE & SANDY, UTAH
    LAKE DISTRIBUTING COMPANY, CENTRAL UTAH WATER
    CONSERVANCY DISTRICT, AND UNITED STATES OF AMERICA,
    Appellees,
    v.
    EVAN JOHNSON,
    Appellant.
    Opinion
    No. 20160547-CA
    Filed June 14, 2018
    Third District Court, Salt Lake Department
    The Honorable Laura Scott
    No. 360057298
    Cole S. Cannon and Jared C. Clark,
    Attorneys for Appellant
    Sean D. Reyes, Sarah M. Shechter, Benjamin J. Jensen,
    Margaret C. Osswald, and Norman K. Johnson,
    Attorneys for Appellee Utah State Engineer
    Shawn E. Draney, Scott H. Martin, and Danica N.
    Cepernich, Attorneys for Appellees Provo River
    Water Users Association, Metropolitan Water
    District of Salt Lake & Sandy, and Utah Lake
    Distributing Company
    Utah State Engineer v. Johnson
    Steven E. Clyde, Edwin C. Barnes, Aaron D. Lebenta,
    and Emily E. Lewis, Attorneys for Appellee Central
    Utah Water Conservancy District
    John C. Cruden, Nicholas A. Dimascio, Jeannette F.
    Swent, and Katherine W. Hazard, Attorneys for
    Appellee United States of America
    JUDGE JILL M. POHLMAN authored this Opinion, in which
    JUDGES GREGORY K. ORME and DAVID N. MORTENSEN concurred.
    POHLMAN, Judge:
    ¶1   Evan Johnson appeals the district court’s grant of
    summary judgment to the Utah State Engineer (Engineer),
    whereby the court dismissed Johnson’s objection to Engineer’s
    Amendment to the Proposed Determination (the Amendment)
    for the Goshen Valley Subdivision and affirmed the
    Amendment. We affirm.
    BACKGROUND
    ¶2      This case involves adjudication of water rights within the
    drainage area of Utah Lake and Jordan River. In 1981, Johnson’s
    predecessor in interest, the East Warm Creek Irrigation and
    Canal Company (the Company), filed a statement of water user’s
    claim (the Original Claim) in the Utah Lake and Jordan River
    adjudication. The Company claimed right to 4.96 cubic feet per
    second of water from Warm Springs to irrigate 407.5 acres of
    land and water 250 livestock units based on a priority date
    before 1900. In 1985, Engineer prepared and filed with the
    district court a Proposed Determination for the Goshen Valley
    Subdivision, of which the Original Claim was a part. No party—
    including the Company or Johnson—filed an objection to the
    Proposed Determination.
    20160547-CA                     2                  
    2018 UT App 109
    Utah State Engineer v. Johnson
    ¶3     In 1999, nearly fourteen years later, the Company filed a
    diligence claim (the Diligence Claim) with Engineer in which it
    claimed water rights from Warm Springs to irrigate an
    additional 64.6 acres of land. In its explanatory remarks, the
    Company represented that the “owner for this diligence claim is
    the same as the original diligence claim,” referring to the
    Original Claim filed in 1981. It also explained that “[t]he original
    claim only accounted for 407.5 acres and the company wants to
    apply for the 64.6 acres that were left off and have always been
    used by [the Company].” Approximately two weeks after filing
    the Diligence Claim, the Company transferred a fifty percent
    interest in the Diligence Claim to Johnson.
    ¶4      In October 2000, and after conducting some on-site
    evaluation of the Diligence Claim, Engineer filed with the
    district court the Amendment, which recommended to the court
    that the Diligence Claim be disallowed. Johnson objected to the
    Amendment. After many years of discovery and negotiations
    between Johnson and Engineer—which included a failed
    stipulation between the two as to the Diligence Claim—Engineer
    in 2016 moved for summary judgment on Johnson’s objection.
    Engineer characterized the Diligence Claim as “an attempt to
    claim additional acreage that the Company failed to include” in
    the Original Claim. Engineer argued that the Diligence Claim
    was barred by Utah Code section 73-4-9 due to the Company’s
    failure to timely file a claim for the water identified therein.
    Engineer also asserted that the Diligence Claim could not be
    used to modify the Proposed Determination, “because the only
    proper mechanism for correcting or modifying a proposed
    determination is through filing an objection [to it] with the
    district court,” which neither Johnson nor the Company filed.
    ¶5     Johnson opposed the summary judgment motion, arguing
    that it was improper for Engineer to amend the Proposed
    Determination regarding “property and water rights not
    previously included in the Determination without giving an
    affected party sufficient opportunity to be heard.” He contended
    20160547-CA                     3                  
    2018 UT App 109
    Utah State Engineer v. Johnson
    that due process required that he have an opportunity to be
    heard regarding the water rights he asserted in the Diligence
    Claim. He also asserted a laches defense, contending that the
    parties who had objected to the Diligence Claim had waited
    fifteen years to pursue their objections and that he was
    prejudiced by the delay. He contended that the evidence
    establishing the Diligence Claim faded and became harder to
    obtain, and that during the delay he had also relied on the rights
    he asserted in the Diligence Claim. And he argued that the
    objecting parties’ failure to pursue remedies constituted a fatal
    failure to prosecute.
