United Savings Ass'n of Texas v. Jim Carpenter Co. , 252 Va. 252 ( 1996 )


Menu:
  • Present: All the Justices
    UNITED SAVINGS ASSOCIATION
    OF TEXAS, F.S.B., ET AL.
    OPINION BY JUSTICE LAWRENCE L. KOONTZ, JR.
    v.   Record No. 951470                  September 13, 1996
    JIM CARPENTER COMPANY
    FROM THE CIRCUIT COURT OF STAFFORD COUNTY
    James W. Haley, Jr., Judge
    TART LUMBER COMPANY, INC.
    v.   Record No. 952238
    DREWER DEVELOPMENT CORPORATION, ET AL.
    FROM THE CIRCUIT COURT OF LOUDOUN COUNTY
    Thomas D. Horne, Judge
    ADDINGTON-BEAMAN LUMBER COMPANY, INC.
    v.   Record No. 960615
    ROBERSON BUILDERS, INC., ET AL.
    FROM THE CIRCUIT COURT OF THE CITY OF CHESAPEAKE
    Russell I. Townsend, Jr., Judge
    In these appeals we consider the applicability of mechanic's
    liens to materials furnished for specific construction projects
    under pre-existing, non-binding credit agreements between
    1
    contractors and materialmen.       In each instance, the contractor
    or its successor-in-interest asserts that the materials were
    furnished under "open accounts," 2 thus each delivery of materials
    1
    In addition to the original contractors and materialmen,
    each suit involved subsequent purchasers of the subject
    properties and their lenders. For the purposes of this opinion,
    we will limit our discussion to the relevant transactions between
    the original parties, since these transactions formed the basis
    for the mechanic's liens at issue.
    2
    Parties on both sides of these disputes use the term "open
    account" to refer to the relationship between the materialmen and
    the contractors, though apparently subscribing to different
    constituted a separate contract.    The materialmen assert that the
    materials and deliveries are identifiable to specific projects
    under "running accounts," 3 thus constituting a single continuing
    contract for each parcel.    For the reasons which follow, and
    under the specific facts of these cases, we agree with the
    materialmen.
    I.
    BACKGROUND
    A. United Savings Association of Texas v.
    Jim Carpenter Company
    In 1983, Kenneth and Keith Ross (Ross Brothers), operating
    as joint proprietors, completed an application for credit with
    Jim Carpenter Company (Carpenter) in contemplation of purchasing
    building materials.    In the application Carpenter agreed to
    extend credit, and Ross Brothers guaranteed payment on any credit
    extended.   Ross Brothers subsequently incorporated, but otherwise
    continued to function as before.
    interpretations of that relationship. The term "open account"
    can be applied generally to any unsecured line of credit.
    Black's Law Dictionary 1090 (6th ed. 1991). For the purposes of
    this opinion, we will use the term "open account" to refer to a
    revolving line of credit based upon a credit application, but for
    which there is no obligation on either party to buy or sell
    materials for specific projects.
    3
    The term "running account," like "open account," has broad
    application to various forms of revolving credit. Black's Law
    Dictionary 1333 (6th ed. 1991). As used generally in our
    opinions, however, the term has a more limited meaning when
    applied to the relationship between materialmen and contractors
    where materials identifiable to specific projects are supplied
    under a continuing contract. See, e.g., Southern Materials Co.
    v. Marks, 
    196 Va. 295
    , 297, 
    83 S.E.2d 353
    , 355 (1954).
    Accordingly, we have selected this term to distinguish the
    materialmen's assertions concerning their relationships with the
    contractors from the "open account" relationship described by the
    contractors.
    In 1989, Ross Brothers began construction of houses on two
    parcels in the Blake Farm subdivision of Stafford County.     Ross
    Brothers ordered materials from Carpenter using separate purchase
    order job sheets for each parcel.   Carpenter furnished the
