I-D Electric Inc. v. Gillman ( 2017 )


Menu:
  •                        
    2017 UT App 144
    THE UTAH COURT OF APPEALS
    I-D ELECTRIC INC.,
    Appellee,
    v.
    LINDA GILLMAN,
    Appellant.
    Opinion
    No. 20150682-CA
    Filed August 10, 2017
    Third District Court, Salt Lake Department
    The Honorable Richard D. McKelvie
    No. 110917777
    Mark D. Stubbs and Barnard N. Madsen, Attorneys
    for Appellant
    Jeffrey T. Colemere and Brady T. Gibbs, Attorneys
    for Appellee
    JUDGE KATE A. TOOMEY authored this Opinion, in which JUDGES
    GREGORY K. ORME and JILL M. POHLMAN concurred.
    TOOMEY, Judge:
    ¶1     This case involves a contract for electrical services
    between a company and a homeowner and a mechanic’s lien to
    secure payment for those services. What began as a dispute over
    less than $2,000 has ballooned into a judgment exceeding
    $36,000. Linda Gillman, the homeowner, appeals the district
    court’s decision in favor of I-D Electric. We affirm in part,
    reverse in part, and remand for further proceedings.
    BACKGROUND
    ¶2   On Thursday, March 10, 2011, Gillman approached Chet
    Hunter at an electrical wholesale supply store. She asked if he
    I-D Electric v. Gillman
    was an electrician and if he could do some emergency electrical
    work at her house in Herriman. Hunter, a journeyman
    electrician, told Gillman to arrange an appointment through his
    employer I-D Electric (I-D). Later that day, I-D sent Hunter to
    Gillman’s house to assess the scope of the work needed. Hunter
    spent approximately two hours discussing it with Gillman, who
    asked him how much the work would cost. Hunter told her he
    did not price the materials and therefore did not know how
    expensive the job would be. I-D usually used a “cost-plus”1
    system, under which the cost of materials and the hourly rate of
    the labor are calculated after a job is completed. Alternatively, at
    the customer’s request, I-D used a bid system, under which it
    calculated the cost of the labor and materials in advance, and the
    price of the job is fixed at this amount. Gillman did not request a
    bid.
    ¶3     Hunter testified there was “a lot of work to be done,” but
    Gillman’s “priority” was work in the attic above the garage.
    Contractors were coming the following week to install a floor in
    the garage attic, and Gillman needed an electrician to move “all
    of the wires draped over the trusses in the attic.” Because the
    work “needed to be done immediately,” I-D rearranged Hunter’s
    schedule to work on Gillman’s project the very next day.
    ¶4     On Friday, Hunter returned to the Herriman house with
    two associates, a residential journeyman and an apprentice. They
    arrived before eight thirty that morning, and spent the entire day
    working on the projects Gillman had assigned. Gillman arrived
    later the same morning and occasionally went to the garage
    where the men were working. That afternoon, Hunter left briefly
    to buy additional supplies. While he was gone, the residential
    journeyman had Gillman sign a work order prepared by Hunter.
    1. A cost-plus contract is one “in which payment is based on a
    fixed fee or a percentage added to the actual cost incurred.”
    Contract, Cost-plus Contract, Black’s Law Dictionary (9th ed.
    2009).
    20150682-CA                     2                
    2017 UT App 144
    I-D Electric v. Gillman
    The order, as it was initially presented to Gillman, did not
    indicate prices, but listed the materials used, summarized the
    completed jobs, and, under the heading “labor hours,” identified
    each of the three electricians by first name. The work order also
    addressed the interest I-D would charge if the payment became
    past due and stated that the “[p]urchaser agrees to pay all costs
    and expenses including reasonable attorney’s fees in the event
    collection becomes necessary.” Gillman signed the work order
    and had left the house for the day by the time Hunter returned.
    The three men finished their work and left for the evening.
    ¶5     The following Monday morning, Kim Olson, I-D’s
    president, calculated the cost of the electrical work at $1,827.61.
    He wanted to inform Gillman of this before I-D did additional
    work on the house. When Olson called her, Gillman was
    “stunned” by the amount. Olson offered to send her an
    itemization of the work order and have Hunter discuss the bill
    with her. Gillman asked how much the rest of the work would
    cost, which Olson interpreted as a request for a bid on the
    remaining work. Later that week, Hunter went to the Herriman
    house and tried to enter the garage, but the security access code
    had been changed and Gillman did not return his calls.
    ¶6     I-D sent Gillman an itemized invoice on March 24 and
    called her several times without reaching her and without
    receiving any return calls.2 Gillman returned the invoice and
    2. In its findings of fact, the district court stated:
    A pattern emerged regarding [Gillman’s]
    unwillingness to directly confront the billing issue;
    in addition to habitually failing to return phone
    calls, she ignored several letters and written
    communications,       including      certified letters
    indicating legal proceedings would be or had been
    initiated. This willful neglect on the part of
    [Gillman] contributed greatly to the costs incurred
    by [I-D] in collecting the debt.
