Pentalon Construction, Inc. v. Rymark Properties, LLC , 779 Utah Adv. Rep. 182 ( 2015 )


Menu:
  •                       
    2015 UT App 29
    _________________________________________________________
    THE UTAH COURT OF APPEALS
    PENTALON CONSTRUCTION, INC.; GRANITE CONSTRUCTION COMPANY;
    AND WIMMER ELECTRIC, INC.,
    Plaintiffs and Appellants,
    v.
    RYMARK PROPERTIES, LLC, AND
    FEDERAL DEPOSIT INSURANCE CORPORATION,
    Defendants and Appellee.
    Opinion
    No. 20130973-CA
    Filed February 5, 2015
    Second District Court, Ogden Department
    The Honorable Ernest W. Jones
    No. 090902634
    Robert F. Babcock, Jason H. Robinson, D. Scott
    DeGraffenried, Michael D. Zimmerman, Troy L.
    Booher, and Clemens A. Landau, Attorneys for
    Appellants Pentalon Construction, Inc. and Granite
    Construction Company
    Dana T. Farmer, Attorney for Appellant Wimmer
    Electric, Inc.
    David M. Bennion and Alan S. Mouritsen,
    Attorneys for Appellee Federal Deposit
    Insurance Corporation
    JUDGE J. FREDERIC VOROS JR. authored this Opinion, in which
    JUDGE JOHN A. PEARCE concurred. JUDGE JAMES Z. DAVIS
    dissented, with opinion.
    Pentalon v. Rymark Properties, LLC.
    VOROS, Judge:
    ¶1     This case concerns whether the near-complete excavation
    for a building’s foundation constitutes commencement of work
    under a now-repealed provision of the Utah Mechanic’s Lien Act
    (the Act). Under the Act, a mechanic’s lien relates back to the
    date work commenced onsite. Therefore, if other legal
    requirements are met, the mechanic’s lien enjoys priority over
    any encumbrance that attaches after the commencement of work.
    In this case, Pentalon Construction, Inc., had nearly completed
    the excavation for a building’s foundation when Barnes Bank—
    Federal Deposit Insurance Corporation’s predecessor in
    interest—recorded a trust deed on the property. When a dispute
    over priority arose, the district court ruled that Pentalon’s near-
    complete excavation work did not constitute ‚commencement to
    do work‛ under the statute and therefore that FDIC’s trust deed
    had priority. Pentalon, Granite Construction Company, and
    Wimmer Electric, Inc., (collectively, Claimants) appeal. We
    reverse and remand for further proceedings.
    BACKGROUND
    ¶2     Rymark Properties, LLC, owned property in Ogden,
    Utah. It hired Pentalon as its general contractor to build an auto
    plaza on the property. On May 5, 2008, Pentalon filed a notice of
    commencement in the state construction registry. On May 8,
    2008, Pentalon and its subcontractors began excavating the
    property. Photographs taken May 27, 2008, show geotextile
    fabric lining trenches that cut across the property, along with
    heavy machinery and mounds of dirt scattered throughout. See
    infra Exhibits A, B, & C. The day after these photographs were
    taken, Barnes Bank recorded its trust deed on the property. FDIC
    succeeded to Barnes Bank’s interest.
    20130973-CA                     2                 
    2015 UT App 29
    Pentalon v. Rymark Properties, LLC.
    ¶3      Pentalon later sought to foreclose its mechanic’s lien
    against Rymark, FDIC, and others (collectively, FDIC). Pentalon
    moved for partial summary judgment, asking the district court
    to rule that Pentalon’s partial excavation of the property—the
    work it had completed before FDIC recorded its trust deed—
    constituted commencement to do work for purposes of the Act,
    and, therefore, that its lien enjoyed priority over FDIC’s trust
    deed. The court denied Pentalon’s motion. Referencing
    photographs of the property, the court ruled that ‚there is no
    real question of fact here‛ and concluded that Pentalon’s
    excavation ‚is not legal commencement.‛ FDIC then filed its
    own motion for summary judgment. FDIC’s motion argued that
    because Pentalon’s excavation did not constitute commencement
    as a matter of law, ‚Claimants cannot establish an essential
    element of their mechanics’ lien foreclosure claims—i.e., that
    their mechanics’ liens have priority over FDIC’s trust deed.‛ The
    district court agreed that no genuine issue of material fact
    existed and that FDIC was entitled to judgment as a matter of
    law.