    ¶6     The district court granted summary judgment in favor of
    Engineer. The court made four determinations. First, the court
    concluded that the Diligence Claim was “untimely and that the
    water right had already been addressed in the original Proposed
    Determination.” In particular, the court determined that the
    Diligence Claim was “an expansion of the water rights claimed
    in [the Original Claim],” and the court concluded that the
    Company was “forever barred and estopped” under section
    73-4-9 from asserting the Diligence Claim, that the Company
    “forfeited” the Diligence Claim water, and that “the 2000
    Amendment properly disallowed” the claim. (Internal quotation
    marks omitted.)
    ¶7     Second, the court determined that the 2000 Amendment
    “did not revive Mr. Johnson’s right to assert a claim for
    additional water in the Goshen Valley adjudication or to
    challenge the original Proposed Determination.” Rather, the
    court noted that the “only way” to challenge the Proposed
    Determination was through filing an objection under section
    73-4-11, and it concluded that the “time to file an objection to the
    original Proposed Determination passed in 1985.” As a result,
    the court concluded that Johnson could not “rely on the 2000
    Amendment to revive any right to assert a claim for water in the
    20160547-CA                     4                  
    2018 UT App 109
    Utah State Engineer v. Johnson
    general adjudication or object to the State Engineer’s
    recommendations in the original Proposed Determination.” 1
    ¶8     Third, the court concluded that the Company and
    Johnson “were afforded the process due to them” under the
    general adjudication statutes. The court determined that the
    Company “was afforded sufficient due process in connection
    with the original Proposed Determination in the 1980s,” and that
    Johnson, as the Company’s successor in interest, was “not
    entitled to any more rights than the Company had, and thus is
    bound by the timeframes for filing a water user’s claim and an
    objection that apply to the Company.”
    ¶9     Fourth, the court was “not persuaded” by Johnson’s
    laches argument. The court explained that “[n]ot only did Mr.
    Johnson have both the opportunity and responsibility to pursue
    his own objection, he did not demonstrate that he would suffer
    any injury or prejudice in his ability to support his objection.”
    ¶10 The court therefore granted Engineer’s motion for
    summary judgment, dismissed Johnson’s objection, and affirmed
    the Amendment. Johnson appeals that order.
    ISSUES AND STANDARDS OF REVIEW
    ¶11 Johnson makes several arguments on appeal. First, he
    argues that the district court incorrectly interpreted and applied
    the general adjudication statutes to bar the Diligence Claim, and
    that thereby he has been improperly denied his due process
    rights. He also argues that the district court incorrectly
    determined that laches and/or failure to prosecute did not bar
    1. The court additionally noted that Johnson had “not requested
    an extension of time to file an objection to the original Proposed
    Determination” under Utah Code section 73-4-10.
    20160547-CA                     5                  
    2018 UT App 109
    Utah State Engineer v. Johnson
    Engineer from opposing the Diligence Claim or third parties
    from continuing to assert their objections to the Diligence Claim.
    ¶12 Johnson’s arguments of error all flow from the district
    court’s summary judgment decision. “We review a district
    court’s legal conclusions and ultimate grant or denial of
    summary judgment for correctness, and view the facts and all
    reasonable inferences drawn therefrom in the light most
    favorable to the nonmoving party. Likewise, we review a district
    court’s interpretation and application of a statute for
    correctness.” Timothy v. Pia, Anderson, Dorius, Reynard & Moss
    LLC, 
    2018 UT App 31
    , ¶ 9 (quotation simplified), petition for cert.
    filed, Mar. 26, 2018 (No. 20180228).
    ANALYSIS
    ¶13 Johnson argues that the district court erred by dismissing
    his objection and affirming the Amendment on summary
    judgment. He contends that the Diligence Claim is not
    statutorily barred, as the district court concluded. Rather, he
    argues that he is entitled to the opportunity to perfect his
    Diligence Claim and that the Amendment filed by Engineer
    improperly and prematurely denied him that opportunity. As
    support for his argument, he makes several contentions.
    ¶14 He contends that diligence claims are different in kind
    from other water claims and that they may be made at any time,
    regardless of whether an action for a general adjudication of
    water rights is ongoing. He also contends that the Amendment
    effectively revived his opportunity to challenge the Proposed
    Determination and that due process requires that he now have
    the opportunity to prove his claim. Relatedly, he also argues that
    the district court’s decision that the doctrines of laches and/or
    failure to prosecute did not apply was incorrect.
    20160547-CA                     6                  
    2018 UT App 109
    Utah State Engineer v. Johnson
    ¶15 We begin by describing the statutory landscape involving
    diligence claims and the general adjudication process. We then
    address Johnson’s arguments.
    I. Diligence Claims and General Adjudication
    ¶16 In Utah, rights to the use of water may be established
    through two methods: the statutory appropriation application
    process, as described in Utah Code sections 73-3-1 to -31, or
    diligence claims, as described in Utah Code section 73-5-13. See
    East Jordan Irrigation Co. v. Morgan, 
    860 P.2d 310
    , 312–13 (Utah
    1993); Eskelsen v. Town of Perry, 
    819 P.2d 770
    , 771 n.1 (Utah 1991).
    ¶17 At issue in this case are diligence claims. “A diligence
    claim is a claim to a water right established by putting water to
    beneficial use prior to March 12, 1903, when the statutes creating
    the mandatory appropriation application process went into
    effect.” Provo River Water Users’ Ass’n v. Morgan, 
    857 P.2d 927
    ,
    929 n.4 (Utah 1993). Once a diligence claim is filed, the state
    engineer will “conduct a field investigation of each claim filed”
    and “prepare a report” of that investigation. 