    materials with invoices, assigning separate account numbers to
    each parcel, and submitted regular statements of the accounts to
    Ross Brothers.   Deliveries were made to each parcel beginning on
    February 12, 1990 and ending on July 26, 1990.    Ross Brothers
    paid for only one delivery.   The two completed homes were sold in
    June and July of 1990.
    On August 21, 1990, Carpenter filed memoranda of mechanic's
    liens on each parcel which it subsequently sought to enforce by
    amended chancery actions filed August 12, 1994.   The two chancery
    suits were consolidated and referred to a commissioner in
    chancery, who concluded the mechanic's liens were proper.     The
    defendants filed exceptions to the commissioner's report,
    including the contention that the liens, or portions thereof,
    would be barred by the 90 day limitation of Code § 43-4 if each
    delivery were viewed as a separate contract.    The chancellor
    sustained the commissioner's findings and awarded judgment to
    Carpenter.   We awarded an appeal to the defendants who are
    principally represented by United Savings Association of Texas,
    F.S.B., a mortgage lien holder on one of the properties.
    B. Tart Lumber Company, Inc. v. Drewer
    Development Corporation
    Tart Lumber Company, Inc. (Tart) entered into a credit
    agreement with Drewer Development Corporation (Drewer) to furnish
    Drewer with materials for building projects.   Between August 8,
    1990 and November 27, 1990, Tart provided Drewer with building
    materials for a number of residential construction projects in
    Loudoun and Fairfax Counties on land owned by Drewer.
    For various aspects of each project, Drewer would submit a
    list of requirements or "takeoff."   Generally, each takeoff would
    list all the materials for a house or townhouse.   Tart would then
    furnish Drewer with a thirty-day firm offer on the materials it
    could supply.   Tart did not supply complete house packages, and
    the record does not establish how Drewer obtained those materials
    which Tart could not furnish.   When Drewer accepted Tart's offer,
    the materials were furnished along with an invoice referencing
    the specific project on which the materials were to be used.     On
    occasion, Drewer would submit "fill-in" requests for additional
    materials which Tart would supply.   Tart provided Drewer with
    regular statements combining charges under invoices for all
    materials furnished during a given time period.
    Beginning in the summer 1990, Drewer experienced financial
    difficulties and ceased payment on its account with Tart.   In
    response, on December 12, 1990, Tart filed memoranda of
    mechanic's liens on twelve properties, organizing in each
    memorandum all the invoices for a specific parcel.
    On June 27, 1991, Tart filed a bill of complaint to enforce
    the liens.   Although Drewer did not file an answer, the secured
    parties and trustees who financed the construction filed timely
    pleadings to contest the liens.   The cases were consolidated and
    referred to a commissioner in chancery.   The commissioner found
    that each delivery of materials was a separate contract, and,
    thus, he concluded that materials delivered more than ninety days
    before the memoranda were filed were not subject to mechanic's
    liens.   The chancellor upheld the commissioner's findings.   We
    awarded Tart an appeal.
    C. Addington-Beaman Lumber Company, Inc. v.
    Roberson Builders, Inc.
    On August 16, 1990, Roberson Builders, Inc. (Roberson)
    completed an application for credit with Addington-Beaman Lumber
    Company, Inc. (Addington-Beaman).   Addington-Beaman furnished
    Roberson with building materials for the construction of houses
    on three parcels owned by Roberson in two subdivisions in the
    City of Chesapeake.   Each invoice referenced the original
    customer number assigned to Roberson's credit application, but
    was segregated by parcel.
    Although it does not appear from the record that Addington-