    20150682-CA                       3               
    2017 UT App 144
    I-D Electric v. Gillman
    requested a labor breakdown and a list of the professional
    credentials of the electricians, which I-D provided at the
    beginning of April.
    ¶7     The next month, Gillman sent a letter to I-D, which read
    in part:
    [I]t is my considered judgment that the 25.5 hours
    charged for what was accomplished is
    commensurately unreasonable and warrants
    careful reconsideration. As you undertake that
    reconsideration, you might want to factor into your
    deliberation other salient information: I work in
    both construction and the practice of law. I am very
    familiar with job sites and courtrooms. I just
    completed the first $4.47 million phase of a 15-
    month construction project in December. The
    second $1.5 million phase is now underway and
    will be finished this summer. This recent
    construction project resulted from a multi-million
    construction defect lawsuit, out of state. The last
    five adversaries who lined up on the other side of a
    courtroom from me are out a total of more than $11
    million.
    I hired another licensed electrician to finish
    the work in my house and garage[,] . . . [which
    was] substantially more complicated, representing
    at least five times more work. I paid $650 for all of
    it (labor only).
    I am willing to pay a realistic amount for the
    work that was done, but no more. Please
    recalculate it.
    The letter’s heading identified Gillman’s return address as the
    Salt Lake City condominium in which Gillman lived. She used
    that address as a billing address and “in all of her
    correspondence.”
    20150682-CA                    4                
    2017 UT App 144
    I-D Electric v. Gillman
    ¶8      Olson interpreted the letter as an attempt to “intimidate
    and bully” him and hired counsel. He instructed counsel to file a
    mechanic’s lien on Gillman’s property to secure payment of the
    bill. Counsel filed the lien, but erroneously listed Gillman’s Salt
    Lake City billing address instead of the address of the Herriman
    house where the electrical work was done.3
    ¶9      I-D sent Gillman a Notice of Mechanic’s Lien by certified
    mail, but it did not hear back from her. Later, I-D sent Gillman,
    also by certified mail, a notice of its intention to initiate a lien
    foreclosure action. Gillman testified she was out of town and did
    not receive either notice.4 She testified that when she learned of
    the mechanic’s lien, she checked with the county recorder’s
    office but found no record of it.
    ¶10 I-D filed a complaint in district court in September 2011,
    and Gillman testified she did not discover the lien had listed the
    wrong address until the middle of October. In November, she
    and her counsel collaborated in drafting another letter, also
    using Gillman’s Salt Lake City address, which Gillman delivered
    directly to I-D. The letter stated:
    Hasn’t this already gone too far? First you file a
    lien on my property and I understand that has
    recently been followed by a lis pendens. Neither is
    either reasonable or justified under the
    circumstances, and without a legal basis. Please
    3. The district court rejected Gillman’s argument that I-D
    deliberately targeted her condominium for the lien: “[T]he Court
    concludes and finds that the placement of the lien on the condo
    rather than the Herriman house was a clerical error made by
    [I-D’s] counsel and not a deliberate act to gain tactical advantage
    in the collection of the debt.”
    4. The district court concluded that Gillman’s “avoidance of
    these letters was willful rather than circumstantial.”
    20150682-CA                     5                
    2017 UT App 144
    I-D Electric v. Gillman
    remove both immediately. There is no point in the
    senseless . . . accumulation of any more legal fees.
    It’s about time to do the right thing.
    The letter did not notify I-D that its lien erroneously identified
    Gillman’s Salt Lake City property and not her Herriman house.5
    ¶11 I-D was informed of the mistake by its counsel in
    December 2011, and it immediately released the lis pendens
    from Gillman’s Salt Lake City property. I-D also recorded an
    amended lien with the address of the Herriman house.
    ¶12 I-D’s complaint against Gillman alleged causes of action
    for breach of contract and lien foreclosure. Gillman filed a
    petition to nullify the lien as wrongful. In a partial motion for
    summary judgment, the district court dismissed the lien
    foreclosure action because the lien, originally listing the Salt
    Lake City address but amended with the correct Herriman
    address, was amended well outside the statutory deadline for
    filing a mechanic’s lien. After a bench trial, the court determined
    that although the mechanic’s lien was unenforceable, it was not
    wrongful. The court also determined the work order was a
    binding contract, even though it lacked a specific price term.