    ISSUES ON APPEAL
    ¶4     Claimants first contend that, contrary to the district
    court’s ruling, Pentalon’s nearly completed excavation either
    constituted commencement to do work under the Act as a matter
    of law or, in the alternative, created a genuine issue of material
    fact as to whether Pentalon had commenced work for purposes
    of the Act.
    ¶5     Claimants also contend that the district court erred in
    striking affidavits submitted with its memorandum in
    opposition to FDIC’s motion for summary judgment and in
    striking its motion for reconsideration.
    ¶6     FDIC responds that, even assuming the excavation
    constitutes the commencement of work for purposes of the Act,
    20130973-CA                     3                
    2015 UT App 29
    Pentalon v. Rymark Properties, LLC.
    this court should affirm the ruling of the district court on
    alternative grounds.
    ANALYSIS
    I. Pentalon’s Excavation Constitutes ‚Commencement to
    Do Work.‛
    ¶7      Claimants contend that the district court erred in ruling as
    a matter of law that Pentalon’s excavation did not constitute
    commencement to do work under the Act, with the result that
    Pentalon’s lien does not enjoy priority. Claimants argue that they
    provided ‚evidence sufficient to establish commencement of
    work as a matter of law.‛ FDIC responds that Pentalon’s
    excavation does not ‚amount to commencement‛ under the Act,
    because the work does not ‚put a reasonable observer on notice
    that lienable work was underway.‛
    ¶8      On appeal, we review a district court’s ‚legal conclusions
    and ultimate grant or denial of summary judgment for
    correctness.‛ Orvis v. Johnson, 
    2008 UT 2
    , ¶ 6, 
    177 P.3d 600
    (citation and internal quotation marks omitted).
    ¶9    Utah Code section 38-1-5 provides the guidelines for
    determining the priority of liens in this case. See 
    Utah Code Ann. § 38-1-5
     (LexisNexis 2005).1 That section provides that
    mechanics’ liens generally date back to the commencement of
    work:
    1. In 2012, this section was amended and renumbered as section
    38-1a-503. See 
    Utah Code Ann. § 38
    -1a-503 (LexisNexis 2014).
    The code now provides that a lien ‚relates back to, and takes
    effect as of, the time of the first preliminary notice filing.‛ 
    Id.
    § 38-1a-503(1).
    20130973-CA                      4                 
    2015 UT App 29
    Pentalon v. Rymark Properties, LLC.
    The liens herein provided for shall relate back to,
    and take effect as of, the time of the
    commencement to do work or furnish materials on
    the ground for the structure or improvement, and
    shall have priority over any lien, mortgage or other
    encumbrance        which   may      have   attached
    subsequently to the time when the building,
    improvement or structure was commenced, [or]
    work begun . . . .
    
    Id.
     The Act ‚is remedial in nature and seeks to provide
    protection to laborers and materialmen who have added directly
    to the value of the property of another by their materials or
    labor.‛ Calder Bros. Co. v. Anderson, 
    652 P.2d 922
    , 924 (Utah 1982).
    As a result, we construe the phrase ‚commencement to do
    work‛ in favor of lien claimants. 
    Id.
     ‚Materialmen’s and
    mechanics’ liens resulting from materials furnished or labor
    performed relate back to and attach as of the date of the
    commencement of the first work on the improvement or
    structure involved.‛ 
    Id.