    Utah Code Ann. § 73-5-13
    (5)(a) (LexisNexis Supp. 2013). While the state engineer
    acts only “in an administrative capacity” by “administering and
    supervising the appropriation of the waters of the state” and the
    district court has the duty to adjudicate the claims, see Jensen v.
    Jones, 
    2011 UT 67
    , ¶¶ 10–11, 
    270 P.3d 425
     (quotation simplified),
    the state engineer’s diligence claim report becomes part of the
    claim file and may be “admissible in any . . . judicial proceeding
    on the validity of the claim,” 
    Utah Code Ann. § 73-5-13
    (5)(b).
    ¶18 One type of judicial proceeding used to determine the
    validity of water claims is a general adjudication, which is
    employed to resolve “all competing claims to water use in [a
    particular] area.” Green River Canal Co. v. Olds, 
    2004 UT 106
    , ¶ 4,
    
    110 P.3d 666
    . See generally 
    Utah Code Ann. §§ 73-4-1
     to -24
    20160547-CA                     7                  
    2018 UT App 109
    Utah State Engineer v. Johnson
    (Michie 1989) (providing for and prescribing the general
    adjudication process). 2 “The purpose of the general adjudication
    process is to prevent piecemeal litigation regarding water rights
    and to provide a permanent record of all such rights by decree.”
    Olds, 
    2004 UT 106
    , ¶ 5 (quotation simplified); see also Green River
    Adjudication v. United States, 
    404 P.2d 251
    , 252 (Utah 1965) (“The
    objective of an adjudication . . . is to determine and settle water
    rights which have not been adjudicated or which may be
    uncertain or in dispute.”). In this regard, “the basic goal of
    general adjudication is to record all water claims from a
    particular source which subsequent appropriators can rely upon
    before making their investments.” Provo River, 857 P.2d at 935
    (quotation simplified); see also Olds, 
    2004 UT 106
    , ¶ 41 (“One of
    the key goals of the general adjudication process is to remove
    doubts about the validity of water rights.”).
    ¶19 The process for asserting and adjudicating water rights
    through a general adjudication is established by Title 73, Chapter
    4 of the Utah Code. See 
    Utah Code Ann. §§ 73-4-1
     to -24 (Michie
    1989). Once a general adjudication is initiated, the state engineer
    must first notify all known water rights holders and also publish
    notification of the adjudication. 
    Id.
     § 73-4-4. Claimants then have
    2. As Engineer notes in his briefing, many of the relevant general
    adjudication provisions in sections 73-4-1 to -24 were left
    unrevised between 1979 and the latter part of the first decade of
    2000. For example, section 73-4-9 remained the same between
    1979 and 2009, when it was then amended. Compare 
    Utah Code Ann. § 73-4-9
     (Michie 1989), with 
    id.
     (LexisNexis Supp. 2009). We
    rely on the pre-amended provisions that were in effect during
    the relevant proceedings in the 1980s in this decision, unless
    otherwise noted. Apart from Johnson’s attempt to rely on a 2013
    amendment in the diligence claim statute as persuasive
    authority, the amendments do not substantively affect the issues
    or the arguments.
    20160547-CA                     8                  
    2018 UT App 109
    Utah State Engineer v. Johnson
    ninety days from the date of notice to file with the district court a
    statement of claim for water rights of the water source being
    adjudicated. 
    Id.
     § 73-4-5. If a claimant fails to timely file its claim,
    the claimant “shall be forever barred and estopped from
    subsequently asserting any rights, and shall be held to have
    forfeited all rights to the use of the water theretofore claimed by
    him.” Id. § 73-4-9.
    ¶20 After the water claims have been filed, the state engineer
    evaluates all of the submitted claims. Id. § 73-4-3. After a “full
    consideration of the statements of claims, and of the surveys,
    records, and files,” the engineer will prepare and file with the
    district court a proposed determination of the water rights for
    that area, which includes the engineer’s recommendation to the
    court for the establishment of the water rights in the area. Id.
    § 73-4-11. A copy of the proposed determination is mailed to
    each claimant, along with a notice that any claimant dissatisfied
    with the proposal may file a written objection within ninety
    days. Id. If no objection is filed by the close of the objection
    period, the district court must enter “judgment in accordance
    with such proposed determination,” id. § 73-4-12, “rendering the
    proposed determination the final adjudication of water rights for
    the given area,” Olds, 
    2004 UT 106
    , ¶ 7; see also United States Fuel
    Co. v. Huntington-Cleveland Irrigation Co., 
    2003 UT 49
    , ¶ 15, 
    79 P.3d 945
    ; Jensen v. Morgan, 
    844 P.2d 287
    , 290 (Utah 1992).
    ¶21 At that point, a claimant who has failed to timely object
    under section 73-4-11 essentially takes on the role of a defaulting
    party and is bound by its failure under section 73-4-12, unless
    and until the claimant seeks leave from the court overseeing the
    general adjudication to file an untimely objection under section
    73-4-10. See 
    Utah Code Ann. § 73-4-10
    ; see also Olds, 
    2004 UT 106
    ,
    ¶¶ 39, 41–44 (explaining that section 73-4-10 permits the district
    court overseeing the general adjudication to “hear petitions for
    an extension of the ninety-day objection period at any time
    before a final judgment on the matter is entered” upon a
    showing of due cause, and describing the required “due cause”
    20160547-CA                       9                  
    2018 UT App 109
    Utah State Engineer v. Johnson
    showing as “strict” in order to “give effect to the time limitation
    of section 73-4-11 and to appropriately serve the goal of
    establishing certainty” as to general adjudications); United States
    Fuel, 
    2003 UT 49
    , ¶¶ 15–20 (explaining the interplay between
    sections 73-4-10, 73-4-11, and 73-4-12, and stating that when a
    party fails to timely object to a proposed determination, it takes
    on “the status of a defaulting party in the general adjudication”).