    Finally, the court awarded attorney fees to I-D under the
    contract, because the action was an “effort to collect a valid
    debt.” The court did not award attorney fees to Gillman for
    defeating the mechanic’s lien, but it reduced I-D’s award of
    attorney fees by $3,632, which equaled the fees I-D generated in
    “active litigation of the Mechanic’s Lien.” Gillman appeals.
    5. The district court characterized the letter as “deliberately
    vague.” Indeed, it found Gillman “knew that the lien had been
    placed on the wrong property, and that she deliberately failed to
    mention that fact in the letter to Olson,” and “did so, after
    consulting with counsel, in a deliberate effort to establish a cause
    of action against [I-D] for filing a wrongful lien.”
    20150682-CA                     6                
    2017 UT App 144
    I-D Electric v. Gillman
    ISSUES AND STANDARDS OF REVIEW
    ¶13 Gillman raises three issues on appeal. She contends the
    district court erred in determining I-D’s mechanic’s lien was not
    wrongful under the Wrongful Lien Act. See 
    Utah Code Ann. § 38-9-1
     (LexisNexis 2010).6 “The question of what constitutes a
    wrongful lien . . . is a legal question of statutory interpretation,”
    which we review for correctness. Hutter v. Dig-It, Inc., 
    2009 UT 69
    , ¶ 8, 
    219 P.3d 918
    . Gillman also contends the district court
    erred in determining there was an express contract between
    herself and I-D. Whether a contract exists is also “a question of
    law, reviewed for correctness.” Cea v. Hoffman, 
    2012 UT App 101
    ,
    ¶ 9, 
    276 P.3d 1178
    . Finally, Gillman disputes the award of
    attorney fees. Gillman specifically contends she should be
    awarded attorney fees because she was the successful party
    under the mechanic’s lien statute. “Whether attorney fees are
    recoverable in an action is a question of law, which we review
    for correctness.” Anderson & Karrenberg v. Warnick, 
    2012 UT App 275
    , ¶ 8, 
    289 P.3d 600
     (citation and internal quotation marks
    omitted).
    ANALYSIS
    I. Wrongful Lien
    ¶14 Gillman contends the district court erred in determining
    that I-D’s mechanic’s lien was not wrongful. The district court
    concluded the lien was authorized by statute even though it
    misidentified the property subject to the lien, and further
    determined “there was a good-faith basis for filing the lien” and
    “the lien was misplaced due to an explainable error.”
    6. Because I-D filed its mechanic’s lien in 2011, we reference the
    version of the Utah Code in effect at that time.
    20150682-CA                      7               
    2017 UT App 144
    I-D Electric v. Gillman
    ¶15 The relevant section of the Utah Code defines a wrongful
    lien as “any document that purports to create a lien, notice of
    interest, or encumbrance on an owner’s interest in certain real
    property and at the time it is recorded is not . . . expressly
    authorized by this chapter or another state or federal statute.”
    
    Utah Code Ann. § 38-9-1
    (6) (LexisNexis 2010). The Wrongful
    Lien Act “does not apply to a person entitled to a lien under
    Section 38-1-3 who files a lien pursuant” to the mechanic’s lien
    statute, 
    id.
     § 38-9-2, which allows “all persons performing any
    services” on a property to “have a lien upon the property . . . for
    the value of the service rendered,” id. § 38-1-3.
    ¶16 Gillman argues the Wrongful Lien Act “does not
    automatically prohibit any mechanic’s lien from being
    wrongful.” Rather, it “only prohibits a mechanic’s lien filed by ‘a
    person entitled to a lien.’” (Emphasis omitted.) In effect, Gillman
    argues that the Wrongful Lien Act could apply to a mechanic’s
    lien if the person filing it is not “entitled to” a lien under that
    statute. Further, because I-D listed the Salt Lake City property on
    its mechanic’s lien, Gillman argues the lien was not “expressly
    authorized” by statute, and therefore I-D was not entitled to it.
    ¶17 The Utah Supreme Court considered “whether an
    unenforceable mechanic’s lien is a wrongful lien subject to
    nullification under Utah’s Wrongful Lien Injunction[s] Act”7 in
    Hutter v. Dig-It, Inc., 
    2009 UT 69
    , ¶¶ 1, 46–52, 
    219 P.3d 918
    . In
    that case, the parties contested the meaning of the phrase,
    “expressly authorized by . . . statute.” One party, whose
    mechanic’s lien was unenforceable, argued that “all mechanic’s
    liens—even if they ultimately prove unenforceable—are
    expressly authorized by statute and therefore are not wrongful
    liens.” Id. ¶ 46 (emphasis added). The opposing party’s
    argument, similar to Gillman’s, was that “unenforceable lien[s]
    7. See 
    Utah Code Ann. § 38
    -9a-201 (LexisNexis 2010). This section
    of the Utah Code provides a mechanism for seeking to enjoin
    wrongful liens.
