Hillcrest v. Department of Transportation , 352 P.3d 128 ( 2015 )


Menu:
  •                        
    2015 UT App 140
    THE UTAH COURT OF APPEALS
    HILLCREST INVESTMENT COMPANY, LLC,
    Plaintiff and Appellant,
    v.
    DEPARTMENT OF TRANSPORTATION,
    Defendant and Appellee.
    Opinion
    No. 20140377-CA
    Filed June 4, 2015
    Second District Court, Farmington Department
    The Honorable John R. Morris
    No. 080700723
    David L. Arrington, Joshua D. Chandler and Rebecca
    G. Van Tassell, Attorneys for Appellant
    Sean D. Reyes, Brent A. Burnett, and Randy S.
    Hunter, Attorneys for Appellee
    JUDGE JAMES Z. DAVIS authored this Opinion, in which JUDGES
    GREGORY K. ORME and MICHELE M. CHRISTIANSEN concurred.
    DAVIS, Judge:
    ¶1     Hillcrest Investment Company, LLC (Hillcrest) appeals
    the district court’s grant of summary judgment in favor of the
    Utah Department of Transportation (UDOT). We affirm.
    BACKGROUND
    ¶2     As part of the Legacy Parkway Project in Centerville,
    Utah, UDOT negotiated a Right of Way Contract (the Contract)
    to purchase three parcels of property held by several different
    trusts (the Trusts). The Trusts’ sole means of accessing their
    remaining property was via a dirt road located on one of the
    Hillcrest Investment Company, LLC v. Department of Transportation
    parcels UDOT intended to purchase. During the negotiations,
    the Trusts expressed this concern and UDOT represented that its
    plans included the construction of a frontage road on one
    particular parcel it sought from the Trusts, Parcel 173C. UDOT
    repeated this representation in several documents it supplied to
    the Trusts. The Trusts ultimately issued warranty deeds in
    accordance with the Contract. In the deeds, the Trusts reiterated
    the public purposes for which each parcel was conveyed,
    including that Parcel 173C was conveyed “for a frontage road
    incident to the construction of a freeway known as [the Legacy
    Parkway Project].” 1 Ultimately, the frontage road was removed
    from the final plans for the Legacy Parkway Project and never
    constructed. The Contract’s terms describe UDOT’s obligation as
    simply to pay the Trusts for the parcels, which the Contract
    identifies by referencing the warranty deeds. The Contract itself
    contained no reference to a frontage road.
    ¶3      Hillcrest, as successor-in-interest to the Trusts, brought
    suit alleging that UDOT breached the Contract with the Trusts in
    which it agreed to pay for and construct a frontage road on
    Parcel 173C. UDOT moved for summary judgment on the
    ground that Hillcrest lacked standing because it was not a party
    to the Contract. The district court granted UDOT’s motion.
    Hillcrest appealed to this court. We reversed the district court’s
    ruling in Hillcrest Investment Co., LLC v. Utah Department of
    Transportation, 
    2012 UT App 256
    , 
    287 P.3d 427
    . Specifically, we
    held that factual questions relating to Hillcrest’s standing
    precluded summary judgment. 
    Id. ¶ 1
    .
    ¶4     On remand, after further briefing and argument by the
    parties, the district court ruled that Hillcrest had standing to
    assert its claims under the Contract. UDOT subsequently filed a
    1. UDOT received four separate warranty deeds for Parcel 173C,
    each conveying the fractional interest owned by the separate
    trusts.
    20140377-CA                     2              
    2015 UT App 140
    Hillcrest Investment Company, LLC v. Department of Transportation
    renewed motion for summary judgment, arguing that the
    Contract is unambiguous and does not obligate UDOT to pay for
    or construct the frontage road. The district court agreed and
    granted summary judgment in favor of UDOT on all of
    Hillcrest’s claims. Hillcrest appeals the ruling on two of its
    claims—breach of contract and unjust enrichment.
    ISSUE AND STANDARD OF REVIEW
    ¶5     “Summary judgment is appropriate where (1) there is no
    genuine issue as to any material fact and (2) the moving party is
    entitled to a judgment as a matter of law.” 
    Id. ¶ 11
     (citation and
    internal quotation marks omitted). “We review a district court’s
    grant of summary judgment de novo, reciting all facts and fair
    inferences drawn from the record in the light most favorable to
    the nonmoving party.” 
    Id.
     (citation and internal quotation marks
    omitted).