    II. The Diligence Claim and the Summary Judgment Ruling
    ¶22 Johnson’s argument—that the Diligence Claim is not
    barred and that he is entitled to an opportunity to prove his
    claim on its merits—requires us to interpret and apply the
    relevant statutes. “When interpreting a statute, this court’s
    paramount concern is to give effect to the legislative intent,
    manifested by the plain language of the statute.” Green River
    Canal Co. v. Olds, 
    2004 UT 106
    , ¶ 18, 
    110 P.3d 666
     (quotation
    simplified). We will “not look beyond the plain language of the
    statute” if the statute is unambiguous. State v. Huntington-
    Cleveland Irrigation Co., 
    2002 UT 75
    , ¶ 13, 
    52 P.3d 1257
    . In this
    regard, “we assume, absent a contrary indication, that the
    legislature used each term advisedly according to its ordinary
    and usually accepted meaning,” and we presume “that the
    expression of one term should be interpreted as the exclusion of
    another” and “seek to give effect to omissions in statutory
    language by presuming all omissions to be purposeful.” Aequitas
    Enters., LLC v. Interstate Inv. Group, LLC, 
    2011 UT 82
    , ¶ 15, 
    267 P.3d 923
     (quotation simplified). We also “read the plain
    language of a statute as a whole and interpret its provisions in
    harmony with other provisions in the same statute and with
    other statutes under the same and related chapters.” H.U.F. v.
    W.P.W., 
    2009 UT 10
    , ¶ 32, 
    203 P.3d 943
    .
    ¶23 As we explain below, we conclude that the district court
    correctly interpreted and applied the plain language of the
    relevant general adjudication statutes to bar the Diligence Claim.
    Despite Johnson’s contentions to the contrary, the language of
    20160547-CA                    10                  
    2018 UT App 109
    Utah State Engineer v. Johnson
    the relevant statutes plainly forecloses Johnson’s arguments. As
    the Company’s successor in interest, Johnson’s water rights do
    not exceed that of the Company, Butler, Crockett & Walsh Dev.
    Corp. v. Pinecrest Pipeline Operating Co., 
    2004 UT 67
    , ¶ 27, 
    98 P.3d 1
    , and he is likewise bound by the Company’s actions in the
    general adjudication, see Penta Creeks, LLC v. Olds, 
    2008 UT 25
    ,
    ¶¶ 2, 33–37, 43, 
    182 P.3d 362
    . And here, it is undisputed that the
    Company failed to include the water represented by the
    Diligence Claim in the Original Claim and that the Company
    thereafter failed to object to the Proposed Determination when
    provided with notice and the opportunity to do so. These
    failures are fatal to Johnson’s attempt to make the Diligence
    Claim now.
    A.     The Statutory Bar Under Section 73-4-9
    ¶24 The plain language of the general adjudication statutes
    demonstrates that diligence rights, like all other water rights,
    must be claimed according to the established general
    adjudication procedures once a general adjudication for a
    particular water area is initiated. Indeed, section 73-4-3 provides
    that once a general adjudication action for a water area has been
    filed with the district court, that filing sets in motion the general
    adjudication procedures in sections 73-4-1 to -24. See 
    Utah Code Ann. § 73-4-3
     (Michie 1989); see also United States Fuel Co. v.
    Huntington-Cleveland Irrigation Co., 
    2003 UT 49
    , ¶ 16, 
    79 P.3d 945
    (providing that “[t]he entry of this order for a general
    adjudication” for “all water rights within” the water area
    identified “set[s] in motion [the] procedures” outlined in the
    general adjudication statutes, including “giving notice to water
    claimants, the filing of statements by claimants, and a
    comprehensive and exhaustive investigation by the state
    engineer”).
    ¶25 These procedures include the requirement that “all
    claimants” in the water area must, after receiving notice of the
    requirement to do so, timely “file a written statement with the
    20160547-CA                     11                  
    2018 UT App 109
    Utah State Engineer v. Johnson
    clerk of the court setting forth his respective claim to the use of
    such water.” 
    Utah Code Ann. §§ 73-4-3
    , 73-4-5 (Michie 1989)
    (providing that “[e]ach person claiming a right to use any water of
    such river system or water source shall, within ninety days after
    the completed service of the notice . . . , file in the office of the
    clerk of the district court a statement in writing” detailing the
    claimed water use (emphasis added)). Thus, per the plain
    language, and without exception, every claimant to water rights
    in the area being adjudicated must timely file a statement of
    claim, one that details the exact extent of the claimant’s water
    use. There is no language suggesting that a claimant whose
    water rights are based on pre-1903 beneficial use is excused or
    excepted from these requirements. See Green River Adjudication v.
    United States, 
    404 P.2d 251
    , 252 (Utah 1965) (noting that “it is
    essential that everyone whose rights are involved or may be
    affected be made parties to the [general adjudication]
    proceeding” and that “they be required to assert whatever rights
    they contend they are entitled to” (emphasis added)).
    ¶26 The plain language of section 73-4-9, the time-bar section,
    also makes no exception for diligence claimants (or any other
    claimants, for that matter). That section provides in broad and
    mandatory language that “any person” who fails to “make and
    deliver such statement of claim to the clerk of the court within
    the time prescribed by law shall be forever barred and estopped
    from subsequently asserting any rights, and shall be held to have
    forfeited all rights to the use of the water theretofore claimed by
    him.” 