    ¶10 To constitute commencement of work under the Act, the
    work must be of the type ‚‘that a person using reasonable
    diligence in examining the property would be able to see it and
    be on notice that lienable work was underway.’‛ EDSA/Cloward,
    LLC v. Klibanoff (Klibanoff I), 
    2005 UT App 367
    , ¶ 22, 
    122 P.3d 646
    (quoting E.W. Allen & Assocs., Inc. v. FDIC, 
    776 F. Supp. 1504
    ,
    1509 (D. Utah 1991)). The work must be visible because ‚visible
    evidence of work performed provides notice to any interested
    party that work has commenced.‛ Anderson, 652 P.2d at 924 n.1;
    accord Ketchum, Konkel, Barrett, Nickel & Austin v. Heritage
    Mountain Dev. Co., 
    784 P.2d 1217
    , 1221 (Utah Ct. App. 1989).
    When considering on-site visible work, we consider whether ‚all
    the work together . . . may contribute to putting a reasonable
    observer . . . on notice that [lienable] work was underway.‛
    EDSA/Cloward, LLC v. Klibanoff (Klibanoff II), 
    2008 UT App 20130973
    -CA                      5                 
    2015 UT App 29
    Pentalon v. Rymark Properties, LLC.
    284, ¶ 11, 
    192 P.3d 296
     (alteration and omissions in original)
    (citation and internal quotation marks omitted).
    ¶11 In general, site preparation does not constitute
    commencement, because it may not put a person using
    reasonable diligence on notice that lienable work is underway.
    For example, in Ketchum, Konkel, Barrett, Nickel & Austin v.
    Heritage Mountain Development Co., 
    784 P.2d 1217
    , 1221 (Utah Ct.
    App. 1989), we held that ‚surveying, staking, and soil testing‛
    do not constitute commencement, because they ‚do not
    constitute a visible on-site improvement.‛Id. at 1228. There, the
    workers performed architectural, engineering, surveying,
    consulting, and planning services for a ski resort. 
    Id. at 1219
    .
    However, their work did not qualify for priority because ‚the
    mere fact that work was a proper subject of a lien cannot
    establish priority where it does not give notice of
    commencement.‛ 
    Id. at 1227
     (citation and internal quotation
    marks omitted).
    ¶12 In Klibanoff II, 
    2008 UT App 284
    , 
    192 P.3d 296
    , this court
    determined that surveys, wetlands delineations, groundwater
    monitoring, geotechnical testing, and irrigation work did not
    constitute commencement of work. 
    Id.
     ¶¶ 10–12. We reasoned
    that because the work did not suggest the existence of an
    ‚impending or ongoing construction project on the *p+roperty,‛
    id. ¶ 12, the work failed ‚to put a prudent lender on notice that
    lienable work was under way,‛ id. ¶ 20.
    ¶13 Furthermore, in Western Mortgage Loan Corp. v. Cottonwood
    Construction Co., 
    424 P.2d 437
     (Utah 1967), our supreme court
    stressed the requirement of visible on-site construction. Id. at
    439. There, the court determined that off-site general subdivision
    improvements not involving the lot at issue did not constitute
    commencement of work. Id. The court stated that ‚*t+he problem
    is one of notice. The presence of materials on the building site or
    evidence on the ground that work has commenced on a structure
    20130973-CA                     6                 
    2015 UT App 29
    Pentalon v. Rymark Properties, LLC.
    or preparatory thereto is notice to all the world that liens may
    have attached.‛ 
    Id.
    ¶14 Accordingly, the United States District Court for the
    District of Utah has ruled that under Utah law ‚*a+ctual
    excavation for the foundation of a building‛ constitutes
    commencement under the Act because ‚a person
    using reasonable diligence in examining the premises would be
    able to see it and be on notice that lienable work was
    underway.‛ E.W. Allen & Assocs., Inc., 
    776 F. Supp. at 1509
    .