    20150682-CA                     8               
    2017 UT App 144
    I-D Electric v. Gillman
    cannot be expressly authorized by statute since the statute only
    allows liens to be recorded that comply with the statutory
    terms.” 
    Id.
    ¶18 The supreme court determined that the phrase “expressly
    authorized” was ambiguous, and so it “look[ed] to [the]
    legislative history as an aid to ascertain the intent of the
    legislature.” Id. ¶ 49. During the floor debates of the pertinent
    bill, the sponsoring senator stated that the bill’s purpose “was to
    impose penalties on those filing common law liens on the
    property of public officials in retaliation for prosecution.” Id.
    ¶ 50. Another senator was concerned that the bill’s “definition of
    a wrongful lien was too broad for the bill’s expressed purpose.”
    Id. The sponsoring senator replied, “‘This act is not intended to
    be applicable to mechanic’s or materialmen’s liens.’” Id. (quoting
    Senate Floor Debates, S.B. 178, 42nd Leg., Gen. Sess. (Utah Feb.
    21, 1985) (statement of Sen. Ivan M. Matheson)). From this
    history, the supreme court concluded that “the legislature
    intended that the definition of ‘wrongful lien’ should encompass
    only common law liens.” Id. ¶ 52. Mechanic’s liens, even if
    unenforceable, are expressly authorized by statute, and contrary
    to Gillman’s argument, are not wrongful under the Wrongful
    Lien Act. Id.
    ¶19 Gillman’s reply brief attempts to distinguish Hutter by
    arguing that the lien I-D filed was not actually a mechanic’s lien
    because the lien did not comply with the statutory requirements
    of a mechanic’s lien. According to Gillman, the Wrongful Lien
    Act therefore would apply.
    ¶20 We addressed a similar question in Bay Harbor Farm, LC v.
    Sumsion, 
    2014 UT App 133
    , 
    329 P.3d 46
    . There, the district court
    determined that an attorney’s lien was wrongful because it did
    not meet the requirements of the attorney’s lien statute. Id. ¶ 8.
    The statute in question allowed an attorney to place a lien on a
    person’s property (1) if the person was the attorney’s client and
    (2) if the person’s property was the subject of or connected with
    work performed for the client. Id. (citing 
    Utah Code Ann. § 38-2
    -
    20150682-CA                     9               
    2017 UT App 144
    I-D Electric v. Gillman
    7(2) (LexisNexis 2010)). The district court determined that the
    client’s property “was not the subject of or connected with [the
    attorney’s] work on the . . . matter.” 
    Id.
     (internal quotation marks
    omitted). Because the lien did not meet the requirements of the
    attorney’s lien statute, the district court determined it was
    wrongful under the Wrongful Lien Act. This court reversed on
    appeal, concluding that the attorney “filed an attorney’s lien
    which is expressly authorized by statute, and it is therefore not
    wrongful. This is true even if it ultimately proves unenforceable.” Id.
    ¶ 11 (emphasis added).
    ¶21 Bay Harbor Farm also clarified what qualifies as a statutory
    lien under the Wrongful Lien Act: it is not created merely by an
    allegation that the lien is expressly authorized by statute; rather,
    a “lien claimant [must have] a good-faith basis for claiming a
    statutory lien.” Id. ¶ 12. “If the claimant has ‘no plausible basis’
    for recording a statutory lien, ‘a court may declare the lien
    wrongful under the Wrongful Lien Act even if it purports to be
    one falling into the category of statutorily authorized liens.’”
    Total Restoration, Inc. v. Merritt, 
    2014 UT App 258
    , ¶ 18, 
    338 P.3d 836
     (quoting Bay Harbor Farm, 
    2014 UT App 133
    , ¶ 12). The
    attorney in Bay Harbor Farm ultimately may not have been
    entitled to an attorney’s lien if the property was not connected to
    the work performed by the attorney. But the lien was not
    wrongful because the attorney had a good-faith basis for his
    claim under the attorney’s lien statute.
    ¶22 In sum, Hutter determined that only common law liens
    may be wrongful liens and that the Wrongful Lien Act does not
    apply to liens, which though unenforceable, are not wrongful.
    But Bay Harbor Farm offers the means of determining when a lien
    is properly characterized as a statutory lien.
    ¶23 Here, I-D filed a mechanic’s lien to secure payment for
    electrical services rendered on Gillman’s property. I-D was
    entitled to place the lien on the Herriman house, but
    unintentionally identified Gillman’s Salt Lake City address in its
    notice of lien. As soon as it realized the error, I-D had the lien
    20150682-CA                      10                
    2017 UT App 144
    I-D Electric v. Gillman
    removed from the Salt Lake City property. We agree with the
    district court that I-D had a “good-faith basis for filing the lien.”