    Utah Code Ann. § 73-4-9
     (Michie 1989) (emphasis added).
    And no language in section 73-5-13, the diligence claim statute,
    otherwise abrogates or avoids this consequence.
    ¶27 Here, because the specific water area at issue became
    subject to a general adjudication nearly forty years ago, the
    Company was required, once it received notice, to timely file a
    statement of claim for the extent of the water it claimed it had a
    right to use from the water source. 
    Id.
     §§ 73-4-3, 73-4-5, 73-4-9.
    But the Original Claim did not include the diligence rights the
    20160547-CA                     12                  
    2018 UT App 109
    Utah State Engineer v. Johnson
    Company attempted to claim in 1999, despite the fact that the
    Company and Johnson both acknowledged that those rights
    should have been included in the Original Claim.
    ¶28 And the plain language of the general adjudication
    statutes mandates a clear consequence for the Company’s failure
    to timely include the additional water described in the Diligence
    Claim: the Company became “forever barred and estopped
    from” thereafter claiming it. 
    Id.
     § 73-4-9. This bar is in line with
    general adjudication’s overall purpose of providing certainty for
    water users in a particular area. See, e.g., Green River Adjudication,
    404 P.2d at 252; see also Green River Canal Co. v. Olds, 
    2004 UT 106
    ,
    ¶ 18, 
    110 P.3d 666
    . As the Company’s successor in interest, this
    bar necessarily extends to Johnson. 3 See Penta Creeks, LLC v. Olds,
    
    2008 UT 25
    , ¶¶ 2, 33–37, 43, 
    182 P.3d 362
    .
    ¶29 Johnson’s arguments to the contrary are unpersuasive,
    given the statutory language. 4 Indeed, the case Johnson
    3. We therefore reject Johnson’s contention that, because the
    Diligence Claim was corrective, the water represented by the
    Diligence Claim was implicit in the Original Claim and was not
    an unclaimed right. No language in either the diligence claim
    statute or the general adjudication statutes suggests that
    allegedly corrective claims are an exception to the statutory bar
    when they are untimely filed in a general adjudication or that it
    is procedurally proper to untimely assert a corrective claim
    through the filing of a new diligence claim outside of the general
    adjudication proceedings already underway. Rather, the plain
    language of both sections 73-4-5 and 73-4-9 require a claimant to
    describe and claim the full extent of his water rights within the
    time frame required and in the general adjudication proceedings
    or suffer the consequence for failing to do so.
    4. Johnson also argues that a 2013 amendment to the diligence
    claim statute, section 73-5-13, see 
    Utah Code Ann. § 73-5-13
    (7)
    (continued…)
    20160547-CA                      13                 
    2018 UT App 109
    Utah State Engineer v. Johnson
    primarily relies upon to argue that diligence claims are an
    exception to general adjudication and the statutory bar, Bauer v.
    Prestwich, 
    578 P.2d 1283
     (Utah 1978), is inapposite. As Engineer
    notes, Bauer involved the defendants’ application to appropriate
    water that was already claimed by the plaintiffs under a
    diligence claim. See 
    id.
     at 1284–85. Bauer did not involve a
    general adjudication or any application of the general
    adjudication statutes to an untimely-filed diligence claim. See 
    id.
    It therefore is not instructive to the case at hand.
    B.    Failure to Object to the Proposed Determination
    ¶30 The Company’s failure to make any objection to the
    Proposed Determination—which apparently failed to describe
    the full extent of the Company’s rights due to its failure to
    include them in the Original Claim—is also fatal to Johnson’s
    claims on appeal. Had the Proposed Determination misstated
    the Company’s water rights, the Company could have objected
    pursuant to section 73-4-11. See 
    Utah Code Ann. § 73-4-11
    (Michie 1989) (providing that a claimant “dissatisfied” with the
    proposed determination “may” file an objection within ninety
    (…continued)
    (LexisNexis Supp. 2013), as well as the state engineers’ historical
    practice, which he contends has included accepting untimely
    diligence claims in areas subject to general adjudication, support
    his argument that we should interpret the diligence claim statute
    as exempting diligence claims from the reach of the general
    adjudication statutes. But here, we have concluded that the plain
    language of the relevant statutory provisions bars the Diligence
    Claim and, moreover, does not support Johnson’s suggested
    interpretation. Thus, we have no need for “other interpretive
    tools” to aid us, such as subsequent legislative history or the
    state engineers’ historical practice, and “our task of statutory
    construction is [therefore] at an end.” See Bagley v. Bagley, 
    2016 UT 48
    , ¶ 10, 
    387 P.3d 1000
     (quotation simplified).
    20160547-CA                    14                  
    2018 UT App 109
    Utah State Engineer v. Johnson
    days from the date the proposed determination was mailed); see
    also Olds, 
    2004 UT 106
    , ¶ 27 & n.7 (“Claimants are aware of the
    claims they have submitted to the state engineer. If a proposed
    determination does not match the contours of a submitted claim,
    the party who submitted that claim is on notice that an objection
    may be warranted.”). But if a claimant fails to make a timely
    objection to a proposed determination, the plain and mandatory
    language of section 73-4-12 assigns a clear consequence for that
    failure upon expiration of the objection period: the district court
    becomes bound to enter judgment in accordance with the rights
    as described in the Proposed Determination. See 
    Utah Code Ann. § 73-4-12
     (Michie 1989) (“If no contest on the part of any claimant
    shall have been filed, the court shall render a judgment in
    accordance with such proposed determination, which shall
    determine and establish the rights of the several claimants to the
    use of the water of said river system or water source . . . .”). No
    language in the diligence claim statute, section 73-5-13, alters this
    result.