    Claimants assert, and FDIC has cited no contrary case, that this
    is the universal rule. See J.R. Harvey, Annotation, What
    Constitutes “Commencement of Building or Improvement” for
    Purposes of Determining Accrual of Mechanic’s Lien, 
    1 A.L.R.3d 822
    (1965 & Supp. 2013) (collecting more than eighty cases that
    support the proposition that excavation of a foundation or
    basement constitutes commencement); see also Wylie v. Douglas
    Lumber Co., 
    8 P.2d 256
    , 257 (Ariz. 1932) (concluding that
    excavation of a foundation is sufficient to constitute
    commencement of work for mechanic’s lien priority); Seracuse
    Lawler & Partners, Inc. v. Copper Mountain, 
    654 P.2d 1328
    , 1330–31
    (Colo. App. 1982); Consolidated Lumber Co. v. Northern Lakes
    Constr. of MN, Inc., No. A10-1472, 
    2011 WL 1545794
    , at *3 (Minn.
    Ct. App. Apr. 26, 2011); Drilling Serv. Co. v. Baebler, 
    484 S.W.2d 1
    ,
    9 (Mo. 1972); Robison v. Thatcher, 
    451 P.2d 863
    , 864 (Or. 1969).
    ¶15 Here, Pentalon had nearly completed excavation for the
    foundation of the building when FDIC recorded its trust deed.
    By that time Pentalon had already spent over 213 hours
    excavating the property with heavy machinery and installing
    geotextile fabric. In fact, the excavation trenches appear to
    outline the footprint of a building. Unlike prior cases where we
    have denied priority to lien claimants because they did not
    conduct visible on-site work, here, a ‚prudent lender [would be]
    20130973-CA                      7                 
    2015 UT App 29
    Pentalon v. Rymark Properties, LLC.
    on notice that lienable work was under way.‛ See Klibanoff II,
    
    2008 UT App 284
    , ¶ 20.2
    ¶16 FDIC argues that Pentalon’s work does not constitute
    commencement, because Pentalon had not actually completed
    excavation before FDIC recorded its trust deed. FDIC posits that
    ‚partial excavation looks very much like the activities that do
    not amount to commencement under Utah law: clearing land,
    grading land, and general excavation.‛ But here, Pentalon’s
    near-complete excavation consisted of digging trenches for the
    foundation of a building, piling mounds of dirt, and installing
    geotextile fabric. This work does not resemble ‚clearing land,
    grading land, or general excavation.‛ Rather, any person using
    reasonable diligence in examining the property would be able to
    see the work and be on notice that lienable work was under way.
    Calder Bros. Co. v. Anderson, 
    652 P.2d 922
    , 924 (Utah 1982).
    ¶17 FDIC, citing a case from Missouri, argues further that
    until excavation of a basement or foundation is complete, a
    reasonable observer would be unable to determine if the work
    constitutes commencement. See H.B. Deal Constr. Co. v. Labor
    Disc. Ctr., Inc., 
    418 S.W.2d 940
    , 944, 952 (Mo. 1967). However, the
    case FDIC cites actually holds that ongoing excavation of a
    foundation constitutes work sufficient to place a reasonable
    observer on notice that construction is underway. Id. at 954. The
    rule derived from this holding, the ‚first-spade rule,‛ provides
    2. We recognize the apparent circularity in tying when a lien
    attaches to when an observer would observe ‚lienable‛ work.
    We read the phrase ‚lienable work‛ as shorthand for ‚work on
    the ground for the structure or improvement.‛ 
    Utah Code Ann. § 38-1-5
     (LexisNexis 2005). We thus understand the rule to be
    that the lien attaches when a prudent lender would recognize
    that work on the ground for a structure or improvement is under
    way. See Klibanoff II, 
    2008 UT App 284
    , ¶ 20, 
    192 P.3d 296
    .
    20130973-CA                     8                 
    2015 UT App 29
    Pentalon v. Rymark Properties, LLC.
    that ‚commencement‛ means ‚the visible commencement of
    actual operations on the ground for the erection of the building
    or the making of the improvement which makes it apparent that
    a building has been commenced or that an improvement is to be
    made.‛ Id. at 951. Claimants rightly point out that FDIC’s
    reading would convert Missouri’s ‚first-spade rule‛ into a ‚last-
    spade rule.‛
    ¶18 Finally, FDIC maintains that Pentalon’s excavation
    amounted to no more than soil leveling, which, they argue,
    under Utah law does not constitute commencement of work. In
    support of this argument, FDIC offers dicta from our opinion in
    Ketchum: ‚Utah’s position is consistent with the majority of
    jurisdictions which have ruled that . . . leveling the ground . . .
