Johnson v. Okland Construction , 2020 UT App 150 ( 2020 )


Menu:
  •                         
    2020 UT App 150
    THE UTAH COURT OF APPEALS
    JULIE JOHNSON AND BRENT JOHNSON,
    Appellants,
    v.
    OKLAND CONSTRUCTION COMPANY INC.,
    Appellee.
    Opinion
    No. 20180967-CA
    Filed November 5, 2020
    Third District Court, Salt Lake Department
    The Honorable Andrew H. Stone
    No. 170904418
    David S. Head, Attorney for Appellants
    Terry M. Plant and Daniel E. Young,
    Attorneys for Appellee
    JUDGE GREGORY K. ORME authored this Opinion, in which
    JUDGES KATE APPLEBY and RYAN M. HARRIS concurred.
    ORME, Judge:
    ¶1    Julie Johnson and Brent Johnson appeal the district court’s
    summary judgment dismissing their complaint against Okland
    Construction Company, Inc. They argue that the district court
    erred in ruling that the two-year statute of limitations under
    Utah Code section 78B-2-225(3)(b) 1 barred their claim on the
    1. In this opinion, we consider the version of the applicable
    statutory provision in effect at the time of Julie’s accident. See
    generally State v. Clark, 
    2011 UT 23
    , ¶¶ 13–14, 
    251 P.3d 829
    . Due
    to subsequent legislative amendment, some of the subsections of
    the key provision have been renumbered and others
    inconsequentially rephrased. Notably, the text formerly found in
    (continued…)
    Johnson v. Okland Construction
    rationale that Okland did not, at the time, have possession or
    control of the sidewalk where Julie’s 2 injury occurred. We affirm.
    BACKGROUND 3
    ¶2     During a lunch break on July 25, 2013, Julie, an eBay
    employee, was walking on a sidewalk Okland had constructed
    on the northeastern portion of the new eBay campus in Draper,
    Utah. Julie tripped and fell where the sidewalk dropped off to a
    concrete driveway, landing on her hands and knees. On July 12,
    2017, almost four years from the date of the accident, the
    Johnsons filed a complaint against Okland alleging that it was
    negligent in its construction of the sidewalk, proximately
    causing Julie’s injuries and Brent’s loss of consortium with her. 4
    Specifically, in their third amended complaint, 5 the Johnsons
    (…continued)
    subsection (3)(b) has been moved to subsection (4)(a). Compare
    Utah Code Ann. § 78B-2-225(3)(b) (LexisNexis 2012), with id.
    § 78B-2-225(4)(a) (Supp. 2020).
    2. Because both appellants share the same surname, we refer to
    them by their first names, with no disrespect intended by the
    apparent informality.
    3. “[W]hen reviewing a grant of summary judgment, we recite
    the disputed facts in a light most favorable to the nonmoving
    party.” Begaye v. Big D Constr. Corp., 
    2008 UT 4
    , ¶ 5, 
    178 P.3d 343
    .
    4. Julie received workers’ compensation in connection with her
    injuries but eventually sought additional recovery from Okland
    via this lawsuit.
    5. The Johnsons also brought similar claims against another
    construction company, the architect, and various subcontractors
    (continued…)
    20180967-CA                     2                
    2020 UT App 150
    Johnson v. Okland Construction
    alleged that because the road “was the same color as the
    adjoining sidewalk,” it “looked like an extension of the
    sidewalk,” which made it difficult for Julie to notice the drop-off.
    This was further compounded, they claimed, by the fact that
    Okland “did not mark the above sidewalks and roads or place
    surrounding signs in order to notify pedestrians” of the drop-off.
    The Johnsons also alleged that “[a]t the time of the . . . accident,
    [Okland was] in possession and control of the road and sidewalk
    where the accident took place, and [was] still performing
    construction.”
    ¶3     The key facts before the district court on summary
    judgment were that in March 2012, eBay engaged Okland as the
    construction manager and general contractor for the eBay
    construction project, which included a three-story office
    building, an amenities building, an enclosed walkway between
    the buildings, surface parking, and landscaping of the thirty-five
    acre campus. Okland completed the project nearly one year later.
    On February 1, 2013, the project’s architect issued a certificate of
    substantial completion that stated eBay could “occupy or utilize”
    the campus and that on March 18, 2013, eBay “will assume full
    possession” of the campus. It also stated that
    eBay assumes all responsibilities for security,
    maintenance, heat, utilities, damage to the
    [campus], and insurance from the date of
    Substantial Completion except as follows: Okland
    Construction assumes all responsibilities for
    (…continued)