    ¶31 Likewise, this result cannot be collaterally challenged
    through a separate proceeding, such as the filing of a separate
    diligence action for rights to water that, at all relevant times, was
    part of the water source already being adjudicated. See United
    States Fuel Co. v. Huntington-Cleveland Irrigation Co., 
    2003 UT 49
    ,
    ¶¶ 15–20, 
    79 P.3d 945
    . The Utah Supreme Court’s reasoning in
    United States Fuel makes that clear. In that case, an irrigation
    company filed a diligence claim in a general adjudication, and
    United States Fuel (USF) objected to the proposed determination
    one day after the statutory ninety-day deadline. 
    Id.
     ¶¶ 3–4. In the
    objection, USF asserted that it held a senior right to the water
    claimed by the irrigation company. Id. ¶ 4. USF then filed a
    separate action to quiet title to the water rights claimed by the
    irrigation company. Id. ¶ 5.
    ¶32 The irrigation company moved to dismiss the separate
    action or stay the proceedings, pending the outcome of the
    general adjudication, and it also moved to bar any objections to
    20160547-CA                     15                  
    2018 UT App 109
    Utah State Engineer v. Johnson
    the validity of its diligence claim where USF filed an untimely
    objection. 
    Id.
     ¶¶ 6–7. The district court denied both motions. 
    Id.
    Instead, the district court determined that it had jurisdiction over
    the dispute and ultimately concluded that the evidence
    demonstrated that USF, not the irrigation company, held priority
    to the water. Id. ¶ 8.
    ¶33 On appeal, the supreme court reversed, holding that
    USF’s failure to timely object was fatal to its attempt to have its
    water right adjudicated in a separate action. Id. ¶ 21. The court
    explained that filing the objection one day late “had
    consequences,” specifically that where no timely objections to
    the proposed determination were filed, the district court
    overseeing the general adjudication became required under the
    “clear mandate” of section 73-4-12 to “enter judgment consistent
    with [the] uncontested elements of [the] proposed
    determination.” Id. ¶¶ 12, 15, 17 (explaining that the “clear
    mandate of section 73-4-12 is that courts must render judgment
    in accordance with a proposed determination where the
    proposed determination is uncontested at the close of the ninety-
    day statutory period”).
    ¶34 The supreme court explained that by failing to timely
    object, USF “took on the status of a defaulting party in the
    general adjudication,” rendering USF unable to defeat the
    irrigation company’s “right to obtain judgment” in accordance
    with the proposed determination through “collateral attack in a
    separate lawsuit.” Id. ¶ 20. Rather, the supreme court stated that
    “it is the obligation of a trial court confronted with a private suit
    seeking relief inconsistent with an uncontested proposed
    determination in a general adjudication to abstain from
    adjudicating the private claims.” Id. ¶ 18. In so doing, the court
    noted that USF did have a potential remedy in the general
    adjudication: it could seek leave from the court overseeing the
    general adjudication “to excuse its tardy objection,” but
    explained that “[u]nless and until” USF sought and obtained
    leave, the court in the general adjudication was required to enter
    20160547-CA                     16                  
    2018 UT App 109
    Utah State Engineer v. Johnson
    judgment “perfecting [the irrigation company’s] claim.” 
    Id.
    ¶¶ 17–18.
    ¶35 While the jurisdictional question presented by United
    States Fuel is not at issue in the present case, Johnson, like USF,
    has effectively sought to collaterally challenge the water rights
    described and established by the Proposed Determination
    through the untimely filed Diligence Claim. But, as explained
    above (and by the Company’s own admission), the water rights
    represented by the Diligence Claim formed part of the water
    source and the associated rights being adjudicated in the general
    adjudication. Given the procedural stage of the general
    adjudication and the failure of any party to timely object to the
    Proposed Determination, the district court was required at the
    close of the statutory objection period to enter judgment in
    accordance with the water rights described therein. See United
    States Fuel, 
    2003 UT 49
    , ¶¶ 15–20. That result cannot now be
    collaterally challenged by the filing of a separate diligence claim.
    Rather, as explained in United States Fuel, the rights described in
    the Proposed Determination are now immune from attack absent
    leave from the court overseeing the general adjudication to lodge
    an untimely objection to the Proposed Determination. See 
    id.
    ¶36 Further, the Amendment, and Johnson’s objections to the
    Amendment, did not open the door to an untimely challenge of
    the Proposed Determination. The Amendment was a proposed
    resolution of only the Diligence Claim, which represented water
    rights that perhaps could have been included in the Proposed
    Determination but, because the Company did not timely assert
    them, were not. The Amendment did not propose any revision
    to the Proposed Determination and instead allowed it to remain
    untouched.
    ¶37 In this way, while it was filed as an inclusion to the
    general adjudication, it is an amendment to the Proposed
    Determination only insofar as it acts to further insulate the
    Proposed Determination from collateral attack. Thus, regardless
    20160547-CA                     17                 
    2018 UT App 109
    Utah State Engineer v. Johnson
    of how the Amendment is characterized (housekeeping measure
    or otherwise) or the path that Engineer took to file it, the
    Amendment recommended a discrete and statutorily mandated
    resolution of a diligence claim that improperly sought to disturb
    the water rights established by the unopposed Proposed
    Determination. On this basis, Johnson’s objections to the
    Amendment therefore could only be objections to the
    Amendment and the recommendation itself, not to the Proposed
    Determination. 5 See, e.g., Butler, Crockett & Walsh Dev. Corp. v.