    *does+ not constitute ‘visible’ on-site improvements required to
    establish priority under mechanics’ liens statutes.‛ Ketchum,
    Konkel, Barrett, Nickel & Austin v. Heritage Mountain Dev. Co., 
    784 P.2d 1217
    , 1227 (Utah Ct. App. 1989) (holding that surveying,
    staking, and soil-core sampling did not constitute visible on-site
    improvement and therefore did not constitute commencement of
    work). If we had previously held that leveling the ground did
    not constitute commencement of work, and had Pentalon done
    nothing more than level the ground, this argument might have
    some force. But our caselaw has never drawn this distinction. In
    any event, Pentalon did very nearly the opposite of leveling the
    ground: it dug wide trenches, in distinctive shapes, see infra
    Exhibit C, in otherwise level ground. In light of the statutory
    text, the difference matters: while level ground might leave a
    reasonable observer to doubt whether work on a particular
    ‚structure or improvement‛ had commenced, excavation in the
    shape of a structure or improvement does not. See 
    Utah Code Ann. § 38-1-5
     (LexisNexis 2005).
    ¶19 In conclusion, Pentalon’s nearly completed excavation
    constitutes ‚commencement‛ under the Act because the
    excavation was sufficient ‚to put a prudent lender on notice that
    20130973-CA                     9                 
    2015 UT App 29
    Pentalon v. Rymark Properties, LLC.
    lienable work was under way.‛ See Klibanoff II, 
    2008 UT App 284
    ,
    ¶ 20, 
    192 P.3d 296
    .3
    II. Pentalon’s Other Contentions Are Not Ripe.
    ¶20 Pentalon also contends that ‚the district court erred in
    striking evidence Pentalon submitted alongside its opposition to
    FDIC’s motion for summary judgment‛ and that ‚the district
    court erred in striking Pentalon’s motion for reconsideration.‛
    Pentalon asks us to address these issues on the ground that
    ‚they will be relevant to the determination of Pentalon’s
    attorney fee award on remand.‛ Pentalon argues that it ‚should
    be entitled to the attorney fees it incurred in preparing these
    erroneously stricken materials.‛ FDIC responds that ‚the trial
    court acted well within its discretion‛ in ‚declining to grant
    Pentalon’s repetitive motions for reconsideration‛ and in
    striking the evidence it submitted.
    ¶21 We decline to address these issues because they are not
    ripe. The ripeness doctrine ‚serves to prevent courts from
    issuing advisory opinions on issues that are not ripe for
    adjudication.‛ Fundamentalist Church of Jesus Christ of Latter-Day
    Saints v. Lindberg, 
    2010 UT 51
    , ¶ 40, 
    238 P.3d 1054
     (citation and
    internal quotation marks omitted). A dispute ‚is ripe when a
    conflict over the application of a legal provision [has] sharpened
    into an actual or imminent clash of legal rights and obligations
    between the parties thereto.‛ Bodell Constr. Co. v. Robbins, 
    2009 UT 52
    , ¶ 29, 
    215 P.3d 933
     (alteration in original) (citation and
    internal quotation marks omitted). On the other hand, a dispute
    is not ripe ‚if there exists no more than a difference of opinion
    3. Because we rule as a matter of law that Pentalon’s excavation
    work constituted commencement under the Act, we do not
    address Pentalon’s alternative contention that a genuine issue of
    material fact existed.
    20130973-CA                    10                
    2015 UT App 29
    Pentalon v. Rymark Properties, LLC.
    regarding the hypothetical application of [a provision] to a
    situation in which the parties might, at some future time, find
    themselves.‛ 
    Id.
     (alteration in original) (citation and internal
    quotation marks omitted).