    who were involved in constructing the eBay campus. For various
    reasons, these defendants were either dismissed by the district
    court or voluntarily dismissed by the Johnsons, resulting in
    Okland remaining as the lone defendant. The Johnsons do not
    appeal the court’s dismissal of their claims against the other
    defendants.
    20180967-CA                     3                
    2020 UT App 150
    Johnson v. Okland Construction
    insurance and damage to the [campus] caused by
    Okland Construction or their subcontractors
    during completion of the [campus] on items
    attached hereto.
    Draper City then issued a temporary certificate of occupancy for
    the office building on March 14, 2013, and a final certificate of
    occupancy for the amenities building on March 18, 2013. A final
    certificate of occupancy for the office building was issued on
    June 28, 2013.
    ¶4     As part of Okland’s contractual obligations, it was
    required to “correct any deficient work on the [campus]” for one
    year after the issuance of the certificate of substantial
    completion. To have Okland return for any such warranty work,
    eBay first needed to request the work, and Okland would then
    have to coordinate with eBay personnel and security to gain
    access to the campus to correct the particular defect. Throughout
    June and July of 2013, Okland responded to a number of eBay
    warranty work requests, which is not uncommon in a large-scale
    commercial construction project. On one occasion, eBay put in a
    request for Okland to fix a “cracked and buckling” sidewalk, but
    the sidewalk in question was on the opposite end of the campus
    from the one on which Julie fell. eBay never requested that
    Okland repair anything in the area where Julie fell.
    ¶5     Okland moved for summary judgment, contending that it
    was “entitled to judgment as a matter of law” because it “did not
    have possession or control of the area where [Julie] allegedly
    fell” and the Johnsons “failed to file their claims within the
    two-year statute of limitations set forth in Utah Code Ann.
    § 78B-2-225(3)(b).” The Johnsons opposed the motion, arguing
    that under Utah Code section 78B-2-225(8), the applicable statute
    of limitations was four years from the time of Julie’s accident, as
    set forth in section 78B-2-307(3), and not two years, because
    subsection (8) rendered section 225 inapplicable because Okland
    20180967-CA                     4               
    2020 UT App 150
    Johnson v. Okland Construction
    was “in possession and control of the road and sidewalk whe[n]
    the . . . accident took place.”
    ¶6     The district court granted Okland’s motion for summary
    judgment, ruling that the two-year statute of limitations applied
    and that the Johnsons failed to bring their claim within that time.
    It further held that “it is not consistent with [section
    78B-2-225(1)(d)] to interpret ‘improvement’ as any ongoing work
    on a large project, extending liability to absolutely all of the
    project regardless of any notice to the defendant contractor.” 6
    And because eBay was in possession and control of the campus
    at the time of the accident and not Okland, the four-year
    exception did not apply, as a matter of law. The Johnsons appeal.
    ISSUE AND STANDARD OF REVIEW
    ¶7       The Johnsons argue that “the trial court erred when it
    granted summary judgment in favor of Okland because it
    erroneously interpreted the word ‘improvement’ in Utah Code
    § 78B-2-225 to mean the exact location of [the] sidewalk where
    the . . . accident took place.” The Johnsons contend that the court
    erroneously determined that Okland did not have possession or
    control of the sidewalk. Thus, in the Johnsons’ view, “the
    exception in Utah Code § 78B-2-225(8)” was applicable. “We
    review a district court’s decision to grant summary judgment for
    correctness, granting no deference to the district court’s
    conclusions.” Gillmor v. Summit County, 
    2010 UT 69
    , ¶ 16, 
    246 P.3d 102
     (quotation simplified).
    6. Utah Code section 78B-2-225 governs statutes of limitation
    regarding “actions related to improvements in real property.”
    The section defines “improvement” as “any building, structure,
    infrastructure, road, utility, or other similar man-made change,
    addition, modification, or alteration to real property.” Utah Code
    Ann. § 78B-2-225(1)(d) (LexisNexis 2012).
    20180967-CA                     5               
    2020 UT App 150
    Johnson v. Okland Construction
    ANALYSIS
    ¶8      “When interpreting statutes, our primary goal is to evince
    the true intent and purpose of the Legislature.” Duke v. Graham,
    