    ANALYSIS
    I. Breach of Contract
    ¶6     Hillcrest challenges the district court’s conclusion that the
    Contract is “clear and unambiguous” and that it “does not
    contain any obligation, executory or otherwise, requiring UDOT
    to pay for or construct a frontage road on Parcel 173C.” Hillcrest
    asserts that the warranty deeds for Parcel 173C identify the
    purpose of that conveyance as “for a frontage road” and that
    because the deeds are incorporated by reference into the
    Contract, the Contract establishes UDOT’s obligation to
    construct a frontage road on that parcel. Alternatively, Hillcrest
    argues that the Contract and warranty deeds are ambiguous,
    particularly in light of “the parties’ undisputed intent at the time
    of contracting” that UDOT would “build a frontage road to
    restore access” to the Trusts’ remaining properties in exchange
    20140377-CA                     3                
    2015 UT App 140
    Hillcrest Investment Company, LLC v. Department of Transportation
    for the Trusts’ agreement to forgo “payment of severance
    damages.”
    ¶7      “[C]ontractual ambiguity can occur in two different
    contexts: (1) facial ambiguity with regard to the language of the
    contract and (2) ambiguity with regard to the intent of the
    contracting parties.” Daines v. Vincent, 
    2008 UT 51
    , ¶ 25, 
    190 P.3d 1269
    . “The first context presents a question of law to be
    determined by the judge,” and the “second context presents a
    question of fact where, if the judge determines that the contract
    is facially ambiguous, parol evidence of the parties’ intentions
    should be admitted.” 
    Id.
     (citation and internal quotation marks
    omitted). Accordingly, “the question of ambiguity begins with
    an analysis of facial ambiguity.” 
    Id. ¶8
         “A contract provision is ambiguous if it is capable of more
    than one reasonable interpretation because of uncertain
    meanings of terms, missing terms, or other facial deficiencies.”
    Winegar v. Froerer Corp., 
    813 P.2d 104
    , 108 (Utah 1991) (citation
    and internal quotation marks omitted). “When determining
    whether a contract is ambiguous, any relevant evidence must be
    considered. Otherwise, the determination of ambiguity is
    inherently one-sided, namely, it is based solely on the extrinsic
    evidence of the judge’s own linguistic education and
    experience.” Ward v. Intermountain Farmers Ass'n, 
    907 P.2d 264
    ,
    268 (Utah 1995) (citation and internal quotation marks omitted).
    “Then, after the trial court has considered evidence of contrary
    interpretations, the [trial court] must ensure that the
    interpretations contended for are reasonably supported by the
    language of the contract.” Hall v. Hall, 
    2013 UT App 280
    , ¶ 12,
    
    316 P.3d 970
     (alteration in original) (citations and internal
    quotation marks omitted); see also Watkins v. Henry Day Ford,
    
    2013 UT 49
    , ¶ 28 n.2 (“The introduction of any relevant evidence
    does not . . . allow a litigant to create ambiguity out of whole
    cloth or to advocate for an interpretation that is in no way
    supported by the language of the underlying contract.”
    (emphasis, citation, and internal quotation marks omitted)). “If
    20140377-CA                     4               
    2015 UT App 140
    Hillcrest Investment Company, LLC v. Department of Transportation
    after considering such evidence the court determines that the
    interpretations contended for are reasonably supported by the
    language of the contract, then extrinsic evidence is admissible to
    clarify the ambiguous terms.” Ward, 907 P.2d at 268.
    ¶9      We must first consider Hillcrest’s relevant extrinsic
    evidence to determine whether the Contract is ambiguous.
    Hillcrest submitted several pieces of correspondence and
    documents exchanged between the Trusts and UDOT during
    their negotiations that indicate the parties’ shared intent that
    UDOT would construct a frontage road on Parcel 173C and that
    the purchase price would reflect that obligation. Likewise, the
    district court acknowledged that initially the parties intended
    that Parcel 173C would be used for a frontage road.
    ¶10 Next, Hillcrest identifies the phrase “for a frontage road”
    appearing in the warranty deeds for Parcel 173C as reflecting
    this intent. Hillcrest asserts that the deeds are incorporated by
    reference in the Contract and, accordingly, that the Contract can
    reasonably be interpreted to require UDOT to build a frontage
    road.
    ¶11 The district court considered the Contract’s reference to
    the deeds to serve the limited purpose of providing the legal
    description of the land UDOT purchased. Additionally, the
    district court interpreted Hillcrest’s evidence “regarding the
    circumstances surrounding the [Contract]” as “merely
    reflect[ing] that the parties had discussions relating to the
    construction of a frontage road and even intended that Parcel
    173C be used for that construction” but concluded that the
    evidence of the parties’ intent was outweighed by the absence of
    supporting language in the final, integrated Contract.2
    2. The district court also indicated that the parties knew at the
    time of contracting “that the Legacy Parkway Project’s plans
    (continued…)
    20140377-CA                     5              
    2015 UT App 140
    Hillcrest Investment Company, LLC v. Department of Transportation
    ¶12 The entire reference to Parcel 173C in the Contract is as
    follows: “[T]he Utah Department of Transportation shall comply
    with the following: . . . (A) Pay Cash in full to the grantor(s) for
    the following: . . . Land as described in Warranty Deed No.