    ¶22 Here, Pentalon asks us to rule on certain ‚procedural
    decisions . . . because they will be relevant to the determination
    of Pentalon’s attorney fee award on remand.‛ Pentalon asks us
    to do so to set the table for its motion for attorney fees in the trial
    court. But Pentalon has not yet prevailed below, nor filed a
    motion for attorney fees, nor has the trial court denied a fee
    motion. Accordingly, the dispute remains at this stage
    hypothetical. It presents ‚a situation in which the parties might,
    at some future time, find themselves,‛ rather than a conflict
    ‚sharpened into an actual or imminent clash of legal rights and
    obligations between the parties.‛ 
    Id.
     (citation and internal
    quotation marks omitted). We accordingly decline to address the
    propriety of the district court’s procedural orders at this time.
    III. We Decline to Affirm the District Court’s Ruling on
    Alternative Grounds.
    ¶23 In addition to defending the district court’s ruling on
    section 38-1-5, FDIC asks us to affirm the district court’s ruling
    that ‚FDIC’s deed of trust is entitled to priority over Pentalon’s
    mechanic’s lien‛ on two alternative grounds: first, that
    Pentalon’s work ‚was not lienable‛ under the Act, because
    Pentalon did not perform its work ‚at the instance of the owner‛
    as the Act requires. See 
    Utah Code Ann. § 38-1-3
     (LexisNexis
    2005); and second, that Pentalon ‚is estopped from asserting the
    priority of its mechanic’s lien.‛
    ¶24 Claimants urge this court not to reach these alternative
    grounds. They contend that FDIC ‚stayed further briefing of
    the[se] arguments in the district court.‛ Claimants further argue
    that had FDIC presented the district court with the argument
    that Pentalon’s work was not performed at the instance of the
    20130973-CA                       11                 
    2015 UT App 29
    Pentalon v. Rymark Properties, LLC.
    owner, they ‚would have developed a record . . . support*ing+
    the proposition that it began (and nearly finished) excavating the
    foundation of the project ‘at the instance of the owner.’‛ Finally,
    Claimants maintain that discovery relevant to FDIC’s estoppel
    argument was still in progress when the district court entered
    the order presently on appeal.
    ¶25 Though we are never obligated to affirm on other
    grounds, this court may choose to affirm the judgment of the
    district court on any legal ground or theory apparent on the
    record:
    [A]n appellate court may affirm the judgment
    appealed from if it is sustainable on any legal
    ground or theory apparent on the record, even
    though such ground or theory differs from that
    stated by the trial court to be the basis of its ruling
    or action, and this is true even though such ground
    or theory is not urged or argued on appeal by
    appellee, was not raised in the lower court, and
    was not considered or passed on by the lower
    court.
    Bailey v. Bayles, 
    2002 UT 58
    , ¶ 10, 
    52 P.3d 1158
     (citation and
    internal quotation marks omitted). ‚Of course, the converse is
    also true: we will not affirm a judgment if the alternate ground
    or theory is not apparent on the record.‛ Francis v. State, 
    2010 UT 62
    , ¶ 19, 
    248 P.3d 44
    . To affirm on a ground not apparent on the
    record ‚would invite *each+ party to selectively focus on issues
    below, the effect of which is holding back issues that the
    opposition had neither notice of nor an opportunity to address.‛
    State v. Montoya, 
    937 P.2d 145
    , 149 (Utah Ct. App. 1997). An
    alternative ground is ‚apparent on the record‛ if the record
    contains ‚sufficient and uncontroverted evidence supporting the
    ground or theory to place a person of ordinary intelligence on
    notice that the prevailing party may rely thereon on appeal.‛ 
    Id.
    at 149–50.
    20130973-CA                     12                 
    2015 UT App 29
    Pentalon v. Rymark Properties, LLC.
    ¶26 We decline to reach the alternative theories advocated by
    FDIC as grounds to affirm. FDIC has not demonstrated that
    these claims are ‚apparent on the record.‛ See Bailey, 
    2002 UT 58
    ,
    ¶ 10. Claims are not apparent on the record where, as here, the
    district court’s consideration of the issues was stayed at a stage
    where, Claimants reasonably argue, further record development
    was necessary. Of course, FDIC is free to pursue these theories
    on remand.