    2007 UT 31
    , ¶ 16, 
    158 P.3d 540
     (quotation simplified). “We look
    first to the plain language of the statute and presume that the
    legislature used each word advisedly and read each term
    according to its ordinary and accepted meaning.” Turner v.
    Staker & Parson Cos., 
    2012 UT 30
    , ¶ 12, 
    284 P.3d 600
     (quotation
    simplified). “The plain language of a statute is to be read as a
    whole, and its provisions interpreted in harmony with other
    provisions in the same statute and with other statutes under the
    same and related chapters.” Duke, 
    2007 UT 31
    , ¶ 16 (quotation
    simplified).
    ¶9     Utah Code section 78B-2-225(3)(b) sets a two-year statute
    of limitations from the date of discovery for causes of action not
    “based in contract or warranty” against a “provider” 7 related to
    an “improvement.” Utah Code Ann. § 78B-2-225(2), (3)(a)–(b)
    (LexisNexis 2012). The statute defines “improvement” as “any
    building, structure, infrastructure, road, utility, or other similar
    man-made change, addition, modification, or alteration to real
    property.” Id. § 78B-2-225(1)(d). “Completion of improvement”
    is defined as “the date of substantial completion of an
    improvement to real property as established by the earliest of:
    (i) a Certificate of Substantial Completion; (ii) a Certificate of
    7. “‘Provider’ means any person contributing to, providing, or
    performing studies, plans, specifications, drawings, designs,
    value engineering, cost or quantity estimates, surveys, staking,
    construction, and the review, observation, administration,
    management, supervision, inspections, and tests of construction
    for or in relation to an improvement.” Utah Code Ann.
    § 78B-2-225(1)(f) (LexisNexis 2012). Under this definition, it is
    clear that Okland is a “provider,” which Okland does not
    dispute.
    20180967-CA                     6                
    2020 UT App 150
    Johnson v. Okland Construction
    Occupancy . . . ; or (iii) the date of first use or possession of the
    improvement.” 
    Id.
     § 78B-2-225(1)(c).
    ¶10 The two-year statute of limitations “does not apply to any
    action against any person in actual possession or control of the
    improvement as owner, tenant, or otherwise, at the time any
    defective or unsafe condition of the improvement proximately
    causes the injury for which the action is brought.” Id.
    § 78B-2-225(8). If a case “qualifies for this exception, . . . the
    generally applicable four-year statute of limitations” governs the
    claim. Turner, 
    2012 UT 30
    , ¶ 1 n.1 (citing Utah Code Ann.
    § 78B-2-307(3) (2012)). Our Supreme Court has held that the
    plain language of subsection (8) “does not require a legal
    possessory interest in the property underlying the
    improvement” for the exception to apply. Turner, 
    2012 UT 30
    ,
    ¶ 13. Instead, it requires only “some degree of possession or
    control over the improvement itself.” 
    Id.
     Therefore, the exception
    allowing a four-year statute of limitations applies only if Julie’s
    injury occurred at or on an “improvement” of which Okland had
    “actual possession or control” at the time of the injury. Utah
    Code Ann. § 78B-2-225(8).
    ¶11 In the context of this case, we must determine whether
    “improvement” means the entire eBay campus at the time of the
    injury, as the Johnsons contend, or is limited to the portions of
    the campus where Okland was actually doing warranty work.
    Experience suggests that a general contractor, like Okland,
    typically has actual possession or control over every part of a
    major construction project until the project’s completion, at
    which point it turns the site over to the owner. And thus, the
    four-year statute of limitations generally will apply to any
    accident that occurs during the construction period, at any part
    of the construction site, because the contractor still has actual
    possession or control over the entire improvement. But once
    certificates of occupancy are issued and the contractor turns the
    site back to the owner, the improvement is deemed
    “[c]omplet[ed],” id. § 78B-2-225(1)(c), and the contractor no
    20180967-CA                      7               
    2020 UT App 150
    Johnson v. Okland Construction
    longer has actual possession or control of the entire site. The
    contractor, therefore, can regain possession or control of any
    portion of the site, to address specific warranty or punch list 8
    issues, only if the owner invites the contractor back to make
    corrections and repairs. In that case, the contractor, as a
    “provider” under the statute, will have control or possession
    only over the portions, or specific improvements, of the area that
    it is actually working on—not the entire site. This is evidenced
    by the fact that the provider will need to obtain permission to
    enter the site and will have “actual possession or control” only of
    the discrete portions of the site that the owner requested that it
    work on. See 
    id.