    Beaman sent Roberson periodic statements, invoices for each
    parcel were separately totaled by Addington-Beaman's accounting
    staff and the statements were bundled together by parcel with the
    adding machine tape showing the total amount due for that parcel.
    In one instance, an Addington-Beaman employee made a notation on
    one set of invoices that settlement of the contract for the sale
    of the home built on that parcel was expected shortly, at which
    time, presumptively, the invoices for the materials furnished for
    that project would be paid.   Roberson did not pay for any of
    these materials before or after it conveyed the properties to
    home buyers.
    For Lot 24, the deliveries were made from September 9, 1990
    to October 25, 1990.   For Lot 122, they were made from September
    6, 1990 to October 31, 1990.   For Lot 227, they were made from
    September 18, 1990 to November 13, 1990.   Addington-Beaman filed
    memoranda of mechanic's liens for Lot 24 and Lot 122 on January
    29, 1991 and on Lot 227 on February 28, 1991.
    After Addington-Beaman filed bills of complaint to enforce
    its mechanic's liens, all three matters were referred to a
    commissioner in chancery.   The commissioner found for Addington-
    Beaman.   The chancellor reversed the commissioner's findings,
    ruling that each delivery was a separate contract required to
    meet the time requirements of Code § 43-4, even if filed under a
    combined lien.   Thus, the chancellor ruled that only those
    deliveries which fell within the statutory time requirement were
    subject to the liens and judgment was awarded only for the
    amounts on those invoices which fell within that time period.     We
    awarded Addington-Beaman an appeal.
    II.
    OPERATION OF MECHANIC'S LIENS UNDER CONTINUING
    CONTRACTS AND OPEN ACCOUNTS
    The central issue of each of these appeals is whether the
    materials were furnished by materialmen under specific continuing
    contracts or merely by marketplace suppliers under general open
    accounts.   See Staples v. Adams, Payne & Gleaves, Inc., 
    215 F. 322
    , 327-28 (4th Cir. 1914).   We have previously stated the
    standard for operation of mechanic's liens under these differing
    forms of contract:
    "If the materials were furnished under a single
    contract, and were in fulfillment thereof, the items of
    the account would be continuous, and the material man
    would have ninety days from the date of the last item
    within which to file his account and perfect his
    lien. . . . On the other hand, if the several items of
    the account, or a portion of them, are furnished under
    separate contracts, then the lien should have been
    filed ninety days from the date of the last item under
    each independent contract."
    First National Bank of Richmond v. William R. Trigg Co., 
    106 Va. 327
    , 339-40, 
    56 S.E. 158
    , 161 (1907)(quoting Central Trust
    Company v. Chicago, K. & T Ry. Co., 
    54 F. 598
    , 599 (1893)).
    However, it appears that the specific issue of
    distinguishing between deliveries of construction materials under
    running accounts amounting to a single continuing contract and
    deliveries under open accounts amounting to separate contracts is
    a matter of first impression in Virginia, although not uncommon
    4
    to the law of mechanic's liens generally.       See, e.g.,
    Annotation, When contract, transaction, or account deemed
    "continuing" one as regards time for filing mechanics' lien, 97
    4
    In Sergeant v. Derby, 
    87 Va. 206
    , 
    12 S.E. 402
     (1890), we
    held that a single contract for a specific amount for
    construction materials for two separate houses provided a
    sufficient foundation for a mechanic's lien on both houses.
    There, we were not required to determine whether multiple
    deliveries of materials identified to a specific construction
    project constitute individual separate contracts. Also, in
    Addington-Beaman Lumber Co. v. Lincoln Savings and Loan Assoc.
    