    It had completed electrical services on the Herriman house, and
    it listed the wrong address on the lien as a result of a clerical
    error on the part of its attorney. The error was inadvertent—the
    address used was the one Gillman used on the letter by which
    she disputed the work order—and does not transform I-D’s
    attempt to secure payment into a common law lien. Because the
    Wrongful Lien Act applies only to common law liens and
    because I-D had a good faith basis for claiming a statutory lien,
    the district court correctly determined that I-D’s lien was not
    wrongful.
    II. Express Contract
    ¶24 Gillman next contends the district court erred in
    determining there was an express contract between the parties in
    the absence of an agreement as to the cost of the work performed
    on her property. Gillman argues that because there was no
    agreement as to price, there cannot have been a meeting of the
    minds.
    ¶25 “It is fundamental that a meeting of the minds on the
    integral features of an agreement is essential to the formation of
    a contract. An agreement cannot be enforced if its terms are
    indefinite.” Nielsen v. Gold’s Gym, 
    2003 UT 37
    , ¶ 11, 
    78 P.3d 600
    (citation and internal quotation marks omitted). A “contract may
    be enforced even though some contract terms may be missing or
    left to be agreed upon, but if the essential terms are so uncertain
    that there is no basis for deciding whether the agreement has
    been kept or broken, there is no contract.” Id. ¶ 12 (citation and
    internal quotation marks omitted). “The court must be able to
    enforce the contract according to the parties’ intentions; if those
    intentions are impenetrable, or never actually existed, there can
    be no contract to enforce.” Id.
    ¶26 In Electrical Contractors, Inc. v. Westwater Farms, LLC, 
    2016 UT App 60
    , 
    370 P.3d 949
    , the “fact that the parties did not know
    20150682-CA                     11               
    2017 UT App 144
    I-D Electric v. Gillman
    what the ultimate cost would be d[id] not demonstrate . . . that
    there was no meeting of the minds.” Id. ¶ 11. In that case, the
    parties agreed to a cost-plus payment structure where one party
    charged the other the actual cost, plus certain, set fee markups
    on specified items. “While the cost-plus terms did not establish a
    precise price to be paid, they did provide a clear method of
    calculating the price once the work was completed . . . [and thus]
    the essential terms of the oral contract were established . . . .” Id.
    ¶27 Other states have determined that a missing price term
    does not necessarily prevent a contract from being formed or
    enforceable. See Goodman v. Physical Res. Eng’g, Inc., 
    270 P.3d 852
    ,
    855 (Ariz. Ct. App. 2011) (“An agreement can be implied and is
    enforceable where there is a valid offer and acceptance, and the
    only term missing is the final price.”); MBH, Inc. v. John Otte Oil
    & Propane, Inc., No. A-00-287, 
    2001 WL 880683
    , at *3 (Neb. Ct.
    App. Aug. 7, 2001) (“[A] contract will not necessarily fail for
    indefiniteness with regard to an open price term . . . if the parties
    have intended to make a contract and there is a reasonably
    certain basis for giving an appropriate remedy.” (citation and
    internal quotation marks omitted)); Fischer v. CTMI, LLC, 
    479 S.W.3d 231
    , 240 (Tex. 2016) (“[W]hen the parties have done
    everything else necessary to make a binding agreement . . . , their
    failure to specify the price does not leave the contract so
    incomplete that it cannot be enforced.”(omission in original)
    (citation and internal quotation marks omitted)).
    ¶28 Here, we agree with the district court that there was a
    meeting of the minds on the integral features of the contract.
    Gillman requested electrical services from I-D and discussed
    with Hunter the scope of those services. When Gillman asked
    how much it would cost, Hunter responded that he did not
    calculate the price of materials and did not know what it would
    cost, implying the cost would be calculated after the job. I-D’s
    general practice was to use a cost-plus payment system, where
    the cost was calculated after the work, unless the customer
    specifically requested a bid. I-D intended to receive payment
    20150682-CA                      12               
    2017 UT App 144
    I-D Electric v. Gillman
    from Gillman and Gillman intended to pay I-D. A court may
    enforce the contract according to those intentions.
    ¶29 In addition, Gillman signed the work order listing the
    materials used, the jobs completed, and the number of
    electricians who would be paid for their labor. Although the
    method for calculating the price may not have been as clear as in
    Electrical Contractors, there was a written contract specifying each
    item to be paid for and each person whose labor would be billed.
    Gillman, an experienced business woman, knew she would have
    to pay for the labor and materials of the jobs completed. She
    signed the work order detailing these expenses (albeit without
    specific price terms), knowing it evidenced her obligation to pay.