    Pinecrest Pipeline Operating Co., 
    2004 UT 67
    , ¶¶ 22–23, 
    98 P.3d 1
    .
    C.     Due Process
    ¶38 We also conclude that Johnson’s due process rights
    related to the Diligence Claim have not been violated. “At a
    minimum, the right to due process requires that those with an
    interest in a proceeding be given notice and an opportunity to be
    heard in a meaningful manner before their interests are
    adjudicated by a court.” Salt Lake Legal Defender Ass’n v. Atherton,
    
    2011 UT 58
    , ¶ 2, 
    267 P.3d 227
    ; see also Mullane v. Central Hanover
    Bank & Trust Co., 
    339 U.S. 306
    , 314 (1950) (“An elementary and
    fundamental requirement of due process in any proceeding
    which is to be accorded finality is notice reasonably calculated,
    under all the circumstances, to apprise interested parties of the
    pendency of the action and afford them an opportunity to
    present their objections.”).
    ¶39 Our supreme court has long held that the notice
    provisions of the general adjudication statutes meet the
    requirements of due process. See Eden Irrigation Co. v. District
    5. We are also unpersuaded by Johnson’s contention that the
    Amendment represented an improper adjudication by Engineer.
    It did not. The Amendment was exactly what it purported to
    be—a recommendation to the district court overseeing the general
    adjudication that the claim be disallowed.
    20160547-CA                     18                 
    2018 UT App 109
    Utah State Engineer v. Johnson
    Court of Weber County, 
    211 P. 957
    , 959 (Utah 1922). Johnson is the
    successor in interest to the Company, and it is without dispute
    that the Company participated in and received the process it was
    due under the relevant general adjudication provisions during
    the 1980s proceedings. See Penta Creeks, LLC v. Olds, 
    2008 UT 25
    ,
    ¶¶ 2, 17–19, 33–37, 
    182 P.3d 362
     (considering the effect of the
    predecessor’s actions, such as failure to properly file an
    objection, on the successor’s interest in general adjudication).
    Through the Company, Johnson therefore received the process
    he would have been due in the general adjudication, including
    the process afforded the Company to both claim the full extent
    of its water rights under section 73-4-5 and to timely object to the
    Proposed Determination under section 73-4-11. See 
    id.
     Johnson is
    not entitled to more process to try to prove on its merits an
    improperly filed challenge to the Proposed Determination that,
    at this stage in the proceedings, is statutorily barred by the
    general adjudication statutes.
    ¶40 Furthermore, the case Johnson primarily relies on to make
    this argument, Provo River Water Users’ Ass’n v. Morgan, 
    857 P.2d 927
     (Utah 1993), is inapposite. There, Utah Supreme Court
    concluded that the decree in that case resolving the general
    adjudication was not intended to adjudicate the rights of users to
    the water sources—isolated springs—at issue. Id. at 933. And, in
    dicta, the court noted that even if the decree were intended to
    adjudicate the rights associated with the isolated springs at
    issue, it was unclear that the users of the isolated springs’ water
    received the process and notice they were due of the
    adjudication and of their duty to assert their rights in it,
    particularly in light of a shift in law mid-proceedings. Id. at 933–
    34.
    ¶41 Here, in contrast, the water represented by the Diligence
    Claim had allegedly been used by the Company since before
    1903 and apparently was part and parcel of the Original Claim.
    Thus, the Company should have been aware that that water
    formed part of its water rights in the area that became subject to
    20160547-CA                     19                 
    2018 UT App 109
    Utah State Engineer v. Johnson
    general adjudication. See generally Green River Canal Co. v. Olds,
    
    2004 UT 106
    , ¶ 27 & n.7, 
    110 P.3d 666
    . And there is no question
    that the Company was notified of the general adjudication and
    of its duty to “assert [its water] rights” in that proceeding “or
    lose them,” Provo River Water, 857 P.2d at 934. There is also no
    question that the Company received the Proposed
    Determination and the required notice that it had ninety days to
    object, which it did not do. And although Johnson attempts to
    argue that applying the statutory bars to diligence claims
    represents a shift in law (like the shift in law at play in Provo
    River, which affected the notice given to the isolated springs’
    users), he has not demonstrated that this is so in light of the
    plain statutory language and the precedent we have discussed.
    As a result, Provo River does not assist Johnson in making his
    case.
    ¶42 Accordingly, we also affirm the district court’s conclusion
    that Johnson has received all the process he is due as related to
    the water rights represented in the Diligence Claim. 6
    6. Johnson does not appear to argue that he did not receive due
    opportunity to object to the Amendment itself. Rather, we
    understand his argument to be that due process requires that he
    now be allowed to challenge the Proposed Determination,
    particularly in light of the Amendment, which he characterizes
    as itself a challenge to the Proposed Determination. We have
    rejected that argument above. But to the extent that Johnson
    might be arguing that he did not receive the process he was due
    as related solely to the Amendment, we reject any such
    contention as well. Johnson received notice of the Amendment,
    which included notice that he had ninety days in which to object,
    and he did object. Further, the court heard and resolved his
    objection. This is sufficient for purposes of due process in these
    circumstances. See Eden Irrigation Co. v. District Court of Weber
    County, 
    211 P. 957
    , 959 (Utah 1922).