    0067:173:C.” While “[p]arties may incorporate by reference into
    their contract the terms of some other document,” Consolidated
    Realty Group v. Sizzling Platter, Inc., 
    930 P.2d 268
    , 273 (Utah Ct.
    App. 1996) (citation and internal quotation marks omitted), “if a
    written contract refers to another writing for a particularly
    designated purpose, the other writing becomes a part of the
    contract only for the purpose specified,” 17A C.J.S. Contracts
    § 402 (Westlaw database updated Mar. 2015); accord Housing
    Auth. v. Snyder, 
    2002 UT 28
    , ¶ 19, 
    44 P.3d 724
     (requiring “specific
    language” in order to incorporate the terms of another
    document); see also Consolidated Realty, 
    930 P.2d at 273
    (explaining that to properly incorporate the terms of another
    document “into the document executed by the parties, the
    reference must be clear and unequivocal, and must be called to
    the attention of the other party, [the party] must consent thereto,
    and the terms of the incorporated document must be known or
    easily available to the contracting parties” (alteration in original)
    (citation and internal quotation marks omitted)).
    ¶13 The Contract’s reference to the warranty deeds is, by its
    very terms, limited to identifying the parcels of land that UDOT
    agreed to purchase from the Trusts. There is no specific language
    incorporating into the Contract any terms from the warranty
    deeds that would add to UDOT’s obligations under the Contract,
    (…continued)
    were not finalized and [were] subject to change.” Hillcrest
    asserts that this is a disputed issue of fact and that there is no
    evidence in the record to support this assertion. Because this
    argument does not affect our analysis on appeal, we do not
    address it.
    20140377-CA                      6               
    2015 UT App 140
    Hillcrest Investment Company, LLC v. Department of Transportation
    such as the “for a frontage road” language relied on by Hillcrest.
    Moreover, there is language to the contrary in the Contract,
    indicating that “[n]o work, improvement, alteration or
    maintenance will be done or made other than or in addition to
    that provided in this agreement.” The Contract’s integration
    clause also provides,
    The parties have here set out the whole of their
    agreement. The performance of this agreement
    constitutes the entire consideration for the grant of
    said tract of land and shall relieve [UDOT] of all
    further obligations or claims on that account, or on
    account of the location, grade and construction of
    the proposed highway.
    We agree with the district court’s assertion that the warranty
    deeds are referenced in the Contract for the limited purpose of
    identifying the parcels of land UDOT agreed to purchase.
    ¶14 Without the language in the warranty deeds for Parcel
    173C, there is nothing in the Contract alluding to a frontage
    road, let alone an obligation on UDOT to pay for and construct a
    frontage road. Thus, we agree with the district court’s ruling that
    “the language of the [Contract] and Warranty Deeds cannot
    reasonably support a construction that obligates UDOT to pay
    for or construct a frontage road on Parcel 173C as part of its
    agreement with the [Trusts].” Accordingly, the Contract is not
    ambiguous and the extrinsic evidence of the parties’ intent
    offered by Hillcrest cannot vary the terms of the unambiguous
    agreement. See Daines v. Vincent, 
    2008 UT 51
    , ¶ 37, 
    190 P.3d 1269
    (“[W]e do not need to resort to the admission of parol evidence
    on the question of intent, because absent a finding of facial
    ambiguity, the parties’ intentions must be determined solely
    from the language of the contract.” (citation and internal
    quotation marks omitted)).
    20140377-CA                     7               
    2015 UT App 140
    Hillcrest Investment Company, LLC v. Department of Transportation
    II. Unjust Enrichment
    ¶15 Hillcrest asserts that UDOT was unjustly enriched by the
    reduced purchase price that the Trusts agreed to based on
    UDOT’s representation that it would pay for and construct a
    frontage road on Parcel 173C. Hillcrest argues that in ruling on
    its unjust enrichment claim, the district court “overlook[ed]
    undisputed evidence establishing all the required elements” of
    the claim, “construed the [C]ontract inconsistent with the court’s
    conclusion regarding Hillcrest’s contract-based claims,” and
    “disregarded authorities that allow Hillcrest to seek redress for
    UDOT’s separate representations and actions in equity
    notwithstanding the Contract.”