    Gillman was also aware that the cost would be calculated by I-D
    after the work was completed. The fact that Gillman later
    disagreed with what was charged does not mean the agreement
    was not sufficiently definite to be enforced.
    ¶30 But even though Gillman demonstrated her intention and
    obligation to pay by signing the contract, she was not bound to
    pay any amount later calculated by I-D; Gillman was only
    obligated to pay a reasonable price. See Standard Coal Co. v.
    Stewart, 
    269 P. 1014
    , 1016 (Utah 1928) (“Where the parties have
    agreed upon the other elements of the sale, but have made no
    reference to the price, . . . the law implies that the goods are to be
    paid for at what they are reasonably worth.” (omission in
    original) (citation and internal quotation marks omitted));
    Fischer, 479 S.W.3d at 240 (“[W]hen the parties have done
    everything else necessary to make a binding agreement . . . , their
    failure to specify the price does not leave the contract so
    incomplete that it cannot be enforced. In such a case it will be
    presumed that a reasonable price was intended.” (omission in
    original) (citations and internal quotation marks omitted)); see
    also United States v. Swift & Co., 
    270 U.S. 124
    , 141 (1926) (“Under
    ordinary conditions, a valid agreement can be made for purchase
    and sale without the fixing of a specific price. In such a case a
    reasonable price is presumed to have been intended.”); Interstate
    Plywood Sales Co. v. Interstate Container Corp., 
    331 F.2d 449
    , 452
    20150682-CA                      13               
    2017 UT App 144
    I-D Electric v. Gillman
    n.6 (9th Cir. 1964) (stating that, under California law, “where the
    contract entirely fails to mention price[,] it will then be implied
    that the parties intended to deal at a reasonable price”); cf. Mills
    v. Brody, 
    929 P.2d 360
    , 367 (Utah Ct. App. 1996) (“Where the
    contract is silent as to when tender of the purchase price is
    required, [c]ourts universally read into such contracts an
    obligation of payment within a time reasonable in the context of
    the transaction and circumstances of the parties.” (alteration in
    original) (emphasis, citation, and internal quotation marks
    omitted)). The district court correctly concluded that the contract
    was enforceable, but did not make a determination regarding the
    reasonableness of the price term, which I-D calculated after
    Gillman had signed the work order.
    ¶31 Whether a price is reasonable is a question of fact. Cf.
    Mills, 
    929 P.2d at 367
     (stating that, in determining the reasonable
    timing of payment on a contract, what “is reasonable is a
    question of fact” (emphasis, citation, and internal quotation
    marks omitted)). There was testimony from both sides regarding
    the reasonableness of the contract price, but because the district
    court is the finder of fact, we will not substitute our judgment
    regarding whether the contract price was reasonable for that of
    the district court. Therefore, we remand this case for the limited
    purpose of determining whether the contract price I-D charged
    Gillman was reasonable. If the district court determines the
    contract price was reasonable, its judgment concerning Gillman
    will remain unchanged. If the court determines the contract price
    was not reasonable, it will determine the reasonable price for
    Gillman to fulfill her obligation under the contract.
    III. Attorney Fees
    A.     Jurisdiction
    ¶32 As a preliminary matter, I-D contends this court lacks
    jurisdiction to hear Gillman’s claim concerning attorney fees. It
    notes that Gillman raised this issue in her rule 52(b) motion to
    amend the district court’s findings and conclusions, and argues
    20150682-CA                     14               
    2017 UT App 144
    I-D Electric v. Gillman
    Gillman failed to timely appeal the district court’s order denying
    her motion.
    ¶33 After a bench trial, the district court entered its findings of
    fact and conclusions of law. It determined I-D prevailed on its
    breach of contract claim and could be entitled to reasonable
    attorney fees, and it directed I-D to submit a proposed order
    regarding the fees. The court also determined there was no cause
    of action for which Gillman could be entitled to attorney fees.
    ¶34 Gillman then filed a rule 52(b) motion to amend the
    court’s findings of fact and conclusions of law, arguing she was
    entitled to statutory attorney fees for her successful defense of
    the mechanic’s lien claim. The district court denied her motion,
    granted I-D’s motion regarding the amount of attorney fees, and
    entered final judgment. The court amended its judgment a week
    later to include a current calculation of I-D’s attorney fees, and
    within thirty days, Gillman appealed.
    ¶35 “As a general rule, an appellate court lacks jurisdiction
    over an appeal that is not taken from a final order or judgment.”
    Anderson v. Wilshire Invs., LLC, 
    2005 UT 59
    , ¶ 9, 
    123 P.3d 393
    (citing Utah R. App. P. 3(a)). Rule 4(b)(1)(B) of the Utah Rules of
    Appellate Procedure extends this time for appeal when certain
    post-trial motions are filed. A party who files a rule 52(b) motion
    has thirty days from the entry of the court’s order on the motion
    to appeal the final judgment when the rule 52(b) motion is filed
    in timely fashion after the judgment is entered. Utah R. App. P.