    241 Va. 436
    , 
    403 S.E.2d 688
     (1991)(hereinafter referenced as
    Lincoln to avoid confusion with the present appeal involving
    Addington-Beaman), a case involving an open account for
    construction materials, we held that where there is a series of
    individual but related transactions identified to specific lots
    benefited by the materials, the materialman is required to
    apportion the costs of the materials in the memoranda of
    mechanic's liens to specific lots. Neither of these cases
    addresses the specific issue of the present appeals by
    distinguishing a running account amounting to a single continuing
    contract from a general open account amounting to multiple
    contracts.
    A.L.R. 780 (1935).   We begin our analysis by reviewing the
    settled law of mechanic's liens in Virginia.
    Mechanic's liens are authorized by Code § 43-3(A), which
    provides:
    All persons performing labor or furnishing materials of
    the value of fifty dollars or more, for the
    construction, removal, repair or improvement of any
    building or structure permanently annexed to the
    freehold . . . shall have a lien, if perfected as
    hereinafter provided, upon such building or
    structure . . . .
    Code § 43-4 establishes the criteria for the filing of a
    memorandum to perfect the mechanic's lien:
    A . . . lien claimant . . . in order to perfect the
    lien given by § 43-3 . . . shall file a memorandum of
    lien at any time after the work is commenced or
    material furnished, but not later than ninety days from
    the last day of the month in which he last performs
    labor or furnishes material, and in no event later than
    ninety days from the time such building, structure, or
    railroad is completed, or the work thereon otherwise
    terminated.
    Mechanic's liens were created to provide the "security of a
    lien to those who, by their labor and materials, have enhanced
    the value of [a] 'building or structure' . . . ."      Lincoln, 241
    Va. at 439, 403 S.E.2d at 689.   Although a mechanic's lien "must
    have its foundation in a contract,"   Rosser v. Cole, 
    237 Va. 572
    ,
    576, 
    379 S.E.2d 323
    , 325 (1989), the contract need not be in
    writing.   Pario v. Bethell, 
    75 Va. 825
    , 829 (1881).
    Nor is there any requirement that the contract at its
    inception state with specificity the nature of the work to be
    done and/or the materials to be furnished.   Rather, where the
    work or materials are furnished as part of a continuing contract
    related to a single property, a single contract adequate to
    underpin a mechanic's lien will be found to exist.   Thus, in
    Osborne v. Big Stone Gap Colliery Co., 
    96 Va. 58
    , 
    30 S.E. 446
    (1898), we stated that "[i]t is true that a number of items were
    furnished more than ninety days before the account was filed
    . . . but it was a running account, and, where nothing to the
    contrary appears, is to be considered as falling due at the date
    of its last item."   Id. at 66, 30 S.E. at 449 (emphasis added).
    Determining whether a particular claim is founded upon an
    account constituting a single continuing contract or upon
    separate and independent contracts is a question of fact, but one
    which turns upon a substantive, rather than technical, view of
    the situation.   See Chicago Lumber Company of Omaha v. Horner,
    