    ¶16 To succeed on a claim for unjust enrichment, a party must
    show that a benefit has been “conferred by one [party] on
    another,” “the conferee must appreciate or have knowledge of
    the benefit,” and “there must be acceptance or retention by the
    conferee of the benefit under such circumstances as to make it
    inequitable for the conferee to retain the benefit without
    payment of its value.” Allen v. Hall, 
    2006 UT 70
    , ¶ 26, 
    148 P.3d 939
    . In addition, “a prerequisite for recovery on an unjust
    enrichment theory is the absence of an enforceable contract
    governing the rights and obligations of the parties relating to the
    conduct at issue” because “[i]f there were a contract, it, rather
    than the law of restitution, would govern the parties’ rights and
    determine their recovery.” Ashby v. Ashby, 
    2010 UT 7
    , ¶ 14, 
    227 P.3d 246
     (“Recovery under [unjust enrichment] presupposes that
    no enforceable written or oral contract exists.” (alteration in
    original) (citation and internal quotation marks omitted)). “Our
    case law, however, supports the proposition that even where
    there is an express contract, an equitable claim may be viable,
    under specific factual circumstances, if the equitable claim is
    based on a separate representation or misleading act arising
    independently of the express contract.” E & M Sales W., Inc. v.
    Diversified Metal Prods., Inc., 
    2009 UT App 299
    , ¶ 8, 
    221 P.3d 838
    .
    20140377-CA                     8               
    2015 UT App 140
    Hillcrest Investment Company, LLC v. Department of Transportation
    ¶17 The district court ruled that because the Contract
    indisputably relates to UDOT’s purchase of the property from
    the Trusts, Hillcrest cannot recover “under an equitable theory
    of unjust enrichment.” In addition, the district court concluded
    that UDOT did not receive a benefit under the Contract for
    which it did not provide just compensation. The court
    considered Hillcrest’s unjust enrichment argument to amount to
    a request that the court “‘make a better contract for the parties
    than they have made for themselves,’” which the court explicitly
    declined to do. (Quoting Ted R. Brown & Assocs. v. Carnes Corp.,
    
    753 P.2d 964
    , 970 (Utah Ct. App. 1988).)
    ¶18 Hillcrest asserts that the Contract does not preclude its
    unjust enrichment claim and that the district court’s conclusion
    is contradictory to the court’s rejection of Hillcrest’s breach of
    contract claim. Hillcrest argues that “[i]f the court’s first holding
    were correct (that the [C]ontract does not involve a frontage
    road), then Hillcrest’s claim for unjust enrichment would not be
    precluded because Hillcrest would not be entitled to relief under
    the [C]ontract.” According to Hillcrest, whether UDOT is
    required by the Contract to build the road is distinct from
    whether “UDOT’s separate, repeated representations and
    misleading acts” “regarding the frontage road [that] induce[d] a
    settlement with the [T]rusts” based on UDOT’s promise of a
    road in exchange for the Trusts waiver of severance damages
    supported an unjust enrichment claim.
    ¶19 We disagree. Hillcrest’s unjust enrichment claim revolves
    around whether the Contract represents a fair bargain. 3
    Although Hillcrest has presented evidence suggesting that the
    parties’ intent at the time of contracting was not adequately
    reflected in the terms of the final Contract, we agree with the
    district court that this does not amount to unjust enrichment.
    3. Hillcrest has not appealed the district court’s dismissal of its
    fraudulent inducement and negligent misrepresentation claims.
    20140377-CA                      9               
    2015 UT App 140
    Hillcrest Investment Company, LLC v. Department of Transportation
    That the Contract was perhaps poorly drafted is not actionable
    under the theories argued, particularly where all parties were
    represented by counsel and the signed Contract was a product of
    extensive negotiations. Hillcrest’s objections to the fairness of the
    bargain struck cannot be remedied at this stage of the
    proceedings. As the district court observed, “‘[a] court may not
    make a better contract for the parties than they have made for
    themselves.’” (Quoting Ted R. Brown, 
    753 P.2d at 970
    ); see also
    Dalton v. Jerico Constr. Co., 
    642 P.2d 748
    , 750 (Utah 1982) (“[I]t is
    not for a court to rewrite a contract improvidently entered into at
    arm’s length or to change the bargain indirectly on the basis of
    supposed equitable principles.”).
    CONCLUSION
    ¶20 The district court’s ruling granting summary judgment in
    favor of UDOT on Hillcrest’s breach of contract and unjust
    enrichment claims was not erroneous. We affirm the district
    court’s ruling.
    20140377-CA                     10               
    2015 UT App 140