    CONCLUSION
    ¶27 Pentalon’s near-complete excavation work constitutes
    commencement of work under section 38-1-5. We therefore
    reverse the district court’s grant of FDIC’s motion for summary
    judgment and its denial of Pentalon’s motion for summary
    judgment and remand the case for further proceedings.
    20130973-CA                    13                
    2015 UT App 29
    Pentalon v. Rymark Properties, LLC.
    EXHIBIT A
    20130973-CA                   14                
    2015 UT App 29
    Pentalon v. Rymark Properties, LLC.
    EXHIBIT B
    20130973-CA                   15                
    2015 UT App 29
    Pentalon v. Rymark Properties, LLC.
    EXHIBIT C
    20130973-CA                   16                
    2015 UT App 29
    Pentalon v. Rymark Properties, LLC.
    DAVIS, Judge (dissenting):
    ¶28 I agree with the majority’s determination that the district
    court erred in concluding that work had not commenced as a
    matter of law. Accordingly, I concur in reversing the district
    court’s grant of summary judgment in favor of FDIC. However, I
    do not agree with the majority that the question of whether work
    had commenced can be decided as a matter of law under the
    circumstances of this case. Thus, I would affirm the district
    court’s denial of Pentalon’s motion for summary judgment on
    alternative grounds, namely, that disputed issues of material fact
    precluded summary judgment.
    ¶29 The question of whether ‚a person using reasonable
    diligence in examining the property would be able to see [the
    work] and be on notice that lienable work was underway‛ is a
    question for the factfinder under the circumstances of this case.
    See Klibanoff I, 
    2005 UT App 367
    , ¶ 22, 
    122 P.3d 646
     (citation and
    internal quotation marks omitted). Although I do not necessarily
    disagree with the majority’s conclusion that the photographs
    depict lienable work, I do not think that this conclusion may be
    reached as a matter of law. See Utah R. Civ. P. 56(c); Jones v.
    Farmers Ins. Exch., 
    2012 UT 52
    , ¶ 8, 
    286 P.3d 301
     (observing that
    ‚*a+ genuine issue of fact exists where, on the basis of the fact in
    the record, reasonable minds could differ on whether . . .
    conduct measures up to the required standard‛ and that
    ‚summary judgment should be granted only when it clearly
    appears that there is no reasonable probability that the party
    moved against could prevail‛ (citations and internal quotation
    marks omitted)). In reaching its determination, I believe the
    majority has impermissibly entered the realm of factfinding,
    which should be left to the trial court judge or jury.
    ¶30 Moreover, in light of our reversal of the court’s ruling on
    FDIC’s motion for summary judgment, I am not convinced that
    the district court’s denial of Pentalon’s motion for summary
    judgment is ripe for appeal. The denial of a motion for summary
    20130973-CA                     17                 
    2015 UT App 29
    Pentalon v. Rymark Properties, LLC.
    judgment is ‚archetypically non-final‛ because it ‚leave*s+ the
    merits of the case unresolved.‛ Mellor v. Wasatch Crest Mut. Ins.,
    
    2012 UT 24
    , ¶ 12, 
    282 P.3d 981
    ; see also Heuser v. Schmittroth, 2002
    UT App 42U, para. 2 (‚The denial of a summary judgment
    motion is not final and appealable because it leaves the case
    pending.‛). Because we have reversed the district court’s grant
    of summary judgment in favor of FDIC, the case is once again
    unresolved. Thus, appeal from the district court’s denial of
    Pentalon’s motion may be more appropriate once the case has
    been resolved on the merits following a trial. See Normandeau v.
    Hanson Equip., Inc., 
    2009 UT 44
    , ¶ 15, 
    215 P.3d 152
     (holding that
    the denial of a motion for summary judgment on purely legal
    grounds may be appealed following a trial on the merits).
    20130973-CA                     18                 
    2015 UT App 29