    20160547-CA                    20                  
    2018 UT App 109
    Utah State Engineer v. Johnson
    ¶43 In sum, the Company failed to timely claim the water
    represented by the Diligence Claim and thereafter timely object
    to the Proposed Determination. See 
    Utah Code Ann. §§ 73-4-3
    ,
    73-4-5, 73-4-9, 73-4-11, 73-4-12 (Michie 1989). Johnson is bound
    by those failures. The Company and Johnson have also failed to
    avail themselves of the proper procedural vehicle—a requested
    extension under section 73-4-10—to try to remedy the failure to
    include in the Original Claim the water represented by the
    Diligence Claim or to object to the Proposed Determination. See
    
    id.
     § 73-4-10. Further, the Company and Johnson, as its successor,
    have received the process they are due, given that the Diligence
    Claim represents an improper collateral challenge to the
    Proposed Determination and that the Company received all the
    process it was due in relation to the Proposed Determination.
    And the Amendment, or the proceedings associated with the
    Amendment, did not revive a right to challenge the Proposed
    Determination. Thus, under the plain language of the statutes in
    question, as well as precedent interpreting those statutes, we
    affirm the district court’s determination that the Diligence Claim
    was barred.
    III. Laches Defense and/or Failure to Prosecute
    ¶44 Finally, Johnson argues that the district court erred when
    it determined that laches and failure to prosecute did not apply
    in these circumstances.
    ¶45 “Laches is designed to shelter a prejudiced defendant
    from the difficulties of litigating meritorious claims after an
    unexplained delay.” Fundamentalist Church of Jesus Christ of
    Latter-Day Saints v. Horne, 
    2012 UT 66
    , ¶ 37, 
    289 P.3d 502
    . “It is a
    negative equitable remedy which deprives one of some right or
    remedy to which he would otherwise be entitled, because his
    delay in seeking it has operated to the prejudice of another.” 
    Id.
    (quotation simplified). “Laches has two elements: (1) lack of
    diligence on the part of the claimant and (2) an injury to the
    20160547-CA                     21                 
    2018 UT App 109
    Utah State Engineer v. Johnson
    defendant because of the lack of diligence.” Plateau Mining Co. v.
    Utah Div. of State Lands & Forestry, 
    802 P.2d 720
    , 731 (Utah 1990).
    ¶46 We agree with the district court’s determination that the
    laches defense does not apply. For one thing, our supreme court
    has rejected a similar argument in Green River Canal Co. v. Olds,
    
    2004 UT 106
    , 
    110 P.3d 666
    , and we are persuaded by the
    reasoning employed by the court there. In Olds, a canal company
    asserted that the state engineer was barred from seeking
    dismissal of its filings because the engineer waited nearly
    twenty-seven years to file the motion to dismiss. 
    Id.
     ¶ 12 n.4. The
    Utah Supreme Court rejected the canal company’s assertion,
    concluding that, “[g]iven the highly unusual nature of general
    adjudication proceedings and the fact that [the canal company]
    itself had an obligation and opportunity to litigate its objection
    during that twenty-seven-year period, [the court was] not
    inclined to hold the State Engineer accountable for the long
    delay.” 
    Id.
    ¶47 Likewise, here, Johnson has not demonstrated why the
    district court erred in determining that laches did not apply,
    given the unusual nature of general adjudication proceedings,
    Johnson’s obligation and opportunity to litigate the Diligence
    Claim and the Amendment, and the various circumstances in
    play, such as the lengthy negotiation proceedings between
    Johnson and Engineer and the failed stipulation. See 
    id.
    ¶48 Similarly, Johnson has failed to demonstrate error in the
    district court’s determination that he has not demonstrated
    prejudice. In particular, Johnson has not shown that it was error
    for the district court to discern no prejudice from the
    disappearance of evidence to prove a claim the court determined
    Johnson was barred from making under statute, a determination
    we have affirmed above. And Johnson has not otherwise
    demonstrated that his reliance on his alleged diligence rights
    ought to have persuaded the court to reach a different
    conclusion.
    20160547-CA                    22                  
    2018 UT App 109
    Utah State Engineer v. Johnson
    ¶49 Johnson also has failed to demonstrate that the third
    parties objecting to the Diligence Claim ought to be barred from
    asserting their objections by a failure to diligently prosecute
    them. He contends that the objecting parties did not pursue
    remedies on their objections for over fifteen years, and cites a
    provision of the Utah Code—section 73-3-15—which he claims
    supports his assertion that the objections can be dismissed for
    failure to prosecute diligently. But section 73-3-15 addresses
    dismissal for failure to prosecute an informal adjudicative
    proceeding, which the present case was not, and he does not
    explain how this provision nonetheless applies. Moreover, other
    than citing general cases for the basic proposition that a party
    must diligently prosecute its claims, Johnson does not explain
    how a failure-to-prosecute theory ought to apply in these
    circumstances, given the nature of general adjudication
    proceedings or the circumstances particular to this case. Cf. Olds,
    
    2004 UT 106
    , ¶ 12 n.4.
    ¶50 Accordingly, we affirm the district court’s conclusion that
    the doctrines of laches and/or failure to prosecute do not apply
    under the circumstances present here.
    CONCLUSION
    ¶51 For the reasons stated above, we affirm the district court’s
    grant of summary judgment on Johnson’s objection.
    20160547-CA                    23                  
    2018 UT App 109