    317 N.W.2d 87
    , 90 (Neb. 1982).   In making this determination, the
    trier of fact should consider the factors surrounding the
    dealings of the parties including their agreement and its
    purpose, the object of the work done or the materials furnished,
    the time when the work was done or materials were furnished, and
    other circumstances which suggest the nature of the parties'
    intentions.
    Unlike the labor of a subcontractor, which can be readily
    identified with a specific project, the utilitarian nature of
    construction materials places upon the materialman a greater
    burden in establishing his right to a lien on a particular
    project.   Accordingly, applying the analysis used in Osborne and
    a non-technical view of the situation, where the course of
    dealing between the parties shows that each understood that the
    materials were being supplied for a particular project, rather
    than merely for general use by the contractor, and nothing in the
    record suggests that a mere open account was intended, a
    continuing contract will be found.   With these principles in
    mind, we turn now to the specific cases in these appeals.
    III.
    NATURE OF THE SPECIFIC ACCOUNTS
    In each of the present cases, the parties focus a great deal
    of attention on the initial applications for lines of credit.
    However, as is shown by each record, these documents are not, and
    do not purport to be, contracts.   The credit applications did not
    obligate either the contractor seeking credit or the materialman
    offering credit to purchase or furnish, respectively, any given
    materials at any given time.   In short, while these documents may
    be evidence of the intentions of the parties with respect to the
    subsequent contracts represented by the accounts in question,
    they do not represent the sole basis of the formation of those
    contracts.
    A. United Savings Association of Texas v.
    Jim Carpenter Company
    In Carpenter, the contract is evidenced by the purchase
    orders, invoices, and account statements.   The materials
    furnished to each parcel were invoiced and billed under an
    account number unique for each parcel.   This method of record-
    keeping clearly reflects an implied, if not express, unitary
    agreement of the parties for furnishing materials for specific
    construction projects under a continuing contract.   Considering
    the substance of this course of dealing, we believe that the
    separate orders and deliveries were part of an ongoing, unitary
    transaction.   Nothing in the record indicates that Ross Brothers
    sought competitive bids or otherwise sought the materials from
    other suppliers.   Accordingly, we hold that the chancellor
    correctly ruled that the materials were furnished under a single,
    unitary contract for each parcel.
    B. Tart Lumber Company, Inc. v. Drewer
    Development Corporation
    In Tart, Drewer's takeoffs clearly constituted requests for
    bids, which, once accepted, created a contract for materials for
    that construction project covered by each takeoff.     Here, the
    materials furnished under each request were part of a single
    construction project, as is shown by the fact that each invoice
    referenced a specific parcel.   Moreover, Tart's salesman
    testified that in most cases the materials were delivered in bulk
    shipments to the individual parcels and that he regularly
    travelled to the job sites "because we were dealing in such large
    quantities, I wanted to make sure . . . the deliveries were
    dropped in the correct locations."
    The salesman testified that materials were supplied under
    "fill-in" orders only where "either the takeoff was incorrect or
    some of the material [had been] broken."   Moreover, when a fill-
    in was requested, it does not appear that any competitive process
    was used.   Rather, Drewer simply contacted Tart and requested
    that the materials be supplied.   Tart then supplied the fill-in
    materials under an invoice referencing the specific parcel. 5
    5
    In certain instances, Tart supplied material to Drewer
    without referencing specific parcels, and these materials were
    billed as part of the combined statements sent to Drewer.
    However, Tart excluded the charges for these materials when
    Thus, once Drewer accepted Tart's bid on a takeoff, the
    deliveries under that account, including those materials supplied
    as fill-ins, became part of a single, continuous contract related
    to a specific construction project.
    The fact that Tart combined invoices for multiple parcels in
    unitary billing statements does not preclude a finding that the
    materials were delivered to the individual parcels under separate
    continuing contracts.   Nothing in the record suggests that the
    combined statements were used for any purpose other than the
    convenience of the parties.   Moreover, when it filed its
    memoranda of mechanic's liens, Tart was able to segregate the
    charges for the materials furnished for each parcel, in a manner
    similar to a permissible apportioning of an account between
    related properties under a single contract.   See Lincoln, 241 Va.
    at 439-40, 403 S.E.2d at 689-90.   Accordingly, we hold that the
    chancellor erred in ruling that each delivery of materials
    constituted a separate contract.
    C. Addington-Beaman Lumber Company, Inc. v.
    Roberson Builders, Inc.
    Finally, in Addington-Beaman, the record shows that each
    order and each delivery of materials was segregated by parcel.
    The record further shows that Addington-Beaman anticipated
    satisfaction of the invoices for a given parcel in conjunction
    with the settlement on the sale of the home constructed on that
    parcel.   As with the other two cases, the substance of the
    relationship between the parties establishes that the materials
    filing its liens.
    were furnished under separate, but continuing contracts for each
    parcel.   We find nothing in the record to support the contrary
    conclusion that the parties viewed the relationship as a mere
    open account.   Accordingly, we hold that the chancellor erred in
    treating the individual deliveries of materials as separate
    contracts.
    IV.
    CONCLUSION
    In United Savings Association of Texas v. Jim Carpenter Co.,
    the chancellor correctly found that the mechanic's liens were
    filed within ninety days from the last delivery of materials
    under continuing contracts for each parcel.   Accordingly, we will
    affirm that judgment.
    In both Tart Lumber Co. v. Drewer Development Corp. and
    Addington-Beaman Lumber Co. v. Roberson Builders, Inc., the trial
    courts erroneously found that the accounts did not constitute
    running accounts amounting to continuing contracts, and hence
    incorrectly ruled on the time limitation for the filing of liens.
    Accordingly, we will reverse the judgment of the trial courts in
    those two cases, and remand the cases for a determination of the
    amount of the liens as filed under continuing contracts for each
    parcel.
    Record No. 951470 --Affirmed.
    Record No. 952238 --Reversed and remanded.
    Record No. 960615 --Reversed and remanded.
    JUSTICE COMPTON concurs in result.
    

Document Info

Docket Number: Record 951470; Record 952238; Record 960615

Citation Numbers: 252 Va. 252

Judges: Koontz

Filed Date: 9/13/1996

Precedential Status: Precedential

Modified Date: 10/19/2024