    4(b)(1)(B).
    ¶36 I-D contends that because Gillman raised the attorney-fee
    issue in her rule 52(b) motion, she had to appeal the court’s
    denial of that motion within thirty days. Here, however, Gillman
    filed her rule 52(b) motion before the district court had entered a
    final judgment.
    ¶37 In its final judgment and amended judgment, the district
    court summarized the judgment entered against Gillman and
    listed the damages, attorney fees, costs, and interest awarded to
    20150682-CA                    15               
    2017 UT App 144
    I-D Electric v. Gillman
    I-D. Gillman appealed this final order within the thirty-day
    deadline, see 
    id.
     R. 3(a), 4(a), and we readily conclude we have
    jurisdiction to hear her claim regarding attorney fees.
    B.    Attorney Fees Award
    ¶38 Gillman disputes the district court’s award of attorney
    fees to I-D. The court determined I-D prevailed on its contract
    claim and successfully defeated Gillman’s wrongful lien claim.
    Because Gillman had breached the contract and because the
    work order included a provision for attorney fees, the court
    awarded I-D $36,939.29 for damages, fees, costs, and interest.
    I-D’s award was reduced by $3,632 for fees generated in
    litigation of the mechanic’s lien, which Gillman defeated on
    summary judgment.
    ¶39 Gillman first argues she is entitled to attorney fees under
    the mechanic’s lien statute. She also argues the court erred in
    awarding attorney fees to I-D on the basis of the parties’
    contractual provision. “Attorney fees are generally recoverable
    in Utah only when authorized by statute or contract.” Reighard v.
    Yates, 
    2012 UT 45
    , ¶ 41, 
    285 P.3d 1168
     (citation and internal
    quotation marks omitted). Both parties request attorney fees on
    appeal.
    1.    Attorney Fees Under the Mechanic’s Lien Statute
    ¶40 Gillman first contends she is entitled to statutory attorney
    fees for defeating I-D’s mechanic’s lien. She argues she was the
    successful party and asserts that “courts do not have discretion
    to decide whether to award reasonable attorney fees to the
    ‘successful party.’” See A.K. & R. Whipple Plumbing & Heating v.
    Guy, 
    2004 UT 47
    , ¶ 7, 
    94 P.3d 270
     (citation omitted).
    ¶41 Under the mechanic’s lien statute, “the successful party
    shall be entitled to recover a reasonable attorneys’ fee,” 
    Utah Code Ann. § 38-1-18
    (1) (LexisNexis 2010), and a “successful
    party includes one who successfully enforces or defends against
    a lien action,” Kurth v. Wiarda, 
    1999 UT App 335
    , ¶ 9, 
    991 P.2d 20150682
    -CA                   16               
    2017 UT App 144
    I-D Electric v. Gillman
    1113. I-D argues that courts have considerable discretion in
    determining which party was the successful party under the
    statute. See R.T. Nielson Co. v. Cook, 
    2002 UT 11
    , ¶ 25, 
    40 P.3d 1119
     (noting the question of which party is the prevailing party
    “depends, to a large measure, on the context of each case, and,
    therefore, it is appropriate to leave this determination to the
    sound discretion of the trial court”). I-D further argues the
    district court acted well within its discretion when it determined
    I-D was the successful party.
    ¶42 In determining “whether a party was ‘successful’ in
    bringing or defending against a mechanic’s lien enforcement
    action,” this court uses “a ‘flexible and reasoned’ approach.” See
    A.K. & R., 
    2004 UT 47
    , ¶ 26. This approach considers the net
    judgment in the case and “the amounts actually sought[,] and
    then balanc[es] them proportionally with what was recovered.”
    
    Id.
     (citation and internal quotation marks omitted). The approach
    also considers common sense factors such as
    (1) [the] contractual language, (2) the number of
    claims, counterclaims, cross-claims, etc., brought
    by the parties, (3) the importance of the claims
    relative to each other and their significance in the
    context of the lawsuit considered as a whole, and
    (4) the dollar amounts attached to and awarded in
    connection with the various claims.
    Anderson & Karrenberg v. Warnick, 
    2012 UT App 275
    , ¶ 11, 
    289 P.3d 600
     (alteration in original) (quoting R.T. Nielson, 
    2002 UT 11
    ,
    ¶ 25).