     § 78B-2-225(8). In this scenario, the four-year
    statute of limitations would apply only to the limited portion of
    the site the provider is working on and not the entire property.
    ¶12 Here, it is undisputed that Okland did not perform any
    punch list or warranty work in the area where Julie fell after it
    turned the campus over to eBay. While the entire campus would
    have fallen under the category of “improvement” prior to the
    issuance of the certificate of substantial completion or certificate
    of occupancy when Okland was managing construction of the
    campus and had possession of it, the entire campus was no
    longer an “improvement” for purposes of section 78B-2-225’s
    statute of limitations at the time of Julie’s injury. As discussed
    above, the “improvement,” that is, the campus, was deemed
    “[c]omplet[ed],” id. § 78B-2-225(1)(c), before Julie’s injury
    because eBay had already explicitly “assume[d] full possession”
    of the campus and Draper City had issued final certificates of
    occupancy. Thereafter, any “actual possession or control” of
    some part of the campus that Okland regained was limited to the
    8. A “punch list” is “a list of usually minor tasks to be
    completed at the end of a project.” Punch List, Merriam-Webster,
    https://www.merriam-webster.com/dictionary/punch%20list [htt
    ps://perma.cc/6R98-W8XQ].
    20180967-CA                     8                
    2020 UT App 150
    Johnson v. Okland Construction
    areas eBay permitted it to return to for the purpose of
    performing warranty or punch list work. 9 See 
    id.
     § 78B-2-225(8).
    ¶13 Thus, because Okland did not have possession or control
    of the sidewalk when Julie tripped, 10 the Johnsons had two years
    9. We note that if Julie had been injured at any place on the
    campus that Okland was working on pursuant to the warranty,
    then the Johnsons would have had four years from the time of
    her accident to bring their claims, and their claims would have
    survived summary judgment given that subsection (8) requires
    only “some degree of possession or control of the improvement
    itself,” such as doing repair work, to apply. See Turner v. Staker
    & Parson Cos., 
    2012 UT 30
    , ¶ 13, 
    284 P.3d 600
    .
    10. The Johnsons assert that “shortly after the . . . accident
    occurred, the sidewalk and curb had been painted to distinguish
    them from the drop-off to the road.” They add that “if there is
    any doubt or uncertainty concerning questions of fact, the doubt
    should be resolved in [their] favor,” and thus that the district
    court erred in granting summary judgment to Okland because
    this work created “a genuine issue of fact regarding whether or
    not Okland or its subcontractors painted the sidewalk and curb.”
    But whether Okland painted the sidewalk after the accident is
    inconsequential. As we have discussed, eBay had possession or
    control of the entire campus and Okland did not have possession
    or control of the sidewalk at the time Julie was injured. Any
    remedial efforts that might have taken place after the accident
    had to start with eBay contacting Okland to come and repair the
    sidewalk and thus, if Okland gained possession or control of the
    sidewalk, it would have happened after the accident. Therefore,
    there is no genuine dispute of material fact in this regard.
    Furthermore, the Johnsons have produced no evidence that it
    was     Okland—rather      than   eBay’s    own     maintenance
    department—that painted the curb after the accident.
    20180967-CA                     9              
    2020 UT App 150
    Johnson v. Okland Construction
    from July 25, 2013, to bring their claims against Okland, which
    they did not do. Therefore, the district court did not err in
    granting summary judgment to Okland on the ground that the
    Johnsons did not satisfy the applicable statute of limitations, as a
    matter of law. 11
    CONCLUSION
    ¶14 Because Okland did not have possession or control of the
    sidewalk at the time when Julie was injured, the statute of
    limitations under Utah Code section 78B-2-225(3)(b) barred the
    Johnsons’ claim against Okland.
    ¶15    Affirmed.
    11. The Johnsons also argue that the district court’s ruling was
    erroneous because its order failed to follow the statute when it
    ruled that at the time of the accident the sidewalk on which Julie
    was injured “was in the possession and control of eBay and not
    Okland.” They argue that the court erred in concluding that
    Okland had to be in possession and control of the improvement
    rather than in possession or control of it. This argument is
    unpersuasive. The court was simply pointing out that eBay had
    both possession and control of the sidewalk and therefore
    Okland could not have had either.
    20180967-CA                     10               
    2020 UT App 150
                                

Document Info

Docket Number: 20180967-CA

Citation Numbers: 2020 UT App 150

Filed Date: 11/5/2020

Precedential Status: Precedential

Modified Date: 12/21/2021