    ¶43 In awarding attorney fees to I-D, the district court
    determined that I-D prevailed on its breach of contract claim,
    and that because the contract had a provision for attorney fees,
    I-D was entitled to reasonable attorney fees. The court ruled
    against Gillman on the breach of contract claim and the
    wrongful lien claim and recognized “no cause of action for
    which [Gillman] may be entitled to fees.” Contrary to I-D’s
    argument, the court did not address which party had been
    20150682-CA                     17               
    2017 UT App 144
    I-D Electric v. Gillman
    successful under the mechanic’s lien statute, and did not engage
    in the “flexible and reasoned approach” as outlined by A.K. & R.
    and Anderson. The court stated only that I-D was successful in its
    breach of contract claim as it related to attorney fees.
    ¶44 Furthermore, the mechanic’s lien action was distinct from
    the breach of contract and wrongful lien claims and was
    dismissed early on in the case. I-D brought a mechanic’s lien
    claim against Gillman, and Gillman successfully defeated that
    claim on summary judgment. The court also recognized I-D was
    not entitled to fees it generated in seeking to enforce its
    mechanic’s lien. We therefore see no reason why Gillman should
    not be entitled to attorney fees under the mechanic’s lien statute.
    While these fees may be relatively small in proportion to the
    award I-D was correctly granted, see infra ¶¶ 45–47, we remand
    for the district court to determine the amount of fees Gillman is
    entitled to, by way of an offset against the judgment against her,
    for successfully defeating the mechanic’s lien claim.
    2.    Attorney Fees Under the Contractual Provision
    ¶45 Next, we conclude the district court correctly awarded I-D
    attorney fees on the basis of the work order’s contractual
    language. The work order stated that the purchaser “agrees to
    pay all costs and expenses including reasonable attorney’s fees
    in the event collection becomes necessary.” “If the legal right to
    attorney fees is established by contract, Utah law clearly requires
    the court to apply the contractual attorney fee provision and to
    do so strictly in accordance with the contract’s terms.” Hahnel v.
    Duchesne Land, LC, 
    2013 UT App 150
    , ¶ 16, 
    305 P.3d 208
     (citation
    and internal quotation marks omitted).
    ¶46 I-D brought this action to secure payment of its work. In
    pursuit of collecting its payment, I-D successfully brought a
    breach of contract claim and successfully defended against
    Gillman’s counterclaim. Therefore, there is no error in the court’s
    decision to award I-D attorney fees under the contract, especially
    where the court concluded that the expenses in the case had
    20150682-CA                    18               
    2017 UT App 144
    I-D Electric v. Gillman
    been “exacerbated by [Gillman’s] continued and unreasonable
    efforts to avoid paying a contractual obligation.”
    ¶47 Additionally, Gillman alleges the district court erred in
    determining there was an express contract and I-D failed in its
    burden of proof under a quasi-contract claim. She argues she
    should therefore be awarded attorney fees under the reciprocal
    attorney fee statute. See Utah Code Ann. § 78B-5-826 (LexisNexis
    2012). As we concluded above, however, the district court
    correctly determined there was an express contract, and we
    discern no other error in the award of attorney fees for the
    breach of contract claim.
    ¶48 In sum, the district court correctly awarded I-D attorney
    fees under the breach of contract claim, but it incorrectly denied
    Gillman attorney fees under the mechanic’s lien statute.
    3.    Attorney Fees on Appeal
    ¶49 Finally, I-D requests an award of attorney fees on appeal.
    “[W]hen a party who received attorney fees below prevails on
    appeal, the party is also entitled to fees reasonably incurred on
    appeal.” Valcarce v. Fitzgerald, 
    961 P.2d 305
    , 319 (Utah 1998)
    (citation and internal quotation marks omitted). As we
    previously determined, the district court correctly dismissed
    Gillman’s wrongful lien claim and correctly determined there
    was an express contract between I-D and Gillman. Though the
    court incorrectly denied Gillman attorney fees under the
    mechanic’s lien statute, these fees are relatively minor when
    compared to I-D’s award under the contract. We thus conclude
    I-D is entitled to reasonable attorney fees for the issues on which
    it succeeded on appeal. We remand for the district court to
    determine the amount of fees properly to be awarded to I-D.
    CONCLUSION
    ¶50 In sum, we conclude the district court correctly
    determined I-D’s mechanic’s lien was not wrongful under the
    20150682-CA                    19               
    2017 UT App 144
    I-D Electric v. Gillman
    statute. We also conclude the court correctly determined there
    was an express contract between I-D and Gillman, even though
    the contract did not include a price term. Finally, we conclude
    the court erred in denying Gillman attorney fees for defeating
    the mechanic’s lien claim, and direct the court to adjust I-D’s
    attorney fee award accordingly. We remand the case for the
    limited purposes of determining whether the contract price was
    reasonable, adjusting I-D’s attorney fee award, and calculating
    I-D’s reasonable attorney fees incurred on appeal.
    20150682-CA                   20               
    2017 UT App 144